PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan:October 01, 2019 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan. Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, Revised November 2017 and August 2018 and applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and works) Up to 100,000 Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-09-30 2021-08-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: / , IBRD / 87800 ASSAM RURAL INFRASTRUCTURE AND AGRICULTURAL SERVICES (ARIAS) SOCIETY Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-ARIAS-34967-CW-RFQ / Under Component A: Enabling Agri Request for Single Stage - One 2018-09- Renovation and refurbishment IBRD / 87800 Post Open - National 79,412.00 0.00 Implementat 2018-01-15 2018-03-17 Enterprise Development Quotations Envelope 13 of PCU office - Block-(B&C) ion IN-ARIAS-34970-CW-RFQ / Under Component A: Enabling Agri Request for Single Stage - One 2018-09- Renovation and refurbishment IBRD / 87800 Post Open - National 86,765.00 0.00 Implementat 2018-01-15 2018-03-17 Enterprise Development Quotations Envelope 13 of PCU office - Block-D ion IN-ARIAS-34971-CW-RFQ / Under Component A: Enabling Agri Request for Single Stage - One 2018-09- Renovation and refurbishment IBRD / 87800 Post Open - National 55,882.00 0.00 Implementat 2018-01-15 2018-03-17 Enterprise Development Quotations Envelope 13 of PCU office - Block-F ion IN-ARIAS-34965-CW-RFQ / ARIAS: Renovation and Component A: Enabling Agri Single Stage - One 2019-01- IBRD / 87800 Post Request for Bids Open - National 219,118.00 199,327.03 Signed 2018-03-02 2017-08-29 2018-03-07 2018-03-22 2017-09-16 2018-04-01 2017-09-19 2018-05-02 2017-12-30 refurbishment of PCU office - Enterprise Development Envelope 27 Block-A IN-ARIAS-43387-CW-RFQ / Interior Furnishing works of Component A: Enabling Agri Request for Single Stage - One 2018-06- IBRD / 87800 Post Open - National 92,308.00 87,935.98 Signed 2018-02-24 2018-04-05 2018-03-12 PCU (ARIAS Society) Building Enterprise Development Quotations Envelope 04 (Part-A) IN-ARIAS-48736-CW-RFQ / Pending ARIAS: Water Supply and Component A: Enabling Agri Request for Single Stage - One 2018-05- IBRD / 87800 Post Open - National 21,538.00 0.00 Implementat 2018-03-04 2018-04-28 sanitary works for Block-C of Enterprise Development Quotations Envelope 28 ion PCU building IN-ARIAS-48849-CW-RFQ / Pending Component A: Enabling Agri Request for Single Stage - One 2019-12- ARIAS: Construction of IBRD / 87800 Post Open - National 46,154.00 0.00 Implementat 2019-06-23 2019-09-21 Enterprise Development Quotations Envelope 20 boundary wall of PCU Building ion IN-ARIAS-48846-CW-RFQ / Component D: Project Request for Single Stage - One 2020-01- ARIAS : Roof treatment for IBRD / 87800 Management, Monitoring and Post Open - National 46,154.00 29,009.22 Signed 2019-07-13 2019-10-10 2020-03-21 Quotations Envelope 08 existing PCU building Learning IN-ARIAS-77374-CW-RFB / Component C: Fostering Pending AGRI (ATMA) : Renovation of Single Stage - One 2019-10- IBRD / 87800 Market-led Production and Post Request for Bids Open - National 172,308.00 0.00 Implementat 2019-01-04 2019-01-09 2019-02-03 2019-03-05 2019-04-09 16 nos. of District ATMA Envelope 06 Resilience Enhancement ion Offices IN-ARIAS-77375-CW-RFB / Component C: Fostering Pending AGRI (ATMA-Block) : Single Stage - One 2019-10- IBRD / 87800 Market-led Production and Post Request for Bids Open - National 230,769.00 0.00 Implementat 2019-01-04 2019-01-09 2019-02-10 2019-03-12 2019-04-16 Renovation of 30 nos. of Envelope 13 Resilience Enhancement ion FIAC/BRC IN-ARIAS-77379-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One 2019-09- AGRI (OPIU) : Upgradation of IBRD / 87800 Market-led Production and Post Open - National 23,077.00 0.00 Implementat 2019-02-02 2019-03-30 Quotations Envelope 26 Nodal Unit Office at HQ Resilience Enhancement ion IN-ARIAS-77387-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One 2019-05- HORT & FP : Upgradation of IBRD / 87800 Market-led Production and Post Open - National 23,077.00 0.00 Implementat 2019-01-26 2019-03-23 Quotations Envelope 22 Nodal Unit Office at HQ Resilience Enhancement ion IN-ARIAS-77406-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One 2019-09- AAU : Renovation of OPIU at IBRD / 87800 Market-led Production and Post Open - National 38,754.00 0.00 Implementat 2019-01-12 2019-03-14 Quotations Envelope 10 AAU, Jorhat Resilience Enhancement ion IN-ARIAS-77412-CW-RFQ / Component C: Fostering Pending DAIRY : Renovation of existing Request for Single Stage - One 2019-05- IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Implementat 2019-01-12 2019-03-14 PIU Building including Quotations Envelope 13 Resilience Enhancement ion furniture IN-ARIAS-77414-CW-RFQ / Component C: Fostering Pending FISHERY : Renovation & Request for Single Stage - One 2019-09- IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Implementat 2019-01-07 2019-03-25 Refurbishment of OPIU, Quotations Envelope 21 Resilience Enhancement ion Fishery IN-ARIAS-88803-CW-RFB / Pending PWD : Construction of Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 49,231.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 Babungaon to NH-37 Road in Agro Cluster Development Envelope 21 ion Morigaon district IN-ARIAS-88804-CW-RFB / Pending PWD : Construction of Bihita Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 498,462.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 to Amlighat Road in Morigaon Agro Cluster Development Envelope 21 ion district IN-ARIAS-88807-CW-RFB / PWD : Construction of Barpeta Component B: Facilitating Single Stage - One 2020-03- -Hajo-Ghy Road (Pub-Adabari IBRD / 87800 Post Request for Bids Open - National 119,123.00 108,056.97 Signed 2019-06-10 2018-11-05 2019-06-15 2019-07-27 2018-11-12 2019-08-26 2019-01-25 2019-09-30 2019-03-05 Agro Cluster Development Envelope 28 Galdighia to Paddy Fields) in Nalbari District IN-ARIAS-88808-CW-RFB / PWD : Construction of Pending Component B: Facilitating Single Stage - One 2020-03- Kaithalkuchi PWD Barama IBRD / 87800 Post Request for Bids Open - National 180,431.00 0.00 Implementat 2019-05-27 2019-06-01 2019-07-13 2019-08-12 2019-09-16 Agro Cluster Development Envelope 14 Road (From Pub-Dahkaunia to ion Bishnupur) in Nalbari District Page 1 IN-ARIAS-88810-CW-RFB / PWD : Construction of Sanirod- Pending Kumarikata Saniroad Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 110,677.00 0.00 Implementat 2019-06-07 2019-06-12 2019-07-24 2019-08-23 2019-09-27 Road(From Bardhap LP School Agro Cluster Development Envelope 25 ion to Kandhbari) in Nalbari District IN-ARIAS-88811-CW-RFB / PWD : Construction of Bunbari Pending Dhamdhama Road (from Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 166,908.00 0.00 Implementat 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 Bishnu Mandir of Dhamdhama Agro Cluster Development Envelope 04 ion Mahina PWD Road to Bunbari village) in Nalbari district IN-ARIAS-88812-CW-RFB / PWD : Construction of Kalbari Pending Component B: Facilitating Single Stage - One 2020-04- Dhupguri namghar to uttar IBRD / 87800 Post Request for Bids Open - National 177,723.00 0.00 Implementat 2019-07-08 2019-07-13 2019-08-24 2019-09-23 2019-10-28 Agro Cluster Development Envelope 25 Satbhanitup PWD Road in ion Barpeta IN-ARIAS-88814-CW-RFB / PWD : Construction of Bahari Component B: Facilitating Single Stage - One 2020-05- Puran Kirtan Ghar to Uttar IBRD / 87800 Post Request for Bids Open - National 436,431.00 398,680.07 Signed 2019-07-15 2019-04-07 2019-07-20 2019-08-31 2019-05-19 2019-09-30 2019-02-21 2019-11-04 2019-03-06 Agro Cluster Development Envelope 02 Haripur road in Barpeta district IN-ARIAS-88815-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 459,108.00 395,438.81 Signed 2019-06-17 2018-11-10 2019-06-22 2019-08-03 2018-11-21 2019-09-02 2019-02-05 2019-10-07 2019-03-04 Sampupara Bazar to Chaygaon Agro Cluster Development Envelope 04 PWD Road in Kamrup District IN-ARIAS-88816-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One 2020-04- Bamundi PWD Road (Beltol- IBRD / 87800 Post Request for Bids Open - National 196,462.00 176,793.28 Signed 2019-07-01 2018-12-01 2019-07-06 2019-08-17 2018-12-01 2019-09-16 2019-02-05 2019-10-21 2019-03-04 Agro Cluster Development Envelope 18 Mahkaltol Dhuliapara Road) in Kamrup district IN-ARIAS-88818-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One 2020-04- Rongphar Village, Phulgaon to IBRD / 87800 Post Request for Bids Open - National 424,615.00 383,814.82 Signed 2019-06-24 2018-11-05 2019-06-29 2019-08-10 2018-12-07 2019-09-09 2019-02-05 2019-10-14 2019-03-05 Agro Cluster Development Envelope 11 Sonapur Burnihat PWD Road in Kamrup district IN-ARIAS-88820-CW-RFB / PWD : Construction of Road Pending from Irongmara Dakbunglow Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 1,080,185.00 0.00 Implementat 2019-06-04 2019-06-09 2019-07-21 2019-08-20 2019-09-24 to Harinagar L.P School (Ch. Agro Cluster Development Envelope 22 ion 1530.00 M to Ch. 2330.00M) in Cachar district IN-ARIAS-88823-CW-RFB / PWD : Construction of Roads from Khambar Bazar centre Component B: Facilitating Single Stage - One 2020-04- approx.. 2 km towards Kalain IBRD / 87800 Post Request for Bids Open - National 46,154.00 40,007.59 Signed 2019-06-17 2018-10-20 2019-06-22 2019-08-03 2018-12-01 2019-09-02 2019-06-28 2019-10-07 2019-09-13 Agro Cluster Development Envelope 04 BMC Building Kosutillain (Ch.0.0 M to Ch.250.00 M ) in Cachar District IN-ARIAS-88826-CW-RFB / PWD : Construction of Roads Pending from Khambar Bazar centre Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 120,000.00 0.00 Implementat 2019-06-18 2019-06-23 2019-08-04 2019-09-03 2019-10-08 towards Silchar to Burunga-I Agro Cluster Development Envelope 05 ion (Ch.0.0 M to Ch.650.00M) in Cachar district IN-ARIAS-88828-CW-RFB / PWD : Construction of Road Pending Component B: Facilitating Single Stage - One 2020-03- from Kajidhar PWD road to NH IBRD / 87800 Post Request for Bids Open - National 240,000.00 0.00 Implementat 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 Agro Cluster Development Envelope 28 54 (CH.0.00 M to Ch. ion 1300.00M) in Cachar district IN-ARIAS-88830-CW-RFB / PWD : Construction of Road Component B: Facilitating Single Stage - One 2020-04- from Sonai Miri Village to IBRD / 87800 Post Request for Bids Open - National 605,477.00 521,668.00 Signed 2019-07-01 2018-10-26 2019-07-06 2019-08-17 2018-12-01 2019-09-16 2019-05-24 2019-10-21 2019-07-02 Agro Cluster Development Envelope 18 Chariduar Bhalukpong Main Road in Sonitpur district IN-ARIAS-88833-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 581,631.00 477,700.28 Signed 2019-06-03 2018-10-29 2019-06-08 2019-07-20 2018-12-07 2019-08-19 2019-02-05 2019-09-23 2019-02-25 from NKS road to Dolibari Agro Cluster Development Envelope 21 Pathar road in Nagaon district IN-ARIAS-88837-CW-RFB / PWD : Construction of Nanoi Pending Component B: Facilitating Single Stage - One 2020-03- Dakhinpat PWD road to IBRD / 87800 Post Request for Bids Open - National 300,000.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 Agro Cluster Development Envelope 21 Dewrigaon No.1 road in ion Nagaon district IN-ARIAS-88838-CW-RFB / PWD : Construction of Darjisit Component B: Facilitating Single Stage - One 2020-03- to Jamunasit via South Laskar IBRD / 87800 Post Request for Bids Open - National 393,538.00 323,217.83 Signed 2019-06-04 2018-11-20 2019-06-09 2019-07-21 2018-12-07 2019-08-20 2019-03-04 2019-09-24 2019-03-07 Agro Cluster Development Envelope 22 Pathar in Nagaon (Hojai) district IN-ARIAS-88840-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 313,723.00 264,332.52 Signed 2019-07-01 2018-12-10 2019-07-06 2019-08-17 2018-12-07 2019-09-16 2019-08-17 2019-10-21 2020-02-17 from NH-15 to Barkumarpara Agro Cluster Development Envelope 18 in Darrang District IN-ARIAS-88842-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 364,815.00 307,381.19 Signed 2019-06-17 2018-11-15 2019-06-22 2019-08-03 2018-12-07 2019-09-02 2019-08-17 2019-10-07 2020-03-17 Bhuktabari Sonapur road in Agro Cluster Development Envelope 04 Darrang district IN-ARIAS-88846-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-04- from Bongshigaon to IBRD / 87800 Post Request for Bids Open - National 242,108.00 197,538.38 Signed 2019-06-17 2018-12-10 2019-06-22 2019-08-03 2018-12-10 2019-09-02 2019-05-24 2019-10-07 2019-07-01 Agro Cluster Development Envelope 04 Bongshigaon H.S in Kokrajhar district Page 2 IN-ARIAS-88854-CW-RFB / PWD : Construction of Dillaji Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 559,862.00 507,538.61 Signed 2019-06-10 2018-12-07 2019-06-15 2019-07-27 2018-12-07 2019-08-26 2019-07-26 2019-09-30 2019-08-28 road (Rongklarbong) in Karbi Agro Cluster Development Envelope 28 Anglong district IN-ARIAS-88856-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-04- IBRD / 87800 Post Request for Bids Open - National 228,231.00 190,795.38 Signed 2019-06-17 2019-09-13 2019-06-22 2019-08-03 2018-12-10 2019-09-02 2019-07-26 2019-10-07 2019-08-21 from Nalbari to Batabari in Agro Cluster Development Envelope 04 Kokrajhar district IN-ARIAS-88858-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-03- from Barmanpara to New IBRD / 87800 Post Request for Bids Open - National 212,754.00 179,848.03 Signed 2019-06-12 2018-10-31 2019-06-17 2019-07-29 2018-12-10 2019-08-28 2019-06-24 2019-10-02 2019-08-29 Agro Cluster Development Envelope 30 Kadamtola Chawk in Kokrajhar district IN-ARIAS-88861-CW-RFB / PWD : Construction of Baijuri Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 191,492.00 152,220.52 Signed 2019-06-03 2019-09-13 2019-06-08 2019-07-20 2018-12-07 2019-08-19 2019-06-28 2019-09-23 2019-08-13 to Watrigiri road in Goalpara Agro Cluster Development Envelope 21 district IN-ARIAS-88862-CW-RFB / PWD : Construction of Jalapara Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 532,554.00 437,933.97 Signed 2019-06-10 2019-09-09 2019-06-15 2019-07-27 2018-12-14 2019-08-26 2019-02-05 2019-09-30 2019-03-01 to Madang road in Goalpara Agro Cluster Development Envelope 28 district IN-ARIAS-88866-CW-RFB / PWD : Construction of Deulgiri Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 214,769.00 182,696.69 Signed 2019-06-10 2018-11-01 2019-06-15 2019-07-27 2018-12-17 2019-08-26 2019-02-05 2019-09-30 2019-03-08 Oil Palm road in Goalpara Agro Cluster Development Envelope 28 district IN-ARIAS-88867-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One 2020-03- from Sonaluguri (Kurshakati) IBRD / 87800 Post Request for Bids Open - National 694,846.00 623,350.05 Signed 2019-06-03 2018-12-10 2019-06-08 2019-07-20 2018-12-10 2019-08-19 2019-09-28 2019-09-23 2020-02-01 Agro Cluster Development Envelope 21 to Ghunghunikhata via Banderkuti in Dhubri district IN-ARIAS-88869-CW-RFB / PWD : Construction of Bokora Component B: Facilitating Single Stage - One 2020-03- Citador road (from Ch.0.00km IBRD / 87800 Post Request for Bids Open - National 630,369.00 571,541.96 Signed 2019-06-10 2018-11-01 2019-06-15 2019-07-27 2018-12-10 2019-08-26 2019-01-25 2019-09-30 2019-02-14 Agro Cluster Development Envelope 28 to Ch. 2.95km) in Majuli (Jorhat) district IN-ARIAS-88873-CW-RFB / PWD : Construction of road from Upper Temera to Component B: Facilitating Single Stage - One 2020-03- Kanphalajan via Kamala Miri IBRD / 87800 Post Request for Bids Open - National 508,985.00 449,940.57 Signed 2019-06-03 2019-09-27 2019-06-08 2019-07-20 2018-12-10 2019-08-19 2019-02-05 2019-09-23 2019-03-07 Agro Cluster Development Envelope 21 Road (from Ch.0.0km to Ch.3.0km) in Golaghat district. IN-ARIAS-88874-CW-RFB / PWD : Construction of Dhalpur Simuluguri PWD to Rangati Component B: Facilitating Single Stage - One 2020-03- IBRD / 87800 Post Request for Bids Open - National 756,538.00 685,933.09 Signed 2019-06-10 2018-12-10 2019-06-15 2019-07-27 2018-12-10 2019-08-26 2019-02-05 2019-09-30 2019-05-24 Arimora Ghat PWD Road via Agro Cluster Development Envelope 28 Ganakdoloni and Nidansuwa village in Lakhimpur diatrict IN-ARIAS-88875-CW-RFB / PWD : Construction of Na- Component B: Facilitating Single Stage - One 2020-03- Charingia Road (from Ch.0.0 IBRD / 87800 Post Request for Bids Open - National 171,231.00 155,287.85 Signed 2019-06-05 2018-10-30 2019-06-10 2019-07-22 2018-12-10 2019-08-21 2019-06-28 2019-09-25 2019-07-29 Agro Cluster Development Envelope 23 km to Ch. 1.0 km) in Sivasagar district IN-ARIAS-88880-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One 2020-03- Barbarua Tekela Road (from IBRD / 87800 Post Request for Bids Open - National 113,538.00 105,486.89 Signed 2019-06-13 2018-10-31 2019-06-18 2019-07-30 2018-12-10 2019-08-29 2019-01-25 2019-10-03 2019-05-25 Agro Cluster Development Envelope 31 Ch.0.0 km to Ch.0.7 km) in Sivasagar district IN-ARIAS-88884-CW-RFB / PWD : Construction of Pending Component B: Facilitating Single Stage - One 2020-04- Dhundar Mukh Road (from IBRD / 87800 Post Request for Bids Open - National 501,538.00 0.00 Implementat 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 Agro Cluster Development Envelope 04 Ch.0.0 km to Ch.3.0 km) in ion Sivasagar district IN-ARIAS-88938-CW-RFQ / PWD : Need based renovation/refurbishment for setting up of the Operational Project Implementation Unit Pending Component B: Facilitating Request for Single Stage - One 2020-03- (OPIU) of Dairy Development IBRD / 87800 Post Open - National 99,108.00 0.00 Implementat 2019-07-06 2019-09-05 Agro Cluster Development Quotations Envelope 03 Department, Fishery ion Development Department, Assam State Agricultural Marketing Board and Sericulture Department. IN-ARIAS-88939-CW-RFQ / PWD : Renovation and Extension of Room for proposed OPIU at Second Component C: Fostering Pending Request for Single Stage - One 2020-03- Floor of D.R. Office, AAU, IBRD / 87800 Market-led Production and Post Open - National 55,692.00 0.00 Implementat 2019-06-29 2019-09-03 Quotations Envelope 01 Jorhat and Renovation/ Resilience Enhancement ion Refurbishment for setting up OPIU in Director of Handloom & Textile office, Guwahati IN-ARIAS-88940-CW-RFQ / PWD : APART_ATMA _NS_1 Renovation/ Repair of District Component C: Fostering Request for Single Stage - One 2020-02- ATMA Offices at Sonitpur, IBRD / 87800 Market-led Production and Post Open - National 64,615.00 52,720.42 Signed 2019-06-23 2019-08-28 2019-07-19 Quotations Envelope 24 Darrang, Nagaon, Karbi Resilience Enhancement Anglong, Morigaon and Lakhimpur IN-ARIAS-88941-CW-RFQ / PWD : APART_ATMA _NS_2 : Component C: Fostering Request for Single Stage - One 2020-02- Renovation/ Repair of District IBRD / 87800 Market-led Production and Post Open - National 32,308.00 26,527.06 Signed 2019-06-23 2019-08-28 2019-07-20 Quotations Envelope 24 ATMA Offices at Kokrajhar, Resilience Enhancement Dhubri & Goalpara. Page 3 IN-ARIAS-88942-CW-RFQ / PWD : APART_ATMA _NS_3: Renovation/ Repair of District Component C: Fostering Pending ATMA Offices at Nalbari & Request for Single Stage - One 2020-03- IBRD / 87800 Market-led Production and Post Open - National 33,309.00 0.00 Implementat 2019-07-06 2019-09-10 Barpeta and Need based Quotations Envelope 08 Resilience Enhancement ion Renovation and Repairing for setting up of the OPIU Horti & FP IN-ARIAS-88943-CW-RFQ / Component C: Fostering PWD : APART_ATMA _NS_4: Request for Single Stage - One 2020-03- IBRD / 87800 Market-led Production and Post Open - National 10,769.00 8,842.35 Signed 2019-07-08 2019-09-12 2019-07-20 Renovation/ Repair of District Quotations Envelope 10 Resilience Enhancement ATMA Offices at Cachar IN-ARIAS-88944-CW-RFQ / PWD : Strengthening of Component C: Fostering Request for Single Stage - One 2020-03- existing Laboratory IBRD / 87800 Market-led Production and Post Open - National 15,385.00 14,035.48 Signed 2019-07-13 2019-09-17 2019-07-19 Quotations Envelope 15 infrastructure of Dairy at Resilience Enhancement Ghungoor, Silchar IN-ARIAS-124928-CW-RFB / Component D: Project Single Stage - One 2020-10- PCU : Interior and Furnishing IBRD / 87800 Management, Monitoring and Post Request for Bids Open - National 507,353.00 395,137.03 Signed 2019-10-14 2019-09-25 2019-10-19 2019-11-30 2019-10-29 2019-12-30 2019-12-04 2020-02-03 2020-03-13 Envelope 30 work of PCU Building [Part B ] Learning IN-ARIAS-77580-CW-RFQ / Component C: Fostering Request for Single Stage - One 2019-09- AHVD-Piggery : Renovation of IBRD / 87800 Market-led Production and Post Open - National 40,000.00 0.00 Canceled 2019-01-07 2019-03-09 Quotations Envelope 05 the OPIU, AHVD Resilience Enhancement IN-ARIAS-77599-CW-RFQ / Component C: Fostering AHVD-INFORMAL DAIRY : Request for Single Stage - One 2019-06- IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Canceled 2019-02-02 2019-04-04 Upgradation of diagnostic lab Quotations Envelope 03 Resilience Enhancement (7 nos.) IN-ARIAS-77583-CW-RFQ / AHVD-Piggery : Establishment Component C: Fostering Request for Single Stage - One 2019-09- of 2 nos. of Satellite liquid IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Canceled 2019-01-26 2019-03-28 Quotations Envelope 24 board semen processing Resilience Enhancement centre IN-ARIAS-87682-CW-RFQ / Component C: Fostering AHVD-INFORMAL DAIRY : Up- Request for Single Stage - One 2019-09- IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Canceled 2019-01-26 2019-03-28 gradation of diagnostic lab (7 Quotations Envelope 24 Resilience Enhancement nos.) IN-ARIAS-224263-CW-RFQ / Component D: Project Pending Request for Single Stage - One 2022-01- Renovation of APC office at IBRD / 87800 Management, Monitoring and Post Limited 26,666.00 0.00 Implementat 2021-05-10 2021-07-05 Quotations Envelope 01 Secretariat Learning ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-19762-GO-RFQ / Pending Purchase of Computers and Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 294,118.00 0.00 Implementati 2018-04-23 2018-08-17 2018-12-15 Office Equipment for PCU and Enterprise Development Quotations Envelope on other implementing Agencies . IN-ARIAS-19790-GO-RFB / Pending Component A: Enabling Agri Single Stage - Two Purchase of Bulk Milk Coolers IBRD / 87800 Post Request for Bids Open - National 145,588.00 0.00 Implementati 2018-07-09 2018-07-14 2018-08-08 2018-10-11 2018-11-15 2020-05-13 Enterprise Development Envelope for Informal Milk Dairy Sector on IN-ARIAS-48741-GO-RFQ / ARIAS: Chairs for PCU's newly Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 15,385.00 11,649.78 Signed 2018-03-10 2018-05-31 2018-09-06 2018-07-30 developed cabins and cubicles Enterprise Development Quotations Envelope (Part-A) IN-ARIAS-48827-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL: Making of IBRD / 87800 Post Open - National 492.00 499.11 Completed 2018-03-15 2018-04-14 2018-04-09 2018-05-14 2018-05-09 Enterprise Development Quotations Envelope Promotional Banner for MAITs IN-ARIAS-48835-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL: Supply & Stitching of IBRD / 87800 Post Open - National 1,646.00 1,604.64 Completed 2018-03-31 2018-05-12 2016-11-14 2018-06-11 2018-07-25 Enterprise Development Quotations Envelope shirts & Trousers for MAITs IN-ARIAS-48858-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL: Supply of Liquid IBRD / 87800 Post Open - National 1,262.00 12,484.21 Signed 2018-04-05 2018-04-30 2017-09-08 2018-05-30 Enterprise Development Quotations Envelope nitrogen IN-ARIAS-48860-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 2,215.00 1,558.94 Signed 2018-03-28 2018-05-04 2017-10-17 2018-06-03 WAMUL: Supply of Ear Tag Enterprise Development Quotations Envelope IN-ARIAS-48861-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Supply of Ear Tag & IBRD / 87800 Post Open - National 1,662.00 2,690.05 Completed 2018-03-31 2018-05-12 2017-06-21 2018-06-11 2017-07-21 Enterprise Development Quotations Envelope Ear Tag Applicator IN-ARIAS-49157-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Jumbo Semen IBRD / 87800 Post Open - National 1,015.00 839.50 Completed 2018-04-28 2018-07-14 2018-04-10 2018-08-13 2019-02-08 Enterprise Development Quotations Envelope storage container IN-ARIAS-49158-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 4,615.00 4,184.85 Completed 2018-04-28 2018-07-09 2018-05-14 2018-08-08 2018-06-23 WAMUL : Laptop to field staff Enterprise Development Quotations Envelope IN-ARIAS-49165-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Android based IBRD / 87800 Post Open - National 25,385.00 22,322.70 Completed 2018-05-05 2018-07-16 2018-05-14 2018-08-15 2018-06-01 Enterprise Development Quotations Envelope Mobile Tablets for MAITS IN-ARIAS-49437-GO-RFQ / Under Component A: Enabling Agri Request for Single Stage - One WAMUL : Furnitures & Fixtures IBRD / 87800 Post Open - National 4,154.00 0.00 Implementati 2018-05-12 2018-07-23 2018-09-21 Enterprise Development Quotations Envelope for Head Office on Under IN-ARIAS-49439-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 18,923.00 0.00 Implementati 2018-05-26 2018-08-06 2018-10-05 WAMUL : AIT furniture set Enterprise Development Quotations Envelope on Page 4 Under IN-ARIAS-49448-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 9,354.00 0.00 Implementati 2018-06-05 2018-08-24 2018-10-23 WAMUL : Frozen Semen dose Enterprise Development Quotations Envelope on IN-ARIAS-49454-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Walk in Coolers IBRD / 87800 Post Open - National 15,385.00 0.00 Canceled 2018-08-25 2018-11-05 2019-02-03 Enterprise Development Quotations Envelope (5000 ltr capacity, 2 Nos.) IN-ARIAS-49456-GO-RFQ / WAMUL : GenSet (2 Nos) for Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 10,769.00 0.00 Canceled 2018-05-28 2018-08-08 2018-10-07 captive power back-up for the Enterprise Development Quotations Envelope Walk-in Coolers IN-ARIAS-49464-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 36,923.00 0.00 Canceled 2018-06-04 2018-08-09 2018-10-08 WAMUL : Visi coolers Enterprise Development Quotations Envelope IN-ARIAS-49465-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Ear Tags for ear- IBRD / 87800 Post Open - National 3,369.00 0.00 Canceled 2018-06-05 2018-08-10 2018-10-09 Enterprise Development Quotations Envelope tagging inseminated animals IN-ARIAS-49467-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 36,923.00 23,211.13 Completed 2018-06-03 2018-08-14 2018-05-13 2018-10-13 2018-06-13 WAMUL : Milk Crates Enterprise Development Quotations Envelope IN-ARIAS-49471-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : (LN2) Liquid IBRD / 87800 Post Open - National 6,185.00 13,939.12 Signed 2018-06-05 2018-08-10 2017-08-28 2018-10-09 Enterprise Development Quotations Envelope Nitrogen IN-ARIAS-49484-GO-RFQ / Pending Component A: Enabling Agri Request for Single Stage - One WAMUL : IT Equipment IBRD / 87800 Post Open - National 4,615.00 0.00 Implementati 2018-08-25 2018-11-05 2019-02-03 Enterprise Development Quotations Envelope (Hardware and Software) on IN-ARIAS-49535-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Support for rearing IBRD / 87800 Post Open - National 30,462.00 18,550.15 Completed 2018-06-16 2018-08-27 2019-07-10 2018-10-26 2019-09-17 Enterprise Development Quotations Envelope heifers (Milk Replacer) IN-ARIAS-49539-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Support for rearing IBRD / 87800 Post Open - National 30,585.00 5,521.32 Completed 2018-06-24 2018-09-04 2020-02-27 2018-11-03 2020-03-18 Enterprise Development Quotations Envelope heifers (Mineral Mixtures) IN-ARIAS-49541-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Automatic Milk IBRD / 87800 Post Open - National 4,923.00 0.00 Canceled 2018-06-30 2018-09-10 2018-11-09 Enterprise Development Quotations Envelope Collection Units (AMCUs) IN-ARIAS-49545-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 1,538.00 0.00 Canceled 2018-06-10 2018-08-21 2018-10-20 WAMUL : Can scrubbers Enterprise Development Quotations Envelope IN-ARIAS-49548-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Road milk tankers IBRD / 87800 Post Open - National 38,462.00 0.00 Canceled 2018-06-18 2018-08-29 2018-10-28 Enterprise Development Quotations Envelope (5000 ltr capacity) IN-ARIAS-49551-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Road milk tanker IBRD / 87800 Post Open - National 53,846.00 0.00 Canceled 2018-07-01 2018-09-11 2018-11-10 Enterprise Development Quotations Envelope (10000 ltr capacity) IN-ARIAS-49558-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 769.00 0.00 Canceled 2018-07-05 2018-09-18 2018-11-17 WAMUL : Adulteration kits Enterprise Development Quotations Envelope IN-ARIAS-49561-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 1,846.00 2,482.10 Completed 2018-07-05 2018-09-15 2019-02-22 2018-11-14 2019-04-05 WAMUL : Milking machines Enterprise Development Quotations Envelope IN-ARIAS-49563-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Power driven Gerber IBRD / 87800 Post Open - National 2,308.00 0.00 Canceled 2018-07-03 2018-09-13 2018-11-12 Enterprise Development Quotations Envelope machines IN-ARIAS-49571-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 61,538.00 0.00 Canceled 2018-05-29 2018-08-09 2018-10-08 WAMUL : Refrigerated vans Enterprise Development Quotations Envelope IN-ARIAS-61743-GO-DIR / PCU Solar PV Power : Installation of Grid Connected Component D: Project Pending Rooftop Solar PV Power Plants IBRD / 87800 Management, Monitoring and Post Direct Selection Direct 7,751.00 0.00 Implementati 2019-01-28 2019-02-07 2019-03-24 2019-05-23 under CAPEX Model at the Learning on building of ARIAS Society under 70 percentage Subsidy Scheme IN-ARIAS-48749-GO-RFQ / ARIAS: Solar Power System (Roof top) for PCU building Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 61,538.00 0.00 Canceled 2018-03-10 2018-05-31 2018-08-29 and Solar Power Street light in Enterprise Development Quotations Envelope the PCU Campus - Supply & Installation IN-ARIAS-19789-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One Purchase of Iron Supplements IBRD / 87800 Market-led Production and Post Open - National 48,529.00 0.00 Implementati 2019-02-02 2019-06-07 2019-08-06 Quotations Envelope for piglet Resilience Enhancement on IN-ARIAS-19775-GO-RFB / Purchase of Vaccines for Pending Food & Mouth Disease (FMD) Component A: Enabling Agri Single Stage - Two IBRD / 87800 Post Request for Bids Open - National 285,294.00 0.00 Implementati 2018-12-24 2018-12-29 2019-01-28 2019-04-12 2019-05-17 2024-09-30 ,Haemorrhagic Septicaemia Enterprise Development Envelope on and Black Quarter (HS & BQ) Disease and Brucellosis IN-ARIAS-48756-GO-RFQ / Pending ARIAS: Elevator for PCU Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 46,154.00 0.00 Implementati 2019-06-29 2019-09-27 2020-03-25 building - Supply & Enterprise Development Quotations Envelope on Installation IN-ARIAS-48820-GO-RFQ / Component D: Project Pending PCU : Supply & Installation of Request for Single Stage - One IBRD / 87800 Management, Monitoring and Post Open - National 46,154.00 0.00 Implementati 2019-06-22 2019-09-08 2020-03-06 silent GenSet for PCU building Quotations Envelope Learning on of 450kva IN-ARIAS-77353-GO-RFQ / Component C: Fostering Pending AGRI (ATMA) : Purchase of Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 33,969.00 0.00 Implementati 2019-01-12 2019-03-09 2019-05-08 Computer with other Quotations Envelope Resilience Enhancement on accessories (48 nos.) Page 5 IN-ARIAS-77355-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AGRI (ATMA) : 16 nos. of IBRD / 87800 Market-led Production and Post Open - National 30,769.00 0.00 Implementati 2019-01-12 2019-03-16 2019-05-15 Quotations Envelope Photocopiers with scanner Resilience Enhancement on IN-ARIAS-77390-GO-RFQ / AAU : Purchase of 14 nos. of Laptop with other accssories Component C: Fostering Pending for 1 no of Project Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 32,308.00 0.00 Implementati 2019-01-09 2019-03-09 2019-04-23 Coordinator, 11 nos. of Quotations Envelope Resilience Enhancement on Project Scientist, 1 no of Accounts Manager and 1 no of MIS Operator at OPIU IN-ARIAS-77401-GO-RFQ / AAU : Purchase of 43 nos. of Component C: Fostering Under Request for Single Stage - One Laptop with other accessories IBRD / 87800 Market-led Production and Post Open - National 99,231.00 0.00 Implementati 2019-01-07 2019-03-12 2019-05-11 Quotations Envelope for Project Scientist and Asstt. Resilience Enhancement on Project Scientist at RARS/KVKs IN-ARIAS-77403-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AAU : Furnitures for OPIU at IBRD / 87800 Market-led Production and Post Open - National 46,154.00 0.00 Implementati 2019-01-09 2019-03-09 2019-05-08 Quotations Envelope AAU, Jorhat Resilience Enhancement on IN-ARIAS-77410-GO-RFQ / Component C: Fostering Pending DAIRY : Procurement of Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 73,846.00 0.00 Implementati 2019-01-26 2019-03-28 2019-04-27 computers & accessories for 4 Quotations Envelope Resilience Enhancement on District Project Offices IN-ARIAS-77569-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD Piggery : Procurement IBRD / 87800 Market-led Production and Post Open - National 15,385.00 5,556.52 Completed 2019-01-23 2019-03-23 2019-07-12 2019-05-22 2019-07-12 Quotations Envelope of Computer & Accessories Resilience Enhancement IN-ARIAS-77571-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD Piggery : Procurement IBRD / 87800 Market-led Production and Post Open - National 42,462.00 35,443.11 Signed 2019-02-02 2019-04-04 2018-12-29 2019-06-03 Quotations Envelope of FMD vaccine Resilience Enhancement IN-ARIAS-77572-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD Piggery : Procurement IBRD / 87800 Market-led Production and Post Open - National 42,462.00 10,644.35 Signed 2019-02-02 2019-04-04 2019-01-30 2019-06-03 Quotations Envelope of 138,000 nos. of Resilience Enhancement Deworming IN-ARIAS-77573-GO-RFQ / Component C: Fostering AHVD Piggery : Procurement Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 49,846.00 13,442.86 Signed 2019-02-09 2019-04-06 2019-01-30 2019-10-03 of 54,000 nos. Iron Quotations Envelope Resilience Enhancement supplementation IN-ARIAS-91925-GO-DIR / Component C: Fostering AHVD Piggery : Procurement IBRD / 87800 Market-led Production and Post Direct Selection Direct 169,846.00 173,582.44 Signed 2019-02-11 2019-11-14 2019-02-16 2019-10-18 2019-03-28 2019-06-09 2019-09-24 of 276,000 nos. Cysticercosis Resilience Enhancement IN-ARIAS-77585-GO-RFQ / Component C: Fostering AHVD-FORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 19,015.00 13,347.21 Signed 2019-01-23 2019-03-25 2019-01-07 2019-09-21 Procurement of 41,200 nos. Quotations Envelope Resilience Enhancement of Brucellosis vaccination IN-ARIAS-77589-GO-RFQ / AHVD-FORMAL DAIRY : Component C: Fostering Request for Single Stage - One Procurement of 316,000 nos. IBRD / 87800 Market-led Production and Post Open - National 48,615.00 18,001.89 Signed 2019-01-26 2019-03-28 2019-01-07 2019-05-27 Quotations Envelope of Haemorrhagic Septicaemia Resilience Enhancement & Blackquarter Vaccine IN-ARIAS-77592-GO-RFQ / AHVD-INFORMAL DAIRY : Component C: Fostering Request for Single Stage - One Procurement of 52,400 nos. IBRD / 87800 Market-led Production and Post Open - National 8,062.00 18,001.89 Signed 2019-01-26 2019-03-28 2019-01-07 2019-05-27 Quotations Envelope of Haemorrhagic Septicaemia Resilience Enhancement & Blackquarter Vaccine IN-ARIAS-77597-GO-RFQ / AHVD-INFORMAL DAIRY : Component C: Fostering Request for Single Stage - One Procurement of 11 nos. of IBRD / 87800 Market-led Production and Post Open - National 7,385.00 4,479.52 Completed 2019-01-16 2019-03-18 2019-07-06 2019-05-17 2019-09-12 Quotations Envelope Deep freezer for vaccine Resilience Enhancement storage IN-ARIAS-78435-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : 3 Litre IBRD / 87800 Market-led Production and Post Open - National 32,000.00 46,627.12 Completed 2019-01-12 2019-03-09 2019-01-14 2019-05-08 2019-02-06 Quotations Envelope LN2 Container Resilience Enhancement IN-ARIAS-78436-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : 33 L IBRD / 87800 Market-led Production and Post Open - National 47,508.00 41,901.74 Completed 2019-01-26 2019-03-23 2019-01-14 2019-05-22 2019-02-03 Quotations Envelope LN2 Container Resilience Enhancement IN-ARIAS-78455-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 39,600.00 36,665.03 Completed 2019-01-23 2019-03-20 2018-11-16 2019-05-19 2018-11-27 Quotations Envelope Netbooks/Tablets to MAITs Resilience Enhancement IN-ARIAS-78459-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : AIT IBRD / 87800 Market-led Production and Post Open - National 51,462.00 44,050.17 Completed 2019-01-23 2019-03-20 2019-02-11 2019-05-19 2019-03-16 Quotations Envelope furniture set Resilience Enhancement IN-ARIAS-78464-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Frozen IBRD / 87800 Market-led Production and Post Open - National 31,092.00 12,129.50 Signed 2019-01-24 2019-03-14 2019-03-26 2019-05-13 Quotations Envelope Semen dose Resilience Enhancement IN-ARIAS-78476-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Liquid IBRD / 87800 Market-led Production and Post Open - National 28,385.00 47,225.68 Signed 2019-02-02 2019-03-23 2019-01-12 2019-05-22 Quotations Envelope Nitrogen Resilience Enhancement IN-ARIAS-78479-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : AIT IBRD / 87800 Market-led Production and Post Open - National 9,815.00 0.00 Implementati 2019-01-28 2019-03-18 2019-05-17 Quotations Envelope Stationeries Resilience Enhancement on IN-ARIAS-78482-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Data IBRD / 87800 Market-led Production and Post Open - National 29,138.00 0.00 Canceled 2019-01-16 2019-03-06 2019-05-05 Quotations Envelope Card cost Resilience Enhancement IN-ARIAS-78646-GO-RFB / Component C: Fostering WAMUL (AWP 18-19) Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 213,785.00 43,756.51 Completed 2019-01-02 2019-06-02 2019-01-07 2019-02-06 2019-06-15 2019-03-08 2019-09-17 2019-04-12 2017-03-29 2019-08-10 2019-12-19 :Extension and Promotion Envelope Resilience Enhancement Material Page 6 IN-ARIAS-78484-GO-RFQ / Under WAMUL (AWP 18-19) : Bulk Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 35,538.00 0.00 Implementati 2019-01-26 2019-03-22 2019-06-20 Milk Coolers (BMCs) : 3000 Ltr Enterprise Development Quotations Envelope on BMCs IN-ARIAS-78485-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Bulk Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 85,292.00 71,929.02 Completed 2019-01-12 2019-03-19 2019-08-07 2019-06-17 2019-10-24 Milk Coolers (BMCs) : 2000Ltr Quotations Envelope Resilience Enhancement BMCs IN-ARIAS-78487-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 14,769.00 0.00 Implementati 2019-02-06 2019-03-28 2019-09-24 Automatic Milk Collection Quotations Envelope Resilience Enhancement on Units (AMCUs) IN-ARIAS-78494-GO-RFB / Component C: Fostering WAMUL (AWP 18-19) : Road Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 161,538.00 274,288.98 Completed 2019-01-07 2019-03-13 2019-01-12 2019-02-11 2019-04-13 2019-03-13 2019-07-08 2019-04-17 2019-08-30 2019-07-16 2020-01-24 milk tanker (10000 ltr Envelope Resilience Enhancement capacity) IN-ARIAS-78495-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Milk IBRD / 87800 Market-led Production and Post Open - National 40,154.00 31,487.21 Completed 2019-02-02 2019-03-23 2019-04-05 2019-06-21 2019-04-05 Quotations Envelope Cans (40 ltr capacity) Resilience Enhancement IN-ARIAS-78522-GO-RFB / Component C: Fostering WAMUL (AWP 18-19) : Solar Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 506,000.00 298,634.53 Completed 2019-01-18 2019-03-14 2019-01-23 2019-02-22 2019-04-12 2019-03-24 2019-06-22 2019-04-28 2019-06-27 2019-07-27 2019-12-23 powered Data Processor Milk Envelope Resilience Enhancement Collection Units (DPMCUs) IN-ARIAS-78523-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Milk IBRD / 87800 Market-led Production and Post Open - National 27,246.00 17,189.87 Completed 2019-01-13 2019-03-15 2019-04-11 2019-05-14 2019-12-24 Quotations Envelope Collection Equipments Resilience Enhancement IN-ARIAS-78544-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Power IBRD / 87800 Market-led Production and Post Open - National 19,462.00 17,536.92 Completed 2019-01-27 2019-03-15 2019-03-30 2019-05-14 2019-06-14 Quotations Envelope driven Gerber machines Resilience Enhancement IN-ARIAS-78545-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 21,000.00 19,095.21 Completed 2019-01-07 2019-02-25 2019-04-11 2019-04-26 2019-04-11 Quotations Envelope Adulteration kits Resilience Enhancement IN-ARIAS-78548-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 77,846.00 25,080.17 Completed 2019-01-08 2019-02-26 2019-06-08 2019-04-27 2019-06-26 Furnitures and fixtures (for Quotations Envelope Resilience Enhancement MPIs/DCSs) IN-ARIAS-78550-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 10,385.00 0.00 Implementati 2019-01-09 2019-02-27 2019-04-28 Furnitures and fixtures (for Quotations Envelope Resilience Enhancement on field offices) IN-ARIAS-78551-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 15,385.00 28,142.36 Completed 2019-01-10 2019-02-28 2019-06-03 2019-04-29 2019-09-05 Provision of Walk in Coolers Quotations Envelope Resilience Enhancement (5000 ltr capacity) IN-ARIAS-78552-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 7,662.00 14,446.49 Completed 2019-02-02 2019-03-30 2019-02-25 2019-05-29 2019-02-25 Quotations Envelope Provision of genset Resilience Enhancement IN-ARIAS-78638-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Visi IBRD / 87800 Market-led Production and Post Open - National 42,462.00 22,216.24 Completed 2019-02-06 2019-03-27 2019-02-19 2019-05-26 2019-05-16 Quotations Envelope coolers Resilience Enhancement IN-ARIAS-78641-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Milk IBRD / 87800 Market-led Production and Post Open - National 79,662.00 25,870.06 Completed 2019-01-27 2019-03-24 2019-07-20 2019-06-22 2019-08-08 Quotations Envelope Crates Resilience Enhancement IN-ARIAS-115292-GO-RFQ / PCU : Procurement of 21 Nos. Component D: Project Pending Request for Single Stage - One of Laptops through GeM for IBRD / 87800 Management, Monitoring and Post Open - National 19,500.00 0.00 Implementati 2019-06-01 2019-07-27 2019-08-26 Quotations Envelope officials under International Learning on Agency for APART IN-ARIAS-78446-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : Laptop IBRD / 87800 Market-led Production and Post Open - National 20,769.00 22,567.86 Completed 2019-02-02 2019-03-30 2018-11-16 2019-05-29 2019-01-14 Quotations Envelope to field staff Resilience Enhancement IN-ARIAS-49559-GO-RFQ / WAMUL : Solar powered Data Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 60,000.00 0.00 Canceled 2018-07-21 2018-10-01 2018-11-30 Processor Milk Collection Enterprise Development Quotations Envelope Units (DPMCUs) IN-ARIAS-49163-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 308.00 0.00 Canceled 2018-04-28 2018-07-09 2018-08-08 WAMUL : Laser Printer (RO) Enterprise Development Quotations Envelope IN-ARIAS-49455-GO-RFQ / WAMUL : Disposable Gloves Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 2,354.00 0.00 Canceled 2018-06-05 2018-08-10 2018-10-09 (50,868 Nos.) for conducting Enterprise Development Quotations Envelope AI IN-ARIAS-49460-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Disposable Sheath IBRD / 87800 Post Open - National 554.00 0.00 Canceled 2018-06-05 2018-08-10 2018-10-09 Enterprise Development Quotations Envelope (27997 nos.) for conducting AI IN-ARIAS-78493-GO-RFB / Component C: Fostering WAMUL (AWP 18-19) : Road Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 115,385.00 0.00 Canceled 2019-01-11 2019-01-16 2019-02-15 2019-03-12 2019-04-16 2019-07-15 milk tankers (5000 ltr Envelope Resilience Enhancement capacity) IN-ARIAS-49564-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Furnitures and IBRD / 87800 Post Open - National 9,231.00 0.00 Canceled 2018-07-05 2018-09-09 2018-11-08 Enterprise Development Quotations Envelope fixtures IN-ARIAS-49560-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Milk Collection IBRD / 87800 Post Open - National 3,231.00 0.00 Canceled 2018-07-21 2018-10-01 2018-11-30 Enterprise Development Quotations Envelope Equipments Page 7 IN-ARIAS-78432-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : LN2 IBRD / 87800 Market-led Production and Post Open - National 76,923.00 0.00 Canceled 2019-01-16 2019-03-13 2019-05-12 Quotations Envelope Silo 5 KL Resilience Enhancement IN-ARIAS-78642-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Canceled 2019-01-26 2019-03-23 2019-06-21 Quotations Envelope Refrigerated vans Resilience Enhancement IN-ARIAS-78486-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 30,769.00 0.00 Canceled 2019-01-26 2019-03-22 2019-06-20 Differential cost for the solar Quotations Envelope Resilience Enhancement powered BMC units IN-ARIAS-49566-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL: Extension and IBRD / 87800 Post Open - National 19,200.00 0.00 Canceled 2018-06-05 2018-08-10 2018-10-09 Enterprise Development Quotations Envelope Promotion Material IN-ARIAS-49526-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 4,462.00 0.00 Canceled 2018-05-19 2018-07-30 2018-09-28 WAMUL : AIT Stationeries Enterprise Development Quotations Envelope IN-ARIAS-49476-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : (LN2) Transportation IBRD / 87800 Post Open - National 6,046.00 0.00 Canceled 2018-06-05 2018-08-10 2018-10-09 Enterprise Development Quotations Envelope of Liquid Nitrogen IN-ARIAS-49443-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Furniture (Cluster IBRD / 87800 Post Open - National 3,692.00 0.00 Canceled 2018-06-05 2018-08-01 2018-09-30 Enterprise Development Quotations Envelope office) IN-ARIAS-49457-GO-RFQ / WAMUL : Insulated Boxes (80 Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 7,385.00 0.00 Canceled 2018-05-26 2018-08-06 2018-10-05 Nos.) for packaged Milk and Enterprise Development Quotations Envelope Milk products at retail level IN-ARIAS-78478-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : AI IBRD / 87800 Market-led Production and Post Open - National 31,185.00 0.00 Canceled 2019-01-27 2019-03-17 2019-05-16 Quotations Envelope Accessories & consumables Resilience Enhancement IN-ARIAS-77570-GO-RFQ / Component C: Fostering AHVD Piggery : Procurement Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 42,462.00 0.00 Canceled 2019-01-12 2019-03-14 2019-05-13 of 138,000 nos. Classical Quotations Envelope Resilience Enhancement swine fever vaccine IN-ARIAS-77593-GO-RFQ / AHVD-INFORMAL DAIRY : Procurement of 17 nos. of Component C: Fostering Request for Single Stage - One Tablet for Information IBRD / 87800 Market-led Production and Post Open - National 3,923.00 0.00 Canceled 2019-01-23 2019-03-25 2019-05-24 Quotations Envelope Network for Animal Resilience Enhancement Productivity and Health (INAPH) IN-ARIAS-77568-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD-Piggery : Cost of 24 IBRD / 87800 Market-led Production and Post Open - National 11,077.00 0.00 Canceled 2019-01-26 2019-03-26 2019-04-25 Quotations Envelope nos. tablet for data entry Resilience Enhancement IN-ARIAS-77579-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD Piggery : 37,920 nos. of IBRD / 87800 Market-led Production and Post Open - National 25,169.00 0.00 Canceled 2019-01-23 2019-03-25 2019-04-24 Quotations Envelope Ear tags Resilience Enhancement IN-ARIAS-77590-GO-RFQ / Component C: Fostering AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 21,523.00 0.00 Canceled 2019-01-09 2019-03-11 2019-05-10 Procurement of 244,720 nos. Quotations Envelope Resilience Enhancement of FMD vaccinations IN-ARIAS-87683-GO-RFQ / Component C: Fostering AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 21,523.00 0.00 Canceled 2019-02-02 2019-04-04 2019-06-03 Procurement of 244,720 nos. Quotations Envelope Resilience Enhancement of FMD vaccinations IN-ARIAS-77587-GO-RFQ / Component C: Fostering AHVD-FORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 97,154.00 0.00 Canceled 2019-01-12 2019-03-09 2019-05-08 Procurement of 631,500 nos. Quotations Envelope Resilience Enhancement of FMD vaccinations IN-ARIAS-77594-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD-INFORMAL DAIRY : IBRD / 87800 Market-led Production and Post Open - National 2,492.00 0.00 Canceled 2019-01-27 2019-03-29 2019-05-28 Quotations Envelope Procurement of 1800 Ear tags Resilience Enhancement IN-ARIAS-67904-GO-RFQ / Component C: Fostering Request for Single Stage - One AHVD: Procurement of IBRD / 87800 Market-led Production and Post Open - National 15,385.00 0.00 Canceled 2018-09-08 2018-11-26 2019-01-25 Quotations Envelope Computer and Accessories Resilience Enhancement IN-ARIAS-49532-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One WAMUL : Support for rearing IBRD / 87800 Post Open - National 30,308.00 0.00 Canceled 2018-06-16 2018-08-27 2018-10-26 Enterprise Development Quotations Envelope heifers (Calf Starter) IN-ARIAS-49553-GO-RFQ / Component A: Enabling Agri Request for Single Stage - One IBRD / 87800 Post Open - National 6,923.00 0.00 Canceled 2018-06-17 2018-08-28 2018-10-27 WAMUL : Milk Cans Enterprise Development Quotations Envelope IN-ARIAS-48870-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL : Supply of AI IBRD / 87800 Market-led Production and Post Open - National 892.00 0.00 Canceled 2018-05-12 2018-06-23 2018-07-23 Quotations Envelope disposable gloves & AI Sheets Resilience Enhancement Component C: Fostering IN-ARIAS-48877-GO-RFQ / Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 431.00 0.00 Canceled 2018-05-06 2018-06-10 2018-07-10 WAMUL : Supply of AI Kits Quotations Envelope Resilience Enhancement IN-ARIAS-48880-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL : Supply of AI IBRD / 87800 Market-led Production and Post Open - National 1,815.00 0.00 Canceled 2019-01-30 2019-03-21 2019-05-20 Quotations Envelope Accessories Resilience Enhancement NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 IN-ARIAS-3142-NC-RFQ / Hiring of Consultancy Firm for Digital mapping and plotting of Block/Village wise Request for Single Stage - One Prioritized Clusters of APART / Post Open - National 30,303.00 26,591.46 Completed 2016-11-15 2016-12-06 2016-11-21 2017-03-06 2017-08-20 Quotations Envelope together with other resources in Google Map and development of a web- enabled Application Software . IN-ARIAS-5209-NC-RFB / Hiring of Manpower Agency Component A: Enabling Agri Single Stage - Two for recruitment and IBRD / 87800 Post Request for Bids Open - National 463,235.00 0.00 Canceled 2018-02-01 2018-02-01 2018-02-22 2018-05-05 2018-06-09 2018-12-06 Enterprise Development Envelope management of Projects Support staff IN-ARIAS-242528-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 16,700.00 10,803.11 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 1 (Kamrup Rural, Kokrajhar, Goalpara, Dima Hasao (N. C. Hills)) IN-ARIAS-242531-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 20,000.00 10,538.70 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 2 ( Jorhat (Undivided), Golaghat, Nalbari, Karbi Anglong (Undivided)) IN-ARIAS-242532-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 13,500.00 7,302.80 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 3 (i.e. Barpeta, Karimganj, Sivasagar (Undivided)) IN-ARIAS-242533-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 13,500.00 6,648.07 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 4 (i.e. Bongaigaion, Sonitpur (Undivided), Dhemaji) IN-ARIAS-242534-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 13,500.00 6,635.48 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 5 (i.e. Dhubri (Undivided), Darrang, Hailakandi) IN-ARIAS-242536-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 13,500.00 11,105.29 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 6 (i.e. Udalguri, Tinsukia, Lakhimpur, Cachar) IN-ARIAS-242537-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering experiments (CCE) on pilot Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 13,500.00 8,310.08 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 basis in different zones of Quotations Envelope Resilience Enhancement Assam- Cluster 7 (i.e. Nagaon (Undivided), Chirang, Dibrugarh) IN-ARIAS-242538-NC-RFQ / RFQ for hiring of services for conducting crop cutting Component C: Fostering Request for Single Stage - One experiments (CCE) on pilot IBRD / 87800 Market-led Production and Post Open - National 13,500.00 4,230.59 Signed 2021-07-16 2021-09-10 2021-07-09 2022-03-09 Quotations Envelope basis in different zones of Resilience Enhancement Assam- Cluster 8 (i.e. Kamrup Metro, Morigaon, Baksa) IN-ARIAS-246885-NC-RFQ / Design, Development and Implementation of Human Component D: Project Under Resource Management System Request for Single Stage - One IBRD / 87800 Management, Monitoring and Post Limited 26,600.00 0.00 Implementati 2021-08-10 2021-08-03 2021-10-05 2022-04-03 (HRMS) for the Directorate of Quotations Envelope Learning on Agriculture, Khanapara & Assam Agriculture University (AAU), Jorhat under APART. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-1741-CS-CQS / Consulting Services for Conducting Environmental and Social Assessment of the Consultant Project APART and Preparation / Post Qualification Open - National 103,470.00 105,933.49 Completed 2016-09-29 2016-02-17 2016-10-20 2016-12-03 2016-06-09 2017-01-02 2016-08-12 2017-02-06 2016-08-16 2017-08-05 2017-07-30 of management plans and/or Selection framework for managing Adverse Environmental and Social impacts, risks and benefits Page 9 IN-ARIAS-1954-CS-QCBS / Project Baseline Survey and Monitoring & Evaluation of the Component A: Enabling Agri Quality And Cost- proposed World Bank aided IBRD / 87800 Post Open - National 250,145.00 125,004.28 Signed 2016-09-30 2017-09-20 2016-10-28 2016-11-27 2017-09-26 2016-12-27 2017-11-13 2017-01-26 2017-11-15 2017-02-25 2018-01-02 2017-03-19 2018-01-18 2019-03-19 Enterprise Development Based Selection Assam Agribusiness & Rural Transformation Project (APART) IN-ARIAS-3143-CS-CQS / Consultancy Service to conduct "Diagnostic Study on Consultant Component A: Enabling Agri Finance Opportunities for IBRD / 87800 Post Qualification Open - National 75,758.00 112,402.44 Signed 2016-11-09 2018-01-22 2016-11-23 2016-12-22 2018-03-30 2017-01-01 2018-05-12 2017-01-03 2018-05-11 2017-04-03 Enterprise Development Producers and Micro Selection Entrepreneurs in the Selected Agri Value Chains" IN-ARIAS-5195-CS-QCBS / Consultancy Service for formation of Farmer Producer Component A: Enabling Agri Quality And Cost- IBRD / 87800 Post Open - National 1,014,706.00 587,327.38 Signed 2017-01-25 2018-03-05 2017-01-27 2017-04-03 2018-03-12 2017-05-03 2018-04-26 2017-06-17 2018-11-02 2017-07-04 2020-12-04 2017-08-04 2021-01-22 2020-08-03 Organizations(FPOs) for Zone Enterprise Development Based Selection 1(Lakhimpur, Sonitpur, Darrang, Nalbari and Barpeta) IN-ARIAS-5197-CS-QCBS / Consultancy Service for formation of Farmer Producer Component A: Enabling Agri Quality And Cost- Under IBRD / 87800 Post Open - National 1,014,706.00 632,889.98 2017-01-25 2018-03-05 2017-01-27 2017-04-03 2018-03-12 2017-05-03 2018-04-26 2017-06-17 2018-11-02 2017-07-04 2019-01-07 2017-08-04 2019-03-04 2020-08-03 Organizations(FPOs) for Zone Enterprise Development Based Selection Implementation 2(Sivasagar, Jorhat, Golaghat, Karbi-Anglong and Cachar) IN-ARIAS-5198-CS-QCBS / Consultancy Service for formation of Farmer Producer Component A: Enabling Agri Quality And Cost- Organizations(FPOs) for Zone IBRD / 87800 Post Open - National 1,014,706.00 756,742.76 Signed 2017-01-25 2018-03-05 2017-01-27 2017-04-03 2018-03-12 2017-05-03 2018-04-26 2017-06-17 2018-11-02 2017-07-04 2020-12-04 2017-08-04 2021-01-22 2020-08-03 Enterprise Development Based Selection 3(Nagaon, Morigaon, Kamrup, Goalpara, Dhubri and Kokrajhar) IN-ARIAS-5204-CS-QCBS / Sector and Subsector scan Component A: Enabling Agri Quality And Cost- IBRD / 87800 Post Open - National 132,353.00 69,023.18 Signed 2017-02-25 2017-10-06 2017-03-07 2017-05-12 2017-12-16 2017-06-09 2018-05-05 2017-07-24 2018-05-19 2017-08-02 2018-06-18 2017-09-02 2018-07-30 2018-09-02 study for Assam Burea of Enterprise Development Based Selection Investment Promotion (ABIP) IN-ARIAS-5206-CS-QCBS / Consultancy Services for Technical Assistance to Component A: Enabling Agri Quality And Cost- IBRD / 87800 Post Open - National 152,940.00 376,947.54 Signed 2017-05-02 2018-06-21 2017-05-04 2017-07-24 2019-02-25 2017-09-07 2020-01-08 2017-10-22 2020-01-08 2017-12-01 2020-02-01 2018-01-03 2020-06-01 2019-01-03 Stewardship Council in Enterprise Development Based Selection Fisheries, Piggery , Spices and Perishables IN-ARIAS-5230-CS-QCBS / Component A: Enabling Agri Quality And Cost- Consultancy Service for IBRD / 87800 Post Open - National 735,294.00 1,200,448.56 Signed 2017-03-03 2018-04-02 2017-03-08 2017-08-30 2017-05-03 2019-06-12 2017-06-17 2020-02-18 2017-08-01 2020-02-18 2017-08-23 2020-03-12 2017-10-07 2020-07-13 2024-10-05 Enterprise Development Based Selection Central IEC Campaign IN-ARIAS-8684-CS-CDS / Consultant Component A: Enabling Agri Muga seed production and IBRD / 87800 Post Qualification Open - National 30,770.00 27,190.18 Signed 2018-06-11 2019-01-03 2018-07-02 2018-08-15 2019-07-10 2018-09-14 2019-09-04 2018-10-19 2020-01-21 2019-01-17 Enterprise Development certification feasibility study Selection Consultant IN-ARIAS-10724-CS-CQS / Component A: Enabling Agri IBRD / 87800 Post Qualification Open - National 38,465.00 35,399.50 Signed 2018-02-27 2018-07-12 2018-03-04 2018-05-03 2018-11-01 2018-05-13 2018-11-01 2018-06-17 2018-10-25 2018-09-15 FISHFED Revival Study Enterprise Development Selection IN-ARIAS-5207-CS-QCBS / CDTA: Consultancy Services Component A: Enabling Agri Quality And Cost- IBRD / 87800 Prior Open - National 514,706.00 3,041,509.33 Signed 2017-12-30 2018-02-01 2018-01-03 2018-02-22 2018-02-12 2018-04-03 2018-07-16 2018-05-03 2018-09-27 2018-06-07 2019-02-22 2018-07-17 2019-05-24 2023-07-16 for hiring a Technical Agency Enterprise Development Based Selection for Cluster Development IN-ARIAS-5229-CS-CQS / Financial services diagnostic Consultant survey: Consulting Agency for Component A: Enabling Agri Under IBRD / 87800 Post Qualification Open - National 29,411.00 0.00 2018-01-03 2019-01-23 2018-01-09 2018-02-13 2018-02-15 2018-03-15 2018-09-11 conducting diagnostic survey Enterprise Development Implementation Selection for status of financial literacy of financial services IN-ARIAS-35798-CS-CQS / Hiring of Architectural Firm Consultant Component A: Enabling Agri for preparation design & plan IBRD / 87800 Post Qualification Open - National 13,235.00 13,812.16 Completed 2017-12-15 2018-01-08 2017-12-25 2018-01-28 2018-02-05 2018-02-17 2018-03-01 2018-03-24 2017-07-09 2018-06-22 2017-08-09 Enterprise Development etc for renovation of existing Selection PCU building IN-ARIAS-35802-CS-QBS / Fund Feasibility Study: Consultancy Services for Conducting Feasibility Component A: Enabling Agri Quality Based IBRD / 87800 Post Open - National 29,412.00 154,334.26 Signed 2017-12-29 2018-01-06 2018-01-03 2018-01-27 2018-01-11 2018-02-24 2018-03-12 2018-03-26 2018-03-19 2018-04-25 2018-04-05 2018-05-30 2018-04-11 2018-08-28 Assessment to set up an Enterprise Development Selection Investment Fund for Small and Medium Enterprises in the Agribusiness Sector of Assam IN-ARIAS-5205-CS-QCBS / Consultant Investment Fund Feasibility Component A: Enabling Agri / Post Qualification Open - National 29,412.00 0.00 Canceled 2017-01-31 2017-11-30 2017-02-21 2017-05-07 2017-06-06 2017-07-11 2017-10-09 Study and Preparation of TOR Enterprise Development Selection for hiring the Fund Manager IN-ARIAS-5335-CS-QCBS / Consultancy Services for hiring an Architectural Firm Component A: Enabling Agri Quality And Cost- / Post Open - National 729,412.00 0.00 Canceled 2017-02-14 2017-10-23 2017-03-07 2017-08-30 2017-05-21 2017-06-20 2017-08-04 2017-08-24 2017-09-21 2017-12-20 for Survey , Feasibility Studies, Enterprise Development Based Selection Design etc for Markets and Warehouses IN-ARIAS-42777-CS-CQS / Consultant ARIAS: Architectural Firm for Component A: Enabling Agri Under IBRD / 87800 Post Qualification Open - National 23,077.00 0.00 2018-02-28 2018-12-03 2018-03-05 2018-03-15 2018-03-25 2018-04-23 2018-05-23 Interior design of PCU Enterprise Development Implementation Selection building (Pt-A) Page 10 IN-ARIAS-8972-CS-QCBS / Market-Warehouse: Consultancy services for Survey, Feasibility Study, Design, Layout, DPR Component A: Enabling Agri Quality And Cost- Preparation, for IBRD / 87800 Post Open - National 1,686,154.00 0.00 Canceled 2018-03-26 2018-04-06 2018-03-31 2018-04-07 2018-05-21 2018-06-20 2018-08-04 2018-09-02 2018-10-08 2022-10-07 Enterprise Development Based Selection modernization & upgradation of Agricultural & allied Markets and Warehouses and Technical Quality Assurance during construction period IN-ARIAS-48691-CS-CQS / Eri&Muga: Market players, Consultant Component A: Enabling Agri market share, market size and IBRD / 87800 Post Qualification Open - National 38,462.00 42,231.25 Signed 2018-02-26 2018-08-06 2018-02-26 2018-04-11 2018-12-01 2018-05-06 2019-01-10 2018-06-10 2019-03-13 2018-09-08 Enterprise Development growth trends study of eri and Selection muga silk in Assam & India IN-ARIAS-48699-CS-CQS / GIFT: Consultancy services for Consultant rapid risk assessment of the Component A: Enabling Agri IBRD / 87800 Post Qualification Open - National 40,000.00 0.00 Under Review 2018-02-26 2018-04-09 2018-02-26 2018-05-01 2018-07-02 2018-05-21 2018-07-27 2018-06-19 2018-09-02 potential invasiveness of Enterprise Development Selection Genetiaclly Improved Farmed Tilapia (GIFT) IN-ARIAS-48705-CS-QCBS / EDPF: Consultancy Service for Component A: Enabling Agri Quality And Cost- setting up and Managing IBRD / 87800 Prior Open - National 3,076,923.00 0.00 Canceled 2018-03-15 2018-03-06 2018-04-05 2018-03-09 2018-05-19 2019-02-28 2018-06-16 2018-12-14 2018-07-31 2019-08-25 2018-09-04 2018-10-09 2024-10-07 Enterprise Development Based Selection Enterprise Development Promotion Facility (EDPF) IN-ARIAS-5203-CS-QCBS / EDPF: Consultancy Service for Component A: Enabling Agri Quality And Cost- setting up and Managing / Post Open - National 773,530.00 0.00 Canceled 2017-01-06 2018-01-30 2017-02-01 2017-04-14 2017-04-17 2017-06-06 2017-07-01 2017-08-01 2019-08-01 Enterprise Development Based Selection Enterprise Development Promotion Facility (EDPF) IN-ARIAS-8693-CS-CDS / Silkworm disease study: Consultant Study on threats to Assam Component A: Enabling Agri IBRD / 87800 Post Qualification Open - National 29,412.00 43,255.99 Signed 2018-10-22 2019-01-02 2018-11-01 2018-12-16 2019-07-10 2019-01-15 2019-09-04 2019-02-09 2020-01-21 2019-05-10 silkworm industry from Enterprise Development Selection disease, and key solutions to manage them. IN-ARIAS-8689-CS-CDS / Seri: Silk food plantation Consultant entrepreneurship: Feasibility Component A: Enabling Agri IBRD / 87800 Post Qualification Open - National 30,770.00 0.00 Under Review 2018-07-16 2019-01-05 2018-08-06 2018-09-19 2018-10-19 2018-11-23 2019-05-22 study of an entrepreneurship Enterprise Development Selection model in silk food plantation through vegetative nurseries. IN-ARIAS-8969-CS-CQS / Weavers' Needs Study: Consultant Component A: Enabling Agri Pending Consultancy services for IBRD / 87800 Post Qualification Open - National 38,465.00 0.00 2018-12-17 2018-12-22 2019-02-10 2019-02-20 2019-03-16 2019-06-14 Enterprise Development Implementation conducting Diagnostic Study Selection on Weavers' Needs IN-ARIAS-49496-CS-CQS / Consultant Component A: Enabling Agri Under WAMUL : HACCP study for IBRD / 87800 Post Qualification Open - National 12,308.00 0.00 2018-05-14 2020-02-13 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-06-18 Enterprise Development Implementation complete value chain Selection IN-ARIAS-49498-CS-CQS / Consultant Component A: Enabling Agri Under WAMUL : Benchmarking of IBRD / 87800 Post Qualification Open - National 15,385.00 0.00 2018-05-28 2020-02-13 2018-06-18 2018-08-01 2018-08-31 2018-10-05 2019-07-02 Enterprise Development Implementation various operating parameters Selection IN-ARIAS-4490-CS-LCS / Hiring a Human Resource Agency for facilitating recruitment of Senior Component A: Enabling Agri Least Cost Specialists for the proposed / Post Open - National 76,471.00 0.00 Canceled 2016-12-13 2017-01-16 2016-12-20 2017-01-24 2017-05-04 2017-02-23 2017-03-16 2017-03-29 2017-04-16 2018-04-11 Enterprise Development Selection World Bank aided Project Assam Agribusiness and Rural Transformation Project (APART) IN-ARIAS-5210-CS-QCBS / Consultancy Service for Component A: Enabling Agri Quality And Cost- Technical Assistance on IBRD / 87800 Post Open - National 831,470.00 0.00 Canceled 2017-05-22 2018-02-19 2017-05-26 2017-07-31 2017-09-14 2017-10-29 2017-11-28 2018-01-03 2025-01-01 Enterprise Development Based Selection setting up of Market Intelligence Cell IN-ARIAS-5351-CS-LCS / Component D: Project ARIAS : Consultancy service to Least Cost Pending IBRD / 87800 Management, Monitoring and Post Open - National 73,529.00 0.00 2019-08-01 2019-08-03 2019-10-08 2019-11-22 2020-01-06 2020-02-10 2020-03-16 2025-03-15 conduct Internal Procurement Selection Implementation Learning audits(for 5 years) IN-ARIAS-5208-CS-QCBS / Hiring of a Training and Capacity Building Agency for Component A: Enabling Agri Quality And Cost- IBRD / 87800 Post Open - National 514,706.00 0.00 Canceled 2018-05-07 2018-05-13 2018-07-27 2018-08-24 2018-09-13 2018-09-27 2018-10-28 2022-10-27 preparation of modules and Enterprise Development Based Selection imparting training to the project stakeholders IN-ARIAS-5232-CS-QCBS / PCU : Hiring of Software Component D: Project Quality And Cost- Pending Development agency for IBRD / 87800 Management, Monitoring and Post Open - National 446,154.00 0.00 2019-06-03 2019-06-07 2019-08-16 2019-09-15 2019-10-15 2019-12-04 2020-01-04 2020-09-30 Based Selection Implementation Project MIS and Management Learning support IN-ARIAS-5339-CS-QCBS / Hiring of software development agency for developing mobile based Component D: Project Quality And Cost- Pending application for community led IBRD / 87800 Management, Monitoring and Post Open - National 179,412.00 0.00 2018-12-12 2018-12-16 2019-03-01 2019-03-29 2019-04-28 2019-06-18 2019-07-23 2024-11-10 Based Selection Implementation procurement for facilitation, Learning monitoring support for 7 years and database generation. IN-ARIAS-76149-CS-CQS / Component D: Project Consultant Labour Influx : Study on IBRD / 87800 Management, Monitoring and Post Qualification Open - National 35,400.00 18,827.40 Signed 2019-01-07 2018-12-24 2019-01-28 2019-03-13 2019-01-23 2019-04-12 2019-07-26 2019-05-17 2019-07-26 2019-09-14 Labour Influx under the Civil Learning Selection Works of APART Page 11 IN-ARIAS-5345-CS-QBS- REBID / TA for ABIP: Providing Component A: Enabling Agri Quality Based Technical Assistance to the IBRD / 87800 Post Open - National 1,470,588.00 1,705,763.74 Signed 2018-11-01 2019-03-01 2018-11-22 2019-01-05 2019-03-02 2019-02-04 2019-05-20 2019-03-06 2019-08-31 2019-03-26 2020-01-21 2019-04-30 2020-05-15 2023-04-29 Enterprise Development Selection Assam Bureau of Investment Promotion (ABIP) IN-ARIAS-5345-CS-QCBS / TA for ABIP: Consultancy Agency for Providing Component A: Enabling Agri Quality And Cost- IBRD / 87800 Post Open - National 1,470,588.00 0.00 Canceled 2018-01-03 2017-12-26 2018-01-07 2018-02-21 2018-01-10 2018-04-07 2018-06-27 2018-05-07 2018-08-06 2018-06-21 2018-09-17 2018-07-26 2022-07-25 Technical Assistance to Assam Enterprise Development Based Selection Bureau of Investment Promotion (ABIP) IN-ARIAS-5350-CS-QCBS / PCU : Hiring a Fund Manager Component A: Enabling Agri Quality And Cost- Under for setting up and managing IBRD / 87800 Prior Open - International 4,633,571.00 0.00 2019-03-07 2019-03-07 2019-03-07 2019-03-07 2019-04-20 2019-05-18 2019-06-17 2019-07-22 2019-08-26 2025-08-24 Enterprise Development Based Selection Implementation an Agribusiness Investment Fund IN-ARIAS-104630-CS-QCBS / Financial Education & Component C: Fostering Counselling : Consultancy Quality And Cost- Pending IBRD / 87800 Market-led Production and Prior Open - International 2,007,143.00 0.00 2019-05-21 2019-06-11 2019-07-25 2019-08-22 2019-09-21 2019-10-26 2019-11-30 2024-08-09 services to develop financial Based Selection Implementation Resilience Enhancement education and counselling program for farmers IN-ARIAS-104684-CS-CQS / Legal Counsel : hiring the Consultant Consultancy Services of a Component A: Enabling Agri IBRD / 87800 Post Qualification Open - National 70,000.00 50,090.06 Signed 2019-03-07 2019-03-07 2019-03-28 2019-05-11 2020-02-13 2019-06-10 2020-04-17 2019-07-15 2020-06-18 2021-03-06 Corporate Law Firm as Legal Enterprise Development Selection Counsel for An Agribusiness Investment Fund IN-ARIAS-93109-CS-CQS / Baseline Environmental Component D: Project Consultant Monitoring : Consultancy IBRD / 87800 Management, Monitoring and Post Qualification Open - National 36,923.00 35,798.63 Signed 2019-03-20 2018-12-24 2019-05-24 2019-06-01 2019-03-06 2019-07-01 2019-05-28 2019-08-05 2019-06-04 2020-02-01 Services for conducting Learning Selection Baseline Environmental Monitoring for APART IN-ARIAS-105830-CS-CQS / PCU-CA Firm: Conducting Audit of the Accounts of the Component D: Project Consultant ARIAS Society (both for APART IBRD / 87800 Management, Monitoring and Post Qualification Open - National 10,000.00 8,931.37 Signed 2019-03-15 2019-07-01 2019-05-24 2019-06-14 2019-10-22 2019-06-29 2019-11-18 2019-06-29 2019-11-18 2019-08-28 & ACCSDP) and Sample Learning Selection Verification of the Procurements & Physical Assets Created IN-ARIAS-105284-CS-QCBS / PCU MW-1 : Consulting Service for "Survey, Feasibility Study, Design and Layout, Component B: Facilitating Quality And Cost- Pending DPR Preparation for IBRD / 87800 Post Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Based Selection Implementation Modernization and Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-1)" IN-ARIAS-105288-CS-QCBS / PCU MW-2 : Consulting Service for "Survey, Feasibility Study, Design and Layout, Component B: Facilitating Quality And Cost- Pending DPR Preparation for IBRD / 87800 Post Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Based Selection Implementation Modernization and Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-2)" IN-ARIAS-105290-CS-QCBS / PCU MW-3 : Consulting Service for "Survey, Feasibility Study, Design and Layout, Component B: Facilitating Quality And Cost- Pending DPR Preparation for IBRD / 87800 Post Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Based Selection Implementation Modernization and Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-3)" IN-ARIAS-105299-CS-QCBS / PCU MW-4 : Consulting Service for "Survey, Feasibility Study, Design and Layout, Component B: Facilitating Quality And Cost- Pending DPR Preparation for IBRD / 87800 Post Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Based Selection Implementation Modernization and Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-4)" IN-ARIAS-105300-CS-QCBS / PCU MW-5 : Consulting Service for "Survey, Feasibility Study, Design and Layout, Component B: Facilitating Quality And Cost- Pending DPR Preparation for IBRD / 87800 Post Open - National 221,429.00 0.00 2019-03-18 2019-05-27 2019-06-20 2019-07-18 2019-08-17 2019-09-21 2019-10-26 2020-10-25 Agro Cluster Development Based Selection Implementation Modernization and Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-5)" IN-ARIAS-157949-CS-QCBS / Direct RFP for ACFIFA : Hiring of the Implementing agency for Assam Challenge Component C: Fostering Fund for Innovative Finance in Quality And Cost- IBRD / 87800 Market-led Production and Post Open - National 778,571.00 292,235.97 Signed 2020-02-16 2020-01-16 2020-03-08 2020-03-11 2020-04-21 2020-05-31 2020-05-19 2020-05-29 2020-06-18 2020-06-20 2020-07-23 2020-08-19 2020-08-27 2020-11-10 2024-09-30 Agriculture (ACFIFA) for Based Selection Resilience Enhancement supporting innovative approaches to deliver financial services at scale for value chains under APART IN-ARIAS-49490-CS-CQS / WAMUL : Techno-commercial Consultant Component A: Enabling Agri feasibility study and DPR IBRD / 87800 Post Qualification Open - National 15,385.00 0.00 Canceled 2018-06-25 2018-07-16 2018-08-29 2018-09-28 2018-11-02 2019-05-01 Enterprise Development preparation for milk Selection processing infrastructure Page 12 IN-ARIAS-188261-CS-QBS / Direct RFP: Engaging Service provider for providing Component A: Enabling Agri Quality Based IBRD / 87800 Post Open - National 779,597.14 1,035,193.95 Signed 2020-08-17 2020-08-14 2020-09-08 2021-03-31 2020-10-22 2020-08-17 2020-11-19 2020-10-05 2020-12-19 2020-11-27 2021-01-18 2021-01-29 2021-02-22 2021-02-01 2022-02-22 incubation and acceleration Enterprise Development Selection support to the Agri enterprises under APART IN-ARIAS-245760-CS-QCBS / Direct RFP: For hiring a Component D: Project Quality And Cost- Pending consultancy firm for IBRD / 87800 Management, Monitoring and Post Open - National 400,000.00 0.00 2021-07-31 2021-08-21 2021-10-04 2021-11-01 2021-12-01 2022-01-05 2022-02-09 2024-10-03 Based Selection Implementation Monitoring and Evaluation of Learning APART. IN-ARIAS-248046-CS-QBS / Direct RFP: Hiring of Service Component C: Fostering Quality Based Pending Provider for implementing IBRD / 87800 Market-led Production and Post Open - National 512,363.00 0.00 2021-08-23 2021-09-13 2021-10-27 2021-11-24 2021-12-24 2022-01-23 2022-02-27 2024-09-30 Selection Implementation Financial Education and Resilience Enhancement Counselling under APART INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-2159-CS-CDS / Consultancy assignment for conducting for 'as is' assessment of the District / Post Direct Selection Direct 15,606.00 16,008.08 Completed 2016-10-04 2016-11-03 2016-10-07 2016-06-01 2016-10-07 2016-06-01 2016-11-06 2016-07-01 Industries & Commerce Centers (DICC) in selected districts of Assam IN-ARIAS-2829-CS-CDS / Consultancy Service Data / Post Direct Selection Direct 45,742.00 47,137.95 Signed 2016-11-03 2016-11-07 2016-11-05 2017-08-28 2016-11-12 2016-11-15 2017-01-11 validation for sectoral interventions under APART IN-ARIAS-2163-CS-CDS / Study on 'Preparation of draft District Agro Industrial Cluster Development Plan' (DAICDP) in the districts of Nagaon & Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 34,858.00 31,532.78 Completed 2016-10-04 2016-10-07 2017-09-18 2016-10-20 2016-06-01 2016-12-19 2016-07-30 Darrang for the proposed Enterprise Development World Bank aided Assam Agri- Business and Rural Transformation Project (APART) IN-ARIAS-5328-CS-CDS / ILRI: Technical Assistance for Component A: Enabling Agri the Livestock (Dairy & Piggery) IBRD / 87800 Prior Direct Selection Direct 1,427,858.00 1,429,576.56 Signed 2018-01-17 2018-02-02 2018-02-01 2018-02-23 2018-03-15 2018-03-16 2023-03-14 Enterprise Development Sub-Component of the World Bank Financed APART IN-ARIAS-5329-CS-CDS / WVC: Technical Advisory Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 1,400,197.00 1,400,197.00 Signed 2018-01-15 2018-01-12 2018-02-14 2018-02-01 2018-04-01 2018-03-16 2023-03-31 Assistance to APART for the Enterprise Development Vegetable Value Chains IN-ARIAS-5325-CS-QCBS / WF: Technical Assistance for Component A: Enabling Agri the Fisheries Sub-Component IBRD / 87800 Prior Direct Selection Direct 1,062,699.00 1,062,699.00 Signed 2017-12-26 2018-01-08 2018-01-03 2018-02-01 2018-01-23 2018-08-10 2023-01-22 Enterprise Development of the World Bank Financed APART IN-ARIAS-5327-CS-CDS / IRRI: Technical Assistance To Increasing Productivity And Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 8,000,000.00 4,577,412.00 Signed 2018-01-10 2018-01-25 2018-01-31 2018-02-20 2018-04-02 2018-03-16 2025-03-31 Profitability of Small And Enterprise Development Marginal Farmers In Rice- Based Cropping Systems IN-ARIAS-1740-CS-CDS / Technical collaborative support by WorldFish during the design phase of APART with thrust on market-led Component A: Enabling Agri climate smart intensification IBRD / 87800 Post Direct Selection Direct 33,824.00 34,401.66 Completed 2017-12-22 2018-01-06 2017-12-31 2018-01-22 2018-01-08 2016-09-15 2018-03-13 2016-11-15 Enterprise Development of production systems, setting up of farmers' Common Service Centres (managed by FPOs) and implement value chain plans IN-ARIAS-40003-CS-CDS / CIP: Technical Assistance for improving farmers' livelihoods through sustainable Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 3,348,378.00 3,348,378.00 Signed 2018-01-10 2018-01-12 2018-01-20 2018-01-29 2018-03-06 2018-03-16 2023-03-05 intensification & Enterprise Development diversification of agri food systems with Climate Smart Potato Technologies IN-ARIAS-5332-CS-CDS / NRC-P: Consultancy Services Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 242,308.00 0.00 Canceled 2018-01-17 2018-02-11 2018-04-23 2023-04-22 of National Research Centre Enterprise Development on Pig IN-ARIAS-47147-CS-CDS / NRC-P: Consultancy Services to support the Pork Value Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 242,308.00 231,006.20 Signed 2018-02-28 2018-02-28 2018-03-10 2018-05-28 2018-04-04 2018-07-12 2023-04-03 Chain interventions by ICAR- Enterprise Development National Research Centre on Pig (NRC-P) IN-ARIAS-5330-CS-CDS / WUR: Pilot Implementation Component A: Enabling Agri IBRD / 87800 Prior Direct Selection Direct 1,825,820.00 0.00 Canceled 2018-01-31 2018-02-25 2018-04-16 2023-04-15 and Redesign of Agri-Food Enterprise Development value Chains under APART Page 13 IN-ARIAS-78907-CS-CDS / Component D: Project Individual PCU : Engagement of Auditor Pending IBRD / 87800 Management, Monitoring and Post Consultant Direct 2,000.00 0.00 2019-02-18 2019-02-28 2019-03-21 2019-04-25 2019-06-24 for conducting audit of ARIAS Implementation Learning Selection for Financial Year 2017-18 IN-ARIAS-88761-CS-INDV / Counsel : Individual Component D: Project Individual consultant to advice the PCU IBRD / 87800 Management, Monitoring and Prior Consultant Open 2,769,231.00 0.00 Canceled 2019-08-04 2019-09-22 2019-10-13 2019-11-17 2024-11-15 on the establishment of the Learning Selection Investment fund IN-ARIAS-112738-CS-INDV / PCU - Tech Expert : Technical Individual Component A: Enabling Agri Pending Expert to Support the IBRD / 87800 Post Consultant Direct 19,800.00 0.00 2019-08-01 2019-08-11 2019-09-01 2019-10-06 2019-11-05 Enterprise Development Implementation Procurement of Agri Business Selection Investment Fund Manager IN-ARIAS-118406-CS-INDV / SABA : Hiring of a short term Component D: Project Individual Pending Senior Agri Business Advisor IBRD / 87800 Management, Monitoring and Post Consultant Direct 12,857.00 0.00 2019-07-22 2019-08-01 2019-08-22 2019-09-26 2020-03-24 Implementation (SABA) As Consultant for Learning Selection APART IN-ARIAS-161904-CS-CDS / Technical advisory support on Component D: Project Augmenting Rapeseed- IBRD / 87800 Management, Monitoring and Post Direct Selection Direct 617,413.00 577,807.92 Signed 2020-03-03 2020-03-03 2020-03-13 2020-03-05 2020-05-07 2020-04-28 2024-05-06 Mustard Production of Assam Learning Farmers for Sustainable Livelihood Security Component D: Project Individual IN-ARIAS-200854-CS-INDV / Pending IBRD / 87800 Management, Monitoring and Post Consultant Open 51,200.00 0.00 2020-10-28 2020-12-16 2021-01-06 2021-02-10 2025-02-09 Hiring of Legal Advisor Implementation Learning Selection IN-ARIAS-231230-CS-CDS / OKDISCD: Engagement of Omeo Kumar Das Institute of Component D: Project Social Change and IBRD / 87800 Management, Monitoring and Post Direct Selection Direct 515,374.00 0.00 Under Review 2021-06-10 2021-06-10 2021-06-20 2021-08-03 2024-10-06 Development as Monitoring & Learning Evaluation Agency under APART IN-ARIAS-245711-CS-CDS / CDS: For hiring a short term consulting firm for designing Component D: Project the data collection formats for IBRD / 87800 Management, Monitoring and Post Direct Selection Direct 25,000.00 0.00 Under Review 2021-07-31 2021-07-31 2021-08-10 2021-10-14 2022-02-11 M&E of APART and one time Learning evaluation of a few selected activities under the project. Page 14