Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan May 29, 2015 2. Date of General Procurement Notice: July 25, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year June 2016 to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) All 2. NCB (Goods) Above US$ 2,000,000 3. ICB (Works) All 4. NCB (Works) Above US$ 10,000,000 2. Pre-qualification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: June 2, 2015. 4. Any Other Special Procurement Arrangement: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / million Post) 1 Summary of the 2.61 12 No Prior/Post NCB (Works) 2 Summary of the 4.50 25 No Prior/Post NCB (Goods) 3 Summary of 1.06 18 No Post Shopping packages (Goods, Works and Non- Consulting Services) III. Selection of Consultants March 29, 2017 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$1,000,000 2. Single Source (Firms) For SSS, USD50,000 (Para 3.9 of Consultant Guidelines, January 2011) and all other SSS contracts. 3. Individual Individuals ≥ USD 0.3 million; and for essential assignments (procurement / legal consultant). For SSS, USD20,000 (Para 5.6 of Consultant Guidelines, January 2011) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimated Packages Review Comments of Cost by Bank Assignment US$ (Prior / million Post) Summary of 1.40 1 Prior QCBS number of contracts that will be let under QCBS Summary of 8.14 88 Prior/Post CQS/IC number of contracts that will be let under other methods March 29, 2017 PROCUREMENT Vietnam : Sustainable Agriculture Transformation Project PLAN General Information Country: Vietnam Banks Approval Date of the Original Procurement Plan: 2016-08-08 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-21 Project ID: P145055 GPN Date: 2016-07-25 Project Name: Sustainable Agriculture Transformation Project Loan / Credit No: IDA / 57040 Executing Agency(ies): Department of Planning of MARD, Central Project Management Unit for Vn-SAT, Can Tho City Project Management Unit, Tien Giang Province Project Management Unit, Dak Nong Province Project Management Unit, Long An Province Project Management Unit, Soc Trang Province Project Management Unit, Lam Dong Province Project Management Unit, Kon Tum Province Proje WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C: Supporting Sustainable Coffee Production Request for Single Stage - One XL09 / Upgrading office IDA / 57040 and Rejuvenation Post Open - National 65,000.00 50,669.84 Signed 2016-12-04 2017-02-03 2017-10-20 2017-06-03 Quotations Envelope Component D: Project Management Component C: Supporting Sustainable Coffee Production Request for Single Stage - One XL14 / Upgrading office IDA / 57040 and Rejuvenation Prior Open - National 65,000.00 0.00 Canceled 2016-12-01 2017-01-26 2017-05-25 Quotations Envelope Component D: Project Management Component C: Supporting Sustainable Coffee Production Request for Single Stage - One XL-14 / Upgrading office IDA / 57040 and Rejuvenation Post Open - National 65,000.00 62,547.42 Completed 2016-12-01 2017-01-26 2017-02-14 2017-05-26 2017-05-12 Quotations Envelope Component D: Project Management Component C: Supporting Single Stage - One Pending XL-19 / Upgrading Nursey IDA / 57040 Sustainable Coffee Production Post Request for Bids Open - National 200,000.00 0.00 2017-02-10 2017-03-02 2017-03-23 2017-05-03 2017-06-09 2017-11-12 Envelope Implementation and Rejuvenation Component C: Supporting Single Stage - One XL19 / Upgrading nursey IDA / 57040 Sustainable Coffee Production Prior Request for Bids Open - National 200,000.00 0.00 Canceled 2016-11-29 2016-12-19 2017-01-09 2017-02-19 2017-02-28 2017-08-31 Envelope and Rejuvenation Component B: Supporting XL04 / Civil works for DARD and Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 205,000.00 0.00 Canceled 2017-03-10 2017-03-15 2017-04-26 2017-05-26 2017-06-30 2017-12-27 revelant departments Envelope Systems Component C: Supporting Single Stage - One XL11 / Upgrading nursey IDA / 57040 Sustainable Coffee Production Prior Request for Bids Open - National 200,000.00 0.00 Canceled 2016-12-30 2017-01-13 2017-02-24 2017-04-10 2017-04-24 2017-11-24 Envelope and Rejuvenation Component C: Supporting Single Stage - One Pending XL-11 / Upgrading nursey IDA / 57040 Sustainable Coffee Production Post Request for Bids Open - National 200,000.00 0.00 2017-03-01 2017-03-08 2017-04-08 2017-05-08 2017-05-29 2017-11-25 Envelope Implementation and Rejuvenation Component B: Supporting XL02-DT / Civil works for DARD Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 205,000.00 0.00 Canceled 2017-01-20 2017-01-25 2017-03-08 2017-04-07 2017-05-12 2017-09-01 and revelant deparment Envelope Systems XL03 / Civil works for DARD and Component B: Supporting revelant deparment. This Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 310,000.00 0.00 Canceled 2016-09-20 2016-09-25 2016-11-06 2016-12-06 2017-01-10 2017-05-10 construction is for the laboratory Envelope Systems and storage units. Component B: Supporting Sustainable Rice-Based XL-07 / Civil works for DARD and Systems Single Stage - One IDA / 57040 Post Request for Bids Open - National 205,000.00 82,938.61 Signed 2017-02-01 2017-09-05 2017-02-06 2017-03-20 2017-09-18 2017-04-19 2017-10-10 2017-05-24 2017-10-16 2017-11-20 revelants department Component C: Supporting Envelope Sustainable Coffee Production and Rejuvenation Component B: Supporting Sustainable Rice-Based XL07 / Civil works for DARD and Single Stage - One IDA / 57040 Systems Prior Request for Bids Open - National 205,000.00 0.00 Canceled 2016-09-01 2016-10-01 2016-11-12 2016-12-12 2017-01-16 2017-07-15 revelant departments Envelope Component D: Project Management Component C: Supporting XL13 / Upgrating nursery Single Stage - One IDA / 57040 Sustainable Coffee Production Prior Request for Bids Open - National 260,000.00 0.00 Canceled 2016-10-02 2017-01-02 2017-02-02 2017-02-16 2017-04-02 2017-09-29 gardens Envelope and Rejuvenation Component C: Supporting XL-13 / Upgrading nursery Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Request for Bids Open - National 260,000.00 0.00 2017-02-09 2017-02-13 2017-03-15 2017-04-14 2017-05-19 2017-11-15 gardens Envelope Implementation and Rejuvenation Component B: Supporting XL06 / Civil works for DARD and Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 205,000.00 0.00 Canceled 2016-10-14 2016-10-19 2016-11-30 2016-12-30 2017-02-03 2017-08-02 revelant departments Envelope Systems Component B: Supporting XL05 / Civil works for DARD and Single Stage - One Under IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 205,000.00 0.00 2017-06-01 2017-09-12 2017-06-06 2017-07-06 2017-10-23 2017-08-20 2017-09-25 2018-03-04 provincial agencies Envelope Implementation Systems Component B: Supporting XL-06 / Civil works for DARD and Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 205,000.00 0.00 Canceled 2017-02-06 2017-02-11 2017-03-25 2017-04-24 2017-05-29 2017-11-25 revelant departments. Envelope Systems Component B: Supporting XL/06 / Civil works for DARD and Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 163,636.00 0.00 2017-09-04 2017-10-30 2018-03-29 revelant department Quotations Envelope Implementation Systems Component B: Supporting XL01 / Civil works to DARD and Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 205,000.00 0.00 2018-01-28 2018-02-02 2018-03-16 2018-04-15 2018-05-20 2018-10-17 relevant department Envelope Implementation Systems Page 1 Component B: Supporting XL02 / Civil Works for DARD and Request for Single Stage - One IDA / 57040 Sustainable Rice-Based Post Open - National 37,971.00 36,947.13 Signed 2017-10-24 2017-12-19 2017-12-18 2018-06-17 revelant deparmer Quotations Envelope Systems Component B: Supporting Sustainable Rice-Based XL 03 / Civil works for DARD and Single Stage - One Pending IDA / 57040 Systems Post Request for Bids Open - National 370,000.00 0.00 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 2018-08-01 revelant department Envelope Implementation Component D: Project Management Component B: Supporting XL-03 / Civil works for DARD and Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 310,000.00 0.00 Canceled 2017-03-03 2017-03-08 2017-04-19 2017-05-19 2017-06-23 2017-12-20 revelant deparment Envelope Systems Component B: Supporting XL-04 / Civil works for DARD and Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 205,000.00 0.00 Canceled 2017-03-10 2017-03-15 2017-04-26 2017-05-26 2017-06-30 2018-02-28 revelant departments Envelope Systems Component C: Supporting XL10 / Upgrading first line seed Request for Single Stage - One IDA / 57040 Sustainable Coffee Production Post Open - National 40,000.00 0.00 Canceled 2017-01-16 2017-03-27 2017-09-27 nursey Quotations Envelope and Rejuvenation Component B: Supporting Sustainable Rice-Based XL 04 / Civil works for DARD and Request for Single Stage - One Pending IDA / 57040 Systems Post Open - National 178,000.00 0.00 2017-12-06 2018-01-31 2018-07-10 revelant departments Quotations Envelope Implementation Component D: Project Management Component C: Supporting Sustainable Coffee Production Request for Single Stage - One Pending XL17 / Upgrading office IDA / 57040 and Rejuvenation Post Open - National 65,000.00 0.00 2016-12-16 2017-02-15 2017-05-15 Quotations Envelope Implementation Component D: Project Management Component C: Supporting XL18 / Upgrading first line seed Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 40,000.00 0.00 2016-12-23 2017-02-22 2017-08-21 nursey Quotations Envelope Implementation and Rejuvenation Component C: Supporting XL VUTN DN 01 / Upgrading Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 106,120.00 0.00 2018-04-17 2018-06-12 2018-09-10 nurseries (Private sector support) Quotations Envelope Implementation and Rejuvenation Component C: Supporting Sustainable Coffee Production XL 20 / Office upgrades (PPMU Request for Single Stage - One Pending IDA / 57040 and Rejuvenation Post Open - National 65,000.00 0.00 2018-03-19 2018-05-14 2018-11-10 and support units) Quotations Envelope Implementation Component D: Project Management Component C: Supporting XL 22 / Construction of the Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 40,000.00 0.00 2018-03-21 2018-05-16 2018-07-15 nursery of the first line Quotations Envelope Implementation and Rejuvenation Component C: Supporting XL 21 / Upgrading nursery Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 58,642.00 0.00 2018-03-19 2018-05-14 2018-08-12 (Government) Quotations Envelope Implementation and Rejuvenation XLLD01 / Support infrastructure Component C: Supporting for subtainable coffee Phuc Lien Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 171,606.00 0.00 2018-05-09 2018-06-12 2018-12-09 group, Lien Ha comune, Lam Ha Quotations Envelope Implementation and Rejuvenation district XLLD02 / Support infrastructure Component C: Supporting for subtainable coffee Dang Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Request for Bids Open - National 231,036.00 0.00 2018-05-04 2018-05-09 2018-06-08 2018-06-28 2018-07-12 2019-01-08 Quang group, Gung Re comune, Envelope Implementation and Rejuvenation Di Linh district Component C: Supporting XL15 / Upgrading of first line Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 20,000.00 0.00 2018-06-01 2018-08-01 2018-10-30 seed nursey Quotations Envelope Implementation and Rejuvenation Component C: Supporting Request for Single Stage - One Pending XL16 / Upgrading of nursey IDA / 57040 Sustainable Coffee Production Post Open - National 100,000.00 0.00 2018-07-02 2018-08-16 2018-11-14 Quotations Envelope Implementation and Rejuvenation Component C: Supporting XLKT01 / Upgrading Quy Ha and Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 39,189.00 0.00 2018-06-01 2018-08-03 2018-11-01 Minh Truong private nurseries Quotations Envelope Implementation and Rejuvenation GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component D: Project Single Stage - One HH04 / Office equipment IDA / 57040 Prior Request for Bids Open - National 134,000.00 92,444.65 Completed 2016-08-29 2016-10-27 2016-09-09 2016-10-14 2016-12-05 2016-11-01 2017-02-14 2016-11-16 2017-03-10 2017-01-16 2017-05-31 Management Envelope Component B: Supporting HH05 / Communication Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 114,362.92 Signed 2016-09-19 2016-10-31 2016-09-24 2016-10-28 2016-11-30 2016-11-14 2016-11-29 2016-12-30 2017-07-31 materials Envelope Systems Component A: Institutional Request for Single Stage - One HH40 / Office equipment IDA / 57040 Strengthening to Support Prior Open - National 90,000.00 59,536.13 Signed 2016-08-10 2016-09-08 2017-03-06 2016-10-31 Quotations Envelope Agricultural Transformation Component A: Institutional HH39 / Software for selected Single Stage - One Pending IDA / 57040 Strengthening to Support Post Request for Bids Open - National 100,000.00 0.00 2017-03-05 2017-03-12 2017-03-19 2017-03-30 2017-04-06 2017-07-30 renovation programs Envelope Implementation Agricultural Transformation Component B: Supporting HH29 / Equipment for seed Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 84,000.00 0.00 2016-10-06 2016-12-01 2017-05-30 center Quotations Envelope Implementation Systems Component C: Supporting DN-HH33 / Procurement of Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 25,000.00 0.00 2016-08-31 2016-10-12 2016-10-26 Equipment for Laboratories Quotations Envelope Implementation and Rejuvenation Page 2 Component D: Project Single Stage - One HH07 / Office equipment IDA / 57040 Prior Request for Bids Open - National 210,000.00 126,134.79 Signed 2016-09-01 2016-10-12 2016-09-06 2016-10-26 2016-11-30 2016-11-10 2017-02-13 2016-12-04 2017-02-22 2017-03-06 Management Envelope Component B: Supporting HH08 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2016-10-01 2016-10-06 2016-11-17 2016-12-17 2017-01-21 2018-04-20 materials Envelope Implementation Systems Component B: Supporting Single Stage - One HH22 / Office equipment IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 168,000.00 148,988.22 Signed 2016-09-05 2016-10-27 2016-09-10 2016-10-25 2016-12-26 2016-11-24 2017-04-18 2016-12-25 2017-06-02 2017-06-23 Envelope Systems Component C: Supporting Sustainable Coffee Production Request for Single Stage - One HH35 / Office equipment IDA / 57040 and Rejuvenation Prior Open - National 60,000.00 48,567.52 Signed 2016-07-04 2016-09-26 2016-12-22 2016-12-26 Quotations Envelope Component D: Project Management Component C: Supporting HH36 / Equipment for Request for Single Stage - One IDA / 57040 Sustainable Coffee Production Post Open - National 25,000.00 23,953.37 Completed 2016-09-19 2016-11-11 2016-12-24 2017-01-23 2017-02-10 laboratories Quotations Envelope and Rejuvenation Component C: Supporting Sustainable Coffee Production Request for Single Stage - One HH37 / Office equipment IDA / 57040 and Rejuvenation Post Open - National 61,000.00 58,867.18 Completed 2016-09-01 2016-10-16 2016-10-17 2017-02-16 2016-11-16 Quotations Envelope Component D: Project Management Component C: Supporting HH38 / Equipment for Request for Single Stage - One Under IDA / 57040 Sustainable Coffee Production Post Open - National 24,000.00 23,082.20 2016-10-07 2016-11-21 2017-03-21 laboratories Quotations Envelope Implementation and Rejuvenation Component C: Supporting Sustainable Coffee Production Request for Single Stage - One HH30 / Office equipments IDA / 57040 and Rejuvenation Post Open - National 50,000.00 42,940.00 Completed 2016-07-19 2016-08-16 2016-08-16 2016-09-15 2016-08-25 Quotations Envelope Component D: Project Management Component C: Supporting HH31 / Equipment for Request for Single Stage - One IDA / 57040 Sustainable Coffee Production Post Open - National 35,000.00 31,280.74 Completed 2016-09-09 2016-11-01 2017-02-24 2016-12-30 2017-04-14 laboratories Quotations Envelope and Rejuvenation Component B: Supporting HH19 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2017-03-20 2017-03-25 2017-05-06 2017-06-05 2017-07-10 2017-10-10 materials Envelope Implementation Systems Component B: Supporting HH20 / Specialized equipments Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 68,000.00 0.00 2017-02-15 2017-04-12 2017-07-12 for revelant departments Quotations Envelope Implementation Systems Component B: Supporting Request for Single Stage - One Under HH28 / Laboratory Equipmentts IDA / 57040 Sustainable Rice-Based Post Limited 65,000.00 141,872.81 2016-11-06 2017-01-10 2017-01-01 2017-06-30 Quotations Envelope Implementation Systems Component B: Supporting HH24 / Equipment for Request for Single Stage - One IDA / 57040 Sustainable Rice-Based Post Open - National 62,000.00 59,995.15 Completed 2016-10-24 2016-12-19 2017-06-15 2017-02-23 2017-08-28 laboratories Quotations Envelope Systems Component B: Supporting HH25 / Equipment for breeding Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 80,000.00 0.00 2016-10-29 2016-12-24 2017-02-28 centers Quotations Envelope Implementation Systems Component B: Supporting Single Stage - One HH10-DT / Office equipment IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 147,000.00 124,717.12 Completed 2016-09-04 2016-11-07 2016-09-09 2016-10-21 2016-12-14 2016-11-20 2017-05-16 2016-12-25 2017-07-26 2017-02-09 2017-08-22 Envelope Systems Component B: Supporting HH11-DT / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2016-11-02 2016-11-07 2016-12-19 2017-01-18 2017-02-22 2018-05-21 materials Envelope Implementation Systems Component B: Supporting HH16 / Equipment for Single Stage - One Under IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 130,000.00 118,747.42 2016-08-29 2016-11-21 2016-09-13 2016-10-25 2017-01-16 2016-11-24 2017-04-06 2016-12-29 2017-04-14 2017-06-27 laboratories Envelope Implementation Systems Component B: Supporting Sustainable Rice-Based Single Stage - One HH18 / Office equipment IDA / 57040 Systems Post Request for Bids Open - National 150,000.00 795,520.12 Signed 2016-08-24 2016-10-24 2016-08-29 2016-10-10 2016-11-28 2016-11-09 2016-12-16 2016-12-14 2016-12-19 2017-03-14 Envelope Component D: Project Management Component A: Institutional HH-26 / Office equipment Request for Single Stage - One IDA / 57040 Strengthening to Support Post Open - National 97,000.00 141,872.81 Signed 2016-11-05 2016-12-31 2016-12-09 2017-06-29 pakage Quotations Envelope Agricultural Transformation Component B: Supporting Sustainable Rice-Based Request for Single Stage - One HH-14 / Office equipment IDA / 57040 Systems Post Open - National 77,705.00 74,385.35 Signed 2016-10-30 2016-12-23 2017-04-10 2017-02-21 Quotations Envelope Component D: Project Management HH26 / Mua sam thiet bi van Component A: Institutional Single Stage - One phong PPMU va cac don vi co IDA / 57040 Strengthening to Support Prior Request for Bids Open - National 161,000.00 0.00 Canceled 2016-09-01 2016-09-06 2016-10-18 2016-11-17 2016-12-22 2017-06-20 Envelope lien quan Agricultural Transformation Component B: Supporting Sustainable Rice-Based Single Stage - One HH14 / Office equipment IDA / 57040 Systems Prior Request for Bids Open - National 120,000.00 0.00 Canceled 2016-09-15 2016-10-15 2016-11-14 2016-11-28 2016-12-27 2017-06-25 Envelope Component D: Project Management Component C: Supporting Sustainable Coffee Production DN-HH32 / Procurement of Request for Single Stage - One IDA / 57040 and Rejuvenation Prior Open - National 60,000.00 0.00 Canceled 2016-08-29 2016-10-10 2017-04-08 Office Equipment Quotations Envelope Component D: Project Management Component B: Supporting Single Stage - One HH-01 / Office equipment IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 200,000.00 184,835.44 Signed 2016-11-23 2016-11-28 2016-11-28 2016-12-28 2016-12-28 2017-01-27 2017-01-10 2017-02-20 2017-02-10 2017-05-21 Envelope Systems Page 3 Component B: Supporting Single Stage - One HH01 / Office equipment IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 200,000.00 0.00 Canceled 2016-09-19 2016-09-24 2016-11-05 2016-12-05 2017-01-09 2017-06-09 Envelope Systems Component B: Supporting HH-02 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2018-06-22 materials Envelope Implementation Systems Component B: Supporting HH02 / Communication Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 Canceled 2016-09-19 2016-09-24 2016-11-05 2016-11-29 2017-01-03 2018-04-03 materials Envelope Systems Component B: Supporting HH03 / Equipment for Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 110,000.00 0.00 Canceled 2016-09-29 2016-09-29 2016-11-10 2016-12-10 2017-01-15 2017-07-06 laboratories Envelope Systems Component B: Supporting HH-03 / Equipment for Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 110,000.00 103,048.00 Signed 2016-11-30 2016-12-26 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2017-05-22 2017-08-18 laboratories Envelope Systems Component C: Supporting DN HH32 / Sustainable Coffee Production Request for Single Stage - One DescriptionProcurement of Office IDA / 57040 and Rejuvenation Post Open - National 60,000.00 57,659.29 Signed 2016-11-21 2016-12-20 2016-12-14 2017-01-19 Quotations Envelope Equipment Component D: Project Management Component C: Supporting Sustainable Coffee Production HH34 / Tool and Office Request for Single Stage - One IDA / 57040 and Rejuvenation Prior Open - National 85,000.00 0.00 Canceled 2016-09-30 2016-11-30 2016-12-30 equipment Quotations Envelope Component D: Project Management Component C: Supporting Sustainable Coffee Production HH-34 / Tool and Office Request for Single Stage - One IDA / 57040 and Rejuvenation Post Open - National 53,000.00 39,516.52 Signed 2016-11-25 2016-12-18 2016-12-23 2016-12-31 Equipment Quotations Envelope Component D: Project Management Component B: Supporting HH23 / Communication Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 120,000.00 0.00 Canceled 2016-10-11 2016-10-16 2016-12-02 2017-01-01 2017-02-05 2017-08-04 materials Envelope Systems Component B: Supporting Request for Single Stage - One Pending HH12 / Equiment for laboratories IDA / 57040 Sustainable Rice-Based Post Open - National 58,000.00 0.00 2017-04-03 2017-06-14 2017-09-14 Quotations Envelope Implementation Systems Component B: Supporting HH06 / Equipment for Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 476,000.00 0.00 Canceled 2016-09-26 2016-10-01 2016-11-02 2016-11-21 2016-12-06 2017-02-06 laboratoies Envelope Systems Component B: Supporting HH-06 / Equipment for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 476,000.00 0.00 2016-12-20 2016-12-25 2017-01-25 2017-02-24 2017-03-11 2017-05-10 laboratories Envelope Implementation Systems Component B: Supporting HH12-DT / Equipment for Request for Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Open - National 58,000.00 0.00 Canceled 2017-02-24 2017-03-21 2017-04-17 laboratories Quotations Envelope Systems HH2016 / 2 rice transplanting Component B: Supporting machines for the provincial seed Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 60,000.00 0.00 2016-12-17 2017-02-11 2017-04-12 center to promote reduction in Quotations Envelope Implementation Systems seed rates in rice cultivation Component B: Supporting HH21 / Equipment for Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 407,000.00 0.00 Canceled 2017-01-10 2017-01-15 2017-02-26 2017-03-28 2017-05-02 2017-09-02 laboratories Envelope Systems Component B: Supporting HH-21 / Equipment for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 407,000.00 0.00 2017-04-03 2017-04-08 2017-05-20 2017-06-19 2017-07-24 2018-01-20 laboratories Envelope Implementation Systems Component B: Supporting HH27 / Communication Single Stage - One IDA / 57040 Sustainable Rice-Based Prior Request for Bids Open - National 120,000.00 0.00 Canceled 2016-09-24 2016-09-29 2016-11-10 2016-12-10 2017-01-14 2017-07-13 materials Envelope Systems Component B: Supporting HH-27 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2017-03-15 2017-03-20 2017-05-01 2017-05-31 2017-07-05 2018-01-01 materials Envelope Implementation Systems Component B: Supporting Request for Single Stage - One Pending HH-TG1 / Rice transplanters IDA / 57040 Sustainable Rice-Based Post Open - National 20,000.00 0.00 2017-02-06 2017-04-03 2017-09-30 Quotations Envelope Implementation Systems Component B: Supporting HH-23 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 120,000.00 0.00 2017-02-28 2017-03-05 2017-04-16 2017-05-16 2017-06-20 2017-12-17 materials Envelope Implementation Systems Component B: Supporting HH 44 / Equipments for Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 83,000.00 0.00 2017-02-25 2017-04-22 2017-05-31 supporting to MARD's agencies Quotations Envelope Implementation Systems HH41 / IEC products (materials, Component A: Institutional news and articles on Request for Single Stage - One IDA / 57040 Strengthening to Support Prior Limited 48,000.00 0.00 Canceled 2016-10-25 2016-11-23 2017-02-28 newspapers, radios, websites of Quotations Envelope Agricultural Transformation participating provinces). Component A: Institutional HH42 / Pulbishing materials and Request for Single Stage - One IDA / 57040 Strengthening to Support Post Open - National 15,000.00 0.00 Canceled 2016-10-28 2016-11-26 2017-02-26 publication on ARP Quotations Envelope Agricultural Transformation Component B: Supporting HH 92 / Communication Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 300,000.00 0.00 2017-08-01 2017-08-06 2017-09-17 2017-10-17 2017-11-21 2018-02-28 document Envelope Implementation Systems Component B: Supporting HH18-KG / 02 transplanters, 02 Request for Single Stage - One Under IDA / 57040 Sustainable Rice-Based Post Open - National 65,000.00 0.00 2017-05-03 2017-06-28 2017-07-28 ferries and spare parts Quotations Envelope Implementation Systems Page 4 Component B: Supporting HH-09 / Specialized equipment Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 150,000.00 0.00 2017-08-20 2017-08-25 2017-10-06 2017-11-05 2017-12-10 2018-03-10 for provintical seed center Envelope Implementation Systems VN-PMU LONG AN-16059-GO- Component B: Supporting Single Stage - One RFB / Specialized equipment for IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-03-25 2017-03-30 2017-05-11 2017-06-10 2017-07-15 2017-11-15 Envelope provintical seed center Systems HH43 / Communication and information products on ARP of Component A: Institutional provinces participating in ARP Request for Single Stage - One IDA / 57040 Strengthening to Support Post Open - National 48,000.00 0.00 Canceled 2017-11-27 2017-12-29 2018-06-27 (HH43) is replaced with HH41 Quotations Envelope Agricultural Transformation package in Decision No. 2603/ Q-BNN-XD dated 28/6/2016 Component B: Supporting HH13-DT / Equipment for seed Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 105,000.00 0.00 Canceled 2017-02-21 2017-02-26 2017-04-09 2017-05-09 2017-06-13 2017-09-01 center Envelope Systems Component B: Supporting HH-08 / 02 transplanting Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 61,000.00 0.00 2017-12-25 2018-02-19 2018-04-20 machines Quotations Envelope Implementation Systems HH-41 / IEC products (materials, Component A: Institutional news and articles on Request for Single Stage - One IDA / 57040 Strengthening to Support Post Open - National 48,000.00 0.00 Canceled 2016-12-26 2017-01-16 2017-03-20 newspapers, radios, website of Quotations Envelope Agricultural Transformation participating provinces Component B: Supporting HH07-CT / Equipment for The Request for Single Stage - One Pending IDA / 57040 Sustainable Rice-Based Post Open - National 77,272.00 0.00 2017-10-16 2017-11-20 2017-12-20 Breeding Center Quotations Envelope Implementation Systems Component C: Supporting XL-13-1 / Upgrading of private Request for Single Stage - One Pending IDA / 57040 Sustainable Coffee Production Post Open - National 173,308.00 0.00 2017-11-25 2018-01-20 2018-07-19 nurseries ( include 6 nurseries) Quotations Envelope Implementation and Rejuvenation Component B: Supporting Request for Single Stage - One HH 01 / Rice transplanters IDA / 57040 Sustainable Rice-Based Post Open - National 63,965.00 60,942.42 Signed 2017-10-24 2017-12-05 2018-02-05 2018-02-03 Quotations Envelope Systems Component B: Supporting HH17 / Equipment of Breeds Request for Single Stage - One IDA / 57040 Sustainable Rice-Based Post Open - National 60,000.00 58,107.72 Signed 2017-10-29 2017-12-24 2017-03-16 2018-06-22 Center Quotations Envelope Systems Component B: Supporting HH09 / Specialized equipment Single Stage - One IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-03-25 2017-03-30 2017-05-11 2017-06-10 2017-07-15 2017-11-15 for provintical seed center Envelope Systems Component C: Supporting Sustainable Coffee Production Request for Single Stage - One XL12 / Upgrating office IDA / 57040 and Rejuvenation Post Open - National 45,000.00 38,138.38 Signed 2016-09-26 2016-10-31 2017-07-18 2017-03-30 Quotations Envelope Component D: Project Management HH15 / Production of specialized television subject, television report, television program. Produce communication articles Component B: Supporting Single Stage - One Pending on local project activities Media IDA / 57040 Sustainable Rice-Based Post Request for Bids Open - National 92,100.00 0.00 2016-09-14 2016-10-14 2016-11-25 2016-12-25 2017-01-29 2017-07-28 Envelope Implementation Posts. Systems Design and produce communication materials for the project education and training NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CQS71 / National consultant on Component A: Institutional Consultant sharing lessons learnt in IDA / 57040 Strengthening to Support Post Qualification Open - National 75,000.00 0.00 Canceled 2017-05-01 2017-05-22 2017-06-29 2017-07-14 2017-07-28 2018-01-24 selected fields Agricultural Transformation Selection CQS72 / National consultant on Component A: Institutional Consultant standardization of the value IDA / 57040 Strengthening to Support Prior Qualification Open - National 150,000.00 0.00 Canceled 2017-05-10 2017-05-24 2017-07-05 2017-07-17 2017-07-25 2018-01-21 chains Agricultural Transformation Selection Component A: Institutional Consultant CQS73 / National consultant on Pending IDA / 57040 Strengthening to Support Post Qualification Open - National 50,500.00 0.00 2016-10-10 2016-10-25 2016-12-08 2016-12-15 2016-12-29 2017-06-27 review of agricultural credits Implementation Agricultural Transformation Selection Component A: Institutional Consultant CQS49 / National consultant for Pending IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 2016-08-15 2016-08-29 2016-10-07 2016-10-20 2017-01-17 2017-03-31 training need assessment Implementation Agricultural Transformation Selection Component A: Institutional Consultant CQS70 / National consultant on Under IDA / 57040 Strengthening to Support Post Qualification Open - National 150,000.00 0.00 2016-10-04 2017-03-13 2016-10-18 2016-11-29 2017-04-25 2016-12-11 2017-06-05 2016-12-21 2018-03-29 TA for value chain organizations Implementation Agricultural Transformation Selection DN-CQS10 / National experts on Component C: Supporting Consultant sustainable development Pending IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 75,000.00 0.00 2016-09-09 2016-09-23 2016-10-14 2016-11-11 2016-12-02 2017-05-31 planning and re-cultivation of Implementation and Rejuvenation Selection coffee trees Consultant CQS 86 / Financial auditing Component D: Project IDA / 57040 Prior Qualification Open - National 210,000.00 99,506.40 Signed 2016-08-29 2016-09-16 2016-09-05 2016-11-10 2017-03-03 2016-12-10 2017-05-08 2016-12-30 2017-05-11 2020-12-31 project Management Selection Page 5 Component B: Supporting Consultant IC30 / Nat. Consultant on Pending IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 60,000.00 0.00 2016-09-15 2016-10-06 2016-11-19 2016-12-19 2017-01-23 2020-06-30 communication strategy Implementation Systems Selection Consultant Component D: Project Pending IC32 / Technical consultant IDA / 57040 Post Qualification Open - National 120,000.00 0.00 2016-09-15 2016-10-06 2016-11-19 2016-12-19 2017-01-23 2020-06-30 Management Implementation Selection CQS02 / Nat. Cons on improving Component C: Supporting Consultant Under coffe sustainable devt and coffe IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 75,000.00 0.00 2016-12-01 2017-04-27 2016-12-15 2017-01-31 2017-03-15 2017-03-27 2020-12-31 Implementation rejuvention plans and Rejuvenation Selection Component C: Supporting Consultant CQS05 / Independent Under IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 125,000.00 0.00 2016-06-15 2016-11-17 2016-10-09 2016-11-17 2017-02-06 2016-12-17 2017-04-18 2017-01-21 2020-12-16 asssessment of farmer adoption Implementation and Rejuvenation Selection CQS06 / National consultant on Component C: Supporting Consultant improving coffee sustainable Pending IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 75,000.00 0.00 2016-06-15 2016-10-06 2016-11-11 2016-12-11 2017-01-15 2020-12-15 development and coffee Implementation and Rejuvenation Selection rejuvenation plan CQS14 / Nat. Cons on improving Component C: Supporting Consultant Pending coffe sustainable devt and coffe IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 75,000.00 0.00 2016-10-29 2016-11-20 2016-12-14 2017-02-09 2017-02-14 2020-12-31 Implementation rejuvention plans and Rejuvenation Selection CQS18 / Nat. Cons on improving Component C: Supporting Consultant Under coffe sustainable devt and coffe IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 75,000.00 0.00 2016-10-15 2017-03-19 2016-11-11 2016-11-23 2017-01-08 2017-01-21 2020-12-31 Implementation rejuvention plans and Rejuvenation Selection Component B: Supporting Consultant CQS-22 / Independent IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 94,662.35 Signed 2016-12-22 2017-01-12 2017-02-25 2017-03-27 2017-05-24 2017-05-01 2017-06-01 2020-12-30 asssessment of farmer adoption Systems Selection Component C: Supporting Consultant CQS17 / Independent IDA / 57040 Sustainable Coffee Production Prior Qualification Open - National 125,000.00 0.00 Canceled 2016-10-01 2016-11-06 2016-11-18 2017-01-12 2017-01-25 2020-12-31 asssessment of farmer adoption and Rejuvenation Selection Component C: Supporting Consultant CQS-17 / Independent Under IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 125,000.00 0.00 2016-12-09 2017-01-18 2017-01-06 2017-02-03 2017-03-05 2017-03-29 2020-12-31 assessment of farmer adoption Implementation and Rejuvenation Selection DN CQS09 / Component C: Supporting Consultant Pending DescriptionIndependent IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 125,000.00 0.00 2016-11-30 2016-12-14 2017-01-04 2017-02-01 2017-02-22 2017-08-21 Implementation Assessment of Farmer Adoption and Rejuvenation Selection Component C: Supporting Consultant CQS-13 / Independent Pending IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 125,000.00 0.00 2016-11-30 2016-12-18 2017-02-09 2017-04-02 2017-04-11 2020-12-31 assessment of farmer adoption Implementation and Rejuvenation Selection Component C: Supporting Consultant CQS13 / Independent IDA / 57040 Sustainable Coffee Production Prior Qualification Open - National 125,000.00 0.00 Canceled 2016-10-20 2016-11-07 2016-12-30 2017-02-20 2017-03-01 2018-05-31 asssessment of farmer adoption and Rejuvenation Selection Component C: Supporting Consultant DN-CQS09 / Independent IDA / 57040 Sustainable Coffee Production Prior Qualification Open - National 125,000.00 0.00 Canceled 2016-09-08 2016-09-22 2016-10-13 2016-11-10 2016-12-01 2017-05-30 Assessment of Farmer Adoption and Rejuvenation Selection Component B: Supporting Consultant CQS31 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-11-01 2016-11-22 2017-01-05 2017-02-04 2017-03-11 2020-06-30 asssessment of farmer adoption Systems Selection Component B: Supporting Consultant CQS43 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-09-29 2016-10-20 2016-12-03 2017-01-02 2017-02-06 2020-12-31 asssessment of farmer adoption Systems Selection Component B: Supporting Consultant CQS-31 / Independent IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 84,915.36 Signed 2016-12-20 2017-04-17 2017-01-10 2017-02-23 2017-07-20 2017-03-25 2017-11-22 2017-04-29 2017-11-29 2020-06-30 asssessment of farmer adoption Systems Selection Component C: Supporting Consultant CQS01 / Independent IDA / 57040 Sustainable Coffee Production Prior Qualification Open - National 125,000.00 0.00 Canceled 2016-11-15 2016-11-29 2017-01-16 2017-03-06 2017-03-20 2020-12-31 asssessment of farmer adoption and Rejuvenation Selection Component C: Supporting Consultant CQS-01 / Independent IDA / 57040 Sustainable Coffee Production Post Qualification Open - National 125,000.00 120,609.13 Signed 2017-01-20 2016-12-24 2017-02-20 2017-05-22 2017-06-30 2017-06-21 2017-11-27 2017-07-12 2017-12-15 2020-12-31 asssessment of farmer adoption and Rejuvenation Selection Component B: Supporting Consultant CQS25 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-09-01 2016-09-05 2016-10-19 2016-11-18 2016-11-25 2020-06-30 asssussement of famer adoption Systems Selection CQS-25 / Independent Component B: Supporting Consultant asssussement of farmer IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 96,868.20 Signed 2016-12-15 2017-03-06 2016-12-30 2017-02-13 2017-05-22 2017-03-02 2017-07-14 2017-03-17 2017-07-20 2020-12-31 adoption. Systems Selection Component B: Supporting Consultant CQS02-DT / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-10-22 2017-01-22 2017-03-07 2017-04-06 2017-01-11 2017-07-10 asssessment of farmer adoption Systems Selection CQS 68 / Development Component B: Supporting Consultant Management Software Pest on IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 140,000.00 117,925.70 Signed 2017-01-12 2017-10-16 2017-02-22 2017-04-07 2017-12-28 2017-05-07 2018-03-26 2017-06-11 2018-04-05 2018-08-01 Rice and Coffee Systems Selection Component B: Supporting Consultant CQS 02 / Independent evaluation Under IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 0.00 2017-01-18 2017-03-15 2017-03-08 2017-04-03 2017-08-08 2017-05-03 2017-09-29 2017-06-07 2020-09-30 consultant Implementation Systems Selection Component B: Supporting Consultant CQS37 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2020-12-31 assessment of farmer adoption Systems Selection Component B: Supporting Consultant CQS-43 / Independent Under IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 0.00 2016-12-16 2017-02-13 2017-01-06 2017-02-19 2017-04-28 2017-03-21 2017-07-31 2017-04-25 2020-12-31 asssessment of farmer adoption Implementation Systems Selection Page 6 Component B: Supporting Consultant CQS-37 / Independent Pending IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 0.00 2017-02-02 2017-02-23 2017-04-08 2017-05-08 2017-06-12 2020-12-31 assessment of farmer adoption Implementation Systems Selection Consultant Component D: Project IC35 / Technical consultant IDA / 57040 Prior Qualification Open - National 120,000.00 0.00 Canceled 2016-08-31 2016-10-27 2016-09-30 2016-11-13 2016-11-28 2016-12-27 2020-12-31 Management Selection Component B: Supporting Consultant CQS40 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-11-20 2016-12-11 2017-01-24 2017-02-23 2017-03-30 2017-09-26 asssessment of farmer adoption Systems Selection Component B: Supporting Consultant CQS-40 / Independent Pending IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 100,000.00 0.00 2017-03-01 2017-03-22 2017-05-05 2017-06-04 2017-07-09 2018-01-05 assessment for farmer adoption Implementation Systems Selection Component B: Supporting Consultant CQS22 / Independent IDA / 57040 Sustainable Rice-Based Prior Qualification Open - National 100,000.00 0.00 Canceled 2016-09-28 2016-10-19 2016-12-02 2017-01-01 2017-02-05 2020-12-31 assessment of farmer adoption Systems Selection CQS78 / Establishment of the guidelines and process for Component A: Institutional Consultant planning at the commune level to IDA / 57040 Strengthening to Support Post Qualification Open - National 22,500.00 0.00 Canceled 2016-10-27 2016-11-10 2016-12-21 2016-12-30 2017-01-16 2017-06-30 enhance the effectiveness of the Agricultural Transformation Selection public investments in support of the ARP CQS-A4 / Consultant to support economic co-operation to implement the National Assembly's Resolution on Component A: Institutional Consultant Pending National Restructuring Plan for IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 2017-05-01 2017-05-16 2017-06-26 2017-07-06 2017-07-21 2018-01-17 Implementation the 2016-2020 period and to Agricultural Transformation Selection conduct study on strengthen the agricultural production linkages following value chain Component A: Institutional Consultant CQS-A5 / National consultant on Pending IDA / 57040 Strengthening to Support Post Qualification Open - National 40,000.00 0.00 2017-05-03 2017-05-18 2017-06-23 2017-06-30 2017-07-12 2017-12-29 land policy review and proposals Implementation Agricultural Transformation Selection CQS-A7 / Review of medium Component A: Institutional Consultant Pending term agricultural public IDA / 57040 Strengthening to Support Post Qualification Open - National 155,000.00 0.00 2017-04-24 2017-05-09 2017-06-19 2017-06-29 2017-07-12 2018-06-19 Implementation investment and expenditure Agricultural Transformation Selection CQS67 / National consultant on Component A: Institutional Consultant capacity and organization IDA / 57040 Strengthening to Support Post Qualification Open - National 100,000.00 0.00 Canceled 2017-03-27 2017-04-10 2017-05-22 2017-06-02 2017-06-09 2017-11-30 arrangements in some pilot Agricultural Transformation Selection PDARDs CQS50 / National consultant for Component A: Institutional Consultant human resources in MARD's IDA / 57040 Strengthening to Support Post Qualification Open - National 90,000.00 0.00 Canceled 2017-02-13 2017-02-27 2017-04-12 2017-04-24 2017-05-03 2017-10-30 agencies Agricultural Transformation Selection Component A: Institutional Consultant CQS60 / National consultant on IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 Canceled 2017-04-05 2017-04-19 2017-05-31 2017-06-12 2017-06-26 2017-09-30 mid-term expenditure framework Agricultural Transformation Selection CQS59 / National consultant for Component A: Institutional Consultant reviewing the public expenditures IDA / 57040 Strengthening to Support Prior Qualification Open - National 100,000.00 0.00 Canceled 2017-03-01 2017-03-16 2017-04-24 2017-05-04 2017-05-18 2017-11-14 in ARD sector Agricultural Transformation Selection Component A: Institutional Consultant Pending CQS-A1 / Public Service anlysis IDA / 57040 Strengthening to Support Post Qualification Open - National 90,000.00 0.00 2017-04-20 2017-05-05 2017-06-12 2017-06-19 2017-06-26 2018-02-26 Implementation Agricultural Transformation Selection Component A: Institutional Consultant CQS-A3 / Consultant to support Pending IDA / 57040 Strengthening to Support Post Qualification Open - National 200,000.00 0.00 2017-04-20 2017-05-05 2017-06-14 2017-06-20 2017-06-29 2018-02-19 8 provinces to reivew ARP Implementation Agricultural Transformation Selection CQS-A2 / Consultant to review Component A: Institutional Consultant Pending and support implementation of IDA / 57040 Strengthening to Support Post Qualification Open - National 150,000.00 0.00 2017-04-20 2017-05-05 2017-06-12 2017-06-21 2017-06-29 2018-02-01 Implementation sector and subsector ARPs Agricultural Transformation Selection CQS-A6 / Consultant on human resources for agencies under Component A: Institutional Consultant MARD, DARDs, and study of IDA / 57040 Strengthening to Support Post Qualification Open - National 240,000.00 0.00 Canceled 2017-04-24 2017-05-09 2017-06-19 2017-06-30 2017-07-12 2018-06-18 capactiy and organizational Agricultural Transformation Selection structure of DARDs Component B: Supporting Consultant CQS 91 / Communication IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 180,000.00 175,000.08 Signed 2017-06-12 2017-11-08 2017-07-03 2017-08-16 2017-12-29 2017-09-15 2018-03-15 2017-10-20 2018-04-05 2020-12-31 Consultant at CPMU Systems Selection CQS61 / National consultant on Component A: Institutional Consultant M&E of the public expenditure IDA / 57040 Strengthening to Support Post Qualification Open - National 40,000.00 0.00 Canceled 2017-04-13 2017-04-27 2017-06-08 2017-06-20 2017-06-30 2017-12-31 restructuring Agricultural Transformation Selection Component A: Institutional Consultant CQS-A8 / Propaganda on the IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 Canceled 2017-06-01 2017-06-15 2017-07-28 2017-08-15 2017-09-04 2018-02-28 agriculture restructuring plan Agricultural Transformation Selection CQS34 / The independent Component B: Supporting Consultant assessment consultancy Under IDA / 57040 Sustainable Rice-Based Post Qualification Open - National 90,000.00 0.00 2017-05-25 2017-04-27 2017-06-15 2017-08-03 2017-10-25 2017-08-17 2017-10-25 2017-09-07 2020-12-20 package: applying technology in Implementation Systems Selection rice production of farmer CQS-A9 / Consultant to provide technical support for PPP Component A: Institutional Consultant Secretariat Board (CQS-A9) is Pending IDA / 57040 Strengthening to Support Post Qualification Open - National 125,000.00 0.00 2017-10-06 2017-10-23 2017-11-13 2017-12-19 2018-01-01 2019-03-27 replaced with CQS69 package in Implementation Agricultural Transformation Selection Decision No. 1885/ Q-BNN-XD dated 23/5/2016 Page 7 CQS-A10 / News, articles to advocate ARP implementation and raise awareness of ARP ( on Component A: Institutional Consultant webisite, radio, newspaper (CQS- IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 Canceled 2017-10-06 2017-10-23 2017-11-13 2017-12-19 2018-01-01 2018-06-30 A10) is replaced with CQS74 Agricultural Transformation Selection package in Decision No. 2603/Q-BNN-XD dated 28/6/2016 Component A: Institutional Consultant CQS69 / TA for PPP secretary IDA / 57040 Strengthening to Support Post Qualification Open - National 125,000.00 0.00 Canceled 2016-10-15 2016-11-05 2016-12-14 2016-12-27 2017-01-11 2017-07-10 board Agricultural Transformation Selection CQS74 / News and articles on Component A: Institutional Consultant ARP (websites, radios, IDA / 57040 Strengthening to Support Post Qualification Open - National 50,000.00 0.00 Canceled 2016-10-29 2016-09-15 2016-11-13 2016-12-25 2017-01-08 2017-01-15 2017-06-15 newspapers, etc.) Agricultural Transformation Selection CQS-A11 / Assessment of the VPA/FLEGT impacts on small scale households which involve in forestation in the context of the Component A: Institutional Consultant Pending ARP implementation"; and IDA / 57040 Strengthening to Support Post Qualification Open - National 120,930.00 0.00 2018-07-05 2018-07-19 2018-09-03 2018-09-10 2018-09-20 2019-03-19 Implementation reviewing and evaluating the Agricultural Transformation Selection current status of agricultural product sales in value chain in Lam Dong province INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Institutional IC53 / National consultant on Individual Consultant Pending IDA / 57040 Strengthening to Support Post Open - National 17,500.00 0.00 2016-08-15 2016-09-06 2016-09-12 2016-09-21 2017-03-20 livestock production for ARP Selection Implementation Agricultural Transformation Component A: Institutional IC54 / National consultant on Individual Consultant Pending IDA / 57040 Strengthening to Support Post Open - National 17,500.00 0.00 2016-08-15 2016-09-07 2016-09-13 2016-09-26 2017-03-25 forestry for ARP Selection Implementation Agricultural Transformation Component A: Institutional IC64 / International consultant Individual Consultant IDA / 57040 Strengthening to Support Prior Open 150,000.00 0.00 Canceled 2017-02-20 2017-03-21 2017-03-27 2017-04-13 2017-10-10 on policy research for renovation Selection Agricultural Transformation Component A: Institutional IC65 / National consultant on Individual Consultant Pending IDA / 57040 Strengthening to Support Post Open - National 45,000.00 0.00 2016-08-25 2016-09-17 2016-09-22 2016-09-30 2018-03-31 policy research for renovation Selection Implementation Agricultural Transformation Component A: Institutional Individual Consultant IC66 / Interpreter IDA / 57040 Strengthening to Support Post Open - National 150,000.00 64,296.10 Signed 2016-07-01 2016-07-18 2016-07-20 2016-07-13 2016-07-28 2016-07-21 2020-12-31 Selection Agricultural Transformation IC76 / National consultant for research and study on existing organization arrangements of Component A: Institutional production modalities in support Individual Consultant Pending IDA / 57040 Strengthening to Support Post Open 7,500.00 0.00 2016-10-12 2016-11-04 2016-11-09 2016-12-13 2017-03-31 ARP towards higher value added Selection Implementation Agricultural Transformation and sustainable development in association with new rural development IC77 / Evaluation of Sciences Component A: Institutional Individual Consultant Pending and technology applications in IDA / 57040 Strengthening to Support Post Open - National 7,500.00 0.00 2016-10-20 2016-11-15 2016-11-18 2016-11-25 2017-02-28 Selection Implementation ARD sector and ARP. Agricultural Transformation IC79 / Development of the Component A: Institutional Individual Consultant guidelines on monitoring of the IDA / 57040 Strengthening to Support Post Open 5,000.00 0.00 Canceled 2016-11-01 2016-11-23 2016-11-28 2016-12-07 2017-02-28 Selection ARD sector public investment Agricultural Transformation IC 80 / CPMU: National Component D: Project Individual Consultant IDA / 57040 Prior Open - National 150,000.00 102,555.63 Signed 2016-02-22 2016-04-11 2016-08-07 2016-08-05 2016-08-29 2016-09-01 2020-12-31 Procurement Consultant Management Selection Component B: Supporting IC24 / Nat. Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Limited 60,000.00 58,118.28 Signed 2016-08-30 2017-07-26 2016-08-31 2017-07-28 2016-09-21 2017-08-21 2016-10-07 2017-09-01 2019-04-10 communication stratery Selection Systems IC46 / National consultant to Component A: Institutional Individual Consultant support for the change IDA / 57040 Strengthening to Support Prior Open - National 75,000.00 64,442.70 Signed 2016-08-07 2016-08-30 2016-09-07 2016-10-12 2016-09-25 2016-11-04 2019-03-30 Selection management group Agricultural Transformation Component A: Institutional Individual Consultant Pending IC51 / IEC consultant IDA / 57040 Strengthening to Support Post Open - National 75,000.00 0.00 2016-08-04 2016-08-25 2016-08-29 2016-09-02 2019-03-31 Selection Implementation Agricultural Transformation Component A: Institutional IC75 / National consultant on Individual Consultant Pending IDA / 57040 Strengthening to Support Post Open - National 5,000.00 0.00 2016-10-05 2016-10-30 2016-11-03 2016-11-09 2017-01-30 review of land policies Selection Implementation Agricultural Transformation Component A: Institutional Individual Consultant Pending IC81 / Coordinator and M&E IDA / 57040 Strengthening to Support Post Open - National 143,000.00 0.00 2016-07-19 2016-08-10 2016-08-17 2016-09-24 2020-12-31 Selection Implementation Agricultural Transformation Component D: Project Individual Consultant IC26 / Technical consultant IDA / 57040 Prior Limited 120,000.00 100,320.00 Signed 2016-08-15 2016-08-16 2016-06-30 2016-09-09 2016-09-15 2016-09-16 2016-09-16 2020-12-31 Management Selection Component B: Supporting IC39 / Nat. Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 36,791.35 Signed 2016-11-01 2016-12-23 2016-12-20 2017-04-17 2017-01-10 2017-06-01 2017-02-14 2017-06-01 2017-08-13 communication strategy Selection Systems DN-IC12 / National Technical Component D: Project Individual Consultant Under IDA / 57040 Prior Open 120,000.00 0.00 2016-08-17 2016-08-25 2016-09-14 2016-09-21 2016-11-12 2016-10-12 2017-04-10 Consultant Management Selection Implementation Component C: Supporting DN-IC11 / National Consultant Individual Consultant IDA / 57040 Sustainable Coffee Production Post Open 30,000.00 25,237.38 Signed 2016-08-17 2016-08-09 2016-09-19 2016-11-28 2016-09-26 2016-12-05 2016-10-17 2016-12-26 2017-04-15 on Communication Strategy Selection and Rejuvenation Page 8 IC03 / Cons. For consolidation Component C: Supporting Individual Consultant and devt of communication IDA / 57040 Sustainable Coffee Production Post Open 30,000.00 29,010.96 Signed 2016-09-15 2016-09-15 2016-10-31 2016-11-24 2016-11-04 2016-11-24 2016-11-18 2016-12-08 2019-11-18 Selection strategies and Rejuvenation Component D: Project Individual Consultant IC04 / Technical consultant IDA / 57040 Prior Open 120,000.00 87,360.00 Terminated 2016-02-22 2016-09-12 2016-09-19 2016-10-05 2016-10-03 2016-10-20 2020-12-31 Management Selection IC19 / Cons. For consolidation Component C: Supporting Individual Consultant and devt of communication IDA / 57040 Sustainable Coffee Production Post Open 30,000.00 29,059.14 Signed 2016-09-08 2016-07-07 2016-10-13 2017-08-23 2016-10-18 2017-08-31 2016-11-01 2017-10-02 2019-05-01 Selection strategies and Rejuvenation IC07 / Individual consultant on Component C: Supporting Individual Consultant consolidation and development IDA / 57040 Sustainable Coffee Production Post Open 30,000.00 28,941.00 Signed 2016-06-15 2016-09-13 2016-10-07 2016-10-18 2017-01-18 2016-11-01 2017-02-06 2018-06-01 Selection communication strategies and Rejuvenation IC08 / Individual Technical Component D: Project Individual Consultant IDA / 57040 Post Open 120,000.00 68,640.00 Signed 2016-06-15 2016-07-20 2016-08-21 2016-09-12 2016-09-05 2016-09-13 2016-09-15 2016-09-15 2020-12-20 consultant Management Selection Component B: Supporting IC03-DT / Nat. Consultant on Individual Consultant Under IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 0.00 2016-07-26 2016-08-30 2016-09-13 2016-10-04 2016-10-20 2017-10-14 communication strategy Selection Implementation Systems IC 81 / National M& E Component D: Project Individual Consultant IDA / 57040 Prior Open 135,000.00 111,073.73 Signed 2016-05-23 2016-07-29 2016-08-25 2016-09-13 2016-09-14 2016-09-30 2020-12-31 Consultant Management Selection IC 82 / National environmental Component D: Project Individual Consultant IDA / 57040 Post Open 75,000.00 60.29 Signed 2016-07-07 2016-06-30 2016-09-09 2016-10-07 2016-10-09 2016-10-11 2016-10-30 2016-11-01 2020-12-31 consultant for rice Management Selection IC 84 / National Social Component D: Project Individual Consultant IDA / 57040 Post Open 75,000.00 54,720.00 Signed 2016-07-07 2016-07-08 2016-09-05 2016-09-06 2016-09-26 2016-09-09 2016-10-19 2016-10-14 2020-12-31 consultant for rice Management Selection IC 85 / National Social Component D: Project Individual Consultant IDA / 57040 Post Open 75,000.00 52,360.00 Signed 2016-07-07 2016-07-08 2016-09-11 2016-09-05 2016-10-02 2016-09-09 2016-10-30 2016-10-14 2020-12-31 consultant for rice Management Selection IC 83 / National environmental Component D: Project Individual Consultant IDA / 57040 Post Open 75,000.00 53,737.63 Signed 2016-07-07 2016-07-08 2016-09-09 2017-01-17 2016-09-30 2017-01-09 2016-10-30 2017-02-15 2020-12-31 consultant for coffee Management Selection Component B: Supporting IC36 / Nat. Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 45,285.11 Signed 2016-08-26 2016-09-20 2016-10-14 2016-12-02 2016-11-04 2016-12-20 2016-12-09 2017-01-06 2020-12-31 communication strategy Selection Systems Component B: Supporting IC42 / Nat. Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 48,143.50 Signed 2016-09-14 2016-09-29 2016-11-02 2016-10-27 2016-11-23 2016-10-31 2016-12-28 2016-12-01 2019-12-26 communication strategy Selection Systems IC15 / Cons. For consolidation Component C: Supporting Individual Consultant and devt of communication IDA / 57040 Sustainable Coffee Production Post Open 30,000.00 28,590.36 Signed 2016-07-25 2016-07-25 2016-10-05 2016-10-19 2016-10-06 2016-11-16 2016-10-14 2016-11-18 2019-04-14 Selection strategies and Rejuvenation Component C: Supporting Individual Consultant IC20 / Technical consultant IDA / 57040 Sustainable Coffee Production Post Open 59,400.00 112,200.00 Signed 2016-06-22 2016-08-03 2016-09-27 2016-09-08 2016-10-02 2016-09-09 2016-11-01 2016-09-28 2020-12-31 Selection and Rejuvenation Component B: Supporting IC33 / Nat. Consultant on Individual Consultant Under IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 0.00 2016-09-15 2016-11-02 2016-11-24 2016-12-09 2017-01-03 2019-06-22 communication strategy Selection Implementation Systems Component D: Project Individual Consultant IC16 / Technical consultant IDA / 57040 Post Open 73,320.00 57,463.12 Signed 2016-06-23 2016-06-26 2016-09-28 2016-09-05 2016-10-19 2016-09-26 2016-11-12 2016-10-01 2020-12-31 Management Selection Component B: Supporting Technical assistance IDA / 57040 Sustainable Rice-Based Prior Direct Selection Direct 1,240,000.00 1,191,136.00 Signed 2016-08-31 2016-12-20 2016-09-25 2016-12-01 2017-07-20 2020-10-30 Systems Component B: Supporting IC-21 / Nat. Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 22,704.00 Signed 2017-01-28 2017-03-18 2017-04-08 2017-05-13 2017-04-28 2020-05-13 communication strategy Selection Systems Component B: Supporting IC21 / Consultant on Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 60,000.00 0.00 Canceled 2016-09-29 2016-11-17 2016-12-08 2017-01-12 2020-01-09 communication strategy Selection Systems Component D: Project Individual Consultant IC44 / Technical consultant IDA / 57040 Prior Open 120,000.00 0.00 Canceled 2016-09-15 2016-10-27 2016-11-03 2016-11-24 2016-12-29 2020-12-31 Management Selection Component D: Project Individual Consultant IC01 / Technical consultant IDA / 57040 Post Open 120,000.00 106,103.00 Signed 2016-07-26 2016-07-28 2016-10-16 2016-10-19 2016-11-04 2016-11-24 2016-12-01 2016-12-01 2020-12-31 Management Selection Component D: Project Individual Consultant IC01-DT / Technical consultant IDA / 57040 Prior Open 120,000.00 0.00 Canceled 2016-07-25 2016-08-31 2016-09-12 2016-10-03 2016-10-07 2020-12-31 Management Selection Component D: Project Individual Consultant IC38 / Technical consultant IDA / 57040 Prior Open 120,000.00 0.00 Canceled 2016-08-26 2016-09-28 2016-10-14 2016-11-04 2016-12-09 2020-12-31 Management Selection Component D: Project Individual Consultant IC-38 / Technical consultant IDA / 57040 Post Open 120,000.00 92,983.84 Signed 2016-09-15 2016-09-20 2016-11-28 2016-11-21 2016-12-05 2016-11-28 2016-12-30 2016-12-19 2020-12-31 Management Selection Component B: Supporting Individual Consultant IC-44 / Technical Consultant IDA / 57040 Sustainable Rice-Based Post Open 120,000.00 73,074.86 Signed 2016-09-29 2016-09-29 2016-11-17 2016-11-08 2016-12-08 2016-12-23 2017-01-12 2017-01-03 2020-12-31 Selection Systems Component D: Project Individual Consultant IC-35 / Technical Consultant IDA / 57040 Post Open 120,000.00 78,070.29 Signed 2016-10-27 2016-11-15 2016-12-15 2017-01-06 2017-01-05 2017-01-10 2017-02-09 2017-01-20 2020-12-31 Management Selection Component D: Project Individual Consultant IC41 / Technical consultant IDA / 57040 Prior Open 120,000.00 0.00 Canceled 2016-09-15 2016-11-03 2016-11-24 2016-12-29 2017-06-27 Management Selection Component B: Supporting Individual Consultant Pending IC-41 / Technical cosnultant IDA / 57040 Sustainable Rice-Based Post Open 120,000.00 0.00 2017-01-20 2017-03-10 2017-03-31 2017-05-05 2017-11-01 Selection Implementation Systems Page 9 IC-45 / International consultant Component A: Institutional Individual Consultant to support for the change IDA / 57040 Strengthening to Support Post Open - National 125,000.00 81,968.00 Signed 2016-12-24 2016-09-23 2017-01-14 2017-01-17 2017-01-24 2016-11-29 2019-01-31 Selection management group Agricultural Transformation IC 89 / Information Technology Component B: Supporting Consultant for developing the Individual Consultant IDA / 57040 Sustainable Rice-Based Post Open 10,000.00 9,683.52 Signed 2017-02-20 2017-07-26 2017-04-10 2017-09-05 2017-05-01 2017-09-08 2017-06-05 2017-09-29 2017-12-29 website and information of rice Selection Systems and coffee industry Component B: Supporting Individual Consultant IC23 / Technical consultant IDA / 57040 Sustainable Rice-Based Prior Open 120,000.00 0.00 Canceled 2016-08-31 2016-10-19 2016-11-09 2016-12-14 2020-12-14 Selection Systems IC45 / International consultant to Component A: Institutional Individual Consultant support for the change IDA / 57040 Strengthening to Support Prior Open - National 125,000.00 0.00 Canceled 2016-08-10 2016-09-28 2016-09-12 2016-09-20 2016-10-03 2017-03-31 Selection management group Agricultural Transformation Component B: Supporting Individual Consultant IC-23 / Technical Consultant IDA / 57040 Sustainable Rice-Based Post Open 120,000.00 113,520.00 Signed 2016-08-30 2016-10-18 2016-11-08 2017-01-04 2017-05-25 2020-12-31 Selection Systems IC 90 / National consultant on Component D: Project Individual Consultant IDA / 57040 Post Open 98,000.00 91,405.25 Signed 2017-04-03 2017-06-20 2017-05-22 2017-09-11 2017-06-12 2017-09-14 2017-07-03 2017-09-27 2020-12-31 project management Management Selection IC82 / 4 national consultants to Component A: Institutional support 4 pilot provinces involving Individual Consultant IDA / 57040 Strengthening to Support Post Open - National 20,000.00 0.00 Canceled 2016-09-09 2016-10-04 2016-10-07 2016-10-18 2016-12-31 in the ARP (Hà T)nh, Bình n Ë h, Selection Agricultural Transformation Lâm nÓ g, n Ó g Tháp) IC63 / National consultant on Component A: Institutional Individual Consultant establishment of the ARP M&E IDA / 57040 Strengthening to Support Post Open - National 7,500.00 0.00 Canceled 2016-07-05 2016-07-29 2016-08-02 2016-08-10 2016-11-30 Selection indicators set Agricultural Transformation IC58 / National consultant on Component A: Institutional Individual Consultant result-based planning, M&E for IDA / 57040 Strengthening to Support Post Open 5,000.00 0.00 Canceled 2017-02-15 2017-03-14 2017-03-20 2017-03-29 2017-05-31 Selection subsectors Agricultural Transformation IC62 / International consultant Component A: Institutional Individual Consultant on establishment of the ARP IDA / 57040 Strengthening to Support Post Open - National 75,000.00 0.00 Canceled 2017-03-15 2017-04-20 2017-05-02 2017-05-16 2017-08-16 Selection M&E indicators set Agricultural Transformation Component A: Institutional IC48 / National consultant for Individual Consultant IDA / 57040 Strengthening to Support Post Open 15,000.00 0.00 Canceled 2017-01-10 2017-02-06 2017-02-10 2017-02-21 2017-08-20 services analysis Selection Agricultural Transformation Component A: Institutional IC57 / National consultant on Individual Consultant IDA / 57040 Strengthening to Support Post Open - National 17,500.00 0.00 Canceled 2016-07-20 2016-08-12 2016-08-16 2016-08-24 2017-02-28 processing for ARP Selection Agricultural Transformation Component A: Institutional IC55 / National consultant on Individual Consultant IDA / 57040 Strengthening to Support Post Open - National 17,500.00 0.00 Canceled 2017-01-20 2017-02-14 2017-02-20 2017-02-28 2017-08-27 fisheries for ARP Selection Agricultural Transformation Component A: Institutional IC56 / National consultant on Individual Consultant IDA / 57040 Strengthening to Support Post Open 17,500.00 0.00 Canceled 2017-01-16 2017-02-08 2017-02-13 2017-02-22 2017-08-21 irrigation for ARP Selection Agricultural Transformation IC83 / National consult to Component A: Institutional Individual Consultant Pending support Change Management IDA / 57040 Strengthening to Support Post Open 64,000.00 0.00 2017-04-20 2017-05-16 2017-05-23 2017-05-30 2020-12-31 Selection Implementation Group (rehiring) Agricultural Transformation Component A: Institutional IC68 / Consultant on human Individual Consultant IDA / 57040 Strengthening to Support Post Open - National 50,000.00 0.00 Canceled 2017-02-23 2017-03-15 2017-03-20 2017-03-27 2018-11-30 resources in pilot PDARDs Selection Agricultural Transformation Component A: Institutional IC52 / International consultant Individual Consultant IDA / 57040 Strengthening to Support Prior Open 225,000.00 0.00 Canceled 2016-10-02 2016-10-30 2016-11-08 2016-11-13 2017-08-31 for subsector restructuring plans Selection Agricultural Transformation Component A: Institutional IC80 / Review of public Individual Consultant IDA / 57040 Strengthening to Support Post Open - National 5,000.00 0.00 Canceled 2016-11-03 2016-11-28 2016-12-02 2016-12-13 2017-02-28 investment policy Selection Agricultural Transformation Component D: Project Individual Consultant IC05 / Technical consultant IDA / 57040 Post Open 114,000.00 68,685.24 Signed 2017-05-10 2017-03-21 2017-07-01 2017-10-02 2017-07-08 2017-09-21 2017-07-16 2017-10-16 2020-12-15 Management Selection Component A: Institutional Individual Consultant Pending IC84 / Interpreter (rehiring) IDA / 57040 Strengthening to Support Post Open 120,000.00 0.00 2017-04-20 2017-05-17 2017-05-22 2017-05-29 2020-12-31 Selection Implementation Agricultural Transformation Component A: Institutional IC47 / International consultant Individual Consultant IDA / 57040 Strengthening to Support Post Open 75,000.00 0.00 Canceled 2017-01-10 2017-02-07 2017-02-10 2017-02-27 2017-05-31 for services analysis Selection Agricultural Transformation Component D: Project Individual Consultant IC 93 / Interpreter Consultant IDA / 57040 Post Open 55,000.00 50,198.76 Signed 2017-10-25 2017-10-06 2017-12-13 2017-11-07 2018-01-03 2017-11-10 2018-02-07 2017-11-17 2020-12-31 Management Selection Component D: Project Individual Consultant Pending IC 94 / Website Consultant IDA / 57040 Post Open 11,000.00 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-01 2020-12-31 Management Selection Implementation IC85 / Analyzing and evaluating the current status and proposing contents, solutions, mechanisms Component A: Institutional Individual Consultant Pending and policies to encourage the IDA / 57040 Strengthening to Support Post Open 5,581.00 0.00 2018-07-12 2018-08-09 2018-08-10 2018-08-17 2018-11-15 Selection Implementation development of safe vegetable Agricultural Transformation value chain in Nam Dinh province. Page 10