PROCUREMENT PLAN Project information: Sierra Leone Safety Nets Project (P143588) Project Implementation agency: National Commission for Social Action (NaCSA) Date of the Procurement Plan: Febry, 2019 Period covered by this Procurement Plan: 12 Months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 216 of the Republic of Sierra Leone, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables Works: No applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the the Project): Thresholds*, Procurement Methods, and Prior Review Expenditure Contract (C) Value Threshold* Contracts Subject to No Procurement Method Category [eq. USD] Prior Review /[eq. US$] All contracts at or above USD 2 Open Competition million are subject to international C ≥ 5,000,000 International Market Approach advertising and the use of the Goods, IT and and Direct Contracting Bank’s SPDs (or other documents 2 non-consulting agreed with the Bank). services Open Competition National : Market Approach None 100,000 < C < 5,000,000 C ≤ 100,000 RfQ None All contracts at or above USD 300,000 are subject to for C < 300,000 international advertising and the use of the Bank’s Consulting Services SPDs (or other documents agreed with the Bank). National shortlist 3 for selection of consultant firms for All contracts at or above USD 300,000 are subject to C ≤ 500,000 Engineering and Construction international advertising and the use of the Bank’s Supervision SPDs (or other documents agreed with the Bank). Selection of ≥ 300,000 ≥ 300,000 4 Individual All Approaches consultants Expenditure Contract (C) Value Threshold* Contracts Subject to No Procurement Method Category [eq. USD] Prior Review /[eq. US$] Training, Workshops, Based on approved Annual 5 Study Tours All Values Work Plan & Budgets (AWPB) This line activity is not subject to procurement Review. by TTL (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will need for prequalification in the procurement arrangements under this project) *These thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. ** Short lists of consultants for services estimated to cost less US$300,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if foreign firms have expressed interest, they will not be excluded from consideration. Prequalification. Not expected for the packages of goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: the project team will prepare Procurement manuals. The Procurement Plan/Manual will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: Not Applicable Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Sierra Leone : Sierra Leone Safety Nets Project PLAN General Information Country: Sierra Leone Bank’s Approval Date of the Original Procurement Plan: 2019-03-15 2019-07-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143588 GPN Date: Project Name: Sierra Leone Safety Nets Project Loan / Credit No: IDA / D0920 Executing Agency(ies): National Soacial Action Commission WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-NACSA-102844-GO-RFQ Development of Systems for Under Request for Single Stage - One / Supply of 4units Off Road IDA / D0920 Implementation of Social Post Limited 24,000.00 0.00 Implementati 2019-04-03 2019-05-29 2019-11-25 Quotations Envelope Motor Bikes Safety Net Interventions on SL-NACSA-104620-GO-RFQ Development of Systems for Under Request for Single Stage - One / Supply of Office stationery IDA / D0920 Implementation of Social Post Limited 10,000.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 Quotations Envelope and other supplies Safety Net Interventions on SL-NACSA-104623-GO-RFQ Development of Systems for Pending / Production of visual Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 10,000.00 0.00 Implementati 2019-04-28 2019-06-23 2019-12-20 materials (documentary) on Quotations Envelope Safety Net Interventions on SSN Project Development of Systems for Under SL-NACSA-104616-GO-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 10,000.00 0.00 Implementati 2019-04-13 2019-06-08 2019-12-05 / Supply of Office Furniture Quotations Envelope Safety Net Interventions on SL-NACSA-102842-GO-RFQ Development of Systems for Pending Request for Single Stage - One / Procurement of 2 desktop IDA / D0920 Implementation of Social Post Limited 5,000.00 0.00 Implementati 2019-05-18 2019-07-13 2020-01-09 Quotations Envelope computers Safety Net Interventions on SL-NACSA-102847-GO-RFQ Development of Systems for Request for Single Stage - One / Supply of 1unit Station IDA / D0920 Implementation of Social Post Limited 50,000.00 49,600.00 Signed 2019-05-14 2019-07-09 2020-01-05 Quotations Envelope wagon Vehicle Safety Net Interventions SL-NACSA-104618-GO-RFQ / Supply of MIS Ehancement (equipment) (Server (Two 1TB HDD Storage, 16GB RAM.17 Processor) Keyboard Development of Systems for Under (English), Monitor (15" Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 60,000.00 0.00 Implementati 2019-05-29 2019-07-24 2020-01-20 Screen), Antivirus Software, Quotations Envelope Safety Net Interventions on Backup batteries (24V 200 AH sealed unit), Inverter (3200W Pure sine wave module), Independent internet Page 1 SL-NACSA-118439-GO-RFQ / System Development and Implementation (System Straightening, U-REPORT DESIGN and ROLLOUT, Development of Systems for Pending Request for Single Stage - One Capacity Building & IDA / D0920 Implementation of Social Post Open - National 184,686.98 0.00 Implementati 2019-06-26 2019-08-21 2020-02-17 Quotations Envelope Training, ACC Infrusture Safety Net Interventions on Support, GRM & Case Management Development, Computers, Phones, Tablets, modem & Internet) SL-NACSA-118440-GO-RFQ / Training For Community Development of Systems for Pending Request for Single Stage - One Monitors (Refreshment, IDA / D0920 Implementation of Social Post Open - National 18,566.59 0.00 Implementati 2019-06-26 2019-08-21 2020-02-17 Quotations Envelope Transport, DSA for Trainers Safety Net Interventions on and Driver, Fuel for vehicle) SL-NACSA-118442-GO-RFQ / REGULAR COMMUNITY MONITORING (Targeting Development of Systems for Pending Request for Single Stage - One and Enrolment Monitoring) IDA / D0920 Implementation of Social Post Limited 10,999.41 0.00 Implementati 2019-06-26 2019-08-21 2020-02-17 Quotations Envelope Project Coordinator, Project Safety Net Interventions on Assistant, District Monitors, Driver, Fuel) SL-NACSA-118470-GO-RFQ / Payment Monitoring Development of Systems for Pending Request for Single Stage - One (Project Coordinator, Project IDA / D0920 Implementation of Social Post Limited 43,835.29 0.00 Implementati 2019-06-26 2019-08-21 2020-02-17 Quotations Envelope Assistant, District Monitors, Safety Net Interventions on Driver, Fuel) SL-NACSA-118471-GO-RFQ / Monitoring and Supervision Visits (Western Rural, Development of Systems for Pending Request for Single Stage - One District Monitors, Project IDA / D0920 Implementation of Social Post Limited 17,132.24 0.00 Implementati 2019-07-02 2019-08-27 2020-02-23 Quotations Envelope Coordinator, Project Safety Net Interventions on Assistant, High-level Monitoring, Driver, Fuel) SL-NACSA-118536-GO-RFQ Development of Systems for Pending / Stationary Printing and Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 15,000.00 0.00 Implementati 2019-07-03 2019-08-28 2020-02-24 assessories (including Quotations Envelope Safety Net Interventions on Photocopier and printer inks Development of Systems for Pending SL-NACSA-118538-GO-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 1,000.00 0.00 Implementati 2019-07-03 2019-08-28 2020-02-24 / Toiletries Quotations Envelope Safety Net Interventions on SL-NACSA-118542-GO-RFQ Development of Systems for Pending Request for Single Stage - One / Fuel, Maintenance and IDA / D0920 Implementation of Social Post Limited 8,000.00 0.00 Implementati 2019-07-03 2019-08-28 2020-02-24 Quotations Envelope Lubricants Safety Net Interventions on Development of Systems for Pending SL-NACSA-118546-GO-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Post Open - National 3,270.59 0.00 Implementati 2019-06-26 2019-08-21 2020-02-17 / Communication Quotations Envelope Safety Net Interventions on Development of Systems for Pending SL-NACSA-119207-GO-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 30,000.00 0.00 Implementati 2019-07-03 2019-08-28 2020-02-24 / Vehicle - Pickup Quotations Envelope Safety Net Interventions on Development of Systems for Pending SL-NACSA-119209-GO-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Post Limited 35,000.00 0.00 Implementati 2019-07-17 2019-09-11 2020-03-09 / Motor Bikes Quotations Envelope Safety Net Interventions on NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-NACSA-104627-NC-RFQ Development of Systems for Pending Request for Single Stage - One / Servicing & Repairs of 11 IDA / D0920 Implementation of Social Post Limited 33,000.00 0.00 Implementati 2019-05-05 2019-06-30 2019-12-27 Quotations Envelope vehicles) Safety Net Interventions on Development of Systems for Under SL-NACSA-106609-NC-RFQ Request for Single Stage - One IDA / D0920 Implementation of Social Prior Open - National 351,000.00 0.00 Implementati 2019-04-06 2019-06-01 2019-11-28 / Payment Service Provider Quotations Envelope Safety Net Interventions on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Development of Systems for SL-NACSA-104632-CS-LCS / Least Cost Under IDA / D0920 Implementation of Social Post Open - National 10,000.00 0.00 2019-05-21 2019-06-11 2019-07-25 2019-08-22 2019-09-21 2019-10-26 2019-11-30 2020-05-28 Financial Audit 2019 SSNP Selection Implementation Safety Net Interventions INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Development of Systems for Individual SL-NACSA-104635-CS-INDV IDA / D0920 Implementation of Social Post Consultant Open 25,620.00 0.00 Canceled 2019-04-17 2019-06-05 2019-06-26 2019-07-31 2020-01-27 / 1 Project Officer Safety Net Interventions Selection Development of Systems for Individual SL-NACSA-104655-CS-INDV IDA / D0920 Implementation of Social Post Consultant Open 25,620.00 0.00 Canceled 2019-06-21 2019-08-09 2019-08-30 2019-10-04 2020-04-01 / Systems Officer Safety Net Interventions Selection SL-NACSA-104657-CS-INDV Development of Systems for Individual / Management Information IDA / D0920 Implementation of Social Post Consultant Open 25,620.00 0.00 Canceled 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 System Developer Safety Net Interventions Selection SL-NACSA-104653-CS-INDV Development of Systems for Individual Under / 2 Community Based IDA / D0920 Implementation of Social Post Consultant Open 25,986.00 0.00 2019-06-14 2019-08-02 2019-08-23 2019-09-27 2020-03-25 Implementation Specialist staff-New Safety Net Interventions Selection Development of Systems for Individual SL-NACSA-108103-CS-CQS / Under IDA / D0920 Implementation of Social Post Consultant Open 12,993.00 0.00 2019-04-02 2019-05-21 2019-06-11 2019-07-16 2020-01-12 Fleet Operator Implementation Safety Net Interventions Selection SL-NACSA-109631-CS-CQS / Development of Systems for Individual Under Recruitment of District IDA / D0920 Implementation of Social Prior Consultant Open 25,624.00 0.00 2019-04-11 2019-05-30 2019-06-20 2019-07-25 2020-01-21 Implementation Coordinator Safety Net Interventions Selection SL-NACSA-109632-CS-INDV Development of Systems for Individual / Recruitment of Information Under IDA / D0920 Implementation of Social Prior Consultant Open 25,624.00 0.00 2019-05-08 2019-06-26 2019-07-17 2019-08-21 2020-02-17 Education and Implementation Safety Net Interventions Selection Communication Officer (IEC) SL-NACSA-109633-CS-INDV Development of Systems for Individual / Community Based Pending IDA / D0920 Implementation of Social Prior Consultant Open 12,993.00 0.00 2019-04-11 2019-05-30 2019-06-20 2019-07-25 2020-01-21 Specialist (Assigned to Implementation Safety Net Interventions Selection Kailahun District) Page 3 Development of Systems for Individual SL-NACSA-104651-CS-INDV Pending IDA / D0920 Implementation of Social Prior Consultant Open 12,110.00 0.00 2019-04-12 2019-05-31 2019-06-21 2019-07-26 2020-01-22 / 2 Data Operator Implementation Safety Net Interventions Selection SL-NACSA-118357-CS-INDV / Recruitment of Community Monitors (Moyamba, Bo, Bonthe, Pujehun,Bombali,Port Development of Systems for Individual Pending Loko, IDA / D0920 Implementation of Social Prior Consultant Limited 8,425.76 0.00 2019-06-21 2019-06-26 2019-07-17 2019-08-21 2020-02-17 Implementation Tonkolili,Kambia,Koinadugu, Safety Net Interventions Selection Falaba, Karene,Kono, Kenema, Kailahun and Western Rural) Development of Systems for Individual SL-NACSA-118539-CS-INDV Pending IDA / D0920 Implementation of Social Post Consultant Open 2,500.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 / Rent (Office) Implementation Safety Net Interventions Selection Development of Systems for Individual SL-NACSA-118544-CS-INDV Pending IDA / D0920 Implementation of Social Post Consultant Open 2,000.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 / Staff Recruitment Implementation Safety Net Interventions Selection Development of Systems for Individual SL-NACSA-118550-CS-INDV Under IDA / D0920 Implementation of Social Prior Consultant Open 39,000.00 0.00 2019-06-21 2019-08-09 2019-08-30 2019-10-04 2020-04-01 / National Coordinator Implementation Safety Net Interventions Selection SL-NACSA-119201-CS-INDV Development of Systems for Individual Under / Monitoring and Evaluation IDA / D0920 Implementation of Social Prior Consultant Open 1,000.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 Implementation Officer Safety Net Interventions Selection Development of Systems for Individual SL-NACSA-119203-CS-INDV IDA / D0920 Implementation of Social Post Consultant Open 500.00 0.00 Under Review 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 / District Monitors Safety Net Interventions Selection SL-NACSA-121008-CS-INDV / System IT Intergration(Cisco WS- C3560CX-8TC-S catalyst 3560-CX 8GB port,Catalyst 2960L 24 port GigE with PoE,4 x 1G SF Switch cabinet b4u rack Development of Systems for Individual Pending Big 42 u rack IDA / D0920 Implementation of Social Post Consultant Limited 88,266.00 0.00 2019-07-19 2019-07-24 2019-08-14 2019-09-18 2020-03-16 Implementation NW Wall module (double) Safety Net Interventions Selection Trunks 1" Trunks 2" Trunks 3" Trunks 4" Duke 30mm-40mm RJ45-Metal CAT 6 Development of Systems for Individual SL-NACSA-119206-CS-INDV Pending IDA / D0920 Implementation of Social Post Consultant Open 39,247.06 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 / Community Monitors Implementation Safety Net Interventions Selection Page 4