Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 12/05/2016 1. Basic Information Project ID & Name P095173: PH Mindanao Trust Fund-Reconstr & Dev Country Philippines Task Team Leader Matthew James Keir Stephens Sector Manager/Director Bassam Ramadan Country Director Mara K. Warwick Original Board Approval Date 07/20/2005 Original Closing Date: 12/31/2015 Current Closing Date 03/31/2017 Proposed Closing Date [if applicable] 03/31/2017 EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 06/01/2005 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 0.00 0.00 PHMF 50.00 8.26 Total 50.00 8.26 3. Borrower Organization Department Location Community and Family Services Philippines International Mindanao Land Foundation Philippines International Labour Philippines Organization 4. Implementing Agency Organization Department Location Bangsamoro Development Agency Philippines i 5. Disbursement Estimates (US$m) Actual amount disbursed as of 01/23/2017 22.32 Fiscal Year Annual Cumulative 2017 1.80 24.12 Total 24.12 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes Project Development Objective Communities of conflict-affected areas, internally displaced people, and rebel returnees benefitfrom visible restoration of some basic services of their choice and sustained by more accountable Local Government Units (LGUs).Project Development Outcomes Outcome 1: Communities of conflict-affected areas, internally displaced people, and rebel returneeshave satisfactorily decided on, planned and implemented sub-projects of their choice. Outcome 2: LGU capacity is improved forproject planning, resolving conflicts, project implementation and seeking resources for sub-projects in conflict- affectedcommunities Outcome 3: The Bangsamoro Development Agency (BDA), as the local program management office and other implementingpartners, have achieved sufficient management capacity to work with local government units (LGUs) and local development groups, inreconstruction and development activities. 7b. Revised Project Development Objectives/Outcomes [if applicable] ii