Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: March ......, 2017 3. Date of General Procurement Notice: ............................ 4. Period covered by this procurement plan: March 17 to Jan 2018. II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (PRT) Comments US$ (Millions) 1. Works (Including turnkey, supply & 5 High installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 1.5 High Consulting Services) 3. Consultant Services (Firms) 0.5 High 4. Consultant Services (Individual Consultants) 0.2 High 2. Pre-qualification NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: Domestic Preference shall apply. 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultants contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Uganda : Uganda Energy for Rural Transformation III PLAN General Information Country: Uganda Bank’s Approval Date of the Original Procurement Plan: 2017-03-22 2019-11-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133312 GPN Date: Project Name: Uganda Energy for Rural Transformation III Loan / Credit No: IDA / 56530 Executing Agency(ies): Rural Electrification Agency WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-REA-40437-CW-RFB / Construction of ERT-3 grid extension projects in Fast Track Lot 1 (Kiganda-Mile 16 with tee-off Katabalanga Open - Single Stage - One & Kibyamirizi) and IDA / 56530 On-grid Energy Access Prior Request for Bids 10,652,600.00 8,209,845.45 Signed 2017-10-30 2018-01-05 2018-02-23 2018-05-14 2018-07-18 2019-12-18 International Envelope Construction of ERT-3 grid extension projects in Fast Track Lot 2: Ruhumba - Kashwa with tee-off Rwebishuri (123km) UG-REA-14928-CW-RFB / Construction of ERT-3 grid extension projects in Fast Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 5,688,800.00 0.00 Canceled 2017-08-17 2017-09-25 2017-12-12 2018-01-11 2018-05-14 2019-10-15 Track Lot 1 (Kiganda-Mile International Envelope 16 with tee-off Katabalanga & Kibyamirizi) UG-REA-18286-CW-RFB / Construction of ERT-3 grid extension projects in Fast Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 4,963,800.00 0.00 Canceled 2017-08-17 2017-09-25 2017-12-12 2018-01-11 2018-05-16 2019-09-13 Track Lot 2: Ruhumba - International Envelope Kashwa with tee-off Rwebishuri (123km) UG-REA-59119-CW-RFB / Procurement of contractors to implement works for grid Under Single Stage - One intensification in Western, IDA / 56530 On-grid Energy Access Prior Request for Bids Open - National 4,499,122.00 0.00 Implementati 2018-06-28 2018-07-19 2018-09-10 2018-11-26 2019-01-07 2020-06-12 Envelope Central and Rwenzori service on territories under Lot 1, Lot 2 and Lot 3 UG-REA-71500-CW-RFB / Single Stage - One Batch 1 for intensification IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 4,000,000.00 3,516,291.97 Signed 2018-11-15 2018-12-24 2019-01-14 2019-02-18 2019-03-24 2020-07-22 Envelope works in Umeme Area UG-REA-14709-CW-RFB / Pending Construction of ERT-3 grid Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 9,603,000.00 0.00 Implementati 2019-08-12 2019-08-26 2019-10-17 2019-11-27 2020-01-10 2021-05-09 extension projects in Lot C International Envelope on (220km) UG-REA-14712-CW-RFB / Pending Construction of ERT-3 grid Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 15,439,600.00 0.00 Implementati 2019-07-22 2019-08-05 2019-09-25 2019-11-05 2019-12-24 2021-04-23 extension projects in Lot B International Envelope on (320km) UG-REA-14892-CW-RFB / Pending Construction of ERT-3 grid Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 9,803,600.00 0.00 Implementati 2019-08-12 2019-08-26 2019-10-17 2019-11-27 2021-05-09 2021-11-05 extension projects in Lot E International Envelope on (214km) Page 1 UG-REA-14896-CW-RFB / Pending Construction of ERT-3 grid Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 11,757,137.00 0.00 Implementati 2019-07-22 2019-08-06 2019-09-26 2019-11-06 2019-12-24 2021-04-23 extension projects in Lot A International Envelope on (307km) UG-REA-14909-CW-RFB / Construction of ERT-3 grid extension projects in Fast Under Open - Single Stage - One Track Lot 3 (Wandi-Yumbe- IDA / 56530 On-grid Energy Access Prior Request for Bids 13,070,400.00 0.00 Implementati 2019-03-13 2019-03-18 2019-05-08 2019-07-03 2019-09-02 2020-12-31 International Envelope Moyo) and Fast Track Lot 4 on (Onduparika-Odramachu- Abiria) UG-REA-18290-CW-RFB / Under Construction of ERT-3 grid Open - Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids 8,374,800.00 0.00 Implementati 2019-08-12 2019-08-26 2019-10-17 2019-11-27 2020-01-10 2021-05-10 extension projects in Lot D International Envelope on (219km) UG-REA-115580-CW-RFB / Procurement of contractors to implement works for grid intensification in 10 STs - North North Western, Open - Single Stage - One Under IDA / 56530 On-grid Energy Access Prior Request for Bids 14,965,016.52 0.00 2019-07-08 2019-07-31 2019-09-13 2019-10-14 2019-12-30 2021-02-27 Northern, West Nile, North International Envelope Review Eastern, Eastern, Central North, Southern, South Western, North Western, and Mid-Western UG-REA-113460-CW-RFB / Under Batch 2 for Grid Single Stage - One IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 3,893,000.00 0.00 Implementati 2019-06-21 2019-06-27 2019-08-01 2019-08-26 2019-10-01 2020-11-29 Intensification works in Envelope on Umeme area GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-REA-14924-GO-RFQ / Pending Request for Single Stage - One Supply of Inspector's IDA / 56530 On-grid Energy Access Post Limited 10,765.00 0.00 Implementati 2017-08-07 2017-10-18 2019-01-16 Quotations Envelope Measurement Equipment on UG-REA-14619-GO-RFB / Supply of (02) Double Cabin Pick-ups and (01) Station Single Stage - One IDA / 56530 On-grid Energy Access Prior Request for Bids Open - National 244,000.00 0.00 Canceled 2017-09-11 2017-10-16 2017-11-15 2017-11-29 2018-01-10 2018-03-26 Wagon for REA and (01) Envelope Double Cabin Pick-up for UNBS UG-REA-8728-GO-RFB / Single Stage - One Supply of a Double Cabin IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 49,000.00 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 2018-03-18 Envelope Pick-up for UNBS UG-REA-14929-GO-RFB / Design, supply, installation and training of PV testing equipment for:- Lot 1: PV modules Single Stage - One IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 300,000.00 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 2018-03-18 Lot 2: Charge controllers Envelope Lot 3: PV batteries Lot 4: PV inverters Lot 5: PV lights Lot 6: PV Field testing kits" Page 2 UG-REA-14916-GO-RFQ / Supply of ICT Equipment Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Open - National 27,750.00 0.00 Canceled 2017-07-10 2017-11-30 2018-04-02 (Laptops, Tablets & Quotations Envelope Projector) UG-REA-54564-GO-RFQ / Supply of (02) Double Cabin Request for Single Stage - One IDA / 56530 On-grid Energy Access Post Limited 195,000.00 163,883.38 Signed 2018-04-03 2018-06-08 2018-09-06 Pick-ups and (01) Station Quotations Envelope Wagon UG-REA-59113-GO-RFQ / Request for Single Stage - One Supply of the aerial imagery IDA / 56530 On-grid Energy Access Post Limited 48,420.00 21,205.19 Signed 2018-05-02 2018-06-15 2018-08-06 Quotations Envelope equipment and software UG-REA-81485-GO-RFQ / Request for Single Stage - One Supply of aerial imagery IDA / 56530 On-grid Energy Access Post Limited 35,000.00 15,314.89 Signed 2018-10-30 2018-12-10 2019-01-11 Quotations Envelope software and equipment UG-REA-108808-GO-RFB / Under Open - Single Stage - One Procurement of 20,000 ready IDA / 56530 On-grid Energy Access Prior Request for Bids 1,820,000.00 0.00 Implementati 2019-04-21 2019-05-10 2019-07-01 2019-07-31 2019-09-27 2020-02-26 International Envelope boards on UG-REA-113430-GO-RFB / Purchase of 4 single cabin pick-ups and 2 double cabin Pending pickups for supervision of Single Stage - One IDA / 56530 On-grid Energy Access Post Request for Bids Open - National 316,000.00 0.00 Implementati 2019-05-18 2019-05-22 2019-06-05 2019-06-21 2019-07-29 2019-10-29 field works under lines 1-4 Envelope on and intensification works under Umeme and other STs NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-REA-14661-NC-DIR / Services for Independent IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 770,000.00 701,364.00 Signed 2017-05-24 2017-06-07 2017-11-17 2020-05-15 Verification Agent for non- OBA connections UG-REA-14710-NC-DIR / Procurement of an Independent Verification Pending Agent (IVA) for the Rural IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 462,057.80 0.00 Implementati 2016-08-01 2016-08-01 2016-11-07 2017-07-29 Electricity Household on Connections under OBA Project: Lot 1: Umeme and non Umeme Connections UG-REA-14708-NC-DIR / Procurement of a wayleaves IDA / 56530 On-grid Energy Access Post Direct Selection Direct 135,000.00 0.00 Canceled 2017-06-19 2017-07-24 2017-12-27 2020-06-24 management software CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 UG-REA-14931-CS-QCBS / Consultancy Services for construction supervision of Fast Track Lot 1 (Kiganda- Quality And Cost- Open - Mile 16 with tee-off IDA / 56530 On-grid Energy Access Prior 580,000.00 1,731,078.65 Signed 2016-11-16 2016-12-07 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2018-10-06 Based Selection International Katabalanga & Kibyamirizi) and Fast Track Lot 2 (Ruhumba-Kashwa with tee- off Rwebishuri) UG-REA-14274-CS-QCBS / Consultancy Services for RAPs, review of engineering designs, preparation of Quality And Cost- Open - bidding documents, IDA / 56530 On-grid Energy Access Prior 1,930,000.00 0.00 Canceled 2017-05-31 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2018-12-10 Based Selection International procurement support, construction supervision and project management for Lot 1 UG-REA-16031-CS-QCBS / Consultancy Services for RAPs, review of engineering designs, preparation of Quality And Cost- Open - bidding documents, IDA / 56530 On-grid Energy Access Prior 2,010,000.00 2,348,549.51 Signed 2017-05-31 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2018-12-10 Based Selection International procurement support, construction supervision and project management for Lot 2. UG-REA-14862-CS-CQS / Consultant Consultancy Services for EIA IDA / 56530 On-grid Energy Access Post Qualification Open - National 150,000.00 136,162.66 Signed 2015-08-13 2015-09-03 2016-06-16 2016-12-02 2017-05-31 2017-09-26 for Lot B Selection UG-REA-14869-CS-CQS / Consultant Consultancy Services for EIA IDA / 56530 On-grid Energy Access Post Qualification Open - National 100,000.00 86,438.87 Signed 2015-07-13 2015-08-03 2016-06-10 2016-12-02 2017-05-31 2017-09-26 for Lot D Selection UG-REA-14849-CS-CQS / Consultant Consultancy Services for EIA IDA / 56530 On-grid Energy Access Post Qualification Open - National 140,000.00 127,732.49 Signed 2015-09-13 2015-10-04 2016-06-24 2016-12-02 2017-05-31 2017-09-26 for Lot A Selection UG-REA-14864-CS-CQS / Consultant Consultancy Services for EIA IDA / 56530 On-grid Energy Access Post Qualification Open - National 100,000.00 91,363.27 Signed 2015-07-13 2015-08-03 2016-06-10 2016-07-10 2017-05-31 2017-09-26 for Lot E Selection UG-REA-14836-CS-CQS / Consultant Under Consultancy Services for EIA IDA / 56530 On-grid Energy Access Post Qualification Open - National 100,000.00 0.00 2015-07-13 2015-08-05 2016-06-10 2016-07-10 2017-05-31 2017-09-26 Implementation for Lot C Selection UG-REA-8819-CS-QCBS / Consultancy Services for Review of Engineering Designs, Preparation of Quality And Cost- Open - IDA / 56530 On-grid Energy Access Prior 599,200.00 0.00 Canceled 2015-05-19 2015-06-09 2015-07-23 2015-08-20 2015-09-19 2015-10-24 2015-11-28 2016-11-27 Bidding Documents and Based Selection International construction supervision for Lot 12: Ngeta & Lot 13: Dokolo UG-REA-14841-CS-QCBS / Consultancy services for construction supervision of Quality And Cost- Open - Fast Track Lot 3 (Wandi- IDA / 56530 On-grid Energy Access Prior 862,500.00 0.00 Canceled 2017-06-15 2017-07-06 2019-05-08 2019-06-05 2019-07-05 2019-08-30 2019-11-15 2020-08-24 Based Selection International Yumbe-Moyo) and Fast Track Lot 4 (Onduparika- Odramachu-Abiria) UG-REA-18292-CS-QCBS / Consultancy Services for Quality And Cost- Open - IDA / 56530 On-grid Energy Access Prior 1,000,000.00 0.00 Canceled 2017-06-20 2017-07-24 2017-09-29 2017-12-15 2017-12-15 2018-03-09 2018-06-25 2021-01-21 Community mobilisation to Based Selection International achieve Connections Page 4 UG-REA-18282-CS-QCBS / Consultancy services for construction supervision of Quality And Cost- Open - Under Fast Track Lot 3 (Wandi- IDA / 56530 On-grid Energy Access Prior 862,500.00 0.00 2017-10-16 2017-11-06 2018-01-29 2018-03-19 2018-05-03 2018-06-25 2018-09-24 2021-06-17 Based Selection International Implementation Yumbe-Moyo) and Fast Track Lot 4 (Onduparika- Odramachu-Abiria) UG-REA-30858-CS-CQS / Consultancy Services for an Consultant Integrated Environmental, IDA / 56530 On-grid Energy Access Post Qualification Open - National 80,000.00 82,612.91 Signed 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2018-08-16 Health and Safety Selection Management System for the Rural Electrification Program UG-REA-14902-CS-INDV / Technical Consultant to Consultant identify equipment and IDA / 56530 On-grid Energy Access Post Qualification Open - National 64,960.00 0.00 Canceled 2017-06-16 2017-06-30 2017-08-30 2017-10-10 2018-05-08 training needs for UNBS Selection technical staff UG-REA-14899-CS-CQS / Consultant Accreditation to Test Open - IDA / 56530 On-grid Energy Access Post Qualification 20,000.00 0.00 Canceled 2017-06-16 2017-06-30 2017-07-27 2017-08-30 2017-09-19 2018-05-02 Laboratory as per ISO/IEC International Selection 17025 UG-REA-14905-CS-CQS / Accreditation of UNBS Consultant Open - Inspection Services (Imports IDA / 56530 On-grid Energy Access Post Qualification 21,500.00 0.00 Canceled 2017-08-28 2017-09-11 2017-10-07 2017-11-11 2017-12-01 2018-07-14 International & Market Surveillance) to Selection ISO 17020 UG-REA-4445-CS-QCBS / Consultancy services for Quality And Cost- Open - Under IDA / 56530 On-grid Energy Access Prior 2,750,000.00 0.00 2018-05-18 2018-07-02 2018-08-30 2018-11-08 2018-12-08 2019-02-22 2019-05-16 2022-03-11 marketing and mobilisation Based Selection International Implementation for connections UG-REA-67362-CS-QCBS / Services for Independent Quality And Cost- Open - Under IDA / 56530 On-grid Energy Access Prior 870,000.00 0.00 2018-06-29 2018-07-20 2018-08-09 2018-10-12 2018-10-26 2019-01-03 2019-03-16 2021-09-14 Verification Agent for 87k Based Selection International Implementation connections (ERT-3 87k) UG-REA-107573-CS-QCBS / Consultancy Services for RAPs, review of engineering designs, preparation of Quality And Cost- Open - bidding documents, IDA / 56530 On-grid Energy Access Prior 1,930,000.00 2,512,906.95 Signed 2017-10-04 2017-10-25 2018-01-15 2018-03-29 2018-07-11 2018-09-04 2019-04-19 2020-07-09 Based Selection International procurement support, construction supervision and project management for Lot 1 UG-REA-115592-CS-QCBS / Quality And Cost- Open - Under Consultancy services for IDA / 56530 On-grid Energy Access Prior 1,100,000.00 0.00 2019-05-31 2019-06-28 2019-08-07 2019-09-26 2019-11-11 2020-01-14 2020-02-17 2021-02-16 Based Selection International Implementation mobilization of connections UG-REA-143341-CS-QCBS / Consultancy services for Quality And Cost- Open - Under IDA / 56530 Off-grid Energy Access Prior 1,605,750.00 0.00 2019-11-01 2019-11-22 2020-01-05 2020-02-02 2020-03-03 2020-04-07 2020-05-12 2021-02-06 Connections data cleaning Based Selection International Implementation and Updating UG-REA-144934-CS-CQS / Consultancy services for for Consultant strengthening and promoting Pending IDA / 56530 On-grid Energy Access Post Qualification Open - National 120,000.00 0.00 2019-11-19 2019-11-25 2019-12-30 2020-03-23 2020-04-08 2020-05-23 the use of Geographic Implementation Selection Information systems (GIS) in uganda’s energy sector Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-REA-14704-CS-CDS / Consultancy Services for RAPs for Fast Track Lot 3 (Wandi-Yumbe-Moyo) and IDA / 56530 On-grid Energy Access Post Direct Selection Direct 220,000.00 169,860.29 Signed 2015-05-20 2015-07-27 2016-05-30 2016-11-26 Fast Track Lot 4 (Onduparika-Odramachu- Abiria) Individual UG-REA-15974-CS-INDV / IDA / 56530 On-grid Energy Access Prior Consultant Open 270,000.00 175,668.29 Signed 2017-05-26 2017-07-24 2017-10-17 2017-11-06 2021-11-12 Project Engineer (01) Selection Individual UG-REA-15975-CS-INDV / IDA / 56530 On-grid Energy Access Prior Consultant Open 270,000.00 175,668.29 Signed 2017-05-26 2017-07-24 2017-10-17 2017-11-06 2021-11-12 Project Engineer (01) Selection UG-REA-16000-CS-CDS / Consultancy services for review of engineering designs & bidding documents IDA / 56530 On-grid Energy Access Post Direct Selection Direct 54,500.00 54,500.00 Signed 2015-05-20 2015-07-27 2016-06-13 2018-07-30 for Fast Track Lot 1 (Kiganda-Mile 16 with tee-off Katabalanga & Kibyamirizi) Individual UG-REA-14313-CS-INDV / IDA / 56530 On-grid Energy Access Prior Consultant Open 105,000.00 206,283.82 Signed 2016-04-08 2016-11-16 2017-03-02 2017-03-24 2019-03-24 Procurement Specialist Selection UG-REA-8825-CS-CDS / Consultancy Services for Review of Engineering Designs & Preparation of Pending IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 61,500.00 0.00 2015-04-26 2015-05-06 2015-07-10 2016-01-06 Bidding Document for Fast Implementation Track Lot 2: Ruhumba- Kashwa with tee-off Rwebishuri Individual UG-REA-013 / Senior Social IDA / 56530 On-grid Energy Access Prior Consultant Open 210,000.00 176,280.61 Signed 2017-06-19 2017-08-21 2017-10-23 2017-11-30 2021-12-01 Development Officer (01) Selection UG-REA-14881-CS-CDS / Consultancy services for review of engineering designs & bidding documents IDA / 56530 On-grid Energy Access Post Direct Selection Direct 172,900.00 0.00 Canceled 2017-05-15 2017-06-07 2017-11-10 2018-12-05 for Fast Track Lot 3 (Wandi- Yumbe-Moyo) and Fast Track Lot 4 (Onduparika- Odramachu-Abiria) UG-REA-18276-CS-CDS / Consultancy services for review of engineering designs & bidding documents IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 172,900.00 199,150.00 Signed 2017-06-19 2017-07-12 2017-11-13 2019-01-28 for Fast Track Lot 3 (Wandi- Yumbe-Moyo) and Fast Track Lot 4 (Onduparika- Odramachu-Abiria) Page 6 UG-REA-8815-CS-CDS / Consultancy Services for environmental audit for three lines constructed under IDA / 56530 On-grid Energy Access Post Direct Selection Direct 95,000.00 0.00 Canceled 2016-11-30 2016-12-10 2017-02-13 2017-08-12 ERT II restructuring, intensification of the 9 lines and agricultural farms UG-REA-14921-CS-CDS / Consultancy Services for update of EIA and RAPs for IDA / 56530 On-grid Energy Access Post Direct Selection Direct 75,000.00 0.00 Canceled 2016-11-30 2016-12-10 2017-02-13 2017-08-12 Fast track Lot 2 (Ruhumba- Kashwa with tee-off Rwebishuri) Individual UG-REA-8888-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 80,925.00 58,138.93 Signed 2017-10-02 2018-01-08 2018-04-05 2018-05-10 2020-05-11 Wayleaves Officer Selection Individual UG-REA-29005-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 80,295.00 61,100.81 Signed 2017-10-02 2018-01-08 2018-04-05 2018-05-10 2020-05-11 Wayleaves Officer (01) Selection Individual UG-REA-29654-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 80,925.00 59,995.46 Signed 2017-10-02 2018-01-01 2018-04-05 2018-05-10 2020-05-11 Wayleaves Officer Selection Individual UG-REA-29624-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 80,925.00 61,100.81 Signed 2017-10-02 2018-01-08 2018-04-05 2018-05-10 2020-05-11 Wayleaves Officer Selection UG-REA-14914-CS-INDV / Individual Training Consultant to train IDA / 56530 On-grid Energy Access Post Consultant Open 23,940.00 0.00 Canceled 2017-06-16 2017-07-26 2017-08-30 2017-09-11 2018-05-02 30 Inspector Staff in ISO Selection 17020 UG-REA-18269-CS-CDS / Consultancy Services for update of EIA and RAPs for IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 80,000.00 0.00 Canceled 2017-06-19 2017-07-06 2017-11-13 2018-02-20 fast track Lot 1(Kiganda - Mile 16 with tee -off Katabalanga &Kibyamirizi) UG-REA-40445-CS-CDS / Consultancy Services for Review and Update of the Resettlement Action Plans Pending (RAPs) for Fast Track Lot 1 IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 127,439.00 0.00 2016-11-30 2017-08-03 2017-10-19 2018-02-05 Implementation – Kiganda Mile 16 and Fast Track Lot 2- Ruhumba – Kashwa with tee – off to Rwebushuri projects UG-REA-59054-CS-INDV / Individual Senior Project Engineer - IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 650.00 Signed 2018-04-24 2018-06-11 2018-06-27 2018-07-31 2019-07-31 short term consultant Selection UG-REA-59036-CS-INDV / Individual Senior Project Engineer - IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2018-04-24 2018-06-11 2018-06-27 2018-07-31 2019-07-31 short term consultant Selection UG-REA-59070-CS-INDV / Individual Senior Project Engineer - IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2018-04-26 2018-06-11 2018-06-27 2018-07-31 2019-07-31 short term consultant Selection UG-REA-59081-CS-INDV / Individual Senior Project Engineer - IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 650.00 Signed 2018-04-16 2018-05-30 2018-06-29 2018-07-19 2019-07-19 short term consultant Selection Page 7 UG-REA-8806-CS-CQS / Procurement of a Consultant to determine baseline status and develop a strategy to Individual strengthen the national IDA / 56530 On-grid Energy Access Post Consultant Open 118,000.00 169,662.00 Signed 2018-07-03 2018-10-30 2018-11-20 2018-12-18 2020-01-17 Quality Assurance framework Selection for Solar Home Systems (SHS), Pico-Solar products and individual solar PV components in Uganda UG-REA-14700-CS-CDS / Consultancy Services for EIA for Fast Track Lot 3 (Wandi- IDA / 56530 On-grid Energy Access Post Direct Selection Direct 180,000.00 149,241.00 Signed 2015-05-20 2015-07-27 2016-03-30 2017-02-20 Yumbe-Moyo) and Fast Track Lot 4 (Onduparika- Odramachu-Abiria). UG-REA-46700-CS-INDV / Individual Senior Project Management IDA / 56530 On-grid Energy Access Prior Consultant Open 364,320.00 0.00 Canceled 2018-02-06 2018-05-29 2018-07-20 2018-09-05 2022-09-05 Advisor Selection Individual UG-REA-66944-CS-INDV / IDA / 56530 On-grid Energy Access Prior Consultant Open 364,320.00 358,800.00 Signed 2018-06-25 2018-12-08 2019-01-07 2019-02-16 2021-02-15 Project Management Advisor Selection UG-REA-59142-CS-CDS / Addendum for Procurement of an Independent Verification Agent (IVA) for the Rural Electricity IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 588,420.00 0.00 Canceled 2018-04-16 2018-05-04 2018-06-11 2019-03-08 Household Connections under OBA Project for Umeme connections and other service providers UG-REA-66690-CS-CDS / Services for Independent Verification Agent for 128k IDA / 56530 On-grid Energy Access Prior Direct Selection Direct 1,195,520.00 1,027,840.00 Signed 2018-06-29 2018-07-17 2018-09-11 2021-09-10 connections (ERT-3 63k, KfW 65k) UG-REA-69454-CS-INDV / Individual Under Database Specialist - ECP IDA / 56530 On-grid Energy Access Post Consultant Open 106,260.00 0.00 2018-08-03 2018-11-16 2019-01-15 2019-02-01 2021-02-01 Implementation Department Selection UG-REA-69450-CS-INDV / Individual Marketing Specialist - Short Under IDA / 56530 On-grid Energy Access Post Consultant Limited 53,130.00 0.00 2018-08-03 2018-09-14 2018-09-28 2018-10-05 2019-10-04 Term Consultant - ECP Implementation Selection Department UG-REA-69458-CS-INDV / Individual Financial Specialist - IDA / 56530 On-grid Energy Access Post Consultant Open 106,260.00 121,788.00 Signed 2018-08-03 2018-11-16 2019-01-15 2019-02-01 2021-01-31 Connections Selection UG-REA-69449-CS-INDV / Individual Senior Connections Officer - IDA / 56530 On-grid Energy Access Post Consultant Open 106,260.00 107,187.76 Signed 2018-08-03 2018-11-16 2019-01-15 2019-02-01 2021-01-31 ECP Department Selection UG-REA-69447-CS-INDV / Individual "Procurement Specialist - IDA / 56530 On-grid Energy Access Prior Consultant Open 106,260.00 106,896.82 Signed 2018-08-03 2018-11-22 2019-03-05 2019-03-29 2021-03-28 Connections" Selection UG-REA-72547-CS-CDS / Consultancy services for quality assurance framework IDA / 56530 On-grid Energy Access Post Direct Selection Direct 300,000.00 294,147.74 Signed 2018-08-08 2018-10-12 2018-11-26 2019-11-26 for component based solar systems Page 8 UG-REA-72545-CS-INDV / Consultancy services for the Individual establishment of the IDA / 56530 On-grid Energy Access Post Consultant Open 36,000.00 0.00 Canceled 2018-08-10 2018-10-17 2018-11-09 2018-11-28 2019-05-29 Monitoring and Evaluation Selection Department UG-REA-69456-CS-CDS / Consultancy services for supervision of batch one IDA / 56530 On-grid Energy Access Post Direct Selection Direct 150,000.00 256,247.46 Signed 2018-09-21 2019-01-05 2019-03-04 2021-11-21 intensification works in Umeme service area Individual UG-REA-88327-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 19,500.00 24,217.08 Signed 2018-12-10 2019-03-16 2019-03-28 2019-04-11 2020-07-04 Clerk of Works (01) Selection Individual UG-REA-88323-CS-INDV / IDA / 56530 On-grid Energy Access Post Consultant Open 19,500.00 24,217.08 Signed 2018-12-10 2019-03-16 2019-03-28 2019-04-11 2020-07-04 Clerk of Works (02) Selection UG-REA-92377-CS-CDS / Addendum for consultancy services to update RAPS for ERT 3 Fast track Grid Under IDA / 56530 On-grid Energy Access Post Direct Selection Direct 145,000.00 0.00 2019-01-24 2019-02-03 2019-02-25 2019-05-11 Extension Projects under Implementation Lot 3: Wandi-Yumbe-Moyo and Onduparika-Odramachu- Abiria: (345.8km) UG-REA-69443-CS-INDV / Individual Marketing Specialist - long IDA / 56530 On-grid Energy Access Post Consultant Open 106,260.00 0.00 Canceled 2018-08-03 2018-11-16 2019-01-15 2019-02-01 2021-01-31 term - ECP Department Selection UG-REA-8821-CS-INDV / Individual Under Senior Project Engineer - IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 2019-05-10 2019-06-11 2019-06-21 2019-07-12 2021-07-11 Implementation four - STs batch 1 Selection UG-REA-108857-CS-INDV / Individual Senior Project Engineer - Under IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 2019-05-10 2019-06-11 2019-06-21 2019-07-12 2021-07-11 three - Umeme batch 1 and Implementation Selection 2 UG-REA-113508-CS-INDV / Individual Senior Project Engineer IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2019-05-17 2019-07-25 2019-08-12 2019-09-04 2021-09-03 five for supervision of 3 STS Selection batch 2 UG-REA-113503-CS-INDV / Individual Senior Project Engineer IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2019-05-17 2019-07-25 2019-08-12 2019-09-04 2020-09-03 six STS for Supervision of 3 Selection STs batch 3 UG-REA-113505-CS-INDV / Individual Senior Project Engineer IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2019-05-17 2019-07-25 2019-08-12 2019-09-04 2021-09-03 seven for supervison of 4 Selection STS batch 4 UG-REA-111641-CS-INDV / Individual Under Marketing Specialist - Long IDA / 56530 On-grid Energy Access Post Consultant Open 106,260.00 0.00 2019-05-13 2019-07-24 2019-08-12 2019-09-01 2021-08-31 Implementation term Selection Individual UG-REA-113502-CS-INDV / Under IDA / 56530 On-grid Energy Access Post Consultant Open 180,000.00 0.00 2019-06-10 2019-08-20 2019-09-10 2019-09-28 2021-09-27 M & E Manager Implementation Selection UG-REA-113504-CS-INDV / Individual Senior Project Engineer IDA / 56530 On-grid Energy Access Post Consultant Open 72,000.00 0.00 Canceled 2019-06-07 2019-08-15 2019-09-02 2019-09-25 2021-09-24 six STS for Supervision of 3 Selection STs batch 3 Page 9 UG-REA-108868-CS-INDV / Individual Clerk of works for Line 4 - Under IDA / 56530 On-grid Energy Access Post Consultant Open 19,500.00 24,249.29 2019-06-07 2019-08-25 2019-09-06 2019-09-16 2020-12-14 Onduparaka - Odramacaku - Implementation Selection Abiria UG-REA-108866-CS-INDV / Individual Under Clerk of works for Line 3 - IDA / 56530 On-grid Energy Access Post Consultant Open 19,500.00 24,217.08 2019-06-07 2019-08-28 2019-09-09 2019-09-19 2020-12-17 Implementation Wandi - Yumbe - Moyo Selection UG-REA-138974-CS-INDV / Individual Under Recruitment of Wayleave IDA / 56530 On-grid Energy Access Post Consultant Limited 462,000.00 0.00 2019-10-20 2019-10-30 2019-11-20 2019-12-25 2021-12-14 Implementation officer (07) Selection UG-REA-142260-CS-INDV / Individual Under Recruitment of three (03) IDA / 56530 On-grid Energy Access Post Consultant Open 216,000.00 0.00 2019-10-31 2019-12-19 2020-01-09 2020-02-13 2020-04-25 Implementation Senior Project Engineers Selection UG-REA-143342-CS-INDV / Individual Pending Recruitment of five clerk of IDA / 56530 Off-grid Energy Access Post Consultant Open 121,875.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2022-02-03 Implementation works for 17 lines Selection Page 10