Guizhou Cultural and Natural Heritage Protection and Development Project Anshun Jiuzhou Tunbao Cultural Heritage Protection Project Procurement Plan Adjustment 1 2 3 4 5 6 7 8 9 10 Estimated Credit Contract Procurement Review by Expected Bid- Ref.No Contract (Description) Type Cost Ceilings Duration Method Bank opening Date USD 104 USD 104 (Month) Construction for public and historical buildings, including: Tourists Information Center (500m2); museum (2000m2) and rehabilitation of Catholic Church (3100m2); Qingyuan Palace (650 m2), Guanyue Temple (300 m2), Wanshou Palace (350 m2). Before 263.46 Prior 05/2010 Construction of local infrastructure, including: parking place (3020m2), pedestrian roads (4.2km), drainage pipe (1km), garbage disposal station (160m2), public toilets (6), river training works, indication signature boards (120), cultural explanation signature boards (120), rubbish bin (80). ASJZ/C1.1 Construction for public and historical buildings, including: Tourist information center rebuilt on a discarded cement plant; Tunbao Cultural Square Civil works 240.05 NCB 24 ASJZ/C1 (12000 m2); rehabilitation of Family Lu’s old residence (400 m2); museum. Construction of local infrastructure, including: parking 214.96 Prior 10/2011 place, pedestrian roads, drainage pipe, garbage disposal station (160 m2), public toilets (2),river After training works, indication signature boards (120), cultural explanation signature boards (120),rubbish bin (80). ASJZ/C1.2 Construction of public and historical buildings: rehabilitation of ancient bell tower (300 m2), rehabilitation of Fufeng Pavilion, Qingyuan Palace (650 48.5 Post 10/2011 m2), Guanyue Temple (300 m2), and Wanshou Palace (350 m2). Cancellation: rehabilitation of Catholic Church, fire fighting facilities, and public toilets (4). Community Private houses protection: traditional private Block Participation- ASJZ/C2 44.9 44.9 Post 10/2011 12 houses(88), demonstrative residential houses (5). Grants Force Account Training ASJZ/C3 Training and Study (many times) 2.99 2.98 SOE Post 10/2011 24 and study 11 Reasons (1) Cancel the civil works of Catholic Church. Fire hydrants have been installed in the Jiuzhou town under the small-town water supply project, so the component is also cancelled. (2) Add the rehabilitation of ancient bell tower and Fufeng Pavilion, since both have played very significant roles in Jiuzhou Tunpu history. Add the construction of Tunbao Cultural Square. Include the rehabilitation of Family Lu’s old residence in the component of the museum development, as it’s located right in front of the museum under this project and is a buliding established before new China was founded. (3) The tourist information center will be re- constructed at the site where a discarded cement plant is located. No need to build a completely new structure. (4) The number of public toilet will be reduced to 2 as it can meet the tourists demand baesd on to 2 as it can meet the tourists demand baesd on the current trend of the tourist increase. Since the actual drainage pipes that need to be laid in Jiuzhou town is 2.38 km, therefore, it’s suggested that the total length be increased to 2.38 km from 1 km. Rehabilitation of traditional houses needs an investment of US$ 380,000 while demonstrative houses require an investment of US$ 69,000.