PROCUREMENT PLAN (Textual Part) Project information: COMESA: Great Lakes Trade Facilitation project P151083[country] [Project name] [P-number] Project Implementation agency: [insert legal name]COMESA Secretariat Date of the Procurement Plan: [insert date]14 June 2016 Period covered by this Procurement Plan: [insert from – to period]1 July 2016 – December 31, 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in COMESA Procurement Implementation Rules of November 2005 (as amended by the Council and 2007)[insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. Rule of origin of the goods: requires that all goods, works and services procured by the COMESA Secretariat shall originate in COMESA and requires tenderers to provide evidence of this through provisions of a certificate of origin duly made out by the competent authority of the supplier’s country of origin. Exceptions require written approval by the COMESA Secretary General. Under bank financed activities this will not apply 2. Participation in bidding: Open competition will be the default method of bidding. Restrictions whereby the Secretariat may deny bidders participation based on restriction for bidding to bidders being nationals of any non-Member States own or controlled bidders or to bidders who have substantial business activities in the territory of the Member State under whose laws it is constituted will not apply. Neither will restriction based on region. 3. Conditions for Use of Restricted Tendering: The restriction by COMESA under restricts tendering process whereby to only those bidders invited by the Secretariat will not apply under Bank financing; 4. Fraudulent practice: COMESA provisions on Fraud and Corruption will be modified to conform with the Banks definition of fraud and corruption which includes cross debarment 5. Tender Security: Tender security will not be restricted to the use of bid security from commercial banks and or bid bonds from insurance firms. At the option of the COMESA Secretariat, use may be made of Bid securing declaration in lieu of requests for provisions of bid security 6. Selection of consultants: Selection of consultant services based on methods and selection process as contained in the Banks Consultants Guidelines will apply in the selection of consultants services 7. Standard Bidding Documents: COMESA will use where possible the banks Standard Bidding documents in cases where COMESA does not have its own standard bidding documents. Where use is made of COMESA’s own Standard Bidding documents, the Bank will review and clear these to ensure they include minimum Banks policy for procurement and selection of consultants. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets: as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable”. Procurement of Second Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable”. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. Contracts selected on basis of CQS, LCS and FBS may not exceed cost estimate of US$200,000 equivalent. 1. Terms of Reference (TOR): TOR for all consulting assignments (firms and individual consultants) irrespective of selection method or value will be subject to prior review by the Bank. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. In the case of this COMESA implemented project, the national consultants at the option of COMESA may be consultants from one member country or from the entire group of COMESA countries. PROCUREMENT Eastern Africa : AFR RI-Great Lakes Trade Facilitation PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-03-28 2021-08-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151083 GPN Date: 2016-12-06 Project Name: AFR RI-Great Lakes Trade Facilitation Loan / Credit No: IDA / 57240 C Executing Agency(ies): ellule Infrastructures WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-CI-5425-CW-RFB / Conception et réalisation des travaux de construction des (a) infrastructures et Component 1: Improving Single Stage - One 21,876,340.0 18,091,059. 2019-11- installations aux postes IDA / 57240 core trade infrastructure and A priori Appel d'offres Open - International Signé 2017-04-06 2017-06-22 2018-05-28 2017-06-22 2019-02-19 2017-04-11 2017-08-31 2019-01-10 2017-09-30 2019-05-23 2017-11-04 2019-04-18 Envelope 0 14 01 frontaliers de (i) petite facilities in the border areas barrière de Goma, (ii) Ruzizi 1, (iii) Kasindi et (iv) Bunagana et (b) deux marchés frontaliers. ZR-CI-5426-CW-RFQ / Component 1: Improving Travaux provisoires au poste Single Stage - One 2017-10- IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 150,000.00 180,010.70 Signé 2017-04-19 2017-07-20 2017-06-14 2017-10-31 frontalier de la petite barrère Envelope 13 facilities in the border areas au Nord Kivu ZR-CI-5648-CW-RFQ / Component 1: Improving Travaux provisoires au poste Single Stage - One 2017-10- IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 150,000.00 204,622.10 Signé 2017-04-19 2017-07-20 2017-06-14 2017-11-28 frontalier de Ruzizi 1 au Sud Envelope 13 facilities in the border areas Kivu ZR-CI-96037-CW-RFQ / Relocalisation des toilettes et construction d'un bloc Component 1: Improving Single Stage - One 2019-03- sanitaire réservé aux IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 25,033.00 24,027.85 Signé 2019-01-23 2018-12-21 2019-02-21 2019-04-08 Envelope 23 personnes à mobilité réduite facilities in the border areas au poste frontalier de la Petite Barrière à Goma ZR-CI-138796-CW-DIR / Entente directe avec PROTEG pour la Construction des points de lavage des mains à Component 1: Improving Passation de robinets automatiques, 2019-12- IDA / 57240 core trade infrastructure and A posteriori marché de gré à Direct 240,000.00 0.00 Annulé 2019-10-09 2019-10-10 2019-10-15 installation des réservoirs 14 facilities in the border areas gré d'eau, et couloir de séparation du flux de migrants à Goma (Petite Barrière et la Grande Barrière) et à Bunagana. ZR-CI-138797-CW-DIR / Entente directe avec HEISEL pour la Construction des points de lavage des mains à Component 1: Improving Passation de 2019-12- robinets automatiques, IDA / 57240 core trade infrastructure and A posteriori marché de gré à Direct 240,000.00 0.00 Annulé 2019-10-09 2019-10-10 2019-10-15 14 installation des réservoirs facilities in the border areas gré d'eau, et couloir de séparation du flux de migrants à Ruzizi 1, Ruzizi 2 et Kavimvira ZR-CI-138798-CW-DIR / Entente directe avec GSC pour la Construction des points de lavage des mains à robinets Component 1: Improving Passation de 2019-12- automatiques, installation des IDA / 57240 core trade infrastructure and A posteriori marché de gré à Direct 160,000.00 0.00 Annulé 2019-10-09 2019-10-10 2019-10-15 14 réservoirs d'eau, motopompes facilities in the border areas gré et couloir de séparation du flux de migrants à Kasindi et à Mahagi GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-5652-GO-RFQ / Component 4: Equipement de bureau pour la Single Stage - One IDA / 57240 Implementation support, A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2016-12-14 2017-02-08 2017-02-23 Coordination Provinciale du Envelope Communication and M&E Nord Kivu ZR-CI-5441-GO-RFQ / Component 4: Equipement de bureau pour la Single Stage - One IDA / 57240 Implementation support, A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2016-12-14 2017-02-08 2017-02-23 Coordination Provinciale du Envelope Communication and M&E Sud Kivu ZR-CI-5408-GO-RFQ / 3 véhicules 4x4 (2 pour la Component 4: Single Stage - One Coordination Provinciale du IDA / 57240 Implementation support, A posteriori Demande de prix Limited 150,000.00 0.00 Annulé 2016-10-30 2016-12-25 2017-02-23 Envelope Nord Kivu et 1 pour celle du Communication and M&E Sud Kivu) ZR-CI-16132-GO-DIR / Fournitures et installation des Component 1: Improving Passation de lampadaires aux zones IDA / 57240 core trade infrastructure and A priori marché de gré à Direct 62,700.00 62,700.00 Signé 2017-05-25 2018-10-30 2017-06-01 2019-01-13 2017-06-12 2017-07-05 2017-07-12 frontières de la Petite Barrière facilities in the border areas gré de Goma et de la Ruzizi 1 avec le Fournisseur GOSHOP ZR-CI-16142-GO-RFQ / Fourniture et installation des 6 toilettes chimiques, 4 Component 1: Improving Single Stage - One poubelles et 4 bancs de repos IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 20,000.00 16,500.00 Signé 2017-04-28 2017-05-24 2017-05-24 2017-06-08 Envelope dans le cadre d'aménagement facilities in the border areas provisoire de la zone frontière de la Petite Barrière de Goma Page 1 ZR-CI-16139-GO-RFQ / Fourniture et installation des 6 toilettes chimiques, 4 Component 1: Improving Single Stage - One poubelles et 4 bancs de repos IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 20,000.00 15,200.00 Signé 2017-04-28 2017-05-24 2017-05-24 2017-06-08 Envelope dans le cadre d'aménagement facilities in the border areas provisoire de la zone frontière de la Ruzizi 1 Component 2: ZR-CI-5410-GO-RFQ / Implementation of Policy and Matériels informatique pour le Procedural Reforms and Single Stage - One IDA / 57240 A posteriori Demande de prix Limited 3,500.00 2,320.00 Signé 2017-01-10 2017-06-15 2017-03-07 2017-07-19 2017-03-22 personnel PFCGL de la CI Capacity Building to Facilitate Envelope (Goma et Kinshsasa) Cross Border Trade in Goo ds and Services ZR-CI-68778-GO-RFQ / Fourniture du mobilier de Component 1: Improving Single Stage - One bureau pour l'équipement des IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 4,800.00 6,190.00 Achevé 2018-07-14 2018-07-10 2018-09-08 2018-08-16 2018-11-07 2018-09-04 Envelope ouvrages provisoires au poste facilities in the border areas frontalier de Ruzizi 1 à Bukavu ZR-CI-68777-GO-RFQ / Fourniture du mobilier de Component 1: Improving bureau pour l'équipement des Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 4,800.00 6,700.00 Achevé 2018-07-21 2018-07-30 2018-09-15 2018-08-28 2018-11-14 2018-08-29 ouvrages provisoires au poste Envelope facilities in the border areas frontalier de la Petite Barrière de Goma ZR-CI-91366-GO-RFQ / FOURNITURE D'ÉQUIPEMENTS Component 1: Improving DE VULGARISATION ET Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 6,500.00 6,700.00 Signé 2018-12-19 2018-12-14 2019-01-17 2019-04-04 2019-02-01 COMMUNICATION PUBLIQUE Envelope facilities in the border areas AU POSTE FRONTALIER DE RUZIZI 1 AU SUD-KIVU. ZR-CI-110774-GO-DIR / Fourniture et installation de Kit solaire photovoltaïque Component 1: Improving Passation de pour l'alimentation en IDA / 57240 core trade infrastructure and A posteriori marché de gré à Direct 20,200.00 20,196.00 Signé 2019-04-21 2019-05-03 2019-04-26 2019-05-03 2019-05-27 2019-05-22 2019-06-26 électricité du bâtiment facilities in the border areas gré provisoire du poste frontalier de Ruzizi 1 à Bukavu au Sud- Kivu ZR-CI-110780-GO-RFQ / Fourniture et installation d'un Component 1: Improving système de vidéosurveillance Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 5,000.00 4,930.00 Signé 2019-04-26 2019-05-03 2019-06-17 2019-07-25 2019-07-17 au bâtiment provisoire du Envelope facilities in the border areas poste frontalier de Ruzizi 1 à Bukavu au Sud-Kivu ZR-CI-134072-GO-RFQ / Fourniture et installation de huit (8) réservoirs d'eau (Tank) de 10 000 litres et Component 1: Improving motopompes pour le stockage Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 64,000.00 0.00 Annulé 2019-09-20 2019-10-21 2019-11-20 et l'approvisionnement en eau Envelope facilities in the border areas chlorée des points de lavage des mains à robinets automatiques aux postes frontaliers ZR-CI-134069-GO-RFQ / Fourniture de chlore pour Component 1: Improving approvisionnement des points Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 47,250.00 0.00 Annulé 2019-10-20 2019-11-20 2020-05-18 de lavage des mains à Envelope facilities in the border areas robinets automatiques aux postes frontaliers NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-5650-NC-RFQ / Impression de 10 000 Component 2: premiers exemplaires de la Implementation of Policy and charte du commerçant et Procedural Reforms and Single Stage - One IDA / 57240 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2016-12-31 2017-02-25 2017-03-13 l'arrêté portant mise en œuvre Capacity Building to Facilitate Envelope du RECOS (Régime Cross Border Trade in Goo ds Commercial Simplifié) traduits and Services en langue locale ZR-CI-68770-NC-RFQ / Relocalisation des toilettes à Component 1: Improving la Petite barrière à Goma et Single Stage - One IDA / 57240 core trade infrastructure and A posteriori Demande de prix Limited 25,050.00 0.00 Annulé 2018-07-16 2018-12-21 2018-09-10 2018-11-09 construction d'un bloc Envelope facilities in the border areas sanitaire réservé aux personnes à mobilité réduite CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: ZR-CI-5404-CS-CQS / Implementation of Policy and Sélection fondée Traduction, reproduction et Procedural Reforms and sur les diffusion de la charte et du IDA / 57240 A posteriori Open - National 150,000.00 0.00 Annulé 2016-12-27 2017-01-17 2017-03-02 2017-04-01 2017-05-06 2017-07-20 Capacity Building to Facilitate qualifications des RECOS (Régime Commercial Cross Border Trade in Goo ds consultants Simplifié) and Services ZR-CI-5645-CS-CQS / Revue organisationnelle de Sélection fondée Component 3: Performance l'Administration des services sur les IDA / 57240 Based Management in Cross A posteriori Open - International 114,000.00 0.00 Annulé 2016-11-28 2016-12-19 2017-02-01 2017-03-03 2017-04-07 2017-09-07 des frontières et proposition qualifications des Border Administration d'un plan de renforcement des consultants capacités Page 2 ZR-CI-5245-CS-QCBS / Component 3: Performance Sélection fondée Elaboration du programme de IDA / 57240 Based Management in Cross A priori sur la qualité et le Open - International 926,000.00 0.00 Annulé 2017-03-10 2017-03-31 2017-05-14 2017-06-11 2017-07-11 2017-08-15 2017-09-19 2018-04-13 gestion du changement Border Administration coût ZR-CI-5420-CS-LCS / Audit Component 4: financier externe des Sélection au IDA / 57240 Implementation support, A priori Open - International 90,000.00 0.00 Annulé 2016-12-14 2017-01-04 2017-02-06 2017-03-06 2017-03-20 2017-04-07 2017-05-05 2018-06-15 exercices 2016 (y compris le moindre coût Communication and M&E PPF) et 2017 ZR-CI-5418-CS-QCBS / Evaluation environnementale et sociale pour les travaux des infrastructures et installations Component 1: Improving Sélection fondée de base du commerce dans IDA / 57240 core trade infrastructure and A priori sur la qualité et le Open - International 260,860.00 0.00 En cours d'examen 2015-09-30 2018-06-09 2015-10-21 2015-12-04 2016-01-01 2016-09-15 2016-01-31 2019-02-12 2016-12-29 2017-02-02 2017-06-02 les zones frontalières à facilities in the border areas coût Mahagi, Kasindi, Bunagana, Goma, Bukavu, Kavumu, Uvira et Kalemie ZR-CI-5417-CS-QCBS / Contrôle et surveillance des travaux de construction (i) des Component 1: Improving Sélection fondée infrastructures et installations IDA / 57240 core trade infrastructure and A priori sur la qualité et le Open - International 974,800.00 821,900.00 Signé 2017-01-16 2018-07-11 2017-02-06 2017-03-22 2017-04-19 2019-04-04 2017-05-19 2019-05-17 2017-06-23 2019-09-04 2017-07-28 2019-09-06 2019-10-28 aux postes frontaliers de facilities in the border areas coût petite barrière, Ruzizi 1, Kasindi et Bunagana et (ii) de deux marchés frontaliers ZR-CI-5649-CS-QCBS / Etude de faisabilité de la phase 2 du projet (postes Component 1: Improving Sélection fondée frontaliers de Mahagi et de IDA / 57240 core trade infrastructure and A priori sur la qualité et le Open - International 500,000.00 373,050.00 Signé 2016-12-14 2017-01-04 2017-08-08 2017-02-17 2018-03-13 2017-03-17 2017-09-19 2017-04-16 2018-06-20 2017-05-21 2018-10-30 2017-06-25 2018-05-29 2017-12-22 Kavimvira, ports de Kalundu facilities in the border areas coût et de Kalemie et aéroport de Kavumu) ZR-CI-5427-CS-QCBS / Enquête CAP VIH Sida dans les Component 1: Improving Sélection fondée zones frontalières à Mahagi, IDA / 57240 core trade infrastructure and A priori sur la qualité et le Open - International 300,000.00 0.00 Annulé 2017-03-10 2017-03-31 2017-05-14 2017-06-11 2017-07-11 2017-08-15 2017-09-19 2017-12-15 Kasindi, Bunagana, Goma, facilities in the border areas coût Bukavu, Kavumu, Uvira et Kalemie ZR-CI-5416-CS-CQS / Etude environnementale détaillée de Sélection fondée la phase 2 du projet (postes Component 1: Improving sur les frontaliers de Mahagi et de IDA / 57240 core trade infrastructure and A priori Open - International 200,000.00 0.00 Annulé 2017-07-03 2017-07-24 2017-09-06 2017-10-06 2017-11-10 2018-03-09 qualifications des Kavimvira, ports de Kalundu facilities in the border areas consultants et de Kalemie et aéroport de Kavumu) ZR-CI-59682-CS-CQS / Evaluation des Avant-Projets Sommaires pour les travaux Sélection fondée de construction (a) des Component 1: Improving sur les infrastructures et installations IDA / 57240 core trade infrastructure and A posteriori Open - National 150,000.00 0.00 Annulé 2018-04-20 2018-05-11 2018-06-24 2018-07-24 2018-09-21 2018-08-28 2018-10-27 qualifications des aux postes frontaliers (i) facilities in the border areas consultants Petite Barrière de Goma, (ii) Ruzizi 1, Kasindi et (iv) Bunagana et (b) de 3 marchés et plate-formes. ZR-CI-207792-CS-CQS / Etudes topographiques, géotechniques, géophysique, hydrogéologique, études Sélection fondée Component 1: Improving d’implantation du poste sur les En attente IDA / 57240 core trade infrastructure and A posteriori Open - National 250,000.00 0.00 2020-12-04 2020-12-19 2021-01-03 2021-01-13 2021-01-23 2021-04-23 frontalier et du marché de qualifications des d'exécution facilities in the border areas Kamvivira, marché de consultants Bunagana, Marché de Kasindi, marché transfrontalier de Goma ZR-CI-198442-CS-CQS / Sélection fondée Etudes techniques et Component 1: Improving sur les économiques des IDA / 57240 core trade infrastructure and A posteriori Open - International 305,000.00 0.00 Annulé 2020-10-31 2020-11-15 2020-11-24 2020-12-24 2021-01-06 2021-05-06 qualifications des infrastructures routières facilities in the border areas consultants prioritaires PFCGL II ZR-CI-198404-CS-CQS / Etudes des sauvegardes Sélection fondée environnementales et sociales Component 1: Improving sur les détaillées pour les IDA / 57240 core trade infrastructure and A posteriori Open - International 425,000.00 0.00 Annulé 2020-10-29 2020-11-13 2020-11-22 2020-12-22 2021-01-04 2021-04-04 qualifications des infrastructures routières et facilities in the border areas consultants portuaires prioritaires du PFCGL II ZR-CI-198423-CS-CQS / Etudes des sauvegardes Sélection fondée Component 1: Improving environnementales et sociales sur les IDA / 57240 core trade infrastructure and A posteriori Open - International 348,870.00 0.00 Annulé 2020-10-30 2020-11-14 2020-11-23 2020-12-23 2021-01-05 2021-04-05 détaillées des infrastructures qualifications des facilities in the border areas (bâtiments) prioritaires du consultants PFCGL II ZR-CI-198457-CS-CQS / Sélection fondée Etude de faisabilité et études Component 1: Improving sur les techniques détaillés de IDA / 57240 core trade infrastructure and A posteriori Open - International 300,000.00 0.00 Annulé 2020-10-31 2020-11-15 2020-11-24 2020-12-24 2020-12-25 2021-01-03 qualifications des l'aménagement des ports de facilities in the border areas consultants Kituku et d'Idjwi (PFCGL II) ZR-CI-239670-CS-CQS / Prestations de service d'un consultant (firme) chargé des études techniques en vue de Sélection fondée Component 1: Improving la réhabilitation du port de sur les En cours IDA / 57240 core trade infrastructure and A posteriori Open - International 160,000.00 0.00 2021-06-30 2021-07-08 2021-07-21 2021-07-19 2021-09-03 2021-10-03 2021-11-07 2022-05-06 Kalundu dans le cadre de la qualifications des d'exécution facilities in the border areas préparation du Projet de consultants Facilitation du Commerce et Intégration dans la Région des Grands Lacs, PFCIGL INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 ZR-CI-5415-CS-INDV / Component 2: Harmonisation de différents Implementation of Policy and textes nationaux sur les Procedural Reforms and IDA / 57240 A posteriori Individuel Open 52,500.00 0.00 Annulé 2016-11-28 2017-01-16 2017-02-06 2017-03-13 2017-07-13 normes et les procédures en Capacity Building to Facilitate matière de transport Cross Border Trade in Goo ds transfrontalier and Services Component 2: ZR-CI-5409-CS-INDV / Implementation of Policy and Cartographie et répertoire des Procedural Reforms and IDA / 57240 A posteriori Individuel Open 50,000.00 0.00 Annulé 2016-11-28 2017-01-16 2017-02-06 2017-03-13 2017-07-13 associations des commerçants Capacity Building to Facilitate transfrontaliers Cross Border Trade in Goo ds and Services ZR-CI-5651-CS-INDV / Component 4: Elaboration et mise en place IDA / 57240 Implementation support, A posteriori Individuel Limited 50,000.00 0.00 Annulé 2016-11-28 2016-12-03 2016-12-24 2017-01-28 2017-05-29 d'une Stratégie de Communication and M&E communication Component 4: ZR-CI-5403-CS-INDV / IDA / 57240 Implementation support, A priori Individuel Open 90,000.00 0.00 Annulé 2015-11-21 2016-01-09 2017-01-20 2017-02-24 2019-02-24 Auditeur Interne Senior Communication and M&E ZR-CI-5653-CS-INDV / Component 4: Chargé de Communication au IDA / 57240 Implementation support, A priori Individuel Open 50,000.00 0.00 Annulé 2016-11-28 2017-01-16 2017-02-06 2017-03-13 2018-03-13 sein de l'UGP Communication and M&E ZR-CI-5413-CS-INDV / Contrôle et surveillance des Component 1: Improving travaux des infrastructures IDA / 57240 core trade infrastructure and A posteriori Individuel Open 12,600.00 0.00 Annulé 2017-03-15 2017-04-18 2017-05-03 2017-05-24 2017-06-28 2017-12-15 provisoires au poste facilities in the border areas frontaliers de la Petite barrière de Goma ZR-CI-5246-CS-INDV / Contrôle et surveillance des Component 1: Improving travaux des infrastructures IDA / 57240 core trade infrastructure and A posteriori Individuel Open 12,600.00 0.00 Annulé 2017-03-15 2017-04-18 2017-05-03 2017-05-24 2017-06-28 2017-11-06 provisoires au poste facilities in the border areas frontaliers de Ruzizi 1 au Sud Kivu ZR-CI-5428-CS-INDV / Component 4: Comptable du Projet au sein IDA / 57240 Implementation support, A priori Individuel Open 25,500.00 48,000.00 Signé 2015-11-20 2018-07-11 2017-01-10 2017-01-27 2017-01-31 2019-02-12 2017-03-07 2017-03-27 2019-03-07 de la CI Communication and M&E ZR-CI-5407-CS-INDV / Conception des infrastructures provisoires Component 1: Improving aux postes frontaliers de la IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 12,800.00 9,975.00 Signé 2016-12-12 2016-12-28 2017-01-30 2017-03-29 2017-02-20 2017-03-30 2017-03-27 2017-04-14 2017-05-26 Petite barrière de Goma au facilities in the border areas Nord Kivu e à Ruzizi 1 au Sud Kivut ZR-CI-23867-CS-CDS / Contrôle et surveillance des travaux des infrastructures Component 1: Improving Sélection de En cours provisoires aux postes IDA / 57240 core trade infrastructure and A priori consultants par Direct 25,200.00 0.00 2017-08-08 2018-06-20 2017-08-18 2017-07-13 2017-10-22 2018-03-21 d'exécution frontaliers de la Petite barrière facilities in the border areas entente directe de Goma et de Ruzizi 1 au Sud Kivu ZR-CI-51579-CS-INDV / Elaboration du Cadre de Gestion Environnementale et Sociale (CGES) sites frontaliers Component 1: Improving Mwenda, Mokambo, Kipushi, IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 70,060.00 85,341.90 Signé 2018-01-18 2017-12-13 2018-01-23 2018-01-26 2018-02-13 2018-01-31 2018-03-20 2018-02-03 2018-09-16 Kasumbalesa dans la Province facilities in the border areas du Haut-Katanga et Kalemie dans la Province du Tanganyika pour la deuxième phase PFCGL ZR-CI-51681-CS-INDV / Elaboration du Cadre de Politique de Réinstallation (CPR) sites frontaliers Component 1: Improving Mwenda, Mokambo, Kipushi, IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 70,060.00 77,899.50 Signé 2018-01-18 2017-12-13 2018-01-23 2018-01-26 2018-02-13 2018-02-01 2018-03-20 2018-02-03 2018-04-19 Kasumbalesa dans la Province facilities in the border areas du Haut-Katanga et Kalemie dans la Province du Tanganyika pour la deuxième phase du PFCGL ZR-CI-51713-CS-INDV / Component 4: Coordonnateur National du IDA / 57240 Implementation support, A priori Individuel Open 78,000.00 0.00 Annulé 2018-02-01 2018-08-31 2018-03-22 2018-04-12 2018-05-17 2019-05-17 Projet au sein de l'UGP Communication and M&E ZR-CI-59687-CS-CDS / Component 4: Sélection de Renouvellement du Contrat au IDA / 57240 Implementation support, A posteriori consultants par Direct 52,800.00 52,800.00 Signé 2018-04-18 2018-04-20 2018-04-28 2018-07-02 2018-05-09 2020-07-01 poste d'Assistant en Passation Communication and M&E entente directe des Marchés au sein de la CI ZR-CI-68829-CS-CDS / Component 4: Sélection de Renouvellement du Contrat au IDA / 57240 Implementation support, A posteriori consultants par Direct 100,800.00 45,720.00 Signé 2018-07-10 2018-07-25 2018-07-20 2018-06-22 2018-09-23 2018-09-04 2020-09-22 poste de Chef de Projet PFCGL Communication and M&E entente directe au sein de la CI ZR-CI-68831-CS-CDS / Renouvellement du Contrat au Component 4: Sélection de poste de Spécialiste en IDA / 57240 Implementation support, A posteriori consultants par Direct 60,000.00 25,320.00 Signé 2018-06-15 2018-07-26 2018-06-25 2018-07-20 2018-08-29 2018-09-04 2020-08-28 Développement Social et Communication and M&E entente directe Réinstallation au sein de la CI ZR-CI-68750-CS-INDV / Component 4: Expert Environnementaliste au IDA / 57240 Implementation support, A posteriori Individuel Open 69,600.00 60,000.00 Signé 2018-07-10 2018-07-04 2018-08-28 2018-12-13 2018-09-18 2019-01-21 2018-10-23 2019-01-23 2020-10-22 sein de la CI Communication and M&E Page 4 ZR-CI-96039-CS-CDS / Recrutement d'un Consultant Individuel pour l'harmonisation des APS (Avant-Projets Sommaires) et Component 1: Improving Sélection de la production du DAO final IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 25,200.00 29,870.00 Signé 2019-01-23 2018-09-21 2019-01-23 2018-09-07 2019-01-30 2018-09-24 2019-02-27 pour la construction des facilities in the border areas entente directe infrastructures définitives aux sites retenus pour la première phase dans le cadre du Projet PFCGL ZR-CI-112198-CS-INDV / réalisation de l'étude des risques de perte économique des transporteurs sur les sites Component 1: Improving frontières de Kasindi, IDA / 57240 core trade infrastructure and A posteriori Individuel Open 87,990.00 87,355.00 Signé 2019-04-30 2019-04-26 2019-05-29 2019-09-26 2019-06-03 2019-09-26 2019-06-16 2019-10-22 2019-08-15 Bunagana et Petite barrière facilities in the border areas dans la province du Nord-Kivu et Ruzizi 1er dans la province du Sud-Kivu dans le cadre du PFCGL ZR-CI-118347-CS-CDS / Renouvellement du Contrat de Monsieur Dieudonné BOGAGA Component 4: Sélection de En cours pour les prestations au poste IDA / 57240 Implementation support, A posteriori consultants par Direct 24,720.00 0.00 2019-03-19 2019-04-05 2019-03-23 2019-03-30 2020-03-24 d'exécution de comptable du projet PFCGL Communication and M&E entente directe au sein de la Cellule Infrastructures ZR-CI-118353-CS-CDS / Renouvellement du Contrat de Monsieur Shamard SHAMALIRWA pour les prestations au poste de Component 4: Sélection de d'Expert en Développement IDA / 57240 Implementation support, A posteriori consultants par Direct 35,400.00 0.00 Annulé 2019-06-14 2019-06-18 2019-06-25 2020-06-19 social, Spécialiste en Communication and M&E entente directe Réinstallation et plan de gestion environnementale et sociale au sein de la Cellule Infrastructures ZR-CI-118351-CS-CDS / Renouvellement du Contrat de Monsieur Oscar BADEO pour Component 4: Sélection de les prestations au poste de IDA / 57240 Implementation support, A posteriori consultants par Direct 50,400.00 0.00 Annulé 2019-06-20 2019-06-24 2019-07-01 2020-06-25 Chef de Projet du Projet Communication and M&E entente directe PFCGL au sein de la Cellule Infrastructures ZR-CI-118189-CS-CDS / Recrutement du Consultant Franklin MUSHAGALUSA pour appui à la CI dans l'examen de Component 1: Improving Sélection de l’Avant-Projet Détaillé des IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 37,612.00 0.00 Annulé 2019-06-05 2019-06-11 2019-06-21 2019-08-05 infrastructures aux postes facilities in the border areas entente directe frontaliers de la Petite barrière, de Bunagana, de Kasindi au Nord-Kivu et de la Ruzizi 1er au Sud-Kivu . ZR-CI-138799-CS-CDS / Entente directe avec M. Franklin MUSHAGALUSA pour le recadrage des données techniques, le Contrôle et Component 1: Improving Sélection de supervision des travaux de IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 46,710.00 46,990.00 Signé 2019-10-09 2019-11-30 2019-10-10 2019-11-15 2019-10-16 2019-11-26 2020-01-04 construction des points de facilities in the border areas entente directe lavage des mains à robinet automatiques sur les poste frontaliers couverts par le PFCGL. ZR-CI-145875-CS-INDV / Recrutement d’un consultant Component 1: Improving En cours individuel au poste d’Expert IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 42,000.00 0.00 2019-11-22 2019-12-11 2019-12-07 2019-12-14 2019-12-26 2020-12-25 d'exécution Environnementaliste au sein facilities in the border areas de la Cellule Infrastructures ZR-CI-145874-CS-INDV / Recrutement d’un consultant Component 1: Improving individuel au poste d’Expert En cours IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 42,000.00 0.00 2019-11-22 2019-12-18 2019-12-07 2019-12-14 2019-12-26 2020-12-25 en Développement Social au d'exécution facilities in the border areas sein de la Cellule Infrastructures ZR-CI-145876-CS-INDV / Recrutement d’un consultant Component 1: Improving En cours individuel au poste de Chef de IDA / 57240 core trade infrastructure and A posteriori Individuel Open 48,000.00 0.00 2019-11-22 2019-12-11 2019-12-28 2020-03-03 2020-01-07 2020-03-10 2020-01-15 2020-12-30 d'exécution Projet PFCGL au sein de la facilities in the border areas Cellule Infrastructures ZR-CI-167015-CS-CDS / Renouvellement du Contrat de prestation d'un consultant Component 4: Sélection de individuel au poste d'Assistant IDA / 57240 Implementation support, A posteriori consultants par Direct 19,800.00 0.00 En cours d'examen 2020-03-30 2020-04-20 2020-04-01 2020-04-04 2020-12-31 en Passation des Marchés au Communication and M&E entente directe sein de la Cellule Infrastructures dans le cadre du PFCGL ZR-CI-167016-CS-CDS / Renouvellement du Contrat de Component 4: Sélection de consultant individuel au poste En attente IDA / 57240 Implementation support, A posteriori consultants par Direct 19,800.00 0.00 2020-03-31 2020-04-01 2020-04-03 2020-12-27 de comptable au sein de la d'exécution Communication and M&E entente directe Cellule Infrastructures dans le cadre du projet PFCGL ZR-CI-167076-CS-CDS / Recrutement par entente directe de la Fondation PANZI pour assurer la mise en œuvre Component 1: Improving Sélection de des activités relatives aux En cours IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 111,000.00 0.00 2020-03-31 2020-04-03 2020-04-07 2020-04-24 2020-12-31 violences basées sur le genre d'exécution facilities in the border areas entente directe au niveau du site frontière de Ruzizi 1 à Bukavu dans le cadre du Projet de Facilitation du Commerce dans la Régi Page 5 ZR-CI-167080-CS-CDS / Recrutement par entente directe de l'ONG Heal AFRICA pour la mise en œuvre des Component 1: Improving Sélection de activités de prévention et En cours IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 222,000.00 0.00 2020-03-31 2020-04-03 2020-04-07 2020-04-24 2020-12-31 prise en charge relatives aux d'exécution facilities in the border areas entente directe violences sexuelles et basées sur le Genre (VSBG) au niveau des postes frontaliers de kasindi et Bunagana. ZR-CI-193649-CS-INDV / Component 4: En cours Spécialiste en Passation des IDA / 57240 Implementation support, A posteriori Individuel Limited 84,000.00 0.00 2020-09-30 2020-10-09 2020-10-14 2020-11-04 2020-11-13 2022-06-30 d'exécution Marchés Communication and M&E ZR-CI-207773-CS-CDS / Elaboration des études cadres de sauvegardes environnementales et sociales : Cadre de gestion Component 1: Improving Sélection de environnementale et IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 348,260.00 0.00 En cours d'examen 2020-12-04 2020-12-16 2020-12-12 2020-12-24 2021-02-25 sociale(CGES), Cadre de facilities in the border areas entente directe politique de réinstallation (CPR) et Cadre de plannification en faveur des peuples autochtones(CPPA) du PFCGL ZR-CI-207777-CS-CDS / Actualisation de l'EIES et PAR des Infrastructures prioritaires poste frontalier et Marché Component 1: Improving Sélection de transfrontalier de Kamvivira, En cours IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 280,000.00 0.00 2020-12-04 2020-12-18 2020-12-12 2020-12-24 2021-02-25 Port de Kalundu, Marché de d'exécution facilities in the border areas entente directe Goma et l’élaboration de l'EIES et du PAR du marché de Kasindi et de Bunagana et du Bureau PFCGL BUKAVU ZR-CI-207799-CS-INDV / Recrutement d'un Consultant Individuel chargé de l’appui à la mise en œuvre du Plan Component 1: Improving En cours d’Actions de Réinstallation IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 91,450.00 0.00 2020-12-04 2020-11-24 2020-12-09 2020-12-17 2020-12-27 2021-04-26 d'exécution (PAR) pour la construction du facilities in the border areas poste frontalier à la petite barrière de Goma dans la province du Nord-Kivu ZR-CI-207800-CS-CDS / Prestations de services d’un consultant ONG locales holistiques pour assurer la Component 1: Improving Sélection de En cours mise en œuvre des activités IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 115,000.00 0.00 2020-12-04 2021-02-02 2020-12-12 2020-12-24 2021-12-24 d'exécution relatives aux violences basées facilities in the border areas entente directe sur le genre au niveau du site frontière de Bukavu dans le Sud Kivu ZR-CI-210567-CS-INDV / Renouvellement du Contrat de Component 1: Improving monsieur Franklin En cours IDA / 57240 core trade infrastructure and A posteriori Individuel Direct 52,800.00 0.00 2020-12-18 2020-12-22 2020-12-20 2020-12-22 2020-12-28 2021-12-31 MUSHAGALUSA au poste de d'exécution facilities in the border areas Chef de Projet PFCGL au sein de la Cellule Infrastructures ZR-CI-210569-CS-INDV / Renouvellement du Contrat de Monsieur Dieudonné BOGAGA Component 1: Improving En cours TELALINGBI au poste de IDA / 57240 core trade infrastructure and A posteriori Individuel Direct 36,000.00 0.00 2020-12-18 2020-12-22 2020-12-20 2020-12-22 2020-12-28 2021-12-31 d'exécution Comptable du projet PFCGL facilities in the border areas au sein de la Cellule Infrastructures ZR-CI-210561-CS-INDV / Renouvellment du contrat de monsieur Isidore NDIBA Component 1: Improving En cours MASIKITA au poste d'Expert IDA / 57240 core trade infrastructure and A posteriori Individuel Direct 42,000.00 0.00 2020-12-18 2020-12-22 2020-12-20 2020-12-22 2020-12-28 2021-12-31 d'exécution Environnementaliste du projet facilities in the border areas PFCGL au sein de la Cellule Infrastructures ZR-CI-210565-CS-INDV / Renouvellement du Contrat de Madame Mecaine MUJINGA au Component 1: Improving En cours poste d'Expert en IDA / 57240 core trade infrastructure and A posteriori Individuel Direct 42,000.00 0.00 2020-12-18 2020-12-22 2020-12-20 2020-12-22 2020-12-28 2021-12-31 d'exécution Développement Social du facilities in the border areas projet PFCGL au sein de la Cellule Infrastructures ZR-CI-216737-CS-INDV / Recrutement d'un consultant Component 1: Improving En cours individuel chargé de IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 75,386.00 0.00 2021-02-04 2021-07-09 2021-02-09 2021-02-24 2021-03-10 2021-05-12 d'exécution l'Evaluation des risques VBG facilities in the border areas du Projet PFCIGL ZR-CI-217128-CS-CDS / Prestations d'un consultant firme chargé de la réalisation de l'EIE et d'un PAR des installlations frontalières Component 1: Improving Sélection de En attente (poste frontalier de IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 191,623.00 0.00 2021-02-05 2021-02-13 2021-02-25 2021-04-29 d'exécution Kamvivira,), Installations facilities in the border areas entente directe portuaires (port de Kalundu), et des infratsructures routières (Kamvivira-Uvira : 7km) ZR-CI-217145-CS-INDV / Réalisation des études techniques pour Component 1: Improving En cours l’aménagement et le bitumage IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 83,000.00 0.00 2021-02-05 2021-02-03 2021-02-10 2021-02-25 2021-03-11 2021-06-09 d'exécution de la RN30 Kavimvira (Uvira) – facilities in the border areas Frontière Burundi (7 km) dans la province du Sud-Kivu Page 6 ZR-CI-207784-CS-CDS / Recrutement d'un consultant Component 1: Improving Sélection de En attente individuel en appui à l'Unité IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 30,000.00 0.00 2020-12-04 2020-12-12 2020-12-24 2021-02-25 d'exécution Environnemental et Social facilities in the border areas entente directe pour la preparation du PFCGL ZR-CI-207787-CS-CDS / Recrutement d'un Consultant (firme) chargée de Component 1: Improving Sélection de En attente l'Actualisation de l' étude IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 100,000.00 0.00 2020-12-04 2020-12-12 2020-12-24 2021-02-25 d'exécution technique existante de facilities in the border areas entente directe réhabilitation du port de Kalundu ZR-CI-217153-CS-INDV / Etudes topographiques, Component 1: Improving géotechniques, géophysique, En cours IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 79,000.00 0.00 2021-02-05 2021-02-11 2021-02-10 2021-04-01 2021-02-25 2021-03-11 2021-06-09 hydrogéologique, études d'exécution facilities in the border areas d’implantation du poste frontalier de Kavimvira ZR-CI-234471-CS-CDS / Élaboration des Études d’Impact Environnemental et Social, EIES, des travaux d’aménagement des Component 1: Improving Sélection de En cours installations frontalières IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 160,000.00 0.00 2021-05-20 2021-05-26 2021-05-30 2021-08-03 2022-01-30 d'exécution (Poste frontalier de facilities in the border areas entente directe Kamvivira), installations portuaires (Port de Kalundu) et des infrastructures routières (Route Kamvivira- Uvira) ZR-CI-234474-CS-CDS / Élaboration du Plan d’Action de Réinstallation en vue de l’aménagement des Component 1: Improving Sélection de installations frontalières En attente IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 160,000.00 0.00 2021-05-21 2021-05-31 2021-08-04 2021-09-18 (Poste frontalier de d'exécution facilities in the border areas entente directe Kamvivira), installations portuaires (Port de Kalundu), et des infrastructures routières (Route Kamvivira- Uvira : 7km) ZR-CI-234476-CS-CDS / Élaboration du Cadre de Gestion Environnementale et Component 1: Improving Sélection de En cours Sociale (CGES) du Projet de IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 125,373.00 0.00 2021-05-24 2021-05-26 2021-06-03 2021-07-20 2021-08-07 2021-10-04 d'exécution Facilitation du Commerce et facilities in the border areas entente directe Intégration dans la Région des Grands Lacs, PFCIGL ZR-CI-234479-CS-CDS / Élaboration du Cadre de Politique de Réinstallation de Component 1: Improving Sélection de En cours Populations (CPR) du Projet de IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 125,373.00 0.00 2021-05-26 2021-07-09 2021-06-05 2021-08-09 2021-10-06 d'exécution Facilitation du Commerce et facilities in the border areas entente directe Intégration dans la Région des Grands Lacs, PFCIGL ZR-CI-234481-CS-CDS / Élaboration du Cadre de Planification en faveur des Component 1: Improving Sélection de Peuples Autochtones (CPPA) En cours IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 125,373.00 0.00 2021-05-27 2021-07-09 2021-06-06 2021-08-10 2021-10-07 du Projet de Facilitation du d'exécution facilities in the border areas entente directe Commerce et Intégration dans la Région des Grands Lacs, PFCIGL ZR-CI-239675-CS-INDV / Prestation de service d’un consultant individuel chargé de la réalisation des études Component 1: Improving En attente techniques pour IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 120,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 d'exécution l’aménagement et le bitumage facilities in the border areas de la route d’accès au port de Kalundu dans la province du Sud-Kivu ZR-CI-245022-CS-CDS / Élaboration du Cadre de Gestion Environnementale et Component 1: Improving Sélection de En cours Sociale (CGES) du Projet de IDA / 57240 core trade infrastructure and A posteriori consultants par Direct 282,129.00 282,129.00 2021-07-22 2021-08-13 2021-08-01 2021-08-30 2021-10-05 2021-12-02 d'exécution Facilitation du Commerce et facilities in the border areas entente directe d'Intégration dans la Région des Grands Lacs, PFCIGL ZR-CI-250126-CS-INDV / Prestations d’un consultant individuel chargé de la Component 1: Improving réalisation des études En attente IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 160,000.00 0.00 2021-08-31 2021-09-05 2021-09-26 2021-10-31 2022-04-29 techniques du projet de d'exécution facilities in the border areas réhabilitation du port de Kalundu dans la province du Sud-Kivu ZR-CI-250127-CS-INDV / Prestations d’un consultant individuel chargé de l’élaboration des études Component 1: Improving En attente économiques en vue définir le IDA / 57240 core trade infrastructure and A posteriori Individuel Limited 30,000.00 0.00 2021-09-16 2021-09-21 2021-10-12 2021-11-16 2022-05-15 d'exécution plan directeur de facilities in the border areas développement du port Kalundu dans la province du Sud-Kivu ZR-CI-250093-CS-CDS / Recrutement d'un Consultant Individuel chargé de l'appui à la mise en œuvre du Plan Component 1: Improving En attente d'Actions de Réinstallation IDA / 57240 core trade infrastructure and A posteriori Individuel Direct 91,000.00 0.00 2021-09-02 2021-09-12 2021-10-03 2021-11-07 2022-05-06 d'exécution (PAR) pour la construction du facilities in the border areas poste frontalier à la petite barrière de Goma dans la province du Nord-Kivu Page 7