PROCUREMENT PLAN (Textual Part) Project information: Brazil: Integrated Landscape Management in the Cerrado Biome Project – P164602 Project Implementation agency: DEUTSCHE GESELLSCHAFT FÜR INTERNATIONALE ZUSAMMENARBEIT GmbH (GIZ) Date of the Procurement Plan: August 21, 2018 Period covered by this Procurement Plan: October 2018- March 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : Integrated Landscape Management in the Cerrado Biome Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2018-09-03 2020-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164602 GPN Date: Project Name: Integrated Landscape Management in the Cerrado Biome Project Loan / Credit No: / , TF / A8532 Executing Agency(ies): German Society for International Cooperation WORKS Procureme Bid Evaluation Activity Reference No. / Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH nt Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Document Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion (US$) Documents Justification Type Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ- 76279-CW-APA / Contratação de empresa da Mainstreaning Landscape Alternative Single Stage - One 2019-05- área de construção civil / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 23 para execução de reforma Watersheds Arrangement do auditório e salas de aula da EMBRAPA Cerrados. EMBRAPA 2 BR-GIZ- 76268-CW-APA / Contratação de empresa da área de construção civil Mainstreaning Landscape Alternative Single Stage - One 2019-05- para reforma e adequação / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 23 do Viveiro de P&D da Watersheds Arrangement Embrapa Cerrados para operar também como Unidade de Aprendizagem EMBRAPA 2 BR-GIZ- 76209-CW-APA / Contratação de empresa da área de construção civil Mainstreaning Landscape Alternative Single Stage - One 2019-05- para reforma e adequação / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 23 e manutenção do Studio Watersheds Arrangement para produção/gravação de vídeos para TT, inclusive EAD, da Embrapa Cerrados EMBRAPA BR-GIZ-161546- CW-RFQ / Contratação de Institutional Development Implementa Solicitação de Single Stage - One 2022-02- empresa para reforma de TF / A8532 and Capacity Building for Posterior Open - National 0.00 ção 2021-07-05 2021-08-30 Cotações Envelope 26 auditório para capacitação Landscape Management Pendente na Embrapa Cerrados. GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ- 76233-GO-APA / Aquisição de equipamentos de Institutional Development Alternative informatica computadores Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 etc.. Para a equipe de Envelope Landscape Management Arrangement processamento e sistematização da informação tecnológica da paisagem da Embrapa Cerrados. EMBRAPA 2 BR-GIZ- 76255-GO-APA / Aquisição Mainstreaning Landscape Alternative de equipamentos de Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 informatica computadores, Envelope Watersheds Arrangement etc.. para a sala de treinamento (EAD) da Embrapa Cerrados. EMBRAPA 1 BR-GIZ- 76272-GO-APA / Aquisição de maquinas e equipamentos tecnicos para Institutional Development Alternative Single Stage - One analises de campo para / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope avaliar o processamento e Landscape Management Arrangement sistematização da informação tecnológica da paisagem da Embrapa Cerrados. EMBRAPA 2 BR-GIZ- 76207-GO-APA / Aquisição Mainstreaning Landscape Alternative Single Stage - One de mobiliário para auditorio / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope e sala de treinamento Watersheds Arrangement (EAD) da Embrapa Cerrados. EMBRAPA 2 BR-GIZ- 76257-GO-APA / Aquisição Mainstreaning Landscape Alternative de material didatico Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-03-10 2019-03-15 2019-04-05 2019-04-12 2019-05-03 2019-10-30 impresso para distribuição Envelope Watersheds Arrangement nos cursos de conservação para os diferentes atores/públicos. EMBRAPA 1 BR-GIZ- 76283-GO-APA / Aquisição de equipamentos Institutional Development Alternative Single Stage - One eletroeletronicos para o / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope auditorio e as salas de Landscape Management Arrangement treinamento da Embrapa Cerrados. Page 1 EMBRAPA 2 BR-GIZ- 76256-GO-APA / Aquisição de material (toner, tinta, Mainstreaning Landscape Alternative papel etc..) para impressao Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 2019-05-23 de material didatico Envelope Watersheds Arrangement (audiovisual) para os cursos de conservação para os diferentes atores/públicos. EMBRAPA 1 BR-GIZ- 76250-GO-APA / Aquisição de equipamentos de audio Institutional Development Alternative Single Stage - One visual etc.. para auditorio / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-02-10 2019-02-15 2019-03-08 2019-03-15 2019-04-05 2019-10-02 Envelope e sala de treinamento Landscape Management Arrangement (EAD) da Embrapa Cerrados. EMBRAPA 1 BR-GIZ- 76258-GO-APA / Aquisição de material de consumo para estudos prospectivos de cenários de conservação Institutional Development Alternative Single Stage - One e produção com / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope tecnologias disponíveis sobre Landscape Management Arrangement o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ- 76291-GO-APA / Aquisição de material de consumo para a realização do componente de conservação Mainstreaning Landscape Alternative Single Stage - One da paisagem nos cursos, / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope treinamentos, dias de Watersheds Arrangement campo etc.sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 1 BR-GIZ- 76269-GO-APA / Aquisição de combustível para a realização dos estudos prospectivos de cenários e Institutional Development Alternative paisagens de conservação e Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 produção com tecnologias Envelope Landscape Management Arrangement disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ- 76208-GO-APA / Aquisição de combustível para a realização dos cursos e estudos de conservação da Mainstreaning Landscape Alternative paisagem nos cursos, Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 treinamentos, dias de Envelope Watersheds Arrangement campo etc.sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa SFB 2 BR-GIZ-76245-GO- Mainstreaning Landscape Alternative APA / Aquisicao de Kits Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-03-15 2019-03-20 2019-04-10 2019-04-17 2019-05-08 2019-11-04 promocionais de Envelope Watersheds Arrangement comunicacao e informativos INPE 1 BR-GIZ-76271-GO- APA / Aquisição de Institutional Development Alternative Single Stage - One material de Campo / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope (mapeamento orbital e Landscape Management Arrangement análise da paisagem) INPE 1 BR-GIZ-76287-GO- APA / Aquisição de Institutional Development Alternative Single Stage - One Material de Escritório / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope (mapeamento orbital e Landscape Management Arrangement análise da paisagem) INPE 1 BR-GIZ-76192-GO- APA / Aquisição de Institutional Development Alternative Single Stage - One equipamentos de / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope Informática (mapeamento Landscape Management Arrangement orbital e análise da paisagem) INPE 1 BR-GIZ-76218-GO- Institutional Development Alternative APA / Aquisição de Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 equipamento Fotográfico Envelope Landscape Management Arrangement (mapeamento orbital) GIZ 3 BR-GIZ-76225-GO- Project Management, Alternative APA / Aquisição de Single Stage - One / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 equipamentos de Envelope Communication Arrangement informática para equipe base da GIZ EMBRAPA BR-GIZ-109835- GO-RFQ / Aquisição de equipamentos de Institutional Development informatica computadores Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2019-05-11 2019-07-06 2020-01-02 etc.. Para a equipe de Cotações Envelope ão Pendente Landscape Management processamento e sistematização da informação tecnológica da paisagem da Embrapa Cerrados Page 2 SFB BR-GIZ-109849-GO- Mainstreaning Landscape RFQ / Aquisicao de Kits Solicitação de Single Stage - One Implementaç TF / A8532 Practices into Selected Posterior Open - National 0.00 2019-09-07 2019-11-02 2020-04-30 promocionais de Cotações Envelope ão Pendente Watersheds comunicacao e informativos INPE BR-GIZ-109966-GO- RFQ / Aquisição de Institutional Development Solicitação de Single Stage - One equipamentos de TF / A8532 and Capacity Building for Posterior Open - National 9,464.01 Assinado 2019-06-08 2019-08-03 2019-07-08 2020-01-30 Cotações Envelope Informática (mapeamento Landscape Management orbital e análise da paisagem) INPE BR-GIZ-109967-GO- Institutional Development RFQ / Aquisição de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 3,003.44 Assinado 2019-08-10 2019-10-05 2019-08-27 2020-04-02 equipamento Fotográfico Cotações Envelope Landscape Management (mapeamento orbital) GIZ BR-GIZ-109985-GO- Project Management, Em fase de RFQ / Aquisição de Solicitação de Single Stage - One TF / A8532 Monitoring, Evaluation and Posterior Open - National 0.00 Implementaç 2019-04-15 2019-06-10 2019-12-07 equipamentos de Cotações Envelope Communication ão informática para equipe base da GIZ EMBRAPA BR-GIZ-123501- GO-RFQ / Adquirir equipamentos para edicao Institutional Development de videos para a Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 8,053.30 Assinado 2019-08-06 2019-10-01 2019-11-11 2020-03-29 Embrapa/Cerrados que Cotações Envelope Landscape Management atenderao demandas do treinamento dos tecnicos do SENAR GIZ-BR-GIZ-143344-GO- Project Management, RFQ / Aquisicao de uma Solicitação de Single Stage - One TF / A8532 Monitoring, Evaluation and Posterior Open - National 369.85 Assinado 2019-11-16 2020-01-11 2019-11-26 2020-07-09 licenca de software para Cotações Envelope Communication gerenciamento de projeto INPE BR-GIZ-161547-GO- Institutional Development RFQ / Equipamentos de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 592.74 Assinado 2020-04-06 2020-06-01 2020-04-13 2020-11-28 escritório (ar-condicionado, Cotações Envelope Landscape Management cadeiras, etc.) INPE BR-GIZ-162147-GO- Institutional Development Em fase de Solicitação de Single Stage - One RFQ / Equipamentos de TF / A8532 and Capacity Building for Posterior Open - National 1,915.01 Implementaç 2020-07-10 2020-09-04 2021-03-03 Cotações Envelope informática Landscape Management ão EMBRAPA BR-GIZ-161606- GO-RFQ / Aquisição de bens para o auditorio para Mainstreaning Landscape Solicitação de Single Stage - One Implementaç capacitação na Embrapa TF / A8532 Practices into Selected Posterior Open - National 0.00 2021-07-05 2021-08-30 2022-02-26 Cotações Envelope ão Pendente Cerrados. (Som + Imagem Watersheds + piso + ar condicionado + cadeiras) EMBRAPA BR-GIZ-162133- GO-RFQ / Compra de materiais para manutenção Institutional Development da Unidades Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-01-04 2021-03-01 2021-08-28 Demonstrativas na Cotações Envelope ão Pendente Landscape Management Embrapa Cerrados. (ILP - Experimento longa duração- Chapadao + ILPF e pastagem solteira) EMBRAPA BR-GIZ-162144- GO-RFQ / Compra de materiais para manutenção Institutional Development Solicitação de Single Stage - One Implementaç da URT na Embrapa TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-01-04 2021-03-01 2021-08-28 Cotações Envelope ão Pendente Cerrados (CTZL - Centro Landscape Management de Tecnologias de Raças Zebuínas Leiteiras). EMBRAPA BR-GIZ-162146- GO-RFQ / Compra de Institutional Development materiais para manutenção Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-01-04 2021-03-01 2021-08-28 da URT na Fazenda Entre Cotações Envelope ão Pendente Landscape Management Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-162145- GO-RFQ / Compra de Institutional Development materiais para manutenção Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-01-04 2021-03-01 2021-08-28 da URT na Fazenda Entre Cotações Envelope ão Pendente Landscape Management Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-109842- GO-RFQ / Aquisição de combustível para a realização dos estudos prospectivos de cenários e Institutional Development paisagens de conservação e Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-07-13 2019-09-07 2020-03-05 produção com tecnologias Cotações Envelope Landscape Management disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa. EMBRAPA BR-GIZ-109840- GO-RFQ / Aquisição de Mainstreaning Landscape material didático impresso Solicitação de Single Stage - One Implementaç TF / A8532 Practices into Selected Posterior Open - National 0.00 2021-01-04 2021-03-01 2021-08-28 para distribuição nos cursos Cotações Envelope ão Pendente Watersheds de conservação para os diferentes atores/públicos. INPE BR-GIZ-109958-GO- APA / Aquisição de Institutional Development Solicitação de Single Stage - One Material de Escritório TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-09-07 2019-11-02 2020-04-30 Cotações Envelope (mapeamento orbital e Landscape Management análise da paisagem) Page 3 INPE BR-GIZ-109957-GO- RFQ / Aquisição de Institutional Development Solicitação de Single Stage - One material de Campo TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-09-07 2019-11-02 2020-04-30 Cotações Envelope (mapeamento orbital e Landscape Management análise da paisagem) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ- 76293-NC-APA / Fornecimento de coffee break e/ou almoço para todas as capacitações do Mainstreaning Landscape Alternative Single Stage - One comp de conserv da / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope paisagem em cursos, dias Watersheds Arrangement de campo etc dos técnicos rurais e/ou produtores durante todos os cursos, seminarios regionais, excursoes tecnicas EMBRAPA 1 BR-GIZ- 76234-NC-APA / Loc. de veiculos para a realização de estudos prospectivos de cenários de conservação e Institutional Development Alternative Single Stage - One produção com tecnologias / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope disponíveis sobre o CAR, Landscape Management Arrangement PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ- 76262-NC-APA / Loc de veic para a realização do comp de estudos e cursos de conserv da paisagem Mainstreaning Landscape Alternative Single Stage - One nos cursos, treinam, dias / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope de campo etc com tecnol Watersheds Arrangement disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ- 76236-NC-APA / Contratação de empresa Mainstreaning Landscape Alternative Single Stage - One gráfica para a impressao / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope de material didatico para Watersheds Arrangement os cursos de conservação para os diferentes atores/públicos. SFB 1 BR-GIZ-76238-NC- APA / Contratação de empresa para realização de Institutional Development Alternative eventos, cursos, oficinas e Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 reuniões de promoção do Envelope Landscape Management Arrangement empoderamento local e integração multi- institucional por Bacia selecionada SFB 2 BR-GIZ-76275-NC- APA / Contratação de pessoa jurídica para Mainstreaning Landscape Alternative realizar 10 oficinas Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 participativas de elaboração Envelope Watersheds Arrangement e pactuação do plano, para o lançamento e a difusão do plano de ação de cada uma das bacias SFB 2 BR-GIZ-76286-NC- Mainstreaning Landscape Alternative Single Stage - One APA / Aluguel de veiculos / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-15 2019-01-20 2019-02-10 2019-02-17 2019-03-10 2019-09-06 Envelope do SFB Watersheds Arrangement INPE 1 BR-GIZ-76273-NC- APA / Serviços de Institutional Development Alternative organização de eventos, Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 publicação e divulgação de Envelope Landscape Management Arrangement resultados (mapeamento orbital) INPE 1 BR-GIZ-76292-NC- Institutional Development Alternative APA / Locação de Veículo Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 (mapeamento orbital e Envelope Landscape Management Arrangement análise da paisagem) GIZ 3 BR-GIZ-76290-NC- APA / Contratação de Project Management, Alternative Single Stage - One serviços para produção dos / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope materiais e peças de Communication Arrangement comunicação do Projeto GIZ 3 BR-GIZ-76276-NC- Project Management, Alternative Single Stage - One APA / Auditorias Externas / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope Independentes do projeto Communication Arrangement SFB BR-GIZ-109851-NC- Mainstreaning Landscape Solicitação de Single Stage - One Implementaç RFQ / Aluguel de veículos TF / A8532 Practices into Selected Posterior Open - National 0.00 2019-08-10 2019-10-05 2020-04-02 Cotações Envelope ão Pendente do SFB Watersheds Page 4 INPE BR-GIZ-109968-NC- Institutional Development RFQ / Aluguel de sala Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 17,449.76 Assinado 2019-05-11 2019-07-06 2019-06-20 2020-01-02 comercial para equipe de Cotações Envelope Landscape Management técnicos em Campinas/SP GIZ BR-GIZ-109987-NC- RFQ / Contratação de Project Management, Solicitação de Single Stage - One Implementaç serviços para produção dos TF / A8532 Monitoring, Evaluation and Posterior Open - National 0.00 2019-12-07 2020-02-01 2020-07-30 Cotações Envelope ão Pendente materiais e peças de Communication comunicação do Projeto GIZ BR-GIZ-109989-NC- Project Management, Solicitação de Single Stage - One RFQ / Auditorias Externas TF / A8532 Monitoring, Evaluation and Posterior Open - National 4,214.35 Assinado 2019-11-23 2020-01-18 2020-01-15 2020-07-16 Cotações Envelope Independentes do projeto Communication SFB BR-GIZ-161619-NC- RFQ / Produção de Institutional Development material informativo e Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2020-06-06 2020-08-01 2021-01-28 vídeo para divulgação das Cotações Envelope ão Pendente Landscape Management atuação do SFB incluindo o projeto FIP Paisagem. SFB BR-GIZ-161627-NC- Institutional Development RFQ / Aquisicao de Kits Solicitação de Single Stage - One Implementaç TF / A8532 and Capacity Building for Posterior Open - National 0.00 2020-06-07 2020-08-02 2021-01-29 promocionais de Cotações Envelope ão Pendente Landscape Management comunicacao e informativos EMBRAPA BR-GIZ-161975- NC-RFQ / Material de Institutional Development Solicitação de Single Stage - One Implementaç apoio para os dois cursos TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-07-05 2021-08-30 2022-02-26 Cotações Envelope ão Pendente presenciais de capacitação Landscape Management BPA e RAD. EMBRAPA BR-GIZ-109841- NC-RFQ / Contratação de serviço de locação de veiculos para a realização de estudos prospectivos de Institutional Development cenários de conservação e Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-08-10 2019-10-05 2020-04-02 produção com tecnologias Cotações Envelope Landscape Management disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa INPE BR-GIZ-162154-NC- RFQ / Contrato Institutional Development Solicitação de Single Stage - One ferramentas TI para TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2020-04-10 2020-06-05 2020-12-02 Cotações Envelope armazenamento de dados e Landscape Management comunicação INPE BR-GIZ-109960-NC- RFQ / Serviços de Institutional Development organização de eventos, Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-11-09 2020-01-04 2020-07-02 publicação e divulgação de Cotações Envelope Landscape Management resultados (mapeamento orbital) INPE BR-GIZ-109964-NC- Institutional Development RFQ / Locação de Veículo Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-11-09 2020-01-04 2020-07-02 (mapeamento orbital e Cotações Envelope Landscape Management análise da paisagem) EMBRAPA BR-GIZ-164514- CW-RFQ / Contratação de Institutional Development Solicitação de Single Stage - One Implementaç empresa para instalações TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-07-05 2021-08-30 2022-02-26 Cotações Envelope ão Pendente Som + Imagem + piso + ar Landscape Management condicionado + cadeiras CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ- 76228-CS-CAPA / CI na area de engenharia para Institutional Development Alternative elaboracao de projeto basico / and Capacity Building for Posterior Procurement Direct 0.00 Cancelado 2018-10-30 2018-12-09 2018-12-30 2019-06-28 e executivo para as Landscape Management Arrangement reformas do auditorio, salas de aula, salas de video e viveiro da EMBRAPA Cerrados. EMBRAPA 1 BR-GIZ- 76229-CS-CAPA / CI para o processamento e sistem da informação tecnol para Institutional Development Alternative a caracterização e análise / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-04-27 2020-04-26 da estrutura e da dinâmica Landscape Management Arrangement das unidades de paisagem para replicabilidade das intervenções de BPA e RAD em diferentes escalas EMBRAPA 2 BR-GIZ- 76270-CS-CAPA / CI para coord, elaboração de cont e apresentação de cursos presenciais e a distância no Mainstreaning Landscape Alternative tema conserv dos rec nat / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 em temas como tecnol de Watersheds Arrangement manejo e uso controlado do fogo, estrat de recomp da vegetação nativas e boas praticas agropecuárias Page 5 EMBRAPA 2 BR-GIZ- 76204-CS-CAPA / Contratação de Consultoria Individual para Mainstreaning Landscape Alternative apresentação de cursos / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 presenciais e a distância no Watersheds Arrangement tema conservação dos recursos naturais (instrutores/equipe de apoio). EMBRAPA 2 BR-GIZ- 76254-CS-CAPA / CI para coordenação da coleta de dados na implantação de tecnologias de manejo e Mainstreaning Landscape Alternative uso controlado do fogo; / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 estratégias de recomposição Watersheds Arrangement da vegetação nativa e boas praticas agropecuárias, em imoveis rurais assistidos pelo Projeto EMBRAPA 2 BR-GIZ- 76205-CS-CAPA / CI para execução da coleta de Mainstreaning Landscape Alternative dados na implant de / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 tecnologias de manejo e Watersheds Arrangement uso controlado do fogo; estratégias de recomp da veg. nativa e boas praticas agropecuárias EMBRAPA 2 BR-GIZ- 76277-CS-CAPA / 3 CIs para apoio na coleta de dados na implantação de Mainstreaning Landscape Alternative tecnologias de manejo e / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 uso controlado do fogo, Watersheds Arrangement estratégias de recomposição da vegetação nativa e boas praticas agropecuárias. EMBRAPA 2 BR-GIZ- 76232-CS-CAPA / CI para Mainstreaning Landscape Alternative levantar subsidios para / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 incentivar à cadeia Watersheds Arrangement produtiva da restauração SFB 1 BR-GIZ-76252-CS- CAPA / Serviços de Consultoria jurídica para Institutional Development Alternative Classificações para o / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 SICAR no Cerrado, Landscape Management Arrangement SENTINEL ou Sensor Compatível 1:10.000 - 2016, 2017, 2018, 2019 SFB 1 BR-GIZ-76264-CS- CAPA / CPJ para realizar diag, mapeam e elaborar portif de divulgação da sistematiz de exp de Institutional Development Alternative imóveis rurais públ e priv / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 qto às ativ e empreend de Landscape Management Arrangement recuperação/recomposição de áreas degradadas, silvicultura e soluções tecnol BPA SFB 1 BR-GIZ-76213-CS- CAPA / CPJ para promoção de uma melhor comunicacao e melhoria institucional das Institutional Development Alternative organizações / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 (Compatibilização de Landscape Management Arrangement informações sobre o Cerrado entre o SFB (Inventário Florestal), INPE (Prodes), EMBRAPA (TerraClass), SENAR, MAPA e MMA) SFB 1 BR-GIZ-76266-CS- CAPA / Contratacao de pessoa juridica para Institutional Development Alternative Elaboracao e / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 disponibilizacao na Landscape Management Arrangement plataforma Saberes da Floresta de 10 cursos com tematica relativa as acoes do projeto SFB 1 BR-GIZ-76237-CS- CAPA / Consultoria pessoa jurídica (OS) para Institutional Development Alternative mobilização e apoio à / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 instalação e fortalecimento Landscape Management Arrangement de Comitês de Bacia Hidrográfica SFB 2 BR-GIZ-76243-CS- CAPA / Contratação de Pessoa Jurídica (OS) para Mainstreaning Landscape Alternative instalar viveiros / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 permanentes e temporarios, Watersheds Arrangement casa de sementes, produção e comercialização de sementes e mudas. Page 6 SFB 2 BR-GIZ-76249-CS- CAPA / Contratação de pessoa jurídica para desenvolver metodologia de monitoramento de áreas Mainstreaning Landscape Alternative restauradas (fortalecer a / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 oferta de serviços de Watersheds Arrangement monitoramento) e aplicação por dois ciclos de monitoramento (T.0, T.1 e T.2). SFB 1 BR-GIZ-76274-CS- CAPA / CI para a elaboração de método, treinamento e apoio à execução da Análise técnica Institutional Development Alternative sobre o CAR e PRAs na / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 área de abrangência do Landscape Management Arrangement projeto no SICAR e elaboração de materiais específicos da área de abrangência do Projeto . SFB 1 BR-GIZ-76280-CS- CAPA / CI pra a sistematização de informações sobre a área selecionada, com a definição Institutional Development Alternative da área de abrangência do / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 projeto, considerando Landscape Management Arrangement passivos florestais em APP, RL, áreas passíveis de restauração e análise multicritérios. SFB 2 BR-GIZ-76288-CS- CAPA / Consultoria Mainstreaning Landscape Alternative Individual para a definição / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 da estrutura e escopo do Watersheds Arrangement plano de ação nas 10 bacias selecionadas. SFB 2 BR-GIZ-76244-CS- CAPA / CI para apoiar os treinamento para funcionários públicos em legislação ambiental, Mainstreaning Landscape Alternative especialmente Código / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Florestal e as relativas ao Watersheds Arrangement CAR, PRA e licenciamento ambiental, bem como sobre as etapas e procedimentos para realização de CAR e PRA INPE 1 BR-GIZ-76253-CS- CAPA / Contratação de 04 Institutional Development Alternative (quatro) consultorias / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 individuais - Serviços de Landscape Management Arrangement Geoprocessamento (mapeamento orbital) INPE 1 BR-GIZ-76241-CS- CAPA / Contratação de Institutional Development Alternative Consultor individual - / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Assistente Landscape Management Arrangement Geoprocessamento júnior (análise da paisagem) INPE 1 BR-GIZ-76289-CS- CAPA / Contratação de Institutional Development Alternative Consultor individual - / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Serviços de Landscape Management Arrangement Geoprocessamento (análise da paisagem) INPE 3 BR-GIZ-76278-CS- CAPA / Contratação de Consultoria pessoa jurídica para a difusão e Project Management, Alternative comunicação dos resultados / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 do projeto em eventos e Communication Arrangement reuniões nacionais ou internacionais técnicos, acadêmicos e políticos GIZ 3 BR-GIZ-76242-CS- CAPA / Consultoria Project Management, Alternative Individual para elaborar / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Relatório Final de Revisão Communication Arrangement de Meio Termo GIZ 3 BR-GIZ-76246-CS- CAPA / Consultorias para Project Management, Alternative Suporte Administrativo e / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 de Aquisições ao Projeto Communication Arrangement (equipe base GIZ) GIZ 3 BR-GIZ-76247-CS- Project Management, Alternative CAPA / Consultorias para / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-13 2020-07-12 Suporte Técnico ao Projeto Communication Arrangement (equipe base GIZ) GIZ 3 BR-GIZ-76203-CS- CAPA / Elaboração do Project Management, Alternative Plano de comunicação do / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 projeto - comuncação geral Communication Arrangement do Projeto Page 7 GIZ BR-GIZ-109973-CS- CQS / Contratação de Consultoria pessoa jurídica para a difusão e Project Management, Seleção Baseada Implementação comunicação dos resultados TF / A8532 Monitoring, Evaluation and Posterior nas Qualificações Open - National 0.00 2019-12-02 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2020-10-07 Pendente do projeto em eventos e Communication dos Consultores reuniões nacionais ou internacionais técnicos, acadêmicos e políticos INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INPE 1 BR-GIZ-76216-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 107,512.82 Assinado 2019-04-22 2019-04-12 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE 1 BR-GIZ-76239-CS- CAPA / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 62,476.22 Assinado 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-05-14 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ 3 BR-GIZ-76281-CS- CAPA / Consultoria para Gerenciamento e Monitoramento Geral do Project Management, Projeto (equipe base GIZ) - TF / A8532 Monitoring, Evaluation and Posterior Individual Open 339,274.24 Assinado 2019-04-04 2019-09-01 2019-05-23 2018-12-05 2019-06-13 2019-01-02 2019-07-18 2019-01-10 2020-01-14 Pelas regras da GIZ, trata- Communication se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105361-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-22 2019-04-22 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105364-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 108,502.36 Assinado 2019-04-22 2019-04-18 2019-06-10 2019-06-05 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105365-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-22 2019-04-12 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105366-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-30 2019-03-06 2019-06-18 2019-06-09 2019-07-09 2019-06-09 2019-08-13 2019-06-24 2020-02-09 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105367-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. Page 8 INPE BR-GIZ-105369-CS- CAPA / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 62,476.22 Assinado 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. EMBRAPA BR-GIZ-109805- CS-INDV / Contratação de Consultoria Individual para sistematização de informações sobre Mainstreaning Landscape recuperação de vegetação TF / A8532 Practices into Selected Posterior Individual Open 15,617.86 Concluído 2019-06-03 2019-04-22 2019-07-22 2019-07-29 2019-08-12 2019-05-02 2019-09-16 2019-05-06 2020-03-14 2019-11-26 nativa - Pelas regras da Watersheds GIZ, trata-se de contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto EMBRAPA BR-GIZ-109831- CS-INDV / Contratação de Consultoria Individual para sistematização de informações sobre ILPF, Mainstreaning Landscape BPA e recuperação de TF / A8532 Practices into Selected Posterior Individual Open 15,710.01 Concluído 2019-05-20 2019-05-08 2019-07-08 2019-06-28 2019-07-29 2019-09-03 2019-09-02 2019-07-05 2020-02-29 2020-09-15 áreas produtivas Watersheds degradadas - Pelas regras da GIZ, trata-se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto SFB BR-GIZ-109844-CS- INDV / Contratação de Consultira Individual para elaborar diagnóstico e caracterização por Mainstreaning Landscape sensoriamento remoto das TF / A8532 Practices into Selected Posterior Individual Open 6,161.37 Concluído 2019-08-05 2019-04-25 2019-09-23 2019-05-02 2019-10-14 2019-05-06 2019-11-18 2019-05-06 2020-05-16 2020-01-01 53 bacias hidrográficas e o Watersheds DF do Projeto FIP/Paisagem.Pelas regras da GIZ, trata-se de contrato de consultoria conforme acordado com o BM SFB BR-GIZ-109845-CS- INDV / Contratação de Consultira Individual para elaborar diagnóstico socio economico ambiental das 53 Mainstreaning Landscape bacias hidrográficas e o DF TF / A8532 Practices into Selected Posterior Individual Open 6,198.71 Concluído 2019-08-05 2019-04-11 2019-09-23 2019-07-05 2019-10-14 2019-05-02 2019-11-18 2019-05-02 2020-05-16 2020-01-01 do Projeto FIP/Paisagem. - Watersheds Pelas regras da GIZ, trata- se de contrato de consultoria conforme acordado com o Banco Mundial INPE BR-GIZ-109862-CS- INDV / Contratação de Consultor individual - Assistente Institutional Development Geoprocessamento júnior Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2019-08-05 2020-09-28 2019-09-23 2019-10-14 2019-11-18 2020-05-16 (análise da paisagem) - Implementação Landscape Management Pelas regras da GIZ, trata- se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ BR-GIZ-109975-CS- INDV / Consultoria Project Management, Implementação Individual para elaborar TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 2022-01-03 2022-02-21 2022-03-14 2022-04-18 2022-10-15 Pendente Relatório Final de Revisão Communication de Meio Termo GIZ BR-GIZ-109979-CS- INDV / Consultorias para Suporte Administrativo e de Aquisições ao Projeto (equipe base GIZ) - Project Management, Consultoria Individual. TF / A8532 Monitoring, Evaluation and Posterior Individual Open 149,828.12 Assinado 2019-04-10 2018-09-14 2019-05-29 2019-02-18 2019-06-19 2019-01-18 2019-07-24 2019-01-21 2020-01-20 Pelas regras da GIZ, trata- Communication se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ BR-GIZ-109980-CS- INDV / Consultorias para Suporte Técnico ao Projeto (equipe base GIZ) - Project Management, Consultoria Individual. Em fase de TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 2019-11-04 2020-07-23 2019-12-23 2020-01-13 2020-02-17 2020-08-15 Pelas regras da GIZ, trata- Implementação Communication se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ BR-GIZ-109986-CS- INDV / Elaboração do Project Management, Implementação Plano de comunicação do TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Pendente projeto - comuncicação Communication geral do Projeto Page 9 SFB BR-GIZ-109990-CS- INDV / Cont de Cons de Pessoa Física para analisar as inform cartográficas de inscrições de imóveis rurais Institutional Development com até 4 módulos fiscais TF / A8532 and Capacity Building for Posterior Individual Open 15,295.68 Assinado 2019-04-22 2019-05-19 2019-06-10 2019-05-15 2019-07-01 2019-06-06 2019-08-05 2019-05-23 2020-02-01 no Cadastro Ambiental Landscape Management Rural do estado do Maranhão (sub lote 1, 2 e 3) para subsídio da qualificação da cobertura do uso do solo SFB BR-GIZ-109991-CS- INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 4,592.07 Concluído 2019-04-15 2019-05-03 2019-06-03 2019-05-15 2019-06-24 2019-05-15 2019-07-29 2019-05-22 2020-01-25 2020-06-08 com até 4 módulos fiscais Landscape Management no Cadastro Ambiental Rural do estado do Minas Gerais (sub-lote 1,2 e 3)o para subsídio da qualificação da cob do sol SFB BR-GIZ-109992-CS- INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 3,365.43 Concluído 2019-04-22 2019-05-02 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-20 2020-02-01 2020-06-08 com até 4 módulos fiscais Landscape Management no Cadastro Ambiental Rural do estado do Minas Gerais (sub-lote 4,5 e 6)o para subsídio da qualificação da cob do sol SFB BR-GIZ-109993-CS- INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de imóveis Institutional Development rurais com até 4 módulos TF / A8532 and Capacity Building for Posterior Individual Open 14,413.97 Assinado 2019-04-22 2019-04-25 2019-06-10 2019-05-15 2019-07-01 2019-05-16 2019-08-05 2019-05-16 2020-02-01 fiscais no Cadastro Landscape Management Ambiental Rural do estado do Maranhão (sub lote 1,2 e 3) para subsídio da qualificação da cobertura do uso do solo SFB BR-GIZ-109996-CS- INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de imóveis Institutional Development rurais com até 4 módulos TF / A8532 and Capacity Building for Posterior Individual Open 4,751.27 Concluído 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-15 2019-08-05 2019-05-20 2020-02-01 2020-06-08 fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 1 e 2) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-109997-CS- INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de imóveis Institutional Development rurais com até 4 módulos TF / A8532 and Capacity Building for Posterior Individual Open 4,003.88 Concluído 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-20 2019-08-05 2019-05-20 2020-02-01 2020-06-08 fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 3 e 4) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-109998-CS- INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de imóveis Institutional Development rurais com até 4 módulos TF / A8532 and Capacity Building for Posterior Individual Open 4,009.84 Concluído 2019-04-22 2019-04-22 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-30 2020-02-01 2020-06-02 fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 5 e 6) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-110007-CS- INDV / Consultoria Individual para Produção de material informativo para divulgação das Institutional Development Implementação atuação do SFB incluindo o TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2019-04-29 2019-06-17 2019-07-08 2019-08-12 2020-02-08 Pendente projeto FIP Paisagem - Landscape Management Pelas regras da GIZ, trata- se de contrato de consultoria conforme acordado com o Banco Mundial na documentação SFB BR-GIZ-110005-CS- INDV / Consultoria Individual para Produção de videos informativos para divulgação do SFB, Institutional Development Implementação incluindo o projeto FIP TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2019-04-29 2019-06-17 2019-07-08 2019-08-12 2020-02-08 Pendente Paisagem - Pelas regras da Landscape Management GIZ, trata-se de contrato de consultoria conforme acordado com o Banco Mundial na documentação Page 10 SFB BR-GIZ-112004-CS- INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 2,024.44 Concluído 2019-05-29 2019-05-02 2019-07-17 2019-05-09 2019-08-07 2019-05-14 2019-09-11 2019-05-19 2020-03-09 2020-06-08 com até 4 módulos fiscais Landscape Management no Cadastro Ambiental Rural do estado do Minas Gerais (sub-lote 6)o para subsídio da qualificação da cob do sol EMBRAPA CERRADO BR- GIZ-150287-CS-INDV / Contratação de assessor técnico para monitoramento nas áreas de referência do Institutional Development Projeto Paisagens Rurais – TF / A8532 and Capacity Building for Posterior Individual Open 50,523.58 Assinado 2019-12-16 2020-02-18 2020-02-03 2020-02-19 2020-02-24 2020-02-20 2020-03-30 2020-03-03 2020-09-26 Gestão Integrada da Landscape Management Paisagem, na Embrapa Cerrado e em outras Unidades de Referência Tecnológica definidas. SFB BR-GIZ-152976-CS- INDV / Contratação de Assessor(a) Técnico(a) para Institutional Development apoio à implementação da TF / A8532 and Capacity Building for Posterior Individual Open 54,122.00 Assinado 2020-01-12 2020-01-08 2020-03-01 2020-02-21 2020-03-22 2020-02-21 2020-04-26 2020-03-02 2020-10-23 Regularização Ambiental Landscape Management nas bacias prioritárias do projeto Paisagens Rurais SFB BR-GIZ-160378-CS- INDV / Elaborar o Plano Institutional Development de Continuidade de Negócio TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 do CAR, suas integrações e Landscape Management o SICAR. SFB BR-GIZ-160383-CS- INDV / Contratar consultor para revisar a topologia, configuração e desenho da Institutional Development rede de dados atual do TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 SICAR, com o objetivo de Landscape Management ampliar, agilizar e maximizar o tráfego de dados internamente dentro da rede dados dos servidores. SFB BR-GIZ-160389-CS- INDV / Contratar consultor Institutional Development para redesenhar a TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 arquitetura do ambiente de Landscape Management hardware de servidores para o CAR SFB BR-GIZ-161615-CS- INDV / Elaboracao e disponibilizacao na Institutional Development Implementação plataforma Saberes da TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 Pendente Floresta cursos com Landscape Management tematica relativa as ações do projeto. SFB BR-GIZ-161618-CS- Institutional Development INDV / Apoio o Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 fortalecimento de redes de Pendente Landscape Management sementes SFB BR-GIZ-161936-CS- INDV / Monitoramento e Institutional Development Implementação avaliaçao das açoes de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 Pendente regularizaçao e Landscape Management recuperaçaoambiental SFB BR-GIZ-161944-CS- INDV / Diagnósticos, mapeamento e elaboração de portifólio de divulgação da sistematização de experiências práticas de Institutional Development Implementação imóveis rurais públicos e TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 Pendente privados quanto às Landscape Management atividades e empreendimentos de recuperação/recomposição de áreas degradadas, silvicultura, e solu SFB BR-GIZ-161951-CS- INDV / Desenvolvimento de metodologia de monitoramento de áreas Institutional Development restauradas (fortalecer a Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 oferta de serviços de Pendente Landscape Management monitoramento) e aplicação por dois ciclos de monitoramento (T.0, T.1 e T.2). SFB BR-GIZ-161952-CS- Institutional Development INDV / Retificação dos Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-10-04 2020-11-22 2020-12-13 2021-01-17 2021-07-16 CARs de imóveis rurais Pendente Landscape Management contemplados pelo Projeto SFB BR-GIZ-161954-CS- INDV / Consultoria Individual para o Institutional Development Implementação levantamento, TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-05 2020-08-23 2020-09-13 2020-10-18 2021-04-16 Pendente sistematização e divulgação Landscape Management de dados e informações (incluindo econômicos); Page 11 SFB BR-GIZ-164470-CS- INDV / Consultoria para redesenhar todo ambiente Institutional Development de TI que sustenta todos TF / A8532 and Capacity Building for Posterior Individual Open 17,130.78 Assinado 2020-03-15 2020-03-26 2020-05-03 2020-05-27 2020-05-24 2020-06-12 2020-06-28 2020-06-12 2020-12-25 os componentes do SICAR Landscape Management através do Projeto Paisagens Rurais (FIP/Paisagem). SFB BR-GIZ-161969-CS- INDV / Contratação de consultor individual para realizar oficinas Institutional Development participativas de elaboração Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 e pactuação do plano, para Pendente Landscape Management o lançamento e a difusão do plano de ação de cada uma das bacias e mobilização dos Comitês de Bacias EMBRAPA BR-GIZ-166991- CS-INDV / Contratação de Consultoria CLT para organizar e elaborar conteúdo técnico para Institutional Development cursos de capacitação de TF / A8532 and Capacity Building for Posterior Individual Open 59,650.48 Assinado 2020-03-31 2020-03-30 2020-05-19 2020-05-14 2020-06-09 2020-05-18 2020-07-14 2020-06-01 2021-01-10 multiplicadores sobre Landscape Management recuperação de áreas com vegetação nativa degradada em paisagem rural no Bioma Cerrado BR-GIZ-179870-CS-INDV SFB / Contratação de Project Management, Assessor(a) Técnico(a) para Em fase de TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 2020-06-14 2020-06-24 2020-08-02 2020-08-23 2020-09-27 2021-03-26 apoio à implementação do Implementação Communication Plano de Comunicação do projeto Paisagens Rurais SFB BR-GIZ-181728-CS- INDV / Consultoria para realizar a organização e compilação das ações realizadas, resultados Institutional Development Em fase de alcançados e impactos TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-06-28 2020-06-25 2020-08-16 2020-09-06 2020-10-11 2021-04-09 Implementação observados na Landscape Management implementação do Plano ABC que podem ser estratégicos para o Projeto Paisagens Rurais (FIP/Paisagem). SFB BR-GIZ-182522-CS- INDV / Consultor 04 – Realizar o levantamento, análise e compilação dos resultados de execução de Institutional Development metas, das experiencias, Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-06-30 2020-07-08 2020-08-18 2020-09-08 2020-10-13 2021-04-11 perspectivas e compromissos Implementação Landscape Management em nível estadual no âmbito do Plano ABC executadas pelos Grupos Gestores Estaduais na região Nordeste SFB BR-GIZ-183115-CS- INDV / Consultor 02 – Organizar e compilar as Institutional Development Em fase de propostas para o TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-12 2020-07-22 2020-08-30 2020-09-20 2020-10-25 2021-04-23 Implementação desenvolvimento e Landscape Management implementação do Plano ABC 2020-2030 SFB BR-GIZ-183116-CS- INDV / Consultor 03 – Realizar o levantamento, análise e compilação das Institutional Development Em fase de experiências, perspectivas e TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-12 2020-07-16 2020-08-30 2020-09-20 2020-10-25 2021-04-23 Implementação compromissos de Landscape Management instituições públicas e privadas parceiras na implementação do Plano ABC SFB BR-GIZ-183117-CS- INDV / Consultor 05 – Realizar o levantamento, análise e compilação dos resultados de execução de Institutional Development metas, das experiencias, Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-12 2020-07-08 2020-08-30 2020-09-20 2020-10-25 2021-04-23 perspectivas e compromissos Implementação Landscape Management em nível estadual no âmbito do Plano ABC executadas pelos Grupos Gestores Estaduais nas regiões Norte e Cent SFB BR-GIZ-183119-CS- INDV / Consultor 06 – Realizar o levantamento, análise e compilação dos resultados de execução de Institutional Development Em fase de metas, das experiencias, TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-12 2020-07-08 2020-08-30 2020-09-20 2020-10-25 2021-04-23 Implementação perspectivas e compromissos Landscape Management em nível estadual no âmbito do ABC executadas pelos Grupos Gestores Estaduais nas regiões Sul e Sudeste EMBRAPA BR-GIZ-183568- CS-INDV / Contratação de Institutional Development Consultoria Pessoa Física TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-07-10 2020-07-10 2020-08-28 2020-09-18 2020-10-23 2021-04-21 para elaborar o logotipo do Landscape Management Projeto Paisagens Rurais projeto Paisagens Rurais Page 12 SFB BR-GIZ-184435-CS- INDV / Técnico 3 - Contratação de Assessor(a) Técnico(a) para apoio na Institutional Development compilação de dados do Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-07-17 2020-07-22 2020-09-04 2020-09-25 2020-10-30 2021-04-28 CAR e em soluções de Implementação Landscape Management geoprocessamento / sensoriamento remoto no âmbito do projeto Paisagens Rurais SFB BR-GIZ-184442-CS- INDV / Contratação de Institutional Development Assessor(a) Técnico(a) para Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 72,080.70 2020-07-17 2020-07-22 2020-09-04 2020-09-14 2020-09-25 2020-09-14 2020-10-30 2021-04-28 apoio ao desenvolvimento Implementação Landscape Management de soluções para Regularização Ambiental EMBRAPA BR-GIZ-161526- CS-INDV / Contratação de consultor para realizar caracterização e análise da estrutura e da dinâmica da Institutional Development recuperação das unidades Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-10-01 2020-11-19 2020-12-10 2021-01-14 2021-07-13 de paisagem e da Pendente Landscape Management capacidade de extrapolação dos resultados e a replicabilidade das intervenções tecnológicas de Boas Praticas Agropecuar EMBRAPA BR-GIZ-161529- CS-INDV / Caracterização e análise da estrutura e da dinâmica das unidades de Institutional Development paisagem (capacidade de Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 extrapolação e Pendente Landscape Management replicabilidade das intervenções tecnológicas de BPA e RAD em diferentes escalas). EMBRAPA BR-GIZ-161602- CS-INDV / Contratação CLT de Pessoa Física Mainstreaning Landscape (analista) para coordenar Implementação TF / A8532 Practices into Selected Posterior Individual Open 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-07-12 apoio e implementação da Pendente Watersheds Recuperação de Reserva Legal nas bacias hidrograficas. EMBRAPA BR-GIZ-161542- CS-INDV / Contratação de Pessoa Física (analista) CLT para monitoramento Institutional Development Implementação de indicadores tecnicos e TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Pendente socioeconomicos da Landscape Management recuperação das pastagens e de APP e de Reserva Legal das URTs Vitrines EMBRAPA BR-GIZ-161599- CS-INDV / Contratação de Consultoria Pessoa Física (analista) para coordenar a assistencia tecnica virtual Mainstreaning Landscape no monitoramento de Implementação TF / A8532 Practices into Selected Posterior Individual Open 0.00 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 indicadores tecnicos e Pendente Watersheds socioeconomicos da recuperação das pastagens e de APP e de Reserva Legal das URTs e nas bacias hidrograficas. EMBRAPA BR-GIZ-109803- CS-INDV / CI para o processamento e sistem da inform tec para a caracterização e análise da Institutional Development estrutura e da dinâmica Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 das unidades de paisagem Pendente Landscape Management (capacidade de extrapolação e replicabilidade das intervenções tec de BPA e RAD em dif escalas) Pelas regras da GIZ CI EMBRAPA BR-GIZ-109839- CS-INDV / Contratação de Consultoria individual na área de engenharia para elaboração de projeto básico Institutional Development e executivo para as Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-04-29 2021-06-17 2021-07-08 2021-08-12 2022-02-08 reformas do auditório, salas Pendente Landscape Management de aula, salas de video e viveiro da EMBRAPA Cerrados - Pelas regras da GIZ, trata-se de contrato de consultor INPE BR-GIZ-137983-CS- INDV / Assistente Institutional Development Administrativo para apoiar TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-10-18 2019-12-06 2019-12-27 2020-01-31 2020-07-29 as atividades relacionadas Landscape Management ao mapeamento do projeto Page 13 INPE BR-GIZ-109857-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Pelas regras da GIZ, trata- Landscape Management se de contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-109854-CS- INDV / Contratação Institutional Development consultoria individual - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Serviços de Landscape Management Geoprocessamento (mapeamento orbital) INPE BR-GIZ-109859-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Pelas regras da GIZ, trata- Landscape Management se de contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-109950-CS- INDV / Contratação de Consultor individual - Serviços de Geoprocessamento (análise Institutional Development da paisagem) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 regras da GIZ, trata-se de Landscape Management contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto INPE BR-GIZ-109860-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Pelas regras da GIZ, trata- Landscape Management se de contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-196031-CS- INDV / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development Implementação (mapeamento orbital) - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2020-09-28 2020-11-16 2020-12-07 2021-01-11 2021-07-10 Pendente Pelas regras da GIZ, trata- Landscape Management se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. Page 14