PROCUREMENT PLAN (Textual Part) Project information: [Afghanistan] [Sehatmandi] [P160615] Project Implementation agency: [Ministry of Public Health] Date of the Procurement Plan: [January 1, 2018] Period covered by this Procurement Plan: [July 1, 2018 – June 30, 2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. PROCUREMENT Afghanistan : Afghanistan Sehatmandi Project PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2018-01-01 2020-02-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160615 GPN Date: Project Name: Afghanistan Sehatmandi Project Loan / Credit No: IDA / D2850, / , TF / A7113 Executing Agency(ies): Ministry of Public Health WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MOPH-73978-GO-RFQ / IP phone and Licensing for Component 2: Strengthening Pending IP Phone for Improving the Request for Single Stage - One IDA / D2850 the Health System and its Post Open - National 40,000.00 0.00 Implementati 2018-08-23 2018-09-24 2018-11-23 Communication among Quotations Envelope Performance. on Central MoPH and Provincial PPHDs MOPH/SEHATMANDI/1397 Component 2: Strengthening Pending /RFQ/ 161 / Office furniture Request for Single Stage - One IDA / D2850 the Health System and its Post Open - National 3,840.00 0.00 Implementati 2018-10-03 2018-11-24 2018-12-13 for Sehatmandi project Quotations Envelope Performance. on finance office MOPH/SEHATMANDI/1397 /RFQ/ 164 / Procurement of Pharmaceuticals for Under Component 1: Improving Request for Single Stage - One Strengthening Mechanism IDA / D2850 Post Open - National 99,600.00 0.00 Implementati 2019-03-05 2019-03-20 2019-04-06 Service Delivery. Quotations Envelope (Parwan, Kapisa, Panjshir on and Pul-e-Charkhi HFs) Provinces MOPH/SEHATMANDI/1397/R FB/03 / Procurement of Under Component 1: Improving Open - Single Stage - One Pharmaceuticals for SM IDA / D2850 Prior Request for Bids 2,500,000.00 0.00 Implementati 2019-05-15 2019-11-11 2019-05-20 2019-11-19 2019-07-01 2019-12-28 2019-07-21 2019-08-25 2020-02-21 Service Delivery. International Envelope provinces BPHS, EPHS and on Pul-e-Charkhi Health Facility MOPH/ SEHATMANDI/1398/ RFB15 Component 2: Strengthening Pending Request for Single Stage - One / Water Dispenser for PMO IDA / D2850 the Health System and its Post Open - National 3,600.00 0.00 Implementati 2019-09-01 2019-09-07 2019-09-28 Quotations Envelope and other MoPH 21 Performance. on Departments Page 1 MOPH/SEHATMANDI/1398/R FQ15 / Office Furniture - 5 sets furniture, 18 Work desks, 30 work chairs, 1. White board, 2. Notice Component 2: Strengthening Pending Request for Single Stage - One boards, 3. Meeting tables, 36 IDA / D2850 the Health System and its Post Open - National 21,000.00 0.00 Implementati 2019-06-20 2019-08-15 2020-02-11 Quotations Envelope meeting chairs, 1. Director Performance. on table and seat, 1. Coat band, 2 Almarids, 1. Air extractor- for Minister and deputy Minsters and 9 dept MOPH/SEHATMANDI/1398/N CB - RFQ/14 / IT equipment (15 multi-functional copier, 5 shredder, 38 lip-taps, 14 Hard desk External, 3 Component 2: Strengthening Pending projectors, 3 flip screens, 2 Open - Single Stage - One IDA / D2850 the Health System and its Post Request for Bids 183,384.00 0.00 Implementati 2019-08-31 2019-09-05 2019-10-17 2019-11-16 2019-12-21 2020-03-10 flat screen TV, 1 cannon International Envelope Performance. on camera, 2. stabilizer, 11 connector, 13 Ex CD writer, 4 Mouse, 77 flash desk PMO and other 12 departments. MOPH/SEHATMANDI/1398/N CB-RFQ15 / Procurement of 6 Servers, 50 Wireless Component 2: Strengthening Pending accesses points with one Request for Single Stage - One IDA / D2850 the Health System and its Post Open - National 130,400.00 0.00 Implementati 2019-10-05 2019-11-13 2019-11-30 controller (Wi-Fi Zone), 12 Quotations Envelope Performance. on windows server license and 2 server firewall licenses for IT Department. MOPH/SEHATMANDI/1398/N CB-RFQ16 / One Power Generator - FG - Wilson - USA - 400KW MoPH is requested to be utilized for Component 2: Strengthening Pending Request for Single Stage - One improving the power IDA / D2850 the Health System and its Post Open - National 55,000.00 0.00 Implementati 2019-10-05 2019-11-20 2019-11-30 Quotations Envelope stability at the MoPH from Performance. on which the Sehatmandi project financed staff will leverage to work more productively. MOPH/SEHATMANDI/1398/R FQ16 / 6 Air-conditioners for Component 2: Strengthening Pending Request for Single Stage - One MoPH Procurement and IDA / D2850 the Health System and its Post Open - National 4,000.00 0.00 Implementati 2019-10-05 2019-10-22 2019-10-31 Quotations Envelope Sehatmandi Coordination Performance. on Office AF-MOPH-154844-GO-RFQ / Procurement of Handheld Component 2: Strengthening Pending Dual IRIS Camera, Green Request for Single Stage - One IDA / D2850 the Health System and its Post Limited 37,800.00 0.00 Implementati 2020-03-07 2020-05-02 2020-10-29 bit dactuscam, Potable Quotations Envelope Performance. on Identity Kit, Raven Software for IT Directorate AF-MOPH-155193-GO-RFQ / Component 2: Strengthening Pending Request for Single Stage - One Furniture for SM (Desk and IDA / D2850 the Health System and its Post Limited 2,600.00 0.00 Implementati 2020-02-04 2020-03-31 2020-09-27 Quotations Envelope Chair) Performance. on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 AFG/MOPH/GCMU/SEHATM ANDI/05 / Proposed Component 1: Improving Open - Single Stage - Two IDA / D2850 Prior Request for Bids 13,348,595.94 6,447,201.11 Signed 2018-01-02 2018-10-07 2018-01-07 2018-11-10 2018-02-18 2018-11-21 2018-05-03 2019-01-04 2018-06-20 2018-12-31 2021-06-30 implementation of BPHS & Service Delivery. International Envelope EPHS in Khost Province AFG/MOPH/GCMU/SEHATM ANDI/15 / Proposed Component 1: Improving Open - Single Stage - One IDA / D2850 Prior Request for Bids 8,719,629.45 4,624,963.02 Signed 2018-01-02 2018-10-04 2018-01-07 2018-11-10 2018-02-18 2018-11-18 2018-03-20 2018-12-30 2018-06-13 2018-12-31 2021-06-30 implementation of BPHS & Service Delivery. International Envelope EPHS in Nimroz Province AFG/MOPH/GCMU/SEHATM ANDI/22 / Proposed Component 1: Improving Open - Single Stage - One IDA / D2850 Prior Request for Bids 22,256,539.75 10,226,087.91 Signed 2017-12-03 2018-10-07 2017-12-08 2018-11-10 2018-01-19 2018-11-19 2018-02-18 2019-01-04 2018-05-23 2018-12-31 2021-06-30 implementation of BPHS in Service Delivery. International Envelope Helmand Province AFG/MOPH/GCMU/SEHATM ANDI/26 / Proposed Component 1: Improving Open - Single Stage - One IDA / D2850 Prior Request for Bids 12,740,954.63 7,268,009.08 Signed 2018-01-02 2018-10-07 2018-01-07 2018-11-10 2018-02-18 2018-11-21 2018-03-20 2019-01-04 2018-06-13 2018-12-31 2021-06-30 implementation of BPHS in Service Delivery. International Envelope Sari Pul Province AFG/MOPH/GCMU/SEHATM ANDI/16 / Proposed Component 1: Improving Open - Single Stage - One IDA / D2850 Prior Request for Bids 22,915,150.80 15,377,123.71 Signed 2018-02-28 2018-10-02 2018-03-05 2018-11-11 2018-04-16 2018-11-18 2018-04-24 2019-01-04 2018-05-29 2018-12-31 2021-06-30 implementation of BPHS in Service Delivery. International Envelope Herat Province AFG/MOPH/GCMU/SEHATM ANDI/02 / Proposed Component 1: Improving Open - Single Stage - One IDA / D2850 Prior Request for Bids 30,073,470.49 17,090,893.35 Signed 2018-02-28 2018-10-14 2018-03-05 2018-11-10 2018-04-16 2018-11-17 2018-04-26 2019-01-04 2018-05-31 2018-12-31 2021-06-30 implementation of BPHS & Service Delivery. International Envelope EPHS in Ghazni Province AFG/MOPH/GCMU/SEHATM ANDI/03 / Proposed Component 1: Improving Open - Single Stage - One implementation of BPHS & IDA / D2850 Prior Request for Bids 38,243,394.30 14,864,067.35 Signed 2018-02-28 2018-10-07 2018-03-05 2018-11-10 2018-04-16 2018-11-17 2018-04-24 2018-12-29 2018-05-29 2018-12-31 2021-06-30 Service Delivery. International Envelope EPHS in Badakhshan Province AFG/MOPH/GCMU/SEHATM ANDI/01 / Proposed Component 1: Improving Open - Single Stage - One implementation of BPHS & IDA / D2850 Prior Request for Bids 46,438,429.29 29,808,641.59 Signed 2018-02-24 2018-10-07 2018-03-01 2018-11-10 2018-04-12 2018-11-19 2018-04-25 2018-12-29 2018-05-30 2018-12-31 2021-06-30 Service Delivery. International Envelope EPHS in Nangarhar Province MOPH/SEHATMANDI/1397/D Component 2: Strengthening Pending IR /NC/ 28 / Internet Single Stage - One TF / A7113 the Health System and its Post Request for Bids Open - National 235,000.00 0.00 Implementati 2018-08-18 2018-08-23 2018-10-04 2018-10-14 2018-10-30 2019-10-25 Services for 34 Provincial Envelope Performance. on Health Offices MOPH/SEHATMANDI/1397/D Component 2: Strengthening Pending IR /NC/ 29 / Procurement Single Stage - One IDA / D2850 the Health System and its Post Request for Bids Open - National 30,000.00 0.00 Implementati 2018-08-15 2018-08-16 2018-09-27 2018-10-02 2018-10-17 2019-10-12 30Mbps Internet Services for Envelope Performance. on MoPH Data Center MOPH/SEHATMANDI/1397/D Component 2: Strengthening Under IR /NC/ 27 / Waste Single Stage - One IDA / D2850 the Health System and its Post Request for Bids Open - National 450,704.12 0.00 Implementati 2018-08-18 2018-11-18 2018-08-23 2018-09-10 2018-12-08 2018-09-26 2018-12-29 2018-10-22 2020-10-21 management of Kabul Envelope Performance. on hospitals MOPH/SEHATMANDI/PHCD/ 1397/NC/DIR/01 / Extension Component 2: Strengthening Pending of 64MBs internet Services IDA / D2850 the Health System and its Post Direct Selection Direct 37,000.00 0.00 Implementati 2018-06-11 2018-06-13 2018-06-24 2018-08-31 for 34 PPHDs for 2 Months Performance. on (JUL and AUG, 2018) MOPH/SEHATMANDI/1397 Component 2: Strengthening Pending Request for Single Stage - One NC/RFQ/162 / Toolkit on IDA / D2850 the Health System and its Post Open - National 35,000.00 0.00 Implementati 2018-11-25 2019-01-22 2019-02-20 Quotations Envelope gender and health Performance. on Page 3 MOPH/SEHATMANDI/1398 /NCS/RFQ/ 01 / 30 MB internet for MoPH Data Component 2: Strengthening Pending Request for Single Stage - One center which will function as IDA / D2850 the Health System and its Post Open - National 30,000.00 0.00 Implementati 2019-09-05 2019-10-31 2020-09-30 Quotations Envelope back up for the MoPH Performance. on during the time in which the MoPH system is down. MOPH/SEHATMANDI/1399/D IR /NC/ 27 / Extension of Pending Component 1: Improving Secondary waste IDA / D2850 Post Direct Selection Direct 58,500.00 0.00 Implementati 2020-01-21 2020-01-21 2020-01-22 2020-07-20 Service Delivery. management of 22 hospital on of Kabul province AF-MOPH-154790-NC-RFB / Pending Secondary Waste Component 1: Improving Single Stage - One IDA / D2850 Post Request for Bids Open - National 260,000.00 0.00 Implementati 2020-01-25 2020-01-30 2020-02-16 2020-03-10 2020-04-14 2021-06-30 Management of Kabul 22 Service Delivery. Envelope on Hospital CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AFG/MOPH/GCMU/SEHATM ANDI/04 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 21,141,074.29 16,551,711.77 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-23 2018-03-05 2018-04-04 2018-11-15 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Wardak Province AFG/MOPH/GCMU/SEHATM ANDI/06 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 14,853,570.56 8,933,149.87 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-06 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Paktia Province AFG/MOPH/GCMU/SEHATM ANDI/07 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 17,806,174.58 11,082,255.57 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-02 2018-05-09 2018-12-12 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Farah Province AFG/MOPH/GCMU/SEHATM ANDI/08 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 12,266,384.99 9,712,375.12 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-11 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Badghis Province AFG/MOPH/GCMU/SEHATM ANDI/09 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 18,208,062.91 11,281,689.96 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-03 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Kunar Province AFG/MOPH/GCMU/SEHATM ANDI/10 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 16,429,777.67 10,141,899.74 Signed 2017-12-02 2018-01-09 2017-12-23 2018-01-11 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-07 2018-05-09 2018-12-15 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Laghman Province AFG/MOPH/GCMU/SEHATM ANDI/11 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 13,944,461.74 10,157,590.67 Signed 2017-12-03 2017-12-24 2018-01-20 2018-02-06 2018-07-25 2018-03-06 2018-04-05 2018-11-06 2018-05-10 2018-12-15 2018-05-30 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Paktiak Province AFG/MOPH/GCMU/SEHATM ANDI/12 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 16,937,283.39 9,971,880.48 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-09 2018-05-09 2018-12-16 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Daikundi Province Page 4 AFG/MOPH/GCMU/SEHATM ANDI/13 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 14,868,982.39 13,194,800.39 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-12 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Logar Province AFG/MOPH/GCMU/SEHATM ANDI/14 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 13,307,316.25 9,772,383.75 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-03 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Urozgan Province AFG/MOPH/GCMU/SEHATM ANDI/17 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 22,949,462.62 13,006,516.60 Signed 2018-01-02 2018-01-23 2018-01-20 2018-03-08 2018-07-26 2018-04-05 2018-05-05 2018-11-15 2018-06-09 2018-12-14 2018-07-14 2019-01-01 2019-07-14 implementation of BPHS in Service Delivery. Based Selection International Balkh Province AFG/MOPH/GCMU/SEHATM ANDI/18 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 17,310,507.44 11,931,293.06 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-12 2018-05-09 2018-12-13 2018-06-13 2019-01-01 2019-06-13 implementation of BPHS in Service Delivery. Based Selection International Kandahar Province AFG/MOPH/GCMU/SEHATM ANDI/19 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 14,840,606.33 10,628,345.47 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-09 2018-05-09 2018-12-12 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Kunduz Province AFG/MOPH/GCMU/SEHATM ANDI/20 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 22,084,909.00 10,980,350.82 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-26 2018-03-05 2018-04-04 2018-11-15 2018-05-09 2018-12-13 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS & Service Delivery. Based Selection International EPHS in Faryab Province AFG/MOPH/GCMU/SEHATM ANDI/21 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 20,459,864.95 10,115,167.03 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-26 2018-03-05 2018-04-04 2018-11-15 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Takhar Province AFG/MOPH/GCMU/SEHATM ANDI/23 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 19,228,548.15 11,505,203.96 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-15 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Baghlan Province AFG/MOPH/GCMU/SEHATM ANDI/25 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 13,839,755.11 7,063,121.09 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-01 2018-05-09 2018-12-13 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Kabul Province AFG/MOPH/GCMU/SEHATM ANDI/27 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 12,399,720.86 7,429,835.49 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-23 2018-03-05 2018-04-04 2018-11-15 2018-05-09 2018-12-12 2018-06-13 2018-12-31 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Jawzjan Province AFG/MOPH/GCMU/SEHATM ANDI/28 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 18,945,301.44 8,831,909.29 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-09 2018-05-09 2018-12-13 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Bamyan Province AFG/MOPH/GCMU/SEHATM ANDI/29 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 11,741,569.58 5,897,253.74 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-25 2018-03-05 2018-04-04 2018-11-02 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Samangan Province AFG/MOPH/GCMU/SEHATM ANDI/30 / Proposed Component 1: Improving Quality And Cost- IDA / D2850 Prior Open - National 8,406,533.43 5,859,835.03 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-26 2018-03-05 2018-04-04 2018-12-04 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection Zabul Province AFG/MOPH/GCMU/SEHATM ANDI/31 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 14,177,686.57 7,445,793.92 Signed 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-07-24 2018-03-05 2018-04-04 2018-11-06 2018-05-09 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Nooristan Province Page 5 AFG/MOPH/GCMU/SEHATM ANDI/24 / Proposed Component 1: Improving Quality And Cost- Open - IDA / D2850 Prior 17,435,539.85 13,248,004.28 Signed 2017-12-06 2017-12-27 2018-07-24 2018-02-09 2018-07-26 2018-03-09 2018-04-08 2018-11-01 2018-05-13 2018-12-14 2018-06-13 2019-01-01 2021-06-30 implementation of BPHS in Service Delivery. Based Selection International Ghor Province AFG/MOPH/GCMU/SEHATM ANDI/01 / Proposed Component 1: Improving Quality And Cost- Open - implementation of BPHS & / Prior 46,438,429.29 0.00 Canceled 2017-12-02 2017-12-23 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Service Delivery. Based Selection International EPHS in Nangarhar Province AFG/MOPH/GCMU/SEHATM ANDI/107 / Third Party Component 2: Strengthening monitoring and evaluation Quality And Cost- Open - IDA / D2850 the Health System and its Prior 4,620,000.00 0.00 Under Review 2018-05-23 2019-12-19 2018-06-13 2019-12-09 2018-07-27 2018-08-24 2018-09-23 2018-10-28 2018-12-15 2021-06-30 for Afghanistan household Based Selection International Performance. survey and sample registration system AFG/MOPH/GCMU/SEHATM ANDI/35_1 / Proposed Component 2: Strengthening implementation of third Quality And Cost- Open - IDA / D2850 the Health System and its Prior 6,465,867.00 7,379,697.98 Signed 2018-05-29 2018-09-04 2018-06-19 2018-10-15 2018-08-02 2019-03-01 2018-08-30 2019-04-21 2018-09-29 2019-06-02 2018-11-03 2019-07-31 2018-12-01 2019-10-03 2021-11-30 party monitoring and Based Selection International Performance. evaluation for BSC, HMIS verification and DQA AFG/MOPH/GCMU/SEHATM ANDI/35 / Proposed Component 1: Improving Quality And Cost- Open - implementation of Third / Prior 8,461,136.00 0.00 Canceled 2018-01-07 2018-01-28 2018-03-13 2018-04-10 2018-05-10 2018-06-14 2018-07-19 2021-06-30 Service Delivery. Based Selection International party Monitoring and Evalutation AFG/MOPH/GCMU/SEHATM ANDI/108 / Procurement of Hiring Consultancy Firm for Component 3: Strengthening Formative and Operational Demand and Community Quality And Cost- Open - Research Health umbrella TF / A7113 Prior 6,584,200.00 0.00 Under Review 2018-06-13 2018-09-04 2018-07-04 2019-10-22 2018-08-17 2018-09-14 2018-10-14 2018-11-18 2018-12-23 2020-12-31 Accountability for Key Based Selection International and four specific Health Services. communication campaigns and capacity building under Health Promotion Project AFG/MOPH/GCMU/SEHATM ANDI/34 / Proposed Component 2: Strengthening Quality And Cost- Open - Under implementation of Public TF / A7113 the Health System and its Post 147,801.00 0.00 2018-08-14 2018-09-09 2018-09-04 2018-10-18 2018-11-15 2018-12-15 2019-01-19 2019-02-23 2019-11-04 Based Selection International Implementation Expenditure Trucking Survey Performance. (PETS) AFG/MOPH/GCMU/SEHATM Component 1: Improving Quality And Cost- Open - ANDI/85 / Implement of IDA / D2850 Prior 12,000,000.00 0.00 Under Review 2018-09-25 2018-10-01 2018-11-14 2018-12-12 2019-01-11 2019-02-15 2019-03-22 2020-03-21 Service Delivery. Based Selection International Kabul Urban Health Project MOPH/SEHATMANDI/1398/D IR/CS01 / This activity involves provision of WHO technical assistance through hiring of individual Component 2: Strengthening UN Agencies Pending consultants for enhancing IDA / D2850 the Health System and its Post Direct 500,000.00 0.00 2019-05-19 2021-06-30 (Direct) Implementation the Sehatmandi project Performance. implementation in performance management, recruitment, procurement and other hands on support. AFG/MOPH/GCMU/SEHATM ANDI/33 / Proposed Component 1: Improving Quality And Cost- Open - implementation of Contract / Prior 19,246,830.81 0.00 Canceled 2017-12-02 2019-03-25 2017-12-23 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Service Delivery. Based Selection International Management in three SM provinces INDIVIDUAL CONSULTANTS Page 6 Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/36 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,055,923.00 10,376,138.17 Signed 2018-05-09 2018-09-04 2018-05-19 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in C1 Badakhshan AFG/MOPH/GCMU/SEHATM ANDI/37 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 2,269,220.00 13,132,674.17 Signed 2018-05-12 2018-09-04 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 BPHS in C2 Badakhshan Service Delivery. Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/38 / Implementationof IDA / D2850 Prior Direct Selection Direct 2,751,424.00 14,066,660.30 Signed 2018-05-12 2018-09-04 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Baghalan Province AFG/MOPH/GCMU/SEHATM ANDI/39 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 1,196,070.00 5,848,304.47 Signed 2018-05-12 2018-09-04 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 BPHS in C1 Bamyan Service Delivery. Province AFG/MOPH/GCMU/SEHATM ANDI/43 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 1,199,814.00 7,117,772.50 Signed 2018-05-12 2018-05-22 2018-07-01 2018-07-01 2018-12-31 BPHS in C2 Bamayn Service Delivery. Province AFG/MOPH/GCMU/SEHATM ANDI/42 / Implementationof Component 1: Improving IDA / D2850 Prior Direct Selection Direct 1,660,417.00 8,451,507.11 Signed 2018-05-12 2018-09-04 2018-05-22 2018-07-01 2018-07-01 2018-12-31 BPHS in C1 Ghazni Service Delivery. Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/45 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,435,327.00 8,527,598.83 Signed 2018-05-12 2018-09-04 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Jawzjan Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/44 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,278,251.00 12,716,913.76 Signed 2018-05-12 2018-09-03 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Faryab Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/46 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,855,054.00 10,317,765.61 Signed 2018-05-12 2018-09-04 2018-05-22 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Kabul Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/48 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,344,123.00 7,049,640.44 Signed 2018-05-12 2018-09-04 2018-05-22 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Khost Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/49 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,041,679.00 8,232,788.34 Signed 2018-05-12 2018-05-22 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Paktika Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/47 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,222,869.00 11,713,989.42 Signed 2018-05-13 2018-09-04 2018-05-23 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Kandahar Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/51 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,506,651.00 14,023,191.96 Signed 2018-05-13 2018-09-04 2018-05-23 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Takhar Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/50 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,669,966.00 8,317,504.12 Signed 2018-05-13 2018-09-04 2018-05-23 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Paktya Province Page 7 AFG/MOPH/GCMU/SEHATM ANDI/52 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 565,681.00 3,680,742.75 Signed 2018-05-14 2018-09-03 2018-05-24 2018-05-29 2018-07-01 2018-07-01 2018-12-31 EPHS in Badakhshan Service Delivery. Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/53 / Implementation of IDA / D2850 Prior Direct Selection Direct 542,341.00 3,554,870.53 Signed 2018-05-14 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Ghazni Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/54 / Implementation of IDA / D2850 Prior Direct Selection Direct 400,829.00 2,609,535.97 Signed 2018-05-14 2018-09-03 2018-05-24 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Khost Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/55 / Implementation of IDA / D2850 Prior Direct Selection Direct 406,426.00 2,379,506.75 Signed 2018-06-11 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Paktika Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/105 / Implementation IDA / D2850 Prior Direct Selection Direct 1,019,407.00 3,282,367.32 Signed 2018-06-11 2018-09-03 2018-06-21 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. of EPHS in Paktya Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/57 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,198,084.00 3,364,671.68 Signed 2018-06-11 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Badghis Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/58 / Implementation of IDA / D2850 Prior Direct Selection Direct 3,292,291.00 9,433,817.19 Signed 2018-06-10 2018-09-03 2018-06-20 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Balkh Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/59 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,924,537.00 5,418,087.29 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Daikundi Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/61 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,537,287.00 7,179,137.44 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Ghor Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/62 / Implementation of IDA / D2850 Prior Direct Selection Direct 3,252,507.00 9,178,346.94 Signed 2018-06-11 2018-09-03 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Helmand Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/63 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,080,242.00 5,838,610.01 Signed 2018-05-13 2018-09-03 2018-05-23 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Kunar Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/64 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,156,843.00 6,092,435.27 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Kunduz Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/65 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,875,857.00 5,294,101.45 Signed 2018-06-11 2018-09-03 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Laghman Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/66 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,730,003.00 4,878,514.02 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Logar Province AFG/MOPH/GCMU/SEHATM ANDI/67 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 4,793,207.00 13,501,804.95 Signed 2018-05-13 2018-09-03 2018-05-23 2018-07-01 2018-07-01 2018-12-31 BPHS in Nangarhar Service Delivery. Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/68 / Implementation of IDA / D2850 Prior Direct Selection Direct 818,339.00 2,332,175.34 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Nimruz Province Page 8 AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/69 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,769,855.00 5,046,756.05 Signed 2018-05-14 2018-09-03 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Nuristan Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/70 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,715,259.00 4,827,770.57 Signed 2018-06-11 2018-09-04 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Samangan Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/71 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,862,948.00 5,240,250.65 Signed 2018-05-14 2018-09-04 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Sarepul Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/72 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,527,109.00 4,318,616.85 Signed 2018-05-13 2018-09-04 2018-05-23 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Urozga n Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/73 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,635,869.00 7,448,976.65 Signed 2018-05-14 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Wardak Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/74 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,231,134.00 7,399,998.52 Signed 2018-05-14 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Zabul Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/75 / Implementation of IDA / D2850 Prior Direct Selection Direct 542,149.00 1,539,841.26 Signed 2018-05-13 2018-05-23 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Daikundi Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/76 / Implementation of IDA / D2850 Prior Direct Selection Direct 513,717.00 1,451,557.17 Signed 2018-06-11 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Farah Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/77 / Implementation of IDA / D2850 Prior Direct Selection Direct 591,490.00 1,659,894.63 Signed 2018-06-11 2018-09-04 2018-06-21 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Kunar Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/78 / Implementation of IDA / D2850 Prior Direct Selection Direct 508,056.00 1,447,117.69 Signed 2018-05-14 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Laghman Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/79 / Implementation of IDA / D2850 Prior Direct Selection Direct 435,730.00 1,229,993.08 Signed 2018-06-11 2018-09-04 2018-06-21 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Logar Province AFG/MOPH/GCMU/SEHATM ANDI/80 / Implementation of Component 1: Improving IDA / D2850 Prior Direct Selection Direct 1,996,576.00 5,653,418.49 Signed 2018-05-14 2018-05-24 2018-07-01 2018-07-01 2018-12-31 EPHS in Nangarhar Service Delivery. Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/81 / Implementation of IDA / D2850 Prior Direct Selection Direct 439,254.00 1,240,330.22 Signed 2018-06-11 2018-09-04 2018-06-21 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Nimruz Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/82 / Implementation of IDA / D2850 Prior Direct Selection Direct 404,762.00 1,141,644.98 Signed 2018-06-11 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Urozgan Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/83 / Implementation of IDA / D2850 Prior Direct Selection Direct 433,577.00 1,225,869.65 Signed 2018-06-11 2018-06-21 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Wardak Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/84 / Implementation of IDA / D2850 Prior Direct Selection Direct 473,139.00 2,702,292.27 Signed 2018-06-11 2018-09-04 2018-06-21 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. EPHS in Badghis Province Page 9 AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/60 / Implementation of IDA / D2850 Prior Direct Selection Direct 2,075,612.57 5,852,735.47 Signed 2018-05-14 2018-09-04 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Farah Province AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/92 / Implementation of IDA / D2850 Prior Direct Selection Direct 1,720,391.69 9,095,024.55 Signed 2018-05-14 2018-09-04 2018-05-24 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Ghazni C2 AFG/MOPH/GCMU/SEHATM Component 1: Improving ANDI/93 / Implementation of IDA / D2850 Prior Direct Selection Direct 3,321,102.65 16,874,690.98 Signed 2018-05-14 2018-09-04 2018-05-24 2018-05-29 2018-07-01 2018-07-01 2018-12-31 Service Delivery. BPHS in Herat Province AFG/MOPH/GCMU/SEHATM ANDI/56 / Proposed Component 1: Improving implementation of Third IDA / D2850 Prior Direct Selection Direct 2,128,482.00 12,302,530.00 Signed 2018-05-14 2018-09-04 2018-05-24 2018-07-01 2018-07-01 2018-12-31 Service Delivery. party Monitoring and Evalutation MOPH/SEHATMANDI/1397/C DS /CS/ 01 / International Component 2: Strengthening Pending Consultant to General IDA / D2850 the Health System and its Post Direct Selection Direct 139,200.00 0.00 2018-06-12 2018-06-18 2018-07-04 2019-06-30 Implementation Director of Policy and Performance. Planning MOPH/SEHATMANDI/1397/C Component 2: Strengthening DS /CS/ 03 / Health Pending TF / A7113 the Health System and its Post Direct Selection Direct 86,346.70 0.00 2018-06-02 2018-06-03 2018-07-15 2018-12-31 Services Management Implementation Performance. Advisor MOPH/SEHATMANDI/1397/C Component 2: Strengthening DS /CS/ 02 / Sehatmandi Pending IDA / D2850 the Health System and its Prior Direct Selection Direct 147,716.00 0.00 2018-06-12 2018-06-16 2018-07-06 2019-06-30 Advisor/ Mentor to Minister Implementation Performance. of Public Health Page 10