The World Bank Report No: ISR12868 Implementation Status & Results Turkey Seismic Risk Mitigation Project (P078359) Public Disclosure Copy Operation Name: Seismic Risk Mitigation Project (P078359) Project Stage: Implementation Seq.No: 22 Status: ARCHIVED Archive Date: 24-Dec-2013 Country: Turkey Approval FY: 2005 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 26-May-2005 Original Closing Date 30-Sep-2010 Planned Mid Term Review Date 30-May-2008 Last Archived ISR Date 24-Jun-2013 Effectiveness Date 03-Feb-2006 Revised Closing Date 31-Dec-2014 Actual Mid Term Review Date 10-Oct-2008 Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to assist the Borrower improve the city of Istanbul's preparedness for a potential earthquake, through enhancing the institutional and technical capacity for disaster management and emergency response, strengthening critical publicfacilities for earthquake resistance, and supporting measures for better enforcement of building codes. Has the Project Development Objective been changed since Board Approval of the Project? ● Yes No Component(s) Component Name Component Cost Enhancing Emergency Preparedness 73.46 Seismic Risk Mitigation for Priority Public Facilities 309.55 Enforcement of Building Codes 7.00 Project Management 8.00 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Low Low Implementation Status Overview Project implementation is progressing satisfactorily towards achievement of its development objectives. By December 2012 all investments foreseen under the original loan were completed and the original loan was closed. The additional loan still has another year till closing. A total 739 public buildings were retrofitted and 21 buildings were reconstructed. In addition, another 29 buildings are being strengthened. The construction of Umraniye Maternity and Obstetrics Hospital, a major investment under the additional loan has started. Page 1 of 5 The World Bank Report No: ISR12868 Based on the designs developed under the project, the seismic strengthening and preservation works on the Archaeological Museum and Mecidiye Kiosk within the Topkapi Palace complex and are advancing. The pilot activities aimed at better building code enforcement in Pendik and Bagcilar district municipalities were completed and introduced improved systems for building permit issuance. The training program in the retrofitting code was provided to 3,630 engineers throughout the country. Public Disclosure Copy Locations Country First Administrative Division Location Planned Actual Turkey Not Entered Istanbul Not Entered Not Entered Istanbul ✔ ✔ Turkey Istanbul Istanbul ✔ ✔ Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target (Rev) Key public facilities retrofitted; skills/ Text Value Level of preparedness is low. Technical capacity for Emergency response units technical capacities of emergency response emergency response was are adequately equipped and units strengthened; transparency/efficiency of strengthened; Istanbul Search trained and emergency bldg permit issuance in 2 pilot municipalities and Rescue teams were response plans tested. improved. certified by INSARAG. Date 03-Feb-2006 15-Nov-2013 31-Dec-2014 Comments (Orig for 12/31/2011: skills and technical capacities of emergency response units are strengthened) Key public facilities retrofitted Number Value 0.00 760.00 763.00 Date 03-Feb-2006 15-Nov-2013 31-Dec-2014 Comments 760 public buildings were All targeted 763 public retrofitted/ buildings retrofitted/ reconstructed; reconstructed ((Orig for Public Disclosure Copy 12/31/2011: Key public facilities are retrofitted to resist a major earthquake) Transparency/efficiency of bldg permit Text Value Document management Document management was Document management issuance in 2 pilot municipalities improved. paper and manual based; system established; building system established; building engineers are not trained permit process optimized permit process optimized (automated, efficient and (automated, efficient and transparent); municipal call transparent); municipal call centers established; 3,630 centers established; 3,000 engineers trained. engineers trained. Page 2 of 5 The World Bank Report No: ISR12868 Date 03-Feb-2006 15-Nov-2013 31-Dec-2014 Comments (Orig for 12/31/2011: building code enforcement is Public Disclosure Copy improved) Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Capacity of public safety organizations in Text Value Capacity to respond to a The new communication is New communication and Istanbul to respond to major disasters is major disaster is insufficient. operational and in daily use; information system is enhanced; coordination between regional emergency response units operational and used in daily emergency response agencies are improved. were equipped; 360,000 operations; PDDEM is volunteers trained; public strengthened; public safety awareness campaignes units are adequately reached estimated 5 million equipped; volunteer and Istanbul residents. relevant agency groups trained; public awareness campaigns reach out to Istanbul population. Date 21-Jun-2007 15-Nov-2013 31-Dec-2014 Comments Key selected public facilities are retrofitted to Text Value 0 760 public buildings Around 762 public buildings ensure their operation in the aftermath of a retrofitted/reconstructed; retrofitted/reconstructed; disaster. vulnerability assessments vulnerability assessment of of selected cultural heritage selected cultural heritage buildings were completed. buildings completed. Date 30-Jun-2005 15-Nov-2013 31-Dec-2014 Comments (Origin. of 12/31/2011) Around 550 public buildings retrofitted/reconstructed; vulnerability assessment of selected cultural heritage buildings completed. Public Disclosure Copy Improved efficiency and transparency of Text Value IT equipment installed; Document management was Document management building permit issuance process in two pilot certificates for data security system established; building system established; building municipalities. received; data digitization in permit process optimized permit process optimized progress. (as of AF Appraisal) (automated, efficient and (automated, efficient and transparent); municipal call transparent); municipal call centers established; 3,630 centers established; 3,000 engineers trained. engineers trained. Date 02-Feb-2011 15-Nov-2013 31-Dec-2013 Page 3 of 5 The World Bank Report No: ISR12868 Comments (Orig of 12/31/2011) Improvement in compliance with building codes and land use plans in selected Istanbul Public Disclosure Copy municipalities. Data on Financial Performance (as of 20-Nov-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P078359 IBRD-47840 Closed 26-May-2005 18-Oct-2005 03-Feb-2006 30-Sep-2010 31-Dec-2012 P078359 IBRD-80330 Effective 21-Apr-2011 04-Aug-2011 22-Nov-2011 31-Dec-2014 31-Dec-2014 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P078359 IBRD-47840 Closed USD 400.00 394.11 5.89 426.16 0.00 108.00 P078359 IBRD-80330 Effective USD 150.00 150.00 0.00 40.17 108.58 27.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation There are no key decisions made. Page 4 of 5 The World Bank Report No: ISR12868 Restructuring History Level two Approved on 28-Mar-2010, Level two Approved on 14-Apr-2010 Public Disclosure Copy Related Projects P122179-ISMEP - ADDITIONAL FINANCING Public Disclosure Copy Page 5 of 5