PROCUREMENT PLAN (Textual Part) Project information: Rwanda, Nile Cooperation for Climate Resilience P- 172848 Project Implementation agency: Nile Equatorial Strategic Action Plan (NELSAP) Date of the Procurement Plan: April 19, 2021 Period covered by this Procurement Plan: April 2021–April 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nile Basin Procurement and Disposal Manual (for NELSAP, NILE-SEC & ENTRO), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other own procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Eastern Africa : Nile Cooperation for Climate Resilience PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2021-08-11 2021-08-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172848 GPN Date: 2021-06-30 Project Name: Nile Cooperation for Climate Resilience Loan / Credit No: TF / B4716 N Executing Agency(ies): ile Basin Initiative Secretariat WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UG-NBI-244825-CW-RFQ / Office renovation: Office Request for Pending Component 1: Advancing Nile Request for Single Stage - One 2021-11- Interior Painting ($18,200) TF / B4716 Post Limited Quotations (Non 48,200.00 0.00 Implementat 2021-09-07 2021-09-30 Basin-Wide Cooperation Quotations Envelope 15 and Sanitation - Wash rooms Bank-SPD) ion and Plumbing: $30,000) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-244423-GO-RFQ / Pending Activity 1.5.2.2: Software Component 1: Advancing Nile Request for Single Stage - One TF / B4716 Post Limited 10,000.00 0.00 Implementati 2021-08-25 2021-09-20 2021-10-08 licenses - EUMETSAT Basin-Wide Cooperation Quotations Envelope on GeoNetCast UG-NBI-245378-GO-RFQ / Pending Component 1: Advancing Nile Request for Single Stage - One Office Air Conditioning Units TF / B4716 Post Limited 12,000.00 0.00 Implementati 2021-08-06 2021-09-06 2021-10-06 Basin-Wide Cooperation Quotations Envelope (8 Units) on UG-NBI-245380-GO-RFQ / Security Equipment: 8 Sets of Pending Security Cameras ($16,000) & Component 1: Advancing Nile Request for Single Stage - One TF / B4716 Post Limited 36,000.00 0.00 Implementati 2021-08-15 2021-09-13 2021-10-20 8 Units of Accessories and Basin-Wide Cooperation Quotations Envelope on Access System Doors & Reporting System ($20,000). UG-NBI-245381-GO-RFQ / Office Furniture: 19 pcs of Pending Component 1: Advancing Nile Klix Single door storage Units TF / B4716 Post Direct Selection Direct 4,380.00 0.00 Implementati 2021-08-16 2021-08-21 2021-08-27 2021-10-06 Basin-Wide Cooperation ($4,180), 01 Desk Extension on Unit ($200). UG-NBI-245382-GO-RFQ / Office Furniture: 2 sets of Pending Office desks-Bow Front Component 1: Advancing Nile Request for Single Stage - One TF / B4716 Post Limited 9,802.00 0.00 Implementati 2021-09-07 2021-10-11 2021-11-16 Workstation Package ($ 2,302) Basin-Wide Cooperation Quotations Envelope on and 25 Conference Chairs ($7,500) UG-NBI-245427-GO-RFQ / Software: Office Productivity Suites ( Pending Microsoft): $15,000 Component 1: Advancing Nile Request for Single Stage - One TF / B4716 Post Limited 23,000.00 0.00 Implementati 2021-08-15 2021-09-15 2021-10-30 MS SQL ( Database Software): Basin-Wide Cooperation Quotations Envelope on $4,000 Other Productivity Software ( Adobe PDF, TV): $4000 UG-NBI-245429-GO-RFQ / Lot 1: Office Equipment (Computers & Projectors) : $84,500 Lot 2: Office Equipment(Copiers, printers & Pending Component 1: Advancing Nile Request for Single Stage - One Scanners): $15,500 TF / B4716 Post Open - National 195,000.00 0.00 Implementati 2021-09-20 2021-11-04 2022-01-20 Basin-Wide Cooperation Quotations Envelope Lot 3: Office Equipment (Video on Conferencing equipment): $50,000 Lot 4: Off. Equip(Network Storage, Routers, LAN/WAN, handsets: $45000 UG-NBI-244419-GO-DIR / Activity 1.5.2.2: ERDAS- Imagine license (5) for Generating basin monitoring Pending Component 1: Advancing Nile information products and TF / B4716 Post Direct Selection Direct 12,500.00 0.00 Implementati 2021-08-10 2021-08-15 2021-08-25 2021-09-27 Basin-Wide Cooperation support their use in water on resources management and development efforts at national and regional levels. UG-NBI-244718-GO-RFQ / Printing Services: Governance meetings in Oct. 2021 ($550) and June 2022 ($550); Corporate report -$2,500 and Pending Component 1: Advancing Nile Request for Single Stage - One Corporate Flyer-$300; NBI TF / B4716 Post Limited 15,300.00 0.00 Implementati 2021-09-22 2021-10-15 2021-10-27 Basin-Wide Cooperation Quotations Envelope 2022 Calendar-$2000; on Communication package for HOSS Meeting - $4,500, Nile Day event-$4600 and Strategic Dialogue:$300 UG-NBI-244461-GO-DIR / Pending Component 1: Advancing Nile Activity 1.5.2.2: ArcGIS license TF / B4716 Post Direct Selection Direct 15,000.00 0.00 Implementati 2021-10-04 2021-10-09 2021-10-20 2022-10-21 Basin-Wide Cooperation renewal on UG-NBI-245423-GO-RFQ / Pending Component 1: Advancing Nile Request for Single Stage - One Power backup system TF / B4716 Post Limited 50,000.00 0.00 Implementati 2021-08-09 2021-09-17 2021-11-08 Basin-Wide Cooperation Quotations Envelope (turnkey) on Page 1 UG-NBI-244829-GO-RFQ / Pending Component 1: Advancing Nile Request for Single Stage - One Office Carpet and Blinds TF / B4716 Post Limited 29,000.00 0.00 Implementati 2021-09-07 2021-10-04 2021-10-20 Basin-Wide Cooperation Quotations Envelope replacement on UG-NBI-244421-GO-RFQ / Software licenses (Office Pending productivity: Office, MS Component 1: Advancing Nile Request for Single Stage - One TF / B4716 Post Limited 32,500.00 0.00 Implementati 2021-08-15 2021-09-07 2021-09-20 Teams, anti-virus, adobe) Basin-Wide Cooperation Quotations Envelope on $30,000); 04 Matlab software license ($2,500) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-245465-CS-CDS / Pending Component 1: Advancing Nile S5: Internet Bandwidth TF / B4716 Post Direct Selection Direct 18,000.00 0.00 Implementati 2021-09-06 2021-09-11 2021-10-06 2022-06-30 Basin-Wide Cooperation connectivity on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-244407-CS-CQS / Activity 1.5.2.2: Consultancy firm: - Generating basin monitoring information Consultant Component 1: Advancing Nile Pending products and support their TF / B4716 Post Qualification Open - International 31,500.00 0.00 2021-11-02 2021-12-02 2021-12-17 2022-01-16 2022-02-20 2022-08-19 Basin-Wide Cooperation Implementation use in water resources Selection management and development efforts at national and regional levels. UG-NBI-244479-CS-CQS / Activity 1.5.3.1: A Consultancy Firm to update design of the selected water Consultant quality monitoring networks Component 1: Advancing Nile Under TF / B4716 Post Qualification Open - International 154,000.00 0.00 2021-08-10 2021-08-18 2021-08-31 2021-09-20 2021-09-24 2021-10-29 2022-06-30 (field stations, and Basin-Wide Cooperation Implementation Selection strengthened national laboratories).& support equipment procurement and installation UG-NBI-244487-CS-CQS / Activity 1.5.3.1: A Consultancy firm to Develop Consultant Component 1: Advancing Nile WQ database (basin-wide TF / B4716 Post Qualification Open - International 198,000.00 0.00 Under Review 2021-09-08 2021-08-25 2021-09-29 2021-11-12 2021-11-30 2021-12-22 2022-06-20 Basin-Wide Cooperation baseline) - including upgrade Selection of IKP to include water quality (backend and User Interface) UG-NBI-244519-CS-CDS / Activity 5.3.1.2: Develop the Nile Basin river flow: Consultant Component 1: Advancing Nile Pending Consultancy firm to TF / B4716 Post Qualification Open - International 341,310.00 0.00 2022-02-03 2022-02-24 2022-04-05 2022-04-15 2022-05-05 2022-11-30 Basin-Wide Cooperation Implementation enhance/refine Nile Basin Selection river flow forecast system - 7 man-months Activity UG-NBI-244400-CS-INDV / Consultancy firm: To design, develop and rollout NBI Data Component 1: Advancing Nile Quality And Cost- Pending TF / B4716 Post Open - International 506,000.00 0.00 2021-09-10 2021-10-01 2021-10-29 2021-11-15 2021-11-25 2021-12-06 2021-12-29 2022-06-30 and Analytic services platform Basin-Wide Cooperation Based Selection Implementation (e.g. Dashboad Development, Apps, Portals) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-243040-CS-INDV / C3.1.1.1 Graphic Designer to design corporate communication products (NileDay:$400 Individual Component 1: Advancing Nile Pending Corp.flyer:$100, SD Mtg: TF / B4716 Post Consultant Open 3,900.00 0.00 2021-08-15 2021-09-11 2021-09-15 2021-09-22 2022-06-30 Basin-Wide Cooperation Implementation $100, 2022 NBI calendar: Selection 300, 4 quarterly newsletter:$1200, Corporate Report - Eng: 1200, HOSS Mtg: $500, TAC Mtg: $100 UG-NBI-243078-CS-INDV / Individual Platform for cooperation and Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 2,000.00 0.00 2021-08-10 2021-09-03 2021-09-06 2021-09-10 2021-10-20 dialogue: A consultant to Basin-Wide Cooperation Implementation Selection prepare media strategy UG-NBI-243087-CS-INDV / C3.1.1.2 - Platform for Individual cooperation and dialogue: Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 1,600.00 0.00 2021-10-04 2021-10-22 2021-10-25 2021-11-29 2021-12-20 Consultancy to train key NBI Basin-Wide Cooperation Implementation Selection staff on media relations and social media UG-NBI-243093-CS-INDV / 6.5.2.5 - Platform for cooperation and dialogue: Individual Component 1: Advancing Nile Pending Stocktaking and designing TF / B4716 Post Consultant Open 4,400.00 0.00 2021-08-04 2021-08-25 2021-08-27 2021-09-06 2021-10-20 Basin-Wide Cooperation Implementation tailor-made actions to remedy Selection performance of platforms / forums. Page 2 UG-NBI-243096-CS-INDV / 6.5.2.3: Platform for cooperation and dialogue: Youth competitions (Nile-SEC, Individual NBD): Organise social media Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 4,000.00 0.00 2021-10-04 2021-10-26 2021-10-29 2021-11-05 2021-12-31 based competitions such as Basin-Wide Cooperation Implementation Selection photo, video, hackathons, Nile Cooperation Story blogs, with themes related to climate change UG-NBI-243119-CS-INDV / 6.2.1.1: Platform for Individual cooperation and dialogue - A Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 3,500.00 0.00 2021-10-04 2021-11-25 2021-11-29 2021-12-06 2021-12-20 Consultant to train Basin-Wide Cooperation Implementation Selection participants on Transboundary Water cooperation UG-NBI-243137-CS-INDV / C2.1.2.4: Platform for Individual cooperation and dialogue: Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 9,000.00 0.00 2021-10-15 2021-11-05 2021-11-08 2021-11-12 2021-11-30 Training on stakeholder Basin-Wide Cooperation Implementation Selection engagement and gender issues UG-NBI-244486-CS-INDV / Consultant 2: Individual Consultant E&S Safeguards Individual Audit (during implementation Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 10,000.00 0.00 2022-02-02 2022-02-25 2022-02-28 2022-03-07 2022-03-31 of WQ monitoring system); Basin-Wide Cooperation Implementation Selection national consultants - 9 countries (fee plus travel to site) UG-NBI-244490-CS-INDV / Activity 1.5.3.1: Individual Individual Consultant to prepare Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 8,250.00 0.00 2022-02-03 2022-02-25 2022-02-28 2022-03-08 2022-06-30 communication and Basin-Wide Cooperation Implementation Selection awareness raising products - up to 10 UG-NBI-244521-CS-INDV / Activity 5.3.1.2: Develop the Nile Basin river flow forecasting system: Component 1: Advancing Nile Pending TF / B4716 Post Direct Selection Direct 9,000.00 0.00 2022-04-05 2022-04-15 2022-06-08 2022-06-30 Consultancy firm to train Basin-Wide Cooperation Implementation trainers on NB-RFFS (2 experts from Nile-SEC); 5 days- (physical) UG-NBI-244529-CS-INDV / Individual Activity 6.1.4.1: Consultant to Component 1: Advancing Nile TF / B4716 Post Consultant Open 24,500.00 0.00 Under Review 2021-08-10 2021-08-25 2021-09-01 2021-09-06 2021-09-14 2021-09-30 formule NBI Capacity Basin-Wide Cooperation Selection development Strategy UG-NBI-244532-CS-INDV / Activity 6.1.4.2: A consultant Individual Component 1: Advancing Nile Pending to train NBI staff in TF / B4716 Post Consultant Open 9,000.00 0.00 2021-08-10 2021-08-31 2021-09-06 2021-09-13 2021-09-30 Basin-Wide Cooperation Implementation stakeholder engagement and Selection gender issues. UG-NBI-244624-CS-INDV / Activity 6.2.1.1: Training on negotiation skills (this will Individual Component 1: Advancing Nile Pending include training in topics such TF / B4716 Post Consultant Open 3,500.00 0.00 2021-08-12 2021-08-20 2021-08-24 2021-09-06 2021-10-14 Basin-Wide Cooperation Implementation as Hydro-diplomacy, Selection international law, negotiation, etc) UG-NBI-244712-CS-INDV / Activity C3.1.1.1a - Develop Individual NBI Corporate Communication Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 3,000.00 0.00 2021-08-10 2021-09-09 2021-09-15 2021-09-24 2022-09-23 Products: Regional Basin-Wide Cooperation Implementation Selection Consultant - French / English Translator (multiple reports) UG-NBI-244715-CS-INDV / Activity C3.1.1.2: Engage Individual Component 1: Advancing Nile Pending media in the Nile Basin: TF / B4716 Post Consultant Open 1,000.00 0.00 2021-10-01 2021-10-26 2021-10-29 2021-11-10 2021-12-15 Basin-Wide Cooperation Implementation Prepare journalists Selection sourcebook UG-NBI-244770-CS-INDV / Activity C4.1.1.1: Develop and operationalize the NBI Individual Component 1: Advancing Nile Pending integrated knowledge TF / B4716 Post Consultant Open 15,600.00 0.00 2021-09-08 2021-10-04 2021-10-08 2021-11-02 2021-12-15 Basin-Wide Cooperation Implementation platform: Prepare training Selection modules and train NBI IT staff on maintenance of IKP UG-NBI-244776-CS-INDV / Activity C4.1.1.1: Develop and operationalize the NBI Individual integrated knowledge Component 1: Advancing Nile Pending TF / B4716 Post Consultant Open 10,000.00 0.00 2022-05-02 2022-05-25 2022-05-30 2022-06-06 2022-06-30 platform: Consultant 1: Basin-Wide Cooperation Implementation Selection Support in periodic maintenance of the NBI-IKP (2022 – 2023) UG-NBI-244778-CS-INDV / Activity C4.1.1.1: Develop Individual Component 1: Advancing Nile Pending and operationalize the NBI TF / B4716 Post Consultant Open 3,000.00 0.00 2022-04-04 2022-04-26 2022-04-29 2022-05-09 2022-06-30 Basin-Wide Cooperation Implementation integrated knowledge Selection platform: Technical Editor UG-NBI-244819-CS-INDV / Individual Component 1: Advancing Nile Pending A consultant: Prepare BoQs / TF / B4716 Post Consultant Open 1,800.00 0.00 2021-08-02 2021-08-17 2021-08-20 2021-08-27 2021-09-30 Basin-Wide Cooperation Implementation supervision Selection UG-NBI-244993-CS-CDS / Dr. Kizza Michael: July 2021 - Component 1: Advancing Nile Pending TF / B4716 Post Direct Selection Direct 57,470.00 0.00 2021-07-22 2021-07-26 2021-07-30 2022-06-30 June 2020 56% salary funded Basin-Wide Cooperation Implementation by World Bank. Page 3 UG-NBI-244997-CS-CDS / Component 1: Advancing Nile Pending Dr. Modathir Zaroug : July TF / B4716 Post Direct Selection Direct 76,356.00 0.00 2021-07-22 2021-07-26 2021-07-30 2022-06-30 Basin-Wide Cooperation Implementation 2021 - June 2022 Salary. UG-NBI-244998-CS-INDV / Individual Component 1: Advancing Nile Water Quality Specialist: July TF / B4716 Post Consultant Open 62,720.00 0.00 Under Review 2021-07-26 2021-08-25 2021-09-13 2021-10-04 2021-11-08 2022-06-30 Basin-Wide Cooperation 2021 - June 2022 Salary Selection UG-NBI-245360-CS-CDS / Component 1: Advancing Nile Pending Mr. Tom Waako: Program TF / B4716 Post Direct Selection Direct 26,103.00 0.00 2021-07-26 2021-07-29 2021-08-31 2022-06-30 Basin-Wide Cooperation Implementation officer UG-NBI-245362-CS-CDS / Component 1: Advancing Nile Pending Ms. Maroushka Kanywani: TF / B4716 Post Direct Selection Direct 40,037.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Basin-Wide Cooperation Implementation Communications Specialist UG-NBI-245364-CS-CDS / Mr. Sowed Wamala: Component 1: Advancing Nile Pending TF / B4716 Post Direct Selection Direct 48,984.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Information Systems Specialist Basin-Wide Cooperation Implementation (ISS). UG-NBI-245366-CS-CDS / Ms. Juliet Nakasagga: Component 1: Advancing Nile Pending TF / B4716 Post Direct Selection Direct 16,413.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Librarian / Knowledge Basin-Wide Cooperation Implementation Management Officer UG-NBI-245371-CS-CDS / Component 1: Advancing Nile Pending Mr. Martin Mutua: Head of TF / B4716 Post Direct Selection Direct 8,733.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Basin-Wide Cooperation Implementation Corporate Services UG-NBI-245373-CS-CDS / Component 1: Advancing Nile Pending Ms. Edith Mbonye: TF / B4716 Post Direct Selection Direct 36,464.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Basin-Wide Cooperation Implementation Procurement Officer UG-NBI-245374-CS-CDS / Component 1: Advancing Nile Pending Mr. Patrick Rutagwera: IT TF / B4716 Post Direct Selection Direct 6,046.00 0.00 2021-07-26 2021-07-28 2021-07-30 2022-06-30 Basin-Wide Cooperation Implementation Officer UG-NBI-245376-CS-CDS / Component 1: Advancing Nile Pending Mr. Charles Mwine: TF / B4716 Post Direct Selection Direct 1,496.00 0.00 2021-07-26 2021-07-28 2021-09-02 2022-06-30 Basin-Wide Cooperation Implementation Administration/HR Officer UG-NBI-245367-CS-CDS / Component 1: Advancing Nile Pending Mr Challa: Earth Observation TF / B4716 Post Direct Selection Direct 75,264.00 0.00 2021-08-25 2021-09-04 2021-11-08 2022-06-30 Basin-Wide Cooperation Implementation & remote Sensing specialist UG-NBI-244804-CS-CDS / CS 2.1: Financial Management Component 1: Advancing Nile Pending TF / B4716 Post Direct Selection Direct 15,000.00 0.00 2021-08-26 2021-09-05 2021-09-16 2021-11-03 & Reporting: External audit Basin-Wide Cooperation Implementation consultant firm UG-NBI-244812-CS-CDS / CS 2.1: Financial Management Component 1: Advancing Nile Pending & Reporting: Consultant - TF / B4716 Post Direct Selection Direct 5,760.00 0.00 2021-07-23 2021-08-02 2021-08-13 2022-06-30 Basin-Wide Cooperation Implementation Maintenance Support Services and Annual License Renewal Page 4