SFG1730 v5 Transmission Company of Nigeria - Project Management Unit (TCN-PMU) Environmental and Social Impact Assessment (ESIA) For the Proposed 132/33kV Transmission Substation at Kabba, Kogi State Draft Final Report BY SMEC INTERNATIONAL (PTY) LIMITED March 2016 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 1 Contents 1 EXECUTIVE SUMMARY 17 1.1 Description of the Proposed Activities 17 Background to the Project 17 Details of Kabba (Kogi State) 17 1.2 Legal and Institutional Framework 18 Federal Ministry of Environment (FMEnv) ESIA Procedure 18 World Bank Standards 18 Dissimilar Standards 19 1.3 Preparation of the ESIA 19 Screening and Scoping 19 Primary Data 19 Secondary Data 19 1.4 Analysis of Alternatives Sites 19 1.5 Summary of Public Consultations 20 1.6 Measures to Address Concerns Raised by Stakeholders 20 Constraints Mapping and GIS 20 Health and Safety during Operation 20 Grievance Redress Mechanisms 21 1.7 Potential Adverse Impacts and Mitigation 21 Noise Levels 21 Climate Change 21 1.8 Positive Impacts 21 1.9 Matrix of Significant Impacts 22 1.10Proposed Mitigation Measures 22 Hiring of Local Labor 22 1.11The ESMP 23 Implementing ESMP 23 The CESMP 23 Cost of implementing ESMP. 24 Monitoring 24 1.12Decommissioning 25 1.13Going Beyond Compliance 25 1.14Capacity Building and Institutional Stengthrning 25 1.15Development of the Site 25 2 INTRODUCTION 26 2.1 Background 26 2.2 Location 26 2.3 Registration 27 2.4 ESIA Procedure 28 Federal Ministry of Environment (FMEnv) 28 World Bank 29 ESMP 29 2.5 Screening and Scoping 29 2.6 Primary Data 29 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 2 2.7 Secondary Data 29 2.8 Constraints Mapping and GIS 29 Constraints Mapping 29 High Definition Remote Sensing Imagery 30 Digital Terrain Mapping (DTM) 30 2.9 Layout of ESIA Report 30 Format of Report 30 Objective and Scope of the ESIA 30 3 LEGAL AND INSTITUTIONAL FRAMEWORK 31 3.1 Legal and Regulatory Requirements 31 Constitution of the Federal Republic of Nigeria (1999) 31 National Environmental Standards & Regulations Enforcement Agency (NESREA) 31 Nigerian Statutory Requirements 32 EIA requirements 32 Planning Requirements 32 Criminal Acts 33 ESIA regulatory requirements 33 EIA Procedure 33 3.2 International Conventions 35 3.3 World Bank Standards 35 OP/BP 4.01 Environmental Assessment 35 OP/BP 4. 12 – Involuntary Resettlement. 36 World Bank Environmental, Health, and Safety Guidelines (EHS) 36 3.4 Environmental and Social Management Framework (ESMF) 36 4 THE PROJECT 37 4.1 Project Description 37 4.2 Electricity Supply in Nigeria 37 Generation 37 Transmission 39 Distribution 40 4.3 Project Justification 40 4.4 The Project Proponent - TCN 46 4.5 Project Location - Kabba (Kogi State) 48 4.6 Role of Transformer Substations 49 Operation of a Substation 49 Function of Transformer Substations 50 Reactors 51 Local Control Kiosk 52 Equipment 53 4.7 Project Implementation 54 4.8 Alternatives 55 Renewable Energy 55 Transmission Alternatives 58 Site Alternatives 59 5 PRELIMINARIES 61 5.1 Screening 61 5.2 Kabba: Kogi State (North Central Nigeria) Reconnaissance Visit 61 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 3 5.3 Scoping 64 Notification 64 Comments from Stakeholders Consulted 64 Spatial boundary 64 Sampling Locations 64 Sampling Procedure 65 5.4 Primary Data Site Assessments 69 Field Sampling Program 69 Field Sampling Plan 69 5.5 Secondary Data 72 5.6 GIS Mapping 72 Constraints Mapping 72 GIS Ground Truthing 72 Kabba: Kogi State (North Central Nigeria) 72 Validation of GIS Data 73 Use of A0 Maps 73 6 THE ENVIRONMENT – KABBA 74 6.1 Baseline 74 6.2 Baseline Data Acquisition Methods 74 6.3 Study Location 74 6.4 Description of Sampling Locations 75 6.5 Spatial Boundary 77 6.6 Environmental Parameters 78 6.7 Quality Assurance / Quality Control 79 6.8 Physical 79 Climate 79 Rainfall 80 Temperature 80 Wind Speed/Direction 80 Relative Humidity 80 Air Quality Assessment 80 Field Work Meteorological Measurements 82 Noise Level Assessment 84 Land Use and Land Cover 87 Soils 87 Geology 89 Hydrology 90 Ground Water 90 Surface Water 92 Sediment 94 6.9 Biological 95 Vegetation 95 Wildlife 99 Soil Fauna 100 6.10Social Indicators 100 Health Status Assessment 100 Socio-Economic Characteristics 101 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 4 History and Culture 104 Governance 105 6.11Community Consultations 106 Consultations 106 The Stakeholders Concerns 106 6.12GIS Data 108 7 CLIMATE CHANGE 114 7.1 Historical Data 114 7.2 Climate Change Projections 116 8 IMPACTS DUE TO LOCATION 119 8.1 General Location 119 8.2 Cultural and Historical Resources 119 8.3 Land Use and Habitat Loss 119 8.4 Public Safety 119 8.5 Storage of Hazardous Materials 120 8.6 Threatened, Endangered, or Rare Species 120 8.7 Wetlands/Waterways 120 8.8 Drainage 120 8.9 Site Access 120 8.10Involuntary Resettlement 120 8.11Potential Positive Socio-economic Impacts 120 8.12Key Aspects 121 9 IMPACTS DUE TO PROJECT DESIGN 122 9.1 Noise 122 Noise Sources 122 Transformer Specifications 122 Near Field and Far Field 123 Noise Level Variation with Load Capacity 124 IEC 60076 125 Noise Measurements, Abuja 126 Results of Noise Measurements 126 Analysis of Noise Measurements 128 Impact of Noise Levels 128 Corona Discharge 130 9.2 Electromagnetic Fields (EMF) 130 Sources of EMF 130 Induced Effects 133 Earthing 133 Screening 133 EMF and Health 133 9.3 Chemical Hazards 135 Hazardous Materials Storage 135 PCBs 136 10 IMPACTS DUE TO CONSTRUCTION WORKS 137 10.1Air Quality 137 Impacts 137 Mitigation 137 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 5 10.2 Water Quality 138 Impacts 138 Mitigation 138 10.3Solid and Liquid Waste 139 Impacts 139 Mitigation 139 10.4Noise 140 Impacts 140 Mitigation 142 10.5Fauna 144 Impacts 144 Mitigation 144 10.6Flora 144 Impacts 144 Mitigation 145 10.7Cultural Resources 145 Impacts 145 Mitigation 145 10.8Occupational Health and Safety 145 Impacts 145 Mitigation 145 10.9 Community 146 Impact 146 Mitigation 146 10.10 Pedestrian Road Safety 146 Impacts 146 Mitigation 146 10.11 Utilities Provision 147 Impacts 147 Mitigation 147 10.12 General House keeping 147 Impacts 147 Mitigation 147 10.13 Potential Socio-economic Benefits 147 Impacts 147 Mitigation 148 11 IMPACTS DUE TO COMMISSIONING PHASE 149 11.1Commissioning Activities 149 11.2Spill Control 150 11.3Fires 150 12 IMPACTS DUE TO OPERATION 151 12.1Air Quality 151 12.2Electro-Magnetic Fields (EMF) 151 12.3Electrical and Magnetic Fields Safety 151 Overhead Electrical Safety 151 Ground-Level Electrical Safety 151 Underground-Level Electrical Safety 152 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 6 12.4Vegetation Management 152 12.5Pesticides 152 12.6Migratory Birds 152 12.7Noise 152 1 2 . 8 Visual Appearance 152 12.9Spills 153 12.10 Fires 153 12.11 HSE 153 Tool box briefings 153 Near Misses 154 Induction Briefings 154 NERC 155 Corrective Action Reporting (CAR) 155 13 IMPACTS DUE TO DECOMMISSIONING 156 13.1Impacts 156 13.2Mitigation 156 14 ESMP - ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 157 14.1Impacts and Mitigation 157 14.2Environmental Management & Monitoring 157 14.3EMP Environmental Management Plan 158 14.4CESMP Contractors Environmental Social Management Plan 158 14.5Pre-Construction Phase 158 Permits and Plans 158 Contractor Management Plans. 159 14.6Construction Phase 160 Air Quality Impacts 160 14.7Water Quality 161 Water Quality and Drainage 161 14.8Solid and Liquid Wastes 161 Workers Camps 161 Construction and Domestic Waste 162 Excavation Spoils 162 Use of Hazardous Substances 163 Fuel Storage and Vehicle Maintenance 163 Waste Oil 165 Bitumen Use for Asphalt for Approach Roads 165 14.9Noise 165 Noise and Vibration Impacts 165 Blasting 166 Quarry and Borrow Sites 167 14.10 Flora and Fauna 167 14.11 Damage to Culturally Significant Areas 168 14.12 Occupational Health and Safety 168 14.13 Community 169 Social Conflicts 169 Damage to Community Facilities 169 Complaints Mechanism 170 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 7 14.14 Traffic Disruption and Access Obstruction 170 14.15 Utilities 170 14.16 General House Keeping 170 14.17 Positive Impacts 171 14.18 Operation Phase 171 NERC HSE Standards 171 14.19 Air Quality 171 14.20 Electro-Magnetic Fields (EMF) 172 14.21 Electrical and Magnetic Fields Safety 172 Overhead Electrical Safety 172 Ground-Level Electrical Safety 172 Underground-Level Electrical Safety 173 14.22 Vegetation Management 173 14.23 Pesticides 173 14.24 Migratory Birds 173 14.25 Noise 173 14.26 Visual Appearance 173 14.27 Spills 173 14.28 Fires 174 14.29 HSE 174 Tool box briefings 174 Near Misses 174 Induction Briefings 175 NERC 176 Corrective Action Reporting (CAR) 176 14.30 Decommissioning Phase 176 14.31 Environmental Social Management Plan 177 14.32 Costs of Implementing the ESMP 198 14.33 Environmental Monitoring 199 Measurements 199 Timing of Monitoring 200 Beyond Compliance 201 14.34 Grievance Redress Mechanism 204 14.35 Corrective Action Reporting 205 14.36 Institutional Roles and Responsibilities 206 Institutional Arrangements 206 Federal Ministry of Environment 206 TCN management 206 TCN-PMU & ERSU-PMU 206 TCN on-site personnel 207 The Supervising Engineer 207 Construction Contractor 207 World Bank 208 Plant Operator 208 15 PUBLIC CONSULTATION 209 15.1Consultation with Stakeholders 209 15.2Interagency 209 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 8 15.3Kabba, Kogi 210 16 CONCLUSIONS 211 16.1Potentially Adverse Impacts and Mitigation 211 Noise Levels 211 Climate Change 211 16.2Positive Impacts 211 16.3Matrix of Significant Impacts 211 16.4Development of the Site 212 17 ANNEXES 213 17.1Annex 1 Environmental Regulations Gazetted 213 17.2Annex 2 Field Sampling and Analysis Plan (FSAP) 215 Materials And Methods 215 Sample Collection and Handling 215 Sample identification 215 Storage/Preservation 216 Fieldwork 216 Chain of samples custody procedure 220 Evaluation of results 220 17.3Annex 3 Secondary Data 234 17.4Annex 4 Public Consultation Kabba 240 17.5Annex 5 Measuring Transformer Noise IEC 60076 245 17.6Annex 6 GENERIC SAMPLE OF C-ESMP 248 17.7Annex 7 EXAMPLE OF C-ESMP . . 249 17.8Annex 8 Generic Decommissioning Plan 303 Reason For Plan 303 Potential Impacts 303 Generic Plan 303 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 9 Figures Figure 1-1 Nigeria and Site Locations : Kano, Gombe, Enugu and Kabba 17 Figure 1-2 Kogi State Kabba/Bunu LGA 18 Figure 1-3 Matrix of Significant Impacts 22 Figure 2-1 Nigeria 26 Figure 2-2 Nigeria and Site Locations : Kano, Gombe, Enugu and Kabba 28 Figure 3-1 FMEnv ESIA Procedure 2015 34 Figure 4-1 Generation, Transmission, Distribution and Consumers 38 Figure 4-2 High Voltage Transmission Towers 39 Figure 4-3 Step Down Transformer Station 40 Figure 4-4 Nigeria Populations in Millions 41 Figure 4-5 Nigeria GDP per capita in Thousands of Dollars 42 Figure 4-6 Nigeria Electricity Production 43 Figure 4-7 Electricity Consumption 44 Figure 4-8 Power Generation in Nigeria 45 Figure 4-9 Existing Power Transmission in Nigeria 47 Figure 4-10 Proposed Power Transmission in Nigeria 48 Figure 4-11 Kogi State Kabba/Bunu LGA 49 Figure 4-12 Elements of a substation 51 Figure 4-13 Substation Transformers 52 Figure 4-14 Wind Turbines and Solar Panels 56 Figure 4-15 Geothermal Plant and Landfill Gas Extraction 57 Figure 5-1 Stakeholders at the proposed project site 62 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 10 Figure 5-2 Discussions at the Proposed Project site 62 Figure 5-3 sloping topography of proposed project site 62 Figure 5-4 Road beside proposed project site 62 Figure 5-5 Stakeholders guided to Proposed project site 63 Figure 5-6 Survey beacon on the Proposed Site 63 Figure 5-7 Site visit with LGA Officials showing rocky lateritic soils and distant buildings 73 Figure 6-1 Administrative Map of Kogi State Showing Kabba/Bonu LGA 75 Figure 6-2 Sampling Map 76 Figure 6-3 Satellite Imagery of Proposed Project site 78 Figure 6-4 Land Cover of Proposed Project Area 87 Figure 6-5 Toolbox meeting before commencement of sampling 87 Figure 6-6 Geotechnical and soil sampling 87 Figure 6-7 Biophysical sampling at Site 89 Figure 6-8 Briefing session with LG Chairman 89 Figure 6-9 Bridge over river sampled for control 94 Figure 6-10 Erosion control point along river 94 Figure 6-11 Tree/shrub specie richness 97 Figure 6-12 Herbaceous species richness 98 Figure 6-13 Occupation Distribution 102 Figure 6-14 Sawmill 102 Figure 6-15 small scale businesses 102 Figure 6-16 Market stall 102 Figure 6-17 Motorbike transportation 102 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 11 Figure 6-18 Income Distribution in Percentage 103 Figure 6-19 Age Distribution 104 Figure 6-20 Symbolic Hills in Kabba-Bunu 105 Figure 6-21 Obaro of Kabba addressing the ESIA team 105 Figure 6-22 Briefing of HRH 106 Figure 6-23 Social science team with HRH 106 Figure 6-24 Community perception of project 107 Figure 6-25 Anticipated Impact of the Proposed Project 107 Figure 6-26 Dimensions of site with nearest development 109 Figure 6-27 Location of site relative to 2 kms and 4kms effects. 110 Figure 6-28 Composite map showing 10m contours and features 111 Figure 6-29 Terrain map showing gradient 112 Figure 6-30 Watershed map showing catchment and flow direction 113 Figure 7-1 Average Monthly Temperature and Rainfall for Nigeria 1900-2009 114 Figure 7-2 Change in Rainfall for Nigeria 1905-2009 115 Figure 7-3 Vegetation Map of Nigeria 116 Figure 7-4 Projected Mean Rainfall 2046-2065 117 Figure 7-5 Projected Maximum Temperatures across Nigeria 117 Figure 7-6 Projected Liability to Flood and Drought 118 Figure 9-1 Typical noise levels of a Siemens 420 MVA transformer 124 Figure 9-2 Sound Pressure Level with Power Rating at 0.3m 125 Figure 9-3 Noise measurements at Katampe, Abuja on Sound Level Meter 126 Figure 9-4 Noise measurements at Katampe Abuja 127 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 12 Figure 9-5 Noise measurements at Katampe, Abuja 127 Figure 9-6 Magnetic Field Strenght Below Power Line 132 Figure 9-7 Recommended Magnetic Fields at Different Location 132 Figure 12-1 Examples of Near Misses - Gas cylinders incorrectly stored and handled 154 Figure 12-2 Examples of Near Misses - Gas cylinders correctly stored and handled 154 Figure 14-1 Spill Protection for Fuel Oil Storage / Rain Proofing for Waste Oil Storage 164 Figure 14-2 Examples of Near Misses - Gas cylinders incorrectly stored and handled 175 Figure 14-3 Examples of Near Misses - Gas cylinders correctly stored and handled 175 Figure 14-4: Complaints Investigations Procedure 205 Figure 14-5: Corrective Action Reporting (CAR) Procedure 206 Figure 16-1 Matrix of Significant Impacts 212 Figure 17-1 Typical Transformer 245 Figure 17-2 Typical description of transformer 245 Figure 17-3 Measuring Positions for one transformer 246 Figure 17-4 Measuring positions for group of transformers 247 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 13 Tables Table 3-1 International Environmental Agreements 35 Table 4-1 Sub-station Works 54 Table 4-2 Cost Ratio of U/G cable to O/H Line 59 Table 5-1 Schedule of Reconnaissance visit 61 Table 5-2 Screening Results 63 Table 5-3 Sampling Locations 64 Table 5-4 Sampling Specifications 65 Table 5-5 Environmental Components and Indices for Biophysical Baseline Assessment 66 Table 5-6 Field Sampling Program 69 Table 5-7 Field Sampling and Analysis Plan (FSAP) 70 Table 6-1 Geographical Reference of Biophysical Sampling Stations 76 Table 6-2 Study Communities 78 Table 6-3 Air Quality Measurements 81 Table 6-4 Prevailing Meteorological Conditions 83 Table 6-5 Noise Level Measurements 85 Table 6-6 Maximum Permissible Noise Levels for General Environment 86 Table 6-7 IFC Noise Limits 86 Table 6-8 Soil Characteristics 88 Table 6-9 Groundwater Analysis 90 Table 6-10 Surface Water Analysis 92 Table 6-11 Physico-Chemical Parameters Sediment Samples 95 Table 6-12 Tree/shrub species composition 96 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 14 Table 6-13 Herbaceous species composition 97 Table 6-14 Food crop composition 98 Table 6-15 Plant Diseases Symptoms and Isolated Pathogens of Some Disease 99 Table 6-16 Wildlife Composition 100 Table 6-17 Disease Prevalence 100 Table 9-1 Noise Levels of 150 MVA Transformer from TCN BOQ 122 Table 9-2 Sound Attenuation with Distance 128 Table 9-3 IFC Guidelines 129 Table 9-4 Maximum Permissible Noise Levels for General Environment 129 Table 10-1 Construction Machinery Noise 141 Table 10-2 Sound attenuation with Distance 141 Table 14-1 Environmental Impacts and Mitigation Measures 178 Table 14-2: Costs of Implementing the ESMP 198 Table 14-2: Measurement of Environmental Parameters during Construction 202 Table 17-1 Generic Decommissioning Plan 303 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 15 Acronyms BOD Bio-Chemical Oxygen Demand CAR Corrective Action Reporting COD Chemical Oxygen Demand CSC Construction Supervision Consultants dB(A) Decibels “A” weighted EHS Environment Health and Safety EHSO Environment Health & Safety Officer ELF Extremely Low Frequency EMF Electro-Magnetic Force ESIA Environmental and Social Impact Assessment ESMP Environmental and Social Impact Management Plan FMEnv Federal Ministry of Environment Nigeria GIS Geographical Information System GPS Global Positioning System GRM Grievance Redress Mechanism PM Particulate Matter PMU Project Management Unit TCN Transmission Company Nigeria WB World Bank Weights and Measures dB – decibel Km – kilometer dB(A) (‘A’-weighing = correction factor that weights sound to reflect sensitivity of the human ear) m meter ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 16 1 Executive Summary 1.1 Description of the Proposed Activities Background to the Project The Federal Government of Nigeria is taking steps to improve the quality and reliability of electricity supply while ensuring sustainability of the power provision industry. By bridging the gap between the available electricity supply, and the demand required for industry, commercial businesses and homes, the project will support domestic economic development, improve lifestyles, provide revenue for government and create employment opportunities in the target states. There are also ongoing discussions with neighboring countries on the foreign export and import of electricity in the future. The Government received funds from the World Bank for the implementation of Nigeria Electricity and Gas Improvement Project. (NEGIP). Some of this financing is allocated to the Transmission Company of Nigeria (TCN) for the construction of four proposed transmission substations at New Kano in Kano State, Biliri in Gombe State, Kabba in Kogi State, and Abor (9th Mile) in Enugu State. TCN is proposing 330/132kV transmission substations at New Kano and 132/33kV transmission substations at Kabba, Biliri and Abor (9th Mile) respectively. However, this ESIA refers only to Kabba in Kogi State. The physical location of the proposed project site is shown below. Figure 1-1 Nigeria and Site Location: Kabba This project will be carried out on unoccupied land designated “greenfield” site. Details of Kabba (Kogi State) The proposed 132/33kV Transmission Substation is to be situated along Kabba – Okene express way, Kogi State in the North- Central Nigeria. The land arises from 300meters along the Niger-Benue confluence, to the height of between 300 and 600 meters above sea level in the uplands, Kogi State is ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 17 drained by the Niger and Benue rivers and their tributaries. Figure 1-2 Kogi State Kabba/Bunu LGA 1.2 Legal and Institutional Framework Federal Ministry of Environment (FMEnv) ESIA Procedure The EIA Act 86 (1992) makes EIA mandatory for development projects likely to have adverse impacts on the environment. The EIA must be prepared and approved prior to implementation. The project was submitted for registration with the Federal Ministry of Environment. The FMEnv EIA process has recently been updated and this ESIA complies with these requirements. World Bank Standards The project comes under World Bank’s Operation Policies. The project triggered OP/BP 4.01 Environmental Assessment and OP/BP 4. 12 – Involuntary Resettlement. These procedures have been followed in the preparation of this ESIA. In terms of involuntary resettlement it was esablished that there were no person found to be resident on or around the immediate vicinity of the proposed site. Some informal growing of crops was taking place for which compensation has been paid. Other than this there are no resettlement issues. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 18 Dissimilar Standards When host country regulations differ from the levels and measures presented in the World Bank Operation Policies, projects will be required to achieve whichever is more stringent. This also applies if there is a difference between Federal and State standards. The standard which is more strict must be followed. 1.3 Preparation of the ESIA Screening and Scoping A preliminary part of the ESIA process is screening and scoping of the proposed transmission substation site at Kabba for potential adverse environmental and social impacts. This exercise was carried out and defined the scope and depth of the technical issues to be addressed during the preparation of the ESIA. The site reconnaissance for this process was completed and the conclusions confirmed by FMEnv. Primary Data Following Screening and Scoping, primary data was obtained by taking samples from the site for subsequent analysis and by taking direct measurements. The site visits were made in August and September 2015.The results were compared with National and International standards and this established the baseline conditions on the sites before any activities commence. The baseline is used to assess the impacts of project activities on the surroundings. Also if at some time in the future the sites are decommissioned then the sites must be returned to their original condition. The baseline establishes the nature of that condition. Secondary Data In addition to primary data collected by the consultants, secondary data were also obtained from other agencies. These included meteorological information or previous environmental reports in similar locations. These were identified during the literature review. 1.4 Analysis of Alternatives Sites The “do-nothing” option had been considered and discarded because there is an urgent need for more power to be supplied to this area. This opinion was expressed strongly by the residents in the public consultations. TCN specified the general area where the substation was to be located based on the proximity to high voltage transmission lines and the necessary size of the substations. This information was passed to the state government who reviewed possibilities, consulted with landowners, and arrived at a decision on the site which was then conveyed to TCN. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 19 TCN did not examine alternative sites because the sites were identified and made available by the state government. As the site was suitable TCN accepted the proposed location. The State Government then transferred to TCN the Site Plan, Survey Plan and Change of Ownership letters. This transaction was confirmed through the various community stakeholders meetings subsequently organised by TCN. Consequently, all negotiations and payments of compensation were carried out by the State Government and the site handed over to TCN free of all encumbrances. 1.5 Summary of Public Consultations Extensive public consultations took place. During Screening and Scoping on-site discussions were held with stakeholders such as local land owners and residents. During primary data collection to establish the baseline social conditions interviews and Focus Group Discussions were conducted. Following this meetings were held in an open forum. An Inter-agency Meeting was held in Abuja and a stakeholder consultation was held in Kabba, Kogi State. These were announced well in advance with formal invitations being sent out and and newspaper adverts published in two newspapers. The attendance was high with over 100 people attending each group. In general the attendees were in favor of the project proceeding and requested commencement of implementation to be accelerated. In general all residents were supportive of the project and saw positive outcomes. 1.6 Measures to Address Concerns Raised by Stakeholders Constraints Mapping and GIS In accordance with FMEnv requirements the spatial boundaries of the study are 2kms for bio-physical impacts and 4 kms for socio-economic impacts. These are reflected in the boundaries of the constraint mapping. Anything beyond 4kms is considered to be outside the zone of influence of the project. High definition remote sensing satellite imagery was obtained for the site. Digital Terrain maps were obtained for the site location. DTM files are three dimensional and include vertical height data embedded in the file. These were used directly for determining catchment areas. Health and Safety during Operation The strength of both electric and magnetic fields is a function of the voltage, distance from the conductors to the ground and the lateral distance from the line to the receptor. It is also a function of frequency. High frequencies radiate much higher emissions than low frequencies. Transmission lines operate at 50Hz which regarded as Ultra Low Frequency. Although there have been many studies published on occupational exposure to Electro-Magnetic Fields (EMF) no clear evidence exists to show that residential exposures to electric and magnetic fields at mains ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 20 frequency are a threat to human health. The Operational ESMP contains details on Health and Safety procedures to be followed by staff and operators to avoid the hazards of electrocution. This is TCN Standard Operating Procedure. Grievance Redress Mechanisms The public consultations showed that there is already a strong communications pathway between TCN and the local communities and this should continue to be used as a basis for the Grievance Redress Mechanism (GRM) which will be set up for the site. In the Construction Phase the contractor will be require to establish a GRM immediately upon occupation of the site. Staff will be designated to respond to complaints on a 24/7 basis and their contact details will be advertised on signboards around the site. During operation TCN will also establish a GRM as part of their ongoing Corporate Social Responsibility program. 1.7 Potential Adverse Impacts and Mitigation Noise Levels The Nigeria National Environmental Noise Standards and Control Regulation (2009) require noise levels of 50dB(A) Leq(12 hours) during the daytime and 35 dB(A) Leq(12 hours) during nighttime at the perimeter of the site to preclude noise nuisance to residential property that may be built adjacent to the site in the future. Based on the Technical Specification for transformers and measured noise levels, it is recommended that transformers should not be located within 80m of the boundary of the site. This is a worst case scenario. Following this recommendation would ensure no complaints over noise intrusion both during the night time and during daytime during operation. It also allows a margin for intensification of use in the future. Climate Change Climate change projections show that there will be significant differences between sites in the north and sites in the south, with the north being more subject to droughts and the south being more subject to floods. This may impact on the demand load imposed on the transmission system but will not impact on the site of this project 1.8 Positive Impacts  The proposed projects will provide short term, local employment opportunities during the construction phase for community members in terms of; site clearance, excavation, loading and offloading of materials. Other short term opportunities may arise from the provision of security services where temporary camps or stores are erected and from opportunities to provide goods and services to construction workers e.g. food kiosks and other shops. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 21  The long term impact is provision of power to the area with associated improvement in standard of living and economic development.  All new transformers are specified as being free of PCBs. No PCBs will be present on the sites and there is no need for concern on this issue. 1.9 Matrix of Significant Impacts The Matrix of Significant Impacts is given below. This site is one of four under consideration for project development. The matrix refers to all four although this ESIA refers only to Kabba. No key issues have been identified that will preclude the development of the site as intended. ENVIRONMENTAL IMPACTS Kabba Construction Operations Water Quality √ √ Flooding fromsleep gradient √√√ √ Soil Contamination from spills √√ √√ Physical Air Quality √ X Waste solid and liquid √ √ Noise √ √ Visual impact √ X Fauna √√ X Biological Flora √√ X Resetlement X X Cultural X X Socio Economic Occupational Health and Safety √√√ √√√ Community √√ X Utilities √ X None X Minor √ Moderate √√ Significant √√√ Figure 1-3 Matrix of Significant Impacts 1.10 Proposed Mitigation Measures Hiring of Local Labor Several stakeholders expressed concerns over bringing in foreign labor during construction. The contractor will be required to give preference to local labor when hiring his workforce. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 22 1.11 The ESMP Implementing ESMP This ESIA contains an ESMP as an integral chapter. The ESMP covers preconstruction, construction, commissioning, operation and decommissioning. This ESMP is written as a stand-alone document. It can be extracted and used as an independent guide. The ESMP will be the guiding document for environmental management and monitoring during construction and operation of the project. 1.11.1.1 Construction The ESMP will guide TCN in determining whether the contractor is following the recommended mitigation measures prior to site occupancy and during construction. TCN will issue the ESMP in the tender documents. The responsibility for Environmental Management and Monitoring during project construction lies with the main contractor and his sub-contractors. TCN will appoint a Construction Supervision Consultant (CSC) to supervise the contractor. The CSC inspectors will check that the contractor is complying with the ESMP. Failure to do so will be brought to the contractors attention in monthly progress meetings. TCN will comply monthly reports and report 6 monthly on EHS issues to World Bank. Annual reports on EHS will be submitted to FMEnv. 1.11.1.2 Operation During operation it is essential to ensure that the environmental requirements stipulated in the ESMP are being implemented effectively. TCN will comply monthly reports and report 6 monthly on EHS issues to World Bank. Annual reports on EHS will be submitted to FMEnv. In addition the TCN in-house Environment Health and Safety staff will carrry out Environmental Audits every three years on the installation. These redults will be forwarded to FMEnv. In the event of non compliance with the legislation FMEnv will require TCN to rectify the situation as soon as reasonably possible. The CESMP The ESMP is of necessity a general document. The contractor must prepare a detailed EMP giving site specific details of construction activities. This is a Contractor Environmental Social Management Plan (CESMP). This must be done within one (1) month of contract signing. The CESMP must be submitted and approved before construction activity may commence. A CESMP is a dynamic document and may be changed and updated at any time during implementation of the Project. Environmental monitoring results shall be documented and reviewed at least monthly to ensure that signs of adverse impacts are detected at an early stage and that actions for mitigation are taken. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 23 Compliance with the ESMP is contractually binding. Failure by the contractor to comply with the EMP may result in financial penalties. A generic sample is given in Annex 6 and an example of a CESMP is given in Annex 7. Cost of implementing ESMP. The main part of the ESMP relates to construction which will be by a contractor. The ESMP is to be included in the Tender Documents against which the contractor will submit a bid. All contractors bidding for the project must include costs for environmental management in their bid price. Construction - The cost to the contractor of meeting the requirements of the ESMP should be included in the tender as a budget line. The contractor must demonstrate that he is implementing the measures such as spill control, control of run off and stormwater, drainage, stockpile of materials, storage of fuels and health and safety issues such as issuing of PPE (Personal Protective Equipment) such as high vis jackets, safety helmets, and boots, and also ear plugs goggles, if required. This will equate to about $150,000. Operationally -The baseline should be repeated every three years in accordance with TCN Standard Practices for Environmental Audits. The cost of this is estimated to be $40,000. Details of cost calculation are given in Section 14.32 Monitoring Monitoring should be carried out on a regular basis. The following list is for guidance and is indicative only. More regular monitoring or spot checks may be required in response to a complaint.  Liquid emissions from sites must be checked every three months or after heavy rain if overflowing is reported. Measurements in streams and water courses must be made.  Grondwater monitoring wells should be established and checked at least annually. (A minimum of one upstream and one downstream of the site is recommended). Samples hould be checked for heavy metals and organics.  Dust emissions on site must be checked weekly by visual inspection and monthly by examining records of water spraying. Ambient air quality must be checked over a 24 hour continuous period at sensitive receptors in the event of complaints.  Noise levels must be checked every three months at site perimeters, or in the event of a complaint, at night as well as during the daytime.  Correct removal and disposal of food waste and waste engine oil and grease must be checked weekly by visual inspection of the camps and checking of records from the waste disposal contractors.  Noise and vibration must be checked at sensitive receptors when blasting first occurs or in the event of complaint. Before blasting commences warning notices must be posted to local residents.  Reinstatement of borrow pits and quarries must be checked after closure of the facility. In addition to regular monitoring, unannounced spot checks must be made by TCN-PMU on contractors ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 24 operations. All of the above procedures should be carried out by the site CSC inspectors, in conjunction with PMU, and where appropriate FMEnv. The results should be formally recorded every week and compiled into a monthly report. This should be submitted to TCN and the contractors as necessary but at a minimum on a monthly basis. Monthly reports should be compiled into quarterly and annual reports to be submitted to WB. 1.12 Decommissioning At some point in the future the site may be decommissioned. At such a time the baseline environmental survey and analysis should be repeated to ensure that no deterioration in soil or groundwater conditions has occurred. Prior to decommissioning, a decommissioning plan will be prepared, according to final monitoring and the decomissioning impacts listed in Table 14.1. Generic Decommissioning plan is given as a guide in Annex 7. Although closure of the site is unlikely, it is conceivable that transfer of ownership of the site may occur, in the event of say, privatisation. In that event the new owner will insist on a Due Diligence and a lack of reliable data on site conditions may jeopardise the transaction. 1.13 Going Beyond Compliance It will be necessary to carry out measurements to establish if the regulations are being met. In fact, simple compliance with the standards is not necessarily the final objective. There is no harm in the contractor or the operator “going beyond compliance” and running an operation better than that required by the FMEnv and World Bank standards. This is the CSR objective of TCN. 1.14 Capacity Building and Institutional Stengthrning In order to implement the project various stakeholders will have a part to play. Their roles and responsibilities as well as appropriate capacity building is discussed in Section 14.37 1.15 Development of the Site No key issues have been identified that will preclude the development of the sites as intended. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 25 2 Introduction 2.1 Background The Federal Government of Nigeria is taking steps to improve the quality and reliability of electricity supply while ensuring sustainability of the power provision industry. By bridging the gap between the available electricity supply, and the demand required for industry, commercial businesses and homes, the project will support domestic economic development, improve lifestyles, provide revenue for government and create employment opportunities in the target states. There are also ongoing discussions with neighboring countries on the foreign export and import of electricity in the future. 2.2 Location Nigeria is located in western Africa on the Gulf of Guinea andoccupies a total area of 923,768 km2 making it the world's 32nd-largest country. It has a 4,047km border which it shares with Benin (773 km), Niger (1497 km), Chad (87 km), Cameroon (1690 km), and it has a coastline of 853 km. Nigeria lies between latitudes 4°and 14°N, and longitudes 2° and 15°E. Figure 2-1 Nigeria Nigeria has a varied landscape. The far south is defined by its tropical rainforest climate, where annual rainfall is 1,500 to 2,000 mm a year. Coastal plains are found in both the southwest and the southeast. This forest zone's most southerly portion is defined as "salt water swamp," or mangrove swamp. North ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 26 of this is fresh water swamp, with different vegetation and north of that is rain forest. 1 The highest point in Nigeria is Chappal Waddi at 2,419 m. The main rivers are the Niger and the Benue which converge and empty into the Niger Delta. This is one of the world's largest river deltas, and the location of a large area of Central African mangroves. To the southwest of the Niger is highland. To the southeast of the Benue are hills and mountains, which form the Mambilla Plateau, the highest plateau in Nigeria. This plateau extends through the border with Cameroon.2 The area near the border with Cameroon close to the coast is rich rainforest and part of the Cross- Sanaga-Bioko coastal forests ecoregion, an area with high biodiversity. Most of Nigeria is savannah with insignificant tree cover, grasses and flowers. Rainfall is limited to between 500 and 1,500 millimetres per year. The savannah zone's three categories are Guinean forest-savanna mosaic, Sudan savannah, and Sahel savannah. Guinean forest-savanna mosaic is plains of tall grass interrupted by trees. Sudan savannah is similar but with shorter grasses and shorter trees. Sahel savannah consists of patches of grass and sand, found in the northeast. In the dry north-east corner of the country lies Lake Chad, which Nigeria shares with Niger, Chad and Cameroon. 3 2.3 Registration The Government received an additional credit from the International Development Association (IDA) under the World Bank for the implementation of Nigeria Electricity and Gas Improvement Project. (NEGIP). Some of this financing is allocated to the Transmission Company of Nigeria (TCN) for the construction of four proposed transmission substations at New Kano in Kano State, Biliri in Gombe State, Kabba in Kogi State, and Abor (9th Mile) in Enugu State. However, this ESIA refers only to Kabba in Kogi State. 1 http://geography.about.com/library/cia/blcnigeria.htm 2 Ibid 3 Ibid ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 27 The physical location of the proposed project site is shown below. 4 . Figure 2-2 Nigeria and Site Location: Kabba This project will be carried out on unoccupied land designated “greenfield” site. The project has been submitted for registration with the Federal Ministry of Environment. 2.4 ESIA Procedure Federal Ministry of Environment (FMEnv) The offices of the FMEnv in Abuja were visited by the Team Leader and helpful and cooperative discussions held. The EIA process has been updated and this ESIA complies with these requirements. 4 TCN PMU TOR ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 28 World Bank This project is financed by World Bank and they have their own Due Process for Environmental and Social Assessment. These procedures have been followed and are discussed in Chapter 2. ESMP This Environmental and Social Assessment contains an ESMP as an integral chapter. The ESMP can be extracted and used as a stand-alone document when appointing contractors. Details are given in Chapter 16. 2.5 Screening and Scoping A preliminary part of the ESIA process is screening and scoping of the proposed 132/33kV transmission substations at Kabba for potential adverse environmental and social impacts. This exercise defines the scope and depth of the technical issues to be addressed during the preparation of the ESIA and these are subject to confirmation by FMEnv. This requires site reconnaissance and this process was completed. 2.6 Primary Data Primary data was obtained by taking samples from the sites for subsequent analysis and taking measurements. The results were compared with National and International standards and this established the baseline conditions on the sites before any activity commences. The baseline is used to assess the impacts of project activities on the surroundings. Also if at some time in the future the sites are decommissioned then the sites must be returned to their original condition. The baseline establishes the nature of that condition. The site visits were made in August and September 2015. 2.7 Secondary Data In addition to primary data collected by the consultants secondary data were also collected. these were obtained from other agencies such as meteorological information, as is regularly collected by airports, or previous environmental reports in similar locations. These were identified during the literature review. The consultants have been involved in many previous studies and material gathered in these activities was accessed and used when relevant. 2.8 Constraints Mapping and GIS Constraints Mapping In accordance with FMEnv requirements the spatial boundaries of the study are 2kms for bio-physical impacts and 4 kms for socio-economic impacts. These are reflected in the boundaries of the constraint mapping. Anything beyond 4kms is considered to be outside the zone of influence of the project. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 29 High Definition Remote Sensing Imagery The consultants have obtained high definition remote sensing satellite imagery for the site. The information is stored in layered PDF files so that specific details such as roads, rivers etc can be switched in and out. This makes identifying impacts simpler. These maps have also been printed up in A0 size for illustrative use in public consultations. Full details are given in Chapter 17. Digital Terrain Mapping (DTM) The consultants are obtaining Digital Terrain maps for the site location. Standard topographical maps printed on paper are two dimensional and give height data by numbers on the maps. DTM files are three dimensional and include vertical height data embedded in the file. They can be used directly for determining catchment areas and calculating rainfall run off. 2.9 Layout of ESIA Report Format of Report The format of the report is in accordance with the requirements of FMEnv ESIA Procedure and World Bank OP4.01. Objective and Scope of the ESIA The objectives of the study are to prepare ESIAs and ESMPs for each of the proposed substations. The scope of services includes the following key steps:  Project Definition  Project registration  Project Description  Environment description  Impact assessment  Analysis of Alternatives  Environmental and Social Impact Assessment (ESIA)  Environmental and Social Management Plans (ESMPs)  Stakeholder consultation  Monitoring plan  Quality assurance and quality control These steps have all been completed and are described in this document. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 30 3 Legal and Institutional Framework The following sections give details on the legal and institutional framework within which the ESIA has been prepared. 3.1 Legal and Regulatory Requirements The ESIA is prepared in accordance with the current legal regime and regulatory framework. The ESIA complies with all existing legislation but also takes cognizance of any forthcoming regulatory requirements that may be related to the project development and operation. Constitution of the Federal Republic of Nigeria (1999) The constitution recognizes the importance of improving and protecting the environment and makes provision for this. Relevant sections are:  Section 20 makes it an objective of the Nigerian State to improve and protect the air, land, water, forest and wildlife of Nigeria.  Section 12 establishes that international environmental treaties ratified by the National Assembly should be implemented as law in Nigeria.  Section 33 and 34 which guarantee fundamental human rights to life and human dignity respectively, have also being argued to be linked to the need for a healthy and safe environment to give these rights effect. National Environmental Standards & Regulations Enforcement Agency (NESREA) The Federal Government promulgated the Harmful Waste Decree 42 of 1988, which facilitated the establishment of the Federal Environmental Protection Agency (FEPA) through Decree 58 of 1988 and 59 (amended) of 1992. FEPA was charged with the overall responsibility for environmental management and protection. It is on record that by the establishment of FEPA, Nigeria became the first African country to establish a national institutional mechanism for environmental protection. FEPA and Departments in other Ministries were merged to form the Federal Ministry of Environment in 1999, but lacked appropriate enabling laws on enforcement. To address this omission, the Federal Government followed section 20 of the 1999 Constitution of the Federal Republic of Nigeria, and established the National Environmental Standards and Regulations Enforcement Agency (NESREA), a parastatal of the Federal Ministry of Environment. The Act establishing NESREA was passed by the National Assembly, signed by the then President and published in the Federal Republic of Nigeria Official Gazette No. 92. Vol. 94 of 31st July, 2007. By the NESREA Act 2007, the Federal Environmental Protection Agency Act Cap F 10 LFN 2004 was repealed. NESREA has responsibility for the protection and development of the environment, biodiversity conservation and sustainable development of Nigeria’s natural resources in general and environmental ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 31 technology including coordination, and liaison with, relevant stakeholders within and outside Nigeria on matters of enforcement of environmental standards, regulations, rules, laws, policies and guidelines. Nigerian Statutory Requirements The NESREA Act empowers the Agency to be responsible for enforcing all environmental laws, guidelines, policies, standards and regulations in Nigeria, as well as enforcing compliance with provisions of international agreements, protocols, conventions and treaties on the environment to which Nigeria is a signatory. The Federal Government through NESREA has developed 24 Environmental Regulations which have been published in the Federal Republic of Nigeria Official Gazette and are now in force. These regulations are given in Annex A. All of these regulations will be taken into account when preparing the ESIA. EIA requirements Under the Environmental Impact Assessment (EIA) Act CAP E12, LFN 2004 an Environmental Impact Assessment can be required in respect of public and private projects. Sections relevant to this ESIA include:  Section 2 (1) requires an assessment of public or private projects likely to have a significant (negative) impact on the environment.  Section 2 (4) requires an application in writing to the Agency before embarking on projects for their environmental assessment to determine approval.  Section 13 establishes cases where an EIA is required and  Section 60 creates a legal liability for contravention of any provision. Planning Requirements The Nigerian Urban and Regional Planning Act CAP N138, LFN 2004 oversees purposeful planning of the country to avoid overcrowding and poor environmental conditions. The following sections are relevant to this ESIA:  Section 30 (3) requires a building plan to be drawn by a registered architect or town planner.  Section 39 (7) establishes that an application for land development would be rejected if such development would harm the environment or constitute a nuisance to the community.  Section 59 makes it an offence to disobey a stop-work order. The punishment under this section, is a fine not exceeding N10, 000 (Ten thousand naira) and in the case of a company, a fine not exceeding N50, 000.  Section 72 provides for the preservation and planting of trees for environmental conservation. The Land Use Act CAP 202, LFN 2004 places the ownership, management and control of land in each state of the federation in the Governor. Land is therefore allocated with his authority for commercial, agricultural and other purposes. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 32 Criminal Acts The Harmful Waste (Special Criminal Provisions) Act CAP H1, LFN 2004 prohibits, without lawful authority, the carrying, dumping or depositing of harmful waste in the air, land or waters of Nigeria. The following sections are notable:  Section 6 provides for a punishment of life imprisonment for offenders as well as the forfeiture of land or anything used to commit the offence.  Section 7 makes provision for the punishment accordingly, of any conniving, consenting or negligent officer where the offence is committed by a company.  Section 12 defines the civil liability of any offender. He would be liable to persons who have suffered injury as a result of his offending act. ESIA regulatory requirements Some of the relevant legislation have been described above. The ESIA will ensure that the project complies with all of these. EIA Procedure Subsequent to UNCED Nigeria promulgated the main EIA legislation. The EIA Act 86 (1992) makes EIA mandatory for development projects likely to have adverse impacts on the environment. The EIA must be prepared and approved prior to implementation. The offices of the FMEnv in Abuja was visited on 11th August, 2015 and discussions held with the Environment Officers responsible for the site. They were helpful and provided the EIA Process Flow Chart given below which has been recently updated. (Figure 3-1) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 33 Figure 3-1 FMEnv ESIA Procedure 2015. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 34 3.2 International Conventions Nigeria has acceded to several international conventions and protocols as given below. Table 3-1 International Environmental Agreements Environment Related International Conventions And Protocol Signed And Ratified By Nigeria  African Convention on the Conservation of Nature and Natural Resources, Algiers), 1968  International Convention for the Prevention of Pollution of the Sea by Oil, 1954-62  Convention on Fishing and Conservation of the living resources of the High Sea, 1985  Convention on the Prevention of Marine Pollution by Dump of Wastes and Other Matters, 1972  Equal Remuneration Convention, 1951  Abolition of Forced Labour Convention, 1957  Discrimination (Employment and Occupation) Convention, 1958  Minimum Age Convention, 1973  Worst Forms of Child Labour Convention, 1999  United Nations Convention on the Law of the Sea, 1982  The RAMSAR Convention on the Conservation of Wetlands of International Importance, especially as Water Fowl Habitat, 1971  The Convention concerning the Protection of the World Culture and Natural Heritage, 1972  Convention on International Trade in Endangered Species of Fauna and Flora (CITES) 1973  Convention on the Conservation of Migratory Species of Wild Animals, 1973  Framework Convention on Climate Change, 1992  Convention to Combat Desertification, 1994  Convention on Biological Diversity 1992  Cartagena Protocol on Biosafety 2000. As there are no international transboundary issues associated with the site it is not considered likely that any agreements made under these conventions will be breached. 3.3 World Bank Standards OP/BP 4.01 Environmental Assessment The proposed activities triggered OP/BP 4.01 and the ESIA is expected to meet the requirements of this policy in terms of content and structure. Under Environmental Assessment (OP 4.01) the Bank requires environmental and social impact assessment (ESIA) of sub-projects proposed for Bank financing to help ensure that they are environmentally sound and sustainable. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 35 The environmental assessment is a process that is conducted to identify the negative impacts that a project may have on aspects of the biophysical and social environment. It analyses the impacts of project alternatives, and provides mitigation measures to be undertaken to eliminate or minimize the impacts identified. The ESIA does follow this policy in terms of content and structure. OP/BP 4. 12 – Involuntary Resettlement. The proposed activities triggered OP/BP 4. 12 – Involuntary Resettlement. However in terms of involuntary resettlement it was esablished that there were no persons found to be resident on or around the immediate vicinity of proposed site. Some informal growing of crops was taking place and compensation has been paid for this by the State Government who were responsible for the land acquisition. . Other than this there are no resettlement issues. World Bank Environmental, Health, and Safety Guidelines (EHS) The World Bank Group Environmental, Health, and Safety Guidelines (known as the "EHS Guidelines") contain the performance levels and measures that are normally acceptable and that are generally considered to be achievable in new facilities at reasonable costs by existing technology. Application of the EHS Guidelines to existing facilities may involve the establishment of site-specific targets with an appropriate timetable for achieving them. The environmental assessment process may recommend alternative (higher or lower) levels or measures, which, if acceptable, become project- or site-specific requirements. The EHS Guidelines are technical reference documents with general and industry-specific examples of Good International Industry Practice (GIIP). When host country regulations differ from the levels and measures presented in the EHS Guidelines, projects will be required to achieve whichever is more stringent. If less stringent levels or measures than those provided in the EHS Guidelines are appropriate in view of specific project circumstances, a full and detailed justification must be provided for any proposed alternatives through the environmental and social risks and impacts identification and assessment process. This justification must demonstrate that the choice for any alternate performance levels is consistent with the objectives of Performance Standard 3. 3.4 Environmental and Social Management Framework (ESMF) TCN issued the Environmental and Social Management Framework (ESMF) for the Nigeria Electricity and Gas Improvement Project (NEGIP) in August 2008. That ESMF does address new substations. It is available from ERSU or at http://documents.worldbank.org/curated/en/2008/08/9968453/nigeria- electricity-gas- improvement-project-environmental-assessment-vol-1-2-environmental-social- management- framework. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 36 4 The Project 4.1 Project Description The Transmission Company of Nigeria (TCN) proposes to build and operate a transmission substation situated at Kabba, in Kogi State. The project will be carried out on unoccupied land designated as a “greenfield” site. The construction during this project is limited to the transformer substation site only. Transmission lines already exist and distribution lines will be constructed later. Transmission and distribution are outside the scope of this report and are not included in this ESIA. Project Objectives The Project intends to achieve the following objectives:  Provide a readily available electricity supply  Improve transmission and supply of electricity statewide  Promote industrial growth  Create job opportunities  Increase revenue for TCN TCN will adopt all steps necessary to ensure responsible engagement with Affected Persons and Project Beneficiaries throughout the process. 4.2 Electricity Supply in Nigeria In order to place this project in the correct context an over view of the electricity supply industry in Nigeria is given below. This is for the benefit of non-technical readers who may not be totally familiar with the history and culture of TCN. Generation Any electricity supply system consists of three basic stages:  Generation  Transmission  Distribution The two mains types of generation are thermal and hydro. Thermal can be by burning of coal, oil, or gas. Natural gas is a by-product of petroleum recovery (“crude oil”) and so is available to be used in Nigeria. Hydropower generation translates the natural potential energy of water stored in reservoirs into electricity by the use of large dams. Also small dams known as “run of river” systems translate kinetic energy of running water into electricity, and due to the small size are known as mini or micro hydel systems. A major significant difference is that thermal plants require fuel and hydro do not. There are many other pros and cons for each type of plant. Generation can be supplemented by renewable energy ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 37 such as solar, geothermal, wind power, tidal and biogas. 5 Figure 4-1 Generation, Transmission, Distribution and Consumers 5Donald G. F., Beaty H. W., Miley G. H. and Clapp A. L. (2000). Standard Hand Book forElectrical Engineers (14th Edition). New York: McGraw-Hill, USA, pp 52. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 38 Transmission It is conventional to split generation, transmission and distribution between separate operators. The responsibility of the transmission company is to take power from the generator and deliver it to distributors, who provide power to the consumers. Every effort is made to do this efficiently with as little loss of power as possible. Currents flowing in transmission lines lose power through heat, which is proportional to current, so to avoid this power is transmitted at very high voltages and low current. The high voltage is then transmitted down the familiar large towers. 6 Figure 4-2 High Voltage Transmission Towers 6Sada, I. (2007). Generation Transmission and Distribution of Nigeria Power Hassan Usman Katsina Polytechnic. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 39 In Nigeria this voltage is 330,000 volts (330kV). The power coming from the generator must be increased in voltage and this requires a step up transformer whereby the voltage is increased. For distribution the voltage must be reduced and this requires a step down transformer. The 330kV is reduced to 132 kV and again to 33kV. The responsibility for delivery of power then shifts from the transmission company to the delivery company (“DISCO”). Figure 4-3 Step Down Transformer Station Distribution There are 11 DISCOs in Nigeria. Power can be distributed by them to industries and utilities at lower voltages such as 11kV. To increase efficiency power is transmitted in 3 phases. Factories such as steelworks with arc furnaces can require large currents and other industries may take 3 phases at 450 volts. Households use the common single phase 240 volts. Utilities such as railways require lower voltage but often direct current (D.C.) as opposed to alternating current (A.C.) produced in the generating power station. The Nigerian nominal frequency is 50 Hz. 4.3 Project Justification Nigeria as a country has the largest population in Africa and accounts for over 47% of the population of ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 40 West Africa.7 It is the biggest oil exporter in Africa, with the largest natural gas reserves in the continent. The GoN “Roadmap 2010” outlined the government’s strategy for power sector reform to expand supply, attract private investment and tackle issues hampering service delivery.8 The population continues to grow and is estimated currently to be around 180million. If the current growth rate continues, by 2050 Nigeria will be the third most populous country in the world. 9 (Figure 4-4) 10 Cou n try 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Nigeria 123 127 130 134 137 129 132 135 146 149 152 155 170 175 177 Figure 4-4 Nigeria Populations in Millions 7 http://www.worldbank.org/en/country/nigeria/overview. 8 Ibid 9 Ibid 10 http://www.indexmundi.com/nigeria/ ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 41 The economy of Nigeria continues to grow with GDP per capita increasing. It currently stands around US$2,700 per person. The expanding population will expect electric power supplies to be available to improve their lifestyle and they will have the ability and willingness to pay for it. This will place a heavy demand growth on TCN. 11 Figure 4-5 Nigeria GDP per capita in Thousands of Dollars In Nigeria electricity production is mainly based on gas fired thermal power stations and hydroelectric plants. The production in kilowatt hours (kWh) is shown below (Figure 3-6); current capacity is slightly below 5,000 MW. Interruptions in gas supply, and low water levels in summer, limit the ability to increase generation capacity. (Figure 4-6)12 11 http://www.indexmundi.com/nigeria/ 12 http://nigeria.opendataforafrica.org/skklwh/nigeria-electricity-consumption-export-import-1980-2013 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 42 Figure 4-6 Nigeria Electricity Production The amount actually consumed is shown below in kWh. The discrepancy between the amount of electricity generated, 24 billion kwhrs13, and the amount consumed, 20kWh, is due to loss in transmission and distribution. (Figure 4-7) 14 13 http://www.indexmundi.com/nigeria/ 14 CIA World Factbook - Unless otherwise noted, information in this page is accurate as of June 30, 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 43 Figure 4-7 Electricity Consumption As a member of the West African Power Pool Nigeria does have agreements to export electricity from hydroelectric power plants in return for riparian rights on water usage. Transmission lines were constructed for this purpose. Recently these exports have reduced to low power levels. In the past Nigeria did import electricity but recently this has ceased. 15 The “Road Map for Power Sector Reform” in Nigeria specifies a rule of thumb of at least 1GW (1,000 megawatts) of electricity generation and consumption for every 1 million head of population for any developed industrial nation. Based on Nigeria’s population of nearly 180 million people, the target should be 180 GW for Nigeria to be ranked as a developed country. Current targets are around 50GW. The ultimate target would give around 1kW/person. At present in Nigeria the supply is around 0.03kW/ person. There are currently 23 power generating plants in total. 16 As can be seen in Figure 4-8 the majority of 15 http://www.indexmundi.com/nigeria/ 16 Factors Affecting Electricity Generation, Transmission and Distribution In Nigeria, Sule, A. H, Hassan ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 44 the power generation capacity is in the south of the country with few in the north. . Figure 4-8 Power Generation in Nigeria 2014. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 45 In 2013 less than 50% of Nigeria's population had access to electricity.17 The peak demand forecast in 2015 is 12,800 MW.18 Nigeria plans to increase generation from fossil fuel to 20,000 MW by 2020 and increase hydroelectricity capacity to 5,690 MW by 2020. The ultimate target is 50,000MW by 2050. Independent Power Projects (IPP's) currently contribute 1,600 MW to the national grid and more investment is being encouraged. The National Policy on Renewable Energy and Energy Efficiency is intended to boost power supply and will make use of Nigeria's natural gas reserves helping to eliminate gas flaring in the country. There is a significant shortage of power availability in Nigeria both now and in the future. Major generation and distribution is in the south of the country with less in the north. This imbalance needs to be rectified. The Transmission Development Project proposed by TCN will help to ease immediate power supply constraints and assist in economic growth. Based on the above discussion the project is considered justified. 4.4 The Project Proponent - TCN The Government owned electricity system currently comprises 19 :  Three hydro and seven thermal generating stations total installed capacity 6,852MW, available capacity 3,542MW.  A radial transmission grid (330kV and 132kV), owned and managed by TCN  Eleven distribution companies at 33kV and below TCN was incorporated in November 2005. It was one of the 18 unbundled Business Units previously 17 National Population Commission 2013 18 Presidential Task Force on Power 2015 19POWER SECTOR OUTLOOK IN NIGERIA: Governments Renewed Priorities, Prof. Bart Nnaji CON, Chairman, Presidential Task Force on Power, Securities and Exchange Commission June, 2011 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 46 under the Power Holding Company of Nigeria (PHCN). TCN licensed activities include electricity transmission, system operation and electricity trading which is ring fenced. TCN carries out the functions of Transmission Service Provider, System Operations and Market Operations. The TCN system comprises 330 kV and 132 kV circuits on overhead lines and substations (Figure 4-9.) A 700kV supergrid is planned. (Figure 4-10.) Distribution is split into 11 zones and the distribution networks comprise 33 kV, 11 kV and low voltage circuits. 20 Figure 4-9 Existing Power Transmission in Nigeria 20POWER SECTOR OUTLOOK IN NIGERIA: Governments Renewed Priorities, Prof. Bart Nnaji CON, Chairman, Presidential Task Force on Power, Securities and Exchange Commission June, 2011 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 47 Figure 4-10 Proposed Power Transmission in Nigeria 4.5 Project Location - Kabba (Kogi State) The proposed 132/33kV Transmission Substation is to be situated along Kabba – Okene express way, Kogi State in the North- Central Nigeria. The land arises from 300meters along the Niger-Benue confluence, to the height of between 300 and 600 meters above sea level in the uplands, Kogi State is drained by the Niger and Benue rivers and their tributaries. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 48 Figure 4-11 Kogi State Kabba/Bunu LGA 4.6 Role of Transformer Substations Operation of a Substation Electricity is generated in a thermal power plant, hydroelectric power plant, or by renewable energy. This electricity is then supplied to a transmission substation. In the transmission substation the voltage is increased substantially using step up transformers. The voltage is increased to reduce the transmission losses over long distances. This electricity is then supplied to a power distribution injection substation where it is stepped down using step down transformers and then supplied to a distribution grid. In the distribution grid there are additional distribution transformers and voltage is further reduced for distributing further down the grid. From here the electricity is supplied to residences, Industries, etcat 220 volts as per requirement. The transformer substation is the component of the electricity supply network that is the subject of this ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 49 project. 21 The substation is where the voltages are increased to high values by using step up transformers, and after the transmission, they are again stepped down for distribution. In addition changing the voltages the substations have a variety of protective devices like circuit breakers and fuses to protect the distribution networks. These are designed in such a way that various distribution circuits can be isolated for repairs and load shedding. 22 Function of Transformer Substations Apart from the distribution of electricity the substations have many other functions as follows:  Step up and step down of the voltage for transmission and distribution. This lowers transmission losses.  Switching and isolating the circuits for maintenance: Switching is also an important function of substations. Closing down a feeder circuit when the load demands are high needs to be done for the safety of the generating plants. Switching high voltages is a dangerous work, and special circuit breakers like air circuit breakers and oil circuit breakers for quenching the arcs have to be used.  Load shedding: When the power demand is more than the supply, the substations do load shedding on distribution circuits to maintain balance.  Correction of power factors circuits: The power factor has to be kept at the correct value when reactive loads are there to protect the generating plant and increase efficiency.  Safety devices like circuit breakers and fuses: These safety devices are provided for protecting the machineries on the distribution circuit as well as in the substation against high short circuit currents.  Bus bars for splitting the power for distribution: These are thick bars of copper to which various distributing circuits are connected by nuts and bolts. Substations are normally outdoors and are enclosed by a wire fence. However, in residential or high Donald, Beaty, Miley and Clapp (2000). Standard Hand Book for Electrical Engineers (14th Edition). 21 New York: McGraw-Hill 22 Ibid ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 50 density areas, the substation may be indoors and even housed inside a building to restrict the humming noise of the large transformers. The elements of a substation are shown below. 23 Figure 4-12 Elements of a substation A: Primary power lines' side B: Secondary power lines' side 1. Primary power lines 2. Shield wire 3.Overhead lines 4.Transformer for measurement of electric voltage 5.Disconnect switch 6.Circuit breaker 7.Current transformer 8.Lightning arrester 9.Main transformer 10.Control building 11.Security fence 12.Secondary power lines The first substations were connected to only one power station, where the generators were housed, and were subsidiaries of that power station. Hence the name “sub-station”. 24 Reactors Efficiency and safety are key considerations in a sub station. For transmission lines, the space between the overhead line and the ground forms a capacitor parallel to the transmission line, which causes an increase in voltage as the distance increases. When a network becomes larger, sometimes the short- circuit current on the transmission line exceeds the short-circuit rating of the equipment. To offset the 23 Ibid 24 Ibid ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 51 capacitive effect of the transmission line and to regulate the voltage and reactive power of the power system, reactors are connected either at line terminals or at the middle, thereby improving the voltage profile of transmission line. Reactors are current-limiting devices and oppose rapid changes in current. They hold down any spikes of current and limit any peak currents. Variable Shunt Reactors are used in high voltage energy transmission systems to stabilize the voltage during load variations. The variability brings several benefits compared to traditional fixed reactors. The VSR can continuously compensate reactive power as the load varies so ensuring voltage stability. 25 Local Control Kiosk All substations contain a local control kiosk. This is manned and used for controlling power allocation but also as a communications hub in case of accident or power outage. The new 132kV and 33kV diameters will be equipped with control kiosk. Figure 4-13 Substation Transformers 25 Ibid ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 52 Equipment The project covers the design, manufacture, delivery, construction, installation and commissioning of 2 X 60MVA - 132/33kV Transformers at Kabba. It includes all works that may be needed to deliver the new sub-station as specified in the bidding document. It includes the works in Table 4-1 below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 53 Table 4-1 Sub-station Works  132kV Equipment  33kV Equipment  Supply and installation of 2x60MVA  Supply and installation of 33 kV double bus 132/33kV transformers, double bus bar bar outdoor switchyard together with all switchyard, complete with all associated associated equipment. equipment. The Double busbar shall be  The 33kV switchyard shall be of double bus designed and constructed for the bar (made of tubes) configuration with six connection to the bays such as detailed (6) overhead outgoing feeders equipped below. with three voltage transformers (one per  phase).  Poles circuit-breakers,  Gantries for bays (one coupler bay) and  Current transformers corresponding overhead liaisons (comprising  Voltage transformers conductors, string insulators, hardware,  poles isolators and isolators with earthing fittings and accessories) between gantries switches shall be installed.  Surge arresters   Supporting steel structures and gantries,  Equipment for the new 33kV Double busbar  Post insulators, shall comprise the following:  Overhead conductors, string insulators and  Earthing transformers hardware,  Poles circuit-breakers,  Earthing materials,  Poles isolators and isolators with earthing  Other fittings and their accessories. switches  Control and Protection Equipment/Panels  Current transformers (one per phase),  Voltage Transformers (one per phase)  Surge arresters (one per phase),  Supporting steel structures and gantries,  Post insulators,  Overhead conductors, string insulators and hardware,  Earthing materials,  Other necessary fittings and accessories.  Protection and control equipment 4.7 Project Implementation The project will be implemented by PMU of TCN and is intended to commence in January / February 2016. Construction time is estimated at 18 months. Allowing for commissioning the substations should be online within 2 years. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 54 4.8 Alternatives Renewable Energy Renewable energy is also called “clean” or “green” energy because it has little to no emissions and can be replenished in a short period of time. The four renewable sources used most often are wind, solar photovoltaics, geothermal and biomass. Hydropower is also a renewable resource and is already used in Nigeria where sufficient head of water and flow is available. The first consideration with “green” energy is whether they are economically feasible when compared with more traditional options. 4.8.1.1 Wind Wind turbines use blades to collect the wind’s kinetic energy. When the wind blows, it flows over the blades creating lift, like the effect on airplane wings, which causes them to turn. The blades are connected to a drive shaft that turns an electric generator.26 The cost of the commercial wind turbines varies from $1 to $2 million per mega watt (MW) of capacity installed. A single 1 MW turbine operating at a 45% production rate will generate about 3.9 million kilowatts (KW) of electricity in a year, meeting the needs of about 500 households annually. However, the average wind turbine turns at approximately 25%. 27 The major challenge of using wind as a source of power is that the wind is intermittent and does not always blow when electricity is needed. Wind energy cannot be stored and not all winds can be harnessed to meet the timing of electricity demands. Wind farms producing energy on a large scale often need to be in locations far removed from the populated areas where the energy is needed. This puts wind energy at a major disadvantage in terms of costs of new substations and transmission lines. 28 26 Renewable Energy : Technology and Systems, Jäger, Olindo, Delft University of Technology, 2014 27 Ibid 28 Ibid ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 55 Figure 4-14 Wind Turbines and Solar Panels 4.8.1.2 Solar Solar energy can be converted directly to electricity by utilizing Photovoltaic (PV) devices, or “solar cells.” Concentrated Solar Plants (CSP) uses solar energy as heat to boils water; the steam drives a turbine; the turbine turns an ordinary generator, which then generates electric power. A 500 megawatt (MW) plant solar power plant could cost about $5 billion to build and would require 4,000 acres whereas a 500 MW natural gas plant would require 40 acres and a coal plant 300 acres. The obvious limitation is that during hours of darkness another fuel source is required. The advantage is that generation can take place next to the consumer, if solar insolation is adequate. 29 29 Photovoltaic Solar Energy, Miro Zeman Delft University of Technology 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 56 4.8.1.3 Geothermal Figure 4-15 Geothermal Plant and Landfill Gas Extraction Geothermal power plants use earth’s heat to generate steam accessed by wells. It is a closed circuit system so there are no liquid or gaseous emissions. Since geothermal plants use smaller land areas, the cost of land is usually less expensive than other power plants. Geothermal is a baseload resource, available 24 hours per day, every day of the year. It is independent of weather conditions and has no associated fuel costs. Drilling and finding geothermal reservoirs can be expensive. The initial cost can be $5M per installed MW and more for a small scale (<1 MW) power plant. The drilling needed can vary greatly depending on geological conditions and generation is very site specific. Consequently transmission costs can be considerable. 30 4.8.1.4 Biomass Biomass energy includes landfill methane gas, wood waste, farm by-products and ethanol. The majority of biomass electricity today is generated using a steam cycle. In this process, biomass is burned in a boiler to make steam. The steam then turns a turbine, which is connected to a generator that produces electricity. Landfill methane gas is collected from decomposing waste by a series of wells strategically 30 Geothermal Energy, Copenhagen Technology University, 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 57 placed throughout the landfill. The wells are connected by a series of pipes under a vacuum created by blowers. Once blowers deliver the gas to the plant, internal combustion engines use the gas as fuel and spin generators to produce electricity. Converting landfill gas (LFG) to electricity reduces emissions of methane, a greenhouse gas 23 times more potent than carbon dioxide. It can be a source of carbon credits. 31 4.8.1.5 Base Load Demand All renewable energy sources face the same problem that is they are not capable of covering the base load demand. Nigeria is currently exploring a secure and reliable energy future based on a combination of natural gas, hydro and renewable energy sources. Transmission Alternatives Transmission in Nigeria is by means of overhead transmission lines. These have significant visual impacts and often placing the cable underground is suggested as an alternative in areas of high scenic value such as national parks. Such a decision needs to take into account a comparison of the cost of installation, maintenance, vulnerability to damage and service provision to the public. Placing a cable underground rather than overhead can incur costs ranging from 4 to 20 times more expensive depending on location. 32 Underground co-axial cables cause capacitive losses whereas overhead lines can cause inductive losses, so changing from overhead lines to underground cables can require modifications to the reactor settings in the substation. (see Section 3-7.1) The costs vary with voltage but indicative overall total costs are given in Table 3-2 below. 31 Landfill Gas Extraction and Usage, Copenhagen Technology University, 2015 Renewable Energy Essentials, www.iea.org, OECD/IEA, 2010 32 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 58 Table 4-2 Cost Ratio of U/G cable to O/H Line Operating and Maintenance: Voltage in KV Cost Ratio of U/G cable to O/H Line 400 18 220 13 132 8 The use of underground cables is only justified in extreme cases. 33 Site Alternatives According to the Nigeria Land Use Act of 1978, all lands in the state is vested in the Governor of the State but the Act categorically states that the land is to be held in trust for the citizens (Sections 34 and 36) and the means of enforcing such rights are provided in sections 39 and 41. With the Land Use Act, Access to land by investors and individuals for various uses is easy, every part of the country has a common Land Tenure System, government controls the use of land and the issue of acquisition of land, compensation and resettlement is made easy. In each case TCN approached the State Government and requested land to be made available. The general location and need for proximity to overhead transmission lines was stated. The Local Government then nominated sites and held all discussions with local land owners and residents. Compensation was agreed and paid. Confirmation of this was then sent from the LGA to TCN. In Kabba the Royal Majesty (The Obaro of Kabba) donated family land to this project and persuaded Kogi state Government to pay for the survey at a cost of over One million naira. Kabba is one of the largest towns in Kogi State with high demand for electricity supply. Presently the town is being fed on 11kV from Lokoja with many Turn-Offs along the route resulting in a very low voltage profile. The town is centrally located linking other Local Government Headquarters in the state Renewable Energy Essentials, www.iea.org, OECD/IEA, 2010 33 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 59 together with some cottage industries and medium factories producing various goods. The central location of the town and linkages to other towns as well as readily available loads were some of the factors that informed the choice and siting of the Substation. The substation is to be fed from already existing 132kV Lokoja-Okeagbe line. The substation will also provide interconnectivity on the 132kV to Isanlu, Obajano and Umaran to close up the loop even up to Ekiti State. TCN did not examine alternative sites themselves because the sites were identified and made available by the respective state governments TCN specified the general area where the substation was to be located based on the proximity to high voltage transmission lines and the necessary size of the substations. This information was passed to the state government who reviewed possibilities, consulted with landowners, and arrived at a decision on the site which was then conveyed to TCN. As the site was suitable TCN accepted the proposed location. The State Government then transferred to TCN the Site Plan, Survey Plan and Change of Ownership letters. This transaction was confirmed through the various community stakeholders meetings subsequently organised by TCN. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 60 5 Preliminaries The preliminaries included Screening, Scoping, Primary and Secondary Data collection and GIS Mapping. 5.1 Screening The site was visited by the consultants and an initial reconnaissance carried out. The proposed sites were assessed based on the following checklist :  Administrative and Legal Framework  Nature of site  project type  location - Visibility – Is the Site generally visible? - Dwellings- Is there a high density of dwellings? - Archaeology/Historical site- Is there a high density of archaeological features? - Topography- Nature of the topography? - Ecology-Is there any ecological potential on the site?  scale (size)  significance or environmental sensitivity of the receiving environment This was a screening exercise to confirm that an ESIA was required. 5.2 Kabba: Kogi State (North Central Nigeria) Reconnaissance Visit The reconnaissance field visit was conducted by the Environmental consultants (SMEC/Metaspec) and the proponent (TCN-PMU Abuja staff and TCN Regional office at Ajoakuta, Kogi State). The schedule of site visit is shown in the table below. Table 5-1 Schedule of Reconnaissance visit S/N DATE LOCATION TEAM nd rd 1. 22 -23 June Kabba (Kogi State) TCN-PMU & SMEC/Metaspec 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 61 Figure 5-1 Stakeholders at the proposed project Figure 5-2 Discussions at the Proposed Project site site Figure 5-3 sloping topography of proposed project Figure 5-4 Road beside proposed project site site ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 62 Figure 5-5 Stakeholders guided to Proposed project Figure 5-6 Survey beacon on the Proposed Site site 5.2.1.1 Screening Results The following results were concluded on screening. Table 5-2 Screening Results  S/N  CRITERIA  RESULTS  1.  Administrative and Legal  Federal Ministry of Environment (Nigeria) EIA sectoral Framework guidelines for Electrification projects  2.  Nature of site  Greenfield-Undeveloped parcel of land with primary vegetation.  3.  Project type  132/33kV Transmission substation  4.  Location  Proposed site is located along the old Kabba - Lokoja Road in Kabba town of Kabba/Bunu LGA  5.  Scale (size)  9.427 ha  6.  Site Description  Proposed site is visible with vegetation  Site located along a major road  slightly sloping undulating terrain  Approximately 1Km to residential settlements  7.  Sensitivity  Sensitive Environment (Social and Biophysical)  8.  Alternatives  The justification for the proposed site to other alternative sites are:  hospitality of host communities,  availability of required land,  cooperation of all relevant authorities ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 63 5.3 Scoping Notification It is a requirement of the Federal Ministry of Environment that all Project Proponents make known to any residents living in close proximity to a proposed development of their intentions to develop that site. Consequently during the Reconnaissance Visits public consultations were held. These were to State authorities, local councils and selected groups of host communities. These are considered to be focus group discussions (FGD). In addition to this well advertised open public forum meetings were also held later in October 2015. Comments from Stakeholders Consulted The state and local authorities applauded the project and promised their full cooperation in executing the ESIA for the Project to commence. The communities expressed disappointment that the project is yet to commence despite the fact the parcel of land had been offered to the proponent a long time ago. They urged for speedy conclusion of the ESIA to pave way for the commencement of the construction works. Spatial boundary A comprehensive description of the biophysical, social and health components of the environment to be studied will be recorded. The Spatial Boundary for the study will be based on regulatory requirements and stakeholder’s concerns. As required by Ministry of Environment, spatial boundaries will be established of 2 km radius from the perimeter of proposed project site for biophysical assessment and 4km radius for socioeconomics and health studies. Sampling Locations Professional judgment was applied in the selection of sampling stations, taking into account ecological features, geographical location of communities and control points in apparently undisturbed areas. Socio-economic & health studies structured questionnaires were administered to a probabilistic sample of households. The sampling locations is given below as agreed after the Scoping Exercise. Table 5-3 Sampling Locations  S/N  Environmental  No. of  Description of sample Stations  Components Sampling  Stations  1.  Climate/Meteorology  1  Project site  2.  Air Quality & Noise  11  10 stations and 1 control  3.  Surface Water  2  1 station and 1 Control  4.  Sediment  2  1 station and 1 Control  5.  Ground Water  3  2 existing boreholes and 1 Control ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 64  6.  Soil  15 (30  10 stations (site) 4 stations samples) (communities) 1 station (Control)  7.  Vegetation  5  2km radius transects  8.  Wildlife  NA  NA  9.  Socio economics and  2  Communities Health Sampling Procedure The sampling procedure was established during Scoping. These measurements were made in situ to establish the Environmental Baseline :  Meteorology  Air Quality and Noise  Soil, Land use and land cover  Vegetation and Wildlife  Geology/Hydrogeology  Surface water  Socio-economics  Health The Sampling Specifications are given below. Table 5-4 Sampling Specifications  S/N  SAMPLE  SAMPLE TYPE/DURATION  1.  Soil  Composite : Surface (0-15cm) and Subsurface (15- 30cm)  2.  Sediment  Grab  3.  Surface Water  Grab  4.  Groundwater  Grab  5.  Vegetation  Transect area  6.  Wildlife  Transect/Visual Observation/Interviews  7.  Air Quality  Spot Measurement : Twenty-five (25) minutes per station The Federal Ministry of Environment representatives were present during the sampling to ensure that environmental samples are collected and preserved (where necessary) according to recommended procedures and practices for environmental data collection in Nigeria. The environmental components and indices for the Biophysical Baseline Assessment were as given below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 65 Table 5-5 Environmental Components and Indices for Biophysical Baseline Assessment  Environmental  Environmental  Data Acquisition  Potential Environmental Impact Indicator Component Aspect  Climate/  Microclimate/Regio  In situ  Temperature, Rainfall, Relative humidity, Wind direction and  Meteorology nal Climatic measurement, speed, visibility. features secondary data  Air Quality  Local and Regional  In situ / laboratory  Particulate, NOx, SOx, CO2, CO, VOC, H2S analysis  Heavy metals (Fe, Cd, Cr, Pb, Ni, Vn, Zn)  Noise  Local  In situ  Ambient noise level dB(A). measurement  Surface Water  Hydrology/  In situ /secondary  Flow direction, flow rate, Drainage characteristic, erosion pattern  (storm water) /  Hydrodynamics data  Sediment Characteristics  Physicochemical  In situ  Colour, alkalinity, TDS, TSS, Turbidity, EC, THC, pH, DO, Redox Features measurements, potential, BOD5, COD, Oil & Grease, PCB, Anions/Cations, NH4+, Composite samples NO3, NO2, PO4, SO4, SiO2, Na, K, Ca, Mn, Mg, for laboratory  Heavy metals (Fe, Cd, Cr, Ni, V, Pb, Zn, Hg). analysis  Hydrobiology  Composite samples  Species composition, distribution, diversity and abundance and for laboratory seasonality of Phytoplankton, Zooplankton, Benthos analysis  Surface Water  Fisheries  Direct  ** Fishery activities  (storm water) / observations/inter  Sediment view, In situ Characteristics measurements, composite samples for laboratory analysis ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 66  Environmental  Environmental  Data Acquisition  Potential Environmental Impact Indicator Component Aspect  Microbiology  Composite samples  Total heterotrophic bacteria, fungi, Total hydrocarbon bacteria and  (surface water) for laboratory fungi, total and faecal coliforms. analysis  Sediments  Composite grab  Colour, Texture, Temperature, pH, Redox potential, THC, Oil & samples for Grease,PCB, Sediment geochemistry (Fe, Ni, V, Cd, Cr, Pb, Zn, Hg), laboratory analysis Sediment microbiology  Water Use  Direct observation/  Traditional use of rivers and water bodies (navigation, sand mining,  interviews food processing, aquaculture, domestic etc)  Ground Water  Physicochemical  In situ / laboratory  Colour, odour, alkalinity, TDS, TSS, Turbidity, EC, THC, DO, pH, Characteristics Features analysis Redox potential, BOD5, COD, Oil & Grease, Anions/Cations, NH4+, NO3, NO2, PO4, SO4, SiO2, Na, K, Ca, Mn, Mg,  Heavy metals (Fe, Cd, Cr, Ni, V, Pb, Zn, Hg).    Microbiology  Composite samples  Total heterotrophic bacteria, fungi, Total hydrocarbon utilizing for laboratory bacteria and fungi, total and faecal coliforms. analysis   Groundwater  In situ  Static Water Level (SWL), Flow direction/ Flow Rate. dynamics  Ground Water  Hydrogeology  Laboratory  Stratigraphy, Aquifer characteristics Characteristics analysis, secondary data sources  Geology  Local and Regional  Secondary data,  Regional geology, Stratigraphic/Lithologic properties etc  laboratory analysis  Soil  Physical  In situ/ composite  Permeability, porosity, bulk density, texture (grain size), colour, characteristics auger samples for lab analysis, Soil profile pits ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 67  Environmental  Environmental  Data Acquisition  Potential Environmental Impact Indicator Component Aspect  Chemical  Composite samples  pH, Anion, Cation and Cation exchange capacity (CEC), THC,PCB, characteristics for laboratory heavy metals, Soil capability analysis  Soil microbiology  Composite samples  Total heterotrophic bacteria, fungi, Total hydrocarbon bacteria and for laboratory fungi. analysis  Land Use/Cover  Satellite Imagery of  Secondary data  Land Use types: Recreational, agricultural, forestry, industrial, Land use/Land sources residential, institutional, commercial. Trends and time-lapse cover mapping.  Wildlife  Transect, direct  Species composition/distribution (vegetation map of locality), observation, seasonality, exploitation methods/level (kill rates/month/year, interviews, estimates of wildlife population etc). IUCN categorization secondary data sources  Vegetation  Transect,  Habitat status, floral composition, density and distribution, herbarium studies, vegetation structure, plant pathology tissue analysis  Biodiversity Status  Conservation  In situ observation,  Conservation status (rare, threatened and endangered species), & issues relevant to interviews, conservation areas (forest reserves etc), environmentally sensitive biodiversity secondary data areas – wetlands and swamps), local conservation practices. Source: FMEnv Standard ESIA Parameters (Nigeria) ** Note: Surface water was not sighted as at the time of the reconnaissance visit close to any of the proposed project sites; however it is expected during the peak of the raining season (July-September) storm water will gather at depressions to form surface water. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 68 5.4 Primary Data Site Assessments Field Sampling Program The field sampling program took place in August and September 2015 as shown below. Table 5-6 Field Sampling Program S/N Assignment Description Date 1. Mobilization of ESIA Team 23rd August 2. Field Sampling at Proposed 330/132kv and 132/33kv 24th – 25th August Transmission Substation Site at New Kano, Kano State 3. Field Sampling of Proposed 330/132kv and 132/33kv 26th -27th August Transmission substation at Biliri, Gombe State 4. Team Re-organization at Abuja Base Office 28th August 5. Field Sampling at Proposed 330/132kv and 132/33kv 29th – 31st August Transmission Substation Site at Kabba, Kogi State 6. Field Sampling at Proposed 330/132kv and 132/33kv 1st – 3rd September Transmission Substation Site at Abor (9th Mile), Enugu State 7. Demobilization of Team 4th September 8. Laboratory Analysis of collected biophysical samples 26th August – 10th September 9. Draft Report Submission to SMEC 15th September Field Sampling Plan Parameters such as temperature, pH, turbidity, electrical conductivity and dissolved oxygen are to be determined in situ because of their rapid change on storage. For other parameters samples which could be subject to microbial degradation and transformation were preserved, stored and analysed at minimum time after collection. A radial pattern of sampling, in web like structure around the site was applied. The distance of influence is: • 2 km radius from proposed project site for biophysical • 4km radius for socioeconomic from proposed project site This combined Work Plan/Field Sampling and Analysis Plan (FSAP) addressed the field sampling, analytical, quality control, and data review procedures for the collection and analysis of samples. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 69 Table 5-7 Field Sampling and Analysis Plan (FSAP)  ENVIRONMENTAL  PARAMETER  EQUIPMENT COMPONENT  METEOROLOGY  Temperature  Traceable Thermometer   Wind speed   Skye Master Anemometer Direction & wind Vane   Humidity,  Skye Master Mini Atmospheric Pressure Weather Station     AIR QUALITY  Suspended Particulate  Met One Instrument Matter Aerosol Mass Monitor   Nitrogen Oxides  Testo 350 XL Gas Analyser   Sulphur Oxides  Testo 350 XL Gas Analyser   Carbon Monoxides  Testo 350 XL Gas Analyser   VOC/HC  Testo 350 XL Gas Analyser  NOISE  Sound level  Tecman Sound Meter  SOIL  Sampling  Stainless steel auger   pH  Hannah pH meter   Electrical conductivity  Hannah conductivity meter.   Soil Texture  Particle Size Matrix   Heavy metals  Digestion/AA Spectrophotometry   Total Hydrocarbon  Extraction / IR Content Spectrophotometry  Vegetation   Quadrant, Binoculars  SURFACE/GROUNDW   surface water sampler & ATER ISCO Borehole Sampler   Temperature  Eco Testr pH/temperature Meter   pH  Eco Testr pH meter   Total, Dissolved and  ExTech Conductivity/TDS Suspended Solid Meter   Total Alkalinity  HACH Digital Titration method ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 70   Dissolved Oxygen  ExTech DO Meter   Biological oxygen  Winkler method Demand (BOD5)   Total Hydrocarbon  Extraction / Content (THC) Spectrophotometer   Conductivity  Ex Tech Conductivity Meter.   Heavy metals  Flame Atomic Absorption Spectrophotometry  SEDIMENTS  Sampling  Ekman Grab     MICROBIOLOGY  Total heterotrophic  Composite samples for bacteria, fungi, laboratory analysis hydrocarbon Utilizing bacteria and fungi, total and faecal coliforms.  WILDLIFE  Conservation status  In situ observation,  (rare, threatened and interviews, secondary  endangered species), data conservation areas (forest reserves etc.), environmentally sensitive areas – wetlands and swamps), local conservation practices.  GEOLOGY  Profile, type and  In situ observation, composition drilling, laboratory analysis, reporting  SOCIO-ECONOMIC  Social Infrastructure  Key informant interviews, STUDIES Cultural Properties, Focus Group Discussion Natural Resources and (FGD), direct observation, Land Use, Perception Administration of of the project, The structured questionnaires role of women and and Collection of children, Physically secondary data. Challenged, Social Structure and Organization, Vehicular Traffic Analysis, Sex Trade  HEALTH STUDIES  Demographic profile  Key informant interviews, of the Communities, FGD, Administration of ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 71 Morbidity/Mortality structured questionnaire Patterns, Healthcare and interviews, Walk- facilities, Nutritional through survey and Status of Under-fives Collection of secondary and the general data. population, Maternal and Child Health, Knowledge, Attitude Practice and Behaviour (KAPB), Environmental health factors 5.5 Secondary Data In addition to primary data collected by the site sampling, information was obtained from other agencies such as meteorological information, as is regularly collected by airports, or previous environmental reports in similar locations. This is identified in the literature review and is given in the Annexes. 5.6 GIS Mapping Constraints Mapping The spatial boundaries of 2kms for bio-physical impacts and 4 kms for socio-economic impacts were also adopted for the GIS evaluation. These were reflected in the boundaries of the constraint mapping. The mapping identified the site, roads, watercourses, and nearby development. The information is used in the Baseline Evaluations to show gradient and catchment areas. GIS Ground Truthing It has been stressed continually during the preparation of the ESIA that although GIS information is extremely valuable there is no substitute for visiting the site and these two activities must be combined. In order to visually check that the GIS data is correct site inspections were made and this is known as Ground Truthing. Kabba: Kogi State (North Central Nigeria) Kabba was visited by road in the company of FMEnv, TCN, and PMU. Local government officials were met and accompanied the team to the site. The site has a gradient from north to south so drainage is in that direction. The nearest buildings, at the moment, are 3 kms distant to the south. The soils are hard fractured lateritic rock. Extensive earthworks will be required for platform construction during site formation. A cut and fill materials balance plan is required. There is extensive ground cover by shrubs and mature tall trees. A waste disposal plan will be required for this vegetation removal. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 72 Figure 5-7 Site visit with LGA Officials showing rocky lateritic soils and distant buildings Validation of GIS Data The site visits have validated the GIS data so it can be used with confidence in the ESIA. Use of A0 Maps The maps produced from downloaded remote sensing data were printed in A0 size and used in the public consultations. These proved very effective in generating lively comments and discussions. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 73 6 The Environment – Kabba 6.1 Baseline The purpose of the baseline data acquisition was to establish, the status of the various environmental components that are likely to be affected by the proposed project. In order to achieve this, environmental parameters were determined from literature survey, fieldwork, laboratory and data analyses. The components of the environment evaluated covered biophysical, social and health. The ESIA study of the project incorporated data from already approved Environmental Impact Assessment reports as secondary data. 6.2 Baseline Data Acquisition Methods The approach adopted was to obtain ecological baseline data from desktop, field and laboratory studies, interviews and consultations with individuals/representatives of the communities of the project area. This approach provides adequate information for establishing the baseline status of the environment of the study area. 6.3 Study Location Kabba is a town in Kogi State in Mid West Nigeria. It lies near the Osse River, at the intersection of roads from Lokoja, Okene, Ogidi, Ado-Ekiti, and Egbe. Kabba is the headquarters of the Kabba/Bonu Local Government Area of Kogi State. Kabba is located on Latitude 749'59.988"N and Longitude 64'0.012"E at an altitude of 435m above sea level. The proposed Transmission Substation site is situated on 9.427 hectares in Ewe Area of Kabba Township and is approximately 20 metres off the Kabba –Okebukun - Obajana Road. The site is 4km from the main heart of Kabba Township. The closest neighbour to Ewe is Okebukun. Other neighbouring communities to Kabba Town are Ayetoro, Ogidi, Yagba, Otu, Okedayo, Kakun, Ogileko, Ayejunle, Iyara, Iyamoye, Ayede, Iluke. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 74 Figure 6-1 Administrative Map of Kogi State Showing Kabba/Bonu LGA 6.4 Description of Sampling Locations The map showing the study area with the sampling stations is shown Figure 6.2. The Sampling points were geo-referenced by means of Global Positioning System (GPS) on the field. Judgment sampling was applied in the selection of study stations, taking into account ecological features, geographical location of communities and control points in apparently undisturbed areas. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 75 Figure 6-2 Sampling Map Table 6-1 Geographical Reference of Biophysical Sampling Stations Station Easting Northing MET1 6°7'20.19" 7°50'39.76" AQ1/SS1 6°7'17.80" 7°50'42.66" AQ2/SS2 6°7'29.07" 7°50'50.35" AQ3/SS3 6°7'12.68" 7°51'01.27" AQ4/SS4 6°6'56.12" 7°50'39.08" AQ5/SS5 6°7'22.92" 7°50'21.32" ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 76 AQ6/SS6 6°6'13.00" 7°50'44.54" AQ7/SS7 6°7'02.44" 7°50'28.15" AQ8/SS8 6°7'41.19" 7°50'45.40" AQ9/SS9 6°7'50.92" 7°50'27.81" AQC/SSC 6°6'01.15" 7°50'17.06" GW1 6°7'02.44" 7°50'28.15" GW2 6°5'59.45" 7°50'14.84" GW3 6°5'59.45" 7°50'32.25" GWC 6°4'24.60" 7°49'51.66" SW1/SD1 6°7'44.94" 7°50'39.59" SW2/SD2 6° 7'0.20" 7°50'20.00" SW/SDC 6°6'36.49" 7°51'7.58" AQ=Air Quality, SS=Soil, GW=Groundwater, SW=Surface Water, SD=Sediment, MET=Meteorology 6.5 Spatial Boundary A radial pattern of sampling, in web like structure around the site was applied. The distance of influence is:  2km radius from proposed project site for biophysical studies  4km radius from proposed project site for socioeconomic studies ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 77 Figure 6-3 Satellite Imagery of Proposed Project site Socio-economic and health studies structured questionnaires were administered to a probability sample of households. The universe of households was obtained from listing by guides and assigned field assistants. The communities in Table 6-2 were identified within the defined study boundary. Table 6-2 Study Communities STATE (1) LOCAL GOVERNMENT AREA (1) COMMUNITY (1) Kogi Kabba/Bunu Kabba 6.6 Environmental Parameters A comprehensive description of the baseline conditions of the proposed project area was undertaken. The scope covered:  Meteorology ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 78  Air Quality and Noise  Soil, Land Use and Land Cover  Vegetation and Wildlife  Geology/Hydrogeology  Surface Water  Human Health  Socio-economics The sampling protocol for each of these parameters is given in the Annexes. 6.7 Quality Assurance / Quality Control The QA/QC procedure covered sample collection and handling, laboratory analyses, generation of data and coding, data storage and treatment as well as report preparation. The quality assurance programme used required:  Only experienced and qualified personnel used in the study  Carrying out field calibrations of equipment and running distilled water blanks to reduce errors that could arise from field measurements.  Replicate samples were collected and used as checks of instrument performance.  Field analytical operations were carried out in a defined sequence to avoid cross contamination of instruments.  Chain of custody protocols were followed Parameters such as temperature and dissolved oxygen were determined in situ because of their rapid change on storage. As samples could experience microbial degradation they were analysed as quickly as possible after collection. Timing of Field Work Field work for this study was carried out on the basis of approval received from the Federal Ministry of Environment (FMEnv). The fieldwork was carried out from 29th to 31st August, 2015 (Wet Season) with supervision from the Federal Ministry of Environment (FMEnv). Laboratory analysis of field samples was conducted at Research and Development Laboratory, Ministry of Science and Technology, Uyo, Akwa Ibom State. 6.8 Physical Climate Kogi State has an average maximum temperature of 33.2°C and average minimum of 22.8°C. Lokoja, the State capital is generally hot throughout the year. The rainy season lasts from April to October. The dry season, which last from November to March, is very dusty and cold as a result of the north-eastern winds, which brings in the harmattan. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 79 Rainfall The annual rainfall of the area is between 1,100mm and 1,300mm. Temperature Air temperatures in the area ranged from 24.2oC to 35.5oC, with a mean of 28.6oC in the dry season. In the rainy season, air temperatures ranged from 24.0oC to 30.0oC, with a mean of 26.7oC. The mean air temperature was relatively lower during the rainy season. The measured temperatures are not significantly different from the average monthly values from historical records Wind Speed/Direction The diurnal wind speed from secondary data sources recorded for the dry season show that the wind speeds in the project area ranges from 0.5-3.9m/s, with a mean of 1.5m/s. Wind speeds of 0.5-2.1m/s constitute over 60%. Dominant directions are Northerly (N), North-Easterly (NE), South-Westerly (SW) and Westerly (W). During the rainy seasons, the range of wind speeds was 0.6-8.3m/s, with a mean of 3.69 m/s. The wind directions observed were South-Westerly (SW), Easterly (E) and South-Easterly (SE). The average wind speed is higher during the rainy season. Calm periods are prevalent at late night. This is as a result of temperature inversion which leads to the atmosphere being stable and could affect air quality at ground level. The observed average wind speeds and directions are within the range of historical records for the area. Relative Humidity The relative humidity is the moisture condition of the atmosphere. The highest relative humidity is always recorded around dawn (09h), while the lowest is recorded at the afternoon (15h). The relative humidity obtained during the period ranged from 55.5 to 94% in the dry season, with a mean of 79.4%. During the rainy season, values ranged from 70 to 96%, with a mean of 87.5%. Average Relative Humidity for the study area from historical records ranges from 73 to 91%. The present values are within the range of historical records for the area. Air Quality Assessment The results of the baseline in-situ ambient air quality assessment were based on direct measurements using portable gas analyzers. The ambient air quality within and around the proposed project area was measured. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 80 Table 6-3 Air Quality Measurements Coordinat AQ1 AQ2 AQ3 AQ4 AQ5 AQ6 AQ7 AQ8 AQ9 AQC Rang FMEnv WHO e e Limit Limit (µg/m3) Oxygen 20.8 20.9 20.8 21.0 20.8 20.9 20.8 20.8 21.0 21.0 20.8 N/A N/A (ppm) – 21.0 Carbon <0.0 <0.0 <0.0 1.0 1.0 <0.0 <0.0 <0.0 <0.0 2 <0.0 10.0 N/A monoxide 1 1 1 1 1 1 1 1 – (ppm) 1.00 Hydrogen <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 0.008 N/A Sulphide 1 1 1 1 1 1 1 1 1 1 1 (ppm) Sulphur <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 0.05 <0.0 0.1 125 oxide 1 1 1 1 1 1 1 1 1 1 (ppm) Nitrogen <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 0.04 <0.0 0.06 200 oxide 1 1 1 1 1 1 1 1 1 1 (ppm) Hydrocar <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 <0.0 N/A N/A bon 1 1 1 1 1 1 1 1 1 1 1 (ppm) TSPM 2.5 2.5 4.0 4.0 3.00 1.5 4.5 3.0 2.0 5.0 1.5 – 250 N/A (µg/m3) 5.0 Source: Field Survey 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 81 The levels of the air quality measured are shown in Table 6.3. Gases measured were below the threshold of detection with the exception of CO. All concentrations were within the Federal Ministry of Environment and WHO limit for gaseous pollutants. The level of suspended particulate matters was low ranging from 1.5 to 5 µg/m3, and the values are below the threshold limits set by the FMEnv and WHO. Field Work Meteorological Measurements Air quality often depends on a combination of meteorological conditions and cumulative local emission sources. Temperature records are important in air quality studies as it determines the stability conditions of the atmosphere and hence the dispersion rates of air pollutants. The prevailing meteorological conditions are shown below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 82 Table 6-4 Prevailing Meteorological Conditions Coordinate AQ1 AQ2 AQ3 AQ4 AQ5 AQ6 AQ7 AQ8 AQ9 AQC Range Pressure 968 967 966 968 969 968 967 968 967 968 967 – 968 (mbar) Temperature 25.3 26.1 26.5 24.0 25.1 26.2 24.8 25.3 25.7 27.6 24.0 – 27.6 (0C) Relative 86 92 94 95 91 90 82 78 76 71 71.0 – 95.0 Humidity (%) Speed 0.2 0.1 0.2 0.1 0.4 0.1 0.3 0.2 0.4 0.1 0.1 – 0.3 (m/s) Wind SW S S SW SW SW SW S S SW N/A Direction Source: Field Survey 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 83 Noise Level Assessment The results of the ambient noise level survey are as shown in Table 6-5 with comparison to NESREA and WHO standards and guidelines. Noise levels ranged from 32.9 to 39.8dBA. Noise level readings were within the NESREA and WHO limit (55dBA) for residential area. In general, the measured noise levels are representative of typical rural area. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 84 Table 6-5 Noise Level Measurements Param AQ AQ AQ AQ AQ AQ AQ AQ AQ AQ Range NESREA WHO eter 1 2 3 4 5 6 7 8 9 C Limit Limit (dBA) Noise 32. 35. 34. 36. 35. 36. 36. 34. 33. 39. 32.9 – 55 55 (dBA) 9 6 4 9 1 3 0 2 5 8 39.8 Source: Field survey 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 85 Table 6-6 Maximum Permissible Noise Levels for General Environment FACILITY Maximum permissible Noise Limits dB (A) (Leq) DAY NIGHT Any building use as hospital, convalescence home, 45 35 home for the aged, sanatorium and institutes of higher learning, conference rooms, public library, environmental or recreational sites. Residential buildings 50 35 Mixed residential (with some commercial and 55 45 entertainment) Residential+ industry or small scale production + 60 50 commerce Industrial ( outside perimeter fence) 70 60 Source: National Environmental Noise Standards and Control Regulation 2009. Table 6-7 IFC Noise Limits Noise Level Guidelines One Hour LAeq (dBA) Receptors Daytime 07:00-22:00 Nighttime 22:00-07:00 Residential, Institutional, Educational 55 45 Industrial; Commercial 70 70 Source: IFC General Guidelines ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 86 Land Use and Land Cover The land uses in the project area and their spatial coverage were ascertained by physical observation and studying topographic maps of the area. The various uses to which land in the study area is put include secondary forest, cultivated agricultural lands, fallow lands and commercial facilities (sawmill), etc. The land-cover types in the study area were Forest I (undisturbed), Forest II (disturbed) and Built up/bare soil with 0%, 80% and 20% respectively. The Land cover types within study area are shown in Figure 6-4. Forest Landcover (undisturbed 0% Built up/bare 20% Forest (disturbed) 80% Figure 6-4 Land Cover of Proposed Project Area Soils Kabba soil is embryonic in nature with few diagnostic horizons; ground water is within 100cm of the mineral soil surface (56cm water table). The colour matrix hue is 10YR and ESP of 35% or more within 50cm mineral surface. All these characteristics classify the soil as Typic Halaquept (USDA) and Eutric Gleysol (FAO, 1974) because of >50% Base Saturation as stated by FAO/UNESCO soil classification system while at series level it was classified as Oshun series. Clayey texture in Kabba is a characteristic of wetland soil and that probably gives its characteristically high water table at 56cm during the dry period of the year. High sand content coupled with heavy rainfall may have resulted in the exchangeable cations being leached out of the profiles. Figure 6-5 Toolbox meeting before Figure 6-6 Geotechnical and soil sampling ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 87 commencement of sampling Soil samples from each of the top (0-15cm deep) and bottom (15 – 30cm deep) layers were collected with the aid of an auger from ten stations of the quadrant specified in the sampling protocol. The soil characteristics are shown below. Table 6-8 Soil Characteristics Top Bottom Etisalat EIA November 2012 Parameter Range Mean Range Mean pH 5.7-8.38 6.66 4.5-8.72 6.771 6.82 Conductivity, µs/cm 12-1864 298.422 6.32-14.8 2.08 NA TOC, mg/kg 0.81-28.8 22.517 1.38-28.8 22.517 NA Phosphorus, mg/kg 0.5-1.89 1.021 2.5-53 16.682 0.8 Sulphate, mg/kg 10-16 12.5 <0.001 <0.001 58 Nitrate, mg/kg 0.3-1.6 0.58 0.2-11.118 8.3371 8.92 Potassium, mg/kg 3.49-7.12 5.6185 1.9-6.4 4.1995 0.56 Vanadium, mg/kg <0.001 <0.001 <0.001 -0.0323 0.009125 <0.001 Nickel, mg/kg 0.53-2.64 1.4332 0.72-2.01 1.1323 0.09 Lead, mg/kg <0.001 -0.124 0.124 <0.001 <0.001 0.01 Chromium, mg/kg 0.006-0.045 0.025 0.012-0.072 0.03 <0.001 Zinc, mg/kg 0.624-5.39 2.0356 0.576-9.4 2.7334 NA Cadmium, mg/kg <0.001 -0.538 0.4704 <0.001 -0.52 0.50875 NA ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 88 Iron, mg/kg 1.056- 74.4 15.8823 1.206-37.4 12.9972 0.50 Arsenic, mg/kg <0.001 <0.001 <0.001 <0.001 <0.001 Mercury, mg/kg <0.001 <0.001 <0.001 <0.001 <0.001 Manganese, mg/kg 0.5-3.52 1.923 0.5-3.55 2.118 1.20 Copper, mg/kg 0.003-0.027 0.011-0.119 0.0383 0.05 PCB, mg/kg <0.001 <0.001 <0.001 <0.001 NA THC, mg/kg <0.001 <0.001 <0.001 <0.001 2.10 Source: Field Survey 2015, Etisalat ESIA 2012 Figure 6-7 Biophysical sampling at Site Figure 6-8 Briefing session with LG Chairman Geology The study area is dominantly underlain by the Precambrian basement complex. However part of the area is underlain by cretaceous sediments which unconformable overlie the basement complex. Migmatite covered about half of the study area outcropping at the southwest, west, northwest and central part of the area. The south and the southeast parts of the area are underlain by undifferentiated older granite, mainly porphyroblastic granite, granite gneiss with porphyroblastic gneiss and fine grained biotite granite. The northern part of the study area is made of ridges of cretaceous sediments of the southern Bida Basin (Lokoja Sub-Basin) the ridges are dominantly composed of feldspathic sandstone and siltstone which are separated by the biotite homblende gneiss. Thick alluvial deposit occurs around the river along Ohie road close to Kabba School of Agriculture drainage system. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 89 Hydrology Kabba is characterized by undulating topography with limited flat terrain. Kabba as well as Lokoja are high lands with a linear NW-SE ridges and altitude of about 440m both following the basin trend and perpendicular to the main axis of the Benue trough (Falconer, 1911). These highlands are capped by indurated and ferruginous sandstones. They also extend across the Niger River towards Bassa and terminating around Gboloko- Monzum area. The eastern, southwestern and southeastern parts of Kabba area have altitudes ranging between 50 meters and 90 meters, and are underlain by basement rocks. The study area falls within crystalline and small sedimentary hydrogeological provinces. The study area is close to Lokoja which is the confluence point of the River Niger and River Benue. The Niger River rises in Guinea and flows through Mali, Niger, and Nigeria before reaching the Atlantic Ocean. The River Benue flows west from the Cameroon and joint the Niger River at Lokoja. Ground Water The ground water availability in crystalline rocks in the area is greatly dependent on the degree of weathering and fracturing of the rocks and the interconnectivity of the fractures. The aquifers found in this area are recharged directly by precipitation but can also be recharged by infiltration from tributaries of River Niger and River Benue. Aquifers found within the study area include the fractured basement aquifer and the weathered overburden aquifer. Ground water abstraction is mainly by hand dug wells, boreholes and especially from springs. Table 6-9 Groundwater Analysis Parameters BH1 (Sawmill) FMEnv Limit WHO limit pH 8.02 6.5 - 8.5 6.5 - 8.5 Temperature (oC) 29.1 N/A N/A EC (mg/l) 329 7.5 N/A Turbidity (NTU) 4.5 1.0 5.0 Hardness (mg/l) 164 200 500 BOD (mg/l) 1.10 0 N/A COD (mg/l) 5.25 0 N/A ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 90 TDS (mg/l) 163 N/A N/A TSS(mg/l) 3.5 10 N/A Sulphates (mg/l) <0.01 500 250 Nitrates (mg/l) 0.003 10 N/A Phosphate 0.76 >5.0 N/A Pb (mg/l) <0.001 0.05 N/A Cd (mg/l) <0.001 0.01 N/A Cr (mg/l) 0.008 0.05 N/A As (mg/l) <0.001 0.2 N/A Cu (mg/l) 0.024 0.1 1 Fe (mg/l) 0.765 1 0.3 Zn (mg/l) 0.364 5 4 Ni (mg/l) 0.050 0.05 N/A Hg (mg/l) <0.001 0.001 N/A PCB (mg/l) <0.001 <0.001 0 Mineral oil (mg/l) <0.001 <0.001 0 Total Coliform cfu/100ml 0 0 0 Faecal Coliform, cfu/100ml 0 0 0 Source: Field survey 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 91 A hand dug well at the sawmill approximately 400 metres from the proposed site was sampled to ascertain the quality of groundwater within the area. Water for domestic use should have a pH between 5.5 and 9. The pH levels of the groundwater sample collected from the hand dug well at the sawmill was 8.02. This value indicates pH being basic and water can form scaling on pipes but it is within the FMEnv and WHO permissible limit (6.5-8.5). The groundwater sampled recorded hardness value of 164mg/l. The water is high in dissolved minerals, specifically calcium and magnesium. Hard water is not a health risk, but a nuisance because of mineral buildup on fixtures and poor soap and/or detergent performance. The turbidity of the groundwater collected from the sawmill hand dug well is 4.50 NTU. The stipulated limit by WHO for the turbidity of groundwater is 5NTU. The heavy metal concentrations complied with the regulatory limit. Surface Water Water samples were collected from the project area from different sources that include water course, wetland, streamlets and control samples from Kabba River. The summary of the physicochemical characteristics of surface water bodies around site axis during the field data gathering are presented in Table 6-10. Table 6-10 Surface Water Analysis Source: Field Survey 2015 Standards in µg/l converted to mg/l SWC FMEnv Limit for Parameters SW1 streamlet SW2 wetland Surface water River (Aquatic Life) pH 7.4 8.4 8.2 6.0 – 9.0 Temperature (oC) 26.3 27.4 26.3 20 – 33 DO (mg/l) 7.85 7.91 6.12 6.8 TDS (mg/l) 26 24 33 NS Conductivity (µs/cm) 52 48 66 NS Turbidity (NTU) 18.2 6.5 5.6 NS BOD (mg/l) 6.47 3.64 5.8 4.0 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 92 COD (mg/l) 11.4 21 10.58 NS TSS(mg/l) 0.026 0.19 0.82 NS Sulphates (mg/l) 0.27 0.34 0.046 NS Nitrates (mg/l) 0.18 0.16 0.168 NS Phosphate (mg/l) 2.4 2.1 3.2 NS Pb (mg/l) <0.001 <0.001 <0.001 0.0017** Cd (mg/l) <0.001 <0.001 <0.001 0.0002 – 0.0018** Cr (mg/l) 0.002 <0.001 0.046 0.02 – 2.0 As (mg/l) <0.001 <0.001 <0.001 0.5 Hg (mg/l) <0.001 <0.001 <0.001 0.001 Fe (mg/l) 1.216 1.124 2.450 1.0 Zn (mg/l) 0.468 0.425 0.562 0.03 Ni (mg/l) 1.124 1.428 1.246 0.025 – 0.150** Cu (mg/l) 0.67 0.130 0.210 0.002 – 0.004** PCB (mg/l) <0.001 <0.001 <0.001 NS Total Hydrocarbon Content (mg/l) <0.01 <0.01 <0.01 NS Total Coliform (cfu/100ml) 38.0 56 10 Nil Faecal Coliform (cfu/100ml) 21 36 4 Nil ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 93 Speed (m/s) 0.8 0.5 2.60 NA Volume (m3/s) 0.11 0.03 124.9 The pH generally ranged from 8.14 to 8.19 with the mean value being 8.16. Water samples in the area were analyzed for heavy metals to determine their concentration and possible contamination of the environment. The heavy metals of interest are, Copper (CU), Zinc (Zn), Iron (Fe), Cadmium (Cd), Lead (Pb), Chromium (Cr), Manganese (Mn), Vanadium (V), Arsenic (Ar), Mercury (Hg), Nickel (Ni) and Barium (Ba). The speed of the two surface water sampled around the project area ranged from 0.5 – 0.8 m/s which is considered slow due to low volume of water and nature of the water course. The Kabba River (Control) recorded a high speed of 2.6 m/s. Factors that increased the speed of the Kabba River included the slope gradient and the roughness of the channel. Figure 6-9 Bridge over river sampled for Figure 6-10 Erosion control point along river control Sediment The physical and chemical parameters of the sediment samples are given in Table 6-11. The sediment pH was acidic (4.891km Sound Level in dB(A) 64 58 52 46 40 34 28 ~20 This is attenuation with distance based purely on the Inverse Square Law. If one includes for ground scrubbing and atmospheric absorption the sound levels will be much lower. However ground scrubbing will not occur immediately next to the transformer as it is located in a concrete paved or gravel yard with no vegetation. To be detectable the noise level needs to be comparable with the ambient, and to be intrusive noise level needs to be 10dB(A) higher than the ambient. The International Finance Cooperation (IFC) Environmental Noise Management Standard states that noise impacts should not increase background levels by 3 dBs at the nearest receptor location off-site. IFC also gives standards for different Land Uses. (Table 9-3) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 128 Table 9-3 IFC Guidelines Noise Level Guidelines One Hour LAeq (dBA) Receptors Daytime 07:00-22:00 Nighttime 22:00-07:00 Residential, Institutional, Educational 55 45 Industrial, Commercial 70 70 The WHO guidelines for nightime noise recommend less than 40 dB(A) outside of bedrooms to prevent adverse health effects from noise. The FMEnv standard is given below : Table 9-4 Maximum Permissible Noise Levels for General Environment FACILITY Maximum permissible Noise Limits dB (A) (Leq) DAY NIGHT Any building use as hospital, convalescence home, home for the aged, sanatorium and institutes of higher 45 35 learning, conference rooms, public library, environmental or recreational sites. Residential buildings 50 35 Mixed residential (with some commercial and 55 45 entertainment) Residential+ industry or small scale production + 60 50 commerce Industrial ( outside perimeter fence) 70 60 Source: National Environmental Noise Standards and Control Regulation 2009. The FMEnv standards are given in Leq dB(A). Noise may be classified as steady, non-steady or impulsive 39 . Steady noise is a noise with negligibly small fluctuations within the period of observation. A non- steady noise is when sound levels shift significantly. This can be intermittent noise. Fluctuating noise 39 ISO 12001 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 129 changes continuously. Tonal noise is characterised by one or two single frequencies. This noise is more intrusive than than broadband noise. In order accommodate the changes the descriptor Leq is used which is the single value equivalent to the weighted average of the period of observation. FMEnv stipulate standards in Leq. As transformers emit tonal and broadband steady noise and transformer noise is continuous the short term SPL is the same as the Leq. Ambients were measured on site and were typically 55dB(A) daytime. One can assume that nighttime ambients are 10dB less than daytime so a target noise level of 45dB(A) at the perimeter of the site would be a good standard. The site is currently a greenfield site and the nearest residential developments are several kilometers away. However the noise standard for operation should assume that development may take place in the future and buildings may be constructed right up to the TCN boundary. One would hope that the local government planners would discourage noise sensitive dwellings, or residential properties, immediately adjacent to the site. Transformers are usually located next to the access road to allow transfer of oil and access for fire engines. This means they are close to the perimeter but TCN activities should not cause noise intrusion beyond the perimeter of their site. Taking a target noise level of 45dB(A) at the perimeter of the site, based on the Technical Specification and measured levels, it is recommended that transformers should not be located within 80m of the boundary of the site. This is a worst case scenario. Following this recommendation would ensure no complaints over noise intrusion both during the night time and during daytime during operation. It also allows a margin for intensification of use in the future. Corona Discharge One of the phenomena associated with all energized electrical devices, including high-voltage transmission lines, is corona. The localized electric field near a conductor can be sufficiently concentrated to ionize air close to the conductors. This can result in a partial discharge of electrical energy called a corona discharge, or corona. Corona occurs on all types of transmission lines, but it becomes more noticeable at higher voltages (345 kV and higher). Under fair weather conditions, the audible noise from corona is minor and rarely noticed. During wet and humid conditions, water drops collect on the conductors and increase corona activity. Under these conditions, a crackling or humming sound may be heard in the immediate vicinity of the line. Corona results in a power loss. Power losses like corona result in operating inefficiencies and a major concern is reduction of losses. TCN will take all practical steps to reduce corona discharge and the noise impacts are not considered to be significant. 9.2 Electromagnetic Fields (EMF) Sources of EMF There are various naturally occurring magnetic fields in the environment such as the Earth’s magnetic ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 130 field. Every live conductor or piece of equipment, from high-power electric lines to domestic appliances, generates electrical and magnetic fields around itself. Electric and magnetic fields act independently of each other and are measured separately. Voltage generates electrical fields, and the higher the voltage, the stronger the resulting field. Electrical field strength is measured in volts per metre (V/m), or kilovolts per metre (kV/m). Magnetic fields are caused by current, the higher the current, the stronger the magnetic field. Magnetic field strength is usually given as the density of the magnetic field, for which the measurement unit is Tesla (T), millitesla (MT) or more usually micro-Tesla (μT). Powerlines come in different configurations. The highest power ones (>400kV) are the long-distance lines from the generating power station to the places where the power is needed. The pylons supporting these power cables are large, metal structures, which have long strings of insulators from which the cables hang. The smallest 230 volt lines start from local substations and supply the power needs for a relatively small area. In between these two extremes are a variety of other types of lines carrying different voltages. The strength of the fields around overhead power lines depends on the voltage and on how much current is passing through the line at a given time. The field is stronger in the immediate vicinity of the line, and further away decreases significantly. The strength of the electrical field is affected by the height of the mast, the layout of the wires on the mast, and the number of sections of the mast. There are two types of electromagnetic fields (EMFs) associated with powerlines; electric fields and magnetic fields. These are at their highest to either side of the central cable of large lines, and underneath the cables of smaller lines. The EMFs come from the cables, not the pylons as the pylons are insulated from the fields generated. As one moves away from the line, the fields begin to drop away. How far they extend depends on the line voltage for the electric field, and the power being supplied for the magnetic field. This is shown on Figure 9-6 below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 131 Figure 9-6 Magnetic Field Strenght Below Power Line The ICNIRP (International Commission of Non ionizing Radiation Protection) recommends that in places where there is regular human presence, the electrical fields from power lines may not under normal circumstances exceed 5 kV/m and the magnetic field must not exceed 100 μT. The same limits are also given in the recommendations of the Council of the European Union. This means there is no reason to restrict activities such as fruit picking, farming or forestry near or under overhead lines. The same limits apply to domestic situations. This is shown on Figure 9-7 below. Figure 9-7 Recommended Magnetic Fields at Different Location ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 132 There are limits set for the maximum strength of electromagnetic fields in residential areas. If the electrical and magnetic fields strengths remain within the limits, there is no negative impact on human health. Induced Effects The electromagnetic fields caused by overhead lines can induce currents and voltage in conductive objects near the line. Induction is also possible in long metal structures such as communications equipment, fences, pipes, or lines near the power lines, or in large objects such as roofs, tanks or large trucks. Earthing Most of the effects of induced voltage are found in metal structures and objects that are not well earthed, and every conducting part of such structures needs to be properly earthed. Long metal structures which are earthed in one or several places and stand parallel to electrical wires, must be repeatedly earthed at appropriate intervals, or interspersed with insulating elements in order to reduce the size of the possible electrical flows. Screening Electric fields from substation equipment are unlikely to extend beyond the equipment housing, as they are screened by practically all building materials. For all practical purposes magnetic fields cannot be stopped and will travel through walls. Buildings and some trees reduce electric fields, but magnetic fields travel through most materials. EMF and Health The issue of EMF and health effects has been extensively reviewed over the past 30 years by Australian and international inquiries and expert panels established for the purpose of trying to determine whether or not human exposure to EMF is related to adverse health effects. Consistently, there is no scientific evidence to conclude that EMF causes cancer or any other disease. There has been a lot of research on whether exposure to ELF (Extremely Low Frequency) EMF from electrical sources below the exposure limits causes any health effects. Most of the research indicates that ELF EMF exposure normally encountered in the environment, including in the vicinity of powerlines, does not pose a risk to human health. However, there are some epidemiological (population) studies that have reported a possible association between prolonged exposure to ELF magnetic fields at levels below the exposure limits but higher than what is typically encountered and increased rates of childhood leukaemia. Based largely on this limited evidence the International Agency for Research on Cancer has classified ELF magnetic fields as possibly carcinogenic to humans. (The term "extremely low" is described as any frequency below 300hertz as opposed to high frequency such as microwave.) EMF contain both electric and magnetic field at 90 degree phase difference. The electric field can cause ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 133 oscillations in human cells at high frequency, causing them to heat up. Similarly the varying magnetic field induces an electric current in human cells and tissues. Thus high-power EMF can damage body cells. (This of course is the principle behind a microwave oven) Studies have been done on people that live within 300 meters of a substation.40 There is some evidence to suggest an increased risk of some type of cancer. However, the evidence has not been conclusive.41 The IARC classification of ELF magnetic fields reflects the fact that some limited evidence exists that ELF magnetic fields might be a risk factor for childhood leukemia.42 However, the vast majority of scientific 43 research to date does not support a link between ELF magnetic field exposure and human cancers. The IARC44 has classified ELF magnetic fields as "possibly carcinogenic to humans". At present, the evidence of a possible link between ELF magnetic field exposure and cancer risk is far from conclusive and more research is needed to clarify this "possible" link. Health Canada is in agreement with both the World Health Organization and IARC that additional research in this area is warranted. The relevant Australian regulatory authority, the Australian Radiation Protection and Nuclear Safety Agency (ARPANSA), concludes that “On balance, the scientific evidence does not indicate that exposure to 50 Hz EMFs found around the home, the office or near power lines is a hazard to human health” (Australian Radiation Protection and Nuclear Safety Agency 2003). There are currently no Australian standards regulating exposure to these fields. The National Health and Medical Research Council issued Interim guidelines on limits of exposure to 50/60 Hz electric and magnetic fields. These guidelines are aimed at preventing immediate health effects resulting from 40 Australian Radiation Protection and Nuclear Safety Agency, 2015 41 “Current standards used for radiation protection remain primarily based on acute high-dose exposures, derived from studies based on atomic bomb survivors in Japan,” IARC Director, 2015 42 Risk of Leukaemia in Nuclear Workers, International Agency for Research on Cancer , WHO, June 2015 43 “Electric and magnetic fields from power lines and electrical appliances”, http://www.canada.ca, 2015 44 Risk of Leukaemia in Nuclear Workers, International Agency for Research on Cancer , WHO, June 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 134 exposure to these fields. The recommended magnetic field exposure limit for members of the public (24 hour exposure) is 100 uT and for occupational exposure whole working day is 500 uT. EnergyAustralia operates its powerlines, substations and other electrical infrastructure well within these interim guideline limits. As the typical level underneath a power line is 10uT, adverse health impacts from EMF are not anticipated. Magnetic fields can also interfere with computers but this is not considered a likely problem on these sites. The scientific evidence does not establish that exposure to ELF EMF around near powerlines or another electrical source is a hazard to human health.45 9.3 Chemical Hazards Hazardous Materials Storage The typical chemicals found in substations include dielectric fluid, transformer oil, capacitor oil, sulphur hexafluoride and sulphuric acid. These are used to insulate and cool electrical conductors, apart from sulphuric acid which is battery acid. Dielectric fluid is a mineral oil used to cool and insulate underground transmission feeders. It is a Non- polychlorinated biphenyl (Non-PCB) oil and can possibly be ignited by electric arcs which have very high temperatures, up to 5,000°C. Transformer oil is the generic name given to the oil used to insulate and cool transformers. Its flash point is approximately 150°C. Historically, this is where PCBs have been found. Utility companies systematically remove carcinogenic PCBs from their old equipment by “retrofilling.” The transformers on the TCN site in this project are new and the procurement specification states they must be free of PCBs. Capacitor oil is a viscous insulating oil used in capacitor banks. It is Non-PCB oil and has a flash point of 140°C. Older capacitor cans may contain PCBs but the new ones for these sites will not be allowed to do 45 Australian Radiation Protection and Nuclear Safety Agency, 2015 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 135 so. Sulphuric acid is contained in the lead/acid batteries used in the backup power source. According to the TCN technical specification the batteries will be 110 volts DC. Substations typically have two battery rooms, each containing 30 to 40 car-type batteries. Each battery can hold up to 50 Litres of acid at 40% concentration. Exposure to liquid sulphuric acid is a skin hazard, but acid mist can produce respiratory injuries. Spills must be contained and treated. The TCN technical specification includes battery chargers. When batteries are charged hydrogen is released. In the event of a fire in a battery room Carbon Monoxide detectors are often used for safety checks. CO sensors are cross-sensitive to hydrogen and this can lead to false readings. Caution must be observed in interpreting readings as they may be false. Sulfur hexafluoride gas is used to insulate and extinguish arcs in circuit breakers and other electrical components. For higher voltages, gas-insulated switch gear reduces the space required around live bus. Instead of bare conductors, bus and apparatus are built into pressurized tubular containers filled with sulfur hexafluoride (SF6) gas. This gas has a higher insulating value than air, allowing the dimensions of the apparatus to be reduced. In addition to air or SF6 gas, apparatus will use other insulation materials such as transformer oil, paper, porcelain, and polymer insulators. Under normal conditions, SF6 is an odorless and colorless gas that is five times heavier than air and presents an asphyxiation hazard in below-grade confined spaces. If exposed to high heat, thermal decomposition produces two hazardous by-products, hydrogen fluoride gas and metal fluorides. Hydrogen fluoride gas (HF) gives off a rotten egg smell and desensitizes the sense of smell, so continuing exposure may make it seem as if it has dissipated. It is a respiratory hazard because in the lungs it mixes with water and produces hydrofluoric acid. Metal fluoride is a white powder which produces a sunburn type effect on the skin. All of these materials will be stored in a Hazardous Material store with strict inventory control. PCBs Polychlorinated biphenyls (PCBs) were used in transformers as dielectric insulating fluids to solve the problem of high flammability for installations in and near buildings. As their negative aspects began to be fully appreciated (high toxicity), other fluids such as silicone oils, high-temperature hydrocarbons, tetrachloroethylenes, and synthetic esters started to be used in transformers located in many of the locations where PCBs were formerly used. These fluids possessed superior fire resistance properties compared to mineral oils, although they were not as fire resistant as PCBs with the exception maybe of tetrachloroethylenes. They did not, however, with the possible exception of synthetic esters, possess biodegradability characteristics that were markedly superior to mineral oils. In the late 1990s, natural esters, a new class of fully biodegradable dielectric insulating fluids, were developed for transfo rmer applications. These vegetable-oil-based fluids meet all the requirements for a high-temperature insulating fluid with the addition of being manufactured from renewable raw materials. There are, today, a number of published industry standards and guides that cover the use of natural ester fluids in transformer applications, such as the American Society for Testing and Materials standard D6871 and the IEEE guide C57.147 in North America, and the IEC Standard 62770. Polychlorinated biphenyl (PCB) is a concern where transformer oils are used. It is reported that some old transformers in Nigeria still contain PCBs. All transformers on these sites are new with no second ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 136 hand recycling of old used transformers. All new transformers are specified as being free of PCBs. 10 Impacts due to Construction Works 10.1 Air Quality Impacts Air quality impacts during construction are likely to result from the following sources:  Dust from movement of haulage trucks and haulage of spoil for disposal  Dust from stripping of vegetation and site formation pavement during road rehabilitation  Dust from earthworks such as use of borrow pits, embankments and cut and fill  Dust from loading, unloading and construction materials from borrow pits particularly in areas where receptors (people) are present such as in villages;  Dust from concrete batching plants  Dust entrained by wind from uncovered surfaces  Minor increases in NOx and SOx from construction machinery and vehicles Air quality issues will be localized. The site at Kabba is remote from existing dwellings and thye should not be adversely affected. Mitigation The mitigation measures to protect sensitive receptors from air quality issues are :  Concrete batching plants to be located at least 300 m downwind or as far as practicable from the nearest dwellings in order to reduce the impact of fumes on humans and to be fitted with necessary equipment such as bag house filters to reduce fugitive dust emissions  Stockpiles of materials such as sand must be managed to reduce dust emissions. The location of the stockpile must be downwind of sensitive receptors. The stockpile must be sprayed with water before material is moved. If the stockpile is within 300 m of dwellings the stockpile should be covered with tarpaulins and fenced in to form a high barrier and prevent wind lifting and dispersing the materials.  Water will be sprayed on construction sites and approach roads to suppress dust in dry weather  Trucks transporting materials will be covered with automatically closing covers or tarpaulins to avoid spilling material on roads  Construction vehicles and machinery will be maintained to minimize emissions of fuel fumes  During construction the contractors will immediately clean up any mud or dusty materials left on public roads. Wheel cleaning facilities will be installed at site access points to stop carry over of materials onto roads Air quality monitoring will take place to confirm the impact of the project on air quality and identify corrective actions if needed. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 137 10.2 Water Quality Impacts Water quality impacts during construction are likely to result from the following sources:  Increased sedimentation of water courses  Accidental spills contaminating wells with oils, lubricants, paint wastes etc  Sanitation facilities such as toilets leaking into potable water source On Kabba there are no nearby water courses within range of contamination. Mitigation The mitigation measures to protect from water quality issues are :  Wells will be identified in advance of construction and demarcated to ensure vehicles and machinery does not encroach on them. Identification will require consultation with community members.  No materials will be stored within 50 m of a water course, including soil, spoil, aggregates, chemicals or other materials used during construction.  Temporary drainage provision will be made during construction to ensure that any rain storm water running off the construction areas will be controlled. It will be lead to silt traps before discharge t the natural drainage system.  Any toilet or personal washing facilities on site will have prefabricated septic tanks installed on site which discharge to a subsurface soakaway, to avoid soil contamination and smell.  Chemical and oils storage areas will be laid on a hard concrete base. Overhead protection from rain and severe weather will be provided. A perimeter kerb will be provided leading to a spill collection sump.  Fuel storage for site vehicles must be in an elevated skid mounted tank placed on a hard area with a kerb built up around it that is capable of holding 110% of the contents of the tank volume. It may have a drainage plug to allow rain water to be discharged but this must have a tap which is Normally Closed and be kept closed at all times.  Vehicle maintenance workshops, vehicle parking areas and vehicle cleaning areas must be placed at least 300 m away from the nearest water body and have surrounding drainage to ensure contaminated water does not enter a watercourse. Maintenance and cleaning activities must be on hard standing surface.  Contingency plans for control of spills of oil and other hazardous substances will be formulated and spill collection kits kept readily available. Water quality monitoring will take place to confirm the impact of the project on water resources and identify corrective actions if needed. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 138 10.3 Solid and Liquid Waste Impacts Waste impacts during construction are likely to result from the following sources:  Clearance of site vegetation. Kabba has extensive vegetation cover. This vegetation will be cleared and removed to a municipal dump site approved by local authorities.  The potential impacts arising from solid and liquid waste production and disposal will be mitigated through a number of activities defined in the EMP, and which will be incorporated in the bid documents and construction contracts. As regards removal of topsoil and underlying materials a mass balance “cut and fill budget” will be prepared so that cut material from an embankment can be reused on site to fill in low lying areas. This will minimize vehicle movement and save money in purchasing fill material. The cut and fill budget will be subject to approval by the materials engineer to confirm the materials are of suitable load bearing integrity. Mitigation The mitigation measures to protect from waste contamination issues are :  Waste removal and disposal will be subject to the waste hierarchy of reduce / reuse / recycle. Where waste materials can be reused they will be, but not if this leads to pollution.  Vegetation will be cleared and removed to a municipal dump site approved by local authorities.  Waste storage containers for worker’s general waste will be provided and emptied regularly  Hazardous liquid wastes will be kept in a dedicated store. Hazardous waste such as oily rags, old oil filters or chemical containers will be disposed of in plastic bags or sealed bins to an approved contractor.  Mud on roads will be avoided by wheel cleaning facilities at entry and exit points  Soil and overburden will be removed, stored and reused as far as possible in accordance with a cut and fill mass balance plan  Spoil will not be disposed of where it may impact on any vegetation  Topsoil will be stockpiled and used for later landscaping  Municipal type waste such as foodwastes, paper, cardboard, clean wood and other materials will be collected in bins and emptied regularly to a municipal waste tip to avoid encouraging vermin and rodents.  Temporary waste storage will be in an area kept as dry as possible with a lightweight roof to keep off rain.  Burning of waste will be prohibited at all times.  It has been noted on some sites that wastes are dumped by residents. The contractor will not be responsible for this in the future and this process will have to be terminated. However existing wastes on site will be removed by the contractor. Waste disposal monitoring will take place by visual inspections of the sites on a regular basis by the construction supervision inspectors. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 139 10.4 Noise Impacts The major sources of noise pollution d u r i n g c o n s t r u c t i o n are removal of existing surface vegetation and overburden and site formation. At Kabba the site has a pronounced gradient and so a platform will be constructed. This will require the use of equipment such as excavators, graders, vibratory rollers for compaction, general site equipment such as generators and a batching plant. Jackhammers may be necessary for breaking up stubborn soils but as there are no elevated structures intended, deep foundations will not be built. Consequently there should be no need for impact piling. No rock will be extracted other than by excavators so no blasting will take place. The general movement of construction vehicles for haulage of removed over burden and delivery of construction materials will create noise and vibration. As regards removal of topsoil and underlying materials a mass balance “cut and fill budget” will be prepared so that cut material from an embankment can be reused on site to fill in low lying areas. This will minimize vehicle movement and save money in purchasing fill material. The cut and fill budget will be subject to approval by the materials engineer to confirm the materials are of suitable load bearing integrity. Table 10-1 indicates noise levels for construction machinery.46 Construction activities could reasonably be expected to produce noise levels up to 90 dB(A) within 5 m of machinery. For the project, no receptors other than construction workers will be this close to the machinery, and they will be required to wear appropriate PPE. Noise from Construction Equipment and Operations, Building Equipment and Home Appliances. US- 46 EPA. December 2011. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 140 Table 10-1 Construction Machinery Noise Noise Emission Level (dBA) at Distances (m) from Equipment Equipment 5 10 15 20 40 60 80 100 150 200 300 1 Bulldozer 86 80 74 68 64.5 62 60 56.5 54 50.5 2 Excavator 84 78 72 66 62.5 60 58 54.5 52 48.8 3 Loader 90 84 78 72 68.5 66 64 60.5 58 54.5 4 Land scraper 90 84 78 72 68.5 66 64 60.5 58 54.5 5 Mixing Equipment 87 81 75 69 65.5 63 61 57.5 55 51.5 6 Roller 87 81 75 69 65.5 63 61 57.5 55 51.5 7 Vibratory roller 86 80 74 68 64.5 62 60 56.5 54 50.5 8 Backhoe 81 9 Compactor 82 10 Concrete mixer 85 11 Crane (mobile) 83 12 Generator 81 13 Jack hammer 88 14 Paver 89 15 Pneumatic tool 85 16 Pump 76 17 Shovel 82 18 Truck 88 The loudest piece of equipment is the jack hammer with a noise level of 90dB(A) at 15m. The Inverse Square Law (ISL) states that sound levels drops at the rate of 6dBs / doubling of distance which would give the Table 12-2 below. Table 10-2 Sound attenuation with Distance Distance from Source in m. 15 30 60 120 240 480 960 ~1km Sound Level in dB(A) 90 84 78 72 64 58 52 ~50 This is attenuation with distance based purely on the ISL. If one includes for ground scrubbing and atmospheric absorption the sound levels will be much lower. To be detectable the noise level needs to be comparable with the ambient, and to be intrusive noise level needs to be 10dB(A) higher than the ambient. Given a daytime ambient of typically 55dB(A) activities that are more than 200 metres from noise sensitive dwellings should not be intrusive. This comment relates to the noisiest activity. Other activities will be quieter than this. The site at Kabba does not have any noise sensitive receptors closer than 250 metres at the moment and noise from construction impacts is not expected to be a nuisance. Noisy activities will not be continuous and the sources will move around the site. Also noisy activities will be limited to daytime hours 0700 to 1900 so there should be no sleep disturbance. Sometimes it is necessary to carry out activities on site which cannot be interrupted, such as concrete pouring. If it should be necessary to work at night, or in close proximity to the site boundary, then a public ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 141 information campaign is essential. Sound levels are only considered intrusive if residents object, and if they are advised in advance in a respectful manner, told how long the activity will take and their indulgence requested, they are likely to agree without protest. This issue is dealt with in more detail in the CEMP. In connection with vehicle movement is safety to residents, particularly children. Noise is an issue here because often audible warning devices are fitted to vehicles particularly when reversing and residents should be made aware of the safety considerations. There will be no impact piling. Ground surface vibration may be caused from the use of heavy construction machinery. Tracked plant such as bulldozers and vibratory rollers m a y cause vibration, more so than rubber wheeled plant such as dumper trucks. However it is anticipated that the receptors are unlikely to be significantly adversely affected by vibration as generally over 20 m from the construction, the vibrations in buildings are beyond human perception47. Mitigation The potential noise impacts will be mitigated through a number of activities which will be defined in the ESMP. These will be incorporated in the bid documents and construction contracts and are :  Source Control Maintain all exhaust systems in good working order; undertake regular equipment maintenance, enclose stationary equipment such as generators where practicable and reduce vehicle speeds around sensitive receptors such as dwellings and schools.  Siting Locate sites for concrete-mixing, batching plants and similar activities at least 500 m away from sensitive areas. 47Martin, D (1977) Transport and Road Research Laboratory, UK. . Ground vibrations caused by road construction. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 142 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 143  Timing Operate between 7am-7pm only and reach an agreement with nearby residents regarding the timing of heavy machinery work, to avoid unnecessary disturbances.  Community notification In advance of construction, representatives from religious buildings, schools and village leaders will be consulted on the timing of construction so key ceremonies, exam times, or other significant events so that impacted upon them are as little as possible.  Consultation and engagement Set up procedure for handling of noise complaints through the Grievance Redress Mechanism and continually seek suggestions from community members to reduce noise intrusion. Potential sensitive receptors in residential areas, businesses, religious buildings and schools may be exposed to short term impacts. With the above mitigation measures in place, potential noise impacts during the construction stage are anticipated to be acceptable. In addition, during construction, noise monitoring will be undertaken near sensitive receptors in order to identify corrective action if needed. 10.5 Fauna Impacts No endangered species or animals of special scientific interest have been detected on the sites during the baseline studies. Removal of the vegetation will not impact on the habitats of any animals. None the less steps will be taken to protect endemic commonly appearing species on the site. The project will not have any impacts on fish. Mitigation Contractors will issue instructions to their staff and workers that no capturing or animals particularly birds is allowed on site for eating or any other purposes. Anyone caught doing so can face dismissal. 10.6 Flora Impacts No rare plant species or flowers, shrubs and trees of special scientific interest have been detected on the sites during the baseline studies. However controls will be exerted on the site over taking vegetation. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 144 Mitigation No open burning will be allowed on site. Workers will not be allowed to use local wood for cooking. Cooking services will be provided in the canteen facilities. 10.7 Cultural Resources Impacts There are no religious buildings or cultural monuments in the vicinity of the sites. No archaeological remains have been identified during the baseline study but should any be found during construction steps will be taken to preserve them. Mitigation If any archaeological remains are uncovered during construction the “chance find” procedure will be invoked. All excavations must stop immediately and the nearest representative of the department of antiquities be notified. Further instructions will be taken from them. This will be considered as a valid claim from the contractor for an extension of time. 10.8 Occupational Health and Safety Impacts The contractors may be exposed to occupational risks during construction work. Risks will arise from a range of hazards such as the use of heavy plant and working with rotating tools. These issues are dealt with in detail in the ESMP Mitigation The civil works contractors must implement adequate precautions to protect the health and safety of construction workers. The occupational health and safety risks will be minimized by not only providing adequate personal protective equipment (PPE) but ensuring workers wear it. In addition, the contractors will undertake the following activities:  An Environment Health and Safety Officer (EHSO) will be appointed prepare a Health and Safety Management Plan, to implement the HSMP and ensure that the requirements of the EMP are met.  The EHSO will ensure that the HSMP is submitted to TCN prior to construction for approval, that accurate records and reports of any occupational health and safety incidents are kept, and reviewing the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.” ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 145 10.9 Community Impact In public consultations anxieties were expressed over the following issues :  Influx of foreign workers and clashes with local residents  Complaints being made but ignored  Risks to the public from heavy machinery and traffic Mitigation The following activities will be undertaken in order to minimize impacts on the community during construction :  To minimize the number of foreign workers being brought to the site, the contractor will be required to hire unskilled labor from local people if they wish to be hired. It is accepted that the contractor may insist in using his own labor for skilled jobs. He must offer employment to women if they are agreeable. He must be able to show from his records that he has done this. This will be a contract condition and so is enforceable.  A “Complaints Mechanism” will be set up and a complaints officer appointed so that any complaints are responded to within 24 hours in a polite and respectful way.  The contractor will be required to prepare a traffic management scheme and submit to the client for approval before occupancy of the site is given to them.  To ensure safety warning signs and fencing will be erected at the construction sites and around borrow pits, in full view of the public, warning people of potential dangers such as moving vehicles, and excavation to raise awareness on safety issues.  Heavy machinery will not be used after day light and all such equipment will be returned to its overnight storage area/position before night.  All sites including storage areas will be made secure, discouraging access by members of the public by fencing when appropriate. In particular children will be warned not play on the sites, especially after dark. 10.10 Pedestrian Road Safety Impacts During construction, there may be a risk to members of the public from hazards such as the use of heavy machinery, excavations, and changes in traffic priorities. The site at Kabba is not near to residential dwellings. Mitigation A traffic management plan will set out safe access during construction. Clear signs will guide and advise other road users. Road control staff will be deployed if necessary when heavy vehicle are turning across traffic particularly on steep hills such as at Kabba where approaching traffic may be travelling fast ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 146 downhill. The community will be involved in road safety with requests for schools, churches and mosques to reinforce the message on safety throughout the communities. In particular children will be warned not play near the access roads when vehicles are passing, especially if it is after dark. 10.11 Utilities Provision Impacts The project may require the relocation of electricity cables which may lead to interruption of electricity supplies for local residents. Mitigation Any disruption will be discussed with utility operators and the community beforehand. People affected will be informed in advance of any power cuts and the duration of the cut will be made clear in order that they can plan around the lack of power. 10.12 General House keeping Impacts When dealing with environmental controls on a construction site it is not possible to detail in writing every possible occurrence. Therefore as a general rule contractors should practice “good housekeeping”. The site should be kept clean and tidy, spills should be mopped up as soon as they occur, rubbish should be collected and removed promptly and tools and equipment stored away neatly when not in use. More details will be given in the ESMP Mitigation The concept of “good housekeeping” is easy for anyone to understand, even those of a non-technical nature. The contractor’s staff are expected to behave in a responsible way and not wait to be told what to do on every occasion. They will benefit from Good Housekeeping as a clean well run site is less likely to have industrial accidents. Monitoring will be by visual inspection by the construction supervision consultants. . 10.13 Potential Socio-economic Benefits Impacts During the construction phase there may be positive impacts. The projects may provide short term local employment opportunities for community members in terms of site clearance, excavation, loading and offloading of materials. Other short term opportunities are likely to arise from the provision of security services where temporary camps or stores are erected and from opportunities to provide goods and services to construction workers e.g. food kiosks and other shops. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 147 Mitigation If impacts are positive mitigation is not required. However the positive impacts will be enhanced by preferentially offering jobs to local labor and encouraging contractors to purchase local produce. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 148 11 Impacts due to Commissioning Phase 11.1 Commissioning Activities The commissioning process is a critical phase in the project development. The assembly of transformers, circuit breakers, CCVTs, circuit switchers, capacitors, and disconnect switches must be closely watched and tested to ensure proper assembly. This is especially true for transformers since their future trouble- free operation is very dependent on proper handling during assembly. The process involves the following tasks related to transformers: • Perform transformer inspection when received • Observe transformer assembly (dress out) • Carry out oil filling procedure • Check operation • Check pumps, fans and heaters • Confirm operation of gauges, relays, controls and alarms • Acceptance testing The site in general must have the following items checked : • Earth grid in yard • Earthing for fences • Central oil pit for transformers • Control building inside works (air conditioning units, water/ sewage supply, electrical installation, painting, building furniture ) • Supplying fire extinguisher • Installation of emergency lights system • Battery rooms • Civil works roads, side-walks, fences, guard towers • Installation of water pumps • Installation of water supply and sewage connection • Padlocks for all outdoor cubicles e.g. circuit breaker cubicles) • Ensure all wastes removed from site • Sanitation facilities such as toilets should be checked When the plant is operating tests of noise levels should be carried out. Transmission line structures and equipment are attractive to birds for roosting and building nests. This may occur after the structures are erected but before they are commissioned. Steps should be taken to minimize the risk of electrocution or injury to birds, of damage to electrical equipment, and of outages that may result when birds come in contact with power lines and structures. Checks should be made that there are no birds nesting before switching on. It is useful to have a final public hearing. Local people can be advised about availability of temporary work for low income residents such as drain cleaning and grass cutting. Any grievances received can be finalised. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 149 11.2 Spill Control Transformers are filled with oil during commissioning and a spill control procedure must be in place before this activity takes place. Staff must be instructed in what actions to take and what PPE to wear. If necessary temporary spill containment such as flexible kerbs should be placed around the possible spill area. Spill collection materials such as absorbent mats should be readily available and containers designated as hazardous waste bins kept nearby. If a spill does occur and is contained and collected the bins must be disposed of to a toxic waste landfill not a municipal dump. If no such facility is available then the spilled oils can be returned to the supplier. 11.3 Fires There is an inherent risk of fire during commissioning as this is the time that damaged components will be tested under real field conditions. The local fire department should be notified of the intention to activate the facility and may agree to have an appliance (fire engine) standing by at the site. Small scale fires should be tackled on site. The choice of fire retardant and flame suppressant should already have been made and suitable fire extinguishers provided. Transformers are provided with a rock filled fire trap which will allow any oil to burn out. In the event of a major fire and large volumes of water being sprayed on the site fire fighting water may become contaminated with oil. This should not be allowed to runoff into neighboring drains. Retention basins to catch oil and a collection system should have been provided. All firefighters at the scene must be aware of the potential dangers and act to safeguard themselves. If there is a fire or hazard in a TCN substation, then policy is to let it burn until a TCN representative arrives and advises on appropriate actions. The attitude “Let it burn” may sound brutal but burning electrical equipment is ruined anyway. To stop further damage water should be sprayed on adjoining plant to protect it but NOT on electrical equipment. Basic rules for enforcing electrical safety at substations are : • Evacuate the area. Keep people at least 100m away. Protect nearby dwellings to prevent fire spreading. • Avoid bringing metal or partially metal tools into the substation, and tools should not be carried over the shoulder. This will breach the allotted safe-clearance distances. • Responders should not climb but stay on the ground. Raising ladders outside the substation may not be safe. The response time of the fire appliance to reach the site should also be established for future reference. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 150 12 Impacts due to Operation 12.1 Air Quality High electric fields around power cables attract airborne pollutants, such as occur near a main road, chemical factory, sprayed fields, etc. These are then deposited downwind or in rain. Ozone may be generated around transmission lines but in low concentrations and there is no evidence of it being harmful to health. 12.2 Electro-Magnetic Fields (EMF) Electric overhead lines are considered a source of power frequency, electric and magnetic fields, which may have a perceived health effect. The strength of both electric and magnetic fields is a function of the voltage, distance from the conductors to the ground and the lateral distance from the line to the receptor. Many studies published during the last decade on occupational exposure to Electro-Magnetic Fields (EMF) have exhibited a number of inconsistencies and no clear, convincing evidence exists to show that residential exposures to electric and magnetic fields are a threat to human health. 12.3 Electrical and Magnetic Fields Safety Overhead Electrical Safety It is common to think that one has to touch an electrical conductor to get hurt. This is not true when dealing with high voltages. Substations use a high-voltage, open-air conductor —called “bus”— which resembles a 75mm conduit pipe. The metal pipes running through the overhead areas of a substation are the conductors of electricity. There are no wires inside the pipe. The electricity is carried on the pipe’s outside skin. Because of the high voltages involved, one need not touch an electrical conductor to be harmed. If close enough, the electricity will contact the person in the form of a high-temperature electrical arc. The potential for an electrical arc becomes greater as voltage increases. For this reason the safety distances must be observed. The proper clearance from the overhead bus is calculated for each station, and conductors are positioned accordingly, using a conservative distance to ensure the safety of anyone walking through a station. For 333kV, a safe distance of 6m has been established. For 11kV to 132kV a safe distance of 4m has been established. To stay safe from the electric bus inside a substation, one should not climb nor carry tools above the shoulder. Ground-Level Electrical Safety The overhead bus is not the only electrical hazard present in a substation. Many electrical hazards are found at ground level also. Safety from these hazards is maintained by restricting access to them and by placing the hazard behind locked doors, cages, and fenced-in areas. Capacitor banks reside in cages, providing a buffer zone between persons and the exposed electrical conductors. Circuit breakers are housed in locked cubicles to eliminate the chance of casual entry into these areas. Lightning arrestors and various other electrical components are placed behind fences. All such areas should have warning signs. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 151 Where a substation has a metallic fence, it must be properly grounded to protect people from high voltages that may occur during a fault in the network. Earth faults at a substation can cause a ground potential rise. Currents flowing in the Earth's surface during a fault can cause metal objects to have a significantly different voltage than the ground under a person's feet; this touch potential presents a hazard of electrocution. Underground-Level Electrical Safety Power cables can be undergrounded. Electric fields will be absorbed by the earth above a buried cable. Magnetic fields will be higher immediately above an underground cable than they will be below an overhead line, because one is are closer, but the fields reduce much more quickly from an underground cable. It should be remembered that the cost of putting cables underground can be twenty times higher than allowing them to go overhead, although less for lower voltage lines. 12.4 Vegetation Management Buried beneath the gravel in a substation yard is a grid of wires that functions as the grounding for the high voltage equipment. In order to ensure safety for utility employees and the public, it is important to prevent this ground grid from being compromised by vegetation growth. For this reason substation yards are regularly maintained by using a variety of herbicides. 12.5 Pesticides Herbicides are one branch of pesticides. Any pesticides stored on site for control of weeds, rodents or vectors (such as mosquitoes) should be should be kept in a secure storage and application should be made under controlled conditions. Technical staff and residents should be advised and workers wear PPE. 12.6 Migratory Birds The project area does not contain any natural habitats considered to be either critical or fragile. The project area does not have any wetlands or forested areas nearby or International Bird areas (IBAs) and there are no international migratory bird Flyways. 12.7 Noise If the noise produced by an operating substation is considered intrusive to adjacent property owners a barrier of mature trees or tall soil berms between the substation and nearby residences can be helpful in partially reducing the perception of noise impacts, although trees do very little in reality. Earth berms can reduce up to 7dBs but as the sound is low frequency barriers are not very effective. 1 2 . 8 Visual Appearance Light pollution may present a nuisance in residential areas. Substations may have lights that operate all night long to discourage vandalism and unauthorized individuals. New downward-focused security ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 152 lighting can help to avoid or reduce light pollution. 12.9 Spills Transformers may occasionally need oil replacement or replenishment but this is usually very infrequent. In the event of a spill the same procedure as given under Commissioning should be followed. 12.10 Fires Mineral-oil-filled transformer explosions and fires causing heavy collateral damage have raised major safety concerns. There have also been major environmental concerns over the toxic effects of uncontained mineral oil spills. This has given rise to a new class of alternative dielectric insulating fluids that have historically been developed to answer these specific concerns. Transformers are fitted with fire traps to allow oil burn out. In the event of a major fire the same fire response procedure as given under Commissioning should be followed. 12.11 HSE There must be adequate precautions to protect the health and safety of plant workers. All staff must be provided with personal protective equipment (PPE) and made to wear it. The details are given in the ESMP but in addition, the facility operators should undertake the following activities:  An Environment Health and Safety Officer (EHSO) should be appointed to ensure that the EMP is implemented  The EHSO will ensure that accurate records and reports of any occupational health and safety incidents are kept, and reviewing the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.”  Site briefings for visitors on restricted areas and emergency evacuation procedure  Induction EHS briefings for new staff  Follow NERC procedures  Implement Corrective Action Reporting (CAR) Tool box briefings Tool box briefings should be held every morning during roll call and a “safety moment” held. This need only last 2-3 minutes and a specific item can be stated, for example when hot work permits are needed, or when safety equipment is needed if working at a height. The essence of Tool Box meetings is repetition. Staff becomes complacent if not continually reminded of safety procedures. Topics can be repeated every few weeks. The topics addressed should be recorded and reported in the monthly management reports. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 153 Near Misses Near Misses are situations that arise that could have led to a safety incident but which were spotted by vigilant staff and avoided by swift action. This may be something as simple as spotting a gas cylinder propped upright without support that may fall and injure someone and insisting that it be held in a cradle on a trolley. (For example see Figures 12-1 and 12-2 below) Figure 12-1 Examples of Near Misses - Gas cylinders incorrectly stored and handled Figure 12-2 Examples of Near Misses - Gas cylinders correctly stored and handled Staff may be reluctant to report “Near Misses” as they fear a reprimand but this reluctance must be overcome. The target should be “Zero Incidents” and many “Near Misses” reported and avoided. An EHS annual report that states No Incidents and No Near Misses will not be believed. Induction Briefings New staff should be given an Induction Briefing at the start of their employment. They should be trained to identify and eliminate, isolate or minimize potential hazards in their working environment. Persons entering the site facility should be issued with personal protective equipment (PPE) and be ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 154 required to wear it. This applies to workers and visitors. Any person found not wearing full PPE should be ordered to wear it and if they refuse they should be ordered off the site. Site supervisors and security guards have the authority to do this. All staff and visitors should be briefed on and follow emergency and evacuation procedures in particular firefighting. NERC As part of normal Occupational Hygiene, Health, Safety and Environment the Nigerian Electricity Regulatory Commission Health and Safety Standards must be followed. The standards are organized into five Parts:  Part I. How to Evaluate Safety Programs;  Part II. Safety and Best Industry Practices;  Part III. Worker Safety Rules;  Part IV. Recordkeeping, Training, Inspections, Accident Investigation and Reporting;  Part V. Risk and Vulnerability Assessments As stated by The Nigerian Electric Regulatory Commission “These Standards are designed to save lives”. The practices defined are legal obligations. Each employer has a legal obligation to ensure that a safe work environment is provided to all employees, both regular and non-regular. Contractors working at substations, transmission stations, power plants or engaging in any work activities involving power generation, transmission, distribution and servicing are also required to follow the best practices and safety standards as defined by NERC. Corrective Action Reporting (CAR) If an incident takes place then it is not enough simply to report it. Steps must be taken to abate the nuisance, end the problem and to avoid it happening again. These steps should be included in Corrective Action Reporting (CAR) which is an iterative process whereby checks are made that the situation has actually been resolved in a prompt manner. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 155 13 Impacts due to Decommissioning 13.1 Impacts The transmission lines and substations are likely to remain in place for many years and therefore any decommissioning works could be a long time in the future. Towers and substations would be dismantled and removed and materials recycled/re-used as far as possible. Any areas disturbed must be restored to pre-project conditions or to conditions acceptable to FMEnv. After decommissioning the site may be handed over to a new owner and developed for another purpose. In order to avoid any contingent liability to TCN on handover, the site must be free of all encumbrances. After removal of all ancillary equipment the main issue will be potential soil contamination. This is why the soil sediments samples during the baseline are important. During the life of the installation all efforts should be made to avoid or minimize spills of potentially contaminating materials and to make strenuous efforts to clean up after any spills. After removal of all site equipment soil samples should be taken and compared with the baseline results. If the post- operative soil samples show similar or lower concentrations of parameters measured in the baseline, then the site is deemed clean and can be handed over. If the concentrations are higher, then it may be necessary to excavate contaminated soils, dispose of the contaminated material and backfill with clean soils. Therefore it is important to store the baseline soils analysis in a secure place. Potential negative impacts during decommissioning could include  Spillages of transformer oils on ground and into groundwater as equipment is removed.  Solid wastes such as brick, concrete and rubble from substation site demolition  Metals and cables from towers dismantling can become an eyesore if not taken off site either for re- use or recycling.  Invasive flora species could colonise former substation sites and the way-leave on decommissioning following removal of structures, buildings and hardcover.  Local residents could be subject to noise and air impacts during demolition. 13.2 Mitigation Environmental impacts associated with decommissioning can minimised through the implementation of an environmental and social management plan (ESMP). If the ESMP is followed faithfully then there should not be any residual environmental impacts during decommissioning. Therefore it is imperative that the ESMP is followed during Operation so that Decommissioning is not onerous. If the ESMP is not followed then remedial works or payment of compensation may have to be paid. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 156 14 ESMP - Environmental and Social Management Plan 14.1 Impacts and Mitigation The following issues have been addressed in this ESIA : • Noise • Air Pollution • Solid Waste • Liquid Wastes • Ground Water Quality • River Water Quality • Soils • Health from Electric Fields • Ecology • Habitats • Flora and Fauna • Endangered Species • Socio Economic – positive and negative • Construction • Operation • Decommissioning • Cultural Heritage • Religious & Traditions • Baselines and Seasonal Variations • ESMP • CESMP • Toxic Wastes • Oil spills • Maximum Credible Event • ALARP Events No issues have been identified that preclude this project proceeding if the following mitigation measures given in the ESMP are implemented. 14.2 Environmental Management & Monitoring TCN will be the executing agency for projects. The supervision and monitoring of Project-related social and environmental activities during the pre-construction, construction and operation phases are the responsibility TCN. They may also be responsible for decommissioning. The PMU set up within TCN is responsible for supervision of environmental management and for environmental monitoring. World Bank environmental requirements and all applicable GoN environmental laws, regulations and standards, must be met prior to the commencement of construction, during construction and operation of the Project. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 157 14.3 EMP Environmental Management Plan An Environmental Management Plan (EMP) has been prepared for pre-construction, construction, operation and decommissioning phases. The EMP includes a text description below and a table. This ESMP is written as a stand-alone document. It can be extracted and used as an independent guide. Therefore there is of necessity some repetition of some items mentioned earlier under the ESIA. The ESMP will be the guiding document for environmental management and monitoring during construction of the projects. It will guide the contractor in determining whether the recommended mitigation measures prior to site occupancy and during construction are being implemented effectively. The main part of the ESMP relates to construction which will be by a contractor. The ESMP is to be included in the Tender Documents against which the contractor will submit a bid. All contractors bidding for the project must include costs for environmental management in their bid price. 14.4 CESMP Contractors Environmental Social Management Plan The responsibility for Environmental Management and Monitoring during project construction lies with the main contractor and his sub-contractors. Compliance with the ESMP is contractually binding. Failure by the contractor to comply with the EMP may result in financial penalties. The ESMP is of necessity a general document. The contractor must prepare a detailed EMP giving site specific details of construction activities. This is a Contractor Environmental Social Management Plan (CESMP). This must be done within one (1) month of contract signing. The CESMP must be submitted and approved before construction activity may commence. A CESMP is a dynamic document and may be changed and updated at any time during implementation of the Project. Environmental monitoring results shall be documented and reviewed at least monthly to ensure that signs of adverse impacts are detected at an early stage and that actions for mitigation are taken. 14.5 Pre-Construction Phase Permits and Plans TCN will issue a permit to occupy the site to the successful contractor. Prior to this all outstanding issues on compensation must be resolved so that conflicts with local villagers do not hinder the contractor’s activities. To ensure that construction works are environmentally sound mitigation requirements are included in the construction contract provisions. The project will follow the standard specifications and General Conditions of Contract for construction contract purposes, as will be decided in the detailed design stage of the project. Appropriate environmental mitigation and monitoring measures are included in the EMP. The proposed environmental mitigation measures will form part of the design documents for the components, and be included in the contracts for procurement of goods and services. All contractors AND subcontractors will be required to comply with the EMP. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 158 Contractor Management Plans. Before the construction starts, the Contractor will prepare a number of mitigation plans and method statements consistent with the ESMP for review and approval by the construction supervision consultant (CSC). Approval will be required one month prior to construction commencing. Contract documents shall explicitly indicate the requirement of these plans that construction cannot start until all documents are approved and also state that all environmental protection measures will be included in the bid price. These management plans are needed in order to address the following issues:  Soil Erosion Management Plan  Borrow Pits and Spoil Management Plan  Spill Management Plan  Construction Camp Management Plan  Waste Management Plan for operation of construction camp and work sites  Health and Safety Management Plan (HSMP). The HSMP will give details of Occupational Health and Safety for the construction workers based on the ESMP. It will be submitted to the PMU for review. The detailed HSMP will include the following provisions: Clean water. Provide a clean and sufficient supply of fresh water, for construction and for all houses, camps, offices and other relevant sites such as workshops. Sewage and wastewater. Provide an adequate number of latrines and other sanitary arrangements at the site and work areas, and ensure that they are cleaned and maintained in a hygienic state. Solid waste. Provide garbage receptacles at construction site and camps, which will be periodically cleared. Liquid chemical waste. Provide receptacles in suitably bunded areas for the storage of liquid chemical waste prior to disposal. Include clear warnings with health risks. Personal protection. Provide personal protection equipment (PPE), such as safety boots, helmets, gloves, protective clothing, goggles, and ear protection for workers ensuring accordance with all national health and safety legislation if appropriate. Emergency Preparedness and Response. An emergency response plan to take actions on accidents and emergencies, including public health emergencies associated with hazardous material spills and similar events will be prepared. Emergency phone contacts with hospital in the nearest township will be established. A fully equipped first-aid base in each construction camp will be organized. Records Management. A Records Management System that will store and maintain easily retrievable records protected against loss or damage will be established. It will include documenting and reporting occupational accidents, diseases, and incidents. The records will be reviewed during compliance monitoring and audits. Safety communication. Ensure that safety, rescue and health matters are given a high degree of publicity ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 159 to all persons regularly or occasionally at active construction sites. Posters in a l l appropriate languages for the contractors will be displayed prominently at the site drawing attention to relevant health regulations and safety issues. Training, awareness and competence. Train all construction workers in basic sanitation and health care issues, general health and safety matters, and on the specific hazards of their work. Implement HIV/AIDS and other communicable diseases awareness and prevention program to target the local community and construction workers. All of the above plans must be prepared by the contractor and be submitted to PMU for review and approval. An example of a Contractors Environmental and Social Management Plan is given in Annex 6. 14.6 Construction Phase Air Quality Impacts During construction, air pollution sources are dust due to earthworks and stockpiling, extraction of fill materials and transport of construction materials such as earth, stone, gravel, sand, and cement; as well as gaseous emissions from construction equipment, vehicles and concrete mixing plants; and removal of surface materials; etc. These impacts, however, are temporary and localized. The following mitigation measures shall be implemented by the contractors to minimize impacts to air quality:  Construction equipment will be maintained to a good standard. Immediate repairs of any malfunctioning construction vehicles and equipment shall be undertaken.  Equipment and vehicles not in use shall be switched off.  Machinery and vehicles causing excessive pollution (e.g., visible black smoke) will be banned from construction sites.  All construction equipment and vehicles shall have valid certifications indicating compliance to vehicle emission standards.  Siting of bitumen plants, concrete mixing plants, crushing plants and other facilities that cause high dust and/or gaseous emissions should be at least 500 m from settlements and other sensitive receptors (schools, hospitals, etc.)  Necessary environmental clearance/approval shall be obtained prior to establishment and operation of asphalt mixing plants, crushing plants and other facilities.  On rainless day undertake watering, at least twice per day, on dusty and exposed areas at construction yards, materials stockpile, construction sites, access roads, quarry areas, borrow sites and other project areas where residential sites and other sensitive receptors are located nearby.  Tightly cover trucks transporting construction materials (sand, soil, cement, gravel, etc.) to avoid spills onto roads and dust emission.  Impose speed limits on construction vehicles to minimize dust emission along areas where sensitive receptors are located (houses, schools, churches, mosques, etc.).  Position any stationary emission sources (e.g., portable diesel generators, compressors, etc.) as far as is practical from sensitive receptors;  Burning on site of wastes generated at the construction sites, at work camps and by other project related activities shall be strictly prohibited. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 160  Provide temporary covers (e.g., tarpaulins, grassing) on long term materials and spoils stockpiles.  Clean road surfaces of debris/spills from construction equipment and vehicles.  Install temporary fencing or barriers around particularly dusty activities in vicinity of sensitive receivers.  Locations for stockpiling spoils, fill and other materials with high dust content shall be at least 500 m from the nearest residential areas and other sensitive receivers. 14.7 Water Quality Water Quality and Drainage Stockpiling of construction materials and spoils and earthworks if not properly managed may affect surface water quality by obstruction flow of watercourses and flooding. These impacts shall be minimized through implementation by the contractor of the following measures:  Firmly consolidate banks of any streams being crossed using stones, concrete and other suitable retaining measures and ensure that water courses are kept free of excavation spoil and construction debris, floating and submerged.  Spoils, construction wastes and construction materials stockpile area shall be located away from water bodies and under no circumstances will these materials be dumped into watercourses.  Do not fill up watercourse even if dry at the construction site. In case filling of local drainage system is necessary, consult with local authorities and get their permission beforehand. An alternative drainage shall be put in place before the existing watercourse is filled in.  Discharge of oily wastewater, fuel, hazardous substances and wastes, and untreated sewage to watercourses/canals and on the ground/soil is prohibited.  Provide drainage at the construction sites around the perimeter to avoid flooding of surrounding areas and minimize flow obstruction of existing watercourses.  Regularly inspect and maintain all drainage channels to keep these free of obstructions. This should be at least once a week and after heavy rain.  Slope stabilization measures (e.g., planting of fast growing native species of grass and shrubs, etc.) shall be implemented on exposed surfaces along to reduce material wash-away.  Do not wash vehicles in streams 14.8 Solid and Liquid Wastes Workers Camps There may be a need to establish workers camps during construction. The operation of these facilities will generate wastes and if improperly handled, these could cause health problems and pollution. The following mitigation measures shall be implemented by the contractor to minimize impacts that may arise from operation of construction/workers camps:  Workers camp location and facilities shall be located at least 500 m from settlements and agreed with local communities and local officials.  Drainage shall be provided to facilitate the rapid removal of surface water from all areas and prevent flooding and accumulation of stagnant water. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 161  Provide adequate housing for all workers at the construction camps and establish clean canteen/eating and cooking areas.  Portable lavatories (or at least pit latrines in remote areas) shall be installed and open defecation shall be prohibited and prevented by cleaning lavatories daily and by keeping lavatory facilities clean at all times.  Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers.  Wastewater from contractors’ workshops and equipment washing-yards will be passed through gravel/sand beds and all oil/grease contaminants will be removed before wastewater is discharged. Oil and grease residues shall be stored in tightly covered drums. Such wastes shall be disposed consistent with national and local regulations.  Construction/workers camps shall be cleaned up after use to the satisfaction of FMEnv and local community. All waste materials shall be removed and disposed to disposal sites approved by local authorities.  Land used for campsites shall be restored to the original condition as soon as practicable after it is vacated and cleaned. Construction and Domestic Waste Various construction activities and operation of workers camps will generate solid wastes. Poor waste management can cause odor and vermin problems and negatively impact the landscape. The following mitigation measures to minimize impacts due to waste generation shall be implemented by the contractor:  Segregate and regularly collect wastes at worker camps and offices.  Construction/workers’ camps shall be provided with garbage bins.  Prohibit disposal of solid wastes into canals, rivers, other watercourses, agricultural field and public areas.  There will be no on site landfills established by the contractors. All solid waste will be regularly collected and removed from the work camps and disposed to areas approved by local authorities.  Prohibit burning of construction and domestic wastes.  Recyclables shall be recovered and sold to recyclers.  Residual and hazardous wastes shall be disposed of in disposal sites approved by local authorities.  Ensure that wastes are not haphazardly dumped within the project site and adjacent areas Excavation Spoils The sites will require removal of vegetation and platform formation on sloping sites as at Kabba. Improper spoils disposal could cause deterioration of water quality and flow obstruction of water courses. The following measures shall be implemented by the contractor to avoid or minimize such impacts.  Provide grass cover and other suitable slope stabilization measures on embankment slopes and on long term stockpile of spoils.  Spoil disposal shall not cause sedimentation and obstruct natural drainage or cause damage to agricultural land and densely vegetated areas. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 162  Spoils shall only be disposed to areas approved by local authority.  Excavated materials shall be reused into low elevation depressions for construction.  On steep slopes plant appropriate native vegetation that retards erosion.  Long term stockpiles such as topsoil is to be covered with native species of grass or other suitable materials to prevent wind erosion. Use of Hazardous Substances Pollution and safety risks due to use of hazardous materials and disposal of hazardous wastes shall be prevented through implementation of the following mitigation measures by the contractor:  Store fuel and hazardous substances and wastes in paved areas with roof and surrounding kerb. If spills or leaks do occur, undertake immediate clean up.  Train relevant construction personnel in handling of fuels and other hazardous substances as well as spill control procedures.  Ensure availability of spill cleanup materials (e.g., absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored.  Segregate hazardous wastes (oily wastes, used batteries, fuel drums) and ensure that storage, transport and disposal shall not cause pollution and shall be undertaken consistent with national and local regulations.  Store waste oil, lubricant and other hazardous materials and wastes in tightly sealed containers to avoid contamination of soil and water resources.  Ensure all storage containers of hazardous substances and wastes are in good condition with proper labeling.  Regularly check containers for leakage and undertake necessary repair or replacement. If necessary store oversize drums to contain leaking drums.  Store hazardous materials above any levels likely to flood during heavy rain.  Storage areas for fuel, oil, lubricant, bitumen and other hazardous substance will be located at least 100 m away from any watercourses.  Storage areas will be bunded and provided with interceptor traps so that accidental spills do not contaminate the environment.  Vehicle maintenance and refueling will be confined to areas in construction sites designed to contain spilled lubricants and fuel.  Bitumen for internal roads shall not be allowed to enter either running or dry streambeds and nor will be disposed of in ditches or small waste disposal sites prepared by the contractor. Fuel Storage and Vehicle Maintenance It is expected that vehicles will be stored at construction sites. Fuel stored on site must follow good industry practice. Fuel suppliers must provide skid mounted tanks with a metered off take and pump, mounted on a concrete hard standing. The concrete base must have a perimeter curb to catch and retain any minor leaks or spills from the main tank manifold. Some vehicle maintenance may take place at commercial garages. This will have no impact on the project area. If maintenance takes place on site, measures must be implemented to control oily water runoff.(See Figure 14-1 below)  Wherever possible, refueling will be carried out at a commercial garage. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 163  Refuelling shall not be permitted within or adjacent to watercourses.  Fuel storage areas must be provided with concrete flooring and surrounded by an embankment to readily contain and clean-up spills. Spill Protection for Fuel Oil Sto Fuel O Rain Water Drain "Normally Closed" Brick Kerb to Contain Spill Concrete B Rain Proofing for Waste Oil Sto Lightweight Roof to Protect from Su ports Wa Concr Figure 14-1 Spill Protection for Fuel Oil Storage / Rain Proofing for Waste Oil Storage ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 164 Waste Oil Waste oil can be sold to local waste subcontractors. This process is endorsed. The project contractor is at liberty to subcontract with any one he chooses. This approach has several advantages:  It allows the contractor to avoid a cost of disposal and brings in revenue to the contractor  The subcontractor will have paid for the waste oil. It is now a valuable commodity to him. Therefore he is extremely unlikely to illegally dump the waste oil or allow any spillage on the road. Notwithstanding this practical point, it is preferable if licensed contractors are commissioned to ensure legal accountability. Any waste oil must be stored in drums which are clearly marked “waste material”. The drums must be of sound structural integrity and not leak, or be covered on the outside with dirty oil. Drums must be stored on a concrete hard standing with a perimeter curb to catch and retain any minor leaks or spills from the drums. The base must be covered with a lightweight rain proof shelter. Simple inclined corrugated lightweight material is sufficient. This must stop rain falling on the drums. (See Figure 14-1 above) Bitumen Use for Asphalt for Approach Roads Bitumen may be used for internal roads. This should be heated by kerosene or gas or as an alternative, cold mix bitumen can be employed. Fuel wood must not be used for heating. Asphalt must not be applied during rain so as to avoid it being washed into watercourses. 14.9 Noise Noise and Vibration Impacts Elevated noise and vibration levels are likely to be experienced during construction phase due to site works and operation of various equipment and vehicles. To minimize noise and vibration impacts, the following measures shall be implemented by the contractor:  No noisy construction-related activities (e.g., transport of materials along residential areas and other sensitive receptors, piling, use of jackhammer, etc.) will be carried out from 1700 to 0700 near sensitive receptors.  Noisy construction activities will be avoided during religious or cultural events in close proximity to the roadside such as Friday prayers attended by Muslims or Sunday mornings near churches or during temple festivals or weddings, etc.  All construction equipment and vehicles shall be well maintained, regularly inspected for noise emissions, and shall be fitted with effective muffler and other appropriate noise suppression equipment consistent with applicable national and local regulations.  Truck drivers and equipment operators shall avoid, as much as possible, the use of horns in densely populated areas and where there other sensitive receptors are found such as schools, hospital, etc. are located.  Impose speed limits on construction vehicles to minimize noise emission along areas where sensitive receptors are located (houses, schools, temples, hospitals, etc.). ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 165  Provide temporary noise barriers as necessary, if site works will generate high noise levels that could disturb nearby households, hospital, school and other sensitive receptors. A 3-5 meter high barrier from soil can reduce noise levels by 5-10 dB(A)  Avoid noisy construction activities in vicinity of sensitive receivers during night time or other sensitive periods (e.g. during exams in vicinity of schools)  Truck drivers and equipment operators shall avoid, the use of horns  In accordance with the FMEnv standard construction noise levels when measured at the boundary of the site should not exceed 75dB(A) daytime and 65dB(A) nighttime 145. The environmental monitoring program will be incorporated into the overall project design to ensure that environmental impacts are closely monitored and the construction and operating activities are closely supervised against the approved ESMP and the implementation of the GRM will be monitored. Blasting Blasting is not anticipated to be undertaken for the project. However, in case this becomes necessary, the following measures shall be implemented by the contractor to ensure safety of workers and the public:  Blasting will be carried out only with permission of the concerned authority, using a pre- established schedule.  All the statutory laws, regulation, rules etc., pertaining to acquisition, transport, storage, handling and use of explosives will be strictly followed.  The timing will be made available to the local people within 500 m of the blasting site in all directions, depending on the total charge used.  Blasting will be held only during day time. Under no circumstance will blasting be undertaken at night.  Where possible, blasting mats will be used to reduce flying rock.  No blasting will take place without a condition survey of any buildings within 500 m  People living near blasting sites will be informed of blasting times prior to the blasting.  Warning sirens will be sounded before blasting.  Where the vibration from blasting is exceeding the maximum permissible level, or damage occurs to local property information from the blasting shall be used to modify blasting patterns and calculate a reduced charge for future blasts  Blasting shall be under careful and strict management/supervision of properly trained and licensed personnel. Workers at blasting sites will be trained prior to blast operations and provided with safety equipment and earplugs.  Blasting shall be initiated by 20 millisecond delays to minimise vibration  Observe proper warning and precautionary measures to ensure safety of residents, pedestrians, motorists and structures during blasting.  All expenses/costs to address injuries, damage to properties, accidents, etc. due to blasting shall be assigned to the contractor. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 166 Quarry and Borrow Sites For the sites with steep gradients it may be necessary to bring fill material in to the site. This will be brought from quarries or borrow areas where soils can be extracted, The following measures shall be implemented at quarry and borrow sites to minimize impacts on water quality, reduce dust emission during transport, minimize erosion and siltation of nearby water courses and avoid damage to productive land and ecologically sensitive areas:  Sourcing of quarry and borrow materials from existing sites shall be preferred over establishment of new sites, as much as possible.  In case the project will involve new quarry/borrow sites, necessary approvals from environmental authorities shall be obtained prior to operation of such sites. Such sites shall be located over 500 m away from residential, school, hospital and other sensitive receptors.  Dust control during excavation and transport (e.g., water spraying on access roads and provision of truck cover) shall be undertaken in areas where there are sensitive receptors such as residential areas, school, hospital, etc.  Long-term material stockpiles shall be covered to prevent wind erosion.  The use of river bed sources shall be avoided, as much as possible. Alluvial deposits which lie on the river beds but are not covered by water in normal hydrological conditions shall be preferred.  Upon completion of extraction activities, borrow pits shall be dewatered and fences shall be installed, as appropriate, to minimize health and safety risks.  To avoid drowning when pits become water-filled, measures such as fencing, shall be implemented.  It is possible that villagers may request borrow pits to be left excavated so that they may be used as water reservoirs or fishponds. If this were to be agreed between the contractors and the villagers, all the full safety measures detailed above must be observed. Such agreements would be formalized in writing between the contractors and the villagers after full discussion with all concerned parties. 14.10 Flora and Fauna Only minimal vegetation clearing is required so loss of habitats is not expected. However, hunting of wildlife and cutting of trees for fuel may not be undertaken by workers and strict prohibitions should be imposed by the contractor. The following conditions shall apply :  Spoils and all types of wastes shall not be dumped into forested areas, agricultural land, densely vegetated areas, and water courses.  Workers shall be prohibited from collecting firewood and construction materials from surrounding forests, and from hunting wild animals.  The contractor shall prohibit cutting of trees for firewood and for use in for construction-related activities  The contractor will not use or permit the use of wood as a fuel for the execution of any part of the Works, including but not limited to the heating of bitumen and bitumen mixtures, and to the extent practicable shall ensure that fuels other than wood are used for cooking, and water heating in all his camps and living accommodations.  Contractor shall not buy or use wood from the illegal sources that come from the illegal logging ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 167  Contractor will take all precautions necessary to ensure that damage to vegetation is avoided due to fires resulting from execution of the works.  As much as possible, construction works will be scheduled in dry season to minimize adverse impacts to fishery, river water quality and other aquatic resources. 14.11 Damage to Culturally Significant Areas To ensure that site works and other project-related activities shall not adversely affect culturally significant sites in the event of any construction work uncovering or revealing archaeological relics these shall be deemed a “chance find” and reported as such to the appropriate Local Government Authority. All work on the site must stop until they issue a statement that work may be resumed. 14.12 Occupational Health and Safety The main risks during the construction stage may arise from: (a) inadequate sanitation facilities in work camps; (b) failure to implement measures to avoid accidents and injuries involving workers and the public; (c) introduction of sexually transmitted or other diseases by non-local workers, and; (d) outbreaks of diseases such as malaria, diarrhea, etc. in the labor force. In order to minimize these risks, the following measures shall be implemented by the contractor:  Conduct orientation for construction workers regarding emergency response procedures and equipment in case of accidents e.g., head injury from falling, burns from hot bitumen, spills of hazardous substances, fire; health and safety measures, such as on the use of rotating machines; prevention of HIV/AIDS, malaria, diarrhea, and other related diseases.  Provide drainage at construction sites and workers camps to prevent water logging/accumulation of stagnant water and formation of breeding sites for mosquitoes.  Provide fire extinguish equipment and appropriate emergency response equipment based on on- going construction activities at the work areas and at construction and workers camps.  Provide first aid kits at each camps and working sites that are readily accessible by workers.  At the workers camps, provide adequate housing for all workers at the construction camps, provide reliable supply of potable water, install separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers and establish clean eating areas and kitchen.  Provide workers with appropriate safety equipment/devices (PPE) such as dust mask, safety helmets, safety shoes or boots, goggles, ear plugs, etc. and strictly require them to use these as necessary.  Install warning sign boards showing hazardous areas where PPE must be warn such as noisy areas or where googles are needed.  Instruct Security Guards to deny entry to persons not wearing PPE.  Strictly impose speed limits on construction vehicles along residential areas and where other sensitive receptors such as schools, churches, hospitals, and other populated areas are located.  Educate drivers on safe driving practices to minimize accidents and to prevent spill of hazardous substances and other construction materials by providing covers over transporting dump trucks.  Install lighting systems at places which are badly lit where accidents may happen.  The general public/local residents shall not be allowed in high-risk areas, e.g., excavation sites and areas where heavy equipment is in operation. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 168  Ensure proper collection and disposal of solid wastes within the construction camps consistent with local regulations.  Provide fencing on all areas of excavation greater than 2 m deep.  Ensure reversing signals are installed on all construction vehicles.  Measures to prevent malaria shall be implemented e.g., provision of insecticide treated mosquito nets to workers, spraying of insecticides, installation of proper drainage to avoid formation of stagnant water, etc.  Discharge of untreated sewage shall be prohibited. The civil works contractors must implement adequate precautions to protect the health and safety of construction workers. The occupational health and safety risks will be minimized by not only providing adequate personal protective equipment (PPE) but ensuring workers wear it. In addition, the contractors will undertake the following activities:  An Environment Health and Safety Officer (EHSO) will be appointed prepare a Health and Safety Management Plan, to implement the HSMP and ensure that the requirements of the EMP are met.  The EHSO will ensure that the HSMP is submitted to TCN prior to construction for approval, that accurate records and reports of any occupational health and safety incidents are kept, and reviewing the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.” 14.13 Community Social Conflicts The presence of workers could cause conflicts with local communities. These can be avoided by implementing the following measures:  Regularly inform in advance the local officials and local residents on the location and schedule of construction activities which may cause impacts on the environment and life of people e.g., roads used for transport of materials locations of worker camps etc.  Locate construction camps away from communities (at least 500 m away) in order to avoid social conflict in using resources and basic amenities such as water supply.  Maximize number of local people employed in construction works.  Maximize goods and services sourced from local commercial enterprises. Damage to Community Facilities Transport of materials and spoils, operation of construction equipment and various construction activities may damage community utilities. The contractor shall implement the following measures to address this impact:  The contractor shall not allow overloading of trucks used for all project-related activities.  The contractor shall immediately repair any damage caused by the project to community facilities such as water supply, power supply, drainage and the like. If compensation is to be paid to affected parties, the contractor will be held responsible for damages. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 169 Complaints Mechanism A Grievance Redress Mechanism (GRM) must be set up by the contractor and a complaints officer appointed. A sign board should be placed outside the construction site giving contact names and mobile phone numbers. These phone numbers should be manned 24/7. Any complaints received should be responded to within 24 hours in a polite and respectful way. Complaints and remedial works should be reported at least once a month to the client under CAR – Corrective Action Reporting. Details of the GRM are given in Section 14.34. 14.14 Traffic Disruption and Access Obstruction The construction works may cause traffic disruption and congestion near roadside properties. Lack of proper traffic warning signs could cause accidents. The following measures shall be implemented by the contractor to minimize such impacts:  Set up clear traffic signal boards and traffic advisory signs at the roads going in and out the construction sites to minimize traffic build-up.  Regularly monitor traffic conditions along access roads so that vehicles do not cause congestion.  Provide sufficient lighting at night within and in the vicinity of construction sites.  Provide temporary accesses to properties and establishments affected by disruption to their permanent accesses.  Reinstate good quality permanent accesses following completion of construction.  Provide safe pedestrian access around construction areas.  Provide adequate signage. The signs should be bold and clearly visible at night. 14.15 Utilities In the event of contractor damaging or disrupting utilities such as pipes or cables the contractor will be liable. To avoid this the utility companies should be contacted to ensure there are underground and unmarked facilities in the area. As the sites are all greenfield sites this is unlikely but it is still the contractors responsibility to check. 14.16 General House Keeping Contractors should practice “good housekeeping”. The concept of “good housekeeping” is easy for anyone to understand, even those of a non-technical nature. The contractor’s staff are expected to behave in a responsible way and not wait to be told what to do on every occasion. The site should be kept clean and tidy, spills should be mopped up as soon as they occur, rubbish should be collected and removed promptly and tools and equipment stored away neatly when not in use. More details will be given in the EMP The staff will benefit from Good Housekeeping as a clean well run site is less likely to have industrial accidents. Monitoring will be by visual inspection by the construction supervision consultants. The contractors must use only vehicles and equipment that are registered and have necessary ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 170 documentation and permits. All drivers must have valid and current HGV driving licences. 14.17 Positive Impacts The contractor should attempt to create positive impacts. Employment opportunities should be offered to local community members for unskilled labor. Other short term opportunities such as providing food should be encouraged as long as high standards of food hygiene and sanitation are observed. 14.18 Operation Phase NERC HSE Standards During operations a key concern is operator safety. The Nigerian Electricity Regulatory Commission Health and Safety Standards developed industry-specific health and safety (H&S) standards. These are a technical reference document and guidelines of International Industry Best Practice (IIBP). The power sector is critical infrastructure needed for the economic, industrial, technological and social development of Nigeria. The World Bank have long recognized that electricity consumption is one of the indices for measuring the standard of living of any country. The backbone of the industry is the labor force. The industry sector employs approximately 34,000 people. The population is of more than 150 million, with about 40% of the population serviced by electricity. The need to protect workers and the general public from the hazards resulting from power generation, transmission, distribution and supply is a matter of protecting human life. Workplaces include all places of work; all non-electrical workers and members of the public in public places. Major causes of fatalities in workplaces include plug in appliances and flexible cords and fixed wiring, and maintenance related activities that are specific to the industry sector. Contact with power lines is a significant causative factor of electrical deaths across several of the electrical safety priorities such as workplaces and public places, but it is not the only one. Workplaces even within the industry sector represent a very diverse group of locations, with very different levels of electrical risk. Prioritization of high risk areas needs to be determined based on data, but is likely to include:  the rural sector  the construction sector  workplaces where water is significantly involved The standards focus on all electrical and non-electrical workers engaged to perform work by electricity entities, involved in the generation, transmission or distribution of power in Nigeria. A review of numerous industry reported studies from the sector support that fatalities occurred which could have been prevented by the use of recognized electricity industry safe systems of work. The procedures are essentially adopted from the U.S. Occupational Safety and Health Act of 1970. 14.19 Air Quality High electric fields around power cables attract airborne pollutants, such as occur near a main road, chemical factory, sprayed fields, etc. These are then deposited downwind or in rain. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 171 Ozone may be generated around transmission lines but in low concentrations and there is no evidence of it being harmful to health. 14.20 Electro-Magnetic Fields (EMF) Electric overhead lines are considered a source of power frequency, electric and magnetic fields, which may have a perceived health effect. The strength of both electric and magnetic fields is a function of the voltage, distance from the conductors to the ground and the lateral distance from the line to the receptor. Many studies published during the last decade on occupational exposure to Electro-Magnetic Fields (EMF) have exhibited a number of inconsistencies and no clear, convincing evidence exists to show that residential exposures to electric and magnetic fields are a threat to human health. 14.21 Electrical and Magnetic Fields Safety Overhead Electrical Safety It is common to think that one has to touch an electrical conductor to get hurt. This is not true when dealing with high voltages. Substations use a high-voltage, open-air conductor —called “bus”— which resembles a 75mm conduit pipe. The metal pipes running through the overhead areas of a substation are the conductors of electricity. There are no wires inside the pipe. The electricity is carried on the pipe’s outside skin. Because of the high voltages involved, one need not touch an electrical conductor to be harmed. If close enough, the electricity will contact the person in the form of a high-temperature electrical arc. The potential for an electrical arc becomes greater as voltage increases. For this reason the safety distances must be observed. The proper clearance from the overhead bus is calculated for each station, and conductors are positioned accordingly, using a conservative distance to ensure the safety of anyone walking through a station. For 333kV, a safe distance of 6m has been established. For 11kV to 132kV a safe distance of 4m has been established. To stay safe from the electric bus inside a substation, one should not climb nor carry tools above the shoulder. Ground-Level Electrical Safety The overhead bus is not the only electrical hazard present in a substation. Many electrical hazards are found at ground level also. Safety from these hazards is maintained by restricting access to them and by placing the hazard behind locked doors, cages, and fenced-in areas. Capacitor banks reside in cages, providing a buffer zone between persons and the exposed electrical conductors. Circuit breakers are housed in locked cubicles to eliminate the chance of casual entry into these areas. Lightning arrestors and various other electrical components are placed behind fences. All such areas should have warning signs. Where a substation has a metallic fence, it must be properly grounded to protect people from high voltages that may occur during a fault in the network. Earth faults at a substation can cause a ground potential rise. Currents flowing in the Earth's surface during a fault can cause metal objects to have a significantly different voltage than the ground under a person's feet; this touch potential presents a hazard of electrocution. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 172 Underground-Level Electrical Safety Power cables can be undergrounded. Electric fields will be absorbed by the earth above a buried cable. Magnetic fields will be higher immediately above an underground cable than they will be below an overhead line, because one is are closer, but the fields reduce much more quickly from an underground cable. It should be remembered that the cost of putting cables underground can be twenty times higher than allowing them to go overhead, although less for lower voltage lines. 14.22 Vegetation Management Buried beneath the gravel in a substation yard is a grid of wires that functions as the grounding for the high voltage equipment. In order to ensure safety for utility employees and the public, it is important to prevent this ground grid from being compromised by vegetation growth. For this reason substation yards are regularly maintained by using a variety of herbicides. 14.23 Pesticides Herbicides are one branch of pesticides. Any pesticides stored on site for control of weeds, rodents or vectors (such as mosquitoes) should be should be kept in a secure storage and application should be made under controlled conditions. Technical staff and residents should be advised and workers wear PPE. 14.24 Migratory Birds The project area does not contain any natural habitats considered to be either critical or fragile. The project area does not have any wetlands or forested areas nearby or International Bird areas (IBAs) and there are no international migratory bird Flyways. 14.25 Noise If the noise produced by an operating substation is considered intrusive to adjacent property owners a barrier of mature trees or tall soil berms between the substation and nearby residences can be helpful in partially reducing the perception of noise impacts, although trees do very little in reality. Earth berms can reduce up to 7dBs but as the sound is low frequency barriers are not very effective. 1 4 . 2 6 Visual Appearance Light pollution may present a nuisance in residential areas. Substations may have lights that operate all night long to discourage vandalism and unauthorized individuals. New downward-focused security lighting can help to avoid or reduce light pollution. 14.27 Spills Transformers may occasionally need oil replacement or replenishment but this is usually very infrequent. In the event of a spill the same procedure as given under Commissioning in Section 13 should ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 173 be followed. 14.28 Fires Mineral-oil-filled transformer explosions and fires causing heavy collateral damage have raised major safety concerns. There have also been major environmental concerns over the toxic effects of uncontained mineral oil spills. This has given rise to a new class of alternative dielectric insulating fluids that have historically been developed to answer these specific concerns. Transformers are fitted with fire traps to allow oil burn out. In the event of a major fire the same fire response procedure as given under Commissioning should be followed. 14.29 HSE There must be adequate precautions to protect the health and safety of plant workers. All staff must be provided with personal protective equipment (PPE) and made to wear it. The facility operators should undertake the following activities:  An Environment Health and Safety Officer (EHSO) should be appointed to ensure that the EMP is implemented  The EHSO will ensure that accurate records and reports of any occupational health and safety incidents are kept, and reviewing the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.”  Site briefings for visitors on restricted areas and emergency evacuation procedure  Induction EHS briefings for new staff  Follow NERC procedures  Implement Corrective Action Reporting (CAR) Tool box briefings Tool box briefings should be held every morning during roll call and a “safety moment” held. This need only last 2-3 minutes and a specific item can be stated, for example when hot work permits are needed, or when safety equipment is needed if working at a height. The essence of Tool Box meetings is repetition. Staff becomes complacent if not continually reminded of safety procedures. Topics can be repeated every few weeks. The topics addressed should be recorded and reported in the monthly management reports. Near Misses Near Misses are situations that arise that could have led to a safety incident but which were spotted by vigilant staff and avoided by swift action. This may be something as simple as spotting a gas cylinder propped upright without support that may fall and injure someone and insisting that it be held in a cradle on a trolley. (For example see figure below) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 174 Figure 14-2 Examples of Near Misses - Gas cylinders incorrectly stored and handled Figure 14-3 Examples of Near Misses - Gas cylinders correctly stored and handled Staff may be reluctant to report “Near Misses” as they fear a reprimand but this reluctance must be overcome. The target should be “Zero Incidents” and many “Near Misses” reported and avoided. An EHS annual report that states No Incidents and No Near Misses will not be believed. Induction Briefings New staff should be given an Induction Briefing at the start of their employment. They should be trained to identify and eliminate, isolate or minimize potential hazards in their working environment. Persons entering the site facility should be issued with personal protective equipment (PPE) and be required to wear it. This applies to workers and visitors. Any person found not wearing full PPE should be ordered to wear it and if they refuse they should be ordered off the site. Site supervisors and security guards have the authority to do this. All staff and visitors should be briefed on and follow emergency and evacuation procedures in particular ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 175 firefighting. NERC As part of normal Occupational Hygiene, Health, Safety and Environment the Nigerian Electricity Regulatory Commission Health and Safety Standards must be followed. The standards are organized into five Parts:  Part I. How to Evaluate Safety Programs;  Part II. Safety and Best Industry Practices;  Part III. Worker Safety Rules;  Part IV. Recordkeeping, Training, Inspections, Accident Investigation and Reporting;  Part V. Risk and Vulnerability Assessments As stated by The Nigerian Electric Regulatory Commission “These Standards are designed to save lives”. The practices defined are legal obligations. Each employer has a legal obligation to ensure that a safe work environment is provided to all employees, both regular and non-regular. Contractors working at substations, transmission stations, power plants or engaging in any work activities involving power generation, transmission, distribution and servicing are also required to follow the best practices and safety standards as defined by NERC. Corrective Action Reporting (CAR) If an incident takes place then it is not enough simply to report it. Steps must be taken to abate the nuisance, end the problem and to avoid it happening again. These steps should be included in Corrective Action Reporting (CAR) which is an iterative process whereby checks are made that the situation has actually been resolved in a prompt manner. 14.30 Decommissioning Phase The transmission lines and substations are likely to remain in place for many years and therefore any decommissioning works could be a long time in the future. Towers and substations would be dismantled and removed and materials recycled/re-used as far as possible. Any areas disturbed must be restored to pre-project conditions or to conditions acceptable to FMEnv. After decommissioning the site may be handed over to a new owner and developed for another purpose. In order to avoid any contingent liability to TCN on handover, the site must be free of all encumbrances. After removal of all ancillary equipment the main issue will be potential soil contamination. This is why the soil sediments samples during the baseline are important. During the life of the installation all efforts should be made to avoid or minimize spills of potentially contaminating materials and to make strenuous efforts to clean up after any spills. After removal of all site equipment soil samples should be taken and compared with the baseline results. If the post- operative soil samples show similar or lower concentrations of parameters measured in the baseline, then the site is deemed clean and can be handed over. If the concentrations are higher, then it may be necessary to excavate contaminated soils, dispose of the contaminated material and backfill with clean ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 176 soils. Therefore it is important to store the baseline soils analysis in a secure place. Potential negative impacts during decommissioning could include  Spillages of transformer oils on ground and into groundwater as equipment is removed.  Solid wastes such as brick, concrete and rubble from substation site demolition  Metals and cables from towers dismantling can become an eyesore if not taken off site either for re- use or recycling.  Invasive flora species could colonise former substation sites and the way-leave on decommissioning following removal of structures, buildings and hardcover.  Local residents could be subject to noise and air impacts during demolition. Environmental impacts associated with decommissioning can minimised through the implementation of an environmental and social management plan (ESMP). If the ESMP is followed faithfully then there should not be any residual environmental impacts during decommissioning. Therefore it is imperative that the ESMP is followed during Operation so that Decommissioning is not onerous. If the ESMP is not followed then remedial works or payment of compensation may have to be paid. An example of a generic Decommissioning Plan is given in Annex 7. 14.31 Environmental Social Management Plan The Environmental and Social Management Plan (ESMP) is given below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 177 Table 14-1 Environmental Impacts and Mitigation Measures Project Potential Proposed Mitigation Measures Location Estimated Responsibility Activity Environmental Cost Impacts/Concer ns Implementati Monitoring on Pre-construction Phase Location of Lack of Establish a grievance redress mechanism (GRM) At TCN No additional TCN PMU WB Sites mechanism to after cost address contract environmental signing complaints Make well known the existence of the GRM through At village No additional TCN PMU WB public awareness campaigns. residences cost and in communiti es Ensure that names and contact numbers of At site No additional Contractor/ WB representatives of TCN-PMU and contractors are entrance cost TCN PMU placed on notice boards outside the construction site and in local and at local government offices community Location of Siting of quarry Use existing sites rather than new sites, as much as Quarry and Part of Contractor TCN PMU quarry and and borrow possible. borrow contractor’s borrow areas could sites bid cost areas cause damage to Quarries and borrow pits shall not be established in Quarry and No additional Contractor TCN PMU ecologically national, provincial, district and village conservation borrow cost sensitive sites, forests and other ecologically sensitive and protected sites productive land areas. and nuisance to Borrow/quarry sites shall not be located in productive Quarry and No additional Contractor TCN PMU sensitive land. borrow cost receptors sites (residential areas, schools, In case the Project will involve new quarry/borrow Quarry and Part of Contractor FMEnv ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 178 Project Potential Proposed Mitigation Measures Location Estimated Responsibility Activity Environmental Cost Impacts/Concer ns Implementati Monitoring on etc.) sites, necessary approvals from environmental borrow contractor’s authorities shall be obtained prior to operation of such sites bid cost sites. Such sites shall be located over 500 m away from residential, school, hospital and other noise sensitive receptors. Location of Siting of various Workers camp location and facilities shall be located at At site No additional Contractor CSC / PMU construction project facilities least 500 m from settlements and agreed with local Cost workers could adversely communities and local officials. camps and affect sensitive Siting of asphalt plants, concrete mixing plants, At site No additional Contractor CSC / PMU other receptors crushing plants and other facilities that cause high dust Cost project (residential and/or gaseous emissions will be at least 500 m from facilities areas, etc.) due settlements and other sensitive receptors (schools, to dust hospitals, etc.) emission, Necessary environmental clearance/approval shall be At site Part of Contractor FMEnv wastewater obtained prior to establishment and operation of contractor’s generation, etc. asphalt mixing plants, crushing plants and other bid cost facilities. Site Disruption to Prior to commencement of site works, relocate or re- At site Part of Contractor CSC / PMU preparation utilities provision water supply pipelines, electricity supplies contractor’s and other facilities that may be affected by bid cost construction works This will be done in agreement with the local community and the utility company. Site Site activities to Site Management Plans must be prepared by the At site Part of Contractor CSC / PMU Managemen be controlled contractor and must be approved by PMU before contractor’s t Plans construction starts. bid cost ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 179 Construction Phase Earthworks & Encroachment/ Upon discovery of any objects of possible At site No additional Contractor CSC / excavations damage to archaeological significance that may be uncovered cost PMU / historically / during construction, the site supervisor shall Departme culturally immediately suspend construction activities affecting nt of significant areas the area and shall alert Local Government district Antiquitie offices to inspect the site. s, Ministry of Culture Work will remain suspended until a site assessment has been made by the concerned authority and the contractor has been given permission by the concerned authority to proceed with the construction activities. Transport of Air pollution due Construction equipment will be maintained to a good All site Part of Contractor CSC / materials, to elevated standard. Immediate repairs of any malfunctioning access contractor’s PMU operation of levels of dust construction vehicles and equipment shall be roads and bid cost construction and gaseous undertaken. borrow equipment emissions roads. Equipment and vehicles not in use shall be switched All site No additional Contractor CSC / off. access cost PMU roads and borrow roads. Machinery and vehicles causing excessive pollution All site No additional Contractor CSC / e.g., visible dark smoke will be banned from access cost PMU construction sites. roads and borrow roads. All construction equipment and vehicles shall have All site No additional Contractor FMEnv valid certifications indicating compliance to vehicle access cost emission standards. roads and borrow ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 180 roads. Operation of Elevated noise No noisy construction-related activities e.g., Throughout No additional Contractor CSC / construction and vibration transport of materials along residential areas and project site cost PMU equipment levels that could other sensitive receptors, piling, use of jackhammer, and vehicles cause nuisance etc. will be carried out from 1900 hrs to 0700 hrs near and damage to sensitive receptors. properties Noisy construction activities will be avoided during Throughout No additional Contractor CSC / religious or cultural events in close proximity to the project site cost PMU roadside such as Muslim Friday prayers, religious festivals or weddings, etc. All construction equipment and vehicles shall be well Constructio Part of Contractor CSC / maintained, regularly inspected for noise emissions, n site contractor’s PMU and be fitted with effective muffler and other bid cost appropriate noise suppression equipment consistent with applicable national and local regulations. Use only vehicles and equipment that are registered Constructio No additional Contractor CSC / and have necessary permits. n site cost PMU Truck drivers and equipment operators shall avoid, as Constructio No additional Contractor CSC / much as possible, the use of horns in densely n site cost PMU populated areas and where there other sensitive receptors are found such as schools, temples, hospital, etc. are located. Impose speed limits on construction vehicles to Constructio No additional Contractor CSC / minimize noise emission along areas where sensitive n site cost PMU receptors are located (houses, schools, temples, hospitals, etc.). Provide temporary noise barriers (3-5 meter high Constructio Part of Contractor CSC / barrier can reduce 5-10 dB(A), as necessary, if site n site contractor’s PMU works will generate high noise levels that could bid cost disturb nearby households, hospital, school and other sensitive receptors ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 181 Avoid noisy construction activities in vicinity of On No additional Contractor CSC / sensitive receivers during night time or other approaches cost PMU sensitive periods (e.g. during school hours in vicinity to of schools) constructio n site Truck drivers and equipment operators shall avoid On No additional Contractor CSC / the use of horns approaches cost PMU to constructio n site Waste from Improper Segregate and regularly collect wastes at worker Constructio Part of Contractor’s CSC / workers handling of camps and offices. n site and contractor’s EHS Office PMU camps wastes could workers bid cost cause odor and camps vermin Construction/workers’ camps shall be provided with Constructio Part of Contractor’s CSC / problems garbage bins. n site and contractor’s EHS Office PMU workers bid cost camps Waste from Improper Prohibit disposal of solid wastes into rivers, Constructio No additional Contractor CSC / disposal of watercourses, agricultural field and public areas. n site cost PMU construction wastes could There will be no site-specific landfills established by Constructio Part of Contractor CSC / cause pollution the contractors. All solid waste will be regularly n site contractor’s PMU / and obstruction collected and removed from the work camps and bid cost State Env of nearby disposed to areas approved by local authorities. watercourses. Prohibit burning of wooden construction and Constructio No additional Contractor CSC / domestic wastes. n site cost PMU Recyclables shall be recovered and sold to recyclers. Constructio No additional Contractor CSC / n site cost PMU Residual and hazardous wastes shall be disposed of in Constructio Part of Contractor CSC / disposal sites approved by local authorities. n site contractor’s PMU / bid cost State Env ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 182 Ensure that wastes are not haphazardly dumped Constructio No additional Contractor CSC / within the project site and adjacent areas n site cost PMU Operation of Operation of Drainage shall be provided to facilitate the rapid Constructio Part of Contractor CSC / construction these facilities removal of surface water from all areas and prevent n Workers contractor’s PMU and workers will generate flooding and accumulation of stagnant water. camps bid cost camps solid and liquid Provide adequate housing for all workers at the Constructio Part of Contractor’s CSC / wastes and if construction camps and establish clean n Workers contractor’s EHS Office PMU improperly canteen/eating and cooking areas. camps bid cost handled, these Portable lavatories (or at least pit latrines in remote Constructio Part of Contractor’s CSC / could cause areas) shall be installed and open defecation shall be n Workers contractor’s EHS Office PMU health problems prohibited and prevented by cleaning lavatories daily camps bid cost and pollution. and by keeping lavatory facilities clean at all times. Provide separate hygienic sanitation facilities/toilets Constructio Part of Contractor’s CSC / and bathing areas with sufficient water supply for n Workers contractor’s EHS Office PMU male and female workers. camps bid cost Wastewater effluents from contractors’ workshops Constructio Part of Contractor CSC / and equipment washing- yards will be passed through n Workers contractor’s PMU gravel/sand beds and all oil/grease contaminants will camps bid cost be removed before wastewater is discharged. Oil and grease residues shall be stored in tightly covered drums. Such wastes shall be disposed consistent with national and local regulations. Construction/workers camps shall be cleaned up after Constructio Part of Contractor’s CSC / use to the satisfaction of FMEnv and local community. n Workers contractor’s EHS Office PMU / All waste materials shall be removed and disposed to camps bid cost State Env disposal sites approved by local authorities. Land used for workers camps shall be restored to the Constructio Part of Contractor CSC / original condition as far as practicable and the area n Workers contractor’s PMU shall be planted with appropriate trees/shrubs as camps bid cost soon as practicable after it is vacated and cleaned. Quarry and Quarry left as Prior to extraction, topsoil (about 15 cm) shall be All quarries No additional Contractor CSC / borrow site open stockpiled, preserved and then refilled after and borrow cost PMU / ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 183 operation excavation. completion of quarry/borrow pit operation for areas State Env rehabilitation purposes after excavation is over. Quarry and Dust Dust control during transport e.g., water spraying on All quarries Part of Contractor CSC / borrow site entrainment by access roads and provision of truck cover and and borrow contractor’s PMU / operation wind. excavation shall be undertaken in areas where there areas bid cost State Env are sensitive receptors such as residential areas, school, hospital, etc. Long-term material stockpiles shall be covered to All quarries Part of Contractor CSC / prevent wind erosion. and borrow contractor’s PMU areas bid cost Quarry and Stagnant water During quarry and borrow site operation, provide All quarries Part of Contractor CSC / borrow site adequate drainage to avoid accumulation of stagnant and borrow contractor’s PMU / operation water. areas bid cost State Env After quarry Safety concerns Upon completion of extraction activities, borrow pits All quarries Part of Contractor CSC / finished shall be dewatered and fences shall be installed, as and borrow contractor’s PMU / appropriate, to minimize health and safety risks. areas bid cost State Env After quarry Safety concerns Borrow pits will be left in a tidy state with stable side All quarries Part of Contractor CSC / finished slopes and proper drainage in order to minimize soil and borrow contractor’s PMU / erosion, siltation of nearby bodies of water and to areas bid cost State Env avoid creation of water bodies favorable for mosquito breeding. After quarry Safety concerns To avoid drowning when pits become water-filled, All quarries Part of Contractor CSC / finished measures such as fencing shall be implemented. and borrow contractor’s PMU / areas bid cost State Env After quarry Water supplies It is possible that villagers may request borrow pits to All quarries Part of Contractor’s CSC / finished be left excavated so that they may be used as water and borrow contractor’s EHS Office PMU / reservoirs or fishponds. If this were to be agreed areas bid cost State Env between the contractors and the villagers, all the full safety measures detailed above must be observed. Such agreements would be formalized in writing between the contractors and the villagers after full discussion with all concerned parties. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 184 Use of Pollution and Store fuel and hazardous substances and wastes in Constructio Part of Contractor CSC / hazardous safety risks due paved areas with roof and embankment. If spills or n site contractor’s PMU substances to use of leaks do occur, undertake immediate clean up. bid cost = such as fuel, hazardous $10,000 oil, materials and Train relevant construction personnel in handling of Constructio Part of Contractor’s CSC / lubricants, disposal of fuels and other hazardous substances as well as spill n site contractor’s EHS Office PMU etc. hazardous control procedures. bid cost wastes Ensure availability of spill clean up materials (e.g., Constructio Part of Contractor’s CSC / absorbent pads, etc.) specifically designed for n site contractor’s EHS Officer PMU petroleum products and other hazardous substances bid cost = where such materials are being stored. $2,000 Segregate hazardous wastes (oily wastes, used Designated No additional CSC / PMU CSC / batteries, fuel drums) and ensure that storage, cost PMU / transport and disposal shall not cause pollution and storage State Env shall be undertaken consistent with national and local sites regulations. Store waste oil, lubricant and other hazardous Designated Part of CSC / PMU CSC / materials and wastes in tightly sealed containers to contractor’s PMU / avoid contamination of soil and water resources. storage bid cost = State Env sites $4,000 Ensure all storage containers of hazardous substances Designated Part of Contractor’s CSC / and wastes are in good condition with proper storage contractor’s EHS Officer PMU / labeling. NOTE. It is illegal to carry a waste drum on sites bid cost State Env the highway without labelling ! Refuelling Regularly check containers for leakage and undertake Designated Part of Contractor’s CSC / and vehicle necessary repair or replacement. storage contractor’s EHS Officer PMU / maintenance sites bid cost State Env Store hazardous materials above flood level. Designated No additional Contractor’s CSC / storage cost EHS Officer PMU / sites State Env Storage areas for fuel, oil, lubricant, bitumen and Designated Part of Contractor’s CSC / other hazardous substance will be located at least 100 contractor’s EHS Officer PMU / ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 185 m away from any watercourses. bid cost State Env storage sites Storage areas will be bunded and provided with Designated Part of Contractor’s CSC / interceptor traps so that accidental spills do not contractor’s EHS Officer PMU / contaminate the environment. storage bid cost State Env sites Storage, transport and disposal of hazardous wastes, Constructio Part of Contractor’s CSC / including spill wastes, shall be consistent with n site contractor’s EHS Officer PMU / national and local regulations. bid cost State Env Wherever possible, refueling will be carried out at a Constructio No additional Contractor’s CSC / garage, gas station or fuel storage area. n site EHS Officer PMU / cost State Env Refuelling shall not be permitted within or adjacent Constructio No additional Contractor’s CSC / to watercourses. n site EHS Officer PMU / cost State Env All areas intended for storage of hazardous materials Designated Part of Contractor’s CSC / will be quarantined and provided with adequate contractor’s EHS Officer PMU / facilities (e.g., fire fighting equipment, sorbent pads, storage bid cost State Env etc.) to combat emergency situations complying with sites all the applicable statutory stipulation. Vehicle maintenance and refueling will be confined to areas in construction sites designed to contain spilled lubricants and fuel. Blasting of Safety risks to Blasting will be carried out only with permission of the All areas No additional Contractor State Env rocks in workers and the concerned authority, using a pre-established where cost quarries or public schedule. blasting will on site. occur All the statutory laws, regulation, rules etc., All areas No additional Contractor’s State Env pertaining to acquisition, transport, storage, handling where cost EHS Officer and use of explosives. blasting will occur ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 186 The timing will be made available to the local people All areas No additional Contractor’s State Env within 500 m of the blasting site in all directions, where cost EHS Officer depending on the total charge used. blasting will occur Blasting will be held only during day time and shall be All areas No additional Contractor State Env carried out not using high powered explosives. Under where cost no circumstance will blasting be undertaken at night. blasting will occur Where possible blasting mats will be used to reduce All areas bid cost Contractor State Env noise levels when blasting is carried out to reduce where flying rock. blasting will occur No blasting will take place without condition survey All areas No additional Contractor State Env of the buildings within 500 m. where cost blasting will occur People living near blasting sites will be informed of All areas No additional Contractor’s State Env blasting times prior to the blasting. where cost EHS Officer blasting will occur Earthworks / Improper spoils The spoils disposal site shall be located at least 50 m Constructio Part of Contractor CSC / excavation disposal could from surface water courses. Avoid steep slopes in n site. contractor’s PMU cause stockpiles. Provide grass cover and other suitable bid cost deterioration of slope stabilization measures on long term stockpile of water quality, spoils to prevent runoff in heavy rain. Spoils shall only damage to be disposed to areas approved by local authority. productive land Under no circumstances will removed spoil materials Constructio No additional Contractor’s State Env and flow be dumped into watercourses. n site. cost EHS Officer obstruction of water courses. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 187 Transport of Damage to The contractor shall not allow overloading of trucks Constructio No additional Contractor’s State Env materials community used for all project- related activities. n site. cost EHS Officer and spoils, The contractor shall immediately repair any damage Constructio Part of Contractor CSC / operation of utilities such as caused by the project to community facilities such as n site. contractor’s PMU / construction water supply water supply, power supply, irrigation canals, bid cost State Env equipment pipes, irrigation drainage and the like. Adequate compensation shall and various canals, drainage, be paid to affected parties, as necessary. construction etc. Access roads damaged during transport of Constructio Part of Contractor CSC / activities construction materials and other project-related n site. contractor’s PMU / may occur activities shall be reinstated upon completion of bid cost State Env during construction works. construction activities. Road traffic Traffic Set up clear traffic signal boards and traffic advisory Road access Part of Contractor CSC / and access to disruption and signs at the road going in and out the construction to contractor’s PMU / sites obstruction of site to minimize traffic build-up outside the houses. constructio bid cost State Env access to Check vehicles are not causing congestion n site / Police roadside Provide sufficient lighting at night within and in the Road access Part of Contractor CSC / properties vicinity of construction sites. to contractor’s PMU / constructio bid cost State Env n site / Police Provide safe temporary accesses to properties and Road access Part of Contractor CSC / establishments affected by disruption to their to contractor’s PMU / permanent accesses. constructio bid cost State Env n site / Police Provide adequate signage and flag persons for traffic Road access Part of Contractor CSC / control. to contractor’s PMU / constructio bid cost State Env Traffic control should be installed to prevent traffic n site / Police accidents. Vehicles on the main road should be given right of way and site vehicles made to wait. Warning signs should be posted uphill of the sites warning oncoming traffic to slow down. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 188 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 189 Temporary bypasses should be constructed. Road access Part of Contractor CSC / to contractor’s PMU / constructio bid cost State Env n site / Police Operation of Impacts to flora Spoils and all types of wastes shall not be dumped Around No additional Contractor CSC / and into forested areas, agricultural land, densely constructio cost PMU / construction vegetated areas, and water courses. n site and State Env site fauna near workers camps The contractor shall prohibit cutting of trees for Around No additional Contractor CSC / concrete formwork and for use in for construction- constructio cost PMU / related activities. The contractor will not use or n site and State Env permit the use of wood as a fuel for the execution of near any part of the Works, including but not limited to the workers heating of bitumen, and ensure that fuels other than camps wood are used for cooking, and water heating in all his camps and living accommodations. Presence of Impacts to flora Workers shall be prohibited from collecting firewood constructio No additional Contractor CSC / workers and from surrounding forests, and from hunting wild n site and cost PMU / animals. near State Env fauna workers camps Construction Health and Conduct orientation for construction workers Constructio Part of Contractor’s CSC / safety risks to regarding emergency response procedures and n site and contractor’s EHS Officer PMU workers workers and the equipment in case of accidents (e.g., burns, spills of workers bid cost = camps public hazardous substances, etc.), fire, etc.; health and camps $5,000 safety measures, prevention of HIV/AIDS, malaria, diarrhea, and other related diseases. Provide drainage at construction sites and workers Constructio Part of Contractor CSC / camps to prevent water logging/ accumulation of n site and contractor’s PMU stagnant water and formation of breeding sites for workers bid cost = mosquitoes. camps $5,000 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 190 Provide fire fighting equipment and appropriate Constructio Part of Contractor CSC / emergency response equipment (based on on-going n site and contractor’s PMU construction activities) at the work areas and at workers bid cost = construction and workers camps. camps $5,000 Provide first aid facilities that are readily accessible by Constructio Part of Contractor’s CSC / workers. n site and contractor’s EHS Officer PMU workers bid cost = camps $5,000 At the workers camps, provide adequate housing for Constructio Part of Contractor CSC / all workers at the construction camps, provide n site and contractor’s PMU reliable supply of potable water, install separate workers bid cost = hygienic sanitation facilities/toilets and bathing areas camps $25,000 with sufficient water supply for male and female workers and establish clean eating areas and kitchen. Provide workers with appropriate safety Constructio Part of Contractor CSC / equipment/devices PPE such as dust mask, hard hats, n site and contractor’s PMU safety shoes, goggles, ear plugs, etc. and strictly workers bid cost = require them to use these as necessary. camps $15,000 Install warning sign boards and lighting systems at the Constructio Part of Contractor CSC / construction sites, borrow pits, or places which may n site and contractor’s PMU cause accidents for people and workers workers bid cost = camps $5,000 Strictly impose speed limits on construction vehicles Constructio No additional Contractor’s CSC / along residential areas and where other sensitive n site and cost EHS Officer PMU receptors such as schools, hospitals, and other workers populated areas are located. camps Educate drivers on safe driving practices to minimize Constructio No additional Contractor’s CSC / accidents and to prevent spill of hazardous n site and cost EHS Officer PMU substances and other construction materials during workers transport. camps Barriers (e.g., temporary fence) shall be installed at Constructio Part of Contractor CSC / construction areas to deter pedestrian access to n site and contractor’s PMU ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 191 these areas. Do not allow people particularly children workers to cross the site. camps bid cost Sufficient lighting at night as well as warning signs Constructio Part of Contractor CSC / shall be provided in the periphery of the construction n site and contractor’s PMU site. workers bid cost camps The general public/local residents shall not be Constructio Cost = Contractor CSC / allowed in high – risk areas, e.g., excavation sites and n site and $25,000 PMU areas where heavy equipment is in operation. Hire workers Security officers. camps Ensure proper collection and disposal of solid wastes Constructio Part of Contractor CSC / within the construction camps consistent with local n site and contractor’s PMU regulations. workers bid cost camps Provide fencing on all areas of excavation greater Constructio Part of Contractor CSC / than 2 m deep. n site and contractor’s PMU workers bid cost camps Ensure audible reversing signals are installed on all Constructio Part of Contractor CSC / construction vehicles. n site and contractor’s PMU workers bid cost camps Measures to prevent malaria shall be implemented Constructio Part of Contractor’s CSC / (e.g., provision of insecticide treated mosquito nets to n site and contractor’s EHS Officer PMU workers, spraying of insecticides, installation of workers bid cost proper drainage to avoid formation of stagnant camps water, etc.). Discharge of untreated sewage shall be prohibited. Constructio Part of Contractor CSC / n site and contractor’s PMU workers bid cost camps ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 192 Operation of Social conflicts Locate construction camps away from communities Constructio No additional Contractor’s CSC / construction (at least 500 m away) in order to avoid social conflict n workers cost EHS Officer / PMU / WB sites and in using resources and basic amenities such as water camps Local workers supply. community camps Maximize number of local people employed in Local No additional Contractor’s CSC / construction works. community cost EHS Officer / PMU / WB Local community Maximize goods and services sourced from local Local No additional Contractor’s CSC / commercial enterprises. community cost EHS Officer / PMU / WB Local community Commissioning Phase Installing Spillages Spillages of transformer oils may occur during loading. Transforme Part of Contractor’s CSC / transformers while loading Use containment around the transformers and have spill r substation commissioni EHS Officer / PMU / oils. mop kits nearby. ng Local Fire WB contractors Department bid price Testing Fire Have fires extinguishers handy. Notify fire department Transforme Part of Contractor’s CSC / switch gear and request an appliance on be on standby or preferably r substation commissioni EHS Officer / PMU / WB and at the site. ng Local Fire capacitors contractors Department bid price ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 193 Operation Phase High voltages Air quality High electric fields around power cables attract Transforme Operational TCN Site Staff TCN PMU airborne pollutants, such as occur near a main road, r substation expenses / WB chemical factory, sprayed fields, etc. These are then deposited downwind or in rain. Anticipate dust down wind of HV lines. Overhead Safety Electric overhead lines are a source of electric and Transforme Operational TCN Site Staff TCN PMU magnetic fields. Safety distances must be observed. r substation expenses / WB The proper clearance from the overhead bus is calculated for each station, and conductors are positioned accordingly, using a conservative distance to ensure the safety of anyone walking through a station. For 333kV, a safe distance of 6m has been established. For 11kV to 132kV a safe distance of 4m has been established. To stay safe from the electric bus inside a substation, one should not climb nor carry tools above the shoulder. Ground level Maintain safety by locked doors on cages, and fenced- Transforme Operational TCN Site Staff TCN PMU Safety in areas for capacitor banks, exposed electrical r substation expenses / WB conductors, circuit breakers and lightning arrestors. All such areas should have warning signs. Underground Ground all electrical conductors. Place warning signs Transforme Operational TCN Site Staff TCN PMU Safety above underground cables and earth grids. r substation expenses / WB Hot work Ensure all maintenance works near HV cables and Transforme Operational TCN Site Staff TCN PMU permits equipment is subject to Hot work permits. No work r substation expenses / WB must be allowed without Possession Orders and Isolation procedures. Pesticides Water Substation yards are regularly maintained by using a Transforme Operational TCN Site Staff TCN PMU contamination variety of herbicides. Ensure pesticides are applied at r substation expenses / WB ground level if possible. If elevated sprays are used do not apply during strong winds. Warn staff to close windows. Ensure workers wear appropriate PPE such as masks. Handle drums cautiously and avoid spills on ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 194 gravel areas where it is difficult to mop up. Elevated Birds Birds may nest in tower and high level structures. Transforme Operational TCN Site Staff TCN PMU structures Thus can lead to power outages. Check for bird nest r substation expenses / WB construction and remove during regular maintenance. Transformer Noise If the noise produced by an operating substation is Transforme Operational TCN Site Staff TCN PMU operation considered intrusive to adjacent property owners a r substation expenses / WB barrier of mature trees or tall soil berms between the substation and nearby residences can be helpful in partially reducing the perception of noise impacts, although trees do very little in reality. Earth berms can reduce up to 7dBs but as the sound is low frequency barriers are not very effective. Carr Security Light pollution Lighting may be considered a nuisance in some Transforme Operational TCN Site Staff TCN PMU lighting residential areas. Substations may have lights that r substation expenses / WB operate all night long to discourage vandalism and unauthorized individuals. Downward-focused security lighting can help to avoid or reduce light pollution. Transformer Spillages of oils. Spillages of transformer oils may occur. Use Transforme Operational TCN Site Staff TCN PMU maintenance containment around the transformers and have spill r substation expenses / WB mop kits nearby. Dispose of oil to sanitary landfill. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 195 General Health and An Environment Health and Safety Officer (EHSO) Transforme Operational TCN Site Staff TCN PMU Operation Safety should be appointed to ensure that the EMP is r substation expenses / WB implemented The EHSO will ensure that accurate records and Transforme Operational TCN Site Staff TCN PMU reports of any occupational health and safety r substation expenses / WB incidents are kept, and reviewing the distribution and use of appropriate PPE. The EHSO will also encourage awareness building on Transforme Operational TCN Site Staff TCN PMU safety through activities such as “Toolbox Briefings” r substation expenses / WB and reporting “Near Misses.” TCN Site Staff Conduct site briefings for visitors on restricted areas Transforme Operational TCN PMU and emergency evacuation procedure. Hold r substation expenses / WB Induction EHS briefings for new staff. Follow NERC procedures as laid down in : Transforme Operational TCN Site Staff TCN PMU r substation expenses / WB  Part I. How to Evaluate Safety Programs;  Part II. Safety and Best Industry Practices;  Part III. Worker Safety Rules;  Part IV. Recordkeeping, Training, Inspections, Accident Investigation and Reporting;  Part V. Risk and Vulnerability Assessments Implement Corrective Action Reporting (CAR) Transforme Operational TCN Site Staff TCN PMU r substation expenses / WB Decommissioning Removing Spillages of oils. Spillages of transformer oils may occur as equipment Transforme Part of Contractors TCN PMU transformers is removed. Use containment around the r substation Contractors / WB transformers and have spill mop kits nearby. costs Demolishing Solid wastes Solid wastes such as brick, concrete and rubble from Part of Contractors TCN PMU buildings substation site demolition will need removal. Hire Contractors / WB licensed waste contractor and remove to LGA costs approved landfill. Recycling of construction rubble ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 196 may be approved if carried out in clean manner. Dismantling Scrap metal Metals and cables from towers dismantling can Transforme Part of Contractors TCN PMU towers become an eyesore if not taken off site either for re- r substation Contractors / WB use or recycling. They can be sold to an approved costs scrap metal dealer. Site Ecology changes Invasive flora species could colonise former Transforme Part of Contractors TCN PMU abandoned substation sites and the way-leave on r substation Contractors / WB decommissioning following removal of structures, costs buildings and hardcover. Arrange for maintenance of site after closure until handover. Use of noisy Excessive noise Local residents could be subject to noise impacts Transforme Part of Contractors TCN PMU machinery levels during demolition. Maintain perimeter noise levels r substation Contractors / WB below 75dB(A) to meet industrial standard and only costs work between 0700 and 1900. Spillages of Soil It is necessary to establish if deterioration has taken Transforme $20,000 Contractors TCN PMU oil contamination place between site occupation and site r substation / FMEnv / decommissioning. Repeat sampling of soils in same WB locations as were sampled in the original baseline. Take to lab for analysis of all parameters recorded in baseline. Then compare results with baseline conditions to give Before and After comparison. Groundwater It is necessary to establish if deterioration has taken Transforme $20,000 Contractors TCN PMU contamination place between site occupation and site r substation / FMEnv / decommissioning. Repeat sampling of groundwater in WB same locations as were sampled in the original baseline. Take to lab for analysis of all parameters recorded in baseline. Then compare results with baseline conditions to give Before and After comparison. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 197 14.32 Costs of Implementing the ESMP The requirements of the ESMP are mainly related to Occupational Health and Safety and compliance with the environmental regulations pertaining in Nigeria at the present time. This is the law of the land and it can be argued that the contractors should be meeting these legal requirements as a matter of course. However contractors often protest that they have not allowed for environmental compliance in their bid prices. Although this is a spurious argument it can be helpful to include a budget line for environmental compliance in the tender documents. This can include, among others, things like appointing an EHO, providing PPE for workers and installing fuel stores correctly. The contractor should be required to show these costs in his bid. The information below is a guide : Table 14-2: Costs of Implementing the ESMP Environmental Control Item Timing Cost US$ Construction of hard standing for fuel storage Before any fuel oils stored $10,000 tank and kerbing around perimeter with on site provision of lightweight roof to prevent ingress of rain. Any oil storage facilities on site must have kerb high enough to contain 110% of tank volume. Provision of spill control materials to mop up Before any fuel oils stored $2,000 any oil spills on site. on site Provision of closed containers on site for Before any vehicles access $4,000 waste oil, engine oil, used engine oil filters the site. and other oily waste hazardous waste. Contract with licensed hazardous waste collector for removal of skips for duration of site works. Provision of cooking area for site staff with Before any workers enter $10,000 enclosed food storage area and clean the site. canteen facilities for staff. Provision of separate toilets for men and Before any workers enter $10,000 women. Toilets must have underground the site. septic tanks or be chemical toilets. Provision of sanitary facilities with showers Before any workers enter $5,000 and washing areas if workers sleep on site. the site. Provision of garbage skips on site for food Before any workers $5,000 waste and other non hazardous waste. occupy site. Contract with licensed waste collector or municipality for removal of skips for duration of site works. Construction of temporary stormwater Before any vegetation is $5,000 drainage channels. removed from site. Covering of stockpiled materials by tarpaulins $2,000 or other covering materials to prevent raw materials such as sand or soil from being carried away into nearby drains by rain water runoff. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 198 Issuing of PPE (Personal Protective Before any workers start $15,000 Equipment) such as high visibility jackets, work. safety helmets, boots, and also ear plugs if using noisy equipment, and protective goggles where using cutting saws or rotating machines. Induction course for all new workers on Before any workers start $5,000 environment health and safety. work. Hiring of security officers with instructions Before work commences. $25,000 not to allow any workers onto the site who are not wearing all the correct PPE. Noise level measurements at four locations Every 6 months or in $12,000 around the site, or if response to complaints, response to complaints. at complainants house or premises. Repeat of baseline environmental survey in After construction $40,000 accordance with TCN Standard Practices for finishes. Environmental Audits. TOTAL $150,000.00 As a general rule 1% to 1.5% of the total contract value should be allocated to environmental compliance. As the contract value is typically US$10M this will equate to about $100,000-$150,000. Operationally -The baseline should be repeated every three years in accordance with TCN Standard Practices for Environmental Audits. Based on information from TCN the cost of this is estimated to be $40,000. 14.33 Environmental Monitoring Measurements The essence of monitoring is to ensure Compliance with Environmental Legislation. The contractors have a duty to comply with the relevant legislation. The supervising consultant must check their activities and report to TCN. In the event of noncompliance TCN can exert pressure on the contractor to comply. The measurements to be made and standards to be met are given below. There will be a “hierarchy” of monitoring and measurements. This would be based on:  Contractors  Construction Superving Consultant Inspector  TCN PMU  FMEnv Initially, contractors should check daily that all operations are being conducted correctly. In general “good housekeeping” must be employed. Overflowing of septic tanks must be checked by visual inspection. Dust must be controlled by covering of stockpiles and water sprays. Solid waste, engine oil and grease, must be taken away by waste removal contractors and records kept. Construction supervision inspectors must make daily spot checks and weekly formal checks on site operations. They must cross check all of the above and view records for waste disposal. They must also ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 199 investigate any pollution incidents or complaints. They must use the checklists for record purposes and make sure that the complaint or incident is brought to the notice of the contractor immediately, verbally and with a follow up written notice. FMEnv staff will have access to noise and water quality monitoring equipment. When requested by TCN-PMU FMEnv inspectors must visit the site and make measurements. The equipment for noise and water will give direct results so data will be available immediately. In the event that more detailed information is required on water quality samples can be taken of water and delivered to a commercial laboratory for analysis. In addition PMU staff should make monthly visits to site to check the veracity of reporting. They should also review the reports submitted by the CSC to TCN and report to the TCN project manager. If vibration measurements or dust measurements are required then specialized equipment will be needed. If dust measurements are needed than a two stage process must be adopted. A High Volume Sampler (HVS) will be deployed by FMEnv or a private local consultant. After a suitable period, usually 24 hours, the filter in the HVS will be retrieved and transported to the laboratory for the second stage which is analysis. This requires highly specialized equipment. The Lab will charge for this service. These charges must be covered by the contractor. The results must be submitted to PMU who will interpret them with respect to the relevant regulations. Discussions must then be held with the contractor to determine how to resolve any problems. After extraction from borrow areas is finished, revegetation and reinstatement must be carried out. Warning signs must be erected to avoid drowning if deep ponds are left. CSC Inspectors staff must make regular checks by visual inspection. Timing of Monitoring The timing of the monitoring is important. The following list is for guidance and is indicative only.  Liquid emissions from sites must be checked every three months or after heavy rain if overflowing is reported. Measurements in streams and water courses must be made.  Dust emissions on site must be checked weekly by visual inspection and monthly by examining records of water spraying. Ambient air quality must be checked over a 24 hour continuous period at sensitive receptors in the event of complaints.  Noise levels must be checked every three months at site perimeters, or in the event of a complaint, at night as well as during the daytime.  Correct removal and disposal of food waste and waste engine oil and grease must be checked weekly by visual inspection of the camps and checking of records from the waste disposal contractors.  Noise and vibration must be checked at sensitive receptors when blasting first occurs or in the event of complaint. Before blasting commences warning notices must be posted to local residents.  Reinstatement of borrow pits and quarries must be checked after closure of the facility. In addition to regular monitoring, unannounced spot checks must be made by TCN-PMU on contractors operations. All of the above procedures should be carried out by the site CSC inspectors, in conjunction with PMU, and where appropriate FMEnv. The results should be formally recorded every week and compiled into a monthly report. This should be submitted to TCN and the contractors as necessary but at a minimum on a monthly basis. Monthly reports should be compiled into quarterly and annual reports to be submitted to WB. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 200 Beyond Compliance It will be necessary to carry out measurements to establish if the regulations are being met. In fact, simple compliance with the standards is not necessarily the final objective. There is no harm in the contractor “going beyond compliance” and running an operation better than that required by the standards. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 201 Table 14-3: Measurement of Environmental Parameters during Construction Environmental Issue Parameter Standard Timing Equipment Institutional Responsibilities Water Quality BOD < 50mg/L every 3 months Water Sampler Contractor SS < 50mg/L or after heavy rain Temperature <45oC pH 6-9 Oil & Grease < 5mg/L Dissolved Oxygen > 5mg/L Air Quality TSP < 0.33 mg/m3 24 hours H.V.S + Lab FMEnv Noise Quality Leq Site Boundary 75dB(A) (daytime 07-19) Noise Meter Contractor Leq Site Boundary 65dB(A) (nighttime, 19- 07) Vibration PPV < 1mm/sec During blasting Vibration meter Contractor Solid Waste Food Waste Properly Removed Daily Visual Inspection Contractor Liquid Waste Waste Oil, Grease Properly Controlled Weekly Visual Inspection Contractor After Removed by Subcontractor Septic Tank Smell, Sewage No Smell, No During Operation Visual Inspection CSC Inspector Overflowing Borrow Pits Condition of Filled after Project After Closure Visual Inspection CSC Inspector Borrow Pits Completion, Topsoil resurfaced Borrow Pits Depth of Borrow No Drowning Hazard After Closure Visual Inspection CSC Inspector pits Borrow Road Location for Meet the Engineer After Closure Visual Inspection CSC Inspector Borrow Road Demand Quarries Condition of Quarries reinstated After Closure Visual Inspection CSC Inspector ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 202 Quarries ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 203 1 4 . 3 4 Grievance Redress Mechanism Villagers and APs are encouraged to voice complaints and these are to be duly investigated and reported through the contractor to PMU and so to TCN. As a consultative procedure has been established through public consultation it is recommended that this procedure be maintained and extended to include environmental issues. Environmental monitoring must be carried out by the construction supervision inspectors, all of whom must have previous experience of environmental issues on similar projects. Response to complaints will be based on the following schedule:  Complaint made to contractor  Response by contractor or construction supervision consultants’ inspectors.  Weekly compiling of checklists by inspectors. Copies of checklists to be given to contractors as official notification of action being required, confirmation of receipt obtained by contractor signing copy, and joint inspection carried out if necessary.  Monthly progress reports by inspectors by consolidating weekly reports.  Corrective Action Reports (CARs) from contractors, as soon as action taken.  Monthly progress meetings with contractors at which CARs from previous month examined and checked.  Three monthly progress reports to WB detailing problems and Corrective Actions taken.  Checks with complainants that they are satisfied Review of progress must be checked on a daily basis by the inspectors. Any urgent issues must be drawn to the contractors’ attention immediately. Failure by the contractor to respond in a timely or adequate manner must be raised with them at the monthly progress meetings. The procedure is shown below. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 204 Figure 14-4: Complaints Investigations Procedure 14.35 Corrective Action Reporting In the event of an incident or complaint Corrective Action Reporting must be implemented. This is an iterative process whereby reported incident cannot be left unattended. In the event of an incident the contractor will be informed verbally to be followed up by a formal instruction, which can be handwritten. This would then be followed by a letter. The contractor will be expected to take action immediately or as soon as reasonably possible. There is no reason to delay. In monthly progress meetings between contractor and client’s representative the incident report will be reviewed. If the incident has been dealt with and the situation is now satisfactory this will be recorded. If the situation is still not acceptable then a CAR will be issued. This warns the contractor that unless action is taken financial penalties may be applied. The situation is then formally reviewed at the next monthly meeting (See Figure 14-5 below) This procedure is intended to ensure that incidents and remedial measure are not overlooked. It does not mean the contractor can wait a month to take action. A prompt response to any situation is expected. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 205 Figure 14-5: Corrective Action Reporting (CAR) Procedure 14.36 Institutional Roles and Responsibilities Institutional Arrangements In order to implement the project various stakeholders will have a part to play. Their roles and responsibilities are described below. Where appropriate, capacity building and enhancement is recommended. Federal Ministry of Environment The Federal Ministry of Environment is the Agency of government responsible for the formulation and enforcement of policies/regulations on environment in Nigeria. Under this project the Federal Ministry of environment will perform supervisory functions at the government level during construction and even during operation of the facility. This will involve taking measurements and collecting relevant samples. Experience, though, has shown that the Ministry lacks the budgetary provisions required to enable it carryout its role in ensuring safeguards compliance. The Ministry lacks the equipment required to carry out basic sampling and even had to be rescued by TCN-PMU through NEGIP for the provision of internet services, a functional website, office equipment, project vehicles and a stand-by generator. It is necessary that the TCN-PMU extend this goodwill to this project by providing basic sampling equipment. TCN management Following the implementation of previous World Bank assisted energy projects like the Nigeria Transmission Development Project (NTDP) and the National Energy Development Project (NEDP) the management of TCN established an Environment, Resettlement and Social Unit (ERSU) at the corporate headquarters. There are plans to extend this structure to the regional offices with the presence of two (2) ERSU personnel at the Regional offices and one (1) in each substation. TCN needs to ensure swift implementation of this ERSU structure and provide appropriate training and equipment for the ERSU staff to enable them carryout their role as stated in this ESIA. TCN-PMU & ERSU-PMU The ESRU-PMU has been managing safeguards compliance of all World Bank financed power projects since the inception of the TCN-PMU. This Unit is made up of well trained personnel that have been involved in safeguards monitoring and preparation of safeguards instruments required by the World Bank for Electric Power Projects. The ERSU will assign specific personnel that will be responsible for monthly safeguards monitoring of the execution of the contract. They will produce monthly reports that will be used in assessing the level of compliance of the contractor with the provisions of this ESIA. The ERSU personnel will also be responsible for raising quarries and penalties ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 206 in the event of a default on the part of the Contractor to avoid a complete deterioration of the safeguards conditions of the project site. The TCN-PMU has in the past provided capacity building and training assistance to the Federal Ministry of Environment and the TCN-ERSU. A lot still needs to be done in this area to ensure safeguards compliance at the project sites considering the non-availability of resources for both agencies to accomplish this task. TCN on-site personnel The TCN on-site personnel will be responsible for the day-to-day safeguards supervision of the execution of the contract. They will alert the regional TCN office and the ERSU PMU of any serious safeguards breaches or accidents for immediate follow-up actions. They will also compile their weekly safeguards monitoring reports and send to the ERSU-PMU and TCN regional offices for any further necessary actions. The Supervising Engineer Besides ensuring strict compliance with the engineering specifications the Supervising Engineer is also expected to ensure compliance with all other aspects of the contract by the Contactor like environmental and social safeguards. Consequently, the supervising Engineer is expected to have a suitably qualified HSE personnel on site on a daily basis. This HSE personnel will grant work permits, enforce use of PPEs, ensure that only suitably qualified and properly trained persons are used by the Contractor for any particular jobs, enforce ‘stop work’ orders in the event of safeguards breach by the Contractor and recommend appropriate punitive measures to prevent re-occurrence of same. Construction Contractor The civil works contractors must implement adequate precautions to protect the environment, avoid disturbance to residents, deterioration of the amenity of the area, and ensure the health and safety of construction workers. The contractors will undertake the following activities:  An Environment Health and Safety Officer (EHSO) will be appointed who must prepare an Environment Health and Safety Management Plan (EHSMP)  The EHSO will ensure that the EHSMP is submitted to TCN prior to construction for approval  The EHSO will ensure that accurate records and reports of any occupational health and safety incidents are kept  The occupational health and safety risks will be minimized by providing adequate personal protective equipment (PPE) and ensuring workers wear it. The EHSO will review the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.” Contractors should check daily that all operations are being conducted correctly. In general “good housekeeping” must be employed. Contractor must report on a monthly basis to the CSC on implementation of the ESMP. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 207 Notwithstanding monthly reporting they must react promptly to any incidents occurring and respond quickly to any complaints received. All monthly reports will be compiled into 3 monthly, 6 monthly and annual reports. World Bank All monthly, 3 monthly and 6 monthly reports will be compiled into an annual report to be submitted by TCN to World Bank. An annual review and environmental and social audit may be carried out by WB at their discretion. Plant Operator After construction the site will be taken over by the plant operator. This will probably be TCN but could be a third party in the event of a transfer such as occurs in privatisation. The operator will be required to observe and comply with the requirements of the ESMP and follow the reporting schedule described above. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 208 15 Public Consultation 15.1 Consultation with Stakeholders Consultations were held with regulatory agencies and other relevant stakeholders as shown below :  Federal Ministry of Environment,  State of Kogi Ministries of Environment,  State of Kogi Ministries of Lands/Surveyor General’s offices,  Community Based Organizations,  TCN Regional Offices in  ERSU - PMU - TCN  Project-affected persons ( PAPs) During the Initial Site reconnaissance consultations were held with PAPs. Then during the Baseline Site Sampling Focus Group discussions were held. Public consultations were then held in Abuja as an Interagency Meeting and in the state. 15.2 Interagency The Interagency Meeting was held at TCN offices in Abuja on September 15th 2015. It was well attended with 30 people present and several presentations were made by TCN, consultants and World Bank. TCN emphasized its approach to Corporate Social Responsibility (CSR) through which it wants to implement a good neighbor policy and will achieve this through preparation and use of good Environmental and Social Impact Assessment (ESIA) and Environmental and Social Management Plan (ESMP). TCN GM PMU Engr. Ciroma Joseph stated that the stakeholder meeting was the first stage of stakeholder engagement. He explained that the Environmental and Social Impact Assessment study is a requirement by the World Bank and must be done before the project can be carried out. He explained that the forum must be an open and interactive session A goodwill message was delivered by Mr. Biodun representative of the Permanent Secretary, Federal Ministry of Finance (FMF). He commended the efforts of the PMU in organizing the forum and the efforts of World Bank in providing funding for the project. He stated that sustainable development is hinged on three pillars- economic viability, social and environmental safety. He stressed that we must ensure that the project does not have adverse impact on the health, livelihood and safety of the communities and the general public. World Bank stressed the need for an effective Grievance Redress Mechanism. FMEnv emphasized the need for site visits to establish the real situation on the ground. SMEC concurred with this approach and stated that the Team Leader had visited the site so that all GIS data could be ground truthed. Metaspec confirmed that their staff were in the field carrying out baseline sampling at that moment. . No objections were raised to the project. Further details were requested as the project progresses. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 209 15.3 Kabba, Kogi The Public Consultation was held in St. Augustine College Hall, Kabba, Kogi State on the 15th of October 2015. Previously letters of invitation had been sent out and adverts placed in two newspapers. The session was well attended with 104 people present and presentations were made by TCN and the consultants. A welcome Address was given by Honourable Segun Ogbonikan (SSA1/Acting Chairman Kabba/Bunu LGA). He stated that he and his people were excited by the presence of the World Bank/ TCN / SMEC team to Kabba and believed the visit will be the last prior to the start of the project. Good will messages were received from participants during the meeting. Stakeholders were optimistic about the project and expressed commitment to ensuring it is successful. In the areas of security, labour demand and materials utilisation, the stakeholders agreed on ensuring support to World Bank. Stakeholders that expressed satisfaction during the meeting included :  J.K. Funsho Education Secretary (Kabba/Bunu LGEA)  Sir A. M. Olorunfemi President, Kabba Development Union (KDU).  Titilayo Omotola, Women Leader (KDU) Mrs Omotola stated that electricity will boost their yield and economic lives of the women as they assist their husband in their different endeavours as seamstress, hairdresser, etc. Mrs Afolabi Fausat of FMEnv) said community participation in World Bank projects is very important as it is used as indices to ascertain if the host community are in support of the project. Chief Dare Adebisi Commissioner of Land Representative asked is there a plan for economic trees on the project site. The response was the land was donated by the Obaro of Kabba and there are no economic trees on the project site. Chief Obafemi, Obarowe of Owe land, asked as to the model of the transmission is it hydro, coal or wind and what is the amperage. The response was the transmission is through power lines and TCN transmits voltage and not current. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 210 16 Conclusions 16.1 Potentially Adverse Impacts and Mitigation Noise Levels The Nigeria National Environmental Noise Standards and Control Regulation (2009) require noise levels of 50dB(A) Leq(12 hours) during the daytime and 35 dB(A) Leq(12 hours) during nighttime at the perimeter of the site to preclude noise nuisance to residential property that may be built adjacent to the site in the future. Based on the Technical Specification for transformers and measured noise levels, it is recommended that transformers should not be located within 80m of the boundary of the site. This is a worst case scenario. Following this recommendation would ensure no complaints over noise intrusion both during the night time and during daytime during operation. It also allows a margin for intensification of use in the future. Climate Change Climate change projections show that there will be significant differences between sites in the north and sites in the south, with the north being more subject to droughts and the south being more subject to floods. This may impact on the demand load imposed on the transmission system but will not impact on the site of this project 16.2 Positive Impacts  The proposed projects will provide short term, local employment opportunities during the construction phase for community members in terms of site clearance, excavation, loading and offloading of materials. Other short term opportunities may arise from the provision of security services where temporary camps or stores are erected and from opportunities to provide goods and services to construction workers e.g. food kiosks and other shops.  The long term impact is provision of power to the area with associated improvement in standard of living and economic development.  All new transformers are specified as being free of PCBs. No PCBs will be present on the sites and there is no need for concern on this issue. 16.3 Matrix of Significant Impacts The Matrix of Significant Impacts is given below. This site is one of four under consideration for project development. The matrix refers to all four although this ESIA refers only to Kabba. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 211 ENVIRONMENTAL IMPACTS Kabba Construction Operations Water Quality √ √ Flooding fromsleep gradient √√√ √ Soil Contamination from spills √√ √√ Physical Air Quality √ X Waste solid and liquid √ √ Noise √ √ Visual impact √ X Fauna √√ X Biological Flora √√ X Resetlement X X Cultural X X Socio Economic Occupational Health and Safety √√√ √√√ Community √√ X Utilities √ X None X Minor √ Moderate √√ Significant √√√ Figure 16-1 Matrix of Significant Impacts Prior to decommissioning, a decommissioning plan will be prepared, according to final monitoring and the decomissioning impacts listed in Table 14.1. A generic Decommissioning plan is given as a guide in Annex 7. 16.4 Development of the Site No key issues have been identified that will preclude the development of the sites as intended. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 212 17 Annexes 17.1 Annex 1 Environmental Regulations Gazetted The Federal Government through NESREA has developed 24 Environmental Regulations which have been published in the Federal Republic of Nigeria Official Gazette and are now in force. The Regulations are: 1. National Environmental (Wetlands, River Banks and Lake Shores) Regulations, 2009. S. I. No. 26. This Regulation provides for the conservation & wise use of wetlands & their resources in Nigeria and ensure sustainable use of wetlands for ecological and tourism purposes and to protect wetland habitats for species of fauna and flora. 2. National Environmental (Watershed, Mountainous, Hilly and Catchments Areas) Regulations, 2009. S. I. No. 27. This makes provisions for the protection of water catchment areas. 3. National Environmental (Sanitation and Wastes Control) Regulations, 2009. S. I. No. 28. The purpose of this Regulation is to provides the legal framework for the adoption of sustainable and environment friendly practices in environmental sanitation and waste management to minimize pollution. 4. National Environmental (Permitting and Licensing System) Regulations, 2009. S. I. No. 29. The provisions of this Regulations enables consistent application of environmental laws, regulations and standards in all sectors of the economy and geographical region. 5. National Environmental (Access to Generic Resources and Benefit Sharing) Regulations, 2009. S. I. No. 30. The overall purpose of these Regulations is to regulate the access to and use of generic resources to ensure the regeneration and sustainability of threatened species. 6. National Environmental (Mining and Processing of Coal, Ores and Industrial Minerals)Regulations, 2009. S. I. No. 31. This Regulation seeks to minimize pollution from mining and processing of coal, ores and industrial minerals. 7. National Environmental (Ozone Layer Protection) Regulations, 2009. S. I. No. 32. These provisions seek to prohibit the import, manufacture, sale and the use of ozone-depleting substances. 8. National Environmental (Food, Beverages and Tobacco Sector) Regulations, 2009. S. I. No. 33. These provides to prevent and minimise pollution from all operations and ancilliary activities of food, beverages and tobacco sector to the Nigerian environment. 9. National Environmental (Textile, Wearing Apparel, Leather and Footwear Industry)Regulations, 2009. S. I. No. 34. The main thrust of this Regulation is to prevent and minimize pollution from all operations and ancilliary activities from the sector to the Nigeria environment 10. National Environmental (Noise Standards and Control) Regulations, 2009. S. I. No. 35. The main objective of the provisions of this Regulation is to ensure tranquility of the human environment or surrounding and their psychological well-being by regulating noise levels. 11. National Environmental (Chemicals, Pharmaceuticals, Soap and Detergent Manufacturing Industries) Regulations, 2009. S. I. No. 36. This Regulation is to prevent and minimize pollution from all operations and ancilliary activities from this Sector in order to protect Nigeria environment. 12. National Environmental (Standards for Telecommunications/Broadcasting Facilities) Regulations, 2010. S. I. No. 11. The main objective of these regulations is to protect the environment and human health, ensure safety and general welfare, eliminate or minimize public and private losses due to activities of the telecommunications and broadcast industry ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 213 13. National Environmental (Soil Erosion and Flood Control) Regulations, 2010. S. I. No. 12. The overall objective of these Regulations is to check all earth-disturbing activities, practices or developments for non-agricultural, commercial, industrial and residential purposes. 14. National Environmental (Desertification Control and Drought Mitigation) Regulations, 2010. S. I. No. 13. This Regulation seeks to provide an effective and pragmatic regulatory framework for the sustainable use of all areas already affected by desertification and the protection of vulnerable lands 15. National Environmental (Base Metals, Iron and Steel Manufacturing/Recycling Industries) Regulations, 2010. S. I. No. 14. The principal thrust of this Regulations is to prevent and minimize pollution from all operations and ancillary activities of the sector in the Nigerian Environment. 16. National Environmental (Control of Bush/Forest Fire and Open Burning) Regulations, 2010. S. I. No. 15. The principal thrust of these Regulations is to prevent and minimize the destruction of ecosystem through fire outbreak and burning of any material that may affect the health of the ecosystem through the emission of hazardous air pollutants. 17. National Environmental (Protection of Endangered Species in International Trade)Regulations, 2010. S. I. No. 16. The major objective of this Regulation is to protect species of endangered wildlife from extinction through the prohibition of trade, importation, etc. 18. National Environmental (Domestic and Industrial Plastic, Rubber and Foam Sector)Regulations, 2010. . S. I. No. 17. The principal thrust of this Regulation is to prevent and minimize pollution from all operations and ancillary activities of the Domestic and Industrial Plastic, Rubber and Foam Sector to the Nigerian environment. 19. National Environmental (Coastal and Marine Area Protection) Regulations, 2010. S. I. No 18. This Regulation provides for the regulatory framework for the application of preventive, precautionary and anticipatory approaches so as to avoid degradation of the coastal and marine environment 20. National Environmental (Construction Sector) Regulations, 2010. S. I. No. 19. The purpose of these Regulations is to prevent and minimize pollution from Construction, Decommissioning and Demolition Activities to the Nigerian Environment. 21. National Environmental (Control of Vehicular Emissions from Petrol and Diesel Engines) Regulations, 2010. S. I. No. 20. The purpose of these regulations is to restore, preserve and improve the quality of air. The standards contained herein provide for the protection of the air from pollutants from vehicular emission. 22. National Environmental (Non-Metallic Minerals Manufacturing Industries Sector) Regulations, 2010. S. I. No. 21. The principal thrust of this Regulation is to prevent and minimize pollution from all operations and ancillary activities of the Non-Metallic Minerals manufacturing sector. 23. National Environmental (Surface and Groundwater Quality Control) Regulations, 2010. S. I. No. 22. The purpose of this Regulation is to restore, enhance and preserve the physical, chemical and biological integrity of the nation's surface waters, and to maintain existing water uses. 24. National Environmental (Electrical/Electronic Sector) Regulations, 2010. S. I. No 23. The principal thrust of this Regulation is to prevent and minimize pollution from all operations and ancillary activities of the Electrical/Electronic Sector. This Regulation covers both new and used Electrical/Electronic Equipment (EEE/UEEE) These Regulations are to ensure that the national development agenda is not at variance with the carrying capacity of the environment. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 214 17.2 Annex 2 Field Sampling and Analysis Plan (FSAP) Materials And Methods A.1 Background The fieldwork for data gathering was embarked upon in August and September 2015 (Rainy season) by a multi-disciplinary team. A reconnaissance visit was carried out to crosscheck potential sampling locations proposed on the location map of this study area with the actual situation on ground. Sampling was then commenced following the conclusion of this exercise. The actual locations where samples of different types were collected are indicated in study sampling Map. Sampling locations were identified using a Global Positioning System (GPSmap 76) Garmin GPS Receiver instrument configured in the Nigerian Minna datum with the geodetic co-ordinates of the points already imputed into the system. In the navigation mode, this equipment provides a compass of the target position, elevation above sea level and the UTM Coordinates of this target position. A.2 Statutory Regulators A representative from the Federal Ministry of Environment and some personnel from Transmission Company of Nigeria (TCN) were present throughout the duration of the fieldwork. Their function was to ensure that environmental samples were collected and preserved (where necessary) according to recommended procedures and practices for environmental data collection in Nigeria. A.3 Quality Control/Quality Assurance (QC/QA) The QC/QA programme covered all aspects of the study, including sample collection and handling, laboratory analyses, generation of data and coding, data storage and treatment as well as report preparation. The quality assurance programme used in the fieldwork and laboratory analyses is in accordance with recommendations by National and International Regulations. Sample Collection and Handling This was done as stipulated in National and International guidelines and standards. In preparation for fieldwork, glassware to be used were washed with detergent solutions, rinsed with tap water, then soaked in 1:3 nitric acid solutions for 24 hours to remove organic materials, washed again with tap water and rinsed with distilled water. Plastic containers were washed with detergents, rinsed with tap water, followed by distilled water. After drying, all the containers were rinsed with acetone to remove organic materials, and rinsed with distilled water. Aluminium foils were obtained for soil and sediment samples. Water sampling equipment was rinsed with portions of the water to be sampled. Composite samples per sampling point were taken with thoroughly cleansed containers. Sterile wide-mouth polypropylene and Pyrex glass sample bottles were used. Samples for oil and grease were collected in clean and dry glass- stoppered bottles and were usually not completely filled to avoid losing oil when the stopper was inserted. Sample identification Specific details on sample identification were entered on a permanent label to reflect project, date, ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 215 sample matrix, sampling point, sample number, depth, as the case may be. Storage/Preservation As samples could be subject to microbial degradation and transformation, they were therefore analysed at minimum time after collection. Since storage may be necessary for water samples for physico-chemical parameters, they were stored in ice-chest as a cooling device and transported to the laboratory where they were refrigerated at 4C. Samples for heavy metal analyses were preserved with 1:1 nitric acid and oil and grease with 1 ml of 1:1 H2SO4 as soon as they were collected as recommended. Adherence to good preservation procedures ensured that errors were not introduced into the analytical process. Fieldwork Carrying out field calibrations of equipment and running distilled water blanks reduce errors that could arise from field measurements. Replicate samples were collected and used as checks of instrument performance. Field analytical operations were done in a defined sequence to avoid cross contamination of instruments. (Conductivity was always determined before pH because concentrated electrolyte in the pH reference electrode may get into the sample and affect conductivity measurements) Field data collection procedures used for this fieldwork are discussed below: A.4.1Aquatic Environment Field Sampling procedures Water Chemistry/Microbiology A stainless steel grab was used to collect surface water samples at the designated locations at the top (a few cm below surface) of the water bodies. The following parameters were measured in-situ: pH, Temperature, Total Dissolved Solids (TDS), Dissolved Oxygen (DO), Electrical Conductivity (EC) and Turbidity. Amber bottles of 250ml capacity were used to collect water samples for microbiological analysis Plastic containers of 250 ml was used for heavy and trace metals and the samples were acidified to pH of 2 in the field using concentrated nitric acid. All the other samples for physico-chemical measurements were transported to the laboratory in ice coolers. Surface water samples were collected at the designated sampling points as in water chemistry. Sterile 1000 ml plastic containers with plastic screw caps were used to transport the samples. Sediment samples were collected at every site where water samples were obtained. Eckman Grab was used to obtain sediment samples. These samples were transferred into sterile polyethylene ziplock sachets. All sachets were appropriately labelled. The samples were preserved in ice chests and transported to the laboratory for analysis. Surface water velocity was measured at the various sample locations using a buoy, a meter rule and ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 216 a timer. The depths of the river were determined using a calibrated pole. A.4.2 Soil Chemistry/Microbiology Soil samples were collected from site as indicated in the location map provided for this exercise. Surface (0 – 15cm) and sub-surface (15 – 30cm) soil samples were collected at these locations using an Arts mfg stainless steel Hand Auger. Sampling tools are; Soil auger: Auger was made of stainless steel, and is capable of retrieving a cylindrical plug of soil 3 inches in diameter and 6 inches deep. Trowels: used for extruding soil sample from the auger and the use of chrome plated trowels was avoided because samples were to be analyzed for trace metals, as they may interfere with the analysis. Collection containers: The following sub-samples were taken for each depth, namely;  Samples for physico-chemical parameters which were put into polythene bags;  Samples for hydrocarbon analysis which were put into glass bottles;  Samples for hydrocarbon and microbiological analysis collected McCartney bottles were stored in ice-packed coolers Gloves: for personal protection and to prevent cross-contamination of samples. May be plastic or latex; should be disposable and powder less. .A.4.3 Vegetation and Wildlife The materials used for the field work include secateurs, polythene bags, large jute bags, laundry pen, labelling tapes, specimen bottles, hand lens, improvised hook and measuring/calibrated tapes. Sampling for diversity and abundance was carried out in blocks of 5 and 50m2 each, which were selected at random from the proposed project site and locations nearby settlements. Direct species counts were taken within the sampling blocks, which also served as quadrants. Leaf and stem materials were taken in specimen bottles containing 70% ethanol, fixative stain solution and formal acetic acid (FAA) for laboratory histochemical analyses. Plants were examined in vivo for signs and evidence of environmentally induced stress as well as disease conditions. General health condition of the vegetation was visually evaluated. Plant materials that could not be identified in the forest (on-site) were taken for identification with taxonomic keys and flora in the Herbarium. The wildlife assessment of this study involved a survey of amphibians, reptiles, birds and mammals within the Study Area. Experienced hunters in the area were located through personal contacts and in the first instance, were asked to give account of the variety of local animals using vernacular names. The names given by the hunters are most often generic, covering several similar species or even whole families. As a result, confirmation of the species present was made by presenting to the hunters colour photographs of the skins of some of the animals (Happold, 1987) and photographs ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 217 of snakes (Cansdale, 1961). A few additional confirmations were made through sighting and vocalization when the Assessment Team went to the bushes within the study area. A.4.4 Air Quality A.4.4.1 Sampling Scheme The primary-Secondary type of schemes for making air pollution measurements was applied to mitigate the problem of air quality sampling which are number of sampling stations, location of the stations, sampling time and the frequency of Sampling (Blokker 1973). The measurements were made with a group of instruments, which are moved from one fixed measuring point to another in a predetermined manner. These measurements are then related to meteorological data made at the same time or obtained from a synoptic meteorological station. An advantage of this scheme is that a large area was covered with a minimum of instruments. The data obtained fulfils the main objectives of characterizing air quality and checking adherence to air quality standards. A.4.4.2 Sample Collection At each sampling station one hour measurements was taken to enable us analyse for particulate matter suspended in the air, Carbon monoxide, nitrogen oxides as nitrogen oxide, sulphur dioxide, oxygen and hydrogen sulphide using a Testo 350XL Flue gas Analyser. The group of equipment for air quality sampling was moved from sampling station to sampling station after each round of sampling was concluded at a particular sampling location. For practical and security reasons, measurements were not taken far into the night. Nocturnal conditions were, therefore, not fully covered. During the sampling, care was taken to avoid undue interference from any ‘external’ gaseous emission source while sampling. (Team Vehicles) A.4.4.3 Meteorological Measurements The following supporting measurements were made: (i) Wind direction and Speed (ii) Air temperature (iii) Relative humidity (iv) Atmospheric Pressure This information is in addition to the continuous meteorological data which is available from the Nigerian Meteorological Agency (NIMET) and previous studies in the geographic area. The parameters were measured using hand held digital Anemometer. A.4.4.3 Noise Measurements Noise levels were measured using a hand-held battery operated noise level meter (TECMAN INSTRUMENTS – Digital Sound Level Meter Model No. TM824) within the proposed site and community respectively after it was calibrated with a digital Multi- Range Sound Acoustical Calibrator. The meter had measuring range of 30 – 130 dB (A), accuracy of ±1.5 dB (A) and Resolution: 0.1 dB. Monitors were located approximately 1.5 m above the ground and no closer than ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 218 3 m to any reflecting surface (e.g., wall). A.4.5Waste Management The various sources of an existing transmission substation generated wastes and the local waste disposal techniques in the project area were identified. This included identification of local waste management techniques and/or the ultimate destination of wastes. A.4.6Geology / Hydrogeology Soil profiles were determined through profile pits and coring with Arts mfg Stainless steel auger. During drilling, soil samples were regularly taken at one metre interval, visually described and a field litholog was prepared. The samples were then stored in polythene bags, sealed and transported to laboratory (geotechnical) for further studies. At each boring site, the following field data were collected: Ground elevation above mean sea level Depth of boring Existing hand dug wells and boreholes were sources of hydrological samples for groundwater quality check. Secondary data with primary data recorded during the field work were used for the geotechnical results. A.5 Laboratory Procedure/Data Analysis A.5.1 QA/QC for Laboratory analysis and generation of data Possible sources of error in laboratory analysis include contamination of reagents and materials, lack of sensitivity of equipment, lack of calibrations, poor data entry and interpretation. Glassware and other containers to be used for each analysis were thoroughly cleansed as appropriate for each parameter. All glassware used for oil and grease determination was pre-rinsed with Analar grade xylene. Glassware for determination of metals were pre-soaked in dilute nitric acid and then rinsed well with distilled water. All reagents and chemicals of high purity (mostly Analar grade) were used. Freshly distilled water prepared in the laboratory was used for all dilutions. The various instruments and equipment for measuring physico-chemical parameters were used while in good working condition. Periodic control checks were usually carried out on such instruments/equipment and performance records maintained. For analytical determination requiring the use of calibration curves, such curves were plotted using standard solutions prepared from analytical grade reagents. Records of such calibration curves were maintained and frequent re- calibration checks were carried out. Analytical blanks are incorporated per specific batches of samples to compensate for the sample preparation and determination steps. All the analyses were replicated and the means reported. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 219 Chain of samples custody procedure There is a Master register for all samples brought into the laboratory. Following registration of the sample, a Sample Data Sheet containing pertinent information on the sample was opened for the samples. The information includes:  sample reference number,  nature or type of sample,  site of collection,  date and time of collection,  mode of preservation (depends on nature of material) and analytical data from the field and results of laboratory analyses of representative samples. Appropriate methods were used in storing the remaining stock materials and sub samples. Samples for storage were kept in labelled compartments on shelves in a storage room. Samples sent to cooperating laboratories were recorded in the Master Register, accompanied by essential data pertaining to the sample material and appropriate custody transfer forms were filled. Evaluation of results Raw data obtained from the instrumental measurement were used in calculating the concentrations of the various parameters, using standardized formulae. All such calculations were crosschecked. Outlying values were deleted from the replicate data before calculation of mean concentrations. A quick identification of results, which deviate from the normal trend, was usually done. Calculated and observed conductivity measurements and other indicator parameters are compared, to check reliability and accuracy of data. A.6 Health Aspects This study was conducted using cross-sectional, descriptive design, consisting of epidemiological and environmental health survey. The tools and techniques of data collection were structured questionnaire, checklists, interviews and focus group discussions. Sample analyses were also carried out on domestic water sources and ambient air by the team. A.6.1Document review This first step of the study included the review of all relevant documents and literature that contribute to the HIA study. A.6.2 Community Consultations/Entry Community consultations form a key component, and have indeed been used as a vital tool in this HIA study. This vital process was intended to secure the much-desired social license (permit) to operate in the host communities. The broad objectives of this consultation process were:  To educate and enlighten the communities on the need for their involvement as partners in progress towards the successful conduct of the health assessment process.  To build up their trust in the project operators. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 220  To build trust and enhance the capacities of the host communities in health management, through participation in the identification of the pathways by which the health hazards may be introduced into the population.  To form and promote partnership with all other stakeholders, such as non-governmental organisations (NGOs), through information exchange and participation in open forum and consultations. During this study, consultations were carried out with communities and all relevant stakeholders prior to community entry and during each stage of the field work. A.6.3Focus Group Discussions and Interviews Focus group discussions were held in each of the study communities. The following focus groups were identified: Teenagers and adolescents  Adult males  Adult females and  Youth Oral Interviews were also conducted. Those interviewed were mostly health personnel and community opinion leaders. The questions were related to the following;  The health facilities available in the community,  The common diseases in the community,  Their health concerns related to the project.  Their health expectations from the project A.6.4Environmental Health Survey This consist of walk through surveys using prepared check list of environmental health issues such as general level of sanitation, waste disposal practices, water supply and the availability of health and health related facilities. Photographs of relevant health activities/ facilities were taken. The main issues assessed included: i. Types and quality of housing ii. Sources of water iii. Type of sewage disposal methods/facilities iv. Methods of refuse disposal/ general physical environmental cleanliness. v. Health facilities available vi. Environment- Health interplay ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 221 ENVIRONMENTAL PARAMETER EQUIPMENT UNIT COMPONENT METEOROLOGY Temperature Traceable C Thermometer Wind speed  Direction Skye Master m/s Anemometer & wind Vane Humidity, Atmospheric Skye Master Mini % Pressure Weather Station AIR QUALITY Suspended Particulate Met One Instrument Mg/m3 Matter Aerosol Mass Monitor Nitrogen Oxides Testo 350 XL Gas ppm Analyser Sulphur Oxides Testo 350 XL Gas ppm Analyser Carbon Monoxides Testo 350 XL Gas ppm Analyser VOC/HC Testo 350 XL Gas ppm Analyser NOISE Sound level Tecman Sound Meter dB(A) SOIL Sampling Stainless steel auger pH Hannah pH meter Electrical conductivity Hannah conductivity µS/cm meter. Soil Texture Particle Size Matrix Heavy metals Digestion/AA mg/kg Spectrophotometry Total Hydrocarbon Extraction / IR mg/kg Content Spectrophotometry Vegetation Quadrant, Binoculars SURFACE/GROUNDWATE surface water sampler R & ISCO Borehole Sampler o Temperature Eco Testr C pH/temperature Meter pH Eco Testr pH meter Total, Dissolved and ExTech mg/l ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 222 Suspended Solid Conductivity/TDS Meter Total Alkalinity HACH Digital Titration mg/l method Dissolved Oxygen ExTech DO Meter mg/l Biological oxygen Demand Winkler method mg/l (BOD5) Total Hydrocarbon Extraction / mg/l Content (THC) Spectrophotometer Conductivity Ex Tech Conductivity Meter. Heavy metals Flame Atomic mg/l Absorption Spectrophotometry SEDIMENTS Sampling Ekman Grab MICROBIOLOGY Total heterotrophic Composite samples for bacteria, fungi, laboratory analysis hydrocarbon Utilizing bacteria and fungi, total and faecal coliforms. WILDLIFE Conservation status (rare, In situ observation, threatened and interviews, secondary endangered species), data conservation areas (forest reserves etc.), environmentally sensitive areas – wetlands and swamps), local conservation practices. GEOLOGY Profile, type and In situ observation, composition drilling, laboratory analysis, reporting SOCIO-ECONOMIC Social Infrastructure Key informant STUDIES Cultural Properties, interviews, Focus Natural Resources and Group Discussion Land Use, Perception of (FGD), direct the project, The role of observation, women and children, Administration of Physically Challenged, structured Social Structure and questionnaires and Organization, Vehicular Collection of ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 223 Traffic Analysis, Sex Trade secondary data. HEALTH STUDIES Demographic profile of Key informant the Communities, interviews, FGD, Morbidity/Mortality Administration of Patterns, Healthcare structured facilities, Nutritional questionnaire and Status of Under-fives and interviews, Walk- the general population, through survey and Maternal and Child Collection of Health, Knowledge, secondary data. Attitude Practice and Behaviour (KAPB), Environmental health factors, A.7 Socio-Economic Aspects A.7.1Research Design The research design entailed determining the study population, i.e. the population of the communities that are regarded as the host communities of the project. It also involved making decisions as to:  Whether to obtain information at one or several points in time  The methods of data collection; and  Whether questionnaires, if used, should be self-administered, or administered face-to-face, using trained interviewers. In effect, this study belongs to the class described as “passive-observational” (Cook and Campbell, 1979), in the sense that subjects have been studied in situ, without any form of experimental manipulation. A one-shot study, such as this, can provide important and comprehensive information. A.7.2Target Populations and Samples A sample size of 5% of the total population of the study communities based on the 1991 national census figures was used in the study. These figures have been adjusted to 2015 using a projection of an annual growth rate of 3.4%. All the inhabitants in the selected houses were then administered questionnaires until the required sample size was met. A sample of the questionnaire is attached. Instrumentation and Data Collection This study employed both primary and secondary data sources. The latter comprised government ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 224 records, maps, and information published in journals and books, while the former included pre- coded questionnaires, key informants, focus groups, direct observation, direct measurement, specially prepared data collection formats, and participatory research. Although the questionnaires largely contained closed-ended questions for easy recording of responses, some open-ended ones were included to allow respondents freedom in structuring their responses. This permitted the researchers to obtain clearer insights into questionnaire items. Trained interviewers administered questionnaires face-to-face to respondents. Furthermore, trained assistants, using specially designed formats, carried out direct observation. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 225 Environmental and Social Impact Assessment (ESIA) for the Proposed 330/132kv and 132/33kv Transmission Substation Social Impact Assessment Questionnaire Instruction: Please answer the following questions to the best of your knowledge. Tick or fill in as appropriate. LOCATION 1. Name of Settlement (or Village):……................................................................. 2. Local Government Area: ……………………………………………………………. PERSONAL/DEMOGRAPHIC PROFILE 3. How old are you? …………………………………… (a) 18 - (b) 25 - (c) 30 - (d) 35- (e) 40 -45 (f) > 25 30 35 40 40 4. Sex of respondent (please tick) (a) Male (b) Female 5. Marital Status (please tick) (a) Married (b) Single (c) Divorced (d) Widow (e) Never (f) other married 6. Respondent’s position in household (please tick) (a) Head (b) Spouse to (c) Son/daughter (d) Other Head relations 7. Please state the number of persons in your household (including yourself) who fall into the following categories. Age cohorts Gender (years) Male Female Total 0–4 5–9 10 – 14 15 – 19 20 – 24 25 – 29 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 226 30 – 34 35 – 39 40 – 44 45 – 49 50 – 54 55 – 59 60 – 64 65 and over ECONOMIC ACTIVITIES, EMPLOYMENT AND INCOME (8) What is your primary occupation/employment status (please specify the sector) ( Public ( Company (c Self ( Not a (govt) b ) employed d employed ) ) ) (9) If you are self employed, please tell us what your occupation is: (a) Fishing (b) Farming (c) Hunting (d) Trading (e) Business (f) othe (10) If you are unemployed, please state what you do for a living…………………………… (11) Kindly tick the range of your income in a month: A Less than N10,000 g N 60,000 – N 69,999 B N10,000 – N 19,999 h N 70,000 – N 79,999 C N 20,000 – N 29,999 I N 80,000 – N 89,999 D N30,000 – N 39,999 J N 90,000 – N 99,999 E N 40,000 – N 49,999 K N 100,000 or more F N 50,000 – N 49,999 SOCIAL ENVIRONMENT 12. Are (a) Christian (b) Muslim (c) Pagan (e) Free you thinker 13. Name the cultural activities/festivals that your people observe (a) …………………….. (b) …………………………… (c ) …………………….. (d) …………………………… 14. Educational status of respondent: (please tick/underline) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 227 (a) No formal Education (b) Primary (c) Secondary (d) Post-Secondary 15. How many of the following exist in your settlement (village)? (a) Nursery Schools ………………….. (b) Primary Schools ………………... (c) Secondary Schools ……………….. (d) Post Secondary Schools ………. UTILITIES/INFRASTRUCTURE 16. From which of these sources do you obtain your water supply? (a) Rain (b) River (c) Borehole (d) Well (e) Stored (f) Pipe runoff borne 17. How do you dispose your wastes (solid/domestic and farm wastes)? (a) Burning (b) Burying (c) Dumping (d) Throwing into running water 18. How is human waste (excreta) disposed of? simple pit latrines (e) Open public sewer (a) (b) into water channels (f) VIP (ventilated) latrine (c) surrounding bushes (g) Other means (specify) ………………. (d) pail system 19. Is your community is connected to any public power (electricity) supply system who installed it? ETHNIC RELATIONS 20. Which of these projects have been initiated and / or completed in your community? (a) Roads/bridges (e) Electricity (h) scholarship (b) Health centre (f) Water (i) Micro-credit facility Supply (C) Market stalls (g) School (j) Other blocks (specify)……………… ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 228 21. Specify which of the following Organizations provided the above facilities (a) Federal govt. (c) Local govt. (b) State govt. (d) Other (specify). PERCEPTION OF TCN OPERATIONS 22. Rate between 1 – 10 what you consider the most beneficial aspects of Transmission Substation presence in your locality Increased employment Others (Specify)…………………… Improved Electricity Taxes to government HEALTH IMPACT ASSESSMENT QUESTIONNAIRE (A) Socio-Demographic Variables (1) Name of Town / Village…………………………………………………………………… (2) Age (Last Birthday)……………………………………………………………………… (3) Sex: (a) Male (b) Female (4) What is your marital status? Single Married Divorced Separated Widow/Widower Reproductive Health Data: (A) Anthropometric measurements a. Weight: ………………………………….. kg b. Height: ……………………………………cm c. Body Mass Index: ………………………… d. Mid Upper Arm Circumference…………… cm e. Skin fold thickness: ………………………... cm f. Waist circumference: ………………………. cm g. Waist- Height Ratio: ………………………… (B) Life Style/ Habits ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 229 (1) Do you drink alcohol? Yes No (2) If yes, How often o Every day o At least once a week o Occasional (3) Do you smoke? Yes / No If yes, how many sticks/day …………. (4) Exercise: Yes / No What type of exercise do you do? ……………………………………………… Knowledge, Attitudes, Practices and Behaviour on Sexually Transmissible Infections 1. Do you have sexual partners not married to you? Yes No 2. How many are they?____________________________________ 3. Have you heard of sexually Transmissible Infections before? Yes No 4. Have you ever had any sexually Transmissible Infections? Yes No 5. What symptoms (complaints) did you have then _____________________ _____________________________________________________________ 6. Were you treated by a doctor, a nurse or by yourself?  Treated by a doctor Yes No  By nurse Yes No  By self Yes No 7. How many times have you had STIs before? _________________________ 8. Have you heard of HIV/AIDS before? Yes No 9. Do you know how HIV/AIDS can infect somebody? Yes No 10. Name the method by which somebody can get HIV/AIDS _____________________________________________________________ 11. Have you checked your HIV status? Yes No 12. Do you know anybody who has HIV/AIDS? Yes No 13. How many do you? _____________________________ 14. Has any member of your family, friend or community had or having tuberculosis? Yes No Health Seeking Behaviour Data 1. Indicate types/number of health care institutions in your community? ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 230 Types Total Total Number Total Total Numbe of Midwives / Number Number of r Nurses of Medical Doctors Staff (i) Hospital (ii) Maternity (iii) Dispensary (iv) Health Center (v) Private Clinic (vi) Patent Medicine Store (vii) Pharmacy (Chemist) (viii)Traditional Healing Homes 2. What treatment did/do you employ when sick? i) Attended hospital/clinic ii) Buys drugs from nearby chemist iii) Consult native doctors iv) Self medication 3. Where did/you go for child delivery (ies)? (ii) Attend hospital/health centre …. (iii) Maternity/private clinic ………. (iv) At home alone ………………… (v) Native Doctor/traditional midwife (vi) Any other (specify) …………… Environmental Health Data: 1. What is the major source of water available to your household? (tick the correct option) (i) River/Stream (ii) Well (iii) Pond (iv) Rain Water (v) Public pipe-borne water (vi) Mono pump (vii) Borehole (Commercial) (viii) Borehole (private) (ix) Commercial tanker 2. What type(s) of residential houses do you have in your community? (Tick the correct option) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 231 Types of Houses (by Nature of construction Materials) Total Number (i) Wood (Batcher) (ii) Mud (iii) Corrugated iron sheets (zinc batcher) (iv) Cellophane (nylon) (v) Thatch (vi) Block (cement or brick) (vii) Others (Specify) 3. How many persons live in a house?___________________________ 5. What type of toilet facility do you use? Please tick from below. (1) Pit (2) Bush (3) Prier head (4) Bucket (5) Water closet (6) Others (specify)_______________________________________ 6. How do you dispose of your household refuse? Please tick from the list below. i) Private open dump ii) Public open dump iii) Organized collection (by Local Government, Community etc) iv) Organized collection *by Individual – Commercial) v) Burning vi) Bush vii) Burying viii) River/Stream ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 232 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 233 17.3 Annex 3 Secondary Data Environmental and Social Impact Assessment (ESIA) for the Proposed 330/132kv and 132/33kv Transmission Substations at New Kano in Kano State, Biliri in Gombe State, Kabba in Kogi State and Abor (9th Mile) in Enugu State SOURCE INFORMATION Nigerian Meteorological Agency (NIMET) Historical Rainfall, Relative Humidity, Ambient Temperature, Atmospheric Pressure data Nigerian Hydrological Services Agency (NIHSA) Geological Maps and Basement complex information National Population Commission (NPC) 1991 and 2006 Census Figures Kogi State Government Strategic Health Development Plan (2010-2015) by Kogi State Ministry of Health March 2010 Health Infrastructure in Kabba/Bonu Local Government Area Environmental Impact Assessment (EIA) of the Ajaokuta – Obajana Gas Pipeline Project Kogi State February 2004 by Dangote Group Infrastructural status of kabba/Bonu, settlement Pattern National Bureau of Statistics Abuja Nigerian Socio Economic data, Job creation survey, Labour, Povery and Consumption, Millenium Development Goals, Health, ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 234 Population, Macro Economic data, Governance, Maps Environmental Impact Assessment of the Proposed Calabar-Umuahia-Ajaokuta Gas Pipeline July 2015 by Federal Ministry Of Petroleum Resources Legal and Administrative Framework of States Preliminary Environmental Impact Assessment of the Proposed 500km Benin – Soil data Onitsha- Aba & Onitsha-Abakaliki Lot 2 (A & B) Standard Gauge Railway Line Project August, 2013 for the Federal Republic of Nigeria Ministry of Transport / Nigerian Railway Authority / Technics Engineering Architecture Marketing (Nig) Ltd Environmental Impact Assessment of Proposed 350 MW Gas Turbine Power NA Project Geregu, Kogi State July 2013 by Yellowstone Electric Power Limited Environmental Impact Assessment of the Proposed Transceiver Station (BTS) Project in Enugu State December 2014 by Airtel Networks NA Environmental Impact Assessment (EIA) Study of the Proposed Etisalat Base Geotechnical and soil data Stations In 10 Local Government Areas Of Enugu State, Nigeria November, 2012 by Emerging Market Telecommunication Services Limited (Etisalat Nigeria) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 235 Environmental Impact Assessment of EMTS Base Stations in Gombe State November 2012 by Emerging Market Telecommunication Services Limited Socio Economic and Soil data (Etisalat Nigeria) Geotechnical and soil data Environmental Impact Assessment of Etisalat Base Stations in Kano State November 2012 by by Emerging Market Telecommunication Services Limited (Etisalat Nigeria) Meteorological and Health information Environmental Impact Assessment (EIA) Study of the proposed Etisalat Base Stations in Seven (7) Local Government Areas of Kogi State, Nigeria N0vember 2012 by by Emerging Market Telecommunication Services Limited (Etisalat Nigeria) NA Environmental Impact Assessment of proposed Geregu 434MW Power Plant Phase II Project Ajaokuta Local Government Area, Kogi State June 2014 by Niger Delta Power Holding Company Limited Meteorological, Flora and Fauna data Environmental And Social Impact Assessment (ESIA) for Gombe-Biu Road Rehabilitation Project 2006 by Prime Consult Limited Energy supply and Conservation in Kano state Environmental Liabilities Audit Report of Power Holding Company of Nigeria (PHCN) Successor Companies (Kano Electricity Distribution Company (KEDCO)) November 2014 by Bureau for Public Enterprises (BPE) / EcoConServ Environmental Solutions Egypt & Metaspec Consult Limited Nigeria ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 236 Energy Supply and Conservation in Kabba/Buno LGA Environmental Liabilities Audit Report of Power Holding Company of Nigeria (PHCN) Successor Companies (Abuja Electricity Distribution Company (AEDC)) November 2014 by Bureau for Public Enterprises (BPE) / EcoConServ Environmental Solutions Egypt & Metaspec Consult Limited Nigeria Energy Supply and Conservation in Gombe state Environmental Liabilities Audit Report of Power Holding Company of Nigeria (PHCN) Successor Companies (Jos Electricity Distribution Company (JEDC)) November 2014 by Bureau for Public Enterprises (BPE) / EcoConServ Environmental Solutions Egypt & Metaspec Consult Limited Nigeria Energy Supply and Conservation in Enugu state Environmental Liabilities Audit Report of Power Holding Company of Nigeria (PHCN) Successor Companies (Enugu Electricity Distribution Company (EEDC)) November 2014 by Bureau for Public Enterprises (BPE) / EcoConServ Environmental Solutions Egypt & Metaspec Consult Limited Nigeria Energy Supply and Conservation of Transmission substations Environmental Liabilities Audit Report of Power Holding Company of Nigeria Project Description (PHCN) Successor Companies (Transmission Company of Nigeria (TCN)) November 2014 by Bureau for Public Enterprises (BPE) / EcoConServ Environmental Solutions Egypt & Metaspec Consult Limited Nigeria Physical Setting, People, Population, settlement Pattern, Education, Nigeria A People United, A Future Assured Volume 2, Survey of States. Millennium Health Services, water supply, Transport and Communication, Natural resources, Geology, Relief, Location, Ethnic composition, Edition May 2000 by A.B. Mamman, J. O. Oyebanji, S. W. Petters. Languages, Ecological problems ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 237 Socio Economic data of 9th Mile and settlement Pattern Environmental and Social Management Plan (ESMP) for 9th Mile Corner Gully Erosion Intervention Site in Udi LGA, Enugu State June, 2014 under the Nigeria Erosion & Watershed Management Project (Newmap) World Bank Assisted by Enugu State-Nigeria Erosion & Watershed Management Project (Enugu-Newmap) Nigerian Hydrological, flood plain and wetland data, Maps Anambra-Imo River Basin Development Authority Hadejia-Jama’are River Basin Development Authority Niger River Basin Development Authority Upper Benue River Basin Development Authority Weather Network International (WNI) Nigeria Meteorological data The History and Culture of ABOR by Festus Madukaligwe Okolo Abor Cultural History University of Calabar Herbarium, Botany Department, Faculty of Sciences, University of Calabar, Calabar Cross River State Vegetative Specie identification data Nigerian Institute of Social and Economic Research (NISER) Socio Economic data of Nigerian communities Forestry Research Institute of Nigeria (FRIN) Regional forest belts of Nigeria ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 238 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 239 17.4 Annex 4 Public Consultation Kabba COMMUNITY STAKEHOLDER’S FORUM FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) FOR THE PROPOSED CONSTRUCTION OF 330/132KV and 132/33KV TRANSMISSION SUB-STATION AT KABBA N.B. Due to the private nature of the names and phone numbers of attendees, at the request of WB this information has been withheld, but is available on record with TCN. The community Stakeholder’s forum for the Environmental and Social Impact Assessment (ESIA) for the proposed construction of 330/132KV and 132/33KV Transmission Sub-Station. Venue: St. Augustine College Hall, Kabba, Kogi State. Date: Thursday 15th October 2015. The Opening Prayer was led by a community member Welcome Address was by SSA1/Acting Chairman Kabba/Bunu LGA). He and his people are excited by the presence of the World Bank/ SMEC/ PHCN team to Kabba and believe the visit will be the last prior to the start of the project. Welcome address was by the AGM (T) who represented the GM(T) Benin as he had to be in Enugu because four world bank stakeholder’s forum are being held simultaneously in different locations Billiri (Gombe), Abor (Enugu), New Kano (Kano) and Kabba (Kogi). He said the project will be a source of empowerment and good livelihood to the people. Goodwill messages: Good will messages were received from the participants during the meeting. It was clear that influential stakeholders were very optimistic about the project and expressed commitment to ensuring that the project is successful. In the areas of security, labour demand and materials utilisation, the stakeholders agreed on ensuring support to World Bank. Among the stakeholders that expressed satisfaction during the meeting included the following: - Education Secretary (Kabba/Bunu LGEA) - President, Kabba Development Union (KDU). - Women Leader (KDU): Electricity will boost their yield and economic lives of the women as they assist their husband in their different endeavours as Seamstress, Hairdresser, etc. Participated Stakeholders: Available information extracted from the attendance sheet shows that the following people attended the meeting. i. Caretaker Chairman of Kabba/Bunu LGA ii. Cross section of traditional rulers from Kabba/Bunu iii. Commissioner of Land (Rep) iv. Word Bank Rep. v. Federal Ministry of Environment(Rep) vi. Regional Mangers of Transmission Company of Nigeria vii. President of Women Association and their members viii. Uniform organisation-Civil Defence, Nigeria Police etc. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 240 ix. Students from secondary schools. x. Project Management Unit (Rep) xi. Development Associations xii. Youths and town Unions xiii. President of Physically challenged persons xiv. Traders Associations xv. SMEC Consultants Overview of ESIA was by representative from TCN-PMU. He appreciated the acting Chairman for dedication and relentless effort to the project. He noted that the project was a Win-Win project, the community will win by constant power and the business unit of Abuja Electricity Distribution Company (AEDC) will also make more money. He appreciated the Royal majesty (The Obaro of Kabba) for his magnanimity of donating his family land to this project. Also, Kogi state Government for paying for the survey which was more than One million naira. Presentation by the Socioeconomist from SMEC PTY Int’l Ltd The presentation by SMEC PTY International was centred the following i. The synergy and interface of federal government of Nigeria and World Bank power substation projects in 4 states. ii. Roles and responsibility of PMU iii. Compliance on environmental laws and regulations in Nigeria iv. Stakeholders consultative meetings v. The objectives of the project which include: • Improve transmission and distribution of electricity to Kogi State and neighbouring States; • Stimulate socio-economic activities; • Improve socio-economic circumstances by providing a readily available electricity supply; • Increase revenue base for TCN and identify requirements for responsible public engagement; and • Create new job opportunities. Community Participation in World Bank projects was by Mrs Afolabi Fausat (FMEnv). She said community participation is very important and it is used as indices to ascertain if the host community are in support of the project. QUESTION AND ANSWERS S/ Name Question Answer N 1 KDU President When is the project starting and The project will its duration. commence as soon as the ESIA is completed 2 Honourable When and how will Appropriate ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 241 Menmber compensation for farmland compensation will be (SSA1/Acting around the project will done made at the right time. Chairman Kabba/Bunu LGA 3 A participant What are the likely hazards Some of the hazards are associated with the project. ditches and itinerant staffs. The construction company will put measures in place to abate them. Also, there is a safety team component in this project. 4 A participant What is the commitment There are towards employment of skilled/unskilled labour, indigenes? more than 90% of the unskilled labour will be localised. 5 A participant What is in place for quality There will be a project delivery for the project? supervising consultant, and also the Project management Unit (PMU) of the Transmission Company of Nigeria (TCN) 6 A participant After the project completion, The project is being will it be handed over to PHCN? handled by TCN. It will also be operated and Who is responsible for the maintained by TCN. project? AEDC is in charge of Will the community be using distribution and will prepaid meter after the project? provide prepaid meter as soon as it is available. 7 A participant SSA3 What is the compensation in There is a project of the place for the farmland that the world Bank called NEPTA transmission line will pass phase 2. It takes farmland through? that the line will pass through. World Bank will adequately compensate base on the Federal Government guideline. All Economic trees will be enumerated. Farm Owners will get a consultant that World bank will pay for the enumeration. 8 Commissioner of What is the plan for the The land was donated by land Economic trees on the project the Obaro of Kabba and representative site? more so there are no ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 242 economic trees on the project site. 9 Community The community people receives Please lodge your member no proof of bill deduction if after complain to AEDC and they have paid their bills keeping your bills. 10 Obarowe of Owe What is the model of the The transmission is land transmission is it hydro, coal or through power lines. wind? TCN transmits voltage and What is the amperage? not current. Vote of Thanks was by TCN Staff He said maximum cooperation and input is needed from the people of Kabba. He thanked the people on behalf of PMU, GM (PMU) and the Worldbank. Closing Prayer was offered by a community member. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 243 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 244 17.5 Annex 5 Measuring Transformer Noise IEC 60076 How to Measure Transformer Noise Using a Sound Level Meter (SLM) In accordance with International Standard IEC 60076-10, Power transformers Part 10: Determination of sound levels, First edition 2001-05. Figure 17-1 Typical Transformer Figure 17-2 Typical description of transformer ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 245 Figure 17-3 Measuring Positions for one transformer Procedure 1. Take Photo of transformer (as in Figure 19-25) 2. Get details of transformer (as in Figure 19-26). Make sure to get the 4 letter series at the end of the description. 3. Measure length and width of transformer 4. Estimate height 5. Make a sketch 6. Take measurements at 3 distances away from transformer : 0.3 meters ; 2 metres; 5 metres for all 4 sides 7. If access is restricted take measurements just on longest side. Stand in middle of longest side and walk away to 0.3 meters ; 2 metres; 5 metres 8. Take measurements with microphone vertical or horizontal pointing towards the wall of the transformer 9. Ask if the transformer is operating at FULL LOAD or NO LOAD. Write this down 10. Take a steady Sound Pressure Level Reading (not Leq) 11. Use dB(A weighting filter) 12. Record reading ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 246 13. Walk away until you cannot hear the tranformer. Measure the ambient in Leq dB(A) for 5 minutes. 14. Note ambient noise level, weather conditions, dry sunny raining, windy, time of day and date. 15. Make sure to calibrate SLM before and after measurements and note any drift. USE A WINDSHIELD. 16. If there are several transformers treat them as one group. Count the number. Take measurements at 5, 10 and 20 meters from the 4 sides of the group. (see Figure 19-28) Figure 17-4 Measuring positions for group of transformers ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 247 17.6 Annex 6 GENERIC SAMPLE OF C-ESMP The following information must be given : 1. Contractors Name and Address : 2. Company Secretary Name and Address : 3. Contract Name : 4. Duration : 5. Value : 6. Project Manager - Name and Contact number and email : 7. Project Director - Name and Contact number and email : 8. Complaints Officer, Name and Contact number and email : 9. Environment Health and Safety Officer (EHSO) - Name and Contact number and email : 10. Emergency contact number 24/7 : NOTE. The civil works contractors must implement adequate precautions to protect the environment, the amenity of the area and not to disturb local residents. He must also protect the health and safety of construction workers. The occupational health and safety risks will be minimized by providing adequate personal protective equipment (PPE) and ensuring workers wear it. The contractors will undertake the following activities:  An Environment Health and Safety Officer (EHSO) will be appointed and will prepare an Environment Health and Safety Management Plan, will implement the EHSMP and ensure that the requirements of the EHSMP are met.  The EHSO will ensure that the EHSMP is submitted to TCN prior to construction for approval, that accurate records and reports of any occupational health and safety incidents are kept, and review the distribution and use of appropriate PPE.  The EHSO will also encourage awareness building on safety through activities such as “Toolbox Briefings” and reporting “Near Misses.”  The contractor will establish a procedure for response to complaint which operates 24/7. The CESMP given below must be completed with site specific details and submitted to TCN within 30 days of contract signing. All matters are contractually binding. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 248 17.7 Annex 7 EXAMPLE OF C-ESMP . .48 CHINA HARBOUR ENGINEERING COMPANY LIMITED CONTRACTORS ENVIRONMENTAL MANAGEMENT PLAN (LAE PORT DEVELOPMENT PROJECT – TIDAL BASIN PHASE 1) August 2012 (Revision2) CHIINA HARBOUR ENGINEERING COMPANY Ltd C-/NEW VISION CONSULTING LEVEL 3 ADF HAUS MUSGRAVE ST P. O. BOX ____PORT MORESBY NATIONAL CAPITAL DISTRICT PAPUA NEW GUINEA CHINA HARBOUR ENGINEERING COMPANY LIMITED 48 With Permission of the author ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 249 CONTRACT NO. 1879 Document No. LAE PORT DEVELOPMENT PROJECT – CEMP-01 TIDAL BASIN PHASE I Revision 2 Contractors Environmental Management Plan Document No. CHEC/LPDP/EN/CEMP-01 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 250 ENGINEER & CONTRACTOR DOCUMENTATION REVIEW: □ STATUS 1 Approved as submitted Approved subject to implementation of Engineer’s and/or Employer’s comments □ STATUS 2 / notation without re-submission Rejected and being subject to full re-submission in response to the Engineer’s □ STATUS 3 and/or Employer’s comments / notation NOTE: Consent by the Employer shall not relieve the Contractor of any duty and responsibility under the Contract. For review and approval Rev. Date Prepared By: Reviewed By: Approved By: 0 Status 15/5/2 Danny Wame Wu Guansheng Ma Jianhua 012 ES&H Manager Deputy project Project Manager Manager For review and approval Date 10/7/2 Status Prepared By: Reviewed By: Approved By: 012 Rev. Danny Wame Wu Guansheng Ma Jianhua 1 ES&H Manager Deputy project Project Manager Manager For review and approval Date 14/8/2 Status Prepared By: Reviewed By: Approved By: 012 Rev. Zhengang Shi Wu Guansheng Ma Jianhua 2 Deputy ES&H Deputy project Project Manager Manager Manager ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 251 CONTENTS Section Page i. FORWARD BY THE PROJECT MANAGER 4 ii. CHEC ENVIRONMENTAL POLICY STATEMENT 5 iii. CHEC ENVIRONMENTAL COMMITMENT 5 1.0 INTRODUCTION 6 2.0 DEFINITION 6 3.0 PROJECT BACKGROUND 7 4.0 PURPOSE 7 5.0 OBJECTIVES & TARGET 7 6.0 ENVIRONMENTAL LAWS, POLICIES & STANDARDS 8 7.0 ENVIRONMENTAL MANAGEMENT STRUCTURE 8 8.0 RESPONSIBILITIES 8 9.0 MPLEMENATION AND MONITORING 11 9.1 Monitoring programme 12 9.2 Preliminary Survey and Resources 12 9.3 Environmental Inspection and Audit 12 9.4 Monitoring and Reporting 13 9.5 Job Hazard 13 9.6 Emergency Preparedness and Response 13 9.7 Performance Monitoring 14 10.0 ENVIRONMENTAL MANAGEMENT AND MITIGATION MEASURES 14 11.0 COMPLAINT MANAGEMENT 14 12.0 ENVIRONMENTAL TRAINING 14 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 252 13.0 ENVIRONMENTAL REPORTING 15 14.0 MANAGEMENT REVIEW 16 15.0 SITE SPECIFIC ENVIRONMENTAL MANAGEMENT PARAMETERS 16 15.1 Noise and Vibration 16 15.2 Air Quality 17 15.3 Water Quality 17 15.4 Affect to Ecology Fisheries 17 15.5 Solid Waste Pollution 18 15.6 Sewage Waste 18 15.7 Oil Spillage & Leakage 18 15.8 Littering 19 15.9 Vegetation Clearance 19 15.10 Visual Impact 19 15.11 Erosion & Sedimentation 19 15.12 Socio-economic Issue 19 15.13 Archaeological & Cultural Heritage 20 16.0 ENVIRONMENTAL MANAGEMENT PLAN 20 17.0 REFERENCES 37 18.0 APPENDICES 37 ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 253 FOREWORD BY THE PROJECT MANAGER: China Harbour Engineering Company Limited (CHEC) has prepared this Contractors Environmental Management Plan (CEMP) as a practical guide for employees & sub-contractors for the proposed Lae Port Development Project-Tidal Basin Phase 1. The document is designed to be a reference point for regulatory authority, external and internal audits and general stakeholder interests in environmental practices. The overall custodian of this CEMP is the Project Manager. “Ownership” of the plan, rests with sectional heads, employees, & sub-contractors. Sectional heads will continuously remind employees of the need to follow the dictates of the CEMP and will carry out checks to enforce environmental controls. Employees are expected to take ownership by adopting and implementing the plan in order to continually maintain and improve environmental performance. They will attend induction sessions, refresher training sessions and have daily reminders on specific topics during daily tool box briefings. Incentives may be offered to staff who demonstrate environmental awareness. The environmental requirements detailed in the CEMP will be included in sub-contracts. Sub- Contractors will be required to implement the CEMP as a contractual obligation and this will be monitored by site supervisory staff. The document is a living “organism”. All requests for modification to this document should be submitted to the Deputy Project Manager through Environment, Safety & Health Office. Suggestions would be reviewed and incorporated where necessary. Together we can create a healthier and safer workplace and protect our environment and assets from harming and ensures continues improvements in our environmental practices. Mr. Ma Jianhua Project Manager ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 254 CHEC ENVIRONMENTAL POLICY STATEMENT: A Project Environmental Management Policy is established to demonstrate the Project Team’s commitment in improving our environmental performance. It aims to communicate CHEC’s mission, vision and beliefs towards the environment to the staff and provides a framework for guiding CHEC’s ongoing environmental improvement efforts. The policy will be reviewed periodically by relevant parties and will be displayed on notice boards in languages suitable for the local workforce. CHEC will modify the CEMP as needed relevant to actual construction work. As a contractor, the Environmental Policy (See Appendix A) will be implemented and maintained by the project team, until the completion of the project. CHEC is certified to ISO Standard 14001 - Environmental Management System (See Appendix B). Thus, the project team will continue to implement and maintain these systems for the Lae Port Development Project Tidal Basin Phase I to prevent accidents and minimize adverse environmental impacts from the project. CHEC ENVIRONMENTAL COMMITMENT The contractor will comply with all PNG environmental legislation, regulations and PNG government policies and procedures. In addition it will comply with the ADB’s Safeguard Policy Statement 2009. China Harbour Engineering Company (CHEC) is internationally recognised as having a reputation for safeguarding the environment and has achieved certification to ISO Standard 14001-Environmental Management System (EMS). CHEC acknowledge that it is essential to maintain the annual renewal of this ISO certification and they ensure construction works comply with environmental standards. The steps needed to meet these standards are included in regular staff training plans. Activities during construction will be constantly monitored on a daily basis to ensure compliance. As part of the continual improvement program, this plan will be reviewed at least once a month, and if necessary amended after discussions with the Supervisory Consultants. It may be amended and updated at any time at the discretion of the Project Management and will be formally reviewed once a year for the life of the project. At completion of the project a Project Completion Report will be submitted confirming that all necessary environmental clean-up measures have been completed. The basis for amendments, improvements and updates will be environmental inspections, audits and reviews of the contractor’s environmental performance. This will ensure procedures for control of contractors are sufficient to maintain project environmental standards, meet project environmental targets and comply with environmental legislation and regulations relevant to the project. 1.0: INTRODUCTION: This Contractors Environmental Management Plan (CEMP) covers the Construction Phases of Lae Port Development Project – Tidal Basin Phase 1. The plan is developed following the findings of the Environmental Impact Assessment (EIA) undertaken by Haskoning Nederland BV in association with Ports & Maritime Consultancy Ltd. Port Moresby, in year 2007. In the EIA, both bio-physical & socio- ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 255 economic impacts of the project have been identified and mitigation measures recommended. It also follows the requirements and recommendations of the Initial Environmental Examination (IEE) of “PNG: Lae Port Development Project – Additional Works” October 2011, prepared by Independent Public Business Corporation for the Asian Development Bank. China Harbour Engineering Company (CHEC) is an internationally recognised company and maintains its reputation in safeguarding the environment by meeting regulatory requirements in the country of operation and adopting a “Best Environmental Code of Practice” which is based on CHEC’s certification to ISO Standard 14001-Environmental Management System (EMS). Thus all construction works will comply with acceptable relevant environmental standards and the steps needed to meet these are included in staff training plans. 2.0: DEFINITION: Terms Definitions Environment Surroundings and conditions in which CHEC’s construction works operates or which it may affect including living systems (human and others) therein. Environment Policy A unique document that shows who does what and when and how to do it. Environment policy does influences all business activities including the selection of people, equipment and materials, the way work is done and how it is designed to provide goods and services. The policy is in compliance with PNG environmental protection laws and ADB’s Safeguard Policy Statement. Hazard Any situation with the potential to cause danger to environment, cause injury or illness to people Accident Any event which result in damage or loss to environment Incident An event which has caused or could have caused damage or loss to environment or injury to personnel on site Near-miss Any event which has the potential to cause damage or loss to environment but avoided by circumstances Risk The potential for a hazard to result in an incident Risk Assessment A careful consideration by competent people of the hazard associated with a task. The potential effect of each hazard, how severe it might be and the likelihood of it occurring Risk Management A management system which eliminates or mitigate the threat from hazard Environmental The company structure, responsibilities practices, procedure process and Management resources for implementing environmental management System Environmental An independent systematic & documented process of assessing compliance Audit of an Environmental program with legislation Contractors A description of the means of achieving environmental objectives during the Environmental construction phase in compliance with the EIA and IEE prepared for the Management Plan project. 3.0: PROJECT BACKGROUND: Due to the archipelagic nature of Papua New Guinea (PNG) and rugged terrain, which creates widely dispersed population pockets and limits mobility and opportunities to develop the domestic market, the country heavily relies on trade, particularly exports, for economic growth and fiscal revenue. The port ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 256 sector provides a vital link between PNG and the world market, with more than 80% of PNG exports shipped from ports. The city of Lae, located in Morobe province, is PNG’s industrial and commercial trade centre. Lae port, the largest port of Papua New Guinea, is centrally located in the country and is on most Pacific shipping routes. It is situated on the coast of the Markham Bay at the north-western corner of the Huon Gulf, approximately 1.5 km east of the mouth of the Markham River. Over the past decade Lae port has been adapting to the demands of container operations. However, the current five berths of Lae port, with a total length of about 520m and a total storage area of 52,600 m2 for cargo marshalling, are aging and insufficient to handle increasing cargo volumes and ship size. As early as the 1970s a plan to expand port capacity by developing a tidal basin project in the marshland area located to the west of the existing port facilities was formulated. The project did not proceed due to a dispute relating to land ownership. During the following two decades decreased economic growth discouraged not only investment in the tidal basin project, but also adequate maintenance of the existing port facilities. Improved economic performance and steady increase of the cargo throughput at Lae port since 2003 have generated revenues for the Government and PNG Ports Corporation Limited. 4.0: PURPOSE: The purpose of this CEMP is to;  Comply with the requirement of PNG Environment Act 2000  Practically apply CHEC’s Environmental Policy  Comply with EMS (ISO 14001) Requirements  Address potential environmental issues pro-actively and systematically in a timely manner  Ensure compliance with PNG’s environmental protection laws and ADB’s Safeguard Policy Statement and agreements between Government and Contractor 5.0: OBJECTIVES & TARGET: Project environmental objective & target are as follows; No Objective Target 1 To comply with legal requirement Zero conviction 2 To ensure best environmental Zero non-compliance in environmental practice performance 6.0: ENVIRONMENTAL LAWS, POLICIES & STANDARDS:  PNG Environmental Act 2000  CHEC Environmental Policy  Environmental Management System  ADB’s Social Safeguard Policy Statement 2009  Standards to be adopted for discharges will be in accordance with the PNG Department of Environment and Conservation Permits for Noise, Air, Water and Land Discharges as issued after Minister’s Approval in Principle is given, which has been obtained  Standards for Mitigation and Monitoring will be as stipulated in the IEE 2011 to include parameters, locations, timing and frequency. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 257 7.0: ENVIRONMENTAL MANAGEMENT STRUCTURE: The ES&H management structure is shown below. The ES&H Manager is directly responsible and report to the Project Manager/ Project Director. ProjectDeputy Project Manager Deputy ProjectES&H Manager Manager Manager ES&ES&H Engineer H Manager ES&HSite Engineers/Assistant Engineers Engineer Site Engineers/Assistant Technical officers/Foreman/Supervi sors Technical officers/Foreman/SuApproved by IES(KECC) Engineers pervisors ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 258 8.0: RESPONSIBILITIES: Respective personnel within the environmental management structure are responsible and accountable for the implementation of this EMP. 8.1: Project Manager (PM); The Project Manager is responsible for providing support in dealing with all aspects of environmental issues within the project, and reporting to the CHEC Supervisory Board. 8.2: Deputy Project Manager (DPM); The responsibilities of the Deputy Project Manager are as follows: a) Ensure works are executed in accordance with the CEMP. b) Arrange routine joint site inspection with ES&H Manager and ES&H Engineer. c) Provide necessary guidance & supervision to ES&H Manager and ES&H Engineer in order to implement CEMP d) Monitor and control the works including those subcontractor(s) to ensure compliance with specified requirements. e) Ensure appropriate environmental protection and pollution control mitigation measures are properly implemented in accordance with the relevant procedures. f) Assist in handling any complaints received from the public. g) Ensure remedial action is undertaken immediately if there is a non-compliance of statutory or contractual requirements of the environment practices. h) Liaise with PMU and PMU’s IES as required 8.3: Environmental, Safety & Health (ES&H) Manager; ES&H Manager is responsible for; a) Providing advice to project management in respect of any environmental protection issues such as noise abatement, air & water pollution control, refuse disposal etc. b) Assuming environmental duty on site with the assistance of Environmental Engineer. Held responsible for any environmental issues arising due to construction activities and in relation to environmental practices adopted on site. c) Providing necessary guidance & supervision to ES&H engineer in order to implement environmental management plan & program d) Ensure works are executed in accordance with this CEMP. e) Liaise with relevant government department in obtaining required license, permit and test report. f) Arrange routine joint site inspection with ES&H engineer in consultation with Deputy Project Manager. g) Prepare, implement and update the Contractors Environmental Management Plan; h) Arrange and provide the environmental training including the site specific induction training and toolbox talks for the staff and workers on the Site, and to organize environmental promotional activities; i) Advise the company on the implementation of an environmental management system; i) Attend Site Safety and Environmental Management Committee (SSEMC) Meetings j) Liaise with PMU and PMU’s IES as required ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 259 k) Apply for environmental permits and ensure conditions stated therein are complied with during construction activities and site works l) Ensure that approved CEMP is available at the site office m) Ensure that the elements from the approved CEMP are translated into site inspection forms and monitoring forms. n) Ensure that the regularity of the site inspections are followed as per the daily and weekly inspection charts given in the Appendices C and D. 8.4: Environmental, Safety & Health (ES&H) Engineer; Duties and responsibilities of the ES&H Engineer are as follows; a) Provide engineering advice to project management in respect of any environmental protection issues such air & water pollution control, refuse disposal etc. b) Work in parallel with the design team and project management to ensure environmental issues are fully considered during the design and implementation stages. c) Advise on measures to be taken in the interest of environmental protection, and implement such measure; d) Liaise on all matters relating to environmental monitoring and auditing; e) Carry out inspections of the site for identifying potential hazards to the environmental, and to report findings with recommendations for corrective actions ; f) Participate in the environmental audit, and monitor the environmental performance on the Site; g) Check and ensure that any polluting or potentially polluting situation is promptly rectified as per ES&H Managers advice h) Attend Site Safety and Environmental Management Committee (SSEMC) Meetings i) Keep a copy of the following documents (including but not limited to):  Any statutory required environmental permits/licenses including construction noise permits, noise levels for compressors and hand held percussive breakers, effluent discharge licenses, dumping permits;  All correspondences with Department of Environment and Conservation. Central Environment Authority and complaints;  Records regarding the handling of contaminated wastes;  Records regarding the disposal of all construction and demolition materials to the specific or designated area.  Record of all trained personnel in the site offices and update the record. j) Update the monthly summary Waste Flow Table k) Report to the ES&H Manager regarding non-compliance of any environmental protection issues and ensure any non-compliance is handled l) Ensure complaints are handled properly m) Liaise with PMU and PMU’s IES as required n) Apply for environmental permits and ensure conditions stated therein are complied with during construction activities and site works o) Ensure that approved CEMP is available at the site office p) Ensure that the elements form the approved CEMP are translated into site inspection forms and monitoring forms q) Updating of CEMP based on changes in operating procedures or new issues brought to light. Proposed revisions to the CEMP will be tabled in the monthly progress meetings CHEC/KECC/IPBC.(See Figure 1 below) ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 260 r) Carry out site inspections in accordance with the monitoring plan and complete daily and weekly inspection charts as given in the appendices C,D. All findings will be reported including “Near Misses”, not just corrective actions. This relates to potential incidents that were avoided and no actions were required but these must still be reported, as lessons learned can be circulated Figure 1 CEMP Revision and Update Process Current CEMP Modified CEMP subject to supercedes periodAdvice earlier vCurrent CEMP subject to periodic review Information collection by HSE confirmMore Manager / information EngineUpdate or requested amend Informati on More Information informati Approvconfirmed inpuInformation on by ADB p collection by HSE rModifie Manager / d CEMP UpdateRe quest Approved by Changes Information input Reviewed by to CEMP Deputy RequesUp projecInformatio date or Advice n amend Update UpdateAp Reviewed proved by Verify by DiscussedUpdate by Deputy PMU ProjecDiscussed or amend by SSEMC ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 261 8.5: Site Engineers &Assistant Engineers; The Site Engineers / Assistant Engineers have the following duties in relation to environmental control; a) Assist the Environmental Manager in implementing the CEMP b) Monitor and control the works including those of sub-contractors to ensure compliance of both contractual and statutory requirements; c) Report to the Environmental Manager or Environmental Engineer regarding non-compliance of any environmental protection issues; d) Investigate and verify the complaint received from public; e) Ensure the remedial actions or mitigation measures are carried out as planned f) Carry out noise and vibration monitoring as required. g) Attend induction and regular meetings on environmental health and safety matters h) In the event of complaints being received by any staff i.e. site engineers/assistant engineers they must report to ESHE and ESHM and follow the procedure laid down in the Complaints Response Procedure. (Figure 2 ) 8.6: Technical officers, Foremen, Supervisors; Technical officers/Foremen/Supervisors are responsible for the following duties in relation to environmental control; a) Assist the Site Engineers/ Assistant Engineers to implement the CEMP b) Control the works, including those of sub-contractors, to fulfil environmental requirements; c) Report to the Site Engineers/ Assistant Engineers any non-compliance of environmental protection and mitigation measures; d) Investigate the complaint received from public, e) Carry out remedial actions or mitigation measures to rectify the non-compliance. i) Attend induction and regular meetings on environmental health and safety matters j) In the event of complaints being received by any staff i.e. site engineers/assistant engineers they must report to ESHE and ESHM and follow the procedure laid down in the Complaints Response Procedure. (Figure 2 ) 8.7: CHEC Employees; a) to carry out agreed site environmental practices as instructed by ES&H Manager, ES&H Engineer, Site Engineers and Foremen. b) Report promptly to their immediate supervisor who will report to ES&H Manger/ or Engineer on any non-compliance of environmental protection and mitigation measures. c) Participate and co-operate with the Project Management Team to achieve the environmental objectives. 9.0: IMPLEMENTATION AND MONITORING: It is essential to formulate monitoring system in order to evaluate remedial action taken in respect of water, air, land & waste pollution etc. The CEMP Monitoring Plan is a process of observing the tasks to be carried out on site after identification of environmental risks and hazard events and check whether the actions were executed according to the codes, regulations, and specification requirements. The ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 262 construction works executed will be observed and checked from time to time through site inspection or Ad-hoc inspection, any non-conformance found will be recorded and collective action will be taken. Thus, work procedures will be setup for controlling and monitoring the construction works to be implemented within the codes and specifications requirements. The CEMP Monitoring Plan includes the following:  Setup CEMP Monitoring Program.  Carry out preliminary survey and take necessary records for all elements involved before construction;  Carry out daily site visit to monitor project construction compliance with codes and regulation requirements (Please refer appendix–C for daily inspection check list)  Weekly site visit to monitor material production plants such as metal quarry, crusher, asphalt plant and concrete batching plant. ( Pls refer appendix –D for weekly inspection check list)  Carry out CEMP site inspection and audit, issue Non-Conformance Record (NCR)  Regular communication with local community, and record any complaint regarding to environmental issues;  Report to the ES&H Manager, Project Manager, Employer and Employer Representative on any non-conformance;  Documentation of records 9.1: Monitoring Program; The monitoring program is a detail environmental monitoring work program, it defines each and individual mitigation action which needs to be taken during the construction period. Moreover, the “daily inspection check list” & “weekly inspection check list” (see Appendix C & D) will be main tool for monitoring program since those lists indicate both compliances and non compliances in all relevant aspects of project activities. (See Appendix E). Within the monitoring period, site inspection, the environmental audit frequency will be planned according to the construction works program. Furthermore, environmental monthly meeting will be assigned as one aspect of monitoring program. The environmental monthly meeting will include Employer, Employer Representative, contractor and sub-contractors (if any). 9.2: Preliminary Survey and Records; Before commencement of construction, each and individual item listed in the EIA report will be reviewed. Action plan will be prepared for the necessary testing items to be carried out on site. Finally, the necessary investigation will be carried out to verify of any changes on the existing environmental conditions. Detail records and testing report will be kept and documented, and it will be submitted for review and approval. 9.3: Environmental Inspection and audit; In the CEMP, the site inspection and audit procedures will be setup. To enhance the environmental management and control, environmental inspections and audit are the effective mitigation measure to reduce the environmental impact. As a minimum, it will include the following: ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 263 1). The environmental site inspection will be carried out according to the program to verify site activities compliance with the project specifications and local codes requirements; 2). The environmental non-conformance records will be listed in the monthly construction progress report to bring the attention to the project team; 3). Non-Conformance Report (NCR) will be issued in an event of non conformity with ES&H aspect and it should be closed after rectifying with given time period .(Pls refer Appendix –E for NCR) 4). Random or Ad-hoc environmental inspection will be carried out to check the site activities without advance notice by senior management staff. 5). The Environmental documentation audit will be carried out periodically and adjust to suit the needs; 6). The anticipated environmental impact will be monitored to provide continuous improvement and maintain at the As Low As Reasonably Practicable level; 7). All NCR, CAR will be reported to Project Manager, Engineer & Employer, and in the monthly meeting. 8). Monitoring report will be prepared and included in the monthly report. The ES&H Manager and ES&H Engineer will be response to carry out the environmental site inspection and audit. 9.4: Monitoring & Reporting; The ES&H Manager will be response for the preparation of monitoring report, and the coordination and communication among Engineer, Employer, and CHEC project team. He is also response for reporting to the Engineer, Employer, ES&H Manager, and Project Manager on major environmental issues or non- conformance found. 9.5: Job Hazard; For those works with high risk or dangerous factors, proper guidance will be provided for safety operational, such as confined space, welding, etc. In accordance with related law, requirements and regulations of job hazard and risk assessment in PNG, prediction and evaluation of the present or expected hazards/ dangers in the operating environment will be conducted. To control ES&H risks more effectively, all the engineering activities must comply with the plan, and with the other relevant applicable PNG ES&H directives. In general, the ES&H risks identified as having the most serious impact or consequences must be dealt immediately. Most of the risks identified have direct repercussions on the construction and operational process; therefore, the continued monitoring of these risks is an important part of Construction Management. Examples of risk that have been identified include: ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 264  Delivery of major equipment & materials such as caissons, piles, quarry rock.  Contamination of sea water or accidental dumping of dredge material.  Environmental impact such as noise and dust during construction  Weather considerations  Accidents.  Precautionary measures with regard to health and safety will be described comprehensively in The Project Health & Safety plan. 9.6: Emergency Response Plan CHEC will establish, implement and maintain a procedure to identify potential emergency situations and potential accidents that can have an impact on the environment. It will consider the following :  Accidents, hospital facilities and ambulances  Fire, distance to fire station, how long does it take a fire engine to get to the site (response time), what on-site fire fighting equipment is maintained on site to fight the fire?  Fire fighting water tank. Does it hold enough water to fight the fire until the fire brigade responds?  Marine spill - does the Lae port have an oil spill response plan? What equipment do the have ? Do they have boats? What is their response time ? Can CHEC participate in their plan? Can this be applied to the dredger?  UXO - what is the procedure in the event of finding UXO ? This procedure will be prepared and submitted to ADB for approval before works commence. 9.7: Performance Monitoring The ES&H Manager will be responsible for the monitoring on the environmental management carried out on site. He will check regularly either on site activities or documented records. The performance of the environmental management will be properly monitored through the site activities, inspection records, audit records, and other reports. If any abnormal situations happen action will be taken either informing site staff to take immediate action or report to the Project Manager/ Employer regarding to the issue. 10.0: ENVIRONMENTAL MANAGEMENT & MITIGATION MEASURES; Summary of the potential hazard events identified in EIA Report are listed below. The initial mitigation measures are proposed for identified impacts. Any other site specific impacts which occur during the construction period will be evaluated and appropriate measures taken accordingly. 11.0: COMPLAINT MANAGEMENT: CHECL have developed a complaint management program to deal with any complaints raised from the public with regard to environment, health and safety issues as a result of operations. The complaint registers will be maintained and will be regularly monitored. 12.0: ENVIRONMENTAL TRAINING: All project personnel carrying out activities affecting the environment are sufficiently trained and competent in performing their assigned duties. All employees will receive appropriate training on environmental and waste management as followings: ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 265 a. Environment Training for Site Supervisory Staff A training session of “Environmental Protection” shall be provided to Site Supervisory Staffs within 14 days from the date of employment of such staff on the Site. b. Environment Management Training for Site Managerial Staff A training session of “ISO14001 Environmental Management System on Site” made by Head Office shall be provided to site managerial staff within 3 month from the date of works commencement. c. Environmental Site Specific Induction Training All staff and workers employed in the Project directly or in connection with the Project indirectly shall attend the Environmental Site Specific Induction Training delivered by the ES&H Manager/ES&H Engineer. They shall also attend the refresher training per every half-year. The training should cover but not be limited to legislation and regulations, policy, organization structure, duties and responsibilities, mitigation measures, targets in Environmental Management Plan, in-house rules and regulations. d. Environmental Toolbox Talk All the workers employed on the Project directly or in connection with the Project indirectly shall attend the Environmental Toolbox Talk regularly regarding the environmental nuisance abatement and waste management. Toolbox meetings will take place daily. The topics of toolbox training shall include but not limited to;  Air pollution control;  Wastewater treatment;  Noise control;  Waste reduction;  Waste management;  Site tidiness;  Handling of chemical waste; and  Environmental emergency preparedness. 13.0: ENVIRONMENTAL REPORTING: Related environmental issues will be included in the monthly report including records from site inspection, environmental accidents, etc. ESH inspection form and reporting procedure have been developed. This form will be modified relevant to actual work. .CHEC is developing relevant forms such as incident investigation form, ESH toolbox forms, incident reporting forms and others with respect to ISO 14001 – EMS. CHEC has developed non conformance record sheets modified to match this project. ESH issues will be recorded in a register and CHEC management will ensure these issues are addressed in a timely manner. The monthly report shall be prepared by the ES&H Engineer containing the following information: ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 266  A list of major forthcoming activities in the next two months which will likely have environmental impacts and nuisances to the surroundings and the control measures in mitigation;  The training programme for the next month and the records of training arranged/ conducted in the previous month;  The updated organization chart on environmental management; and  A summary of defects and deficiencies identified during inspections and weekly environmental walks and the follow-up actions and remedies taken to prevent recurrence. The ESH Manager will prepare a quarterly ESH performance report and submitted to Project Manager who then report to PMU & IPES. In addition, the Employer/ Employer’s Representative will be informed immediately if any major environmental incident occurs. The evaluation and identification of all possible hazard events will follow the procedure as described below. 14.0: MANAGEMENT REVIEW: Top management of CHEC will review the Environmental Management System, at planned intervals, to ensure its continuing suitability, adequacy and effectiveness. Reviews will include assessing opportunities for improvement and the need for changes to the Environmental Management System, including the environmental objectives and targets. Moreover the ISO14001 Environmental Management System will be followed in implementation of the CEMP. 15.0: SITE SPECIFIC ENVIRONMENTAL PARAMETERS: Potential site related specific environmental issues identified in the EIA and IEE are listed here under. a) Noise emission & Vibration b) Air quality c) Water quality d) Ecology & fisheries e) Solid waste f) Sewage waste g) Oil spillage & leakage h) Littering i) Vegetation j) Visual impact k) Erosion & sedimentation l) Socio-economic impact m) Archaeological & cultural heritage n) Environmental training 15.1: Noise & Vibration Noise emission will comes from the following sources  Construction works carried out in land, ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 267  Vehicular traffic associated with construction requirement  Operation of machineries and equipments.  The construction activities for breaking, piling, excavation, loading/unloading materials, reclamation  Site formation work Other major source of noise and vibration includes  Quarry, crusher plant  Asphalt plant operations. With the proper implementation of all noise & vibration mitigation measure during the construction period, the resultant noise & vibration impacts can be mitigated and minimized to an acceptable level. It is expected that the vibration issue will arise during the breaking of rock profile at a location along the quarry wall foundation. CHEC management will overcome this by using control blasting method under the supervision of qualified engineer. To minimise noise and reduce vibration forces, quarry site will have to be located further away from residential areas to reduce level of vibration and noise reaching them. Noise emitted from the sources identified poses a threat to the employees working in the site and general public. This noise causes naissance and can cause problems in hearing. However impact level is expected to be a minor medium level. A sound noise survey will be undertaken periodically to establish noise levels within the construction site. 15.2: Air Quality The potential of air quality impact during construction is limited. Air pollutants will come from the following sources  Breaking  Excavation  Loading/unloading materials  Reclamation operations  Acquiring of construction materials such as metal aggregates and sand etc from outsourcers Small particles dispersed in the air and ozone sourced from the mentioned areas are air pollutants. When inhaled, these pollutants can aggregate the lungs and can lead to chest pain, coughing, shortness of breath and throat irritation. Air quality & vibration management plan is being developed to deal with air quality issues at the construction site. 15.3: Water Quality The major cause of marine water quality impacts will be due to dredging marine sediments and the associated reclamation activities. The dredging works and reclamation are planned to be carried out simultaneously in a marine environment. These will likely to give rise to the following environmental impacts ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 268  Increased turbidity  Threatened geotechnical stability  Siltation in the existing harbour  Sediment transportation  Change in the current pattern  Change in adjacent beaches  Wave disturbance and impact on water quality It is necessary to note that periodic widespread high turbidity will be common in the project area because of sedimentation processes caused by the Markham River. The surface runoff from construction site may create potential pollution to the sea water during construction period. This will be effectively mitigated through the implementation of standard control measure, such as sediment traps, on-site wastewater collection and treatment systems, chemical toilet etc. 15.4: Ecology & Fisheries The dredging and reclamation work will cause permanent loss of benthic habitat over about 340 ha of seabed for the reclamation, and temporary loss of 820 ha for the approach channels and basin, the benthic habitat support mollusks, crustaceans, and fishes. Fish and shrimp spawn generally appear on the sandy sea bottom. The ecological value of benthic in these areas is not significant and similar habitats exist elsewhere. There are also two small isolated areas of limestone cap rock at the proposed entrance channel, but they do not provide a habitat for sponges, corals, and echinoderms. There are no protected habitats close to the project area, and therefore dredging and reclamation are not anticipated to have significant impacts on identified habitat in the dredging and reclamation areas. However, due to the high rock profile at a location along the quay wall foundation, under-water blasting is necessary. This may affect to marine fauna badly if blasting take places without considering possible danger for marine fauna. 15.5: Solid Wastes Different types of waste will be generated during the construction period Following are the major construction wastes;  Construction and dredged materials,  Chemical waste  General refuse. Unsuitable dredged & paving materials, used materials for temporary works such as concrete, off-cut timbers, paving materials, unsuitable metal and glass etc. are unavoidable although the amount can be controlled and minimized at the construction site. It is estimated that there will be a large volume of waste produced every month. CHEC management realizes the importance of proper management of waste arising from the construction works and has developed a Waste Management Plan to minimise environmental impact during the construction period. Waste Management Register will be developed to track down types and classes of wastes produced during the construction activities. 15.6: Sewage Sewage waste and grey water would be produced from the construction area as the construction works will accumulate construction personnel for the project duration. Such waste would require proper ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 269 management as this may contribute towards problems of odor, surface and groundwater pollution. 15.7: Oil spillage & leakage Environmental issue in relation to a spill and leak are expected in the construction area. Leak & spills can escapes into the storm water drainage accelerated by fluvial processes and can pollutes storm & marine water. Hazardous materials such as battery acids can cause significant effect on both health and environment when improperly and or incorrectly used or applied. Proper storage, handling and usage of both hazardous and non hazardous chemical at the construction site are required to reduce the risk of spillage and leachate which will have impact on the health and environment when carelessly stored, handled or used. 15.8: Littering Littering of construction site by the employees and sub-contractors may become an environmental health hazard if trash and other solid wastes are not properly managed. Although impact would be minor and temporary, it requires proper management and therefore specific details of managing littering will be implemented. 15.9: Vegetation Clearance Portions of the proposed construction area and the surrounds are fully covered by vegetation of mainly short grasses and scattered scrubs. The terrestrial ecological status is being maintained over time. This means that the area is a bird and insects friendly environment 15.10: Visual impacts Visual impact of the proposed construction site due to clearance of vegetation and alteration of landscape is inevitable hence will cause nuisance to the nearby community and the general public. Therefore it is an issue required to be addressed in this EMP. 15.11: Erosion & Sedimentation The key environmental issue for consideration with respect to topography, geology & soil are erosion & sedimentation control. Proposed construction site clearance will be implemented with respect to design drawing or site plan to maintain the potential of erosion and sedimentation. 15.12: Socio-economic issues: The Lae Port Development Project would generally have a positive impact on the lives of the locals. This project already provides employment opportunities for the locals who would earn some cash from the project and improve local income generation. However, with the positive impacts, there are also negative impacts that are anticipated on the social environment. However due to the Resettlement Program the local community now live further away from the project site so negative impacts are expected to be minimal. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 270 15.13: Archaeological & Cultural Heritage The proposed construction project may uncover some relics of archaeological and cultural significances. Archaeological and cultural heritage management issues are considered during the construction periods. 16.0: ENVIRONMENTAL MANAGEMENT PLAN: Table 1 below summarizes the environmental monitoring plan, showing the environmental issues, proposed mitigation measures and monitoring plan (locations, parameters, frequency, and responsibility). The monitoring plan for construction operations will be refined after the baseline is completed. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 271 Table 1 - Environmental Management and Monitoring Plan of Lae Harbor Construction and Operation Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility DESIGN / PRE-CONSTRUCTION PHASE Avoidance of  Detailed field surveys in Proposed Design plans Verify draft and CHEC / PMU sensitive areas consultation with dredged final plans for dredge authorities ascertained material disposal that proposed dredged disposal site material disposal sites are not in sensitive areas. Area is clearly delineated and tipping must remain further than 300m from mouth of Markham River and in at least 50m depth of water. Environmentally  Ensure that final harbor Adjacent shore Design plans Verify draft and CHEC / PMU sound design configuration will not line beach and final plans cause changes to river mouth shoreline, entrance to existing port and dynamics of adjacent areas. CONSTRUCTION PHASE ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 272 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility Turbidity  CHEC will identify and Construction  CHEC will inspect its Weekly during Contractor- (suspended map all area where soil areas surrounding to ensure dredging CHEC sement disturbances will occur that the erosion and operations load/sediment  For each of these areas sediment control plumes) during identify appropriate measures harbor dredging sediment control recommended are structures (silt fences, implemented on site bunds, sediment traps,  If the recommended basins and various measures are not sediment control drains implemented, and install these appropriate action will structures prior to be undertaken commencement of work immediately to remedy  CHEC will establish which the situation month of the year are  Areas that have been likely to experience re-vegetated will be higher rainfall inspected on a regular  Site preparation works basis to ensure that Contractor- will be minimised during vegetation is re- Daily with CHEC period of high rainfall established. direct reading  Works will be undertaken  Turbidity will be instruments for during dry season so that measured directly at turbidity and large quantities of the edge of the bi-weekly for unconsolidated materials construction site where suspended are not exposed to rain runoff may occur. sediments and run-off.  A bund or trench will be constructed to divert runoff to sediment ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 273 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility control structures. These bunds and trench will be removed after completion of construction works.  All disturbed earthworks sites will be covered or protected to avoid exposed soil from being washed away  All construction will be implemented according to the design plans that are compatible with respect to soil, climate, landform, drainage, vegetation cover and land use factors at the site.  All drainage on site will be constructed according to design plan so that run-off from outside the construction area does not mix with unfiltered run-off within the works area  Earthwork area will be protected as much as possible so that only a ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 274 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility smallest area is required to be exposed at any one time. Disturbed soil will be compacted on an artificial slopes  Construction spoil materials will not be placed on high grounds where materials can easily be washed off during unexpected rainfall period. Spoil material stockpile will be stored in bunded areas to prevent erosion. If necessary such stockpiles will be covered up with mulch or temporary vegetation Excessive noise  All employees working in Construction  ES&H Manager will Vibration and Contractor during dredging, an environment subject area carry out visual noise levels will CHEC sheet-piling, and to high ambient noise monitoring within the be measured demolition level would be required construction areas. Any periodically PMU to wear hearing workers not wearing (half yearly protectors, which meets full PPE including ear intervals) to KECC an international noise protectors in noisy verify its standard so that areas will be acceptability as excessive noise is limited disciplined. per standards. and minimized. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 275 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility  ES&H Manager will  Any noise complaints provide hearing from residents will be protectors such as dealt with in a timely earplug and ear muffs to an effective manner. Noise the employees exposed measurements to noise emitted by will be made if machinery within the necessary in construction site response to  The ES&H Manager in complaints. liaison with ES&H Engineer will ensure that equipment and machinery utilized in the construction works are well maintained and serviced so that the noise levels are minimized as much as possible.  Noises sourced from crusher plants & asphalt plant will be minimised by providing adequate buffer zone away from any residential areas  Working area will be suitably shielded from surrounding area either by bunding or appropriate noise ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 276 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility reflective security fencing.  Silencers or mufflers will be utilized in all construction equipment and properly maintained  Any areas where noise levels are above 85 dB(A) will be highlighted with sign boards and appropriate control measures taken Disposal of  Surface debris will be  Construction Direct readings will be Daily Contractor dredge spoils cleared and disposed of site made of water quality for observation CHEC to an approved landfill  Approved turbidity near the onshore  Dredged materials which dumping discharge point and PMU are unsuitable will be ground around the dumping zone dumped in an approved 300m KECC Disposal Area offshore. offshore in > Stockpiled materials will be Silt curtains will be 50m water inspected for dust deployed at the depth. generation. excavation area and at the dumping area. See Dredging Plan in Appendix G for details.  Dredged material which is useful will be stockpiled on site for future use in the platform age ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 277 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility construction. Stockpiles will be covered with tarpaulins to prevent dust entrainment by winds  Silt traps will be installed in runoff drains  Cutter suction hopper dredger will be employed as far as practically possible to minimize increased turbidity  Level of suspended solid, turbidity, dissolved oxygen and PH will be monitored during dredging operation in order to identify changes in marine water .If any significant changes occur, remedial action ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 278 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility will be taken promptly.  A stable transition region will be established between existing sea bed and the area to be dredged in order minimize risk of geotechnical instability.  The dredging will increase turbidity, but the spread of suspended solids is anticipated to be limited. The impacts related to a high level of suspended solids will not significantly reduce the primary productivity of these areas. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 279 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility  Although high level of suspended solids in the water column are not uncommon and localized increase in turbidity are not expected to significantly impact on water quality, the best practice controls in dredging operations will be executed to minimize the risk of uncontrolled release of sediment-laden water.  All construction plant and equipment will be designed and maintained properly to avoid the risk of silt, sediments, ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 280 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility contaminants or other pollutants being released or leaked into the sea.  Silt curtain will be deployed around the immediate dredging area when there is significant chance of silt dispersion to surrounding water body. Marine ecology  To reduce the  CHEC will carry Contractor and fishery impact to the out ecological CHEC marine fauna survey & during blasting at sediment PMU quay wall analysis half foundation, yearly intervals KECC control blasting to identify practices and changes in setting up of marine fauna bubble curtains and flora. will be carried out Thereby during blasting magnitude of work. changes can be  Ensuring that the identified by dredging and ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 281 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility reclamation as benchmarking well as those results. construction of  CHEC will the permanent monitor marine and temporary and fishery revetments do impacts by not extend observation of beyond the behaviour of designated areas marine fauna regularly to help identify any changes in behavioural pattern. Spills of fuel and  Material Safety Data Work sites  ES&H Manager will Daily Contractor other hazardous Sheet (MSDS) will be undertake regular inspection CHEC materials made available as a guide inspection of fuel for the proper use of a storage tanks or drums PMU type of chemical. to ensure that no leach  MSDS will be consulted or spill occurs. KECC whenever needed to  ES&H Manager will guide the use of undertake daily visual hazardous & non checks around the hazardous chemicals. construction site to  The CHEC management detect any leakages or will construct a hard spill of effluents. surface area with a  ES&H Manager will containment bund for the make Regular checks of refuelling facility to containers for any ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 282 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility contain spills should a minor leaks where in refuelling facility be built service or in storage within the construction after being emptied. site.  Oil storage containers or drums will be placed in the bunded area to contain leach and spill.  Drip trays will be used under drums during fuel or solvent transfer  Waste oil will be collected and removed from the site by a licensed contractor to an authorised disposable location Truck / traffic  Implementation of From port area Complaints or traffic jams Daily Contractor impacts due to hauling schedules that to land disposal observation CHEC hauling of rock minimize local traffic sites and from Reports from local traffic from quarry and problems quarry to port police spoil removal as  Implementation of traffic site may interfere control scheme to with local vehicle minimize need to cross traffic. Falling against existing traffic rocks from flows vehicles or mud  All vehicles carrying loads on road. to be covered with tarpaulins ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 283 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility  Wheel washing facilities and “cattle grids” at access points to site Disturbance of  Protect and never touch Harbor area and Reports from site staff, site Constant Contractor cultural remains known cultural relic surroundings supervisors observation CHEC building during working.  Report to the Engineer Daily reminders PMU for instruction when to staff during possible cultural relics are “Tool Box” KECC found and stop work until briefings getting approval from the Engineer. Archaeological  CHEC will raise  CHEC’s Contractor and cultural awareness among construction heritage employees, on personnel are the significances to watch out of archaeological for any items of relics and cultural heritage found on significances site  CHEC will  CHEC will ensure ensure that the that personnel on sub-contractors site are aware of and employees or trained in the are mindful of need to report cultural any sightings of heritage when artefacts and undertaking relics or heritage the works ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 284 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility remains that are uncovered or disturbed during the excavations activities  Any archaeological finds during works should be reported to ES&H Manager to have them salvaged  The National Museum will be immediately contacted to undertake any salvage activity which cannot be handled by CHEC Complaints from  Report to the Engineer Harbor area and Reports from site staff, site Daily reminders Contractor local Community for instruction when surroundings supervisors concerning to staff during CHEC over complaints received. verbal or formal “Tool Box” construction  Follow complaints complaints briefings PMU activities procedure KECC ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 285 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility Construction  CHEC will provide Site area CHEC will undertake visual Daily Contractor Workers Camp showers, toilets, and monitoring to ensure the Observation CHEC clothes washing facilities adequate treatment of Use of camps for for use by employees at sewage and grey water Monthly formal PMU vehicle parking, convenient locations before being discharged reporting maintenance within the construction KECC and repair site  Waste water discharges Use of camp for from general site refuelling activities includes waste water treatment units, oil HIV Awareness traps, silt traps and settlement tanks will be Gender Issues properly controlled before released to the city sewer system or through any temporary outfall.  If connection to the city system is not feasible CHEC will ensure that all sewage waste are properly treated prior to discharge into surroundings  Ensure that sewage treatment units established on site are working adequately ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 286 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility  Ensure that all grey water is also treated prior to discharge  Provide awareness to all personnel working on site to use the toilet facilities provided and not the bushes  If alternative pit toilet are used on site, they will be kept hygienic to avoid nuisance  Any cooking facilities will be cleaned regularly and maintained in a sanitary condition  Any food waste will be stored in closed bins to be bagged and removed from site daily  All other waste such as paper, cardboard, plastic bags and bottles, glass bottles, and cans will be segregated for recycling if possible and the removed by an authorised sub- contractor to a ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 287 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility government approved sanitary landfill.  Scavenging of recyclable solid waste materials by employees will be disallowed.  Forbid unnecessary burning of garbage within the construction site as this will contributes to Green House Effect.  Vermin control will be implemented. Uncontrolled waste food disposal will not be permitted as it encourages vermin and disease bearing vectors.  Regular pesticide and insecticide spraying will be implemented to control mosquitoes  Stagnant water will not be allowed to accumulate as it provides a haven for mosquito breeding.  HIV awareness programs will be instituted and all ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 288 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility workers required to attend  Interaction with local populace will be carefully monitored and workers continually reminded to avoid conflict situations  The Workers Camp will enforce a Zero Tolerance Policy towards possession on site or in the camp of alcohol, drugs, and weapons. Littering  CHEC will Site area  ES&H Manager Daily Contractor establish a will undertake CHEC central litter visual collection centre monitoring on PMU at the a regular basis construction area to ensure that KECC so that all litter at littering does the construction not become a area are collected problem at the at the main construction collection point area which will be disposed at the authorised site.  Place rubbish bins at the strategic ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 289 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility locations within the construction site to store rubbish.  ES&H Manager will notify and encourage all sites personnel to avoid littering and dump their wastes at the central collection points or into the rubbish bins provided. Vegetation  Any unreasonable Site area  ES&H Manager Daily Contractor removal of the will monitor by CHEC vegetation doing spot surrounding the checks to PMU construction area ensure that an will be avoided as unreasonable KECC much as possible removal of  Avoid making fire vegetation at on the grasses the surrounding surrounding construction site areas do not which may occur destroy the  ES&H manager will undertake ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 290 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility grassland visual ecosystems. inspection to ensure that the making of fires surrounding area is avoided as much as possible. Rock Quarry  Water sprinkling  ES&H Manager As required Contractor Operation will be done as will make spot CHEC required in checks on exposed area of quarries to PMU quarry site and review their transport route to operation. suppress dust generation.  Water sprinkling system will be adopted in crusher plant as applicable in loading point of hopper and other parts of the crusher which emits dust  Material transport route is also to be ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 291 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility watered to minimize dust emission.  When transporting dusty material by vehicles, those materials will be covered with tarpaulin cover in order to prevent accidental spillage. OPERATION PHASE Pollution from  Waste water discharges Harbor area IPBC will undertake visual Monthly IPBC/ Port port’s sewage from port activities monitoring to ensure the Management and stormwater includes waste water adequate treatment of Authority treatment units, oil traps, sewage and grey water silt traps and settlement before being discharged tanks will be properly controlled before released to the city storm-drainage system or through any temporary outfall.  Toilet and other sanitary facility for employees will be provided at ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 292 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility convenient locations within the port  All sewage waste will be properly treated prior to discharge into surroundings  Provide awareness to all personnel working on site to use the toilet facilities provided and not the bushes Pollution from  All solid wastes Harbor area  ES&H Manager will Weekly IPBC / Port port’s solid will be placed watch out for any Management wastes into the rubbish unacceptable practice Authority bin drums. When of waste disposal full, they will be within the port by removed and employees and visitors. disposed of to an  ES&H Manager will authorised dump ensure that the site for land employees and waste filling. collectors are adhering to this solid waste management plan. Pollution from  Disposal of Harbor area Illegal sewage discharges Daily when Visiting ships sewage of ships sewage and bilge ships are in and Harbor in port water in harbor Master accordance with MARPOL 73/78. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 293 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility Oil spills and  The sewage and Port area and Illegal waste water Daily Harbor leakage within waste oil of offshore water discharges Master & harbour, or vessels should be Port escape the collected. Management harbour area Applications Authority should be applied before pumping out of tanks. All vessels’ engineers should make records of the Oil Discharges. Oil spills from  Implementation Port area and Spills of oils Daily when Visiting ships vessels entering, of the Cook offshore water ships are in and Harbor berthing and Islands harbor Master leaving the Prevention of harbour Marine Pollution Act (1998) and of existing oil spill contingency plan Pollution from  Disposal of Harbor area Illegal sewage and bilge Daily when Harbor sewage and bilge sewage and bilge water discharges, presence ships are in Master water from ships water in of oil sleek harbor in harbor areas accordance with MARPOL 73/78. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 294 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility Pollution from  With prior notice, Harbor area Illegal dumping of solid Daily when Harbor solid wastes of CIPA will provide wastes ships are in Master ships in port solid waste harbor reception for disposal in accordance with MARPOL 73/78. Pollution due to  Implementation Harbor area Release of materials during During Harbor accidents or of a Contingency accidents and emergencies accidents and Master emergencies Plan with the emergencies necessary equipment and personnel training. Proactive  Implement an Harbor area EMS components Monthly IPBC PMU management of environmentally port’s responsible port environmental management footprint and system (EMS) to advance port achieve and sustainability maintain continual environmental quality of the harbor area. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 295 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility Air quality  Periodic emission Harbor area  Carryout a Monthly IPBC PMU test will be regular visual carried out on inspection machineries & around the equipment in port to ensure order to identify that the does malfunction areas not becomes a and possible problem inefficiency of emission control mechanisms  Water sprinkling will be applied on exposed excavation areas to suppress dust generation.  Ambient air quality test will be carried out half yearly at the port.  Loading, unloading, transfer, handling or storage of bulk cement will be carried out in an enclosed area ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 296 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility and any vent or exhaust will be fitted with air pollution control system. Water quality  Refuelling facility Harbor area  ES&H Manager Monthly IPBC PMU will be bunded to will continue to prevent spill undertake a which when daily visual percolated into monitoring the soil will within the pollute the facility and underground surrounds to water table and ensure that all when washed solid wastes down to into the are correctly storm water disposed off drainage and and spill should further into the not occur and sea will affect all forms of aquatic & marine liquid wastes organisms. are being  .Sewerage water discharged or arisen from toilet placed in a will driven to designated sewerage water area. treatment unit for required purification ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 297 Environmental Management and mitigation monitoring Environmental Mitigation Measures Locations monitoring parameter monitoring monitoring Issue frequency responsibility before disposed to marine environment or city sewer water drainage pipeline. ESIA for Proposed 132/33 kV Transmission Substation at Kabba in Kogi State | 298 Appendix C - Daily Monitoring check list –Construction area DAILY MONITORING CHECK LIST – CONTRUCTION AREA Date____________ Time__________________Location________________ Key Aspects Constraints/ Mitigation Measures Yes No NR Remarks/ Action taken( if any NCR ) Are TB(dredger name) used for dredging Are there any spillage of oil or other hazardous substance from Dredging machineries/equipment Is level of suspended solid within tolerance Is level of turbidity within tolerance Is level of dissolve oxygen within tolerance Is any complication observed in marine fauna Disposal of sewage and Is oil trap/ grease trap working properly waste water from land – based source Is sewer water treatment plant working satisfactory Disposal of sewage and waste water from Is there any leakage or spillage of waste water construction Vessels. Are silt/sand traps available in required area Surface water runoff from Are de silting done satisfactory reclamation area Are manhole covered adequately Are material stockpiles covered adequately Are emission test available for equipments , machineries & Breaking, excavation, vehicles loading/unloading If yes, are they conformed with required standards materials and reclamation operations Are Silencers or mufflers fixed in machineries Is water sprinkling system adequate Are disposal bins available for bio degradable waste & non bio General refuse disposal degradable waste Is previous day waste collection carried out Construction waste Are stock piles are covered or applied wet process disposal Is chemical waste storage met with CEA requirements Inspected by: _________________ Approved by: _________________ ES&H Engineer ES&H Manager Appendix D - Weekly Monitoring Checklist – Plant Date_____________ Time________________Location______________________________ Constraints/ Mitigation Measures Yes No NR Remarks/ Action taken( if any NCR ) Key Aspects Is noise /vibration level within standards at the boundary Is it necessary to adopt sound proof measure Are there any spillage of oil or other hazardous substance from machineries/equipment Is waste water generated If “yes” , is there any waste water treatment system Production Process Is waste water analytical report available If “yes” are tested parameters conformed with standards Is air emission possible If “ yes” is emission control system / water sprinkling available If “yes’ ,is treatment system satisfied Is ambient air quality test report available If “Yes” , are tested parameters conformed with standards Are stock piles are covered or applied wet process Storage of materials Is chemical waste storage met with CEA requirements . Are silt/sand traps available in required area Surface water runoff Are de silting done satisfactory Are manholes covered adequately Are emission test available for equipments , machineries loading/unloading and & vehicles transportation of If yes, are they conformed with required standards materials Are silencers or mufflers fixed in machineries Are disposal bins available for bio degradable waste & General refuse disposal non bio degradable waste Is previous day waste collection carried out Inspected by : ________________ Approved by : _______________ ES&H Engineer ES&H Manager Appendix – E Non Conformance Report NCR No. ____________ To___________________ Location ______________Date ______________ Time______________________ Description of non- conformity: Suggestion for rectification: ---------------------------- ES&H Manager TO: …………………………………. Please implement above suggestions immediately / within ------ days & report ------------------------- ES&H Manager TO : ES&H manager Completed/ not completed. --------- Head of the department (NCR receiver) Satisfactory / Unsatisfactory ----------------------------------- ES&H Engineer / Safety Officer Approved & recommend for closing ES&H Manager 17.8 Annex 8 Generic Decommissioning Plan Reason For Plan After decommissioning the site may be handed over to a new owner and developed for another purpose. Although decommissioning works could be a long time in the future plans should be drawn up now to restore the site to conditions acceptable to FMEnv. Care must be taken during decommissioning not to cause contamination. Potential Impacts Environmental impacts associated with decommissioning can minimised through the implementation of an environmental and social management plan (ESMP). Potential negative impacts during decommissioning could include  Spillages of transformer oils on ground and into groundwater as equipment is removed.  Solid wastes such as brick, concrete and rubble from substation site demolition  Metals and cables from towers dismantling can become an eyesore if not taken off site either for re-use or recycling.  Invasive flora species could colonise former substation sites and the way-leave on decommissioning following removal of structures, buildings and hardcover.  Local residents could be subject to noise and air impacts during demolition. Generic Plan The following generic plan should be followed : Table 17-1 Generic Decommissioning Plan Timing Action Impact Rationale Prior to Prepare TCN must Ensures that decommissioning plan complies decommissioni detailed review and with TCN EHS Policy and World Bank Safeguard ng decommissio approve Policies. ning plan and decommissioni submit to ng plan. TCN for approval. Prior to Obtain Give legal right Ensures that Operation has ceased decommissioni Possession to enter site ng Order from TCN Prior to Contact Disconnect all Ensures that power water and gas are decommissioni utility utilities. disconnected and cutting utility supply pipes or ng companies. lines is not hazardous. Prior to Contact TCN Staff to vacate Ensures that all non-essential staff have left the decommissioni Operational site site. ng staff. Prior to Contact TCN Avoids Decommissioning involves entering confined decommissioni EHS Section contractors spaces with inherent hazards. Hot Work ng to obtain any staff working in permitting is an essential mitigation measure. “Hot Work” hazardous Permits areas. needed. Decommission Removing Spillages of oils. Spillages of transformer oils may occur as ing transformers equipment is removed. Use containment around the transformers and have spill mop kits nearby. Place waste oil in a drum within a second containment drum and remove off site to a licensed waste contractor’s premises for recycling or destruction. Decommission Demolishing Solid wastes Solid wastes such as brick, concrete and rubble ing buildings from substation site demolition will need removal. Hire licensed waste contractor and remove to LGA approved landfill. Recycling of construction rubble may be approved if carried out in clean manner. Decommission Dismantling Scrap metal Metals and cables from towers dismantling can ing towers become an eyesore if not taken off site either for re-use or recycling. They can be sold to an approved scrap metal dealer. Decommission Site Ecology Invasive flora species could colonise former ing abandoned changes substation sites and the way-leave on decommissioning following removal of structures, buildings and hardcover. Arrange for maintenance of site after closure until handover. Decommission Use of noisy Excessive noise Local residents could be subject to noise impacts ing machinery levels during demolition. Maintain perimeter noise for levels below 75dB(A) to meet industrial standard demolition and only work between 0700 and 1900. Decommission Leakages of Soil It is necessary to establish if deterioration has ing oil contamination taken place between site occupation and site decommissioning. Repeat sampling of soils in same locations as were sampled in the original baseline. Take to lab for analysis of all parameters recorded in baseline. Then compare results with baseline conditions to give Before and After comparison. Soil removal If soil is contaminated then it must be removed off site and disposed of in accordance with Local Government practices. Groundwater It is necessary to establish if deterioration has contamination taken place between site occupation and site decommissioning. Repeat sampling of groundwater in same locations as were sampled in the original baseline. Take to lab for analysis of all parameters recorded in baseline. Then compare results with baseline conditions to give Before and After comparison. Groundwater If groundwater is contaminated then it may be remediation necessary to seal off sampling well and drill new well. Decommission FMEnv Site declared Final soil and water samples must be submitted ing Approval of clean to FMEnv for their approval. When their remediation approval is obtained then site can be handed over to next owner as being free of all contaminants. FMEnv certificate must be submitted to TCN. Post Site handed TCN accept site Contractor must obtain signed letter of Decommission back to TCN as being free of acceptance from TCN. TCN are now at liberty to ing all dispose of the site to a third party without fear contamination of liabilities.