Page 1 i Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 03/24/2011 1. Basic Information Project ID & Name P103539: GY-GEF Conservancy Adaptation Project Country Guyana Task Team Leader Sylvie Debomy Sector Manager/Director Guang Zhe Chen Country Director Francoise Clottes Original Board Approval Date 10/11/2007 Original Closing Date: 06/30/2011 Current Closing Date 06/30/2011 Proposed Closing Date [if applicable] 03/31/2013 EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 01/01/2009 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 1.20 1.20 GEFU 3.80 3.80 Total 5.00 5.00 3. Borrower Organization Department Location 4. Implementing Agency Organization Department Location 5. Disbursement Estimates (US$m) Actual amount disbursed as of 04/05/2011 0.71 Fiscal Year Annual Cumulative 2011 0.00 0.71 Total 0.71 Page 2 ii 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select from the checklist below and update ISDS accordingly before submitting the package. N 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The objective of the CAP is to reduce the vulnerability of catastrophic flooding in Guyana's low-lying coastal area that is currently threatened by sea level rise resulting from global climate change. 7b. Revised Project Development Objectives/Outcomes [if applicable]