PROCUREMENT METHODS AND PRIOR REVIEW THRESHOLDS (a) Goods/Works: All ICB contracts for Goods and Works; First two NCB contracts for Goods and First two NCB contracts for Works irrespective of the cost of the First Shopping contract for Goods and First Shopping contract for Works. b) Consultants services FIRMS: All contracts with consulting firms estimated to cost US$300,000 or more; First contract with consulting firms selected on the basis of Consultants Qualifications (CQ) Individual Consultant All contracts with individual consultants estimated to US$50,000 or more All contracts with PIU staff irrespective of the cost of the contract ; General: - The Terms of Reference for all consultant contracts with consulting firms and individual consultants Short lists comprising entirely national consultants shall be for assignments below USD 300,000; Procurement method threshold ICB NCB $ USD $ USD Goods Works Goods Works ≥1.000.000 ≥ 5.000.000 < 1.000.000 <5.000.000 Prior review threshold ICB NCB $ USD $ USD Goods Works Goods Works All All First 2& >2.000.000;First 2&>10.000.000 AND PRIOR REVIEW THRESHOLDS or Works irrespective of the cost of the contract; ts Qualifications (CQ) sulting firms and individual consultants irrespective of their costs; ssignments below USD 300,000; method threshold SHOPPING $ USD Goods Works ≤ 100.000 ≤ 200.000 ew threshold CONSULTANTS $ USD Firms Individual* >1.000.000 > 300.000 *Individual Consultant Prior Review only under exceptional circumstances Plan vs./ Actual Days Execution Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval BEEP- Energy efficiency Proj ect Rev ie Proposal No Name of Cate Not Adv erti- Reception Short Technical No Final Ref No in Federation B&H October, Selectio w No Inv itation Submissi Obj ection Contract Comple- Assignment/Contract gory e # sement of Listing Ev aluatio Obj ection Ev aluatio Start 2014 n by Obj ection for RFP on Date to Signature tion for EOI expression and RFP n + PSC n Date Method Bank Date Date Date sign Date Date Date of interest ready Date Date Date Prior / contract Post A B D E F H I J Consulting firms COMPONENT 1 Combined Serv ices for Clinics and chosen Schools Detailed Energy Audit, P TME before, Design, Package 1: Audit of Design University Clinical Center A Sarajevo Ortopedic and Traumatology; BEEP- Surgery Clinic in Tuzla; Supervision, TME after, P143580-CQ- P CS CQ Prior 10/5/2015 14 24/5/2015 8 1/6/2015 7 8/6/2015 0 8/6/2015 10 18/6/2015 4 22/6/2015 0 22/6/2015 0 22/6/2015 7 29/6/2015 170 16/12/2015 0 ######## 300 ######## Psychiatric Hospital Mostar Energy Labelling 02-CS-15-FBIH A 10/5/2015 14 24/5/2015 8 1/6/2015 7 8/6/2015 0 8/6/2015 10 18/6/2015 4 22/6/2015 0 22/6/2015 0 22/6/2015 7 29/6/2015 170 17/12/2015 0 1/2/2016 408 15/3/2017 Package 2 (10+3=13 obj ects) Ze-Do, Una-Sana, HNK Elementary School Ivana fra Frane Jukica Sivsa Usora; Elementary School 21. mart Doboj Jug; Gimnasium Rizah Odzeckic Zavidovici; Elementary School "Gazi Ferhad-beg" Combined Services BEEP- Tesanj; Secondary Mutual (Design, technical P143580-CQ- P CS CQ Prior 1/12/2015 14 15/12/2015 8 ######## 7 ######## 0 ######## 10 9/1/2016 4 13/1/2016 0 13/1/2016 0 13/1/2016 7 20/1/2016 2 22/1/2016 0 22/1/2016 450 16/4/2017 School Zepce; Hospital Bihać; monitoring (before and 04-CS-15-FBIH Elementary school Bosanska after), works supervision) Otoka; I Secondary school Dr. Husein Džanić & II secondary schoo l, Gymnasium; Elementary school Stijena Cazin; I & II Secondary school Cazin; Elementary School Fra Didaka Buntića Čitluk; Secondary 22.01.201 22.01.201 29.01.201 A 2/12/2015 13 15/12/2015 24 8/1/2016 10 05.02.2016. 0 05.02.2016. 0 05.02.2016. 12/2/2016 15/2/2016 15/2/2016 30/6/2018 6. 6. 6. Package 3 (12+4=16 obj ects Ze- Detailed Energy Audit, Do, Saraj ev o, HNK) TME before, Design P Secondary Mutual School completed for „Mula Stjepana Radica Usora; Mustafa Baseskija“ Elementary School Safvet-beg A Basagic Visoko; Elementary School Kulin Ban Visoko; Elementary School "Musa Cazim Catic" Zenica; Elementary School "Hamdija Kresevljakovic" Kakanj; Elementary School 15. April Kakanj; Elementary School „Mula Mustafa Baseskija“ Visoko; Combined Services BEEP- First elementary school (Design, technical P143580-CQ- CS CQ Prior 1/12/2015 14 15/12/2015 8 ######## 7 ######## 0 ######## 10 9/1/2016 4 13/1/2016 0 13/1/2016 0 13/1/2016 7 20/1/2016 2 22/1/2016 0 22/1/2016 450 16/4/2017 Zavidovici; Hospital Tesanj; monitoring (before and 05-CS-15-FBIH Elementary School „Zahid after), works supervision) Barucija; Elementary School „Hasim Spahic“; Elementary School „Srednje“ Ilijas; Secondary School Juraja Dalmatinca Mostar; Hospital Jablanica; Secondary School 22.01.201 22.01.201 29.01.201 A 2/12/2015 13 15/12/2015 08.01.2016. 05.02.2016. 0 05.02.2016. 0 05.02.2016. 12/2/2016 15/2/2016 15/2/2016 30/6/2018 6. 6. 6. BEEP- Package 2, 3 P143580-CQ- P (allocated) Audit of Design CS CQ Post 1/12/2015 14 15/12/2015 8 ######## 0 ######## 0 ######## 10 2/1/2016 0 2/1/2016 7 9/1/2016 0 9/1/2016 0 9/1/2016 2 11/1/2016 0 11/1/2016 65 16/3/2016 01-CS-15-FBIH A 2/12/2015 13 15/12/2015 14.01.2016. - 20.01.2016. 27.01.2016. 01.02.2016. 0 01.02.2016. 0 01.02.2016. 0 - 0 8/2/2016 15/2/2016 90 15/5/2016 Combined Services (Design for 18 objects, BEEP- Technical monitoring Package 4 (2017. buldings) P143580-CQ- P before and after for 19 CS CQ Post 15/1/2017 14 29/1/2017 2 31/1/2017 3 N/A 0 3/2/2017 7 10/2/2017 3 13/2/2017 0 N/A 2 15/2/2017 0 N/A 0 15/2/2017 0 15/2/2017 410 1/4/2018 (allocated) 06-CS-16-FBIH objects, Works Supervision for 13 Objects) A 17/1/2017 15 1/2/2017 15/2/2017 0 N/A 0 15/2/2017 7 22/2/2017 24/2/2017 0 N/A 0 24/2/2017 N/A 2/3/2017 0 2/3/2017 30/6/2018 Combined Services BEEP- (Works Supervision for 5 P143580-CQ- P federal level objects + 1 CS CQ Post 15/1/2017 14 29/1/2017 2 31/1/2017 3 N/A 0 3/2/2017 7 10/2/2017 3 13/2/2017 0 N/A 0 13/2/2017 2 N/A 2 15/2/2017 0 15/2/2017 410 1/4/2018 07-CS-16-FBIH Package 5 (2017. buildings) object for Piloting, Audit (allocated) of design for 19 objects) A 17/1/2017 15 1/2/2017 15/2/2017 0 N/A 0 15/2/2017 7 22/2/2017 24/2/2017 0 N/A 0 24/2/2017 N/A 6/3/2017 0 6/3/2017 30/6/2018 Combined Services BEEP- Package 6 (2018. buldings) (to (Design for 11 objects, P143580-CQ- P CS CQ Post 11/1/2018 14 25/1/2018 2 27/1/2018 3 N/A 0 30/1/2018 7 6/2/2018 3 9/2/2018 0 N/A 2 11/2/2018 0 N/A 0 11/2/2018 0 11/2/2018 450 7/5/2019 be allocated) Works Supervision for 11 08-CS-18-FBIH Objects) 03.01.2018 17.01.2018 A & 14 & 7 & 23/2/2017 0 N/A 0 27/2/2018 8 7/3/2018 8/3/2018 0 N/A 0 13/3/2018 N/A 26/3/2017 0 26/3/2017 ######## 15.02.2018 22.02.2018 Combined Services (DEA, Design for XXX BEEP- objects, Technical P143580-CQ- P monitoring before and CS CQ Post 11/1/2019 14 25/1/2019 2 27/1/2019 3 N/A 0 30/1/2019 7 6/2/2019 3 9/2/2019 0 N/A 0 9/2/2019 2 N/A 2 11/2/2019 0 11/2/2019 323 ######## 10-CS-19-FBIH Package 7 (2019. buildings) after for XXX objects, (to be allocated) Works Supervision for XXX Objects) A Package 6 (2018. buldings - 11 BEEP- obj ects) P143580-CQ- P Audit of Design CS CQ Post 11/1/2018 14 25/1/2018 2 27/1/2018 3 N/A 0 30/1/2018 7 6/2/2018 3 9/2/2018 0 N/A 2 11/2/2018 0 N/A 0 11/2/2018 0 11/2/2018 50 2/4/2018 (to be allocated) 09-CS-18-FBIH A 3/1/2018 14 17/1/2018 23/2/2017 0 N/A 0 28/2/2018 8 8/3/2018 8/3/2018 0 N/A 0 13/3/2018 N/A 26/3/2017 0 26/3/2017 ######## BEEP- Package 7 (2019. buildings) P143580-CQ- P (to be allocated) Audit of Design CS CQ Post 11/1/2019 14 25/1/2019 2 27/1/2019 3 N/A 0 30/1/2019 7 6/2/2019 3 9/2/2019 0 N/A 2 11/2/2019 0 N/A 0 11/2/2019 0 11/2/2019 50 2/4/2019 11-CS-19-FBIH A F. Preliminary/Detailed energy audits BEEP- 72 detailed energy audits - Consultant engineering P143580-CQ- P CS CQ Post 1/2/2016 14 15/2/2016 8 23/2/2016 7 N/A 0 23/2/2016 10 4/3/2016 4 8/3/2016 0 N/A 0 8/3/2016 7 N/A 2 10/3/2016 0 10/3/2016 90 8/6/2016 2017. buldings service 11-CS-16-FBIH A 19/4/2016 14 4/5/2016 6/5/2016 N/A 9/5/2016 7 16/5/2016 19/5/2016 0 N/A 0 24/5/2016 0 N/A 0 9/6/2016 0 9/6/2016 90 7/9/2016 BEEP- 30 detailed energy audits - Consultant engineering P143580-CQ- P CS CQ Post 25/5/2016 14 8/6/2016 8 16/6/2016 7 N/A 0 16/6/2016 10 26/6/2016 4 30/6/2016 0 N/A 0 30/6/2016 7 N/A 2 2/7/2016 0 2/7/2016 45 16/8/2016 2017. buldings service 18-CS-16-FBIH A 4/7/2016 14 18/7/2016 25/7/2016 N/A 3/8/2016 7 10/8/2016 1 11/8/2016 0 N/A 0 12/8/2016 0 N/A 0 25/8/2016 25/8/2016 60 ######## BEEP- 50 preliminary energy audits (to Consultant engineering P143580-CQ- P be allocated) - 2018./2019. CS CQ Post 25/5/2017 14 8/6/2017 8 16/6/2017 7 N/A 0 16/6/2017 10 26/6/2017 4 30/6/2017 0 N/A 0 30/6/2017 7 N/A 2 2/7/2017 0 2/7/2017 60 31/8/2017 service 12-CS-18-FBIH buldings A G. Social monitoring and ev aluation BEEP- Social monitoring and P143580-CQ- P Consultant services CS CQ Post 20/12/2015 14 3/1/2016 8 11/1/2016 7 N/A 0 11/1/2016 10 21/1/2016 4 25/1/2016 0 N/A 0 25/1/2016 7 N/A 2 27/1/2016 0 27/1/2016 790 27/3/2018 evaluation -(IA) (alocated) 12-CS-15-FBIH A 11.01.2016. 25.01.2016. 1/2/2016 - 9/2/2016 7 16/2/2016 1 17/2/2016 0 N/A 0 28/3/2016 - 5/4/2016 0 5/4/2016 1/6/2019 #REF! Total Estimate cost Subtotal Allocated To be allocated TOTAL COMPONENT 1 COMPONENT 2 Sub-Component A: Support for scalable financing mechanisms Consultant firms Senior International Energy BEEP- Efficiency Consultant for the P143580-IC- P Development of the Issue and Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Options Study on Scalable I Financing Mechanisms A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 11/8/2017 31/8/2017 48 30/4/2018 BEEP- Financial Expert for the P143580-IC- Development of the Issue and Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Options Study on Scalable II Financing Mechanisms A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 50 30/4/2018 BEEP- Policy/Regulatory Expert for the P143580-IC- Development of the Issue and Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Options Study on Scalable III Financing Mechanisms A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 65 30/4/2018 BEEP- Technical Expert for the P143580-IC- Development of the Issue and Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Options Study on Scalable IV Financing Mechanisms A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 40 30/4/2018 BEEP- Further development of the Issue P143580-IC- P and Options Study on Scalable Consultant service CS IC Post 1/5/2018 14 15/5/2018 8 23/5/2018 7 30/5/2018 0 30/5/2018 10 9/6/2018 4 13/6/2018 0 13/6/2018 0 13/6/2018 7 20/6/2018 2 27/6/2018 0 27/6/2018 ######## 13-CS-18-FBIH Financing Mechanism A #REF! Subtotal Allocated A To be allocated A Subtotal Subcomponent A Sub-Component B: Capacity building BEEP- Training Municipality energy P143580-CQ- P Consultant service CS CQ Post 1/12/2016 14 15/12/2016 8 ######## 7 ######## 0 ######## 10 9/1/2017 4 13/1/2017 0 13/1/2017 0 13/1/2017 7 20/1/2017 2 27/1/2017 0 27/1/2017 450 22/4/2018 management-certification 14-CS-16-FBIH A 4/1/2017 14 18/1/2017 27/1/2017 0 27/1/2017 0 30/1/2017 7 6/2/2017 1 7/2/2017 0 7/2/2017 0 7/2/2017 0 7/2/2017 0 2/3/2017 2/3/2017 ######## BEEP- "Communications, awareness P143580-CQ- P Consultant service CS multi CQ Post 15/1/2016 14 29/1/2016 8 6/2/2016 7 13/2/2016 0 13/2/2016 10 23/2/2016 4 27/2/2016 0 27/2/2016 0 27/2/2016 7 5/3/2016 2 12/3/2016 0 12/3/2016 811 1/6/2018 raising and outreach". 15-CS-16-FBIH A 13.01.2016. 26.01.2016. 1/2/2016 - 9/2/2016 7 16/2/2016 17/2/2016 - 19/2/2016 - 22/2/2016 22/2/2016 30/6/2018 BEEP- P143580-CQ- P Promotion of EE results Consultant service CS multi CQ Post 20/2/2016 14 5/3/2016 8 13/3/2016 7 20/3/2016 0 20/3/2016 10 30/3/2016 4 3/4/2016 0 3/4/2016 0 3/4/2016 7 10/4/2016 2 17/4/2016 0 17/4/2016 775 1/6/2018 16-CS-16-FBIH A 22/2/2016 14 7/3/2016 20/3/2016 - 20/3/2016 24/3/2016 25/3/2016 - 29/3/2016 0 - 0 5/4/2016 5/4/2016 30/6/2018 Developing and implementing a BEEP- communication campaign and P143580-CQ- P promotion activties for the energy Consultant service CS multi SS Post 8/8/2018 7 15/8/2018 6 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 27/8/2018 0 27/8/2018 0 29/8/2018 0 29/8/2018 ######## 16-CS-18-FBIH efficiency improvements in public buildings A 8/8/2018 7 15/8/2018 6 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 27/8/2018 0 27/8/2018 0 31/8/2018 0 31/8/2018 ######## BEEP- Other technical assistance and P143580-CQ- P Consultant service CS multi CQ Post 1/12/2017 14 15/12/2017 8 ######## 7 ######## 0 ######## 10 9/1/2018 4 13/1/2018 0 13/1/2018 0 13/1/2018 7 20/1/2018 2 27/1/2018 0 27/1/2018 ######## Trainings 17-CS-16-FBIH A #REF! Subtotal Allocated B To be allocated B Subtotal Subcomponent B Total A+B - allocated To be allocated TOTAL COMPONENT 2 COMPONENT 3 Proj ect management BEEP- P143580-IC- 01-CS-14- Project Coordinator Consultant service CS IC Prior 21/2/2014 7 28/2/2014 3/3/2014 12/3/2014 1 13/3/2014 1 14/3/2014 0 14/3/2014 0 12/3/2014 0 17/3/2014 ######## 16/12/2015 0 ######## 167 31/5/2016 FBIH/BEEP- P143580-IC- 001-FBIH IC Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 2/7/2018 ######## BEEP- P143580-IC- 02-CS-14- Procurement specialist Consultant service CS IC Prior 21/2/2014 7 28/2/2014 3/3/2014 12/3/2014 1 13/3/2014 1 14/3/2014 0 14/3/2014 0 12/3/2014 0 17/3/2014 ######## 16/12/2015 0 ######## 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 21/7/2018 9 30/7/2018 2/8/2018 2/8/2018 6/8/2018 0 6/8/2018 ######## BEEP- P143580-IC- Financial specialist Consultant service CS IC Prior 26/8/2015 18 13/9/2015 ######## ######## 1 ######## 7 ######## 1 ######## 3 ######## 1 ######## 7/1/2016 16/12/2015 0 ######## 167 31/5/2016 06-CS-14- Post 1/6/2016 0 1/6/2016 328 25/4/2017 Prior 21/4/2017 21/4/2017 1 22/4/2017 1 23/4/2017 0 26/4/2017 0 9/5/2017 0 9/5/2017 9/5/2017 11/5/2017 0 11/5/2017 ######## BEEP- P143580-IC- 04-CS-14- Technical Expert I Consultant service CS multi IC Prior 22/10/2014 14 5/11/2014 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 ######## 167 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 ######## BEEP- P143580-IC- Technical Expert II Consultant service CS multi IC Prior 22/10/2014 14 5/11/2014 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 ######## 167 31/5/2016 05-CS-14- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 2/7/2018 ######## BEEP- P143580-IC- Administrative assistant Consultant service CS IC Prior 22/10/2014 14 5/11/2014 7 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 ######## 167 31/5/2016 03-CS-14- FBIH/BEEP- Post 1/6/2016 0 1/6/2016 ######## BEEP- P143580-IC- Temporary Technical Expert Consultant service CS IC Post 10/8/2016 5 15/8/2016 16/8/2016 N/A N/A N/A N/A N/A 16/8/2016 N/A 23/8/2016 23/8/2016 ######## 44-CS-16-FBIH IC Post 20/2/2018 7 27/2/2018 27/2/2018 N/A N/A N/A N/A N/A 27/2/2018 N/A 28/2/2018 1/3/2018 121 30/6/2018 IC Post 21/7/2018 9 30/7/2018 0 1/8/2018 ######## 21/7/2018 9 30/7/2018 2/8/2018 2/8/2018 9/8/2018 1/9/2018 31/1/2019 BEEP- Financial Software for World P143580-SSS- P software SSS Prior 14/9/2015 7 21/9/2015 7 28/9/2015 7 5/10/2015 7 ######## 7 ######## 3 ######## 1 ######## 1 ######## 5 ######## 48 15/12/2015 0 ######## 30 15/1/2016 Bank Project 28-S-15-FBIH A 14/10/2015 0 14/10/2015 0 ######## 0 ######## 0 ######## 1 ######## 11 ######## 0 ######## 0 ######## 0 ######## 51 16/12/2015 ######## 30 15/1/2016 Incremental operating costs A Annual financial audit A Total component 3 - allocated To be allocated 1/9/2014 1398 30/6/2018 TOTAL COMPONENT 3 contarct Siganture Days Execution Days Execution Plan vs./ Actual Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Review Submis- No Invita- Bid- Evalu- No Contract Comple- date BEEP- Energy efficiency Project in Name of Cate Selection by Bank sion/ Start Ref no Note # Objection tion Opening ation & Objection Award tion Federation B&H December, 2013 Assignment/Contract gory Method Prior / Readiness Date Date Date Date Recomm. Date + PSC Date Date Post Date CLINICS BEEP-P143580- PACKAGE 1 University Clinical Center Works on reconstruction of W NCB Prior 1/5/2015 7 8/5/2015 3 11/5/2015 28 8/6/2015 14 22/6/2015 4 26/6/2015 5 1/7/2015 16 17/7/2015 0 17/7/2015 123 17/11/2015 1 NCB-29-W-15-FBIH Sarajevo Ortopedic and Traumatology Clinics A 29.04.2015. 03.05.2015. 13.05.2015. 09.06.2015. 30.06.2015. 08.07.2015. 18.12.2015. 18.12.2015. 02.03.2016. 30.06.2016. PACKAGE 2 LOT 1 - Psychiatric Hospital W 20/5/2015 7 27/5/2015 2 29/5/2015 28 26/6/2015 14 10/7/2015 7 17/7/2015 3 20/7/2015 11 31/7/2015 0 31/7/2015 114 22/11/2015 1 Mostar BEEP-P143580- Works on reconstruction of NCB Prior NCB-30-W-15-FBIH Clinics PACKAGE 2 LOT 2 - Health Centre Tuzla - W 20/5/2015 7 27/5/2015 2 29/5/2015 28 26/6/2015 14 10/7/2015 7 17/7/2015 3 20/7/2015 11 31/7/2015 0 31/7/2015 121 29/11/2015 1 Surgery Clinic A 14.05.2015. 18.05.2015. 21/5/2015 17.06.2015. 08.08.2015. 22.09.2015. 18.12.2015. 18.12.2015. 01.02.2016. 31.05.2016. CANTONS 2016. buildings BEEP-P143580- PACKAGE 3 - 2016. buildings (3 buildings) Works on reconstruction of Estimated Cost is P W NCB Post 18/4/2016 0 18/4/2016 0 18/4/2016 21 9/5/2016 5 14/5/2016 5 19/5/2016 2 21/5/2016 30 20/6/2016 0 20/6/2016 90 18/9/2016 1 NCB-31-W-16-FBIH (allocated) Sarajevo Canton from Design A 20/4/2016 21 12/5/2016 15/7/2016 N/A 15/7/2016 22/7/2016 1/8/2016 90 30/10/2016 BEEP-P143580- PACKAGE 5 - 2016. buildings (5 buildings) Works on reconstruction of Estimated Cost is P W NCB Post 18/4/2016 0 18/4/2016 0 18/4/2016 21 9/5/2016 5 14/5/2016 5 19/5/2016 2 21/5/2016 30 20/6/2016 0 20/6/2016 90 18/9/2016 1 NCB-33-W-16-FBIH (allocated) ZE-DO Canton from Design A 29/4/2016 21 20/5/2016 13/7/2016 N/A 13/7/2016 22/7/2016 8/8/2016 114 30/11/2016 PACKAGE 6 - LOT 1 - 2016. buildings (2 Estimated Cost is P W NCB Post 25/4/2016 0 25/4/2016 0 25/4/2016 21 16/5/2016 5 21/5/2016 5 26/5/2016 2 28/5/2016 30 27/6/2016 0 27/6/2016 90 25/9/2016 1 buildings) (allocated) from DEA BEEP-P143580- Works on reconstruction of NCB-34-W-16-FBIH HNK Canton PACKAGE 6 - LOT 2 - 2016. buildings (5 Estimated Cost is W NCB Post 25/4/2016 0 25/4/2016 0 25/4/2016 21 16/5/2016 5 21/5/2016 5 26/5/2016 2 28/5/2016 30 27/6/2016 0 27/6/2016 90 25/9/2016 1 buildings) (allocated) from DEA A LOT 1 27/5/2016 21 17/6/2016 14/7/2016 N/A 14/7/2016 25/7/2016 3/8/2016 139 20/12/2016 LOT 2 27/5/2016 21 17/6/2016 14/7/2016 N/A 14/7/2016 25/7/2016 8/8/2016 145 31/12/2016 TOTAL 2016. BUILDINGS CANTONS 2017. buildings BEEP-P143580- PACKAGE 7 2017. buildings (4 buildings) Works on reconstruction of P W NCB Post 1/7/2017 0 1/7/2017 0 1/7/2017 21 22/7/2017 5 27/7/2017 14 10/8/2017 2 12/8/2017 30 11/9/2017 0 11/9/2017 120 9/1/2018 1 NCB-35-W-16-FBIH (allocated) 4 objects in HNK Canton A 16/11/2017 7/12/2017 20/12/2017 20/12/2017 21/12/2017 9/1/2018 1/2/2018 180 31/7/2018 BEEP-P143580- PACKAGE 8 2017. buildings (5 buildings) Works on reconstruction of P W NCB Post 3/5/2017 0 3/5/2017 0 3/5/2017 21 24/5/2017 5 29/5/2017 14 12/6/2017 2 14/6/2017 30 14/7/2017 0 14/7/2017 120 11/11/2017 1 NCB-36-W-16-FBIH (allocated) 5 objects in ZE-DO Canton A 15/5/2017 21 5/6/2017 10/7/2017 10/7/2017 28/7/2017 22/8/2017 23/8/2017 240 20/4/2018 Works on reconstruction of BEEP-P143580- PACKAGE 9 2017. buildings (6 buildings) P 1 object in Canton Sarajevo W NCB Post 15/6/2017 0 15/6/2017 0 15/6/2017 21 6/7/2017 5 11/7/2017 14 25/7/2017 2 27/7/2017 30 26/8/2017 0 26/8/2017 120 24/12/2017 1 NCB-37-W-16-FBIH (allocated) & 5 federal level objects A 7/6/2017 21 28/6/2017 17/7/2017 17/7/2017 28/7/2017 22/8/2017 23/8/2017 162 1/2/2018 Works on reconstruction of BEEP-P143580- PACKAGE 10 2017. buildings (2 buildings) P 2 objects in Livanjski W NCB Post 3/5/2017 0 3/5/2017 0 3/5/2017 21 24/5/2017 5 29/5/2017 14 12/6/2017 2 14/6/2017 30 14/7/2017 0 14/7/2017 120 11/11/2017 1 NCB-38-W-16-FBIH (allocated) Canton A 22/5/2017 21 12/6/2017 10/7/2017 10/7/2017 28/7/2017 22/8/2017 23/8/2017 250 30/4/2018 BEEP-P143580- PACKAGE 11 2017. buildings (1 building) Works on reconstruction of P W NCB Post 15/7/2017 0 15/7/2017 0 15/7/2017 21 5/8/2017 5 10/8/2017 14 24/8/2017 2 26/8/2017 30 25/9/2017 0 25/9/2017 120 23/1/2018 1 NCB-44-W-16-FBIH (allocated) 1 object in Canton Sarajevo A 17/8/2017 21 7/9/2017 18/9/2017 18/9/2017 19/9/2017 4/10/2017 16/10/2017 242 15/6/2018 BEEP-P143580- PACKAGE 12 2017. buildings (1 building) Works on reconstruction of W NCB Post 27/6/2017 0 27/6/2017 0 27/6/2017 21 18/7/2017 5 23/7/2017 14 6/8/2017 2 8/8/2017 30 7/9/2017 0 7/9/2017 90 6/12/2017 NCB-45-W-16-FBIH (allocated) 1 object in ZE-DO Canton A 11/7/2017 21 1/8/2017 17/8/2017 17/8/2017 21/8/2017 12/9/2017 13/9/2017 90 12/12/2017 TOTAL 2017. BUILDINGS CANTONS 2018. buildings BEEP-P143580- PACKAGE 13 2018. buildings (3 buildings) Works on reconstruction of P W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 NCB-46-W-18-FBIH (allocated) 3 objects in HNK Canton A BEEP-P143580- PACKAGE 14 2018. buildings (5 buildings) Works on reconstruction of P W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 NCB-47-W-18-FBIH (allocated) 5 objects in ZE-DO Canton A BEEP-P143580- PACKAGE 15 2018. buildings (6 buildings) Works on reconstruction of P W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 NCB-48-W-18-FBIH (allocated) 3 object in Canton Sarajevo A TOTAL 2018. BUILDINGS CANTONS 2019. buildings BEEP-P143580- Works on reconstruction of NCB-479-W-19- PACKAGE 16 2019. buildings (allocated) W NCB Post 1/6/2019 0 1/6/2019 0 1/6/2019 21 22/6/2019 5 27/6/2019 14 11/7/2019 2 13/7/2019 30 12/8/2019 0 12/8/2019 90 10/11/2019 xxx objects in 2019. FBIH A TOTAL 2019. BUILDINGS Total works - Component 1 / Hospitals, Schools and Administrative buildings/ allocated #REF! to be allocated GOODS Purchasing and Instalation (Performance Monitoring System for measuring the BEEP-P143580-SH- temperature and humidity) (20+7=27 G SH Post 5/2/2016 2 7/2/2016 3 10/2/2016 14 24/2/2016 1 25/2/2016 3 28/2/2016 0 28/2/2016 0 28/2/2016 0 28/2/2016 20 19/3/2016 1 39-G-16-FBIH buildings) - 2016./2017. buldings (allocated) A 25.01.2016. 01.02.2016. 3/2/2016 3/2/2016 - 5/2/2016 8/2/2016 8/2/2016 105 23/5/2016 Purchasing and Instalation (Performance Monitoring System for measuring the heat BEEP-P143580-SH- energy usage) (20+7=27 buildings) - G SH Post 5/2/2016 2 7/2/2016 3 10/2/2016 14 24/2/2016 1 25/2/2016 3 28/2/2016 0 28/2/2016 0 28/2/2016 0 28/2/2016 20 19/3/2016 1 40-G-16-FBIH 2016./2017. buldings (allocated) A 25.01.2016. 01.02.2016. 3/2/2016 3/2/2016 - 5/2/2016 8/2/2016 8/2/2016 105 23/5/2016 Purchasing and Instalation (Performance Monitoring System for measuring the BEEP-P143580-SH- temperature and humidity) (for 19 buildings) - G SH Post 15/1/2017 0 15/1/2017 0 15/1/2017 7 22/1/2017 1 23/1/2017 3 26/1/2017 0 26/1/2017 0 26/1/2017 0 26/1/2017 30 25/2/2017 1 41-G-16-FBIH 2017. buldings (allocated) A 23/1/2017 0 23/1/2017 0 23/1/2017 7 30/1/2017 2 1/2/2017 0 1/2/2017 0 1/2/2017 0 16/2/2017 0 16/2/2017 30 18/3/2017 1 Purchasing and Instalation (Performance Monitoring System for measuring the heat BEEP-P143580-SH- energy usage) (for 19 buildings) - 2017. G SH Post 15/1/2017 0 15/1/2017 0 15/1/2017 7 22/1/2017 1 23/1/2017 3 26/1/2017 0 26/1/2017 0 26/1/2017 0 26/1/2017 30 25/2/2017 1 42-G-16-FBIH buldings (allocated) A 23/1/2017 0 23/1/2017 0 23/1/2017 7 30/1/2017 2 1/2/2017 0 1/2/2017 0 1/2/2017 0 16/2/2017 0 16/2/2017 30 18/3/2017 1 BEEP-P143580-SH- Purchasing of Motor Vechicle G SH Post 10/2/2016 8 18/2/2016 3 22/2/2016 14 22/2/2016 1 22/2/2016 3 - 0 7/3/2016 0 8/3/2016 0 8/3/2016 30 7/4/2016 1 43-G-16-FBIH (allocated) A 10/2/2016 8 18/2/2016 3 22/2/2016 14 22/2/2016 1 22/2/2016 3 - 0 7/3/2016 0 8/3/2016 0 8/3/2016 30 7/4/2016 1 Procure and install additional equipment of seasonal pellet tank with pellet transporter BEEP-P143580-SH- from pellet tank to pellet boiler to make it G SH Post 11/9/2017 0 11/9/2017 0 11/9/2017 14 25/9/2017 1 26/9/2017 3 29/9/2017 0 29/9/2017 0 29/9/2017 0 29/9/2017 20 19/10/2017 1 44-G-17-FBIH easier for beneficiaries for 7 public buildings (allocated) A 11/9/2017 0 11/9/2017 0 11/9/2017 7 18/9/2017 7 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 130 2/2/2018 Procure and install automatic regulation system for 11 objects as follows: a. Comprehensive automatic regulation system for 5 objects; BEEP-P143580-SH- b. Room temperature sensors with G SH Post 11/9/2017 0 11/9/2017 0 11/9/2017 14 25/9/2017 1 26/9/2017 3 29/9/2017 0 29/9/2017 0 29/9/2017 0 29/9/2017 20 19/10/2017 1 45-G-17-FBIH programming of existing controller with goal to make correction in line with interior temperature for 6 objects. A 11/9/2017 0 11/9/2017 0 11/9/2017 7 18/9/2017 7 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 202 15/4/2018 Purchasing and Instalation of Goods (for 5 BEEP-P143580-SH- buildings) - 2018. buldings G SH Post 11/1/2018 0 11/1/2018 0 11/1/2018 14 25/1/2018 1 26/1/2018 3 29/1/2018 0 29/1/2018 0 29/1/2018 0 29/1/2018 30 28/2/2018 1 46-G-18-FBIH (allocated) A TOTAL GOODS (Performance Monitoring System) 1 allocated #REF! to be allocated TOTAL COMPONENT 1 W+G