PROCUREMENT PLAN (Textual Part) Project information: P164551 - Mozambique Land Administration Project (Terra Segura) Project Implementation agency: FNDS Date of the Procurement Plan: April 8, 2018 Period covered by this Procurement Plan: 12 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The procedures to be followed for NCB shall be those set forth in the “Regulamento de Contratação de Empreitada de Obras Públicas, Fornecimento de Bens e Prestação de Serviços ao Estado” of the Republic of Mozambique of Março 08, 2016 (“the Regulation”), as per Decree No. 5/2016 , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). To be specified Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. To be detailed PROCUREMENT Mozambique : Mozambique Land Administration Project (Terra Segura) PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2018-04-10 2021-04-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164551 GPN Date: Project Name: Mozambique Land Administration Project (Terra Segura) Loan / Credit No: IDA / V1430, IDA / D4010 MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 49/MLAND/W/19 / Renovate Institutional Development Pending Single Stage - One 2022-01- the DINAT Data Center IDA / D4010 and Strengthening of the Post Request for Bids Open - National 550,000.00 0.00 Implementat 2020-09-28 2020-10-03 2020-11-14 2020-12-25 2021-01-31 Envelope 31 premises. Legal Framework ion 31/MLANDS/W/18 / Institutional Development Pending Construction of buildings for Single Stage - One 2021-12- IDA / V1430 and Strengthening of the Post Request for Bids Open - National 5,500,000.00 0.00 Implementat 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 Provincial and Regional Envelope 17 Legal Framework ion Offices GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14/MLAND/G/2018 / IT Project Management and Request for Single Stage - One IDA / V1430 Post Limited 40,000.00 42,435.61 Signed 2018-05-22 2018-06-12 2018-07-17 2018-06-27 2019-01-13 equipment Coordination Quotations Envelope 15/MFIP/G/2018 / Office Project Management and Request for Single Stage - One IDA / V1430 Post Limited 50,000.00 66,393.25 Signed 2018-06-04 2018-08-20 2018-07-30 2018-09-14 2019-01-26 equipment - Furniture Coordination Quotations Envelope 45/MLAND/G/19 / IT Project Management and Request for Single Stage - One IDA / D4010 Post Open - National 30,000.00 21,338.81 Signed 2019-06-25 2019-08-20 2019-09-11 2020-02-17 Equipament Coordination Quotations Envelope Project Management and Single Stage - One 13/MLAND/G/18 / Vehicles IDA / V1430 Post Request for Bids Open - National 350,000.00 138,396.78 Signed 2019-07-05 2019-08-19 2019-07-10 2019-08-21 2019-10-01 2019-09-20 2019-11-04 2019-10-25 2019-11-29 2020-04-22 Coordination Envelope 32/MLAND/W/2018 / Renovation of Data Center Institutional Development premises and purchase and Single Stage - One IDA / V1430 and Strengthening of the Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2020-05-04 2020-05-11 2020-06-22 2020-07-22 2020-08-26 2021-02-22 installation of hardware, Envelope Legal Framework security and licensing for DINAT Data Center 51/MLAND/G/19 / Purchase Institutional Development Pending Single Stage - One of generators for provincial IDA / D4010 and Strengthening of the Post Request for Bids Open - National 400,000.00 0.00 Implementati 2021-09-29 2021-10-14 2021-11-25 2021-12-27 2022-02-02 2022-08-02 Envelope and regional offices. Legal Framework on 13/MLAND/G/2020-1 / Project Management and Request for Single Stage - One IDA / V1430 Post Limited 75,000.00 73,279.06 Signed 2020-04-20 2020-03-04 2020-06-15 2020-03-24 2020-12-12 Acquisition of one vehicle. Coordination Quotations Envelope 22/MLAND/G/2018 / Institutional Development Pending Single Stage - One Purchase furniture for IDA / V1430 and Strengthening of the Post Request for Bids Open - National 900,000.00 0.00 Implementati 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 2023-04-03 Envelope Provincial and Regional offices Legal Framework on 20/MLAND/G/18 / ICT equipment and network Pending Systematic Land Single Stage - One installation and maintenance IDA / V1430 Prior Request for Bids Open - International 2,000,000.00 0.00 Implementati 2022-03-16 2022-03-21 2022-05-02 2022-06-01 2022-07-06 2023-01-02 Regularization Envelope for the new provincial and on regional offices 59/MLAND/G/2020 / Supply Contingent Emergency and Distribution of Emergency IDA / D4010 Prior Direct Selection Direct 9,400,000.00 0.00 Under Review 2020-10-20 2020-10-22 2020-10-30 2020-12-01 2020-12-04 2021-06-02 Response Component (CERC) Kit Seeds 24/MLAND/G/2020 / Institutional Development Under ACQUISITION OF ORTHO- Single Stage - One IDA / D4010 and Strengthening of the Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-12-21 2020-11-17 2020-12-28 2020-12-28 2021-02-12 2021-03-05 2021-04-23 2021-10-20 RECTIFIED HIGH-RESOLUTION Envelope Legal Framework on IMAGERY 67/MLAND/G/2021 / PRODUCTION AND SUPPLY OF GRAPHIC AND SERIGRAPHY Institutional Development Pending Request for Single Stage - One MATERIALS FOR THE PUBLIC IDA / D4010 and Strengthening of the Post Limited 60,000.00 0.00 Implementati 2021-03-03 2021-04-28 2021-06-27 Quotations Envelope HEARINGS IN THE SCOPE OF Legal Framework on THE REVISION OF THE NATIONAL LAND POLICY 38/MLAND/G/19 / Upgrade the capacity for processing and use of imagery and base Pending Systematic Land Single Stage - One map, purchase necessary IDA / V1430 Post Request for Bids Open - National 350,000.00 0.00 Implementati 2021-03-31 2021-04-05 2021-05-17 2021-06-16 2021-07-21 2022-01-17 Regularization Envelope hardware, software including on field equipment and training of personnel Institutional Development Pending 44/MLAND/G/20 / UN Agencies IDA / V1430 and Strengthening of the Post Direct 480,000.00 0.00 Implementati 2021-06-01 2021-06-06 2021-07-11 2022-01-07 Acquisition of vehicles (Direct) Legal Framework on 72/MLAND/G/2021 / Pending PURCHASE OF HOES FOR THE Contingent Emergency Single Stage - One IDA / D4010 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2021-02-26 2021-02-28 2021-04-11 2021-04-12 2021-05-08 2021-07-07 BENEFICIARIES OF THE SEED Response Component (CERC) Envelope on KITS 90/MLAND/G/21 / Institutional Development Pending Request for Single Stage - One PURCHASE OF OFFICE IDA / D4010 and Strengthening of the Post Limited 12,000.00 0.00 Implementati 2021-05-05 2021-06-30 2021-08-29 Quotations Envelope EQUIPMENT FOR CRPNT Legal Framework on Page 1 91/MLAND/G/21 / Institutional Development Pending PURCHASE OF Request for Single Stage - One IDA / D4010 and Strengthening of the Post Limited 8,500.00 0.00 Implementati 2021-05-05 2021-06-30 2021-08-29 COMMUNICATIN EQUIPMENT Quotations Envelope Legal Framework on FOR CRPNT 89/MLAND/G/21 / PURCHASE OF CONSTRUCTION Pending Systematic Land Request for Single Stage - One MATERIALS FOR IDA / D4010 Post Limited 13,000.00 0.00 Implementati 2021-05-13 2021-07-02 2021-08-01 Regularization Quotations Envelope DENSIFICATION OF GEODETIC on NETWORK 87/MLAND/G/21 / PURCHASE OF IT TECHNICAL Pending Systematic Land Request for Single Stage - One EQUIPMENT FOR IDA / D4010 Post Limited 2,100.00 0.00 Implementati 2021-05-17 2021-07-12 2021-08-11 Regularization Quotations Envelope DENSIFICATION OF EXISTING on GEODETIC NETWORK 88/MLAND/G/21 / PURCHASE OF CAMPING EQUIPMENT FOR Pending Systematic Land Request for Single Stage - One DENSIFICATION OF EXISTING IDA / D4010 Post Limited 7,200.00 0.00 Implementati 2021-05-17 2021-07-08 2021-08-07 Regularization Quotations Envelope GEODETIC NETWORK AND on DELIMITATION OF ADMINISTRATIVE BOUNDARIES 96/MLAND/G/21 / PURCHASE OF GENERATORS Pending FOR DENSIFICATION OF Systematic Land Request for Single Stage - One IDA / D4010 Post Limited 5,500.00 0.00 Implementati 2021-05-17 2021-07-12 2021-08-11 EXISTING GEODETIC NETWORK Regularization Quotations Envelope on AND DELIMITATION OF ADMINISTRATIVE BOUNDARIES NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/MLAND/NCS/2018 / Upgrade a capacity for processing and use of imagery and base map, Systematic Land Single Stage - One purchase necessary hardware, IDA / V1430 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-03-12 2019-03-17 2019-04-28 2019-05-28 2019-07-02 2019-12-29 Regularization Envelope software including field equipment and training of personnel and development of QAQC procedures 24/MLAND/NCS/2018 / Densification of existing Systematic Land Single Stage - One IDA / V1430 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-10-15 2019-10-21 2019-12-02 2020-01-01 2020-02-05 2020-08-03 Geodetic Network for selected Regularization Envelope project areas 57/MLAND/NCS/19 / Delimitation of communities and basic land use planning Pending and land regularization, Systematic Land Single Stage - One IDA / D4010 Prior Request for Bids Open - International 31,200,000.00 0.00 Implementati 2021-04-01 2021-04-16 2021-05-28 2021-06-27 2021-08-02 2022-08-02 parcels demarcation, Regularization Envelope on boundaries survey, preparation and issuance of DUATs - Phase II 29/MLAND/NCS/2018 / Delimitation of communities and basic land use planning Under and land regularization, Systematic Land Single Stage - One IDA / V1430 Prior Request for Bids Open - International 12,500,000.00 0.00 Implementati 2020-03-18 2020-06-17 2020-03-23 2020-07-22 2020-05-04 2020-08-31 2020-06-03 2021-03-09 2020-07-08 2021-01-04 parcels demarcation, Regularization Envelope on boundaries survey, preparation and issuance of DUATs - Phase I 23/MLAND/NCS/2018 / Acquisition of high resolution Systematic Land Single Stage - One IDA / V1430 Prior Request for Bids Open - International 5,300,000.00 0.00 Canceled 2020-03-02 2020-07-10 2020-03-07 2020-07-21 2020-04-18 2020-09-22 2020-05-18 2020-06-22 2020-12-19 orthorectified imagery (base Regularization Envelope map) 28/MLAND/CS/2018 / Public Pending Systematic Land Single Stage - One Information and Sensitization IDA / V1430 Post Request for Bids Open - National 1,800,000.00 0.00 Implementati 2020-05-31 2020-06-07 2020-07-19 2020-08-18 2020-10-01 2021-10-01 Regularization Envelope campaign on 24/MLAND/NCS/2020 / Institutional Development Under Single Stage - One Purchase of satelite imagery IDA / V1430 and Strengthening of the Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-04-30 2020-11-09 2020-05-05 2020-11-17 2020-06-16 2020-07-16 2020-08-20 2021-02-16 Envelope and training Legal Framework on 58/NCS/MOZBIO/2020 / Services for the launching Institutional Development Request for Single Stage - One ceremony of the auscultation IDA / D4010 and Strengthening of the Post Limited 47,000.00 40,441.14 Signed 2020-08-29 2020-07-10 2020-10-24 2020-07-15 2021-04-22 Quotations Envelope process of the land political Legal Framework national and land legislation 19/MLAND/NCS/2018 / CORS Network design, Institutional Development Under Single Stage - One Upgrade establishment IDA / V1430 and Strengthening of the Post Request for Bids Open - National 1,800,000.00 0.00 Implementati 2020-11-19 2020-11-19 2020-11-21 2021-02-01 2020-12-21 2021-01-20 2021-05-04 2025-10-09 Envelope capacity building during the Legal Framework on project time 23/MLAND/NCS/2020-1 / ACQUISITION OF HIGH Under Systematic Land Single Stage - One RESOLUTION ORTHO- IDA / V1430 Prior Request for Bids Open - International 5,300,000.00 0.00 Implementati 2021-03-01 2021-02-24 2021-03-11 2021-03-12 2021-04-29 2021-05-31 2021-07-12 2023-07-12 Regularization Envelope RECTIFIED AEREAL on PHOTOGRAPHY 77/MLAND/NCS/21 / Pending Contingent Emergency Single Stage - One CONTRACTING OF FIELD IDA / D4010 Post Request for Bids Open - International 500,000.00 0.00 Implementati 2021-04-15 2021-04-20 2021-06-01 2021-07-01 2021-08-05 2021-10-04 Response Component (CERC) Envelope CLEARING SERVICES on Page 2 54/MLAND/NCS/19 / Implementation of the new version of the Land Institutional Development Pending Information Management Single Stage - One IDA / D4010 and Strengthening of the Prior Request for Bids Open - International 4,200,000.00 0.00 Implementati 2021-04-16 2021-04-21 2021-06-02 2021-07-02 2021-08-06 2023-01-28 System (SiGIT), including web Envelope Legal Framework on portal, mobile app, interoperability, quality control and maintenance 79/MLAND/NCS/2021 / RECRUITMENT OF A FIRM FOR Pending Systematic Land Single Stage - One PRODUCTION OF IDA / D4010 Post Request for Bids Open - International 530,000.00 0.00 Implementati 2021-03-26 2021-03-31 2021-05-12 2021-06-11 2021-07-16 2022-01-12 Regularization Envelope COMMUNICATION MATERIALS- on PHASE 01 66/MLAND/NCS/21 / RECRUITMENT OF A SERVICE PROVIDER-2 FOR Institutional Development Pending DISSEMINATION OF THE IDA / D4010 and Strengthening of the Post Direct Selection Direct 20,000.00 0.00 Implementati 2021-05-03 2021-05-08 2021-06-12 2021-12-09 ACTIVITIES OF THE Legal Framework on COMMISSION FOR THE REVISION OF THE NATIONAL LAND POLICY. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/MLAND/CS/2018 / Land Consultant Information System (SIGIT) IDA / V1430 Post Qualification Open - International 150,000.00 0.00 Canceled 2018-06-06 2018-04-27 2018-06-27 2018-08-10 2018-09-09 2018-10-14 2019-04-12 Technical Review Selection 16/MLAND/CS/18 / Land Institutional Development Consultant information System (SIGIT) IDA / V1430 and Strengthening of the Post Qualification Open - International 150,000.00 190,562.30 Signed 2018-06-15 2018-04-18 2018-06-29 2018-08-13 2018-07-26 2018-09-12 2018-11-07 2018-10-17 2018-12-12 2019-04-15 technical review Legal Framework Selection 17/MLAND/CS/18 / Institutional Development Consultant Infrastructure needs IDA / V1430 and Strengthening of the Post Qualification Open - International 100,000.00 109,305.37 Signed 2018-06-20 2018-07-24 2018-07-11 2018-08-24 2018-07-24 2018-09-24 2018-08-31 2018-10-29 2018-09-21 2019-04-27 assessment Legal Framework Selection 10/MLAND/CS/2018 / Revision of the Land Systematic Land Quality And Cost- Legislation and land use IDA / V1430 Prior Open - International 500,000.00 443,102.90 Signed 2018-12-10 2018-12-06 2018-12-31 2019-01-14 2019-02-13 2019-03-28 2019-03-13 2019-06-24 2019-04-12 2019-07-05 2019-05-17 2019-07-15 2019-06-21 2019-09-26 2020-06-20 Regularization Based Selection planning (including consultations) 44/MLAND/CS/19 / Communities delimitation and Systematic Land Quality And Cost- IDA / D4010 Post Open - National 400,000.00 0.00 Canceled 2019-11-28 2019-12-19 2020-02-01 2020-02-29 2020-03-30 2020-05-04 2020-06-08 2021-06-08 land regularization quality Regularization Based Selection assurance and quality control 26/MLAND/CS/2018 / Institutional Development Consultant Interoperability of SiGIT and e- IDA / V1430 and Strengthening of the Post Qualification Open - National 250,000.00 0.00 Canceled 2019-07-02 2019-07-23 2019-09-05 2019-10-05 2019-11-09 2020-05-07 Government integration Legal Framework Selection 27/MLAND/CS/2018 / Institutional Development Consultant Redesign and upgrade of IDA / V1430 and Strengthening of the Post Qualification Open - National 200,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-08-20 SIGIT web-portal Legal Framework Selection 09/MLAND/CS/18 / Institutional Assessment and Consultant Consolidation Business Plan IDA / V1430 Post Qualification Open - National 150,000.00 0.00 Canceled 2018-05-31 2018-06-21 2018-08-04 2018-09-03 2018-10-08 2019-04-06 (1. Management / 2. Capacity Selection building) 39/MLAND/CS/19 / Institutional Development Consultant Development of a business IDA / D4010 and Strengthening of the Post Qualification Open - National 200,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 plan for land administration Legal Framework Selection institution 33/MLAND/IC/2018 / Development of DINAT's ICT Institutional Development Consultant Pending strategy and enterprise IDA / D4010 and Strengthening of the Post Qualification Open - National 125,000.00 0.00 2021-04-30 2021-05-21 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Implementation architecture towards the Legal Framework Selection centralized system 43/MLAND/CS/19 / External Project Management and Least Cost Pending IDA / D4010 Post Open - National 40,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-01 2021-11-01 2021-12-06 2022-01-10 2022-04-10 Audits Coordination Selection Implementation 41/MLAND/CS/19 / Design Institutional Development Consultant Pending the operationalization plan of IDA / D4010 and Strengthening of the Post Qualification Open - National 150,000.00 0.00 2021-02-28 2021-03-21 2021-05-06 2021-06-05 2021-07-10 2022-01-06 Implementation the land tax system Legal Framework Selection 38/MFIP/CS/18 / Redesign of Land Information Systematic Land Quality And Cost- Under IDA / V1430 Post Open - National 300,000.00 0.00 2020-03-03 2020-03-24 2020-03-24 2020-03-31 2020-05-07 2020-06-04 2020-07-04 2020-08-08 2020-09-12 2021-09-12 Management System (SiGIT), Regularization Based Selection Implementation including technical specifications 25/MLAND/CS/2018 / Consolidation, maintenance and upgrade of SiGIT software Institutional Development toward a centralized system Quality And Cost- IDA / V1430 and Strengthening of the Prior Open - International 3,800,000.00 0.00 Canceled 2019-10-01 2019-10-22 2019-12-05 2020-01-02 2020-02-03 2020-03-09 2020-04-13 2020-10-10 architecture (data quality, Based Selection Legal Framework increased volume data, high availability, communication and licenses cost) 42/MLAND/CS/19 / Independent Process Quality Assurance Entity (support of conflict resolution Systematic Land Quality And Cost- IDA / D4010 Post Open - National 493,750.00 0.00 Canceled 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 mechanism, training of Regularization Based Selection authorities, safeguard monitoring in communities (social impact) Page 3 60/MLAND/CS/2020 / CONSULTANCY SERVICES FOR INDEPENDENT VERIFICATION Consultant Contingent Emergency Under OF THE DISTRIBUTION OF THE IDA / D4010 Post Qualification Limited 75,000.00 0.00 2020-12-21 2021-02-01 2021-01-04 2021-01-08 2021-01-25 2021-02-24 Response Component (CERC) Implementation EMERGENCY SEED KITS IN Selection CABO DELGADO AND NAMPULA 55/MLAND/CS/19 / INSTITUTIONAL ASSESSMENT Institutional Development AND DEVELOPMENT OF Quality And Cost- Under IDA / D4010 and Strengthening of the Post Open - National 365,000.00 0.00 2021-08-20 2021-03-16 2021-09-10 2021-04-14 2021-10-24 2021-11-21 2021-12-21 2022-01-26 2022-03-02 2022-08-29 BUSINESS PLAN FOR A LAND Based Selection Implementation Legal Framework ADMINISTRATION INSTITUTION 61/MLAND/CS/2020 / CONSULTANCY SERVICES FOR SURVEY AND REGISTRATION Consultant Contingent Emergency Under OF CERIP ELIGIBLE IDA / D4010 Post Qualification Open - National 100,000.00 0.00 2021-01-08 2021-01-08 2021-01-29 2021-02-17 2021-03-14 2021-04-13 2021-05-18 2021-11-14 Response Component (CERC) Implementation BENEFICIARIES IN THE Selection PROVINCES OF NAMPULA AND CABO DELGADO 70/MLAND/CS/2021 / RECRUITMENT OF ASSOCIATIONS OF Consultant PARALEGALS/CIVIL SOCIETY Systematic Land Pending IDA / D4010 Post Qualification Limited 26,000.00 0.00 2021-03-01 2021-03-15 2021-04-14 2021-05-19 2021-08-17 ORGANIZATIONS FOR Regularization Implementation Selection TRAINING OF COMMUNITIES IN LAND USE RIGHTS IN NIASSA PROVINCE - PHASE 01 69/MLAND/CS/2021 / RECRUITMENT OF ASSOCIATION OF Consultant PARALEGALS/CIVIL SOCIETY Systematic Land Pending IDA / D4010 Post Qualification Limited 73,000.00 0.00 2021-03-01 2021-03-15 2021-04-14 2021-05-19 2021-08-17 ORGANIZATIONS FOR Regularization Implementation Selection TRAINING OF COMMUNITIES IN LAND USE RIGHTS IN MANICA PROVINCE-PHASE 01 64/MLAND/CS/2021 / RECRUITMENT OF ASSOCIATION OF Consultant PARALEGALS/CIVIL SOCIETY Systematic Land Pending IDA / D4010 Post Qualification Limited 32,000.00 0.00 2021-03-01 2021-03-15 2021-04-14 2021-05-19 2021-08-17 ORGANIZATION FOR Regularization Implementation Selection TRAINING OF COMMUNITIES IN LAND USE RIGHTS IN SOFALA PROVINCE - PHASE 01 65/MLAND/CS/2021 / RECRUITMENT OF ASSOCIATION OF PARALEGALS/CIVIL SOCIETY Consultant Systematic Land Pending ORGANIZATION FOR IDA / D4010 Post Qualification Limited 82,000.00 0.00 2021-03-01 2021-03-15 2021-04-14 2021-05-19 2021-08-17 Regularization Implementation TRAINING OF COMMUNITIES Selection IN LAND USE RIGHT IN NAMPULA PROVINCE - PHASE 01 63/MLAND/CS/2020 / RECRUITMENT OF ASSOCIATION OF PARALEGALS/CIVIL SOCIETY Consultant Systematic Land Pending ORGANIZATION FOR IDA / D4010 Post Qualification Open - National 108,000.00 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2021-09-07 Regularization Implementation TRAINING OF COMMUNITIES Selection IN LAND USE RIGHTS IN MAPUTO AND GAZA PROVINCES - PHASE 01 05/MLAND/CS/2020 / Institutional Development Consultant Design and supervision of Pending IDA / V1430 and Strengthening of the Post Qualification Open - National 75,000.00 0.00 2021-04-30 2021-05-21 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Renovation of DINAT Data Implementation Legal Framework Selection Center 21/MLAND/CS/2018 / Institutional Development Design and supervision works Quality And Cost- Pending IDA / V1430 and Strengthening of the Post Open - International 885,000.00 0.00 2021-03-31 2021-04-21 2021-06-04 2021-07-02 2021-08-01 2021-09-05 2021-10-10 2022-10-10 of buildings offices (Regional Based Selection Implementation Legal Framework & Provincial) 93/MLAND/CS/21 / Consultant HISTORICAL AND LEGACY Systematic Land Pending IDA / D4010 Post Qualification Limited 90,000.00 0.00 2021-05-03 2021-05-17 2021-06-16 2021-07-21 2022-01-17 DATA MIGRATION INTO NEW Regularization Implementation Selection SYSTEM 75/MLAND/CS/21-1 / INDEPENDENT QUALITY Consultant Systematic Land Under ASSURANCE ENTITY FOR IDA / D4010 Post Qualification Open - National 475,000.00 0.00 2021-03-26 2021-03-25 2021-04-10 2021-04-14 2021-04-16 2021-05-01 2021-05-25 2021-11-21 Regularization Implementation DELCOM/RDUAT PROCESS - Selection PHASE 01 75/MLAND/CS/2021 / INDEPENDENT QUALITY Systematic Land Quality And Cost- ASSURANCE ENTITY FOR IDA / D4010 Post Open - National 475,000.00 0.00 Canceled 2021-03-01 2021-02-12 2021-03-22 2021-02-25 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2022-09-05 Regularization Based Selection DELCOM/RDUAT PROCESS - PHASE 01 92/MLAND/CS/21 / RECRUITMENT OF AN NGO FOR TRAINING OF DISCTRICT Institutional Development Consultant AGENTS FOR FOR THE PUBLIC Pending IDA / D4010 and Strengthening of the Post Qualification Limited 115,000.00 0.00 2021-05-03 2021-05-17 2021-05-27 2021-07-01 2021-08-30 HEARING AT THE DISTRICT Implementation Legal Framework Selection LEVEL IN THE SCOPE OF THE REVISION OF THE LAND POLICY AND LAW INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Development Individual 02/MLAND/IC/18 / Social IDA / V1430 and Strengthening of the Post Consultant Open 75,000.00 0.00 Canceled 2018-04-26 2018-05-25 2018-06-14 2018-06-08 2018-07-05 2018-08-09 2019-02-05 Analysis Legal Framework Selection Page 4 Institutional Development Individual 03/MLAND/IC/2018 / IDA / V1430 and Strengthening of the Post Consultant Open 50,000.00 62,517.14 Signed 2018-04-25 2018-05-25 2018-06-13 2018-06-08 2018-07-04 2018-06-10 2018-08-08 2018-06-21 2019-02-04 Environment analysis Legal Framework Selection 04/MFIP/IC/2018 / Cadastral Institutional Development Individual Survey and Mapping needs IDA / V1430 and Strengthening of the Post Consultant Open 65,000.00 71,523.00 Signed 2018-05-24 2018-04-24 2018-07-12 2018-06-22 2018-08-02 2018-06-21 2018-09-06 2018-06-29 2019-03-05 assessment Legal Framework Selection Institutional Development Individual 06/MLAND/IC/18 / Economic IDA / V1430 and Strengthening of the Post Consultant Open 50,000.00 73,532.15 Signed 2018-06-12 2018-05-01 2018-07-31 2018-07-27 2018-08-21 2018-07-27 2018-09-25 2018-07-31 2019-03-24 and Financial Analysis (EFA) Legal Framework Selection 07/MLANDS/IC/208 / Design Individual the Communication Strategy IDA / V1430 Post Consultant Open 50,000.00 0.00 Canceled 2018-06-20 2018-08-08 2018-08-29 2018-10-03 2019-04-01 and Awareness Campaign Selection 01/MLAND/IC/18 / Individual Infrastructure Needs IDA / V1430 Post Consultant Open 100,000.00 0.00 Canceled 2018-05-23 2018-03-23 2018-07-11 2018-08-01 2018-09-05 2019-03-04 Assessment Selection 07/MLAND/CS/2018-2 / Design the Communication Systematic Land IDA / V1430 Post Direct Selection Direct 50,000.00 23,649.34 Signed 2018-12-10 2019-01-08 2018-12-20 2019-05-16 2019-02-23 2019-07-23 2019-08-22 Strategy and Awareness Regularization Campaign Individual 05/MFIP/IC/2018 / Project IDA / V1430 Post Consultant Open 50,000.00 0.00 Canceled 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 Implementation Manual (PIM) Selection 36/MLAND/IC/2018 / Individual Technical Assistanceto Systematic Land IDA / V1430 Post Consultant Open 40,000.00 0.00 Canceled 2019-01-09 2019-02-27 2019-03-20 2019-04-24 2019-10-21 develop RFBids for Regularization Selection Orthorectified imagery 30/MLAND/IC/2018 / Individual Technical Assistance to Systematic Land IDA / V1430 Post Consultant Open 40,000.00 49,512.50 Signed 2019-04-30 2019-02-28 2019-06-18 2019-07-16 2019-07-09 2019-07-16 2019-08-13 2019-07-16 2020-02-09 develop Request for Bids for Regularization Selection DELCOM/LTR contracts 08/MLAND/IC/2018 / E- Individual Government Legal Framework IDA / V1430 Post Consultant Open 25,000.00 0.00 Canceled 2018-05-24 2018-07-12 2018-08-02 2018-09-06 2019-03-05 Assessment Selection 35/MLAND/IC/2018 / Individual Technical Assistance to Systematic Land IDA / V1430 Post Consultant Open 40,000.00 0.00 Canceled 2018-12-17 2019-03-01 2019-02-04 2019-02-25 2019-04-01 2019-09-28 Develop Request forFBids for Regularization Selection the DELCOM/LTR Contracts Individual 48/MLAND/IC/19 / Project Management and IDA / V1430 Prior Consultant Open 72,000.00 0.00 Canceled 2019-11-29 2019-12-10 2020-01-17 2020-02-07 2020-03-13 2021-03-13 Procurement Specialist Coordination Selection Individual 37/MLAND/IC/19 / Project Management and IDA / V1430 Prior Consultant Open 96,000.00 0.00 Canceled 2019-03-29 2019-04-05 2019-06-03 2019-06-24 2019-07-29 2020-07-28 Procurement Specialist Coordination Selection 40/MLAND/IC/19 / Gender- Individual Based Violence (GBV) Project Management and Under IDA / D4010 Post Consultant Open 15,000.00 0.00 2020-05-31 2020-04-29 2020-07-19 2020-08-09 2020-09-13 2020-11-12 Assessment as part of Coordination Implementation Selection safeguards implementation. Individual 57/MLAND/IC/20 / Project Management and IDA / V1430 Prior Consultant Open 72,000.00 119,685.00 Signed 2020-05-29 2020-04-28 2020-07-20 2020-07-27 2020-08-10 2020-09-17 2020-09-13 2020-09-30 2021-03-12 Procurement Specialist Coordination Selection 71/MLAND/CS/2021 / LAND Institutional Development Individual Pending POLICY AND LEGISLATION IDA / D4010 and Strengthening of the Post Consultant Limited 44,000.00 0.00 2021-02-23 2021-02-28 2021-03-21 2021-04-25 2022-04-20 Implementation SPECIALIST Legal Framework Selection 73/MLAND/CS/2021 / Institutional Development Individual Pending ADMINISTRATIVE AND IDA / D4010 and Strengthening of the Post Consultant Limited 43,200.00 0.00 2021-02-23 2021-02-28 2021-03-21 2021-04-25 2022-04-20 Implementation FINANCIAL ASSISTANCE Legal Framework Selection Institutional Development Individual 74/MLAND/CS/2021 / HEAD Pending IDA / D4010 and Strengthening of the Post Consultant Limited 56,000.00 0.00 2021-02-23 2021-02-28 2021-03-21 2021-04-25 2021-04-28 OF TECHNICAL SECRETARIAT Implementation Legal Framework Selection 66/MLAND/IC/2021 / RECRUITMENT OF A CARTOGRAPHER FOR THE Systematic Land Pending IDA / D4010 Post Direct Selection Direct 9,000.00 0.00 2021-03-16 2021-03-26 2021-05-30 2021-08-28 NATIONAL DIRECTORATE FOR Regularization Implementation LAND AND TERRITORIAL DEVELOPMENT 62/MLAND/IC/2021-2 / RECRUITMENT OF A GEOGRAPHIC INFORMATION Systematic Land Pending SYSTEMS TECHNICIAN FOR IDA / D4010 Post Direct Selection Direct 15,000.00 0.00 2021-03-16 2021-03-26 2021-05-30 2023-05-30 Regularization Implementation THE NATIONAL DIRECTORATE FOR LAND AND TERRITORIAL DEVELOPMENT 56/MLAND/IC/2021 / RECRUITMENT OF A TOPOGRAPHER FOR THE Systematic Land Pending IDA / D4010 Post Direct Selection Direct 9,000.00 0.00 2021-03-16 2021-03-26 2021-05-30 2023-05-30 NATIONAL DIRECTORATE FOR Regularization Implementation LAND AND TERRITORIAL DEVELOPMENT 62/MLAND/IC/2021-1 / RECRUITMENT OF A GEOGRAPHIC INFORMATION Systematic Land Pending SYSTEMS TECHNICIAN FOR IDA / D4010 Post Direct Selection Direct 15,000.00 0.00 2021-03-16 2021-03-26 2021-05-30 2023-05-30 Regularization Implementation THE NATIONAL DIRECTORATE FOR LAND AND TERRITORIAL DEVELOPMENT Page 5 62/MLAND/IC/2021-3 / RECRUITMENT OF A GEOGRAPHIC INFORMATION Institutional Development Pending SYSTEMS TECHNICIAN FOR IDA / D4010 and Strengthening of the Post Direct Selection Direct 15,000.00 0.00 2021-03-16 2021-03-26 2021-05-30 2023-05-30 Implementation THE NATIONAL DIRECTORATE Legal Framework FOR LAND AND TERRITORIAL DEVELOPMENT 50/MLAND/IC/19 / Individual Development of QAQC Systematic Land Pending IDA / D4010 Post Consultant Open 100,000.00 0.00 2021-05-30 2021-07-18 2021-08-08 2021-09-12 2022-03-11 procedures for CENACARTA, Regularization Implementation Selection including training. 76/MLAND/CS/21 / Individual Project Management and Under RECRUITMENT OF A IDA / D4010 Post Consultant Open 90,000.00 0.00 2021-03-26 2021-04-23 2021-04-21 2021-05-06 2021-06-10 2022-06-10 Coordination Implementation PROCUREMENT SPECIALIST Selection 77/MLAND/CS/21 / Individual Project Management and Pending RECRUITMENT OF A LAND IDA / D4010 Post Consultant Limited 50,000.00 0.00 2021-03-26 2021-04-10 2021-05-01 2021-06-05 2021-06-08 Coordination Implementation ADMINISTRATION SPECIALIST Selection 78/MLAND/CS/21 / Individual Project Management and Pending ENVIRONMENTAL AND SOCIAL IDA / D4010 Post Consultant Limited 50,000.00 0.00 2021-03-26 2021-04-10 2021-05-01 2021-06-05 2022-05-31 Coordination Implementation & GRM SPECIALIST Selection 79/MLAND/CS/21 / Individual Project Management and Pending RECRUITMENT OF A IDA / D4010 Post Consultant Limited 40,000.00 0.00 2021-03-26 2021-03-31 2021-04-15 2021-05-14 2022-05-09 Coordination Implementation FINANCIAL ASSISTANT Selection 80/MLAND/CS/21 / LAND Individual Project Management and Pending ADMINISTRATION SPECIALIST IDA / D4010 Post Consultant Limited 50,000.00 0.00 2021-04-02 2021-04-07 2021-04-22 2021-05-21 2022-05-16 Coordination Implementation FOR GAZA PROVINCE Selection 81/MLAND/CS/21 / RECRUITMENT OF AN Individual Project Management and Pending ENVIRONMENTAL AND SOCIAL IDA / D4010 Post Consultant Limited 40,000.00 0.00 2021-04-02 2021-04-17 2021-05-02 2021-05-31 2022-05-26 Coordination Implementation ASSISTANT FOR GAZA Selection PROVINCE 82/MLAND/CS/21 / Individual FINANCIAL MANAGEMENT Project Management and Pending IDA / D4010 Post Consultant Limited 30,000.00 0.00 2021-04-02 2021-04-07 2021-04-22 2021-05-21 2022-05-16 ASSISTANT FOR THE Coordination Implementation Selection PROVINCE OF GAZA 83/MLAND/CS/21 / LAND Individual Project Management and Pending ADMINISTRATION SPECIALIST IDA / D4010 Post Consultant Limited 50,000.00 0.00 2021-04-02 2021-04-07 2021-04-22 2021-05-21 2022-05-16 Coordination Implementation FOR THE PROVINCE OF NIASSA Selection 84/MLAND/CS/21 / RECRUITMENT OF Individual Project Management and Pending ENVIRONMENTAL AND SOCIAL IDA / D4010 Post Consultant Limited 40,000.00 0.00 2021-04-02 2021-04-17 2021-05-02 2021-05-31 2022-05-26 Coordination Implementation ASSISTANT FOR NIASSA Selection PROVINCE 85/MLAND/CS/21 / Individual FINANCIAL MANAGEMENT Project Management and Pending IDA / D4010 Post Consultant Limited 30,000.00 0.00 2021-04-02 2021-04-07 2021-04-22 2021-05-21 2022-05-16 ASSISTANT FOR NIASSA Coordination Implementation Selection PROVINCE Page 6