PROCUREMENT Tajikistan : Strengthening Critical Infrastructure against Natural Hazards PLAN General Information Country: Tajikistan Banks Approval Date of the Original Procurement Plan: 2016-09-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2016-10-18 Project ID: P158298 GPN Date: Project Name: Strengthening Critical Infrastructure against Natural Hazards Loan / Credit No: IDA / V0220 Executing Agency(ies): STATE INSTITUTION "Project Implementation Unit for Acess to Green and Rural Development Finance" un WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCINHP/QCBS/2016-01 / Quality And Cost- Feasibility Study and Detail IDA / V0220 Prior Open - International 950,000.00 0.00 Under Review 2016-09-14 2016-10-05 2016-10-10 2016-11-18 2016-12-16 2017-01-15 2017-02-19 2017-03-26 2018-03-26 Based Selection Design for Bridges SCINHP/LCS/2016 / Project Pending IDA / V0220 Prior Least Cost Selection Open - International 20,500.00 0.00 2017-05-01 2017-05-22 2017-07-05 2017-08-02 2017-09-01 2017-10-06 2017-11-10 2018-05-09 Audit Implementation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCINHP/IC/2016-01 / Local Individual Consultant Pending Bridge Engineer Consultant (for IDA / V0220 Post Open 21,760.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Selection Implementation MoT) SCINHP/IC/2016-02 / Local Environmental Consultant for the Individual Consultant Pending IDA / V0220 Post Open 16,320.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 development of the EIA studies Selection Implementation for bridges rehabilitation (for MoT) SCINHP/IC/2016-03 / Local Individual Consultant Pending IDA / V0220 Post Open 16,320.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Social Consultant (for MoT) Selection Implementation SCINHP/IC/2016-04 / Local Flood Individual Consultant Pending IDA / V0220 Post Open 17,000.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Engineer Consultant (for ALRI) Selection Implementation SCINHP/IC/2016-05 / Local Environmental Consultant for the Individual Consultant Pending development of EIA and the RPF IDA / V0220 Post Open 16,320.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Selection Implementation studies for capital works for the flood protection (for ALRI) SCINHP/IC/2016-06 / Local Social Consultant for the Individual Consultant Pending development of EIA and the RPF IDA / V0220 Post Open 16,320.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Selection Implementation studies for capital works for the flood protection (for ALRI) SCINHP/IC/2016-07 / Project Individual Consultant Pending IDA / V0220 Post Open 20,400.00 0.00 2016-10-13 2016-12-01 2016-12-22 2017-01-26 2017-07-25 Coordinator (for MoF PIU) Selection Implementation SCINHP/IC/2016-08 / Internatonal Individual Consultant Pending consultant on flood management IDA / V0220 Prior Open 100,000.00 0.00 2016-10-20 2016-12-08 2016-12-29 2017-02-02 2017-08-01 Selection Implementation activities (for MoF PIU) Page 1