PROCUREMENT PLAN (Textual Part) Project information: India - Green National Highways Corridor Project (GNHCP) Project Number: P167350 Project Implementation agency: MoRTH Date of the Procurement Plan: 28th October 2019 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Project Procurement Strategy for Development (PPSD): PPSD is under preparation Procurement methods. Table 1 describes the various procurement methods to be used for activities financed by the loan. The thresholds indicated in Table 1 will apply to the initial 18 months of implementation and may be modified during project implementation based on procurement performance. Table 1: Procurement Methods Thresholds (US$ Procurement Approaches and Methods Equivalent) Open international (Goods, IT, and Non-consulting > 10 million services) Open national (Goods, IT, and Non-consulting up to 10 million services) National request for quotation (Goods/Works) Up to 100,000 Open international (Works) > 40 million Open national (Works) up to 40 million Thresholds (US$ Procurement Approaches and Methods Equivalent) Direct selection No threshold; For Goods / Works / Non- consulting services: According to paragraphs 6.8– 6.10 of the Regulations; For Consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 Procurement prior-review thresholds. The Bank will prior review contracts above the threshold indicated below: The Bank will prior review contracts above the threshold indicated below: a. Works including Supply & Installation of Plant and Equipment: All contracts more than US$ 15 million equivalent b. Goods and IT System: All contracts more than US$ 4 million equivalent c. Non-consulting services: All contracts more than US$ 4 million equivalent d. Consultants: All contracts (i) more than or equal to US$ 2 million equivalent for firms; and (i) more than or equal to US$ 400,000 equivalent for individuals e. In addition to above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: • procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulation; • competitive dialogue; • sustainable procurement; • selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and • best and final offer. National procurement procedure conditions (NPP conditions). National competition for the procurement of goods, works, and non-consulting services per established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the provisions contained in the loan agreement and the following provisions: a. Only the model bidding documents agreed with the World Bank (and as amended from time to time) shall be used for bidding. b. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. c. No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from any given state. d. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. e. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. f. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system g. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations h. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. j. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Use of GeM (Government e-Marketplace) will be allowed in lieu of RFQ (Request for Quotation) as per following details: a) up to INR 50,000 in catalog mode (viz. any available item could be selected by Implementing Agency without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. b) up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. c) up to INR equivalent of US$ 100,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. d) While making use of GeM portal, Borrower shall make use of Special Terms and Conditions meant for World Bank financed projects. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: is applicable for those contracts identified in the Procurement Plan tables Works: is not applicable Prior review by World Bank. In the case of contracts subject to prior review, the Implementing Agencies will seek the World Bank’s no objection before granting/agreeing to: (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; (c) any variation order or amendment (except in cases of extreme urgency) that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and (d) the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews of all the contracts financed under the loan. Even for Post Review cases, the inputs of Bank on Technical Specifications/TORs will be obtained by project. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: (i) a Procurement Plan and updates; (ii) an invitation for bids for goods and works for all contracts; (iii) request for expression of interest for selection/hiring of consulting services; (iv) contract awards of goods and works procured under international and national procedures; (v) a list of contracts/purchase orders placed under shopping procedures on a quarterly basis; (vi) a list of contracts under direct contracting (DC) on a quarterly basis; (vii) a monthly financial and physical progress report of all contracts; and (viii) an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: (a) an invitation for bids for procurement of goods and works using open international procedures, (b) contract award details of all procurement of goods and works using open international procedure, and (c) a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, IAs will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. Procurement Packages for key procurements – for 18 months (as per STEP) Request for Bids Bid Evaluation Specific Report Revie Market Estimated Procurem Signed Activity Reference No. Catego Procureme and w Approac Amount Contract / Description: ry nt Process ent Notice Recomme Type h (US$) ndation for Award Actual Planned Planned GNHCP_HP_NH-707_17 / Rehabilitation and Upgradation to Intermediate lane configuration of Gumma to Fediz Section (km Open - Single 13,730,0 2020/02/1 2020/03/3 1 95.000 to km 104.800) Prior Works Nation Stage Two 00 0 0 of NH-707 (Package-V) al Envelope in the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_15 / Rehabilitation and Upgradation to 2-lane of Bohrad to Bandli Section (km 50.000 to Open - Single 37,830,0 2019/12/1 2020/02/0 2020/03/2 2 km 75.000) of NH-707 Prior Works Nation Stage Two 00 3 3 3 (Package-III) in the al Envelope State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_1 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Bowdara - Open - Single Vizianagaram Section 14,000,00 2019/12/1 2020/02/1 2020/03/3 3 Prior Works Nation Stage Two (km 0.000 to km 0 3 0 0 al Envelope 26.937) of NH-516E (Package-VI) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode Request for Bids Bid Evaluation Specific Report Revie Market Estimated Procurem Signed Activity Reference No. Catego Procureme and w Approac Amount Contract / Description: ry nt Process ent Notice Recomme Type h (US$) ndation for Award Actual Planned Planned GNHCP_HP_NH-707_13 / Rehabilitation and Upgradation to 2- lane/2-lane with paved shoulders/4-lane configuration of Open - Single Paonta Sahib-Hewna 27,180,0 2019/12/0 2020/02/0 2020/03/1 4 Prior Works Nation Stage Two Section (km 000.000 00 1 2 9 al Envelope to km 25.000) of NH- 707 in the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_9 / Rehabilitation and Upgradation to 4-lane configuration of Asind - Mandal Section (km Open - Single 22,360,0 2019/12/2 2020/02/1 2020/03/3 5 74.000 to km 116.750) Prior Works Nation Stage Two 00 3 0 0 of NH-158 (Package-III) al Envelope in the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCPAP_NH-516E_3 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Gondiguda to Araku Open - Single Section (km 27.480 to 32,520,0 2019/12/1 2020/02/1 2020/03/3 6 Prior Works Nation Stage Two km 51.772) of NH- 00 3 0 0 al Envelope 516E (Package-V) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_16 / Rehabilitation and Open - Single Upgradation to 38,480,0 2019/12/1 2020/02/1 2020/03/2 7 Prior Works Nation Stage Two Intermediate lane 00 3 0 7 al Envelope configuration of Bandli to Gumma Section (km 75.000 to km 94.900) Request for Bids Bid Evaluation Specific Report Revie Market Estimated Procurem Signed Activity Reference No. Catego Procureme and w Approac Amount Contract / Description: ry nt Process ent Notice Recomme Type h (US$) ndation for Award Actual Planned Planned of NH-707 (Package- IV) in the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_8 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Beawar-Asind Section Open - Single 24,570,0 2019/12/2 2020/02/1 2020/03/3 8 (km 30.000 to km Prior Works Nation Stage Two 00 3 0 0 74.000) of NH-158 al Envelope (Package-II) in the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_14 / Rehabilitation and Upgradation to 2-lane of Hewna to Bohrad Section (km 25.000 to Open - Single 26,530,0 2019/12/0 2020/02/1 2020/03/3 9 km 50.000) of NH-707 Prior Works Nation Stage Two 00 6 0 0 (Package-II) in the al Envelope State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_7 / Rehabilitation and Upgradation to 4-lane configuration of Ras- Bewar Section (km Open - Single 36,220,0 2020/02/1 2020/03/3 10 0.000 to km 30.000) of Prior Works Nation Stage Two 00 0 0 NH-158 (Package-I) in al Envelope the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode Request for Bids Bid Evaluation Specific Report Revie Market Estimated Procurem Signed Activity Reference No. Catego Procureme and w Approac Amount Contract / Description: ry nt Process ent Notice Recomme Type h (US$) ndation for Award Actual Planned Planned GNHCP_AP_NH-516E_2 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Paderu to Gondiguda Open - Single 24,100,0 2019/12/1 2020/02/1 2020/03/3 11 Section (km 2.400 to Prior Works Nation Stage Two 00 3 0 0 km 27.480) of NH- al Envelope 516E (Package-IV) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode Quality and Cost Based Selection (QCBS), Fixed Budget Based Selection (FBBS), Least Cost Based Selection (LCBS) Revie Signed Categor Market Estimated Activity Contract Activity Reference No. / Description: w y Approach Amount (US$) Status Type Planned GNHCP_HP_NH-707_AE_28 / Procurement of Consultancy Services of Authority’s Engineer for the work of Consulta Open - "Rehabilitation and Upgradation of Cleare 2020/04/ 1 Prior nt Internatio 4,370,000.00 Paonta Sahib-Gumma-Fediz Section d 18 Services nal (km 000.000 to km 104.800) of NH- 707" in the State of Himachal Pradesh under GNHCP GNHCP_RAJ_NH-158_AE_26 / Procurement of Consultancy Services of Authority’s Engineer for the work of Consulta Open - Cleare 2020/05/ 2 "Rehabilitation and Upgradation of Ras- Prior nt Internatio 2,500,000.00 d 12 Beawar-Asind-Mandal Section (km Services nal 0.000 to km 116.750) of NH-158" in the State of Rajasthan under GNHCP GNHCP_AP_NH-516E_AE_24 / Consultancy Services of Authority’s Engineer for the work of "Rehabilitation Consulta Open - and Upgradation of Bowdara- Cleare 2020/04/ 3 Prior nt Internatio 2,120,000.00 Vizianagram (km 0.000 to km 26.937) d 19 Services nal and Paderu-Araku (km 2.400 to km 51.772) Section of NH-516E" in the State of Andhra Pradesh under GNHCP PROCUREMENT India : Green National Highways Corridor Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2019-11-07 2021-10-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167350 GPN Date: 2019-10-31 Project Name: Green National Highways Corridor Project Loan / Credit No: / , IBRD / 90620 M Executing Agency(ies): inistry of Road Transport and Highways WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GNHCP_HP_NH-707_13 / Rehabilitation and Upgradation to 2-lane/2-lane with paved shoulders/4-lane configuration of Paonta Sahib- Green Highway Corridor Single Stage - Two 27,180,000.0 23,787,344. 2022-03- Hewna Section (km 000.000 / Improvement and Prior Request for Bids Open - National Signed 2019-11-07 2019-11-26 2019-11-14 2019-12-01 2019-12-29 2020-06-17 2020-02-02 2020-09-01 2020-03-19 2021-03-17 Envelope 0 46 19 to km 25.000) of NH-707 in Maintenance the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_14 / Rehabilitation and Upgradation to 2-lane of Hewna to Bohrad Section (km Green Highway Corridor 25.000 to km 50.000) of NH- Single Stage - Two 26,530,000.0 20,536,815. 2022-03- / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-11-26 2019-11-22 2019-12-06 2020-01-06 2020-06-19 2020-02-10 2020-09-03 2020-03-30 2021-02-16 707 (Package-II) in the State Envelope 0 40 30 Maintenance of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_15 / Rehabilitation and Upgradation to 2-lane of Bohrad to Bandli Section (km Green Highway Corridor Under 50.000 to km 75.000) of NH- Single Stage - Two 37,830,000.0 2020-06- / Improvement and Prior Request for Bids Open - National 0.00 Implementat 2019-11-08 2019-12-12 2019-11-15 2019-12-13 2019-12-30 2020-06-22 2020-02-03 2020-08-25 2020-03-23 707 (Package-III) in the State Envelope 0 04 Maintenance ion of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_16 / Rehabilitation and Upgradation to Intermediate lane configuration of Bandli to Green Highway Corridor Under Gumma Section (km 75.000 to Single Stage - Two 38,480,000.0 32,780,486. 2022-03- / Improvement and Prior Request for Bids Open - National Implementat 2019-11-15 2019-12-12 2019-11-22 2019-12-13 2020-01-06 2020-06-24 2020-02-10 2020-08-24 2020-03-27 km 94.900) of NH-707 Envelope 0 25 27 Maintenance ion (Package-IV) in the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_7 / Rehabilitation and Upgradation to 4-lane configuration of Ras-Bewar Green Highway Corridor Under Section (km 0.000 to km Single Stage - Two 36,220,000.0 2022-09- / Improvement and Prior Request for Bids Open - National 0.00 Implementat 2019-11-15 2020-08-12 2019-11-22 2020-08-25 2020-01-06 2020-10-21 2020-02-10 2021-04-19 2020-03-30 30.000) of NH-158 (Package- Envelope 0 26 Maintenance ion I) in the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_8 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration Green Highway Corridor of Beawar-Asind Section (km Single Stage - Two 24,570,000.0 17,342,048. 2022-03- / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-12-20 2019-11-22 2019-12-23 2020-01-06 2020-06-02 2020-02-10 2020-08-10 2020-03-30 2020-11-16 30.000 to km 74.000) of NH- Envelope 0 55 30 Maintenance 158 (Package-II) in the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_RAJ_NH-158_9 / Rehabilitation and Upgradation to 4-lane configuration of Asind - Green Highway Corridor Mandal Section (km 74.000 to Single Stage - Two 22,360,000.0 15,773,906. 2022-03- / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-12-20 2019-11-22 2019-12-23 2020-01-06 2020-06-04 2020-02-10 2020-08-10 2020-03-30 2020-11-16 km 116.750) of NH-158 Envelope 0 29 30 Maintenance (Package-III) in the State of Rajasthan under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_1 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Bowdara - Vizianagaram Green Highway Corridor Single Stage - Two 14,000,000.0 11,106,060. 2021-09- Section (km 0.000 to km / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-12-09 2019-11-22 2019-12-13 2020-01-06 2020-06-11 2020-02-10 2020-08-11 2020-03-30 2020-10-27 Envelope 0 59 28 26.937) of NH-516E (Package- Maintenance VI) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_2 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Paderu to Gondiguda Green Highway Corridor Single Stage - Two 24,100,000.0 18,318,925. 2022-03- Section (km 2.400 to km / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-12-09 2019-11-22 2019-12-13 2020-01-06 2020-07-30 2020-02-10 2020-09-11 2020-03-30 2020-12-09 Envelope 0 41 30 27.480) of NH-516E (Package- Maintenance IV) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode Page 1 GNHCPAP_NH-516E_3 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Gondiguda to Araku Green Highway Corridor Single Stage - Two 32,520,000.0 25,887,545. 2022-03- Section (km 27.480 to km / Improvement and Prior Request for Bids Open - National Signed 2019-11-15 2019-12-09 2019-11-22 2019-12-13 2020-01-06 2020-07-31 2020-02-10 2020-09-14 2020-03-30 2020-10-22 Envelope 0 69 30 51.772) of NH-516E (Package- Maintenance V) in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-707_17 / Rehabilitation and Upgradation to Intermediate lane configuration of Gumma Green Highway Corridor Under to Fediz Section (km 95.000 Single Stage - Two 13,730,000.0 2021-09- / Improvement and Prior Request for Bids Open - National 0.00 Implementat 2019-11-15 2021-07-25 2019-11-22 2021-08-23 2020-01-06 2020-02-10 2020-03-30 to km 104.800) of NH-707 Envelope 0 28 Maintenance ion (Package-V) in the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_UP_NH-730C_20 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration Green Highway Corridor of Bewar-Allahganj Section Single Stage - Two 34,600,000.0 Under 2022-03- IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 2020-05-13 2021-02-10 2020-05-20 2021-03-30 2020-07-04 2021-06-22 2020-08-08 2020-09-26 (Km 0.000 to Km 52.770) of Envelope 0 Review 27 Maintenance NH-730C in the State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_UP_NH-730C_21 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Allahganj-Miranpur Katra Green Highway Corridor Under Single Stage - Two 33,530,000.0 2022-03- Section (Km 52.770 to Km IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-13 2021-02-10 2020-05-20 2021-03-30 2020-07-04 2021-06-23 2020-08-08 2020-09-26 Envelope 0 27 114.000) of NH-730C in the Maintenance ion State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_UP_NH-730C_22 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Miranpur Katra to Radhaita Green Highway Corridor Under Single Stage - Two 19,258,000.0 2022-03- Section (Km 114.000 to Km IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-15 2021-02-10 2020-05-22 2021-03-30 2020-07-06 2021-06-24 2020-08-10 2020-09-28 Envelope 0 29 137.250) of NH-730C in the Maintenance ion State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_UP_NH-731K_23 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration Green Highway Corridor of Radhaita to Pilibhit Section Single Stage - Two 21,986,000.0 Under 2022-03- IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 2020-05-15 2021-02-10 2020-05-22 2021-03-30 2020-07-06 2021-06-25 2020-08-10 2020-09-28 (Km 137.250 to Km 183.380) Envelope 0 Review 29 Maintenance of NH-731K in the State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_4 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Koyyuru to Chaprathipalem Green Highway Corridor Under Single Stage - Two 38,396,000.0 2022-03- section (Km 120+000 to Km IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-14 2021-09-30 2020-05-21 2021-10-11 2020-07-05 2020-08-09 2020-09-27 Envelope 0 28 165+500) of NH-516E in the Maintenance ion State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_5 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Chaprathipalem to Green Highway Corridor Single Stage - Two 34,119,000.0 Under 2022-03- Lambasingi section (Km IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 2020-05-14 2021-09-30 2020-05-21 2020-07-05 2020-08-09 2020-09-27 Envelope 0 Review 28 165+500 to Km 205+000) of Maintenance NH-516E in the State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_AP_NH-516E_6 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Lambasingi to Paderu Green Highway Corridor Under Single Stage - Two 39,732,000.0 2022-03- section (Km 205+000 to Km IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-14 2021-09-30 2020-05-21 2020-07-05 2020-08-09 2020-09-27 Envelope 0 28 253+010) of NH-516E in the Maintenance ion State of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_UP_NH-92_18 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration Green Highway Corridor Under of Bewar-Near Karri Village Single Stage - Two 25,986,000.0 2022-03- IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-16 2021-09-09 2020-05-23 2021-09-15 2020-07-07 2020-08-11 2020-09-29 Section (Km 0.000 to Km Envelope 0 30 Maintenance ion 30.000) of NH-92 in the State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode Page 2 GNHCP_UP_NH-92_19 / Rehabilitation and Upgradation to 2-lane with paved shoulders configuration Green Highway Corridor of Near Karri Village - Etawah Single Stage - Two 23,158,000.0 Under 2022-03- IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 2020-05-16 2020-05-23 2020-07-07 2020-08-11 2020-09-29 Section (Km 30.000 to Km Envelope 0 Review 30 Maintenance 57.346) of NH-92 in the State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-70_10 / Rehabilitation and Upgradation to 2-lane / 2- lane with paved shoulders configuration of Hamirpur- Green Highway Corridor Under Single Stage - Two 39,898,000.0 2022-03- Karnohal Section (Km 141.000 IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-12 2021-09-10 2020-05-19 2021-10-01 2020-07-03 2020-08-07 2020-09-25 Envelope 0 26 to Km 181.000) of NH-70 in Maintenance ion the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-70_11 / Rehabilitation and Upgradation to 2-lane / 2- lane with paved shoulders configuration of Karnohal - Green Highway Corridor Under Single Stage - Two 27,568,000.0 2022-03- Kalwahn Section (Km 181.000 IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2020-05-12 2021-09-10 2020-05-19 2020-07-03 2020-08-07 2020-09-25 Envelope 0 26 to Km 208.950) of NH-70 in Maintenance ion the State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-70_12 / Rehabilitation and Upgradation to 2-lane / 2- lane with paved shoulders configuration of Kalwahn - Green Highway Corridor Single Stage - Two 34,018,000.0 2022-03- Mandi Section (Km 181.000 to IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Canceled 2020-05-13 2020-05-20 2020-07-04 2020-08-08 2020-09-26 Envelope 0 27 Km 208.950) of NH-70 in the Maintenance State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GNHCP_HP_NH-70-12 / Rehabilitation and Upgradation to 2-lane configuration of Kalwahn - Green Highway Corridor Under Mandi Section (Km 208.950 to Single Stage - Two Other (with field 34,018,000.0 2023-05- IBRD / 90620 Improvement and Prior Request for Bids Open - National 0.00 Implementat 2021-07-14 2021-09-10 2021-07-21 2021-09-04 2021-10-09 2021-11-27 km 250.592) of NH-70 in the Envelope for explanation) 0 28 Maintenance ion State of Himachal Pradesh under Green National Highways Corridor Project (GNHCP) on EPC mode GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GNHCP_HP_NH-707_AE_28 / Procurement of Consultancy Services of Authority’s Engineer for the work of "Rehabilitation and Green Highway Corridor Quality And Cost- Upgradation of Paonta Sahib- / Improvement and Prior Open - International 4,370,000.00 1,868,758.50 Signed 2019-11-14 2019-11-13 2019-12-14 2020-04-29 2020-01-20 2020-08-11 2020-01-20 2020-10-12 2020-02-04 2020-12-15 2020-02-29 2021-01-20 2020-04-18 2021-02-18 2022-04-18 Based Selection Gumma-Fediz Section (km Maintenance 000.000 to km 104.800) of NH-707" in the State of Himachal Pradesh under GNHCP GNHCP_AP_NH-516E_AE_24 / Consultancy Services of Authority’s Engineer for the work of "Rehabilitation and Upgradation of Bowdara- Green Highway Corridor Quality And Cost- Vizianagram (km 0.000 to km / Improvement and Prior Open - International 2,120,000.00 2,400,168.46 Signed 2019-11-15 2020-04-21 2019-12-15 2020-04-29 2020-01-21 2020-08-18 2020-01-21 2020-10-08 2020-02-05 2020-11-09 2020-03-01 2020-12-29 2020-04-19 2021-02-05 2022-04-19 Based Selection 26.937) and Paderu-Araku Maintenance (km 2.400 to km 51.772) Section of NH-516E" in the State of Andhra Pradesh under GNHCP GNHCP_RAJ_NH-158_AE_26 / Procurement of Consultancy Services of Authority’s Engineer for the work of Green Highway Corridor "Rehabilitation and Quality And Cost- / Improvement and Prior Open - International 2,500,000.00 2,723,762.98 Signed 2019-11-15 2020-04-21 2019-12-15 2020-04-29 2020-02-13 2020-08-11 2020-02-13 2020-10-09 2020-02-28 2020-11-18 2020-03-24 2021-01-07 2020-05-12 2021-02-11 2022-05-12 Upgradation of Ras-Beawar- Based Selection Maintenance Asind-Mandal Section (km 0.000 to km 116.750) of NH- 158" in the State of Rajasthan under GNHCP Page 3 GNHCP-NGO-RJ-1 / Consultancy Services for Implementation of the Resettlement Action Plan (RAP) for “Rehabilitation and Green Highway Corridor Upgrading to 2 lanes/2 lane Quality And Cost- / Improvement and Prior Open - International 71,500.00 0.00 Canceled 2020-03-25 2020-04-21 2020-04-01 2020-04-29 2020-05-15 2020-06-12 2020-06-26 2020-07-31 2020-09-04 2021-09-04 with paved shoulders Based Selection Maintenance Configuration and Strengthening of Ras – Beawar – Asind – Mandal Section (from km 0.000 to km 116.750) o GNHCP-NGO-AP_516-4 / Consultancy Services for Implementation of the Resettlement Action Plan Green Highway Corridor (RAP) for “Rehabilitation and Quality And Cost- IBRD / 90620 Improvement and Post Open - National 71,500.00 114,591.46 Signed 2020-05-04 2020-05-08 2020-05-25 2020-08-29 2020-07-08 2020-10-20 2020-08-05 2021-01-19 2020-09-04 2021-04-05 2020-10-09 2021-05-17 2020-11-13 2021-08-04 2021-11-13 Upgradation to 2-lane with Based Selection Maintenance paved shoulders configuration of Bowdara-Vizianagaram and Paderu-Araku Section of NH- 516E in AP". GNHCP_AP_NH-516E_AE_25 / Consultancy Services for Authority’s Engineer for “Rehabilitation and Upgradation to 2-lane with Green Highway Corridor Quality And Cost- paved shoulders configuration IBRD / 90620 Improvement and Prior Open - International 2,245,000.00 0.00 Under Review 2020-05-16 2020-07-27 2020-06-15 2020-10-07 2020-07-22 2021-09-06 2020-07-22 2020-08-06 2020-08-31 2020-10-19 2022-10-19 Based Selection of Koyyuru- Paderu (km Maintenance 120+000 to km 253+010) Section of NH-516E in the State of Andhra Pradesh under GNHCP on EPC mode GNHCP_HP_NH-70_AE_27 / Consultancy Services for Authority’s Engineer for “Rehabilitation and Upgradation to 2-lane/2-lane Green Highway Corridor Quality And Cost- with paved shoulders IBRD / 90620 Improvement and Prior Open - International 2,030,000.00 0.00 Canceled 2020-05-11 2020-06-01 2020-06-10 2020-07-17 2020-07-17 2020-08-01 2020-08-26 2020-10-14 2022-10-14 Based Selection configuration of Hamirpur- Maintenance Mandi Section (Km 141.000 to Km 208.950) of NH-70 in Himachal Pradesh under GNHCP on EPC mode GNHCP_HP_NH-70-AE-27 / Consultancy Services for Authority’s Engineer for “Rehabilitation and Upgradation to 2-lane/2-lane Green Highway Corridor Quality And Cost- Under with paved shoulders IBRD / 90620 Improvement and Prior Open - International 2,030,000.00 0.00 2020-08-06 2020-08-06 2020-08-06 2020-08-07 2020-10-05 2021-10-08 2020-10-05 2020-10-20 2020-11-14 2021-01-02 2023-01-02 Based Selection Implementation configuration of Hamirpur- Maintenance Mandi Section (Km 141.000 to Km 208.950) of NH-70 in Himachal Pradesh under GNHCP on EPC mode GNHCP_PMC / Project Management Consultancy Services for Rehabilitation and Upgradation of National Green Highway Corridor Highways in the states of Quality And Cost- IBRD / 90620 Improvement and Prior Open - International 4,850,000.00 3,999,370.71 Signed 2020-08-11 2020-08-19 2020-09-01 2020-09-22 2020-10-15 2021-01-17 2020-11-12 2021-04-06 2020-12-12 2021-05-20 2021-01-16 2021-06-22 2021-02-20 2021-07-27 2022-02-20 Himachal Pradesh, Rajasthan, Based Selection Maintenance Uttar Pradesh and Andhra Pradesh with the loan assistance of World Bank under GNHCP. GNHCP_UP_NH-92_AE_29 / Authority’s Engineer for “Rehabilitation and Upgradation of Bewar-Near Karri Village (Km 0 to Km 30) Green Highway Corridor Quality And Cost- Under & Near Karri Village-Etawah IBRD / 90620 Improvement and Post Open - International 1,670,000.00 0.00 2020-10-09 2020-10-07 2020-11-08 2020-11-03 2020-12-15 2021-04-11 2020-12-15 2020-12-30 2021-01-24 2021-03-14 2023-03-14 Based Selection Implementation (Km 30to Km 57.346) section Maintenance of NH-92 and Bewar- Allahganj (Km 0 to Km 52.7) Section of NH-730C in UP under GNHCP GNHCP_UP_NH-730_AE_30 / Authority’s Engineer for “Rehabilitation and Upgradation Allahganj- Miranpur Katra (Km 52.7 to Green Highway Corridor Quality And Cost- Under Km 114) & Miranpur Katra- IBRD / 90620 Improvement and Post Open - International 1,500,000.00 0.00 2020-10-09 2020-10-07 2020-11-08 2020-11-03 2020-12-15 2020-12-15 2020-12-30 2021-01-24 2021-03-14 2023-03-14 Based Selection Implementation Radhaita (Km 114 to Km Maintenance 137.2) Section of NH-730C and Radhaita-Pilibhit (Km 137.2 to Km 183.3) Section of NH-731 in UP under GNHCP GNHCP_IAC / Internal Audit Consultancy Services for “Rehabilitation and Upgrading of stretches of various Green Highway Corridor National Highways in the Quality And Cost- Under IBRD / 90620 Improvement and Post Open - International 1,800,000.00 362,866.32 2020-10-26 2020-10-26 2020-11-25 2020-11-03 2021-01-01 2021-05-12 2021-01-01 2021-03-30 2021-01-16 2021-05-12 2021-02-10 2021-06-11 2021-03-31 2023-03-31 states of Rajasthan, Himachal Based Selection Implementation Maintenance Pradesh, Uttar Pradesh and Andhra Pradesh under Green National Highways Corridor Projects (GNHCP)" GNCHP_TAC / Technical Audit Consultancy (TAC) for “Rehabilitation and Upgrading to 2-lanes/2-lane with paved Green Highway Corridor Quality And Cost- shoulders/4 lane IBRD / 90620 Improvement and Post Open - International 1,250,000.00 0.00 Canceled 2020-12-04 2020-12-04 2021-01-03 2021-01-19 2021-02-09 2021-02-09 2021-02-24 2021-03-21 2021-05-09 2023-05-09 Based Selection configuration from Maintenance single/intermediate lane and strengthening of stretches under GNHCP & NHIIP Page 4 GNCHP-TAC / Technical Audit Consultancy (TAC) for “Rehabilitation and Upgrading to 2-lanes/2-lane with paved Green Highway Corridor Quality And Cost- Under shoulders/4 lane IBRD / 90620 Improvement and Post Open - International 1,850,000.00 0.00 2021-04-07 2021-04-07 2021-05-07 2021-07-20 2021-06-13 2021-08-17 2021-06-13 2021-06-28 2021-07-23 2021-09-10 2023-09-10 Based Selection Implementation configuration from Maintenance single/intermediate lane and strengthening of stretches under GNHCP & NHIIP GNHCP-NGO-UP_730-7 / Consultancy Services for Implementation of the Resettlement Action Plan Green Highway Corridor (RAP) for “Rehabilitation and Quality And Cost- IBRD / 90620 Improvement and Post Open - National 72,000.00 0.00 Canceled 2020-05-04 2021-05-24 2020-05-25 2021-06-29 2020-07-08 2020-08-05 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Upgradation to 2-lane with Based Selection Maintenance paved shoulders configuration of Bewar-Pilibhit Section of NH-730C & NH-731K in the State of UP". GNHCP-NGO-UP_92-6 / Consultancy Services for Implementation of the Resettlement Action Plan Green Highway Corridor Quality And Cost- (RAP) for “Rehabilitation and IBRD / 90620 Improvement and Post Open - National 71,500.00 0.00 Canceled 2020-05-04 2021-05-26 2020-05-25 2020-07-08 2020-08-05 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Based Selection Upgradation to 2-lane with Maintenance paved shoulders configuration of Bewar-Etawah Section of NH-92 in the State of UP". GNHCP-NGO-AP_516-5 / Consultancy Services for Implementation of the Resettlement Action Plan Green Highway Corridor Quality And Cost- (RAP) for “Rehabilitation and IBRD / 90620 Improvement and Post Open - National 71,500.00 0.00 Canceled 2020-05-04 2021-05-26 2020-05-25 2021-06-29 2020-07-08 2020-08-05 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Based Selection Upgradation to 2-lane with Maintenance paved shoulders configuration of Koyyuru-Paderu Section of NH-516E in the State of AP". GNHCP-NGO-HP_70-3 / Consultancy Services for Implementation of the Resettlement Action Plan Green Highway Corridor (RAP) for “Rehabilitation and Quality And Cost- IBRD / 90620 Improvement and Post Open - National 71,000.00 0.00 Canceled 2020-05-04 2020-05-28 2020-05-25 2021-06-29 2020-07-08 2020-08-05 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Upgradation to 2-lane/2-lane Based Selection Maintenance with paved shoulders configuration of Hamirpur- Mandi Section of NH-70 in HP under GNHCP." GHNCP-NGO-RJ-1 / Consultancy Services for Implementation of the Resettlement Action Plan (RAP) for “Rehabilitation and Green Highway Corridor Quality And Cost- Upgrading of Ras – Beawar – IBRD / 90620 Improvement and Post Open - National 71,500.00 0.00 Canceled 2020-09-02 2020-09-02 2020-09-23 2020-09-11 2020-11-06 2020-10-20 2020-12-04 2021-01-19 2021-01-03 2021-04-08 2021-02-07 2021-03-14 2022-03-14 Based Selection Asind – Mandal Section (from Maintenance km 0.000 to km 116.750) in the State of Rajasthan under GNHCP with loan assistance of World Bank GNHCP-NGO-HP_707-2 / Consultancy Services for Implementation of the Resettlement Action Plan (RAP) for “Rehabilitation and Green Highway Corridor Quality And Cost- Upgradation to Intermediate IBRD / 90620 Improvement and Post Open - National 72,000.00 0.00 Canceled 2020-05-04 2020-05-07 2020-05-25 2020-08-24 2020-07-08 2020-10-20 2020-08-05 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Based Selection lane/2-lane/2-lane with Maintenance paved shoulders/4-lane configuration of Paonta Sahib- Gumma-Fediz Section (km 0.000 to km 103.550) of INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ERP-NISG / Talent Acquisition Institutional Capacity Under IBRD / 90620 Post Direct Selection Direct 380,000.00 0.00 2021-07-27 2020-11-06 2021-08-06 2020-11-06 2021-10-10 2022-04-08 and Management for MoRTH Enhancement Implementation Page 5