Sample Procurement Plan July 9, 2010 PROCUREMENT Nepal : Nepal-India Regional Trade And Transport Project PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-05-17 2019-09-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144335 GPN Date: Project Name: Nepal-India Regional Trade And Transport Project Loan / Credit No: IDA / 52730, / , IDA / H8630 Executing Agency(ies): Department of Roads, Ministry of Commerce WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP/PCO/NITDB/W/ICB- 7 / Construction and Modernize transport and Pending Open - development of existing / transit arrangements Post Request for Bids 1,100,000.00 0.00 Implementati 2016-05-20 2016-06-22 2016-07-23 2016-08-24 2016-09-17 2018-03-16 International railway tracks into between Nepal and India on ballastless tracks NIRTTP/PCO/PPD/W/NCB-9 / Construction of Sanitary Strengthen Trade-Related Under and Phyto-santary SPS/Plant IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 800,000.00 0.00 Implementati 2017-02-26 2017-02-27 2017-03-29 2017-03-30 2017-04-15 2018-07-15 Quarantine and Regional Nepal on Plant ProtectionLaboratory NIRTTP/PCO/NITDB/W/NCB- 3 / Construction of flexible and rigid pavements with Improve Select Trade- IDA / 52730 Prior Request for Bids Open - National 1,580,459.77 1,014,567.52 Signed 2013-10-07 2013-11-29 2014-01-14 2014-02-20 2014-03-25 2015-10-21 drains for pavement Related Infrastructure restoration at Bhairahawa ICD NIRTTP/PCO/DOTM/W/NCB- Modernize transport and Pending 6 / Consturction of / transit arrangements Post Request for Bids Open - National 500,000.00 0.00 Implementati 2016-01-07 2016-01-24 2016-02-23 2016-03-10 2016-03-25 2017-03-24 Weighbridges for Axle Load between Nepal and India on Control -2 Nos NIRTTP/PCO/NITDB/W/ICB- Improve Select Trade- Open - Single Stage - One 1 / Extension of Storage IDA / 52730 Post Request for Bids 237,000.00 0.00 Canceled 2017-09-12 2017-09-17 2017-10-29 2017-11-28 2018-01-02 2019-01-02 Related Infrastructure International Envelope Shed at Birgunj ICD NIRTTP/PCO/NITDB/W/ICB- Pending Improve Select Trade- Open - Single Stage - One 1 / Extension of Storage IDA / 52730 Post Request for Bids 237,000.00 0.00 Implementati 2018-01-10 2018-01-15 2018-02-26 2018-03-28 2018-05-02 2018-10-29 Related Infrastructure International Envelope Shed at Birgunj ICD on NIRTTP/PCO/NITDB/W/ICB- 4 / Construction of Improve Select Trade- Open - IDA / 52730 Prior Request for Bids 18,700,000.00 13,288,546.55 Signed 2018-01-15 2018-01-15 2018-03-06 2018-05-05 2018-06-29 2019-05-30 Kathmandu ICD/CFS (Part- Related Infrastructure International A: Main Block (Phase 1) NIRTTP/PCO/NITDB/W/NCB- 62 / Construction of Improve Select Trade- Single Stage - One Kathmandu ICD/CFS (Part- IDA / 52730 Post Request for Bids Open - National 27,000,000.00 2,038,137.60 Signed 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2019-12-24 Related Infrastructure Envelope B: Office and Quarters (Phase 1)) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NIRTTP/PCO/DOTM/G/SHP- Modernize transport and Pending Request for 23 / Procurement of Office / transit arrangements Post Limited - National 2,200.00 0.00 Implementati 2015-10-05 2015-10-14 2015-11-05 Quotations Furniture for DoTM between Nepal and India on NIRTTP/PCO/TEPC/G/NCB- 25 / Procurement of Strengthen Trade-Related Under Deasktop and Laptop IDA / 52730 Institutional Capacity in Post Request for Bids Open - National 70,000.00 0.00 Implementati 2016-06-21 2016-06-22 2016-07-22 2016-07-23 2016-07-31 2016-08-31 Computers, and necessary Nepal on equipments for TEPC NIRTTP/PCO/DOTM/G/DC- Modernize transport and Pending 28 / Procurement of LED / transit arrangements Post Direct Selection 42,000.00 0.00 Implementati 2016-09-21 2016-10-20 Television Screen and between Nepal and India on Memory Sticks NIRTTP/PCO/PPD/G/SHP-29 / Procurement of Laptop Modernize transport and Pending Request for Computers, SLR Camera etc. / transit arrangements Post Limited - National 5,600.00 0.00 Implementati 2016-11-22 2016-11-30 2016-12-31 Quotations for Plant Protection between Nepal and India on Directorate NIRTTP/PCO/DOTM/G/NCB- 30 / Procurement of Server, Modernize transport and Under Smart Phone/Tabs, Laptop IDA / 52730 transit arrangements Post Request for Bids Open - National 148,000.00 0.00 Implementati 2017-02-27 2017-03-05 2017-04-04 2017-04-10 2017-04-27 2017-06-26 Computers and necessary between Nepal and India on equipment for RAIMS NIRTTP/PCO/DOTM/G/NCB- Modernize transport and Pending 31 / Printing of various / transit arrangements Post Request for Bids Open - National 28,000.00 0.00 Implementati 2017-02-27 2017-03-05 2017-04-04 2017-04-10 2017-04-27 2017-06-26 Road Safety Regulations and between Nepal and India on Materials NIRTTP/PCO/DOTM/G/SHP- 34 / Procurement of Modernize transport and Pending Request for Computers, Printers, GIS / transit arrangements Post Limited - National 7,200.00 0.00 Implementati 2016-12-02 2016-12-21 2017-07-11 Quotations Software and furnitures for between Nepal and India on DOTM NIRTTP/PCO/G/SHP-35 / Modernize transport and Pending Supply and Installation of Request for / transit arrangements Post Limited - National 11,000.00 0.00 Implementati 2017-01-06 2017-01-22 2017-02-21 Solar System with Batteries Quotations between Nepal and India on and Power Inverter NIRTTP-MOCS-155-CP-B- NIRTTP/PCO/DOTM/G/S / Modernize transport and Pending Request for Single Stage - One Procurement of Computers, IDA / H8630 transit arrangements Post Open - National 7,200.00 0.00 Implementati 2017-09-01 2017-10-27 2018-04-25 Quotations Envelope Printers, GIS Software and between Nepal and India on furnitures for DOTM NIRTTP/PCO/G/SHP-39 / Strengthen Trade-Related Pending Request for Single Stage - One Procurement of Computer, IDA / H8630 Institutional Capacity in Post Limited 15,000.00 0.00 Implementati 2018-03-06 2018-05-01 2018-06-30 Quotations Envelope Laptop, Printer Nepal on NIRTTP/PCO/G/SHP- / Modernize transport and Supply and Installation of Request for / transit arrangements Post Limited - National 11,000.00 0.00 Canceled 2013-12-02 2013-12-25 2014-07-15 Solar System with Batteries Quotations between Nepal and India and Power-Inverter for PCO NIRTTP/PCO/DOC/G/NCB- 32 / Procurement of Strengthen Trade-Related Equipments for Custom Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 160,000.00 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Laboratory for kathmandu ( Envelope Nepal DoC ) & birgunj Customs Laboratory NIRTTP/PCO/DOC/G/NCB- Strengthen Trade-Related 63 / Procurement of Lab Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 60,000.00 44,871.93 Signed 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Equipment for Department Envelope Nepal of Customs Page 2 NIRTTP/PCO/TEPC/G/SHOPP Strengthen Trade-Related Under ING-64 / Solar Backup Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 16,000.00 0.00 Implementati 2018-05-20 2018-07-15 2018-09-13 System for Nepal Trade Quotations Envelope Nepal on Information Portal NIRTTP/PCO/G/SHP-33 / Modernize transport and Procurement of Office Request for / transit arrangements Post Limited - National 9,200.00 0.00 Canceled 2016-11-26 2016-12-23 2017-07-15 Furniture, Fixtures and Quotations between Nepal and India Furnishing for PCO NIRTTP/PCO/G/SHP-20 / Modernize transport and Request for Procurement of Stationery / transit arrangements Post Limited - National 8,800.00 0.00 Canceled 2015-10-11 2015-10-20 2015-10-20 Quotations and Sundries for PCO between Nepal and India NIRTTP/PCO/TEPC/G/SHP- Modernize transport and 26 / Procurement of Office Request for / transit arrangements Post Limited - National 5,000.00 0.00 Canceled 2016-07-16 2016-07-25 2016-08-25 Furniture and furnishing for Quotations between Nepal and India TEPC NIRTTP/PCO/DOC/G/NCB- 66 / Equipment for Custom Strengthen Trade-Related Under Single Stage - One Laboratory for kathmandu ( IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 160,000.00 149,478.74 Implementati 2018-09-02 2018-09-12 2018-10-12 2018-12-11 2019-01-15 2019-07-14 Envelope DoC ) & birgunj Customs Nepal on Laboratory NIRTTP/PCO/PPD/G/NCB-69 Strengthen Trade-Related Pending Single Stage - One / Lab equipments and IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-08-21 Envelope accessories for SPS Lab Nepal on NIRTTP/PCO/DOTM/G/NCB- 79 / Hardware for Road Modernize transport and Single Stage - One Accident Information IDA / H8630 transit arrangements Post Request for Bids Open - National 35,000.00 0.00 Canceled 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 2020-01-18 Envelope Management System( between Nepal and India RAIMS) NIRTTP/PCO/TEPC/G/NCB- 82 / Procurement of Desktop Strengthen Trade-Related Pending Single Stage - One and Laptop Computers, and IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 78,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-05-19 Envelope necessary equipment for Nepal on TEPC NIRTTP/PCO/TEPC/G/NCB- Strengthen Trade-Related Pending Single Stage - One 83 / SOlar Backup system IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 42,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-03-20 Envelope for NTIP ( TEPC) Nepal on NIRTTP/PCO/DOC/G/NCB- Strengthen Trade-Related Pending 86 / Installation of Scanning Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 270,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-05-19 Electron microscope (SEM) Envelope Nepal on with EDX Detector NIRTTP/PCO/DOC/G/NCB- 87 / Installation of High Strengthen Trade-Related Pending Single Stage - One Performance Liquid IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-05 2019-10-05 2019-11-09 2020-03-08 Envelope Chromatography ( HPCL) for Nepal on DoC NIRTTP/PCO/DOC/G/NCB- Strengthen Trade-Related Pending Single Stage - One 89 / Sport Utility Vehicles IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 80,000.00 0.00 Implementati 2019-08-15 2019-08-20 2019-09-19 2019-10-19 2019-11-23 2020-03-22 Envelope for NNSW PIU Office Nepal on NIRTTP/PCO/DOC/G/SHP-90 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Business IDA / H8630 Institutional Capacity in Post Limited 9,000.00 0.00 Implementati 2019-08-09 2019-10-04 2019-11-03 Quotations Envelope Series Laptop (package-1) Nepal on NIRTTP/PCO/DOC/G/SHP-91 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Branded IDA / H8630 Institutional Capacity in Post Limited 8,000.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 Quotations Envelope High End Laptop (package-2) Nepal on Page 3 NIRTTP/PCO/DOC/G/SHP-92 Strengthen Trade-Related Pending / Procurement of It Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 3,300.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 Equipment ( Printer,I-Pad & Quotations Envelope Nepal on USB Hard disk) (Package-3) NIRTTP/PCO/DOC/G/SHP-93 Strengthen Trade-Related Pending / Procurement of It Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 4,700.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 Equipment ( Photocopy,Color Quotations Envelope Nepal on Printer,Scanner) Package-4 NIRTTP-PCO-DOC-G-SHP- 81 / IT Equipment & Strengthen Trade-Related Pending Accessories for NNSW PIU Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 20,000.00 0.00 Implementati 2019-10-06 2019-11-24 2019-12-24 Office ( Laptop,Desk Top, Quotations Envelope Nepal on Scanner,Printer,Photocopy, Vacuum Cleaner) -package-5 NIRTTP/PCO/DOC/G/SHP-84 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Motorcycle IDA / H8630 Institutional Capacity in Post Limited 10,000.00 0.00 Implementati 2019-09-04 2019-10-16 2020-04-13 Quotations Envelope & Scooter for DoC Nepal on NIRTTP/PCO/G/SHP-87 / IT Strengthen Trade-Related Pending Request for Single Stage - One Equipment and other IDA / H8630 Institutional Capacity in Post Limited 9,000.00 0.00 Implementati 2019-09-04 2019-10-30 2020-04-27 Quotations Envelope Accessories for PCO Nepal on NIRTTP-PCO-DOTM-G-SHP- Modernize transport and 79 / Procurment of Request for Single Stage - One IDA / H8630 transit arrangements Post Open - National 20,000.00 0.00 Canceled 2019-06-14 2019-08-02 2019-09-01 additional hardware for Quotations Envelope between Nepal and India RAMIS NIRTTP/PCO/CAL/G/NCB- 104 / Supply & Installation of Lab Equipment for SPS Strengthen Trade-Related Pending Single Stage - One /Plant Quarantine and IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-09-01 2019-09-06 2019-10-18 2019-11-17 2019-12-22 2020-04-20 Envelope Regional Plant Protection Nepal on Laboratory , Hariharbhawan, Lalitpur NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP/PCO/NS/SHP-26 / Computer software design, Modernize transport and Pending installation helpful in Request for / transit arrangements Post Limited - National 5,700.00 0.00 Implementati 2016-11-10 2016-11-19 2017-07-05 improvement of operation Quotations between Nepal and India on and management of the Project NIRTTP/PCO/DOTM/NS/SHP- Modernize transport and Pending 33 / Selection & Recruitment / transit arrangements Post Request for Bids Open - National 24,000.00 0.00 Implementati 1901-01-01 2015-05-15 1901-01-01 1901-01-01 2015-06-28 2019-06-30 of Office Secretay between Nepal and India on NIRTTP/PCO/DOTM/NS/NCB- 35 / Developing web based Road Accident Management Modernize transport and Pending Information System (RAMIS) / transit arrangements Post Direct Selection National 40,000.00 0.00 Implementati 2016-01-20 2016-07-15 and piloting in Kathmandu between Nepal and India on valley and along the Birgunj- Kathmandu corridor Page 4 NIRTTP/PCO/NS/NCB-29 / Kolkata-Kathmandu Corridor Modernize transport and Monitoring and Evaluation / transit arrangements Post Request for Bids Open - National 278,000.00 0.00 Canceled 2016-01-07 2016-01-11 2016-02-10 2016-02-21 2016-03-04 2016-12-30 Data Management System between Nepal and India (CMEDMS) NIRTTP/PCO/TEPC/NS/SHP- Strengthen Trade-Related Pending 34 / Selection & Recruitment Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 24,000.00 0.00 Implementati 2017-09-17 2017-11-12 2019-12-31 of Office Secretay for TEPC, Quotations Envelope Nepal on Number -1 NIRTTP/PCO/NITDB/NS/SHP- 37 / Procurement of firm for Determination of Border crossing and transportation Pending Improve Select Trade- Request for Single Stage - One time of Cargo.(Originating at IDA / 52730 Post Open - National 10,000.00 0.00 Implementati 2017-09-22 2017-11-17 2018-05-16 Related Infrastructure Quotations Envelope Kolkata to reach Kathmandu on and vice versa for the both Road and Railway mode of transportation) NP-MOC-23661-NC-RFB / Procurement of Design, Supply and Build National Single Window IT system in Strengthen Trade-Related Open - Single Stage - Two Nepal ( Previous ID as per IDA / H8630 Institutional Capacity in Prior Request for Bids 12,780,000.00 7,608,077.56 Signed 2017-08-03 2017-10-19 2017-10-19 2017-08-08 2017-12-28 2018-03-12 2018-04-16 2019-10-08 International Envelope approved PP 2017-01 is Nepal NIRTTP-MOCS-87-LPI-S- NIRTTP/PCO/DOC/NS/ICB- 1(Two stage bidding) NIRTTP/PCO/NITDB/SHP-65 / Border Crossing & Under Improve Select Trade- Request for Single Stage - One Transportation time of cargo IDA / 52730 Post Open - National 22,000.00 0.00 Implementati 2018-06-06 2018-08-01 2018-09-30 Related Infrastructure Quotations Envelope (Raxaul-Birgunj-Kathmandu- on Birgunj) NIRTTP/PCO/DOTM/NS/DIR- 57 / Technical support for Modernize transport and maintenance of Vehicle IDA / 52730 transit arrangements Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-03-01 2018-03-06 2018-04-10 2018-10-07 Fitness Testing between Nepal and India Center(VFTC) and capacity Buildings of staffs NIRTTP/PCO/NS/SHP-31 / Modernize transport and Selection and Recruitment of / transit arrangements Post Request for Bids Open - National 196,800.00 0.00 Canceled 1901-01-01 2015-10-02 1901-01-01 1901-01-01 2015-10-31 2019-12-31 Assistants for PCO between Nepal and India NIRTTP/PCO/PPD/NS/SHP- 38 / Developmentof National Modernize transport and Request for Pest Surveillance / transit arrangements Post Limited - National 18,500.00 0.00 Canceled 2016-11-05 2016-11-14 2016-11-14 Quotations Management Information between Nepal and India System NIRTTP/PCO/DOC/NS/SHP- Modernize transport and 32 / Selection & Recruitment / transit arrangements Post Request for Bids Open - National 24,000.00 0.00 Canceled 1901-01-01 2015-05-15 1901-01-01 1901-01-01 2015-06-28 2019-06-30 of Office Secretay between Nepal and India NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 94 / Internet Service for IDA / H8630 Institutional Capacity in Post Limited 1,200.00 0.00 Implementati 2019-08-16 2019-09-13 2020-09-12 Quotations Envelope NNSW PIU Office Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending 100 / Recruitment of Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 7,200.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Computer Operator for Quotations Envelope Nepal on NNSW Page 5 NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 101 / Recruitment of IDA / H8630 Institutional Capacity in Post Open - National 7,200.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope Project Assistant for NNSW Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 102 / Recruitment of Office IDA / H8630 Institutional Capacity in Post Open - National 6,000.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope Assistance for NNSW Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 103 / Recruitment of Driver IDA / H8630 Institutional Capacity in Post Open - National 6,000.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope for NNSW Nepal on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP-DOR-S-QCBS-1 / Consulting services for Modernize transport and Quality And Cost- Open - Feasibility study, Detailed IDA / 52730 transit arrangements Prior 0.00 3,181,587.36 Signed Based Selection International design & Constr. supervision between Nepal and India of various Roads NIRTTP/PCO/NITDB/S/QCBS- 23 / Design and Improve Select Trade- Quality And Cost- Under Construction Supervision of IDA / H8630 Post Open - National 191,700.00 0.00 2015-10-12 2015-12-24 2016-01-15 2016-02-05 2017-02-05 Related Infrastructure Based Selection Implementation Railway Tracks Modification at BirgunjICD NIRTTP/PCO/NITDB/S/QCBS- 46 / Detailed Design Review Improve Select Trade- Quality And Cost- Open - Under and Supervision Consultant IDA / H8630 Post 350,000.00 0.00 2016-11-16 2017-01-31 2017-02-14 2017-02-21 2019-06-30 Related Infrastructure Based Selection International Implementation for Construction of ICD, Kathmandu NIRTTP/PCO/DOTM/S/LCS- 47 / Consulting Servieces to support DOTM for bus Modernize transport and Least Cost Under routes, vehicle standard IDA / 52730 transit arrangements Post Open - National 75,000.00 0.00 2016-11-25 2017-03-01 2017-03-10 2017-03-31 2017-06-30 Selection Implementation survey and for preparing between Nepal and India standard criteria for route permits NIRTTP/PCO/DOTM/S/CQS- Modernize transport and 48 / Survey and Detailed Quality And Cost- Under IDA / 52730 transit arrangements Post Open - National 40,000.00 0.00 2017-03-17 2017-05-25 2017-05-30 2017-06-02 2017-12-01 Design Weigh Bridge Based Selection Implementation between Nepal and India Stations NIRTTP/PCO/S/CQS-52 / Feasibility Study for FTA Modernize transport and Consultant Pending with a Country considering / transit arrangements Post Qualification Open - National 18,500.00 0.00 2016-11-17 2017-01-02 2017-07-01 Implementation long term trade benefit to between Nepal and India Selection Nepal NIRTTP/PCO/DOC/S/QCBS-9 / Selection of Firm for Nepal National Single Window and Trade Portal Strengthen Trade-Related Quality And Cost- Open - Implementation"Quality IDA / 52730 Institutional Capacity in Prior 1,930,000.00 1,636,533.58 Signed 2014-06-25 2014-10-20 2014-11-02 2014-11-30 2017-11-30 Based Selection International Assurance and Advisory Nepal Services(including Bid document prepartion)(International) Page 6 NIRTTP/PCO/NITB/S/QCBS- 17 / Selection of Project Modernize transport and Implementation/Supervision Quality And Cost- IDA / 52730 transit arrangements Prior Open - National 228,735.63 240,862.34 Signed 2013-11-29 2014-05-15 2014-06-21 2014-07-14 2016-01-07 Consultant for NITDB Based Selection between Nepal and India (Birgunj and Bhairahawa ICD Improvement works) NP-MOC-23665-CS-CQS-40 / Selection of firm for preparing Master Plan and Strengthen Trade-Related Consultant Detailed Design/Drawing of Pending IDA / H8630 Institutional Capacity in Post Qualification Open - National 65,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-06 2017-12-11 2018-06-09 Referral/SPS and Regional Implementation Nepal Selection Plant Protection Laboratory including Supervision of Constriction Works NITDB/PCO/PPD/S/QCBS-45 / Consulting Services for Modernize transport and Pest Surveillance in six Quality And Cost- / transit arrangements Post Open - National 124,000.00 0.00 Canceled 2016-11-11 2017-01-10 2017-01-10 2017-02-12 2017-07-12 major crops and Pest Based Selection between Nepal and India Detection Survey in three major medicinal Herbs NIRTTP/PCO/TEPC/S/QCBS- 39 / Selection of Firm for Strengthen Trade-Related Quality And Cost- Open - Pending Development and IDA / H8630 Institutional Capacity in Prior 570,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-04 2017-12-04 2018-01-08 2018-02-12 2019-02-12 Based Selection International Implementation Implementation of the Nepal Nepal Trade Information Portal NIRTTP/PCO/DOTM/S/LCS- 26 / Consulting Servieces to support DOTM for bus Modernize transport and Least Cost Pending routes, vehicle standard IDA / H8630 transit arrangements Post Open - National 35,000.00 0.00 2017-09-12 2017-10-03 2017-11-16 2017-12-14 2018-01-13 2018-02-17 2018-03-24 2018-09-20 Selection Implementation survey and for preparing between Nepal and India standard criteria for route permits NIRTTP/PCO/NITDB/S/QCBS- 24 / Survey Environmental Improve Select Trade- Quality And Cost- Pending IDA / 52730 Post Open - National 240,000.00 0.00 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2019-03-23 Study and Detailed Design Related Infrastructure Based Selection Implementation for Kathmandu CFS/ICD NIRTTP/PCO/S/CQS-56 / Consultant's services for a comprehensive study of Nepal's existing transit Strengthen Trade-Related Consultant Pending agreements with India, IDA / H8630 Institutional Capacity in Post Qualification Open - National 30,000.00 0.00 2017-09-17 2017-10-08 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Implementation Bangladesh and China and Nepal Selection receive recommendations for amendments and improvements NIRTTP/PCO/S/CQS-57 / Consultant's services for a comprehensive study on the Strengthen Trade-Related Consultant Pending potentiality of trade-in- IDA / H8630 Institutional Capacity in Post Qualification Open - National 30,000.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Implementation services with SAARC Nepal Selection countries to develop Nepal's service trade NIRTTP/PCO/NITDB/S/CQS- 21 / Data Capture Consultant Improve Select Trade- Pending Framework For Kolkata- IDA / 52730 Post Qualification Open - National 22,000.00 0.00 2017-09-17 2017-10-08 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Related Infrastructure Implementation Kathmandu Corridor Selection Monitoring NIRTTP/PCO/S/CQS-53 / Preparation of Mid-term and Modernize transport and Consultant Long-term Strategy Plan for / transit arrangements Post Qualification Open - National 37,000.00 0.00 Canceled 2016-11-17 2017-01-02 2017-07-01 Trade sector including between Nepal and India Selection infrastructure Page 7 NIRTTP/PCO/S/CQS-73 / Strengthen Trade-Related Consultant Study on Possibilities of Pending IDA / H8630 Institutional Capacity in Post Qualification Open - National 40,000.00 0.00 2018-12-01 2018-12-22 2019-02-04 2019-03-06 2019-04-10 2019-10-07 Transit Trade Facility Implementation Nepal Selection through Inland Water Wages NP-MOC-23681-CS-CQS-45- PPD / Consulting Services Strengthen Trade-Related Consultant for Pest Surveillance in six IDA / H8630 Institutional Capacity in Post Qualification Open - National 124,000.00 0.00 Canceled 2017-08-04 2017-08-25 2017-10-08 2017-11-07 2017-12-12 2018-06-10 major crops and Pest Nepal Selection Detection Survey in three major medicinal Herbs NIRTTP/PCO/NITDB/S/QCBS -55 / Design, Development and Operation of Corridor Improve Select Trade- Quality And Cost- Pending IDA / H8630 Post Open - National 278,000.00 0.00 2017-08-27 2017-09-17 2017-10-31 2017-11-28 2017-12-28 2018-02-01 2018-03-08 2020-03-07 Monitoring and Evaluation Related Infrastructure Based Selection Implementation Data Management System (CMEDMS) NIRTTP/PCO/DOTM/S/LCS- Modernize transport and 78 / Consulting service for Least Cost Pending IDA / H8630 transit arrangements Post Open - National 40,000.00 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-10-23 "Construction Supervision of Selection Implementation between Nepal and India weighbridge station " INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Modernize transport and Individual NIRTTP/PCO/S/IND-28 / IDA / 52730 transit arrangements Prior Consultant Open 0.00 119,603.22 Canceled Technical Adviser to NITDB between Nepal and India Selection NIRTTP/PCO/S/IND-19 / Modernize transport and Individual Selection of Expert for IDA / 52730 transit arrangements Prior Consultant Limited 30,000.00 30,000.00 Signed 2014-03-31 2015-01-03 Study on Transshipment between Nepal and India Selection NIRTTP/PCO/S/IND-27 / Modernize transport and Individual Selection of full time IDA / 52730 transit arrangements Prior Consultant Limited 100,000.00 57,532.13 Signed 2015-06-05 2019-06-30 Procurement between Nepal and India Selection Specialist/Consultant NIRTTP/PCO/S/IND-28 / Strengthen Trade-Related Individual Selection of Technical IDA / 52730 Institutional Capacity in Prior Consultant Limited 110,000.00 83,757.40 Signed 2015-11-05 2019-12-31 Adviser for NITDB Nepal Selection NIRTTP/PCO/DOTM/S/IND- Modernize transport and Individual 29 / Selection of Technical IDA / 52730 transit arrangements Prior Consultant Limited 100,000.00 45,313.41 Signed 2015-11-05 2019-12-31 Adviser for DoTM (National) between Nepal and India Selection NIRTTP/PCO/S/IND-30 / Modernize transport and Individual Selection of Trade IDA / 52730 transit arrangements Prior Consultant Limited 100,000.00 97,117.14 Signed 2015-06-30 2019-12-31 Facilitation Adviser between Nepal and India Selection (National) NIRTTP/PCO/S/IND-31 / Modernize transport and Individual Selection of Trade IDA / 52730 transit arrangements Prior Consultant Limited 100,000.00 101,175.24 Signed 2015-06-30 2019-12-31 Development Adviser for between Nepal and India Selection PCO NIRTTP/PCO/PPD/S/IND-44 Strengthen Trade-Related Individual / Selection of Expert for Under IDA / H8630 Institutional Capacity in Post Consultant Limited 23,500.00 17,800.00 2016-12-12 2016-12-12 updating National Phyto- Implementation Nepal Selection Sanitary System of Nepal Page 8 NIRTTP/PCO/PPD/S/IND-43 / Selection of Expert for Modernize transport and Individual Pending Plant Health Management / transit arrangements Post Consultant Limited 9,500.00 0.00 2016-12-12 2016-12-12 Implementation study based on Traditional between Nepal and India Selection Transborder Trade NIRTTP/PCO/S/IND-49 / Modernize transport and Individual Selection of Non Tariff Pending / transit arrangements Post Consultant Limited 70,000.00 0.00 2016-12-15 2019-06-30 Measures (NTM) Tracking Implementation between Nepal and India Selection System Analyst NIRTTP/PCO/S/IND-50 / Modernize transport and Individual Selection of Consultant for Pending / transit arrangements Post Consultant Limited 18,500.00 0.00 2016-12-04 2016-12-04 study on Improvement of Implementation between Nepal and India Selection Nepal-India Trading Regime NIRTTP/PCO/DOC/S/IND-50 / Selection of an Strengthen Trade-Related Individual International Procurement IDA / 52730 Institutional Capacity in Prior Consultant Limited 50,000.00 0.00 Canceled 2017-01-16 2017-07-15 Specialist/Consultant Nepal Selection (Intermittent) NIRTTP/PCO/DOC/S/IND-51 / Selection of an Strengthen Trade-Related Individual International IT IDA / 52730 Institutional Capacity in Post Consultant Limited 50,000.00 0.00 Canceled 2017-01-16 2017-07-15 Specialist/Consultant Nepal Selection (Intermittent) NIRTTP/PCO/S/IND-52 / Strengthen Trade-Related Individual Selection of full time Under IDA / H8630 Institutional Capacity in Prior Consultant Limited 87,000.00 0.00 2017-01-18 2019-12-31 Procurement Implementation Nepal Selection Adviser/Consultant NIRTTP/PCO/S/IND-11 / Modernize transport and Individual Selection of full time IDA / 52730 transit arrangements Prior Consultant Limited 18,045.98 21,496.57 Signed 1901-01-01 2014-07-15 Procurement between Nepal and India Selection Specialist/Consultant NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 18 / Selection of Engineering IDA / 52730 Institutional Capacity in Post Consultant Limited 17,241.38 0.00 2015-12-04 2019-12-31 Implementation Support to NITDB Nepal Selection NIRTTP/PCO/S/IND-13 / Strengthen Trade-Related Individual Selection of Environmental Pending IDA / H8630 Institutional Capacity in Post Consultant Open 40,000.00 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2019-12-31 Safeguards Specialist Implementation Nepal Selection (Intermittent) NIRTTP/PCO/S/IND-14 / Strengthen Trade-Related Individual Selection of Social Pending IDA / H8630 Institutional Capacity in Post Consultant Open 35,000.00 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2018-06-24 Safeguards Specialist Implementation Nepal Selection (Intermittent) NIRTTP/PCO/S/IND-58 / Consultanting service for the development of a system on Strengthen Trade-Related Individual Pending Non-Tariff Measures of IDA / H8630 Institutional Capacity in Post Consultant Open 40,000.00 0.00 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 Implementation major export markets for Nepal Selection export promotion measures in Nepal NIRTTP/PCO/DOTM/IND-4 / Modernize transport and Individual Pending Selection of Project Assistant IDA / H8630 transit arrangements Post Consultant Open 50,000.00 0.00 2017-09-17 2017-11-05 2017-11-26 2017-12-31 2019-12-31 Implementation for DOTM (National) between Nepal and India Selection NIRTTP/PCO/NITDB/S/SSS- Improve Select Trade- Under 42 / Selection of Corridor IDA / 52730 Post Direct Selection Direct 3,000.00 2,698.86 2017-09-17 2017-09-27 2017-12-01 2018-05-30 Related Infrastructure Implementation Monitoring Consultant Page 9 NIRTTP/PCO/PPD/S/IND-59 Strengthen Trade-Related Individual / Consultant for preparation Pending IDA / H8630 Institutional Capacity in Post Consultant Open 20,000.00 0.00 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-09-11 of pest surveillance of 100 Implementation Nepal Selection pests of 10 major crops NITTP/PCO/PPD/S/IND-60 / Strengthen Trade-Related Individual Preparation of Internal Pending IDA / H8630 Institutional Capacity in Post Consultant Open 15,000.00 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-07-15 Quarantine Procedure and Implementation Nepal Selection Guideline NIRTTP/PCO/S/IND-54 / Preparation of Mid-term and Strengthen Trade-Related Individual Pending long-term strategy plan for IDA / H8630 Institutional Capacity in Post Consultant Open 50,000.00 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Implementation trade sector including Nepal Selection infrastructure NIRTTP/PCO/DOTM/S/IND- Strengthen Trade-Related Individual 56 / Selection of Technical IDA / 52730 Institutional Capacity in Prior Consultant Open 50,000.00 56,815.29 Signed 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2019-12-31 Adviser for DoTM (National) Nepal Selection NIRTTP/PCO/PPD/IND-61 / Civil Engineer( Intermittent) Strengthen Trade-Related Individual Pending For supervision of IDA / H8630 Institutional Capacity in Post Consultant Open 16,000.00 0.00 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-02-10 Implementation Construction work under Nepal Selection NIRTTP project NIRTTP/PCO/DOTM/S/IND- 54 / Selection of an Modernize transport and Individual International Consultant to Under IDA / H8630 transit arrangements Post Consultant Limited 25,000.00 0.00 2018-08-08 2018-10-15 2018-10-30 2019-04-30 2019-09-30 Support Establishment and Implementation between Nepal and India Selection Operation of Vehicle Fitness Testing Center in Nepal NIRTTP/PCO/S/IND-74 / Strengthen Trade-Related Individual Study on Possibility of Pending IDA / H8630 Institutional Capacity in Post Consultant Open 30,000.00 0.00 2018-09-02 2018-10-21 2018-11-11 2018-12-16 2019-06-14 Service trade with SAARC Implementation Nepal Selection countires NIRTTP/PCO/S/IND-34 / Modernize transport and Individual Selection of MoCS Capacity / transit arrangements Post Consultant Limited 110,000.00 0.00 Canceled 2015-10-30 2019-12-31 Enhancement Specialist between Nepal and India Selection (National) NIRTTP/PCO/S/IND-15 / Modernize transport and Individual Selection of Finance / transit arrangements Post Consultant Limited 18,045.98 0.00 Canceled 2015-11-15 2019-12-31 Specialist/Consultant between Nepal and India Selection NIRTTP/PCO/DOC/S/IND-26 / Selection of Legal Adviser Modernize transport and Individual for Dept. of Customs for / transit arrangements Prior Consultant Limited 1,700.00 0.00 Canceled 2015-11-30 2019-06-30 advice on the proposed between Nepal and India Selection Single Window System NIRTTP/PCO/S/IND-53 / Selection of Senior Modernize transport and Individual Procurement / transit arrangements Prior Consultant Limited 22,500.00 0.00 Canceled 2017-01-31 2019-06-30 Specialist/Consultant between Nepal and India Selection (Intermittent) NIRTTP/PCO/S/IND-51 / Selection of Consultant for Modernize transport and Individual study on Requirements of / transit arrangements Post Consultant Limited 18,500.00 0.00 Canceled 2016-12-04 2016-12-04 Additional Facility in between Nepal and India Selection Birgunj Integrated Check Point (ICP) NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 67 / Social Safeguard IDA / H8630 Institutional Capacity in Post Consultant Open 15,000.00 0.00 2018-12-01 2019-01-19 2019-02-09 2019-03-16 2020-01-30 Implementation Mobiliser Nepal Selection Page 10 NIRTTP/PCO/S/IND-68 / Study on reorganizing the Nepal Transit and Strengthen Trade-Related Individual Under Waterhousing Company IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2018-12-31 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Implementation Limited (NTWCL) and the Nepal Selection Nepal Inter-modal transport Development Board(NITDB) NIRTTP/PCO/TEPC/S/IND- 69 / Project Management Advisor for Quality Strengthen Trade-Related Individual Under Assurance and Advisory IDA / H8630 Institutional Capacity in Post Consultant Open 24,000.00 0.00 2018-12-31 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Implementation Services in Support of Nepal Nepal Selection Trade Information Portal Extension NIRTTP/PCO/TEPC/S/IND- 70 / National IT Specialist Strengthen Trade-Related Individual for Quality Assurance and Under IDA / H8630 Institutional Capacity in Post Consultant Open 5,000.00 0.00 2018-12-31 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Advisory Services in Support Implementation Nepal Selection of Nepal Trade Information Portal Extension NIRTTP/PCO/PPD/S/IND-67 / Study to find out modality Strengthen Trade-Related Individual Under to provide efficient plant IDA / H8630 Institutional Capacity in Post Consultant Open 10,000.00 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-08-13 Implementation protection services in Federal Nepal Selection and Provinces NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 71 / Social Safeguard Expert IDA / H8630 Institutional Capacity in Post Consultant Open 26,000.00 0.00 2019-01-22 2019-03-12 2019-04-02 2019-05-07 2019-11-23 Implementation for Kathmandu ICD Nepal Selection NIRTTP/PCO/S/IND-72 / Strengthen Trade-Related Individual Preparation of Strategies for Under IDA / H8630 Institutional Capacity in Post Consultant Open 6,000.00 0.00 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Export Promotion to the Implementation Nepal Selection European Union (EU) NIRTTP/PCO/S/IND-73 / Strengthen Trade-Related Individual Under Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Implementation Export Promotion to India Nepal Selection NIRTTP/PCO/IND-75 / Strengthen Trade-Related Individual Preparation of Strategies for Under IDA / H8630 Institutional Capacity in Post Consultant Open 5,000.00 0.00 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Export Promotion to the Implementation Nepal Selection United Arab Emirates (UAE) NIRTTP/PCO/DOTM/S/IND- 77 / "System Design and Modernize transport and Individual Under software/hardware IDA / H8630 transit arrangements Post Consultant Open 5,000.00 0.00 2019-04-30 2019-05-26 2019-06-02 2019-06-24 2019-08-23 Implementation requirement for GPS vehicle between Nepal and India Selection tracking system" NIRTTP/PCO/S/IND-80 / Strengthen Trade-Related Individual Under Environmental Specialist IDA / H8630 Institutional Capacity in Post Consultant Open 19,000.00 0.00 2019-05-05 2019-05-31 2019-06-07 2019-06-29 2019-12-31 Implementation Consultant (National) Nepal Selection NIRTTP/PCO/DOC/S/SSS-87 / Quality Assurance and Advisory Services for Strengthen Trade-Related Pending Implementation of Nepal IDA / H8630 Institutional Capacity in Post Direct Selection Direct 970,000.00 0.00 2019-08-01 2019-08-11 2019-10-15 2021-10-14 Implementation National Single Window Nepal System & NTIP Extension work (TEPC) Page 11 NIRTTP/PCO/DOC/S/IND-88 Strengthen Trade-Related Individual / Nepal National Single Pending IDA / H8630 Institutional Capacity in Post Consultant Open 60,000.00 0.00 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2021-12-24 Window Project management Implementation Nepal Selection Consultant Strengthen Trade-Related Individual NIRTTP/PCO/S/IND-99 / Pending IDA / H8630 Institutional Capacity in Prior Consultant Open 56,000.00 0.00 2019-08-18 2019-10-06 2019-10-27 2019-12-01 2021-12-31 Procurement Specialist Implementation Nepal Selection NIRTTP/PCO/S/IND-105 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to UK Nepal Selection NIRTTP/PCO/S/IND-106 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to EU Nepal Selection NIRTTP/PCO/S/IND-107 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to Japan Nepal Selection NIRTTP/PCO/S/IND-108 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to Canada Nepal Selection NIRTTP/PCO/S/IND-109 / Strengthen Trade-Related Individual Preparation of Strategies for Pending IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Export Promotion to Implementation Nepal Selection Bangladesh Page 12