Procurement Plan Balochistan Integrated Water Resources Management and Development Project I. General 1. Bank’s approval Date of the procurement Plan March 19,2016 2. Date of General Procurement Notice: January 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB (Goods) Above US$ 600,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 4 million All 4. NCB (Works) Upto US$ 4 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract 6. Community Driven Development Above US$ 25,000 First contract 2. Pre-qualification. Bidders for $ 15 million shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Balochistan Government July 9, 2010 5. Any Other Special Procurement Arrangements: Some preparatory activities under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contract (Works) for Prior Review Summary 1.86 4 No Post 1st of the NCB contract (Goods) for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK-Balochistan Integrated Water Resources Management & Development Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-10-14 2021-03-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154255 GPN Date: 2017-07-10 Project Name: PK-Balochistan Integrated Water Resources Management & Development Project Loan / Credit No: IDA / 58850 P Executing Agency(ies): MU Balochistan Integrated Water Resources Management and Development Project WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PMU-BIWRMDP-14383- Component B: Water, Single Stage - One 12,906,271.0 11,689,958. 2020-02- CW-RFB / Construction of IDA / 58850 Infrastructure and Prior Request for Bids Open - International Signed 2017-05-11 2017-05-17 2017-05-16 2017-05-23 2017-06-30 2017-07-10 2017-07-30 2017-08-21 2017-09-03 2017-09-08 Envelope 0 60 20 Nari Gorge Integrated Scheme Management Investments PK-PMU-BIWRMDP-14453- Component B: Water, CW-RFB / Construction of Single Stage - One 6,475,606.4 2020-03- IDA / 58850 Infrastructure and Post Request for Bids Open - International 8,995,675.00 Terminated 2017-05-22 2017-05-26 2017-05-27 2017-05-26 2017-07-11 2017-07-20 2017-08-10 2017-11-06 2017-09-14 2017-11-20 Gundacha-Nurg Hingri Envelope 9 02 Management Investments Integrated Scheme PK-PMU-BIWRMDP-2420-CW- RFB / Nari Gorge Perennial Component B: Water, Irrigation Scheme - Package 3 Single Stage - One 2018-12- IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,510,643.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-05-06 2017-06-17 of 5 (Luni, Kurak, Bakhra Envelope 09 Management Investments Ghulam Bolak and Marghzani Channels) PK-PMU-BIWRMDP-2419-CW- Component B: Water, RFB / Nari Gorge Perennial Single Stage - One 2018-09- IDA / 58850 Infrastructure and Prior Request for Bids Open - National 1,434,724.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-04-27 2017-06-08 Irrigation Scheme - Package 2 Envelope 01 Management Investments of 5 (Dehpal Channel) PK-PMU-BIWRMDP-2432-CW- RFB / Gundacha Nurg Hingri Scheme - Package 2 of 2 (Construction of Irrigation Channel, Nurg Hingri Off Take Component B: Water, Single Stage - One 2019-09- Weirs and Under Sluice, Nurg IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,601,570.00 0.00 Canceled 2017-05-09 2017-05-19 2017-07-10 2017-08-04 2017-09-17 Envelope 07 Hingri Channels and Guide Management Investments Banks, Glacis Fall Structures, Road Culverts, Outlet Structures and Drainage Culverts) PK-PMU-BIWRMDP-2431-CW- RFB / Gundacha Nurg Hingri Component B: Water, Irrigation Scheme - Package 1 Single Stage - One 2019-08- IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,941,491.00 0.00 Canceled 2017-05-09 2017-05-19 2017-06-24 2017-07-15 2017-08-28 of 2 (Construction of Weir, Envelope 18 Management Investments Undersluice and Head Regulator) PK-PMU-BIWRMDP-2427-CW- RFB / Yetabad Flood Irrigation Component B: Water, Scheme - Package 2 of 6 Single Stage - One 2021-11- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 (Conveyance System Including Envelope 14 Management Investments Cross Drainage (RD 0+00 to RD 10+750) PK-PMU-BIWRMDP-2428-CW- RFB / Yetabad Flood Irrigation Component B: Water, Scheme - Package 3 of 6 Single Stage - One 2021-11- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-12 2018-11-25 (Conveyance System including Envelope 24 Management Investments Cross Drainage Structures RD 10+750 to RD 21+500) PK-PMU-BIWRMDP-2423-CW- Component B: Water, RFB / Yetabad Flood Irrigation Single Stage - One 2021-11- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 9,014,788.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 Scheme - Package 1 of 6 (Weir Envelope 14 Management Investments & Buildings) PK-PMU-BIWRMDP-69116- CW-RFB / Yetabad Flood Component B: Water, Single Stage - One 15,151,815.0 2020-09- Irrigation Scheme - Package 2 IDA / 58850 Infrastructure and Prior Request for Bids Open - International 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 Envelope 0 05 (Conveyance System KM Management Investments 6+000 to KM 21+500) PK-PMU-BIWRMDP-69112- CW-RFB / Yetabad Flood Component B: Water, Single Stage - One 148,484,235. 2020-09- Irrigation Scheme - Package 1 IDA / 58850 Infrastructure and Prior Request for Bids Open - International 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 Envelope 00 05 (Weir and Conveyance System Management Investments (KM 0+000 to KM 6+000) PK-PMU-BIWRMDP-79952- Component B: Water, CW-RFB / Construction of Single Stage - One 2021-09- IDA / 58850 Infrastructure and Post Request for Bids Open - International 7,464,230.00 0.00 Canceled 2018-11-12 2018-11-17 2018-11-12 2019-01-04 2019-02-03 2019-03-10 Mushkaf Flood Irrigation Envelope 07 Management Investments Scheme PK-PMU-BIWRMDP-92413- CW-RFQ / Procurement of Works for Production of Plants Component B: Water, Request for Single Stage - One 2019-07- Through Raising of Nurseries IDA / 58850 Infrastructure and Post Open - National 145,279.00 109,366.58 Signed 2019-01-05 2019-02-01 2019-09-20 Quotations Envelope 31 Under B2 Sub Component of Management Investments BIWRMDP at Uthal, Dhadar & Harnai PK-PMU-BIWRMDP-93196- CW-RFB / Procurement of Component B: Water, Single Stage - One 3,589,182.9 2021-04- Civil Works for Nari Gorge IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,270,000.00 Signed 2019-01-03 2019-03-11 2019-01-08 2019-03-11 2019-02-27 2019-04-29 2019-03-29 2019-09-03 2019-04-26 2020-02-07 Envelope 4 15 Integrated Scheme (Package- Management Investments 01) PK-PMU-BIWRMDP-93197- Component B: Water, CW-RFB / Construction of Single Stage - One 2,709,109.5 2021-05- IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,971,014.00 Signed 2019-02-12 2019-03-14 2019-02-17 2019-03-11 2019-03-31 2019-04-15 2019-04-30 2019-07-23 2019-05-28 2019-09-30 Nimmi Perennial Irrigation Envelope 5 27 Management Investments Scheme Page 1 PK-PMU-BIWRMDP-96459- CW-RFB / Construction of Component B: Water, Single Stage - One 2021-06- Gandacha Nurg-Hingri IDA / 58850 Infrastructure and Prior Request for Bids Open - International 8,915,217.00 0.00 Canceled 2019-02-15 2019-02-20 2019-04-03 2019-05-03 2019-06-07 Envelope 06 Integrated Scheme (Package- Management Investments 1) PK-PMU-BIWRMDP-97035- Component B: Water, CW-RFB / Construction of Single Stage - One 5,946,973.3 2021-05- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 7,464,230.00 Signed 2019-02-06 2019-02-11 2019-02-11 2019-02-13 2019-03-25 2019-04-04 2019-04-24 2019-08-21 2019-05-29 2019-09-30 Mushkaf Flood Irrigation Envelope 7 28 Management Investments Schemes PK-PMU-BIWRMDP-104392- CW-RFB / Construction of Component B: Water, Water Supply Scheme for 4 Single Stage - One 2019-12- IDA / 58850 Infrastructure and Post Request for Bids Open - National 775,362.00 0.00 Canceled 2019-03-10 2019-05-27 2019-03-15 2019-04-14 2019-04-15 2019-05-14 2019-06-18 villages within the ambit of Envelope 15 Management Investments Nari Gorge Integrated Scheme, Sibi PK-PMU-BIWRMDP-113051- CW-RFB / Construction of Component B: Water, Single Stage - One 3,642,140.1 2020-03- Gundacha Nurg Hingri IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,477,220.85 Signed 2019-05-15 2019-05-27 2019-05-20 2019-07-01 2019-07-04 2019-07-31 2019-10-08 2019-09-04 2020-04-06 Envelope 5 02 Integrated Scheme - Package Management Investments 2 (Works at Nurg Hingri) PK-PMU-BIWRMDP-73478- CW-RFB / Procurement of Works Yetabad Flood Irrigation Scheme - (Weir and Component B: Water, Single Stage - One 34,997,555.0 2020-09- Conveyance System (KM IDA / 58850 Infrastructure and Prior Request for Bids Open - International 0.00 Canceled 2018-08-30 2018-09-27 2018-11-15 2018-11-15 2018-09-04 2019-01-24 2019-02-23 2019-03-30 Envelope 1 20 0+000 to KM 6+000) and Management Investments Conveyance System and Buildings (KM 6+000 to KM 21+500) PK-PMU-BIWRMDP-93985- CW-RFB / Water Supply Component B: Water, Scheme for three villages Single Stage - One 2020-04- IDA / 58850 Infrastructure and Post Request for Bids Open - National 469,989.00 0.00 Canceled 2019-01-15 2019-03-13 2019-01-20 2019-03-11 2019-02-19 2019-04-15 2019-03-21 2019-04-18 constituting domain of Envelope 17 Management Investments Mushkaf Flood Irrigation Scheme PK-PMU-BIWRMDP-2437-CW- Component B: Water, Single Stage - One 2022-02- RFB / Flood Protection Works IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,408,021.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-12 2020-02-25 Envelope 14 - Package 1 of 5 Management Investments PK-PMU-BIWRMDP-2435-CW- RFB / Water Supply Schemes Component B: Water, Single Stage - One 2021-08- Package 2 of 4 - 3 Water IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,842,458.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-16 2020-02-29 Envelope 22 Supply Schemes in District Management Investments Loralai PK-PMU-BIWRMDP-2441-CW- RFB / Small Scale Irrigation Component B: Water, Single Stage - One 2021-12- Schemes in District Khuzdar - IDA / 58850 Infrastructure and Post Request for Bids Open - National 268,568.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-20 2020-07-03 Envelope 25 Khazeni Bent Perennial Management Investments Irrigation Scheme PK-PMU-BIWRMDP-2439-CW- RFB / Small Scale Irrigation Component B: Water, Single Stage - One 2021-09- Schemes in District Khuzdar - IDA / 58850 Infrastructure and Post Request for Bids Open - National 692,764.00 0.00 Canceled 2019-11-30 2019-12-07 2020-01-06 2020-01-27 2020-03-11 Envelope 02 Naik Mohammad Bent Management Investments Perennial Irrigation Scheme PK-PMU-BIWRMDP-2433-CW- RFB / Drilling & Development Component A: Institutions, Single Stage - One 2021-06- IDA / 58850 Post Request for Bids Open - National 947,550.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-13 2020-06-26 of Groundwater Monitoring Capacity and Information Envelope 26 Wells PK-PMU-BIWRMDP-2429-CW- RFB / Nimmi Perennial Component B: Water, Irrigation Scheme - Package 1 Single Stage - One 2022-05- IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,249,665.00 0.00 Canceled 2020-02-20 2020-03-01 2020-03-31 2020-04-21 2020-06-04 of 2 (Construction of Weir, Envelope 25 Management Investments Undersluice, & Head Regulator) PK-PMU-BIWRMDP-2438-CW- Component B: Water, Single Stage - One 2022-02- RFB / Flood Protection Works IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,323,315.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-19 2020-03-03 Envelope 21 - Package 2 of 5 Management Investments PK-PMU-BIWRMDP-2430-CW- RFB / Nimmi Perennial Irrigation System - Package 2 of 2 (Construction of Component B: Water, Irrigation Canal System, Guide Single Stage - One 2022-07- IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,924,502.00 0.00 Canceled 2020-03-16 2020-03-26 2020-05-15 2020-06-14 2020-07-28 Banks, Fall Structure, Road Envelope 18 Management Investments Culverts, Outlet Structures, Drainage Box and Pipe Culverts, Regulators and Aquaducts. PK-PMU-BIWRMDP-2434-CW- RFB / Water Supply Schemes Component B: Water, Single Stage - One 2021-06- Package 1 of 4 - Construction IDA / 58850 Infrastructure and Post Request for Bids Open - National 297,186.00 0.00 Canceled 2020-02-29 2020-03-07 2020-04-06 2020-04-27 2020-06-10 Envelope 10 of 3 Water Supply Schemes in Management Investments District Lasbela PK-PMU-BIWRMDP-113054- Component B: Water, CW-RFB / Construction of Single Stage - One 2020-03- IDA / 58850 Infrastructure and Post Request for Bids Open - National 754,691.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 Nari Gorge Water Supply Envelope 02 Management Investments Scheme PK-PMU-BIWRMDP-68771- CW-RFB / Construction of Command Area Infrastructure Component B: Water, Viz. WC, WST, KT,EWST, EWC ( Single Stage - One 2021-02- IDA / 58850 Infrastructure and Post Request for Bids Open - National 887,000.00 0.00 Canceled 2020-05-03 2020-05-08 2020-06-19 2020-07-19 2020-08-23 Perennial and Spate)( Package Envelope 19 Management Investments 1 of 3) NARI GORGE PIS COMMAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-96461- Component B: Water, CW-RFB / Construction Nari Single Stage - One 2021-06- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 5,268,116.00 0.00 Canceled 2019-02-20 2019-02-11 2019-02-25 2019-02-13 2019-04-08 2019-04-08 2019-05-08 2019-06-12 Gorge Integrated Scheme Envelope 11 Management Investments (Package-2) Page 2 PK-PMU-BIWRMDP-143842- Component B: Water, CW-RFB / Construction Nari Single Stage - One 2020-09- IDA / 58850 Infrastructure and Prior Request for Bids Open - International 5,270,000.00 0.00 Canceled 2019-11-30 2019-12-05 2020-01-16 2020-02-15 2020-03-21 Gorge Integrated Scheme Envelope 17 Management Investments (Package-2) PK-PMU-BIWRMDP-68772- CW-RFB / Construction of Command Aare Component B: Water, Single Stage - One 2021-01- Infrastructures ( Khuskaba IDA / 58850 Infrastructure and Post Request for Bids Open - National 518,000.00 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 Envelope 16 FArming) Package 1 of 10 Management Investments NARI GORGE PIS COMMAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-144874- CW-RFB / Works for Construction of Shab-e- Component B: Water, Single Stage - One 2021-12- Maidan Irrigation Scheme IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,683,871.00 0.00 Canceled 2020-03-24 2020-03-29 2020-04-02 2020-05-17 2020-06-21 Envelope 13 Package 1 of 2 - Construction Management Investments of Weir and Main Canal and Related Hydraulic Structures PK-PMU-BIWRMDP-144869- CW-RFB / Works for Construction of Sehan Component B: Water, Under Single Stage - One 2022-03- Irrigation Scheme Package 2 IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,848,000.00 0.00 Implementat 2020-06-01 2020-11-20 2020-06-06 2020-07-06 2020-08-05 2020-09-09 Envelope 03 of 3 - Construction of Main Management Investments ion Canal and Related Hydraulic Structures PK-PMU-BIWRMDP-144876- CW-RFB / Works for Construction of Shab-e- Component B: Water, Maidan Irrigation Scheme Single Stage - One 3,102,667.0 2022-03- IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,335,483.00 Signed 2020-05-18 2020-08-11 2020-05-23 2020-07-07 2020-09-15 2020-08-06 2020-10-13 2020-09-10 2020-12-15 Package 2 of 2 - Construction Envelope 8 04 Management Investments of Main Canal, Distributories and Related Hydraulic Structures PK-PMU-BIWRMDP-145601- Component B: Water, CW-RFB / Civil Works for Single Stage - One 2021-05- IDA / 58850 Infrastructure and Post Request for Bids Open - National 298,426.00 262,554.67 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 2020-06-12 Construction of Nari Gorge Envelope 03 Management Investments Water Supply Scheme PK-PMU-BIWRMDP-143841- Component B: Water, Single Stage - One 2021-04- CW-RFB / Civil Works for IDA / 58850 Infrastructure and Post Request for Bids Open - National 267,567.00 182,191.01 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-01 2020-03-02 2020-03-02 2020-04-22 2020-04-06 2020-06-12 Envelope 05 Mushkaf Water Supply Scheme Management Investments PK-PMU-BIWRMDP-153953- CW-RFB / Construction of Component B: Water, Single Stage - One 3,172,325.3 2022-05- Gundacha Nurg Hingri IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,032,258.00 Signed 2020-02-03 2020-04-30 2020-02-08 2020-03-09 2020-06-10 2020-04-08 2020-06-26 2020-05-13 2020-08-31 Envelope 4 13 Integrated Scheme - Package Management Investments 1 of 2. PK-PMU-BIWRMDP-153957- CW-RFB / Construction of Component B: Water, Single Stage - One 2022-05- Nari Gorge Integrated Scheme IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,709,677.00 0.00 Canceled 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 Envelope 03 - Package 2 of 3 - Lining of Management Investments Khajjak Channels. PK-PMU-BIWRMDP-153960- CW-RFB / Construction of Component B: Water, Single Stage - One 1,965,335.1 2022-05- Nari Gorge Integrated Scheme IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,025,806.00 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 2020-05-19 Envelope 4 03 - Package 3 of 3 - Management Investments Construction of Arand & Bori Channels PK-PMU-BIWRMDP-153985- CW-RFB / Works for Construction of Sehan Component B: Water, Irrigation Scheme - Package 1 Single Stage - One 3,680,180.3 2022-01- IDA / 58850 Infrastructure and Post Request for Bids Open - International 4,625,806.00 Signed 2020-04-13 2020-08-11 2020-04-18 2020-06-02 2020-09-15 2020-07-02 2020-10-13 2020-08-06 2020-12-15 of 3 - Construction of Weir, Envelope 1 28 Management Investments Undersluice, Head Regulator, Guide Bunds, Main Canal and Related Structures PK-PMU-BIWRMDP-159126- CW-RFB / Works for Plant Production Through Raising of Nurseries and Other Allied Component B: Water, Activities under B2 Sub Single Stage - One 2020-12- IDA / 58850 Infrastructure and Post Request for Bids Open - National 300,645.00 0.00 Canceled 2020-02-28 2020-02-24 2020-03-04 2020-04-15 2020-05-15 2020-06-19 Component Of BIWRMDP Envelope 16 Management Investments Second Phase For Following LOTs. LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 - Uthal Lot 8 – Khuzdar PK-PMU-BIWRMDP-133752- CW-RFQ / Works for Plant Production Through Raising of Nurseries and Other Allied Activities under B2 Sub component Of BIWRMDP Component B: Water, Single Stage - One 2020-08- Second Phase For Following IDA / 58850 Infrastructure and Post Request for Bids Open - National 300,645.00 0.00 Canceled 2019-10-15 2019-11-16 2019-10-20 2019-12-01 2019-12-23 2019-12-31 2020-02-10 2020-02-04 Envelope 02 LOTs. Management Investments LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 -Uthal Lot 8 - Khuzdar PK-PMU-BIWRMDP-144858- GO-RFB / Civil Works for Construction of Measurement Component A: Institutions, Single Stage - One 2021-01- Weir / Flume and Guard IDA / 58850 Post Request for Bids Open - National 451,612.00 0.00 Canceled 2020-02-17 2020-02-22 2020-03-23 2020-04-22 2020-05-27 Capacity and Information Envelope 22 Houses as part of Establishing Phase-I of Hydro-met Network. PK-PMU-BIWRMDP-159162- CW-RFQ / Civil Works for Component B: Water, Request for Single Stage - One 2020-09- Plantation at Nari Gorge and IDA / 58850 Infrastructure and Post Open - National 45,500.00 23,101.38 Signed 2020-02-22 2020-03-27 2020-06-18 Quotations Envelope 23 Mushkaf Integrated Schemes Management Investments in Nari River Basin Page 3 PK-PMU-BIWRMDP-167783- CW-RFB / Lining of Water Courses in Command Area of Nari Gorge Integrated Scheme - Lot-1 & Lot-2 with following detail: Component B: Water, Single Stage - One 2021-07- Lot-1: Water Courses at IDA / 58850 Infrastructure and Post Request for Bids Open - National 795,180.00 745,887.52 Signed 2020-04-13 2020-04-23 2020-04-18 2020-05-18 2020-06-05 2020-06-17 2020-08-28 2020-07-22 2020-11-06 Envelope 21 Bakhra S.Khan & Ghulam Management Investments Bolak, Gullu Shaher, Luni & Sib Jarib Lot-2: Water Courses at Khajjak, Kurak, Mazre & Marghazani PK-PMU-BIWRMDP-171492- CW-RFB / Works for Plant Production Through Raising of Nurseries and Other Allied Component B: Water, Activities under B2 Sub Single Stage - One 2021-08- IDA / 58850 Infrastructure and Post Request for Bids Open - National 300,645.00 295,921.80 Signed 2020-05-04 2020-05-01 2020-05-09 2020-06-08 2020-06-10 2020-07-08 2020-08-10 2020-08-12 2020-09-25 Component Of BIWRMDP Envelope 11 Management Investments Second Phase For Following LOTs. LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 - Uthal Lot 8 – Khuzdar PK-PMU-BIWRMDP-172748- CW-RFB / Construction of Component B: Water, Single Stage - One 2,880,032.8 2022-05- Nari Gorge Integrated Scheme IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,593,750.00 Signed 2020-05-09 2020-05-10 2020-05-11 2020-06-10 2020-06-10 2020-07-10 2020-06-26 2020-08-14 2020-09-05 Envelope 6 06 Package 2 of 3 - Lining of Management Investments Khajjak Channels PK-PMU-BIWRMDP-144866- CW-RFB / Works for Construction of Sehan Irrigation Scheme - Lot No.1 Component B: Water, Single Stage - One 2021-03- Construction of Weir, IDA / 58850 Infrastructure and Post Request for Bids Open - National 4,567,000.00 0.00 Canceled 2020-05-29 2020-06-03 2020-07-15 2020-08-14 2020-09-18 Envelope 17 Undersluice, Head Regulator, Management Investments Guide Bunds, Main Canal and Related Structures - Civil Works PK-PMU-BIWRMDP-144870- CW-RFB / Works for Construction of Sehan Irrigation Scheme Package 3 Component B: Water, Under of 3 - Construction of Dis Single Stage - One 2022-05- IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,680,358.00 0.00 Implementat 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-30 2021-02-11 tributaries & Related Envelope 07 Management Investments ion Hydraulic Structures and Augmentation of Potable Water Supply System of Mekhtar Town PK-PMU-BIWRMDP-203186- CW-RFB / Works for Construction of Shab-e- Component B: Water, Under Single Stage - One 2022-05- Maidan Irrigation Scheme IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,850,662.00 0.00 Implementat 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-30 2021-02-11 Envelope 07 Package 1 of 2 - Construction Management Investments ion of Weir, Main Canal & Related Hydraulic Structures PK-PMU-BIWRMDP-143843- CW-RFB / Works for dry- afforestation, rangeland Component B: Water, Under Single Stage - One 2022-05- improvement through water IDA / 58850 Infrastructure and Post Request for Bids Open - National 525,078.00 0.00 Implementat 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-30 2021-02-11 Envelope 07 harvesting structures and Management Investments ion plantation/ sowing Package 1 - Nari River Basin PK-PMU-BIWRMDP-203187- CW-RFB / Works for dry- afforestation, rangeland Component B: Water, Under Single Stage - One 2022-05- improvement through water IDA / 58850 Infrastructure and Post Request for Bids Open - National 681,818.00 0.00 Implementat 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-30 2021-02-11 Envelope 07 harvesting structures and Management Investments ion plantation/ sowing Package 2 - Porali River Basin PK-PMU-BIWRMDP-206305- CW-RFB / Construction of Component B: Water, Pending Single Stage - One 2021-10- Lined Water Courses for Nari IDA / 58850 Infrastructure and Post Request for Bids Open - National 285,000.00 0.00 Implementat 2020-12-15 2020-12-20 2021-01-31 2021-03-02 2021-04-06 Envelope 03 Basin (Narigurage) package 2 Management Investments ion 0f 2 PK-PMU-BIWRMDP-206310- Component B: Water, Pending CW-RFB / Civil Works Single Stage - One 2021-09- IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,349,953.00 0.00 Implementat 2020-12-10 2020-12-15 2021-01-26 2021-02-25 2021-04-01 Construction of Check Dams Envelope 28 Management Investments ion Nari Basin package 1 of 2 PK-PMU-BIWRMDP-206297- CW-RFB / Construction of Component B: Water, Pending Water storage Tanks and Single Stage - One 2021-09- IDA / 58850 Infrastructure and Post Request for Bids Open - National 730,348.00 0.00 Implementat 2020-12-15 2020-12-20 2021-01-19 2021-02-18 2021-03-25 Katcha Tracks for Nari Basin Envelope 21 Management Investments ion Package 1 of 2 (Nari Gorge & Mushkaf) PK-PMU-BIWRMDP-206302- CW-RFB / Construction of Component B: Water, Under Water Storage Tanks and Single Stage - One 2021-09- IDA / 58850 Infrastructure and Post Request for Bids Open - National 557,156.00 0.00 Implementat 2020-12-15 2020-12-14 2020-12-20 2021-01-19 2021-02-18 2021-03-25 Katcha Tracks for Poralis Envelope 21 Management Investments ion Basin Package 1 of 2 (Gundacha-Nimmi) PK-PMU-BIWRMDP-213890- Component B: Water, Pending CW-RFB / Construction of Single Stage - One 2022-06- IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,313,787.00 0.00 Implementat 2021-01-18 2021-01-23 2021-02-22 2021-03-15 2021-04-19 Flood Protection Works at Envelope 13 Management Investments ion Porali River Basin PK-PMU-BIWRMDP-213891- CW-RFB / Construction of Component B: Water, Pending Single Stage - One 2022-06- Flood Protection Works at Nari IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,519,027.00 0.00 Implementat 2021-01-25 2021-01-30 2021-03-01 2021-03-22 2021-04-26 Envelope 20 River Basin - Package 1, Management Investments ion Works at Tariqabad PK-PMU-BIWRMDP-206313- Component B: Water, Pending CW-RFB / Civil Works Single Stage - One 2022-05- IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,161,795.00 0.00 Implementat 2021-02-10 2021-02-15 2021-03-29 2021-04-28 2021-06-02 Construction of Check dams Envelope 01 Management Investments ion for Porali Basin package 2 of 2 Page 4 PK-PMU-BIWRMDP-220308- Component B: Water, Pending CW-RFB / Civil Works for Single Stage - One 2022-06- IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,848,402.00 0.00 Implementat 2021-02-24 2021-03-01 2021-03-31 2021-04-30 2021-06-04 Construction of Sibi Town Envelope 04 Management Investments ion Water Supply Scheme PK-PMU-BIWRMDP-223765- CW-RFB / Procurement of Component B: Water, Pending Single Stage - One 2022-06- Works for Construction of IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,380,000.00 0.00 Implementat 2021-03-25 2021-03-30 2021-04-29 2021-05-29 2021-06-29 Envelope 29 Perennial Irrigation Schemes Management Investments ion of District Khuzdar GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2336-GO- RFQ / Office Equipment for Component C: Project PMU - Desktops, laptops, Request for Single Stage - One IDA / 58850 Management and Technical Prior Open - National 50,000.00 49,337.27 Signed 2016-10-08 2016-11-03 2016-11-01 2016-12-03 printers, scanners, cameras, Quotations Envelope Assistance internet devices, multimedia etc. PK-PMU-BIWRMDP-2338-GO- RFQ / Furniture & Fixture for Component C: Project Request for Single Stage - One PMU at Quetta including IDA / 58850 Management and Technical Post Open - National 34,299.00 39,744.82 Completed 2016-10-27 2016-11-29 2016-11-28 2016-12-27 2017-01-10 Quotations Envelope Reversible Split AC for PD Assistance Office PK-PMU-BIWRMDP-2406-GO- Component C: Project Request for Single Stage - One RFQ / Procurement of Diesel IDA / 58850 Management and Technical Post Open - National 15,314.00 19,553.87 Completed 2016-11-14 2016-12-14 2017-04-20 2017-01-13 2017-05-03 Quotations Envelope Generator for PMU Assistance PK-PMU-BIWRMDP-2413-GO- Component C: Project Request for Single Stage - One RFQ / Furniture & Fixture for IDA / 58850 Management and Technical Post Open - National 25,842.00 27,052.71 Completed 2016-11-18 2016-12-24 2017-03-06 2017-01-23 2017-05-04 Quotations Envelope PIUs at Sibi & Uthal Assistance PK-PMU-BIWRMDP-2414-GO- RFQ / Field Equipment - Component C: Project Relaskops, Clinometers, Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 21,535.00 25,063.67 Signed 2016-12-09 2017-01-12 2017-12-22 2017-02-11 Range Finders, Level Machines Quotations Envelope Assistance etc. for Watershed & Rangeland Management PK-PMU-BIWRMDP-2415-GO- Component C: Project RFQ / Procurement of Video Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 12,443.00 13,146.03 Completed 2016-11-10 2016-12-14 2017-05-17 2017-01-13 2017-06-18 Conference Equipment for Quotations Envelope Assistance PMU PK-PMU-BIWRMDP-2417-GO- Component C: Project Request for Single Stage - One RFQ / Purchase of Computer IDA / 58850 Management and Technical Post Open - National 47,856.00 29,805.88 Signed 2016-11-30 2017-01-21 2018-01-15 2017-02-26 Quotations Envelope Software - GIS & Autocad Assistance PK-PMU-BIWRMDP-14395- Component C: Project GO-RFQ / Purchase of Office Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 72,000.00 72,486.33 Signed 2017-05-11 2017-06-02 2017-06-15 2017-06-30 Equipment for PMU & PIUs at Quotations Envelope Assistance Sibi & Uthal PK-PMU-BIWRMDP-14456- GO-RFQ / Purchase of Split Component C: Project Request for Single Stage - One Air Conditioners, Refrigerators IDA / 58850 Management and Technical Post Open - National 50,500.00 40,052.89 Signed 2017-05-12 2017-06-05 2017-11-23 2017-07-05 Quotations Envelope etc for PMU & PIUs and Diesel Assistance Generators for PIUS PK-PMU-BIWRMDP-18626- NC-RFQ / Purchase of Component C: Project Request for Single Stage - One Software - MS Office, Adobe IDA / 58850 Management and Technical Post Open - National 29,400.00 25,688.50 Signed 2017-08-02 2017-09-01 2018-01-15 2017-10-16 Quotations Envelope Pro, Microsoft Project, Assistance Autocad Civil 3D etc. PK-PMU-BIWRMDP-18629- Component C: Project Request for Single Stage - One GO-RFQ / Special Desktop IDA / 58850 Management and Technical Post Open - National 9,375.00 7,467.27 Signed 2017-08-05 2017-09-08 2018-01-15 2017-10-23 Quotations Envelope Computers for Arc GIS Assistance PK-PMU-BIWRMDP-2409-GO- Component C: Project RFQ / Procurement of Office Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 43,070.00 0.00 Canceled 2016-11-21 2016-12-25 2017-01-24 Equipment & Generators for Quotations Envelope Assistance PIUs at Sibi & Uthal PK-PMU-BIWRMDP-34361- Component B: Water, GO-RFQ / Procurement of Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 20,000.00 7,284.88 Signed 2017-11-20 2018-01-15 2018-01-10 2018-07-14 Furniture for Agriculture Field Quotations Envelope Management Investments Office PK-PMU-BIWRMDP-34363- Component B: Water, GO-RFQ / Procurement of IT Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 18,000.00 11,234.74 Signed 2017-11-20 2018-01-15 2018-01-15 2018-05-15 Equipment for Agriculture Quotations Envelope Management Investments Field Offices PK-PMU-BIWRMDP-34364- Component B: Water, Request for Single Stage - One GO-RFQ / Procurement of IDA / 58850 Infrastructure and Post Open - National 80,000.00 39,815.82 Signed 2017-11-20 2018-01-15 2018-01-05 2018-05-15 Quotations Envelope Survey Equipment Management Investments PK-PMU-BIWRMDP-2408-GO- Component C: Project RFQ / Procurement of Request for Single Stage - One IDA / 58850 Management and Technical Prior Open - National 71,784.00 0.00 Canceled 2016-12-07 2017-01-26 2017-04-26 Additional Vehicles for Project Quotations Envelope Assistance - 3 Door Jeeps PK-PMU-BIWRMDP-2418-GO- RFB / Supply/ installation of Hdyro-meteorological observation stations, rain Component A: Institutions, Single Stage - One gauging stations, stream IDA / 58850 Post Request for Bids Open - International 2,692,000.00 0.00 Canceled 2017-11-19 2017-11-29 2018-01-20 2018-02-19 2018-03-22 2019-09-13 Capacity and Information Envelope gauging stations and groundwater observation wells including establishment of Data Centre Page 5 PK-PMU-BIWRMDP-96456- GO-RFB / Establishment of Pending Hydro-met networks Pilot Component A: Institutions, Single Stage - One IDA / 58850 Post Request for Bids Open - National 770,000.00 0.00 Implementati 2019-02-11 2019-02-16 2019-03-18 2019-04-17 2019-05-22 2020-05-21 Project (Hydro-met Data Capacity and Information Envelope on Collection and Management System) PK-PMU-BIWRMDP-153962- GO-RFB / Procurement of Component B: Water, Single Stage - One Goods for Construction of IDA / 58850 Infrastructure and Post Request for Bids Open - National 406,451.00 341,590.17 Signed 2020-03-05 2020-05-10 2020-03-10 2020-04-09 2020-06-10 2020-05-09 2020-08-08 2020-06-13 2020-09-25 2021-02-08 Envelope Nari Gorge Water Supply Management Investments Scheme PK-PMU-BIWRMDP-153979- Component B: Water, GO-RFB / Procurement of Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 198,806.00 207,540.98 Signed 2020-03-05 2020-05-07 2020-03-10 2020-04-09 2020-06-10 2020-05-09 2020-08-08 2020-06-13 2020-09-25 2021-02-08 Goods for Construction of Envelope Management Investments Mushkaf Water Supply Scheme PK-PMU-BIWRMDP-159160- GO-RFQ / Purchase of Plants Component B: Water, Request for Single Stage - One for Plantation at Nari Gorge IDA / 58850 Infrastructure and Post Open - National 26,000.00 23,717.20 Signed 2020-02-22 2020-03-27 2020-05-29 2020-09-23 Quotations Envelope and Mushkaf Integrated Management Investments Schemes of Nari River Basin PK-PMU-BIWRMDP-166190- GO-DIR / Procurement of Goods Pkg 2: : Lot 1,Mobile X- Ray Machines with CR-System Component A: Institutions, / DR-Based Mobil X-Ray IDA / 58850 Post Direct Selection Direct 2,017,164.00 1,759,284.64 Signed 2020-03-30 2020-03-25 2020-04-04 2020-04-03 2020-05-09 2020-07-22 2020-11-05 2020-08-21 Capacity and Information Machines along with Dry Laser Imagers, Lot 2, Patient Monitors,Lot 3, ICU Ventilators PK-PMU-BIWRMDP-187938- GO-RFQ / Procurement of Component C: Project Miscellaneous Furniture and Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 11,500.00 11,233.61 Signed 2020-08-21 2020-09-26 2021-01-11 2020-11-10 Equipment e.g Storage Quotations Envelope Assistance Cabinets, Voltage Stabilizer, LED TV etc. PK-PMU-BIWRMDP-166183- GO-DIR / Procurement of Goods Package No: 1 Full Fowler Hospital Motorized/ Manual Beds along Component A: Institutions, with following Accessories: a) IDA / 58850 Post Direct Selection Direct 73,760.00 0.00 Canceled 2020-03-30 2020-04-04 2020-05-09 2020-11-05 Capacity and Information Mattress b) IV Pole (Separate / Built-In) c) Over Head Table d) Bed Side Locker e) Bed Side Screen f)Patient Footstep g) Pillow & Cover PK-PMU-BIWRMDP-135510- GO-RFB / Procurement of Goods for Establishment of Hydro-met Network Phase-I - Under Lot No 1. Design, supply and Component A: Institutions, Single Stage - One IDA / 58850 Post Request for Bids Open - International 493,103.00 0.00 Implementati 2020-11-09 2020-12-14 2020-11-14 2020-12-15 2020-12-29 2021-01-28 2021-03-12 2021-11-07 installation of 9 No Automatic Capacity and Information Envelope on Stations, Lot No.2 Design, supply and installation of 2 No Stream flow Gauging Stations PK-PMU-BIWRMDP-206307- Component B: Water, Under GO-RFB / Goods: Procurement Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-12-15 2020-12-14 2020-12-20 2021-01-19 2021-02-18 2021-03-25 2021-09-21 of PVC Pipelines forPorali Envelope Management Investments on Basin (Gundacha-Nimmi) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2442-NC- RFQ / Project Website Design Component C: Project Development, Domain Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 2,400.00 2,943.83 Signed 2016-10-20 2016-11-26 2016-11-16 2017-01-10 Registration, Hosting, Quotations Envelope Assistance Maintenance and Updating fro One Year PK-PMU-BIWRMDP-18623- NC-DIR / Purchase of 0.3m to Component C: Project 0.5m Resolution Satellite IDA / 58850 Management and Technical Post Direct Selection Direct 54,600.00 0.00 Canceled 2017-07-26 2017-10-25 2017-07-31 2017-11-06 2017-08-25 2017-10-09 Image for Nari Gorge & Assistance Gundacha Area. PK-PMU-BIWRMDP-19640- Component C: Project NC-DIR / Purchase of Arc GIS IDA / 58850 Management and Technical Post Direct Selection Direct 30,563.00 0.00 Canceled 2017-07-19 2017-10-26 2017-07-24 2017-08-15 2017-09-29 - Two Basic & One Standard Assistance Version PK-PMU-BIWRMDP-38144- NC-RFQ / Baseline Component C: Project Request for Single Stage - One sampling(Laboratory Testing) IDA / 58850 Management and Technical Post Open - National 6,000.00 28,014.89 Signed 2018-01-05 2018-03-02 2018-01-04 2018-05-01 Quotations Envelope of two integrated schemes for Assistance ESMP PK-PMU-BIWRMDP-45893- NC-RFQ / Baseline Sampling(Laboratory Testing) Component B: Water, Request for Single Stage - One (Ambient IDA / 58850 Infrastructure and Post Open - National 35,000.00 57,805.06 Signed 2018-02-01 2018-02-27 2018-02-21 2018-03-15 Quotations Envelope Air/Noise/Water/Soil) for Nur- Management Investments Hingri-Gunacha Irrigation Scheme Scheme for ESMP PK-PMU-BIWRMDP-68865- NC-RFQ / Procurement of Demo Plots (PLL, HEIS, Component B: Water, Livestock, Tunnel farming, Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 95,500.00 0.00 Canceled 2019-11-20 2020-01-15 2020-07-13 nurseries, crops) First Lot Quotations Envelope Management Investments GUNDACHA & NARI GUARGE PIS COMMAND AREA INFRSTRUCTURE Page 6 PK-PMU-BIWRMDP-144898- Component C: Project Pending NC-RFQ / PROCUREMENT OF Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 30,000.00 0.00 Implementati 2020-03-03 2020-03-26 2020-09-22 FINANCIAL/ACCOUNTING & Quotations Envelope Assistance on PAYROLL SOFTWARE PK-PMU-BIWRMDP-65562- NC-RFQ / Environmental Component C: Project Request for Single Stage - One Baseline studies (Laboratory IDA / 58850 Management and Technical Post Open - National 100,000.00 81,189.59 Signed 2020-02-05 2020-04-01 2020-08-19 2020-09-28 Quotations Envelope Testing) for different schemes Assistance regarding ESMPs & Checklists PK-PMU-BIWRMDP-190066- CW-DIR / Mangroves Component B: Water, Pending Restoration and Plantation in IDA / 58850 Infrastructure and Post Direct Selection Direct 117,420.00 0.00 Implementati 2020-09-29 2020-10-01 2020-10-16 2021-10-16 MianiHor (Coastal Area of Management Investments on Porali River Basin) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2240-CS- Component C: Project QCBS / Project Supervision & Quality And Cost- IDA / 58850 Management and Technical Prior Open - International 8,824,655.00 9,592,440.89 Signed 2016-10-18 2016-11-20 2016-11-13 2016-11-23 2016-11-30 2017-04-05 2017-01-05 2017-05-29 2017-02-04 2017-08-29 2017-03-04 2017-09-21 2017-04-03 2017-11-30 2022-10-31 Implementation Assistance Based Selection Assistance Consultancy PK-PMU-BIWRMDP-2335-CS- Component C: Project Consultant CQS / Hiring Accountancy IDA / 58850 Management and Technical Post Qualification Open - National 103,369.00 180,643.38 Signed 2016-11-15 2017-02-10 2016-12-13 2017-01-06 2017-05-16 2017-01-31 2017-07-18 2017-02-24 2017-10-11 2022-10-31 Firm for Quarterly Internal Assistance Selection Audit PK-PMU-BIWRMDP-2245-CS- Component C: Project Quality And Cost- QCBS / Monitoring & IDA / 58850 Management and Technical Prior Open - International 1,758,231.00 0.00 Canceled 2016-10-24 2017-01-03 2016-11-21 2017-02-26 2016-12-15 2017-01-20 2017-02-19 2017-03-19 2017-04-22 2022-10-30 Based Selection Evaluation Consultancy Assistance PK-PMU-BIWRMDP-2334-CS- Component C: Project Consultant INDV / Hiring of Accountancy IDA / 58850 Management and Technical Prior Qualification Open - National 4,786.00 4,173.09 Signed 2016-10-27 2017-02-23 2016-11-21 2016-12-15 2017-08-07 2016-12-25 2017-09-12 2017-01-14 2017-09-22 2017-02-13 Firm for External Audit of Assistance Selection Retroactive Financing PK-PMU-BIWRMDP-50078-CS- CQS / HIRING A CONSULTING Component C: Project Consultant FIRM FOR THE PREPARATION IDA / 58850 Management and Technical Post Qualification Open - National 170,000.00 0.00 Canceled 2018-03-15 2018-03-14 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-01-19 OF CULTURAL HERITAGE Assistance Selection MANAGEMENT PLAN (CHMP) PK-PMU-BIWRMDP-109329- CS-CQS / Hiring of Audit Firm Component C: Project Consultant to Carryout Special Audit of IDA / 58850 Management and Technical Post Qualification Open - National 10,000.00 2,437.30 Signed 2019-04-08 2019-04-11 2019-04-23 2019-05-10 2019-05-01 2019-05-17 2019-05-01 2019-05-21 2019-05-03 2019-06-04 Project Supervision & Assistance Selection Implementation Assistance Consultants PK-PMU-BIWRMDP-2250-CS- Component C: Project Quality And Cost- QCBS / Institutional Reforms IDA / 58850 Management and Technical Post Open - International 765,697.00 0.00 Canceled 2018-10-15 2018-11-14 2018-12-15 2019-01-29 2019-02-23 2019-03-30 2019-04-30 2020-04-29 Based Selection Consultants Assistance PK-PMU-BIWRMDP-135514- Component C: Project Least Cost CS-LCS / Hiring Monitoring & IDA / 58850 Management and Technical Post Open - National 550,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2020-10-22 Selection Evaluation Consultancy Assistance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2315-CS- Component C: Project Individual INDV / Social Safeguards IDA / 58850 Management and Technical Post Consultant Open 103,369.00 4,178.54 Terminated 2016-10-28 2016-12-08 2016-12-18 2017-04-10 2016-12-25 2017-04-24 2017-01-06 2017-04-25 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2317-CS- Component C: Project Individual INDV / Communications IDA / 58850 Management and Technical Post Consultant Open 33,021.00 3,132.42 Terminated 2016-10-28 2016-12-08 2016-12-24 2017-05-17 2016-12-31 2017-01-12 2017-05-17 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2319-CS- Component C: Project Individual INDV / Water Resources IDA / 58850 Management and Technical Post Consultant Open 87,864.00 6,323.39 Terminated 2016-10-28 2017-01-04 2017-01-11 2017-01-23 2017-12-20 2022-10-31 Specialist Assistance Selection Component C: Project Individual PK-PMU-BIWRMDP-2320-CS- IDA / 58850 Management and Technical Post Consultant Open 87,864.00 3,613.37 Terminated 2016-11-21 2016-12-08 2017-01-07 2017-10-20 2017-01-14 2017-10-20 2017-01-26 2017-10-23 2022-10-31 INDV / Agriculture Specialist Assistance Selection PK-PMU-BIWRMDP-2321-CS- Component C: Project Individual INDV / Environmental IDA / 58850 Management and Technical Post Consultant Open 86,141.00 3,611.41 Terminated 2016-10-28 2016-12-08 2016-12-30 2017-07-10 2017-01-06 2017-07-05 2017-01-18 2017-07-14 2022-10-31 Safeguards Specialist Assistance Selection PK-PMU-BIWRMDP-2325-CS- Component C: Project Individual INDV / Monitoring & IDA / 58850 Management and Technical Post Consultant Open 117,152.00 1,993.36 Terminated 2016-11-21 2016-12-08 2017-01-30 2017-02-06 2017-04-13 2017-02-18 2017-05-02 2022-10-31 Evaluation Specialist Assistance Selection PK-PMU-BIWRMDP-2326-CS- Component C: Project Individual INDV / Matching Grant IDA / 58850 Management and Technical Post Consultant Open 86,141.00 2,184.24 Terminated 2016-11-21 2016-12-08 2017-01-25 2017-04-17 2017-02-01 2017-04-20 2017-02-13 2017-04-27 2022-10-31 2018-09-15 Specialist Assistance Selection PK-PMU-BIWRMDP-2332-CS- Component C: Project Individual INDV / Gender Development IDA / 58850 Management and Technical Post Consultant Open 51,685.00 2,183.20 Terminated 2016-11-21 2016-12-08 2017-01-13 2017-09-25 2017-01-20 2017-02-01 2017-10-03 2022-10-31 Specialist Assistance Selection Component C: Project Individual PK-PMU-BIWRMDP-2333-CS- IDA / 58850 Management and Technical Post Consultant Open 68,338.00 0.00 Canceled 2016-11-21 2016-12-08 2017-02-09 2017-02-16 2017-02-28 2022-10-31 INDV / Livestock Specialist Assistance Selection Page 7 Component C: Project Individual PK-PMU-BIWRMDP-2318-CS- IDA / 58850 Management and Technical Prior Consultant Open 117,152.00 0.00 Canceled 2016-10-27 2016-12-01 2016-12-11 2016-12-18 2016-12-30 2022-10-30 INDV / Procurement Specialist Assistance Selection PK-PMU-BIWRMDP-19626-CS- Component C: Project Individual INDV / Hiring of Procurement IDA / 58850 Management and Technical Post Consultant Open 275,071.00 3,320.53 Terminated 2017-07-14 2017-09-01 2017-08-16 2017-08-14 2017-08-30 2017-09-29 2017-09-14 2017-09-29 2022-11-06 Specialist Assistance Selection PK-PMU-BIWRMDP-2308-CS- Component C: Project Individual INDV / Financial Management IDA / 58850 Management and Technical Prior Consultant Open 116,769.00 0.00 Canceled 2016-10-08 2016-10-29 2016-11-09 2016-11-08 2016-11-15 2016-11-18 2022-11-01 Specialist at Project Assistance Selection Management Unit Quetta PK-PMU-BIWRMDP-26486-CS- Component C: Project Individual INDV / Hiring of Financial IDA / 58850 Management and Technical Post Consultant Open 285,714.00 29,917.08 Terminated 2017-09-07 2017-07-28 2017-10-03 2016-11-23 2017-10-10 2016-11-23 2017-10-22 2016-11-22 2022-10-31 Management Specialist Assistance Selection PK-PMU-BIWRMDP-38131-CS- Component C: Project Individual CDS / Hiring of Individual IDA / 58850 Management and Technical Post Consultant Limited 3,000.00 26,196.92 Signed 2017-11-27 2017-11-30 2017-12-02 2017-12-07 2017-12-22 2017-12-15 2017-12-27 2018-01-15 Consultant(Environmental Assistance Selection Specialist) for short term PK-PMU-BIWRMDP-7458-CS- Individual INDV / Hiring of Hydrologist Component A: Institutions, IDA / 58850 Post Consultant Open 50,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2017-11-11 for Design of Hydro-met Capacity and Information Selection Network PK-PMU-BIWRMDP-2323-CS- Component C: Project Individual INDV / Training Management IDA / 58850 Management and Technical Post Consultant Open 72,358.00 0.00 Canceled 2016-11-21 2016-12-08 2017-01-19 2017-01-26 2017-02-07 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-60509-CS- Component C: Project Individual INDV / Hiring of IDA / 58850 Management and Technical Post Consultant Open 80,000.00 0.00 Canceled 2018-04-24 2018-06-12 2018-07-03 2018-08-07 2019-02-03 Environmental Safeguard Assistance Selection Specialist PK-PMU-BIWRMDP-61675-CS- INDV / Hiring of Individual Individual Component A: Institutions, Consultant for National IDA / 58850 Prior Consultant Direct 9,000.00 0.00 Canceled 2018-05-04 2018-05-04 2018-05-06 2018-05-07 2018-05-08 2018-05-22 Capacity and Information Consultative Workshop foe Selection Establishment of BWRMA PK-PMU-BIWRMDP-61884-CS- INDV / Hiring of Individual Consultant to Facilitate in Individual Holding of National Component A: Institutions, IDA / 58850 Post Consultant Direct 9,000.00 7,341.82 Completed 2018-05-08 2018-05-08 2018-05-08 2018-05-08 2018-05-09 2018-05-08 2018-05-09 2018-05-10 2018-05-19 2018-05-18 Consultative Workshop for Capacity and Information Selection Establishment of Balochistan Water Resource Management Authority. PK-PMU-BIWRMDP-92788-CS- Component C: Project Individual FBS / Hiring of Individual IDA / 58850 Management and Technical Post Consultant Open 15,652.00 1,271.64 Signed 2019-02-05 2019-03-08 2019-04-09 2019-03-13 2019-03-27 2019-04-22 2020-03-26 2020-04-22 Consultant - Financial Assistance Selection Management Specialist PK-PMU-BIWRMDP-97771-CS- Component C: Project Individual INDV / Hiring of Procurement IDA / 58850 Management and Technical Post Consultant Open 15,652.00 1,259.19 Signed 2019-02-05 2019-03-08 2019-04-21 2019-03-15 2019-04-22 2019-03-30 2019-04-23 2020-03-29 Specialist to work as Assistance Selection Individual Consultant PK-PMU-BIWRMDP-104301- CS-INDV / Selection of Social Component C: Project Individual Safeguards IDA / 58850 Management and Technical Post Consultant Open 13,043.00 1,255.03 Signed 2019-03-10 2019-03-21 2019-04-28 2019-05-19 2019-06-23 2019-04-23 2019-12-20 Specialist/Individual Assistance Selection Consultant PK-PMU-BIWRMDP-104309- CS-INDV / Selection of Component C: Project Individual Environmental Safeguards IDA / 58850 Management and Technical Post Consultant Open 13,043.00 1,657.00 Signed 2019-03-10 2019-04-28 2019-04-19 2019-05-19 2019-05-19 2019-06-23 2019-05-13 2019-12-20 Specialist/Individual Assistance Selection Consultant PK-PMU-BIWRMDP-174159- Component C: Project Individual CS-INDV / Hiring of M&E IDA / 58850 Management and Technical Post Consultant Open 18,750.00 1,088.01 Signed 2020-05-21 2020-05-20 2020-07-19 2020-08-07 2020-07-29 2020-08-07 2020-08-19 2020-09-01 2021-08-19 Specialist to work as Assistance Selection Individual Consultant at PMU PK-PMU-BIWRMDP-174177- Component C: Project CS-INDV / Hiring of Gender IDA / 58850 Management and Technical Post Direct Selection Direct 18,750.00 1,070.63 Signed 2020-06-02 2020-05-22 2020-06-12 2020-06-25 2020-07-10 2020-07-01 2021-07-10 Specialist to work at PMU as Assistance Individual Consultant PK-PMU-BIWRMDP-187935- Component C: Project Individual CS-INDV / Hiring of IDA / 58850 Management and Technical Post Consultant Open 19,354.00 1.57 Signed 2020-08-09 2020-08-11 2020-09-12 2020-11-10 2020-09-19 2020-11-11 2020-10-01 2020-11-25 2021-10-01 Environmental Safeguards Assistance Selection Specialist PK-PMU-BIWRMDP-215734- Individual Component A: Institutions, CS-INDV / Hiring of Water IDA / 58850 Post Consultant Open 37,500.00 0.00 Under Review 2021-01-27 2021-01-15 2021-03-21 2021-04-11 2021-05-02 2022-05-02 Capacity and Information Resource Specialist Selection PK-PMU-BIWRMDP-218775- Component C: Project Individual Under CS-INDV / hiring of Gender IDA / 58850 Management and Technical Post Consultant Open 18,750.00 0.00 2021-02-15 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2022-06-30 Implementation Specialist for PMU Assistance Selection PK-PMU-BIWRMDP-220430- Individual Component A: Institutions, Pending CS-INDV / Hiring of Water IDA / 58850 Post Consultant Open 37,500.00 0.00 2021-03-02 2021-04-24 2021-05-08 2021-05-23 2022-05-23 Capacity and Information Implementation Governance Specialist Selection PK-PMU-BIWRMDP-226348- CS-CDS / Technical Component A: Institutions, Pending Assistance for Institutional Re- IDA / 58850 Post Direct Selection Direct 320,000.00 0.00 2021-03-30 2021-04-09 2021-05-10 2022-05-10 Capacity and Information Implementation structuring and Legal Reforms in Water Sector Page 8