PROCUREMENT PLAN Project information: Country - Cooperative Republic of Guyana Project Name – Guyana Petroleum Resources Governance and Management Project (GPRGMP) Project No. – P166730 Project Implementation agency: Ministry of the Presidency, Department of Energy Date of the Procurement Plan: April 10, 2019 Period covered by this Procurement Plan: April 10, 2019 to April 10, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Laws of Guyana – Procurement Act 2003 and its respective updates, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods “Not Applicable” PROCUREMENT Guyana : Guyana Petroleum Resources Governance and Management Project PLAN General Information Country: Guyana Bank’s Approval Date of the Original Procurement Plan: 2019-04-10 2021-02-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166730 GPN Date: 2019-03-29 Project Name: Guyana Petroleum Resources Governance and Management Project Loan / Credit No: IDA / V2160, IDA / 63820 D Executing Agency(ies): epartment of Energy WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GPRGMP/G/DC/2019/01 / Component - D. Project Procurement of software for IDA / V2160 Management & Project Prior Direct Selection Direct 155,005.56 Signed 2019-03-28 2019-05-08 2019-04-02 2019-05-17 2019-05-07 2019-08-07 2019-11-03 petroleum data management Preparation Facility system GPRGMP/G/RFQ/2019-01 / Pending Procurement of Hardware for Component – B Capacity Request for Single Stage - One IDA / V2160 Post Limited 0.00 Implementati 2019-10-04 2019-11-29 2020-02-27 petroleum data management Building of Key Institutions Quotations Envelope on system GPRGMP/G/NS/2019-01 / Component - D. Project Pending Request for Single Stage - One Procurement of Office and IDA / V2160 Management & Project Post Limited 0.00 Implementati 2019-10-18 2019-12-13 2020-03-12 Quotations Envelope Computer Equipment Preparation Facility on GPRGMP/G/DC/2020/01 / Procurement of Petroleum Component – B Capacity IDA / V2160 Post Direct Selection Direct 57,434.52 Signed 2020-08-21 2020-08-24 2020-08-26 2020-08-21 2020-09-17 2020-09-04 2022-09-17 Data Management Software Building of Key Institutions Renewal License - A NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GPRGMP/G/2019-02 / Component - D. Project Pending Request for Single Stage - One Publications and IDA / V2160 Management & Project Post Limited 0.00 Implementati 2019-10-20 2019-12-15 2020-12-14 Quotations Envelope Communications Preparation Facility on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GPRGMP/QCBS/2019/0-1 / Component- A. Enhancement Hiring of a law firm to provide Quality And Cost- IDA / V2160 of Legal Framework and Prior Open - International 2,194,440.67 Terminated 2019-06-03 2019-04-15 2019-06-24 2019-04-25 2019-08-07 2019-07-17 2019-09-04 2019-08-20 2019-10-04 2019-11-12 2019-11-08 2020-01-09 2019-12-13 2020-01-31 2020-12-12 advisory services on O&G Based Selection Stakeholder Engagement sector legislation GPRGMP/QCBS/2019/02 / Hiring of a communications Component- A. Enhancement Quality And Cost- Pending firm to implement GOG IDA / V2160 of Legal Framework and Post Open - International 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 Based Selection Implementation communications' strategy on Stakeholder Engagement O&G GPRGMP/QCBS/2019/03 / Component - C. Hiring of an Independent Quality And Cost- IDA / V2160 Enhancement of Fiscal Post Open - International 117,560.00 Signed 2019-09-02 2019-08-19 2019-09-23 2019-08-26 2019-11-06 2019-11-14 2019-12-04 2019-12-10 2020-01-03 2020-01-07 2020-02-07 2020-02-05 2020-03-13 2020-06-11 2021-03-13 Administrator to prepare EITI Based Selection Management reports (3) GPRGMP/QCBS/2019/04 / Component - C. Quality And Cost- Pending Hiring of a firm to provide IDA / V2160 Enhancement of Fiscal Post Open - International 0.00 2019-08-19 2019-09-09 2019-10-23 2019-11-20 2019-12-20 2020-01-24 2020-02-28 2021-02-27 Based Selection Implementation cost audit advisory services Management GPRGMP/QCBS/2019/05 / Component - C. Quality And Cost- Under Hiring of a firm to conduct a IDA / V2160 Enhancement of Fiscal Prior Open - International 0.00 2019-09-16 2019-06-24 2019-10-07 2019-06-27 2019-11-20 2019-10-30 2019-12-18 2019-12-03 2020-01-17 2020-01-08 2020-02-21 2020-03-27 2021-03-27 Based Selection Implementation SESA of O&G Management GPRGMP/QCBS/2019/07 / Component - C. Quality And Cost- Hiring of consultant to IDA / V2160 Enhancement of Fiscal Post Open - International 0.00 Canceled 2019-11-01 2019-11-22 2020-01-05 2020-02-02 2020-03-03 2020-04-07 2020-05-12 2021-05-12 Based Selection perform audit of PIU Management GPRGMP/CQS/2019/01 / Component- A. Enhancement Consultant Consultancy services for IDA / V2160 of Legal Framework and Post Qualification Limited 38,133.26 Signed 2019-04-19 2019-04-30 2019-05-03 2019-06-27 2019-06-02 2019-11-29 2019-07-07 2019-11-29 2020-01-03 Design and Development of Stakeholder Engagement Selection Website GPRGMP/CQS/2019/0-1 / Component - D. Project Consultant Consultancy services for Oil IDA / V2160 Management & Project Prior Qualification Limited 281,085.00 Signed 2018-08-25 2019-04-25 2018-09-08 2019-05-01 2018-10-08 2019-05-03 2018-11-28 2019-02-15 2019-02-26 and Gas Project Evaluation Preparation Facility Selection (Phase 1) GPRGMP/QCBS/2019/01 / Component - D. Project Quality And Cost- Consultancy services for PSC IDA / V2160 Management & Project Prior Open - International 301,702.00 Under Review 2018-09-25 2019-04-25 2018-10-16 2019-05-03 2018-11-29 2019-05-09 2018-12-27 2019-03-19 2019-01-26 2019-05-21 2019-03-02 2019-10-25 2019-04-06 2019-11-11 2019-08-04 Based Selection Audit Support (Phase 1) Preparation Facility Page 1 GPRGMP/CS/DC/2019/01 / To facilitate a three (3) days general discussion and analysis, taking into consideration the generation Component- A. Enhancement Non-Profit of particular documents. While IDA / 63820 of Legal Framework and Post Direct 93,200.00 Signed 2019-06-27 2019-06-29 2019-07-08 2019-07-15 2019-07-15 2019-08-15 2019-08-14 Organizations pertinent information Stakeholder Engagement necessary to strategically guide and support legislative and institutional reforms going forward. GPRGMP/QCBS/2019/06 / Component - C. Hiring of a firm to propose Quality And Cost- IDA / V2160 Enhancement of Fiscal Prior Open - International 0.00 Under Review 2019-08-18 2019-10-09 2019-09-08 2020-02-28 2019-10-22 2019-11-19 2019-12-19 2020-01-23 2020-02-27 2021-02-26 Design Enterprise Architecture Based Selection Management for Ministry of Finance GPRGMP/CQS/2019/02 / Consultant Hiring of Consultancy Services Component – B Capacity IDA / V2160 Post Qualification Limited 386,830.00 Signed 2019-09-09 2019-09-30 2019-09-23 2019-11-14 2019-10-23 2019-12-26 2019-11-27 2019-12-27 2020-05-25 for Oil and Gas Project Building of Key Institutions Selection Evaluation (Phase 2) GPRGMP/QCBS/2021/01 / Hiring of Law Firm for the Component- A. Enhancement Quality And Cost- Pending Development of Legal and IDA / 63820 of Legal Framework and Prior Open - International 0.00 2021-02-21 2021-02-28 2021-04-04 2021-05-02 2021-05-16 2021-06-06 2021-07-04 2023-07-04 Based Selection Implementation Regulatory Frameworks for Oil Stakeholder Engagement and Gas Sector INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GPRGMP/IC/2019/07 / Hiring Individual of consultant to perform Component – B Capacity IDA / V2160 Post Consultant Limited 0.00 Canceled 2019-05-13 2019-04-15 2019-05-18 2019-04-16 2019-06-08 2019-07-13 2020-01-09 Petroleum Commission's Building of Key Institutions Selection needs assessment. GPRGMP/IC/2019/0-1 / Individual Component – B Capacity Hiring Petroleum IDA / V2160 Post Consultant Limited 0.00 Canceled 2019-04-15 2019-04-15 2019-04-20 2019-04-16 2019-05-11 2019-06-15 2019-12-12 Building of Key Institutions Development Management Selection Specialist GPRGMP/IC/2019/13 / Hiring Component - D. Project Individual Pending of a member for the IDA / V2160 Management & Project Post Consultant Open 0.00 2019-09-10 2019-10-13 2019-10-27 2019-11-24 2020-11-23 Implementation Investment Committee (SWF) Preparation Facility Selection GPRGMP/IC/2019/14 / Hiring Component - D. Project Individual of M&E Specialist (part-time) IDA / V2160 Management & Project Post Consultant Limited 0.00 Canceled 2019-06-03 2019-08-06 2019-06-08 2019-06-29 2019-08-03 2020-08-02 (PIU) Preparation Facility Selection GPRGMP/IC/2019/0-2 / Individual Component – B Capacity Hiring of Gas Negotiations IDA / V2160 Post Consultant Limited 0.00 Canceled 2019-04-29 2019-04-15 2019-05-04 2019-04-16 2019-05-25 2019-06-29 2020-06-28 Building of Key Institutions Specialist Selection Individual GPRGMP/IC/2019/04 / Hiring Component – B Capacity IDA / V2160 Post Consultant Open 140,000.00 Signed 2019-04-15 2019-04-15 2019-05-18 2019-08-30 2019-06-01 2019-10-31 2019-07-06 2019-10-31 2020-07-05 of O&G Commercial Specialist Building of Key Institutions Selection Individual GPRGMP/IC/2019/05 / Hiring Component – B Capacity IDA / V2160 Post Consultant Open 180,000.00 Signed 2019-04-22 2019-04-15 2019-05-25 2019-08-02 2019-06-08 2019-10-25 2019-07-06 2019-10-31 2020-07-05 of Crude Marketing Specialist Building of Key Institutions Selection Individual GPRGMP/IC/2019/06 / Hiring Component – B Capacity IDA / V2160 Post Consultant Open 160,000.00 Signed 2019-04-12 2019-04-15 2019-05-15 2020-01-06 2019-05-29 2020-02-02 2019-06-19 2020-02-21 2020-06-18 of O&G Accounting Specialist Building of Key Institutions Selection GPRGMP/IC/2019/10 / Hiring Component - C. Individual of an advisor to Pending IDA / V2160 Enhancement of Fiscal Post Consultant Open 0.00 2019-10-16 2019-11-18 2019-12-02 2019-12-30 2020-12-29 Macroeconomic Committee Implementation Management Selection (SWF) GPRGMP/IC/2019/11 / Hiring Component - D. Project Individual of a member for the Pending IDA / V2160 Management & Project Post Consultant Open 0.00 2019-10-16 2019-11-18 2019-12-02 2019-12-30 2020-12-29 Macroeconomic Committee Implementation Preparation Facility Selection (SFW) GPRGMP/IC/2019/12 / Hiring Component - C. Individual Pending of an advisor to the IDA / V2160 Enhancement of Fiscal Post Consultant Open 0.00 2019-10-30 2019-12-02 2019-12-16 2020-01-13 2021-01-12 Implementation Investment Committee (SWF) Management Selection GPRGMP/DC/IC/01 / Component - D. Project Consultancy services for DOE IDA / V2160 Management & Project Post Direct Selection Direct 120,000.00 Signed 2019-04-19 2019-04-25 2019-04-29 2019-04-22 2019-05-23 2019-07-03 2020-05-22 Communications Preparation Facility GPRGMP/IC/2019/03 / Hiring Individual Component – B Capacity Under of Petroleum Economics & IDA / V2160 Post Consultant Open 0.00 2019-04-29 2019-04-17 2019-06-08 2019-06-22 2019-07-20 2020-07-19 Building of Key Institutions Implementation Fiscal Modelling Specialist Selection GPRGMP/IC/2019/01 / Hiring Individual Component – B Capacity Petroleum Development IDA / V2160 Post Consultant Open 180,000.00 Signed 2019-04-17 2019-04-17 2019-05-09 2019-12-13 2019-05-23 2020-01-06 2019-06-20 2020-01-06 2020-06-19 Building of Key Institutions Management Specialist Selection GPRGMP/IC/2019/0-7 / Hiring of Consultant to Individual Component – B Capacity Perform Petroleum IDA / V2160 Post Consultant Open 150,000.00 Signed 2019-04-17 2019-04-17 2019-05-07 2019-11-17 2019-05-21 2019-12-31 2019-06-18 2020-01-07 2020-06-17 Building of Key Institutions Commission's needs Selection assessment Individual GPRGMP/IC/2019/02 / Hiring Component – B Capacity IDA / V2160 Post Consultant Open 180,000.00 Terminated 2019-04-17 2019-04-17 2019-05-07 2019-12-06 2019-05-21 2020-02-03 2019-06-18 2020-02-03 2020-06-17 of Gas Negotiations Specialist Building of Key Institutions Selection GPRGMP/IC/2019/PPF-2 / Component - D. Project Individual Consultancy Services IDA / V2160 Management & Project Prior Consultant Limited 68,900.00 Signed 2018-10-05 2019-04-24 2018-10-25 2018-09-28 2018-11-15 2019-05-22 2018-12-20 2019-02-25 2019-06-18 Assessment and Action Plan Preparation Facility Selection for EPA Page 2 GPRGMP/IC/2019/PPF-1 / Component - D. Project Individual Consultancy services for Local IDA / V2160 Management & Project Prior Consultant Limited 104,500.00 Signed 2018-09-21 2019-05-08 2018-09-26 2018-09-14 2018-10-17 2019-05-17 2018-11-21 2019-02-07 2019-05-20 Content Analysis Preparation Facility Selection GPRGMP/IC/2018/01 / Component - D. Project Individual Consultancy on Project IDA / V2160 Management & Project Prior Consultant Limited 64,293.57 Signed 2018-10-07 2019-05-09 2018-10-12 2018-08-15 2018-11-02 2019-05-23 2018-12-07 2018-09-06 2019-06-05 Management Preparation Facility Selection GPRGMP/IC/2018/02 / Component - D. Project Individual Consultancy on Financial IDA / V2160 Management & Project Prior Consultant Limited 62,534.15 Signed 2018-07-16 2019-05-09 2018-07-21 2018-08-15 2018-08-11 2019-05-23 2018-09-15 2018-09-10 2019-03-14 Management Preparation Facility Selection GPRGMP/IC/2018/03 / Component - D. Project Individual Consultancy on Procurement IDA / V2160 Management & Project Prior Consultant Open 50,000.00 Signed 2018-07-16 2019-05-21 2018-09-03 2018-10-08 2018-09-24 2019-06-07 2018-10-29 2018-12-03 2019-10-29 Services Preparation Facility Selection GPRGMP/CS/DC/2019/02 / To facilitate a two (2) days Component- A. Enhancement general discussion an analysis IDA / 63820 of Legal Framework and Post Direct Selection Direct 20,000.00 Signed 2019-06-30 2019-08-02 2019-07-04 2019-07-12 2019-07-23 2019-07-30 2019-08-22 on crude lifting, taking into Stakeholder Engagement consideration the generation of particular documents. GPRGMP/IC/DC/2019/01 / To support the Department of Energy (DE), to evaluate Procurement submissions by Component – B Capacity IDA / 63820 Post Direct Selection Direct 15,000.00 Signed 2019-06-25 2019-06-29 2019-07-05 2019-07-05 2019-09-08 2019-07-25 2020-03-06 providing specialized Building of Key Institutions guidance and advisory services to the GCRG under the GPRGMP. GPRGMP/IC/DC/2019/02 / To support the Department of Energy (DE), to evaluate Procurement submissions by Component – B Capacity IDA / 63820 Post Direct Selection Direct 15,000.00 Signed 2019-06-25 2019-06-29 2019-06-28 2019-07-09 2019-07-15 2019-07-25 2019-08-14 providing specialized Building of Key Institutions guidance and advisory services to the GCRG under the GPRGMP. GPRGMP/IC/DC/2019/03 / To support the Department of Energy (DE), to evaluate Procurement submissions by Component – B Capacity IDA / 63820 Post Direct Selection Direct 15,000.00 Signed 2019-06-25 2019-07-16 2019-06-28 2019-08-01 2019-07-15 2019-08-23 2019-08-14 providing specialized Building of Key Institutions guidance and advisory services to the GCRG under the GPRGMP. GPRGMP/IC/2019/15 / Hiring Component - D. Project Individual of Environmental and Social IDA / V2160 Management & Project Prior Consultant Limited 39,000.00 Signed 2019-08-16 2019-08-21 2019-08-21 2019-03-15 2019-09-04 2019-11-21 2019-09-25 2019-11-26 2020-09-24 Safeguard Officer Preparation Facility Selection Component - D. Project Individual GPRGMP/IC/2019/16 / Hiring IDA / V2160 Management & Project Post Consultant Limited 25,200.00 Signed 2019-08-12 2019-08-23 2019-08-17 2019-08-16 2019-08-31 2019-10-22 2019-09-21 2019-10-22 2020-09-20 of a Project Aide Officer Preparation Facility Selection GPRGMP/IC/2019/17 / Hiring Component- A. Enhancement Individual Under of a Legal Consultant for the IDA / V2160 of Legal Framework and Post Consultant Limited 0.00 2019-08-12 2019-08-22 2019-08-17 2019-08-28 2019-09-07 2019-10-12 2020-04-09 Implementation Department of Energy Stakeholder Engagement Selection GPRGMP/IC/2018/06 / Component - D. Project Individual Consultancy on Under IDA / V2160 Management & Project Post Consultant Open 0.00 2018-08-15 2019-11-29 2018-09-24 2018-10-08 2018-11-12 2019-11-12 Administration (confidential Implementation Preparation Facility Selection secretary) GPRGMP/IC/2018/07 / Component - D. Project Individual Pending Consultancy for Office IDA / V2160 Management & Project Post Consultant Limited 0.00 2018-08-15 2018-09-05 2018-09-26 2018-10-31 2019-10-31 Implementation Manager Preparation Facility Selection GPRGMP/IC/2018/04 / Component - D. Project Individual Pending Consultancy on Accountancy IDA / V2160 Management & Project Post Consultant Open 0.00 2018-08-15 2018-09-17 2018-10-01 2018-11-01 2019-04-30 Implementation Services Preparation Facility Selection GPRGMP/IC/2019/14-1 / Component - D. Project Individual Hiring of Monitoring and IDA / V2160 Management & Project Post Consultant Limited 40,000.00 Signed 2019-08-12 2019-08-19 2019-08-17 2019-09-11 2019-08-31 2019-10-25 2019-09-21 2019-10-25 2020-09-20 Evaluation Officer Preparation Facility Selection Individual GPRGMP/IC/2019/09 / Hiring Component – B Capacity Pending IDA / V2160 Post Consultant Open 0.00 2019-11-03 2019-12-06 2019-12-20 2020-01-17 2021-01-16 of an advisor to EPA on O&G Building of Key Institutions Implementation Selection GPRGMP/IC/2019/15-B / To support PIU to ensure the environmental, social and Component - D. Project Individual safeguards aspects of the IDA / V2160 Management & Project Prior Consultant Open 30,000.00 Signed 2019-11-05 2019-11-20 2019-11-09 2019-03-15 2019-11-13 2019-12-04 2019-11-19 2019-12-05 2020-11-18 project are developed and Preparation Facility Selection implemented efficiently and effectively. GPRGMP/IC/2019/08 / Hiring of a consultant to conduct Individual Component – B Capacity needs assessment on IDA / V2160 Post Consultant Open 0.00 Canceled 2019-10-20 2019-11-22 2019-12-06 2019-12-30 2020-12-29 Building of Key Institutions petroleum data management Selection and provide support GPRGMP/IC/2020/DS1 / Component- A. Enhancement Consulting Services for Legal IDA / 63820 of Legal Framework and Prior Direct Selection Direct 207,000.00 Signed 2020-01-30 2020-02-10 2020-02-09 2020-02-13 2020-03-15 2020-02-28 2020-09-11 Consultant for PSC Audit Stakeholder Engagement GPRGMP/IC/2019/08-1 / Consulting Services for Component – B Capacity Under IDA / 63820 Prior Direct Selection Direct 0.00 2020-01-30 2021-01-12 2020-02-09 2021-01-15 2020-03-13 2021-03-13 Petroleum Data Management Building of Key Institutions Implementation Needs Assessment GPRGMP/2020/DS1 / To assist in all accounting, Component - D. Project financial reporting and IDA / V2160 Management & Project Post Direct Selection Direct 12,000.00 Signed 2020-02-28 2020-03-03 2020-03-02 2020-03-05 2020-03-09 2020-03-17 2020-05-08 internal controls for the Preparation Facility GPRGMP Page 3 GPRGMP/IC/2020/DC2 / Individual Consultancy For Component – B Capacity IDA / V2160 Post Direct Selection Direct 180,000.00 Signed 2020-08-21 2020-08-21 2020-08-26 2020-08-15 2020-09-07 2020-10-05 2021-03-06 Strategic Oil and Gas Advisory Building of Key Institutions Services Component - D. Project GPRGMP/IC/2018/02-A / IDA / V2160 Management & Project Post Direct Selection Direct 35,000.00 Signed 2020-12-30 2020-12-31 2021-01-01 2020-12-23 2021-01-04 2021-01-08 2021-03-31 Financial Management Officer Preparation Facility GPRGMP/IC/2019/15-A1 / Component - D. Project Environmental and Social IDA / V2160 Management & Project Post Direct Selection Direct 15,000.00 Signed 2020-12-30 2020-12-31 2021-01-01 2020-12-23 2021-01-04 2021-01-08 2021-03-31 Safeguards Officer No. 1 Preparation Facility GPRGMP/IC/2019/15-B1 / Component - D. Project Environmental and Social IDA / V2160 Management & Project Post Direct Selection Direct 10,000.00 Signed 2020-12-30 2020-12-31 2021-01-01 2020-12-23 2021-01-04 2021-01-08 2021-03-31 Safeguards Officer No. 2 Preparation Facility Component - D. Project GPRGMP/IC/2018/03-A / IDA / V2160 Management & Project Post Direct Selection Direct 21,000.00 Signed 2020-12-30 2020-12-31 2021-01-01 2020-12-23 2021-01-04 2021-01-08 2021-03-31 Procurement Officer Preparation Facility GPRGMP/IC/2021/01 / Hiring Individual Component – B Capacity Pending of Natural Gas Negotiations IDA / 63820 Post Consultant Open 0.00 2021-02-23 2021-03-19 2021-04-02 2021-04-16 2022-04-16 Building of Key Institutions Implementation Specialist Selection Page 4