Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) KP Southern Area Development Project (P130835) SOUTH ASIA | Pakistan | Agriculture Global Practice | Recipient Executed Activities | Specific Investment Loan | FY 2013 | Seq No: 9 | ARCHIVED on 07-Jun-2017 | ISR28477 | Implementing Agencies: KP SADP PMU - Local Government, Elections & Rural Development Department, Economic Affairs Division Key Dates Key Project Dates Bank Approval Date:11-Jan-2013 Effectiveness Date:06-Feb-2013 Planned Mid Term Review Date:31-Mar-2014 Actual Mid-Term Review Date:11-Apr-2014 Original Closing Date:30-Jun-2015 Revised Closing Date:31-Dec-2018 Project Development Objectives Project Development Objective (from Project Appraisal Document) To strengthen the capacity of the poor to improve their livelihood options through access to social and productive infrastructure using participatory approaches in the selected southern districts of Khyber Pakhtunkhwa province. i.e. Dera Ismail Khan (DIK), Tank and Lakki Marwat that are adversely affected by the crisis. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A: Community Development Support:(Cost $1.50 M) Component B: Community Driven Investment Program:(Cost $14.00 M) Component C: Project Implementation Support:(Cost $2.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  High  High 6/7/2017 Page 1 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) Implementation Status and Key Decisions In response to a request by KP Government, an additional financing of US$ 4 million was signed on March 30, 2017 and project closing date was extended to December 31, 2018. With total financing of US$22 million, the project will extend its outreach to a total of 53 union councils including 25 existing and 28 new UCs in three southern districts of Dera Ismail Khan, Tank and Lakki Marwat. Accordingly. the project outcomes and targets have been updated. SADP has maintained a steady implementation pace. The project mobilized 751 community groups (441 CBOs and 310 Economic Interest Groups) with a membership of 17,497 households, of which 31.5% (237) are female groups representing 4,442 households. The project has established 13 vocational centres for women. Of all the ongoing Bank funded projects in KPK, SADP has 47% - the largest proportion of - female beneficiaries i.e. 176,431 females out of a total of 373,574 beneficiaries. In order to strengthen the community institutions, the project has provided required training to 696 office bearers including 152 females through 27 training events. The formation of community action plans is progressing at a slow pace, with 274 community actions plans prepared and under implementation. The social mobilization component has been instrumental in strengthening ‘State-Citizen Trust’. By strengthening the capacity of relevant departments within the Government of KP, the project has contributed towards institutional strengthening, helped develop capacity and facilitated linkages between the communities and government departments especially in remote and isolated parts of KPK. Going forward, the project is paying greater attention to engage youth, women, women headed households and ultra-poor. The project has initiated a youth internship program and has taken on board 45 youth including 14 females. The project has made a steady progress and has achieved all due targets. Acute shortage of irrigation water and long spells of drought has adversely affected small farmers and local livelihoods, an increasing number of local communities had approached the project to help them rehabilitate dysfunctional irrigation system to stores and conserve water especially during the monsoon season. Initially three potential sites have been identified with a potential to help irrigate 59,000 acres of land and benefit rehabilitated would help irrigate 59,00 acres of land and benefit 39,00 households. The feasibility of one site in district Dera Ismail Khan is being examined and possibility of co-financing from the KP government is being explored. Many of the project communities are not linked with the national electricity grid and even those connected suffer due to acute electricity shortages spread over many hours with adverse effects on local business, livelihoods, and services. The project is exploring the possibility of community managed local solutions such as solar energy to promote local livelihoods. In order to meet all the project outcomes and targets in the remaining period, the project needs to adopt a multi pronged approach to extend project interventions to the 28 new union councils as well as continue working with the existing and unserved communities in the existing 25 UCs. it would require more strategic and efficient deployment of project staff as well as utilizing the services of community activists and dynamic community groups. 6/7/2017 Page 2 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) 6/7/2017 Page 3 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  High  High Macroeconomic  --  Substantial  Substantial Sector Strategies and Policies  --  Substantial  Substantial Technical Design of Project or Program  --  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  --  High  High Fiduciary  --  High  High Environment and Social  --  Moderate  Moderate Stakeholders  --  High  High Other  --  --  -- Overall  --  High  High Results Project Development Objective Indicators PHINDPDOTBL  Project beneficiaries: Support at least 260,000 project beneficiaries of which 30 percent women (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 373,797.00 373,797.00 260,000.00 Date 31-Mar-2013 30-Sep-2016 30-Sep-2016 31-Dec-2018 Comments 6/7/2017 Page 4 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) The methodology to measure project beneficiaries has changed. Current actual measures direct and indirect beneficiaries of project activities and secondary beneficiaries of infrastructure, whereas the revised target seeks to measure only the direct and indirect beneficiaries of project interventions. Secondary beneficiaries of infrastructure, generated through the project is expected to be 654,304, of which 324,878 are expected to be women. Gender disaggregation of end target: M: 182,000, F: 78,000 PHINDPDOTBL  Establish and/or revitalize 1,300 CBOs and EIGs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 751.00 751.00 1,300.00 Date 31-Mar-2013 30-Sep-2016 31-Mar-2017 31-Dec-2018 PHINDPDOTBL At least 60 percent of CAPs have arrangements for community engagement in post-project sustainability or O&M (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 31-Mar-2013 -- -- 31-Dec-2018 PHINDPDOTBL At least 80 percent of CBOs/EIGs use participatory planning to develop CAPs and use them for implementation (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 80.00 80.00 Date 31-Mar-2013 -- 31-Mar-2017 31-Dec-2018 PHINDPDOTBL  Change in percent of population accessing productive infrastructure and services provided through this project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 6/7/2017 Page 5 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) Date 31-Mar-2013 -- 31-Mar-2017 31-Dec-2018 PHINDPDOTBL  Number of CBO/EIG members (gender disaggregated) benefitting from productive infrastructure (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5,557.00 -- 5,557.00 8,000.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 Comments Gender disaggregation of baseline: M: 2,724, F: 2833 Gender disaggregation of end target: M: 3,977, F: 4,023 PHINDPDOTBL  Number of CBO/EIG members (disaggregated by gender) benefiting from social infrastructure (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 75,106.00 -- 75,106.00 100,000.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 Comments Gender disaggregation of baseline: M: 37,221, F: 37,885 Gender disaggregation of end target: M: 49,364, F: 50,636 Overall Comments Intermediate Results Indicators 6/7/2017 Page 6 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) PHINDIRITBL  70 percent of grants disbursed timely to EIGs/CBOs out of the total approved CAP (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 44.95 70.00 Date 31-Mar-2013 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL At least 70 percent of project staff, disaggregated by gender, utilized knowledge and skills gained through capacity development activities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 0.00 70.00 Date 31-Mar-2013 30-Sep-2016 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of EIG members benefiting from livelihoods support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 3,099.00 100.00 3,099.00 5,000.00 Date 31-Mar-2017 30-Sep-2016 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of EIG female members benefiting from livelihoods support (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1,216.00 -- 1,216.00 1,962.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 6/7/2017 Page 7 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) PHINDIRITBL  Number of EIG male members benefiting from livelihoods support (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1,883.00 -- 1,883.00 3,038.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of CBO members (disaggregated by gender) benefiting from social and productive infrastructure (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 14,398.00 85.00 14,398.00 30,000.00 Date 31-Mar-2017 30-Sep-2016 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of CBO female members benefiting from social and productive infrastructure (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 3,226.00 -- 3,226.00 6,722.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of CBO male members benefiting from social and productive infrastructure (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 11,172.00 -- 11,172.00 23,278.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 6/7/2017 Page 8 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) PHINDIRITBL  60% of approved CAPs completed in time after receipt of grant, and published in the project website (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 44.95 60.00 Date 31-Mar-2013 30-Sep-2016 31-Mar-2017 31-Dec-2018 PHINDIRITBL  100 percent of CAPs approved by the SARAC (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 44.95 -- 44.95 100.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Monitoring system established and functioning: timely reporting against activity and output indicators (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL  1245 community members received training through the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 696.00 -- 696.00 1,245.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 6/7/2017 Page 9 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) PHINDIRITBL  Number of community female members received training through the project (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 152.00 -- 152.00 272.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 PHINDIRITBL  Number of community male members received training through the project (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 544.00 -- 544.00 973.00 Date 31-Mar-2017 -- 31-Mar-2017 31-Dec-2018 Overall Comments The results framework was revised and updated for additional financing of US$ 4.00 million effective March 30, 2017 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P130835 TF-13560 Effective USD 22.00 22.00 0.00 10.76 11.24 49% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P130835 TF-13560 Effective 06-Feb-2013 06-Feb-2013 06-Feb-2013 30-Jun-2015 31-Dec-2018 Cumulative Disbursements 6/7/2017 Page 10 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report KP Southern Area Development Project (P130835) Restructuring History Level 2 Approved on 22-Jun-2015 ,Level 2 Approved on 10-Dec-2015 ,Level 2 Approved on 23-Jun-2016 ,Level 2 Approved on 15-Dec-2016 Related Project(s) There are no related projects. 6/7/2017 Page 11 of 11 Public Disclosure Copy