PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Water For Agro-Pastoral and Reselience Productivity c. Project Number: P167826 d. Total Finance: USD 5 Million 2. Project Implementation Agency: South West State of Somalia 3. Date of Project Plan: October 2018 4. Period Covered by this Procurement: January 2019 – June 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable 1 VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation Nation Quotation (US$ al al (RfQ) millions) Works all ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Engineering and (US$, Services Construction millions) Supervision Consultants n.a n.a. all (Firms) Individual all n.a. n.a. Consultants 2 South West Procurement Plan XI. Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) R Contract Estimate Revie Market Sel Eval Procure Preq Do Expected Expected ef Description d Cost w by Approac ecti uati ment ualif mes date of date of . (US$) Bank h (Open- on on Process icati tic bid/ Contract N (Prior National Me Opti (Single on Pref proposal Signatur o / / Limited tho ons stage- (Yes/ ere opening e Post) etc.) d (BA single No) nce (RF FO envelop (Yes P, Rat e etc.) /No) RF ed B, Crit RF eria Q etc. etc ) .) GOODS Low est Single G Purchase of 5 Open Eval stage 02/Mar/20 02/Apr/20 $175,000 Prior RFB N/A N/A 1 vehicles National uate One- 19 19 d Envelop Cost Low Office Equipment est Singe (Laptops, G Eval stage 04/Mar/20 04/Apr/20 Desktops, $30,000 Prior Limited RFQ N/A N/A 2 Projector, Printers uate One - 19 19 and accessories) d Envelop Cost 3 Low est Single G Eval Stage 05/May/20 05/Jun/201 GIS Equipment $25,000 Prior Limited RFQ N/A N/A 3 uate One- 19 9 d Envelop Cost Low est Single Hydrological G Eval Stage 15/Oct/20 16/Nov/20 Water Monitoring $12,000 Prior Limited RFQ N/A N/A 4 Tools uate One- 19 19 d Envelop Cost Low est Single G Open Eval Stage 21/Mar/20 22/Apr/20 Vehicle Fuels $80,000 Prior RFQ N/A N/A 6 National uate One- 19 19 d Envelop Cost Low est Single G Office furniture Eval Stage 12/Jun/202 13/Jul/202 $30,000 Prior Limited RFQ N/A N/A 7 (Chairs, Tables, ) uate One- 0 0 d Envelop Cost Total Goods $352,000 WORKS Construction of Low Sand Dams/Sub- est Single W surface Dams Open Eval stage – 09/Nov/20 10/Dec/20 $90,000 Prior RFQ N/A N/A 1 National uate one 19 19 d envelope Cost 4 Construction of Low Earth Dams est Single W Open Eval stage – 01/Oct/20 02/Nov/20 $90,000 Prior RFQ N/A N/A 2 National uate one 19 19 d envelope Cost Construction/Reh Low abilitation of 10 est Single W Berkads Open Eval stage – 01/Sep/20 01/Oct/20 $42,000 Prior RFQ N/A N/A 3 National uate one 19 19 d envelope Cost Rehabilitation of Low Boreholes/Shallow est Single W Wells Open Eval stage – 18/Aug/20 19/Sep/20 $50,000 Prior RFQ N/A N/A 4 National uate one 19 19 d envelope Cost Office Low Construction/Reh est Single W abilitation Open Eval stage – 01/Aug/20 01/Sep/20 $70,000 Prior RFQ N/A N/A 5 National uate one 19 19 d envelope Cost Total Works $342,000 Non -Consulting Services Total Non- Consultant Service Consulting Services 5 Re Contract Estimate Review Market Selecti Shortli Expected Expected f Description d Cost by Bank Approach on sting Date of Date of No (US$) (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Site selection, geophysical surveying, Open – 16/Mar/201 15/Apr/20 C1 100,000 Prior CQS N/A contracting and National 9 19 engineering support Develop GIS map Prior Open - CQS 08/Aug/20 C2 for potential sites 20,000 N/A 08/Jul/2019 National 19 creation of village livelihood development Open - 13/May/202 10/Jun/202 C3 plans & water 500,000 Prior QCBS N/A International 0 0 budgets implement rural development policies and laws Open 12/Feb/20 C4 to regulate sector 50,000 Prior CQS N/A 15/Jan/2020 and ensure National 20 sustainability technical assistance agency Open 22/Feb/202 19/Mar/20 C5 for training 60,000 Prior CQS N/A assessment, National 0 20 selecting, training 6 and monitoring field service support, acquisition and application of geo-spatial Open – 01/Mar/202 01/Apr/20 C6 imagery for 20,000 Prior CQS N/A before and after National 0 20 satelite photos Procurement 05/Feb/20 C7 50,000 Prior Open INDV N/A 05/Jan/2019 Specialist 19 Open INDV 05/Feb/20 C8 Finance Specialist 50,000 Prior N/A 05/Jan/2019 19 Open INDV 10/Feb/201 10/Mar/20 C9 Project Engineer 72,000 Prior N/A 9 19 C1 Open INDV 31/Oct/20 2 Site Engineers 21,000 Prior N/A 01/Oct/2019 0 19 Total $943,000 Consulting Services $1,637,0 Grand Total 00 7 PROCUREMENT Somalia : Somalia - Water for Agro-pastoral Productivity and Resilience PLAN General Information Country: Somalia Bank’s Approval Date of the Original Procurement Plan: 2020-04-07 2021-08-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167826 GPN Date: Project Name: Somalia - Water for Agro-pastoral Productivity and Resilience Loan / Credit No: IDA / D4970 Ministry of Planning and Economic Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SO-MOPED - GS-223990-CW- Request for RFQ / Ministry of Energy and Component 2. Institutional Request for Single Stage - One 2022-01- IDA / D4970 Prior Limited Quotations (Non 34,000.00 32,815.20 Signed 2021-05-10 2021-05-29 2021-07-05 2021-06-21 Water Resource's boundary and Capacity Development Quotations Envelope 01 Bank-SPD) wall Construction. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPED - GS-239465-CS- CQS / CONSULTANCY TO DEVELOP AN ENVIRONMENTAL STRATEGIC PLAN AND Consultant Component 2. Institutional Under RANGELAND MANAGEMENT IDA / D4970 Prior Qualification Limited 30,000.00 0.00 2021-06-16 2021-06-14 2021-06-30 2021-07-30 2021-09-03 2022-03-02 and Capacity Development Implementation PLAN FOR GALMUDUG Selection MINISTRY OF ENVIRONMENT CLIMATE CHANGE AND RURAL DEVELOPMENT INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project SO-MOPIED-FGS-167354-CS- Individual Management, M & E, INDV / Galmudug IDA / D4970 Prior Consultant Limited 25,000.00 67,260.00 Signed 2020-04-04 2020-04-08 2020-04-09 2020-06-15 2020-04-16 2020-06-16 2020-05-03 2020-06-20 2021-05-03 Knowledge Management and Procurement Specialist Selection Learning Component 4: Project SO-MOPIED-FGS-167356-CS- Individual Management, M & E, INDV / Galmudug Financial IDA / D4970 Prior Consultant Limited 20,000.00 29,820.00 Signed 2020-04-04 2020-04-07 2020-04-09 2020-12-13 2020-04-19 2020-12-14 2020-05-09 2020-12-13 2021-05-09 Knowledge Management and Management Specialist Selection Learning SO-MOPIED-FGS-167358-CS- Component 4: Project Individual INDV / Galmudug Management, M & E, IDA / D4970 Prior Consultant Limited 20,000.00 44,520.00 Signed 2020-04-04 2020-04-07 2020-04-09 2020-08-01 2020-04-16 2020-08-12 2020-05-03 2020-08-06 2021-05-03 Environmental and Safeguards Knowledge Management and Selection Specialist Learning SO-MOPED - GS-235883-CS- Component 1: Support the Individual INDV / Site Engineer for IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 0.00 Under Review 2021-05-28 2021-06-02 2021-06-23 2021-07-28 2022-01-24 Biyoole Galmudug, MOEWR Water Sources Selection SO-MOPED - GS-235884-CS- Component 1: Support the Individual Under INDV / Site Engineer for IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 0.00 2021-05-28 2021-06-02 2021-06-02 2021-06-23 2021-07-28 2022-01-24 Implementation Biyoole Galmudug, MOEWR Water Sources Selection SO-MOPED - GS-249301-CS- INDV / CONSULTANCY TO DEVELOP AN ENVIRONMENTAL STRATEGIC PLAN AND Individual Component 2. Institutional Pending RANGELAND MANAGEMENT IDA / D4970 Prior Consultant Limited 30,000.00 0.00 2021-08-19 2021-08-24 2021-09-14 2021-10-19 2022-04-17 and Capacity Development Implementation PLAN FOR GALMUDUG Selection MINISTRY OF ENVIRONMENT CLIMATE CHANGE AND RURAL DEVELOPMENT. Page 1