PROCUREMENT PLAN (Textual Part) Project information: Maldives [Maldives Clean Environment Project P 160739 Project Implementation agency: Ministry of Environment and Energy Date of the Procurement Plan: 23 August 2017 Period covered by this Procurement Plan: 23 August 2017 to 23 February 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Maldives : Maldives Clean Environment Project PLAN General Information Country: Maldives Bank’s Approval Date of the Original Procurement Plan: 2017-08-23 2020-10-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160739 GPN Date: 2017-08-23 Project Name: Maldives Clean Environment Project Loan / Credit No: IDA / D1990 Executing Agency(ies): Ministry of Environment and Energy WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MV-MEE-60158-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope M.Mulah MV-MEE-61003-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope Madifushi, Meemu Atoll MV-MEE-61004-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope Kinbidhoo, Thaa Atoll MV-MEE-91835-CW-RFB / Upgrading of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 60,000.00 62,278.43 Completed 2018-12-17 2018-12-18 2018-12-18 2019-01-03 2019-01-13 2019-01-08 2019-01-17 2019-01-27 2019-02-06 2019-05-27 Management Centre at Lh. Management Systems Envelope Kurendhoo MV-MEE-92436-CW-RFQ / Provision of Three Phase Component 3: Island Waste Request for Single Stage - One IDA / D1990 Post Open - National 35,000.00 31,625.16 Signed 2018-12-25 2019-01-27 2019-02-20 2019-03-28 Electricity to IWMC of Management Systems Quotations Envelope B.Kihaadhoo & N.Maafaru MV-MEE-98538-CW-RFB / Component 2: Regional Single Stage - One Construction of RO Plant IDA / D1990 Post Request for Bids Open - National 90,000.00 58,418.92 Completed 2019-02-06 2019-02-03 2019-02-10 2019-02-24 2019-02-26 2019-03-10 2019-04-15 2019-04-14 2019-05-23 2019-06-28 Waste Management Systems Envelope Building at Vandhoo RWMF MV-MEE-98559-CW-RFB / Construction of a Store Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 140,000.00 120,502.66 Completed 2019-02-06 2019-02-04 2019-02-10 2019-02-24 2019-02-26 2019-03-10 2019-04-15 2019-04-14 2019-05-23 2019-06-28 Room and Guard House in Waste Management Systems Envelope Vandhoo RWMF MV-MEE-106513-CW-RFB / Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 60,000.00 53,673.20 Signed 2019-03-18 2019-03-19 2019-03-19 2019-04-04 2019-04-10 2019-04-09 2019-06-30 2019-04-28 2019-07-17 2019-08-26 Management Systems Envelope Ungoofaaru, Raa Atoll MV-MEE-106522-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 135,036.52 Signed 2019-03-18 2019-03-17 2019-03-19 2019-04-04 2019-04-10 2019-04-18 2019-06-29 2019-05-16 2019-07-17 2019-10-13 Management Centre in B. Management Systems Envelope Dhonfanu MV-MEE-106524-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 113,209.28 Signed 2019-03-18 2019-03-19 2019-03-19 2019-04-04 2019-04-10 2019-04-18 2019-06-30 2019-05-16 2019-07-10 2019-09-13 Management Centre in B. Management Systems Envelope Hithaadhoo Page 1 MV-MEE-84075-CW-RFB / Component 2: Regional Single Stage - One Extension of Existing Utility IDA / D1990 Post Request for Bids Open - National 100,000.00 115,486.64 Signed 2019-05-21 2019-02-04 2019-05-22 2019-06-12 2019-02-26 2019-06-19 2019-04-15 2019-07-10 2019-05-20 2019-09-08 Waste Management Systems Envelope Building at Vandhoo RWMF MV-MEE-101303-CW-RFB / Upgrading of Waste Storage Facilities and Extension Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 620,000.00 791,314.01 Signed 2019-05-10 2019-03-18 2019-05-13 2019-05-27 2019-04-08 2019-06-03 2019-06-15 2019-06-24 2019-07-17 2019-10-22 Works of the Existing Waste Management Systems Envelope Vehicle Shed in Vandhoo RWMF MV-MEE-121323-CW-RFB / Re-location of Existing Fuel Tanks, construction of new Component 2: Regional Single Stage - One fuel storage tank and pump IDA / D1990 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-06-27 2019-06-30 2019-06-30 2019-07-14 2019-07-30 2019-08-19 2019-08-29 2019-10-03 2020-03-31 Waste Management Systems Envelope room and construction of 200 CBM Water storage Tank at R.Vandhoo MV-MEE-148349-CW-RFB / Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 110,000.00 93,027.60 Signed 2019-12-15 2020-01-05 2019-12-18 2020-01-06 2020-01-08 2020-01-28 2020-01-22 2020-03-01 2020-02-19 2020-04-30 2020-06-18 Management Systems Envelope Maakurathu, Raa Atoll MV-MEE-148353-CW-RFB / Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 130,000.00 123,518.10 Signed 2019-12-15 2019-12-30 2019-12-18 2020-01-06 2020-01-08 2020-01-19 2020-01-22 2020-02-26 2020-02-19 2020-04-30 2020-06-18 Management Systems Envelope Holhudhoo, Noonu Atoll MV-MEE-64621-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 management Centre in Management Systems Envelope Omadhoo, Thaa Atoll MV-MEE-64624-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Thimarafushi, Thaa Atoll MV-MEE-64627-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Hirilandhoo, Thaa Atoll MV-MEE-64630-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Guraidhoo, Thaa Atoll MV-MEE-65143-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Maaenboodhoo, Dhaalu Atoll MV-MEE-65371-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Feeali, Faafu Atoll MV-MEE-64620-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Buruni, Thaa Atoll MV-MEE-65373-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Kolhufushi, Meemu Atoll Page 2 MV-MEE-65374-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope Dhiggaru, Meemu Atoll MV-MEE-136387-CW-RFB / Re-location of Existing Fuel Tanks, construction of new fuel storage tank and pump Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 650,000.00 0.00 Canceled 2020-02-09 2020-02-15 2020-03-16 2020-04-15 2020-05-20 2020-11-16 room and construction of Waste Management Systems Envelope 200 CBM Water storage Tank at R.Vandhoo and construction of fuel trench MV-MEE-160654-CW-RFB / Completion of IWMC in Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 130,000.00 0.00 Canceled 2020-07-26 2020-08-02 2020-08-23 2020-08-30 2020-09-27 2020-12-26 Faafu Magoodhoo and Thaa Management Systems Envelope Vandhoo MV-MEE-183903-CW-RFB / Pilot Projects for Bio- Component 3: Island Waste Open - Single Stage - One IDA / D1990 Post Request for Bids 455,000.00 0.00 Canceled 2020-08-25 2020-08-26 2020-09-16 2020-09-23 2020-10-14 2021-08-10 treatment of Organic Waste Management Systems International Envelope in Zone 4, 5 and 2 MV-MEE-84206-CW-RFQ / Rehabilitation of the Component 2: Regional Request for Single Stage - One IDA / D1990 Post Limited 50,000.00 0.00 Canceled 2020-09-22 2020-11-17 2021-07-15 Existing Landfill and Waste Management Systems Quotations Envelope Leachate Pond (with pumps) MV-MEE-159362-CW-RFB / Upgrading of Island Waste Pending Component 3: Island Waste Single Stage - One Resource Management IDA / D1990 Post Request for Bids Open - National 780,000.00 0.00 Implementat 2021-02-11 2021-02-18 2021-03-11 2021-04-01 2021-05-06 2021-10-03 Management Systems Envelope Centres in Zone 4&5 - ion Batch 3 MV-MEE-189207-CW-RFB / Upgrading of Island Waste Pending Component 3: Island Waste Single Stage - One Resource Management IDA / D1990 Prior Request for Bids Open - National 1,040,000.00 0.00 Implementat 2021-03-04 2021-03-11 2021-04-01 2021-04-15 2021-05-20 2021-10-17 Management Systems Envelope Centres in Zone 4&5 - ion Batch 4 MV-MEE-189200-CW-RFB / Construction of Island Waste Pending Component 3: Island Waste Single Stage - One Resource Management IDA / D1990 Prior Request for Bids Open - National 1,200,000.00 0.00 Implementat 2020-12-03 2020-12-06 2020-12-27 2021-01-10 2021-01-31 2021-06-30 Management Systems Envelope Centres in Zone 4&5 - ion Batch 2 MV-MEE-148352-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 199,400.00 0.00 Implementat 2020-11-15 2020-11-18 2020-12-09 2020-12-23 2021-01-27 2021-07-26 Management Systems Envelope Eydhafushi, Baa Atoll ion MV-MEE-159361-CW-RFB / Construction of Island Waste Pending Component 3: Island Waste Single Stage - One Resource Management IDA / D1990 Prior Request for Bids Open - National 1,200,000.00 0.00 Implementat 2020-11-05 2020-11-12 2020-12-03 2020-12-17 2021-01-14 2021-06-13 Management Systems Envelope Centres in Zone 4&5 - ion Batch 1 MV-MEE-158460-CW-RFB / Pending Upgrading of water network Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Implementat 2020-11-12 2020-11-15 2020-12-06 2020-12-27 2021-01-17 2021-07-16 and storage capacity in Waste Management Systems Envelope ion Vandhoo RWMF MV-MEE-181011-CW-RFB / Pending Component 2: Regional Single Stage - One Landscaping of Vandhoo IDA / D1990 Post Request for Bids Open - National 75,000.00 0.00 Implementat 2020-08-02 2020-08-09 2020-08-30 2020-09-13 2020-10-11 2021-06-08 Waste Management Systems Envelope RWMC ion MV-MEE-158463-CW-RFB / Pending Surveying, setting out, Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 325,000.00 0.00 Implementat 2021-02-01 2021-02-08 2021-03-01 2021-03-15 2021-04-12 2021-11-08 clearance and road Waste Management Systems Envelope ion construction at Vandhoo Page 3 MV-MEE-158461-CW-RFB / Upgrading of fuel Pending Component 2: Regional Single Stage - One distribution network and IDA / D1990 Post Request for Bids Open - National 300,000.00 0.00 Implementat 2020-11-05 2020-11-12 2020-12-03 2020-12-24 2021-01-14 2021-07-13 Waste Management Systems Envelope storage capacity in Vandhoo ion RWMF MV-MEE-158462-CW-RFB / Rehabilitation and Pending Component 2: Regional Single Stage - One Remediation of the Existing IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Implementat 2020-11-15 2020-11-22 2020-12-20 2021-01-03 2021-02-07 2021-09-05 Waste Management Systems Envelope Landfill and Leachate Pond ion in Vandhoo MV-MEE-201843-CW-RFB / Pending Component 3: Island Waste Single Stage - One Construction of IWMC in IDA / D1990 Post Request for Bids Open - National 200,000.00 0.00 Implementat 2022-03-03 2022-03-10 2022-03-31 2022-04-21 2022-05-26 2022-10-23 Management Systems Envelope Feeali, Faafu Atoll ion MV-MEE-201845-CW-RFB / Pending Component 3: Island Waste Single Stage - One Construction of IWMC in IDA / D1990 Post Request for Bids Open - National 200,000.00 0.00 Implementat 2022-03-03 2022-03-10 2022-03-31 2022-04-21 2022-05-26 2022-10-23 Management Systems Envelope Dhiggaru, Meemu Atoll ion MV-MEE-189099-CW-RFB / Civil Works for Establishing Pending Pilot Organic Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 500,000.00 0.00 Implementat 2021-01-28 2021-02-02 2021-02-23 2021-03-16 2021-04-20 2021-08-18 Treatment Plants including Management Systems Envelope ion Upgrading of selected IWRMCs GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-36104-GO-RFQ / Setting up Procurement and Component 4: Project Request for Single Stage - One Financial Management IDA / D1990 Post Limited 10,000.00 10,833.12 Signed 2017-11-21 2018-02-20 2017-12-26 2018-05-24 2018-01-25 2018-08-24 Management Quotations Envelope Systems including hardware and software MV-MEE-31491-GO-RFB / Component 2: Regional Single Stage - One Procurement of an excavator IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2017-11-09 2017-11-14 2017-12-26 2018-01-16 2018-02-20 2018-05-21 Waste Management Systems Envelope for Vandhoo RWMF MV-MEE-31434-GO-RFB / Component 1: National Solid Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 0.00 Canceled 2017-10-30 2017-11-02 2017-12-14 2018-01-13 2018-02-17 2018-10-15 International Envelope Vessel and Policy MV-MEE-37121-GO-RFB / Component 1: National Solid Under Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 1,256,000.00 Implementati 2017-11-26 2018-05-06 2017-12-03 2018-05-13 2018-01-14 2018-11-12 2018-02-04 2019-03-16 2018-03-18 2019-05-30 2019-03-18 International Envelope Vessel and Policy on MV-MEE-37101-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of computer IDA / D1990 Post Limited 15,000.00 0.00 Canceled 2017-11-24 2017-11-29 2017-12-22 2018-01-05 Management Quotations Envelope systems for PMU MV-MEE-37101-GO-RFQ-2 / Component 4: Project Request for Single Stage - One Desktop and Laptop IDA / D1990 Post Limited 18,000.00 19,109.48 Completed 2018-02-15 2018-03-11 2018-03-16 2018-04-29 2018-04-30 2018-05-21 Management Quotations Envelope Computers for PMU MV-MEE-48442-GO-RFB / Component 4: Project Single Stage - One Speedboat for Intra-zone IDA / D1990 Post Request for Bids Open - National 200,000.00 223,120.50 Completed 2018-02-28 2018-07-11 2018-03-07 2018-04-04 2018-10-11 2018-04-25 2019-01-10 2018-05-23 2019-02-17 2018-12-19 2019-09-30 Management Envelope travel Page 4 MV-MEE-83998-GO-RFB / Component 2: Regional Open - Single Stage - One Procurement of a Landing IDA / D1990 Post Request for Bids 750,000.00 0.00 Canceled 2018-11-06 2018-11-26 2018-11-11 2018-12-23 2019-02-11 2019-01-06 2019-02-10 2019-10-08 Waste Management Systems International Envelope Craft for Vandhoo RWMF MV-MEE-88180-GO-DIR / Component 1: National Solid Mobile Stack Emission IDA / D1990 Waste Management Strategy Post Direct Selection Direct 25,000.00 25,149.23 Completed 2018-11-27 2018-11-27 2018-11-29 2018-11-28 2018-12-08 2018-12-06 2019-01-22 2019-02-10 Monitoring Equipment and Policy MV-MEE-83258-GO-DIR / Component 1: National Solid Supply of Mobile Stack IDA / D1990 Waste Management Strategy Prior Direct Selection Direct 25,000.00 0.00 Canceled 2018-10-25 2018-10-28 2018-11-10 2018-12-10 Emission Monitoring and Policy Equipment MV-MEE-96293-GO-RFB / Supply and Installation of Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 300,000.00 0.00 Canceled 2019-01-24 2019-01-31 2019-02-28 2019-03-14 2019-04-18 2019-07-17 Water and Fuel Storage Waste Management Systems International Envelope Tanks at Vandhoo RWMF MV-MEE-83996-GO-RFB / Procurement of Reach Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-02-15 2019-02-18 2019-03-11 2019-03-25 2019-04-22 2019-06-21 Stackers (2 nos) for Vandhoo Waste Management Systems Envelope RWMF MV-MEE-81934-GO-RFB / Component 2: Regional Single Stage - One Procurement of a tractor IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-02-14 2019-02-17 2019-03-17 2019-03-24 2019-04-21 2019-06-20 Waste Management Systems Envelope and trailer MV-MEE-83997-GO-RFB / Procurement of Hooklift Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2019-02-14 2019-02-19 2019-03-12 2019-03-26 2019-04-16 2019-06-15 Trucks (2 nos.) for Vandhoo Waste Management Systems Envelope RWMF MV-MEE-83999-GO-RFB / Procurement of Generator Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 75,000.00 0.00 Canceled 2019-02-15 2019-05-19 2019-02-20 2019-05-20 2019-03-13 2019-06-02 2019-03-27 2019-04-24 2019-06-23 (300 KVA) for Vandhoo Waste Management Systems Envelope RWMF MV-MEE-99932-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Weighing IDA / D1990 Post Open - National 25,000.00 15,230.00 Completed 2019-02-11 2019-03-21 2019-06-04 2019-04-25 2019-09-01 Management Quotations Envelope Scales MV-MEE-110470-GO-RFQ / Component 3: Island Waste Request for Single Stage - One Purchase Glass Crusher N. IDA / D1990 Post Limited 6,500.00 6,449.27 Completed 2019-04-17 2019-03-25 2019-05-07 2019-05-21 2019-06-06 2019-05-22 Management Systems Quotations Envelope Kudafari MV-MEE-106471-GO-RFB / Component 2: Regional Open - Single Stage - One Landing craft for waste IDA / D1990 Prior Request for Bids 750,000.00 0.00 Canceled 2019-05-13 2019-05-16 2019-06-13 2019-06-23 2019-07-21 2020-02-16 Waste Management Systems International Envelope transfer in zone II MV-MEE-115522-GO-RFB / Vandhoo Fire Fighting Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-05-20 2019-07-07 2019-05-25 2019-07-07 2019-06-15 2019-06-29 2019-07-27 2019-09-25 System - Immediate Waste Management Systems Envelope Requirement MV-MEE-60157-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Tablet IDA / D1990 Post Limited 20,840.00 0.00 Canceled 2019-07-14 2019-07-30 2019-09-01 2019-10-01 Management Quotations Envelope Computers MV-MEE-121944-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 25,000.00 0.00 Canceled 2019-07-19 2019-09-13 2019-10-13 Office Furniture Management Quotations Envelope MV-MEE-121947-GO-RFQ / Component 4: Project Request for Single Stage - One Purchase of Photography / IDA / D1990 Post Open - National 20,000.00 19,700.13 Completed 2019-07-23 2019-09-17 2019-11-04 2019-10-17 2019-11-07 Management Quotations Envelope Videography equipment MV-MEE-121950-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 15,000.00 17,598.33 Signed 2019-07-26 2019-09-20 2019-12-10 2019-10-20 Software Management Quotations Envelope Page 5 MV-MEE-124036-GO-RFB / Supply and Installation of Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 64,366.10 Completed 2019-07-23 2019-07-31 2019-07-28 2019-08-04 2019-08-18 2019-08-25 2019-09-01 2019-10-13 2019-09-29 2019-11-19 2019-11-28 2019-12-09 Fire Fighting Equipment - Waste Management Systems Envelope Immediate Requirement MV-MEE-128581-GO-DIR / Upgrading of CEMS with Component 2: Regional IDA / D1990 Post Direct Selection 28,000.00 27,913.24 Completed 2019-08-22 2019-08-27 2019-08-25 2019-08-22 2019-09-08 2019-09-24 2019-11-07 2019-11-15 CO and NOx probes and Waste Management Systems larger analyzer control unit MV-MEE-128582-GO-RFQ / Component 4: Project Request for Single Stage - One Desktops and Computer IDA / D1990 Post Limited 15,000.00 19,961.39 Completed 2019-08-28 2019-09-04 2019-10-16 2019-10-07 2019-11-15 2019-10-30 Management Quotations Envelope Accessories MV-MEE-128583-GO-RFQ / Component 4: Project Request for Single Stage - One Laptops and Tablet IDA / D1990 Post Limited 20,000.00 24,848.77 Signed 2019-08-28 2019-09-04 2019-10-16 2020-01-06 2019-11-15 Management Quotations Envelope computers MV-MEE-135475-GO-RFB / Component 2: Regional Single Stage - One Supply and Installation of IDA / D1990 Post Request for Bids Open - National 75,000.00 39,401.62 Signed 2019-09-24 2019-09-25 2019-09-29 2019-11-10 2019-10-10 2019-12-10 2019-12-01 2020-01-14 2020-02-02 2020-07-12 Waste Management Systems Envelope 300 KVA Generator MV-MEE-84003-GO-RFB / Waste Collection Vehicles Component 3: Island Waste Open - Single Stage - One IDA / D1990 Prior Request for Bids 703,500.00 0.00 Canceled 2019-12-30 2020-01-06 2020-02-03 2020-02-17 2020-03-09 2020-05-08 with Trailers for Islands of Management Systems International Envelope Zone 2 (Batch 1) MV-MEE-158423-GO-RFQ / Component 4: Project Request for Single Stage - One Supply and Delivery of IDA / D1990 Post Limited 10,000.00 7,884.86 Signed 2020-03-04 2020-03-01 2020-04-22 2020-08-13 2020-05-22 Management Quotations Envelope Office Printers MV-MEE-158445-GO-RFB / Component 1: National Solid Supply of Equipment for Open - Single Stage - One IDA / D1990 Waste Management Strategy Post Request for Bids 125,000.00 0.00 Canceled 2020-08-02 2020-08-05 2020-09-02 2020-09-16 2020-10-14 2021-01-12 Monitoring and Research International Envelope and Policy Vessel MV-MEE-160642-GO-RFB / Under Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Prior Request for Bids 500,000.00 0.00 Implementati 2020-07-20 2020-08-24 2020-07-27 2020-09-07 2020-09-21 2020-10-26 2021-06-23 Commissioning of a Waste Waste Management Systems International Envelope on Sorting line MV-MEE-81932-GO-RFB / Under Procurement of 1 Backhoe Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 200,000.00 0.00 Implementati 2020-07-23 2020-08-21 2020-07-30 2020-08-21 2020-09-10 2020-09-24 2020-10-22 2021-03-21 Loader and 1 Wheel Loader Waste Management Systems International Envelope on for Vandhoo RWMF MV-MEE-162964-GO-DIR / Under Supply and installation of Component 2: Regional IDA / D1990 Post Direct Selection 3,300.00 0.00 Implementati 2020-04-15 2020-03-06 2020-04-19 2020-03-07 2020-05-02 2020-05-16 Instrument Air Clean Up Waste Management Systems on System MV-MEE-158467-GO-RFB / Supply and Delivery of Component 3: Island Waste Open - Single Stage - One Autoclaves and Accessories IDA / D1990 Post Request for Bids 430,000.00 0.00 Canceled 2020-04-15 2020-04-22 2020-05-20 2020-06-10 2020-07-08 2020-11-05 Management Systems International Envelope for Health Care Facilities of Zone 2 MV-MEE-158471-GO-RFB / Supply and Delivery of Component 3: Island Waste Open - Single Stage - One Autoclaves and Accessories IDA / D1990 Post Request for Bids 430,000.00 0.00 Canceled 2020-08-01 2020-08-08 2020-09-19 2020-10-03 2020-10-31 2021-02-28 Management Systems International Envelope for Health Care Facilities of Zone IV & V MV-MEE-183904-GO-RFB / Supply and Delivery of Component 3: Island Waste Open - Single Stage - One Autoclaves and Consumables IDA / D1990 Prior Request for Bids 860,000.00 0.00 Canceled 2020-07-20 2020-07-27 2020-08-24 2020-09-07 2020-09-28 2021-02-25 Management Systems International Envelope for Hospitals and Health Centers in Zone 2, 4 and 5 Page 6 MV-MEE-189102-GO-UN / Under Medical Waste Autoclaves Component 3: Island Waste UN Agencies IDA / D1990 Prior Direct 860,000.00 0.00 Implementati 2020-08-25 2020-09-14 2020-09-01 2020-09-29 2020-12-28 for Hospitals and Health Management Systems (Direct) on Centers of Zone 2, 4 and 5 MV-MEE-158470-GO-RFB / Installation of Organic Component 3: Island Waste Open - Single Stage - One IDA / D1990 Post Request for Bids 360,000.00 0.00 Canceled 2021-05-16 2021-05-23 2021-06-13 2021-06-27 2021-07-25 2021-12-22 Waste Treatment Systems in Management Systems International Envelope Islands of Zone 2 MV-MEE-158454-GO-RFB / Pending Supply and installation of a Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 50,000.00 0.00 Implementati 2022-10-20 2022-10-27 2022-11-24 2022-12-08 2023-01-05 2023-04-05 waste monitoring system for Waste Management Systems International Envelope on Zone 2 MV-MEE-158474-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Waste Management IDA / D1990 Prior Request for Bids 960,000.00 0.00 Implementati 2021-01-21 2021-01-28 2021-03-11 2021-03-25 2021-04-29 2021-10-26 Management Systems International Envelope Equipment for Islands of on Zone IV & V MV-MEE-190295-GO-RFB / Supply, Installation and Pending Commissioning of Pilot Component 3: Island Waste Open - Single Stage - One IDA / D1990 Post Request for Bids 525,000.00 0.00 Implementati 2020-11-15 2020-11-22 2020-12-20 2021-01-10 2021-02-14 2021-11-11 Systems for Bio-treatment of Management Systems International Envelope on Organic Waste (AD and Composting technology) MV-MEE-158469-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Additional Waste IDA / D1990 Post Request for Bids 407,500.00 0.00 Implementati 2020-11-15 2020-11-20 2020-12-18 2021-01-01 2021-01-29 2021-06-28 Management Systems International Envelope Management Equipment for on IWMCs of Zone 2 Pending MV-MEE-160655-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Limited 6,258.00 0.00 Implementati 2020-11-29 2021-01-10 2021-02-09 Furniture for PMU Management Quotations Envelope on MV-MEE-160637-GO-RFB / Pending Component 2: Regional Open - Single Stage - One Supply and Delivery of a IDA / D1990 Prior Request for Bids 750,000.00 0.00 Implementati 2021-04-01 2021-04-08 2021-05-06 2021-05-27 2021-07-01 2022-02-26 Waste Management Systems International Envelope Landing Craft on MV-MEE-158459-GO-RFB / Pending Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 100,000.00 0.00 Implementati 2021-02-04 2021-02-11 2021-03-11 2021-04-01 2021-04-29 2021-09-26 Commissioning of a Weigh Waste Management Systems International Envelope on Bridge for Vandhoo RWMF MV-MEE-189271-GO-DIR / Component 1: National Solid Pending Equipment for Monitoring IDA / D1990 Waste Management Strategy Post Direct Selection Direct 170,000.00 0.00 Implementati 2020-11-05 2020-11-12 2020-12-03 2021-03-03 and Research Vessel and Policy on MV-MEE-158448-GO-RFB / Pending Component 2: Regional Single Stage - One Supply and Delivery of 1 IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2020-11-15 2020-11-22 2020-12-20 2021-01-10 2021-02-07 2021-07-07 Waste Management Systems Envelope Flat Bottom Whaler on MV-MEE-158449-GO-RFB / Pending Supply and Installation of 2 Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 100,000.00 0.00 Implementati 2021-01-14 2021-01-21 2021-02-18 2021-03-04 2021-04-08 2021-09-05 static Cranes at Vandhoo Waste Management Systems International Envelope on Harbour MV-MEE-158450-GO-RFB / Pending Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 150,000.00 0.00 Implementati 2020-11-10 2020-11-17 2020-12-08 2020-12-22 2021-01-19 2021-07-18 Commissioning of an RO Waste Management Systems International Envelope on Plant with Borehole Drilling MV-MEE-158451-GO-RFQ / Pending Supply and Installation of Component 2: Regional Request for Single Stage - One IDA / D1990 Post Limited 20,000.00 0.00 Implementati 2020-11-18 2021-01-27 2021-04-27 Surface Aerators for Waste Management Systems Quotations Envelope on Leachate Pond Page 7 MV-MEE-201690-GO-RFB / Pending Equipment for the Regional Component 2: Regional Open - Single Stage - One IDA / D1990 Prior Request for Bids 1,537,500.00 0.00 Implementati 2021-01-28 2021-02-02 2021-03-16 2021-04-06 2021-05-11 2021-12-07 Waste Transfer System of Waste Management Systems International Envelope on Zone 4 & 5 MV-MEE-201700-GO-RFB / Pending Component 2: Regional Open - Single Stage - One Waste Transfer Vessels for IDA / D1990 Prior Request for Bids 2,550,000.00 0.00 Implementati 2021-02-04 2021-02-11 2021-03-25 2021-04-22 2021-05-27 2022-02-21 Waste Management Systems International Envelope Zones 4 & 5 on MV-MEE-158468-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Vehicles for Island Level IDA / D1990 Post Request for Bids 421,500.00 0.00 Implementati 2021-01-24 2021-01-31 2021-03-14 2021-04-04 2021-05-02 2021-09-29 Management Systems International Envelope Waste Collection Systems in on Zone 2 (Batch 2) MV-MEE-158472-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Vehicles for Island Level IDA / D1990 Prior Request for Bids 1,075,000.00 0.00 Implementati 2021-01-14 2021-01-21 2021-03-04 2021-03-18 2021-04-22 2021-10-19 Management Systems International Envelope Waste Collection Systems - on Zone 4 & 5 MV-MEE-201836-GO-RFB / Pending Vehicles for Island Level Component 3: Island Waste Open - Single Stage - One IDA / D1990 Prior Request for Bids 703,500.00 0.00 Implementati 2020-11-15 2020-11-22 2021-01-03 2021-01-17 2021-02-07 2021-07-07 Waste Collection Systems of Management Systems International Envelope on Zone 2 (Batch 1) MV-MEE-158475-GO-RFB / Pending Supply and Delivery of Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 30,100.00 0.00 Implementati 2021-01-14 2021-01-21 2021-02-18 2021-03-11 2021-04-15 2021-08-13 Weighing Scales for IWMCS Management Systems Envelope on of Zone IV & V MV-MEE-158424-GO-RFQ / Pending Supply and Delivery of Component 4: Project Request for Single Stage - One IDA / D1990 Post Limited 14,270.00 0.00 Implementati 2020-11-29 2021-01-24 2021-02-23 Tablets and Peripherals for Management Quotations Envelope on Surveying NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-153553-NC-DIR / Installation and Component 2: Regional commissioning support of IDA / D1990 Post Direct Selection Direct 6,000.00 5,954.92 Signed 2020-02-02 2020-03-01 2020-02-07 2020-01-08 2020-02-19 2020-03-06 2020-03-04 Waste Management Systems CEMS and Analyzer and delivery of training. MV-MEE-189371-NC-RFQ / Pending 3D Visualization of Zone 2 Component 3: Island Waste Request for Single Stage - One IDA / D1990 Post Limited 7,000.00 0.00 Implementati 2020-11-22 2021-01-03 2021-03-04 Regional Waste Management Management Systems Quotations Envelope on System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-25845-CS-QCBS / Feasibility Study for a Regional Waste Management Component 3: Island Waste Quality And Cost- Open - IDA / D1990 Prior 200,000.00 265,200.34 Signed 2017-08-23 2017-08-24 2017-08-24 2017-08-24 2017-09-21 2018-01-23 2017-10-19 2018-03-12 2017-11-02 2017-12-07 2018-09-26 2018-01-04 2018-12-10 2018-09-01 System in Zone IV (Meemu, Management Systems Based Selection International Faafu and Dhaalu Atoll) and V (Thaa and Laamu Atoll) Page 8 MV-MEE-46609-CS-LCS / Component 4: Project Least Cost IDA / D1990 Post Open - National 15,000.00 24,747.08 Signed 2018-02-12 2018-03-15 2018-02-26 2018-03-12 2018-06-03 2018-03-26 2018-06-24 2018-04-02 2018-07-05 2018-04-23 2018-07-14 2018-05-14 2018-09-24 2024-01-08 Services of Internal Auditor Management Selection MV-MEE-60156-CS-CQS / Institutional Needs Component 1: National Solid Consultant Assessment and Developing IDA / D1990 Waste Management Strategy Post Qualification Open - National 25,000.00 0.00 Canceled 2018-05-01 2018-05-15 2018-06-05 2018-06-12 2018-07-17 2018-10-15 a Capacity Building Plan for and Policy Selection Waste Management Corporation Ltd. MV-MEE-80796-CS-CQS / Preparation of Environmental and Social Impact Component 1: National Solid Consultant Assessment for the proposed IDA / D1990 Waste Management Strategy Post Qualification Limited 20,000.00 22,004.25 Completed 2018-10-04 2018-10-02 2018-10-11 2018-10-21 2018-10-17 2018-11-14 2018-11-01 2018-11-26 2018-12-25 2019-01-07 upgrading of infrastructure and Policy Selection at Regional Waste Management Facility - Zone 2 MV-MEE-110477-CS-QCBS / Revision of Waste Component 1: National Solid Quality And Cost- Management Policy and IDA / D1990 Waste Management Strategy Post Open - National 75,000.00 0.00 Under Review 2019-04-16 2019-04-15 2019-04-30 2019-05-12 2019-06-02 2019-06-09 2019-06-19 2019-07-24 2019-12-21 Based Selection Preparation of Waste and Policy Management Strategy MV-MEE-136399-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste IDA / D1990 Post Qualification Open - National 20,000.00 0.00 Canceled 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Selection Waste Management Centre in F. Feeali, M. Kolhufushi, Th. Guraidhoo & Th. Hirilandhoo MV-MEE-136401-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste IDA / D1990 Post Qualification Open - National 20,000.00 0.00 Canceled 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Selection Waste Management Centre in Dh. Maaenboodhoo, M. Dhigarru, L. Gan & L. Dhanbidhoo MV-MEE-128592-CS-CQS / Selection of a Consultancy Consultant Firm to prepare the detailed Component 2: Regional IDA / D1990 Post Qualification Open - National 50,000.00 0.00 Canceled 2019-08-25 2019-08-27 2019-09-15 2019-09-08 2019-10-29 2019-11-28 2020-01-02 2020-06-30 design for Fire Protection Waste Management Systems Selection System in R. Vandhoo and Supervision Consultancy MV-MEE-142985-CS-CQS / Selection of a Consultant to Consultant prepare the detailed design Component 2: Regional IDA / D1990 Post Qualification Open - National 50,000.00 0.00 Canceled 2020-02-27 2020-03-01 2020-03-19 2020-03-02 2020-04-09 2020-04-16 2020-05-10 2021-02-04 for Fire Protection System Waste Management Systems Selection in R. Vandhoo and Supervision MV-MEE-158464-CS-CQS / Consultant Component 3: Island Waste Under ESIAs/ ESMPs for Island IDA / D1990 Post Qualification Open - National 99,000.00 0.00 2020-07-19 2020-08-06 2020-07-26 2020-08-12 2020-08-16 2020-08-30 2020-09-20 2020-12-19 Management Systems Implementation Waste Management Centres Selection MV-MEE-158446-CS-CQS / Consultant Detailed Design & Work Component 2: Regional IDA / D1990 Post Qualification Open - National 150,000.00 0.00 Canceled 2021-01-17 2021-01-24 2021-03-07 2021-03-21 2021-04-25 2022-12-16 Supervision of the RWMF - Waste Management Systems Selection Zone IV/V Page 9 MV-MEE-158447-CS-CQS / Consultant ESIA for the Proposed Component 2: Regional IDA / D1990 Post Qualification Open - National 100,000.00 0.00 Canceled 2020-10-20 2020-11-17 2020-12-15 2020-12-16 2021-01-13 2021-07-12 Regional Waste Management Waste Management Systems Selection System - Zone IV & V MV-MEE-181012-CS-CQS / Consultancy for the Detailed Consultant Design and Work Component 2: Regional Under IDA / D1990 Post Qualification Open - National 50,000.00 0.00 2020-07-20 2020-07-22 2020-07-27 2020-07-22 2020-08-31 2020-08-19 2020-09-14 2020-10-05 2021-07-02 Supervision of the Fire Waste Management Systems Implementation Selection Protection System in Vandhoo RWMF MV-MEE-158466-CS-CQS / Consultant Development of Information, Component 3: Island Waste Under IDA / D1990 Post Qualification Open - National 100,000.00 0.00 2020-08-27 2020-08-27 2020-09-03 2020-09-14 2020-10-01 2020-10-22 2020-11-12 2021-05-11 Education and Management Systems Implementation Selection Communication Toolkit MV-MEE-158465-CS-CQS / Consultant Design and Works Component 3: Island Waste Under IDA / D1990 Post Qualification Open - National 100,000.00 0.00 2020-08-25 2020-08-25 2020-08-28 2020-09-18 2020-10-02 2020-10-23 2021-09-18 Supervision Consultant for Management Systems Implementation Selection IWMCs of Zone IV & V MV-MEE-158432-CS-CQS / Component 1: National Solid Consultant Design and Establishment of Pending IDA / D1990 Waste Management Strategy Post Qualification Open - National 100,000.00 0.00 2022-01-06 2022-01-13 2022-03-03 2022-03-24 2022-04-21 2022-10-18 a National Solid Waste Implementation and Policy Selection Monitoring System MV-MEE-160554-CS-CQS / Component 1: National Solid Consultant Study on the Quantum and Open - Pending IDA / D1990 Waste Management Strategy Post Qualification 100,000.00 0.00 2020-11-05 2020-11-12 2020-12-31 2021-01-21 2021-02-11 2021-08-10 Collection of User-fee and International Implementation and Policy Selection Tariffs for SWM MV-MEE-160547-CS-CQS / Review of Nation Waste Component 1: National Solid Consultant Open - Pending Management Policy and IDA / D1990 Waste Management Strategy Post Qualification 175,000.00 0.00 2020-11-10 2020-11-17 2020-12-29 2021-01-19 2021-02-09 2021-12-06 International Implementation formulation of a National and Policy Selection WM Strategy MV-MEE-158433-CS-CQS / Augmentation of Curriculum Component 1: National Solid Consultant Pending for Bachelor of IDA / D1990 Waste Management Strategy Post Qualification Open - National 25,000.00 0.00 2020-11-12 2020-11-26 2020-12-10 2020-12-31 2021-01-21 2021-04-21 Implementation Environmental Management and Policy Selection Programme, MNU MV-MEE-201832-CS-CQS / Environmental & Social Consultant Component 3: Island Waste Pending Impact Assessments for IDA / D1990 Post Qualification Open - National 56,000.00 0.00 2020-11-15 2020-11-20 2020-12-18 2021-01-01 2021-01-29 2021-04-29 Management Systems Implementation IWMCs to be Upgraded in Selection Zone IV and V INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-37124-CS-INDV / Component 1: National Solid Individual Consultancy for Preparing IDA / D1990 Waste Management Strategy Prior Consultant Direct 24,000.00 29,350.00 Under Review 2017-11-26 2018-01-21 2017-12-06 2018-02-26 2017-12-13 2018-03-21 2017-12-27 2018-03-21 2018-02-10 the Operations Plan of and Policy Selection Vandhoo RWMF (Zone 2) MV-MEE-37110-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Prior Consultant Direct 90,000.00 124,695.98 Signed 2017-11-21 2017-11-24 2017-11-27 2017-12-10 2017-12-04 2018-02-13 2017-12-16 2018-02-15 2020-12-15 Management Specialist for PMU Selection Individual MV-MEE-39091-CS-INDV / Component 4: Project IDA / D1990 Post Consultant Open 90,000.00 90,000.00 Signed 2017-12-28 2018-02-01 2018-01-13 2018-03-04 2018-01-15 2018-03-04 2018-02-01 2018-03-19 2021-01-17 Civil Engineer for PMU Management Selection Page 10 MV-MEE-41149-CS-INDV / Individual Component 4: Project Monitoring and Evaluation IDA / D1990 Post Consultant Open 90,000.00 0.00 Under Review 2017-12-31 2018-08-01 2018-01-17 2018-01-22 2018-02-15 2021-01-30 Management Specialist for PMU Selection MV-MEE-41150-CS-INDV / Individual Component 4: Project Communications Specialist IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2018-01-04 2018-03-12 2018-01-28 2018-05-29 2018-01-31 2018-05-29 2018-02-15 2018-06-16 2021-01-30 Management for PMU Selection MV-MEE-48404-CS-CDS / Component 4: Project Procurement Specialist for IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Under Review 2018-02-14 2018-02-22 2018-02-28 2021-02-28 Management PMU MV-MEE-48407-CS-CDS / Environmental and Social Component 4: Project IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Canceled 2018-02-15 2018-02-26 2018-02-22 2018-02-28 2021-02-28 Safeguards Specialist for Management PMU MV-MEE-53309-CS-INDV / Component 1: National Solid Individual Preparation of EMPs for 6 IDA / D1990 Waste Management Strategy Post Consultant Open 15,000.00 11,966.36 Signed 2018-03-18 2018-04-10 2018-04-04 2018-05-15 2018-04-11 2018-05-15 2018-05-09 2018-06-11 2018-07-08 Selected Island Waste and Policy Selection Management Centres MV-MEE-53794-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-08-06 2018-04-16 2018-10-04 2018-04-23 2018-10-17 2018-05-14 2018-10-21 2021-08-16 for PMU Component Selection MV-MEE-54013-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-08-06 2018-04-07 2018-11-22 2018-04-14 2018-12-12 2018-05-12 2018-12-16 2021-08-14 for PMU Component Selection MV-MEE-64614-CS-INDV / Institutional Needs Component 1: National Solid Individual Assessment of Waste IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 Under Review 2018-06-03 2018-06-06 2018-07-02 2018-07-16 2018-08-13 2018-10-12 Management Corporation and Policy Selection Ltd. MV-MEE-79643-CS-INDV / Services of a Naval Individual Architect/Engineer for the Component 4: Project IDA / D1990 Post Consultant Limited 35,000.00 29,922.38 Completed 2018-09-28 2018-10-08 2018-09-30 2018-10-23 2018-10-15 2018-10-23 2018-11-01 2019-01-15 2019-12-31 2020-01-14 supervision of marine vessel Management Selection construction projects under MCEP MV-MEE-81147-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Post Consultant Open 54,000.00 46,944.37 Signed 2018-10-08 2018-08-07 2018-10-14 2018-10-08 2018-10-21 2018-10-29 2018-11-01 2018-11-16 2021-10-31 Management Assistant Selection MV-MEE-81381-CS-INDV / Preparation of the detailed master plan layout and Individual detailed design of required Component 2: Regional IDA / D1990 Post Consultant Limited 20,000.00 24,655.90 Signed 2018-10-18 2018-10-04 2018-10-21 2018-10-10 2018-10-28 2019-01-10 2018-11-18 2018-11-22 2019-01-02 additional infrastructure for Waste Management Systems Selection the Regional Waste Management Facility of Zone- 2 MV-MEE-87721-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-11-22 2018-08-06 2018-11-22 2018-11-22 2018-12-10 2018-12-11 2018-12-16 2019-01-16 2022-03-20 for PMU Component Selection MV-MEE-48421-CS-CDS / Component 4: Project IDA / D1990 Prior Direct Selection Direct 108,000.00 0.00 Canceled 2018-02-15 2018-02-28 2018-02-23 2018-02-28 2021-02-28 Project Manager for PMU Management Individual MV-MEE-93341-CS-INDV / Component 4: Project IDA / D1990 Post Consultant Open 48,000.00 67,063.39 Signed 2019-02-10 2018-11-14 2019-03-08 2019-03-26 2019-03-22 2019-03-26 2019-04-19 2019-04-09 2021-04-19 Project Coordinator (Zone 2) Management Selection Page 11 MV-MEE-80820-CS-INDV / Individual Component 4: Project Project Coordinator (Zone IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2019-05-17 2018-07-23 2019-05-30 2018-10-04 2019-06-02 2018-10-18 2019-06-19 2018-10-21 2022-06-18 Management 4&5) for PMU Selection MV-MEE-83452-CS-CDS / Operations Specialist for Component 2: Regional IDA / D1990 Prior Direct Selection Direct 120,000.00 297,807.18 Signed 2019-05-10 2019-05-19 2019-05-15 2019-05-27 2019-06-01 2019-06-07 2020-05-31 Vandhoo RWMF (12 month Waste Management Systems assignment) MV-MEE-83995-CS-CDS / Incinerator Specialist for Component 2: Regional IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Canceled 2019-05-15 2019-05-25 2019-06-15 2020-04-10 Vandhoo RWMF (10 months Waste Management Systems period) MV-MEE-113875-CS-INDV / Development of a Component 1: National Solid Individual Management Information IDA / D1990 Waste Management Strategy Post Consultant Limited 7,500.00 0.00 Canceled 2019-05-10 2019-05-19 2019-05-13 2019-06-03 2019-05-16 2019-06-01 2019-07-01 System (MIS) Database for and Policy Selection Solid Waste Management MV-MEE-113891-CS-INDV / Individual Consultancy Services for Component 4: Project IDA / D1990 Post Consultant Limited 15,000.00 14,961.19 Signed 2019-05-10 2019-05-19 2019-05-13 2019-05-24 2019-05-16 2019-05-29 2019-06-02 2019-06-18 2019-07-02 Undertaking an Independent Management Selection Evaluation of MCEP MV-MEE-115528-CS-INDV / Individual Component 2: Regional Fire Fighting Design and IDA / D1990 Post Consultant Limited 50,000.00 0.00 Canceled 2019-05-26 2019-06-30 2019-05-29 2019-07-31 2019-06-01 2019-06-18 2019-08-17 Waste Management Systems Supervision Consultant Selection MV-MEE-126235-CS-INDV / Component 1: National Solid Individual Consultancy for Strategic IDA / D1990 Waste Management Strategy Post Consultant Open 4,000.00 4,527.81 Signed 2019-08-06 2019-08-20 2019-08-27 2019-09-01 2019-09-01 2019-09-02 2019-10-06 2019-09-15 2019-10-12 planning of Single use and Policy Selection plastic phase-out Plan MV-MEE-133400-CS-INDV / Preparation of ESMP for Component 1: National Solid Individual upgrading of IWMCs in 2 IDA / D1990 Waste Management Strategy Post Consultant Open 10,000.00 0.00 Canceled 2019-12-15 2020-01-01 2020-01-08 2020-02-05 2020-04-05 selected islands of Zone 2 - and Policy Selection (B. Eydhafushi & R. Maakurathu) MV-MEE-159364-CS-INDV / Services of a Naval Individual Architect / Engineer for the Component 4: Project IDA / D1990 Post Consultant Limited 30,000.00 27,943.08 Signed 2020-02-27 2020-03-02 2020-03-05 2020-07-07 2020-03-19 2020-07-19 2020-04-05 2020-08-26 2021-04-04 supervision of marine vessel Management Selection construction projects under MCEP MV-MEE-48441-CS-INDV / Augmentation of Curriculum Component 1: National Solid Individual for Environmental IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 Canceled 2020-09-01 2020-10-06 2020-10-20 2020-11-17 2021-04-16 Management Diploma/Degree and Policy Selection Program of MNU MV-MEE-189094-CS-CDS / Updating of Environmental and Social Management Plans (ESMPs) for the Component 3: Island Waste IDA / D1990 Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-08-24 2020-08-24 2020-08-31 2020-08-26 2020-09-11 2020-10-11 islands of M. Mulah, Th. Management Systems Omadhoo, Th. Buruni, Th. Thimarafushi, Th. Kinbidhoo and Th. Madifushi MV-MEE-158444-CS-INDV / Component 1: National Solid Individual International Advisor on IDA / D1990 Waste Management Strategy Prior Consultant Open 400,000.00 0.00 Canceled 2020-10-01 2020-11-19 2020-12-03 2021-01-01 2022-12-31 SWM (to be based in Waste and Policy Selection Department, MoE) Page 12 MV-MEE-189092-CS-CDS / Completion of Feasibility Component 2: Regional Pending Studies for a Regional Solid IDA / D1990 Post Direct Selection Direct 100,000.00 0.00 2020-11-05 2020-11-19 2020-12-10 2021-04-09 Waste Management Systems Implementation Waste Management System in Zone 4 & 5 MV-MEE-201704-CS-INDV / Individual Operations and Management Component 2: Regional Pending IDA / D1990 Post Consultant Limited 45,000.00 0.00 2021-11-18 2021-11-23 2021-12-14 2022-01-25 2022-06-24 Plan for Zone IV/V Regional Waste Management Systems Implementation Selection Waste Management System MV-MEE-201860-CS-INDV / Individual Consultancy Services for Component 4: Project Pending IDA / D1990 Post Consultant Limited 15,000.00 0.00 2021-02-04 2021-02-18 2021-03-04 2021-04-08 2021-07-07 Undertaking an Independent Management Implementation Selection Evaluation of the Project Page 13