SFG3705 REV Guangxi Hezhou Urban Water Infrastructure & Environment Improvement Project Environmental Impact Assessment Report Management Agency: Hezhou World Bank Loan Project Management Office Prepared by: Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: January 2018 CONTENT 1. GENERAL ........................................................................................................ - 1 - 1.1 RATIONALE .......................................................................................................- 3 - 1.2 OBJECTIVES OF EIA ........................................................................................- 8 - 1.3 PRINCIPLES OF EIA ...........................................................................................- 8 - 1.4 ENVIRONMENTAL FUNCTIONAL ZONING AND EVALUATION CRITERIA ..........................- 8 - 1.5 ASSESSMENT LEVEL ........................................................................................- 13 - 1.6 KEY ASSESSMENT TASKS AND ASSESSMENT METHODS .....................................- 15 - 2. ENGINEERING ANALYSIS .............................................................................. - 17 - 2.1 PROJECT OVERVIEW ........................................................................................- 17 - 2.2 CURRENT CONDITIONS .....................................................................................- 31 - 2.3 IDENTIFICATION AND SCOPE OF ASSESSMENT OF PROJECT IMPACTS.....................- 38 - 2.4 PLANNING COMPLIANCE ANALYSIS ....................................................................- 68 - 3. DUE DILIGENCE OF LINKED PROJECTS ...................................................... - 77 - 3.1 LINKED PROJECT SCREENING ..........................................................................- 77 - 3.2 DUE DILIGENCE ..............................................................................................- 78 - 4. STATUS QUO SURVEY AND ANALYSIS........................................................ - 88 - 4.1 NATURAL ENVIRONMENT CONDITIONS ................................................................- 88 - 4.2 OVERVIEW OF SOCIAL ENVIRONMENT ...............................................................- 91 - 4.3 STATUS QUO OF ECOLOGICAL ENVIRONMENT ....................................................- 98 - 4.4 STATUS QUO INVESTIGATION AND EVALUATION OF ENVIRONMENT QUALITY ........- 101 - 5. ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION MEASURES ..... - 127 - 5.1 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION - 127 - 5.2 ANALYSIS OF ENVIRONMENTAL IMPACTS IN THE OPERATION STAGE ....................- 176 - 6. ENVIRONMENTAL RISK ANALYSIS AND MITIGATION MEASURES ......... - 189 - 6.1 IDENTIFICATION OF ENVIRONMENTAL RISKS ......................................................- 189 - 6.2 ANALYSIS OF POTENTIAL IMPACTS FROM WWTP ACCIDENTS WITH ENVIRONMENTAL RISKS .................................................................................................................- 189 - 6.3 RISK MITIGATION MEASURES ...........................................................................- 191 - 6.4 WWTP EMERGENCY RESPONSE UNIT AND ITS ROLES AND RESPONSIBILITIES ....- 194 - 7. CUMULATIVE IMPACT ASSESSMENT ...................................................... - 195 - 7.1 SCOPE OF CUMULATIVE IMPACT ASSESSMENT ..................................................- 195 - 7.2 STATUS QUO OF VEC ....................................................................................- 214 - 7.3 VEC CUMULATIVE IMPACT ANALYSIS...............................................................- 216 - 7.4 RECOMMENDED SAFEGUARD MEASURES .........................................................- 221 - 7.5 STAKEHOLDER PARTICIPATION IN THE CUMULATIVE IMPACT ASSESSMENT ...........- 221 - 8. LAR SOCIAL IMPACTS AND MITIGATION MEASURES .............................. - 228 - 8.1 LAND ACQUISITION AND RESETTLEMENT OF THE PROJECT .................................- 228 - 8.2 MEASURES FOR MITIGATING SOCIAL IMPACTS UNDER THE PROJECT ...................- 228 - 8.3 PUBLIC PARTICIPATION AND CONSULTATION ......................................................- 235 - 8.4 INSTITUTIONAL ARRANGEMENT AND DEVELOPMENT ...........................................- 235 - 8.5 GRIEVANCE REDRESS MECHANISM ..................................................................- 237 - 8.6 MONITORING AND EVALUATION ARRANGEMENTS ...............................................- 238 - 9. ALTERNATIVE ANALYSIS............................................................................. - 240 - 9.1 PURPOSE AND PRINCIPLES .............................................................................- 240 - 9.2 W ITH-/W ITHOUT-PROJECT ANALYSIS .............................................................- 240 - 9.3 DREDGING ALTERNATIVES ..............................................................................- 242 - 9.4 ALTERNATIVES FOR HYDROPOWER STATION IMPROVEMENT................................- 244 - 9.5 WWTP ALTERNATIVES ..................................................................................- 255 - 10. PUBLIC PARTICIPATION AND INFORMATION DISCLOSURE ................. - 260 - 10.1 PURPOSE OF PUBLIC PARTICIPATION ..............................................................- 260 - 10.2 SCOPING AND STAKEHOLDER IDENTIFICATION .................................................- 261 - 10.3 PUBLIC CONSULTATION.................................................................................- 265 - 10.4 INFORMATION DISCLOSURE ..........................................................................- 300 - 10.5 PUBLIC PARTICIPATION FOR SOCIAL IMPACT ASSESSMENT ..............................- 306 - 11. ENVIRONMENTAL & SOCIAL MANAGEMENT PLAN ................................ - 319 - 11.1 ENVIRONMENT AND SOCIAL MANAGEMENT SYSTEM ........................................- 319 - 11.2 ENVIRONMENTAL AND SOCIAL IMPACTS AND THEIR MITIGATION MEASURES .......- 325 - 11.3 ENVIRONMENTAL MONITORING PLAN .............................................................- 481 - 11.4 CAPACITY DEVELOPMENT AND TRAINING .......................................................- 497 - 11.5 REPORTING MECHANISM ..............................................................................- 502 - 11.6 GRIEVANCE REDRESS MECHANISM ...............................................................- 503 - 11.7 INVESTMENT ESTIMATION FOR ENVIRONMENTAL PROTECTION .........................- 505 - 12. EIA CONCLUSIONS AND RECOMMENDATIONS ...................................... - 507 - ANNEX 1:MONITORING DATA OF ENVIRONMENTAL QUALITY CONDITIONS IN THE PROJECT AREA ........................................................................................ - 510 - ANNEX 2:SURFACE WATER IMPACT PREDICTION PROCESS .................... - 554 - ANNEX 3:PUBLIC PARTICIPATION QUESTIONNAIRE AND FEEDBACKS .... - 563 - 1. General Hezhou Municipality is located in the northeastern part of Guangxi Zhuang Autonomous Region (GZAR) in Southwest China. A prefecture-level city established in Year 2002 with Hezhou Prefecture and Wuzhou Prefecture as its predecessors, Hezhou Municipality administers two districts of Babu District and Pinggui Administration District and three counties of Zhongshan County, Fuchuan Yao Autonomous County and Zhaoping County, with a total population of 2.35 million. Hezhou Municipality is located at east longitude 111°25′ ~ 112 ° 03 ′ and north latitude 23°39′~25°09′ and covers a total area of 11,855km2. Hezhou Municipality is located at the border area of Hunan Province, Guangdong Province and GZAR, known as the “Three-Province Thoroughfare� and “Backyard of Guangdong, Hong Kong and Macao�. Along with the construction of four expressways of Gui-Wu Expressway, Guang-He Expressway (2009), Yong-He Expressway (2010), and Nan-He Expressway and three railways of Luo-Zhan Railway (2009), Gui-Guang High-Speed Railway and Liu-Shao Railway as well as the development of airport and harbor, Hezhou will set up an integrated transportation network with all-directional reach and embrace unprecedented development opportunities. Hezhou Municipality does not only have advantages of geographic location, but also has rich ecological resources, in particular forest resources far much higher than the national average. Hezhou has a forest coverage rate of 72.88%, higher than the national average by a factor of 3.6 and ranks the second in the region. In addition, Hezhou Municipality has outstanding air quality and hot springs, waterfalls and beautiful scenery are distributed all over the city. Hezhou’s rich ecological resources have now become its most significant advantage and core competitiveness. He River is the main river in Hezhou Municipality and runs across the city from northwest to southeast before it joins Xijiang River System in Fengkai, Guangdong. Finalization of the city’s development strategy of "further expansion to the southern and western parts, further extension to the eastern part and focused optimization of the northern part� and the development orientation of “an emerging industrial and tourism city along Gui-Guang Economic Belt and portal and hub city in Northeast Guangxi� has paved the way for He River to become an important river in the urban centre in Hezhou serving the important functions of industrial and agricultural water supply, urban flood discharge and providing services for the cultural activities of local residents. Within the context of high-speed industrialization and urbanization and intensified global climate change over the recent years, Hezhou is in the face of increasingly prominent issues of frequent water disasters, aquatic ecological imbalance and water pollution and so on. All such issues have impeded the development of local economy and society. The main problems in flood control and water environment that Hezhou faces in the current stage include: Firstly, the flood control and drainage infrastructure in the urban area of Hezhou is very weak in contrast to the frequent flood events. He River runs through the urban -1- area of Hezhou Municipality, the major part of which is located in He Riverside belt along He River with no built dike or revetment in most parts. Without a sound flood control system, He River Watershed is very poor in terms of flood control. The increasingly frequent flood events have resulted in increasing serious economic losses. In the latest flood event in mid-November 2015, Hezhou experienced the heaviest winter rainfall ever recorded and 33 townships/towns/communities in the five counties/districts with a total population of 83,450 (including 4376 people for emergency displacement) and a total farmland area of more than 3100 ha were affected, ending up with a direct economic losses of over CNY 70 million. Secondly, municipal infrastructure construction is slow and the living environment needs further improvement. In Hezhou, which was established as a municipality quite recently, the existing municipal infrastructures constructed at lower standards and the road network poorly planned in both layout and structure cannot meet the needs of the growing size of the city. Most of the drainage networks are combined system of wastewater and stormwater constructed in 1990s against lower design standard. In the developed areas, wastewater and rainwater are directly discharged into adjacent rivers or He River via surface flow or ditch without any treatment, resulting in deteriorated water quality in city rivers and He River. The key water quality indicators, such as ammonia nitrogen, total nitrogen and fecal coliform, have exceeded relevant standards, implying the presence of pollution from domestic wastewater. Thirdly, some urban inland canals are slow in terms of water flow and deteriorated in terms of water quality because sediments and debris carried by the inner rivers of Huangansi and Shizigang flowing through the built urban area deposit on He River bed due to the absence of effective sewage interception. This situation is worsened by direct discharge of domestic wastewater of riverside residents and organizations. Consequently, He Rivers are very poor in terms of water quality and suffer from severe odors and black water. Deteriorated water environment and poor municipal infrastructures have become a bottleneck for external communication and economic integration, a serious restriction to the social and economic sustainability of Hezhou Municipality and a serious threat to the water security of Pearl River-Xijiang River Watershed. In order to promote the flood control capacity of He River and the drainage capacity and integrated utilization of water resources in the project area and improve the ecological environment and municipal infrastructure of Hezhou Municipality to support integrated development of the city, Hezhou Municipal Government decided to apply for a loan from the World Bank (Hereinafter referred to as “WB�) for the project. WB Loan Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project has been included in the national list of candidate projects utilizing WB loans. According to WB’s environmental policies, the project is categorized as a “Category A� project requiring a complete environmental impact assessment report, an environmental & social management plan and an executive summary. Hezhou Municipal Project Management Office of WB Loan (hereinafter referred to as the "PMO") entrusted Guangxi Zhengze Environmental Protection Technology Co., Ltd. (hereinafter referred to as "EIA consultant") to carry out the environmental impact assessment (hereinafter referred to as "EIA") for the Project. -2- 1.1 Rationale This report is prepared based on the requirements of the Law of the People’s Republic of China on Environmental Impact Assessment, the Management Regulations on Environment Protection of Construction Projects, and the Notice on Strengthening Management of Environmental Impact Assessment of Construction Projects Utilizing Loans from International Financial Institutions as well as WB Safeguard Policies. The EIA process is carried out not only in accordance with relevant laws and regulations, policies and standards of China, but also the relevant policies of the World Bank. 1.1.1 PRC National Laws and Regulations and Sector Regulations on Environmental Protection and Social Issues (1) Environmental Protection Law of the People’s Republic of China (amended in Year 2014); (2) Law of the People’s Republic of China on Environmental Impact Assessment (amended in Year 2016); (3) Law of the People’s Republic of China on Prevention and Control of Air Pollution (amended in Year 2015); (4) Law of the People’s Republic of China on Prevention and Control of Water Pollution (amended in Year 2008); (5) Law of the People’s Republic of China on Prevention and Control of Noise Pollution (amended in Year 1997); (6) Law of the People’s Republic of China on Prevention and Control of Environmental Pollution of Solid Wastes (amended in Year 2016); (7) Water and Soil Conservation Law of the Peoples Republic of China (amended in Year 2011); (8) Flood Control Law of the People’s Republic of China (amended in Year 2015); (9) Interim Methods for Public Participation in Environmental Impact Assessment (SEPA Huanfa Circular No. 2006[28], Feb. 14, 2006); (10) Methods for Public Participation in Environmental Protection (MoEP Decree No. (2015)35); (11) Notice on Strengthening Management of Environmental Impact Assessment of Construction Projects Utilizing Loans from International Financial Institutions (Huanjian Circular No. [1993]324); (12) Notice by the National Development and Reform Commission on Further Strengthening Management of Projects Utilizing Loans from International Financial Institutions (NDRC Foreign Investment Circular No. [2008]1269); (13) Management Catalogue of EIA Categories of Construction Projects (Sept. 1, 2017); (14) Notice by the State Council on Printing and Issuing the Action Plan on Prevention and Control of Water Pollution (State Council Circular No. [2015]17). (15) Law of the People’s Republic of China on Protection of Minors (Oct. 26, 2012); (16) Stipulations on Prohibition of Use of Child Labour (Issued in 1991 by the State Council); (17) Law of the People’s Republic of China on Protection of Women’s Rights and Interests (Aug. 28, 3005); (18) Labor Law of the People’s Republic of China (Aug. 27, 2009). -3- 1.1.2 Technical guidelines and specifications of EIA (1) Technical Guidelines on Environmental Impact Assessment – General (HJ2.1-2016) (2) Technical Guidelines on Environmental Impact Assessment - Surface Water Environment (HJ / T2.3-93) (3) Technical Guidelines on Environmental Impact Assessment - Atmospheric Environment (HJ2.2-2008) (4) Technical Guidelines on Environmental Impact Assessment - Sound Environment (HJ2.4-2009) (5) Technical Guidelines on Environmental Impact Assessment - Ecological Impact (HJ19-2011) (6) Technical Specifications on Soil and Water Conservation in Development and Construction Project (GB50433-2008) 1.1.3 Environmental quality and pollutant discharge standards Based on the features and nature of the Project, a comparative analysis will be carried out in the EIA process of the Project on the PRC national standards on environmental quality and pollutant discharge and the pollutant control standards and requirements included in General Guidelines on Environment, Health and Safety issued by the World Bank Group and the more stringent ones will be used as the basis for execution of the monitoring and assessment activities. (1) Ambient Air Quality Standard (GB3095-2012); (2) Surface Water Environmental Quality Standard (GB3838-2002); (3) Sound Environmental Quality Standard (GB3096-2008); (4) Soil Environmental Quality Standard (GB15618-1995); (5) Integrated Air Pollutant Emission Standard (GB16297-1996); (6) Odor Pollutant Emission Standard (GB14554-93); (7) Integrated Wastewater Discharge Standard (GB8978-1996); (8) Environmental Noise Emission Standards for Construction Sites (GB12523-2011); (9) Ambient Noise Emission Standard on the Boundary of Industrial Enterprises (GB12348-2008); (10) World Bank Group’s General Guidelines on Environment, Health and Safety; (11) World Bank Group’s Guidelines on Water and Sanitation, Health and Safety. 1.1.4 Relevant plans and references (1) The “13th Five-Year Plan �of Water Conservancy Development in Guangxi (2) The “13th Five-year Plan� of National Economic and Social Development of Hezhou Municipality (Draft); (3) Master Environmental Plan of Hezhou Municipality (2016-2030) (exposure draft) (4) Master Urban Plan of Hezhou Municipality (2016~ 2030); (5) Report of Urban Flood Control Planning of Hezhou Municipality, Guangxi (2010 ~ 2030); (6) Special Plan of Urban Road System and Vertical Design of Hezhou Municipality (2016~2030); (7) Planning of Ecological Water Areas and Water Systems in Hezhou Municipality (2014-2030); -4- (8) Controlled Detail Plan of the “One River, Two Banks" Core Area of Hezhou Municipality; (9) Comprehensive Planning of He River Watershed; (10) Feasibility Study Report of Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project (31 October, 2017); (11) Resettlement Plan of Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project (9 November, 2017). (12) Dam Safety Assessment Report of the Project ; (13) Report on the Soil and Water Conservation Program of the Project. 1.1.5 WB Safeguard Policies and Guidelines The correlation of the project and the WB's safeguards policy / procedure is analyzed. The results are shown in Table 1-1 below. Table 1-1 Correlation Analysis of the Project and the WB Safeguard Policies Safeguard S/N Triggered ? Explanation Policies The project is designed to assist Hezhou Municipality to address its existing challenges on environmental protection and flood control. The proposed investments include river rehabilitation and dredging, improvement of drainage system (pumping stations), construction of sewage interceptor, WWTP and associated pipelines and roads, and strengthening of water and ecological environment monitoring capacity. Based on the characteristics and scope of the Project, it is anticipated that the Project will involve the following environmental impacts: (1) The construction activities in the downtown area of Hezhou Municipality will generate certain environmental Environmental and social impacts, especially to the nearby residents 1 Assessment Yes and historical and heritage buildings on Xiyue Street. OP/BP 4.01 (2) Dredging of He River and its tributaries will generate environmental and social impacts. In the EIA process, the sludge nature and dredging quantity have been assessed and methods for dredging, sludge transportation, treatment and disposal are designed to minimize the impacts on local environment and residents. (3) The construction works under the Project (river rehabilitation, pumping station and wastewater treatment plant) will involve land acquisition and resettlement and thus significant social impacts. (4) The Project and the other development activities already -5- Table 1-1 Correlation Analysis of the Project and the WB Safeguard Policies Safeguard S/N Triggered ? Explanation Policies implemented, to be implemented and reasonably foreseeable on the urban section of He River will have accumulative impacts on flood control and water environment, which, according to analysis, are primarily positive impacts. Therefore, the Project triggers World Bank OP4.01 and is identified as Category A Project. The policy is triggered because the construction and operation of proposed WB investments will have impacts on natural habitats including aquatic and terrestrial ecosystem along He River and its tributaries. As per the requirements of OP4.04, survey on aquatic and terrestrial ecosystem were conducted in the project-affected area and no critical/sensitive natural habitat has been identified. The Natural project-related ecological impacts will be generally positive, 2 Habitats Yes and the anticipated adverse impacts are short-term, OP/BP 4.04 temporary and site-specific. The project has been developed in an environmentally sustainable way considering the protection of local species and biodiversity, and the specific mitigation measures were incorporated into the ESMP and ECOPs to ensure the potential adverse impacts were sufficiently addressed during construction and operation. The project will not finance activities that involve significant Forests conversion or degradation of critical forest or related critical 3 No OP/BP 4.36 habitat defined under the policy. This policy will not be triggered. Pest The proposed project will neither procure pesticides nor 4 Management No result in increased use of pesticides. This policy will not be OP 4.09 triggered. The EA process confirms that He River rehabilitation subprojects of He River main watercourse rehabilitation (Guangming Bridge - Lingfeng Bridge section), Huang’ansi Physical Flood Discharge Pump station and Discharge Canal Cultural Rehabilitation will have indirect impacts on some ancient 5 Yes Resources buildings on the nearby historical and cultural street of Xiyue OP/BP 4.11 Street in the construction stage. In particular, a 120m-long downstream section of Huang’ansi Channel is part of this provincial-level protected historic quarter. A PCR management plan has been developed as part of the ESMP -6- Table 1-1 Correlation Analysis of the Project and the WB Safeguard Policies Safeguard S/N Triggered ? Explanation Policies and mitigation measures have been developed to avoid, minimize and compensate the project-related impacts. In addition, the RAP survey also found that the subproject of central green corridor will affect 53 new tombs of rural family and might generate impacts on local sacrificial customs. All the compensation and relocation measures for those tombs have been formally planned and developed in the RAP based on detailed survey and extensive consultation. The Project is located in Hezhou Municipality of GZAR. Indigenous According to the investigation, there are no ethnic minorities 6 Peoples No in the project areas. Therefore, the project will not affect the OP/BP 4.10 ethnic minorities. Details will be further investigated during the project preparation. Project components, including watercourse widening of He River and its tributaries for flood discharge, river-lake Involuntary connection, Jiangnan WWTP, will involve extensive 7 Resettlement Yes occupation of land and also private house demolition. OP/BP 4.12 Therefore, in the project design, the impact of land acquisition has been minimized. The Project triggers OP4.12 and a Resettlement Plan has thus been prepared. It has been found during environmental screening that there are two dams upstream of the proposed WB Loan Project. However, there are three small hydroelectric stations involved in the Project for rehabilitation. This policy is therefore triggered considering their direct impacts on the Safety of safety of proposed interventions. The Borrower has 8 Dams OP/BP Yes arranged one independent dam specialist to: 1) Inspect and 4.37 evaluate the safety status of existing dams identified as relevant; 2) Review and evaluate the owner’s operation and maintenance procedures; and 3) Provide a written report of findings and recommendations for any remedial work or safety-related measures. Projects on International This Project involves no international waterways. The policy 9 No Waterways is not applicable and no action is required. OP/BP 7.50 Projects in Disputed All the project areas are in Guangxi and no disputed areas 10 No Areas OP/BP are involved. 7.60 -7- 1.2 Objectives of EIA The main objectives of the EIA is to identify the current status of natural and social environment and environmental quality; evaluate the positive environmental impact of the project implementation; identify, screen and predict the possible negative impacts; propose effective mitigation measures and provide environmental & social management plan for the unavoidable negative environmental impacts so as to provide a rationale for the WB’s independent assessment of the project as well as references and basis for project decision making, environmental management and engineering design optimization. 1.3 Principles of EIA The EIA shall be organized and implemented in accordance with the principle of sustainable development and in a scientific, fair and practical way to support environmental decision-making and management. Principles to be followed include: (1) Complying with the national industrial polices, environmental policies and regulations; (2) Complying with the watershed and regional functional zoning plan, ecological protection plan and urban master plan and adopting an appropriate layout; (3) Complying with laws and regulations on ecological protection such as biodiversity; (4) Complying with policies of integrated resource utilization; (5) Complying with land use policies; and (6) Complying with pollutant discharge standards and regional environmental quality requirements. 1.4 Environmental functional zoning and evaluation criteria 1.4.1 Environmental functional zoning and environmental standards in force (1) Atmospheric functional zoning According to the Principles and Technical Method for Environmental Air Quality Functional Zoning (HJ14-1996), the project is located in a functional area subject to Class II standard specified in the Ambient Air Quality Standards (GB3095-1996). The standard limits are shown in Table 1-2. -8- Table 1-2 Standard Values of the Ambient Air Quality Standard (Excerption) Unit: mg/m3 Assessment factor Time of valuation Class II limits Annual Average 0.20 Total Suspended Solids (TSP) Daily Average 0.30 Annual Average 0.10 inhalable Particulate Matter (PM10) Daily Average 0.15 Annual Average 0.06 Sulfur Dioxide Daily Average 0.15 (SO2) Hourly Average 0.50 Annual Average 0.08 Nitrogen Dioxide Daily Average 0.12 (NO2) Hourly Average 0.24 (2) Surface water functional zoning Hezhou Municipality Water Functional Zoning, approved in 2012, defines the water functional zone of the total catchments of 32 medium and small rivers in Hezhou municipality with a catchment area ranging from 100km2 to 1000 km2. According to Hezhou Municipality Water Functional Zoning, one Class I water functional zone is defined in He River catchment – Hezhou He River Development Zone (i.e., 97.9km of river section of He River, from Dongxin Village of Fuyang Town, Fuchuan County to Hezhou and Longma Village). The targeted water quality of this zone is Class III standards of Surface Water Environmental Quality Standards (GB 3838-2002). The remaining watersheds have not been defined and will follow Class IV standards of Surface Water Environmental Quality Standards (GB 3838-2002). The limits of the standards are shown in Table 1-3. -9- Table 1-3 Standard Values of Surface Water Environmental Quality Standard (Excerption) Unit: mg/L Class V Item Class Ⅲ Limits Class IV Limits Limits pH 6~9 6~9 6~9 Dissolved Oxygen 5 3 2 Permanganate Target water 6 10 15 Index bodies: East BOD5 4 6 Trunk Canal, 10 COD 20 30 40 Lining River, SS 30 60 150 NH3-N 1.0 1.5 Changlong River, 2.0 Total Phosphorus Huangtian 0.2 0.3 0.4 (TP) Branch Canal, Petro 0.05 0.5 1.0 Target water body: Guposhan Volatile Phenol 0.005 0.01 0.1 Cyanide 0.2 He River 0.2 Drainage Canal, 0.2 Anionic Surfactant 0.2 0.3 East No. 5 0.3 Sulfide 0.2 0.5 Branch Canal, 1.0 Copper(Cu) 1.0 1.0 1.0 Huangansi Zinc (Zn) 1.0 2.0 2.0 Drainage Canal, Lead(Pb) 0.05 0.05 0.1 Cadmium (Cd) 0.005 0.05 Shizigang 0.01 Arsenic (As) 0.05 0.1 Drainage Canal 0.1 Hexavalent 0.05 0.05 0.1 Chromium Hg 0.0001 0.001 0.001 (3) Acoustic functional zoning According to the acoustic environment functional zoning requirements in the Acoustic Environmental Quality Standard (GB3096-2008), the area along the Class II highway between Pinggui District and Guposhan Forest Park is classified as Class 4 acoustic environment functional zone while the residential areas with a distance of 35±5m on both side of the Class II highway is classified as Class 4a; schools, hospitals and other sensitive areas are classified as Class 2. The environmentally sensitive sites involved in the Project are located in Class 2 functional zones and the Class II standards specified in the Acoustic Environment Quality Standard (GB3096-2008) shall apply. Such standard values are shown in Table 1-4. - 10 - Table 1-4 Standard values of Acoustic Environment Quality Standard (Excerption) Unit: dB(A) Class Daytime Nighttime Class 2 60 50 Class 4a 70 55 (4) Ecological functional zoning According to the Ecological Functional Zoning Plan of GZAR, the Project is located in “Hezhou Central City Functional Zone�. 1.4.2 Discharge standards According to the project characteristics and discharge of pollutants, construction wastewater discharge, domestic wastewater discharge from the construction worker and wastewater discharge from sludge dewatering of Subproject 1 – Flood Control and Subproject 2 – Urban Drainage Improvement should meet Class I standard of Integrated Wastewater Discharge Standard (GB8978-1996). Exhaust gas from construction sites, river dredging sites and sludge dewatering sites should meet Integrated Air Pollutants Emission Standard (GB16297-1996) and the unorganized discharge limits of Odor Pollutant Emission Standard (GB14554-93). The construction site noise should meet the requirements of Environmental Noise Emission Standards for Construction Sites (GB12523-2011). The limits of these standards are shown in Table 1-5 ~1-8. Table 1-5 Integrated Wastewater Discharge Standard Unit: mg/L, except pH Anionic Indicators pH SS COD BOD5 NH3-N Phosphate Oil Surfactants Limits 6~9 70 100 20 15 0.5 5 5 Table 1-6 Integrated Air Pollutant Emission Standard (Excerption) Unit: mg/m³ Indicators TSP Class Unorganized discharge Limits 5 Table 1-7 Odor Pollutant Emission Standard (Excerption) - 11 - Indicator NH3 Odor H2S Class 2 Limits 1.5 20 0.06 Table 1-8 Environmental Noise Emission Standards for Construction Sites (Excerption) Unit: dB(A) Standard Item Limits Environmental Noise Daytime [dB(A)] 70 Emission Standards for Construction Sites Nighttime [dB(A)] 55 (GB12523-2011) During the project operation stage, the treated effluent and odor emitted by Jiangnan Wastewater Treatment Plant should meet Class 1A effluent discharge standard and odor emission standard of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) The noise from the wastewater treatment plant and drainage pumping stations should comply with Class 2 standards of Ambient Noise Emission Standard on the Boundary of Industrial Enterprises (GB12348-2008). The wastewater discharge from the associated project – Hezhou Municipal Solid Waste Landfill should meet the Class 2 standard of Standard for Pollution Control on the Landfill Site of Municipal Solid Waste(GB16889-2008). The discharge standards that the project should meet during the operation stage are shown in Table 1-9 ~ Table 1-12. Table 1-9 Municipal Wastewater Treatment Plant Pollutants Discharge Standards (Wastewater) Unit: mg/L, except pH Animal and Indicators pH SS COD BOD5 NH3-N TP TN vegetable oil Limits 6~9 10 50 10 5(8) 0.5 15 1 Table 1-10 Municipal Wastewater Treatment Plant Pollutants Discharge - 12 - Standards (Exhaust gas) Unit: mg/m³ Odor concentration Item NH3 H2S (dimensionless) Limits 1.5 0.06 20 Table 1-11 Ambient Noise Emission Standard on the Boundary of Industrial Enterprises (Excerption) Unit: dB(A) Class Daytime Nighttime Class 2 60 50 Table 1-12 Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (Wastewater) Unit: mg/L, except pH Indicators Chroma COD BOD5 SS TN NH3-N TP Limits 40 100 30 30 40 25 3 6+ Indicators Fecal Coliform Hg Cd Cr Cr As Pb Limits 10000 no./L 0.001 0.01 0.1 0.05 0.1 0.1 1.5 Assessment level The assessment level of the Project is classified based on the characteristics, nature, scale, scope and degree of impacts, as well as the relevant requirements of the Circular on strengthening EIA Management of Construction Projects Loaned by International Financial Organization (Environment Supervision [1993] No. 324) issued by the former State Environmental Protection Administration and other ministries, the relevant “EIA Technical Guidelines� and “the World Bank Operational Manual – Environmental assessment OP4.01". The specific classification principles are shown in Table 1-13. - 13 - Table 1-13 EIA Classification of the World Bank Projects Types of Environment Impacts Assessment Contents Assessment Construction projects likely to Comprehensive EIA is required Category A generate great negative impacts for these projects. on environment Construction projects likely to Comprehensive EIA is generally generate negative impacts on not required for this category of environment that are of limited projects, but special EIA or Category B scope and degree and may be Environment Impact Analysis is significantly mitigated by means of required based on the project advanced technology and mature features and environment prevention measures as regulated elements. Except for fulfilling the formalities Construction projects that generate of environment protection Category C zero or little negative impacts on management, no EIA or environment Environment Impact Analysis is required for such projects. Although the Project has significant positive impacts on local environment, especially in terms of flood control and water environment improvement, certain negative impacts will also be generated, including: (1) environmental and social impacts resulting from construction activities of the Project in urban center of Hezhou, especially the impacts on local residents and the historical buildings in the historical and cultural preservation area; (2) environmental and social impacts from the dredging operation of He River and its tributaries. The dredging load and sediment quality will be clarified in the preparation stage of the Project and it is estimated that the Project will produce about 184,590 m 3 of sludge with water content of 95% (equivalent to 18,500 m3 of sludge cakes with a moisture content of 50%). A proper design has been worked out in the EIA for transport, treatment and disposal of dredged sediments based on the different sludge nature of the main watercourse, urban inland canals and branch canals involved in the Project to mitigate such impacts on the environment and local residents; and (3) significant impacts from land acquisition and resettlement to be involved in the project construction (river channel improvement, stormwater and sewage network improvement); (4) environmental and social impacts from reconstruction of the three small hydropower stations on the main watercourse of He River; (5) regarding the soil erosion impacts arising from river - 14 - rehabilitation, road and pipeline construction, WWTP and pump station construction activities, water and soil conservation solutions are proposed in this EIA; (6) cumulative impacts of the Project and other constructed, planned and reasonably foreseeable development activities on the urban sections of the main watercourse of He River. Bank OP4.01 is triggered. Therefore, the project is proposed as a Category A project. 1.6 Key Assessment Tasks and Assessment Methods 1.6.1 Key Assessment Tasks According to the national EIA technical guidelines and the requirements of World Bank Safeguard Policies, the key assessment tasks of the environmental impact report includes: (1) Analyzing the overall positive benefits of the Project; (2) Assessing the effects of the dredging works on river water quality, aquatic ecological environment, and proposing mitigation measures; analyzing the impacts of dredging order and proposing requirements on temporary disposal sites of dredged sediments and recommending plans of sediment transportation and disposal; (3) Analyzing the impacts of water and soil erosion and developing soil and water conservation programs; (4) Conducting cumulative impact analysis; (5) Conducting alternative analysis; (6) public participation and information disclosure; (7) resettlement plan and social impact assessment; (8) environmental & social management plan. 1.6.2 Assessment methods According to the requirements in the Regulations on Environmental Protection of Construction Projects, Technical Guidelines on Environmental Impact Assessment, WB’s Safeguard Policies and WB’s EIA requirements for Category A projects, the EIA process of the Project is divided into three stages – TOR Preparation, Environmental Impact Prediction and Evaluation; and Report Preparation. The detailed tasks for each stage are shown in Figure 1-1 as follows. - 15 - Accepting task Project understanding and analysis, preliminary survey of TOR Preparation environmental condition, data collection Identifying Identifying EIA Identifying Identifying Identifying Proposing Public Environment principles and EIA level objects of technical work plan consultation Function methods and scope EP requirement & information disclosure Preparing EIA Outlines Investigation and monitoring Prediction and Evaluation Survey Environment Social Water and Environmental of Ecological soil quality environment investigation of pollution monitoring & investigation condition conservation resettlement area source survey survey investigation Engineering Evaluation of Public Analysis environmental status participation and information disclosure Alternative Analysis Environmental Impact Prediction Cumulative Impact assessment Environment Environment Environmental Environmental risk Environmental protection economy measures Monitoring Management assessment and Benefits & Losses Plan and supervision emergency plan Analysis Report Preparation Conclusion Preparing Project EIA and/or ESMP Feedback from domestic and WB Conclusion and documentation expert panel review Figure 1-1 Flowchart of Project EIA Process - 16 - 2. Engineering analysis 2.1 Project overview 2.1.1 Project background Within the context of high-speed industrialization and urbanization and intensified global climate change, Hezhou is in the face of increasingly prominent issues of frequent water disasters, aquatic ecological imbalance and water pollution and so on. All such issues have impeded the development of local economy and society. The main problems in flood control and water environment that Hezhou faces in the current stage include: Firstly, the flood control and drainage infrastructure are very weak in contrast to the frequent flood events. Secondly, the issue of environmental pollution has not been resolved. Thirdly, some urban inland canals suffer from deteriorating water quality due to limited water flow. And fourthly, the living environment is yet to be improved on account of the slow progress of municipal infrastructure development. These prominent water environment issues and the poor municipal infrastructures have become a “bottleneck� for economic integration, an obstacle to sustainable economic and social development, and a threat to water safety in the Pearl River and Xijiang River Watershed. In order to improve the flood control capacity of He River, the drainage and integrated water resource utilization in the project area and the ecological environmental and municipal infrastructure in Hezhou, Hezhou Municipal Government (HMG) decided to work with the World Bank and utilize a WB loan to implement Hezhou Urban Water Infrastructure and Environment Improvement Project. 2.1.2 Project objectives To be implemented following the guidelines of development, livelihood and innovation and the principles of stabilized growth, deeper reform, strengthened restructuring, improved livelihood, controlled risks and integrated balancing and taking into consideration the relevant special plans and the practical situation and economic conditions, the Project intends to develop a system that covers flood risk management, urban drainage improvement, water environment improvement, ecological landscape promotion, and technical assistance management, etc. In addition, the Project will adopt the standards of “green water service, eco-friendly water service and storm and flood safety� to implement water environment rehabilitation and urban infrastructure development, safeguard regional drainage and flood safety, and improve regional water environment, and develop high standard and modern urban infrastructure and public service to support the sustainable development of Hezhou and demonstrate the integration of reform and innovation. 2.1.3 Project description Hezhou is located in the northeastern part of GZAR. He River is a part of the Xijiang River System in the Pearl River Watershed and a major tributary of Xijiang River. It runs from northwest to southeast across the urban area and joins Xijiang River at - 17 - Huikai in Guangdong Province. Along with the all-direction expansion of Hezhou Municipality that identifies itself as an industrial and tourism city on the Guizhou-to-Guangdong Economic Belt and a portal and hub for Guangxi to the northeast direction, He River has become an important watercourse in the urban area with important functions to serve the city’s needs for industrial and a gricultural water, drainage and residents’ cultural activities. The geographic location of the Project is illustrated in Figure 2-1. The World Bank Loan Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project comprises of the following three components: Component 1: He River Flood Risk Resilience Improvement This component aims at reducing the flood risks of He River urban section. The main contents include (1) upgrading (or demolishing) several small hydro-power stations to improve the flood discharging capacity; (2) widening some sections in the main watercourse of He River in the urban area to improve the flood discharging capacity and developing a green waterfront corridor; and (3) rehabilitating and connecting the main watercourse to Mawei River to divert upstream flood in the northern urban area to the downstream, and developing a green waterfront corridor to improve the flood discharging capacity and reducing the flood risk in downtown area. Component 2: Urban Drainage and Wastewater Management Improvement The purpose of this component is to rehabilitate and connect the urban water bodies including urban inland canals and lakes to improve the flood storage capacity, regulate the drainage and reduce flood risk, and improve the drainage capacity of tributaries and channels; to improve the urban water environment, especially at dry seasons, by developing wastewater collection and treatment facilities; and developing a “green circle and green corridor� by rehabilitating the water wa ys in the urban area. The main contents include (1) rehabilitating urban inland canals and developing green waterfront corridors to divert the local floods; (2) developing storm water pipelines and pumping stations at selected areas; and (3) developing Jiangnan WWTP and main sewers. Component 3: Institutional Strengthening, Capacity Building and Project Management This component will mainly improve the management capacity in Hezhou Municipality. Subcomponent 3.1: Institutional strengthening Integrated water management: Technical Assistance will be provided to streamline the management of the water affairs of the Hezhou Municipality. The details include: 1) to set up a mechanism for integrating the water sector master planning and coordinating multiple water-administrative government institutions to improve the consistency and efficiency of the water management in the city and 2) to further optimize the operation of the dams in the region towards an integrated water resources management. A flood risk early warning and management system will also be developed and training will be provided to protect vulnerable people (aged, children, and disabled) from floods. Strengthening the institutional capacities in hydraulic, environmental and ecological monitoring, including: 1) strengthening capacity of Hezhou Environment Protection Bureau (HEPB) by constructing water quality monitoring stations and ecological monitoring station, providing equipment and data processing systems and training of - 18 - HEPB staff; and 2) Strengthening the capacity of the Project Implementation Units (PIUs), i.e. Hezhou Municipal Water Resources Bureau (HWRB) by constructing hydraulic station and training of staff. Training and Study Tours. Trainings, workshop and study tours will be conducted to enhance the capacity of the official of the institutions involved in the water management of Hezhou Municipality. Subcomponent 3.2: Project managmenet and supervision. This subcomponent will provide institutional support to the PMO by: i) engaging a consulting firm to assist in finalizing the preliminary design, bidding documents, and final engineering designs; ii) advising construction supervisors in contract management; iii) preparing semi-annual project progress reports, mid-term review, and implementation completion report. The PMO will also engage with consultants as third-part to conduct the external EA and RAP reporting. - 19 - Figure 2-1: Project Location Map - 20 - Figure 2-2: Layout Map of Subprojects - 21 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB 1 Flood risk control 67729.63 He River Rehabilitation of He River Huangshi Hydropower Station – Guangming Integrated Bridge section involves a total length of 12.66 km. The channel width Rehabilitation between the dikes on both sides ranges from 120m to 150 m. There (Huangshi will be a 20.25 km long new dike including 18.85 km long earth dike A-1 2019 and 2020 23515.46 Hydropower and 1.4 km long flood retaining dike. The design water level of floods Station – with a recurrence period of 50 years ranges from 107.4 m to 111.36 m. Guangming He Riverbed elevation is between 103.1 m and 98.47 m. He Riverbed Bridge) slope is 0.0366%. Rehabilitation of He River Guangming Bridge --- Lingfeng Bridge section involves a total length of 2.1 km. The channel width between the dikes on both sides ranges from 120m to 135 m. There will be a 2.4 km long new dike including 1.2 km long earth dike, 0.2 km long He River mobile gate dike and 1.0 km long flood retaining wall plus glass baffle Integrated dike. The design water level of floods with a recurrence period of 50 Rehabilitation years ranges from 106.04 m to 107.4 m. He Riverbed elevation is A-2 2019 and 2020 17321.87 (Guangming between 96.25 m and 98.47 m. He Riverbed slope is 0.106%. Babu Bridge --- Lingfeng Bridge has significant back water effect and, therefore, it is planned to Bridge) replace the 2 spans on the right side of He River with a new beam bridge to meet the flood control needs. After span increase, the bridge will be 35.5 m long and 8 m wide. The design elevation of He Riverbed beneath the bridge is 102.5 m, and the elevation of the bridge surface is between 108.75 m and 106.2 m. He River Rehabilitation of He River Lingfeng Bridge – Xiadao Hydropower Integrated Station section involves a total length of 6.9 km. The channel width A-3 Rehabilitation between the dikes on both sides is between 120 and 186 m. A new 2019 and 2020 6692.30 (Lingfeng Bridge – Xiadao flood dike in a total length of 5.98 km will be constructed, including a - 22 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB Hydropower 2.3 km long road dike section, a 1.0 km long flood retaining dike and a Station) 2.68km long earth dike. The design water level of floods with a recurrence period of 50 years is between 103.12 m and 106.04 m. He Riverbed elevation is between 93.69 m and 96.25 m. He Riverbed slope is 0.037%. The East Trunk Canal connects with the planned Bodailing Road in the upstream and the Xitiankou Diversion Canal in the downstream. The flood control standard is for floods with a recurrence period of 20 years. The total length of the works is 9.88 km. He Riverbed width is between 1.66 and 8 m and the opening is between 6.6 and 23.88 m. The design elevation of He Riverbed is between 118.64 m and 123.54 m. The design slope of He Riverbed is between 0.013% and 0.086%. The design water level is between 125.04 m and 119.47 m. The total East Trunk Canal dredging volume is 4610 m3. The canal dike elevation will be based on Integrated existing dike with moderate modification. The elevation of the left bank A-4 Rehabilitation and dike is between 130.72 m and 119.77 m. The elevation of the right 2023 and 2024 12743.21 Mawei River bank dike is between 131.62 m and 119.77m. Connection The East Trunk Canal diversion canal connects with East Trunk Canal in the upstream and the Mawei River in the downstream. The total length of the works is 2.69 km. He Riverbed width is 6 m and the opening is between 11.22 and 12 m. The design elevation of He Riverbed is between 107.00 m and 118.64 m. The design slope of He Riverbed is between 0.28% and 0.42%. The design water level is between 119.47 m and 109.50 m. The dike elevation is between 119.77 m and 109.80 m. A-5 Xiadao Xiadao Hydropower Station has an installed capacity of 6000kw with 3 2019 and 2020 305.10 - 23 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB Hydropower Nos. 2000 kw generator units. The average annual power generation Station Integrated capacity is 15.39 million kwh. The power station is a dam-type Rehabilitation hydropower station with weir-top elevation of 96.13 m for the dam and 96.95 m for the hydraulic flap gates. Average single-hole width is 11 m for the 6-hole side and 28.7 m for the 3-hole side. The width of the center pier is 1.8 m. After comprehensive alternative comparison, the recommended alternative is to keep the existing structures and upgrade the external building surface of the plant, and to upgrade the upstream dike by increasing the dike top elevation by 0 to 1.0 m within 4 km length to ensure upstream flood safety. In addition it is recommended to integrate the operational scheduling of Xiadao Hydropower Station into the triple-prevention system (flood prevention, drought prevention and gale prevention system)of Hezhou.. Fanglin Hydropower Station has an installed capacity of 525kw and 2 Nos. 100kW generator units, 1 No. 200kW generator unit and 1 No. 125kW generator unit. Hejiang Power Station has an installed capacity of 1000 KW for 5 No. 200kW generator units.The two hydropower stations share the same impounding dam and are dike-type Fanglin hydropower station with a crest elevation of 102.72m, a base elevation A-6 Hydropower 2018 and 2019 Station Integrated of 97.71m. 33 sluice gates distributed in 11 spans will be arranged, 1631.30 Rehabilitation with a maximum dike height of 4.26m and a dike section length of 225. According to the reconsturction program of Fanglin / Hejiang Hydropower Stations, these hydropower stations shall be buy-back hydropower stations and the existing sluice gates and intermediate sluice piers will be demilished and Fanglin Bridge will be retained. Rhe facade of the power plant buildings will be rehabilitated. 4 new - 24 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB centrifugal irrigation pumps with a unit capacity of 324m³ / h, a lift of 30m, and a motor power of 55 kW will be built. Due to water resistance, it is necessary to increase the height of a 4.4km long dike upstream of Fangling Bridge by 0 to 0.8m. Huangshi Hydropower Station is a run-off dam hydropower station with a total installed capacity of 1000kW and 5 Nos. 200 KW generator units. The designed annual power generation capacity is 4.7 million KWh. The dam type is a 100m long masonry gravity dam with a crest elevation of 109.00 m and a maximum dam height of 4.0m. Huangshi The existing fixed dam with safety risks will be demolished and A-7 Hydropower 2020 Station Integrated replaced with an adjustable hydraulic lifting dam, which will be 2008.01 Rehabilitation designed into a continuous hydraulic lift dam with 13 holes and a single-hole-width of 7 m. The size of the new dam is n × B × H = 13 m * 7 m * 4.5 m. The water gate height is 4.5 m and the discharge channel width is 91 m. The water gate is composed of the upper deck, the gate chamber, the stilling basin and the Haiman section, with length of 6 m, 10 m, 10 m and 8.5 m, respectively. He River Removal of silt, sandbank, sediment, garbage, weeds, debris, and (Huangshi construction waste such as brick and stone in the channel or on the Hydropower bank. The dredging section is from GL6 + 100 to GL7 + 700 and from A-8 Station - Xiadao 2018 and 2019 2512.38 Hydropower GL11 + 300 to GL13 + 300 with total length of approximately 3.6 km, a Station) Dredging total dredging volume of approximately 332,500 m 3 (including Works 156,900n m3 of sediment and 175,600 m 3 of sand or stone). 2 Urban drainage 106966.54 improvement B-1 Huangansi 2018 and 2019 Canal Huangansi Drainage Canal is used only for local flood discharge. The 1095.00 Drainage - 25 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB Pump Station design flow of the pumping station is 6.0 m3/s. Shizigang Shizigang Drainage Canal is used to transfer the storm water from the B-2 Drainage Canal catchment upstream of Huangansi. The design flow of the pumping 2018 and 2019 8145.00 Pump Station station is 36 m3/s. The rehabilitation works will follow the planned river alignment with a total length of6 km (4.38 km for Lining River and 1.62 km for Guangming Canal). The flood control standard for floods with a recurrence period of 20 years will be followed. The Lining River has a riverbed width ranging from 6 m to 8 m and an opening width of 10 m to 15 m. The design bottom elevation is between 102 m and 104 m. The design slope is 0.3%. The design water level is between 125.58 m B-3 Lining River 2022 Rehabilitation and 119.47 m. The design dike top elevation on the left side is 8380.20 between 127.79 m and 119.77m and right side between 127.79 m and 120.07 m. The works for Guangming Channel is 1.62 km. The channel bottom width is between 6 m and 8 m and the opening width is between 10 m and 15 m. Its function is to transfer the supplement water from EastNo.5 Branch Canal to Jintai Lake instead of being a drainage canal. The design bottom elevation is between 102 m and 104 m and design slope is 0.3%. The rehabilitation works will follow the planned river alignment with a total length of4.90 km. The flood control standard for floods with a recurrence period of 20 years will be followed. He Riverbed width is Changlong River between 6 m and 8 m, and the opening width is between 10 m and 15 B-4 2022 9659.84 Rehabilitation m. The design bottom elevation is between 102 m and 104 m. The design slope is 0.3%. The design water level is between 125.58 m and 119.47 m. The design dike top elevation on the left side is between 127.79 m and 119.77m and right side between 127.79 m and 120.07 - 26 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB m. The water replenishing channel of Changlong River upstream of Xiufeng Lake is 0.69 km long. Its function is to replenish water from Huangtian Canal to Xiufeng Lake and is not a drainage canal. The design bottom elevation is between 102 m and 104 m and the design slope is 0.3%. The rehabilitation works will follow the planned river alignment with a total length of6.20 km. The flood control standard for floods with a recurrence period of 20 years will be followed. He Riverbed width is between 2 m and 10 m, and the opening width is between 7.5 m and 25 m. The design bottom elevation is between 102 m and 104 m. The Huangtian Branch design slope is between 0.067 and 0.3%. The design water level is B-5 Canal 2021 2811.91 Rehabilitation between 105.4 m and 119.37 m. The design dike top elevation on the left side is between 105.7 m and 119.77m and right side between 105.7 m and 119.77 m. The dredging volume for Huangtian Canal is 7440 m3. Huangtian Branch Canal has interceptors along the canal to intercept the dry season sewage from Huangtian Township. The DN400 interceptor has a length of approximately 600 m. The rehabilitation works will follow the planned river alignment with a total length of3.93 km. The flood control standard for floods with a recurrence period of 20 years will be followed. He Riverbed width is between 1 m and 1.9 m, and the opening width is between 2.6 m and 4 Guposhan m. The design bottom elevation is between 103 m and 111.57 m. The B-6 Drainage Canal 2021 1476.42 Rehabilitation design slope is 0.21%. The design water level is between 112.55 m and 105.22 m. The design dike top elevation on the left side is between 112.85 m and 105.52 m and right side between 112.85 m and 105.52 m. The dredging volume for Guposhan Drainage Canal is 3540 m3. As the intercepting facilities, DN 400 interceptors with a length of - 27 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB approximately 50m are installed at the end of Guposhan Drainage Canal or where it enters Shizigang Drainage Canal. The rehabilitation works will follow the planned river alignment. The East No.5 Branch Canal was used mainly for irrigation. After the Project it will serve for various functions including irrigation, drainage and landscaping. The canal alignment is adjusted and planned to be rerouted at Zhanqian Avenue and enters He River directly with a total East No. 5 Branch length of 8.39 km. The flood control standard for floods with a B-7 Canal recurrence period of 20 years will be followed. He Riverbed width is 2023 and 2024 6822.45 Rehabilitation between 6 m and 8 m, and the opening width is between 10 m and 15 m. The design bottom elevation is between 102 m and 104 m. The design slope is 0.3%. The design water level is between 125.58 m and 119.47 m. The design dike top elevation is between 127.79 m and 119.77 m on the left side and between 127.79 m and 120.07 m on the right side. 3 Water quality 33879.65 improvement The length of the rehabilitation works is 1.23 km. The flood control standard for floods with a recurrence period of 20 years will be followed. The main canal is 1.5 deep and 8 to 10 m wide. The design Huangansi slope is 0.15%. The design bottom elevation is between 102.41 m and C-1 Drainage Canal 100.70 m. The design dike top elevation is between 106.60 m and 2018 and 2019 1997.94 Rehabilitation 102.80 m. The design discharge flow is 7.6 m3/s (and the maximum discharge capacity is 20 m3/s). The design water level is between 103.66 m and 101.95 m. The dredging volume is 8800 m3. The interceptor is DN400-500 and approximately 1900 m long. - 28 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB The length of the rehabilitation works is 3.72 km. The flood control standard for floods with a recurrence period of 20 years will be followed. The main canal is 21 to 32 m wide. The design slope is Shizigang 0.09% to 1%. The design bottom elevation is between 103.00 m and C-2 Drainage Canal 98.9 m. The design dike top elevation is between 105.36 m and 2018 and 2019 12342.70 Rehabilitation 105.80 m. The design discharge flow is 104.4 m3/s. The design water level is between 105.33 m and 103.89 m. The dredging volume is 3300 m3. The interceptor is DN500-600 and approximately 6000 m long. 1 No. WWTP (Jiangnan WWTP) with a treatment capacity of 15000 m3/day. The main structures include: fine screen, aeration grit chamber (integrated with fine screen), A2/O micro-aeration oxidation ditch, distribution well, sedimentation tank, high-efficiency sedimentation tank, drum filter, buffer tank, gravity condensing tank, sludge storage tank, dewatering room, blower room, contact reactor Jiangnan WWTP tank, drainage pumping house, etc. C-3 and associated The associated pipeline network includes: 5.384 km new sewage 2018 and 2019 21099.99 pipeline networks pipeline (including 3.084km long DN500-DN1350 gravity flow pipeline with and 2.3 km long DN 600 pressurized flow pipeline), and 1.165 km long DN500 new pre-buried sewage pipeline. Construction of a new road, namely Binjiangnan Road in a length of 5.56km and the associated facilities for storm water, sewage, power, telecommunication, lighting, landscaping and traffic management, etc. Ecological 4 landscaping 11640.71 improvement D-2 Center axial green Rehabilitation of Lining River and Changlong River focuses on 2021 11640.71 - 29 - Table 2-1: Summary of Project Activities for Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project Cost No. Project activities Description Implementation estimate schedule 00,000 RMB corridor greening and afforestation. The deep water and shallow shoals will be development utilized closely linked to the theme of riverside waterfront ecology to develop a riverside eco-park to deliver waterfront experience mainly in the form of gentle eco-slope. Within He River channel limited by the boundary of municipal roads and built areas, a waterfront greenbelt comprising of shallow water aquatic plants will be built with a greening area of 6.46 ha, a pavement area of 0.3 ha, a garden path area of 7.4 ha and pavilions and structures with a total area of 600 m 2. 5 Technical 5483.58 assistance River governor system + Internet Development of an urban early warning management system, E-1 intelligent improvement of main watercourse hydrological monitoring stations; 2019 -2024 874.51 management and development of branch channel hydrological monitoring stations. control system He River Watershed water Development of automatic water quality monitoring stations for main environment watercourse and branch channels; construction of Municipal monitoring, early E-2 Environmental Monitoring Station as a part of the national 2018 and 2019 4609.07 warning and standardization project; development of automatic water environment integrated monitoring and early warning platform management system - 30 - 2.1.4 Project implementing agencies and schedule (1) Management agencies The World Bank Financed Hezhou Urban Water Infrastructure and Environment Improvement Project Leading Group (PLG) is the highest leading agency for the Project. Leaders from Hezhou Municipal Development and Reform Commission (HDRC), Hezhou Municipal Finance Bureau (HFB), Hezhou Municipal Human Resources Bureau (HHRB), Hezhou Municipal Land Resources Bureau (HLRB), Hezhou Municipal Environmental Protection Bureau (HEPB), Hezhou Municipal Housing and Construction Bureau (HHCB), Hezhou Municipal Transportation Bureau (HTB), Hezhou Municipal Water Resource Bureau (HWRB), Hezhou Municipal Audit Bureau (HAB), Hezhou Municipal Engineering Administration Bureau (HMEAB), Hezhou Municipal Planning Bureau (HPB), the State Asset Supervision and Management Commission (SASAC), Municipal Finance Office, Railway and Aerial Administration Office, Babu District and Pinggui District governments are also members of the Leading Group. Under the Project Leading Group, a municipal project management office (PMO) is established to be responsible for the daily work. The municipal PMO is located at HDRC. The project implementing units (PIUs) include HWRB, HMEAB and HEPB. (2) Construction schedule The Project will be implemented in three stages: the preparation stage, the main works construction stage and the completion stage. The main tasks in the preparation stage are construction of access roads, living and production facilities inside and outside the project site; the main works construction mainly includes earthwork excavation, backfill, and construction of slope, dike, pumping stations and water gates; in the completion stage, the main tasks are site cleanup and documentation. Based on the actual conditions, the Project is scheduled to be constructed over a period of 7 years, commencing in early January 2018 and ending with the final acceptance test at the end of December 2024. 2.2 Current conditions 2.2.1 Current conditions for urban flood control Hezhou is located in the Babu Basin, spreading from east to west like a belt along He River. The elevation along He River is relatively low, with the minimum elevation of the built area ranging from 102.08 m to 103.08 m. As a result, buildings and streets in these areas suffer from flood almost every year. According to the historic records, the City was hit by major floods in the years of 1813, 1908, 1914, 1915, 1954, 1956, 1978 and 1994. Since the city was established, Hezhou Municipality has experienced major floods in the years of 2002, 2005, 2008 and 2020, with both the urban and rural areas - 31 - flooded by river water overflowed from the dike, causing significant waterlogging and flooding disasters. The flood in 1994, in particular, caused huge loss in the urban area. Hezhou is an emerging tourism city with its infrastructures being developed in all aspects. Its first effort in development of special plans for flood control can be traced back to Year 1995. However, up till now, the city still does not have a complete flood management system, making it the only municipal-level city in Guangxi having no integrated management system. The flood control and drainage infrastructure in Hezhou is still very weak, with most of He River sections in the city having no dikes or embankment. Even for some of those in place, the flood control capacity is insufficient. The only dikes in place are the 965m long dike from Jiangbeizhong Road and Jianan Road to Shizigang Drainage Canal, the 764m long dike from Hezhou Bridge to Guidong Electrical Company, and the 2836m long dike (still under construction) from Guidong Electrical Company to Wayoutou Section. Without a sound dike system, Hezhou still has a long way to go to improve its flood management system. Built dike 1 Built dike 2 2.2.2 Current conditions of the drainage system Currently in Hezhou there are 98.63 km drainage pipeline in place in total, most of which are combined sewers system. This is because they are mostly built in the 1990’s when the design standards were not as strict as today. The storm water is mainly discharged to surrounding area through scattered ditches or pipes, mostly of small diameter of 300*300 or DN300. In addition, due to severe sedimentation, the drainage capacity of the pipelines is very limited. Without separate stormwater and sewage pipeline systems, a part of the domestic sewage, industrial wastewater and storm water are discharged directly into Huangansi River, Shizigang Drainage Canal or He River. During storm events, storm water and sewage overflow will occur due to limited drainage capacity, causing significant impacts on daily life and hygiene of local people. To the north of He River in the urban area, there are three major drainage canals, namely Huangansi Drainage Canal, Shizigang Drainage Canal, and Nanshetang Drainage Canal serving as the main drainage passage in the northern part of the City - 32 - and joining He River eventually. Huangansi Drainage Canal and Shizigang Drainage Canal run across the downtown area, receiving most of sewage before entering He River. The service area of Nanshetang Drainage Canal is currently a suburban area with much less sewage to receive. 2.2.3 Current conditions of rivers to be rehabilitated (1) Main watercourse of He River The main watercourse of He River to be rehabilitated in the Project is approximately 21.6 km long. The sections under construction include Beidi Park Section, Jiangnanzhong Road Section, Dongludi Dike Section and Pinggui Section in the upstream. With a ground elevation of 102.8 m to 117.5 m on both banks, the existing river banks are mostly farmland, bamboo forest or dry lands except the built area section that is protected with a vertical retaining wall. Most parts of He River bank are floodplain and Level 1 terrace. Photo No. 1 for current status of He Photo No. 2 for current status of He River River (1) Huangansi Drainage Canal The section of Huangansi Drainage Canal to be rehabilitated is 1.23 km long. It has vertical masonry retaining wall on both sides except the natural slope in only some individual sections. Both sides are crowded with residential houses. The terrain is relatively flat, slightly high in the north and low in the south with elevations ranging from 103.9 m to 105.2 m. The water quality of the canal gradually deteriorates from upstream to downstream along with the increase of sewage discharge. In the upstream sections, there is basically no siltation while in the downstream section siltation is as thick as 1.0m. Results of geological survey and drilling show that the bedrock in the Project is not deep and the Project is located within the area of karsts terrain. (2) Shizigang Drainage Canal The section of Shizigang Drainage Canal to be rehabilitated is 3.8 km long. There are artificial dike along the both sides of the canal with masonry retaining wall except in some parts there are natural slopes which are now used as gardens for local residents. The canal is narrow with shallow and black water. With open canal and - 33 - blind culvert each taking half of the canal, the canal involves thick sediments of 1.3 to 3.7m. Shizigang Drainage Canal Huangansi Drainage Canal (3) Lining River, Changlong River, Huangtian Branch Canal and Guposhan Drainage Canal The section to be rehabilitated is respectively 4.4km, 4.4km, 6.16km and 3.96km long for the planned Lining River, the planned Changlong River, Huangtian Branch Canal Guposhan Drainage Canal. The landform in the area is typical peak-forest eroded plain featuring a flat terrain high in the northwest and low in the southeast. Banks along the canals are mostly farmland or dry land, partly having exposed base rock, and the current ground elevation ranges from 111.5 m and 119.3 m. The canals are, in most of the sections, supported by vertical retaining walls, with only a very few parts being soil slope. With a very small width, siltation in these parts is not serious. (4) East Trunk Canal The section to be rehabilitated for Guishidong Trunk Canal is 9.89 km long and is located in the northern part of the project area. The upstream and midstream section of the canal belong to eroded terrace terrain while the downstream section belongs to peak-forest eroded plain and peak-forest depressions. The existing canal is supported by vertical and inclined retaining walls. Wider than the other canals, but without perennial flow, the canal does not involve siltation. On both sides of the canal are farm land and dry land. In the upstream section, deep soil slope is formed through back filling. Some sections of the canal are close to limestone hills. The terrain of most of the project area belongs to karsts terrain. - 34 - Lining River Changlong River Huangtian Branch Canal East Trunk Canal (5) East No.5 Branch Canal The diversion water gate for East No.5 Branch Canal is located at 43 + 075. It serves the irrigation needs for a land area of 24780 mu. The canal length is 11.78 km. The average flow at the start point and end point of the canal is respectively 1.8 m3/s and 0.7 m3/s. Jizishi Branch Canal is a branch of East No. 5 Canal starting at Xiwan Village and finally joining Huangansi River. The diversion water gate for East No.6 Branch Canal is located at 54+090. It serves the irrigation needs for a land area of 18130 mu. The canal length is 10.13 km. The average flow at the start point and end point of the canal is respectively 1.61 m3/s and 0.1 m3/s. Due to aging and improper maintenance, some urban sections of the canal are already damaged. Irrigation water can only be supplied from another branch canal. Water from the canal joins Ailian Lake in the end. - 35 - East No.5 Branch Canal 2.2.4 Current conditions of the hydropower stations to be upgraded (1) Huangshi Hydropower Station Huangshi Hydropower Station is located at Yangshou Town in Zhongshan County and is a run-off dam-type hydropower station. With the construction commenced in 1975, the hydropower station was completed and put into operation in 1978. It has a total installed capacity of 1000kW with 5 Nos. 200 KW generator units. The designed annual power generation capacity is 4.7 million KWh. The actual annual power generation is 4.3 million KWh. As a masonry gravity dam with a length of 100 m, a crest elevation of 109.00 m and a maximum dam height of 4.0 m, Huangshi Hydropower Station is currently operated and managed by Hezhou Huangshi Hydropower Station Co., Ltd. on behalf of Yangtou Town Government. Dam at Huangshi Hydropower Station Water Gate at Huangshi Hydropower Station (2) Fanglin Hydropower Station Fanglin Hydropower Station is located at 300 m upstream of the merging point of He River and Shatian River in the Pinggui District and is a run-off hydropower station. Adopting a masonry dam, the hydropower station dam is integrated with a 225m long, 11-span bridge across He River. 3 iron plate flap gates are installed for each span, - 36 - totally 33 such flap gate for the entire bridge. The flap gate has a top elevation of 105.00m. When flood comes, it pushes off the flap gate and is discharged, restoring He River bed to nearly its natural status. The Fanglin Hydropower Station (right bank) was built in 1971 with an installed capacity of 450 kw for 2 Nos. 100kW generator units and 2 Nos. 125kW generator units. In 2001, the hydropower station was transferred to and operated and managed by Hezhou Minfeng Industry Co., Ltd. Fanglin Hydropower Station (left bank) commenced construction in July 1987 and started operation in October 1988. With an installed capacity of 1000 KW for 5 generator units, the power station is currently operated and managed by Babu District Hydropower Engineering Machinery Construction Team. Dam at Fanglin Hydropower Station Gates at Fanglin Hydropower Station (3) Xiadao Hydropower Station Xiadao Hydropower Station is located on the section of He River at Xiadao Village of Ertang Town in Babu District located 4 km away from the city. As a river-bed power station located on the right bank, the hydropower station commenced construction in October 1967 and was put into operation in July 1972. At the beginning, it contained one irrigation water pump and one small hydropower station with an installed capacity of 535 KW and an average annual power generation of 4.59 million kWh. After several upgrades and expansion, the hydropower station has achieved an installed capacity of 6000kW and a total storage capacity of 7.07 million m 3 and become a multi-function hydropower station of power generation, irrigation and navigation with a multi-year average power generation capacity of 20.13 KWh. Originally a 95.5m long rubber dam, the dam has been converted into a flap gate dam. The current water level is 101.80m and the minimum water level is 95.50m. As the inflow gets to more than 586 m 3/s, the hydropower station will suspend power generation and all flap gates and sediment washing gates will be opened for flood discharge. Based on the analysis of the characteristics of the rated head of the hydraulic turbine on the premise that the water head and flow needed for full load power generation is satisfied, Xiadao Hydropower Stations should adopt the following operation mode: (1) The hydropower station will operate in normal mode when inflow is less than 180 m 3/s and the dam water level is - 37 - maintained at 101.80m (normal storage level); 2) Operation is suspended when inflow is greater than 180 m3/s but less than 400 m3/s. Dam at Xiadao Hydropower Station Gates at Xiadao Hydropower Station 2.3 Identification and scope of assessment of project impacts 2.3.1 Identification of environmental and social impacts The project has three components, namely, He River Flood Risk Resilience Improvement, Urban Drainage and Wastewater Management Improvement, and Institutional Strengthening, Capacity Building and Project Management. These components are further divided into 23 subcomponents. The EIA summarized the contents, identified potential environmental and social impacts and proposed safeguard measures under the WB policy for these components. Details are summarized in Table 2-2. - 38 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 1 Improving He River Flood Risk Resilience 1.1 A-1 He River Integrated Rehabilitation Impact of river widening and dredging on Permanent Dike work (Huangshi Hydropower Station – hydrology; land ECOP, Guangming Bridge): Rehabilitation of He Construction stage: dust, wastewater, acquisition, ESMP, EIA, River Huangshi Hydropower Station – RAP, SA* Main watercourse widening for flood discharge noise, solid waste (borrow and dispose, demolishing Guangming Bridge section involves a total construction waste disposal, disposal and length of 12.66 km. The channel width site), soil erosion, construction camp; wet resettlement, between the dikes on both sides ranges season construction risk and safeguard; temporary from 120m to 150 m. There will be a 20.25 construction vehicles’ impact. land km long new dike including 18.85 km long occupation. earth dike and 1.4 km long flood retaining dike. The design water level of floods with a recurrence period of 50 years ranges from 107.4 m to 111.36 m. He Riverbed elevation is between 103.1 m and 98.47 m. He Riverbed slope is 0.0366%. A-2 He River Integrated Rehabilitation Hydrological impacts of river widening Permanent Dike work (Guangming Bridge --- Lingfeng Bridge): and dredging; land ECOP, Rehabilitation of He River Guangming Construction stage: dust, wastewater, acquisition, ESMP (PCR Bridge --- Lingfeng Bridge section involves a noise, solid waste (borrow and dispose, demolishing Managemen total length of 2.1 km. The channel width construction waste disposal, disposal and t Plan**), between the dikes on both sides ranges site), soil erosion, construction camp; wet resettlement; EIA, RAP, from 120m to 135 m. There will be a 2.4 km season construction risk and safeguard; temporary SA long new dike including 1.2 km long earth construction vehicles’ impact. land dike, 0.2 km long mobile gate dike and 1.0 occupation, - 39 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts km long flood retaining wall plus glass baffle construction dike. The design water level of floods with a activity recurrence period of 50 years ranges from impact on the 106.04 m to 107.4 m. He Riverbed elevation Xiyue Street is between 96.25 m and 98.47 m. He historic Riverbed slope is 0.106%. Babu Bridge has cultural street significant back water effect and, therefore, it and on the is planned to replace the 2 spans on the CCP Babu right side of He River with a new beam Special bridge to meet the flood control needs. After Branch span increase, the bridge will be 35.5 m long historic site. and 8 m wide. The design elevation of He Riverbed beneath the bridge is 99.95 m, and the elevation of the bridge surface is between 108.75 m and 106.2 m. A-3 He River Integrated Rehabilitation Impact of river widening and dredging on Permanent Dike work (Lingfeng Bridge – Xiadao Hydropower: hydrology; land ECOP, Rehabilitation of He River Lingfeng Bridge – Construction stage: dust, wastewater, acquisition, ESMP (PCR Xiadao Hydropower Station section involves noise, solid waste (borrow and dispose, Demolishing Managemen a total length of 6.9 km. The channel width construction waste disposal, disposal and t Plan**), between the dikes on both sides is between site), soil erosion, construction camp; wet resettlement; EIA, RAP, 120 and 186 m. A new flood dike in a total season construction risk and safeguard; Temporary SA length of 5.98 km will be constructed, construction vehicles’ impact. land including a 2.3 km long road dike section, a occupation 1.0 km long flood retaining dike and a 2.68km long earth dike.. The design water level of floods with a recurrence period of 50 - 40 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts years is between 103.12 m and 106.04 m. He Riverbed has an elevation of 93.69 m to 96.25 m and a slope of 0.037%. - 41 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 1.2 A-4 East Trunk Canal Integrated Impact of main watercourse widening and Permanent ECOP of Rehabilitation and Mawei River Connection: dredging on hydrology; land Small The East Trunk Canal connects with the Construction stage: small hydraulic facility acquisition, Waterworks, planned Bodailing Road in the upstream and with short duration, the impact is local and Demolishing ESMP, EIA, the Xitiankou diversion canal in the temporary and limited. The main impacts and RAP, SA downstream. The flood control standard is include dust, wastewater, noise and solid resettlement; for floods with a recurrence period of 20 waste, temporary sediment storage site, Temporary years. The total length of the works is 9.88 transportation routes, sediment disposal land km. He Riverbed width is between 1.66 and plan; and dredging impact on water occupation 8 m and the opening is between 6.6 and quality (temporary: SS) 23.88 m. The design elevation of He Riverbed is between 118.64 m and 123.54 Diversion of flood in canals m. The design slope of He Riverbed is between 0.013% and 0.086%. The design water level is between 125.04 m and 119.47 m. The total dredging volume is 4610 m3. The canal dike elevation will be based on existing dike with moderate modification. The elevation of the left bank dike is between 130.72 m and 119.77 m. The elevation of the right bank dike is between 131.62 m and 119.77m. The East Trunk Canal diversion canal connects with East Trunk Canal in the upstream and the Mawei River in the downstream. The total length of the works is 2.69 km. He Riverbed width is 6 m and the opening is between 11.22 and 12 m. The design elevation of He Riverbed is between 107.00 m and 118.64 m. The design slope of - 42 - He Riverbed is between 0.28% and 0.42%. The design water level is between 119.47 m Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 1.3 A-5 Xiadao Hydropower Station Integrated Temporary ESMP, EIA, Rehabilitation: Xiadao Hydropower Station Refer to A3, the impacts from dike works land SA has an installed capacity of 6000kw with 3 occupation, Nos. 2000 kw generator units. The average Impacts on annual power generation capacity is 15.39 normal million kwh. The power station is a dam-type operation of hydropower station with weir-top elevation the power 96.13 m for the dam and 96.95 m for the plant, and hydraulic flap gates. Average single-hole revenue Hydraulic facility upgrade width is 11 m for the 6-hole side and 28.7 m for the 3-hole side. The width of the center pier is 1.8 m. After comprehensive alternative comparison, the recommended alternative is to keep the existing structures and upgrade the external building surface of the plant, and to upgrade the upstream dike by increasing the dike top elevation by 0 to 1.0 m within 4 km length to ensure upstream flood safety. In addition it is recommended to integrate the operational scheduling of Xiadao Hydropower Station into the triple-prevention system (flood prevention, drought prevention and gale prevention system)of Hezhou. A-6 Fanglin Hydropower Station Integrated Temporary ESMP, EIA, Rehabilitation: Fanglin Hydropower Station Water involved construction impact: dust, land SA has an installed capacity of 525kw and 2 Nos. wastewater, noise, solid waste occupation; - 43 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 100kW generator units, 1 No. 200kW (demolishing waste, waste equipment Demolishing generator unit and 1 No. 125kW generator and waste engine oil disposal), the Fanglin unit. Hejiang Power Station has an installed transportation vehicle’s impact Hydropower capacity of 1000 KW for 5 No. 200kW Station dam generator units.The two hydropower stations will impact on share the same impounding dam and are local dike-type hydropower station with a crest residents’ elevation of 102.72m, a base elevation of travel and 97.71m. 33 sluice gates distributed in 11 local traffic. spans will be arranged, with a maximum dike Impacts on height of 4.26m and a dike section length of normal 225. operation of According to the reconsturction program of the power Fanglin / Hejiang Hydropower Stations, these plant, and hydropower stations shall be buy-back revenue. hydropower stations and the existing sluice Impacts on gates and intermediate sluice piers will be upstream demilished and Fanglin Bridge will be retained. irrigation and Rhe facade of the power plant buildings will be normal rehabilitated. 4 new centrifugal irrigation agricultural pumps with a unit capacity of 324m³ / h, a lift of production. 30m, and a motor power of 55 kW will be built. Due to water resistance, it is necessary to increase the height of a 4.4km long dike upstream of Fangling Bridge by 0 to 0.8m. . A-7 Huangshi Hydropower Station Impacts from waterworks: dust, Temporary ESMP, EIA, - 44 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts Integrated Rehabilitation: Huangshi wastewater, noise, solid waste land SA Hydropower Station is a run-off dam (demolishing waste, waste equipment occupation hydropower station with a total installed and waste engine oil disposal), Impacts on capacity of 1000kW and 5 Nos. 200 KW transportation vehicle’s impact normal generator units. The designed annual power operation of generation capacity is 4.7 million KWh. The the power dam type is a 100m long masonry gravity plant, and dam with a crest elevation of 109.00 m and a revenue. maximum dam height of 4.0m. Impacts on The existing fixed dam with safety risks will upstream be demolished and replaced with an irrigation and adjustable hydraulic lifting dam, which will normal be designed into a continuous hydraulic lift agricultural dam with 13 holes and a single-hole-width of production. 7 m. The size of the new dam is n × B × H = 13 m * 7 m * 4.5 m. The water gate height is 4.5 m and the discharge channel width is 91 m. The water gate is composed of the upper deck, the gate chamber, the stilling basin and the Haiman section, with length of 6 m, 10 m, 10 m and 8.5 m, respectively. - 45 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 1.4 A-8 He River (Huangshi Hydropower Station Construction stage: solid waste: impacts ESMP,EIA - Xiadao Hydropower Station) Dredging from sediment temporary storage site, Works: Removal of silt, sandbank, sediment, odor, sediment transportation routes, garbage, weeds, debris, and construction disposal plan, noise; dredging impact on waste such as brick and stone in the water quality (temporary: SS). Dredging channel or on the bank. The dredging section is from GL6 + 100 to GL7 + 700 and from GL11 + 300 to GL13 + 300 with total length of approximately 3.6 km, a total dredging volume of approximately 332,500 m3 (including 156,900n m3 of sediment and 175,600 m3 of sand or stone). Dredging method: dredging boat. 2 Improving Urban Drainage and Wastewater Management - 46 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 2.1 B-1 Huangansi Drainage Canal Pump Construction stage: small civil works. The Permanent ECOP of Station: Huang’ansi Drainage Canal is used impacts are local, temporary and land Small only for local flood discharge. The design insignificant. The impacts are from acquisition, Waterworks, Hydraulic facility development flow of the pumping station is 6.0 m3/s. wastewater, waste air, noise, and solid resettlement; ESMP, EIA, B-2 Shizigang Drainage Canal Pump waste. Temporary RAP, SA Station: Shizigang Drainage Canal is used land to transfer the storm water from the Operation stage: Noise impact from occupation; catchment upstream from Huangansi. The pumping house. Construction design flow of the pumping station is 36 for the m3/s. pumping station will generate impacts on the Xiyue Street historic cultural street. 2.2 B-3 Lining River Rehabilitation: The Construction stage: small hydraulic civil Permanent ECOP of rehabilitation works will follow the planned works. The impacts are local, temporary land Small river alignment with a total length of 6 km and insignificant. The impacts are from acquisition, Waterworks, River and lake connectivity (4.38 km for Lining River and 1.62 km for dust, wastewater, noise, solid waste Demolishing ESMP, EIA, Guangming Canal). The flood control (borrow and disposal, location of disposal and RAP, SA standard for floods with a recurrence period sites), transportation vehicles, soil resettlement; of 20 years will be followed. Lining River has erosion, etc. Temporary a riverbed width ranging from 6 m to 8 m and land an opening width of 10 m to 15 m. The Operation stage: Noise impact from occupation; design bottom elevation is between 102 m control gate. During the - 47 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts and 104 m. The design slope is 0.3%. The construction design water level is between 125.58 m and of the section 119.47 m. The design dike top elevation on underpassing the left side is between 127.79 m and Gui-Guang 119.77m and right side between 127.79 m High-speed and 120.07 m. The works for Guangming Railway, Channel is 1.62 km. The channel bottom impacts will width is between 6 m and 8 m and the be generated opening width is between 10 m and 15 m. Its on the railway function is to replenish water from East No.5 base. Branch Canal to Jintai Lake and is not a drainage canal. The design bottom elevation is between 102 m and 104 m and the design slope is 0.3%. B-4 Changlong River Rehabilitation: The Construction stage: small hydraulic civil Permanent ECOP of rehabilitation works will follow the planned works. The impacts are local, temporary land Small river alignment with a total length of 4.90 km. and insignificant. The impacts are from acquisition, Waterworks, The flood control standard for floods with a dust, wastewater, noise, solid waste Demolishing ESMP, EIA, recurrence period of 20 years will be (borrow and disposal, location of disposal and RAP, SA followed. He Riverbed width is between 6 m sites), transportation vehicles, soil resettlement; and 8 m, and the opening width is between erosion, etc. Temporary 10 m and 15 m. The design bottom elevation land is between 102 m and 104 m. The design Operation stage: Noise impact from occupation. slope is 0.3%. The design water level is control gate. between 125.58 m and 119.47 m. The design dike top elevation on the left side is between 127.79 m and 119.77m and right - 48 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts side between 127.79 m and 120.07 m. The Changlong River in the upstream of Xiufeng Lake is 0.69 km long. Its function is to replenish water from Huangtian Canal to Xiufeng Lake and is not a drainage canal. The design bottom elevation is between 102 m and 104 m and design slope is 0.3%. B-5 Huangtian Branch Canal Rehabilitation: Construction stage: small hydraulic civil Permanent ECOP of The rehabilitation works will follow the works. The impacts are local, temporary land Small planned river alignment with a total length and insignificant. The impacts are from acquisition, Waterworks, of6.20 km. The flood control standard for dust, solid waste (borrow and disposal, demolishing ESMP, EIA, floods with a recurrence period of 20 years location of disposal sites), transportation and RAP, SA will be followed. He Riverbed width is vehicles, soil erosion, and noise, etc. The resettlement; between 2 m and 10 m, and the opening odor from dredging and sediment storage; Temporary width is between 7.5 m and 25 m. The the sediment storage site, transportation land design bottom elevation is between 102 m routes, and disposal plan; the dredging occupation; and 104 m. The design slope is between impact on water quality (temporary: SS); Interceptor 0.067 and 0.3%. The design water level is the dust and noise from laying interceptor pipeline between 105.4 m and 119.37 m. The design pipelines. laying might dike top elevation on the left side is between impact on 105.7 m and 119.77m and right side other utility between 105.7 m and 119.77 m. The lines. dredging volume for Huangtian Canal is 7440 m3. The Branch Canal will also have interceptors along the canal to intercept dry season sewage from Huangtian Township. The DN400 interceptor has a length of - 49 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts approximately 600 m. B-6 Guposhan Drainage Canal Construction stage: small hydraulic civil Permanent ECOP of Rehabilitation: The rehabilitation works will works. The impacts are local, temporary land Small follow the planned river alignment with a and insignificant. The impacts are from acquisition; Waterworks, total length of 3.93 km. The flood control dust, solid waste (borrow and disposal, Temporary ESMP, EIA, standard for floods with a recurrence period location of disposal sites), transportation land RAP, SA of 20 years will be followed. He Riverbed vehicles, soil erosion, and noise, etc. The occupation; width is between 1 m and 1.9 m, and the odor from dredging and sediment storage; Interceptor opening width is between 2.6 m and 4 m. the sediment storage site, transportation pipeline The design bottom elevation is between 103 routes, and disposal plan; the dredging laying might m and 111.57 m. The design slope is 0.21%. impact on water quality (temporary: SS); impact on The design water level is between 112.55 m the dust and noise from laying interceptor other utility and 105.22 m. The design dike top elevation pipelines. lines. on the left side is between 112.85 m and 105.52 m and right side between 112.85 m Operation stage: Noise impact from and 105.52 m. The dredging volume for control gate. Guposhan Drainage Canal is 3540 m3. As - 50 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts the intercepting facilities, DN 400 interceptors with a length of approximately 50m are installed at the end of Guposhan Drainage Canal or where it enters Shizigang Drainage Canal. B-7 East No. 5 Branch Canal Rehabilitation: Construction stage: small hydraulic civil Temporary ECOP of The rehabilitation will follow the planned works. The impacts are local, temporary land Small river alignment. The East No.5 Branch and insignificant. The impacts are from occupation, Waterworks, Canal was used mainly for irrigation. After dust, solid waste (borrow and disposal, Permanent ESMP, EIA, the Project it will serve for various functions location of disposal sites), transportation land RAP, SA including irrigation, drainage and vehicles, soil erosion, and noise, etc. The acquisition, landscaping. The canal alignment is odor from dredging and sediment storage; demolishing adjusted and planned to be rerouted at the sediment storage site, transportation and Zhanqian Avenue and enters He River routes, and disposal plan; the dredging resettlement; directly with a total length of 8.39 km. The impact on water quality (temporary: SS). During the flood control standard for floods with a construction recurrence period of 20 years will be Operation stage: Noise impact from of the section followed. He Riverbed width is between 6 m control gate. underpassing and 8 m, and the opening width is between Gui-Guang 10 m and 15 m. The design bottom elevation High-speed is between 102 m and 104 m. The design Railway, slope is 0.3%. The design water level is impacts will between 125.58 m and 119.47 m. The be generated design dike top elevation on the left side is on the railway between 127.79 m and 119.77 m and right base.. side between 127.79 m and 120.07 m. Excavation might affect - 51 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts other utility pipelines. - 52 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 2.3 C-1 Huangansi Drainage Canal Construction stage: small hydraulic civil Permanent ECOP of Rehabilitation: The length of the works. The impacts are local, temporary land Small rehabilitation works is 1.23 km. The flood and insignificant. The impacts are from acquisition, Waterworks, control standard for floods with a recurrence dust, solid waste (borrow and disposal, demolishing ESMP (PCR period of 20 years will be followed. The main location of disposal sites), transportation and Managemen canal is 1.5 deep and 8 to 10 m wide. The vehicles, soil erosion, and noise, etc. The resettlement; t Plan), EIA, Huangansi Drainage Canal Rehabilitation design slope is 0.15%. The design bottom odor from dredging and sediment storage; Temporary RAP, SA elevation is between 102.41 m and 100.70 the sediment storage site, transportation land m. The design dike top elevation is between routes, and disposal plan; the dredging occupation. 106.60 m and 102.80 m. The design impact on water quality (temporary: SS); Construction discharge flow is 7.6 m3/s (and the the dust and noise from laying interceptor for the maximum discharge capacity is 20 m3/s). pipelines. pumping The design water level is between 103.66 m station will and 101.95 m. The dredging volume is 8800 generate m3. The interceptor is DN400-500 and impacts on approximately 1900 m long. the Xiyue Street historic cultural street, and on people’s travel and traffic. Interceptor pipeline laying might impact on other utility lines. - 53 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 2.4 C-2 Shizigang Drainage Canal Construction stage: small hydraulic civil Permanent ECOP of Rehabilitation: The length of the works. The impacts are local, temporary land Small rehabilitation works is 3.72 km. The flood and insignificant. The impacts are from acquisition, Waterworks, control standard for floods with a recurrence dust, solid waste (borrow and disposal, demolishing ESMP, EIA, period of 20 years will be followed. The main location of disposal sites), transportation and RAP, SA canal is 21 to 32 m wide. The design slope is vehicles, soil erosion, and noise, etc. The resettlement; Shizigang Drainage Canal Rehabilitation 0.09% to 1%. The design bottom elevation is odor from dredging and sediment storage; Temporary between 103.00 m and 98.9 m. The design the sediment storage site, transportation land dike top elevation is between 105.36 m and routes, and disposal plan; the dredging occupation; 105.80 m. The design discharge flow 104.4 impact on water quality (temporary: SS); Impacts on m3/s. The design water level is between the dust and noise from laying interceptor people’s 105.33 m and 103.89 m. The dredging pipelines. travel and volume is 3300 m3. The interceptor is traffic. DN500-600 and approximately 600 m long. Reopening of buried ditches will impact on shops revenue; Interceptor pipeline laying might impact on other utility lines. - 54 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 2.5 C-3 Jiangnan WWTP and associated Construction stage: dust, noise, Permanent Road and pipeline networks and road improvement. wastewater, solid waste (road excavation land pipeline Construction of 1 No. WWTP (Jiangnan disposal amount and destiny, disposal acquisition; network WWTP) with a treatment capacity 15000 sites arrangements), and soil erosion. Temporary ECOP, m3/day. The main structures include: fine Operation stage: odor in wastewater land ESMP, EIA, screen, aeration grit chamber (integrated with treatment, WWTP sludge, effluent occupation. RAP, SA Improvement of drainage system fine screen), A2/O micro-aeration oxidation discharge on He River water quality. Impacts on ditch, distribution well, sedimentation tank, people’s high-efficiency sedimentation tank, drum filter, travel and buffer tank, gravity condensing tank, sludge traffic. storage tank, dewatering room, blower room, contact reactor tank, drainage pumping house, etc. The associated pipeline network includes: 5.384 km new sewage pipeline (including 3.084km long DN500-DN1350 gravity flow pipeline with and 2.3 km long DN 600 pressurized flow pipeline), and 1.165 km long DN500 new pre-buried sewage pipeline. Construction of a new road, namely Binjiangnan Road in a length of 5.56km and the associated facilities for storm water, sewage, power, telecommunication, lighting, landscaping and traffic management, etc. / / All of above subprojects: A-1 to A-4; B-1 to Water replenishing, river rehabilitation B-7; and C-1 to C-3 and dredging together generate impacts - 55 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts on the hydrology and water quality in He River and urban inland canals, and on the ecological system in He River. Water replenishing and river/lakes connectivity generate impacts on regional water resource utilization. Water replenishing and river/lakes connectivity have positive impacts on water storage, drainage and flood control. 2.6 D-2 Center axial green corridor Permanent ESMP, EIA, development: Rehabilitation of Lining River land RAP, SA and Changlong River focuses on greening acquisition; Ecological landscaping and afforestation. The deep water and shallow shoals will be utilized closely linked Temporary improvement to the theme of riverside waterfront ecology land to develop a riverside eco-park to deliver Construction stage: Impacts of temporary occupation waterfront experience mainly in the form of land occupation on local ecological gentle eco-slope. Within He River channel environment. limited by the boundary of municipal roads and built areas, a waterfront greenbelt comprising of shallow water aquatic plants will be built with a greening area of 6.46 ha, a pavement area of 0.3 ha, a garden path area of 7.4 ha and pavilions and structures with a total area of 600 m2. 3 Institutional Strengthening, Capacity Building and Project Management - 56 - Table 2-2 Project activities and potential environmental and social impacts No. Project Contents Potential environmental impacts Potential Safeguard activity social tools impacts 3.1 E-1 River governor system + web-based As a small water works with relatively Small Permanent hydrological intelligent management and control system: short construction period, the impacts will waterworks, land monitoring Development of an urban early warning be local, short and minimal. ECOP, acquisition station management system, improvement of main ESMP, EIA, and watercourse hydrological monitoring RAP, SA temporary stations; development of branch channel land hydrological monitoring stations. occupation 3.2 E-2 He River Watershed water environment No civil works involved, except equipment Environment monitoring monitoring, early warning and integrated procurement. Rehabilitation and management system: Development of upgrading to be conducted on the basis of automatic water quality monitoring stations existing monitoring station and discharge stations for main watercourse and branch channels; of laboratory wastewater, exhaust gas, construction of Municipal Environmental waste drugs and agents will be involved in Monitoring Station as a part of the national the operation stage.. standardization project; development of automatic water environment monitoring and early warning platform. *ECOP: Environmental Codes of Practice; ESMP: Environmental and Social Management Plan; EIA: Environmental Impact Assessment; RAP: Resettlement Action Plan; SA: Social Assessment. **PCRMP: Physical Cultural Resource Management Plan - 57 - 2.3.2 Scope of assessment In order to make sure that the assessment is conducted in a more scientific and site-specific way, spatial scope for environmental elements baseline survey, impact prediction and assessment, and accumulative impact assessment are identified for the project implementation and associated facilities, based on the nature of the project, regional environmental characteristics, impact characteristics, World Bank requirements, national technical guidelines, and lessons learned and experience gained from similar domestic projects. They are summarized in Table 2-3. The scope of assessment for the Project covers not only the scope required by domestic technical guidelines, but also the scope of temporary dewatering sites required for the relevant activities, e.g. dredging, and the associated facilities of the main works, e.g. construction camps, construction access roads, borrow area, disposal site, and Yongfeng Lake, Jintai Lake to be associated after river-lake connection, the linked construction works of Hezhou Municipal WWTP, Hezhou Municipal Solid Waste Landfill, and Hezhou Harmless Sludge Disposal Center, and special sites with social impacts, i.e. the Gui-Guang High Speed Railway, and the irrigation area affected by Fanglin Hydropower Station rehabilitation works. In terms of timeframe, the scope of prediction and assessment over the various elements covers both the construction stage and operation stage. Table 2-3 Spatial scope of assessment Spatial scope Elements Baseline survey Impact assessment He River main watercourse: from Huangshi Hydropower Station dam to Xiadao Hydropower Station dam Mawei River: from 500 m upstream of the merging point of East Trunk Canal into He River main watercourse. East Trunk Canal: entire watershed He River main watercourse: from Lining River: entire watershed Huangshi Hydropower Station to 2 Changlong River: entire km downstream of Mawei River Surface watershed merging point. water Huangtian Canal: entire All tributaries, canals and urban watershed inland canals in baseline survey. East No.5 Branch Canal: from East Trunk Canal to where it merges into He River. Huangansi Drainage Canal: entire watershed Shizigang Canal: entire watershed Associated Jintai Lake and Yongfeng Lake: whole water body. - 58 - Table 2-3 Spatial scope of assessment Spatial scope Elements Baseline survey Impact assessment Dredging area in He River main The dredging sections of He watercourse, Huangtian Branch River, Huangtian Branch Canal, Guposhan Drainage Canal, Canal, Guposhan Drainage Shizigang Drainage Canal, Canal, Shizigang Drainage Huangansi Drainage Canal and 50 Canal, Huangansi Drainage m within the boundary of sediment Canal, dewatering sites. Proposed Jiangnan WWTP site, Temporary dewatering site, road and pipeline sites. construction camp, access roads, Ambient air Temporary sites including borrow area, disposal site. sediment dewatering site, Within 100 m the boundary of construction camp, access proposed Jiangnan WWTP. roads, borrow area, disposal site Within 50 m the proposed pipeline Associated facilities including boundary. Hezhou WWTP, Hezhou Landfill, Within 100 m the associated Hezhou Sludge Disposal Center, facilities including Hezhou WWTP, etc. Hezhou Landfill, Hezhou Sludge Disposal Center, etc. Villages, towns, schools and Within 30 m from construction site Sound units at project implementation boundaries. environment sites. Territorial ecological environment: ecological Within 200 m from the both banks Territorial environment: Within 200 m from main Rivers of He including He River the both banks of He Rivers canals and urban inland tributaries, watercourse, canals; including He River main Within 200 m from the boundary of watercourse, tributaries, canals temporary sites including the and urban inland canals; Within 200 m from the alignment temporary dewatering site, borrow Ecological area, disposal site. of the re-routed rivers including Within 200 m from environment the boundary of Lining Rive and Changlong other works. River. Within 200 m from the boundary Aquatic ecological environment: of the WWTP and pipeline He River main watercourse section works. Aquatic ecological environment: from Huangshi Hydropower He River main watercourse Xiadao Hydropower Station. of the Station to 2 km downstream section in the urban area. Hezhou Babu District and Pinggui Hezhou Babu District and District, in particular, Gui-|Guang Pinggui District, in particular, High-speed Railway and irrigation Social Gui-|Guang High-speed Railway areas affected by rehabilitation environment and irrigation areas affected by works of Huangshi Hydropower Fanglin Hydropower Station Station and Fanglin Hydropower rehabilitation works Station. 2.3.3 Identification of key targets for environmental protection According to the domestic laws and regulations for EIA and World Bank Safeguard Policy, the principals for selection of environmental protection targets (sensitive sites) include: - 59 - (1) Special protection areas: areas requiring special protection specified in national regulations and planning or approved by people’s governments at or above county level, such as drinking water source protection areas, nature reserves, famous scenic spots, ecological function protection areas, basic farmland protection areas, key soil erosion prevention and control areas, forest parks, geological parks, world heritage sites, key cultural resource protection units, etc.; (2) Ecologically sensitive areas: areas with severe water shortages, habitats for rare animals and plants and aquatic creatures, spawning ground for fishes and shrimps, important wetlands, and natural fishing areas, etc.; (3) Socially concerned area: population concentration area, cultural and educational area, office building areas for CCP and government agencies, nursing homes, hospitals, etc.; (4) Physical cultural resources including the existing cultural resources, such as: obvious cultural relics, temples with historical and cultural value, representative local residential houses, ancestral halls, tombs, religious monuments, cultural relics and old trees, etc. (5) Ethnic groups and involuntary resettlement. (6) Sensitive objects for which environmental protection measures have difficulty in mitigating impacts based on the above screening principles and taking into consideration of the extent to which sensitive targets may be affected, mainly focusing on schools, hospitals, nursing homes, residents who need special attention. Environmental protection targets selected based on the above principles and likely to be affected by the Project are summarized in Table 2-4. - 60 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name A. Construction stage 1. Surface water environment quality Object Target Water bodies involved Water qualities in He River, East Trunk Canal and the Mawei River. 2. Ecological protection target Object Target Famous and ancient trees (not Banyan tree (Xialiangzhai Village, N24.41045°, E111.53795°), Banyan tree(Xialiangzhai Village within the project area but N24.41004°, E111.53714°), Banyan tree(Xialiangzhai Village N24.40992°, E111.5369°), Banyan tree close to the construction sites (Xialiangzhai Village N24.40956°, E111.53646°), Hackberry tree (Jiangbeizhong Road, N24.41264°, (within 50 m). the temporary E111.54208°), Hackberry tree(Jiangbeizhong Road N24.40426°,E111.55506°,),Banyan tree borrow or disposal, (Jiangbeizhong Road, N24.40623°, E111.55424°), Camphor tree (Jiangbeizhong Road, N24.40658°, construction waste storage, E111.55409°), Canephor tree (Xinan No.2 Alley, N24.41076°, E111.53140°), Camphor tree (Xinan No.2 construction vehicles or Improving He Alley, N24.41068°, E111.53168°) Camphor tree (Xinan No.2 Alley, N24.41072°, E111.53164°) Banyan equipment transportation might River Flood tree (Xinan No.2 Alley, N24.41034°, E111.53027°) affect its normal growth.) Risk 3, Ambient air and noise protection targets Resilience Subproject name Name of sensitive site Nature Location Distance (m) Basic information Impact factors Shangsong Village Residential Left bank 3~30 55 families Noise, dust Shangsong Village Residential Right bank 3~25 12 families Noise, dust A-1 He River Xiwan Township Residential Left bank 2~20 52 families Noise, dust Integrated temporary housing area Rehabilitation Xiwan Township residents Residential Left bank 2~20 38 families Noise, dust (Huangshi Hydropower Affecting 50 Noise, dust Pinggui District Station – Office Left bank 6 people’s office Government Guangming work Bridge) Xiwanzhai Village Residential Right bank 3~25 68 families Noise, dust Residents near He River Estimated 10 Noise, dust Residential Left bank 9~16 in Jinshuiwan Community families moved in - 61 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name (not moved in yet) Jigongzhou Residential Left bank 5~30 9 families Noise, dust Songmuji in Gonghe Noise, dust Residential Left bank 10~30 7 families Village Gongqiaotou Residential Right bank 5~30 13 families Noise, dust Longjiangdu Residential Right bank 13~30 3 families Noise, dust Hezhou Institute Education Left bank 3~25 500 people Noise, dust Sanjia Village Residential Left bank 2~25 13 families Noise, dust Fanglin Street Residential Right bank 8~30 13 families Noise, dust 436 people (1 staff Noise, dust Hezhou Experimental dormitory building Education Right bank 6~15 Middle School and 1 student dormitory building) Fanglin Village Residential Right bank 2~30 21 families Noise, dust Laozengwu Residential Right bank 3~30 28 families Noise, dust Residential building near Noise, dust He River in 30 families (2 Residential Left bank 30 Wenyuanhuadu buildings) Community A-2 He River Residential houses in Noise, dust Integrated Xinan No.2 Alley in Babu Residential Left bank 2~30 30 families Rehabilitation District (Guangming Residential houses in Noise, dust Residential Left bank 2~10 69 families Bridge --- Lingfeng Xiyue Street Bridge) Xialiang Village Residential Right bank 2~25 158 families Noise, dust A-3 He River Diandengzhai Village Residential Right bank 3~30 52 families Noise, dust Integrated Chushuitang Village Residential Right bank 3~20 8 families Noise, dust Rehabilitation Xiadao Elementary School Education Right bank 0 Approximately 200 Noise, dust - 62 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name (Lingfeng Bridge – people Xiadao Xiadaozhai Village Residential Right bank 50 17 families Noise, dust Hydropower Jichitan Village Residential Left bank 2~30 20 families Noise, dust Station) A-4 East Trunk Noise, dust Canal Integrated Rehabilitation and Xianghuadao Island Residential Right bank 13~26 8 families Mawei River Connection A-5 Xiadao To the north of Noise, dust Hydropower Xiadao Jichitan Village Residential 10~15 2 families Station Integrated Hydropower Rehabilitation Station 4, Social impact protection target Subproject name Object Target A-2 He River Integrated Physical cultural Rehabilitation Historic site for CCP Babu Special Branch resource (Guangming Bridge --- Lingfeng Bridge) A-6 Fanglin Hydropower Station On the right bank side of Fanglin Hydropower Station, approximately 400 mu in Tianchang Irrigation area Integrated Village, 200 mu in Mintian Village and 1000 mu in Fanglin Village. Rehabilitation A. Construction stage Improving 1, Surface water environment quality Urban Object Target Drainage and Water qualities in Huangansi Drainage Canal, Shizigang Drainage Canal, the Lining River, Changlong Water bodies involved Wastewater River, the Huangtian Branch Canal, and He River. Management 2, Ecological protection target Subproject Name Object Target - 63 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name Famous and ancient trees (not within the project area Camphor tree (Jianshezhong Road, N24.41611°, C-1 Huangansi but close to the construction sites (within 50 m). the E111.53616°), Camphor tree (Xinan No.1 Alley, Drainage Canal temporary borrow or disposal, construction waste N24.41330°, E111.535°) Camphor tree (Xiyue Street, Rehabilitation storage, construction vehicles or equipment N24.41255°, E111.53447°) transportation might affect its normal growth.) 3, Ambient air and noise protection targets Subproject Name of sensitive Distance Nature Location Basic information Impact factors name site (m) B-1 Huangansi Residential houses in North of pumping Drainage Canal Residential 2~20 20 families Noise, dust Xiyue Street station Pump Station Residential houses in B-2 Shizigang Jiangbeizhong Road, North of pumping Drainage Canal Dormitory building for Residential 0~30 25 families Noise, dust station Pump Station Transportation Bureau Starting point of the Pingjing Residential 10~30 8 families Noise, dust canal Lijiatang Residential Left bank 5~30 4 families Noise, dust Lining Village Residential Right bank 3~30 12 families Noise, dust B-3 Lining River Daninggang Village Residential Left bank 6~30 20 families Noise, dust Rehabilitation Xiangjiayuan Residential Pass by 2~30 15 families Noise, dust Community Taipingzhai Village Residential Right bank 10~30 6 families Noise, dust Yingshi Elementary Education Pass by 0 300 人 Noise, dust School Changlong Village Residential Both sides 3~30 58 families Noise, dust B-4 Changlong Huangtian Township Residential Both sides 0~30 152 families Noise, dust River Douxing Residential Left bank 5~30 12 families Noise, dust Rehabilitation Yatanggang Village Residential Left bank 0~30 8 families Noise, dust B-5 Huangtian Huangtian Township Residential Right bank 0~30 87 families Noise, dust Branch Canal Pinggui No.3 Middle Education Left bank 0~30 Approximately 120 Noise, dust - 64 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name Rehabilitation School people Xinzhai Village Residential Left bank 5~30 13 families Noise, dust B-6 Guposhan Huangtian Village Residential Both sides 0~30 68 families Noise, dust Drainage Canal Muyuanna Village Residential Both sides 0~30 46 families Noise, dust Rehabilitation Baijiazhai Village Residential Both sides 0~30 71 families Noise, dust Shizigang Village Residential Right bank 0~20 52 families Noise, dust Tianchongzhai Residential Both sides 0~30 26 families Noise, dust B-7 East No. 5 Village Branch Canal Tangpingzhai Village Residential Both sides 0~30 18 families Noise, dust Rehabilitation Xiwan Village Residential Both sides 0~30 77 families Noise, dust Xiwan Township Residential Both sides 0~30 165 families Noise, dust Residential houses in Residential Both sides 0~30 56 families Noise, odor Badaxi Road Residential houses in Residential Both sides 0~30 30 families Noise, odor Qianjin Road C-1 Huangansi Residential houses in Drainage Canal Residential Both sides 0~30 32 families Noise, odor Jianshezhong Road Rehabilitation Residential houses in Residential Both sides 0~30 82 families Noise, odor Youxing Alley Residential houses in Residential Both sides 0~30 20 families Noise, odor Xiyue Street Residential houses in Residential Both sides 0~30 240 families Noise, odor Wanquan Street Residential houses in Residential Both sides 0~30 43 families Noise, odor Zhushan Road C-2 Shizigang Residential houses in Residential Both sides 0~30 46 families Noise, odor Drainage Canal Longxing Alley Rehabilitation Both side (reopening Residential houses in Residential of 350 m buried 0~30 104 families Noise, odor Yinhe Street ditches) Backyard of Pass by, (reopening Office 0 150 people’s offices Noise, odor Municipal Land of 100 m buried - 65 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name Resource Bureau ditches) Office building and Pass by, (reopening dormitory building for 200 people’s offices Office/residential of 150 m buried 0 Noise, odor Guidong Electricity and dormitories ditches) Company Residential houses in Residential Both sides 0~30 30 families Noise, odor Wangjia Alley Residential houses in Residential Left bank 0~30 65 families Noise, odor Jianshe Road Residential houses in Residential Both sides 0~30 50 families Noise, odor Longshan Road Residential houses in Residential Both sides 0~30 190 families Noise, odor Xingguang Road Shops and pool in Municipal Water Office Both sides 0 60 people Noise, odor Resource Bureau Residential houses in Residential Both sides 0~30 20 families Noise, odor Pinganxi Road Office building for municipal hygiene Office Both sides 0 100 people’s offices Noise, odor and planning committee Office building, backyard and dormitory building for 80 people’s offices, Noise, odor, Office/residential Pass by 0 Babu District 14 families traffic Transportation Bureau Residential houses in Residential Both sides 0~30 15 families Noise, odor Jiangbeizhong Road C-3 Jiangnan Residential houses in Residential Both sides 0~30 20 families Noise, dust WWTP and Niulanpai - 66 - Table 2-4 Summaries of key targets for environmental protection Project Key environmental protection targets name associated pipeline networks 4, Social impact protection target Subproject name Object Target The protected buildings in Xiyue Street historic cultural street, including the old C-1 Huangansi Drainage Canal dike, the Yijing Bridge, the Stone Wall, the Tianyi Cigarettes Shop, the Qianji Physical cultural Rehabilitation, B-1 Huangansi Convoy Store, the Jiancheng Rice Store, etc., are not in the project area, but resource Drainage Canal Rehabilitation they might be affected during the construction stages. The ancient dike, ferry and city walls are in the project area. A-4 East Trunk Canal Integrated The intersection between East No.5 Branch Canal and Gui-Guang High Speed Rehabilitation and Mawei River Railway (DW0 + 628 to DW0 + 655) Railway facility Connection, B-3 Lining River The intersection between Lining River and Hezhou Railway Station (LN1 + 025 Rehabilitation to LN1 + 147.5) B. Operation stage Noise protection targets Subproject name Sensitive site name Location Distance (m) Nos. of families B-1 Huangansi Drainage Residential houses in North of the pumping station 10m 27 Canal Pump Station Xiyue Street B-2 Shizigang Drainage Residential houses in North of the pumping station 20m 8 Canal Pump Station Jiangbeizhong Road Institutional Strengthening, Capacity No specific protection targets because the amount of works is small and the impacts are insignificant. Building and Project Management - 67 - 2.4 Planning compliance analysis 2.4.1 Compliance with the Hezhou Municipality Master Urban Plan The Hezhou Municipality Master Urban Plan (2016-2030) stipulated the nature, the development objectives, the scale of the city, and formulated relevant policies for regional cooperation, economic transformation, social harmony and ecological protection, identified the layout of spatial and structural development, and planned the supporting system for the center urban area. The details of the planning and the compliance of the Project with the plan are summarized in Table 2-5. - 68 - Table 2-5: Compliance of the Project with the Hezhou Municipality Master Urban Plan (2016-2030) Item Planning This project Compliance analysis The nature of the city is identified as: a world famous city with long life expectation, a new The implementation of The project objective is to improve the industry, tourism, and leisure city on the Gui-Guang the Project is important flood management, reduce wastewater Nature High Speed Railway, and the important portal of in realizing the pollution and enhance water resource Guangxi to the eastern and central regions, a identified nature of the management planning in Hezhou. livable modern city with good ecological system and city. style. Using He River and the existing State Road 207 as The implementation of Development axis, the city will focus expansion towards northwest The project area are mainly He River main the Project can help the watercourse in the urban area, and the direction and across He River to the south bank, and also city develop in its urban inland canals and lakes. moderately towards the east. direction To build a "one main center, four sub-centers, two axis, and three regions" in terms of spatial layout of the municipality. One main center: the Hezhou city. Four sub-centers: Zhongshan, Xindu, Fuchuan and This project can help develop a "green The implementation of Spatial Zhaoping cities. circle and green corridor" spatial structure the Project is in line with structure in Hezhou through the rehabilitation of the the spatial layout of the Two axis: the main axis and secondary axis for water way system. city. urban development. Three regions: the central core development region, the western ecological conservation region, and the eastern region for the Guangdong and Guangxi Cooperation Area. The central urban area is divided into 7 catchments The project will develop the Jiangnan The implementation of Wastewater for sewage collection. 7 WWTPs are planned, WWTP and its associated storm water the Project can improve management including the Hezhou WWTP (existing to be and sewage main to ensure effective the storm water and system upgraded), Shatian WWTP, Jiangnan WWTP, Hejie collection and treatment in the catchment sewage management, WWTP, Xiwan WWTP, and Wanggao Industrial in the future. and help improve the - 69 - Table 2-5: Compliance of the Project with the Hezhou Municipality Master Urban Plan (2016-2030) Item Planning This project Compliance analysis Park WWTP. regional water environment. Spatial layout with one belt, four axis, nine areas and multiple corridors. By widening and dredging in He River One belt: a water front landscape belt with main watercourse, and branch channels integrated “water and green� along the “mother (Lining River and Changlong River), river� of Hezhou – He River. Huangtian Branch Canal, Guposhan Drainage Canal, East No.5 Branch Canal, Four axis: including the Ailian Lake Ecological Huangansi Drainage Canal and Shizigang Green Axis, the Jichitan Ecological Green Axis, the Drainage Canal, increase their flood Center urban Huangansi Ecological Green Axis and He Riverside carrying cross-sectional area. By Ecological Green Axis. The project is in line area diverting, regulating, pumping and with the Hezhou Water landscaping Nine areas: including the High Speed Railway draining, reduce the water levels. Way System Plan. plan Commercial Area, the Cultural and Art Area, the Administration and Finance Area, the Gardening Green City Area, the Ecological Industrial Area, the The project will develop 6.5 ha greening Ethnic Tribal Custom Area, the Ancient Hezhou City area along the central main green corridor Area, the Low-carbon Industrial Area and the to develop an ecological green corridor. Leisure Tourism and Residential Area. Multiple corridor: there are many riverside landscaping corridors and roadside landscaping corridors in the downtown area. - 70 - 2.4.2 Compliance analysis with Hezhou Municipality Urban Flood Control Plan The urban flood control plan is a special plan under the city master plan. It aims at solving the problem that the city has barely any flood control facility and has been suffering from flooding problems for long time, and at preparing the urban flood safety system, so that it can support the urban development in Hezhou. Its scope covers the area from the Liantang Township in the east, and to the Xiwan Street in the west, from the Etang Town in the south and to the Luoyang-to-Zhanjiang Railway in the north. The planed timeframe is to short term to 2020 and long term to 2030. The details of the plan the compliance analysis with the project are summarized in Table 2-6. - 71 - Table 2-6: Analysis of Compliance of the Project with Hezhou Municipality Urban Flood Control Plan (2015-2030) Compliance Item Planning This project analysis Based on the layout of He River and its tributary, and on the existing city layout and its expansion direction, the Plan proposed a flood control system that consists of three districts and seven sub-districts, including the Xiwan sub-districts and Pinggui sub-districts under the Pinggui District; the Shatian sub-districts, Jiangbei sub-districts, Jiangnan sub-districts, Liantang sub-districts under the Hezhou Core Urban District, and the Hejie sub-districts in Hejia Township. For each sub-district, the flood control The flood control standard for He River The project is in line standard is different based on its significance. The urban Overall under the Project is floods with a with Hezhou area along He River main watercourse will use once every layout recurrence period of 50 years. Municipality Urban 50 years reoccurrence frequency after regulation from Flood Control Plan upstream reservoir. For the urban area along the tributary (2015-2030) without upstream reservoir regulation, the standards of once every 20 – 50 years reoccurrence frequency will be used. In each sub-district, flood control dike will be built along He River and its tributaries including Xiwan River, Pangu River, Huashan River and Mawei River. Flood control gate and pumping stations will be built at the merging site of each outlet of drainage ditch and He Rivers. Short term (2020): the planed facilities include : Pinggui New In the A-1 He River Integrated Planned The implementation District Dike (He River), Huangtian Dike, Jiangnan Dike Rehabilitation (Huangshi Hydropower flood of the Project will be control (Jiangnan He River Dike - south bank, Pangu River dike – Station – Guangming Bridge) supplementary for the both sides, Huashan River dike – left bank dike and right subproject, the length for rehabilitation facility existing flood control bank embankment), Hejiedong Dike (town area), Hejiexi Dike is 12.569 km. The project widens the facilities. (town area). The total dike length is 26.33 km and total watercourse to break the bottleneck - 72 - Table 2-6: Analysis of Compliance of the Project with Hezhou Municipality Urban Flood Control Plan (2015-2030) Compliance Item Planning This project analysis embankment length is 30.272 km. sections (control width between dikes is 120 m). The dike elevation is between 112.07 m and 112.52 m at stake number 17+200-19+500 at Long term (2020-2030), the planned facilities include: Pinggui New Area, sufficient to meet Shatian Embankment, Hezhou Institute Dike, Fanglin Senior the flood control requirement, therefore High School Dike, Liantangdong Dike, Liantangxi Dike, the dike at this section will remain Hejiedong Dike, Hejiexi Dike. The total dike length is 24.766 intact. km and total embankment length is 30.935 km. In the A-2 He River Integrated Rehabilitation (Guangming Bridge --- Lingfeng Bridge) subproject, the length for rehabilitation is 2.1 km. The project widens the watercourse to break the bottleneck sections (control width between dikes is 120 m). The dike on the north bank from Babu Bridge to Lingfeng Bridge is already in place. Therefore this subproject will focus on the right bank to widen the channel and develop new dike. In the A-3 He River Integrated Rehabilitation (Lingfeng Bridge – Xiadao Hydropower Station) subproject, the length for rehabilitation is 6.9 km. He River alignment will remain unchanged. The project widens the watercourse to break the bottleneck sections (control width between dikes is 120 m). The left bank is the Jiangbei Dike in place. The right bank from Lingfeng Bridge to Huashan River is under construction. The subproject will focus on the widening of the 3 km - 73 - Table 2-6: Analysis of Compliance of the Project with Hezhou Municipality Urban Flood Control Plan (2015-2030) Compliance Item Planning This project analysis section from Huashan River entry point to Xiadao Hydropower Station dam, and building the new dike for this section. (1) Short term In short term there will be 14 drainage pumping station (total installed capacity 6585 kw and total flow 121.06 m3/s) and By widening and dredging in He River 17 drainage gates (total flow 293.09 m3/s) and 2 connecting main watercourse, and branch pipeline. channels (Lining River and Changlong River), Huangtian Branch Canal, a. Pinggui Management District Guposhan Drainage Canal, East No.5 According to the layout and topography of Xiwan River Xiwan Branch Canal, Huangansi Drainage Canal and Shizigang Drainage Canal, Group Tea Farm, and the Xiwan Bridge right bank renovation the project will increase their flood project (Xiwanxi Dike) in Pinggui Management District, one carrying cross-sectional areas. In Planed flood control gate will be established for each of the three This project is an addition, by diverting, regulating, drainage drainage catchments including the Pinggui Senior High important part of the pumping and draining, the project will School catchment, Pinggui Coal Mine Catchment, and the planned flood control facility help reduce the water levels. Xiamaling Catchment. A pumping station will also be facilities in the special established for the Pinggui Senior High School catchment. plan. The project will also install 2 drainage pumping station at catchment area b. Core Urban Area District near end of the Huangansi and Shizigang Drainage Canals so that For the Jiangbei sub-district, 4 drainage gates will be established for Liwu, Lianhualing, Pingdizhai and Tianchong, floods with high water level will be drained by gravity while floods with low respectively, and 2 pumping stations will also be installed; 3 water level will be drained by pumping. drainage gates and 3 pumping stations will be established at the end of the Huangansi, Shizigang and Taoyuan drainage canals, respectively. 5 drainage gates and 5 pumping stations will be established at the catchments of Xuewu of Jiangnan dike, Babu Bridge, Chengnan, Pangu River and Huashan River, respectively. - 74 - Table 2-6: Analysis of Compliance of the Project with Hezhou Municipality Urban Flood Control Plan (2015-2030) Compliance Item Planning This project analysis c. Hejie Town District For Hejie Town District, the short term works are focused on flood control on the left bank of He River and the right bank of Daning River to protect the town area. based on the topographic condition, the area is divided into 4 catchments, namely the Caijiacun Village, the Hejie Town, the Shenshuiping and the Chenjia Village. 4 drainage water gates will be established for the 4 catchment respectively. 3 pumping stations will be installed for the Caijiacun Village, the Hejie Town, the Shenshuiping catchments respectively. (2) Long term In long term there will be development of 5 drainage pumping station (total installed capacity 4585 kw and total flow 64.31 m3/s) and 19 drainage gates (total flow 315.45 m3/s), and 8 connecting pipeline, rehabilitation of 2 drainage canals, and expansion of 3 flood diversion canals. a. Core Urban Area District Jiangbei sub-district: expand 3 flood diversion canal (Zhutudun, Xintang and Chongtang) to discharge the storm water of maximum 24-hour storm of once every 20 years reoccurrence frequency. In the city, develop Yongfeng Lake to regulate the flood in Huangansi Catchment; plan the Taibai Lake to regulate the flood in Nanshetang Catchment. Rehabilitate the Huangansi and Shizigang Drainage Canals, and conduct dredging and channelizing for the canals. Jiangnan sub-district: Conduct dredging and channelizing for the canals by rehabilitating the Xuewu Drainage Canal. The drainage canal can be divided into two sections separated at - 75 - Table 2-6: Analysis of Compliance of the Project with Hezhou Municipality Urban Flood Control Plan (2015-2030) Compliance Item Planning This project analysis Nanhuan Road. The first section is 0.89 km from Fanglin Village Yutian Group to the Nanhuan Road culvert. The second section is 1.129 km from the Nanhuan Road culvert to He River while passing by the Zeng’s ancestral hall and the Xuewu at Fanglin Village. The flow carrying capacity is 12.1 m3/s. In the long term the catchment in the area is the Fanglin catchment. At Fanglin Senior High School, one drainage gate and one pumping house will be installed. b. Hejie Town District For Hejie town district, the long term plan is to develop flood control dikes on both sides of He River to protect the town. Based on the topographic condition, there will be 6 catchment areas, namely the Litangping, Lijiazhai, Niuzailing, Nanchong, Zhouwuzhai and Longjiazhai catchments. For these catchments, 6 drainage gates will be installed respectively. - 76 - 3. Due Diligence of Linked Projects 3.1 Linked Project Screening According to the project appraisal, the World Bank Loan Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project (hereinafter referred to as “The Project�) mainly have the following linked projects: Guangxi Main Tributary He River Integrated Rehabilitation, Hezhou Jintai Lake Integrated Water Environment Improvement, Hegang Yongfeng Lake Integrated Water Environment Improvement, Hezhou WWTP, Hezhou Sludge Harmless Disposal, Hezhou Solid Waste Landfill, etc. as detailed in Table 3.3-1. Table 3-1 Linked Projects Screening Results Sub-project Linkage with the Project Hezhou Urban Flood Control under Guangxi Main Tributary He River Integrated Rehabilitation Project (Pingguixincheng Dike: Existing river dike A-1 He River Integrated Rehabilitation will be kept as it is in the linked project; under the Project, connection dikes (Huangshi Hydropower Station – will be constructed where there is no river dike.) Guangming Bridge) Huangtian Dike: Existing river dike will be kept as it is in the linked project. Under the Project, connection dikes will be constructed where there is no river dike.) Hezhou Urban Flood Control under Guangxi Main Tributary He River Main Integrated Rehabilitation Project (Jiangbei Dike: the north dike from A-2 He River Integrated Rehabilitation watercourse Guangming Bridge to Lingfeng Bridge is Jiangbei Dike which was already (Guangming Bridge – Lingfeng Bridge) Widening for built. Under the Project, dike height will be increased and bank road will be Flood Control widened to the south dike, and a new flood dike will be constructed) Hezhou Urban Flood Control under Guangxi Main Tributary He River A-3 He River Integrated Rehabilitation Integrated Rehabilitation Project(Jiangbei Dike: dike height will be (Lingfeng Bridge – Xiadao Hydropower increased on existing Jiangbei Dike. Station) Jiangnan Dike: under construction and to be connected with the Project at the upstream and downstream sections). A4 East Trunk Canal Integrated Hezhou Municipality Solid Waste Landfill: to receive dewatered sludge Rehabilitation and Mawei River cake from river dredging under the Project. Connection Guangxi Main Tributary He River Integrated Rehabilitation Project Hezhou Urban Area Flood Control: within the same river reach, dredging will occur A-8 He River (Huangshi Hydropower in He River course and not affect existing river dike. Dredging Station – Guangming Bridge) Dredging Hezhou Municipality Solid Waste Landfill: to receive dewatered sludge cake from river dredging under the Project. B-3 Lining River Rehabilitation Hezhou Municipality Jintai Lake Integrated Water Environment Improvement project: Lining River and Changlong River are located B-4 Changlong River Rehabilitation upstream of Jintai Lake, which serves as the hub of river-lake connection and the function of flood control and storage regulation. Hezhou Municipality Yongfeng Lake Integrated Water Environment Improvement Project: Huangtian Branch Canal is upstream of Yongfeng Lake, which serves as the hub of river-lake connection and the function of flood control and storage regulation. B-5 Huangtian Canal Rehabilitation Hezhou Municipality WWTP: to receive and treat sewage collected by River-lake interceptor sewer pipe network connection Hezhou Municipality Solid Waste Landfill: to receive dewatered sludge cake from river dredging in the Project. Hezhou Municipality Yongfeng Lake Integrated Water Environment Improvement project: Guposhan Drainage Canal is upstream of Yongfeng Lake, which serves as the hub of river-lake connection and the function of B-6 Guposhan Drainage Canal flood control and storage regulation. Rehabilitation Hezhou Municipality WWTP: to receive and treat sewage collected by interceptor sewer pipe network Hezhou Municipality Solid Waste Landfill: to receive dewatered sludge cake from river dredging in the Project. - 77 - Table 3-1 Linked Projects Screening Results Sub-project Linkage with the Project Huangansi Hezhou Municipality Yongfeng Lake Integrated Water Environment C-1 Huangansi Drainage Canal Drainage Canal Improvement project: Huangansi River is downstream of Yongfeng Lake, Rehabilitation Rehabilitation which serves as the hub of river-lake connection and the function of flood control and storage regulation. Shizigang Hezhou Municipality WWTP: to receive and treat sewage collected by C-2 Shizigang Drainage Canal interceptor sewer pipe network; Drainage Canal Rehabilitation Rehabilitation Hezhou Municipality Solid Waste Landfill: to receive dewatered sludge cake from river dredging in the Project. Drainage C-3 Jiangnan WWTP and Associated Hezhou Sludge Harmless Disposal: to receive sludge from Jiangnan System Sewer Network and Road Improvement WWTP. Improvement Figure 3-1: Project and Linked Projects Layout Map 3.2 Due Diligence 3.2.1 Guangxi Main Tributary He River Integrated Rehabilitation Project Subproject A-1, A-2 and A-3 under the Main Watercourse Widening of the Project are linked to Hezhou Urban Flood Control under Guangxi Main Tributary He River Integrated Rehabilitation Project. Here described as follows is the due diligence for Hezhou Urban Flood Control under Guangxi Main Tributary He River Integrated - 78 - Rehabilitation Project. 1. Contents and scope of Guangxi Main Tributary He River Integrated Rehabilitation Project Pinggui New City Dike: Located on the right dike of He River reach within Pinggui Administration District, Pinggui New City Dike starts at the end point of Pinggui New City river dike Fujiang section (STA. PG1+080.00), with Shanzhou Head and Xiwan village along its route, and ends at Shiniudu at the lower reaches of Xiiwan village with a total length of 1.07km. The flood control dike is designed against the Dike-Park-Road model: planned municipal road + dike width 6m + bank revetment. Huangtian Dike: Located at left bank of He River reach within Pinggui Administration District, Huangtian Dike starts at Jigongtou Mountain in Pinggui Administration District and ends at 400m close section downstream of Dongmu Park with a total length of 3.066km.The whole dike is earth dike. The design water level is 111.24~110.27m and 15 wharfs are included in the design. Jiangbei Dike Flood Control Improvement River Dike: Jiangbei Dike starts at He River Bridge and ends at Wayaotou, comprising of Jiangbei West Dike, Jiangbei Middle Dike and Jiangbei East Dike. The total length of dike is 6.127km and the dike is a mixture of earth dike / earth and rock mixed dike / masonry dike / concrete mixture dike with a design water level of 108.78~ 104.60m and include 29 wharfs. Jiangnan Dike Flood Control Improvement River Dike: Jiangnan Dike comprises of Jiangnan Dike of He River section, Pangu River left and right dike sub-dike and Huashan River left sub-dike. Jiangnan Dike of He River section starts at Xihuan Road connecting He River Bridge, runs along Pangu River Estuary and ends at Huashan River Estuary. The dike has a total length of 4.524 km with a design water level of 108.78~104.25m and there are 20 wharfs included. 2. Approval of Environmental Protection Hezhou Municipality EPB issued approval for Guangxi Main Tributary He River Integrated Rehabilitation Project EIA Report on January 8th, 2016. 3. Status of Project Construction Currently, construction has been completed for Pinggui New City Dike, Huangtian Dike and Jiangbei Dike in Guangxi Main Tributary He River Integrated Rehabilitation Project Hezhou Municipality Urban Flood Control Project, Jiangnan Dike has not been completed construction, which is planned to be completed in 2018. 3.2.2 Hezhou Jintai Lake Integrated Water Environment Improvement project B-3 and B-4 as a part of He River-lake connection Works under the Project will be connected with Jintai Lake. Here described as follows is the due diligence work for Hezhou Jintai Lake Integrated Water Environment Improvement Project: 1. Scale and Scope of Construction Jintai Lake of Hezhou Municipality is located south of Zhanqian Avenue, east to Aimin Road, north to Wanxing Road and west to Xiangda No.1 Road of Hezhou Municipality. The construction scope includes: 1 proposed Jintai Lake, 2.379km of Jintai Lake revetment, 1.845km of Yucai River improvement (the downstream of Jintai Lake connects to existing Guangming Drainage Canal through Yucai River), 3.69km of proposed Yucai River revetment, 1 proposed Hydraulic Lift Dam at Yucai River, - 79 - associated works including artificial island and municipal landscaping facilities. 2. Approval of Environmental Protection Hezhou Municipality EPB issued approval for the EIA of Inter-provincial He River Watershed (Xiwan to Xiadao river reach) Jintai Lake Integrated Water Environment Improvement Project EIA on November 8th, 2016. 3. Status of Construction The project is not yet constructed and is estimated to be completed in September, 2019. 3.2.3 Hezhou Municipality Yongfeng Lake Integrated Water Environment Improvement Project B-5, B-6 and C-1 as a part of He River-lake connection Works under the Project will be connected with Yongfeng Lake. Here described as follows is the due diligence work for Hezhou Yongfeng Lake Integrated Water Environment Improvement Project. 1. Scope and Scale of Construction Location: an area south to Heping Road, east to Aimin Road in Hezhou Municipality, along Xinhua Road to Yucai Road intersection, and west to Zhushan Road to Guposhan Avenue. Construction scope and scale: 1 new Yongfeng Lake, 6.60km of ecological revetment of Yongfeng Lake, 1.30km of Aimin River Improvement (upstream of Yongfeng Lake connects to Jintai Lake through Yucai River and Aimin River), 2.60km of Aimin River ecological revetment, 1 hydraulic lift dam each on Aimin River, Huangansi River and Shizigang River, 30m of proposed Guangming Avenue bridge, proposed associated artificial island and municipal landscaping facilities. 2. Approval of Environmental Protection Hezhou Municipality EPB issued approval for the EIA of Inter-provincial He River Watershed (Xiwan to Xiadao river reach) Jintai Lake Integrated Water Environment Improvement Project EIA on November 8th, 2016. 3. Status of Construction The project is not yet constructed and is estimated to be completed in September, 2019. 3.2.4 Hezhou Municipal WWTP Sewage discharge from B-5 Huangtian Canal Rehabilitation Project, B-6 Guposhan Drainage Canal Rehabilitation Project, C1 Huangansi Drainage Canal Rehabilitation and C2 Shizigang Drainage Canal Rehabilitation is conveyed to Hezhou Municipality WWTP. Here described as follows is the due diligence study for Hezhou Municipality WWTP: 1. Hezhou Municipality WWTP Construction Scope and Scale Hezhou Municipality WWTP is located at the north dike of He River Wayaotou in Lingfeng Village, Babu Township, Hegang City (originally the Red Brick Factory in Hezhou Municipality). The plant occupies an area of 55,274.29 m2. It was constructed in 2 phases. Phase I of the WWTP involves a land occupation of 46,236.69 m2 and a design capacity of 30,000 t/d and provides service to the planned Jiangbei District of Hezhou Municipality as the service area of approximately 15~17 km2 and a population - 80 - of 175,000, mainly designed for treatment of domestic wastewater from urban area. Phase II of the WWTP project is located at the west side of Phase I and has a design capacity of 30,000 m3/d. Service area: expanded to receive wastewater from Babu Center Group, Taibai Lake District and Rufengzhai Industrial Park. 2. Approval of Environmental Protection GZAR EPB issued the approval for Hezhou Municipality WWTP EIA Table on December 10th, 2007. GZAR Environmental Protection Department issued approval for Hezhou Municipality WWTP Project Completion Environmental Protection Acceptance Monitoring Report Table in June 2010. Hezhou Municipality EPB issued approval for Hezhou Municipality WWTP Expansion Project EIA Table (Phase II project) on July 25th, 2016. 3. Status of Construction and Operation Hezhou Municipality WWTP Phase I was put into trial operation in 2008 and official operation in December 2010. Phase II of the WWTP commenced in August, 2016 and is scheduled to complete and put into operation in October 2017. Status of construction for sewer pipe networks: Jiangbeizhong Road Branch Sewer Rehabilitation Project was completed at the end of 2013 and connected with 7 sewer outfalls; construction for interceptor trunk sewer from Babu Bridge to Wanxing Road intersection was completed in December 2015; currently the sewer pipe networks in urban area is continuously being improved. 4. Treatment Processes Hezhou Municipality WWTP Phase I uses A2/O oxidation ditch as treatment process. After secondary treatment, wastewater is disinfected using UV light to meet Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant Class IA Standard and then the effluent is discharged into He River through 600 m discharge pipe. Sludge is dewatered and condensed and no sludge nitration tank is being used. The volume of sludge after dewatering is 16.8t/d. After dewatering (water content 80%), sludge cake is transported to Guangxi Hezhou Sludge Harmless Disposal Plant for treatment. After such treatment, sludge achieves a moisture content of 60% and then transported to Hezhou Municipality Solid Waste Landfill for landfill. Detailed in the following table are the results of review of 2017 Quarter 3 Hezhou Municipality WWTP monitoring data published by Hezhou Municipality EPB on GZAR Government Integrated Public Information Platform and the water quality characteristics of the influent and effluent of Hezhou Municipality WWTP. Table 3-2 Influent and Effluent Water Quality Characteristics Design Daily Influent Effluent Standard Effluent Monitoring Standards Treatment Concentration Concentration Unit Compliance Flow (t/d) Criteria (mg/L) Capacity (mg/L) (mg/L) (Y/N) (t/d) pH / 7.36-7.47 6-9 N/A Y 30,000 30,096.00 BOD / 2.5 10 mg/L Y TP / 0.06 0.5 mg/L Y - 81 - Table 3-2 Influent and Effluent Water Quality Characteristics Design Daily Influent Effluent Standard Effluent Monitoring Standards Treatment Concentration Concentration Unit Compliance Flow (t/d) Criteria (mg/L) Capacity (mg/L) (mg/L) (Y/N) (t/d) COD 62 6 50 mg/L Y TSS / 7 10 mg/L Y Fecal / 17 1000 个/L Y Coliforms NH3-N 10.42 0.05 5 mg/L Y TN / 4.48 15 mg/L Y Petroleum / 0.09 1 mg/L Y Based on the table above, the effluent of Hezhou Municipality WWTP Phase I meets Class IA standard of the Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002)and is discharged into He River. Phase II uses “A2/O (anoxic→anaerobic→aerobic) + Chemical Phosphorus Removal + Filtration� treatment process. Wastewater is treated in the A2/O process, then disinfected by UV and discharged into He River through effluent discharge pipe. Sludge from Hezhou WWTP is dewatered and condensed. No sludge nitration tank is used. Sludge cake is transported to Guangxi Hezhou Sludge Harmless Disposal Plant for disposal. Phase II of the WWTP adopts the same treatment process as Phase I. Based on the operation situation of WWTP Phase I, the A2/O treatment process used in Phase II can ensure the compliance of Class 1A standard in the Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002). 5. Compatibility of Wastewater Treatment Capacity Hezhou Municipality WWTP Phase I has a design capacity of 30,000 m3/d. According to data provided by Guangxi Hezhou Beijing Enterprises Water Group Limited, the annual average daily influent is 25,990 m3 in 2016; Phase II has a design capacity of 30,000 m3/d, and is scheduled to be put into operation in October 2017. The sewage interceptor component under the project has a design flow of 15,000 m3/d and the interception area is a part of the service range of this WWTP and its treatment capacity will meet the demand for treatment of wastewater collected by interceptor sewer. 6. Summary According to the due diligence of Hezhou Municipality WWTP, the construction and operation of WWTP Phase I project meet relevant laws and regulations of the nation, and meet the requirement for EIA approval procedure. All the pollutants meet the respective standards and the project has passed the acceptance of environmental protection; Hezhou Municipality WWTP Phase II is under construction and planned to be put into operation in October 2017. The subprojects of B-5 Huangtian Drainage Canal Rehabilitation, B-6 Guposhan Drainage Canal Rehabilitation, C1 Huangansi Drainage Canal Rehabilitation and C2 Shizigang Drainage Canal Rehabilitation under the Project will be implemented after 2018 and the planned WWTP will meet the - 82 - wastewater treatment demand of the Project. After the Project is put into operation, the construction and operation status of WWTP Phase II will be continuously tracked. 3.2.5 Hezhou Municipality Sludge Harmless Disposal Project Sludge generated from Jiangnan WWTP under The Project will be treated by Hezhou Municipality Sludge Harmless Disposal Project, the results of due diligence of which are described as below: 1. Construction Scope and Scale of Hezhou Municipality Sludge Harmless Disposal Project Hezhou Municipality Sludge Harmless Disposal Project is located in Jiuniu Village in Liantangxinyan Village in Hezhou Municipality, with a treatment capacity of 100t/d (counted as 80% water content), a land occupation of 5,917.87 m2, the total footprint of the plant is 1,356.97 m2, and a total investment of 23.73 million RMB. It will mainly receive dewatered sludge from domestic WWTP in all level cities and townships in Hezhou (with 80% water content). No sludge from industrial WWTP is involved.. 2. Approval of Environmental Protection Hezhou Municipality EPB issued approval for Hezhou Municipality Sludge Harmless Disposal Project EIA Report on November 8th, 2016. 3. Status of Construction and Operation Construction for Hezhou Sludge Harmless Disposal Project started in January 2016. The trial operation was carried out in August. Hezhou Sludge Harmless Disposal project accept dewatered sludge from domestic WWTP of all cities and townships in Hezhou (with 80% water content). Currently, it accepts sludge from 4 domestic WWTPs (Hezhou Municipality WWTP, Zhongshan County WWTP, Fuchuan County WWTP and Shaoping County WWTP) in a capacity of 33.3 t/d. Treated sludge with a water content of lower than 60% meets relevant standards and requirements in GB/T 23485-2009 Disposal of Sludge from Municipal Wastewater Treatment Plant - Quality of Sludge for Co-landfilling and will be co-landfilled with domestic solid waste in Hezhou Municipality Solid Waste Harmless Disposal Plant Landfill. Filtered wastewater will be collected and treated by EIC-MBR Integrated Wastewater Treatment System and the treated effluent shall meet Class I standard of the Integrated Wastewater Discharge Standard and then discharged into Mawei River to the northeast of the Project. 4. Treatment Process Hezhou Municipality Sludge Harmless Disposal Project uses “Dilution Regulation + Advanced Dewatering� treatment process, with the sludge delivered to site (80% water content) dewatered to a water content of 60%. Discharged sludge is disposed through landfill disposal. 5. Analysis of Compatibility of Sludge Harmless Treatment Capacity The design capacity of Hezhou Sludge Harmless Treatment Project is 100 t/d. Currently, Hezhou Sludge Harmless Treatment Project accepts sludge from 4 domestic WWTPs with total quantity of 33.3 t/d, so the project still has a redundant treatment capacity of 66 t/d. Jiangnan WWTP in the Project generates 3 t/d of sludge, accounting for 4.5% of the treatment capacity of 66 t/d. Therefore, Hezhou Sludge Harmless Treatment Project can meet the demand for sludge disposal of the Project. - 83 - 6. Summary Sludge generated by Jiangnan WWTP will be treated by Hezhou Sludge Harmless Treatment Project. According to the due diligence results for Hezhou Sludge Harmless Treatment Project, the Project is currently in trial operation stage and its construction and operation meet requirements of relevant national laws and regulations. After project implementation, the operation status will be continuously monitored and tracked for Hezhou Sludge Harmless Treatment Project and the supervisory monitoring requirements listed in its EIA will be included in the Environmental Management Monitoring Plan of the Project. The monitoring reports will be regularly submitted as one of the mandatory deliverables of The Project. 3.2.6 Hezhou Municipality Domestic Solid Waste Landfill 1. Scope and Scale of Construction Hezhou Municipality Domestic Solid Waste Landfill is located in Dafachong on the west side of Jiuniu Village in Xiyan Village, Liantang Township, Hezhou Municipality. The landfill will manly handle domestic solid waste from the downtown area of Hezhou Municipality (including Liantang Town and Hejie Town) and a part of the domestic solid waste from Pinggui District. The landfill occupies an area of 129,114 m2 and comprises of 2 landfill zones. Landfill Zone No.1 has a capacity of 370,000 m3 and a daily design treatment capacity of 180 t of domestic solid waste. 1 leachate treatment station as an associated facility has been constructed with a daily treatment capacity of 300 m3 . Landfill Zone No.2 has a capacity of 1.92 million m 3 and is not yet constructed. 2. Approval of Environmental Protection Hezhou Municipality Domestic Solid Waste Landfill was initially named as Guangxi Hezhou Municipality Domestic Solid Waste Harmless Disposal Plant. On October 30th, 2002, GZAR EPB issued approval for Guangxi Hezhou Municipality Domestic Solid Waste Harmless Disposal Plant Environmental Impact Assessment Report , and granted approval for the construction. On April 22nd, 2005, due to the big adjustment of treatment method and composition, at the 22nd executive meeting of Hezhou Municipality Government, the plant was renamed Guangxi Hezhou Municipality Domestic Solid Waste Harmless Disposal Plant from Hezhou Municipality Domestic Solid Waste Landfill. On May 9th, 2005, GZAR EPB issued approval for Hezhou Municipality Domestic Solid Waste Landfill Environmental Impact Assessment Report. In October 2017, Hezhou Municipality Babu District EPB issued approval for Hezhou Municipality Domestic Solid Waste Landfill Seepage Treatment Station Upgrading and Reconstruction Project Environmental Impact Assessment Report. 3. Status of Construction and Operation Construction of Hezhou Municipality Domestic Solid Waste Landfill No.1 was completed and put into operation in 2008. 4. Treatment Process and Standard Compliance Hezhou Municipality Domestic Solid Waste Landfill was put into operation in 2008. The selected solid waste treatment process is sanitary landfill and the leachate treatment process is “Biological Treatment + Flocculation and Sedimentation� . The treated leachate meets Class II standards specified in the Standard for Pollution - 84 - Control on the Landfill Site of Municipal Solid Waste (GB16889-1997). It is specified in Articles 9.1.2 - 9.1.3 of the Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008) that all existing and newly constructed municipal solid waste landfills shall meet water pollutants discharge limits in Table 2 starting from July 1st, 2009. After July 1st, 2011, all existing municipal solid waste landfills shall treat its own municipal solid waste leachate against the water pollutants discharge limits in Table 2. According to data of the conventional monitoring of the municipal solid waste landfill conducted by City Environment Monitoring Station in the recent 5 years, COD, BOD 5 and TN in treated leachate from Hezhou Domestic Solid Waste Landfill exceed the limits in Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008) (See details in Table 3.3 below). Therefore, Hezhou Domestic Solid Waste Landfill applies temporary measures for disposal of leachate by means of transporting the pretreated leachate in tankers to Hezhou Municipality WWTP for further treatment. Meanwhile, Hezhou Domestic Solid Waste Landfill conducted upgrading and reconstruction for solid waste leachate treatment station by relocating the leachate regulation tank from Landfill No.1 to Landfill No.2 where the leachate is treated with “Membrane Biological Reactor (MBR) + Nanofiltration (NF) + Reverse Osmosis (RO)� process. According to the predicted results included in the Environmental Impact Assessment Report for Hezhou Municipality Domestic Solid Waste Landfill Leachate Treatment Station Upgrading and Reconstruction Project, after such upgrading and reconstruction of seepage treatment station, treated leachate can meet the limits specified in Table 2 of the Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008). - 85 - Table 3.3 Summary of Conventional Monitoring Data of Hezhou Municipality Solid Waste Landfill Unit: mg/L(Chromaticity:multiple, Total Coliform:CFU/L) Hehuanjian Standard for Pollution Control Hehuanjian Hehuanjian Hehuanjian Hehuanjian Hehuanjian Hehuanjian Location (Jiang) Zi on the Landfill Site of (Jiang) Zi (Jiang) Zi (Jiang) 〔2013〕 (Jiang) [2014] (Jiang) 〔2015〕(Jiang) 〔2016〕 Municipal Solid Waste Criteria 〔2010〕No. [2011] No. 135 〔2012〕 No. 104 No.75 099 No.111 No.45 No.51 (GB16889-2008) 2011.12.14 2012.6.21 2013.10.15 2014.7.7 2015.6.5 2016.9.30 2010.7.1 pH 7.89 6.86~7.56 7.20~7.34 7.65~7.68 7.56~7.76 7.76~7.78 6.38~7.82 6~9 Chromaticity — 4 16 4 40 8 32 40 SS — 28 50 11 6 13 12 30 COD 362 165 203 95 92 31 166 100 BOD5 — 48 31 25.7 23.5 9.5 38.8 30 NH3-N 242.0 1.871 37.65 9.285 2.251 2.201 20.88 25 Treated Leachate TN — 8.322 62.8 29.8 27.8 44.3 214 40 TP 0.349 0.09 0.07 0.18 0.05 10.01 0.14 3 Total 0.955 ND 0.01228 ND ND 0.00062 ND 0.001 Mercury Total Lead 0.2L ND 0.087 ND ND ND ND 0.1 Total 0.05L ND 0.082 0.0005 0.0002 ND ND 0.01 Cadmium Total Arsenic 0.046 ND 0.0032 0.0006 0.0019 0.0014 0.0021 0.1 Total — 0.016 ND 0.005 ND ND ND 0.1 Chromium Chromium-6 0.004L 0.010 ND ND ND ND ND 0.05 Total 170 1700 2100 1700 30 350 30 10000 Coliform - 86 - 5. Treatment Capacity Hezhou Municipality Domestic Solid Waste Landfill is currently using Landfill No.1 with capacity of 370,000 m3. As of September 2017, a capacity of 320,000 m3 has been used, with a balanced capacity of 50,000 m3. In the meanwhile, Hezhou Municipality Domestic Solid Waste Landfill, scheduled to be completed in December 2017, will upgrade and reconstruct the solid waste leachate treatment station by relocating the leachate regulation tank from Landfill No.1 to Landfill No.2, and using the former site of the leachate regulation tank as a landfill site (with a design capacity of 300,000 m3), making the total balanced capacity reach 350,000 m3. Calculated based on the existing solid waste delivery of 700 t/d, the future demand for 3 years will be satisfied. Sludge cake generated from dredging in the Project is 18,459 m 3, accounting for 5.3% of the total balanced capacity. Therefore, the capacity of Hezhou Municipality Domestic Solid Waste Landfill can meet the landfill demand of the Project. 6. Summary According to the due diligence conducted for Hezhou Municipality Domestic Solid Waste Landfill, the leachate discharged from the landfill does not meet standard limits listed Table 2 of the Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008), but the landfill is currently upgrading and reconstructing the leachate treatment station scheduled to be commissioned in December 2017. The subprojects of A-8: He River Main Watercourse Dredging, C-1 Huangansi Drainage Canal Rehabilitation and C-2 Shizigang Drainage Canal Rehabilitation will be implemented in 2018-2019 and the dewatered sludge to be generated from these subprojects will be disposed in Hezhou Municipality Domestic Solid Waste Landfill. Therefore, it is recommended that Hezhou Municipality Domestic Solid Waste Landfill should accelerate the reconstruction progress and implement the final acceptance of environment protection as a part of the final acceptance process according to the national and provincial regulations. In addition, after the Project is completed, the status of construction and operation of the Leachate Wastewater Treatment Station Upgrading and Reconstruction Project of Hezhou Municipality Domestic Solid Waste Landfill will be followed up with and the supervisory monitoring requirements included in the EIA of Hezhou Municipality Domestic Solid Waste Landfill will be incorporated into the Environmental Management Monitoring Plan of the Project, with its monitoring report regularly submitted as one of the mandatory deliverables of the Project. - 87 - 4. Status quo Survey and Analysis 4.1 Natural environment conditions 4.1.1 Geographical location Hezhou Municipality is located in the northeastern part of GZAR, at 111°05 '~ 112°03' east longitude and 23°39 '~ 25°09' north latitude in the border area of Hunan, Guangdong, Guangxi provinces and embraces the most convenient access from South Western China to Guangdong Province, Hong Kong and Macau. Hezhou Municipality borders Lianshan County, Huaiji County and Fengkai County of Guangdong Province to the east, Shaoping County and Zhongshan County to the west, Cangwu County to the north, and Fuchuan Yao Autonomous County and Jianghua County in Hunan Province to the south. Hezhou Municipality has a total area of 11,822 km2, accounting for 5.01% of GZAR, including 4,062 km2 for mountains, 1,420 km2 for plains and 6,373 km2 for low hills. Hezhou Municipality administers 1 district (Babu District), 2 counties (Shaoping County and Zhongshan County), 1 Autonomous County (Fuchuan Yao Autonomous County) and Pinggui Administrative District. The project construction activities will occur in urban area in Pinggui District and Babu District. Babu District is where Hezhou Municipality Government located, which borders Lianshan County, Huaiji County and Fengkai County in Guangdong Province to the east, Shaoping County and Zhongshan County to the west, Cangwu County to the north, and Fuchuan Yao Autonomous County and Jianghua County in Hunan Province to the south. Pinggui District is located on the North Western side of Hezhou Municipality, with its south eastern part at 7.5 km from urban center of Hezhou Municipality, north western part at 31 km from Zhongshan County urban area, and at the boundary of Hezhou Municipality Babu District and Zhongshan County. 4.1.2 Geology and Geomorphology Hezhou is geologically a part of Nanling mountainous area and also a part of hilly area across Guangdong and Guangxi Provinces. High mountains are mostly distributed in the northern and eastern parts, with a succession of mountain ranges extending from the east to the north and then to the south. The northern part of Babu District is a mountainous highland, starting from north eastern boundary to south western end, with a succession of mountain ranges; the mid-south part is mostly towering and steep mountains, with 5 small basins of Nanxiang, Guiling, Lisong, Babu and Xidu distributed in mountain valleys; high mountains are located in the middle part, which naturally forms a terrain that is higher in the northern part and lower in the southern. The whole district is mostly covered by mid-level and lower level mountains forming 5 small basins Nanxiang, Guiling, Lisong, Babu and Xidu in the valleys. Pinggui District is located in Nanling mountainous area, which is also a part of hilly area cross Guangdong and Guangxi Provinces, belonging to two of the five big mountain systems including Dupangling and Mengzhuling, and the transition zone between 1° north to tropic of cancer (north latitude 24°17′~24°46′) and subtropical monsoon climate zone. The terrain is rather complicated, including plain area, hilly area, basin and mountainous area. Eastern, northern, western and south western sides of the County are mountainous area, with multiple mountains and high terrain - 88 - surrounded, in the middle, there is depressed basins. Plain area and hilly area with mild slope is distributed between edge of mountain and basins. 4.1.3 Seismic Intensity According to Code for Seismic Design of Buildings (GB50011—2010) Appendix A, the seismic fortification intensity is 6 for Hezhou Municipality and all the buildings (structures) shall be designed with 6 seismic fortification intensity and a basic seismic acceleration rate of 0.05g. 4.1.4 Meteorology and Climate Hezhou Municipality is located in the eastern part of Guangxi Province, within subtropical monsoon climate zone south to 10°north to tropic of cancer, with subtropical monsoon climate. The climate is characterized by four distinct seasons and a high temperature and rainy summer. Winter is mild and dry; Spring is warm, wet, and rainy, with late spring cold; Autumn has clear sky and dry weather. Cold, heat, dryness and flood have big changes due to the influence of monsoon during the year. Wind speed is small and prevailing wind direction is WN, the secondary prevailing wind direction is E. According to precipitation data from 1952 to 2014 collected by Hezhou Municipality meteorological station, multi-year annual average precipitation is 1565.0mm, with maximum annual precipitation 2324.90mm (1973), minimum year 1006.3mm (1956). Precipitation is unevenly distributed during a year, with rainy season from mid-April to mid-September, and highest precipitation from April to August, accounting for 67.5% of the annual precipitation. The maximum multi-year average annual 24-hr rainfall is 113.0mm, the maximum 24-hr rainfall measured is 301.7mm (July 22nd, 1994), multi-year average evaporation is 1575.3mm. 4.1.5 Hydrology The main river in Hezhou Municipality urban area is He River, He River belongs to Xijiang River system of The Pearl River Watershed as a primary tributary of Xijiang River. He River is originated from Ming Mountain in Changchun Village, Mailing Township, Fuchuan County in Guangxi Province and flows through Fuchuan County, Zhongshan County, Hezhou Municipality, Fengkai County in Guangdong Province to the south and then into Xijiang River in Jiangkou Township, Fengkai County. He River course starting from its origin to U shape river reach in Pinggui District urban area is named as Fujiang River while the downstream section from the U shape river reach is named as He River, with a total length of 3,573km and an average slope of 0.47‰ in the main river course. According to data from Hejieduling Hydrological Station, the normal flow rate in He River is 80.3m3/s and the minimum and maximum flows are respectively 16.2m3/s (1986) and 1,500m3/s. He River flows through the city area from north to the east and divides the urban area into the southern and the northern parts. The main tributaries in the northern part include Xiwan River, Mawei River and Daning River and while those in the southern part are Shatian River, Pangu River and Huashan River. The main drainage canals in the northern part are Huangansi, Shizigang and Nanshetang drainage canals while those in the southern part are Xuewu and Chengnan drainage canals. Figure 4-1 is the layout map of He River water resources in the urban area. - 89 - - 90 - 4.2 Overview of Social Environment 4.2.1 Administrative Division and Population Hezhou Municipality is located in the northeastern part of GZAR occupying an area of 11,900 km2 and administers 2 Districts, 2 Counties, 1 Autonomous County, including Babu District, Pinggui District, Zhongshan County, Shaoping County and Fuchuan Yao Autonomous County. The total population of the City amounted to 2.4252 million at the end of 2016, increased by 33,000 from the previous year. Population of permanent residents is 2.0387 million, increased by 12,800 from the previous year, including an urban population of 896,600. 4.2.2 Social and Economic Development The regional GDP in 2016 was CNY 51.822 billion, representing an increase of 8.1 percent over the previous year. The added value of the primary industry was CNY 11.177 billion, increased by 4.1% over the previous year; the added value of the second industry was CNY 21.155 billion, increased by 10.0% over the previous year; the added value of the tertiary industry was CNY 19.489 billion, increased by 8.3% over the previous year. The added value of primary, secondary and tertiary industries accounted for 21.57%, 40.82% and 37.61% of GDP, respectively, and the contribution to economic growth was 11.19%, 49.94% and 38.87%, respectively. The average GDP per capita is CNY 25,499 per capita calculated based on permanent population. 4.2.3 Culture, Education and Health The city has many research institutions in the disciplines of agriculture, forestry, agricultural machinery and science and technology information. There are 746 primary schools in Hezhou Municipality with 291,346 primary school students, achieving a schooling rate of 100% for school-age children. There are 4 high schools, 8 secondary schools, and 103 junior high schools hosting 67,839 students and 2 special education schools with 1,523 students on campus. Hezhou Municipality has 25 kindergartens with 1,213 preschool classes and 5988 children. There are 20 secondary specialized (vocational) schools of different types, 1 general institution of higher education, 10 schools of various kinds of adult schools. The City as a whole has a teaching faculty of 21,936 persons in senior, junior and vocational middle school. There are 112 medical and health institutions, 93 hospitals and health centers, and 2587 hospital beds. 4.2.4 Transportation With an urban area of up to 15 km2, Hezhou Municipality has 121 urban roads in a total length of 73.68km. The transportation system in Hezhou Municipality mainly comprises of highways and waterways. National Highway 207 and 323, as well as 3 provincial highways run through the city; Guilin-Wuzhou Expressway and Luoyang-Zhanjiang Railway Guangxi Section, Guangzhou-Hezhou Expressway also run across Hezhou Municipality, constituting a local transportation system “like five dragons flying towards the sea�. Hezhou Municipality has a total length of 2,543km for classified roads, including more than 300km for Class II roads. The percentage of high-class roads in the city’s road network is far much higher than the provincial - 91 - average of GZAR. With a road density 21.27km/100km2, Hezhou has basically achieved the goal of connecting every county to Class II roads, some towns and townships to asphalt pavement roads and every village to roads accessible to motorized vehicles. Waterway transportation mainly relies on Guijiang River and He River that joins Xijiang River and connects Wuzhou Port, providing a 1-day waterway access to Guangzhou, Hong Kong and Macau. 4.2.5 Landscape and Culture Relics (1) Landscape There are rich and beautiful scenic spots in Hezhou Municipality, which include natural landscapes such as Guposhan Mountain National Forestry Park, Hezhou Hot Spring, Yushilin, Ziyunxianjing and Bishuiyan Stone, etc. According to site investigations, The Project will not involve any scenic area, natural preservative zone or forestry parks and the project area are mainly farmlands or residential areas. However, due to frequent damage from flood on He River dike and littering and dumping of garbage into He River by riverside residents, parts of the project areas along He River are dirty and messy from the landscape view. (2) Physical Cultural Resources Hezhou boasts of rich reserves of cultural relics and simple but deeply-rooted folk customs. The Kirin Wine Vase (Qilinzun) a nationally-valued cultural relics (with a history of 2300 years from the Spring and Autumn period) was unearthed in Hezhou Municipality; the humane historical destinations include Shantianmafeng Wugui Bridge, Longjing Ancient Village, Zhuang Minority Cultural Village, and Local Yao Minority Cultural Park, etc,; the historical streets include Xiyue Street Historical and Cultural Quarter, Hedong Street and Xiwan Hydropower Station Street, and relics such as the Old Site of Babu Special Branch of the Chinese Communist Party (CCP). According to investigation, the components of He River Integrated Rehabilitation (Guangming Bridge – Lingfeng Bridge) and Huangansi Drainage Canal Rehabilitation under the Project will affect Xiyue Historical Cultural Street. He River Integrated Rehabilitation (Lingfeng Bridge – Xia Island Hydropower station) Project will affect the Old Site of CCP Babu Special Branch. 1. Xiyue Street Historical and Cultural Quarter Xiyue Street Historical and Cultural Quarter is located in the mid-southern urban area of Babu District and borders the old site of Pingle Special Administration to the west, Babu Bridge to the east, the Linjiang north shore to the south and the north border of Xiyue Street to the north. As one of the first historical and cultural quarter of GZAR, the Quarter involves a planned area of protection of 5.17 ha, including a core area of protection of 1.78 hectares, accounting for 34.43% of the preserved area. The streets and lanes in the area have a full length of 509 m. In the historic and cultural quarter, there are six immovable historical relics including Babu Old River Bank, Yijing Bridge, Heweizhongjian Stone Wall, Tianyi Tobacco Shop, Qianji Pawnshop and Jiancheng Rice Shop and four recommended historic architectures. Land area occupied by traditional buildings, including the immovable cultural relics, historic buildings and traditional style buildings, accounts for 63.62% of the total area of the preserved zone. Preservation elements of Xiyue Street Historical and Cultural Quarter is shown in Figure 4-1 as follows. - 92 - - 93 - Table 4-2 Catalog of Historical Buildings on Xiyue Street Name of Protection Characteristics Location Usage Year Description Current situation buildings nature and values A 3-storey brick-wooden structure with an area of 308.2 The building was already `No.66 Republic Historical m2, the hotel used to be the demolished and reconstructed Yijing Hotel Xiyue Commercial of China building gathering place for progressive against the original architecture street era activists during the period of style in August 2016. Anti-Japanese war. A 3-storey brick-wood structure It is among the with an area of 205.7 m2, the few building was built as the site well-preserved office of He County Tobacco representative company. It is a building buildings of overhang with 2 stories (with an commercial No.71 and attic on the second floor), two sector in Commercial Republic Tobacco No.73 of Historical bays in the front and back, with Hezhou from and of China Shop company Xiyue building flush-gable-roof and brick-wood late Qing residential era Street structure, green brick walls and dynasty. small tiles. The staircase is in the middle of the two buildings, with a patio for lighting. The front and rear façades are heavily decorated with beauteous western-style gray plasters. It is a building of A 3-storey brick-concrete the specific structure with an area of historical period 664.1m2, the building has white Sino-Soviet No.6 Republic in Hezhou and a Historical walls and green tiles, with 5 Friendship Shajie residential of China representative idle and uninhabited building pentagrams decorated on the Association Street era building in the wall. The association played a historical period special role in promoting of the Republic Sino-Soviet relations. of China. Pousutong Xiyue Historical residential Republic A 3-storey brick-wood structure A representative idle and uninhabited - 94 - Table 4-2 Catalog of Historical Buildings on Xiyue Street Name of Protection Characteristics Location Usage Year Description Current situation buildings nature and values 2 Street building of China with an area of 376.0m , the building in the era building is located in No.33 Republic of Shajie Lane and nearby Sanban China era with Bridge. It is a well-preserved value of architecture of the Republic of historical China era, where Ms He research in the Xiangning used to live. city A stone masonry bridge that is development about 20m long and 5.5 meters and lifestyle of East side wide, the bridge was built in urban residents of Sanban Republic Immovable 1934 financed by Babu in Hezhou. Yijing Bridge Bridge, transport of China In normal service cultural relics Chamber of Commerce and Shajie era carries the inscribed text of Lane Zhang Tingjian. It is an ancient stone bridge in Xiyue Street. The masonry wall of Heweizhongjian Stone Wall was Heweizhongjian Xiyue Immovable Qing built on 6th of lunar January / Preserved as original stone wall Street cultural relics Dynasty utilizing fund raised by the squires for control floods of He River. 370m long revetment along the left bank of He River, it was built Republic with the funds raised by Shen Xiyue Immovable Babu old dike Transport of China Hongying during the Republic of Preserved as original Street cultural relics era China era. The entire river revetment is stacked with stones along He River. IA 3-storey brick-wood structure The building is No.23 Commercial Republic covering an area of 665.1 1m2, the typical The first floor is occupied as Tianyi Tobacco Immovable Xiyue and of China the building adopt a commercial and shops whilst the second and third shop cultural relics Street residential era flush-gable-roof and brick-wood residential floors are idle. structure of green brick walls. In building of - 95 - Table 4-2 Catalog of Historical Buildings on Xiyue Street Name of Protection Characteristics Location Usage Year Description Current situation buildings nature and values 1948 it was established by Hezhou during underground communist party the specific Fanglin branch to be the CCP period as well underground communication as the station in Eastern Guangxi, representative functioning as the main building during communication station for Babu the Republic of underground CCP groups during China era. the era of the War of Liberation. A 3-storey brick-wood structure covering a floor area of 529.7 m2, the building used to be a pawnshop run by Canton merchants in Hezhou. At the main entrance it is featured with No.8 the plaque “Qianji pawnshop�. Shajie Republic The windows of the building It is among the Qianji Immovable Lane, commercial of China façade are specialized, with few idle and uninhabited pawnshop cultural relics Xiyue era lacework on the mullion. The well-preserved Street second floor is featured with a representative small attic of well-designed buildings of shape. The building is heavily commercial decorated with a variety of sector in decorations with western style. Hezhou during In the periphery of the buildings the Republic of are mostly commercial houses. China era It is a 2-storey brick-and-wood No.10 structure covering an area of Hebian Republic 243.1 m2. During the period of Jiancheng rice Immovable Lane, residential of China the Republic of China, it was a idle and uninhabited shop cultural relics Xiyue era rice shop owned by Guangdong Street merchants in Hezhou. As a typical brick-wood building, the - 96 - Table 4-2 Catalog of Historical Buildings on Xiyue Street Name of Protection Characteristics Location Usage Year Description Current situation buildings nature and values first floor has a masonry wall while the second floor has a façade mainly comprising of logs. At the entrance, there are 4 well-preserved steps. - 97 - 2. Old Site of CCP Babu Special Branch The Old Site of CCP Babu Special Branch is located within Xiadao Primary School of Xiadao Village, Etang Township. As a representative building of the modern times constructed in 1943, the main school building is designed into a U-shaped plane with a north-facing gate. Nowadays, the teaching building has been destroyed, with only the school gate preserved. On its west, a “Memorial Hall of CCP Babu Special Branch� is constructed for exhibition of historical materials of CCP Babu Special Branch. The CCP Babu Special Branch has led the underground party work in Babu, Yongying, Guiling, Nanxiang and Pinggui mining area. The Old Site of CCP Babu Special Branch was back then a key activity base and is currently still an important red cultural heritage in Hezhou district and a base for patriotic education with important value for red cultural tourism development. 4.2.6 Local Drinking Water Sources According to the Letter of Approval by GZAR People’s Government on Classification Proposal Hezhou Urban Drinking Water Source Protection Zone (GZAR Guizheng Letter〔2016〕No. 203) issued in 2016, it has been approved to cancel the He River Babu Drinking Water Source Protection Zone and establish the Guishi Reservoir Drinking Water Source Protection Zone. The project area involves no drinking water source protection zone. 4.3 Status Quo of Ecological Environment 4.3.1 Status Quo of Constructional Land Use He River section included in the Project belongs to Babu-He Street Basin in terms of regional topography, with large tracts of farmland and village residential houses on both banks. In the basin, karsts topography is widely developed, creating a landform featuring in mountain peaks and woods valley, depressions and isolated peak plains. He River section of He River in Pinggui District is located in the leading edge of the He River first terrace. This curved river section has exposed sand and gravel on He Riverbed and shoals widely distributed in the upstream riverbed. Jiangbei dike in Babu District is located in the first terrace on the left bank of He River, with a bank base from He River Bridge to Guangming Bridge mostly comprising of farmland and dry land and the dike slope of bamboo revetment. He River section from Guangming Bridge to Babu Bridge is located in old urban area, with densely populated residential buildings and houses on both sides. and the existing dike slope is consisted of masonry retaining wall and bamboo revetment. He River section between Babu Bridge and Hezhou Bridge is new urban area, with an undulating terrain mostly covered by farmland and dry land. 4.3.2 Status Quo of Terrestrial Ecology Hezhou Municipality is located to the north of Tropic of Cancer and belongs to the subtropical monsoon climate zone. The area for evaluation is located in the urban area, where, due to long history of urban development, the primary ecological environment has been severely damaged, with no native vegetation and the existing vegetation being secondary natural vegetation or artificial vegetation. The natural - 98 - vegetation is divided into warm evergreen coniferous forest, limestone mountain deciduous broadleaf shrub and warm and hot grass, with majority of the vegetation warm evergreen coniferous forest and limestone mountain deciduous broadleaf shrub, and warm and hot grass as minor vegetation. Artificial vegetation consists of evergreen economic forest, paddy field and dry land, with mostly paddy field and dry land. The regional ecology system is mainly an agricultural ecosystem and forestry ecosystem and the quality of terrestrial ecology is average. Currently the majority of the tree species in the project evaluation area are common greening and landscaping plants such as bamboo and willow, etc., as well as crops. There are a small number of hydrophilic birds in the area. 4.3.3 Status Quo of Aquatic Ecology Here described as follows is the analysis and evaluation of the status quo of aquatic ecology in the He River Watershed introduced in the Report on Post Evaluation of the Ecological Impacts of Abrupt Environmental Incidents in He River (July 2013): 1. Phytoplankton In July 2013, a total of 40 Phytoplankton was monitored in He River, including 4 species of Cyanophyta, 1 Cryptophyta, 1 Euglenophyta, 1 Pyrrophyta, 10 species of Bacillariophyta and 23 species of Chlorophyta, which accounts for 10%, 2.5%, 2.5%, 2.5%, 25% and 57.5% of the total species, respectively, with Chlorophyta the highest proportion and Bacillariophyta the second highest. 2. Cell Density of Phytoplankton The total density of algae cells in He River Watershed is in the range of 5.54×105 ~ 1.16×107cells/L, Guishi reservoir has the highest density of algae cells. In all river sections in He River Watershed, Cyanophyta, Bacillariophyta and Chlorophyta have relatively high cell density; however, different species has different distributions at different monitoring sites. 3. Phytoplankton-based Water Quality Evaluation of He River Monitoring results at three monitoring sites at Guishi reservoir, the confluence of He River and Mawei River, and under Xindu bridge within the evaluation area show that the Shannon - wiener diversity indexes (H’) are all slightly lower than 3.0. According to the Phytoplankton biological diversity index, the aquatic ecological environment of He River Watershed is good. 4. Fishes The major economic fish species in He River Watershed are Crucian, Grass Carp, Sharpbelly, Southern quasi sharpbelly, Black Amur Bream, Catfish, Yellow catfish, etc., which are common in Guangxi and Guangdong Provinces, they are the major economic fish species. The major fish species for cage culture in this river section are Siniperca scherzeri, Spinibarbus denticulatus, Grass Carp and Yellow Catfish, etc. According to different living water layer for different fish species, the fish ecological groups of He River water system can be divided into following groups: Mid-upper layer group: Sharpbelly, Siniperca scherzeri, Rhodeus lighti, etc., these fish species are mainly living in the mid-upper layer of the stagnant water body during the non-winter season, often with the regularity of cluster activities. Mid-lower layer group: most of species under Carp, Crucian, Siluridae, Bagridae and - 99 - Xenocypris argentea Gunther and Leuciscinae. 5. “Spawning Grounds� Investigations of Fishes in the Project Watershed It has been observed through interviews with specialists in local fishery authority and site investigations that, since the water flow in the entire He River Watershed (Fujiang River to Yuhemianshi) is relatively gentle and slow, the annual net flow rate has an uneven distribution; due to relatively high-intensity development of this River Watershed, a number of large dams are built during the construction of hydropower stations, blocking the pass ways for fishes and their habitats; with the biological characteristics of He River fishes taken into account, there is no centralized large spawning ground in He River (Fujiang River to Yuhemianshi) basin, no spawning ground for large fish, and no spawning ground for fish that lays floating eggs such as grass carp, silver carp and bighead fish, and no small spawning grounds for fish that lays sticky eggs such as carp, crucian, catfish, etc. The overwintering ground for river fish is often in deep water. He River (Fujiang River to Yuhemianshi) is located in subtropical area, with relatively short low-temperature periods in winter. With the relatively shallow water depth and the interruption by large dams, He River has no overwintering ground for river fishes. The fish feeding ground is normally located where there is abundant food, He River (He Jiang River to Yuhemianshi) has dense population on both banks and rich aquatic-plants in midstream and upstream basin, providing abundant food for fishes. 4.3.4 Status Quo of Agricultural Ecology The major crops in the evaluation area include the common crops of rice, corn, Sanhua plum, water chestnut, tobacco and vegetables, etc. and there is no local special species. Rice is double cropping rice, part of which is used as dry crops and vegetables in winter season. 4.3.5 Status Quo of Soil Erosion According to Notice by GZAR People’s Government on the Zoning for Key Soil Erosion Prevention and Improvement Zones in GZAR (Guizhengfa〔2017〕No.5), Hezhou Municipality Babu District is one of the Key Soil Erosion Prevention and Improvement Zones while Pinggui District is not. The project area belongs to the southern red soil hilly area as a part of the Class II zones in the National Soil Erosion Classification Plan and the southeastern Gui low mountain area defined in the GZAR Soil and Water Preservation Planning and Zoning Program with a soil loss tolerance of 500t/(km 2·a). Investigation in the status quo in the project area shows that the type of soil erosion in the project area is mainly water erosion, in the form of surface scours and gully scours and the project area belongs to the slight-to-mild soil erosion area. The average soil erosion modulus background value in the project area is approximately 317t /(km 2 ·a). - 100 - 4.4 Status Quo Investigation and Evaluation of Environment Quality 4.4.1 Status Quo Investigation and Evaluation of Ambient Air Environment Quality According to the Technical Guidelines for Environmental Impact Assessment Atmospheric Environment (HJ2.2-2008), the project area mainly involves the urban area in Hezhou Municipality and its adjacent villages. Therefore, the conventional monitoring data from automatic monitoring stations in the city area is used for the analysis of the status quo of air environment quality in the project area. For the proposed WWTP, NH3, H2S, and odor concentration are added as the criteria of monitoring. Since the Project involves sediment dredging in He River course, which will cause odor emission, odor is sampled and analyzed based on the distribution of sensitive sites. The layout of the monitoring sites is shown in Figure 4-2. I. Ambient Air Monitoring of SO2, NO2, and PM10 Environmental Quality Weekly Report for Hezhou Municipality in Year 2017 (Issue No.24) published by Hezhou Municipal EPB is quoted for ambient air quality evaluation of the urban areas of Hezhou Municipality conducted under the Project. Details of the monitoring data are included in Annex Table 1. Analysis of the weekly monitoring data indicates that the monitoring factor AQI index at various monitoring sites in Hezhou urban area is generally in the range of 27~65, indicating that the air quality is good and the air quality at all monitoring sites meets Class II standard specified in Ambient Air Quality Standard (GB3095-2012). II. NH3 and H2S Monitoring 1. Location of Monitoring sites A11 Shatian WWTP site, A12 proposed Jiangnan WWTP site as detailed in Figure 4.2-2. 2. Monitoring Time and Frequency Sampling was carried out continuously for 2 days from May 16 th 2017 to May 17th 2017 to monitor the 1-hour average level, with each sampling lasting for 45 minutes. 3. Monitoring and Analysis Methodology The status quo monitoring and analysis of ambient air quality in the Project is conducted according to Methods for Monitoring and Analysis of Ambient Air and Exhaust Gas 4th Edition (Ministry of Environmental Protection, 2003). Details of the analytical methods are listed in Table 4-3. - 101 - - 102 - Table 4-3: Monitoring and Analysis Methods and Detection Limits Monitoring S/N Analytical Methods Detection Limits Items Methylene blue spectrophotometric method Methods for Monitoring and Analysis of 1 H2S Ambient Air and Exhausted Gas 4th 0.001mg/m³ Edition Ministry of Environmental Protection, 2003 Environmental air ammonia 0.01mg/m3 determination 2 NH3 (10ml of absorption liquid, 45L Nessler's reagent colorimetric method HJ 533-2009 of sampling volume) 4. Evaluation Methods Calculating the percentage of maximum mass concentration value versus corresponding standard mass concentration limits at various sampling time: P=Ci/Si Where: Pi—the percentage of maximum mass concentration value versus corresponding standard mass concentration limits; Ci—the measured pollutant concentration, mg/m3; Si—the evaluated pollutant concentration, mg/m3. Note: for undetected items, the standard limits are calculated using 50% of the detected value. 5. Evaluation Standards H2S and NH3 are evaluated according to Hygienic Standards for the Design of Industrial Enterprises(TJ36-79). 6. Analysis of Monitoring and Evaluation Results The monitoring results are listed in Annex Table 2. According to the data listed in annex table, the monitoring data of H2S and NH3 at proposed WWTP site complies with the momentary maximum allowable concentration (TJ36-79) in Hygienic Standards for the Design of Industrial Enterprises for residential area. - 103 - III. Status Quo Monitoring of Odor Emission Table 4-4 Locations of Odor Concentration Monitoring Sites Monitoring Watershed Monitoring Location Factor A1 South side of He River dredging section, at Qiangdong Road close to riverside residential areas He River A2 South side of He River dredging section, at Nanshan Road close to riverside residential areas Huangtian A3 Huangtian Branch Canal dredging section, at Sanqi Branch Canal bridge close to riverside residential areas Guposhan A4 Guposhan Drainage Canal dredging section, at Drainage Shizigang close to riverside residential areas Canal Taoyuan A5 Taoyuan Drainage Canal dredging section, at Xindu Drainage Village close to riverside residential areas Odor Canal A6 Huangansi Drainage Canal dredging section, at Fumin Concentration Huangansi Rd close to riverside residential areas Drainage A7 Huangansi Drainage Canal dredging section, at Xiyue Canal St. close to riverside residential areas A8 Shizigang Drainage Canal dredging section, at Zhushan Rd. close to riverside residential areas Shizigang A9 Shizigang Drainage Canal dredging section, at Wangjiao Drainage Rd. close to riverside residential areas Canal A10 Shizigang Drainage Canal dredging section, at Yinhe St. close to riverside residential areas He River A11 at proposed Jiangnan WWTP site 3. Monitoring Time and Frequency Monitoring was carried out for 1 day on May 16 th, 2017, with 4 sampling per day at each monitoring site. 4. Monitoring and Analytical Methods The status quo of ambient air quality in the Project was monitored and analyzed according to Methods for Monitoring and Analysis of Ambient Air and Exhausted Gas 4th Edition (by Ministry of Environmental Protection, 2003). Details of the analytical methods are listed in Table 4-5. Table 4-5 Detection and Analytical Methods for Odor Concentration No. Monitoring Item Analytical Method Detection Limits 1 Odor Concentration Triangle Odor Bag Method 10(No Unit) 5. Evaluation Standard Since there is no environment quality standard for odor, the monitoring value for odor emission is evaluated based on Integrated Air Pollutant Emission Standard (GB16297-1996)Table 1 secondary standards. 6. Evaluation of Status Quo Monitoring Results - 104 - Monitoring results are listed in Appendix Table 3. Reference is made to the odor concentration limits specified in Class II standard indicated in Table 1 in the Integrated Air Pollutant Emission Standard (GB16297-1996). Results of this monitoring show that odor emission at Xiyue St. close to riverside residential areas along A7 Huangansi Drainage Canal dredging section and at Zhushan Rd. close to riverside residential areas along A8 Shizigang Drainage Canal dredging section exceeds the Class II standard indicated in Table 1 in the Integrated Air Pollutant Emission Standard (GB16297-1996) while the other monitoring sites meet the above standard. According to site investigation, due to historical reasons, no sewer pipe network was constructed at Huangansi and Shizigang Drainage Canal sections and domestic wastewater from residents along He River was directly discharged into He River course without any treatment, causing deterioration of the water quality and odor emission, and relatively high odor concentration in He Riverside residential areas. 4.4.2. Status Quo Investigation and Evaluation of Water Environment Quality According to the Environmental Impact Evaluation Technology Guidelines for Surface Water Environment (HJ2.3-1993), with the terrain features along He River taken into consideration, the Project involves the water systems of He River, Mawei River, Changlong River, Lining River, Shizigang River, East Trunk Canal, Dongwu Branch Canal, Huangansi Drainage Canal and Shizigang Drainage Canal. Status quo monitoring of water environment of the surface water in the region was conducted in July 2016 and May 2017 by a qualified monitoring unit authorized by the project owner while the monitoring data and results of Babu District EPB for key rivers in Babu District are quoted for the status quo of water quality in Mawei River. Details of regional surface water monitoring are described as follows: 1. Location of Monitoring sites and Monitoring Frequency Location of the monitoring sites is shown in Figure 4-3. - 105 - - 106 - Table 4-6 Location of Surface Water Monitoring Sites in the Project Monitored No. Monitoring Location Monitoring Time Items 1 W1 Lining River start point section W2 Lining River and Huangtian Branch Canal 2 confluence point front section 3 W3 Changlong River start point section 4 W4 Changlong River Tianbaotang section W5 Huangtian Branch Canal start point 5 22 items section including pH, W6 Huangtian Branch Canal Anshan village DO, CODMn, 6 section BOD5, COD, W7 Huangtian Branch Canal Shizigang TSS, NH3-N, 7 TP, Petroleum, section 2016.6.6~2016.6.8 Volatile W8 Huangansi River Jianshezhong Rd. Phenol, 8 Continuous sampling section Cyanide, for 3 days, 1 9 W9 Shizigang River start point section Anionic sampling each day surfactant, 10 W10 Shizigang River Wangjiang section Sulfide, 11 W11 Taoyuan River Dawodu section Copper, Zinc, Lead, W12 Guishidongliu Branch Canal Cadmium, 12 Nanshetang section Arsenic, 13 W13 Guishidong Trunk Canal section Chromium 6, Mercury. W14 Guishidongwu Branch Canal start point 14 section 15 W15 He River Jigong Island section 16 W16 He River Babu Bridge section 17 W17 He River Lingfeng Bridge section W18 Mawei River and He River confluence 2017.3.21, 2017.6.27 18 front section 1 sampling each day 2. Monitoring Methods Sampling methods are adopted from the Technical Specifications on Environment Monitoring published by Ministry of Environmental Protection. The water quality analysis methods are adopted from Surface Water Environmental Quality Standard (GB3838-2002)Table 4. Details are listed in Table 4-7. - 107 - Table 4-7 Analysis Methods for Basic Items of Surface Water Environmental Quality Standard Detection Source of No. Monitoring Items Analysis Methods Limits(mg/L) methods 1 pH Glass electrode method 0.01pH GB/T6920-1986 2 DO Iodometric method 0.2 GB/T7489-1987 3 TSS Gravimetric method 4 GB11901-1989 Determination of 4 CODMn 0.5 GB/T11892-1989 permanganate index Dilution and inoculation 5 BOD5 0.5 HJ505-2009 method Methods for Fast confined catalytic Monitoring and digestion-spectrophotomete 6 COD 5 Analysis of Water r (including and Wastewater spectrophotometer) (4th Edition) Nessler’s reagents 7 NH3-N 0.025 HJ535-2009 spectrophotometer method Ammonium molybdate 8 TP 0.01 GB/T11893-1989 spectrophotometric method Alkaline persulphate 9 TN digestion UV 0.05 HJ636-2012 spectrophotometer Infrared spectrophotometric 10 Petroleum 0.01 HJ637-2012 method 4-AAP spectrophotometric 11 Volatile Phenol 0.0003 HJ503-2009 method 12 Cyanide Spectrophotometric method 0.004 HJ484-2009 Ethylene blue 13 Anionic surfactant 0.05 GB7494-1987 spectrophotometric method Ethylene blue 14 Sulfide 0.005 GB/T16489-1996 spectrophotometric method 1,5-diphenylcarbazide 15 Chromium 6 0.004 GB/T7467-1987 spectrophotometric method 16 Copper(Cu) 0.00008 17 Cadmium(Cd) Inductively coupled plasma 0.00005 HJ700-2014 mass spectrometry 18 Lead(Pb) 0.00009 19 Zinc (Zn) 0.00067 20 Arsenic (As) Atomic fluorescence 0.0002 HJ694-2014 21 Mercury spectrometry 0.00001 - 108 - 3. Evaluation Standard Water quality in He River and Mawei River shall meet Class III standard specified in the Surface Water Environmental Quality Standard (GB3838-2002). All rest of the flood discharge rivers and rivers within the city shall meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002), which means W15~W19 shall meet Class III surface water standard, W1~W14 shall meet Class IV surface water standard. 4. Evaluation Methods Single factor evaluation method is used for evaluation. The formula is: Sij=Cij/Csi Where: Sij——the standard index of pollutant i at monitoring point j, standard index larger than 1 indicates water is polluted by pollutant I; Cij——concentration of pollutant i at monitoring point j; Csi——surface water quality standard of water quality parameter i. The standard index of DO is: Where: SDOj——water quality index of DO; DOf——saturated DO level, mg/L; DOs——DO standard,mg/L; DOj——measured level of DO,mg/L; DOf=468/(31.6+T); T——water temperature,℃。 Water quality index of pH is: Where: SpH,j——pH water quality index; pHj——measured pH; - 109 - pHsu——pH upper limit of surface water quality standard; pHsd——pH bottom limit of surface water quality standard; Standard index of water quality parameter greater than 1 indicates that the water quality parameter exceeds the limits specified in the water quality standard; a greater standard index of water quality parameter indicates a more severe noncompliance with the water quality standard. 5. Monitoring Results and Evaluation Conclusion Monitoring results for surface water are listed in Table 4 as attached while the evaluation results are described in Table 5 (1) Analysis of water quality monitoring results for urban canal Lining River: The water quality at W1 Lining River start point section and W2 Lining River and Huangtian Branch Canal confluence point front section meets Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) and the water quality in Lining River meets Class IV quality standard for surface water. Changlong River: All the monitoring items at W3 Changlong River start point section meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002); NH3-N and TP at W4 Changlong River Tianbaotang section exceed Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002); NH3-N exceeds the standard by a factor of 0.01 and TP by a factor of 0.5. Meanwhile, the TP at W4 Changlong River Tianbaotang section exceeds Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) while the water quality at Changlong River is worse than Class V. Huangtian Branch Canal: All the monitoring items at W5 Huangtian Branch Canal start point section meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002); NH3-N and TP at W6 Huangtian Branch Canal Anshan village section exceed Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002), NH3-N exceeds the standard by a factor of 3.31 and TP exceeds the standard by a factor of 0.83. NH3-N at W7 Huangtian Branch Canal Shizigang section exceeds Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) by a factor of 0.89. Meanwhile, NH3-N and TP at W6 monitoring section, NH3-N at W7 monitoring section exceed Class V standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) while the water quality in Huangtian Branch Canal is worse than Class V. Huangansi River: NH3-N and TP at W8 Huangansi River Jianshezhong Rd. section exceed Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002), with NH3-N exceeding the standard by a factor of 0.9 multiplier and TP by a factor of 0.07. Meanwhile, NH3-N at monitoring section exceeds Class V standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) and the water quality in Huangansi River is worse than Class V standard. - 110 - Shizigang River: All the monitoring items at W9 Shizigang River start point section meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002); NH3-N and TP at W10 Shizigang River Wangjiao section exceed Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002), with NH3-N exceeding the standard by a factor of 3.85 and TP by a factor of 0.47. Meanwhile, NH3-N and TP at W10 monitoring section exceed Class V standard specified in the Surface Water Environmental Quality Standard (GB3838-2002)and the water quality in Shizigang River is worse than Class V, with water pollution in the downstream section worse than the upstream. Guishidong Trunk Canal: All the monitoring items at W13 cross section of Guishidong Trunk Canal meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) and the water quality at Guishidong Trunk Canal meets Class IV standard. East Trunk Canal No.5 Branch Canal: All the monitoring items at W14 Guishidongwu Branch Canal start point section meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) and the water quality at East Trunk Canal meet Class IV standard. In summary, water quality in Lining River, Guishidong Trunk Canal and East Trunk Canal No.5 Branch Canal meet Class IV standard specified in the Surface Water Environmental Quality Standard (GB3838-2002); water quality in Changlong River, Huangtian Branch Canal, Huangansi River and Shizigang River is worse than Class V, indicating that these rivers are severely polluted mainly for the following reasons: The water systems of Changlong River, Huangtian Branch Canal, Huangansi Drainage Canal and Shizigang Drainage Canal do not only perform the function of flood discharge, they also accept domestic wastewater from areas along He Rivers as drainage channels for industrial and domestic wastewater. The received domestic sewage has exceeded the self-purification capacity of He Rivers, causing deteriorated water quality in the urban canal water system. (2)Analysis of water quality monitoring results of the main watercourse of He River and the tributary of Mawei River He River: All the monitoring items at W15 He River Jigongzhou section, W16 He River Babu Bridge section and W17 He River Lingfeng Bridge section meet Class III standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) , indicating that the water quality in He River meet Class III standard. Mawei River: All the monitoring items at W18 Mawei River and He River confluence front section meet Class III standard specified in the Surface Water Environmental Quality Standard (GB3838-2002) , indicating that the water quality in Mawei River meet Class III standard. In summary, water quality in He River and Mawei River meets Class III standard specified in the Surface Water Environmental Quality Standard (GB3838-2002). - 111 - 4.4.3 Status quo investigation and evaluation of acoustic environment quality 1. Layout of monitoring sites According to Technical Guidelines for Noise Impact Assessment (HJ 2.4-2009). monitoring was conducted at representative environmentally sensitive sites along the Project. Details of the locations of the monitoring sites are listed in Table 4-8 and Figure 4-4. Table 4-8 Noise Monitoring sites No. Name of Monitoring Points Description of Surrounding Environment 1 N1 Jigongzhou Villages 2 N2 Tianchong Village Villages 3 N3 Sanjia Elementary School Villages Located in urban area adjacent to 4 N4 Huzhou College National Highway G207 5 N5 Sanjia Village Villages, adjacent to Fanglin Road N6 Hezhou Municipality 6 Adjacent to Wenyuan Road Experimental Elementary School Urban residents, adjacent to Fanglin 7 N7 Wenyuanhuadu Road 8 N8 Xiyue Street Old urban residential area N9 Hezhou Municipality 9 Adjacent to Jiangbeizhong Road Transportation Bureau Xijie street residents committee (RC), 10 N10 Xiwan Elementary School surrounded by residents committee (RC) residents 11 N11 Lining Village Villages 12 N12 Changlong Village Villages Township residents, adjacent to 13 N13 Huangtian Township Guposhan Avenue N14 Pinggui No.3 Junior High 14 Adjacent to Guposhan Avenue School N15 Qianjin Road Elementary 15 Urban area, adjacent to Qianjin Road School N16 Babu District Experimental 16 Urban area, adjacent to Qianjinxi Road Elementary School N17 Hezhou Municipality People’s 17 Urban area, adjacent to Qianjinxi Road Hospital Suburban area, adjacent to Zhushan 18 N18 Anshan Village Road N19 Guangji Obstetrics and Urban area, adjacent to Guposhan 19 Gynecology hospital Avenue 20 N20 Technician Training School Urban area, adjacent to Anshanxi Road N21 Hezhou Municipality Chinese 21 Urban area, adjacent to Longshan Road Medicine Hospital 22 N22 Baimian Mountain Village 23 N23 Dawodu Village 2. Monitoring Methods and Frequency Noise measurement is carried out according to Environmental Quality Standard for Noise (GB3096-2008) in a weather condition with no rain, no snow and no thunder storm and a wind speed of less than 5m/s. Monitoring time was June 7th 2016~June 8th 2016, once each in day and at night. The monitoring hours are 6:00~22:00 in day - 112 - time and 22:00~6:00 in night time. 3. Evaluation Methods Monitoring sites in residential area on both sides of flood discharge river in the urban area of Babu District are located on one side of the main street and the applicable standard for the noise level at these monitoring sites is Class 4a in the Environmental Quality Standard for Noise (GB3096-2008). The local acoustic environment for hospitals, government offices and residential areas along He River shall meet Class 2 standard specified in the Environmental Quality Standard for Noise (GB3096-2008). 4. Conclusion of Noise Monitoring and Evaluation Results of noise monitoring are listed in Table 6 as attached. Noise in day and night time at all sensitive sites along the Project meets the respective standard requirements in the Environmental Quality Standard for Noise (GB3096-2008), indicating that the project area is in a generally good condition in terms of acoustic environment quality. - 113 - - 114 - 4.4.4 Status Quo Investigation and Evaluation of Soil Environment Quality 1. Layout of monitoring sites Based on the project characteristics and with the length and scope of impact of river dredging section taken into account, sites of investigation of the soil background value are mainly distributed along the dredging section of the main watercourse of He River with a total of 8 soil monitoring sites as listed in Table 4-9 and Figure 4-5. Table 4-9 Soil Monitoring sites Sampling Monitoring sites Location Soil Characteristics Depth S21 500m upstream of Lingfeng 20cm Gray brown, loam Bridge (right bank) S22 1000m upstream of Lingfeng 20cm Brown, loam Bridge (right bank) S23-1 50m upstream of Fanglin 20cm Yellow brown, loam Hydropower Station(left bank) S23-2 50m upstream of Fanglin 20cm Brown, loam Hydropower Station(right bank) S24-1 1000m upstream of Fanglin 20cm Brown, loam Hydropower Station(left bank) S24-2 1000m upstream of Fanglin 20cm Brown, loam Hydropower Station(right bank) S25-1 2000m upstream of Fanglin 20cm Brown, loam Hydropower Station(left bank) S25-2 2000m upstream of Fanglin 20cm Brown, loam Hydropower Station(right bank) - 115 - - 116 - (2) Monitoring Items Monitoring items: pH, Copper, Zinc, Lead, Chromium, Cadmium, Mercury and Arsenic. (3) Monitoring and Analysis Methods Soil monitoring and analysis is conducted according to the relevant stipulations in the Technical Specification of Soil Analysis and the Monitoring and Analysis Methods of Soil Environment Quality. The soil analysis methods and detection limits are listed in Table 4-10. Table 4-10 Soil Monitoring Items and Analysis Methods Detection Type Item Analysis Methods and Source Limits pH Determination of pH in soil, NY/T 1377-2007 0.1 pH Determination of total mercury, arsenic and lead in soil, Arsenic 0.01mg/kg Atomic Fluorometry GB/T 22105.2-2008 Determination of total mercury, arsenic and lead in soil, Mercury 0.002mg/kg Atomic Fluorometry GB/T 22105.2-2008 Determination of lead and cadmium in soil, Graphite Cadmium furnace atomic absorption spectrophotometer, GB/T 0.01mg/kg 17141-1997 Substrate, Soil Determination of lead and cadmium in soil, Graphite Lead furnace atomic absorption spectrophotometer, GB/T 0.1mg/kg 17141-1997 Determination of copper and zinc in soil, Flame atomic Copper 1mg/kg absorption spectrophotometer, GB/T 17138-1997 Determination of copper and zinc in soil, Flame atomic Zinc 0.5mg/kg absorption spectrophotometer, GB/T 17138-1997 Total Determination of total chromium in soil, Flame atomic 5mg/kg Chromium absorption spectrophotometer, HJ491-2009 (4) Monitoring time and frequency One sampling was conducted in the period from September 15th to September 17th, 2017. (5) Evaluation Methods and Evaluation Standards The evaluation is conducted according to Class II standard specified in the Environmental Quality Standard for Soils (GB15618-1995) using the single factor standard index method. Pi = C i / S i Formula: Where: Pi——mass index of soil pollutant, Pi>1 means soil is polluted; Ci——content of soil pollutant; - 117 - Si——evaluation standard. (6) Monitoring results and evaluation Monitoring and analysis results are listed in Table 7. According to monitoring results, arsenic detected at S25 2000m upstream of Fanglin Hydropower Station (left bank) exceeds Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) by a factor of 1.5; arsenic and mercury detected in soil on the right bank exceeds Class III standard, with arsenic exceeding the standard by a factor of 1.63 and mercury by a factor of 1.9. Cadmium, arsenic and mercury detected at S24 1000m upstream of Fanglin Hydropower Station (left bank) exceeds Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) respectively by a factor of 0.29, 0.31 and 0.10. Arsenic in soil on the right bank exceeds Class III standard by a factor of 0.45. Soil at S23 50m upstream of Fanglin Hydropower Station (left bank) meet Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) ; Mercury at right bank exceeds Class III standard by a factor of 0.15. Cadmium and arsenic at S22 300m upstream of Lingfeng Bridge (right bank) exceeded Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995), respectively by a factor of 0.06 and 0.05.. Soil at S21 500m downstream of Lingfeng Bridge meets Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) . In summary, except the monitoring results of soil monitoring sites at S21 500m downstream of Lingfeng Bridge (right bank) and S23 50m upstream of Fanglin Hydropower Station (left bank), the soil quality detected at the monitoring sites at S25 2000m upstream of Fanglin Hydropower Station (left and right banks), S24 1000m upstream of Fanglin Hydropower Station (left and right banks) , S23 50m upstream of Fanglin Hydropower Station (left bank) , S22 1000m upstream of Lingfeng Bridge (right bank) does not meet Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) and the noncompliant monitoring items are Arsenic, Mercury and Cadmium. Cause analysis: According to Investigations of Background Values of a number of Metal Elements in the Agricultural Soil Environment in the Northeastern Parts of GZAR published by Guangzhou Agricultural Environment Monitoring Station, the background values of copper, zinc, lead, cadmium and nickel are the highest in soil developed from limestone substrate and the background values of arsenic, mercury and cadmium are the highest in soil developed from quaternary red clay. Soil in Hezhou Municipality is mainly developed from quaternary red clay, which belongs to the karsts landform and limestone substrate is distributed in a certain proportion. Therefore, the background value of heavy metals is relatively high. According to 2014 Report on Soil Environment Quality Monitoring in Areas around Centralized Drinking Water Sources in Hezhou Municipality, the soil monitoring results at Hezhou Babu water intake point (the water intake located at 600m upstream of Guangming Bridge in Hezhou Urban area has already been cancelled) indicate that arsenic exceeds the standard by a factor of 1.70-7.30, implying that the background values of heavy metal factors in soil in the project area in Hezhou are relatively - 118 - high. The results of this monitoring process further demonstrate that the background values of arsenic, cadmium and mercury in soil in the project area are high. 4.4.5 Investigation and Evaluation for Existing Condition of Sediment Environmental Quality 1. Layout of Monitoring sites Based on the project characteristics and the length and scope of impact of He River dredging section, totally 15 sediment monitoring sites are distributed at upstream, midstream and downstream of He River dredging section as detailed in Table 4-10 and Figure 4-6. Table 4-10 Layout of Sites and Frequency of Sampling for Sediment Monitoring Monitoring methods and Watershed Monitored Section monitoring items S1 100m downstream of He River and Huangansi River confluence He River S2 Lingfeng Bridge S3 100m downstream of He River and Shizigang River confluence East Trunk S4 East Trunk Canal dredging section Canal S5 Dongwu Branch Canal dredging section Dongwu Branch Canal S6 downstream of Dongwu Branch Canal dredging section Based on Dongliu Branch sampling and S7 Dongliu Branch Canal dredging section According to Canal analysis Identification Huangtian methods in S8 Huangtian Branch Canal dredging section Standards for Branch Canal Environmental Hazardous Quality Standard Wastes- Guposhan for Soils S9 Guposhan Drainage Canal dredging section Screening Test for Drainage Canal (GB15618-1995) Leaching Toxicity , the monitoring Taoyuan (GB5085.3-2007), S10 Taoyuan Drainage Canal dredging section items include Drainage Canal the monitoring pH, copper, zinc, items include lead, S11 upstream of Huangansi Drainage Canal lead, total cadmium, dredging section chromium, Huangansi mercury, arsenic cadmium, Drainage Canal S12 downstream of Huangansi Drainage Canal and chromium 6. mercury and dredging section arsenic S13 upstream of Shizigang Drainage Canal dredging section Shizigang S14 midstream of Shizigang Drainage Canal Drainage Canal dredging section S15 downstream of Shizigang Drainage Canal dredging section S16 500m downstream of Lingfeng Bridge (right bank) He River S17 300m upstream of Lingfeng Bridge (left and right bank) - 119 - Table 4-10 Layout of Sites and Frequency of Sampling for Sediment Monitoring Monitoring methods and Watershed Monitored Section monitoring items S18 50m upstream of Fanglin Hydropower Station (left and right bank) S19 1000m upstream of Fanglin Hydropower Station (left and right bank) S20 2000m upstream of Fanglin Hydropower Station (left and right bank) Note: During actual sampling, sediments detected at S18 upstream of Fanglin Hydropower Station (right bank) and S19 1000m upstream of Fanglin Hydropower Station (right bank) exceed 1m in depth and, therefore, vertical layered sampling was conducted at these 2 sections. 2. Monitoring Time and Frequency Sampling time for S1~S15 is May 16th, 2017. S16~S20 are additional monitoring and the sampling time is September 15 to September 17, 2017. One sampling was conducted at each sampling point. 3. Monitoring and Analysis Methods The same analysis methods and detection limits for soil monitoring are adopted for sediment as detailed in Table 4-10. - 120 - - 121 - 4. Evaluation Methods and Evaluation Standard Single factor standard index method is used for the evaluation, Pi = C i / S i Formula: Where: Pi —— mass index of soil pollutant, Pi>1 means soil is polluted; Ci —— content of soil pollutant; Si —— evaluation standard. Environmental Quality Standard for Soils (GB15618-1995) Class III standard is used for evaluation standards. 5. Monitoring Results and Evaluation Monitoring results are listed in Table 8. Based on sediment monitoring data, the sediment monitoring results at river dredging sections is analyzed as follows: Dongwu Branch Canal dredging section: The monitoring item of arsenic at S4 upstream and downstream of Dongwu Branch Canal dredging section exceeds Class III standard by a factor of 0.435 at the upstream section and 0.863 at downstream section. Huangtian Branch Canal: The monitoring items of cadmium and arsenic at S7 Huangtian Branch Canal dredging section exceed Class III standard requirement, with cadmium exceeding the standard by a factor of 1.38 and arsenic by a factor of 0.063. Guposhan Drainage Canal: Te monitoring items of cadmium and arsenic at S9 Guposhan Drainage Canal dredging section exceed Class III standard, with cadmium exceeding the standard by a factor of 0.91 and arsenic by a factor of 0.6. Huangansi Drainage Canal: The monitoring items of zinc, cadmium and arsenic at Huangansi Drainage Canal dredging section exceed Class III standard. At S11 upstream of Huangansi Drainage Canal dredging section, zinc exceeds the standard by a factor of 0.19, cadmium by a factor of 1.93, arsenic by a factor of 0.41 at S11 while at S12 downstream of Huangansi Drainage Canal dredging section, zinc exceeds the standard by a factor of 0.09, cadmium by a factor of 1.73 and arsenic 0.555. Shizigang Drainage Canal: The monitoring item of arsenic at S13 upstream of Shizigang Drainage Canal dredging section exceeds Class III standard by a factor of 0.275; the monitoring items of zinc, cadmium and arsenic at S14 midstream of Shizigang Drainage Canal dredging section exceed Class III standard respectively by a factor of 0.14, 1.12 and 1.135. At S15 downstream of Shizigang Drainage Canal dredging section, the monitoring items of zinc, cadmium, arsenic and mercury exceed Class III standard, respectively by a factor of 0.27, 1.6, 1.14 and 0.48. - 122 - He River dredging section: The monitoring item of arsenic at S1 100m downstream of Huangansi River confluence monitoring section exceeds Class III standard by a factor of 0.45; cadmium and arsenic at S2 Lingfeng Bridge He River section monitoring section exceed the standard respectively by a factor of 0.25 and 1.39; the monitoring item of arsenic exceeds the standard at S3 downstream of He River and Shizigang River confluence by a factor of 1.95. East Trunk Canal dredging section: The monitoring item of arsenic at S4 East Trunk Canal dredging section exceeds the Class III standard by a factor of 1.875. Analysis of supplementary monitoring results is as follows: Lingfeng Bridge dredging section: All the monitoring items at S16 500m downstream of Lingfeng Bridge (right bank) meet Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) ; All the monitoring items at S17 300m upstream of Lingfeng Bridge (left bank) meet Class III standard; the monitoring items of cadmium and arsenic at S17 300m upstream of Lingfeng Bridge (right bank) exceeds Class III standard by a factor of 0.14 and 0.25 respectively. Fanglin Hydropower Station dredging section: The monitoring items of cadmium and arsenic at S18 50m upstream of Fanglin Hydropower Station exceed Class III standard respectively by a factor of 0.08 and 0.63; layered sampling was conducted for the sediment at S18 50m upstream of Fanglin Hydropower Station (right side) and the monitoring items of cadmium and arsenic exceed Class III standard by a factor of 0.42 and 0.463 respectively. Cadmium in lower layer sediment exceeds the standard by a factor of 1.24. The monitoring item of arsenic at S19 1000m upstream of Fanglin Hydropower Station (left bank) exceeds Class III standard by a factor of 0.13; layered sampling was conducted for the sediment at S18 1000m upstream of Fanglin Hydropower Station (right side) and the monitoring items of cadmium and arsenic exceed Class III standard respectively by a factor of 1.32 and 1.205, with cadmium in lower layer sediment exceeding the standard by a factor of 0.79 and arsenic 0.88. The monitoring items of cadmium and arsenic at S20 2000m upstream of Fanglin Hydropower Station (left bank) exceed Class III standard respectively by a factor of 0.91 and 0.905; the monitoring items of cadmium and arsenic at S20 2000m upstream of Fanglin Hydropower Station (right bank) exceed Class III standard requirement respectively by a factor of 0.98 and 1.295. In summary, the monitoring items of zinc, cadmium, arsenic and mercury at He River sediment monitoring sites in the Project are found unexceptionally exceeding Class III standard specified in the Environmental Quality Standard for Soils (GB15618-1995) . Standard noncompliance for heavy metals is relatively severe at Shizigang Drainage Canal, Huangansi Drainage Canal and upstream of Fanglin Hydropower Station dredging section. - 123 - Analysis of causes for standard noncompliance: (1) According to the analysis in section 4.4.4, the background values of arsenic, cadmium and mercury in the soil in the project area are relatively high. (2) Hezhou Municipality has rich mineral resources. With more than 60 proven mineral resources in its territory, Hezhou is known as the largest white marble mine in central and southern China and ranks the first in terms of the reserves of tungsten, tin, rare earth, veneer granite, and silicon stone in GZAR. Hezhou has a long history of mining and long-term scattered and small private mines have been the cause of direct discharge of untreated wastewater from mine pit, mining selection, metallurgical refinery and tailings into He River course. As a result of lasting accumulation of heavy metals and discharge into He River, heavy metal content in river sediment is found exceeding the standard. 6. Identification of Leaching Toxicity In order to identify the sediment leaching toxicity and determine if the sediment is hazardous, monitoring was carried out for the sediment leachate based on Identification Standards for Hazardous Wastes - Screening Test for Leaching Toxicity (GB5085.3-2007). The monitoring items include lead, cadmium, mercury, arsenic and Chromium 6. Monitoring results are listed in Table 9 as attached. According to monitoring data, Lead, Cadmium, Arsenic, Mercury, Chromium 6 in sediment leachate are all within the concentration limits for hazardous chemicals specified in Identification Standards for Hazardous Wastes (GB5085.3-2007), thus not belonging to hazardous waste, and can be disposed according to Standard for Pollution Control of Sites for Storage and Disposal of General Industrial Solid Wastes (GB18599-2001). 4.5 Pollution Sources in the Project Area Situated at midstream and downstream of He River, Hezhou Municipality has rich water resources, which is the strong support for its industrial and agricultural development. Along with the acceleration of urbanization, discharge of domestic wastewater is increasing each year. At river sections near the urban area, in dry season, large amount of domestic sewage is directly discharged into He River, forming a pollution belt along He River. The estuaries of Huangansi Drainage Canal and Shizigang Drainage Canal at the northern part of city are the largest discharge outlets in urban area while the inland rivers accept wastewater along the urban section of He Rivers and finally join into He River. 4.5.1 Investigation on pollution sources of He River and its tributaries According to site investigation and in association with the investigation materials on the existing condition of He River urban section pollution sources conducted by Hezhou Municipal EPB, there are the following pollution sources for the urban section - 124 - of He River. The section from Fanglin Hydropower Station to Xiadao Power Station has a total length of 11km and there are a total of 44 stormwater and wastewater discharge outlets along He River. 2 of these outlets are industrial wastewater discharge outlets, namely, the Ecological Industrial Park discharge outlet and Guidong Electronics industrial wastewater discharge outlet (the two enterprises have self-built wastewater treatment stations and the effluent meets Integrated Wastewater Discharge Standard Class I standard before discharge into He River); the other 42 discharge outlets are combined sewer outlets (one of which is a temporary domestic wastewater treatment facility effluent outlet for Jiangnan District, which mainly collects domestic sewage from Jiangnan District and treats wastewater to meet Class I standard specified in the Integrated Wastewater Discharge Standard before discharged into He River; the rest of the outlets are all for direct discharge of wastewater). The main discharge outlet into He River urban section are Shizigang Drainage Canal, Huangansi Drainage Canal and the effluent outlet of Hezhou Municipal WWTP, accounting for 51.9% of the total discharges. Due to large flow in He River, the natural treatment capacity is high and currently, the water quality in He River urban section still meet Class III standard for surface water quality. River Watershed of Mawei River is located in an agricultural farming area, with agricultural pollutants along He River flowing into He River with rainfall. Therefore, the NPS pollution is the main pollution source. Currently, land is undeveloped on both sides of He River and water quality in Mawei River meets Class III standard for surface water quality. 4.5.2 Water Quality Pollution is Severe in Inner Rivers According to Investigation Report on Black and Odorous Water Bodies in the Urban Area of Hezhou Municipality, He Rivers where black and odorous water bodies are found in Hezhou urban area are mainly the downstream section of the main watercourses of Shizigang Drainage Canal and Huangansi Drainage Canal as well as their tributaries on the east side. Due to historical reason, the control width of Shizigang and Huangansi Drainage Canals are relatively narrow within the project area and the flood control feature is difficult to achieve. In addition, there is no reserved regulation volume at the upstream sections and waterlogging can easily occur once there is a storm. Shizigang Drainage Canal is already channelized. Huangansi Drainage Canal is the largest pollutant discharge outlet and there a large number of residential buildings along He River in the urban area, with combined domestic wastewater and stormwater collected, conveyed and discharged in combined sewers into He River. The east tributaries join the main watercourse at Gong Bridge Health Clinic and enter the densely populated residential area. Domestic wastewater directly discharged from the residential areas along He River is the main pollution source. Meanwhile, there are extensive farmland and residential areas surrounding the upstream of Huangansi River, with lotus root and rice as the major crops. Agricultural fertilizer and chemical residues flow into Huangansi River with - 125 - surface runoff, causing extensive discharge of pollutants. In the meanwhile, decomposed organics from crops such as lotus root and rice also flow into Huangansi River along with surface runoff. The water quality in He River is worse than Class V water quality, causing severe black and odorous water body. Shizigang Drainage Canal is the major drainage canal and one of the pollutant discharge outlets in urban area. There a large number of residential buildings along He River in the urban area, with combined domestic wastewater and stormwater collected, conveyed and discharged in combined sewers into He River. The water quality in He River is worse than Class V water quality, causing severe black and odorous water body. Changlong River and Huangtian Branch Canal are for agriculture irrigation. However, since He River Watersheds are located in undeveloped urban area, large area of farmland and few residents are located along He Rivers, due to the underdeveloped infrastructure in the area, Changlong River and Huangtian Branch Canal serve as the drainage canal for the industrial and domestic wastewater along He Rivers and the water quality in He River is worse than Class V. Artificial water diversion canals in Hezhou Municipality urban area include East Trunk Canal and Dongwu Branch Canal. The water supply is mainly diverted from Guishi Reservoir and used for irrigation along the canal. Land use along the canal mainly include farmland and dry land, with agricultural pollutants discharged into the canal along with rainfall, making NPS pollution as the major pollution source in this watershed. - 126 - 5. Environmental Impact Assessment and Mitigation Measures 5.1 Environmental Impacts and Mitigation Measures during Construction Based on the nature of project activities, environmental impacts for the construction period and operation period are identified respectively. Construction activities that will generate environmental impacts include earth excavation, earth and construction material transportation, watercourse widening, dike construction, dredging, hydropower station improvement and construction of WWTP and associated pipeline networks. Therefore, major environmental impacts during construction include soil erosion caused by excavation, exhaust emission and noise from transportation of earth and construction material on construction site and construction access roads, and wastewater discharge from construction camp and sediment dewatering facility and odor from dredging and temporary storage of dredged sediment. Additionally, social impacts include disturbance to local traffic by construction vehicles and Fanglin Hydropower Station improvement, impact to physical cultural resources (Xiyue Block and The Old Site of CCP Babu Special Branch) by He River rehabilitation, interference with railway from river-lake connection, and impact on existing farmland irrigation by Fanglin Hydropower Station improvement. Environmental impacts during construction will be assessed in these aspects. Particularly, as dredging will affect multiple environmental elements such as ambient air and water, dredging impacts and mitigation measures will be analyzed in a separate subsection. 5.1.1 Soil Erosion Analysis and Mitigation Measures 5.1.1.1 Analysis of Soil Erosion Impact (i) Causes of Soil Erosion Vegetation will be removed in the process of construction site clearing, leveling, watercourse widening, road construction and pipeline construction. Excavation of drainage foundation trench will lead to temporary earth storage; excavation and backfilling associated with watercourse and pipeline construction will change original landform and generate new unstable slope without vegetation. Affected by the aforesaid construction activities, surface erosion and gully erosion will be caused by rain in the project area. (ii) Environment Impact of Soil Erosion (a) Increased turbidity and impacts on water quality of the rovers Soil will directly enter He River in the process of watercourse excavation and lead to high turbidity of river water and deteriorated water quality, if construction is not under good management. Waste soil generated from dike construction, site excavation or - 127 - road construction will flow into He River through stormwater runoff and affect water quality especially in strong wind and heavy rain, if the soil is not cleaned in a timely manner or not properly covered. (b) Loss of Land Vegetation, Decreased Land Production and Degraded Ecology Affected by soil erosion associated with construction site clearing, surface runoff will carry more suspended solids, inorganic and organic substances into He River and cause degraded water function, adverse impact on aquatic environment for water supply and inconvenience of daily life of local residents. Decreased land production, degraded water body function and deteriorated ecological environment caused by soil erosion will hinder sustainable economic development in surrounding area. 5.1.1.2 Result of Soil Erosion Prediction Prediction indicates that construction of the Project will disturb land area of 399.88 hm2 and damage water and soil conservation facility of 294.38 hm2. Quantity of waste soil that requires for permanent disposal is 1,273,400m 3. Soil loss during construction will total 136,787 tons. . Occurrence of soil erosion concentrates in construction period and concentrates in construction site of He River rehabilitation, temporary soil storage site, borrow area and waste soil disposal site. 5.1.1.3 Water and Soil Conservation Zone and Measures (i) Water and Soil Conservation Zone The water and soil conservation zone of the Project is divided into four Class 1 conservation zones, namely, flood risk control construction zone, urban drainage improvement construction zone, water quality improvement construction zone and temporary construction zone. (ii) General layout of water and soil conservation measures (a) Flood risk control construction zone (1) He River Rehabilitation (Huangshi Hydropower Station to Guangming Bridge) Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 227,900m3 surface soil, 227,900m3 surface soil backfill, and construction of 15,123 m long bio-swale (already included in the technical design). Greening measures: 330031 m2 embankment slope covered with grass, 30246 m2 planting of trees, bush and grass, and 60 m2 vertical greening (already included in the technical design). Temporary measures: temporary covering by 10,000m 2 dense-mesh net (newly - 128 - included in the technical design). (2) He River Rehabilitation (Guangming Bridge to Lingfeng Bridge) Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 31300 m3 surface soil, 31300 m3 surface soil backfill, and construction of 750 m long bio-swale (already included in the technical design). Greening measures: 99,030 m2 embankment slope covered with grass, 750 m2 planting of trees, bush and grass; 944m2 for vertical greening; 1145m2 for key area greening and 137998m2 for greening in total (already included in the technical design). Temporary measures: temporary covering by 1,000 m2 dense-mesh net (newly included in the technical design). (3) He River Rehabilitation (Lingfeng Bridge to Xiadao Hydropower Station) Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 35,100 m3 surface soil, 35,100 m3 surface soil backfill, and construction of 3,040 m long ecological swale (already included in the technical design). Greening measures: 102,554 m2 embankment slope covered with grass, 3,040 m2 planting of trees, bush and grass, 64,441m2 for greening (already included in the technical design). Temporary measures: temporary covering by 7,000 m 2 dense-mesh net (newly included in the technical design). (4) East Trunk Canal Rehabilitation and Connecting Trunk Canal and Mawei River Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. East Trunk Canal Rehabilitation Structural measures: removal of 20,100 m3 surface soil, 20,100 m3 surface soil backfill, 12300m2 for permeable bricks (already included in the technical design). Greening measures: 62,424 m2 three-dimensional geo-technical net embankment slope with grass, 16,343 m2 for greenbelt and 99,492m2 for greening (already - 129 - included in the technical design). Temporary measures: temporary covering by 5,000 m 2 dense-mesh net (newly included in the technical design). Flood Diversion Canal of East Trunk Canal Structural measures: removal of 5,500 m3 surface soil, 5,500 m3 surface soil backfill, 5386m for ecological swale; 5386m2 for permeable bricks (already included in the technical design). Greening measures: 24267 m2 three-dimensional geo-technical net embankment slope with grass, 5386 m2 greening belt, 4200 m2 landscaping and greening (already included in the technical design). Temporary measures: temporary covering by 3,000 m 2 dense-mesh net (newly included in the technical design). (b) Urban Drainage Improvement Construction Zone (1) Huangansi Stormwater Pump Station Cut slope and ground without vegetation being removed should be covered with dense-mesh net during construction, and temporary drainage channels and structures should be built on construction site. Structural measures: 20 m long stormwater pipelines (already included in the technical design) Temporary measures: 42 m long temporary earth drainage channel, 2 temporary sedimentation tanks, and temporary covering of dense-mesh net of 100 m2 (newly included in the technical design) (2) Shizigang Stormwater Pump Station Cut slope and ground with vegetation being removed should be covered with dense-mesh net during construction, and temporary drainage channels and structures should be built on construction site. Structural measures: 150 m long stormwater pipelines (already included in the technical design) Temporary measures: 150 m long temporary earth drainage channel, 2 temporary sedimentation tanks, and temporary covering of dense-mesh net of 500 m2 (newly included in the technical design) (3) Lining River Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. - 130 - Structural measures: removal of 28,600 m3 surface soil, 28,600 m3 surface soil backfill (already included in the technical design). Greening measures: 56146 m2 three-dimensional geo-technical net embankment slope covered with grass, 9310 m2 greening belt, 35,020 m2 landscaping and greening (already included in the technical design). Temporary measures: temporary covering by 10,000 m2 dense-mesh net (newly included in the technical design). (4) Changlong River Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 22,600 m3 surface soil, 22,600 m3 surface soil backfill, 6306m for ecological swale (already included in the technical design). Greening measures: 47113m2 three-dimensional geo-technical net embankment slope covered with grass, 7966 m2 greening belt, 29,630 m2 landscaping and greening (already included in the technical design). Temporary measures: temporary covering by 10,000 m 2 dense-mesh net (newly included in the technical design). (5) Dongwu Branch Canal Improvement Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 45,000 m3 surface soil, 45,000 m3 surface soil backfill, 4270m for ecological swale, 18675m2 for permeable bricks (already included in the technical design). Greening measures: 113930 m2 bush planting and 7685 m2 greening (already included in the technical design). Temporary measures: temporary covering by 15,000 m 2 dense-mesh net (newly included in the technical design). (6) Huangtian Branch Canal Improvement Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 24,400 m3 surface soil, 24,400 m3 surface soil backfill, - 131 - 18750m2 for permeable bricks (already included in the technical design). Greening measures: 54260m2 three-dimensional geo-technical net embankment slope covered with grass, 14880m2 for greenbelt and 45000 m2 for landscaping (already included in the technical design). Temporary measures: temporary covering by 10,000 m 2 dense-mesh net (newly included in the technical design). (7) Guposhan Drainage Canal Improvement Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction. Greening measures: 6000 m2 for landscaping (already included in the technical design). Temporary measures: temporary covering by 5,000 m 2 dense-mesh net (newly included in the technical design). (c) Water Quality Improvement Construction Zone (1) Huangansi Drainage Canal Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and land surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: 6,500 m3 surface soil backfill (already included in the technical design). Greening measures: 21,528 m2 greening, and 1,920 m2 wetland planting (already included in the technical design). Temporary measures: temporary covering by 3,000 m 2 dense-mesh net (newly included in the technical design). (2) Shizigang Drainage Canal Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and land surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: 3,990 m long bio-swale, 2,247 m long covered drainage channel, and 9,000 m3 surface soil backfill (already included in the technical design). Greening measures: 23,340m2 three-dimensional geo-technical net embankment slope covered with grass, 30,057 m2 greening, and 3,990 m2 wetland planting (already included in the technical design). Temporary measures: temporary covering by 5,000 m 2 dense-mesh net (newly - 132 - included in the technical design). (3) Jiangnan WWTP and Associated Pipeline Construction Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Temporary drainage channels and other drainage structures should be built on site. Structural measures: removal of 5,000 m3 surface soil, 5,000 m3 surface soil backfill and 800 m long stormwater pipelines (already included in the technical design). Greening measures: 0.96 hm2 landscaping and greening (already included in the technical design). Temporary measures: 880 m long temporary earth drainage channel, 4 temporary sedimentation tanks, and temporary covering by 1,000 m 2 dense-mesh net (newly included in the technical design). (4) Binjiangnan Road Construction Surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Temporary drainage channels and other drainage structures should be built on site. Structural measures: removal of 99500 m3 surface soil, 99500 m3 surface soil backfill and 5,560 m long stormwater pipelines (already included in the technical design). Greening measures: 146126m2 vegetated slope and 21770m2 road greening (already included in the technical design). Temporary measures: 11,120 m temporary earth drainage channel, 20 temporary sedimentation tanks, and temporary covering by 5,000 m 2 dense-mesh net (newly included in the technical design). (d) Temporary Construction Zone (1) Construction access roads Surface soil should be removed and be stored in temporary storage site in The main watercourse of He River rehabilitation zone, and temporary drainage and sedimentation structures should be built along both sides of the road. The site should be restored at the end of the construction stage. Structural measures: removal of 41600 m3 surface soil, 41600 m3 surface soil backfill and 20.82 hm2 for land rehabilitation (newly included in the technical design). Greening measures: 5.12 hm2 for forest land restoration and 7.04 hm2 for grass land restoration (newly included in the technical design). - 133 - Temporary measures: 138,660 m temporary earth drainage channel, and 139 temporary sedimentation tanks (newly included in the technical design). (2) Construction Site and Camp Surface soil should be removed and be stored in designated storage site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary material storage site should be covered during and restored at the end of the construction stage. Structural measures: removal of 9,000 m3 surface soil, 9,000 m3 surface soil backfill and 4.50 hm2 for land rehabilitation (newly included in the technical design). Greening measures: 0.11 hm2 garden plot restoration and 2.71 hm2 grass land restoration (newly included in the technical design). Temporary measures: 4,685 m temporary earth drainage channel, and 26 temporary sedimentation tanks, and 7,700 m2 dense-mesh net (newly included in the technical design). (3) Temporary Soil Storage Site Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored at the end of the construction stage. Structural measures: 18.05 hm2 for land rehabilitation (newly included in the technical design). Greening measures: 4.31 hm2 forest land restoration, 1.38hm2 garden restoration and 2.22 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 8,658 m long temporary straw bag stuffed with soil, 5,758 m temporary earth drainage channel, and 53 temporary sedimentation tanks, and 206,250 m2 dense-mesh net (newly included in the technical design). (4) Borrow Area Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage channels and structures should be built around the site. The borrow area should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: removal of 11,080 m3 surface soil, 11,080 m3 surface soil backfill, - 134 - 36.95 hm2 for land rehabilitation, 3,800 m long brick masonry drainage channel, and 15 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 36.95 hm2 grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m retaining wall for temporary storage site and 36,000 m 2 dense-mesh net (newly included in the technical design). (5) Waste Disposal Site Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage channel and various drainage structures should be built around the site. The disposal site should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage channel, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 bushes (newly included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly included in the technical design). (6) Mud transfer tanks Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork excavation and backfill; 861m3 for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches. 5.1.2 Analysis of Social Impacts and Mitigation Measures 5.1.2.1 Land Acquisition and Resettlement Impacts and Mitigation Measures Resettlement will inevitably affect daily life of residents in the project area in certain period of time. The IAs will provide resettlement compensation in cash and will work with local governments to make proper arrangements in accordance with concerned policies to ensure livelihood of the relocated residents to avoid social issues. Details of social impacts and mitigation measures associated with land acquisition and resettlement are given in Section 8 of this report and Resettlement Action Plan of the Project. 5.1.2.2 Impact on Railway Operation Safety and Mitigation Measures Dongwu branch canal and Lining River, under Improving Urban Drainage and - 135 - Wastewater Management component, cross existing Gui-Guang high-speed railway. As required by urban area flood control safety program, rehabilitation of Dongwu branch canal and Lining River will be needed as below: Jacking of two-hole culvert with size of 3.0 m in width, 2.2 m in height and 26 m in length will be done at intersection of Dongwu branch canal and Gui-Guang high-speed railway, located at DW0+628 to DW0+655. Construction platform is 40 m in length and 11 m in width, located at DW0+588 to DW0+628. Affected width of culvert jacking is same as width of the construction platform. Jacking of three-hole culvert with size of 3.7 m in width, 2.0 m in height and 122.5 m in length will be done at intersection of Lining River and Hezhou Railway Station, located at LN1+025 to LN1+147.5. Construction platform is 140 m in length and 16 m in width, located at LN0+885 to LN1+025. Affected width of culvert jacking is same as width of the construction platform. In accordance Regulation on Railway Transportation Safety Protection, the DI is coordinating with the railway authority, Nanning Railway Bureau, and the final construction program will be approved by Nanning Railway Bureau before put into implementation. 5.1.2.3 Impact on Public Traffic and Mitigation Measures Soil, construction material (sand, cement) and waste soil storage and transportation during construction will increase local traffic flow, occupy existing road, and cause traffic congestion and access difficulty. Pipeline construction has significant impact to local traffic. Temporary earth storage associated with pipeline construction during construction will have significant traffic impact. Open excavation for laying road-crossing wastewater interception pipelines will interrupt road traffic and cause significant traffic impact. Construction activities that affect daily life of the residents include foundation excavation, excavation and pipeline laying, backfilling, and road excavation and occupation, which will reduce urban road surface, decrease traffic capacity, lead to road blockage and congestion, traffic inconvenience of local residents, and also will affect social economy to some extent. Particularly, occupation of school access road will cause access difficulties of students, school staff and parents and may affect access safety of the students and normal school activities, including Hezhou College, Pinggui No.3 Middle School, Hezhou Pilot Middle School and Xiadao Primary School in urban area. Rehabilitation of Fanglin Hydropower Station includes improvement of existing river-crossing gate dam (combination of gate dam and bridge) and connection of bridge approach and upstream and downstream dike. Fanglin Bridge will be closed during construction in order to ensure construction and traffic safety, and access of nearby residents in Fanglin Street and Tianchang Village south to Fanglin Bridge will be affected. The following measures should be taken to avoid public traffic impact caused by - 136 - construction activities: 1. For construction activities that will affect public traffic, construction program should be provided to public traffic authority in advance for arrangements for adjusting public traffic route, and construction cannot commence until permission is obtained. 2. Signs should be set on construction site before construction indicating construction description and schedule, requesting public understanding of inconvenience caused by construction activities, and disclosing contact information and complaint hotline. This information could be disclosed in advance through media, micro-blog and wechat, as possible. 3. Excavation and backfilling should be done by zone. 4. Temporary access roads should be built when construction site is near public facilities like bus stop. Material transportation should be scheduled to avoid peak hours to reduce peak traffic volume. Separate construction access road should be built for construction in rural area to avoid use of rural road and damage of rural road by oversize equipment and vehicle. 5. Pipeline construction should avoid peak hours or traffic diversion and adjustment should be done by traffic police in peak hours to mitigate traffic congestion and ensure convenience of pedestrians to minimize traffic impact to local residents. 6. Training on construction management and environmental protection should be strengthened. For construction near school, traffic diversion and adjustment should be done by traffic police in peak hours of the school, and temporary traffic lights and other signs should be set. During construction of Fanglin Hydropower Station improvement, travel from Fanglin Street and Tianchang Village to area north of He River will be re-routed along Fanglin Road, G207 and Sanjia Bridge or through Mintian rural road and Bahuang Class 2 road. Traffic re-routing plan is subject to approval of traffic police and road closing and re-routing signs will be posted. 5.1.2.4 Impact on Underground Pipelines Foundation excavation may interfere with existing underground pipelines and damage of existing pipelines will affect daily life of the residents. Based on existing pipeline survey, existing pipelines that will be possibly affected by project construction activities are listed in Table 5-1. Table 5-1 Associated Underground Pipelines of the Project Construction Location of Concerned SN Type of Pipelines Works Pipelines 1 He River 23 m upstream of Sanjia Bridge Water Supply Pipeline - 137 - Table 5-1 Associated Underground Pipelines of the Project Construction Location of Concerned SN Type of Pipelines Works Pipelines Rehabilitation Shizigang Water Supply Pipeline, combined Babu District Transport Bureau 2 Stormwater Pump stormwater and sewage pipeline, TV on Middle Jiangbei Road Station cable, street light cable Lining River Intersection of Lining River and 3 Street light cable, TV cable Rehabilitation Zhanqian Road Changlong River Intersection of Changlong River 4 Street light cable, TV cable Rehabilitation and Guangming Road Guposhan Drainage 5 East of Guposhan Road Water Supply Pipeline, TV cable Canal Improvement Water supply pipeline, natural gas pipeline, combined stormwater and Dongwu Branch 6 Intersection with G207 Road sewage pipeline, electricity, Canal Improvement communication, TV and street light cables Natural gas pipeline, water supply pipeline, TV cable, street light cable, Intersection with Badaxi Road combined stormwater and sewage Huangansi Drainage pipeline, communication cable 7 Canal Rehabilitation Combined stormwater and sewage Intersections with Qianjin Road pipeline, communication, electricity and middle Jianshe Road and street light cables, water supply pipeline, TV cable Water Supply Pipeline, TV cable, Intersection with Guposhan communication cable, combined Road stormwater and sewage pipeline, street light cable, natural gas pipeline Intersection with Wanquan Water Supply Pipeline Street Shizigang Drainage 8 Intersection with Zhushan Road Street Light cable Canal Rehabilitation combined stormwater and sewage pipeline, TV cable, water supply Intersection with Bada Road pipeline, street light cable, communication cable, natural gas pipeline Yinhe Street section Street light cable, combined - 138 - Table 5-1 Associated Underground Pipelines of the Project Construction Location of Concerned SN Type of Pipelines Works Pipelines stormwater and sewage pipeline, TV cable, water supply pipeline, Intersection with middle Jianshe communication cable, combined Road stormwater and sewage pipeline, street light cable, electricity pipeline TV cable, water supply pipeline, Intersection with Pinganxi Road communication cable, combined (Municipal Land Resources stormwater and sewage pipeline, Bureau) street light cable, electricity pipeline, natural gas pipeline TV cable, water supply pipeline, Intersection with Longshan communication cable, combined Road stormwater and sewage pipeline, street light cable, natural gas pipeline TV cable, natural gas pipeline , combined stormwater and sewage Intersection with West pipeline, street light cable, Anshan Road communication cable, water supply pipeline Communication cable, electricity Intersection with Xingguang pipeline, TV cable, street light cable, Road water supply pipeline, combined stormwater and sewage pipeline Communication cable, TV cable, Intersection with Pinganxi Road street light cable, water supply (Municipal Water Resources pipeline, combined stormwater and Bureau) sewage pipeline, natural gas pipeline Intersection with middle Same as Shizigang Stormwater Pump Jiangbei Road Station The following mitigation measures should be required to avoid impact of pipeline interruption to daily life of residents caused by excavation for pipeline construction. 1. The contractor should further coordinate with municipal and urban development authorities during construction for collection of underground pipeline information including pipeline type, alignment and depth, and establish pipeline coordination team. Prior approval should be obtained from municipal and urban development authorities for excavation interfering with underground pipelines. 2. Construction plan and emergency response plan should be developed based on pipeline alignment and depth to avoid interference with existing underground - 139 - pipelines as much as possible. 3. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities to be prepared for emergency responses. 5.1.2.5 Impact of Fanglin Hydropower Station Improvement on Irrigated Area and Mitigation Measures Based on investigation, Fanglin Hydropower Station has irrigation function to some extent. Relying on high water level contributed by barrage, river water can flow to irrigation channels through diversion culverts by gravity. Irrigation area of Fanglin Hydropower Station covers about 400 mu dry and paddy field in Tianchang Village, 200 mu farmland in Mintian Village and 1,000 mu farmland in Fanglin Village on the right bank. Crops on the farmland include corn, rice, peanut, sweet potato, vegetable and water chestnut. As water level will decrease due to removal of gate dam during Fanglin Hydropower Station improvement and river water cannot flow to the farmland by gravity, farmland irrigation of Tianchang, Fanglin and Mintian villages will be affected. In order to ensure normal irrigation of paddy and dry farmland in Tianchang, Fanglin, and Mintian villages on the right bank, project design includes new construction of a small-sized irrigation lift station with cost of CNY 4 million. River water will be lifted by three pumps with designed delivery head of 30 m and distance of 800 m and diverted to irrigated area in Tianchang, Fanglin and Mintian villages through existing water diversion culverts and channels. 5.1.2.6 Impact of Covered to Open Canal and Mitigation Measures Rehabilitation of Shizigang Drainage Canal includes the restoration of existing covered canal into open canals. The precast slabs covering the existing canal under Yinhe Street will be removed; parking lot of Hezhou Municipal Land Resources Bureau will be partly excavated; pavement of the internal roads in the sites of the office and staff dormitory buildings of Guidong Power Company will be demolished to restore the covered canals with a length of 350 m, 100 m and 150 m respectively at these sites into open canals. Buildings/structures affected are temporary shops constructed over the precast-slab covered canal on Yinhe Street, existing parking lot over the covered canal in the Land Resource Bureau office area, and office and staff dormitory buildings and roads of Guidong Power Company. During the restoration of the covered canals to open canals, traffic on major roads in this area will not be interrupted, including Badaxi Road, Jianshezhong Road, Pinganxi Road and Jianshedong Road. During construction, residents in Yinhe Street have to make a detour of 100 m to Badaxi Road to cross the canal, and internal access in residential area of Guidong Power Company will be affected and Jianshedong Road will be relied on as before for going out. Business of shops in Yinhe Street will not be restored after change of the canal, and income of the shop owners will be affected. Part of the parking lot of Hezhou Municipal Land Resources Bureau will not be restored, and the - 140 - resulted gap of parking space will be filled up by diverting traffic, restricting access of vehicles from other organizations and taking advantage of the surrounding parking lots. For the sake of traffic accessibility for residents of Yinhe Street, Hezhou Municipal Land Resources Bureau and Guidong Power Company, it is considered in technical design that a small-sized river-crossing bridge is built for each of Yinhe Street, Hezhou Municipal Land Resources Bureau and Guidong Power Company. Impacts on normal operation of Yinhe Street shops, Hezhou Municipal Land Resources Bureau and Guidong Power Company will be mitigated through resettlement compensation, and details are given in Resettlement Action Plan of the Project. 5.1.2.7 Community health The Project involves 22 construction camps in the construction process and these construction camps will host approximately 60 to 80 persons in the peak period.The planned construction camps are mostly located in open spaces in the outskirt or on the river banks, with Shizigang Construction Camp No. 1 as an exception located in the downtown area; a certain distance has been considered in the planning from the construction camps to the residential areas. In the camps, simple barracks will be constructed to provide shelter for construction workers and the construction camps will be fenced up to form a relatively enclosed and independent space so as to minimize flow of people and contact between construction workers and community residents. Therefore, in the construction stage of the Project, the construction workers will have little communication and contact with local community in Hezhou and the risks of community health will also be relatively insignificant. Analysis shows that the construction workers of the Project are mainly local people and only a limited number of non-local workers are needed. Therefore, with the small number of non-local workers, the Project will not incur problems of increase of population due to the immigration of families of the construction workers and thus brings no pressure on the community service. China has relatively comprehensive laws and regulations on labor and various criminal offenses (e.g. sexual harassment, etc.) and strict law enforcement. The overall social security condition in Hezhou is fine and the community is harmonious. In summary, the negative impacts likely to arise from the construction workers of the Project on the local community will be very insignificant. In order to safeguard community health and prevent negative impacts on local community by the construction workers, the following measures should be taken: (1) Basic hygienic facilities should be provided in the construction camps and managed with greater efforts to avoid spread of diseases. (2) All efforts should be made to control the scale of Shizigang Construction Camp No. 1 and a certain distance should be kept from the construction camp site to the residential areas. Local workers should be employed to the best possibility. - 141 - (3) Education on laws, social security and traffic safety should be organized for the workers to promote their awareness of safety. (4) Health education should be organized for workers to increase their knowledge of HIV and other infectious diseases and encourage them to take protective measures and avoid spread of diseases to others by using condoms. (5) Education on environmental protection should be organized for the workers to assure that the ESMP requirements are followed for disposal of wastewater and solid wastes on the construction camps to prevent spread of diseases. 5.1.3 Environmental Impacts of Dredging and Sediment Disposal and Mitigation Measures 5.1.3.1 Dredging and Sediment Dewatering Methods and Disposal method Different dredging methods are selected based on size of water body. For He River that has wide water surface and large quantity of dredged sediment, cutter suction dredger is selected. Dredged sediment is treated at No.1 and No.2 dewatering facilities located along He River into sludge cake with 50% moisture content. Dewatering effluent is discharged back to He River. Huangansi and Shizigang Drainage Canals have a worse water quality and stinky sediment due to domestic sewage received along the canal throughout the year. These two canals are located in densely populated urban center with limited operation space. Therefore suction pumping plus manual excavation is selected for dredging. Dredged sediment with a 95% water content will be hauled by fecal suction trucks to No. 1 dewatering site located along He River. The sediment will be dewatered to sludge cake with 50% moisture content, and the effluent is discharged to He River. Mechanical excavation supplemented by manual excavation is chosen for dredging of Huangtian Branch Canal, Guposhan Drainage Canal and East Trunk Canal. These canals are surrounded by farmland and unused land with adequate operation space, therefore onsite movable vehicular dewatering facility is used and effluent is discharged back to the canals. Interception and diversion + dry dredging may be used as the dredging method for the inner rivers of Shizigang Drainage Canal and Huang’ansi Drainage Canal provided that the construction condition (the space of operation is available for interception and diversion of the inner rivers) is available and a sound regional intercepting pipeline network is in place. Dredging methods, siting of sediment dewatering facility and final disposal methods for He River and its tributaries are shown in Table 5-2. - 142 - Table 5-2 Dredging and Sediment Disposal Methods for He River and Its Tributaries Implementation Quantity of Surrounding Dredging and Dewatering Disposal Subcomponent River/Canal Time Dredged Sediment environment Transportation Method Location method Sediment from Lingfeng Bridge 156,900 m3 (water section to No. A-8 The main content 95%), 1 dewatering The main Cutter suction dredger + Solid watercourse of equivalent to 15,690 site, and watercourse 2018-2019 Urban Area dewatering facility at Waste He River m3 sludge cake with Sediment of He River dewatering site Landfill Dredging 50% moisture from Fanglin content Bridge section to No. 2 dewatering site 8,800 m3 (water content 95%), Manual operation + sludge C-1 Huangansi Huangansi Adjacent to To No. 1 Solid equivalent to 880 m3 pump + fecal suction truck + Drainage Canal Drainage 2018-2019 Residential dewatering Waste sludge cake with No. 2 dewatering site at Rehabilitation Canal Area site Landfill 50% moisture dewatering site content 3,300 m3 (water content 95%), Manual operation + sludge C-2 Shizigang Shizigang Adjacent to To No. 1 Solid equivalent to 330 m3 pump + fecal suction truck + Drainage Canal Drainage 2018-2019 Residential dewatering Waste sludge cake with dewatering facility at Rehabilitation Canal Area site Landfill 50% moisture dewatering site content - 143 - Table 5-2 Dredging and Sediment Disposal Methods for He River and Its Tributaries Implementation Quantity of Surrounding Dredging and Dewatering Disposal Subcomponent River/Canal Time Dredged Sediment environment Transportation Method Location method 7,440 m3 (water content 95%), Manual operation + B-5 Huangtian Huangtian No Solid equivalent to 744 m3 Farmland, mechanical excavation + Branch Canal Branch 2020 dewatering Waste sludge cake with Unused Land bankside vehicle-mounted Improvement Canal site is needed Landfill 50% moisture drying equipment content 3,540m3 (water content 95%), Manual operation + B-6 Guposhan Guposhan No Solid equivalent to 354 m3 Farmland, mechanical excavation + Drainage Canal Drainage 2020 dewatering Waste sludge cake with Unused Land movable vehicle-mounted Improvement Canal site is needed Landfill 50% moisture drying equipment content 4,610 m3 (water A-4 East Trunk content 95%), Manual operation + Canal No Solid East Trunk equivalent to 461 m3 Farmland, mechanical excavation + Rehabilitation 2022 dewatering Waste Canal sludge cake with Unused Land movable vehicle-mounted and Connection site is needed Landfill 50% moisture drying equipment with Mawei River content - 144 - Dredged sediment has a water content as high as 95% or more, and dewatering is required. Movable vehicular dewatering facility is used for East Trunk Canal, Huangtian Branch Canal and Guposhan Drainage Canal, and sediment dewatering is done along the canal. As Huang’ansi Drainage Canal and Shizigang Drainage Canal both flow through the densely populated urban area and connection of fecal suction truck and vehicular dewatering facility may cause sediment leakage and spill, a fixed sediment dewatering site is required. The advantage of fixed dewatering facility is the easy implementation of retaining, covering, interception, odor removal and ground cleaning measures. Two fixed dewatering facilities are set for preliminary drying of sediment from He River, Huang’ansi Drainage Canal and Shizigang Drainage Canal. Dewatering Facility No.1 (located on flood land along He River about 100 m upstream of Lingfeng Bridge) and Dewatering Facility No. 2 (located on flood land along He River about 100 m upstream of Fanglin Bridge) cover a land area of approximately 500 m2 each and are equipped with temporary sediment storage tank, dewatering operation area, interception channel and wastewater collection tank. Sediment monitoring results given in Section 4 show that the monitored values of arsenic and cadmium in the sediment of He River and the urban inland canals could not meet Environment Quality Standard for Soil (GB15618-1995) Class III limits for normal agricultural and forest production and plant growth, therefore the dredged sediment is not suitable for application to forest land or dry farmland. Based on investigation there are no any other sediment disposal methods in Hezhou City such as incineration facility or co-incineration cement kiln, therefore dewatered sediment will be hauled to Hezhou municipal solid waste landfill for disposal. Sludge cake will be transported in closed vehicle to the landfill for disposal. Transportation route from No. 1 dewatering site to solid waste landfill covers distance of about 14 km through south Lingfeng Road, G207, Gongye Road, G323, and landfill access road. Transportation route from No. 2 dewatering site to solid waste landfill covers distance of about 18 km through Fanglin Road, Guangming Road, G207, Gongye Road, G323, and landfill access road. Transportation route is selected to minimize environmental impacts by avoiding densely populated area and shortening transportation distance. Locations of dewatering facilities and transportation routes are demonstrated in Figure 5-1. - 145 - Figure 5-1: Schematic Diagram of Sludge Dewatering Sites and Transportation Routes - 146 - 5.1.3.2 Ambient Air Impact of Dredging and Sediment Dewatering and Mitigation Measures Dredging methods with less ambient air impact are selected through comparison of alternatives during design. For example, cutter suction dredger is selected for He River dredging andsuction pump selected for urban river dredging. In the underwater dredging, the water seal has effective control of odor emission and can significantly reduce odor generated in the process of sediment agitation. Meanwhile, dredging is scheduled in autumn and winter with low temperature and organic substance fermentation rate, which will generate less odor emission compared with dredging in summer and minimize odor impact from the source. Moreover, doors and windows of residential buildings in densely populated area along Huang’ansi Drainage Canal and Shizigang drainage canal are usually closed in autumn and winter, which will weaken direct impact of dredging odor to residents. For sections of Shizigang Drainage Canal that will be changed from covered to open canal, residents of Yinhe Street, staff in Land Resources Bureau and Guidong Power Company office buildings and residents in residential area of Guidong Power Company will be directly affected by odor emission once canal cover is removed. Odor impact will be greatly mitigated through scheduling construction activities in autumn and winter. Dredged sediment with a water content of 95% from He River, Huang’ansi Drainage Canal and Shizigang Drainage Canal will be hauled to dewatering facilities No.1 and No.2 for dewatering. Temporary sediment storage in dewatering facility will generate odor emission, and analogical method is adopted for analysis of odor pollution intensity. Dry-method dredging of Mudanjiang City Nanpaozi Lake is used as reference, as the way of odor generation is similar of dry-method dredging and temporary sediment storage process in terms of direct sediment exposure to air. Analysis of odor intensity is showed in Table 5-3. Table 5-3 Odor Intensity of Mudanjiang Nanpaozi Lake Dry Dredging Distance Odor Intensity Level Bankside Significant Level 3 30 m away from Bank Insignificant Level 2 80 m away from Bank Very Insignificant Level 1 More than 100 m away No Level 0 from Bank Analogical analysis indicates there will be significant odor next to temporary sediment storage tank, and odor intensity will decrease to Level 2 at 30 m away, better than odor intensity standard limit of Level 2.5 to 3.5. There will be almost no odor 50 m away from the storage tank. Dewatering facilities are located along He River, and environmental sensitive receptors are avoided during site selection. Distance between dewatering facility and the nearest sensitive receptor is more than 100 m, therefore temporary sediment storage in dewatering facility will not have impact on environmental sensitive receptors. Sludge cake with moisture content of 50% should be transported out in a timely - 147 - manner, and quicklime and deodorant should be supplied for site disinfection and odor removal. In addition, personal health protection supplies should be provided to construction workers to effectively mitigate impact of odor. 5.1.3.3 Impact of Dredging and Dewatering on Water Environment and Mitigation Measures Environmental-friendly and mature cutter suction dredging method is used for The main watercourse of He River. Suspended solid concentration around the cutter suction dredger will increase to some extent during dredging, but the coarse particles will settle rapidly after the fine particles are sucked up to the dredging boat. Moreover, as He River has large water flow and diluting capacity, small scope of sediment disturbance will not deteriorate water quality. Huang’ansi Drainage Canal, Shizigang Drainage Canal, East Trunk Canal, Huangtian Branch Canal and Guposhan Drainage Canal have small quantity of dredged sediment, but the canals are quite narrow and cutter suction dredger is not suitable for dredging. Sludge suction pump or mechanical excavation has advantage of flexible operation and slight disturbance to river water quality. Therefore, impact of dredging on water environment is temporary, and river water quality will be improved as large quantity of substrate pollution sources are removed and organic pollutant release is greatly reduced. Dredged Sediment with water content of 95% from He River, Huang’ansi Drainage Canal and Shizigang Drainage Canal will be transported to No.1 and No.2 dewatering sites located along He River for dewatering. Stormwater leaching and river water scouring may cause generation of muddy runoff during temporary sediment storage and secondary pollution to He River. Additionally, dewatering effluent still contains suspended solids and organic pollutants although majority of the solids has been intercepted by dewatering, therefore wastewater treatment facility is required on sediment dewatering site. (a) Interception ditch surrounding the temporary sediment storage tank will be built to divert wastewater to sedimentation tank; (b) Stormwater and dewatering effluent collected in the interception ditch should be treated in wastewater sedimentation tank before discharged to He River; and (c) Sediment should be dewatered and hauled out of the site in a timely manner to avoid generation of leachate from storage of large quantity of sediment. 5.1.3.4 Impact of Dredged Sediment and Disposal Measures Dredging methods, siting of dewatering facilities and final sediment disposal methods for He River and its tributaries are shown in Table 5-2. Dredged sediment with water content of 95% will be dewatered In an integrated drying facility to sludge cake with moisture content of 50%. Sludge cake should be transported out of site for disposal in a timely manner to avoid stormwater erosion or river water scouring and secondary pollution to surface water. Retaining, covering and interception measures should be taken to effectively mitigate impact of sediment leakage and overflow. Additionally, quicklime and deodorant should be provided for odor removal. - 148 - Following project implementation schedule, quantities of sludge cake with moisture content of 50% from sediment dredging and dewatering of He River, Huang’ansi Drainage Canal and Shizigang Drainage Canal are 15,690 m3, 880 m3 and 330m3 respectively. Implementation period of East Trunk Canal, Huangtian Branch Canal and Guposhan Drainage Canal rehabilitation is 2020 to 2022, and quantities of sludge cake with moisture content of 50% will be 744 m3, 354 m3 and 461 m3 respectively. Sludge cake will be hauled to Hezhou solid waste landfill for disposal. Currently capacity of zone 1 plus capacity contributed by original adjustment tank of this landfill can meet demand for solid waste disposal of Hezhou City in the coming three years and can also accommodate disposal of sludge cake from the Project. 5.1.4 Impact of Noise and Mitigation Measures 5.1.4.1 Analysis of Construction Noise Construction noise is generated by construction machine and transportation vehicle. Construction noise occurs in a certain period, temporarily and not in fixed locations. Noise varies with construction machine. Intensity of major noise sources is projected in Table 5-4. Table 5-4 Noise Level of Major Construction Machines Noise Level/dB (A) (5 m away from the SN Construction Machine machine) 1 Loader 90 2 Truck 87 3 Pump 80 4 Vibrator 79 5 Bulldozer 90 6 Excavator 83 7 Sludge Suction Pump 80 As shown in Table 5-4, operation of multiple machines at the same time will lead to superposition of noise level. According to the prediction, it is estimated that the superimposed noise level will increase by no more than 3 dB(A). As shown in Table 5-5, noise level of construction machine decreases with distance. Table 5-5 Prediction of Noise Level Varying with Distance Unit: dB (A) Intensity of Distance (m) Construction Noise Source Machine 15 30 50 80 100 150 200 300 500 (Distance: 5m) Loader 85 75.5 69.4 65.0 60.9 59.0 55.5 53.0 49.4 45.0 Truck 87 77.5 71.4 67.0 62.9 61.0 57.5 55.0 51.4 47.0 - 149 - Pump 80 70.5 64.4 60.0 55.9 54.0 50.5 48.0 44.4 40.0 Vibrator 79 69.5 63.4 59.0 54.9 53.0 49.5 47.0 43.4 39.0 Bulldozer 85 75.5 69.4 65.0 60.9 59.0 55.5 53.0 49.4 45.0 Excavator 83 80.2 74.2 69.7 65.6 63.7 60.2 57.7 54.2 49.7 In accordance with Hezhou Urban Area Environmental Noise Standard Application Zoning, the Project is located in Class II area and applicable standard is Acoustic Environment Quality Standard (GB 3096-2008) Class 2 with a noise limit of 60 dB (A) for daytime and 50 dB (A) for nighttime. Major construction plants include excavator, bulldozer, loader, vibrator and dump truck with an operation noise level ranging from 80 to 90 dB (A). Prediction results in Table 5-5 show that impact of excavation noise is within 150 m during daytime and 500 m during night at places there is no any sound barrier between noise source and receptors. Noise level can be reduced by 15-25 dB (A) when temporary hoarding and sound barrier are installed, and noise level at environmental sensitive receptors caused by construction equipment will range from 54 to 60 dB(A) after mitigation measures are taken, which meets Environmental Quality Standard for Noise (GB3096-2008) Class 2. Benefited from noise buffering by the first row residential buildings, the second row residential buildings are almost not affected by construction noise. In this case, noise impact during construction concentrates on area within 30 m of the construction site. Sensitive receptors within 30 m of the construction site are listed in Table 2-4. Particularly, more stringent noise reduction measures should be taken to mitigate impact of construction noise on Hezhou College, Hezhou Pilot Middle School, Pinggui No.3 Middle School and Xiadao Primary School. Construction activities should be prohibited during normal school time to avoid disturbance. 5.1.4.2 Noise Impact Mitigation Measures The ESMP includes common practices to mitigate noise impact by better managing construction activities such as earth excavation, earth and material transportation and construction of buildings and structures. Major mitigation measures include: (1) Advanced and reliable low-noise equipment should be selected. (2) Construction period is from 8:00 to 20:00, with construction activities being suspended from 12:00 to 14:00 for noon break. Construction activity during night is allowed only when permission is obtained from construction authority and approved by local EPB and disclosed to nearby residents. (3) Construction activities should be reasonably scheduled avoiding operation of multiple high-noise machines at the same time and on the same construction site. Construction period should be shortened as possible to minimize noise impact on construction workers. (4) Vibration damping foundation or support should be used for machines that generate high noise, including use of damping material. - 150 - (5) Noise from transportation vehicle will affect sensitive receptors along the route to some extent. The contractor should improve environmental awareness of the construction workers, understand local folk custom and habit, and carefully schedule transportation time and limit vehicle speed and prohibit use of horn in environmentally sensitive area such as densely populated area. (6) The contractor should consult with nearby agencies, residents and schools, and arrange construction activities with high noise in summer and winter vacations and holidays as much as possible. Meanwhile, construction should be accelerated to shorten construction period. High-noise construction activities should be concentrated in weekends to minimize impact on nearby sensitive receptors. (7) High-noise construction plants should be located on the construction site far away from residential area. 1.8m high hoarding for noise reduction should be installed on construction site located within 5 m of residential area. (8) The contractor should have reasonable construction staffing to shorten working time of workers that operate high-noise machine. Earmuff should be provided to construction workers to reduce noise impact. (9) All the construction equipment should be maintained on a regular basis to keep them in good condition, reduce noise and prolong operation life. (10) Stringent requirements should be made for construction scheduling, machine and vehicle operator and operation practice. Particularly, temporary sound barrier not lower than 2m and with good noise reduction effect should be installed on construction site near Hezhou College, Hezhou Pilot Middle School, Pinggui No.3 Middle School and Xiadao Primary School., and construction during normal school time should be avoided. 5.1.5 Impact on Physical and Cultural Resources and Mitigation Measures Rehabilitation of He River (Guangming Bridge to Lingfeng Bridge), rehabilitation of Huang’ansi Drainage Canal and construction of Huangansi stormwater pump station will possibly affect ancient wharf and city wall in Xiyue historical and cultural block. This project will do nothing to the ancient dike other than backfilling and compression outside the ancient wharf and city wall to ensure dike stability. Landscaping construction will be combined with flood control dike outside existing Babu river dike to demonstrate prosperous shipping culture of Hezhou City in old time with the subject of “silk road on the sea and thousands of boats racing across He River�. Meanwhile, corridor frameworks are designed to hide vertical flood control gate. In order to protect memorial hall and old school gate of The Old Site of CCP Babu Special Branch that may be affected by He River rehabilitation (Guangming Bridge to Lingfeng Bridge), project scope has been optimized in the design stage to avoid protected area of Xiyue historical and cultural block and new buildings and structures are designed in consistent style with existing historical and cultural block. - 151 - Embankment design has been revised by changing the originally-designed T-shaped revetment to vertical retaining wall to avoid interference with the Old Site of CCP Babu Special Branch. Uncontrolled construction activities and weak relics protection awareness of the construction workers may lead to damage to structure of the relics and pollution, and the damage may be irremediable. Therefore, physical and cultural resources management plan included in the ESMP specifies major measures for construction activities concerning physical and cultural relics as below: (1) Protective Measures for Xiyue Historical and Cultural Block (i) Protection of existing river dike and ancient wharf, construction of ancient-style recreational waterside bridge and corridor, and construction of wastewater interception pipelines along He River; (ii) Training on Historical and Cultural Relics Protection Law and local regulations on historical and cultural relics protection should be provided to the construction team before site mobilization, in order to increase historical and cultural relics protection awareness of the construction workers; (iii) Local historical and cultural relics authority should be consulted by the IA prior to construction and realistic relics protection program should be developed; (iv) Detailed construction program should be prepared before construction activities commence. Relics protection signs should be posted on construction site providing information of nature of the relics, importance, protected scope, protection measures, and contact person and channel of the historical and cultural relics authority; (v) Safety and stability of the relics in construction area should be ensured. Site safety rules and operation practice should be prepared based on concerned national laws and regulations and various requirements by the IA should be followed, to make sure relics will not be damaged or stolen; (vi) Manual excavation should be adopted in protected scope of the relics instead of use of excavator and piling machine to minimize vibrating impact; (vii) Setting of construction camp or temporary surface soil storage site should be banned within protected scope of the relics; (viii) Oversize vehicle and equipment are not allowed to enter protected scope of the relics; (ix) Relics protection training should be provided to the construction workers by contractor. Construction activities should be kept far away from the relics as possible to avoid damage to the relics; (x) In the event fossil, ancient coin, valuable article, ancient structure and other relics of geological or historical significance are found during construction, construction - 152 - activities should be stopped immediately and this should be promptly reported to construction supervisor, the IA and local relics protection authority. Effective measures should be taken to protect the site and construction activities should not continue until permission is obtained from local authority; and (xi) Knowledge of physical and cultural resources should be delivered to Xiyue Street residents for them to understand historical and economic value of these relics and get involved in physical and cultural relics protection and development of protection plan and regulations. (2) Protective Measures for the Old Site of CCP Babu Special Branch (a) Local historical and cultural relics authority should be consulted by the IA prior to construction and realistic relics protection program should be developed; (b) Training on Historical and Cultural Relics Protection Law and local regulations on historical and cultural relics protection should be provided to the construction team before site mobilization, in order to increase historical and cultural relics protection awareness of the construction workers; (c) Detailed construction program should be prepared before construction activities commence. Relics protection signs should be posted on construction site providing information of nature of the relics, importance, protected scope, protection measures, and contact person and channel of the historical and cultural relics authority; (d) Safety and stability of the relics in construction area should be ensured. Site safety rules and operation practice should be prepared based on concerned national laws and regulations and various requirements by the IA should be followed, to make sure relics will not be damaged or stolen; (e) Manual excavation should be adopted in protected scope of the relics instead of use of excavator and piling machine to minimize vibrating impact; (f) Setting of construction camp or temporary surface soil storage site should be banned within protected scope of the relics; (g) Oversize vehicle and equipment are not allowed to enter protected scope of the relics; (h) Relics protection training should be provided to the construction workers by contractor. Construction activities should be kept far away from the relics as possible to avoid damage to the relics; and (i) In the event fossil, ancient coin, valuable article, ancient structure and other relics of geological or historical significance are found during construction, construction activities should be stopped immediately and this should be promptly reported to construction supervisor, the IA and local relics protection authority. Effective measures should be taken to protect the site and construction activities should not continue until permission is obtained from local authority. - 153 - 5.1.6 Impact on Ambient Air and Mitigation Measures Major air pollution source during watercourse widening, construction of drainage gates, pump station and water replenishing canal improvement, construction of road and pipelines is dust caused by open excavation, which includes dust from earth excavation, onsite storage and backfilling, dust suspension caused by people and vehicles, as well as transportation vehicle leakage. Transportation vehicle is the major source of construction dust. Construction access road of 80.9 km will be built, 65.4 km of which will be rebuilt and maintained as embankment road and the remaining 15.5 km access road will be restored once construction is completed. Moving vehicle wheels generate dust, especially heavy vehicle that generates more dust. Vehicle moving faster generates greater quantity of dust. Meanwhile, dust generation is related to physical condition of road surface and cleanness condition. On fully dry road surface, dust generated can be calculated by the following empirical formula:  0 Q.   V 123 5W6 8 . P5 0 . . 85 0 0 . 75 Where: Q - Quantity of dust from vehicle moving, kg/km/vehicle V - Velocity, km/h; W - Weight, ton P - Quantity of dust on road surface, kg/m2 Under normal meteorological condition, dust generation by a 10 ton vehicle driving through 1 km road surface with different cleanness degrees and under different driving velocities is given in Table 5-6. Table 5-6 Dust Generation Varying with Driving Speed and Road Surface Cleanness Unit: kg/km/vehicle Pkg/m2) Velocity 0.1 0.2 0.3 0.4 0.5 1.0 (km/h) 5 0.051 0.086 0.116 0.144 0.171 0.287 10 0.102 0.172 0.232 0.288 0.342 0.574 15 0.153 0.258 0.348 0.432 0.513 0.861 20 0.204 0.344 0.464 0.576 0.684 1.148 30 0.306 0.516 0.696 0.864 1.026 1.722 Table 5-6 indicates that vehicle that moves faster generates more dust under the - 154 - same road surface cleanness condition, and dirty road surface causes more dust when vehicle speeds are the same. Analogy analysis shows that impact of the dust generated by construction site and transportation road under natural wind condition is confined to the scope within 50 km. 4 to 5 times of water spraying on the road during construction will reduce dust suspension by approximately 70%. Speed limit and keeping road clean are effective measures for reducing dust caused by vehicles. Dust control measures, such as watering on and covering of onsite lime, soil and sand as well as construction debris, should be taken. Transportation of construction material and waste soil should be covered and should not be overloaded. Vehicle wheels should be cleaned before the vehicle leaves construction site, and leakage and spill should be avoided. Environmental sensitive receptors within 50 m along the transportation route are listed in Table 2-4 (Distribution of Environmentally Sensitive Sites). He River dredging and river and lake connecting subcomponents have many sensitive receptors and APs that are mostly located within a distance of 50 m from the project area. ESMP provides necessary construction practices for better management of excavation, soil and material transportation and building/structure construction to minimize dust impact. Major mitigation measures include the following: (a) Construction site management should be strengthened. Transportation vehicle should be in good condition and should not be overloaded for cement and lime transportation, and covering and enclosing measures should be taken to avoid spill and reduce dust generation. Reasonable locations should be selected for material and waste soil storage, and material such as cement and lime should be stored at the same area and wind protection and covering measures should be taken. Sand screening and cement bag opening should be done in the lee, and site that has significant dust generation should be installed with windbreak facilities. (b) Clean-up and water spraying can be done for dust control on construction site and road. Spraying water 4 to 5 times each day on construction site is suggested. Practice in China concluded that Integrated Air Pollutant Emission Standard (GB16298-1996) can be met by adopting these mitigation measures, in terms of concentration of uncontrolled emission of particulates. Damaged vegetation should be restored in a timely manner. (c) Transportation vehicles should be cleaned and washed in a timely manner before leave construction site. Wheel washing equipment should be provided on site to clean earth on the wheels. (d) Onsite fume control should be enhanced. Toxic fume and gas emission is prohibited on construction site to mitigate waste gas pollution to sensitive receptors. (e) Stringent site management measures should be taken, which include installation of hoarding not lower than 2 m along both sides of construction site, enclosed construction, containment structure installed at hoarding bottom with no space between hoardings and between hoarding and containment structure, and setting of - 155 - No-entry signs for banning non-construction workers to enter the site. (f) Loading/unloading and transportation process should be strictly managed. Transportation of sand, cement and waste soil should be covered, and construction material should be loaded and unloaded carefully. (g) Temporary storage of earth and sand during construction should be covered and watered, and should be hauled out of the site as early as possible. (h) Start-up frequency of fuel powered machine should be minimized to effectively reduce exhaust generated by construction plants. (i) Transportation vehicle and construction equipment should be properly maintained to keep normal operation and avoid more exhaust emission caused by improper maintenance. Use of equipment that significantly violates applicable emission standard should be banned. 5.1.7 Impact on Water Environment and Mitigation Measures 24 construction sites and camps are set in total. Storage of construction material such as asphalt, fuel and chemicals should be properly managed and be covered as necessary to avoid water environment pollution to He River and its tributaries caused by stormwater runoff in rainy season. Oily wastewater during construction is generated from leakage and spill in the process of construction equipment repair and maintenance, which includes lubricant, diesel and petrol and may pollute water body. This type of wastewater is characterized by small quantity and greatly varying concentration and very limited scope affected. Proper measures should be taken by the contractor to prevent potential water pollution. Large amount of construction workers will be required during construction, which are mostly local workers and will generate certain quantity of domestic sewage. As most of construction areas are located in built urban area, existing municipal infrastructure and sanitation facilities can be used for treatment of domestic sewage of the construction workers and no separate facilities are needed. Where municipal infrastructure and sanitation facility are absent in construction area, necessary environmental protection facilities should be provided or mitigation measures should be taken. Hydropower station improvement have potential surface water pollution caused by dike construction, drilling debris associated with hydropower station foundation construction, construction wastewater (drilling wastewater, oily wastewater) and disturbance to local water by dredging activities. The ESMP includes common practices for management of construction activities to mitigate impact on water environment, and major measures to be taken include the following: (a) Sand and stone processing wastewater should be treated in sedimentation tank, and the effluent should be reused for concrete production and dust control rather than discharged into nearby water body. Construction slurry should be pumped into sedimentation tank for treatment and drying through evaporation. Construction - 156 - machine cleaning wastewater should be treated in oil separation and sedimentation tanks and the effluent should be reused for dust control and vehicle cleaning. (b) Siting of construction site should fully accommodate need for drainage and should be far away from water body. Construction site, warehouse, and diesel and asphalt storage site as well as asphalt making facility should not be located within 500 m of He River. Necessary measures should be taken to prevent discharge of pollutants into He River, especially through stormwater runoff in rainy season. (c) Operation area should be kept clean during construction to prevent discharge of wastewater and pollutants into the open channel and penetration. (d) In the event onsite oil fuel storage is required, anti-seepage measures should be adopted for storage and use to prevent oil leakage and spill and water pollution. (e) Foundation construction should be done in non-rainy days as much as possible to minimize impact on construction activities due to shallow groundwater level. (f) Water-related construction such as hydropower station and dredging should be done in dry season as much as possible, and construction period should be shortened as possible to reduce disturbance to water body. (g) Personal protective equipment and life-saving appliance should be provided to prevent accident. (h) Domestic sewage and solid waste collection and treatment facilities should be provided in construction camp without centralized municipal facilities. Domestic sewage can be discharged to nearby farmland as fertilizer, after treated. 5.1.8 Impact of Solid Waste and Mitigation Measures Solid wastes during construction are mostly contributed by removal of existing river dams of Fanglin and Huangshi power stations, demolition of buildings acquired, construction of new structures (sand and stone, lime, concrete, timber, waste brick, and earth) as well as domestic solid waste generated by construction workers. Construction solid waste will total 99,100 m3 and will be hauled to municipal construction solid waste landfill in Huangtian Town Gonghe Village for disposal. In addition, hazardous waste such as waste oil may enter surface water and cause water quality pollution if storage and transportation is not properly managed. Therefore, management measures should be enhanced in response to possible generation of hazardous waste, which include provision of special container for collecting waste oil from equipment maintenance and repair and provision of onsite emergency-responsive box, sand or saw powder for absorbing waste oil. Based on earth balance analysis, during construction the Project will have excavation of 3,433,500 m3, filling of 5,451,500 m3, reuse of 59,100 m3 excavated earth, 3,291,400 m3 earth from external source, and final disposal of 1,273,400 m3 (184,600 m3 sediment will be dewatered and hauled to Hezhou municipal solid waste landfill for - 157 - disposal, 556,400 m3 will be transported to Hezhou City electronic technology ecological industrial park for lowland filling, and 532,400 m3 will be hauled to the disposal site of the Project). Two borrow areas have been selected for the Project. One borrow area is located 1,000 m east to Hezhou City electronic technology ecological industrial park. This borrow area occupies 16.85 hm2 hilly land covered mostly with grass and eucalyptus. The other borrow area is located 750 m west to Gongye Road and 100 m north to G207 road, occupying 20.1 hm2 hilly land covered mostly with grass and eucalyptus. One disposal site will be set southwest to Donglu Village and 500 m south to Guang-He Highway, covering total land area of 7.40 hm 2. This disposal site will receive residual surface soil, unusable earth and stone, and soft earth. Water and soil conservation and restoration measures for borrow area and disposal site are described in Section 5.1.1 5.1.9 Ecological Impact Analysis and Mitigation Measures 5.1.9.1 Impact on Terrestrial Ecosystem and Mitigation Measures The project area is located in the built urban area or city outskirt without native vegetation. Ecosystem in the project area is composed of urban ecosystem and farmland ecosystem. Vegetation along He River mainly comprises of bamboo forest and bushes, and vegetation along urban inland canals comprises of farmland crops, aquatic plants and artificial secondary forest. Rehabilitation of He River will affect habitat of some waterside birds. Survey shows major bird species frequently found along He River include partridge, cuckoo, drongo cuckoo and oriental skylark, which are all ordinary species. Construction will damage vegetation habitat, and the direct result of vegetation damage will be land bareness, and greater water and wind erosion. Furthermore, modified ecosystem structure and function will lead to deterioration of regional ecological environment. Movement of construction plants and workers during construction will significantly damage vegetation on construction site. Therefore, necessary environmental protection measures should be taken during construction for effective control of impact of construction activities on local vegetation. For example, scope of construction activities should be narrowed and construction period should be shortened as much as possible, and vegetation should be restored once construction is finished to minimize local ecological impact. Construction activities will disturb inhabitation and breeding of waterside bird species along He River, but ecological system along He River will be restored after construction and will be improved over time. After implementation of the Project, introduction of variety of local plant species that are adapted to local condition will not only increase number of regional plant species and population and vegetation coverage, but also will improve environmental quality and provide better condition for normal growth of plants. Survey results indicate that 15 ancient and rare trees are distributed in Xialiang - 158 - Village, Middle Jiangbei Road, Xiyue Street, Xinaner Street, Xinanyi Street and Jianshezhong Road along He River are not within the construction area of the Project, but quite near the construction site, approximately 50 m away from the site. Normal growth of these trees will possibly be affected by earth taking and disposal, storage of construction solid waste, moving of construction vehicles and transportation of construction equipment, therefore attentions should be paid during construction and the following protective measures should be taken. 1. Construction scope should be narrowed and construction period should be shortened as much as possible; 2. Tree felling, unauthorized transplanting, bark peeling, root digging and injection of toxic and hazardous substances to trees should be prohibited; 3. It is not allowed to construct buildings or structures, lay pipelines, install power cables, excavate borrow areas, mine sand and stone, flood or seal the ground, emit fumes, discharge wastewater and dump solid wastes, stockpile or dump flammables, explosives or toxic and hazardous substances in the area with a distance of less than 5m from the outer edge of the crown shadow of trees. 4. It is not allowed to engrave, nail, wind, hang or support or stack articles on or around tree trunks; and 5. Construction vehicles and plants are not permitted to enter or roll the area with a distance of less than 5m from the outer edge of the crown shadow of trees. 5.1.9.2 Impact on Aquatic Ecology and Mitigation Measures Water-related construction activities and dredging may affect aquatic ecosystem of He River and its tributaries. Ecological survey reveals all the aquatic animals in He River are ordinary species, and there is no fish spawning field, feeding field, winter habitat or rare aquatic animal species in He River. He River dredging covers a river length of 3.6 km. Small-scope of water-related hydropower station improvement and dike construction are scheduled in dry season. Huang’ansi Drainage Canal, Shizigang Drainage Canal, Huangtian Branch Canal and Guposhan Drainage Canal are all located in urban area with intensive human activities, and major functions of these canals are flood discharge and providing water for irrigation purpose. Polluted by domestic sewage, these canals have deteriorated water quality and severe sediment deposit. Major aquatic plant species is green alga, and benthos organism is ordinary benthos species. There is no fish spawning field, feeding field, winter habitat or rare aquatic animal species in these canals, and none of these canals is important natural habitat. Water-related construction and dredging will result in disappearance of some benthos lives, but this will be restored over time after dredging is finished. Therefore, implementation of the Project will have insignificant impact on aquatic life and will not degrade or modify ecology of He River and urban inland canals. - 159 - 5.1.10 Conclusion of Dam Safety Assessment and Action Plan World Bank Safeguard Policy OP/BP 4.37 for dam safety is triggered by the Project. Therefore, Hezhou Water Resources Bureau, the IA, collected basic information of the concerned 21 dams, conducted dam safety survey, and proposed rehabilitation measures and action plan for dam with issues, and proposed completion date. Information of the dams is summarized in Table 5-7, and dam rehabilitation program and action plan are given in Table 5-8. - 160 - Table 5-7 Summary Dam Information Existing/Under Safety Basic Information of Reservoir/Dam Construction/New Assessment/Maintenance Construction in the last 5 Years SN Reservoir/Dam Location Reservoir Dam Capacity, Construction Operation Safety Dam Type Height, Function Maintenance 10,000 Time Status Assessment m m3 Flood control, Guishi Reservoir power Middle stream of Masonry 1 Dam in Hezhou 42.7 59,500 generation, 1966.3 Normal 2005.1 2009.1 Fuchuan River gravity dam City irrigation, and aquaculture On Fujiang River, Normal tributary of He River, Irrigation, Chayuan located east to supplemented 2 Reservoir Dam in Huping and Clay core dam 19.3 156 1968.3 2008.12 2010.12 by flood Zhongshan County Weilanggu villages in control Zhongshan Town of Zhongshan County Irrigation, Normal Junchong Near Rongma Village supplemented 3 Reservoir Dam in Clay core dam 13.5 576 1970 2007.5 2008.4 of Zhongshan Town by flood Zhongshan County control On Fu River of Zhu Normal River Watershed, Irrigation, Luojiu Reservoir near Luojiu Village on Homogeneous supplemented 4 Dam in Zhongshan 18.4 54 1981.5 2010.7 2012.11 Zhongshan Town in earth dam by flood County Zhongshan County control Hongshuiping On Keda River Concrete Normal 5 Reservoir Dam in (tributary of Baisha double-arch 43.7 870 1991.2 2009.12 2011.5 Fuchuan County River), at foot of Gupo dam 161 Table 5-7 Summary Dam Information Existing/Under Safety Basic Information of Reservoir/Dam Construction/New Assessment/Maintenance Construction in the last 5 Years SN Reservoir/Dam Location Reservoir Dam Capacity, Construction Operation Safety Dam Type Height, Function Maintenance 10,000 Time Status Assessment m m3 Mountain near Baisha Town Baisha Street of Fuchuan County Irrigation, Normal Shalongchong Upstream of Baisha Homogeneous supplemented 6 Reservoir Dam in River in Baisha Town 30 492 1977.5 2007.5 2008.4 earth dam by flood Fuchuan County of Fuchuan County control Upstream of Mafeng Clay core dam Irrigation, Normal Shidong Reservoir River (tributary of He flood control, 7 Dam in Pinggui River in Zhu River 39.5 1658 water supply 1963.3 2007.3 2008.12 District Watershed) in Babu and power District of Hezhou City generation On Huashanchong Clay core dam Normal River (primary Irrigation, Huashan tributary of He River), supplemented 8 Reservoir Dam in north to Etang Town 20 579 1964.4 2007.8 2008.11 by flood Pinggui District Huashan Village of control Hezhou City Babu District Clay core dam Irrigation, Normal Pangu Reservoir At end of Panguchong supplemented 9 Dam in Pinggui River, tributary of He 30.9 388 1976.12 2007.5 2008.7 by flood District River control Dachong On tributary of He Homogeneous Irrigation, Normal 10 20 85 1976.11 2008.12 2011.12 Reservoir Dam in River, at Shatian earth dam supplemented 162 Table 5-7 Summary Dam Information Existing/Under Safety Basic Information of Reservoir/Dam Construction/New Assessment/Maintenance Construction in the last 5 Years SN Reservoir/Dam Location Reservoir Dam Capacity, Construction Operation Safety Dam Type Height, Function Maintenance 10,000 Time Status Assessment m m3 Pinggui District Town Daoxi Village of by flood Hezhou City Pinggui control and District aquaculture On Dayao River, Clay core dam Normal Irrigation, Dayao Reservoir tributary of He River supplemented 11 Dam in Pinggui of Zhu River 40 322 1975 2008.11 2010.12 by flood District Watershed Xijiang control water system Clay core dam Irrigation, Normal supplemented Guishan Reservoir Guishan River, by power 12 Dam in Pinggui primary tributary of He 26.5 432 1974.3 2007.8 2009.11 generation District River and flood control On Fujiang River Clay core dam Normal (tributary of He River), Irrigation, Changtang south to Yangtou supplemented 13 Reservoir Dam in 11.5 171 1957.4 2008.11 2011.1 Town Jinzhu Village by flood Pinggui District of Hezhou City control Pinggui District On Fujiang River Normal Irrigation, Luoxi Reservoir (tributary of He River), Homogeneous supplemented 14 Dam in Pinggui northwest to 19.5 123 1910s 2008.11 2010.12 earth dam by District Wanggao Town Luoxi aquaculture Village of Hezhou City 163 Table 5-7 Summary Dam Information Existing/Under Safety Basic Information of Reservoir/Dam Construction/New Assessment/Maintenance Construction in the last 5 Years SN Reservoir/Dam Location Reservoir Dam Capacity, Construction Operation Safety Dam Type Height, Function Maintenance 10,000 Time Status Assessment m m3 Pinggui District On Lisong River Normal (tributary of He River of Zhu River Huimiandu Watershed Xijiang Masonry 15 Reservoir Dam in 34 330 1986.1 2014.2 2016 water system) within gravity dam Pinggui District Huangtian Town Luhua Village of Pinggui District Guangming Tributary of He River Homogeneous Normal 16 Reservoir Dam in in Zhu River earth dam 25 127 Irrigation 1960.1 2010.1 2010.9 Pinggui District Watershed Homogeneous Irrigation, Normal Guanyawo Yangtou Town Dajing earth dam supplemented 17 Reservoir Dam in Village of Hezhou City 15.8 95 by flood 1955.3 2008.12 2011.12 Pinggui District Pinggui District control and aquaculture Zhemu Reservoir On small tributary of Homogeneous Normal 1950s to 18 Dam in Pinggui Fujiang River, earth dam 16.5 26.6 Irrigation 2008.12 2011.12 1960s District tributary of He River On He River section Normal River Dam of near Etang Town Reinforced Irrigation and Xiadao Power 19 Xiadao Village of concrete gate 4.5 707 power 1972.7 Station in Hezhou Hezhou City Babu dam generation City District 164 Table 5-7 Summary Dam Information Existing/Under Safety Basic Information of Reservoir/Dam Construction/New Assessment/Maintenance Construction in the last 5 Years SN Reservoir/Dam Location Reservoir Dam Capacity, Construction Operation Safety Dam Type Height, Function Maintenance 10,000 Time Status Assessment m m3 River Dam of On He River section Normal Fanglin near Shatian Town Irrigation and Masonry 20 Hydropower Fanglin Village of 4.26 178 power 1971.1 gravity dam Station in Hezhou Hezhou City Pinggui generation City District On He River section Normal River Dam of near Yangtou Town Power Huangshi Power Masonry 21 Huangshi Village of 4 30 generation 1978.1 Station in Hezhou gravity dam Hezhou City Pinggui and irrigation City District 165 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program (1) Diversion of seepage collected from gallery top drain to discharge channel to keep gallery dry; (2) Closer coordination with Fuchuan Water Resources Bureau for clear responsibility allocation for safety management of auxiliary dam; Reservoir risk elimination and rehabilitation was inspected and (3) Provision of professional training on observation data analysis accepted by Guangxi Autonomous Region Water Resources for dam safety monitoring staff; Department in 2015. The reservoir has gone through extremely Guishi Reservoir heavy flood in 2015 and is under safe operation. Issues include (4) Analysis of observation data of the last 5 years; 1 Dam in Hezhou City unclear responsibility allocated for auxiliary dam management, (5) Development of automatic dam safety monitoring system; lack of observation data processing and analysis capacity by dam (6) Study on extent of impact on facility safety by scouring pit safety monitoring staff, and need for landslide mass treatment at behind overflow dam; and Wugong Mountain. Follow-up action plan is required. (7) Special geo-investigation and design necessary for treatment of Wugong Mountain landslide mass. Completion time: 31 December 2021 Cost estimate: CNY 13 million Technical design of Chayuan Reservoir risk elimination and Chayuan Reservoir (1) Restoration/new construction of channel connecting with rehabilitation in 2011 generally meets requirements of applicable 2 Dam in Zhongshan discharge culvert; standards and the construction quality meets the design County (2) Adding dam seepage monitoring facilities; requirements. The reservoir has been under normal operation for 6 166 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program years. Issues include 3m wide dam crest not in compliance with (3) Change of existing drainage channel downstream from draining criteria and artificial damage to right retaining wall of discharge prism to seepage collection channel and construction of measuring culvert channel. Follow-up action plan is required. weir for seepage observation; (4) Increasing the thickness of downstream slope of the dam to widen the dam crest to 4 meters. (5)Improving the flood control emrgency response plan. Completion time: 31 December 2021 Cost estimate: CNY 2.5 million (1) Removing/trimming of weed on downstream slope and downstream draining structure as early as possible; Technical design of Junchong Reservoir risk elimination and (2) Adding dam seepage monitoring facilities; rehabilitation in 2010 generally meets requirements of applicable (3) Change of existing drainage channel next to draining prism to Junchong standards and the construction quality meets the design seepage collection channel for seepage observation; and 3 Reservoir Dam in requirements. The reservoir has been under normal operation for 7 (4) Widening downstream slope of the dam to widen dam crest to 4 Zhongshan County years. Issues include 3m wide dam crest not in compliance with meters. criteria and absence of seepage interception channel next to the (5) Improving the flood control emrgency response plan. draining prism. Follow-up action plan is required. Completion time: 31 December 2021 Cost estimate: CNY 2 million Luojiu Reservoir Technical design of Luojiu Reservoir risk elimination and (1) Installation of reservoir water gauge for water level observation; 4 Dam in Zhongshan rehabilitation in 2014 generally meets requirements of applicable and County standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities; 167 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program requirements. The reservoir has been under normal operation for 3 years. Issues include absence of reservoir water level observation, (3) Construction of seepage collection channel next to draining and absence of seepage collection channel downstream from the prism and installation of measuring weir for seepage observation; draining prism. Follow-up action plan is required. (4) Improving the flood control emrgency response plan. Completion time: 31 December 2019 Cost estimate: CNY 30,000 (1) Enhancement of daily operation management, and weeding on Technical design of Hongshuiping Reservoir risk elimination and right jetty head; and rehabilitation in 2012 generally meets requirements of applicable Hongshuiping standards and the construction quality met design requirements. (2) Installation of water gauge for reservoir. 5 Reservoir Dam in The reservoir has been under normal operation for 5 years. Issues (3) Improving the flood control emrgency response plan. Fuchuan County include absence of reservoir water level observation, weed Completion time: 31 December 2019 growing at right jetty head, and inadequate facilities. Follow-up Cost estimate: CNY 100,000 action plan is required. (1) Weeding on upstream and downstream slope, restoration of Technical design of Shalongchong Reservoir risk elimination and dam top road as early as possible to restore dam appearance. rehabilitation in 2011 generally meets requirements of applicable Shalongchong standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities; 6 Reservoir Dam in requirements. The reservoir has been under normal operation for 6 (3) Improving the flood control emrgency response plan. Fuchuan County years. Issues include absence of upstream and downstream slope Completion time: 31 December 2019 clean-up and maintenance for a long time, and damage of dam top Cost estimate: CNY 300,000 road. Follow-up action plan is required. 7 Shidong Reservoir Technical design of Shidong Reservoir risk elimination and (1) Improving seepage collection channel next to the draining prism 168 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program Dam in Pinggui rehabilitation in 2010 generally meets requirements of applicable for seepage observation; District standards and the construction quality meets the design (2) Provision of professional training on use of dam safety requirements. The reservoir has been under normal operation for 7 monitoring equipment and preliminary information processing; years. Issues include absence of seepage collection channel and downstream from the draining prism, absence of monitoring (3) Improving flood control emergency response program. capacity of reservoir staff, and absence of emergency response Completion time: 31 December 2019 program. Follow-up action plan is required. Cost estimate: CNY 200,000 (1) Construction of seepage collection channel next to draining Technical design of Huashan Reservoir risk elimination and prism for seepage observation; rehabilitation in 2010 generally meets requirements of applicable (2) Adding dam seepage monitoring facilities; standards and the construction quality meets the design (3) Widening downstream slope of the main and auxiliary dam to Huashan Reservoir requirements. The reservoir has been under normal operation for 7 widen dam crest to 4 meters to meet criteria requirement; 8 Dam in Pinggui years. Issues include dam crest width of around 3.5 m that is not in (4) Arrangement of reservoir staff in non-flood season and making District compliance with criteria, absence of seepage collection channel sure reservoir staff on duty throughout the year; and downstream from the draining prism, absence of reservoir staff on (5) Improving flood control emergency response program. duty in non-rainy season, and absence of emergency response program. Follow-up action plan is required. Completion time: 31 December 2021 Cost estimate:CNY 3 million Technical design of Pangu Reservoir risk elimination and (1) Construction of seepage collection channel next to slope Pangu Reservoir rehabilitation in 2010 generally meets requirements of applicable draining structure for seepage observation; 9 Dam in Pinggui standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities ; District requirements. The reservoir has been under normal operation for 7 (3) Improving flood control emergency response program; and 169 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program years. Issues include dam top width of 3.5 m that is not in (4) Widening downstream slope of the dam to widen dam crest to 4 compliance with criteria, absence of seepage collection channel meters. downstream from the draining prism, and absence of emergency Completion time: 31 December 2021 response program. Follow-up action plan is required. Cost estimate: CNY 2 million (1) Installation of reservoir water gauge for water level observation; construction of seepage collection channel next to draining Technical design of Dachong Reservoir risk elimination and prism for observation of dam seepage; rehabilitation in 2012 generally meets requirements of applicable standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities ; Dachong Reservoir requirements. The reservoir has been under normal operation for 5 (3) Extension of new discharge culvert pipe, and new construction 10 Dam in Pinggui years. Issues include absence of reservoir water level observation, of diversion channel; District absence of seepage collection channel downstream from the (4) Improving flood control emergency response program; and draining prism, absence of reservoir staff on duty in non-rainy (5) Arrangement of reservoir staff in non-flood season and making season, and absence of emergency response program. Follow-up sure reservoir staff on duty throughout the year. action plan is required. Completion time: 31 December 2019 Cost estimate: CNY 400,000 (1) Installation of reservoir water gauge for water level observation; Technical design of Dayao Reservoir risk elimination and rehabilitation in 2011 generally meets requirements of applicable (2) Adding dam seepage monitoring facilities ; Dayao Reservoir standards and the construction quality meets the design (3) Arrangement of reservoir staff in non-flood season and making 11 Dam in Pinggui requirements. The reservoir has been under normal operation for 6 sure reservoir staff on duty throughout the year; and District years. Issues include absence of reservoir water level observation, (4) Improving flood control emergency response program. absence of reservoir staff on duty in non-rainy season, and Completion time: 31 December 2019 absence of emergency response program. Follow-up action plan is Cost estimate: CNY 300,000 170 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program required. (1) Installation of reservoir water gauge for water level observation; Technical design of Guishan Reservoir risk elimination and (2) Adding dam seepage monitoring facilities ; rehabilitation in 2010 generally meets requirements of applicable (3) Weeding within 20 m of the dam, improvement of seepage standards and the construction quality meets the design collection channel next to draining prism for observation of dam Guishan Reservoir requirements. The reservoir has been under normal operation for 7 seepage; 12 Dam in Pinggui years. Issues include absence of reservoir water level observation, (4) Arrangement of reservoir staff in non-flood season and making District absence of seepage collection channel downstream from the sure reservoir staff on duty throughout the year; and draining prism, absence of reservoir staff on duty in non-rainy (5) Improving flood control emergency response program. season, and absence of emergency response program. Follow-up action plan is required. Completion time: 31 December 2019 Cost estimate: CNY 300,000 (1) Installation of reservoir water gauge for water level observation; Technical design of Changtang Reservoir risk elimination and (2) Adding dam seepage monitoring facilities rehabilitation in 2011 generally meets requirements of applicable standards and the construction quality meets the design (3) Improvement of seepage collection channel next to draining Changtang requirements. The reservoir has been under normal operation for 6 prism for observation of dam seepage; 13 Reservoir Dam in years. Issues include absence of reservoir water level observation, (3) Arrangement of reservoir staff in non-flood season and making Pinggui District absence of seepage collection channel downstream from the sure reservoir staff on duty throughout the year; and draining prism, absence of reservoir staff on duty in non-rainy (4) Improving flood control emergency response program. season, and absence of emergency response program. Follow-up Completion time: 31 December 2019 action plan is required. Cost estimate: CNY 350,000 Luoxi Reservoir Technical design of Luoxi Reservoir risk elimination and (1) Change of drainage ditch next to draining prism of main dam to 14 Dam in Pinggui rehabilitation in 2011 generally meets requirements of applicable seepage collection channel; installation of long culvert pipe linking 171 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program District standards and the construction quality meets the design auxiliary dam discharge culvert pipe and channel, and change of requirements. The reservoir has been under normal operation for 6 existing drainage ditch to seepage collection channel; observation years. Issues include absence of seepage collection channel of main and auxiliary dam seepage. downstream from the draining prism, absence of reservoir staff on (2) Adding dam seepage monitoring facilities ; duty in non-rainy season, and absence of emergency response (3) Arrangement of reservoir staff in non-flood season and making program. Follow-up action plan is required. sure reservoir staff on duty throughout the year. (4) Improving flood control emergency response program; Completion time: 31 December 2019 Cost estimate: CNY 400,000 Dam safety assessment was done by design institute hired by Pinggui District Water Resources Bureau in February 2014. Design for reservoir risk elimination and rehabilitation was Huimiandu approved by Guangxi Autonomous Region Water Resource 15 Reservoir Dam in Bureau in November 2015. Construction commenced in August Pinggui District 2016 and is in progress. Technical design meets requirements of applicable standard, and construction quality will be assessed once finished. Currently no follow-up actions are required. Technical design of Guangming Reservoir risk elimination and (1) Change of drainage channel to seepage collection channel for Guangming rehabilitation in 2013 generally meets requirements of applicable seepage observation of the dam; 16 Reservoir Dam in standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities ; Pinggui District requirements. The reservoir has been under normal operation for 4 (3) Confirmation of dam top elevation and dam crest width; and years. Issues include absence of seepage collection channel next 172 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program to draining prism, inaccuracy of dam top elevation, and absence of (4) Improving flood control emergency response program; emergency response program. Follow-up action plan is required. Completion time: 31 December 2019 Cost estimate: CNY 300,000 (1) Adding dam seepage monitoring facilities ; Technical design of Guanyawo Reservoir risk elimination and (2) Arrangement of reservoir staff in non-flood season and making rehabilitation in 2012 generally meets requirements of applicable sure reservoir staff on duty throughout the year. standards and the construction quality meets the design Guanyawo (2) Construction of seepage collection channel for seepage requirements. The reservoir has been under normal operation for 5 17 Reservoir Dam in observation of the dam and the closed old culvert; years. Issues include absence of seepage collection channel next Pinggui District (3) Improving flood control emergency response program; to draining prism, absence of reservoir staff on duty in non-rainy Completion time: 31 December 2019 season, and absence of emergency response program. Follow-up action plan is required. Cost estimate: CNY 300,000 (1) Installation of reservoir water gauge for water level observation; Technical design of Zhemu Reservoir risk elimination and (2) Adding dam seepage monitoring facilities ; rehabilitation in 2012 generally meets requirements of applicable (3) Change of drainage ditch downstream from the draining prism to standards and the construction quality meets the design seepage collection channel, and installation of measuring weir for Zhemu Reservoir requirements. The reservoir has been under normal operation for 5 dam seepage observation; 18 Dam in Pinggui years. Issues include absence of reservoir water level observation, (4) Improving flood control emergency response program; District absence of seepage collection channel next to draining prism, absence of reservoir staff on duty in non-rainy season, and (5) Widening downstream slope of the dam to widen dam crest to 4 absence of emergency response program. Follow-up action plan is meters; and required. (6) Arrangement of reservoir staff in non-flood season and making sure reservoir staff on duty throughout the year. 173 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program Completion time: 31 December 2021 Cost estimate: CNY 1.5 million (1) A dam and workshop safety monitoring system will be constructed in accordance with the requirements of the “Technical Specifications on Safety Monitoring of Concrete Damsd (DL/T5178-2003) and in association with the actual situations of the Project so as to monitor the gate dam and horizontal and vertical displacement, inclination, pier joint and crack opening and closing degree and foundation uplift pressure, leakage. River Dam of Dam safety specialists have been employed for safety assessment (2) A separate circuit breaker and protection circuit will be added to ensure Xiadao Power 19 of hub facility, and safety assessment report is expected to be the safe operation of booster station. Station in Hezhou available by the end of October. (3) The left gate of the overflow gate dam will be repaired to assure safe City opratoin of the barrage dam. Pier joint and crack opening and closing degree Uplift pressure of foundation Leakage volume Completion time: 31 December 2021; Cost estimate: CNY 500,000 River Dam of Fanglin Dam safety specialists have been employed for safety assessment 20 Hydropower of hub facility, and safety assessment report is expected to be Station/Hejiang available by the end of October. Power Station in 174 Table 5-8 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program Hezhou City River Dam of Dam safety specialists have been employed for safety assessment Huangshi Power 21 of hub facility, and safety assessment report is expected to be Station in Hezhou available by the end of October. City 175 5.2 Analysis of Environmental Impacts in the Operation Stage This Project includes three components, namely, Improving He River Flood Risk Resilience, Improving Urban Drainage and Wastewater Management, and Institutional Capacity Building and Project Management. Once completed, the Project will improve the urban flood control capacity, mitigate local water pollution, increase landscaping value, improve ecological environment, and improve municipal infrastructure of Hezhou Municipality. Adverse environmental impacts include effluent, odor and noise generated by Jiangnan WWTP operation and noise generated by stormwater pump stations. As a whole, the Project will have significant benefits and insignificant adverse impacts. 5.2.1 Analysis of Environmental Benefits during Operation 5.2.1.1 Change of Hydrological Condition and Flood Control Benefits (i) Change of He River Hydrological Condition and Flood Control Benefits In the watercourse widening works under the Project, the natural gradient of the main watercourse of He River will be maintained and sections with uneven riverbeds and serious sedimentation (e.g. the section upstream of existing hydropower station) will be dredged without widening of the main river channel. Water flow of He River is determined by precipitation and catchment area that are not changed due to the implementation of the Project. Therefore, the Project will not result in changes of the water flow of He River. As the main water channel will not be widened, the hydrological conditions such as the water velocity and flow rate in normal and dry seasons will not change. Hydrological modeling analysis is conducted over the relationship between inundation loss and engineering investment under different flood control standards. Results of such analysis show that the most cost effective scenario will be achieved when flood control system is designed against the flood control standard for floods with a recurrence period of 50 years for main watercourse and floods with a recurrence period of 20 years for tributaries. The DHI-MIKE series software is used for modeling analysis and the actual topographic map is used, with the engineering design and inflow locations of each sub-catchment area on the main watercourse identified. Based on the finalized center line of the main watercourse, a hydraulic model is developed for He River and its tributaries to evaluate urban area inundation and economic loss under the applicable flood control standards and determine the technical design and mitigation measures. Modeling calculation indicates that, when flood is controlled within the main channel, the regional flow section will decrease from the urban area floodplain section to the main channel section under the scenario of designed flood level. Peak flood flow and velocity in main watercourse will increase by approximately 10%, compared with existing peak flood in urban area floodplain section. As an emerging tourism city, rapid development of various infrastructures in Hezhou - 176 - City will increase risk of regional soil erosion. The slightly increased river course scouring impact due to the increased peak flow and velocity after rehabilitation will be mitigated by sand control using adjustable power station flashboard. Meanwhile, revetment construction, vegetated revetment, ecological swale and other structural measures, planting measures, temporary protective measures will be taken to prevent soil erosion and form an integrated and scientific soil erosion prevention system and reduce sand discharge into He River. Analysis indicates that, without rehabilitation of He River and its tributaries, the flooded area and average flooded depth of Hezhou urban area will be 13.10km 2 and 1.23 m respectively under floods with a recurrence period of 50 years. The flooded area is mainly located in the middle reaches of He River mostly occupied by residential buildings, hospital and school buildings between Guangming Bridge and Lingfeng Bridge on the left bank of He River. The total floor area of the flooded buildings and farmland area will be 3.22 km 2 and 9.88 km2 respectively, causing economic loss of approximately CNY 2.044 billion. Main watercourse will be improved through dike and revetment construction, river dredging and hydropower station improvement. The dike and revetment construction includes the construction of a multi-functional dike of Xiyue Street section and dikes of other river sections. River dredging covers an 2km long river section upstream of Fanglin Hydropower Station and the 1.6 km long river section upstream and downstream of Lingfeng Bridge. Hydropower station improvement includes upgrade of Huangshi, Fanglin and Xiadao power stations. These rehabilitation measures will increase flood discharge capacity of main river course and avoid flooding of urban area. The flood control capacity of Hezhou Municipality is improved through the promotion of the flood control standards of both the main watercourse and the tributaries. Improvement of flood control capacity of the main river course alone will have the flood control standard promoted to the level for floods with a recurrence period of 50 years and reduce the flooded urban area by about 9 km2 or 68.7% and economic loss by approximately CNY 1.70 billion or 83.2%, thus capable of safeguard the flood safety in the urban area to a large extent. (ii) Change of Urban Canal Hydrological Condition and Flood Control Benefits Rehabilitation of urban inland canals will be done through river/lake retention, water diversion and discharge measures. Jintai Lake and Yongfeng Lake will be used for retention of regional peak flood flow to release pressure on downstream river course. Jintai Lake and Yongfeng Lake have a retention capacity of 300,000 m3 and 590,000 m3, respectively. Huang’ansi Drainage Canal is only used for discharge of stormwater within its own catchment area, and water received from upstream will be diverted to Shizigang Drainage Canal. Stormwater lift stations will be built at Huangansi and Shizigang canal estuaries to lift stormwater of urban area to river when He River is at high water level. River rehabilitation will eliminate inundation occurrence in urban area under 1-in-20 years precipitation and ensure urban safety. Meanwhile, river-lake connection, and water diversion and water replenishment will increase water flow as a - 177 - whole, increase assimilative capacity of urban inland canals and help improve water environment. Under scenario of rehabilitation of He River and without rehabilitation of its tributaries, flooded area and average flooded depth of Hezhou urban area will be 3.10 km 2 and 1.07 m respectively under floods with a recurrence period of 20 years. Flooded area concentrates in lower-elevated area along Huangansi and Shizigang canals occupied by residential buildings, hospitals and schools, especially protected Xiyue historical and cultural block located downstream of Huangansi canal. Total flooded floor area of the buildings and farmland area will be 0.38 km 2 and 2.72 km2 respectively, causing economic loss of approximately CNY 250 million. 5.2.1.2 Benefits of Water Environment Improvement The existing urban rivers in Hezhou City are mostly natural channels with low drainage capacity and without efficient management. Major issues include small discharge section, serious sediment deposit and the resulted weak flood discharge capacity. Uncontrolled wastewater discharge along Huang’ansi Drainage Canal, Shizigang Drainage Canal, Huangtian Branch Canal and Guposhan Branch Canal has resulted in deteriorated water quality and occupied or covered watercourse. The Project intends to address the problems of restricted space of watercourse, inflow of wastewater from both banks and water-human separation. This Project will follow the water system planning and implement ecologically-friendly river rehabilitation and river section determination on the basis of the existing water surface ratio. Service roads will be built along He River and trees and grass will be planted as the boundary line of He River channel. Wastewater will be intercepted along He River in dry season and Jiangnan WWTP and associated pipeline networks will be built to increase wastewater collection rate, reduce pollutant loading into He River, and finally improve water quality of He River. (i) Benefits of River-Lake Connection, Water Diversion and Wastewater Interception River-lake connection is favorable for the establishment of an urban river system and replenishment of fresh water. The first major source for water replenishment is Xitiankou Water Diversion Canal that diverts water from Mawei River with maximum diversion flow of 2.0 m3/s. The other source is Wugongshui Water Diversion Canal that diverts water of Xiwan River with maximum diversion flow of 1.51 m 3/s. The standby source for water replenishment is Guishidong Trunk Canal that diverts water from Guishi Reservoir. Regular renewal of river and lake water achieved through river/lake connection will help improve self-purifying capacity of water body, prevent occurrence of water body eutrophication, ensure landscaping water use requirements being met by artificial lake, and ensure water quality will not deteriorate through regular renewal. Wastewater interception along He River will greatly reduce pollutant load discharged into He Rivers and improve river water quality. Based on catchment area, quantities of wastewater intercepted will be 4,300 m3/d along Huang’ansi Drainage Canal, 6,500 - 178 - m3/d along Shizigang Drainage Canal, 1,600 m3/d along Huangtian Branch Canal, and 2,600 m3/d along Guposhan Drainage Canal, respectively. Wastewater interception totals 15,000 m3/d along the four urban rivers. Treatment of wastewater intercepted in Hezhou municipal WWTP will reduce pollutant loading into He River in terms of COD, BOD, SS, TN, NH3-N and TP by 1888.88 t/a, 903.38 t/a, 1231.88 t/a, 328.5 t/a, 221.75 t/a and 3 t/a, respectively. Pollutant load reduction benefits are significant. (ii) Benefits of Pollution Reduction by the WWTP After the Project is fully completed, water quality of He River and its tributaries will be improved. This project will have significant benefits in improving flood control and aquatic environment. Operation of Jiangnan WWTP will greatly reduce pollutant load into He River, as shown in Table 5-9. Table 5-9 Pollutant Load Reduction by WWTP Operation Pollutant Influent Pollutant Effluent Pollutant Concentration Capacity Load Facility 3 Pollutant Quality Load Quality Discharge Decrease (m /d) Reduction (mg/L) (kg/d) (mg/L) (kg/d) (mg/L) (kg/d) COD 280 4200 50 750 230 3450 BOD 120 1800 10 150 110 1650 Jiangnan SS 160 2400 10 150 150 2250 15,000 WWTP TN 55 825 15 225 40 600 NH3-N 32 480 5 75 27 405 TP 5.5 82.5 0.5 7.5 5 75 Table 5-9 indicates that operation of Jiangnan WWTP will reduce the inflow load of COD, BOD, SS, TN, NH3-N and TP respectively by 1259.25 t/a, 602.25 t/a, 821.25 t/a, 219 t/a,147.83 t/a and 2 t/a, respectively, generating significant benefits in reduction of pollutant load. (iii) Benefits of River Dredging Surface substrate structure on He Riverbed will become more stable after dredging, helpful to increasing DO concentration, change redox reaction condition of bottom interface, and reduce release of nutrients. River dredging will effectively remove a considerable part of nitrogen, phosphorus and heavy metal; with wastewater intercepted along the major drainage canals, the waterfront pollution belt will be significantly reduced. The main watercourse of He River will become unobstructed and freeflowing to facilitate sand sedimentation, decrease water turbidity, and increase intensity of sunlight illumination and the growth of floating phytoplankton. Increased plankton reproduction will further increase secondary breeding of aquatic - 179 - lives ranging from invertebrate to fish species. Improved water quality and assimilative capacity of He River will, to some extent, slow down water body eutrophication in this region. Animals that are adaptable to clean water will become dominating species. For example, quantity of diatom will increase over time and finally become dominating species, and blue-green algae will become less. Meanwhile, quantities of aquatic vascular plants will increase, and restoration of aquatic vascular plants has extremely important role in aquatic ecosystem. Fish species is at high tropic level in aquatic ecosystem. Restoration and multiplication of fish species rely on water quality and restoration of other aquatic biological groups at lower trophic levels. Restoration and multiplication of fish species will be achieved only when other aquatic lives are under normal growth and benign ecological cycle has been achieved. In the long run, river dredging will remove most of heavy metals and toxic substances in sediment and cut off migration and enrichment of these substances in food chain, which will increase economic value of fish. Moreover, restoration of phytoplankton and zooplankton over time will provide more attractive food and will benefit growth of chub and crucian that rely on the algae. Improved water quality, more transparent water and disappearance of odor will provide more favorable condition for growth of fish and other aquatic animal species, and will further help maintain healthy aquatic ecosystem. 5.2.1.3 Benefits of Landscaping and Ecological Environment Improvement The landscaping construction works of the Project will be implemented in accordance with the Master Urban Plan and in association with the development of flood risk control system and the urban drainage improvement system. Urban greenbelts and ecological corridor will be constructed to increase landscaping continuity, protect animal habitat, and create natural and continuous recreational space that encourages ecological-friendly hiking and cycling. Such efforts will play a critical role in protecting the urban ecosystem structure and functions and creating an urban eco-network and planning the open urban spaces. They will help increase the value of the urban landscaping system, maintain a healthy water environment, and facilitate human-water harmony. Such landscaping efforts will be helpful to maintaining the integrity of water system and full utilization of water resources. Interaction and integration of the water and mountain systems will enable the water system to become a medium connecting all blocks and create a more stable and ecologically-sustainable system of blue water and green mountains. The rehabilitated river channels will provide the local residents and tourists with a waterfront recreational area comprising of river course, revetments and urban landscaping along He River. Improved urban landscaping and ecological environment will set up a scientific link between the landscaping, cultural environment and the natural environment comprising of the surrounding mountains and water bodies to form an environment-friendly ecological landscaping system. This will also improve city attractiveness, increase land value, and create livable environment, and achieve co-development of city and urban residents. - 180 - 5.2.1.4 Benefits of Municipal Infrastructure Construction Flood control, wastewater and stormwater collection and drainage facilities provide physical assurance for normal urban operation and healthy urban development, and play an indispensable role in improving dwelling condition and urban capacity and increasing urban operation efficiency. Implementation of the Project will assure safe urban area against flood risk, improve regional water environment, construct high-standard and modernized municipal infrastructure and public service facilities to provide strong support and assurance for sustainable economic development of Hezhou city, increase urban development level, and achieve integration of reform and innovation. Meanwhile, the Project will improve institutional capacity building by providing water affair management technical assistance for Hezhou Municipal Government. Institutional capacity building will establish coordination mechanism among water affair master plan agency and water resources authorities, provide concerned training, workshop and study tour, in order to improve professional capacity of Hezhou City water resources authorities and agencies and provide powerful software support and assurance for sustainable economic development of Hezhou City. 5.2.2 Adverse Environmental Impacts and Mitigation Measures Upon the completion of the Project, adverse environmental impacts in the operation stage will mainly be generated from the Subproject of Improving Urban Drainage and Wastewater Management. Such impacts mainly include effluent, odor and noise discharged from Jiangnan WWTP in operation and noise generated stormwater pump station in operation. 5.2.2.1 Adverse Environmental Impacts associated with Jiangnan WWTP Operation and Mitigation Measures Thanks to the operation of Jiangnan WWTP, domestic sewage in this region will be collected and treated to prevent direct discharge of untreated domestic sewage into the surface water in WWTP service area and will significantly improve water environment. However, WWTP effluent will have slight impacts on receiving water body. Additionally, odor generated by wastewater aeration and sludge storage and noise from operation of pumps and air blowers will have impact on the surrounding environment, and wastewater sludge will cause environmental pollution in case of improper disposal. (i) Impact of WWTP Effluent After project implementation, uncontrolled domestic sewage will be collected in associated pipeline networks and discharged to He River after treated. Therefore, wastewater discharge impact prediction is based on scenario with WWTP operation. Jiangnan WWTP has a designed treatment capacity of 15,000 m3/day receiving domestic sewage collected in the Jiangnan East Area of Hezhou. Outfall of the WWTP is near Zhegutou along the main watercourse of He River. Considering that urban river rehabilitation and separate wastewater and stormwater collection are included in the Project, other pollution sources that discharge into the projected river sections will be ignored during the assessment of water quality impact by WWTP effluent. - 181 - Receiving water body of Jiangnan WWTP is He River. Flow velocity, river width, river depth and gradient cited for water quality prediction are all sourced from hydrological parameters of GZAR Surface Water Environment Capacity Study Report prepared by Chinese Research Academy of Environmental Sciences and Guangxi Environmental Protection Science Research Institute. The two-dimensional steady-state mixed attenuation model of bankside discharge recommended by Environmental Impact Assessment Technical Guidelines for Surface Water Environment (HJ/T2.3-93) and the S-P model recommended in HJ/T2.3-93 are used as the prediction models for the fully mixed river sections. The prediction process is shown in Annex 2. Prediction results show that an 11m long and 3m wide polluted mass will be formed around WWTP outfall under scenario of normal WWTP discharge, but the water quality of the other downstream sections will meet Class III of Surface Water Environment Quality Standard (GB3838-2002) along with the dilution and self-purification of He River. The predicted COD concentration at 2.8 km downstream of the WWTP outfall is almost same as baseline level upstream of the WWTP outfall, and predicted value of ammonia nitrogen at 11km downstream of the outfall will decrease to baseline level of influent from upstream of the outfall. Prediction results show that COD concentration at 2.8 km downstream of the WWTP outfall will decrease to baseline level. The projected COD concentration in fully mixed river sections at 3.1 km downstream of the outfall is 9.9mg/L, decreased by 10% compared with existing monitoring value of 11 mg/L. The projected ammonia nitrogen concentration in fully mixed river sections is 0.314 mg/L, slightly higher than existing monitoring value of 0.313 mg/L but decreases afterwards to baseline level at 11km downstream of the WWTP outfall. (ii) Impact of WWTP Odor and Mitigation Measures WWTP will inevitably generate odor during operation. Odor generation concentrates in bar screen, wastewater pump chamber, grit removing tank, A 2/O reaction tank, sludge concentration tank, and dewatering facility. Odor is caused by generation of H2S, ammonia, volatile phenol, methane, and methanol in the process of biological anaerobic and aerobic fermentation. Based on information collected of municipal WWTP odor analysis, uncontrolled H2S and NH3 emission has relatively higher concentration and will pollute ambient air within and outside the WWTP. As presented in Typical Case Studies for Environmental Impact Assessment, monitored odor concentration of a WWTP with a design capacity of 40,000 m3/day was 11.0, 4.4 and 1.1 at 100 m, 200 m, and 400 m downstream of the WWTP, respectively, under meteorological condition of breeze and air temperature of 22 degree centigrade. All these monitoring values could meet Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) Class 2 waste gas emission limit (odor concentration limit 20) within 100 m and farther. Finalized health protection distance of Hezhou municipal WWTP (capacity expanded to 30,000 m3/day) also located in Hezhou City is 100 m, therefore this distance is also applied to Jiangnan WWTP. Based on field investigation, the nearest environmental - 182 - sensitive receptor is located more than 100m away from the plant boundary and WWTP odor will have very insignificant impact on environmental sensitive receptors. Odor capture and treatment measures can be taken for major odor-generating structures to make sure odor level could meet applicable standard at WWTP boundary. Major structures that have odor generation include inflow pump chamber, aeration tank, sludge concentration tank, and sludge dewatering chamber. Currently biological odor removing methods are adopted in most cases. Biological odor removal depends on micro-organic metabolism to degrade odor substances and is suitable for removal of WWTP odor. Biological filter is the most mature technology and is odor removing method widely applied. Under suitable condition, solid carrier (stuffing) attached by large quantity of micro-organics absorbs odor pollutants and decomposes odor pollutants to carbon dioxide and water. Bio-filter has advantages of low operation cost, high removing efficiency, and easy operation without secondary pollution, and is widely applied. (iii) Impact of WWTP Noise and Mitigation Measures Noise sources of WWTP include air compressor, air blower and pumps concentrating in inflow pump chamber, sludge dewatering structure, sludge circulating pump and air blower chamber. Noise intensity is shown in Table 5-10. Table 5-10 Impact of Major WWTP Equipment Noise Noise Source Intensity dB (A) Equipment With Mitigation With Mitigation Measures Measures Wastewater Pump 90-100 80 Sludge Pump 90-100 80 Air Compressor 95-105 85 Air Blower 80-90 80 Transportation 75-80 -- Vehicle It can be seen from Table 5-10, noise intensity can be as high as 105 dB (A) without mitigation measures being taken. When noise damper is installed and the building is enclosed, noise intensity will decrease by around 20 dB (A). Major noise-generating equipment of WWTP includes water pump, air compressor and air blower. Noise level in air blower room ranges from 80 to 90 dB (A), and will decrease to 80 dB (A) when noise reduction measures are taken. Usually pumps are installed within buildings, in which noise level is 90 to 100 dB (A) and will decrease to 80 dB (A) after mitigation measures are taken. Further reduced by ambient air and distance, noise at WWTP boundary can meet Ambient Noise Emission Standard on the Boundary of Industrial Enterprises (GB12348-2008) Category 2, allowable maximum noise level 60 dB (A) for daytime and 50 dB (A) during night. Noise mitigation measures include: - 183 - (1) Selection of advanced low-noise equipment and submerged wastewater and sludge pumps, and installation of air blower indoors. (2) Firm pump foundation that can damp various vibrations and provide solid support; (3) Proper maintenance of water pump, regular inspection of concentricity of motor and pump axle, and good lubrication of bearings to reduce abrasion of pump components and parts; (4) Installation of acoustical material and vibration damping devices along internal wall of pump chamber, roof, floor and next to equipment to effectively control and eliminate noise transmission and reflection, such as asbestos board and vibration damper; and (5) A greenbelt around the pump house should be constructed through inter-planting trees and bushes to improve landscaping and reduce waste gas, noise and odor impacts on surrounding environment. Tree species with strong pollution resistance should be selected. (iv) Impact of Solid Waste during WWTP Operation and Disposal method A2/O micro-aeration oxidation ditch process is proposed for Jiangnan WWTP. Solid wastes generated include residual sludge and screening solid waste. Using Hezhou municipal WWTP expansion that adopts A2/O process as reference, it is anticipated Jiangnan WWTP will generate residual sludge of 3 tons each day or 1,095 tons per year, and generate screenings of 0.1 tons each day or 36.5 tons per year. Sludge cake will be hauled to Hezhou sludge treatment facility for safe disposal. Hezhou sludge treatment facility is located in Xinyan Village Jiuniu Community of Hezhou City Liantang Town (planned landfilling area of Hezhou municipal solid waste landfill zone 2), with designed treatment volume of 100 ton/day sludge with water content of 80%. This facility is composed of sludge receiving system, sludge treatment system, odor treatment system and wastewater treatment system. Conditioning by dilution plus deep dewatering process is adopted to dewater the sludge received with water content of 80% to dry sludge cake with moisture content 60%, and then the sludge cake is disposed of in landfill together with domestic solid waste. Sludge generated in Jiangnan WWTP is domestic sewage sludge with high water content of 80% or more, and sludge quantity will be approximately 3 tons a day. Currently construction of Hezhou sludge treatment facility has commenced and construction will be finished before operation of Jiangnan WWTP. Hezhou sludge treatment facility has adequate capacity to accommodate sludge from Jiangnan WWTP. Therefore, disposal of Jiangnan WWTP sludge in Hezhou sludge treatment facility is feasible. (v) Health Impact and Protective Measures - 184 - Jiangnan WWTP has a staff of around 30. Wastewater and sludge contain various pathogenic bacteria and parasitic ovum, and vapor over wastewater treatment facility could spread bacteria and virus. Exposed to micro organics in wastewater and sludge, operation staff of WWTP may be infected and catch disease. Infection may be caused by direct inhalation or indirectly by water drops sticking to skin and clothes, which occur in aeration tank, effluent weir, irrigation spraying outlet, air blower room, and dewatering room. In area with much moisture condensation, chiffon-type respirator will help reduce inhalation of toxic substances. Usually this kind of direct pathogen infection is confined to operators of the WWTP, with very low probability of occurrence in other people. However, if infection of the operators cannot be effectively controlled, disease may be spread to people outside the WWTP. Therefore, the following measures should be taken to ensure health of WWTP staff. (1) Proper protective clothes, gloves and respiration mask should be provided for WWTP workers. Anti-skid shoes should be provided for transportation workers and steel-toe shoes should be provided for all the workers to prevent foot injury. Workers working near high-noise equipment should be provided with noise protective devices. Workers operating near heavy movable equipment, bucket, crane and transportation vehicle dumping site should be equipped with safety helmet. Guardrails should be installed around all the process containers and water tanks. Lifeline and personal floating device should be available for use when operators are working within the guardrails, to make sure life saving devices being in place in emergencies. (2) Dangerous contact should be reduced through design and development of technical and material specifications (e.g. ventilation, air conditioning, enclosed conveyor belt, low-load and different heights, anti-skid floor, safety guardrails for stairways and aisles, spill protection and leakage prevention, noise control, dust prevention measures, gas alarm system, fire alarm and control system, and evacuation devices). (3) Bathroom and dressing area should be provided for the operators for after-work bath and dressing, and work clothing laundry service should be provided. Additionally, frequent hand washing of WWTP staff should be encouraged. (4) Enclosed space access plan conforming to the national requirements and internationally recognized standards should be developed for construction activities in enclosed treatment zone. Ventilation is mandatory before entering. Operators should be equipped with gas detector and valve connected with process container should be locked to prevent accidental overflow during maintenance. (5) Eating, smoking and water drinking should be banned outside the designated area. (6) Operators should be separated from bacteria spreading channels via mechanical overturning (e.g. use of tractor or front-end loader with enclosed air - 185 - conditioning or heating driver cab). Ventilation system should be provided in case of manual overturning. (7) Provision and use of proper personal protection clothes and devices should be required to prevent wastewater contact, such as rubber gloves, apron and boots. Medical care should be provided in a timely manner to prevent infection, for example binding up of skin injury like cut and scrape wound. Protective clothes and glasses should be used to prevent spill contact. (8) Instruction to use of safety devices and personal health practice should be included in safety training program for the operators to reduce exposure to pathogen and bacteria carrier. (9) Vaccination for preventing B type hepatitis and tetanus and health monitoring should be provided for the operators, including regular health check. Persons having asthma, diabetes or weak immune function are not suitable for working in WWTP. 5.2.2.2 Impact of Stormwater Pump Station Noise and Protective Measures Stormwater lift stations are designed for Shizigang Drainage Canal and Huang’ansi Drainage Canal. The pump stations are suspended under normal condition and are only put into operation to prevent backward flowing of river water. Major impact during operation is noise. Noise sensitive receptors are residential buildings in Xiyue Street and Mid Jiangbei Road. Short term and intermittent operation of these pump stations will have insignificant impact on environmental sensitive receptors after noise reduction by foundation and proper equipment maintenance measures are taken. Noise reduction measures to be taken are listed as below. (1) Selection of equipment with good operation performance and low noise, and vibration damping measures are taken during equipment installation to reduce noise; (2) Firm pump foundation that can damp various vibrations and provide solid support; (3) Proper maintenance of water pump, regular inspection of concentricity of motor and pump axle, and good lubrication of bearings to reduce abrasion of pump components and parts; and (4) Installation of acoustical material and vibration damping devices along internal wall of pump chamber, roof, floor and next to equipment to effectively control and eliminate noise transmission and reflection, such as asbestos board and vibration damper. 5.2.2.3 Analysis and protection measures for the operaitonal impacts of the monitoring station laboratory Equipment and test reagent must be purchased as a part of the monitoring station construction to increase the monitoring capacity. A certain volume of wastewater and a small volume of exhaust gas and waste test reagents will be generated in the - 186 - operation of the laboratory. Wastewater generated in the laboratory is mainly wastewater from washing of instruments. Although such wastewater contains little pollutants, there are relatively many types and compositions of the pollutants, including the most common organics, heavy metal ions and hazardous microorganisms as well as the less commonly seen baceria, toxins, pesticide residues, test reagent residues, etc. The wastewater containing strong acid, strong alkaline or toxic substances will generate serious enviornmental pollution if directly discharged into the natural environment. Therefore, such wastewater must be treated before discharged into the municipal pipelines. In the process of test, a small amount of exhaust gas will be generated, mainly organic exhaust gas that is ventilated outside the laboratory via the ventilation cupboard and will generate little environmental impacts. The waste drugs and test reagents are hazardous wastes and must be recovered for disposal by a qualified unit. Therefore, the wastewater, exhaust gas and solid wastes in a laboratory require reaosnable disposal, thus raising the requirements of management for the laboratory. 1. The wastewater, exhaust gas and solid wastes in the laboratories must be properly treated according to the national laws and regulations on environmental protection and random dumping, storage and discharge are prohibited. 2. Acid and alkaline waste liquid generated in the process of test and analysis and waste liquid containing highly toxic drugs must be dumped into the waste liquid cylinders for the right classification and delivered to the waste liquid storage room for centralized treatment by a qualified unit. 3. Digestion of specimens must be conducted in a ventilated cupboard and all the exhaust gas generated must be discharged at high altitude via the air duct. 4. Wastes generated in the process of testing and analysis shall be handled in such a way that intoxic wastes are dumped into the garbage bins, contaminating wastes are collected and delivered to the waste storage room for centralized treatment by a qualified unit. 5. Proper preventive measures should be taken against fire, burglary and poisoning hazards and risks. Fire protection devices and necessary poison prevention facilities should be provided in the laboratory. 6. Flammables, explosives and toxic substances must be properly stored, claimed and registered according to the respective stipulations. - 187 - 7. Smoking, laundry, cooking and storage of personal food in the refrigerators are prohibited in the laboratory. Loud noises and frolic are banned during test operation. 8. The codes of operation should be strictly followed. - 188 - 6. Environmental risk analysis and mitigation measures 6.1 Identification of environmental risks The potential environmental risks in World Bank Loan Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project will arise from the proposed Jiangnan WWTP as a part of the Urban Drainage and Wastewater Management Improvement Subproject considering the engineering features of the Project. The main environmental risks include: (1) massive direct discharge of untreated sewage may occur in case of any events of emergency, such as power outages, natural disasters and equipment failure ; (2) Environmental risks may arise from leakage of sewage into storm water pipe and discharge of untreated sewage into surface water caused by broken sewage pipes; (3) Personal safety risks may arise from the accumulation of harmful gas in the course of sewage pipeline maintenance. 6.2 Analysis of potential impacts from WWTP accidents with environmental risks 6.2.1 Emergency accidents Improper equipment maintenance or quality problem may cause failure of equipment and facilities and reduction of treatment efficiency, or even cause direct discharge of untreated sewage. Some irresistible external causes, such as power outage, natural disaster might result in equipment failure and direct discharge of untreated sewage. This is the worst case of abnormal operation. The sewage will be discharged into surface water through bypass if power outage causes facility failure. 6.2.1.1 Water quality prediction model The effluent of Jiangnan WWTP will be discharged into He River. Considering the size of He River, the impact of discharged of untreated sewage is projected using the two-dimensional steady-state attenuation model recommended in the Technical Guideline of Environmental Impact Assessment-Surface Water (HJ/T2.3-93). The S-P mode was adopted for the full mixture section. The impact of discharge of untreated sewage (i.e. at the designed influent concentration of the WWTP) was also predicted in the scenario of accidental discharge. The details of the prediction process is described in Annex 2. According to the prediction results, COD of the 10 m wide and 220 m long river section downstream of the outlet exceeds the discharge standard by a maximum factor of 6.46. NH3-N of the 10m wide and 500 m long section downstream of the outlet exceeds the standard by a maximum factor of 15.10. It can thus be seen that the water quality of He River will be affected to a certain extent or even exceeds the standard at some river sections in the case of accidental discharge. Therefore, it is - 189 - necessary to strengthen WWTP operation and management to prevent accidental discharge. 6.2.2 Risks of sewage pipeline leakage In case of any leakage of sewage pipelines, collection of sewage will become unlikely. Untreated sewage will cause pollution to surface water environment. Sewage leaked from pipelines and permeated into the ground may result in pollution of not only the soil and environment in the surrounding areas and also negative impacts on ground water quality. Based on the status of operation of the existing stormwater and sewage pipelines, the probability of pipeline leakage is not high unless in the case of uncivilized construction and human damages. 6.2.3 Staff health risks from failures of WWTP system As the WWTP system failure is always unexpected, it will cause significant damage to the working staff and endanger their life. When environmental accident occurs, the first thing affected is the health and safety of the staff in the wastewater treatment plant. 6.2.3.1 Analysis on poisoning risks and impacts caused by toxic gases When an accident occurs in a particular structure of the sewage treatment system, maintenance workers need to enter the enclosed space, such as sewer, water collection well and wastewater tank, to repair the system immediately. In such places, high-concentration toxic gases, such as hydrogen sulfide, methane, carbon dioxide, etc. are likely to occur and accumulate. If no protective measures are taken during maintenance, the workers might inhale the toxic gases due to poor ventilation, which might result in dizziness, poor breath and other symptoms or even casualty. According to relevant data, there have been dozens of accidents with threats personal safety in more than 20 cities caused by exposure to toxic gases in the sewers and combined pipelines or fire explosions resulted from flammable methane in the pipelines. Therefore, it is essential for the WWTP operators to take occupational safety measures to prevent damages from toxic gases. The most effective way to prevent poisoning is to take ventilation measures to disperse the poisonous and harmful gases completely and make the working space full of fresh air. If adequate ventilation is not possible, the dangerous space should be avoided and effective protective equipment must be worn during operation. Protective equipment includes gas marks, air supply masks and so on. Testing devices needed include test paper and gas detector, etc. 6.2.3.2 Analysis on health risks and impacts caused by pathogens The wastewater and sludge contain a variety of pathogens and parasite eggs. The fog and water on the treatment facilities can spread bacteria and viruses. The WWTP workers exposed to the micro-organisms in the sewage and sludge have the risk of infection through direct inhalation of gas or caused by droplets on the skin or clothing. This kind of gas can be found at aeration tank, effluent weir, irrigation outlet, blower room, dewatering workshop and other places. In places where water vapor is highly - 190 - condensed, the gauze-type respirator can reduce the inhalation of toxic substances. This type of environmental risk mainly results diseases caused by direct infection of pathogen. People outside of the plant is unlikely to be infected, but their heath will be also endangered by spread of disease due to poor control of the condition of infected workers.. 6.3 Risk mitigation measures 6.3.1 Equipment safety assurance measures The failure of pump, valve, electrical apparatus and other instrument used in the treatment facilities and system will reduce the treatment efficiency or even cause outage of the whole WWTP. This is a kind of potential risk. The emergency response actions in this regard include: (1) A redundancy equivalent to 0.5 times of the maximum capacity is considered in the process design for the WWTP system so as to have a buffer in the event of accidents; Compatible processing equipment (reflux pump, reflow pipes, valves and meters) should be provided so that the system buffer and backflow equipment can be started to retreat the unacceptable effluent to the specified discharge standard in case of equipment failure affecting the normal operation of the system. (2) For the vulnerable equipment, multiple standby equipment and adequate spare parts should be assured on site. All key mechanical and electrical equipment should be configured in such a way that one standby is available. (3) Use high-quality equipment. All machinery, electrical appliances, instruments and other equipment selected should have good quality, low failure rate, good durability and be easy to maintain and repair. (4) During operation, the operators shall strictly follow the rules and regulations of facility operation and conduct regular inspection and timely maintenance to reduce equipment failure rate. (5) The electrical equipment should be operated in compliance with the grounding protection regulation and be equipped with automatic tripping circuit. The main equipment shall be operated under the surveillance of a computer data monitoring system and be capable of giving alarms and recording the location, time and features of accident so that the workers can organize maintenance promptly. All electrical equipment shall be installed with a protection system according to the relevant safety requirements. (6) Dual-circuit power supply shall be used to assure normal operation of the power supply facilities and lines. 6.3.2 Protection measures for abnormal wastewater discharge 1. Emergency responses to unstable water amount caused by various factors shall be fully considered in the design to alleviate the unfavorable situations. 2. Technical management measures during WWTP operation include: - 191 - (1) Establishing a WWTP operation and management responsibility system; (2) Organizing trainings for the management and technical staff and establishing technical appraisal records so that those failing the technical appraisal are not allowed to be on duty; (3) Employing experienced professional and technical staff to be responsible for the technical management in the WWTP; (4) Organizing domestic and abroad trainings for the technical staff; (5) Strengthening inspection of pipelines and detecting and resolving problems in a timely manner; (6) Strengthening maintenance and management of equipment and facilities. Key equipment shall have standby and dual power supply. 6.3.3 Emergency responses to unexpected wastewater discharge accident The following measures shall be taken in the event of unexpected wastewater discharge accident in a WWTP: (1) Ensuring the normal operation of grid and grit chamber so that the SS and COD in the influent can be reduced to certain extent; (2) In the event of irresistible external causes, such as blackout of dual power supply and natural disaster that will lead to discharge of untreated wastewater, the wastewater shall be stored in the emergency tank and treated once the wastewater treatment system is repaired to ensure the safety of the water body; (3) In the event of and during the handling of an accident, warning signs shall be erected in the waters near the outfall to remind all parties concerned to take precautionary measures. 6.3.4 Prevention and control measures for risks of pipeline leakage (1) The local conditions shall be considered to select proper pipe material and ensure pipeline quality and service life. The drainage foundation shall meet the mechanical design requirements and be constructed in strict accordance with the detailed design of width, thickness and strengths of foundation to assure good construction quality. (2) Careful inspection shall be conducted before pipeline installation. All pipe materials shall be carefully checked to avoid any cracks and leakage. On the other hand, it is necessary to check the center line and the edge of the foundation with the drawings and ensure the size and strength of all bed course satisfy the requirement. It is also necessary to check whether the manhole location, spacing and concrete strength and the preparation of anti-seepage mortar can comply with the national standard. (3) During pipeline installation, the cement mortar shall be prepared according to the stipulated mix design. Protruded seams often occur at the pipeline connections due to squeezing during installation. If not handled in a timely - 192 - manner, the water flow profile and velocity may be affected and debris accumulation and pipeline congestion may occur. (4) The pipe base concrete and plaster mortar must reach the required strength before trench backfill. Action should be taken to avoid gravel impacts on the pipelines. Large crushed stone and hard objects should not be contained in the gravel and aggregates. Backfill and compaction should be conducted simultaneously on both sides of the pipeline and lay-by-layer on top of the pipeline so as to form an integral load-carrying mass to spread the unloading force at the pipe crest to protect the pipelines. (5) The construction unit shall establish a complete system of pipeline monitoring and management during operation, and clear the pipe network and replace the damaged pipes in time to avoid water pollution caused by pipeline leakage. 6.3.5 Personal safety protection measures (1) The operation and management staff shall receive safety education before formal operation. The plant shall establish a set of safety operation procedures and management system. These procedures shall be strictly enforced and the performance shall be inspected during operation. (2) The requirements of water supply and drainage, heating and ventilation, lighting and health shall be considered in the design. Air conditioning facilities shall be provided in the places involving lengthy operation. The enclosed structure or work place with poor ventilation shall have mechanical ventilation facilities. (3) Life jacket, life buoy, safety belt and safety helmets and other personal protective supplies shall be provided on site. The workers who have to enter the pipeline for inspection or operation shall wear the necessary protective devices, such as safety suits, gas masks, air masks, gas detection equipment, test strips, etc., to prevent poisoning and at least two persons present. (4) The walkway of tanks shall have handrails and lighting facilities to ensure pedestrian’s safety. (5) All electrical equipment shall have protection system that meet the relevant safety requirements and grounding protection shall be properly executed for high-voltage equipment. (6) The hazardous parts of machinery and equipment, such as belt, gear and wheel shall be installed with protective device. (7) It is necessary to strengthen safety management and establish a responsibility system. All dangerous areas shall have warning signs at visible positions. Platforms with a height of more than 1.2 m shall have fences. Ventilation shall be provided in the places where toxic and harmful gas might gather. The operation and maintenance unit shall set up a safety and labor protection department to be responsible for safety protection and labor protection. (8) Sanitation room (toilets, lavatories, dressing rooms, etc.) shall be provided for the sake of actual needs and convenience. In addition to providing ventilation in the places with poor working condition and shading for the outdoor work, - 193 - lounge shall also be provided. There shall be centralized bathrooms in the plant. (9) The staff directly exposed to sludge, wastewater or domestic solid waste shall take physical examination and be vaccinated on a regular basis (such as hepatitis A, hepatitis B, etc.). 6.4 WWTP emergency response unit and its roles and responsibilities The emergency response unit of a WWTP mainly comprises of the leading group office and the emergency response teams of different disciplines, including rescue team, liaison team, logistics team and fleet team. The roles and responsibilities of each team are as follows and shown in Figure 6-1. 1. The leading group is responsible for i) developing and implementing emergency response plans; ii) guiding and coordinating with external agencies. 2. The leading group office will assist the leading group in task allocation, supervision and inspection. 3. The rescue team is responsible for handling accidents and repair equipment under the guidance of the leading group. 4. The liaison team is responsible for communication and coordination with the rescue team, logistic team and vehicle team. 5. The logistics team is responsible for assisting in the rescue of poisoned victims and taking appropriate first aid measures, hospitalization, nursing the poisoning victims and mobilizing rescue resources. 6. The vehicle team is responsible for arranging vehicles and sending the poisoned victims to hospital and delivering rescue materials, etc. Leading Group Office Rescue Liaison Logistics Vehicle Team Team Team Team Figure 6-1: Emergency Response Mechanism of Wastewater Treatment Plants - 194 - 7. Cumulative impact assessment Hezhou Municipality was built along the He River. The urban center is on the north bank of He River. However, the terrain of the urban center is flat and depressed and the water conservancy infrastructure constructed in the past against the standard for a county town no longer match with the requirement of development of a municipal-level city. Hezhou Municipality has development a future strategy for development of the main axis along the He River, where the urban center is the most important node. In order to achieve the goal of urban development, the relevant government departments have begun to plan and construct flood control and drainage projects in recent years. On the other hand, if Hezhou’s water pollution control cannot keep up with the pace of urban development, the pollution of urban inland canals in Babu old city area and tributaries of He River will become more serious and even expand to northwest and south of He River. In order to alleviate water pollution, Hezhou will make vigorous efforts in promoting the construction of drainage works, including wastewater treatment plants and the associated sewage and storm water pipelines. The relevant government departments are also planning to promote wastewater treatment in villages and towns in the territory. Due to possible superimposition of impacts from projects already constructed, under construction or to be constructed along the main watercourse and tributaries of He River, such as flood control and drainage works, wastewater treatment plant and other infrastructures, and the impacts of the Project, cumulative impacts may arise on the valued environmental and social component (VEC) in the watershed. In such a context, with reference to IFC’s Cumulative Impact Assessment and Management: Guidance for the Private Sector in Emerging Markets and through consultation with the stakeholders, the key VECs were identified and screened to determine the scope, indicators and thresholds of cumulative impact assessment. The cumulative impacts on the identified VECs were assessed. In addition, the Project and its linked projects will bring significant social benefits and certain negative impact. Therefore, the cumulative social impacts were also assessed. A series of safeguard measures were put forward on the basis of consultation with relevant departments. 7.1 Scope of cumulative impact assessment 7.1.1 Affected VEC As discussed in Section 5.2, the long-term impacts of the Project will be mainly reflected in the reduction of water pollutants and improvement of flood control and drainage management. Upon full completion of the Project, significant positive impacts will be produced on the urban water environment in Hezhou from improvement of water quality in the tributaries of He River thanks to the construction of the sewage interception and dredging works. The proposed Jiangnan WWTP will - 195 - greatly reduce pollutant load into He River. This Project will greatly reduce the flooded area and economic loss and assure urban flood safety through improvement of flood control standard and rehabilitation of the main watercourse of He River. There will be remarkable benefits from flood control. Based on desktop review and consultation with relevant departments, the activities likely to produce cumulative impacts with the long-term impacts of the Project are identified, including the existing and proposed flood control works (dikes, pumping stations, etc.) along the main watercourse of He River, river-lake connection works and water environment remediation works (urban and rural wastewater treatment facilities). The potential affected VEC, including flood control and drainage benefits, reduction of river pollutants, hydrological conditions and aquatic ecosystem, were screened at the early stage of cumulative impact assessment. As discussed in section 5.2.1, the Project will not change the velocity, and flow of dry season and normal season and other hydrological condition of main watercourse of He River. In the event of a flood of the design level, the peak flow and velocity in the main watercourse will increase and the water will flood over the bank. During the flood period, He River erosion will be more serious. However, with various measures taken, the changes of sediment volume will be insignificant. According to the analysis, the impacts caused by the proposed dikes and drainage pump station on the main watercourse of He River will be basically similar with the Project. There will be no influence on the velocity and flow of normal season and dry season as the main watercourse will not be widened; the impact on sediment volume is negligible; the peak flow and velocity will increase during the flood period but at the same time, the floodplain area and the economic loss can be reduced. The main function of the proposed river-lake connection is to regulate peak flow in the flood period. All of these works will bring positive flood control benefits. Therefore, the cumulative impact assessment focuses on the impact in the flood period. The hydrological situation will not be significantly affected, thus not considered as important VEC, while the benefits of flood control and drainage are identified as key VECs to be assessed. According to survey and consultation with experts, the aquatic organisms in He River are common species. There are no fish spawning grounds, feeding grounds or overwintering grounds in He River. After decades of development, there are cascade hydropower stations before He River flows into Xijiang River. There are no rare aquatic organisms or migratory fish species, or important natural habitat. Most of the fishes are economic species. As discussed in section 5.1.5, the Project has little impact on aquatic organism. The linked projects identified in the cumulative impact assessment are similar to the Project: the construction activities of dike and pump station may cause minimal disturbance to the surface water body, but the impact on aquatic organisms is temporary, minimal and reversible. Such disturbance will disappear as the construction is completed. The Project and the other linked projects will not cause long term cumulative impact on aquatic ecosystem. Therefore, it is not determined as a key VEC under this assessment. - 196 - In summary, it is finally determined that the benefits of flood control and drainage and reduction of water pollutants are determined as the key VECs under the cumulative impact assessment. 7.1.2 Temporal and spatial scope of assessment In the course of the cumulative impact assessment, the relevant activities are screened from the four plans, i.e. Hezhou Urban Flood Control Plan, Hezhou Municipality Master Urban Plan (2016-2030) (Draft), Implementation Plan for Integrated River Rehabilitation of Urban Section of He River (2017-2020), and Hezhou Urban Ecological River System Planning (2014-2030), based on the results of consultation with Hezhou Municipal Planning Bureau, Hezhou Municipal Water Resources Bureau, Hezhou Municipal Engineering Administration Bureau, Hezhou Municipal Housing and Urban-Rural Development Bureau and Hezhou Municipal Environmental Protection Bureau. The scope of this assessment was determined on the basis of comparison with the scopes specified in each of the aforesaid plans. Table 7-1: Plans and Scope of Impacts of the Related Development Activities Description Planning Planning Scope Affected VEC Period WB Loan Hezhou 2017-2022 Main watercourse of He River: He River: Huangshi project (the Project) the upper Huangshi hydropower station – 11 hydropower station - Downstream Jiangnan WWTP m downstream of outfall Jiangnan WWTP outfall Tributaries: Hejiang north branch (except for Taoyuan Core area of Hezhou River) Municipality Hezhou Urban Flood Baseline: Main watercourse of He River: Main watercourse of He Control Plan, Hezhou 2010; Xiwan town of Pinggui at River: Xiwan town of Municipality Master upstream –Hejie town at Pinggui at upstream – Urban Plan Short term: downstream Hejie town at 2020; downstream Planned urban center of Long term: Hezhou Municipality: east to Planned urban center of 2030 Liantang town and Hejie town, Hezhou Municipality west to Xiwan street, south to Etang town, north to the southern edge of Luo-Zhan railway Hezhou Municipality Baseline: Babu street, Xiwan street, Main watercourse of He Master Urban Plan 2015; Yangtou town, Wanggao town, River: Pinggui WWTP (2016-2030) (Draft) Huangtian town, Hejie town, at upstream-outfall of Short term: Liantang town, Etang town and Hejie WWTP at surrounding villages, Fanglin - 197 - Table 7-1: Plans and Scope of Impacts of the Related Development Activities Description Planning Planning Scope Affected VEC Period 2020; village of Shatian town. downstream Long term: Planned urban center of 2030 Hezhou Municipality Hezhou urban center: east to Liantang town and Hejie town, west to Xiwan street, south to Etang town, north to south of Luo-Zhan railway Drainage planning: 1)Main watercourse of He River: Pinggui WWTP at upstream-outfall of Hejie WWTP at downstream; 2) Xiwan River: upstream to Wanggao industrial WWTP Implementation Plan Baseline: Main watercourse of He River: Main watercourse of He for Integrated River 2016 upstream Huangshi River: Huangshi Rehabilitation of Urban hydropower station-Xiadao hydropower Section of He River Planning power station station-outfall of (2017-2020) 2020 Hezhou WWTP Tributaries: northern Hejiang and Taoyuan River and Tributaries in the Jiangnan district Hezhou urban center and surrounding Wastewater treatment facilities villages and towns in the surrounding villages and towns of tributaries: Etang town, Shatian town, villages surrounding the mainstream and tributaries Hezhou Urban Baseline: Same as Hezhou Municipality Planned urban center of Ecological River 2014 Master Urban Plan (2016-2030) Hezhou Municipality System Planning (Draft) Short term: 2020 Long term: 2030 Considering the impact of the Project and related planning, the scope of the cumulative impact assessment is identified and comprises of two parts, namely, main watercourse of He River and the urban center of Hezhou Municipality. As shown in the table above, the section of the main watercourse of He River to be influenced by the related planning is the section from the upstream Huangshi Hydropower Station to the downstream Hejie WWTP. The Jiangnan WWTP proposed in the Project is at the downstream. The water quality at 11 m downstream of its outfall can meet with the - 198 - water environment quality standard. The effluents of Jiangnan WWTP and the Mawei River joining He River at 200 m downstream will have certain cumulative impacts. The cumulative impact of Hejie WWTP at 8 km downstream is minimal. In order to narrow the scope of assessment, the boundary of cumulative impact was set at the Duling Hydrological Station located 4.5 km downstream of the junction of Mawei River and He River. In such a context, the scope of cumulative impact assessment of the main watercourse of He River starts at the upstream Huangshi Hydropower Station and ends at the downstream Duling Hydrological Station with total length of 30 km. On the other hand, the proposed river rehabilitation works of the northern tributaries of He River and river-lake connection works will cause cumulative impact to the Project. Therefore, the northern part of the urban center is also included into the identified scope of assessment. To sum up, the spatial scope of assessment covers the main watercourse of He River (Huangshi Hydropower Station to Duling Hydrological Station) and north part of Hezhou urban center (see Figure 7-1). The baseline year of the cumulative impact assessment is 2017; according to the schedule of the Project and timeframe of relevant planning activities, the temporal scope of the predictions and analysis will be 2018-2023 for the short term and 2030 for the long term. - 199 - Figure 7-1: Schematic Diagram of the Scope of Cumulative Impact Analysis - 200 - 7.1.3 Related development activities As mentioned above, He River flows from northwest to southeast through Hezhou Municipality. He River will be the main axis of Hezhou Municipality in the future, with the urban center of Hezhou as the most important node. In order to achieve the goal of Hezhou urban development, the relevant departments are revising "Hezhou Municipality Master Urban Plan (2016-2030) (draft)". However, the flood control facilities of Hezhou Municipality are yet to be improved and the City is affected by floods almost every year. The existing flood control facilities in Hezhou Municipality cannot meet the needs of urban development. To this end, the relevant departments have developed the Urban Flood Control Plan of Hezhou, Guangxi, which integrated flood prevention and control measures to enhance the urban flood control capacity. On the other hand, the combined storm water and sewage system are still common in Hezhou urban area. The tributaries and drainage canals along He River receive large volume of sewage and He River is thus polluted. In order to achieve maximum collection rate of urban sewage, improve the urban drainage network, and address the problems of flooding and water pollution, the relevant departments developed a specific implementation plan in 2017, planning to implemented comprehensive river rehabilitation in 2-3 years in the urban river sections. The Hezhou Municipality Master Urban Plan (2016-2030) (draft) also develops an outlook for the urban sewage treatment facilities in the long term. Under the guidance of the Master Urban Plan, Hezhou Municipality proposed to connect as many natural rivers and lakes as possible in the future and speed up the construction of a modernized regional ecological water system relying on the projects of regulation and connection of natural rivers and lakes, medium-sized reservoirs. The Hezhou Municipality Urban Ecological Water System Planning (2014-2030) has been developed to constantly optimize configuration of water resources and further improve water resources and water environment capacity of Hezhou Municipality. The linked projects already constructed, under construction and proposed to be constructed were identified on the basis of Hezhou Urban Flood Control Plan, Hezhou Municipality Master Urban Plan (2016-2030) (Draft), Implementation Plan for Integrated River Rehabilitation of Urban Section of He River (2017-2020) and Hezhou Municipality Ecological Water System Planning (2014-2030). The identification matrix is given in Table 7-2. The related development activities are shown in Figure 7-2. Based on the temporal scope of the cumulative impact assessment, statistics of the expected progress of the Project and the related activities for the short-term scenario of 2018-2023 and the long-term scenario of 2023-2030 are summarized in Table 7-3 for further analysis and assessment. - 201 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants Existing Hezhou WWTP Current capacity: 30,000 m3/d; the wastewater is treated to Completed Positive Class 1A of Pollutant Discharge Standards for Municipal impact 1. Wastewater Treatment Plants (GB18918-2002) before discharged into He River through 1000 m long dedicated pipeline. WWTP of Pinggui Current capacity: 30,000 m3/d; the wastewater is treated to Completed Positive District Class 1A of Pollutant Discharge Standards for Municipal impact 2. Wastewater Treatment Plants (GB18918-2002) before discharged into He River. Jiangbeizhong 0.964 km from Jian’an Road to Shizigang; Completed Positive Temporary Road dike 0.764 km at downstream of Hezhou Bridge in Jiangbeidong impact and reversible 3. Road. negative impact during construction Jiangnan Road Crest road with a length of 1.9 km Completed Positive Temporary dike impact and reversible 4. negative impact during construction Pinggui New Xiwan estuary at the right bank of He River-Xiwan village, 1.28 Completed Positive Temporary District dike km impact and reversible 5. ((Fujiang section) negative impact during construction Pinggui Old Urban Huangshi Hydropower Station-both sides of Xiwan estuary, Completed Positive Temporary Area dike (Fujiang 3.321 km impact and reversible 6. section) negative impact during - 202 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants construction Anju dike Xiwan estuary at left bank of He River-Licun village, 1.445km Completed Positive Temporary impact and reversible 7. negative impact during construction Xuwan East Dike Xiwan tea farm - both sides of Xiwan estuary banks, with a Completed Positive Temporary and Xiwan West length of 3.475km and 3.24km respectively impact and reversible 8. Dike negative impact during construction To be completed by end of 2023 Expansion of Newly built 2 A2/O tanks and 2 high efficient sedimentation 2018 Positive Hezhou WWTP tank; build another 30,000 m3/d capacity so that the total impact capacity can reach 60,000 m3/d. The ultraviolet light will be 9. adopted for disinfection. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He River through 1000 m long dedicated pipe. Shatian WWTP A new WWTP will be built in Shatian town to receive domestic 2020 Positive wastewater in west part of river south. The designed capacity is impact 10. 10,000 m3/d in short term. Total of 0.98 km sewage and storm water pipes will be installed to serve an area of 523 ha. Etang town A set of integrated wastewater treatment facility will be 2018 Positive wastewater constructed with a capacity of 1,000 m3/d before connecting to impact treatment station of Jiangnan WWTP. The wastewater is treated to Class 1A of 11. Pinggui District Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into Pangu River. - 203 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants Liantang town A WWTP with a capacity of 5,000 m3/d and associated 2017 Positive WWTP of Babu wastewater pipeline will be constructed. The wastewater will be impact 12. District treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into Mawei River. Rural wastewater Integrated domestic wastewater treatment facilities and 2019 Positive treatment facilities supporting pipes and engineering wetlands will be provided for impact of Shatian town, villages with a population greater than 200 along Mintian River, Pinggui district Shatian River, Xuewu River and urban section of He River. 13. Total of 33 sets of rural wastewater treatment facilities will be constructed with a capacity of 50-80 m3/d each. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Rural wastewater Integrated domestic wastewater treatment facilities and 2019 Positive treatment facilities supporting pipes and engineering wetlands will be provided for impact of Huangtian town, villages with a population greater than 200 along flooding Pinggui district drainage river at Huangansi, Shizigang and urban section of He River. Total of 18 sets of rural wastewater treatment 14. facilities will be constructed with a capacity of 50-80 m3/d each. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Rural wastewater Integrated domestic wastewater treatment facilities and 2019 Positive treatment facilities supporting pipes and engineering wetlands will be provided for impact 15. of Etang town, villages with a population greater than 200 along Pangu River, Pinggui district Huashan River and urban section of He River. Total of 10 sets of rural wastewater treatment facilities will be constructed with - 204 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants a capacity of 50-80 m3/d each. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Rural wastewater Integrated domestic wastewater treatment facilities and 2019 Positive treatment facilities supporting pipes and engineering wetlands will be provided f. impact of Yangtou town, Total of 15 sets of rural wastewater treatment facilities will be 16. Pinggui district constructed with a capacity of 50-80 m3/d each. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Rural wastewater One set of integrated domestic wastewater treatment facilities 2019 Positive treatment facilities with a capacity of 50-80 m3/d and supporting pipes and impact of Xiwan street, engineering wetlands will be provided for villages with a Pinggui district population greater than 200 along urban section of He River. 17. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Rural wastewater One set of integrated domestic wastewater treatment facilities 2019 Positive treatment facilities with a capacity of 50-80 m3/d and supporting pipes and impact of Bagu street, engineering wetlands will be provided for villages with a Babu district population greater than 200 along urban section of He River. 18. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He Rivers nearby. Phase I Dike Hejiang Bridge-ferry, 9.378 km; flood protection standard: 2020 Positive Positive Temporary 19. Construction under P=5% impact impact and reversible - 205 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants Hezhou Flood negative Control and impact during Drainage construction Improvement Project Phase II Dike Hejiang Bridge-Huashan River, 5.622 km; flood protection 2020 Positive Temporary Construction under standard: P=5% impact and reversible Hezhou Flood negative 20. Control and impact during Drainage construction Improvement Project Flood control and Outlet of Taibai Lake-He River, 1.618km; flood protection 2020 Positive Temporary drainage project of standard: P=5% impact and reversible 21. Taoyuan, Taibai negative Lake area in east impact during new urban area construction Flood control of the Huangshi power station-Xiwan estuary, dike: 3.321km; flood 2020 Positive Temporary section from protection level: P=2% in city urban area and P=10% in town impact and reversible Yangtou town urban area (after regulation) negative 22. section of Fujiang impact during River in Pinggui construction district (urban section) Flood control of the Xiwan estuary-Jigong mountain, 2.725 km; flood protection 2020 Positive Temporary section from level P=2% (after regulation) impact and reversible 23. Liangting village to negative Li village, and impact during Pinggui Mining construction - 206 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants Affairs Bureau to Liangting village of Fujiang River in Pinggui district River rehabilitation Xiwan tea farm-Xiwan estuary; left bank: 3.457km, right bank: 2020 Positive Temporary of the section from 3.178km; flood protection level: P=5% impact and reversible 24. Xiwan tea farm to negative Xiwan Bridge in impact during Pinggui district construction Jiangbei Dike Hejiang Bridge-Wayaotou (including dikes of Jiangbei west 2020 Positive Temporary road, central road and east road); dike: 6.129 km; dike: impact and reversible 25. 6.999km; flood protection level: P=2% (after regulation) negative impact during construction Jiangnan Dike Dike: 4.524 km; revetment: 4.387 km, including Hejiang bridge 2020 Positive Temporary to estuary of Huashan River (dikes of Jiangnan west road, impact and reversible central road and south road); flood protection level: P=2% negative 26. after regulation; dikes for Pangu River (Hezhou avenue to impact during estuary of Pangu River), dikes and revetment for Huashan construction River(Dading village to estuary of Huashan River), flood protection level: P=2%。 Dikes of Pinggui Xiwan village-Shiniudu, dike: 0.87km, revetment: 0.87km; flood 2020 Positive Temporary new urban area protection level: P=2% after regulation impact and reversible 27. (He River section) negative impact during construction Huangtian dike Jigongtou-Dongmuyuan, dike of 3.066km, revetment of 2020 Positive Temporary 28. 3.512km; flood protection standard: P=2% (after regulation) impact and reversible negative - 207 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants impact during construction Hejie East Dike Dike: 6.688km; revetment: 4.573km, including the section of He 2020 Positive Temporary (the downtown River in Hejie; flood protection standard: P=2% impact and reversible 29. section) negative impact during construction Hejie West Planning red line of ancient city of Hejie, revetment: 0.938 km; 2020 Positive Temporary Revetment flood protection standard: P=2% impact and reversible 30. negative impact during construction Flood drainage Total of 14 pumping stations, with a capacity of 6585 kW, 2020 Positive Temporary works in Pinggui 121.06m3/s; 17 sluices, with a capacity of 293.09 m3/s; two impact and reversible district, core urban connecting tunnel. negative 31. area of Hezhou impact during Municipality, Hejie construction town Expand the flood P=5% 2020 Positive Temporary diversion channel impact and reversible 32. in Zhutoudun, negative Xintang village and impact during Chongtang construction River rehabilitation Rehabilitation of flood drainage channel in Xuewu, river 2020 Positive Temporary project dredging and channelization, cleaning river islands. impact and reversible negative 33. impact during construction; positive impact - 208 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants during operation. Demolition of flood Demolition of the weir for water pump of Babu; demolition of 2020 Positive Temporary passage obstacles the private fishery farm from Babu Bridge to Babu water pump impact and reversible on the right bank of He River; demolition of the illegal negative residential structures in the downstream and upstream of Babu impact during 34. Bridge; cleaning of the scattered dirty places from Huangshi construction; dam to Xiadao power station. positive impact during operation. New flood Construction of weirs in Liwu of Pinggui district 2020 Positive Positive Temporary drainage works impact impact and reversible 35. negative impact during construction Rehabilitation ofThe major functions of both rivers are water recharge, flood 2019 Positive Positive Yucai River and drainage, water linkage, landscaping and navigation. The impact impact Aimin River lengths of Yucai River and Aimin River are 1400 m and 1300m 36. respectively. The maximum discharge capacity of the two rivers in 1/20 flood is 38.3 m3/s. Maximum flood level: 106.00 m; crest height: 107.20 m; normal water level during dry season: 105.40m; river width of blue line: 22.2 to 27.4 m. Rehabilitation of Taoyuan River has multi-functions such as water recharge, 2021 Positive Positive Taoyuan River flood drainage, water linkage and landscaping. The total length impact impact 37. of Taoyuan River is 4,600 m. Total of 2,946 m will be rehabilitated. Two sluices will be constructed. To be completed by the end of 2030 Expansion of The ultraviolet light will be adopted for disinfection after treated 2030 Positive 38. Hezhou WWTP by A2/O process. The wastewater will be treated to Class 1A of impact - 209 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He River through 1000 m long dedicated pipe. The capacity will be expanded to 100,000 m3/d. Expansion of Construction of municipal WWTP and sewage pipeline network 2030 Positive Pinggui municipal for Pinggui urban area with a capacity of 80,000 m3/d in long impact 39. WWTP term. The wastewater will be treated to Class 1A of Pollutant Discharge Standards for Municipal Wastewater Treatment Plants (GB18918-2002) before discharged into He River. Shatian WWTP Expansion of Shatian WWTP to 70,000 m3/d in long term. 2030 Positive 40. impact Dikes of Hezhou Zhanqian Avenue-Hejiang Bridge, dikes: 4.458 km, revetment: 2030 Positive Temporary Institute 4.458km. Flood protection level: P=2% after regulation. impact and reversible 41. negative impact during construction Dikes of Fanglin Zhujiadong-Hejiang Bridge, dikes: 3.42 km, revetment: 3.42km. 2030 Positive Temporary High School Flood protection level: P=2% after regulation. impact and reversible 42. negative impact during construction Embankments of Ximuyuan-Matouling, revetment: 6.27km. Flood protection 2030 Positive Temporary Shatian level: P=5% after regulation. impact and reversible 43. negative impact during construction West and east Liantang west dike: Mawei Bridge-Xinjing Bridge, dikes: 5.51 2030 Positive Temporary 44. dikes of Liantang km, revetment: 5.51km; impact and reversible town Liantang east dike: Mawei Bridge-Xiaoshui village, dikes: 4.488 negative - 210 - Table 7-2 Identification Matrix of Related Development Activities Related Development Activities Identified Impacts Flood Reduced SN Development Completion Drainage Details Control Inflowing Activities Date Benefits Benefits Pollutants km, revetment: 4.488 km. impact during Flood protection level: P=2% for mainstream after regulation, construction P=2% for tributary East and west Hejie east dike: Planned bridge-Lijia village, dikes: 1.328 km, 2030 Positive Temporary dikes of Hejie revetment: 1.328km. impact and reversible 45. Hejie west dike: Planned bridge-Sanbuti, dikes: 5.572 km, negative revetment: 5.461km. impact during Flood protection level: P=5% after regulation. construction Flood drainage 5 of flood drainage pump stations with total capacity of 总装机 2030 Positive Temporary works in Pinggui 4585 kW and total drainage flow of 64.31m3/s; 19 sluices with impact and reversible 46. district, core urban total flow of 315.45m3/s; 8 connection tunnels. negative area of Hezhou impact during Municipality, Hejie construction town Xiufeng Lake New construction of Xiufeng Lake with total area of 0.3 km2. 2030 Positive 47. project The normal area during dry season is 0.2 km2. During flood impact period, P=0.33% and water level is 119.50 m. Ailian Lake project Rehabilitation of Ailian Lake (formerly Taibai Lake), covering an 2030 Positive 48. area of 1.21km2. The designed water area is 0.36km2. impact Renovation of east Linking the Liuzhi canal from its starting point with upstream of 2030 Positive Positive Liuzhi canal Taoyuan flood drainage channel; dredging the 7,800 m length impact impact 49. R existing canal; new construction of concrete culvert to recharge Ailian Lake. *Huangansi and Shizigang pump stations under the drainage works are included in the World Bank Loan Hezhou Project. - 211 - Table 7-3 Scenarios for Cumulative Impact Assessment Time The Project Flood Control and Drainage Activities Water Environment Rehabilitation Activities Baseline (2017) None No.3-8: existing dike with length of 16.389 km. No. 1-2: two existing WWTPs Short term (2018-2023) All completed No. 25-37: construction of 48.462 km bank protection; No. 9-24: expansion of one WWTP, construction of 14 pump stations and 17 sluices, and construction of three new WWPTs; 1 weir; construction of 2 river channels and construction of a number of new rehabilitation of 2 river channels. rural wastewater treatment facilities. Long term (2023-2030) All completed No. 41-49: construction of 31.046 km bank protection; No. 38-40: expansion of three construction of 5 pump stations and 19 sluices; WWTPs. construction of 1 new lake, and rehabilitation of 1 lake; rehabilitation of 1 canal. - 212 - Figure 7-2: Schematic Diagram of Related Development Activities in the Cumulative Impact Analysis - 213 - 7.2 Status quo of VEC The current conditions of VEC included in the scope of cumulative impact analysis, i.e. the current conditions of flood control, flood drainage and inflowing pollutant discharge, are summarized based on analysis in the previous sections. The overall condition of the He River Watershed is that floods are frequent and the water environment is poor. 7.2.1 Status quo of flood control and drainage The flood control system of the main watercourse of He River is not completely enclosed. Due to slow construction progress of flood control infrastructure, He River does not have a sound flood control engineering system. The hydropower stations constructed along He River lack effective regulation and management. The existing flood control infrastructures are mainly flood dikes. Except the dikes constructed in a few sections in the urban center of Hezhou against the standard for floods with a recurrence period of 20 years (with a length of about 2.8 km), no dikes or revetments are constructed in the other river sections. There is no flood control facility in Pinggui district and the fold control capacity is weak. There are two existing large reservoirs, namely Guishi Reservoir and Hemianshi Reservoir. However, the flood control function of Guishi Reservoir has not been determined. Constructed a long time ago, the other hydropower stations along He River were are aged and commissioned or transferred to other administration authorities. Therefore, flood regulation is of significant difficulty and the flood control capacity is affected. The current drainage capacity in the watershed is very low. The flood drainage system was constructed a long time ago. Most channels were damaged seriously. Many villages and towns still don’t have any flood drainage facility. Hezhou urban area is located in the karsts basin. The terrain is flat and shallow. Flash flood flows into the city during flood season and, under the effect of backwater, flood drainage becomes difficult. Most of the drainage system in old urban area are rain and sewage combined drainage system. Due to the absence of a separate drainage system, a part of the municipal domestic and industrial wastewater is discharged into Huangansi Drainage Channel, Shizigang Drainage Channel and He River together with storm water through the pipelines under the roads. Poor drainage capacity leads to waterlogging of sewage and stormwater during rainstorms. Currently, the storm water in the current scope of design is discharged into the surrounding environment freely or via the trenches. The size of the pipeline trench is normally 300×300 or d300 pipe. As the pipe is too narrow, blockage and sedimentation is serious. The urban area of Hezhou Municipality within the scope of assessment is the flood-prone area in the He River Watershed. Since 1990, there have been significant floods in the He River Watershed, such as the floods happened in July 1994, June 1998, July 2002, and June 2005. The flood occurred in July 2002 alone resulted in the flooding 127,800 mu cultivated land and - 214 - affected crops in a total area of 964,000 mu and a total population of 1.1615 million. This flood caused a direct economic loss of CNY 2.043 billion. With the poor flood protection system of He River, Guishi Reservoir, a reservoir in the watershed with an active capacity of 155 million cubic meters, has a certain buffer function to the urban area 59 km away down the stream, but its flood prevention function remains undefined. With a low flood control level, the current revetments cannot play their roles of flood control. Substantially in a state of zero protection against floods, some townships have no effective measures to resist floods from the external river. The dike construction works in Hezhou urban area have just started and the flood protection system is not yet enclosed and far from enough to meet the requirements of urban flood control. Besides, there are many structures across He River in the urban area and these structures will involve certain impact on flood passage capacity of He River channel. 7.2.2 Current status of water environment According to the historical monitoring data1, the fecal coliform of some locations at Pinggui section exceeded the standard. All of other parameters meet the Class III standards specified in the Surface Water Quality Standard (GB3838-2002). The non-compliance of fecal coliform is mainly caused by the domestic wastewater discharged along He River. All monitored indicators downstream of He River urban section have satisfied the requirement of Class III of Surface Water Quality Standard (GB 3838-2002)2. The monitoring results as shown in Section 4 indicate that the water quality of the main watercourse of He River satisfies the standard. In general, the current water quality of the main watercourse of He River is fine, but still threatened by the direct discharge of sewage along He River. As analyzed in section 4.4, the current water quality of Lining River, Changlong River, Huangtian Branch Channel and Shizigang Drainage Channel is worse than Class V, thus no satisfying Class IV standard specified in the Surface Water Quality Standard (GB 3838-2002). In addition to the function of flood discharge, these urban inland canals and branch channels are also receptors of industrial and municipal wastewater along He River. Such wastewater is far beyond self-purification capacity of these rivers, resulting in deterioration of water quality of the urban inland canals. The key non-compliance indicators are typical pollutant of municipal wastewater, such as ammonia nitrogen, total nitrogen, total phosphorus and fecal coliform. The pollution of these urban inland canals and channels is mainly caused by municipal wastewater along He Rivers. Incorporation of the polluted water will threat the water quality of the main watercourse of He River. 1 Referring to the EIA Report of Hezhou Pinggui WWTP and the Supporting Pipeline Project (monitoring data developed in June 2012). 2 Referring to the EIA Report of Hezhou WWTP Expansion Project (monitoring data developed in December 2014, July and August in 2015) - 215 - 7.3 VEC Cumulative impact analysis 7.3.1 VEC assessment indicator system The VEC assessment indicator system and assessment standard or limits for this assessment are defined with reference to the flood protection and drainage objectives determined in the top planning for the He River Watershed as well as the relevant standards. See Table 7-4 for detail. Table 7-4 Assessment Indicators of VEC Category Indicator Standard/Limit Basis Benefits of flood Flood control P=2% after regulation Flood Control Standard control standard of (GB50201-94); the main watercourse of Integrated Planning of He River He River Watershed (2010-2030); Urban Flood Control Planning of Hezhou, Guangxi Benefits of flood Drainage Self-drainage capacity: Urban Flood Control drainage capacity 24-hours maximum storm Planning of Hezhou, under 1/20 years flood Guangxi Pumping capacity: 24-hours maximum storm under 1/10 years flood Reduction of flood Annual N/A N/A losses average reduction of flood losses (10,000 CNY) Reduction of Reduction of N/A N/A pollutants to main pollutant watercourse of He (kg/d) River 7.3.2 Cumulative impact analysis 7.3.2.1 Analysis of cumulative flood control benefits According to the analysis presented in section 5.1, the Project, especially Project - 216 - Component No. 1, will produce significant benefits of flood control upon completion. A part of the dike construction works under the Project is also included in the Master Planning of Urban Flood Control of Hezhou Municipality. Superimposition of the benefits of the Project and the other flood control works listed in Table 7-2 will lead to significant improvement of the flood control capacity of He River Watershed. See Table 7-5 for further details. Table 7-5: Analysis of Flood Control Benefits Item Short-term benefits (2023) Long-term benefits (2030) The flood protection level of mainstream and tributaries of He River are Outcomes of the respectively P=2% and P=5%; the design standards of the main watercourse Project dike and cofferdam are Level 2 and Level 5 respectively while that for the tributaries is Level 4. With 61% of the dike construction With the entire dike construction completed for the main watercourse completed for the main watercourse of He River, the flood control standard of He River, the flood control standard for the completed section will reach for the whole He River will reach P=2% after regulation. The flood P=2% after regulation. The fully Outcomes of the protection level of the tributaries is realized flood protection level of the relevant activities P=2%-5%; the design standard of tributaries in Jiangbei Area is dike and revetment is Level 4. The P=2%-5%; the design standard of design standard of cofferdam is Level dike and revetment is Level 4. The 5. design standard of cofferdam is Level 5. After the Project and other linked By 2030, 100% of the planned flood projects are completed in 2023, the control works for the main food control capacity of the urban watercourse of He River will be center of Hezhou Municipality will be competed. The urban inland canals significantly improved. More than and canals in Jiangbei area will be 61% of the dikes along the main connected to fully play function of watercourse of He River will reach the peak flow regulation. Together with flood control standard for floods with He River rehabilitation works under a recurrence period of 50 years. The the Project, Hezhou Municipality will flood control works of the tributaries form a completely closed flood control Cumulative can provide supports to the main system and the flood control capacity benefits watercourse. By then the majority will be significantly improved. With all part of the urban canal and branch the projects completed and flood canal rehabilitation works will be regulation is realized, the main water completed in Jiangbei area and most course of He River will meet the of rivers and lakes will be connected standard for floods with a recurrence to regulate peak flow. However, some period of 50 years. Superimposition of the dikes and revetments are still of the benefits of the Project and the unable to satisfy the flood control other linked projects will generate standard as Hezhou urban area still significant flood control benefits. does not have a fully enclosed flood control system by then. - 217 - 7.3.2.2 Analysis of Cumulative Drainage Benefits Some of the flood drainage works under the Project are also part of the overall planning of flood control in Hezhou Municipality. Superimposition of the benefits of the Project and the drainage works listed in Table 7-2 will greatly improve the drainage capacity of Hezhou Municipality and the drainage capacity of the flood drainage zones in Hezhou Municipality will be significantly increased and the cumulative drainage benefits will be significant. See Table 7-6 for detail. Table 7-6 Analysis of Drainage Benefits Item Drainage capacity in 2023 Drainage capacity in 2030 Outcomes of the Pumping capacity of Shizigang and Huangansi pump stations: maximum Project 24-hours storm under 1/10 years flood Upon completion of most of river After completion of all river rehabilitation works for urban inland rehabilitation works for urban inland canals and canals in Jiangbei area, a canals and canals in Jiangbei area, self-drainage capacity to withstand a self-drainage capacity to maximum 24-hour storm under 1/20 withstand maximum 24-hour storm Outcomes of the years flood will be achieved. under 1/20 years flood will be relevant activities achieved. The pumping capacity of the 14 pump stations to be constructed (excluding The pumping capacity of the 19 Huangansi and Shizigang pump planned pump stations can stations) can withstand maximum withstand maximum 24-hour storm 24-hour storm under 1/20 years flood. under 1/20 years flood. By 2023, the drainage capacity of By 2030, the drainage capacity of Pinggui District, the urban center of Pinggui district, Hezhou urban Hezhou Municipality and Hejie Town center and Hejie town will meet with Cumulative will be greatly improved. 74% of planning standards if 100% of the benefits planned pumping drainage capacity flood drainage works as planned are will be achieved after completion of completed. the Project and some of the linked projects. 7.3.2.3 Analysis of Reduction of Inflowing Pollutants In accordance with the VEC assessment indicator system, the major assessment indicator of cumulative impacts on water environment is the reduction of pollutants of COD and NH3-N flowing into the main watercourse of He River. As a part of the assessment, a quantitative analysis was conducted over the reduction of COD and NH3-N in 2023 and 2030. The wastewater discharge standard adopted by the various WWTPs for the long term (2030) is uncertain and that currently in force is selected. - 218 - Based on the calculation in section 5.1, the reduction of pollutants flowing into He River Watershed is shown in Table 7-7. Table 7-7: Reduction of water pollutants under the Project Treatment capacity Project component Pollutant Pollutant reduction (kg/d) (m3/d) COD 3450 Jiangnan WWTP 15000 NH3-N 405 After the completion of planned urban WWTPs and rural wastewater treatment facilities in the related development activities, the wastewater treatment capacity of Hezhou urban area and townships along He River will be greatly increased to reduce inflow pollutants. The capacity of these WWTPs is calculated based on the current size and design scale. The scale of rural wastewater treatment facility is uncertain. The designed scale is 50-80 m3/d each set. In order to evaluate the maximum impact from the implementation of the related activities, it is assumed in this assessment that the treatment capacity is 80m3/d each set. Expansion by 2030 is not considered. The influent concentrations of COD and NH3-N are 280 mg/L and NH3-N 32 mg/L respectively for the inflowing pollutants before the various WWTPs / facilities are completed. After the completion of these WWTPs and facilities, the effluent concentrations of COD and NH3-N will reach 50mg/L and 5 mg respectively, meeting the Class 1A standard specified in the Discharge Standard of Municipal Wastewater Treatment Plant (GB18918-2002). The reduction of COD and NH3-N in 2023 and 2030 is estimated based on the treatment volume and concentration of pollutant as shown in Table 7-8. It can be seen in Table 7-9 that the Project together with other urban WWTPs and rural wastewater treatment facilities will produce significant benefits of pollutant reduction. By 2023, the cumulative reduction of COD and NH3-N will reach 17,765 kg/d and 2,085 kg/d respectively. By 2030, the cumulative reduction of COD and NH3-N will reach 45,365 kg/d 和 5,325 kg/d respectively. If the possibility of stricter discharge standard to be enforced in the future, the benefits from reduction of pollutants will be greater. Table 7-8: Reduction of inflowing pollutants Reduction of inflowing Reduction of inflowing WWTP/facility pollutants by 2023 (kg/d) pollutants by 2030 (kg/d) COD NH3-N COD NH3-N Hezhou Municipal WWTP expansion 6900 810 9200 1080 Pinggui District WWTP construction 2300 270 16100 1890 Shatian WWTP 2300 270 13800 1620 Etang wastewater treatment station of 230 27 230 27 - 219 - Pinggui District Liantang WWTP of Babu District 1150 135 1150 135 Rural wastewater treatment facilities of 607.2 71.28 607.2 71.28 Shatian town, Pinggui district Rural wastewater treatment facilities of 331.2 38.88 331.2 38.88 Huangtian town, Pinggui district Rural wastewater treatment facilities of 184 21.6 184 21.6 Etang town, Pinggui district Rural wastewater treatment facilities of 276 32.4 276 32.4 Yangtou town, Pinggui district Rural wastewater treatment facilities of 18.4 2.16 18.4 2.16 Xiwan street, Pinggui district Rural wastewater treatment facilities of 18.4 2.16 18.4 2.16 Bagu street, Babu district Total 14315 1680 41915 4920 Table 7-9: Cumulative reduction of inflowing pollutants (Unit: kg/d) Scenario Item COD NH3-N Reduction of the Project 3450 405 Reduction of related activities 14315 1680 2023 Scenario Cumulative reduction 17765 2085 Reduction of related activities 41915 4920 2030 Scenario Cumulative reduction 45365 5325 7.3.2.4 Analysis of cumulative social impacts The Project and other linked projects will reduce the flooded area in The urban center of Hezhou Municipality and reduce the number of flooded houses, buildings, equipment and farmland, thereby reducing the economic losses of industry and agriculture caused by floods. The cumulative reduction of flood losses in 2030 is quantitatively evaluated based on the feasibility study report of Hezhou Urban Water Infrastructure and Environment Improvement Project and Guangxi Hezhou Urban Flood Control Planning. The annual average flood control benefits of the Project and other linked projects are CNY 130.32 million and 72.0533 million respectively, totaling 202.3733 million. The cumulative benefits of flood alleviation is remarkable. The Project and other linked projects can also improve water environment, thereby improving investment environment. These projects will contribute to promotion of economic development, especially tourism and modern service industry. Therefore, theses cumulative impacts will bring social and economic benefits. The implementation of linked projects will also produce negative social impacts similar to the Project. The dike construction, river rehabilitation and drainage pump stations construction components might involve permanent acquisition of land and the lake, river and WWTP construction works (e.g. Xiufeng Lake, Yucai River and Aimin River) to be constructed will also involve permanent land acquisition and resettlement. These social impacts might be cumulated with the Project. Total of 7 rural and 2 urban residents resettlement sites are planned under the Project. The land acquisition and house demolition shall also be properly handled during the implementation of the - 220 - linked projects. The relevant government departments shall ensure that the resettlement house construction will be completed before the demolition and proper measures are implemented for the transition period from house demolition and relocation. It may affect the progress of the Project and lead to social conflicts if the resettlement issue cannot be resolved properly. On the other hand, when the linked projects are constructed concurrently with the Project, the impacts of earth stacking and increased traffic may be cumulated. During construction period, the increased vehicles may affect traffic in the areas along the mainstream. It may lead to traffic congestion and cause cumulative social and economic impacts if the linked projects nearby are constructed at the same time. Therefore, it is necessary to take proper traffic organization and management measures to mitigate cumulative impacts during construction. 7.4 Recommended safeguard measures As discussed in section 7.3, the cumulative impacts of the Project and the linked projects are basically positive, but land acquisition and demolition may cause certain negative impacts. As the Project and linked projects involve various government departments, the multi-departmental mitigation measures are proposed under this assessment to safeguard the cumulative benefits mentioned above and minimize negative social impacts. These measures aim to strengthen enforcement capability of the various departments and promote smooth interdepartmental communication. 1. Establishing a flood early warning system and conducting trainings to promote smart water resources management. The responsible authority is WRB. 2. Strengthening water quality monitoring and regularly tracking the water quality of He River. Hezhou EPB is responsible for setting up monitoring section at Hejie and Fulong ferry and conducting artificial monitoring on a monthly basis. 3. Taking actions to ensure the construction of resettlement houses. The Project should be properly coordinated with the construction of resettlement houses. Demolition shall be conducted only when the construction of resettlement houses is completed. If there are difficulties, a subsidy plan for the transition period should be developed and implemented in a reasonable and effective way so as to complete the construction of the resettlement houses and achieve resettlement of affected people at the earliest possible time. The departments involved include resettlement office of Hezhou urban area and Hezhou WRB. 7.5 Stakeholder participation in the cumulative impact assessment The stakeholders, including relevant departments and APs (outside of the Project influence area) in the area of the assessment, were identified at early stage considering all activities might produce cumulative impacts with the Project. The main departments involved are Hezhou Planning Bureau, Hezhou WRB, Municipal - 221 - Engineering Administration Bureau (MEAB), EPB and resettlement office if land acquisition and demolition is involved. The stakeholder participation during the cumulative impact assessment process is conducted in the following manners: � Collecting relevant planning and information from stakeholders to screen key VEC through consultation with relevant departments and determine the temporal and spatial scope of the assessment. � Consulting the relevant departments and collecting their feedbacks when the draft assessment is ready. � Consulting the relevant departments and collect their feedbacks when the safeguard measures are proposed to promote inter-departmental communications and cooperation during implementation. In addition to consultation with relevant departments, the potential affected public (outside of the Project influence area) were also interviewed. The details of the consultation and results are given in Table 7-10. - 222 - Table 7-10 Stakeholder Participation in Cumulative Impacts Assessment Time Participants Types of participation and key Comments by stakeholders EIA feedbacks contents July-August WRB, EPB, Provision of relevant documents and -- The relevant planning constitute the 2017 MEAB information: Hezhou Urban Flood basis of the identification of the Control Plan, Hezhou Municipality relevant activities under this Master Urban Plan (2016-2030) cumulative impact assessment. (Draft), Implementation Plan for Integrated River Rehabilitation of Urban Section of He River (2017-2020) and Hezhou Municipality Ecological Water System Planning (2014-2030). August 2017 Affected public: Interview: suggestion and There is no wastewater network in Public’s concern about the effluent residents of expectation on the Project and Xiwanzhai. The municipal wastewater discharge shows the urgency of Xiwanzhai linked projects. is discharged into He River after pollutant reduction. The reduction treated by septic tank. The public of pollutants flowing into He River consulted suggested improving the has been selected as a key VEC. municipal utility network of this area. The issue of wastewater treatment for Xiwanzhai area will be incorporated into the linked project of Pinggui WWTP and supporting pipeline construction. - 223 - Table 7-10 Stakeholder Participation in Cumulative Impacts Assessment Time Participants Types of participation and key Comments by stakeholders EIA feedbacks contents August 2017 Affected public: Interview: suggestion and Hezhou Experimental Middle School Public’s concern about the effluent Hezhou expectation on the Project and is located on the right bank of discharge shows the urgency of Experimental linked projects. downstream of Fanglin Hydropower pollutant reduction. The reduction Middle School Station. There is no wastewater of pollutants into He River has been network in Fanglin village. The selected as key VEC. wastewater produced by the 3600 teachers and students is treated by The construction of Shatian WWTP on-site facility and then discharged to and supporting pipeline will help He River. The operation cost of addressing wastewater issue of this wastewater treatment facility is very area. high. The school expects connection to the municipal wastewater treatment The issue of wastewater treatment facility. In addition, Fanglin Junior for the Experimental Middle School High School and Fanglin School of area will be incorporated into the Shatian town in this area also linked project of Shatian WWTP produced great amount of sewage. and supporting pipeline construction. August 2017 Affected public: Interview: suggestion and The residents along Taoyuan canal Public’s concern about the effluent residents along expectation on the Project and expressed supports to dredging works discharge shows the urgency of Taoyuan canal linked projects. and hope the water quality and living pollutant reduction. The reduction environment can be improved. of pollutants into He River has been selected as key VEC. The rehabilitation works of Taoyuan canal will contribute to improvement of living environment - 224 - Table 7-10 Stakeholder Participation in Cumulative Impacts Assessment Time Participants Types of participation and key Comments by stakeholders EIA feedbacks contents for the residents along the canal. August 2017 Aquatic and There are no concentrated Aquatic ecology is no longer regarded livestock “spawning grounds�, rare aquatic as a key VEC in this assessment. husbandry and organisms or migratory fish species veterinary: in the main watercourse of He River. distribution of “spawning grounds� and rare aquatic organisms in main watercourse of He River. September WRB, EPB, Collecting comment and feedback EPB: please clarify the relations of the The contents of linked projects 2017 MEAB on this report. Questions related to Project and Implementation Plan for were sorted out to better present the cumulative impact assessment Integrated River Rehabilitation of the major works. A supplementary in the questionnaire are as follows: Urban Section of He River measure is added for “development (2017-2020). of a sound flood early warning 1. Do you think the relevant system� The corresponding development activities listed in WRB: Strengthening the control and responsible departments are WRB section 7.1.1.3 of the report are management capacity of the joint and MEAB. complete and accurate? If not, operation of reservoir and hydropower please add or provide your station; the flood drainage benefit comment. safeguard measures should be revised to MEAB and WRB. 2. What is your opinion on the - 225 - Table 7-10 Stakeholder Participation in Cumulative Impacts Assessment Time Participants Types of participation and key Comments by stakeholders EIA feedbacks contents results of cumulative impact assessment presented in section 7.3 of the report? 3. What is your opinion on the safeguard measures proposed in section 7.4 of the report? Please add other recommended safeguard measures if any. 4. Please add your comment on chapter 7 if any. - 226 - Stakeholder participation has been conducted through the whole process of cumulative impact assessment. The affected public and relevant experts and departments have been consulted. Their comments and recommendations were summarized in this report. In general, the public are mainly concerned with the issue of effluent discharge. The reduction of pollutants into He River has been selected as key VEC. Through consultation with fishery experts, it was understood that there were no rare aquatic organisms or migratory fish species and no important habitat in He River. On this basis, the “aquatic ecology� is not regarded as a key VEC of this assessment. Relevant departments provided the related planning before the assessment as the basis to identify other existing and proposed projects. The draft report has been circulated to the relevant departments for consultation. The Water Resources Bureau (WRB) and Environmental Protection Bureau (EPB) have provided their comments. Relevant comments have been reflected in the report. - 227 - 8. LAR social impacts and mitigation measures 8.1 Land acquisition and resettlement of the Project Here summarized as follows is the information of LAR under the Project based on the Resettlement Plan for the proposed World Bank Loan Hezhou Urban Water Infrastructure and Environment Improvement Project prepared by Guangxi Guoye Project Management Consulting Co., Ltd., in November 2017. The Project involves a permanent land acquisition of 3760.41 mu, including 47.13 mu state-owned land and 3713.28 mu rural collective owned land (with 2222.01mu arable land) and will affect 759 families and 4563 persons. Buildings to be demolished involve a total floor area of 164,194.71 m2 and an affected population of 3632 of 814 households, including 93207.60 m2 for residential houses, affecting 690 families and 3105 persons. (Rural residential houses to be demolished involve a total floor area of 55,742.29m2 and affect 373 families and 1837 persons; urban residential houses to be demolished involve a total floor area of 37465.31m2 and affecting 317 families and 1268 persons). Ancillary and temporary buildings to be demolished involve a total area of 49,278.64 m2. Buildings in a total area of 14,249.54 m2 owned by enterprises and institutions will be demolished. State-owned shops in a total area of 7,458.93 m 2 will be demolished, affecting 124 tenants. Involving a total area of 1045.67 mu, the temporary land occupation under the Project will affect 307 families and 1849 persons. The related ground attachments and infrastructures, such as fence walls, toilets, and bamboo, power and communication facilities will also be affected. The total population to be affected under the Project is 10044 persons from 1880 families, including 273 persons from 83 families identified as vulnerable groups. 8.2 Measures for mitigating social impacts under the Project Land acquisition and resettlement represents the most significant social impact under the Project. In order to minimize the scope of land acquisition and resettlement and the impacts from the construction activities on local people, measures have been taken, such as optimizing the design proposal. In the preliminary design and feasibility study period, in order to avoid or minimize land acquisition and resettlement, the social assessment team and the design institute have conducted extensive field survey and close consultation with the local officials and residents. Measures, such as optimizing the project design, strengthening project management, improving construction technology and public consultation and participation have been taken to minimize the adverse impact of land acquisition and resettlement. In addition to the measures to reduce land acquisition and resettlement during feasibility study and preliminary design stage, compensation and resettlement plans are developed for permanent land acquisition and resettled people. The compensation standard for permanent land acquisition is based on the relevant regulations and policies of PRC, GZAR, Hezhou city and the Environmental and Social Safeguard Policy (2016) of the World Bank. The resettlement plan is developed on the basis of consultation with local governments and APs and current practices. - 228 - Livelihood restoration program is developed for the farmers whose farmland will be acquired. Compensation and resettlement plan are developed for the rural relocated families, urban relocated families, non-residential relocated families, affected enterprises and institutions, affected ground attachments and infrastructures and affected vulnerable groups. Livelihood restoration plan is also developed for women to protect their right and interests. The specific compensation standards and measures are presented in the Resettlement Plan for the World Bank Loan Hezhou Urban Water Infrastructure and Environment Improvement Project. The LAR and social impacts and mitigation measures are summarized in Table 8-1. - 229 - Table 8-1: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency 1. State-owned floodplain land involves no compensation as the implementation of the Project will not lead to any changes of the nature and ownership relationship of such land. State-owned land: All affected families (AFs) PMO, 2. State-owned allocated land will be replaced with state-owned 47.13 mu will receive cash Owner, land of the corresponding area to be allocated in the vicinity under Floodplain: 34.57 mu compensation. HDAO the Project. 3. Young crop compensation per mu of floodplain land: CNY 2100 /mu 1. Land acquisition compensation: CNY 60,500 per mu of paddy field; CNY 51,800 per mu of dry land; CNY 47,000 per mu of forest land. To be prudent, the compensation criteria for other types of land is set at CNY 47,000 /mu. Permanent land acquisition 2. Crop compensation: CNY 1600-2100/mu depending on the crop types. 3. Compensated land: the planned industrial land equal to 10% of acquired agricultural land will be allocated to the affected rural 3713.28 mu collective collective economy organizations. land in total, including 4. All APs will receive: i) employment and revenue generation 972.08mu for paddy opportunities during project implementation; ii) free employment field,1249.93 mu for supports and vocational training. 4563 persons from 759 PMO, dry land, 533.52 mu 5. Registered population at or above the age of 16 entitled to rural households Owner, for forest land and collectively-owned land contracting at the time of land acquisition HDAO 957.75mu for other will receive subsidies for rural pension insurance to the farmers types of land. AFs: who lost their land. Such subsidies will be calculated based on the 759; affected persons number of people affected by, and the frequency and scope of (AP): 4563. land acquisition. The minimum subsidy for each land acquisition equals 60% of the average wage of workers employed by urban units in the region in the previous year times the per capita area of land acquired from local farmers. Where the per capita area of land acquired from local farmers exceeds 8 mu after one or multiple land acquisitions, the surplus part will not receive any pension insurance subsidy. Where a farmer household whose land is totally acquired and the per capita area of land acquired from the affected HHs is less than 1 mu, the subsidy will be 230 Table 8-1: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency calculated on the basis of 1 mu. Total land occupation: occupation Temporary 1045.67 mu, including 1849 persons from 307 PMO, 434.96 mu paddy field, Compensation for temporary land occupation: CNY 3900 per mu land households Owner; 423.58mu dry land; of paddy field; CNY 3400 per mu of forest land HDAO 187.13mu forest land; AFs: 307; AP: 1849. 1. The PMO provides two types of resettlement for households affected by housing acquisition to choose from at free will: monetary compensation and property right replacement. Residential houses and ancillary and temporary structures 2. Monetary resettlement: monetary compensation (generally higher than the replacement price) is provided for all persons whose houses are demolished. Such compensation includes housing compensation and housing decoration compensation after assessment. Housing compensation and housing decoration compensation: The assessment is conducted by an intermediary agency with good credit-standing and good 1. Demolition of urban reputation commissioned under joint agreement by the residential houses: demolishing party and the affected party and the 37465.31m2, brick and 1268 persons from 317 compensation is effected based on the assessed price. PMO, concrete structure; households 3. Property right replacement: built housing is provided and Owner; AFs: 317; APs: 1268. housing decoration is compensated. HDAO 2. Demolition of urban Provision of built housing in the ratio of 1:1. If the area of built temporary houses: housing is greater than the demolished area, the relocated 18689.74 m2. family needs to buy the exceeding area at market price. Provision of housing decoration compensation. The construction unit and the relocated family will commission an independent qualified intermediaries to assess the value of decoration, based on which monetary compensation will be provided. 4. Provision of relocation subsidy and temporary housing subsidy at a rate of CNY 10 / m2 or provision of public housing. 5. Provision of CNY 5,000/family as an one-off incentive to those who sign the LAR compensation agreement and hand over 231 Table 8-1: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency the housing within the specified deadline. 6. Cash compensation will be made for urban temporary housing at a price assessed based on market price by an independent and qualified intermediary comissioned jointly by the construction unit and the relocated household. 1. The PMO provides two types of resettlement for households affected by housing acquisition to choose from at free will: monetary compensation and homestead replacement. 2. Monetary compensation is made based on the housing replacement price of CNY 1000 to 1300/m2 for brick structure. For households choosing monetary replacement for their main houses, compensation on the main house homestead will be made at the assessed land price for reallocation of resettlement homestead. 1. Demolition of rural 3. Homestead resettlement: Each household is entitled to one residential houses: homestead and each demolished homestead will be 55742.29 m2; brick compensated with one resettlement homestead in an area of and concrete no more than 120m2; the inadequate part will be compensated 1837 persons from 373 structure; AFs: 373; at the assessment price. The main house to be demolished households APs: 1837. will be compensated for at the replacement price of the same 2. Demolition of rural standard as for monetary compensation of CNY 1000 to 1300 ancillary houses: for brick structures. The government will be responsible for 30588.89 m2. providing water supply, power supply, access road and site leveling for the resettlement area as well as the supporting public infrastructures such as schools and hospitals; water and electricity will be delivered to the gate of each household and then connected by the household into their houses. 4. Provision of relocation subsidy and temporary housing subsidy at a rate of CNY 10 / m2. 5. Provision of CNY 5,000/family as an one-off incentive to those who sign the LAR compensation agreement and hand over the housing within the specified deadline. 6. Monetary compensation will be provided for rural ancillary 232 Table 8-1: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency housing unexceptionally at a standard of CNY 100-700/m2 depending on the building structure. Compensation for the acquired land will be made at the standard for acquisition of rural homesteads. Hezhou Municipal Land Resources Bureau (LRB), Health and Family Planning Government, public institutions and Relocation and reconstruction of Hezhou Health and Family Commission, Hezhou WRB, Planning Commission and Babu District Transportation Bureau. Transportation Bureau of Hezhou WRB and LRB choose monetary compensation for the Babu District, Guangxi demolished buildings. Totally 11 government, Guidong Electric Power Guidong Electric Power Limited Company: monetary enterprises public institutions and Limited Company, Yingshi compensation for its office building to be demolished at assessed PMO, enterprises will be Primary School of Huangshi value and new office building will be constructed. Owner; affected with a Town, Xiadao Power Station Yingshi Primary School and Xiadao Primary School: relocation. HDAO demolition area of of Hezhou Pengyuan 2 Hezhou Minfeng Industrial Limited Company and Hezhou 14249.54 m Hydropower Development Huangshi Power Station Limited Company: monetary Limited Company, Fanglin compensation for the production losses due to stoppage during Hydropower Station of project construction. Hezhou Minfeng Industrial Limited Company, Hezhou Huangshi Power Station Limited Company Demolition of shops: Compensation for the business losses and relocation cost to be PMO, Shops 527 persons from 124 7458.93m2; AFs: 124; made on the basis of replacement price ratified according to the Owner; affected shop tenants. APs: 527 relevant compensation standard. HDAO 233 Table 8-1: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency Sewers: 220 m; Land attachments All APs or owners will Tombs: 53; power The APs will receive cash compensation. Sewage pipe: CNY receive equivalent cash poles: 42; 300/m; power pole: CNY 150 each; communication pole: CNY 150 compensation. PMO, communication poles: each; wall: CNY 70 /m2; bamboo: CNY 1-4 / per bamboo; trees: The land attachments Owner; 22; bamboo: 26489; CNY 10-180 / tree; graves: CNY 5500 each. planted or constructed after HDAO wall: 700m2; trees: The trees described above will be compensated at the actual the cut-off date will not be 15162; transformer: 1 assessed value on the basis of the guiding price. compensated. set. (1) The local Civil Affairs Bureau and the Labor and Social Security Bureau will be responsible for including these families in the social security schemes. Vulnerable group (2) Provision of pension insurance. (3) Provision of new rural cooperative medical insurance paid by PMO, All affected vulnerable 83HH, 273 persons the collective unit. Owner; groups (4) The local rural credit cooperatives and banks can provide the HDAO vulnerable groups with small loans. (5) Provision of project-related employment opportunities. (6) Provision of project-related vocational trainings to vulnerable groups. (1) Create employment and livelihood opportunities for women. (2) Ensure women participation. PMO, (3) The local government and resettlement office shall ensure the Female 4148 persons Owner; female has the same rights as male in terms of land property. HDAO (4) Gender discrimination shall be eliminated to encourage women to create their own business. 234 8.3 Public participation and consultation During preparation of the project plan and the resettlement plan, the resettlement consultant team identified all the stakeholders and conducted various interviews, meetings and consultations on the land acquisition and compensation policy. The stakeholders of the Project can be divided into three different categories, i.e. governmental departments, construction unit/contractor and APs. The resettlement consultant team conducted equal consultations with the APs in the project area to inform them of all aspects of the Project. 91.17% of the public are very supportive or supportive to the implementation of the Project. Only 8.83% of the consulted persons hold neutral attitude to the Project. Basically, no one expressed objection to the Project. 72.06% of respondents believe the Project would be very beneficial or beneficial. The stakeholders in the project area have understood the project information through public consultation and expressed their support to the Project. Meanwhile, concerns were also expressed over possible reduction of income and temporary impacts from the construction activities on their livelihood. In order to properly and promptly address the issues and demands of the APs, public consultation will continue before the commencement of the project construction and implementation of the resettlement plan so that all the problems may be resolved. The implementation agencies shall organize resettlement workshops/meetings appropriately. For details, please refer to Chapter 10 for arrangements of public consultation during the implementation of the Resettlement Plan (RP). 8.4 Institutional arrangement and development 8.4.1 Resettlement-related institutions In the implementation process of the Project, a top-down organization structure must be developed to plan, coordinate and monitor the resettlement activities. See Figure 8-1 for the organization chart. - 235 - PLG Municipal PMO Babu District Pinggui District Hezhou EPB HDAO HDAO WRB; MEAB Resettlement LAG ... LAG LAG ... LAG External Monitoring Village Committee Village Committee ( (Community ) Office) (Community Office) APs APs PLG = project leading group; LAG = land acquisition group; HDAO = land acquisition and resettlement office; APs = affected persons; WRB = water resource bureau; EPB = environmental protection bureau; MEAB = municipal engineering administration bureau Figure 8-1: Institutional Arrangements for Resettlement 8.4.2 Institutional organization and responsibilities 1. Project leading group (PLG) The Project Leading Group of World Bank Loan Hezhou Urban Water Infrastructure and Environment Improvement Project is the highest leadership agency in the implementation of the Project to provide policy guidance and facilitate coordination at municipal level to support the implementation of the Project. 2. Project management office (PMO) Hezhou World Bank Project Management Office is headed by Hezhou Municipal Development and Reform Commission (DRC) and fully responsible for the overall plan of and providing guidance on the land acquisition and resettlement work of the Project. Its specific duties include: providing guidance on the resettlement work in accordance with World Bank’s Resettlement Policy, submitting reports on resettlement work to the World Bank, conducting preliminary review of the resettlement plan and implementation plan submitted by project owner and submitting such plans to the municipal government for approval; supervising and inspecting the status of implementation of resettlement plan and payment and use of compensation - 236 - fund; supervising and reporting to the World Bank the progress of resettlement implementation; and conducting internal monitoring. 1. Urban land acquisition and resettlement office (HDAO) The Project will involve Babu District and Pinggui District and the Urban Land Acquisition and Resettlement Office (HDAO) is responsible for the specific work of land acquisition and resettlement. Its specific responsibilities include: developing resettlement plan and implementation plan; properly carrying out the resettlement work following the plan of PMO; inspecting the status of implementation of resettlement work; iv) soliciting comments from the relevant departments and individuals and address complaints and appeals promptly; submitting timely report to World Bank on issues, comments and suggests encountered in the process of land acquisition and resettlement and assisting PMO in internal monitoring. 2. Village committee resettlement working group The major responsibilities include participating in socio-economic and project impact survey; organizing public consultation; disseminating resettlement policy; organizing public hearings; selecting resettlement sites; allocating housing land for AFs; allocating and managing compensation fees; organizing production and training activities; delivering comments and suggestions of AFs to the higher authority; reporting the resettlement progress; and providing assistance to the vulnerable groups. 3. External independent monitoring and evaluation agency The independent external monitoring agency is responsible for monitoring resettlement work, collecting comments and feedbacks from the affected institutions and persons in a timely manner; and reporting and submitting recommendations to the PMO and IAs. The specific duties include: investigating the social and economic conditions in the planned area and preparing and submitting social baseline survey report to the World Bank; estimating the specific impacts and progress of livelihood restoration; analyzing data collected and monitoring the whole process of implementation of the resettlement plan; preparing and submitting to the PMO and implementing agency the resettlement progress report; and preparing and submitting half-year monitoring reports to the World Bank; carry out resettlement assessment at least twice a year and reporting to the project owner and the World Bank. 8.5 Grievance redress mechanism The APs will sign the agreement to confirm their rights and entitlements if they are satisfied with the proposed compensation. A procedure for information disclosure in the process of resettlement is helpful to increase the transparency of the Project. Through information disclosure, the APs will be informed of the multiple complaint channels (including village committees, departments, PMO, land acquisition and demolition office, external monitoring agency, government petition office, and court) and a variety of ways (such as petition and telephone) to express complaints and appeal. In the process of development and implementation of the RP of the Project, great - 237 - attention will be paid to the participation of APs and a grievance redress mechanism will be established to handle complaints and appeals from the APs in the following procedure: Stage 1: If not satisfied with the resettlement plan, the APs can express their complaints to the village committees in oral or written form; oral complaints must be handled and recorded in writing by the village committees or street offices / town or township authorities. Such complaints shall be addressed within one week by the project group at village level, village committee, or street / township authorities. Stage 2: If the APs are still not satisfied with the resolutions made in Stage 1, an appeal can be filed to the PMO after such resolution is received and the PMO shall make a further resolution within 2 weeks. Stage 3: If the APs are still not satisfied with the resolutions made in Stage 2, an appeal can be filed to the HDAO after such resolution is received and the HDAO shall make a further resolution within 2 weeks. Stage 4: If the APs are still not satisfied with the resolutions made in Stage 3, an appeal can be filed to the External Monitoring Agency after such resolution is received and the External Monitoring Agency shall make a further resolution within 2 weeks. All the complaints and appeals (in oral o written form) shall be reported to the World Bank in the resettlement monitoring report. Stage 5: If the APs are still not satisfied with the resolution made in Stage 4, an appeal may be filed to the government petition office after such resolution is received. The petition office shall make a further resolution within 2 weeks. The APs may directly file a lawsuit to the civil court if he / she is not satisfied with the existing GRM procedures or resolutions made in any of the above stages. 8.6 Monitoring and evaluation arrangements In order to ensure the smooth implementation of land acquisition and resettlement work and proper resettlement of the APs, the resettlement progress will be monitored and evaluated regularly in strict accordance with the terms specified in World Bank’s Operation Policy (OP 4.12) of Involuntary Resettlement and Guidance on Resettlement Monitoring and Evaluation for Business in PRC. Such monitoring shall comprises of two parts, namely the internal monitoring carried out by the resettlement agency and the external independent monitoring. The internal monitoring will be conducted by the PMO to ensure the resettlement activities are carried out in accordance with the principles and timetable specified in the Resettlement Plan. The purpose of internal monitoring is to enable the resettlement institutions to maintain excellent functions during implementation. The external monitoring refers to the regular monitoring and evaluation on resettlement activities conducted by the independent monitoring agency (IMA). This external monitoring shall be undertaken by a competent IMA. - 238 - After the completion of the project, post-project evaluation will be conducted on the basis of monitoring and evaluation results to evaluate the experiences and lessons for reference in terms of land acquisition and resettlement for future projects. The owner of subproject will commission the external monitoring agency to conduct post-project evaluation. The post-project evaluation agency will develop a terms of reference and evaluation indicator system for the post-evaluation, conduct social and economic survey and preparing and submitting the LAR post evaluation report to the PMO and World Bank. - 239 - 9. Alternative Analysis 9.1 Purpose and principles The purpose of alternative analysis is to minimize the environmental impact by optimizing the project design from environmental perspective through comparative analysis of a number of alternatives that may be selected for the Project. The general principles for alternative analysis include: 1. Quantitative comparison: quantifying the environmental impact from project implementation as much as possible for each alternative; 2. Comprehensive comparison: conducting a multi-dimension comparison and analysis of the alternatives from the environmental, technical, economic, and social perspectives; 3. Compatibility comparison: The selected alternative shall be compatible with relevant development planning and standards and the local conditions. 9.2 With-/Without-project analysis Without-project alternative refers to the scenario where the project will not be implemented. Analysis was conducted from the perspectives of environmental benefits and costs and social and economic development, with results summarized in Table 9-1. Table 9-1 With-/Without- Project Comparison Category With-Project Without-Project (1) Improved urban safety, improved flood risk control capacity. The flood control standard of He River main watercourse is improved to floods with a recurrence period of 50 years; flooded (1) The current status can be area is reduced by 13.1 km2. The maintained, i.e. the vegetation will avoided economic loss amounts to CNY remain intact; 2044 million. The flood control standard (2) No change on land value (no land for the inner urban rivers is improved to occupation); the permanent land floods with a recurrence period of 20 acquisition is reduced by 3760.41mu; years. Flooded area is reduced by 3.1 the temporary land occupation is Advantages km2. The avoided economic loss reduced by 1045.67 mu; the house amounts to CNY 248.74 million. demolition is reduced by 93207.60 (2) Reduced pollutant load to rivers, m2; impact on the 1880 families or improved water environment; load 10044 people can be avoided. reduction thanks to development of (3) No environmental impacts in Jiangnan WWTP includes: COD terms of noise pollution and 1259.25t/a, BOD 602.25t/a, SS vegetation damage will be generated 821.25t/a, TN 219t/a, NH3-N 147.83t/a, during the construction stage. and TP 2t/a; sewage interception along Huangtian Branch Canal, Guposhan Drainage canal, Huangansi Drainage canal, Shizigang Drainage canal helps - 240 - Table 9-1 With-/Without- Project Comparison Category With-Project Without-Project to achieve a load reduction of 15000 m3/day and the reduction of COD 1888.88 t/a and NH3-N 221.75 t/a discharged into He River in an uncontrolled way. (3) Improved hydrology and municipal infrastructure. (1) Flood control dikes are incomplete. At the discharging points of drainage system the elevation is low. When the water river in the He Rive is high, backflow occurs easily. In the event of a flood with a recurrence period of 50 years, the consequences will be a flooded area of 13.1 km2 and an economic loss of CNY 2044 million. (1) Land occupation and house (2) Covered-up inner urban rivers, demolition will happen. The project will increasing use of impermeable involve permanent land acquisition of pavement and the decreasing storm 3760.41 mu and temporary land water storage capacity in the city occupation of 1045.67 mu; the Project would end up with a flooded area of will also involving demolition of 3.1 km2 and an economic loss of CNY buildings in a total area of 93207.60 m2, 248.74 million in the event of a flood Disadvantages affecting 1880 families or 10044 people. with a recurrence period of 20 years. (2) During construction there will be (3) The Shizigang, Huangansi and vegetation damage, and noise and Taoyuan Drainage Canals are narrow flying dust issues. and have difficulty of flood passage. (3) During construction there will be In addition, domestic sewage from impacts on traffic and daily travel of local residents are discharged into local residents. the canals, resulting in poor water quality in dry seasons featuring in high turbidity and strong odor. Pollutants such as ammonia and TP are worse than Class V standards, making He Rivers “black and stinky water bodies�. Without sewage interception along the He River, sewage is discharged into He River without proper treatment, causing deteriorating water quality. From social and environmental perspectives, the with-project alternative is more Summary preferable than the without-project alternative. It is shown from Table 9-1 that, although the without-project scenario does not generate additional environmental impacts from project construction, problems of poor flood dike, discharge outlets of low elevation, covered-up urban inland canals and decreasing flood storage capacity still exist. A flood with a recurrence period of 50 years in He River would end up with a flooded area of 13.10 km2 and a total economic loss of CNY 2044 million. A flood with a recurrence period of 20 years in He River would end up with a flooded area of 3.1 km2 and a total economic loss of CNY 248.74 - 241 - million. The narrow urban inland canals restrict their flood carrying capacities and continuous discharge of domestic sewage from residents along He Rivers without any treatment would end up with deterioration of water quality in He River. For the with-project alternative, although implementation of the Project will bring some environmental impacts, most of these impacts, except the irreversible ones from permanent land acquisition, can be avoided or mitigated through proper environmental protection measures. Implementation of the Project will end up with improved flood management capacity of He River and help reducing the economic loss by CNY 204.4 million in the event of a flood with a 50-year recurrence period. In addition, it will also be helpful to improving Hezhou’s city appearance and protecting the people's health and protect the water quality of He River and promote integrated rehabilitation of the He River and the urban inland canals. The amount of COD and NH3-N discharged into He River will be reduced by 1259.25 t/a and 47.83 t/a. The amount of sewage interception along Huangtian Branch Canal, Guposhan Drainage Canal, Huangansi Drainage Canal and Shizigang Drainage Canal may reach 15,000 m3/d and the amount of COD and NH3-N discharged in an uncontrolled way into He River will be reduced by 1888.88t/a and 221.75t/a, contributing remarkably to rehabilitation of black and odor urban waters. Therefore, this alternative will be helpful to protection of ecological safety and improvement of Hezhou’s urban environment. Polluted rivers will be converted into livable landscaping areas and value of local land will be increased. In addition, the Project can also facilitate the urban and rural economic and social development and generate significant social, environmental and economic benefits. Therefore, from the perspective of promoting social and economic development and environmental protection, the with-project alternative is better than the without-project alternative and the project implementation is necessary. 9.3 Dredging alternatives The Project involves dredging of various rivers and drainage canals. Four different dredging methods were considered as shown in Table 9-2. Table 9-2 Comparisons of dredging methods Contents Method 1 Method 2 Method 3 Method 4 Cutter suction Grab dredger Suction Description of methods Direct digging dredgers (boat) (boat) dredging Technical With certain With certain Low technical Low technical difficulties and technical technical difficulties difficulties feasibility difficulties difficulties Fit for rivers Fit for rivers Fit for rivers Fit for rivers with Construction with wide with wide with wide wide surface and conditions surface and surface and surface and certain depth Technical certain depth certain depth certain depth Construction Low Low Low Low difficulties High efficiency High Low efficiency High Construction and short efficiency and and long efficiency and duration duration short duration duration short duration Temporary storage Requiring a Requiring a Requiring Requiring a of sediments temporary temporary temporary temporary dredged de-watering site de-watering storage and de-watering - 242 - Table 9-2 Comparisons of dredging methods Contents Method 1 Method 2 Method 3 Method 4 site temporary site de-watering site CNY 100-150 CNY 60-100 / CNY 100-120 CNY 100-150 / O&M cost / m3 dry m3 dry / m3 dry m3 dry sediment sediment sediment sediment Impacts on Insignificant Insignificant Insignificant Insignificant sensitive receptors Water environment Insignificant Significant Insignificant Negligible impact disturbance disturbance disturbance disturbance Certain Significant Limited odor Limited odor degree of odor impact impact during Environmental impacts impact during odor impact during dredging. The dredging. The during dredging and odor impact odor impact dredging and Odor impact de-watering. distance from distance from de-watering. The impact de-watering de-watering site The impact distance is site is is approximately distance is approximately approximately 30 m. approximately 100 m. 30 m. 30 m. Mainly from Some degree Mainly from boat boat and Limited noise of noise and pump grabber from impact from Noise impact operation. Noise operation. manpower submersible impact limited, Noise impact operation. pumps, 70-80dB(A) limited, 60-70dB(A) 75-85dB(A) 70-80dB(A) Storage site need land impacts Dewatering site Dewatering Dewatering Social Temporary land 50m2, needs site needs site needs acquisition Dewatering land1500m2 land1500m2 land1500m2 site needs land1500m2 - 243 - Table 9-2 Comparisons of dredging methods Contents Method 1 Method 2 Method 3 Method 4 Advantage: simple Advantage: method; Fit Fast speed Advantage: for narrow and high simple space such as Advantage: Fast efficiency in method; Fit ditches and speed and high construction. for narrow buried efficiency in Fit for wide space such as culverts. construction. Fit rivers with ditches and Using for wide rivers large dredging buried submersible with large load. culverts. pumps can Main advantage / dredging load. Disadvantage: Disadvantage: reduce some disadvantages Disadvantage: Significant low efficiency. odor technically disturbance to Requiring not problems. difficult. river and only sediment Disadvantage Requiring significant de-watering : some noise sediment odor impact. site, but also problem s dewatering site. Requiring temporary during sediment storage site. dredging. dewatering Significant Requiring site. odor impact. sediment dewatering site. For He River main channel, Alternative 1 is recommended. For the Huangansi Drainage canal, and Shizigang Drainage canal, Recommended Alternative 4 is recommended. For Huangtian Conclusions alternatives Branch Canal, Guposhan Drainage canal,and East Trunk Canal, Alternative 3 + Alternative 4 is recommended as the construction space is available. For different rivers and drainage canals, different dredging methods can be used. Involving huge dredging load, He River, with wide river surface and favorable depth, have the conditions needed for operation of large dredging vessels. Alternative dredging methods include cutter suction dredgers or grab dredger. The recommended option is the cutter suction dredgers because of its higher dredging efficiency, shorter dredging duration, insignificant disturbance to water body and the reduction of duration of impacts from the sediment dewatering site. For Huangtian Branch Canal, Guposhan Drainage Canal, Huangansi Drainage Canal and Shizigang Drainage Canal, due to work space restrictions, large dredging vessels cannot be used. The alternatives include direct digging or suction dredging. Because the urban inland canals have poor water quality and stinky sediments due to perennial reception of sewage; in addition, located in the densely-populated urban area, in-water suction method is recommended in order to reduce the odor impacts on the environmentally sensitive sites. For Huangtian Branch Canal, Guposhan Drainage canal and the upstream section of East Trunk Canal, Alternative 3 + Alternative 4 is recommended, i.e. construction plant dredging plus suction dredging, as these construction sites are located far away from the residential areas and mostly farmland and unused land. 9.4 Alternatives for hydropower station improvement - 244 - In the feasibility study stage, several alternatives are proposed and compared for improvement of Huangshi Hydropower Station, Fanglin Hydropower Station and Xiadao Hydropower Station. The results of such comparison are summarized in Tables 9-3 to 9-5. Table 9-3 Comparison of upgrading alternatives for Huangshi Hydropower Station Alternative 3: Alternative 2: Alternative 1: Demolishing Upgrading the Upgrading the the Content hydropower hydropower hydropower station after station station after buy-back buy-back After buy-back, After buy-back, demolishing the keeping the workshops, Keeping the power power station and turbine, sluice station; upgrading the Description upgrading the gate and existing water gate to existing water associated a hydraulic lift gate. gate to a structures of the hydraulic lift gate. hydropower station. CNY 24.03 million (CNY 0.45 million for CNY 28.45 demolishing existing million (CNY 6 water gate; CNY 22 million for CNY 7.00 million million for installing a buy-back; CNY (CNY 6 million for Engineering cost new gate; CNY 1.58 22 million for new buy-back and 1 million as gate and CNY million for compensation for 0.45 million for demolishing). temporary shut-down demolishing of the station during existing gate) construction) Construction duration Long Long Short Backwater Backwater upstream upstream the the gate reduced from gate reduced He River section 1.6 m to 0.64 m in from 1.6 m to will be restored to Flood control benefits terms of water level 0.64 m in terms its original natural and 7.8 km to 3.1 km of water level and status. in terms of length. 7.8 km to 3.1 km in terms of length. Impact on Limited Limited Limited sensitive sites Requiring both Requiring both Requiring only demolition of existing demolition of demolition of Environmental concrete gate and existing concrete Water existing concrete impact installation of a new gate and environment gate, the duration adjustable hydraulic installation of a impact of disturbance on lift gate; the duration new adjustable water quality is of both construction hydraulic lift gate; short. and disturbance on the duration of - 245 - Table 9-3 Comparison of upgrading alternatives for Huangshi Hydropower Station Alternative 3: Alternative 2: Alternative 1: Demolishing Upgrading the Upgrading the the Content hydropower hydropower hydropower station after station station after buy-back buy-back water quality are long. both construction and disturbance on water quality are long. Land acquisition No No No and resettlement The government Compensation in an becomes the CNY 1.58 million Benefits from amount of CNY 1.58 owner after / year as power million for production Social impact buy-back. economic loss of generation suspension during Compensation is power generation construction. not needed. To be re-opened To be re-opened after after temporary Placement of temporary shut-down 15 people losing shut-down for staff for one year. Nobody their jobs. one year. Nobody loses job. loses job. Advantage: enabling adjustment of flood control through the adjustable Advantage: enabling hydraulic lift gate adjustment of flood and the creation control through the of a waterfront Advantage: He adjustable hydraulic landscape in the River course will lift gate, and the upstream and be restored creation of a improved original natural waterfront landscape environmental condition; no in the upstream and benefit. No need impact on flood Main advantage/disadvantages improved of compensation carrying capacity; environmental for the Disadvantage: benefit. suspension of No upstream Disadvantage: longer power generation waterfront construction duration during landscape will be and greater construction. created. investment needed. Disadvantage: longer construction duration and more investment needed. Long implementation duration leading - 246 - Table 9-3 Comparison of upgrading alternatives for Huangshi Hydropower Station Alternative 3: Alternative 2: Alternative 1: Demolishing Upgrading the Upgrading the the Content hydropower hydropower hydropower station after station station after buy-back buy-back to too much uncertainty. Conclusions Alternative 1 is recommended. Based on the above comparisons, Alternative 1 will reduce the impact of the gate dam on the flood carrying capacity, reduce the upstream flooding loss (which increases by approximately CNY 0.5 million each year), and avoid difficulties in flood control. At the same time, with the gate dam of the hydropower station upgraded, an upstream waterfront landscape will be created and the flood regulating capacity will be improved. The environmental benefits will be improved thanks to improvement of flood carrying capacity. The disadvantages are that the long construction duration will lead to loss of revenue from power generation and generate some environmental impacts, most of which are temporary. In Alternative 2, the government becomes the owner after buy-back, therefore only the buy-back cost will be needed and compensation to losses due to power generation suspension is not needed. However, this alternative has the disadvantage of too much uncertainty due to long implementation time. In Alternative 3, the construction period is very short. However, after the removal of the gate dam, power generation will be permanently terminated, resulting in a yearly loss of approximately 1 million KW in power generation and 15 jobless employees of the hydropower station. These are permanent impacts and can cause greater social impacts than Alternative 1. After the comprehensive comparison, Alternative 1 is recommended (upgrading the hydropower station gate dam). Table 9-4 Comparison of upgrade alternatives for Fanglin Hydropower Station Alternatives Alternative1: (1) Alternative 2: (1) Alternative 3: (1) keeping Fanglin demolishing the keeping the power Bridge; (2) power station; (2) station; (2) removing the slider demolishing and demolishing and gate on the dam reconstructing reconstructing Fanglin Bridge as Fanglin Bridge as planned (half-width planned (half-width to be constructed in to be constructed in short term and short term and second half-width second half-width after the power after the power station is demolished station is demolished according to the road according to the road planning); (3) planning); (3) removing the gate removing the gate dam. dam and building another gate dam at - 247 - Table 9-4 Comparison of upgrade alternatives for Fanglin Hydropower Station a different location downstream. Scope (1) Demolition of (1) Demolition of (1) Demolition of the slider gate of Fanglin Hydropower bridge and gate dam Fanglin station; (2) and keeping the Hydropower Demolition of Fanglin power station; (2) Station; (2) Bridge and Construction of a Keeping Fanglin construction of a new new 84m gate dam Bridge; bridge with 226 m with water retention span and 15 m width height of 4.5 m; (3) (half-width). construction of a new Fanglin Bridge with 226 m span and 15 m width. Water gate / / The new water gate design is located between the two power stations in the downstream and will adopt the continuous hydro-lifting water gate design, totally having 12 holes with a single-hole width of 7m. After upgrading, the hydraulic dam will be sized 12 m * 7 m * 4.5 m. Bridge design / The approach The approach bridges on both ends bridges on both ends will adopt 3-span will adopt 3-span 20m prefabricated 20m prefabricated hollow slab beam hollow slab beam structure with a structure with a beam height of 0.95 beam height of 0.95 m. The main bridge m. The main bridge will adopt will adopt 30+40+30m 30+40+30m cast-in-place cast-in-place pre-stressed pre-stressed concrete continuous concrete continuous box girder with a box girder with a beam height of 2.0m. beam height of 2.0m. The navigation The navigation requirements for requirements for Class 4 navigation Class 4 navigation canal with a net width canal with a net of 30m and a net width of 30m and a height of 7m will be net height of 7m will satisfied. be satisfied. Impact on flood There will be some No impact The back water control back water from the effect is relatively old bridge and the smaller with 2.56 km water gate bottom. back water length. - 248 - Table 9-4 Comparison of upgrade alternatives for Fanglin Hydropower Station The back water The elevation of length is 6.8 km. upstream dike needs The elevation of be increased. upstream dike needs be increased. Additional area No 128m2 brick house 128m2 brick house of LAR Placement of 79 employees need 79 employees need Nobody gets unemployed reemployment reemployment unemployed Impact on A new small A new small irrigation 1600 mu paddy field irrigation irrigation pumping pumping station and dry land to be station needs to be needs to be built as affected. No built as compensation for the compensation compensation for affected farmland of measures. the affected 1600 mu. farmland of 1600 mu. Impact on No environmentally No environmentally No environmentally environmentally sensitive sites sensitive sites sensitive sites sensitive sites Impact on water Involving only the Since the Since both environment demolition of the construction demolition of existing existing water gate, activities will be water gate and the duration of both carried out in two construction of a the construction stages including both new road will be activities and demolition of existing involved, the disturbance on water gate and duration of both the water quality will be construction of a new construction period short. road, the duration of and the disturbance both the construction to water quality will period and the be long. disturbance to water quality will be long. Engineering cost CNY 28.02 million 54.50 million RMB CNY 102.32 million (including CNY (including 15.02 (including CNY 6 15.02 million for million for buy-back, million for Fanglin buy-back, CNY 1 4.32 million for the Bridge and water million for water power station gate demolition, gate demolition, demolishing, 6 CNY 25 million for CNY 8.9 million for million for Fanglin bridge construction, new dike and CNY Bridge and water CNY 67.2 million for 4 million for new gate demolishing, 25 new water gate small irrigation million bridge construction, CNY pumping station to construction, 16.64 2.8 million for be constructed.) million for land additional dike, CNY acquisition and 1.15 million for resettlement, and 4 compensation for million for additional temporary power irrigation pumping generation station.) suspension during CNY 54.50 million construction, and (including CNY 15.02 CNY 16.64 million million for buy-back, for land acquisition - 249 - Table 9-4 Comparison of upgrade alternatives for Fanglin Hydropower Station CNY 4.32 million for and resettlement. power station demolition, CNY 6 million for Fanglin Bridge and water gate demolition, CNY 25 million for bridge construction, CNY 16.64 million for land acquisition and resettlement, and CNY 4 million for additional irrigation pumping station.) Existing No Transportation and Will planning, problems planning authorities construction and need to be consulted approval of the on the feasibility of navigation channel the half-width be considered upon construction of construction of the Fanglin Bridge. new water gate? Safety assessment on the hydropower station workshops and structures is needed to determine whether the structural safety will affect the construction of the water gate? Advantages (1) The back water (1) Bridge safety (1) Bridge safety effect of the power issue resolved; (2) issue resolved; (2) station is reduced; Traffic jam pressure environmental (2) no need of land is alleviated; (3) back impacts on both acquisition and water effect basically banks mitigated; (3) demolishing; (3) the removed with no normal power environmental impact on flood generation assured; impact from Fanglin control and (4) no (4) irrigation needs Bridge upgrade is LAR is involved. satisfied. eliminated. Disadvantages (1) High cost for (1) High cost for (1) There will still be power station power station some back water buy-back; (2) some buy-back; (2) effect; therefore impacts will be Construction of the upstream dike is generated on Fanglin Bridge will needed; and (2) irrigation and a new generate significant construction of small irrigation impacts on traffic Fanglin Bridge will pumping station is (traffic diversion at generate significant needed; (3) the 2km upstream of impact on traffic bridge safety issue Mintian Bridge and (traffic diversion at remains not 1km downstream of 2km upstream of resolved; (4) the Hezhou Bridge may Mintian Bridge and back water effect be considered to 1km downstream of - 250 - Table 9-4 Comparison of upgrade alternatives for Fanglin Hydropower Station from the bridge relieve traffic Hezhou Bridge may remains significant; pressure); and (3) be considered to and (5) need to some impacts will be relieve traffic increase the dike generated on pressure). height in upstream. irrigation on both banks; therefore, a new small irrigation pump station is needed; Reasons for Reduced backwater Backwater effect Backwater effect recommendation effect from the from the power from the power power station and station is station is savings on cost; substantially substantially consideration of eliminated, the eliminated, the navigational plan engineering cost is engineering cost is and transportation higher. Coordination very high. plan is not needed. with transportation Coordination with Project plan is needed. transportation plan is implementation is Project needed. Project easier. implementation is implementation is more difficult. more difficult. Recommended Alternative 1 alternatives In Alternative 1 for Fanglin Hydropower Station upgrading, the length of upstream back water is reduced through demolition of the existing concrete water gate. Compared with the other alternatives, Alternative 1, with no requirement of resettlement, features the best savings on investment, shortest construction period and relatively insignificant environmental impacts from construction. Its disadvantages include the high buy-back cost, the loss of power generation and the need of reemployment of unemployed power plant staff, and the impact on upstream irrigation leading to the addition of a new irrigation pumping station, the unresolved bridge safety issue, and the remaining back water effect from the bridge making necessary the increase of downstream dike elevation. However, compared with Alternative 2 and 3, this alternative is advantageous in its significant savings on investment, zero need of resettlement, and shortest construction duration and can generate some flood control benefits. Therefore, Alternative 1 is recommended for its highest cost-effectiveness and best price performance. - 251 - Table 9-5 Comparison of alternatives for Xiadao Hydropower Station Alternative 2: Alternative 1: Alternative 4: keeping the power Alternative 3: Keeping the power Keeping the power Alternative 6: station after the Keeping the power station and station after buy-back Alternative 5: Upgrading Upgrading the Content buy-back and station and building increasing the and building the power station power station after increasing the additional flood upstream dike additional flood buy-back upstream dike channel height channel height Keeping the power Keeping the power Power station Keeping the power station: building an Power station station: reducing the After power station buy-back: station: increasing additional flood buy-back: increasing crest elevation of gate buy-back, upgrading increasing the Description the upstream dike channel to remove the upstream dike dam to reduce the hydropower upstream dike height and keeping backwater and then height as in backwater; changing station as in height as in the power station keeping the power Alternative 3. gate type from flap gate Alternative 3 Alternative 1 station to flat gate CNY 39.35 million CNY 64.1 million (including CNY 0.5 (including CNY 4.6 CNY 85.35 million CNY 10.1 million CNY 110.1 million million for gate million for land (including CNY 53.5 (including CNY 2.6 CNY 57.4 million (including CNY 53.5 demolishing, CNY 30 acquisition, CNY 52 million for buy-back, million for new dike, RMB (including million for buy-back, million for gate upgrade, million for additional CNY 0.5 million for CNY 7.5 million for CNY 53.5 million CNY 4.6 million for CNY 1.35 million for Engineering cost flood channel, CNY gate demolishing, compensation of for buy-back and land acquisition and additional dike, and CNY 7.5 million for CNY 30 million for power generation CNY 2.6 million for CNY 52 million for 7.5 million for compensation of gate upgrade, CNY shut-down during new dike) additional flood compensation of power power generation 1.35 million for construction) channel) generation shut-down shut-down during additional dike) during construction) construction) Due to backwater Due to backwater Due to backwater effect, it is Due to backwater effect, effect, it is No backwater from No backwater from effect, it is necessary to it is necessary to necessary to the water gate. the water gate. necessary to Flood control benefit increase the increase the height of a increase the height Upstream dike is still Upstream dike is still increase the height height of a 4.0m 1.8km long dike by of a 4.0m long dike needed. needed. of a 1.8km long dike long dike by 0-0.37m. by 0-1.0m. by 0-0.37m. 0-1.0m. Limited to the area Limited to the area Limited to the area Limited to the area Limited to the area Limited to the area Impact on sensitive sites around the dike around the dike around the around the additional around the flap gate around the - 252 - Table 9-5 Comparison of alternatives for Xiadao Hydropower Station Alternative 2: Alternative 1: Alternative 4: keeping the power Alternative 3: Keeping the power Keeping the power Alternative 6: station after the Keeping the power station and station after buy-back Alternative 5: Upgrading Upgrading the Content buy-back and station and building increasing the and building the power station power station after increasing the additional flood upstream dike additional flood buy-back upstream dike channel height channel height construction site construction site additional flood flood channel upgrade site additional flood channel construction construction site channel site construction site The disturbance to water body is limited to the flap Water environment impact No impacts No impacts No impacts No impacts No impacts gate construction period. The duration is not long. Land acquisition and No No 47360m2 47360m2 No No resettlement After the buy-back CNY 7.5 million as CNY 7.5 million as After the buy-back After the buy-back the government CNY 7.5 million as compensation for compensation for the government the government Benefit from power becomes the compensation for power power generation power generation becomes the owner, becomes the owner, generation owner, therefore generation suspension suspension during suspension during therefore no need for therefore no need no need for during construction. construction. construction. compensation. for compensation. compensation. Placement of staff No No No No No No Advantage: back Advantage: back Advantage: limited Advantage: limited water effect water effect impact on the power impact on the removed. removed. Advantage: back station. Easy power station. Disadvantage: Long Disadvantage: Long Advantage: back water water effect construction; low Easy construction; construction construction effect reduced. reduced. cost. low cost. Main advantages / duration; land duration; land Disadvantage: Long Disadvantage: Long Disadvantages: Disadvantage: disadvantages acquisition and acquisition and construction duration and construction Increased dike Increased dike resettlement resettlement needed; high cost for gate duration and high height may increase height may needed; greater greater impacts on upgrading. cost for gate flooding risk on both increase flooding impacts on the the environment and upgrading. banks. risk on both banks. environment and local residents’ life. local residents’ life. Higher cost. - 253 - Table 9-5 Comparison of alternatives for Xiadao Hydropower Station Alternative 2: Alternative 1: Alternative 4: keeping the power Alternative 3: Keeping the power Keeping the power Alternative 6: station after the Keeping the power station and station after buy-back Alternative 5: Upgrading Upgrading the Content buy-back and station and building increasing the and building the power station power station after increasing the additional flood upstream dike additional flood buy-back upstream dike channel height channel height Higher cost. Conclusions Alternative 1 is recommended. - 254 - In Alternative 1 for Xiadao Power Station Upgrading, upstream dike height is increased to satisfy flood control requirements in the upstream areas. Increase of dike height involves relatively low cost. Advantages in reduced upstream flooding loss and avoided flood regulation difficulties assure the feasibility and implementability of the alternative. The upstream area of Xiadao Power Station is dominated by low hills and features in higher planned land elevation. Increasing the dike height will have little impact on local flood drainage and control and involves a very low cost. With the impacts from water construction activity on water environment avoided and with no land acquisition and resettlement required, Alternative 1 for Xiadao Power Station Upgrading features in the biggest savings on investment and is therefore recommended. 9.5 WWTP Alternatives Different alternatives for the proposed Jiangnan WWTP are compared in terms of siting, treatment process and outlet locations. Results of such comparison are shown in Table 9-6 to 9-10 as follows. Table 9-6 Comparison of siting alternatives for the Jiangnan WWTP Content Site alternative 1 Site alternative 2 East of planned Mid-west of Jiangnan Jiangnan district. East of District, south bank of the Luo-Zhan Railway, Description the He River. Near the south of the He River, Taoyuan Road and and west of the Gubo Shengping Road. Village Songbaizhai Village. Flat terrain with limited Flat terrain, favorable earthwork needs, Site condition for WWTP layout favorable for WWTP layout Sewage Located in the planned Low elevation, favorable collection areal convenient for sewage collection for sewage collection. Technical Flooding risk Little possibility of Little possibility of flooding flooding Discharge Pressurized flow. Pressurized flow. outlet Construction and Construction and installation cost for installation cost for pumping station is CNY pumping station is CNY 8.4515 million 9.5782 million Sewer network Construction and Construction and cost installation cost is CNY installation cost is CNY 9.8738 million 11.6406 million Environmental Impacts on Some sensitive sites Distance to the nearest impact environmentally are in the protection sensitive site is larger - 255 - Table 9-6 Comparison of siting alternatives for the Jiangnan WWTP Content Site alternative 1 Site alternative 2 sensitive sites area than 100 m Discharged into He Discharged into He Impacts on River; a pollutant flume River; a pollutant flume water is formed within 5 m is formed within 5 m environment from the outlet. from the outlet.. Involving impact on No sensitive sites in the Odor impacts sensitive sites nearby affected area. Involving impact on No sensitive sites in the Noise impacts sensitive sites nearby affected area. Demolition of residential Insignificant need of Social impact Resettlement houses and extensive demolition, thus resettlement is needed. insignificant cost of LAR Advantage: Convenient Advantage: Its location transportation, easy in the middle of the urban area of Jiangnan sewage collection and effluent discharge. District and in the Insignificant need of vicinity of residential house demolition and areas allows easy transportation and easy low cost of land acquisition; the flat sewage collection. terrain allows easy Flooding risk is low sewage collection and Main advantages / thanks to its location in requires little earthwork disadvantages the inner side of the quantity. Located at the planned urban area. leeward of prevailing Disadvantage: More wind direction, impacts significant on residents in the environmental impacts leeward direction are as it is located in the small. downtown center. The Disadvantage: some protection distance to surrounding area is not filling works are needed as the terrain is low and sufficient. flat. Conclusion Alternative 2 is recommended. From the comparison above, Alternative 2 is better because it allows easy sewage collection; although pipeline investment is relatively higher, Alternative 2 involves little house demolishing and resettlement and no impacts on environmentally sensitive sites as there are no sensitive sites in the protection area. Therefore the site described in Alternative 2 east of planned Jiangnan district and Luo-Zhan Railway, south of He River and west of Gubo Village and Songbaizhai Village is recommended as the WWTP site. Table 9-7 Comparison of WWTP treatment processes Content Process 1 Process 2 Description A2/O Micro-pore MBR - 256 - Table 9-7 Comparison of WWTP treatment processes Content Process 1 Process 2 aeration oxidation process 1. Conventional biological denitrification and dephospheration method with stable performance. 2. Use of Micro-pore 1. Low residual sludge aeration pipes, easy production Special installation and 2. solid-liquid separation is features maintenance, easy achieved requiring no management, little secondary settling tank maintenance, much smaller energy consumption than the conventional oxidation ditch method Involving fewer Involving more equipment equipment types and types and quantities and quantities and less strict more complicated Technical Equipment requirements of requirements of equipment quality and management and maintenance. maintenance. Automated control Automated control system system involving little involving strong workload workload of of programming, high cost programming, low cost of PLC hardware, but Operational of PLC hardware, but lower labor intensity. more management high labor intensity. Less strict requirements on strict requirements on operator qualifications; operator qualifications; high overall equipment Low overall equipment cost. cost. Construction and CNY 34.4758 million CNY 51.2855 million installation cost Operational CNY1.41 / ton CNY 2.55 / ton cost Water Stable Difficult O&M lead to Easy O&M. environment poorer stability of effluent effluent quality impact quality. Structures with odor problem including Structures with odor aeration tank, sludge problem including screens, Environmental Odor impact condensing tank and sludge condensing tank. impact sludge room. Certain Scope of odor impact is odor impacts will be relatively small. generated. Noise impact Major noisy equipment is No high-noise equipment. the air compressor Sludge 0.31kg sludge/kg BOD 0.1kg sludge/kg BOD production Social impact Land 1.65 hm2 1.28 hm2 - 257 - Table 9-7 Comparison of WWTP treatment processes Content Process 1 Process 2 acquisition Advantage: Advantage 1. Conventional 1. Low residual biological denitrification sludge production; and dephospheration 2. solid-liquid method with stable separation is achieved performance; requiring no secondary 2. Use of Micro-pore settling tank aeration pipes, easy Disadvantage installation and High investment cost. maintenance, easy Main Stricter qualification management, little advantage/disadvantage much requirements for operators maintenance, ensure stable smaller energy performance. More consumption than the equipment types and conventional oxidation quantities are needed, ditch method; effluent implying greater 3. Stable complexity in management quality and maintenance and Disadvantage: Involving larger area of greater possibility in unstable effluent quality. land occupation Conclusion Alternative 1 is recommended. It can be seen from the above comparison that, compared with the MBR process, the A2/O micro-pore aeration and oxidation process involves a low process investment, less difficulty in operational management, greater savings on operational cost and more stable effluent quality. Although it will generate some odor impacts and noise impacts, such impacts can be contained within the plant area if appropriate measures are taken. Therefore, Alternative 1, i.e. the A2/O micro-pore aeration and oxidation process, is recommended as the treatment process for the WWTP under the Project. Table 9-8 Comparison of alternative locations of discharge outlet of Jiangnan WWTP Content Alternative 1 Alternative 2 Description Jingyue Lake Downstream He River Installation depth of Shallow Deep associated pipelines Pipeline cost CNY 9.8738 million CNY 11.6406 million Technical Technical difficulty and Technically feasible Technically feasible Environmental feasibility impact Construction condition Available Available Construction difficulty Minor Major Construction period Short Long O&M Convenient Fairly convenient He River downstream, Mid-stream He River, downwind direction of the Water environment greater environmental prevailing wind direction. impact impacts Greater environmental Technical benefits. Still water, difficult for Flowing water. Easy for Receiving water body pollutant diffusion. Poor pollutant diffusion. Good self-purifying capacity self-purifying capacity self-purifying capacity - 258 - Table 9-8 Comparison of alternative locations of discharge outlet of Jiangnan WWTP Content Alternative 1 Alternative 2 Surrounded in the urban In the suburban area and Odor impact area. Odor impact is downwind direction. Odor significant. impact is insignificant. Noise impact Significant Insignificant Land acquisition Significant Insignificant Engineering Construction cost Significant Insignificant cost Operational cost Similar Similar Advantage: Convenient sewage collection and lower sewer network Advantage: Greater cost; environmental benefits Disadvantage: located and insignificant Main advantages / disadvantages in the urban center; demolition demand; involving impacts on Disadvantage: Bigger surrounding area. pipeline length and depth Extensive demolition is involved. needed. Conclusion Alternative 2 is recommended It can be seen from the above comparison that Alternative 2 for the location of the discharge outlet of Jiangnan WWTP requires installation of longer sewer pipelines and greater buried depth. Despite of the construction difficulty, this alternative involves greater long-term environmental benefits because the discharge outlet is located at the lower reaches of He River and downwind direction of residential areas in the suburb. Pollutant load from the effluent can be quickly diluted and purified once it enters He River. In the other alternatives, diffusion and self-purification of pollutant in the effluent are difficult. Therefore, the outlet at the lower reaches of He River is recommended as the discharge outlet of Jiangnan WWTP. - 259 - 10. Public Participation and Information Disclosure 10.1 Purpose of public participation The purpose of public participation is to improve the quality of EIA, to provide more information and advice, and to make the EIA process more open and public so as to enable all the people with direct or indirect connection with the Project to participate in the EIA process to ensure transparency and credibility of the EIA results and to bring forward their own views and opinions to make the EIA process better and fairer. Public participation is an important part of EIA process and an effective way to improve scientific decision-making. Public participation for construction projects is an important means of enhancing the two-way communications between project construction units, EIA consultants and the public. Through extensive public participation, the public directly or indirectly affected by the construction project can have a full understanding of the potential environmental impacts, mitigation measures and the economic and social benefits brought by the project construction, and can provide feedback opinions and actively offer suggestions to jointly find a solution for potential problems. Thus the impact of project implementation on the environment can be minimized, potential pollution induced conflicts can be avoided, and environmental protection and economic development can be better coordinated. The main purposes of public participation include: (1) Summarizing and analyzing public opinions, so that they can be included in the environmental protection measures. Public opinions should also be used as the work guidelines in the implementation stage of the Project. (2) Conducting two-way communication between the public and the construction unit, introducing project overview, potential pollution, control measures, EIA prediction results, etc., to the public in detail and collecting public opinions and suggestions, etc. and giving feedback to the construction unit so that the project design can be properly modified to bridge the public and the construction unit for mutual understanding. (3) Soliciting, through public participation, public views and opinions of the Project, finding a basis for safeguarding public interest, fully adopting the feasibility suggestions in the EIA process to ease public concerns induced by lack of communications between the construction unit and the public, and mitigating as much as possible the adverse impacts on and making necessary compensation for public interests. (4) The post-EIA assessment mainly relies on public supervision. Public participation is an important part of environmental management mechanism, which is conducive to protecting the ecological environment, improving the environmental and economic benefits of the Project, and improving environmental quality, and ensuring the implementation of sustainable development strategies. - 260 - 10.2 Scoping and stakeholder identification Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project plans to apply for a loan from the World Bank to further accelerate infrastructure development under the Project, and create conditions for coordinated social and economic development in the region. Implementation of the Project will facilitate improvement of water environment in He River Watershed and Hezhou Municipality, watershed ecological function and city style and quality as well as local peoples’ livelihood and lay a solid foundation for sustainable development in Hezhou. However, during project construction and operation, there will be some environmental impacts on the surrounding area concerning the personal interests of local people. Such impacts will cover individual residents and organizations within the range of red lines (RoRL) and in the affected areas of the Project. In the project-affected area, all individuals or organizations that are directly or indirectly benefiting from or adversely impacted by the Project are the stakeholders of the Project. At the same time, project-related government agencies or experts in the related disciplines are also stakeholders. Stakeholders of the Project are identified based on the subprojects defined in the feasibility study report and are summarized in Table 10-1. - 261 - Table 10-1 Summary of project stakeholders Stakeholders Subproject S.N Subproject Related government agencies component Affected people and experts Residents along the watershed (Shangsong Village, A-1 He River integrated Xiwan Village, Xiwanzhai Village, Jigongzhou village, rehabilitation Xibenyuan Village, Gongqiaotou Village, Longjiangdu HWRB, HAAHB, HFoB, HLRB, (Huangshi Hydro- Village, Hezhou Institute, Shizigang Village, Sanjiacun HPB, HTPD Power station to Village, Fanglin Village, Fanglin Village, Laoxuewo Guangming Bridge) Village, Laozengwo Village), Hezhou Experimental Middle School HWRB, HAAHB, HFoB, HLRB, A-2 He River integrated HMEAB (river widening might Residents along the watershed (Babuxi South No.2 Alley rehabilitation involve infrastructure), residential house, Xiyue Street residential house, (Guangming Bridge to HCPPRFTB (Office of Historical Jiangbeizhong Road residential house, Xialiang Village) Lingfeng Bridge) Cultural City Application), HPB, HTPD Improving Residents along the watershed (Jiangbeizhong Road Flood Risk A-3 He River integrated residential house, Diandengzhai Village, Pinganzhai 1 Resilience of rehabilitation (Lingfeng Village, Laiwu Village, Chetianzhai Village, Yazhai HWRB, HAAHB, HFoB, HLRB, He River Bridge to Xiadao Village, Duchuantou Village, Chushuitang Village, HPB, HTPD Hydropower Station) Xiadaozhai Village, Jichitan Village), Xiadao Primary School. A-4 East Trunk Drainage Canal Residents along the watershed (Huangtianzhai Village, rehabilitation and Dabanqiao Village, Fengfeiling Village and Xianghuadao HWRB, HPB, HAAHB, HLRB Mawei River Village). connectivity A-5 Xiadao Residents along the watershed (Jichitan Village, Hydropower Station Niulanpai Village, Hydropower station owner and HWRB, HPB integrated operator) improvement A-6 Fanglin Residents along the watershed (Sanjia Village, Fanglin HWRB, HPB, HTPD Hydropower Station Street; Hydropower station owner and operator ) - 262 - Table 10-1 Summary of project stakeholders Stakeholders Subproject S.N Subproject Related government agencies component Affected people and experts integrated improvement A-7 Huangshi Hydropower Station Residents along the watershed (Shangsong Village; HWRB, HPB integrated Hydropower station owner and operator ) improvement A-8 He River dredging (Huangshi HWRB, HMEAB (garbage, Hydropower Station to Same as A-1, A-2, and A-3 in-situ treatment for sand and Xiadao Hydropower stones), HPB and HAAHB Station) B-1 Huang’ansi Drainage Canal Xiyue Street residential house HWRB, HPB and HCPPRFTB pumping station B-2 Shizigang Drainage Canal Jiangbeizhong Road residential house HWRB and HPB pumping station Residents along the watershed (Pingjing Village, B-3 Lining River Baimenlou Village, Lijiatang Village, Lining Village, HWRB, HLRB, HPB and Improving rehabilitation Daninggang Village, Jizishi Village, Laozhaishan Village, Railway Authority Urban Xiangjiayuan Village) and Yingshi Primary School 2 Drainage and Residents along the watershed (Huangtianzhen B-4 Changlong River HWRB, HLRB, HPB and Wastewater township, Sanqiqiao Village, Douxing Village, Tianjingnao rehabilitation Railway Authority Management Village, Yatanggang Village, Changlong Village) Residents along the watershed (Ershiao Village, B-5 Huangtian Branch Sanqiqiao Village, Huangtian Township, Huangtian HWRB, HMEAB, HPB, HLRB Canal rehabilitation Village, Anshan Village), Hezhou Pinggui No.3 Junior and Railway Authority High School. HWRB, HMEAB, HLRB, HPB B-6 Guposhan Residents along the watershed (Huangtian Township, and authorities involved in utility Drainage Canal Huangtian Village, Anshan Village, Benyuanna Village, pipelines: water, sewer, gas, rehabilitation Baijiazhai Village and Shizigang Village) telecommunication and - 263 - Table 10-1 Summary of project stakeholders Stakeholders Subproject S.N Subproject Related government agencies component Affected people and experts electricity HWRB, HMEAB, HPB, HLRB, Residents along the watershed (Tianchongzhai Village, and authorities involved in utility B-7 East No. 5 Branch Tangpingzhai Village, Xiwan Village, Xiwan Township, pipelines: water, sewer, gas, Canal rehabilitation Guanyingyan Village) telecommunication and electricity C-1 Huang’ansi Residents along the watershed (residential buildings at HWRB, HMEAB, HPB, HLRB Drainage Canal Badaxi Road, Qianjin Road, Jianshezhong Road, and HTPD rehabilitation Youxingxiang Alley, Xinan No.1 Alley, Xiyue Street). Residents along the watershed (residential buildings at C-2 Shizigang Wanquan Street, Zhushan Road, Longxing alley, Yinhe HWRB, HMEAB, HPB, HLRB Drainage Canal Street, Wangjiao Alley, Longshan Road, Xingguang and HTPD rehabilitation Road, Pinganxi Road, Jiangbeizhong Road) Residents along the watershed (Fanglin Village, C-3 Jiangnan WWTP Laoxuewu Village, Laozengwu Village, Xinxuewu Village, and associated sewer Zhegutou Village, Chaan Village, and residential HWRB, HLRB, HPB, and system and road buildings at Guangming Avenue, Nanhuan Road, HMEAB improvement Binjiangnan Road, Xinxingnan Road, Xiadao Village, Xiadaozhai Village, and Tongluozhou Village.) Institutional Hydraulic monitoring Responsible person of relevant agency HWRB, and HPB Strengthening, station Capacity Environmental 3 Responsible person of relevant agency HWRB, HEPB, and HPB Building and monitoring station Project Ecological monitoring Responsible person of relevant agency HLRB, and HPB Management station HAAHB: Municipal Aquatic & Animal Husbandry Bureau; HCPPRFTB: Hezhou Municipal Culture, Press, Publication, Radio, Film & TV Bureau; HMEAB: Hezhou Municipal Engineering Administration Bureau; HFoB: Hezhou Municipal Forestry Bureau; HFB: Hezhou Financial Bureau; HLRB: Hezhou Municipal Land and Resources Bureau; HPB: Hezhou Municipal Planning Bureau; HWRB: Hezhou Municipal Water Resource Bureau; HEPB: Hezhou Municipal Environmental Protection Bureau; HTPD: Hezhou Municipal Traffic Police Department. - 264 - 10.3 Public consultation 10.3.1 Executive arrangements The implementation of the Project will be helpful for the water environment improvement in the project related watershed and urban area, effectively improve the ecological functions of the basin and enhance the city's style and taste, improve the quality of people's life, and provide a solid basis for sustainable development of Hezhou in the future. As the construction and operation of the Project involves land acquisition, resettlement, and possibly local environmental changes, two rounds of public participation were carried out for the Project according to the requirements of domestic laws and regulations for environmental protection and the World Bank Safeguard Policy (OP4.01). The first round was in the preparation phase, or during the preparation of the EIA outline; the second round was after the draft EIA report was finalized. The public participants mainly include residents in the project area or project-affected area, i.e., the residents near the sections of He River and urban inland canals to be rehabilitated and the WWTP to be built. In addition, the public participants also include representatives and experts from government agencies related to the Project The first round was conducted in the project preparation phase or during the preparation of the EIA outline. The main purpose was to introduce the basics of the Project so that the public could have a basic understanding of the Project and make comments or suggestions for project implementation. During this round, the EIA consultant solicited comments and suggestions from the public through online information disclosure, poster disclosure, interviews, questionnaires survey and seminars. Such comments and suggestions were delivered as feedbacks to the Project EA and feasibility study designer to provide references for the project design as this EIA. The second round of public participation was implemented after the first draft of the EIA Report was completed. The main purpose was to provide feedbacks on comments and suggestions solicited during the first round, and solicit comments and suggestions on the proposed mitigation measures. During the second round, the EIA consultant also solicited comments and suggestions from the public through expert consultation, online disclosure, poster disclosure, interviews and seminars. At the same time, the draft EIA report was made available at places of public accessibility including offices of the PMO, HEPB, relevant village committees, or street committees, etc. Details of the public participation are summarized in the Table 10-2 and Table 10-3. The process is illustrated in Figure 10-1 and Figure 10-2. - 265 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments First Round Government Introducing basic agencies, Timely communication will be assured with the FSR information and village The design should be optimized to design institute to provide feedback to them so that potential committee avoid land acquisition and land acquisition and resettlement can be avoided as 2016.4.1 environmental HDRC Seminar leader and resettlement. Resettlement activities much as possible. Relevant national and local 4 impacts of the villager should be well implemented to regulations for land acquisition, resettlement and Project, soliciting representatives achieve land resource balance. compensation will be respected and relevant measures public opinions and involved in the and requirements will be included in the ESMP. suggestions Project Village Introducing basic The resettlement and compensation plan should not committee and information and lead to negative impacts on the livelihood of land-losing Villagers’ opinions should be fully villagers. Measures to be taken should comply with Gonghe Site visit, villager in potential respected to ensure all lands relevant national laws and regulations so that they are 2016.4.1 Village, Question Gonghe Village; environmental acquired are fully compensated and acceptable to people and make sure that everybody 5 Sanjia naires Village impacts of the the life and work of villagers who has a job and lives a good life in the end instead of only Village survey committee and Project, soliciting lose their lands will be restored. compensated financially. villager in public opinions and Sanjia Village; suggestions 1. The Project EIA proposed different environmental protection measures based on the nature of each component to make sure the impact on water environment and ecological environment from construction is minimized. Detailed measures include: Village Introducing basic Stronger efforts should be made in (1) Enhance the environmental training for construction committee and information and water quality monitoring and workers to improve their environmental awareness, Lining Site visit, villager in Lining potential improvement to protect the and forbid random littering and dumping; (2) Arrange 2016.4.1 Village and Question Village; Village environmental ecological environment. Local construction in non-wet seasons or sunny days to 6 Changlong naires committee and impacts of the construction labor force may be reduce the impact on water quality in He River; (3) Village survey villager in Project, soliciting hired for the project construction to Implement soil erosion control based on the soil Changlong public opinions and create job opportunity for local erosion control plan, and improve the ecological Village suggestions residents. revetment. The detailed measures are also summarized in Chapter 5. 2. The contractor should hire local labor where possible provided that the construction requirements are satisfied. 2016.4.1 Babu Site visit, Babu Street Introducing basic Proper arrangements should be For the comments raised by the public, the EIA 7 Street Question Office, the information and made to the construction works to proposed the following measures: (1) selecting - 266 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments Office, the naires project areas in potential avoid noise disturbance to advanced low-noise equipment; (2) prohibiting project survey the city environmental residents. construction activities at noon (12:00-14:00) or at night areas in the impacts of the (22:00 – 6:00 next day); (3) Using vibration damping city Project, soliciting foundation or vibration damping support with damping public opinions and material for noisy machinery or equipment; (4) erecting suggestions noise-reduction fences around construction sites with a distance of less than 5 m from residential buildings and schools; temporary sound barriers with effective noise attenuation should be erected for construction sites close to schools; (5) all machinery and equipment should be maintained and repaired effectively and periodically to stay in good conditions for the final purpose of noise reduction and longer service life; and (6) stricter requirements should be raised for management of construction intensity, machinery or vehicle operator and codes of operation, etc. 1. The EIA proposed the following protection measures for historical famous trees: (1) minimizing the Introducing the construction area and shorten the construction basic information 1. Whether the project area duration; (2) prohibiting tree felling, transplanting, bark HWRB, HAB, and scope of the involves the historic famous trees. peeling, root digging, or injection of hazardous or toxic HTB, HLRB, Project. Each If any, they should be protected materials to the historic famous trees; (3) prohibiting HFoB, HAAHB, agency should during construction. construction of buildings or structures, laying pipelines, HCPPRFTB, identify its key 2. The historic scenery and erecting cables, digging borrow areas, mining and sand Eco-city responsibilities. A ecological environment on both excavation, flooding or sealing ground, emitting fumes management coordination sides of He River, especially the and dumping wastewater or solid wastes, stockpiling or committee, mechanism at 2017.2.2 ancient ferry, pier and dike, should dumping flammables, explosives or other hazardous HWRB Seminar village different levels 0 be protected. substances on sites with a horizontal distance of less committee should be than 5 m of from the projected shades of crowns of representatives, established to 3. Before construction a traffic historic famous trees ; (4)prohibiting activities including design institute explore potential management plan needs to be carving, nailing, winding, hanging on the trees or piling representative environmental prepared to ensure smooth traffic material against the tree trunk (5) prohibiting rolling and and project impacts during and safety. compaction by construction vehicles or plant in areas owner construction and 4. Due diligence should be with a distance of 5m outside the vertical projection of representatives. operation stages. conducted for associated facilities. the crowns of ancient and famous trees. 2. The EIA proposed the following protection measures for cultural heritage: (1) the project design should avoid construction in the protection area of the - 267 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments existing historic culture street; (2) before commencement of construction works under the Project, the relevant authorities should be consulted to develop an effective cultural relics protection plan; 3) construction camps, temporary top soil stockpiling sites are not allowed to be located in the protection area; and (4) A Physical Cultural Resources Management Plan should be developed to regulate and standardize the constriction operations. 3. (1) Construction works should be carried out on a section-by-section basis to enable early excavation and backfill; (2) A bulletin board should be erected at construction site to inform the public of project background, construction duration, etc. and seek the public understanding on the inconvenience brought about by the Project; information on contact person and complaint hot line number should also be disclosed; (3) the pipeline construction should avoid the peak hours or traffic police guide should be utilized in peak hours to divert traffic and ensure smooth pedestrian and motorized vehicle to minimize traffic jam and reduce impact on local residents’ travel; and (4) construction management and trainings on environmental protection for construction workers should be strengthened. 4. The associated projects identified for the Project include Guangxi He River Rehabilitation Project, Hezhou Domestic Solid Wastes Landfill Project, Hezhou Jintai Lake Rehabilitation Project, Hezhou Yongfeng Lake Rehabilitation Project, Hezhou WWTP Project, Hezhou Sludge Harmless Disposal Project etc. The status of these associated projects is detailed in Chapter 3, Due diligence of associated projects. 1. Based on the protection area of the Xiyue Cultural 1. Wherever possible, the project Street, the design institute optimized the RoRL for the Question Basic information design should avoid the national Project. In-situ protection will be used to protect the 2017.2.2 HCPPRFT naires HCPPRFTB about Xiyue Street level historic famous city and its ancient dike and ferry with no further upgrade except 5 B survey and its protection protection area, and avoid the filling the outside with compressed soil to improve the ancient ferry, dike, bridge and trees stability of the dike. to protect the cultural heritage in 2. Relevant authorities should be consulted to - 268 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments Hezhou. develop an effective cultural heritage protection plan; 2. The planning and design for 3. Education and training should be strengthened Xiyue Street should follow the during construction to raise construction workers’ suggestions of Hezhou National awareness of cultural heritage protection. If a cultural Historic Cultural Famous City heritage is identified in the construction process, the Application Office and be submitted construction unit or construction supervising unit to the municipal government for should suspend the construction activity immediately, approval prior to the and report the cultural heritage authority for proper commencement of any construction handling. The construction can only be resumed at the works. Buildings close to or within cultural heritage authority’s approval. the famous city should have the 4. For the historical street protection section at the same style with the existing historic estuary of He River and Huangansi Drainage Canal, a cultural street. dual-function dike combining landscaping with flood 3. Lessons and experiences from control may be constructed outside the existing Babu the other cities such as Yongzhou in Minguo Dike as a part of the flood control component Hunan Province, Wuzhou in to manifest the prosperity of shipping culture in ancient Guangxi Province, should be used Hezhou while hide the vertical-moving flood gate inside as references and the dikes to be the dike relying on the corridor support structures. constructed should be located as 5. Management and maintenance in the operation close to He River as possible; the stage should be strengthened. original dike and ancient ferries should be protected; antique water-front bridge gallery should be built to cover up the sewer pipelines along He River to enhance the aesthetics of the city as a whole. 4. It is suggested that Wuzhou and Guilin’s model in the dike design should be followed to exhibit the Hezhou mining culture, Qianjiang culture, and red culture in the form of embossment on the dike. The water environment rehabilitation should be integrated with the urban development to create a new leisure space in Hezhou and revitalize the historic and old communities. 2017.3.2 HEPB HEPB EIA Consulting and 1. The EIA for He River EIAS have been prepared and approved for the Site division and identifying the EIA Rehabilitation Project has been associated facilities. Hezhou WWTP is operating - 269 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments interview Pollution approval process approved. Currently the Pinggui smoothly with effluent quality meeting relevant Control and progress of New District Dike, Huangtian Dike standards. Currently it is undergoing Phase II Division. associated facilities, and Jiangbei Dike have been expansion. Once Phase II is completed, it can and the pollutant completed and the Jiangnan Dike is accommodate the sewage intercepted in the Project. discharge points in not yet started and is estimated to The current sludge treatment project has a designed the city. complete in 2018. treatment capacity of 100 tons/day. The current load is 2. The EIA for the Hezhou Jintai 33 tons/day, therefore there is still room for more load. Lake Integrated Rehabilitation When the Jiangnan WWTP is completed, it will produce Project has been approved. 3 tons/day of sludge, within the acceptable range for Currently, construction of the project the Hezhou Sludge Disposal Center for handling. After subcomponent has not commenced dewatering, the moisture content can be reduced to and is anticipated to complete by 50%. After negotiating with the HMEAB, the dredged September 2019. sediments can be send to Hezhou Landfill for disposal after dewatering process. The details of the associated 3. The EIA for the Hezhou facilities are summarized in Chapter 3. Yongfeng Lake Integrated Rehabilitation Project has been Based on the survey results for the associated facilities, approved. Currently, construction of appropriate environmental protection measures should the project subcomponent has not be proposed and effectively implemented causing no commenced and is anticipated to secondary pollution. Detailed measures are introduced complete by September 2019. in Chapter 5, Environmental Impact Analysis and Mitigation Measures, of the report. 4. The EIA for Hezhou WWTP (Phase I ) has been approved and the plant has passed the acceptance test and is in stable operation. The effluent water quality can meet relevant discharge standards. The EIA for Phase II expansion has been approved and current Phase II is under construction. 5. The EIA for the Hezhou Sludge Disposal Center has been approved. The facility is currently under trial operation. The EP acceptance test will be conducted later. 6. The EIA for the Hezhou Landfill has been approved, and the landfill have been built and put into operation. Currently it is undergoing - 270 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments a technological upgrade on its leachate treatment station. Consulting and The dredged sediment from He River rehabilitation identifying the component has a moisture content of approximately development and 95%. It is planned to use the integrated solidification operation status of method for sediment treatment and reduce the Hezhou Sludge Disposal Center is moisture content to less than 80% (60-70%) so as to the Hezhou Sludge already built and put in operation. meet the acceptance requirement of Hezhou Sludge Disposal Center, The treatment capacity is 100 Disposal Center. and the operation tons/day. It can accept sludge with a status of the After discussion among different parties, the sediment Site HMEAB Utilities moisture content of 80%. After 2017.7 HMEAB Hezhou Landfill. disposal plan was adjusted. The integrated interview Division leader treatment the moisture content can Discussing and solidification method can reduce the moisture content be reduced to 60%. The treated confirming whether of the sediment to 50% and achieve the required sludge can then be sent to landfill for the disposal center disposal. moisture content (of less than 60%) of the solid waste can accept the landfill for direct landfill rather than having to be treated sediment dredged in the sludge disposal center. from He River After the Project becomes operational, sludge from rehabilitation Jiangnan WWTP will be dewatered at the disposal component. center before being sent to the landfill for disposal. Based on the Hezhou municipal pipeline survey results, a number of pipelines are identified in the construction area, for which the EIA report proposes the following protection measures: (1) Coordinating with relevant agencies including the HMEAB, HHURB to acquire underground pipeline The Hezhou municipal pipeline survey data and basic information of the pipelines Leader of the survey is still being constantly including pipeline type, alignment, buried depth, etc.; Urban Consulting and updated and improved. Some of the establishing a pipeline coordination team. Excavation 2017.8.3 Site Development identifying the HHCB pipelines are too old to have track activities involving underground pipelines should be 1 interview Management layout of record. In the construction stage, pre-approved by the authorities, such as HMEAB, Division of underground utilities contractors should be very careful HHURB; (2) developing a construction plan and an HHCB about underground pipelines. emergency response plan based on the pipeline alignment and buried depth to avoid underground pipelines where possible; and (3) before commencement of excavation activities involving underground pipelines, reporting the construction area and construction time to relevant authorities before excavation so as to get prepared for emergency - 271 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments responses. 1. There are no concentrated 1. In the EIA it is clarified that the project area does feeding areas or spawning area in not involve fishery site or rare species. Dredging will the urban section of He River. In have some impact on plants and animals living in He Consulting and addition, as Hezhou is located in the River bottom, however they are not rare species and confirming whether southern part of China, wintering can recover after a certain period of time. Leaders in the project area area is not needed. Furthermore, there are many power stations 2. The fishery department is doing proliferation at Fishery involves fishery site Phone blocking the urban section of He the dam for Guishi Water Reservoir Power Station to 2017.9.1 HAAHB Administration or rare species, and interview River, therefore there are no restore the aquatic culture. This can effectively help Division of discussing the migratory channel in this section. protect the aquatic environment. HAAHB potential impacts on the aquatic 2. Dredging will cause impact on 3. The EIA also proposed the following measures: ecological system in aquatic plants or animals using He (1) the construction will be arranged at low-water He River River bottom as habitat. But they are seasons as much as possible; (2) the construction not rare species, and will recover activities will be limited within minimized area and in after a certain period of time. shortest duration. The Project will further improve the design and preparation work to enable early commencement. The construction activities will strictly follow the design and construction plan; pollution control measures should be Introducing the The public expressed their well developed to avoid repetitive construction. In basic information understanding and support. addition, this Report proposes the following measures and scope of the for the dredging process: (1) Dredging will be arranged Project, disclosing The site should be located away Residents in the in low-water seasons with shortest duration to minimize Site visit, information on the from residential area. The Temporary area disturbance to water body; (2) The dredged sediments Question potential construction should be conducted in 2017.9.7 de-waterin surrounding the will be dewatered into sludge cakes and then naires environmental autumn and winter. It is desirable to g site temporary transported in enclosed vehicles to Hezhou Domestic survey impacts and commence and complete the de-watering site Solid Waste Landfill for disposal; (3) Temporary associated construction works as early as dewatering site should be equipped with temporary measures for the possible at one go to minimize the storage and sedimentation tanks. The wastewater from temporary impact on local residents. dewatering process is treated in the sedimentation tank dewatering site. before being discharged; (4) Fencing, covering and intercepting measures will be taken for the dewatering sites and lime and deodorant will be made available for disinfection and odor removal. Hezhou Site visit, Responsible Introducing the 1. The project area is limited 1. This issue has been discussed with the design 2017.9.8 Experiment Question persons of project scope and outside the boundary wall of the institute. The RoRL will be adjusted to exclude the al Middle naires Hezhou overview, school, therefore the school is not roads. - 272 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments School survey Experimental discussing the involved. However the Project RoRL 2. The EIA proposed the following measures for the Middle School potential impact of covered the main entrance roads for construction noises: (1) no construction activities are the Project on the the school. Therefore, traffic jam will allowed during noon time (12:00 - 14:00) or night time school and the become inevitable to affect the (22:00 - 6:00); (2) fences or temporary sound barriers potential control teaching activities. should be erected around construction sites; (3) measures. 2. The Project RoRL are close to management should be strengthened over the student and faculty dormitory construction intensity, machinery or vehicle operators, buildings. Therefore the construction and codes of operation, etc. following the detailed should not be conducted during the measures described in Chapter 5. resting time. 3. The wastewater management system of Hezhou 3. Currently sewage produced in is being continuously improved. The sewage from the school is sent to its own Fanglin district will be sent to the planned Shatian treatment facility for treatment to the Township WWTP (not under the Project). discharge standard before being discharged. The operation cost is very high. Therefore, the school anticipates that sewage can be accepted by the city sewer network. 1. A new multi-functional office building (3-storey reinforced concrete structure) and school public toilets (brick and concrete structure for both sides) are within The Yingshi Primary School will be relocated. Currently Introducing the the RoRL. The school currently has the local government has included in the planning a 50 project scope and more than 500 teachers and mu site at the intersection of Xinyuan Road and Minle overview, Site visit, students with limited space for Road in the New Eco-city for the relocation of the Yingshi Headmaster of discussing the Question teaching or offices. If these lands school. The new campus is planned to complete by the 2017.9.8 Primary the Yingshi potential impact of naires are occupied, it will seriously affect end of 2018. In order not to affect the regular teaching School Primary School the Project on the survey the school’s teaching activities. activities, it is planned to conduct the relocation during school and the the winter break in 2018 and then the old campus will potential control 2. In order to avoid the impact of be demolished. After the relocation the school will not measures. construction noise on the school’s be affected by the Project. teaching activities, it is recommended that the construction should be carried out during the vacations. 2017.9.1 Pinggui Site visit, Headmaster of Introducing the It is suggested to adjust the red line 1. The comments have been sent to design institute 1 No.3 Question the Pinggui project scope and to exclude the school so that the and adjustment has been made to the RoRL, which are Middle naires No.3 Middle overview, Project will not involve the school now outside the fencing wall of the school, thus no - 273 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments School survey School discussing the campus and not affect the regular school land will be involved. potential impact of teaching activities. 2. The Project borders on the eastern fencing wall of the Project on the the school. Within the wall is the sports ground. The school and the classrooms and the dormitory buildings are relatively potential control far from the project area, thus the project construction measures. will have little impact on school teaching. 1. It has been confirmed with HCPPRFTB that the Babu CCP Special Branch in Xiadao Primary School is a cultural heritage site, which should be protected on its original site. The following protection measures are to be taken: (1) The project design and construction should avoid the protection area of the current Babu Special Branch Historic Site in Xiadao Primary School, and to keep the historical cultural heritage intact. (2) Before the construction commencement, the relevant authorities should be consulted to develop effective cultural relics protection plans. (3) Detailed construction plan should be developed prior to Introducing the construction commencement and warning signs should project scope and be erected on site for cultural heritage protection to overview, provide information on the nature, significance, Site visit, There is a memorial museum for a Xiadao Headmaster of discussing the protection area, protection measures for the historical 2017.9.1 Question special branch of CCP in the Primary Xiadao Primary potential impact of and cultural heritage, and contact person and contact 1 naires project-affected area which has School School the Project on the information for the management entity. (4) survey special educational significance. school and the Construction activity should not be allowed within the potential control cultural heritage protection area. Use of excavator or measures. piling machines is prohibited and manpower excavation should be used instead to minimize vibration impact on the cultural heritage. (5) Training should be provided for construction workers to enhance their awareness of cultural heritage protection so that the cultural heritage can be avoided in construction activities and artificial damage to the cultural heritage can be prevented. 2. The EIA proposed the following measures for the construction noises: (1) no construction activities are allowed during noon time (12:00 - 14:00) or night time (22:00 - 6:00); (2) Fences and temporary sound barriers should be erected around the construction - 274 - Table 10-2 Summary of comments and feedbacks for the first round of public consultation Time Venue Method Objects Contents Public comments/opinions Feedback to public comments sites when necessary; (3) Strict requirements should be proposed on management of construction intensity, machinery or vehicle operators, and codes of operation, etc. See Chapter 5 of the report for details regarding such measures. Consulting and confirming whether The Babu Special Branch of CCP in the CCP Special Xiadao Primary School has not Director of Branch Memorial submitted the declaration for object Pinggui District Hall in Xiadao of preservation as physical cultural After confirmation with the HCPPRFTB, it is concluded Pinggui 2017.9.1 Site CNRTB, Primary School is resources. Whether it will be treated that the Babu Special Branch of CCP in Xiadao Primary District 1 interview Cultural, an object of as an object of preservation as School is a cultural heritage site. The detailed CNRTB Director of preservation as physical cultural resources needs to protection measures can be referred to the above. CHMI physical cultural be further confirmed with the resources, and the municipal bureau because it has a level of protection long history. and requirements Consulting and The comments have been sent to the design institute. This place was registered and The dike protection plan has been adjusted from confirming whether became a provincial object of T-shaped revetment to vertical retaining wall to reduce the CCP Special preservation as physical cultural the construction affected area so that the cultural Branch Memorial resources in Guangxi in 1989. It is heritage can be avoided and the in-situ protection can Site visit, Hall in Xiadao suggested to conduct in-situ be conducted. 2017.9.1 Hezhou Question Primary School is Museum curator protection and convert the 2 Museum naires an object of The detailed protection measures for this site are surrounding area to a cultural park. survey preservation as included in the ECOP for management of physical In addition there are some historic physical cultural cultural resources. Based on the site investigation, the sites in Diandengzhai Village. If resources, and the historic sites in the Diandengzhai Village are not these sites are involved in-situ level of protection involved in the Project. protection should be conducted. and requirements. CCP: Chinese Communist Party; CPPRFTB: Cultural, Press, Publication and Radio, Film & TV Bureau; CHMI: Cultural Heritage Management Institute; HAB: Hezhou Municipal Agricultural Bureau; HAAHB: Municipal Aquatic & Animal Husbandry Bureau; HCPPRFTB: Hezhou Municipal Cultural, News and Radio & TV Bureau; HDRC: Hezhou Municipal Development and Reform Commission; HMEAB: Hezhou Municipal Engineering Administration Bureau; HFoB: Hezhou Municipal Forestry Bureau; HFB: Hezhou Financial Bureau; HHCB: Hezhou Municipal Housing and Construction Bureau; HLRB: Hezhou Municipal Land Resource Bureau; HPB: Hezhou Municipal Planning Bureau; HWRB: Hezhou Municipal Water Resource Bureau; HEPB: Hezhou Municipal Environmental Protection Bureau; HTPD: Hezhou Municipal Traffic Police Department. - 275 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions Public Village Changlo consultation for committee ng key contents and and villagers Village, conclusions for The public support Site from Anshan the draft EIA to the Project and visit, Changlong The Project will strictly follow the ESMP 2017.9 Village, seek public approve the proposed Questio Village, to implement relevant environmental .13 Yingshi understanding environmental nnaires Anshan protection measures. Village, and support for protection measures. survey Village, and the Project and Yingshi Lining the mitigation Village, and Village. measures Lining Village. proposed Villagers from Public Residen 1. The public support The Project will strictly follow the ESMP Diandengzhai consultation for ts along the Project and to implement relevant environmental Village, key contents and Dianden approve the proposed protection measures. Site residents conclusions for gzhai, environmental Initiate the project construction as soon visit, along the draft EIA to 2017.9 Huanga protection measures. as possible, and strictly follow the design Questio Huangansi seek public .13 nsi 2. The public It is requirements and the construction plan. nnaires Temple and understanding Temple, suggested that the Implement the pollution control measures survey Shizigang, and support for Shizigan construction to be accordingly and try to complete by one village the Project and g, commenced and take. Complete the construction as soon committee the mitigation Xialiang completed as soon as as possible so that the facilities can be and villagers measures - 276 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions Village from Xialiang proposed possible. put in operation early. Village, and Babu District Chengdong Street Office Public consultation for key contents and Village conclusions for Meiyi Site The public support committee the draft EIA to Village visit, the Project and The Project will strictly follow the ESMP 2017.9 and villagers seek public and Questio approve the proposed to implement relevant environmental .14 from Meiyi understanding Gubai nnaires environmental protection measures. Village and and support for Village survey protection measures. Gubai Village the Project and the mitigation measures proposed Sanjia Village Public 1. The public 1. The Project will strictly follow the Village, Site committee consultation for support the Project ESMP to implement relevant Mintian visit, and villagers key contents and 2017.9 and approve the environmental protection measures. Village, Questio from Sanjia conclusions for .14 proposed 2. The area where the Laozenwu in Xialiang nnaires Village, the draft EIA to environmental Xialiang Village and Laoxuewu in Fanglin Village, survey Mintian seek public protection measures. Village are in involves He River section and Village, understanding - 277 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions Fanglin Xialiang and support for 2. Representatives from Fanglin Hydropower Station to Village Village, and the Project and from Laozenwu in Xiadao Power Station. For the Xiadao Fanglin the mitigation Xialiang Village and Power Station, the project design is Village measures Laoxuewu in Fanglin limited to the upgrade of the building proposed Village raised an surface, thus it will not affect the issue. Because of the upstream water level. Therefore the demolishing of the Project will not affect the groundwater Babu Bridge water level in the area where the gate, the water level representatives are living in. the water will decrease and the supply pipelines will be installed groundwater level gradually as the urban area develops. and the drinking water in the area will be affected. They hope their drinking water supply can be improved by installing water supply pipeline and connecting tap water to the villages. Xiwan Site Xiwan Street Public 1. The public 1. The Project will strictly follow the 2017.9 Street visit, Office, Village consultation for support the Project ESMP to implement relevant .15 Office, Questio committee key contents and and accept the environmental protection measures. Xiwan nnaires and villagers conclusions for proposed 2. The Xiwanzhai area is within the - 278 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions Village, survey from Xiwan the draft EIA to environmental service area of the Pinggui District Gonghe Village, seek public protection measures. WWTP which has already been Village Gonghe understanding 2. The residents in constructed and put into operation. The and Village and and support for Gonghe Village sewer network for the area is gradually Gongqia Gongqiao the Project and Xiwanzhai area hope being constructed. o Village Village the mitigation that their sewer can measures be accepted in the proposed city sewer system. 1. The representatives are supportive to the Project and consider Soliciting the Project very comments on the important and potential impact Questio necessary. The Project will strictly follow the ESMP 2017.9 on underground / nnaires HHCB 2. Accepting the to implement relevant environmental .14 pipelines and survey environmental protection measures. mitigation protection measures measures to be to be taken. taken 3. It is suggested that the project owners and constrictors should - 279 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions prepare relevant emergency plans. 1. Fully supportive to the Project; 1. The Project will strictly follow the 2. Accepting the ESMP to implement relevant environmental environmental protection measures. protection measures 2. The design institute provide to be taken; supplement assessment to clarify that 3. Further the Project will not change the overall Soliciting assessment should structure of the Xiadao Power Station, comments on the be conducted on thus the ship passage facility will not be Questio potential impact flood carrying involved. In addition, the water level of 2017.9 / nnaires HTB on traffic and capacity of He River will remain largely unchanged, .14 survey mitigation small-scaled thus no impact on navigational measures to be Hydropower stations environment will be caused. taken and on the 3. During the project design, many dimensions of the coordination have been conducted with navigation channel, the management committee of the new reserve ship passage eco-city and reached agreement. facilities to ensure 4. Tried to solicit comments from the safe bridge operation; railway authorities, however no response 4. It is suggested have been received. that comments should - 280 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions be solicited from the Eco-city management committee on the implementation He River Embankment component. 5. It is suggested that the IAs should conduct further assessment on flood carrying capacity and navigation channel dimensions of the bridge for safety assurance; 6. He River rehabilitation might cause safety issue for Gui-Guang Express Railway. Therefore, it is suggested that comments be solicited from the municipal railway - 281 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions authority. 1. The representatives all support the Project and consider the Project very important and necessary. Soliciting 2. Accepting the The Project will strictly follow the ESMP comments on the environmental to implement relevant environmental potential impact protection measures protection measures. Questio on the Historic to be taken. In addition to original proposed protection 2017.9 / nnaires HCPPRFTB cultural street 3. Suggesting to measures, add a new measure: “the .15 survey (Xiyue Street) add “the protection of protection of the historic buildings in and mitigation the historic buildings Xiyue Street (historic cultural street) measures to be in Xiyue Street should follow relevant cultural heritage taken (historic cultural protection requirement.� street) should follow relevant requirements on cultural heritage protection� in the proposed protection measures. 2017.9 / Comme HEPB Soliciting 1. It is suggested 1. The Report is further improved based - 282 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions .14 nts comments on the that the Project on Hezhou He River Urban Section solicitin Chapter of should be further Integrated Rehabilitation Implementation g Accumulative coordinated with Plan. Impact Analysis. relevant documents 2. The Report is further improved based such as the Hezhou on WB environmental specialist’s He River Urban comments. Section Integrated Rehabilitation Implementation Plan. 2. For technical issues such as the project impact and measures to be taken, refer to WB environmental specialist’s comments as final decision. Soliciting Comme comments on the 2017.9 nts / HMEAB Chapter of No further comments / .18 solicitin Accumulative g Impact Analysis. 2017.9 / Comme HWRB Soliciting Suggesting to change Accepted - 283 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions .18 nts comments on the the responsible entity solicitin Chapter of to HMEAB and g Accumulative HWRB Impact Analysis. 1. The underground utilities pipelines documents have been collected. 1. Fully supportive to the Project 2. The following measures will be taken Soliciting when underground utilities pipelines are 2. Accepting the comments on the involved: (1) Coordinate with relevant environmental project impact agencies including the municipal protection measures from dredging, or engineering administration departments to be taken. on the and housing and urban-rural 3. Suggesting to development authority to acquire Questio underground 2017.9 request relevant underground pipeline survey material, / nnaires HMEAB utility pipelines, .19 underground understand the basic information survey famous and pipelines data from including pipeline type, alignment, buried historic trees, and HHURDB. depth, etc., establish coordination team mitigation Establishing a for pipeline. Excavation activities measures to be pipeline coordination involving underground pipelines should taken team and designate be pre-approved by the authorities, such special liaison as the municipal engineering person. Developing a administration departments and the construction plan housing and urban-rural development based on actual authority; (2) develop construction plan - 284 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions pipeline conditions. and emergency plan based on the When the excavation pipeline alignment and buried depth, to involves existing avoid underground pipelines as much as pipelines, informing possible; and (3) before commencement relevant property of excavation activities involving owners to supervise underground pipelines, report the and prepare construction area and construction time emergency plans. For to relevant authorities before excavation excavation in so that necessary preparation of municipal roads, emergency plans can be made. relevant approval 3. The following measures will be taken documents should be when historic famous trees are involved: prepared at relevant (1) minimize the construction area and authorities. shorten the construction duration; (2) 4. The protection prohibit cutting, moving, bark peeling, measures for historic root digging, or infection of hazardous or famous trees should toxic materials to the historic famous be strictly trees; (3) prohibit activities within 5 implemented. meters of horizontal distance from the crowns of historic famous trees include developing buildings or structures, laying pipelines, establishing cable lines, excavation for borrowing pit, ground inundation or sealing, fume discharging, - 285 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions sewage dumping, or stacking and dumping flammable, explosive, toxic or hazardous materials; (4)prohibit activities including carving, stapling, winding, hanging or leaning against and piling against; (5)prohibit running over with construction vehicles or equipment within 5 meters of horizontal distance from the crown. 1. Fully supportive to the Project and cooperative in 1. The Project will strictly follow the relevant planning ESMP to implement relevant Soliciting service. environmental protection measures. comments on the 2. Suggesting to 2. During the project design, relevant Questio project impact on coordinate with plans including the drainage plans and 2017.9 / nnaires HPB Xiyue Street and drainage and water water way system plans have been taken .20 survey mitigation way system planning, into consideration. During the project measures to be especially the implementation, the planning authorities taken planning under will be further coordinated for further preparation, such as optimization of the project design based the sponge city on the city master plan. planning, the downtown area style - 286 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions guideline, and the controlling plans for each district, to ensure the implementation of each plans and the Project. 1. All participants 1. The Project will strictly follow the are supportive for the ESMP to implement relevant Project. environmental protection measures. Owners and 2. Accepting the 2. The EIA consultant and the water operators of Exploring the environmental resource departments conducted Huangshi, project impact on protection measures survey on the farm lands affected. Semina Irrigation in areas upstream of Fanglin, power stations to be taken. rs and Huangshi Power Station will not be 2017.9 Xiadao power owners and 3. The upgrades of HWRB Questio affected. The Fanglin Hydropower .20 stations. operators and Huangshi Power nnaires Station will have some irrigation Representativ mitigation Station and Fanglin survey functions. As the water gate will be es from traffic measures to be Hydropower Station police taken removed under the Project, the back will impact on the department water level will fall, causing certain upstream irrigation of impact on the irrigation of farm land large area of farm on the right bank in a total area of lands. 1600 mu. The Project proposed to 4. The traffic police build a new irrigation pumping station - 287 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions department to pump He River water from He River suggested: (1) before to safeguard supply of irrigation water. construction 3. The comments from the traffic police commencement, department have been incorporated relevant preparation into the ESMP. should be done including campaign, coordination with transportation authorities, and re-routing of bus lines, etc. (2) construction vehicles should not speed or overload. They should be sealed and cleaned regularly to mitigate environmental impacts. Representativ Negotiating and It is confirmed that the The following protection measures are to 2017.9 Hezhou Semina es from HPB, confirming the Babu Special Branch be taken: (1) For the current Babu .20 DRC rs HEB, plan for the Babu Historic Site in Xiadao Special Branch Historic Site in Xiadao HCPPRFTB, Special Branch Primary School is a Primary School, the dike protection plan - 288 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions HPDG, Historic Site in cultural heritage has been adjusted from T-shaped Pinggui Xiadao Primary protection unit. It is an revetment to vertical retaining wall to District EPB, School important existing reduce the construction affected area so and Pinggui “red culture� heritage that the cultural heritage can be avoided District in Hezhou, and a and the in-situ protection can be CNRTB base for promoting conducted (2) Before the construction patriotism education commencement, negotiate with the and red culture-based relevant authorities to develop effective tourism. Therefore it cultural relics protection plans. (3) has high value and Develop detailed construction plan prior should have in-situ to construction commencement, place protection. warning signs on site for cultural heritage protection, in which information provided will include the nature, significance, protection area, protection measures for the heritage, and contact person and contact information for the management entity. (4) Do not allow construction activity within the cultural heritage protection area. Do not use excavator or piling machines, instead use manpower excavation to minimize the vibration impact on the cultural heritage. (5) Conduct cultural heritage protection - 289 - Table 10-3 Summary of second round of public participation and feedbacks Public Time Venue Method Objects Contents Feedback to public comments comments/opinions awareness training for construction workers, so that they can avoid the cultural heritage in construction activities and avoid man-made damage to the cultural heritage. CCP: Chinese Communist Party; CNRTB: Cultural, News and Radio & TV Bureau; CHMI: Cultural Heritage Management Institute; HAB: Hezhou Municipal Agricultural Bureau; HAAHB: Municipal Aquatic & Animal Husbandry Bureau; HCPPRFTB: Hezhou Municipal Cultural, News and Radio & TV Bureau; HDRC: Hezhou Municipal Development and Reform Commission; HMEAB: Hezhou Municipal Engineering Administration Bureau; HFoB: Hezhou Municipal Forestry Bureau; HFB: Hezhou Financial Bureau; HHCB: Hezhou Municipal Housing and Construction Bureau; HLRB: Hezhou Municipal Land Resource Bureau; HPB: Hezhou Municipal Planning Bureau; HWRB: Hezhou Municipal Water Resource Bureau; HEPB: Hezhou Municipal Environmental Protection Bureau; HTB: Hezhou Municipal Transportation Bureau; HTPD: Hezhou Municipal Traffic Police Department. HPDG: Hezhou Pinggui District Government - 290 - Figure 10-1: Photos taken at the seminars - 291 - Figure 10-2: Photos taken during public participation surveys - 292 - 10.3.2 Public Participation Outcomes and Discussions The 5 key issues concerned by the affected people and relevant authorities during the public participation process and the corresponding feedbacks are summarized as follows: 1st Issue: Land acquisition and resettlement, and replacement of resettled farmers losing their lands Feedback: (1) The design will be optimized to minimize land acquisition and resettlement and thus minimize the number of resettled people in the Project; (2) the relevant national and local laws and regulations will be strictly followed to develop a reasonable compensation standard to compensate people affected in the land acquisition and resettlement; (3) for the rural labors who lose their land, aids will be provided to get employed in non-agricultural industries by means of targeted recommendation and in-person communications, etc. 2nd Issue: Expectations on early commencement and early completion of the Project and actions to avoid repetitive construction. Feedback: Improvements will be made to the project design and preparation to enable early commencement of the construction works. The construction will strictly follow the design and construction plan and the pollution control measures. The contractors should make all efforts to complete the construction works at one go as soon as possible and avoid repetitive construction. 3rd Issue: Arrangement of sewage discharge in the surrounding area. Currently there are no complete sewage collection system in Xiwanzhai and Fanglin Villages (Hezhou Experimental Middle School). The sewage is discharged to He River after treatment in septic tanks or small-scaled treatment facilities. The performance of these small-scaled facilities is not stable and the operational cost is very high. Therefore it is suggested to improve the drainage system for these areas, so that the sewage can be collected and sent to WWTPs for treatment to avoid river pollution. Feedback: The Xiwanzhai Village is within the service area of Pinggui District WWTP already in operation. The sewer system for the WWTP is being improved and will cover Xiwanzhai Village very soon. The sewage from Fanglin Village will be sent to the planned Pinggui District WWTP. 4th Issue: Mitigation measures for construction noise. There are four schools (Hezhou Experimental Middle School, Pinggui No.3 Middle School, Yingshi Primary School and Xiadao Primary School) in the close neighborhood of the project area. Will the teaching activities in these schools be affected? Feedback: For Hezhou Experimental Middle School, temporary sound barrier will be established. For Yingshi Primary School, the entire school will be relocated. For Pinggui No.3 Middle School and Xiadao Primary School, the construction area will be separated by the sport grounds from the schools teaching buildings and dormitory buildings, therefore the construction activities will have no impact on regular teaching activities. - 293 - 5th Issue: The protection plan for the Babu Special Branch of CCP in Xiadao Primary School. Feedback: It is confirmed that the Babu Special Branch Historic Site in Xiadao Primary School is a cultural heritage protection unit. It is an important existing “red culture� heritage in Hezhou, and a base for promoting patriotism education and red culture-based tourism. Therefore it has high value and should have in-situ protection. It is planned to adjust the original dike protection plan from T-shaped revetment to vertical retaining wall to reduce the construction area and avoid this cultural relics site. Public comments and suggestions are summarized in Table 10-2, which have been taken into account by the EIA consultant and feasible adjustment suggestions and pollution control measures were proposed on such a basis. 10.3.3 Statistics of Public Participation Questionnaire Survey The targets of the survey are the residents in the affected area. Site visits were conducted and universal and representative samples were taken from the different subproject areas. Results of such survey are summarized as follows: (1) Statistics of basic information of respondents For the first public consultation survey a total of 170 individual questionnaires were distributed with a 100% recovery rate. 158 out of the 170 recovered questionnaires were valid, with a validity ratio of 92.9%. For the second public consultation survey a total of 180 individual questionnaires were distributed with a 100% recovery rate. 171 out of the 180 recovered questionnaires were valid, with a validity ratio of 95.0%. The survey visits and seminars are illustrated in the Figure 10-1 and Figure 10-2. The profile of the questionnaire respondents is summarized in Table 10-4. Table 10-4 Profile of the public consultation questionnaire respondents First Round Second Round No. Item No. of Percentage No. of Percentage people (%) people (%) Gen Male 111 70.3 113 66.1 1 der Female 47 29.7 58 33.9 College or 48 30.4 13 7.6 above Diploma 17 10.8 13 7.6 Edu 3 cati Junior 6 3.8 10 5.8 on diploma Senior High 15 9.5 26 15.2 School - 294 - Table 10-4 Profile of the public consultation questionnaire respondents First Round Second Round No. Item No. of Percentage No. of Percentage people (%) people (%) Junior High 27 17.1 64 37.4 School Primary School 32 20.3 17 9.9 and less 20 or less 0 0 2 1.2 21-30 22 13.9 26 15.2 31-40 50 31.6 38 22.2 4 Age 41-50 29 18.4 44 25.7 51-60 32 20.3 35 20.5 Above 60 20 12.7 24 14.0 Pinggui District Huangtian HDRC Township Lining village committee Hezhou Pinggui District Huangtian Township LARO Anshan village committee Pinggui District Huangtian Hezhou Pinggui District Township Lining village WRB committee Hezhou Pinggui District Pinggui District Huangtian Units or groups Huangtian Township Township Yingshi Village covered during Gonghe Village Committee Committee 5 the questionnaire Pinggui District Huangtian survey Hezhou Institute Township Chonglong Village Hezhou Babu District Babu Street Sanjia Village Xiadao Village Committee Committee Hezhou Babu District Hezhou Babu District Jiangnan Street Xialiang Chengdong Street Office Village Committee Hezhou Babu District Babu Meiyi Village Committee Street Office - 295 - Table 10-4 Profile of the public consultation questionnaire respondents First Round Second Round No. Item No. of Percentage No. of Percentage people (%) people (%) Babu District Land acquisition and Xialiang Village Committee Resettlement Office Hezhou Babu District Lingfeng Village on People’s Government Office Chengdong Street Hezhou Pinggui District Liantang Township Gubai Huangtian Township Lining Village Committee Village Committee Hezhou Pinggui District Huangtian Township East district management Qingmian Village station Committee Hezhou Babu District Liantang Township Fanglin Village Committee Government Hezhou Pinggui District Pinggui District Xiwan Huangtian Township Street Shangsong Village Changlong Village Committee Committee Pinggui District Xiwan HLRB Street Xiwan Village Committee Pinggui District Xiwan HTB Street Office Babu District LARO Gonghe Village Committee HCPPRFTB Mintian Village Committee Hezhou Babu District Babu HFoB Street Sanjia Village Committee Guidong Power Group HWRB Company Hezhou Pinggui District HPB No.3 Junior High School Hezhou Pinggui District Guangxi Zhengyou Group Huangtian Township - 296 - Table 10-4 Profile of the public consultation questionnaire respondents First Round Second Round No. Item No. of Percentage No. of Percentage people (%) people (%) Yingshi Primary School Company Etang Township Xiadao Hezhou HMEAB Primary School Hezhou Experimental High School HCPPRFTB: Hezhou Municipal Culture, Press, Publication, Radio, Film and TV Bureau; HFoB: Hezhou Municipal Forestry Bureau; HMEAB: Hezhou Municipal Engineering Administration Bureau; HLRB: Hezhou Municipal Land Resource Bureau; HPB: Hezhou Municipal Planning Bureau; HTB: Hezhou Municipal Transportation Bureau; LARO: Land Acquisition and Resettlement Office; WRB: Water Resource Bureau; (2) Survey results analysis The survey results are summarized in Table 10-5 and Table 10-6. Table 10-5 Public Survey Results (Individual) First round Second round Chosen Content No. of Percent No. of Percentag answer people age (%) people e (%) 1. Are you familiar A. Familiar 134 84.8 132 77.2 with the Hezhou Urban Water Infrastructure and B. Not familiar 24 15.2 39 22.8 Environment Improvement Project 2. Are you satisfied A. Satisfied 23 14.6 37 21.6 with the current B. Fair 70 44.3 68 39.8 conditions of water environmental and C. Not urban flood control in 65 41.1 66 38.6 satisfied Hezhou? 3. What do you think A. Environme 19 12.0 31 18.1 are the impacts that ntal impact the Project will bring B. Job upon you? 8 5.1 9 5.3 (income) - 297 - Table 10-5 Public Survey Results (Individual) First round Second round Chosen Content No. of Percent No. of Percentag answer people age (%) people e (%) C. Residential land (farm 31 19.6 40 23.4 land) being occupied D. Other 8 5.1 6 3.5 E. No impacts 99 62.7 91 53.2 A. Air 18 11.4 26 15.2 pollution 4. What do you think B. Water is the biggest impact 36 22.8 54 31.6 pollution on environment in the C. Noise 27 17.1 55 32.2 project implementation? D. Solid 26 16.5 23 13.5 Waste E. No impacts 68 43.0 23 13.5 A. Air 36 22.8 45 26.3 5. Which of these pollution areas do you think B. Water should be 85 53.8 85 49.7 pollution strengthened in C. Solid terms of 51 32.3 50 29.2 Waste environmental pollution control D. Noise 35 22.2 48 28.1 (multiple choices). E. Ecological 76 48.1 51 29.8 protection A. Positive 93 58.9 109 63.7 6. How will the B. Negative 2 1.3 13 7.6 Project affect your C. Negative daily work and life but 9 5.7 18 10.5 after completion? acceptable D. No impact 52 32.9 30 17.5 7. What kind of A. Very 125 79.1 121 70.8 impact do you think positive the Project will have B. Fair 22 13.9 43 25.1 - 298 - Table 10-5 Public Survey Results (Individual) First round Second round Chosen Content No. of Percent No. of Percentag answer people age (%) people e (%) on the coordinated C. Negative 1 0.6 2 1.2 economic and social development? D. No impact 5 3.2 4 2.3 8. Based on above, A. Support 158 100 171 100 what is your attitude towards the Project? B. Oppose 0 0 0 0 Table 10-6 Public Survey Results (Group) Second First round SN Content Chosen answer round Person % Person % A. News 1 4.2 3 13 B. Government 20 83.3 19 82.6 Before this survey, meetings have you received C. Construction any information 0 0 2 8.7 1 unit about the Project and what is the D. Public 1 4.2 0 0 source? discussion E. Other means 4 16.7 3 13.0 F. Do not know 0 0 0 0 In your opinion how A. Very good 2 8.3 4 17.4 are the current B. Fairly good 5 20.8 7 30.4 conditions on water 2 C. Fair 7 29.2 10 43.5 environmental and urban flood control D. Poor 5 20.8 2 8.7 in Hezhou? E. Very poor 5 0 0 0 A. Air pollution 2 8.3 2 8.7 What do you think is B. Water pollution 5 20.8 13 56.5 the biggest impact 3 on environment in C. Noise 11 45.8 8 34.8 the project D. Solid Waste 6 25.0 3 13.0 implementation? E. No impacts 5 20.8 3 13.0 In your opinion A. Air pollution 8 33.3 6 26.1 4 which of these areas B. Water pollution 15 62.5 12 52.2 should be strengthened in C. Solid Waste 11 45.8 7 30.4 - 299 - Table 10-6 Public Survey Results (Group) Second First round SN Content Chosen answer round Person % Person % terms of D. Noise 11 45.8 7 30.4 environmental pollution control E. Ecological 18 75.0 13 56.5 (multiple choices). protection Do you think the A. Positive 24 100 23 100 Project will have positive effect on the 5 coordinated economic and social B. Negative 0 0 0 0 development? What do you think is A. Positive 12 50.0 15 65.2 the impact of the B. Negative 2 8.3 1 4.3 6 Project on your C. No impacts 6 25.0 6 26.1 organization? D. Negative but 3 12.5 1 4.3 acceptable Considering the A. Supportive 24 100 23 100 local economic development and environmental 7 protection, what is B. Not supportive 0 0 0 0 your attitude towards the Project? According to the statistical results, 100% of the residents surveyed favored the Project. The public are very supportive to the project implementation. 10.4 Information Disclosure According to requirements in the Interim Measures for Public Participation in Environmental Impact Assessment, the Environmental Information Disclosure Measures (Trial) and the World Bank OP / BP4.01 (Environmental Assessment), BP 17.50 (Information Disclosure), the Project disclosed relevant information by means of online disclosure and field posters, and distributed the EIA report and ESMP report at places with easy public access, including the PMO office, the municipal EPB, the EIA consultant, and offices of village committees. - 300 - The preparation progress of EIA and ESMP and the information disclosure status are summarized in Table 10-7. Table 10-7 Time, Location and Methods of Information Disclosure Title and content of disclosed Round Time Method Location information Official website for HEPB: http://hezhou.gxepb.gov.c April 2016 disclosure Online n/xxgk/ztfl/xzsp/gsgg/2016 04/t20160420_10202723.h tml, and official website for HDRC 1. Title of the document: First Bulletin boards for Babu round information disclosure District Government, for the EIA for Hezhou Urban Pinggui District Water Infrastructure and Government, Huangtian Environment Improvement Township Government, Project. and village committees or 2. Content: (1) Project street offices for overview; (2) EIA procedure Shangsong Village, Xiwan First Round and content; (3) Channels and February 2017 Village, Xiwan Street, deadlines for public access to Mintian Village, Fanglin Poster the ESIA report; (4) Deadlines Village, Gonghe Village, for public comments; (5) Lining Village, Changlong Contact information, including Village, Yingshi Village, mailing address, postal code, Huangtian Village, Anshan phone number, fax number, Village, Sanjia Village, contact person and email Gubai Village, Xiadao address etc. for the Village, Xialiang Village, construction unit and the EIA Lingfeng Village, consultant. Chengdong Street, Babu Street and Jiangnan Street. Official website for HEPB: disclosur Online 2017 June http://www.hzsepb.gov.cn/ e xxgk/jgfl/hpk/201706/t2017 0628_33576.html disclosu October Official website for HEPB Second 9, 2017 1. Title of the document: First Round Online and official website for re round information disclosure HDRC for the EIA for Hezhou Urban - 301 - Table 10-7 Time, Location and Methods of Information Disclosure Title and content of disclosed Round Time Method Location information Bulletin boards for Babu Water Infrastructure and District Government, Environment Improvement Pinggui District Project. Government, Huangtian 2. Content: (1) Project Township Government, background; (2) Potential and village committees or environmental impacts; (3) street offices for Measure for avoiding or Shangsong Village, Xiwan mitigating the impacts; (4) Main October 9, 2017 Village, Xiwan Street, conclusions of EIA; (5) Mintian Village, Fanglin Channels and deadlines for Poster Village, Gonghe Village, public access to the ESIA Lining Village, Changlong report; (6) Scope and items for Village, Yingshi Village, public consultation; (7) Huangtian Village, Anshan methods for public comments; Village, Sanjia Village, (8) Contact information; and (9) Gubai Village, Xiadao the full reports of the EIA and Village, Xialiang Village, ESMP. Lingfeng Village, Chengdong Street, Babu Street and Jiangnan Street. - 302 - Photos of First Round Online Disclosure Photos of First Round Field Posters - 303 - Photos of 2nd Round Online Disclosure - 304 - Photos of 2nd Round Field Posters - 305 - 10.5 Public Participation for Social Impact Assessment 10.5.1 Public participation and community consultation activities Since March 2016, a series of public participation and community consultation activities (see Table 10-8) have been carried out for the preparation of the Resettlement Plan by the consultants and the World Bank experts. These include: (1) In March 2016, the World Bank dispatched its first Pre-Identification Mission to conduct its preliminary project identification. The Mission also provided guidance for the social safeguard related works and provided detailed requirements. During the land acquisition and resettlement survey conducted between March 2016 and April 2017, representatives from agencies of different levels in charge of land acquisition and resettlement, and representatives from villages and shops all participated in the survey. During the survey, the female representatives were all present and examined closely the indicators for final survey results. (2) During the periods from April 16 to April 26 in 2016, July 21 to July 27 in 2016, August 10 to August 20 in 2016, January 20 to January 24 in 2017, February 20 February 23 in 2017, March 2017, March 17 to March 21 in 2017, April 24 to April 29 in 2017, the consultants, PMO, IAs, and the Resettlement Office organized a number of meetings among representatives from different agencies and the affected people. These agencies include the land resource bureaus, planning bureaus, and housing and urban-rural development bureaus for Babu District and Pinggui District. At these meetings, information was disclosed on the existing policies on land acquisition and resettlement compensation standards at national, regional or municipal levels, and the World Bank policy document (OP/BP4.12). From the participants, comments have been solicited on mitigating project impacts, confirming compensation standards, and resettlement and livelihood restoration plans etc. Based on these comments, the design institute has adjusted the project design several times to minimize the impact of resettlement. Through extensive consultation, it is all agreed that the loss on the affected people’s side will be compensated with cash compensation or physical placement following relevant national laws and regulations. (3) During the preparation of the Resettlement Plan from March 2016 to June 2017, the resettlement consultants, PMO, IAs, design institute and other relevant agencies visited various villages and villagers, held meetings with participating village leaders and villagers' representatives, interviewed representatives of participating units and shops, to solicit their opinions on land acquisition, resettlement policies and standards, resettlement plans and restoration methods. The meeting and surveys have been helpful to the resettlement issues, compensation policies, compensation eligibilities, and restoration plans. Other topics of discussion include the siting of office buildings for resettled units, self-owned buildings or concentrated compounds for resettled farmers. (4) In order to raise the project awareness, PMO, IAs, and the Resettlement consultant conducted a questionnaire survey on the affected communities and affected people during the period from March 2016 to April 2017. The survey covered all affected villages and tenants, as well as units and shops. Therefore the sampling is representative, structurally reliable, and can truly reflect the wishes of the affected people. (5) Seminars on environmental and resettlement were held between November 2016 and February 2017. - 306 - The consultation concluded that the affected people do not want further adjustment on land related issues. For the loss of income due to loss of land, the affected people demanded for cash compensation and provision of employment opportunities, required the government to solve the permanent homestead issue as soon as possible and build the foundation with full cash compensation in place. Compared with the house demolition, the affected people cared less about land acquisition. This is because the project area is along He Rivers and main channels. The lands to be acquired are basically those lands that can be useful only when inundation is not a problem. And because these affected people are near the city, they are not willing to be working on agricultural or salt production. Therefore they hope that the Project can bring about economic transformation and new employment opportunities, and that they can get the homestead for house building, or get fully compensated in cash. All the questionnaire respondents expressed their wishes to use the compensation to rebuild the house, and most of them also want to use the compensation to start some business, or master some skills through training, or even be employed in big enterprises, instead of going back to land farming business. They want to use the cash compensation for their land loss to restore their livelihoods and income, such as: 1) the purchase of social insurance; 2) self-owned business in the tertiary industry, i.e. clothing stores, grocery stores, transport, freight, community services, repair shop, hairdressing, salon, dry cleaners, entertainment, catering and hotel services, and tourism service, etc.; 3) investment in their children's education. They hope that through training they can find jobs in other institutions, business units and business organizations. Affected people are satisfied with the compensation arrangement and the resettlement measures. However, they also expressed their concern about fair and timely payment of compensation. - 307 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants Morning Conference Explain the importance PMO Representatives from PMO, 60 15 Conduct front end of March room at of the Project. District Governments, campaign 24, 2016 HDRC Campaign and Street Offices, Village mobilization committees, and Resettlement Consultant March Conference Discuss the Project owner Representatives from PMO, 20 0 Sort out and 25, 2016 room at resettlement impact and Project owners, design discuss issues on HDRC within the scope of resettlement institutes, Municipal reducing land project design RoRL. consultant Planning Bureau, Municipal acquisition and Housing and Construction resettlement in the Bureau, Offices of Land project-affected Acquisition and area Resettlement for Babu District and Pinggui District, and Resettlement Consultant April 13, Conference Understand the project District LAROs Representatives from PMO, 56 12 Further understand 2016 room at awareness of District District Governments, the attitude of HDRC Governments, Village Street Offices, Village affected people to Committees and committees, villagers the Project villagers within the representatives and preliminarily Resettlement Consultant determined affected area. April 14 – Village Resettlement social Resettlement Related village committee 210 60 Clarify the social 18, 2016 committee of economic survey, consultant and affected people, and economic - 308 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants affected project-affected area Resettlement Consultant conditions in the villages, and and attachment survey project area and affected impacts from the units Project April 28, Conference Understanding WB PMO PMO consultant, 52 15 The implementation 2016 room at Social Safeguard representatives from project parties understand HDRC policies owners, District relevant WB social Governments, Street safeguard policies. Offices, Village committees, and Resettlement Consultant April 29 15 affected Soliciting resettlement Resettlement Relevant township 13 6 Negotiate on land to May 8, villages and opinions Consultant governments, street offices, acquisition 2016 affected village committees, affected compensation units. people and Resettlement methods and Consultant standards. Morning Mintian Conduct willingness Mintian Village Representatives of Mintian 30 6 Follow recent of July Village survey on land Committee Village committee and compensation 22, 2016 Committee, acquisition and village groups, villagers and policies. During village and resettlement related Resettlement Consultant project project site issues with the implementation, representatives from reduce excavation. Mintian Village Restore road Committee and village surface promptly groups. after surface breaking. Afternoo Fanglin Conduct willingness Fanglin Village Representatives of Fanglin 23 6 Try best to solve n of July Village survey on land Committee Village committee and the sewer problems 22, 2016 Committee, acquisition and village groups, villagers and and the tap water village and resettlement related pipeline problems - 309 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants project site issues with the Resettlement Consultant for the village representatives from Fanglin Village Committee and village groups. Morning Gonghe Conduct willingness Gonghe Representatives of Gonghe 29 13 The compensation of July Village survey on land Village Village committee and standards should 23, 2016 Committee, acquisition and Committee village groups, villagers and be publicly village and resettlement related Resettlement Consultant disclosed. The project site issues with the compensation representatives from should be directly Gonghe Village paid to individual Committee and village account. groups. Morning Sanjia Conduct willingness Sanjia Village Representatives of Sanjia 32 5 The compensation of July Village survey on land Committee Village committee and will be used to 25, 2016 Committee, acquisition and village groups, villagers and improve the village and resettlement related Resettlement Consultant housing conditions. project site issues with the It is hoped that the representatives from house building Sanjia Village approval process Committee and village can be simplified. groups. Morning Huangtian Interview with Huangtian Huangtian Village 22 6 Follow recent of July Village Huangtian Village Village Committee and compensation 26, 2016 Committee Committee Committee Resettlement Consultant policies; make and village payment in a timely manner; Make no unattainable promises.. - 310 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants Afternoo Xiwan Visit Xiwan Village Xiwan Village Xiwan Village Committee 28 8 Follow recent n of July Village Committee Committee and Resettlement compensation 26, 2016 Committee Consultant policies; make and village payment in a timely manner; Make no unattainable promises.. Morning Shangsong Interview with Fanglin Fanglin and Fanglin and Sanjia Village 10 4 Follow recent of July Village and Sanjia Village Sanjia Village Committee, and compensation 27, 2016 Committee Committee Committee Resettlement Consultant policies; make and Lining payment in a timely Village manner; Make no Committee unattainable promises.. Morning Conference Seminar with affected PMO and Affected village committee, 45 15 Communication on of room at village committee Resettlement villagers and Resettlement project scope January HDRC representative due to Consultant Consultant change. The 22, 2017 design changes changes are believed as beneficial to environmental improvement and thus supported. January Xialiang Focus group PMO and Representatives from street 21 6 The houses to be 23, 2017 Village discussion about Resettlement offices, project owners and demolished are - 311 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants Committee resettlement hospital Consultant affected people urban residential buildings, should follow urban residents resettlement policies to settle the affected people. January HAB office Focus group Resettlement Representatives from HAB, 25 10 Shops are 24, 2017 discussion on shops Consultant HWRB and shops along the transitional housing and resettlement Yinhe Street that emerged under hospital special historical conditions. It has no property rights but only tenure rights. People all know that they need to move when the government wants us to move, but they should be compensated following the most recent policy and standards. Morning Conference Consultation on HWU and 2-3 women representatives 27 Women are also of room at women’s rights Resettlement from affected villages in entitled to be February Babu District Consultant Babu District informed the 23, 2017 Government resettlement arrangement and have equal rights in - 312 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants terms of compensation money. Morning Conference Consultation on HWU and 2-3 women representatives 26 Women are also of room at women’s rights Resettlement from affected villages in entitled to be February Pinggui Consultant Pinggui District informed the 23, 2017 District resettlement Government arrangement and have equal rights in terms of compensation money. March Conference project-affected area Resettlement Representatives from PMO, 46 18 Fully understand 18, 2017 room at and attachment survey Consultant Project owners, LAROs of affected people’s HDRC feedback meeting Babu District and Pinggui attitude towards the District, 9 affected Project. Develop an township (including information Huangtian, Shatian, Babu communication and Street, etc.) and major feedback affected villages mechanism. Let affected people fully understand their rights. Morning Conference Coordination between World Bank PMO, Project owner, 22 6 Relevant agencies of April room at resettlement Senior Social Resettlement Consultant, expressed their 25, 2017 Municipal implementation Safeguard HLRB, HHCB, HPB, District support to the Government organization and Specialist LAROs, District Project. Clarified Education relevant agencies. Government leaders and their responsibilities Center township government in the resettlement leaders. process and - 313 - Table 10-8 Record of public participation process of affected people No. of No. of Results of Time Venue Agenda (topics) Organizer Participants female participants negotiation participants relevant agencies should prepare emergency plan for potential issues. Understanding lawsand Discussing about regulations, ownership of flood PMO, LRB, DI, supporting project plains on river banks; Resettlement consultant construction, willing Morning, DRC Resettlement training on national team. Urban district to abide by laws Sept. 5, Conference consultant 35 9 river management law; government leader, relevant and regulations, 2017 Room team negotiating about village committees, villager hoping to get paid resettlement representatives of the young crop compensation plan. compensation according to the standard HAB: Hezhou Municipal Agricultural Bureau; HDRC: Hezhou Municipal Development and Reform Commission; HHCB: Hezhou Municipal Housing and Construction Bureau; HLRB: Hezhou Municipal Land Resource Bureau; HPB: Hezhou Municipal Planning Bureau; HWU: Hezhou Municipal Woman’s Union: HWRB: Hezhou Municipal Water Resource Bureau; LARO: Land Acquisition and Resettlement Offices; PMO: Project Management Office. - 314 - 10.5.2 Public participation plan during project implementation In order to properly and promptly address the difficulties and needs of the affected people on land acquisition and resettlement, public consultation will continue after the commencement of the project implementation and before the implementation of Resettlement Plan, so that all problems can be resolved. The implementation unit shall arrange the meeting properly on the issue of land acquisition and resettlement. Each AF will have the opportunity to negotiate a compensation contract with the Office of Land Acquisition and Resettlement. The public consultation plans and processes are summarized in Table 10-9. 315 Table 10-9 Public Consultation Plan and Process for Land Acquisition and Resettlement Purpose Form Time Implementation unit Target Notes participants 1. Introducing the Village December PMO, EA, IAs, design institute, All affected people The meetings will be held in Project and representative 2017 to District Governments, Village involved in LAR of each affected village and Resettlement Plan to conference and February Committees and units. the Project unit. affected people for Unit staff 2018 their opinions representative conference 2. Disclosing the Public village November PMO, EA, IAs, District All affected people Disclosing resettlement resettlement committee and 2017 Governments, Village involved in LAR of information brochure, information brochure enterprise Committees, units, HLRB and the Project discussing concerned meeting, and HLARO issues and suggestions on discussion among resettlement concerned group 3. Submitting the final Public and September PMO, EA, IAs, District All affected people Disclosing the final draft of draft of Resettlement community 2017 Governments, Village involved in LAR of Resettlement Plan to Plan to affected meeting, unit Committees, enterprises the Project affected people and people meeting, focus discussing relevant group discussion questions, accepting comments and suggestions from different parties 4. Conducting detailed Site survey and January PMO, IAs, District All affected people Conducting full-range survey family interview 2018 to May Governments, Village involved in LAR of survey for land acquisition 2018 Committees, units, HLRB, the Project and property indicator, and District LAROs collection social economic data 5. Advising the affected Public meeting March 2018 PMO, IAs, District All affected people Holding AF and staff people of rights and to July 2018 Governments, Village and beneficiaries meetings to cover 316 Table 10-9 Public Consultation Plan and Process for Land Acquisition and Resettlement Purpose Form Time Implementation unit Target Notes participants payment deadlines Committees, units involved in LAR of compensations and rights the Project 6. Disclosing details of Public and November PMO, IAs, and LAROs All involved parties, Meeting with beneficiaries Resettlement Plan to community 2017 beneficiaries and and affected people affected people meeting, unit affected people of before being meeting, focus the Project approved by WB group discussion 7. Monitoring the Family interview January PMO, IAs, District Random sampling Providing Resettlement affected people and 2018 to Governments, Township Plan and Implementation beneficiaries December Governments, Village Monitoring Plan 2022 Committees, units, HLARO, independent monitoring agency LARO: Land Acquisition and Resettlement Office; HLRB: Hezhou Municipal Land Resource Bureau 317 In order to successfully implement the Resettlement Plan, the affected people will be encouraged to participate actively in various LAR activities. The Project will have certain impacts on the local residents. To ensure that the affected people can benefit from the Project, the local residents and workers are encouraged to actively participate in the project construction. It is necessary to consider local residents and workers in terms of employment of labor force and provide them with the necessary assistance. - 318 - 11. Environmental & Social Management Plan 11.1 Environment and Social Management System Hezhou Municipal Environmental Protection Bureau is responsible for the review and approval of the various subprojects of the Project according to the administrative authority stipulated in the Law of the People’s Republic of China on Environmental Protection and the Regulations on Environmental Protection Management of Construction Projects. As the environment management agency of the Project, Hezhou Municipal Environmental Protection Bureau is mainly responsible for proposing environmental protection requirements based on the contents of the EIA Report of the Project, coordinating the environment management work of the various departments and organizing the “three-simultaneousness� acceptance of the environmental protection facilities. The World Bank Loan Project Management Office is responsible for managing the implementation of the entire Project while the Project Owner is responsible for implementing the various specific activities under the general administration framework of the Project as well as the leadership of Hezhou Municipal Government. In order to assure smooth implementation of the environment management activities of the Project, a number of full-time or part-time environment management personnel are assigned in the PMO, the Project Owner, the Contractor and the Operator to implement the Environmental & social management plan. 11.1.1 Environment Management Agency As the environment management activities of the Project in the construction stage are significantly different from those in the operation stage and such activities are either short-term or long-term in terms of their deadlines, the Contractor and the Operator should set up separate organizations to take the responsibility for different stages. As the construction stage ends, the management organization of the construction stage will be cancelled while that of the operation stage will start to operate, with a certain overlapping period allowed based on the progress of the specific management activities. - 319 - World Bank EIA consultant HPMO HEPB HWRB HMEAP HEPB External Monitoring agency Contractor Construction Supervision Engineer Supervisory Management Consulting agency Agency agency Project Owner Implementation Agency Figure 11-1: Schematic Diagram of the Environment Management Agencies in the Construction Stage of the Project HPMO World Bank Consultant External HEPB Operator Monitoring agency Supervisory Management agency Agency Operating Monitoring Agency agency Figure 11-2: Schematic Diagram of Environment Management Agencies in the Operation Stage of the Project - 320 - 11.1.2 Responsibilities and Contents of Environment Management The contents of environment management in the construction stage are remarkably different from those in the operation stage of the Project and the ESMP is implemented by different responsible departments. Table 11-1 shows the contents and staffing of each environment management agency for environment management work in different stages. Table 11-1 Contents of Environment Management in Different Stages Project Stage Key Contents of Environment Management Staffing stakeholders Contacting and coordinating with the competent government department of environment management PMO 2 for implementation of the environment management matters; 1. Responsible for a series of environmental protection management work in the design and preparation stage of the Project; 2. Securing the fund needed for the environmental protection work; Project Owner 3. Responsible for coordinating with the competent 3 government department of environment management for implementation of the environment management matters; Design and 4. Recruiting supervision engineer and collecting preparation records. 1. Incorporating the environmental protection measures into the design program and budget; Designer 3 2. Incorporating the ESMP mitigation measures into the technical specifications of the bidding documents. 1. Providing technical support to the environmental protection work included in the project design; EIA consultant 5 2. Preparing the EIA documents of the Project; 3. Development ESMP. 1. Responsible for review and approval of EIA Report of the Project; Municipal 2. Providing guidance to the urban and county EPBs on 2 EPB proper implementation of the routine environment supervision and management work of the Project. 1. Responsible for a series of environmental protection management work in the construction stage of the Project and securing the fund needed for the environmental protection work; 2. Managing and supervising the environmental protection work in the construction stage and investigating into and handling problems of public disturbance or pollution arising in the construction Construction Project Owner process; 3 stage 3. Responsible for coordinating with the competent government department of environment protection for implementation of the environment management matters; 4. Following up with the execution status of the ESMP and reporting on a periodical basis to the competent government department of the same level, the provincial PMO and the World Bank ; - 321 - Table 11-1 Contents of Environment Management in Different Stages Project Stage Key Contents of Environment Management Staffing stakeholders 5. Accepting and handing public complaints. 1. Implementing the environmental protection measures and the various activities in the construction stage based on the bidding documents, the construction contract and this ESMP; 2. Accepting guidance and supervision by the environment management personnel of the Project Owner, the construction supervision engineer and the Contractor related government departments; 3 3. Accepting technical supports provided by the environmental protection consulting agency; 4. Implementing safety protection measures, e.g. erecting signs and fences on the boundary of construction sites, setting up channels of public communication and assuring construction safety; 5. Executing the ESMP. 1. Supervising the contractor ’s execution of the ESMP and carrying out the environment mitigation measures in the construction contract; 2. Carrying out site supervision of the implementation Construction status of the Contractor; Supervision 5 3. Assisting the EA in carrying out the environment Engineer management work; 4. Keeping records of and developing and submitting to the Project Owner on a periodical basis ESMP execution status reports. 1. Carrying out the environmental monitoring work of the construction stage and operation stage of the Project Depending based on the authorization of the Project Owner and the Environmental on the environmental monitoring plan included in this EIA Monitoring scope of report; Agency authorized 2. Conducting the monitoring activity under the assignment authorization of the Project Owner in case of any abnormalities in the construction process. 1. Supervising and inspecting the environmental protection measures of the Project Owner and the Contractor; 2. Receiving ESMP execution reports submitted by the Project Owner and the PMO and performing the Local EPB administration functions based on such reports; 2 3. Arranging emergency response actions in the event of any abnormal environmental conditions in the construction process; 4. Accepting and coordinating the handling process of public complaints. 1. Providing technical supports to the environmental protection work in the construction stage of the Project according to the authorization of the Project Owner and Technical this EIA Report as well as the environmental protection Assistance / design outcomes; Unlimited Consultant 2. Providing the contractor with technical guidance on the environmental protection work and properly carrying out the environmental protection training work in the construction stage of the Project. - 322 - Table 11-1 Contents of Environment Management in Different Stages Project Stage Key Contents of Environment Management Staffing stakeholders 1. Responsible for the post-operation management work of environmental protection and implementing the mitigation measures and monitoring of the ESMP in the operation stage; 2. Responsible for contacting and coordinating with the competent government department about the implementation of the environment management Project Owner matters; 3 or Operator 3. Making emergency responses to environmental accidents; 4. Providing periodical staff training to enhance their competence and actively organizing activities for exchange of environmental protection technology and experiences to further improve the management work of environmental protection. 1. Carrying out the environmental monitoring work of the Depending Operation operation stage of the Project as authorized by the Environmental on the stage Project Owner and required in the environmental Monitoring scope of monitoring plan; Agency authorized 2. Carrying out the routine monitoring activities related to assignment the Project on a periodical basis. 1. Responsible for the final acceptance of the environmental protection work of the Project; Municipal 2. Guiding the county EPB to properly carry out the 2 EPB routine environment supervision and management work of the Project. 1. Managing and supervising the status of compliance with the environmental protection standards in the operation stage; Local EPB 2 2. Carrying out routine supervision and inspection of the operation status of the built environmental protection facilities. Public or Public supervision Not limited organizations 11.1.3 Environmental protection supervision plan Based on the characteristics of the Project, the implementation status of the environmental protection work of the Project is not only subject to the supervision of Hezhou Municipal EPB, but also the relevant department of the World Bank. Construction supervision engineers should be employed to assist the EA in site supervision and inspection in the construction stage of the Project and an environmental protection division should be set up to supervise the Project in the operation stage. See Table 11-2 for the environmental protection supervision plan of the Project. - 323 - Table 11-2 Environmental Protection Supervision Plan of the Project Stage Agency Content of Supervision Purpose of Supervision 1. To make sure the EIA Report has complete content, well-selected topics and clear focus; 2. To make sure that any 1. Reviewing EIA Outlines; significant and potential issues Municipal EPB, FS stage 2. Reviewing EIA Report; likely to arise in the Project are WB 3. Reviewing EAP reflected; 3. To make sure that a specific and feasible implementation plan is available for the mitigation measures of the environmental impacts. 1. Reviewing the preliminary environmental protection 1. To strictly enforce the design and ESMP; “three-simultaneousness� policy of 2. Inspecting the restoration of the Project; temporarily occupied land, and 2. To assure that all the vegetation and environment construction sites satisfy the affected by the construction environmental protection works; requirements; Municipal 3. Inspecting measures for 3. To reduce the impacts on the Government control of dust and noise surrounding environment in the Municipal EPB pollution and deciding construction stage and enforce the Babu District construction time; relevant laws and regulations and Design and EPB 4. Inspecting emission of air standards of environmental construction Pinggui District pollutants; protection; stage EPB 5. Inspecting discharge and 4. To make sure that the water Municipal Culture treatment of domestic sewage quality of He River and Inner River & Tourism and waste engine oil on the are not polluted; Bureau construction sites; 5. To make sure that the landscape 6. Inspecting restoration and and land resources are not treatment of borrow areas and seriously damaged to avoid soil waste disposal sites; erosion; 7. Inspecting disposal of 6. To make sure that the sludge is sludge; properly disposed; 8. Inspecting and determining 7. To protect the cultural resources whether there any from damages. underground cultural relics. 1. Inspecting the implementation of EAP in the operation stage; Municipal EPB 2. Inspecting the 1. To implement EAP; Babu District implementation of the 2. To implement monitoring plan; EPB monitoring plan; 3. To protect environment in the Pinggui District 3. Inspecting sensitive sites true sense; Operation EPB where further environmental 4. To strengthen environment stage Municipal public protection measures are management and actually security and fire needed (and where safeguard personal health; protection unanticipated environmental 5. To assure that the pollutant authorities problems may arise); emission satisfies the emission 4. Inspecting whether the standards. environment quality at the environmentally-sensitive sites satisfies the requirements of - 324 - Table 11-2 Environmental Protection Supervision Plan of the Project Stage Agency Content of Supervision Purpose of Supervision the corresponding quality standard; 5. Strengthening supervision to prevent unanticipated incidents and developing emergency response plans so that the environmental risks can be eliminated in time in the event of any accidents. 11.2 Environmental and Social Impacts and their Mitigation Measures The Project Components include He River Flood Risk Resilience Improvement Subproject and Urban Drainage and Wastewater Management Subproject. In accordance with the relevant laws and codes of China and Guangxi and in association with the World Bank General Environment, Health and Safety (EHS) Guidelines, EHS Guidelines for Water Supply and Drainage, general and special countermeasures and mitigation measures are proposed for the preparation stage, the construction stage and the operation stage of different types of subprojects. For the general countermeasures and mitigation measures, three ECOPs and 1 MP are developed as annexes to the ESMP, namely Annex 1: ECOP for Embankment Construction Component, Annex 2: ECOP for Small Waterworks Construction Component, Annex 3: ECOP for Road and Pipeline Network Construction Component and Annex 4: Management Plan of Physical Cultural Resources. Table 11-3 shows the ECOPs and MP applicable to the respective subprojects while Tables 11-4 to 11-13 present a summary of the environmental and social impacts as well as the mitigation measures. Table 11-14 summarizes the LAR and social impacts and their mitigation measures while Table 11-15 presents the Dam Safety Action Plan. Table 11-3 ECOP and ESMP applicable to each subproject S.N Name of subproject Applicable ECOP I Flood risk control He River Integrated Rehabilitation ESMP Annex 1: ECOP for Embankment A-1 Subproject (Huangshi Hydropower Construction Component Station – Guangming Bridge) He River Integrated Rehabilitation ESMP Annex 1: ECOP for Embankment A-2 Subproject (Guangming Bridge --- Construction Component; Annex 4: Physical Lingfeng Bridge) Cultural Resources Management Plan He River Integrated Rehabilitation ESMP Annex 1: ECOP for Embankment A-3 Subproject (Lingfeng Bridge – Xiadao Construction Component Hydropower Station) East Trunk Canal Integrated ESMP Annex 2: ECOP for Small Waterworks A-4 Rehabilitation and Mawei River Construction Component Connection Subproject II Urban drainage improvement ESMP Annex 2: ECOP for Small Waterworks B-1 Huangansi Drainage Pump Station Construction Component; Annex 4: Physical - 325 - Table 11-3 ECOP and ESMP applicable to each subproject S.N Name of subproject Applicable ECOP Cultural Resources Management Plan ESMP Annex 2: ECOP for Small Waterworks B-2 Shizigang Drainage Pump Station Construction Component ESMP Annex 2: ECOP for Small Waterworks B-3 Lining River Rehabilitation Construction Component ESMP Annex 2: ECOP for Small Waterworks B-4 Changlong River Rehabilitation Construction Component ESMP Annex 2: ECOP for Small Waterworks Huangtian Branch Canal Construction Component ; Annex 3: ECOP for B-5 Rehabilitation Road and Pipeline Network Construction Component Guposhan Drainage Canal ESMP Annex 2: ECOP for Small Waterworks B-6 Rehabilitation Construction Component East No. 5 Branch Canal ESMP Annex 2: ECOP for Small Waterworks B-7 Rehabilitation Construction Component III Water quality improvement ESMP Annex 1: ECOP for Embankment Huangansi Drainage Canal C-1 Construction Component; Annex 4: Physical Integrated Rehabilitation Cultural Resources Management Plan Shizigang Drainage Canal Integrated ESMP Annex 1: ECOP for Embankment C-2 Rehabilitation Construction Component Jiangnan WWTP and associated ESMP Annex 3: ECOP for Road and Pipeline C-3 pipeline construction Network Construction Component Institutional Capacity Building and IV Project Management River supervisor system + Internet ESMP Annex II: ECOP for Small Waterworks E-1 Smart Management System Construction Component - 326 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 1. He River (Huangshi Hydropower Station to Guangming Bridge, GL20+800~GL21+485), 685 m in length. Embankment width of the right bank is Original technical narrowed by 40 m and glass retaining design requires wall will be built to avoid relocation of demolition of large residents downstream from Huangshi Main quantities of Hydropower Station. Watercourse Residents on the residential buildings 2. He River (Huangshi Hydropower Widening for right bank of He on the right bank of Station to Guangming Bridge, Flood Discharge: River downstream He River GL10+545~GL10+940), 395 m in length. A-1 He River from Huangshi downstream from Technical design is optimized by Rehabilitation Hydropower Station, Huangshi changing earth dike to glass retaining (Huangshi ancient buildings in Hydropower Station, wall to narrow land area occupied and Hydropower Xiyue Street occupation of part of Design Design Technical design avoid impact to Hezhou High School on / / Station to Historical and land of Hezhou Institute the right bank. Guangming Cultural Quarter, Municipality High 3. He River (Huangshi Hydropower Bridge); The Old Site of CCP School, demolition Station to Guangming Bridge, A-2 He River Babu Special of The Old Site of GL2+760~GL2+800), 40 m in length. Rehabilitation Branch within CCP Babu Special T-shaped revetment slope is changed to (Guangming Xiadao Primary Branch, and vertical retaining wall to narrow land Bridge to School occupation of area occupied and avoid demolition of Lingfeng Bridge); protected area of The Old Site of CCP Babu Special A-3 He River Xiyue Street Branch. Rehabilitation Historical and 4. Construction area boundary is (Lingfeng Bridge Cultural Quarter. changed to avoid protected area of to Xiadao Xiyue Street Historical and Cultural Hydropower Quarter. Station) Watercourse Shangsong Village, Operation noise of As specified in Annex 1 of the ESMP, widening, civil shanty town of excavator, bulldozer, ECOP for Embankment Construction, work construction, Xiwan Village, loader, vibrator and temporary sound barrier with height not Hezhou Construction 30 Contractor construction Xiwan Town dump truck during lower than 2 m should be set for Municipal EPB material and residents, Pinggui construction will construction sites near Hezhou College, soil/stone District Government, have certain impact Hezhou Pilot Middle School and Xiadao - 327 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 transportation, Xiwan Community, on sensitive Primary School, and construction construction houses of receptors within 30 activities should be scheduled to avoid camp, and Jinshuiwan m around the normal school time. temporary Community by He construction site. construction site River (not delivered Earth excavation, access road for use), onsite storage, Jigongzhou, backfilling, people Songmuji and vehicle moving, Community of and leakage and Gonghe Village, spill of earth Longjiangdu, transportation Hezhou vehicles will have College, Sanjia impact on sensitive Village, Fanglin receptors within 50 Street, Hezhou m around Municipality Pilot construction site. Middle School, Construction solid Fanglin Village, waste generated Loacengwu, from demolition of residential buildings buildings acquired of Wenyuanhuadu and waste soil/stone Community by He from construction of River, residents in new No.2 Xinan Alley of buildings/structures Babu Street, Xiyue will have Street residents, environmental Xialiang Village, impact, if not well Diandengzhai, managed. Chushuitang, Xiadao Primary School, Xiadao Village, Jichitan Soil erosion area of ① He River Rehabilitation (Huangshi Land area 2 166.09 hm and soil Hydropower Station to Guangming permanently and Hezhou Water loss of 24,350 tons Bridge) temporarily 15.6 Contractor Resources caused by Reusable surface soil in disturbed area occupied by the Bureau construction should be removed and stored in Project activities designated area before construction. - 328 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 3 3 227900m surface soil, 227900m surface soil backfill, and construction of 15123 m long bio-swale (included in technical design). 2 Greening measures: 330031 m embankment slope covered with grass, 2 30246 m planting of trees, bush and 2 grass, and 60 m vertical greening (included in technical design).Temporary measures: temporary covering by 2 10,000m dense-mesh net (new). ② He River Rehabilitation (Guangming Bridge to Lingfeng Bridge) Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 31300 3 3 m surface soil, 31300 m surface soil backfill, and construction of 450 m long 2 bio-swale, 3795m for permeable bricks (included in technical design). 2 Greening measures: 31924 m embankment slope covered with grass, 2 750 m planting of trees, bush and 2 grass, 944m vertical landscaping, 2 1145m key area landscaping, 2 137998m landscaping (included in - 329 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 technical design).Temporary measures: 2 temporary covering by 1,000 m dense-mesh net (new). ③ He River Rehabilitation (Lingfeng Bridge to Xiadao Hydropower Station) Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 35,100 3 3 m surface soil, 35,100 m surface soil backfill, and construction of 3040 m long ecological swale (included in technical 2 design).Greening measures: 209926 m embankment slope covered with grass, 2 3,040 m planting of trees, bush and 2 grass, 64441m landscaping (included in technical design).Temporary measures: 2 temporary covering by 7,000 m dense-mesh net (new). Without good management, 1. Construction should be scheduled in construction dry season as much as possible. material such as 2. Construction area should be asphalt, fuel, minimized and construction period Watercourse chemicals and He River water should be shortened. Hezhou widening, and domestic sewage of 10 Contractor quality 3. Vegetation should be restored as Municipal EPB dike construction construction early as possible to minimize impact. workers may enter 4. ECOP for dike construction, included surface water and as Annex 1 of the ESMP should be cause water followed. environment pollution. Watercourse Ancient buildings in There are no Physical and cultural resources Hezhou Culture 10 Contractor widening, civil Xiyue Street protected ancient management plan as included in Annex and Press and - 330 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 work construction, Historical and buildings or relics 4 of the ESMP should be strictly Publications construction Cultural Quarter, within construction followed by construction activities. Bureau material and The Old Site of CCP area, but soil/stone Babu Special uncontrolled transportation Branch within construction Xiadao Primary activities may lead School to damage to ancient buildings and the relics and pollution, and the damage may be irremediable. 6. Construction scope should be minimized and construction period should be shortened as possible; 7. It is prohibited to chop down the Ancient and rare trees, transplant without being trees are not within permitted, peel the bark, dig out the construction area of root and inject toxic and harmful the Project, but quite substance to the trees; near the 8. It is not allowed within 5 meters construction site, outside crown shadow of the trees approximately 50 m 4 banyan in Xialiang for construction of buildings or civil work away from the site. Community, 2 structures, laying of pipelines, construction, Normal growth of hackberries, 1 laying of power cables, pit Hezhou Urban construction these trees will banyan and 1 excavation and earth taking, sand / Contractor Administration material and possibly be affected Cinnamomun and stone taking, inundation or Bureau soil/stone by earth taking and camphor in Mid paving ground surface, fume transportation disposal, storage of Jiangbei Road emission, wastewater discharge construction solid and solid waste dumping, storage waste, moving of or dumping of flammable and construction combustible or toxic and harmful vehicles and substances; transportation of 9. It is not allowed for carving, nailing, construction winding, hanging on the trees or equipment. piling material against the tree trunk; and 10. Entry of construction vehicles and equipment is not allowed within 5 - 331 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 meters outside crown shadow of the trees. 7. For construction activities that will affect public traffic, construction program should be provided to public traffic authority in advance for arrangements for adjusting public traffic route, and construction cannot commence until permission is obtained. 8. Signs should be set on construction site before construction indicating construction description and schedule, requesting public Occupation of understanding of inconvenience school access road caused by construction activities, Road occupation will cause access and disclosing contact information by construction Hezhou College, difficulties of and complaint hotline. This Hezhou activity, Hezhou Municipality students, school information could be disclosed in Transport construction Pilot Middle School, staff and parents advance through media, micro-blog 2 Contractor Bureau, Hezhou material and and Xiadao Primary and may affect and wechat, as possible. Traffic Police soil/stone School access safety of the 9. Excavation and backfilling should Group transportation students and disturb be done by zone. normal school 10. Temporary access path should be activities. built when construction site is near public facilities like bus stop. Material transportation should be scheduled to avoid peak hours to reduce peak traffic volume. 11. Traffic diversion and adjustment should be done by traffic police in peak school hours and temporary traffic lights and other signs should be set. 12. Training on construction management and environmental protection should be strengthened. Civil work Water supply Interruption of 4. The contractor should further Hezhou Housing / Contractor construction, and pipeline located 23 existing coordinate with municipal and and Urban and - 332 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 watercourse m upstream from underground urban development authorities Rural widening Sanjia Bridge pipelines due to during construction for collection of Development poor construction underground pipeline information Bureau management including pipeline type, alignment and depth, and establish pipeline coordination team. Prior approval should be obtained from municipal and urban development authorities for excavation interfering with underground pipelines. 5. Construction plan and emergency responsive program should be developed based on pipeline alignment and depth to avoid interference with existing underground pipelines as much as possible. 6. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities, and emergency responsive program should be in place. 2 borrow areas ① Temporary Construction Path located at 1.25 km Surface soil should be removed and be east to Xiadao stored in temporary storage site in The Soil erosion area of Bridge in eastern 2 main watercourse of He River 87.72 hm and soil Hezhou Municipality rehabilitation zone, and temporary loss of 100058 tons and west to Hezhou drainage and sedimentation structures caused by earth Earth borrow, and Municipality should be built along both sides of the Hezhou Water borrow and disposal waste soil electronic road. The site should be restored in late 1491.16 Contractor Resources for temporary land disposal technology construction stage. Bureau use, construction ecological industrial Structural measures: removal of 41600 access road, 3 3 park; the disposal m surface soil, 41600 m surface soil construction camp, 2 site located in backfill and 20.82 hm land restoration etc. construction solid (new). 2 waste landfill in Greening measures: 5.12 hm forest 2 Huangtian Town restoration and 7.04 hm grass land - 333 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 Gonghe Village of restoration (new). Hezhou Municipality Temporary measures: 138660 m temporary earth drainage canal, and 139 temporary sedimentation tanks (new). ② Construction Site and Camp Surface soil should be removed and be stored in designated storage site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary material storage site should be covered during construction. The site should be restored in late construction stage. Structural measures: removal of 9,000 3 3 m surface soil, 9,000 m surface soil 2 backfill and 4.50 hm land restoration (new). 2 Greening measures: 0.11 hm garden 2 plot restoration and 2.71 hm grass land restoration (new). Temporary measures: 4,685 m temporary earth drainage canal, and 26 temporary sedimentation tanks, and 2 7,700 m dense-mesh net (new). ③ Temporary Soil Storage Site Straw bag stuffed with soil will be put surrounding the site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during construction. The site should be restored in late construction stage. 2 Structural measures: 18.05 hm land restoration (new). 2 Greening measures: 4.31 hm forest 2 land restoration, 1.38hm garden 2 restoration and 2.22 hm grass land - 334 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 restoration (new). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m temporary earth drainage canal, and 53 temporary 2 sedimentation tanks, and 206250 m dense-mesh net (new). ④ Borrow Area Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting. Structural measures: removal of 11,080 3 3 m surface soil, 11,080 m surface soil 2 backfill, 36.95 hm land restoration, 3,800 m long brick drainage canal, and 15 brick sedimentation tanks (new). 2 Greening measures: 36.95 hm grass planting, planting of 46,187 pines and 92,375 bushes (new). Temporary measures: 1,000 m retaining wall for temporary storage site and - 335 - Table 11-4 Environment Impacts and Mitigation Measures of Main Watercourse Widening Subcomponent Cost Environmental Implemented Subcomponent Period Activity Potential Impact Mitigation/Prevention Measures CNY Supervised By Sensitive Receptor By 10,000 2 36,000 m dense-mesh net (new). ⑤ Disposal Site Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should built around the site. The disposal site should be restored in late construction stage through surface soil backfill and vegetation replanting. Structural measures: removal of 22,200 3 3 m surface soil, 22,200 m surface soil 2 backfill, 7.4 hm land restoration, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick sedimentation tanks (new). 2 Greening measures: 7.4 hm grass planting, planting of 9,250 pines and 18,500 bushes (new). Temporary measures: installation of 2 2,000 m dense-mesh net (new). ⑥Mud transfer tank: Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork excavation and backfill; 3 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches. - 336 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 Noise of exactor, bulldozer, loader, vibrator and dump truck during construction will have certain impact on sensitive receptors within 30 m. Dust from earth exaction, onsite storage and backfilling, moving of construction workers and vehicles, and ECOP for small waterworks as leakage and spill of included in Annex 2 of the Hezhou Xianghuadao 1 Contractor transportation vehicles will ESMP should be followed. Municipal EPB Watercourse have impact on sensitive widening, civil receptors within 50 m of the work construction site. construction, Demolition of buildings Water Diversion construction acquired and construction of (A-4 East Trunk material and new buildings/structures will Canal Construction earth generate construction solid Rehabilitation transportation, waste and waste soil, which and Connection construction will have environmental impact with Mawei River) camp, without proper management. temporary Reusable surface soil in construction disturbed area should be path removed and stored in designated area before construction. Cut slope and Land area surface with vegetation being Soil erosion area and soil loss permanently and removed should be covered Hezhou Water caused by construction of the temporarily 2 with dense-mesh net for 18 Contractor Resources Project will be 26.10 hm and occupied by the protection during construction Bureau 2,368 tons, respectively. Project and restored through soil covering and greening in later stage. East Trunk Canal Rehabilitation Structural measures: removal of 3 20,100 m surface soil, 20,100 - 337 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 3 m surface soil backfill, 12300 permeable bricks (included in technical design). 2 Greening measures: 62424m 2 turfing, 16343m greenbelt, 2 99492m landscaping (included in technical design). Temporary measures: 2 temporary covering by 5,000 m dense-mesh net (new). Flood Diversion Canal of East Trunk Canal Structural measures: removal of 3 3 5,500 m surface soil, 5,500 m surface soil backfill, 5386m 2 ecological swale, 5386m permeable bricks (included in technical design). 2 Greening measures: 24267 m three-dimensional geo-technical net embankment 2 slope with grass, 5386 m 2 greening belt, 4200 m landscaping and greening (included in technical design). Temporary measures: 2 temporary covering by 3,000 m dense-mesh net (new). 1. Information of construction Dredging will have temporary schedule, environmental Operation of Water quality of disturbance to water body, impact and sediment dredging East Trunk Canal, cause increase of suspended transportation route should equipment area along solids, and possibly have odor Hezhou be disclosed to the public 2 Contractor and sediment emission. Without strict Municipal EPB in a timely manner. dewatering transportation management, transportation 2. Dredging should be facility route process may have secondary scheduled in dry season as pollution. possible and construction - 338 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 period should be shorted to minimize disturbance to water body. 3. Mechanical excavation supplemented by manual excavation is adopted for East Trunk Canal, and movable vehicular dewatering equipment is used for onsite dewatering. Dredging effluent is discharged to the canal. Interception and diversion + dry dredging method may be used for dredging provided that the construction condition permits (with the required operation space available for inner river interception and diversion) and a sound regional intercepting pipeline network is in place. 4. Sediment is dewatered to sludge cake with moisture content less than 50%, and is hauled through enclosed vehicle to Hezhou solid waste landfill for disposal. 5. Strict equipment inspection should be done during dredging to prevent oil leakage. Wastewater and solid waste should be collected with other construction waste, and is - 339 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 not allowed to enter surface water. 1. Construction should be scheduled in dry season as possible. 2. Construction area should Without appropriate be minimized as possible management, construction and construction period material (asphalt, oil, should be shortened. Watercourse Water quality of chemicals), oily construction 3. Vegetation should be Hezhou widening, dike East Trunk Canal wastewater and domestic 1 Contractor restored as early as Municipal EPB construction and Mawei River sewage of construction possible to minimize workers may enter surface impact on local water and cause water environment. pollution. 4. ECOP for small waterworks as included in Annex 2 of the ESMP should be followed. ① Temporary Construction Path Two borrow areas Surface soil should be removed located 1.25 km and be stored in temporary east to Xiadao storage site in The main Bridge in eastern watercourse of He River Hezhou and west Soil erosion area and soil loss rehabilitation zone, and to Hezhou caused by earth borrow and temporary drainage and Municipality disposal for temporary land sedimentation structures should Hezhou Water Earth borrow electronic use, construction access road be built along both sides of the 1491.16 Contractor Resources and disposal technology and construction camps will be road. The site should be Bureau ecological 2 87.72 hm and 100058 tons, restored in late construction industrial park; respectively. stage. disposal site Structural measures: removal of located in 3 41600 m surface soil, 41600 construction solid 3 m surface soil backfill and waste landfill in 2 120.82 hm land restoration Gonghe village. (new). 2 Greening measures: 5.12 hm - 340 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 2 forest restoration and 7.04 hm grass land restoration (new). Temporary measures: 138660 m temporary earth drainage canal, and 139 temporary sedimentation tanks (new). ② Construction Site and Camp Surface soil should be removed and be stored in designated storage site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary material storage site should be covered during construction. The site should be restored in late construction stage. Structural measures: removal of 3 3 9,000 m surface soil, 9,000 m surface soil backfill and 4.50 2 hm land restoration (new). 2 Greening measures: 0.11 hm garden plot restoration and 2.71 2 hm grass land restoration (new). Temporary measures: 4,685 m temporary earth drainage canal, and 26 temporary sedimentation tanks, and 7,700 2 m dense-mesh net (new). ③ Temporary Soil Storage Site Straw bag stuffed with soil will be put surrounding the site, and temporary drainage and - 341 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during construction. The site should be restored in late construction stage. 2 Structural measures: 18.05 hm land restoration (new). 2 Greening measures: 4.31 hm forest land restoration, 1.38hm2 garden restoration and 2.22 2 hm grass land restoration (new). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m temporary earth drainage canal, and 53 temporary sedimentation tanks, and 2 206250 m dense-mesh net (new). ④ Borrow Area Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done - 342 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting. Structural measures: removal of 3 11,080 m surface soil, 11,080 3 m surface soil backfill, 36.95 2 hm land restoration, 3,800 m long brick drainage canal, and 15 brick sedimentation tanks (new). 2 Greening measures: 36.95 hm grass planting, planting of 46,187 pines and 92,375 bushes (new). Temporary measures: 1,000 m retaining wall for temporary 2 storage site and 36,000 m dense-mesh net (new). ⑤ Disposal Site Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures - 343 - Table 11-5 Environmental Impacts and Mitigation Measures of Water Diversion Subcomponent Environmental Cost Mitigation/Prevention Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact CNY Measures By By Receptor 10,000 and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should built around the site. The disposal site should be restored in late construction stage through surface soil backfill and vegetation replanting. Structural measures: removal of 3 22,200 m surface soil, 22,200 3 2 m surface soil backfill, 7.4 hm land restoration, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick sedimentation tanks (new). 2 Greening measures: 7.4 hm grass planting, planting of 9,250 pines and 18,500 bushes (new). Temporary measures: 2 installation of 2,000 m dense-mesh net (new). ⑥ Mud transfer tank: Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork 3 excavation and backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches. - 344 - - 345 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 Operation noise of exactor, bulldozer, loader, vibrator and dump truck during construction will have certain impact on sensitive receptors within 30 m. Dust from earth exaction, onsite storage and backfilling, moving of construction workers and vehicles, and Water-related leakage and spill of Hezhou Waterworks ECOP for small waterworks as included in construction, Jichitan transportation vehicles 1 Contractor Municipal Improvement: Annex 2 of the ESMP should be followed. transportation will have impact on EPB A-5 Xiadao of sensitive receptors Hydropower construction within 50 m of the Station Upgrade; material and construction site. A-6 Fanglin Construction earth, Demolition of buildings Hydropower construction acquired and Station Upgrade; camp, and construction of new A-7 Huangshi temporary buildings/structures will Hydropower construction generate construction Station Upgrade path solid waste and waste soil, which will have environmental impact without proper management. Without appropriate 1. Construction should be scheduled in management, dry season as possible. construction material 2. Construction area should be minimized (asphalt, oil, as possible and construction period Hezhou Water quality of chemicals) , oily should be shortened. 1 Contractor Municipal He River construction wastewater 3. Vegetation should be restored as early EPB and domestic sewage of as possible to minimize impact on local construction workers environment. may enter surface water 4. ECOP for dike construction as included - 346 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 and cause water in Annex 1 of the ESMP should be pollution. followed. 1. For construction activities that will affect public traffic, construction program should be provided to public traffic authority in advance for arrangements for adjusting public traffic route, and construction cannot commence until permission is obtained. 2. Signs should be set on construction site before construction indicating construction description and schedule, requesting public understanding of inconvenience caused by construction activities, and disclosing contact information and complaint hotline. This Removal of information could be disclosed in Huangshi Hezhou advance through media, micro-blog and Hydropower Residents of Transport Traffic interruption and wechat, as possible. Station and Fanglin Street Bureau, travel inconvenience 3. Excavation and backfilling should be 1 Contractor Fanglin and Tianchang Hezhou during construction done by zone. Hydropower Village Traffic Police 4. Temporary access path should be built Station gate Group when construction site is near public dams. facilities like bus stop. Material transportation should be scheduled to avoid peak hours to reduce peak traffic volume. Separate construction access road should be built for construction in rural area to avoid use of rural road and damage of rural road by oversize equipment and vehicle. 5. Training on construction management and environmental protection should be strengthened. 6. During construction of Fanglin Hydropower Station improvement, travel from Fanglin Street and - 347 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 Tianchang Village to area north to He River will be re-routed along Fanglin Road, G207 and Sanjia Bridge or through Mintian rural road and Bahuang Class 2 road. Traffic re-routing plan is subject to approval of traffic police and road closing and re-routing signs will be posted. Fanglin Hydropower Station has irrigation 400 mu dry and function. Relying on paddy field in A small-sized pump station will be built. high water level Removal of Tianchang River water will be lifted by three pumps with contributed by barrage, Hezhou Fanglin Village, 200 mu designed delivery head of 30 m and river water can flow to Water Hydropower farmland in distance of 800 m and diverted to irrigated 400 Contractor irrigation channels Resources Station river Mintian Village area in Tianchang, Fanglin and Mintian through diversion Bureau flashboard and 1,000 mu villages through existing water diversion culverts by gravity. As farmland in culverts and channels. flashboard is removed, Fanglin Village existing irrigated area will be affected. Two borrow ① Temporary Construction Path areas located Surface soil should be removed and be 1.25 km east to stored in temporary storage site in The main Xiadao Bridge in watercourse of He River rehabilitation zone, eastern Hezhou and temporary drainage and sedimentation Soil erosion area and and west to structures should be built along both sides soil loss caused by earth Hezhou of the road. The site should be restored in borrow and disposal for Municipality late construction stage. Hezhou temporary land use, 3 Earth borrow electronic Structural measures: removal of 41600 m Water construction access 3 1491.16 Contractor and disposal technology surface soil, 41600 m surface soil backfill Resources roads and construction 2 ecological 2 and 20.82 hm land restoration (new). Bureau camps will be 87.82 hm 2 industrial park; Greening measures: 5.12 hm forest and 10058 tons, 2 disposal site restoration and 7.04 hm grass land respectively. located in restoration (new). construction Temporary measures: 138660 m temporary solid waste earth drainage canal, and 139 temporary landfill in sedimentation tanks (new). Gonghe village. ② Construction Site and Camp - 348 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 Surface soil should be removed and be stored in designated storage site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary material storage site should be covered during construction. The site should be restored in late construction stage. 3 Structural measures: removal of 9,000 m 3 surface soil, 9,000 m surface soil backfill 2 and 4.50 hm land restoration (new). 2 Greening measures: 0.11 hm garden plot 2 restoration and 2.71 hm grass land restoration (new). Temporary measures: 4,685 m temporary earth drainage canal, and 26 temporary 2 sedimentation tanks, and 7,700 m dense-mesh net (new). ③ Temporary Soil Storage Site Straw bag stuffed with soil will be put surrounding the site, and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during construction. The site should be restored in late construction stage. 2 Structural measures: 18.05 hm land restoration (new). 2 Greening measures: 4.31 hm forest land restoration, 1.38hm2 garden restoration and 2 2.22 hm grass land restoration (new). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m temporary earth drainage canal, and 47 temporary 2 sedimentation tanks, and 206250 m dense-mesh net (new). - 349 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 ④ Borrow Area Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting. 3 Structural measures: removal of 11,080 m 3 surface soil, 11,080 m surface soil backfill, 2 36.95 hm land restoration, 3,800 m long brick drainage canal, and 15 brick sedimentation tanks (new). 2 Greening measures: 36.95 hm grass planting, planting of 46,187 pines and 92,375 bushes (new). Temporary measures: 1,000 m retaining wall 2 for temporary storage site and 36,000 m dense-mesh net (new). ⑤ Disposal Site Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage - 350 - Table 11-6 Environmental Impacts and Mitigation Measures of Waterworks Improvement Environmental Cost Implemented Supervised Subcomponent Period Activity Sensitive Potential Impact Mitigation/Prevention Measures CNY By By Receptor 10,000 site before construction. Retaining wall, masonry drainage canal and various drainage structures should built around the site. The disposal site should be restored in late construction stage through surface soil backfill and vegetation replanting. 3 Structural measures: removal of 22,200 m 3 surface soil, 22,200 m surface soil backfill, 2 7.4 hm land restoration, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick sedimentation tanks (new). 2 Greening measures: 7.4 hm grass planting, planting of 9,250 pines and 18,500 bushes (new). Temporary measures: installation of 2,000 2 m dense-mesh net (new). ⑥ Mud transfer tank: Temporary measures: 21 mud transfer tanks 3 to be provided; 11193m for earthwork 3 excavation and backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches. Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) River Hezhou Institute, Odor 1. With heavy load of Design Schematic dredging Hezhou generated in dredging, wide water surface / FS unit stage design (A-8 He Experimental dredging and a certain water depth, - 351 - Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) River Middle School, process, odor He River has the conditions Dredging areas along and leachate required for operation of Subproject sludge generated large dredgers. In the (Huangshi transportation from optimized design proposal, Hydropower route temporary cutter suction dredger known Station – sludge for its high dredging Xiadao storage, tail efficiency is selected to Hydropower water significantly shorten the Station) generated construction period, reduce from sludge disturbances to water dewatering systems and correspondingly and impacts reduce the time of impacts of from sludge the sludge dewatering sites. transportation 2. As the optimum choice, No. route, etc. 1 dewatering site (river shores on the right bank of He River approximately 100m upstream from Lingfeng Bridge) and No. 2 dewatering site (river shore on the left bank of He River approximately 100m upstream from Fanglin Bridge) are selected, both located more than 100m away from the closest sensitive spot, helpful to avoid impacts on the environmentally sensitive sites from temporary storage and dewatering of sludge. 3. Optimization of sludge transportation routes: The - 352 - Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) transportation route from No. 1 sludge dewatering site to the solid waste landfill is from Lingfengnan Road to National Highway 207, Gongye Avenue, National Highway 323 and then the access road to the solid waste landfill, involving a haulage of approximately 14km; The transportation route from No. 2 sludge dewatering site to the solid waste landfill is from Fanglin Road to Guangming Avenue, National Highway 207, Gongye Avenue, National Highway 323 and then the access road to the solid waste landfill, involving a haulage of approximately 18km. Such a selection of the sludge transportation routes has considered the need for avoiding densely populated residential areas, shortening haulage to the best possibility and reducing the environmental impacts. Operation Hezhou Institute, The dredging 1. Information on the Construction Construction Municipal of Hezhou process will construction plan, the 5 stage contractor EPB dredging Experimental generate environmental impact - 353 - Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) vessel, Middle School, temporary descriptions, dredger operation water quality of disturbances operation route and sludge of He River to water transportation route should be integrated systems and disclosed in time to the public. sludge result in 2. The dredging operation treatment increased SS should be conducted in the facility, concentration low-water season and the sludge and possibly construction time should be dewatering fugitive odor in shortened, if possible, to and onsite a small reduce disturbances to water dewatering amount. systems. Improper 3. Cutter suction dredger is management selected for the dredging of sludge operation of the main dewatering or watercourse of He River and transportation the sludge is delivered to process may dewatering facilities on No. 1 cause and No. 2 dewatering sites secondary along He River and dewatered pollution. into sludge cakes with a moisture content of less than 50%, which are then transported in enclosed vehicles to Hezhou Municipal Domestic Solid Waste Landfill for disposal. 4. Construction plants and vessels involved in the dredging process must be subject to strict inspection to prevent oil leakage. Sewage, - 354 - Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) solid wastes and oily wastewater from vessel cabins must not be cast into the water systems and should, instead, be collected and treated together with the other construction wastes. 5. Flood interception ditches should be excavated around the temporary sludge storage tanks on the dewatering site and connected to the wastewater sedimentation tanks. 6. Stormwater, tail water from sludge dewatering collected by the flood interception ditches should be discharged into the wastewater sedimentation tank for sedimentation before finally discharged into He River. 7. The sludge should be dewatered and transported out of site in a timely manner to avoid the generation of leachate due to excessive storage. 8. Quick lime and deodorants should be provided for sterilization and deodorization - 355 - Table 11-7 Environmental impacts of He River Dredging Subproject and their mitigation measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) of the dewatering site and labor protection devices such as masks should be provided to the construction workers. Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 1. The optimized design takes account of the Water Xiyue Street Flood risks for preservation of the historical conservancy Historical and the Xiyue Street and cultural relics of Xiyue infrastructure Cultural Quarter, Historical and Street and aims to assure construction residential Cultural that the cultural relics (B-1 buildings on Quarter, noise protection zone is not Huangansi Xiyue Street, impacts from Design Schematic flooded and not relocated, Drainage residential the operation of / FS unit / stage design land use difficulty is Canal Pump buildings and pump stations addressed through capacity Station, B-2 staff dormitory of along minimization of drainage Shizigang Transportation Huangansi pump stations and selection Drainage Bureau on Drainage Canal of existing watercourses Canal Pump Jiangbeizhong and Shizigang needing no widening and full Station) Road Drainage Canal diversion of regional flood via Shizigang Drainage - 356 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Canal. 2. In order to reduce the impacts of noises generated in the operation of the drainage pump stations, well-designed and low-noise mechanical equipment is selected and vibration insulation and control measures are adopted where possible during installation and operation to reduce noise; the robust structure and evenly grouted bases of the pump equipment can absorb vibrations and provide a solid support to the base plate. Through reasonable arrangement of sound absorbing materials and vibration reduction devices, e.g. asbestos boards and shock absorbers, on the inner walls, ceilings, floors and beside the equipment in the pump station helps to effectively control and eliminate spread and reflection of noises. Construction Civil works Residential Noises Requirements included in 5 Construction Municipal - 357 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) stage construction, buildings on generated in the ESMP Annex 2: World Bank contractor EPB construction Xiyue Street, operation of Loan Guangxi Hezhou material and residential excavators, bull Urban Water Infrastructure earth and buildings and dozers, dump and Environment aggregate staff dormitory of trucks and other Improvement Project ECOP transportation, Transportation construction for Small Waterworks construction Bureau on plants used in Construction Component will camps, Jiangbeizhong the construction be implemented. access roads Road stage will generate certain impacts on sensitive sites within a distance of 30m in the neighborhood. Dust generated in earthwork excavation, stockpiling, backfill, pedestrian and motor vehicle movement, spillage from earthwork transportation vehicles in the construction stage will generate - 358 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) certain impacts on sensitive sites within a distance of 50m in the neighborhood. Poor management of construction wastes and debris, waste soil generated in the demolition of acquired buildings and construction of new buildings will cause impacts on the environment. (1) Huangansi Drainage Pump Station Construction Cut slope and ground with activities will Right of way and vegetation being removed result in temporary land should be covered with Construction Municipal additional soil 24.95 use for the dense-mesh net during contractor WRB erosion of Project construction, and 0.37hm2 and temporary drainage canals 20t. and structures should be built on construction site. - 359 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Structural measures: 20 m long stormwater pipelines (already included in the technical design) Temporary measures: 42 m long temporary earth drainage canal, 2 temporary sedimentation tanks, and temporary covering of dense-mesh net of 100 m2 (newly included in the technical design)。 (2) Shizigang Drainage Pump Station Cut slope and ground with vegetation being removed should be covered with dense-mesh net during construction, and temporary drainage canals and structures should be built on construction site. Structural measures: 150 m long stormwater pipelines (already included in the technical design) Temporary measures: 150 m long temporary earth drainage canal, 2 temporary sedimentation - 360 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) tanks, and temporary covering of dense-mesh net of 500 m2 (newly included in the technical design)。 No preserved ancient buildings are distributed in the construction area. However, poor The construction activities construction Construction will be carried out in strict management of civil works, accordance with the and uncivilized transportation Ancient buildings requirements included in construction of in the Xiyue ESMP Annex 4: World Bank behaviors may Construction Municipal construction Street Historical Financed Guangxi Hezhou 2 lead to contractor CPPRFTB materials and and Cultural Urban Water Infrastructure irrevocable earth and Quarter and Environment consequences stone Improvement Project such as materials Management Plan of damage, Physical Cultural Resources. contamination and even destruction of the preserved ancient buildings and sites. Construction 2 camphor trees No famous or 1. Construction scope / Construction Municipal - 361 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) of civil works, and 1 banyan ancient trees should be narrowed contractor MEB transportation tree at Xinaner are found in the and construction period of Street, 1 project should be shortened as construction camphor tree at implementation much as possible; materials and Xiyue Street area, but 2. Tree felling, unlicensed earth and temporary transplanting, bark stone borrow and peeling, root digging materials dump of soil, and injection of toxic stockpiling of and hazardous construction substances to trees wastes and movement of should be prohibited; construction 3. It is not allowed to vehicles and construct buildings or plants on the structures, lay construction pipelines, install power sites may affect cables, excavate the normal borrow areas, mine growth of such sand and stone, flood trees in the or seal the ground, emit vicinity with a fumes, discharge distance of less wastewater and dump than 50m. solid wastes, stockpile or dump flammables, explosives or toxic and hazardous substances in the area with a distance of less than 5m from the outer edge of the crown shadow of - 362 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) trees. 4. It is not allowed to engrave, nail, wind, hang or support or stack articles on or around tree trunks; and 5. Construction vehicles and plants are not permitted to enter or roll the area with a distance of less than 5m from the outer edge of the crown shadow of trees. 1. The contractor should further coordinate with municipal and urban Pipelines at the development intersection authorities during Poor between construction for construction Excavations Shizigang management collection of during civil Drainage Canal Construction Municipal may lead to underground pipeline / works and the contractor HURB interruption of information including construction Transportation underground pipeline type, Bureau on pipelines. alignment and depth, Jiangbeizhong Road and establish a pipeline coordination team. Prior approval should be obtained - 363 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) from municipal and urban development authorities for excavation interfering with underground pipelines. 2. Construction plan and emergency response plan should be developed based on pipeline alignment and depth to avoid interference with existing underground pipelines as much as possible. 3. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities to be prepared for emergency responses. Borrow fill and Borrow area Borrow fill and (1) Construction access Construction Municipal 1491.16 waste oil located 1.25km waste soil for roads contractor WRB - 364 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) east of Xiadao temprary land Prior to construction, top soil Bridge in the use, in the right of way will be eastern part of construction removed and stockpiled on a Hezhou access road temporary stockpiling site in Municipality, and the construction area of the borrow area construction main stream rehabilitation located at camps will works of He River. In the Hezhou result in soil meanwhile, temporary Electronic erosion in a drainage and sedimentation Technology total area of measures will be taken on Ecological 87.72hm2 and both sides of the road and Industry Park an additional land rehabilitation and and the soil erosion of cut-over land restoration will construction 100058t. be conducted in the late waste disposal stage of the Project. site located at Structural measures: top soil Gonghe Village, removal in a total volume of Huangtian of 41600m3, top soil backfill in a Hezhou total volume of 41600 m3 Municipality and land rehabilitation in a total area of 20.82hm2 (newly included in the technical design); Greening measures: 5.12hm2 for forest land restoration, 7.04hm2 for grassland restoration (newly included in the technical design); Temporary measures: 138660m for temporary - 365 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) earth drainage gutter; 139 temporary sedimentation tanks (newly included in the technical design). (2) Construction production and domestic activity areas Prior to construction, top soil in the right of way will be removed and stockpiled on a temporary stockpiling site in the construction area of the main stream rehabilitation works of He River. In the meanwhile, temporary drainage and sedimentation measures will be taken on both sides of the road and land rehabilitation and cut-over land restoration will be conducted in the late stage of the Project. Structural measures: top soil removal in a total volume of 9000m3, top soil backfill in a total volume of 9000 m3 and land rehabilitation in a total area of 4.50hm2 (newly included in the technical design); Greening measures: - 366 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 0.11hm2 for garden land restoration, 2.71hm2 for grassland restoration (newly included in the technical design); Temporary measures: 4685m for temporary earth drainage gutter; 26 temporary sedimentation tanks; 7700m2 for dense-mesh net (newly included in the technical design). (3) Temporary soil storage site Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored through land rehabilitation and cut-over land restoration at the end of the construction stage. Structural measures: 18.05 hm2 land rehabilitation (newly included in the technical design). - 367 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Greening measures: 4.31 hm2 forest land restoration, 1.38hm2 for garden restoration and 2.22 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m long temporary earth drainage canal, and 53 temporary sedimentation tanks, and 206250 m2 dense-mesh net (newly included in the technical design). ① Borrow sites Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site - 368 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting Structural measures: 11,080 m3 for surface soil removal, 11,080 m3 for surface soil backfill, 36.95 hm2 for land rehabilitation, 3,800 m long brick masonry drainage canal, and 15 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 36.95 - 369 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) hm2 for grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m long retaining wall for temporary storage site and 36,000 m2 dense-mesh net (newly included in the technical design). (4) Waste disposal sites Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should be built around the site. The disposal site should be restored at the end of the - 370 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 bushes (newly included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly included in the technical design). ⑥ Mud transfer tank: Temporary measures: 21 mud transfer tanks to be provided; 3 11193m for earthwork excavation 3 and backfill; 861m for fencing - 371 - Table 11-8 Environmental Impacts of the Water Conservancy Infrastructure Construction Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and demolition of earth-filled woven bags; 495m for temporary drainage ditches. Maintenance and servicing Noise impacts of water pumps should be Residences on from operation strengthened by means of Xiyue Street and of drainage periodical inspection of Operation of Jiangbeizhong Operation pump station of electric motor and pump axle Municipal drainage Road and staff 1 Operator stage Huangansi concentricity and assuring EPB pump station dormitory of Drainage Canal excellent lubrication of axles Transportation and Shizigang so as to reduce wearing of Bureau Drainage Canal pump parts and reduce noise. - 372 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Noises generated in Requirements included the operation in ESMP Annex 2: of excavators, World Bank Loan bull dozers, River-lake Guangxi Hezhou Urban dump trucks connection Pingjing, Water Infrastructure and other (B-3 Lining Lijiatang, Lining and Environment construction River Village, Improvement Project plants used in Rehabilitation, Daninggang, ECOP for Small Watercourse the B-4 Xiangjiayuan, Waterworks widening, Civil construction Changlong Taipingzhai, Construction works stage will River Yingshi Primary Component will be construction, generate Rehabilitation, School, implemented. construction certain impacts B-5 Huangtian Huangtian Town, Temporary sound Construction material and on sensitive Construction Municipal Branch Canal Pinggui No. 3 barriers with a height of 25 stage earth and sites within a contractor EPB Rehabilitation, Middle School, no less than 2m and aggregate distance of B-6 Douhang, high effectiveness of transportation, 30m in the Guposhan Bantanggang, noise reduction should construction neighborhood. Drainage Xinzhai, be provided for camps, Dust Canal Huangtian construction sites access roads generated in Rehabilitation, Village, around Yingshi Primary earthwork B-7 East No. Muyuanna, School and Pinggui No. excavation, 5 Branch Baijiazhai, 3 Middle School and stockpiling, Canal Shizigang the construction backfill, Rehabilitation) activities should be pedestrian and scheduled in such a motor vehicle way that the teaching movement, periods are avoided. spillage from earthwork - 373 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) transportation vehicles in the construction stage will generate certain impacts on sensitive sites within a distance of 50m in the neighborhood. Poor management of construction wastes and debris, waste soil generated in the demolition of acquired buildings and construction of new buildings will cause impacts on the environment. Construction (1) Lining River Right of way and activities will Rehabilitation temporary land Construction Municipal result in 60 use for the Reusable surface soil contractor WRB additional soil Project erosion of in disturbed area - 374 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 67.73hm2 and should be removed and 6040t. stored in designated area before construction. Cut slope and surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 28,600 m3 surface soil, 28,600 m3 surface soil backfill (already included in the technical design). Greening measures: 56146 m2 three-dimensional - 375 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) geo-technical net embankment slope covered with grass, 9310 m2 greening belt, 35,020 m2 landscaping and greening (already included in the technical design). Temporary measures: temporary covering by 10,000 m2 dense-mesh net (newly included in the technical design). (2) Changlong River Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be - 376 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 22,600 m3 surface soil, 22,600 m3 surface soil backfill, 6306m ecological swale (already included in the technical design). Greening measures: 2 47113m three-dimensional geo-technical net embankment slope covered with grass, 7966 m2 greening belt, 29,630 m2 landscaping and greening (already included in the - 377 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) technical design). Temporary measures: temporary covering by 10,000 m2 dense-mesh net (newly included in the technical design). (3) Dongwu Branch Canal Rehabilitation Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and surface with vegetation removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. - 378 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Structural measures: removal of 45,000 m3 surface soil, 45,000 m3 surface soil backfill, 4270m ecological swale, 18675m2 permeable bricks (already included in the technical design). Greening measures: 113930 m2 bush planting and 7685m2 greening (already included in the technical design). Temporary measures: temporary covering by 15,000 m2 dense-mesh net (newly included in the technical design). (4) Huangtian Branch Canal Rehabilitation Reusable surface soil - 379 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) in disturbed area should be removed and stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Structural measures: removal of 24,400 m3 surface soil, 24,400 m3 surface soil backfill, 18750m2 permeable bricks (already included in the technical design). Greening measures: 2 54260m - 380 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) three-dimensional geo-technical net embankment slope covered with grass and 14880 m2 greenbelt, 45000m2 landscaping (already included in the technical design). Temporary measures: temporary covering by 10,000 m2 dense-mesh net (newly included in the technical design). (5) Guposhan Drainage Canal Rehabilitation Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction. Greening measures: - 381 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 6000 m2 landscaping and greening (already included in the technical design). Temporary measures: temporary covering by 5,000 m2 dense-mesh net (newly included in the technical design). Improper 1. The construction management works should be of construction arranged in the materials such low-water season as asphalt, where possible; Water quality of oils, chemical 2. The scope of the Lining River, substances construction activities Changlong River, and oily should be narrowed Watercourse Huangtian construction and the construction widening, dike Construction Municipal Branch Canal, wastewater, period should be 10 construction, contractor EPB Guposhan domestic shortened as much as etc. Branch Canal sewage of possible. and East No. 5 construction 3. The construction Branch Canal workers may works should be result in their implemented according discharge into to the requirements the surface included in ESMP water and Annex 1: ECOP for the cause pollution Embankment - 382 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) of the water Construction environment. Component of World Bank Financed Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project. 1. Information on the construction plan, the The dredging environmental impact process will descriptions and sludge generate transportation route should temporary be disclosed in time to the disturbances to public. water systems 2. The dredging operation Water systems of and result in Operation of should be conducted in the Huangtian increased SS dredging low-water season and the Branch Canal, concentration plants, construction time should be Guposhan and possibly operation of shortened, if possible, to Construction Municipal Branch Canal fugitive odor in 4 integrated reduce disturbances to contractor EPB and areas along a small sludge water systems. the sludge amount. treatment 3. Dredging for Huangtian transportation Improper facility Branch Canal and routes management Guposhan Branch Canal is of conducted through transportation mechanical dredging process may assisted with artificial cause operation. Dewatering is secondary achieved on site using the pollution. movable vehicle-mounted integrated drying facility - 383 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and the residual water is discharged into Huangtian Branch Canal and Guposhan Branch Canal in the vicinity. Interception and diversion + dry dredging method may be used for dredging provided that the construction condition permits (with the required operation space available for inner river interception and diversion) and a sound regional intercepting pipeline network is in place. 4. The sludge is dewatered into sludge cakes with a moisture content of less than 50%, which are then transported in enclosed vehicles to Hezhou Municipal Domestic Solid Waste Landfill for disposal. 5. Construction plants involved in the dredging process must be subject to strict inspection to prevent oil leakage. Sewage and solid wastes must not be cast into the water systems - 384 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and should, instead, be collected and treated together with the other construction wastes. 1. A construction plan should be submitted to the transportation authority for construction activities with impacts on public School access transit and re-routing of roads are public transit must be occupied, well planned and permit resulting in must be obtained Occupation of travelling before proceeding with local roads by difficulty for Municipal such construction the students, Transportation activities. construction Pinggui No. 3 school faculty Construction Bureau 2. A bulletin board 1 activities, Middle School and parents contractor Municipal should be erected on transportation and possibly Traffic Police the construction site of earth and affecting traffic Brigade before the construction aggregates safety of works commences to students and introduce the project order of school components and teaching. construction time to obtain public understanding of inconveniences generated in the construction process. Contact information - 385 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and complaint hotlines should be also disclosed. If possible, such prior announcement may be achieved via the news media, micro blog, wechat, etc. 3. The construction works should be implemented on a section-by-section or zone-by-zone basis and excavation and backfill should be carried out in the shortest possible time. 4. Temporary access roads should be provided for construction works close to bus stops and other public facilities. Material transportation should be time in such a way that the traffic peak hours are avoided to alleviate pressure on urban traffic. 5. Traffic police guiding and dispatching should - 386 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) be needed during school peak hours and temporary signal lights and other signs should be provided. 6. Stronger efforts should be made in construction management and environmental protection training for construction workers. 1. The contractor Pipelines at the should further intersection of Lining River with coordinate with Zhanqian municipal and Avenue, the urban Poor intersections of construction development Civil works Changlong River management authorities during construction, with Guangming Construction Municipal may lead to / watercourse Avenue and construction for contractor HURDB interruption of widening, etc. Guposhan underground collection of Avenue and the pipelines. underground intersection of East No. 5 pipeline Branch Canal information with National Highway No. 207 including pipeline type, alignment - 387 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and depth, and establish a pipeline coordination team. Prior approval should be obtained from municipal and urban development authorities for excavation interfering with underground pipelines. 2. Construction plan and emergency response plan should be developed based on pipeline alignment and depth to avoid interference with existing underground - 388 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) pipelines as much as possible. 3. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities to be prepared for emergency responses. Requirements included Improper in ESMP Annex 4: LAR involved implementation World Bank Financed Resettlement in Changlong 53 recently of LAR may Guangxi Hezhou Urban Construction external River constructed / affect the Water Infrastructure contractor monitoring Integrated private tombs progress of the and Environment agency Rehabilitation Project. Improvement Project Management Plan of - 389 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Physical Cultural Resources Earthwork and stonework Improper construction construction at the measures and intersections management Nanning Gui-Guang Construction of East Trunk may affect the / Railway Express Railway contractor Canal and foundation Bureau Lining River stability and with safe operation Gui-Guang of railway Express Railway Borrow area Borrow fill and (1) Construction located 1.25km waste soil for access roads east of Xiadao temporary land Prior to construction, Bridge in the use, top soil in the right of eastern part of construction way will be removed Hezhou access road and stockpiled on a Municipality, and temporary stockpiling Borrow fill and borrow area construction site in the construction Construction Municipal 1491.16 waste oil located at camp will result area of the main stream contractor WRB Hezhou in soil erosion rehabilitation works of Electronic in a total area He River. In the Technology of 87.72hm2 meanwhile, temporary Ecological and an drainage and Industry Park additional soil sedimentation and the erosion of measures will be taken construction 100058t. on both sides of the - 390 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) waste disposal road and land site located at rehabilitation and Gonghe Village, cut-over land Huangtian of restoration will be Hezhou conducted in the late Municipality stage of the Project. Structural measures: top soil removal in a total volume of 41600m3, top soil backfill in a total volume of 41600 m3 and land rehabilitation in a total area of 20.82hm2 (newly included in the technical design); Greening measures: 5.12hm2 for forest land restoration, 7.04hm2 for grassland restoration (newly included in the technical design); Temporary measures: 138660m for temporary earth drainage gutter; 139temporary sedimentation tanks (newly included in the technical design). (2) Construction - 391 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) production and domestic activity areas Prior to construction, top soil in the right of way will be removed and stockpiled on a temporary stockpiling site in the construction area of the main stream rehabilitation works of He River. In the meanwhile, temporary drainage and sedimentation measures will be taken on both sides of the road and land rehabilitation and cut-over land restoration will be conducted in the late stage of the Project. Structural measures: top soil removal in a total volume of 9000m3, top soil backfill in a total volume of 9000 m3 and land rehabilitation in a total area of 4.50hm2 (newly included in the - 392 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) technical design); Greening measures: 0.11hm2 for garden land restoration, 2.71hm2 for grassland restoration (newly included in the technical design); Temporary measures: 4685m for temporary earth drainage gutter; 26 temporary sedimentation tanks; 7700m2 for dense-mesh net (newly included in the technical design). (3) Temporary soil storage site Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored through land rehabilitation and - 393 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) cut-over land restoration at the end of the construction stage. Structural measures: 18.05 hm2 land rehabilitation (newly included in the technical design). Greening measures: 4.31 hm2 forest land restoration, 1.38hm2 garden restoration and 2.22 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m long temporary earth drainage canal, and 53 temporary sedimentation tanks, and 206250 m2 dense-mesh net (newly included in the technical design). (4) Borrow sites Water and soil - 394 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow - 395 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) area should be restored in late construction stage through surface soil backfill and vegetation replanting Structural measures: 11,080 m3 for surface soil removal, 11,080 m3 for surface soil backfill, 36.95 hm2 for land rehabilitation, 3,800 m long brick masonry drainage canal, and 15 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 36.95 hm2 for grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m long retaining wall for temporary storage site and 36,000 m2 dense-mesh net (newly included in the technical design). - 396 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) (5) Disposal sites Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should be built around the site. The disposal site should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 - 397 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 bushes (newly included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly included in the technical design). ⑥ Mud transfer tank: Temporary measures: 21 mud transfer tanks to be 3 provided; 11193m for earthwork excavation and 3 backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary - 398 - Table 11-9 Environmental impacts of He River-lake connection Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) drainage ditches. Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 1. The design boundary is optimized based on the scope of preservation of the Flood risk to the Xiyue Street Historical and Xiyue Street Cultural Quarter and the Historical and Huangansi Xiyue Street area needed to be Cultural Drainage Historical and preserved is avoided. Quarter; Canal Cultural Quarter, 2. Due to the perennial impacts of river Integrated residential reception of domestic dredging odor Rehabilitation buildings on sewage along He River, Design Schematic on the (C-1 Badaxi Road, Huangansi Drainage Canal / FS unit / stage design residential Huangansi Qianjin Road, is known for its poor water buildings on Drainage Jiangbeizhong quality and odor sediments. Badaxi Road, Canal Road, Youxing Since the drainage canal is Qianjin Road, Integrated Street and Xiyue located in the urban center Jiangbeizhong Rehabilitation) Street that is densely populated Road, Youxing with limited space for Street and operation, the optimized Xiyue Street program chooses the underwater dredging method with suction sludge - 399 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) pump assisted with artificial operation. Water sealing plays a significant role in reducing odor emission and reducing the amount of odor generated from sludge agitation. 3. As the optimum choice, No. 1 dewatering site (river shores on the right bank of He River approximately 100m upstream from Lingfeng Bridge) is selected. It is located more than 100m away from the closest sensitive spot, helpful to avoid impacts on the environmentally sensitive sites from temporary storage and dewatering of sludge. Civil works Noises construction, Residential generated in Requirements included in construction buildings at the operation of ESMP Annex 1: World Bank material and Badaxi Road, excavators, bull Loan Guangxi Hezhou Construction earth and Qianjin Road, dozers, dump Urban Water Infrastructure Construction Municipal 3 stage aggregate Jianshezhong trucks and and Environment contractor EPB transportation, Road, Youxing other Improvement Project ECOP construction Street and Xiyue construction for Embankment camps, Street plants used in Construction Component access roads the construction - 400 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) stage will generate certain impacts on sensitive sites within a distance of 30m in the neighborhood. Dust generated in earthwork excavation, stockpiling, backfill, pedestrian and motor vehicle movement, spillage from earthwork transportation vehicles in the construction stage will generate certain impacts on sensitive sites within a distance of 50m in the neighborhood. Poor management of - 401 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) construction wastes and debris, waste soil generated in the demolition of acquired buildings and construction of new buildings will cause impacts on the environment. Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope Construction and land surface with activities will vegetation being removed Right of way and result in should be covered with temporary land Construction Municipal additional soil dense-mesh net for 3.6 use for the contractor WRB erosion of protection during Project 4.13hm2 and construction and restored 143t. through soil covering and greening in later stage. Structural measures: 6,500 m3 surface soil backfill (already included in the technical design). - 402 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Greening measures: 21,528 m2 greening, and 1,920 m2 wetland planting (already included in the technical design). Temporary measures: temporary covering by 3,000 m2 dense-mesh net (newly included in the technical design). The dredging 1. Information on the process will construction plan, the generate environmental impact temporary descriptions and sludge disturbances to transportation route should Operation of water systems be disclosed in time to the dredging and result in public. vessel, Water system of increased SS 2. The dredging operation of Huangansi concentration operation should be integrated Drainage Canal, and possibly conducted in the Construction Municipal sludge areas along the 5 fugitive odor in low-water season and contractor EPB treatment sludge a small amount. the construction time facility, sludge transportation Improper should be shortened, if dewatering routes management of possible, to reduce and onsite sludge disturbances to water dewatering dewatering or systems. transportation 3. The dredging method process may selected for Huangansi cause Drainage Canal is suction secondary sludge pump plus artificial - 403 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) pollution. operation. The dredged sludge with a moisture content of 95% are conveyed through fecal suction truck to No. 1 dewatering site along He River. Interception and diversion + dry dredging method may be used for dredging provided that the construction condition permits (with the required operation space available for inner river interception and diversion) and a sound regional intercepting pipeline network is in place 4. Sludge is dewatered into sludge cakes with a moisture content of less than 50%, which are then transported in enclosed vehicles to Hezhou Municipal Domestic Solid Waste Landfill for disposal. 5. Construction plants involved in the dredging process must be subject to strict inspection to prevent oil leakage. Sewage and solid wastes must not be - 404 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) cast into the water systems and should, instead, be collected and treated together with the other construction wastes. 6. Flood interception ditches should be excavated around the temporary sludge storage tanks on the dewatering site and connected to the wastewater sedimentation tanks. 7. Stormwater, tail water from sludge dewatering collected by the flood interception ditches should be discharged into the wastewater sedimentation tank for sedimentation before finally discharged into He River. 8. The sludge should be dewatered and transported out of site in a timely manner to avoid the generation of leachate due to excessive storage. 9. Quick lime and deodorants should be provided for sterilization - 405 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) and deodorization of the dewatering site and labor protection devices such as masks should be provided to the construction workers. No preserved ancient buildings are distributed in the construction area. However, poor The construction activities construction will be carried out in strict Construction management accordance with the of civil works, and uncivilized requirements included in transportation Ancient buildings construction ESMP Annex 4: World Bank of in the Xiyue behaviors may Financed Guangxi Hezhou Construction Municipal construction Street Historical 2 lead to Urban Water Infrastructure contractor CPPRFTB materials and and Cultural irrevocable and Environment earth and Quarter consequences Improvement Project stone such as Management Plan of materials damage, Physical Cultural contamination Resources. and even destruction of the preserved ancient buildings and sites. - 406 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 1. Construction scope should be narrowed No famous or and construction ancient trees period should be are found in the shortened as much as project implementation possible; area, but 2. Tree felling, unlicensed temporary transplanting, bark borrow and Construction peeling, root digging dump of soil, of civil works, and injection of toxic 2 camphor trees stockpiling of transportation and 1 banyan construction and hazardous of tree at Xinaner wastes and Construction Municipal construction substances to trees / Street, 1 movement of contractor MEB materials and should be prohibited; camphor tree at construction earth and Xiyue Street vehicles and 3. It is not allowed to stone plants on the construct buildings or materials construction sites may affect structures, lay the normal pipelines, install power growth of such cables, excavate trees in the vicinity with a borrow areas, mine distance of less sand and stone, flood than 50m. or seal the ground, emit fumes, discharge wastewater and dump - 407 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) solid wastes, stockpile or dump flammables, explosives or toxic and hazardous substances in the area with a distance of less than 5m from the outer edge of the crown shadow of trees. 4. It is not allowed to engrave, nail, wind, hang or support or stack articles on or around tree trunks; and 5. Construction vehicles and plants are not permitted to enter or roll the area with a distance of less than 5m from the outer edge of the crown shadow of trees. - 408 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 1. The contractor should further coordinate with municipal and urban development authorities during construction for collection of underground pipeline Pipelines at the information including intersection Poor pipeline type, between construction Excavations alignment and depth, Huangansi management during civil Construction Municipal Drainage Canal may lead to and establish a / works contractor HURB and Badaxi Road interruption of pipeline coordination construction and underground Jianshezhong pipelines. team. Prior approval Road should be obtained from municipal and urban development authorities for excavation interfering with underground pipelines. 2. Construction plan and emergency response - 409 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) plan should be developed based on pipeline alignment and depth to avoid interference with existing underground pipelines as much as possible. 3. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities to be prepared for emergency responses. Borrow area Borrow fill and (1) Construction access Borrow fill and located 1.25km waste soil for roads Construction Municipal 1491.16 waste oil east of Xiadao temporary land Prior to construction, top contractor WRB Bridge in the use, soil in the right of way will - 410 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) eastern part of construction be removed and stockpiled Hezhou access road on a temporary stockpiling Municipality, and site in the construction area borrow area construction of the main stream located at camp will result rehabilitation works of He Hezhou in soil erosion River. In the meanwhile, Electronic in a total area temporary drainage and Technology of 87.72hm2 sedimentation measures Ecological and an will be taken on both sides Industry Park additional soil of the road and land and the erosion of rehabilitation and cut-over construction 100058t. land restoration will be waste disposal conducted in the late stage site located at of the Project. Gonghe Village, Structural measures: top Huangtian of soil removal in a total Hezhou volume of 41,600m3, top Municipality soil backfill in a total volume of 41,600 m3 and land rehabilitation in a total area of 20.82hm2 (newly included in the technical design); Greening measures: 5.12hm2 for forest land restoration, 7.04hm2 for grassland restoration (newly included in the technical design); Temporary measures: 138660m for temporary - 411 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) earth drainage gutter; 139 temporary sedimentation tanks (newly included in the technical design). (2) Construction production and domestic activity areas Prior to construction, top soil in the right of way will be removed and stockpiled on a temporary stockpiling site in the construction area of the main stream rehabilitation works of He River. In the meanwhile, temporary drainage and sedimentation measures will be taken on both sides of the road and land rehabilitation and cut-over land restoration will be conducted in the late stage of the Project. Structural measures: top soil removal in a total volume of 9000m3, top soil backfill in a total volume of 9000 m3 and land rehabilitation in a total area of 4.50hm2 (newly included - 412 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) in the technical design); Greening measures: 0.11hm2 for garden land restoration, 2.71hm2 for grassland restoration (newly included in the technical design); Temporary measures: 4685m for temporary earth drainage gutter; 26 temporary sedimentation tanks; 7700m2 for dense-mesh net (newly included in the technical design). (3) Temporary soil storage site Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored through land rehabilitation and cut-over land restoration at the end of the construction stage. - 413 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Structural measures: 18.05 hm2 land rehabilitation (newly included in the technical design). Greening measures: 4.31 hm2 forest land restoration, 1.38hm2 garden restoration and 2.22 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758m long temporary earth drainage canal, and 53 temporary sedimentation tanks, and 206250 m2 dense-mesh net (newly included in the technical design). (4) Borrow areas Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system - 414 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting Structural measures: 11,080 m3 for surface soil removal, 11,080 m3 for surface soil backfill, 36.95 hm2 for land rehabilitation, - 415 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 3,800 m long brick masonry drainage canal, and 15 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 36.95 hm2 for grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m long retaining wall for temporary storage site and 36,000 m2 dense-mesh net (newly included in the technical design). (5) Waste disposal sites Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil - 416 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should be built around the site. The disposal site should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 bushes (newly - 417 - Table 11-10 Environmental Impacts of Huangansi Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly included in the technical design). ⑦ Mud transfer tank: Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork 3 excavation and backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Shizigang Residential Dredging odor 1. Due to the perennial Drainage buildings at will generate reception of domestic Design Schematic Canal Wanquan Street, impacts on sewage along He River, / FS unit / stage design Integrated Zhushan Road, residential Shizigang Drainage Canal is Rehabilitation Longxing Road, buildings at known for its poor water - 418 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) (C-2 and Yinhe Street; Wanquan quality and odor sediments. Shizigang office building of Street, Since the drainage canal is Drainage Hezhou Land Zhushan Road, located in the urban center Canal and Resources Longxing that is densely populated Integrated Bureau, office Road, and with limited space for Rehabilitation) building and staff Yinhe Street; operation, the optimized dormitory office building program chooses the building of of Hezhou underwater dredging Guidong Land and method with suction sludge Electricity Resources pump assisted with artificial Bureau, Bureau, office operation. Water sealing residential building and plays a significant role in buildings at staff dormitory reducing odor emission and Wangjiao Road, building of reducing the amount of odor Jianshe Road, Guidong generated from sludge Longshan Road, Electricity agitation. Xingguang Road; Bureau, 2. As the optimum choice, shops and residential No. 1 dewatering site (river swimming pool of buildings at shores on the right bank of Hezhou Water Wangjiao He River approximately Resources Road, Jianshe 100m upstream from Bureau, Road, Lingfeng Bridge) is residential Longshan selected. It is located more building at Road, than 100m away from the Pinganxi Road, Xingguang closest sensitive spot, office building of Road; shops helpful to avoid impacts on Hezhou Health and swimming the environmentally and Family pool of Hezhou sensitive sites from Planning Water temporary storage and Committee, office Resources dewatering of sludge. building and staff Bureau, 3. Upon transformation of - 419 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) dormitory residential blind canal to open canal, building of Babu building at the optimized program District Pinganxi Road, considers the construction Transportation office building of one small overbridge Bureau, of Hezhou each at Yinhe Street, the residential Health and Land & Resources Bureau buildings at Family and Guidong Electricity Jiangbeizhong Planning Bureau to mitigate impacts Road Committee, on travelling of local office building residents due to such and staff transformation. dormitory building of Babu District Transportation Bureau, residential buildings at Jiangbeizhong Road. Blind-to-open canal transformation will generate impacts travelling convenience of residential buildings at Yinhe Street, office building - 420 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) of Hezhou Land & Resources Bureau, office building and staff dormitory building of Guidong Electricity Bureau. Residential Noises buildings at generated in Wanquan Street, the operation Zhushan Road, of excavators, Longxing Road, bull dozers, and Yinhe Street; dump trucks Civil works office building of and other construction, Hezhou Land construction Requirements included in construction and Resources plants used in ESMP Annex 1: World Bank material and Bureau, office the Financed Guangxi Hezhou Construction earth and Construction Municipal building and staff construction Urban Water Infrastructure 10 stage aggregate contractor EPB dormitory stage will and Environment transportation, building of generate Improvement Project ECOP construction Guidong certain impacts for Embankment camps, Electricity on sensitive Construction Component. access roads Bureau, sites within a residential distance of buildings at 30m in the Wangjiao Road, neighborhood. Jianshe Road, Dust generated Longshan Road, in earthwork - 421 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Xingguang Road; excavation, shops and stockpiling, swimming pool of backfill, Hezhou Water pedestrian and Resources motor vehicle Bureau, movement, residential spillage from building at earthwork Pinganxi Road, transportation office building of vehicles in the Hezhou Health construction and Family stage will Planning generate Committee, office certain impacts building and staff on sensitive dormitory sites within a building of Babu distance of District 50m in the Transportation neighborhood. Bureau, Poor residential management buildings at of construction Jiangbeizhong wastes and Road debris, waste soil generated in the demolition of acquired buildings and construction of new buildings - 422 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) will cause impacts on the environment. Reusable surface soil in disturbed area should be removed and stored in designated area before construction. Cut slope and land surface with vegetation being removed should be covered with Construction dense-mesh net for activities will Right of way and protection during result in temporary land Construction Municipal additional soil construction and restored 6 use for the contractor WRB erosion of through soil covering and Project 13.62hm2 and 1045t. greening in later stage. Structural measures: 3,990 m long bio-swale, 2,247 m long covered drainage canal, and 9,000 m3 surface soil backfill (already included in the technical design). Greening measures: - 423 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 23,340m2 three-dimensional geo-technical net embankment slope covered with grass, 30,057 m2 greening, and 3,990 m2 wetland planting (already included in the technical design). Temporary measures: temporary covering by 5,000 m2 dense-mesh net (newly included in the technical design). The dredging 1. Information on the Operation of process will construction plan, the dredging generate environmental impact vessel, Water system of temporary descriptions, dredger operation of Shizigang disturbances to operation route and sludge integrated Drainage Canal, water systems transportation route should Construction Municipal sludge areas along the 5 and result in be disclosed in time to the contractor EPB treatment sludge increased SS public. facility, sludge transportation concentration 2. The dredging dewatering route and possibly operation should be and onsite fugitive odor in conducted in the dewatering a small low-water season and - 424 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) amount. the construction time Improper should be shortened, if management possible, to reduce of sludge disturbances to water dewatering or systems. transportation 3. The dredging method process may selected for Shizigang cause Drainage Canal is suction secondary sludge pump plus artificial pollution. operation. The dredged sludge with a moisture content of 95% are conveyed through fecal suction truck to No. 1 dewatering site along He River. Interception and diversion + dry dredging method may be used for dredging provided that the construction condition permits (with the required operation space available for inner river interception and diversion) and a sound regional intercepting pipeline network is in place. 4. Sludge is dewatered into sludge cakes with a moisture content of less than 50%, which are then transported in enclosed vehicles to - 425 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Hezhou Municipal Domestic Solid Waste Landfill for disposal. 5. Construction plants and vessels involved in the dredging process must be subject to strict inspection to prevent oil leakage. Sewage, solid wastes and oily wastewater from vessel cabins must not be cast into the water systems and should, instead, be collected and treated together with the other construction wastes. 6. Flood interception ditches should be excavated around the temporary sludge storage tanks on the dewatering site and connected to the wastewater sedimentation tanks. 7. Stormwater, tail water from sludge dewatering collected by the flood interception ditches should be discharged into the wastewater sedimentation - 426 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) tank for sedimentation before finally discharged into He River. 8. The sludge should be dewatered and transported out of site in a timely manner to avoid the generation of leachate due to excessive storage. 9. Quick lime and deodorants should be provided for sterilization and deodorization of the dewatering site and labor protection devices such as masks should be provided to the construction workers. Interrupted 1. Impacts on the normal Residential operation of operation of shops at Yinhe building at Yinhe shops at Yinhe Street, Hezhou Land & Street, office Street will Resources Bureau and building of generate Guidong Electricity Bureau Hezhou Land & Blind-to-open impacts on will be mitigated mainly Resources Construction canal income of through implementation of / MEB Bureau, office contractor transformation business LAR and compensation and staff owners. Some measures detailed in the dormitory parking spaces RP. buildings of in Hezhou 2. Impacts on the parking lot Guidong Land & of the Land & Resources Electricity Bureau Resources Bureau may be mitigated - 427 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Bureau will through diversion of traffic, become no restricting access of longer usable, vehicles of other imposing organizations, which may be pressure on diverted to the parking lots office parking in the vicinity. for this unit. 1. The contractor should Pipelines at the intersection further coordinate with between municipal and urban Shizigang development Drainage Canal and Guposhan authorities during Avenue, construction for Wanquan Street, collection of Poor Zhushan Road, construction underground pipeline Excavations Badaxi Road, management information including during civil Yinhe Street, Construction Municipal may lead to / works Jianshezhong pipeline type, contractor HURDB interruption of construction Road, Pinganxi underground alignment and depth, Road, Longshan pipelines. and establish a Road, Anshanxi Road, Xingguang pipeline coordination Road, Pinganxi team. Prior approval Road and the Transportation should be obtained Bureau at from municipal and Jiangbeizhong urban development Road authorities for - 428 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) excavation interfering with underground pipelines. 2. Construction plan and emergency response plan should be developed based on pipeline alignment and depth to avoid interference with existing underground pipelines as much as possible. 3. In the event of interference with existing pipelines, the concerned authority should be informed of particular construction location and schedule of excavation activities to be prepared for emergency responses. Borrow fill and Borrow area Borrow fill and (1) Construction access 1491.16 Construction Municipal - 429 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) waste oil located 1.25km waste soil for roads contractor WRB east of Xiadao temporary land Prior to construction, top soil Bridge in the use, in the right of way will be eastern part of construction removed and stockpiled on Hezhou access road a temporary stockpiling site Municipality, and in the construction area of borrow area construction the main stream located at camp will result rehabilitation works of He Hezhou in soil erosion River. In the meanwhile, Electronic in a total area temporary drainage and Technology of 87.72hm2 sedimentation measures will Ecological and an be taken on both sides of Industry Park additional soil the road and land and the erosion of rehabilitation and cut-over construction 100058t. land restoration will be waste disposal conducted in the late stage site located at of the Project. Gonghe Village, Structural measures: top soil Huangtian of removal in a total volume of Hezhou 41,600m3, top soil backfill in Municipality a total volume of 41,600 m3 and land rehabilitation in a total area of 20.82hm2 (newly included in the technical design); Greening measures: 5.12hm2 for forest land restoration, 7.04hm2 for grassland restoration (newly included in the technical design); - 430 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Temporary measures: 138660m for temporary earth drainage gutter; 139 temporary sedimentation tanks (newly included in the technical design). (2) Construction production and domestic activity areas Prior to construction, top soil in the right of way will be removed and stockpiled on a temporary stockpiling site in the construction area of the main stream rehabilitation works of He River. In the meanwhile, temporary drainage and sedimentation measures will be taken on both sides of the road and land rehabilitation and cut-over land restoration will be conducted in the late stage of the Project. Structural measures: top soil removal in a total volume of 9000m3, top soil backfill in a total volume of 9000 m3 and land rehabilitation in a total - 431 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) area of 4.50hm2 (newly included in the technical design); Greening measures: 0.11hm2 for garden land restoration, 2.71hm2 for grassland restoration (newly included in the technical design); Temporary measures: 4685m for temporary earth drainage gutter; 26 temporary sedimentation tanks; 7700m2 for dense-mesh net (newly included in the technical design). (3) Temporary soil storage site Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored through land rehabilitation and cut-over land restoration at the end of the construction stage. - 432 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Structural measures: 14.75 hm2 land rehabilitation (newly included in the technical design). Greening measures: 4.31 hm2 forest land restoration and 2.42 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 6,985 m long temporary straw bag stuffed with soil, 7,085 m long temporary earth drainage canal, and 47 temporary sedimentation tanks, and 173,800 m2 dense-mesh net (newly included in the technical design). (4) Borrow areas Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary - 433 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage through surface soil backfill and vegetation replanting Structural measures: 11,080 m3 for surface soil removal, 11,080 m3 for surface soil backfill, 36.95 hm2 for land rehabilitation, 3,800 m long brick masonry drainage canal, and 15 brick masonry sedimentation tanks (newly - 434 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) included in the technical design). Greening measures: 36.95 hm2 for grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m long retaining wall for temporary storage site and 36,000 m2 dense-mesh net (newly included in the technical design). (5) Disposal sites Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining - 435 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) wall, masonry drainage canal and various drainage structures should be built around the site. The disposal site should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 bushes (newly included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly - 436 - Table 11-11 Environmental Impacts of Shizigang Drainage Canal Integrated Rehabilitation Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) included in the technical design). ⑧ Mud transfer tank: Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork 3 excavation and backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches - 437 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 1. The WWTP siting should be optimized and the area east of the planned Jiangnan District of Hezhou, east of Luo-Zhan Railway, south of He River and west of Songbozhai of Gubai Village is recommended as the WWTP site to reduce Drainage Impacts on the resettlement and avoid system environmentally impacts on environmentally improvement sensitive sites sensitive sites. Sensitive sites (C-3 from operation of 2. In order to reduce the around the Jiangnan Design Schematic WWTP; impacts impacts of noises generated WWTP, water / FS unit / WWTP and stage design on water quality in the operation of the pumps quality of He associated of He River from and equipment in the WWTP, River pipeline and accidental well-designed and low-noise road discharge of mechanical equipment is construction WWTP selected and vibration insulation and control measures are adopted where possible during installation and operation to reduce noise; the robust structure and evenly grouted bases of the pump equipment can absorb vibrations and provide a solid support to the base - 438 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) plate. Through reasonable arrangement of sound absorbing materials and vibration reduction devices, e.g. asbestos boards and shock absorbers, on the inner walls, ceilings, floors and beside the equipment in the pump station helps to effectively control and eliminate spread and reflection of noises. 3. A certain allowance will be considered in the WWTP design to keep a certain buffer in accident state and avoid impacts on the water quality of He River from accidental discharge. Construction Noises of civil works, generated in the Requirements included in transportation operation of ESMP Annex 3: World Bank of excavators, bull Loan Guangxi Hezhou Urban construction dozers, dump Residential Water Infrastructure and Construction materials and trucks and other Construction Municipal buildings at Environment Improvement 5 stage earth and construction contractor EPB Niupailan Project ECOP for Road and aggregates, plants used in Pipeline Construction construction the construction Component will be camps, stage will implemented. access generate certain roads, etc. impacts on - 439 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) sensitive sites within a distance of 30m in the neighborhood. Dust generated in earthwork excavation, stockpiling, backfill, pedestrian and motor vehicle movement, spillage from earthwork transportation vehicles in the construction stage will generate certain impacts on sensitive sites within a distance of 50m in the neighborhood. Poor management of construction wastes and debris, waste soil generated in the demolition of - 440 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) acquired buildings and construction of new buildings will cause impacts on the environment. (1) Jiangnan WWTP and Associated pipeline networks Surface soil in disturbed area should be removed and stored in designated area Construction before construction. Cut activities will Right of way and result in soil slope and ground surface temporary land erosion in a total with vegetation being Construction Municipal 38.36 use for the area of 34.12hm2 removed should be covered contractor WRB Project and an additional with dense-mesh net for soil erosion of 2949t. protection during construction and restored through soil covering and greening in later stage. Temporary drainage canals and other drainage structures should be built on - 441 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) site. Structural measures: removal of 5,000 m3 surface soil, 5000 m3 surface soil backfill and 800 m long stormwater pipelines (already included in the technical design). Greening measures: 0.96 hm2 landscaping and greening (already included in the technical design). Temporary measures: 880 m long temporary earth drainage canal, 4 temporary sedimentation tanks, and temporary covering by 1,000 m2 dense-mesh net (newly included in the technical design). (2) Binjiangnan Road Surface soil in disturbed area should be removed and - 442 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) stored in designated area before construction. Cut slope and ground surface with vegetation being removed should be covered with dense-mesh net for protection during construction and restored through soil covering and greening in later stage. Temporary drainage canals and other drainage structures should be built on site. Structural measures: removal of 99500 m3 surface soil, 99500 m3 surface soil backfill and 5,560 m long stormwater pipelines (already included in the technical design). Greening measures: 2 146126m embankment - 443 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) greening and21770m2 road greening (already included in the technical design). Temporary measures: 11,120 m temporary earth drainage canal, 20 temporary sedimentation tanks, and temporary covering by 5,000 m2 dense-mesh net (newly included in the technical design). Borrow area (1) Construction access located 1.25km Borrow fill and roads east of Xiadao waste soil for Prior to construction, top soil Bridge in the temporary land in the right of way will be eastern part of use, construction removed and stockpiled on a Hezhou access road and temporary stockpiling site in Municipality, construction the construction area of the Borrow fill Construction Municipal borrow area camps will result main stream rehabilitation 1491.16 and waste oil contractor WRB located at in soil erosion in works of He River. In the Hezhou a total area of meanwhile, temporary Electronic 87.72hm2 and an drainage and sedimentation Technology additional soil measures will be taken on Ecological erosion of both sides of the road and Industry Park 100058t. land rehabilitation and and the cut-over land restoration will - 444 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) construction be conducted in the late stage waste disposal of the Project. site located at Structural measures: top soil Gonghe Village, removal in a total volume of Huangtian of 41,600m3, top soil backfill in a Hezhou total volume of 41,600 m3 and Municipality land rehabilitation in a total area of 20.82hm2 (newly included in the technical design); Greening measures: 5.12hm2 for forest land restoration, 7.04hm2 for grassland restoration (newly included in the technical design); Temporary measures: 138660m for temporary earth drainage gutter; 139 temporary sedimentation tanks (newly included in the technical design). (2) Construction production and domestic activity areas Prior to construction, top soil in the right of way will be removed and stockpiled on a temporary stockpiling site in the construction area of the main stream rehabilitation works of He River. In the - 445 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) meanwhile, temporary drainage and sedimentation measures will be taken on both sides of the road and land rehabilitation and cut-over land restoration will be conducted in the late stage of the Project. Structural measures: top soil removal in a total volume of 9000m3, top soil backfill in a total volume of 9000 m3 and land rehabilitation in a total area of 4.50hm2 (newly included in the technical design); Greening measures: 0.11hm2 for garden land restoration, 2.71hm2 for grassland restoration (newly included in the technical design); Temporary measures: 4685m for temporary earth drainage gutter; 26 temporary sedimentation tanks; 7700m2 for dense-mesh net (newly included in the technical design). (3) Temporary soil storage site - 446 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) Straw bag stuffed with soil will be placed and temporary drainage and sedimentation structures should be built around the site before construction. Temporary soil storage site should be covered during and restored through land rehabilitation and cut-over land restoration at the end of the construction stage. Structural measures: 18.05 hm2 land rehabilitation (newly included in the technical design). Greening measures: 4.31 hm2 forest land restoration, 1.38hm2 garden restoration and 2.22 hm2 grass land restoration (newly included in the technical design). Temporary measures: installation and removal of 8658 m long temporary straw bag stuffed with soil, 5758 m long temporary earth drainage canal, and 53 temporary sedimentation tanks, and 206250 m2 dense-mesh net (newly - 447 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) included in the technical design). (4) Borrow sites Water and soil conservation measures for borrow area are not included in project technical design, which should be a comprehensive system composed of structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Excavation during construction should be done from top to bottom and bench by bench to form stable cut slope. Retaining wall of soil bags should be built along slope bottom and bare ground surface should be covered with dense-mesh net. Temporary drainage canals and structures should be built around the site. The borrow area should be restored in late construction stage - 448 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) through surface soil backfill and vegetation replanting Structural measures: 11,080 m3 for surface soil removal, 11,080 m3 for surface soil backfill, 36.95 hm2 for land rehabilitation, 3,800 m long brick masonry drainage canal, and 15 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 36.95 hm2 for grass planting, planting of 46,187 pines and 92,375 bushes (newly included in the technical design). Temporary measures: 1,000 m long retaining wall for temporary storage site and 36,000 m2 dense-mesh net (newly included in the technical design). (5) Waste disposal sites Water and soil conservation measures for disposal site are not included in project technical design, which should be a comprehensive system composed of - 449 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) structural measures, planting measures and temporary measures. Surface soil should be removed and be stored in temporary storage site before construction. Retaining wall, masonry drainage canal and various drainage structures should be built around the site. The disposal site should be restored at the end of the construction stage through surface soil backfill and vegetation replanting. Structural measures: 22,200 m3 for surface soil removal, 22,200 m3 for surface soil backfill, 7.4 hm2 for land rehabilitation, 150 m long masonry retaining wall, 1,100m long masonry interception/drainage canal, and 4 brick masonry sedimentation tanks (newly included in the technical design). Greening measures: 7.4 hm2 grass planting, planting of 9,250 pines and 18,500 - 450 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) bushes (newly included in the technical design). Temporary measures: installation of 2,000 m2 dense-mesh net (newly included in the technical design). Mud transfer tanks: Temporary measures: 21 mud transfer tanks to be provided; 11193m3 for earthwork excavation 3 and backfill; 861m for fencing and demolition of earth-filled woven bags; 495m for temporary drainage ditches.: 1. Measures of odor collection and biological deodorization will be taken for the key odor-generating structures such as influent pump station, Impacts aeration tank, sludge generated by concentration tank, and odor, noise and Operation WWTP WWTP site and sludge dewatering workshop. Municipal sludge 30 Operator stage operation its neighborhood 2. A health protection EPB generated in the distance of 100m is set on the operation of the periphery of the major WWTP odor-generating structures such as influent pump house, aeration tank, sludge concentration tank and sludge dewatering workshop. - 451 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) 3. Maintenance and servicing of water pumps should be strengthened by means of periodical inspection of electric motor and pump axle concentricity and assuring excellent lubrication of axles so as to reduce wearing of pump parts. 4. A greenbelt around the pump house should be constructed through inter-planting trees and bushes to improve landscaping and reduce waste gas, noise and odor impacts on surrounding environment. Tree species with strong pollution resistance should be selected. 5. Sludge generated from Jiangnan WWTP is transported to Guangxi Hezhou Sludge Harmless Treatment Project for dewatering and then to Hezhou Solid Waste Landfill for disposal. In the operating 1. Proper protective clothes, WWTP staff 20 Operator environment, gloves and respiration mask Municipal - 452 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) staff of Jiangnan should be provided for Occupational WWTP is WWTP workers. Anti-skid Disease extensively shoes should be provided Prevention exposed to for transportation workers and Control wastewater or and steel-toe shoes should Center sludge be provided for all the containing workers to prevent foot various injury. Workers working near pathogenic high-noise equipment bacteria and should be provided with parasitic ovum. noise protective devices. Mist and vapor Workers operating near generated by heavy movable equipment, wastewater bucket, crane and treatment facility transportation vehicle could spread dumping site should be bacteria and equipped with safety helmet. virus. Exposed Guardrails should be to installed around all the microorganisms process containers and in wastewater water tanks. Lifeline and and sludge, personal floating device operation staff should be available for use of WWTP may when operators are working be infected and within the guardrails, to catch disease. make sure life saving devices being in place in emergencies. 2. Dangerous contact should be reduced through design and development of - 453 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) technical and material specifications (e.g. ventilation, air conditioning, enclosed conveyor belt, low-load and different heights, anti-skid floor, safety guardrails for stairways and aisles, spill protection and leakage prevention, noise control, dust prevention measures, gas alarm system, fire alarm and control system, and evacuation devices). 3. Bathroom and dressing area should be provided for the operators for after-work bath and dressing, and work clothing laundry service should be provided. Additionally, frequent hand washing of WWTP staff should be encouraged. 4. Enclosed space access plan conforming to the national requirements and internationally recognized standards should be developed for construction activities in enclosed treatment zone. Ventilation - 454 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) is mandatory before entering. Operators should be equipped with gas detector and valve connected with process container should be locked to prevent accidental overflow during maintenance. 5. Eating, smoking and water drinking should be banned outside the designated area. 6. Operators should be separated from bacteria spreading channels via mechanical overturning (e.g. use of tractor or front-end loader with enclosed air conditioning or heating driver cab). Ventilation system should be provided in case of manual overturning. In the event of 1. Emergency response an accidental measures against instable Accidental discharge from water supply caused by Water quality of Municipal discharge of Jiangnan various factors should be fully 20 Operator He River EPB WWTP WWTP, a 10 m considered in the design to wide and 220 m mitigate the adverse long area conditions. - 455 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) downstream of 2. A WWTP operation the outlet will management and experience accountability system should non-compliant be set up. COD discharge 3. Management and higher than the operation staff training should standard by a be organized and technical factor of 15.10. examination files developed. In such an Those who fail such event, the water examination shall not be quality of He allowed to take the post. River will be Experienced technical affected to a professionals should be certain extent employed to be responsible and such event for internal technical may even lead management work; to professional and technical non-compliance personnel should be selected in a certain area to take part in domestic or in the international technical downstream training. section. 4. Inspection of water conveyance pipelines should be strengthened so that problems are identified and addressed in a timely manner. 5. Multiple stand-by equipment should be provided for vulnerable equipment and adequate spare parts required for - 456 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) maintenance and upgrading should be assured. The mechanical and electronic equipment in the treatment system should at least have one in operation and one stand-by. 6. High quality equipment should be selected. The various machines, electrical appliances and instruments in the treatment facilities should be products of high quality and low fault rate that satisfy the design requirements and are suitable to long-term operation and easy maintenance. 7. During operation, the on-duty operators must operate in strict accordance with the rules and regulations of the treatment facilities, conduct frequent inspections and carry out timely maintenance and servicing to reduce the fault rate. 8. The electrical equipment should follow the requirements of grounding protection specifications and - 457 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) be equipped with automatic tripping circuit. Operation of key equipment is subject to computer digital monitoring to enable timely alarms and recording of location, nature and time of occurrence of accidents so that timely repair can be organized. The installation protections for all electrical equipment must satisfy the relevant safety requirements for electrical equipment. 9. Dual feed electricity supply should be adopted to assure normal operation of the electricity supply facilities and lines. As a result of 1. Upon pipeline design, leakage of suitable pipe material should sewage be selected based on the pipelines, specific conditions and Accidental Surface water, collection of characteristics of the city leakage due ground water and wastewater will where they are located and Municipal to broken 10 Operator soil around the become unlikely actions should be taken to EPB sewage pipelines and untreated assure pipeline quality and pipeline wastewater will service life. The groundwork be discharged of pipeline drainage works into surface must satisfy the mechanical waters, causing design requirements, with - 458 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) impacts on corresponding actions taken surface water where such requirements are environment. failed. Such groundwork Wastewater should be constructed in strict leaked from accordance with the width, pipelines will thickness and strength permeate into required in the design the ground, not drawing for quality assurance. only polluting the 2. Inspections should be soil and carried out accordingly before sanitation pipeline laying. On one hand, environment, but pipes delivered to site should also generating be carefully inspected to adverse impacts avoid situations where pipes on water quality with cracks or voids are laid in of ground water. the trenches; on the other hand, centerlines and side lines of pipeline foundation and size and strength of manhole foundation should be carefully checked against the drawings; finally, location and distance of manholes, concrete strength at all locations and mix ratio of waterproof mortar at all junctions must be checked against the national standards. 3. Upon pipeline installation, cement mortar needed for - 459 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) plaster band should be prepared according to the specified mix ratio. Stand-up seams often occur due to pressing upon the installation of junctions between two drainage pipelines. In order to assure smooth flow of the drainage pipelines, the stand-up seams at the junctions should be handled in time to avoid reduction of flow section, impacts on flow speed and even accumulation of debris in and even obstruction of pipelines. 4. Trench backfill should not be conducted until the cradle concrete and plaster band mortar reach a certain strength and direct impact by aggregates on the pipes should be avoided. Large rocks, bricks and hard substances should not be present in the aggregates. Backfill and compaction on both sides of the pipeline should be conducted simultaneously while that on the top should be conducted - 460 - Table 11-12 Environmental Impacts of the Drainage System Improvement Subproject and their Mitigation Measures Environmental Name of Environmentally Potential Mitigation / control protection Supervision Stage Activity EA subproject sensitive spot impact measures investment agency (CNY10000) in layers to form a mass of integral stress which can disperse and discharge the stress over the crest to protect pipeline safety. 5. In the operation stage of the Project, the EA should set up a sound pipeline management system to enable timely dredging and renewal of pipelines and avoid possible contamination of surrounding waters and ground water from sewage leakage. - 461 - Table 11-13: Environmental impacts and mitigation measures for the Technical Assistance Management Subproject Environmental Environmentally Mitigation/prevention protection Supervisory Sbuproject Period Activity Potential impact EA sensitive site measures investment agency (CNY10000) Noises generated in the operation of excavators, bull dozers, dump trucks and other construction plants used in the construction stage will Technical generate certain impacts assistance on sensitive sites within Requirements included in management a distance of 30m in the ESMP Annex 2: World Bank (E-1: River neighborhood. Loan Guangxi Hezhou Urban governor Hydrological Dust generated in Water Infrastructure and Construction Construction system + station / earthwork excavation, Environment Improvement 1 HEPB stage contractor Internet construction stockpiling, backfill, Project ECOP for Small intelligent pedestrian and motor Waterworks Construction management vehicle movement, Component will be and control spillage from earthwork implemented. system) transportation vehicles in the construction stage will generate certain impacts on sensitive sites within a distance of 50m in the neighborhood. - 462 - Poor management of construction wastes and debris, waste soil generated in the demolition of acquired buildings and construction of new buildings will cause impacts on the environment. 1. The wastewater, exhaust gas and solid wastes The wastewater Technical in the laboratories must be containing strong acid, assistance properly treated according to strong alkaline or toxic management the national laws and substances will generate (E-2: He regulations on environmental serious enviornmental River protection and random pollution if directly Watershed dumping, storage and discharged into the water Operation Laboratory Around the discharge are prohibited. natural environment. / Owner HEPB environment stage operation laboratory 2. Acid and alkaline waste Exhaust gas will cause monitoring, liquid generated in the hazard to laboratory early process of test and analysis staff while the waste warning and and waste liquid containing drugs and test reagents integrated highly toxic drugs must be are hazardous wastes to management dumped into the waste liquid the environment if not system) cylinders for the right properly disposed. classification and delivered to the waste liquid storage - 463 - room for centralized treatment by a qualified unit. 3. Digestion of specimens must be conducted in a ventilated cupboard and all the exhaust gas generated must be discharged at high altitude via the air duct. 4. Wastes generated in the process of testing and analysis shall be handled in such a way that intoxic wastes are dumped into the garbage bins, contaminating wastes are collected and delivered to the waste storage room for centralized treatment by a qualified unit. 5. Proper preventive measures should be taken against fire, burglary and poisoning hazards and risks. Fire protection devices and necessary poison prevention facilities should be provided in the laboratory. 6. Flammables, explosives and toxic substances must be properly stored, claimed - 464 - and registered according to the respective stipulations. 7. Smoking, laundry, cooking and storage of personal food in the refrigerators are prohibited in the laboratory. Loud noises and frolic are banned during test operation. 8. The codes of operation should be strictly followed. - 465 - Table 11-14: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency 1. State-owned floodplain land involves no compensation as the implementation of the Project will not lead to any changes of the nature and ownership relationship of such land. State-owned land: All affected families (AFs) PMO, 2. State-owned allocated land will be replaced with state-owned 47.13 mu will receive cash Owner, land of the corresponding area to be allocated in the vicinity under Floodplain: 34.57 mu compensation. HDAO the Project. 3. Young crop compensation per mu of floodplain land: CNY 2100 /mu 1. Land acquisition compensation: CNY 60,500 per mu of paddy field; CNY 51,800 per mu of dry land; CNY 47,000 per mu of forest land. To be prudent, the compensation criteria for other types of land is set at CNY 47,000 /mu. Permanent land acquisition 2. Crop compensation: CNY 1600-2100/mu depending on the crop types. 3. Compensated land: the planned industrial land equal to 10% of acquired agricultural land will be allocated to the affected rural 3713.28 mu collective collective economy organizations. land in total, including 4. All APs will receive: i) employment and revenue generation 972.08mu for paddy opportunities during project implementation; ii) free employment field,1249.93 mu for 4563 persons from 759 supports and vocational training. PMO, dry land, 533.52 mu households 5. Registered population at or above the age of 16 entitled to rural Owner, for forest land and collectively-owned land contracting at the time of land acquisition HDAO 957.75mu for other will receive subsidies for rural pension insurance to the farmers types of land. AFs: who lost their land. Such subsidies will be calculated based on the 759; affected persons number of people affected by, and the frequency and scope of (AP): 4563. land acquisition. The minimum subsidy for each land acquisition equals 60% of the average wage of workers employed by urban units in the region in the previous year times the per capita area of land acquired from local farmers. Where the per capita area of land acquired from local farmers exceeds 8 mu after one or multiple land acquisitions, the surplus part will not receive any pension insurance subsidy. Where a farmer household whose land is totally acquired and the per capita area of land acquired - 466 - Table 11-14: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency from the affected HHs is less than 1 mu, the subsidy will be calculated on the basis of 1 mu. Total land occupation: occupation Temporary 1045.67 mu, including 1849 persons from 307 PMO, land 434.96 mu paddy field, Compensation for temporary land occupation: CNY 3900 per mu households Owner; 423.58mu dry land; of paddy field; CNY 3400 per mu of forest land HDAO 187.13mu forest land; AFs: 307; AP: 1849. 1. The PMO provides two types of resettlement for households affected by housing acquisition to choose from at free will: Residential houses and ancillary and temporary structures monetary compensation and property right replacement. 2. Monetary resettlement: monetary compensation (generally higher than the replacement price) is provided for all persons whose houses are demolished. Such compensation includes housing compensation and housing decoration compensation after assessment. Housing compensation and housing decoration compensation: The assessment is conducted by 1. Demolition of urban an intermediary agency with good credit-standing and good residential houses: reputation commissioned under joint agreement by the 37465.31m2, brick and 1268 persons from 317 demolishing party and the affected party and the PMO, concrete structure; households compensation is effected based on the assessed price. Owner; AFs: 317; APs: 1268. 3. Property right replacement: built housing is provided and HDAO 2. Demolition of urban housing decoration is compensated. temporary houses: Provision of built housing in the ratio of 1:1. If the area of built 18689.74 m2. housing is greater than the demolished area, the relocated family needs to buy the exceeding area at market price. Provision of housing decoration compensation. The construction unit and the relocated family will commission an independent qualified intermediaries to assess the value of decoration, based on which monetary compensation will be provided. 4. Provision of relocation subsidy and temporary housing subsidy at a rate of CNY 10 / m2 or provision of public housing. - 467 - Table 11-14: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency 5. Provision of CNY 5,000/family as an one-off incentive to those who sign the LAR compensation agreement and hand over the housing within the specified deadline. 6. Cash compensation will be made for urban temporary housing at a price assessed based on market price by an independent and qualified intermediary comissioned jointly by the construction unit and the relocated household. 1. The PMO provides two types of resettlement for households affected by housing acquisition to choose from at free will: monetary compensation and homestead replacement. 2. Monetary compensation is made based on the housing replacement price of CNY 1000 to 1300/m2 for brick structure. For households choosing monetary replacement for their main houses, compensation on the main house homestead will be made at the assessed land price for reallocation of 1. Demolition of rural resettlement homestead. residential houses: 3. Homestead resettlement: Each household is entitled to one 55742.29 m2; brick homestead and each demolished homestead will be and concrete 1837 persons from 373 compensated with one resettlement homestead in an area of structure; AFs: 373; households no more than 120m2; the inadequate part will be compensated APs: 1837. at the assessment price. The main house to be demolished 2. Demolition of rural will be compensated for at the replacement price of the same ancillary houses: standard as for monetary compensation of CNY 1000 to 1300 30588.89 m2. for brick structures. The government will be responsible for providing water supply, power supply, access road and site leveling for the resettlement area as well as the supporting public infrastructures such as schools and hospitals; water and electricity will be delivered to the gate of each household and then connected by the household into their houses. 4. Provision of relocation subsidy and temporary housing subsidy at a rate of CNY 10 / m2. 5. Provision of CNY 5,000/family as an one-off incentive to those - 468 - Table 11-14: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency who sign the LAR compensation agreement and hand over the housing within the specified deadline. 6. Monetary compensation will be provided for rural ancillary housing unexceptionally at a standard of CNY 100-700/m2 depending on the building structure. Compensation fo the acquired land will be made at the standard for acquisition of rural homesteads. Hezhou Municipal Land Resources Bureau (LRB), Health and Family Planning Government, public institutions and Relocation and reconstruction of Hezhou Health and Family Commission, Hezhou WRB, Planning Commission and Babu District Transportation Bureau. Transportation Bureau of Hezhou WRB and LRB choose monetary compensation for the Babu District, Guangxi demolished buildings. Totally 11 government, Guidong Electric Power Guidong Electric Power Limited Company: monetary enterprises public institutions and Limited Company, Yingshi compensation for its office building to be demolished at assessed PMO, enterprises will be Primary School of Huangshi value and new office building will be constructed. Owner; affected with a Town, Xiadao Power Station Yingshi Primary School and Xiadao Primary School: relocation. HDAO demolition area of of Hezhou Pengyuan Hezhou Minfeng Industrial Limited Company and Hezhou 14249.54 m2 Hydropower Development Huangshi Power Station Limited Company: monetary Limited Company, Fanglin compensation for the production losses due to stoppage during Hydropower Station of project construction. Hezhou Minfeng Industrial Limited Company, Hezhou Huangshi Power Station Limited Company Demolition of shops: Compensation for the business losses and relocation cost to be PMO, Shops 527 persons from 124 7458.93m2; AFs: 124; made on the basis of replacement price ratified according to the Owner; affected shop tenants. APs: 527 relevant compensation standard. HDAO - 469 - Table 11-14: Summary of LAR and Social Impacts and Mitigation Measures Type of Eligible beneficiary of Responsible Degree of impact Compensation policy and standard impact compensation agency Sewers: 220 m; Land attachments All APs or owners will Tombs: 53; power The APs will receive cash compensation. Sewage pipe: CNY receive equivalent cash poles: 42; 300/m; power pole: CNY 150 each; communication pole: CNY 150 compensation. PMO, communication poles: each; wall: CNY 70 /m2; bamboo: CNY 1-4 / per bamboo; trees: The land attachments Owner; 22; bamboo: 26489; CNY 10-180 / tree; graves: CNY 5500 each. planted or constructed after HDAO wall: 700m2; trees: The trees described above will be compensated at the actual the cut-off date will not be 15162; transformer: 1 assessed value on the basis of the guiding price. compensated. set. (7) The local Civil Affairs Bureau and the Labor and Social Security Bureau will be responsible for including these families in the social security schemes. Vulnerable group (8) Provision of pension insurance. (9) Provision of new rural cooperative medical insurance paid by PMO, All affected vulnerable 83HH, 273 persons the collective unit. Owner; groups (10) The local rural credit cooperatives and banks can provide the HDAO vulnerable groups with small loans. (11) Provision of project-related employment opportunities. (12) Provision of project-related vocational trainings to vulnerable groups. (5) Create employment and livelihood opportunities for women. (6) Ensure women participation. PMO, (7) The local government and resettlement office shall ensure the Female 4148 persons Owner; female has the same rights as male in terms of land property. HDAO (8) Gender discrimination shall be eliminated to encourage women to create their own business. - 470 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program (8) Diversion of seepage collected from gallery top drain to discharge channel to keep gallery dry; (9) Closer coordination with Fuchuan Water Resources Bureau for clear responsibility allocation for safety management of auxiliary dam; Reservoir risk elimination and rehabilitation was inspected and (10) Provision of professional training on observation data analysis accepted by Guangxi Autonomous Region Water Resources for dam safety monitoring staff; Department in 2015. The reservoir has gone through extremely Guishi Reservoir heavy flood in 2015 and is under safe operation. Issues include (11) Analysis of observation data of the last 5 years; 1 Dam in Hezhou City unclear responsibility allocated for auxiliary dam management, (12) Development of automatic dam safety monitoring system; lack of observation data processing and analysis capacity by dam (13) Study on extent of impact on facility safety by scouring pit safety monitoring staff, and need for landslide mass treatment at behind overflow dam; and Wugong Mountain. Follow-up action plan is required. (14) Special geo-investigation and design necessary for treatment of Wugong Mountain landslide mass. Completion time: 31 December 2021 Cost estimate: CNY 13 million Technical design of Chayuan Reservoir risk elimination and (3) Restoration/new construction of channel connecting with rehabilitation in 2011 generally meets requirements of applicable discharge culvert; Chayuan Reservoir standards and the construction quality meets the design (4) Adding dam seepage monitoring facilities; 2 Dam in Zhongshan requirements. The reservoir has been under normal operation for 6 (3) Change of existing drainage channel downstream from draining County years. Issues include 3m wide dam crest not in compliance with prism to seepage collection channel and construction of measuring criteria and artificial damage to right retaining wall of discharge weir for seepage observation; culvert channel. Follow-up action plan is required. - 471 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program (4) Increasing the thickness of downstream slope of the dam to widen the dam crest to 4 meters. (5)Improving the flood control emrgency response plan. Completion time: 31 December 2021 Cost estimate: CNY 2.5 million (1) Removing/trimming of weed on downstream slope and downstream draining structure as early as possible; Technical design of Junchong Reservoir risk elimination and (2) Adding dam seepage monitoring facilities; rehabilitation in 2010 generally meets requirements of applicable (3) Change of existing drainage channel next to draining prism to Junchong standards and the construction quality meets the design seepage collection channel for seepage observation; and 3 Reservoir Dam in requirements. The reservoir has been under normal operation for 7 (4) Widening downstream slope of the dam to widen dam crest to 4 Zhongshan County years. Issues include 3m wide dam crest not in compliance with meters. criteria and absence of seepage interception channel next to the (5) Improving the flood control emrgency response plan. draining prism. Follow-up action plan is required. Completion time: 31 December 2021 Cost estimate: CNY 2 million Technical design of Luojiu Reservoir risk elimination and (1) Installation of reservoir water gauge for water level observation; and rehabilitation in 2014 generally meets requirements of applicable Luojiu Reservoir standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities; 4 Dam in Zhongshan requirements. The reservoir has been under normal operation for 3 County years. Issues include absence of reservoir water level observation, (3) Construction of seepage collection channel next to draining and absence of seepage collection channel downstream from the prism and installation of measuring weir for seepage observation; - 472 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program draining prism. Follow-up action plan is required. (4) Improving the flood control emrgency response plan. Completion time: 31 December 2019 Cost estimate: CNY 30,000 (1) Enhancement of daily operation management, and weeding on Technical design of Hongshuiping Reservoir risk elimination and right jetty head; and rehabilitation in 2012 generally meets requirements of applicable Hongshuiping standards and the construction quality met design requirements. (2) Installation of water gauge for reservoir. 5 Reservoir Dam in The reservoir has been under normal operation for 5 years. Issues (3) Improving the flood control emrgency response plan. Fuchuan County include absence of reservoir water level observation, weed Completion time: 31 December 2019 growing at right jetty head, and inadequate facilities. Follow-up Cost estimate: CNY 100,000 action plan is required. (1) Weeding on upstream and downstream slope, restoration of Technical design of Shalongchong Reservoir risk elimination and dam top road as early as possible to restore dam appearance. rehabilitation in 2011 generally meets requirements of applicable Shalongchong standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities; 6 Reservoir Dam in requirements. The reservoir has been under normal operation for 6 (3) Improving the flood control emrgency response plan. Fuchuan County years. Issues include absence of upstream and downstream slope Completion time: 31 December 2019 clean-up and maintenance for a long time, and damage of dam top Cost estimate: CNY 300,000 road. Follow-up action plan is required. Technical design of Shidong Reservoir risk elimination and (3) Improving seepage collection channel next to the draining prism Shidong Reservoir rehabilitation in 2010 generally meets requirements of applicable for seepage observation; 7 Dam in Pinggui standards and the construction quality meets the design (4) Provision of professional training on use of dam safety District requirements. The reservoir has been under normal operation for 7 monitoring equipment and preliminary information processing; years. Issues include absence of seepage collection channel - 473 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program downstream from the draining prism, absence of monitoring and capacity of reservoir staff, and absence of emergency response (3) Improving flood control emergency response program. program. Follow-up action plan is required. Completion time: 31 December 2019 Cost estimate: CNY 200,000 (1) Construction of seepage collection channel next to draining Technical design of Huashan Reservoir risk elimination and prism for seepage observation; rehabilitation in 2010 generally meets requirements of applicable (2) Adding dam seepage monitoring facilities; standards and the construction quality meets the design (3) Widening downstream slope of the main and auxiliary dam to Huashan Reservoir requirements. The reservoir has been under normal operation for 7 widen dam crest to 4 meters to meet criteria requirement; 8 Dam in Pinggui years. Issues include dam crest width of around 3.5 m that is not in (4) Arrangement of reservoir staff in non-flood season and making District compliance with criteria, absence of seepage collection channel sure reservoir staff on duty throughout the year; and downstream from the draining prism, absence of reservoir staff on (5) Improving flood control emergency response program. duty in non-rainy season, and absence of emergency response program. Follow-up action plan is required. Completion time: 31 December 2021 Cost estimate:CNY 3 million (1) Construction of seepage collection channel next to slope Technical design of Pangu Reservoir risk elimination and draining structure for seepage observation; rehabilitation in 2010 generally meets requirements of applicable Pangu Reservoir standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities ; 9 Dam in Pinggui requirements. The reservoir has been under normal operation for 7 (3) Improving flood control emergency response program; and District years. Issues include dam top width of 3.5 m that is not in (4) Widening downstream slope of the dam to widen dam crest to 4 compliance with criteria, absence of seepage collection channel meters. downstream from the draining prism, and absence of emergency Completion time: 31 December 2021 - 474 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program response program. Follow-up action plan is required. Cost estimate: CNY 2 million (6) Installation of reservoir water gauge for water level observation; construction of seepage collection channel next to draining Technical design of Dachong Reservoir risk elimination and prism for observation of dam seepage; rehabilitation in 2012 generally meets requirements of applicable (7) Adding dam seepage monitoring facilities ; standards and the construction quality meets the design Dachong Reservoir requirements. The reservoir has been under normal operation for 5 (8) Extension of new discharge culvert pipe, and new construction 10 Dam in Pinggui years. Issues include absence of reservoir water level observation, of diversion channel; District absence of seepage collection channel downstream from the (9) Improving flood control emergency response program; and draining prism, absence of reservoir staff on duty in non-rainy (10) Arrangement of reservoir staff in non-flood season and making season, and absence of emergency response program. Follow-up sure reservoir staff on duty throughout the year. action plan is required. Completion time: 31 December 2019 Cost estimate: CNY 400,000 Technical design of Dayao Reservoir risk elimination and (1) Installation of reservoir water gauge for water level observation; rehabilitation in 2011 generally meets requirements of applicable (2) Adding dam seepage monitoring facilities ; standards and the construction quality meets the design Dayao Reservoir (3) Arrangement of reservoir staff in non-flood season and making requirements. The reservoir has been under normal operation for 6 11 Dam in Pinggui sure reservoir staff on duty throughout the year; and years. Issues include absence of reservoir water level observation, District (4) Improving flood control emergency response program. absence of reservoir staff on duty in non-rainy season, and absence of emergency response program. Follow-up action plan is Completion time: 31 December 2019 required. Cost estimate: CNY 300,000 Technical design of Guishan Reservoir risk elimination and Guishan Reservoir (1) Installation of reservoir water gauge for water level observation; 12 rehabilitation in 2010 generally meets requirements of applicable Dam in Pinggui (2) Adding dam seepage monitoring facilities ; standards and the construction quality meets the design - 475 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program District requirements. The reservoir has been under normal operation for 7 (3) Weeding within 20 m of the dam, improvement of seepage years. Issues include absence of reservoir water level observation, collection channel next to draining prism for observation of dam absence of seepage collection channel downstream from the seepage; draining prism, absence of reservoir staff on duty in non-rainy (4) Arrangement of reservoir staff in non-flood season and making season, and absence of emergency response program. Follow-up sure reservoir staff on duty throughout the year; and action plan is required. (5) Improving flood control emergency response program. Completion time: 31 December 2019 Cost estimate: CNY 300,000 (1) Installation of reservoir water gauge for water level observation; Technical design of Changtang Reservoir risk elimination and (2) Adding dam seepage monitoring facilities rehabilitation in 2011 generally meets requirements of applicable standards and the construction quality meets the design (3) Improvement of seepage collection channel next to draining Changtang requirements. The reservoir has been under normal operation for 6 prism for observation of dam seepage; 13 Reservoir Dam in years. Issues include absence of reservoir water level observation, (3) Arrangement of reservoir staff in non-flood season and making Pinggui District absence of seepage collection channel downstream from the sure reservoir staff on duty throughout the year; and draining prism, absence of reservoir staff on duty in non-rainy (4) Improving flood control emergency response program. season, and absence of emergency response program. Follow-up Completion time: 31 December 2019 action plan is required. Cost estimate: CNY 350,000 Technical design of Luoxi Reservoir risk elimination and (1) Change of drainage ditch next to draining prism of main dam to Luoxi Reservoir rehabilitation in 2011 generally meets requirements of applicable seepage collection channel; installation of long culvert pipe linking 14 Dam in Pinggui standards and the construction quality meets the design auxiliary dam discharge culvert pipe and channel, and change of District requirements. The reservoir has been under normal operation for 6 existing drainage ditch to seepage collection channel; observation years. Issues include absence of seepage collection channel of main and auxiliary dam seepage. - 476 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program downstream from the draining prism, absence of reservoir staff on (2) Adding dam seepage monitoring facilities ; duty in non-rainy season, and absence of emergency response (3) Arrangement of reservoir staff in non-flood season and making program. Follow-up action plan is required. sure reservoir staff on duty throughout the year. (4) Improving flood control emergency response program; Completion time: 31 December 2019 Cost estimate: CNY 400,000 Dam safety assessment was done by design institute hired by Pinggui District Water Resources Bureau in February 2014. Design for reservoir risk elimination and rehabilitation was Huimiandu approved by Guangxi Autonomous Region Water Resource 15 Reservoir Dam in Bureau in November 2015. Construction commenced in August Pinggui District 2016 and is in progress. Technical design meets requirements of applicable standard, and construction quality will be assessed once finished. Currently no follow-up actions are required. (1) Change of drainage channel to seepage collection channel for Technical design of Guangming Reservoir risk elimination and seepage observation of the dam; rehabilitation in 2013 generally meets requirements of applicable Guangming standards and the construction quality meets the design (2) Adding dam seepage monitoring facilities ; 16 Reservoir Dam in requirements. The reservoir has been under normal operation for 4 (3) Confirmation of dam top elevation and dam crest width; and Pinggui District years. Issues include absence of seepage collection channel next (4) Improving flood control emergency response program; to draining prism, inaccuracy of dam top elevation, and absence of Completion time: 31 December 2019 emergency response program. Follow-up action plan is required. Cost estimate: CNY 300,000 - 477 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program (1) Adding dam seepage monitoring facilities ; Technical design of Guanyawo Reservoir risk elimination and (2) Arrangement of reservoir staff in non-flood season and making rehabilitation in 2012 generally meets requirements of applicable sure reservoir staff on duty throughout the year. standards and the construction quality meets the design Guanyawo (2) Construction of seepage collection channel for seepage requirements. The reservoir has been under normal operation for 5 17 Reservoir Dam in observation of the dam and the closed old culvert; years. Issues include absence of seepage collection channel next Pinggui District (3) Improving flood control emergency response program; to draining prism, absence of reservoir staff on duty in non-rainy Completion time: 31 December 2019 season, and absence of emergency response program. Follow-up action plan is required. Cost estimate: CNY 300,000 (1) Installation of reservoir water gauge for water level observation; (2) Adding dam seepage monitoring facilities ; Technical design of Zhemu Reservoir risk elimination and (3) Change of drainage ditch downstream from the draining prism to rehabilitation in 2012 generally meets requirements of applicable seepage collection channel, and installation of measuring weir for standards and the construction quality meets the design dam seepage observation; Zhemu Reservoir requirements. The reservoir has been under normal operation for 5 (4) Improving flood control emergency response program; 18 Dam in Pinggui years. Issues include absence of reservoir water level observation, (5) Widening downstream slope of the dam to widen dam crest to 4 District absence of seepage collection channel next to draining prism, meters; and absence of reservoir staff on duty in non-rainy season, and absence of emergency response program. Follow-up action plan is (6) Arrangement of reservoir staff in non-flood season and making required. sure reservoir staff on duty throughout the year. Completion time: 31 December 2021 Cost estimate: CNY 1.5 million 19 River Dam of Dam safety specialists have been employed for safety assessment (4) A dam and workshop safety monitoring system will be constructed in - 478 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program Xiadao Power of hub facility, and safety assessment report is expected to be accordance with the requirements of the “Technical Spe cifications on Station in Hezhou available by the end of October. Safety Monitoring of Concrete Damsd (DL/T5178-2003) and in City association with the actual situations of the Project so as to monitor the gate dam and horizontal and vertical displacement, inclination, pier joint and crack opening and closing degree and foundation uplift pressure, leakage. (5) A separate circuit breaker and protection circuit will be added to ensure the safe operation of booster station. (6) The left gate of the overflow gate dam will be repaired to assure safe opratoin of the barrage dam. Pier joint and crack opening and closing degree Uplift pressure of foundation Leakage volume Completion time: 31 December 2021; Cost estimate: CNY 500,000 River Dam of Fanglin Dam safety specialists have been employed for safety assessment Hydropower 20 of hub facility, and safety assessment report is expected to be Station/Hejiang available by the end of October. Power Station in Hezhou City River Dam of Dam safety specialists have been employed for safety assessment 21 Huangshi Power of hub facility, and safety assessment report is expected to be - 479 - Table 11-15 Dam Safety Action Plan and Rehabilitation Program SN Reservoir/Dam Requirement for Follow-up Actions Rehabilitation Program Station in Hezhou available by the end of October. City - 480 - 11.3 Environmental Monitoring Plan 11.3.1 Objectives of Environmental Monitoring Environmental monitoring covers the construction stage and the operation stage of the Project and aims to acquire full and timely information on the pollution conditions of the proposed project, the degree of changes made and scope of impacts brought by the project construction to and on the environment quality of the project area as well as the status of environmental quality in the operation stage so as to give timely feedbacks to the competent authority and provide a scientific basis for the environment management work of the Project. 11.3.2 Environment Monitoring Agency Environmental monitoring in the construction stage and the operation stage is undertaken by a qualified monitoring agency entrusted by and on behalf of the project contractor or operator. The undertaking agency should be certified in the national environmental quality certification program, have complete equipment and strong technical competence and are able to carry out the respective environmental monitoring task in a satisfactory manner. Sensitive and concerned spots that probably involve significant pollution as shown in the prediction results of environment impacts are chosen as the monitoring spots to follow up with the pollution status of the monitored items in the construction stage and the operation stage. Noise, ambient air and surface water that involve significant environmental impacts are chosen as the monitoring contents. The monitoring factors are determined based on the pollution characteristic factors of the Project. The monitoring and analysis method for the respective items specified in the Technical Specifications on Environmental Monitoring promulgated by MoEP is chosen and the national standards confirmed in the EIA of each subproject are adopted as the assessment standard. 11.3.3 Environmental Monitoring Plan and Budget The environmental monitoring plan and budget for the construction stage and operation stage of each subproject is shown in Table 11-13 in detail. The requirements of the monitoring plan of the linked projects are shown in Table 11-14 while the water and soil conservation monitoring program is shown in Table 11-15. - 481 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) Shangsong A-1He River Integrated Village, Hezhou Rehabilitation (Huangshi Institute, Hezhou 2400 2.88 Hydropower Station - Experimental Guangming Bridge) Middle School, Laozengwu 2 periods / A-2He River Integrated year, 2 days Rehabilitation (Guangming Xialiang Village 600 0.72 / period,1 Bridge - Lingfeng Bridge) Construction stage time / day. A-3 He River Integrated The Ambient air Rehabilitation (Lingfeng Diandengzhai, “Ambient air quality aforesaid Qualified Bridge – Xiadao Xiadao Primary 1200 1.44 Construction standard� TSP School frequency monitoring Hydropower Station) contractor (GB3095-2012); should be agency Class II A-4 East Trunk Canal followed Integrated Rehabilitation throughout Xianghuadao the 600 0.72 and Mawei River Connection construction A-5 Xiadao Hydropower stage. Station Integrated Jichitan 600 0.72 Rehabilitation Residential B-1 Huangansi Drainage building at Xiyue 600 0.72 Canal Pump Station Street B-2 Shizigang Drainage Dormitory 600 0.72 - 482 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) Canal Pump Station building of Transportation Bureau Lining Village, B-3 Lining River Integrated Yingshi Primary 1200 1.44 Rehabilitation School B-4 Changlong River Changlong 600 0.72 Integrated Rehabilitation Village B-5 Huangtian Branch Pinggui No. 3 Canal Integrated Middle School, 1200 1.44 Rehabilitation Huangtian Town B-6 Guposhan Drainage Canal Integrated Baijiazhai 600 0.72 Rehabilitation B-7 East No. 5 Branch Canal Integrated Xiwanzhen 600 0.72 Rehabilitation Residential C-1 Huangansi Drainage buildings at Canal Integrated 1200 1.44 Badaxi Road and Rehabilitation Youxing Street Residential C-2 Shizigang Drainage buildings at Canal Integrated 1200 1.44 Wanquan Street Rehabilitation and Yinhe Street C-3 Jiangnan WWTP Residential 600 0.72 associated pipeline buildings at - 483 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) networks and road Niupailan improvement Residential buildings at C-1 Huangansi Drainage Badaxi Road, 4 periods / Canal Integrated Youxing Street year, 1 day / 7920 3.17 Rehabilitation and Xiyue Street period,4 Design hygiene along Huangansi times / day, standard for industrial Drainage Canal The enterprises (TJ 36-79); H2S, NH3, Residential aforesaid Qualified maximum allowable Construction odor buildings at frequency monitoring concentration for contractor concentration Wanquan Street, should be agency residential areas; Yinhe Street and followed “Odor Pollutant C-2 Shizigang Drainage throughout Emission Standard� Xingguang Canal Integrated the 10560 4.22 (GB14554-93) Street and Rehabilitation dredging Jiangbeizhong Road along stage. Shizigang Drainage Canal Cross sections at 2 periods / the starting and year, 2 days �Surface Water ending points of / period,1 Environmental Quality COD, BOD5, A-4 East Trunk Canal East Trunk time / day Qualified Standard� SS, Integrated Rehabilitation Canal The Construction 3000 3.6 monitoring (GB3838-2002); petroleum, and Mawei River Rehabilitation aforesaid contractor agency Class Ⅲ for Mawei NH3-N, TP Connection Section, cross frequency River and Class IV for section 500m should be East Trunk Canal ahead of the followed confluence point throughout - 484 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) of Mawei River the and East Trunk construction Canal stage. He River Xiadao A-5 Xiadao Hydropower Hydropower Station Integrated 1000 1.2 Station cross Rehabilitation section “Surface Water He River Fanglin Environmental Quality A-6 Fanglin Hydropower Hydropower Standard� Station Integrated 1000 1.2 Station cross (GB3838-2002); Rehabilitation section Class Ⅲ He River A-7 Huangshi Huangshi Hydropower Station Hydropower 1000 1.2 Integrated Rehabilitation Station cross section Wastewater discharge outlets A-8 He River (Huangshi GB of sediment Hydropower Station - 8978-1996 �Integrated dewatering sites 1000 1.2 Xiadao Hydropower wastewater discharge at Fanglin Bridge Station) Dredging Works standard� Class I and Lingfeng Bridge Lining River “Surface Water B-3 Lining River Rehabilitation Environmental Quality 2000 2.4 Rehabilitation Section starting Standard� and ending cross (GB3838-2002); - 485 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) sections Class Ⅳ Changlong River Rehabilitation B-4 Changlong River Section starting 2000 2.4 Rehabilitation and ending cross sections Huangtian Branch Canal B-5 Huangtian Branch Rehabilitation 2000 2.4 Canal Rehabilitation Section starting and ending cross sections Guposhan Drainage Canal B-6 Guposhan Drainage Rehabilitation 2000 2.4 Canal Rehabilitation Section starting and ending cross sections East No. 5 Branch Canal B-7 East No. 5 Branch Rehabilitation 2000 2.4 Canal Rehabilitation Section starting and ending cross sections Huangansi C-1 Huangansi Drainage Drainage Canal 2000 2.4 Canal Rehabilitation Rehabilitation Section starting - 486 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) and ending cross sections Shizigang Drainage Canal C-2 Shizigang Drainage Rehabilitation 2000 2.4 Canal Rehabilitation Section starting and ending cross sections Shangsong A-1 He River Integrated Village, Hezhou Rehabilitation (Huangshi Institute, Hezhou 2 periods / 960 0.29 Hydropower Station - Experimental year, 2 days Guangming Bridge) Middle School, / period,2 Laozengwu times / A-2 He River Integrated day(one Rehabilitation (Guangming Xialiang Village time each 240 0.58 Bridge - Lingfeng Bridge) day and “Sound environment night) Qualified Noise A-3 He River Integrated Construction quality standard� dB(A) Diandengzhai, The monitoring Rehabilitation (Lingfeng contractor (GB3096-2008); Xiadao Primary aforesaid 480 0.29 agency Bridge – Xiadao Class II School frequency Hydropower Station) should be A-4 East Trunk Canal followed Integrated Rehabilitation throughout Xianghuadao 240 0.29 and Mawei River the Connection construction A-5 Xiadao Hydropower stage. Station Integrated Jichitan 240 0.29 Rehabilitation - 487 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) Residential B-1 Huangansi Drainage building at Xiyue 240 0.29 Canal Pump Station Street Dormitory B-2 Shizigang Drainage building of 240 0.58 Canal Pump Station Transportation Bureau Lining Village, B-3 Lining River Integrated Yingshi Primary 480 0.29 Rehabilitation School B-4 Changlong River Changlong 240 0.58 Integrated Rehabilitation Village B-5 Huangtian Branch Pinggui No. 3 Canal Integrated Middle School, 480 0.29 Rehabilitation Huangtian Town B-6 Guposhan Drainage Canal Integrated Baijiazhai 240 0.29 Rehabilitation B-7 East No. 5 Branch Canal Integrated Xiwan Town 240 0.58 Rehabilitation Residential C-1 Huangansi Drainage buildings at Canal Integrated Badaxi Road and 480 0.58 Rehabilitation Youxingxiang Street C-2 Shizigang Drainage Residential 480 0.29 - 488 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) Canal Integrated buildings at Rehabilitation Wanquan Street and Yinhe Street C-3 Jiangnan WWTP Residential associated pipelines and building at 240 0.29 road improvement works Niupailan A-4 East Trunk Canal Integrated Rehabilitation and Mawei River Connection Sludge dewatering cake A-8 He River (Huangshi Hydropower Station – Once a Guangming Bridge) week during Dredging Qualified The moisture content Moisture Sludge dredging; 5 Construction 20 1.0 monitoring should be lower than content dewatering site samples contractor agency 50%. per B-5 Huangtian Branch monitoring Canal Rehabilitation B-6 Guposhan Drainage Canal Integrated Rehabilitation - 489 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) C-1 Huangansi Drainage Canal Integrated Rehabilitation C-2 Shizigang Drainage Canal Integrated Rehabilitation 4 periods / year, “Pollutant Discharge Exhaust gas 1 day / Upwind and H2S, NH3, C-3 Jiangnan WWTP period,4 Qualified Standards for Municipal downwind of the Project odor associated pipelines and times / day; 5280 10.56 monitoring Wastewater Treatment boundary of Owner concentration road improvement works until project agency Plants� Jiangnan WWTP account (GB18918-2002) closure Operation stage 200m ahead of C-1 Huangansi Drainage the confluence of Canal Integrated Huangansi 4 periods / 1000 2 Rehabilitation Drainage Canal year, “Surface Water 2 days Surface water into He River / period,1 Environmental Quality COD, BOD5, Standard� qualified SS, 200m ahead of time / day; Project (GB3838-2002); monitoring petroleum, C-2 Shizigang Drainage the confluence of until project Owner Class Ⅳ agency NH3-N, TP Canal Integrated Shizigang account 1000 2 Rehabilitation Drainage Canal closure into He River C-3 Jiangnan WWTP 500m upstream “Surface Water 2000 4 associated pipelines and and downstream Environmental Quality - 490 - Table 11-13 Environment Monitoring Plan Total Cost per Monitoring Monitoring Monitoring cost Monitoring Client Applicable standards Period Subproject Monitoring site monitoring object item frequency (CNY agency agency and specifications (CNY) 10000) road improvement works of the discharge Standard� outlet of (GB3838-2002); Jiangnan WWTP Class III into He River 4 periods / “Pollutant Discharge year, 2 days COD, BOD5, Standards for Municipal C-3 Jiangnan WWTP Discharge outlet / period,1 SS, Wastewater Treatment Wastewater associated pipelines and of Jiangnan time / day; 1000 2 petroleum, Plants� road improvement works WWTP until project NH3-N, TP (GB18918-2002); account Class 1A closure 4 periods / year, 2 days / period,2 On the eastern, “Ambient Noise times / southern, Emission Standard on Site C-3 Jiangnan WWTP day(one Qualified western and Project the Boundary of boundary dB(A) associated pipelines and time each 960 1.92 monitoring northern Owner Industrial Enterprises� noise road improvement works day and agency boundaries of (GB12348-2008); night); until Jiangnan WWTP Class II project account closure - 491 - Table 11-14 Environment monitoring plan of linked projects Linked Monitoring Monitoring Monitoring Client Monitoring item Monitoring site Applicable standard projects element frequency agency agency COD, NH3-N pH value, COD, BOD-5, NH3-N, SS, animal and vegetable oils, Surveillance petroleum, anionic surfactants, monitoring, Qualified total nitrogen, total phosphorus, Discharge outlet of Hezhou 2 periods / year, monitoring chrome, fecal coliform, total WWTP “Pollutant Discharge Wastewater 1 day / period,4 agency mercury, alkyl mercury, total Standards for Municipal times / day cadmium, total chromium, Wastewater Treatment hexavalent chromium, total Plants�(GB18918-2002); arsenic, total lead Class 1A Hezhou WWTP Online monitoring comparison, Qualified Discharge outlet of Hezhou Project COD, NH3-N 4 periods / year, monitoring WWTP Owner 1 day / period,3 agency times / day “Pollutant Discharge Exhaust Upwind and downwind of 2 periods / year, Qualified Standards for Municipal hydrogen sulfide, ammonia, odor gas concentration the site boundary of 2 days / period,4 monitoring Wastewater Treatment Hezhou WWTP times / day agency Plants�(GB18918-2002) 2 periods / year, On the eastern, southern, “Ambient Noise Emission boundary 2 days / period,2 Qualified noise western and northern Standard on the Boundary Site dB(A) times / day(one monitoring of Industrial Enterprises� boundaries of Hezhou time each day agency WWTP (GB12348-2008) ; Class II and night) - 492 - Table 11-14 Environment monitoring plan of linked projects Linked Monitoring Monitoring Monitoring Client Monitoring item Monitoring site Applicable standard projects element frequency agency agency Upwind of the site of Exhaust Hezhou Sludge Harmless 2 periods / year, Qualified “Odor Pollutant Emission hydrogen sulfide, ammonia, odor gas Treatment Project, outlet of 2 days / period,4 monitoring Standard� concentration the exhaust pipe of the times / day agency (GB14554-1993) ; Class II deodorization workshop Outlet of self-built Wastewa 2 periods / year, Qualified “Integrated wastewater Hezhou Sludge Harmless Treatment wastewater treatment discharge standard� ter COD, BOD-5, NH3-N, SS system of Hezhou Sludge 2 days / period,4 monitoring times / day agency (GB8987-1996); Class I Harmless Treatment Project On the eastern, southern, 2 periods / year, “Ambient Noise Emission boundary western and northern 2 days / period,2 Qualified noise Standard on the Boundary Site dB(A) boundaries of Hezhou times / day(one monitoring Project of Industrial Enterprises� Sludge Harmless Treatment time each day agency Owner (GB12348-2008) ; Class II Project and night) pH value, turbidity, 1 observation well in and 2 2 periods / year, Permanganate index, nitrate “Ground water quality Ground observation wells 2 days / period,1 Qualified water nitrogen, nitrite nitrogen, NH3-N, downstream the site of time / day, for a monitoring standard� (GB/T 14848-93) ; chloride, lead, mercury, cadmium, Hezhou Sludge Harmless monitoring period agency Class III hexavalent chromium, arsenic, Treatment Project of 2 years total coliform, total bacteria Farmland downstream of Cadmium, mercury, arsenic, the flow direction of ground Qualified “Soil Environment Quality 1 period / year,1 Soil copper, lead, chromium, zinc, water inside the site and monitoring Standard�(GB1518-1995) ; day / period nickel area of Hezhou Sludge agency Class II Harmless Treatment Project Domestic Exhaust “Odor Pollutant Emission Hezhou Upwind and downwind of 2 periods / year, Qualified Landfill Waste Solid Total SS, hydrogen sulfide, Project gas Hezhou Domestic Solid 2 days / period,4 monitoring Standard� ammonia, odor concentration Owner Waste Landfill times / day agency (GB14554-1993) ; Class II - 493 - Table 11-14 Environment monitoring plan of linked projects Linked Monitoring Monitoring Monitoring Client Monitoring item Monitoring site Applicable standard projects element frequency agency agency pH value, chrome, COD, BOD-5, Wastewater SS, NH3-N, total phosphorus, total “Standard for Pollution 2 periods / year, Qualified nitrogen, fecal coliform, total Outlet of leachate treatment Control on the Landfill Site mercury, total cadmium, total station 2 days / period,4 monitoring of Municipal Solid Waste� times / day agency chromium, hexavalent chromium, (GB16889-2008) ; Class II total arsenic, total lead On the eastern, southern, 2 periods / year, “Ambient Noise Emission boundary western and northern 2 days / period,2 Qualified noise Standard on the Boundary Site dB(A) boundaries of Hezhou times / day(one monitoring of Industrial Enterprises� Domestic Solid Waste time each day agency (GB12348-2008) ; Class II Landfill and night) pH value, Total hardness, permanganate index, NH3-N, Groundwater nitrate, nitrite, sulfate, chloride, “Ground water quality 5 upstream and 2 periods / year, Qualified volatile phenols, cyanide, fluoride, standard� downstream monitoring 2 days / period,1 monitoring arsenic, mercury, hexavalent (GB/T14848-1993) ; Class wells of ground water time / day agency chromium, copper, zinc, lead , III Cadmium, iron, manganese, total coliform The monitoring plan required in the EIA of the linked projects should be incorporated into this ESMP and its monitoring report should be submitted on a periodical basis as one of the reports due under the Project. - 494 - Table 11-15 Water and soil conservation monitoring plan Monitoring frequency Total Monitoring cost Monitoring Client Period Monitoring contents and monitoring methods area (CNY agency agency 10000) (1) Pre-construction soil erosion status and background Monitoring period: value; The monitoring period (2) Using survey method and remote sensing method to starts in June 2018 in monitor changes of terrain and landform, disturbance the construction of surface and vegetation and number of damaged preparation stage and Flood risk water and soil conservation facilities; ends in December 2024 control Qualified (3) Using survey method to monitor volume of earthwork in the year of design Construction subproject 15 monitoring excavation and fill and transportation under the level. contractor area agency Project; Monitoring frequency: (4) Using sedimentation tank method to monitor volume Stockpiling volume of of soil erosion; the temporary Construction stage (5) Using survey method to monitor status of protection stockpiling sites in use and effectiveness of operation of the water and soil and the implementation conservation measures. status of the water and (1) Pre-construction soil erosion status and background soil conservation value; measures in effect shall (2) Using survey method and remote sensing method to be monitored and monitor changes of terrain and landform, disturbance recorded at least once of surface and vegetation and number of damaged every 10 days; area of Urban water and soil conservation facilities; disturbed surface, drainage Qualified (3) Using survey method to monitor volume of earthwork retaining and fencing Construction Rehabilitation 24 monitoring excavation and fill and transportation under the effect of water and soil contractor subproject agency Project; conservation measures area (4) Using sedimentation tank method to monitor volume shall be monitored and of soil erosion; recorded at least once (5) Using survey method to monitor status of protection every month; Since and effectiveness of operation of the water and soil rainfall in the Project conservation measures. area mainly occurs in Water quality (1) Pre-construction soil erosion status and background the months of April to 10 Qualified Construction - 495 - Table 11-15 Water and soil conservation monitoring plan Monitoring frequency Total Monitoring cost Monitoring Client Period Monitoring contents and monitoring methods area (CNY agency agency 10000) improvement value; September, routine monitoring contractor subproject (2) Using survey method and remote sensing method to monitoring should be agency area monitor changes of terrain and landform, disturbance conducted in these of surface and vegetation and number of damaged months at the water and soil conservation facilities; monitoring frequency (3) Using survey method to monitor volume of earthwork indicated in the excavation and fill and transportation under the previous table. In the Project; months of October to (4) Using sedimentation tank method to monitor volume March the next year, no of soil erosion; fixed site monitoring (5) Using survey method to monitor status of protection shall be conducted and and effectiveness of operation of the water and soil only site inspections will conservation measures, and survival rate, coverage be arranged. and growth status of trees and grass for water and soil The other monitoring conservation. activities shall be (1) Using survey method and remote sensing method to conducted once every 3 monitor changes of terrain and landform, and the months. height, slope length and land occupation of stockpiles In the event of any rain storms or heavy winds, Qualified Temporary of the temporary stockpiling sites; Construction 1 to 2 additional 7 monitoring works area (2) Using sedimentation tank method to monitor volume contractor monitoring should be agency of soil loss; (3) Using survey method to monitor the implementation arranged in time. status and benefits of temporary measures. - 496 - 11.4 Capacity Development and Training 11.4.1 Capacity Development and Training Requirements The key objects of environmental capacity development are the environment managers and construction supervision engineers, training for whom is one of the key component of technical supports under the Project. In order to assure smooth and effective implementation of the ESMP, it is necessary to provide training on ESMP and other relevant knowledge and skills to the staff of the Project Owner / EA, the operator, the contractor, the supervision engineer, the local PMOs and other stakeholders and also provide different training to staff on different job positions. Training on social issues should also be organized for public subject to social impacts from land acquisition and resettlement, etc. 11.4.2 Contents and Cost Estimate of Capacity Development and Training (1) Environment Managers and Construction Supervision Engineer The training will be organized by the PMO and conducted by the Environment Technology Specialist one year before the implementation of the Project for the full-time environment management personnel of the PMO, the full-time environment management coordinators of the subprojects and the construction supervision engineers. (2) Contractor and Construction Workers The training will be organized by the PMO or the subproject contractors in the project area prior to the implementation of the Project and may be specifically implemented by the Environment Management Specialist or trained full-time environment management staff of the enterprises. (3) Operator The training will be organized by the PMO or the Employer in the project area before the Project is put into operation and may be specifically implemented by the Environment Management Specialist or trained full-time environment management staff of the enterprises. (4) Groups involved in the LAR process The training will be organized by the PMO or the Employer in the project area before the LAR process comences and may be specifically implemented by the PMO or the Social Specialist employed by the PMO. (5) Vulnerable groups such as women, children and poor households The training will be organized by the PMO or the Employer in the project area before the Project is put into operation and may be specifically implemented by the PMO or the Social Specialist employed by the PMO. Details of the contents, trainees, time table and estimated budget of the training are shown in Table 11-1 and Table 11-2. . - 497 - Table 11-14 Sample Training Schedule for Environmental Training Training No. of Training Total cost Supervision Subproject Training objects Training time IA stage trainees duration (*CNY10000) Agency 1. He River Flood Risk Resilience Improvement Subproject Full-time environment Main Prior to management personnel, Watercourse implementation PMO and its Construction full-time environment Widening and 3 3 days of the 0.6 Environment World Bank stage management coordinator, Flood Discharge construction Specialist construction supervision A-1 – A-3 plan engineer Full-time environment Prior to management personnel, Trunk Canal implementation PMO and its Construction full-time environment Flood Diversion 3 3 days of the 0.6 Environment World Bank stage management coordinator, A-4 construction Specialist construction supervision plan engineer Full-time environment Prior to management personnel, implementation PMO and its Water Construction full-time environment 9 3 days of the 1.35 Environment World Bank Conservancy stage management coordinator, construction Specialist Infrastructure construction supervision plan Improvement engineer A-5 – A-7 Prior to official PMO and its Operation Operation agency 3 2 days operation of 0.3 Environment World Bank stage the Project Specialist Full-time environment Prior to management personnel, implementation PMO and its Dredging Works Construction full-time environment 9 3 days of the 1.35 Environment World Bank A-8 stage management coordinator, construction Specialist construction supervision plan engineer 2. Urban Drainage and Sewage Management Subproject - 498 - Table 11-14 Sample Training Schedule for Environmental Training Training No. of Training Total cost Supervision Subproject Training objects Training time IA stage trainees duration (*CNY10000) Agency Full-time environment Prior to management personnel, implementation PMO and its Water Construction full-time environment 3 3 days of the 0.6 Environment World Bank Conservancy stage management coordinator, construction Specialist Infrastructure construction supervision plan Development engineer B-1 – B-2 Prior to official PMO and its Operation Operation agency 3 2 days operation of 0.3 Environment World Bank stage the Project Specialist Full-time environment Prior to management personnel, River-lake implementation PMO and its Construction full-time environment Connection 24 3 days of the 3.6 Environment World Bank stage management coordinator, B-3 – B-9 construction Specialist construction supervision plan engineer Full-time environment Huangansi Prior to management personnel, Drainage Canal implementation PMO and its Construction full-time environment Integrated 6 3 days of the 0.6 Environment World Bank stage management coordinator, Rehabilitation construction Specialist construction supervision C-1 plan engineer Full-time environment Shizigang Prior to management personnel, Drainage Canal implementation PMO and its Construction full-time environment Integrated 6 3 days of the 0.6 Environment World Bank stage management coordinator, Rehabilitation construction Specialist construction supervision C-2 plan engineer Drainage System Construction Full-time environment Prior to PMO and its 6 3 days 0.6 World Bank Improvement stage management personnel, implementation Environment - 499 - Table 11-14 Sample Training Schedule for Environmental Training Training No. of Training Total cost Supervision Subproject Training objects Training time IA stage trainees duration (*CNY10000) Agency C-3 full-time environment of the Specialist management coordinator, construction construction supervision plan engineer Prior to official PMO and its Operation Operation agency 3 2 days operation of 0.3 Environment World Bank stage the Project Specialist Full-time environment Prior to Ecological management personnel, implementation PMO and its Landscaping Construction full-time environment 3 3 days of the 0.6 Environment World Bank Improvement stage management coordinator, construction Specialist D-2 construction supervision plan engineer 3. Institutional Capacity Building and Project Management Full-time environment Prior to PMO and its Construction management personnel, Hydrological 2 2 days implementation 0.2 Environment World Bank stage full-time environment Monitoring of the Project Specialist management coordinator Station E-1 Prior to official PMO and its Operation Operation agency 2 2 days operation of 0.2 Environment World Bank stage the Project Specialist Full-time environment Prior to PMO and its Environmental Construction management personnel, 2 2 days implementation 0.2 Environment World Bank Monitoring stage full-time environment of the Project Specialist Station management coordinator Development Prior to official PMO and its E-2 Operation Operation agency 2 2 days operation of 0.2 Environment World Bank stage the Project Specialist - 500 - Table 11-2 Sample Training Schedule for Social Training Number Training Training Total cost Implementation Supervisory Content Trainees of duration time (CNY10000)) body body persons PMO and its social Training on LAR policies Groups affected by LAR 100 1 day Before LAR 3 World Bank specialist Before Knowledge training on water Vulnerable groups such formal PMO and its social environment protection and as women, children in the 50 1 day 2 World Bank operation of specialist urban development project area the Project Before Vulnerable groups such Employment skill training for formal PMO and its social as women and poor 50 3 days 5 World Bank vulnerable groups operation of specialist households the Project - 501 - 11.5 Reporting Mechanism 11.5.1 Information Exchange Environment management requires necessary exchange of information among the PMO, the Project Owner, the Contractor, the Operator and the different departments and jobs in the organization and also requires disclosure of relevant information to the external parties (stakeholders, general public, etc.). Internal information exchange may be implemented in diversified forms, such as meetings, internal briefings, but at least 1 formal meeting must be organized each month. All information exchange should be recorded and archived. External information exchange is implemented on a half-year or one-year basis. For information exchange with the cooperative units, meeting minutes shall be developed and put into archives. 11.5.2 Record Mechanism In order to assure the effective operation of the environment management system, the organization must set up a sound record system and keep records in the following aspects: (1) Laws and regulations; (2) Government permits; (3) Environmental factors and the relevant EIA documents and ESMP reports; (4) Training records; (5) Records of inspections, calibrations and maintenance activities; (6) Monitoring data; (7) Effectiveness of corrective and preventive measures; (8) Information of stakeholders; grievance redress procedure and records of results; In addition, the aforesaid records shall be subject to necessary control, including identification, collection, cataloging, archiving, storage, management, maintenance, inquiry, retention life and disposal of records. 11.5.3 Reporting Mechanism The Contractor, the Operator, the Monitoring Agency, the construction supervision engineer and the PMO shall keep records of project progress, ESMP execution status, environmental monitoring results throughout the implementation of the Project and report in a timely manner to the concerned departments. Monitoring records of the operation status of the solid waste landfills and WWTPs involved in the linked projects and the due diligence study shall also be acquired and collected on a periodical basis. The relevant requirements shall be incorporated into the monitoring plan, which mainly consist of the six aspects as follows: - 502 - (1) The construction supervision engineer of the Project shall keep detailed records of the execution status of the ESMP on a monthly basis and submit the monthly report to the Project Owner and the Municipal PMO in a timely manner. The weekly and monthly reports should include information on the execution status of the environmental protection measures, and the progress and data of environmental monitoring. (2) The Contractor and Operator shall keep detailed records of the progress of the Project and the execution status of the ESMP on a quarterly basis and submit the quarterly report to the PMO in a timely manner, with a copy to Hezhou Municipal EPB. (3) The Monitoring Agency shall submit the monitoring report to the Contractor (Operator) and the construction supervision engineer in a timely manner after the monitoring assignment is carried out. (4) The Contractor and the Operator shall submit the Environmental Monitoring Report of the Project to Hezhou Municipal EPB, Babu District EPB and Hezhou Municipal PMO in a timely manner. Hezhou Municipal PMO shall submit the monthly report, the quarterly report and the yearly report on the progress and effectiveness of the execution of the ESMP of the Project to Hezhou Municipal EPB and the relevant organizations and, when necessary, to the World Bank. (5) In the event of any specific non-compliances in terms of environmental protection, the construction supervision engineer and the PMO shall submit a report to the local competent authority of environmental protection and to the superior levels if necessary. (6) 2 ESMP Execution Reports should be submitted each year to the World Bank. The ESMP Execution Report may include the following contents: a. Project implementation progress, e.g. construction progress and length of sections completed in the dike construction works, He River rehabilitation works, the pavement works and the pipeline works; b. Execution status of the environmental protection measures of the Project; c. Implementation status and key results of environmental monitoring; d. Implementation status of the training program; e. Information of continuous public participation; public complaints and the records of key contents, solution and public satisfaction of such complaints, if any; f. Existing problems and solutions; g. ESMP Execution Plan for the second half of the year. 11.6 Grievance Redress Mechanism The grievance redress mechanism of the Project covers all stages of implementation of the Project, including resettlement, resident disturbance in the construction stage and supervision of the operation stage. - 503 - (1) Public grievances on resettlement: Any problems arising in the resettlement process may be appealed according to Section VIII: Grievance Redress Procedure. (2) Public grievances in the construction period: The Contractor of the Project and the Municipal PMO and Municipal EPB shall follow up with the progress of the Project in a timely manner to learn about inconveniences brought to the local people in the construction of the Project. The construction contractor shall make public the responsible person’s name and contact information for the sake of public supervision and complaint. The Municipal PMO and the Municipal EPB shall set up a special reception window and assign special personnel to collect the public opinions in a timely manner. Public opinion books should be provided so that records are kept of telephone calls or personal visits, including the name and contact information of the callers and visitors, impacts from project implementation and their opinions. Such records shall be archived and reported in a timely manner and questions raised by the public shall be replied within three working days and a solution shall be proposed and implemented within 10 to 15 working days depending on the level of difficulty. The final results of the process of implementation and coordination and resolution shall be added into the Public Opinion Book. In order to better address the inconveniences brought by the construction of the Project to the daily life of local people, the Contractor and the external monitoring agency are required to submit the Public Opinion Book to Hezhou Municipal EPB at the end of each month so that such opinions are handled in time under the supervision of Hezhou Municipal EPB. If the complainant remains dissatisfied with the resolution made the Municipal PMO or EPB, he / she may, upon receipt of such resolutions, file a lawsuit at the local people's court according to the Civil Procedure Law of the People's Republic of China. (3) Operation stage supervision: The public may raise any questions in the operation stage directly to the Municipal PMO or Hezhou Municipal EPB (EP complaint hotline: 12369), which shall record, study and discuss and respond to such questions within 3 working days and propose and implement a solution within 10 to 15 working days depending on the level of difficulty. If the complainant remains dissatisfied with the resolution made the Municipal PMO or EPB, he / she may, upon receipt of such resolutions, file a lawsuit at the local people's court according to the Civil Procedure Law of the People's Republic of China. The aforesaid channels of grievance redress shall be made public via meetings or by other means to enable the public to be fully aware of their rights to complain. In addition, the public media shall be utilized for extensive advertisement. The grievance redress institution shall handle the complaints free of charge and all expenses incurred there from shall be disbursed as a part of the contingency fee by the Municipal PMO. - 504 - 11.7 Investment Estimation for Environmental Protection Table 11-15 shows the estimated investment required for the aforesaid additional environmental measures needed in the design stage, construction stage and operation stage of the Project. Table 11-15: Investment Estimation for Environmental Protection of the Project Estimated investment SN Stage Cost description (CNY10000) 1 Design stage EIA 200 Subtotal 200 Additional environmental protection 2 141 measures Additional water and soil conservation 3 1657.67 measures 4 Environment monitoring 56 Construction stage Water and soil conservation monitoring and 5 91 supervision 6 Implementation of Dam Safety Action Plan 2655 7 Operation of external monitoring agency 24 8 Staff training in the construction stage 11 Training on LAR policies 3 Subtotal 4638.67 Final acceptance of environmental 9 80 protection 10 Operation Environment monitoring 23 stage 11 Operation of external monitoring agency 20 12 Staff training in the operation stage 2 Knowledge training on water environment 3 protection and city development Training on employment skills of vulnerable 5 groups Subtotal 133 Total 4970.67 - 505 - - 506 - 12. EIA Conclusions and Recommendations The following conclusions may be drawn from the comprehensive environmental impact assessment of the Project: (1) The Project aims to implement integrated improvement of water environment and construction of urban infrastructure under the guidelines of development, livelihood and innovation and following the standards of “green water service, eco-friendly water service and storm and flood safety�. The Project will be helpful to safeguarding regional flood protection and waterlogging drainage, improving regional water environment and building high-standard and modernized urban infrastructure and public facilities; it will provide powerful support and assurance to the sustainable economic development of Hezhou Municipality to promote the level of sustainable urban development and realize the integration of reform and innovation. Identified from the perspectives of task demand and target realization, the key design elements of the Project comprise of five engineering systems of flood risk control, urban drainage improvement, water environment improvement, ecological landscape improvement and technical assistance and management. Flood risk control --- Through improvement of the flood discharge capacity of the mainstream and tributaries, flood risks will be prevented and put under control by means of assured discharge of flood. The flood control status of the main watercourse of He River and its urban tributaries will be analyzed and an enclosed flood control system will be constructed to bring the flood control capacity of the urban area of Hezhou to the respective standard. Urban drainage improvement --- Through improvement of the storage capacity, the stormwater retention capacity will be increased for the purpose of reducing the pumping and drainage volume. The terrain and topographical condition of the urban area and the existing urban drainage system will be analyzed and measures of storage regulation and pumping will be taken to assure flood discharge safety and reduce waterlogging risks in the urban area of Hezhou Municipality. Water environment improvement --- Improvement of the water diversion and exchange system and the wastewater collection and treatment system will help improving the water quality of He River channels and lay a foundation for improvement of ecological environment in He River Watershed and final realization of the targets of water quality and ecological safety of the water systems in the region. Ecological landscape improvement --- Construction of the urban green ring and ecological corridor will be helpful to the improvement of landscape continuity, preservation of animal habitats, establishment of continuous leisure and - 507 - entertainment network close to nature, encouragement of walking and bicycle travelling and protection of natural ecology. The urban green ring and ecological corridor will become the center for protecting the urban ecological structure and functions and developing the urban ecological network and urban open space planning and will promote the value of the urban landscape system, maintain the health and life of the water environment of the water systems and facilitate human-water harmony. Technical assistance and management --- The management capacity of the various functional departments and the smart water management level of Hezhou Municipality as a whole will be promoted through construction of the water quality monitoring station and the flood warning system as well as training of the full-time staff. Upon the implementation of the Project, the main watercourse of He River will reach a flood control standard of 1 in 50 years while the urban river system will achieve a 20-year recurrence period in terms of waterlogging hazard. Effective collection and treatment of wastewater in Jiangnan District will contribute to improved water quality of the urban water system and improved urban environment quality and drive the sustainable development of Hezhou Municipality. He River shores and other low-impact development facilities will be fully utilized to reduce energy consumption, save land and alleviate pressure of water environment. Upon completion, the Project will play an extremely important role in safeguarding social stability and economic prosperity in the region and generate huge social, economic and environment benefits, making it an important project serving multiple purposes. (2) The construction of the Project complies with the national laws and regulations and the master urban plan and environmental protection plan of the project area, which are the policy and legal foundation for the implementation of the Project. (3) The implementation of the Project may involve some environmental protection objects (sensitive sites), such as residential areas, schools and physical cultural resources, etc. In the feasibility study, the Project is reasonably sited to avoid the aforesaid environmental protection objects. In the Environment Assessment, optimization of design program is achieved through analysis of the siting alternatives to mitigate impacts on the environmental protection objects. (4) Some adverse impacts are likely to arise from the implementation of the Project on the surrounding environment. Such impacts may come from the construction stage and may also occur in the operation stage. 1) Adverse impacts in the construction period mainly include soil erosion caused by excavation, exhaust gas and noise from transportation of earth and construction material on construction site and access roads, and wastewater - 508 - discharged from construction camps and sediment dewatering facilities and odor from dredging and temporary storage of dredged sediment. Additionally, social impacts include disturbance to local traffic by construction vehicles and Fanglin Hydropower Station improvement, impact by He River rehabilitation to the physical cultural resources of Xiyue Historical and Cultural Street and the site of CCP Babu Special Branch, interference with railway from He River-lake connection works, and impact on existing farmland irrigation by Fanglin Hydropower Station improvement. 2) Upon completion of the Project, the urban flood risk control capacity of Hezhou will be enhanced, the black and odorous urban waters will be eliminated and the landscape value, ecological environment and municipal infrastructure will be improved. However, adverse environmental impacts will arise, mainly including effluent, odor and noise generated in the operation of Jiangnan WWTP and noise generated by stormwater pump stations in operation. Nevertheless, the positive benefits of the Project as a whole will be far more significant than its adverse impacts. (5) The level and scope of the adverse impacts likely to arise from the Project will be controlled within the scope permitted by the national laws and regulations and standards and codes by means of alternatives, mitigation measures, ESMP implementation, public participation and consultation, involuntary resettlement, and implementation of the dam safety action plan, etc. In conclusion, the Project is feasible if the alternatives, mitigation measures, ESMP, public consultation, involuntary resettlement plan, dam safety action plan and other countermeasures proposed under the Project are executed. - 509 - Annex 1:Monitoring data of environmental quality conditions in the project area Table 1 Ambient Air Quality Weekly Report in Hezhou City (for Period No. 24) 3 3 3 Date of monitoring SO2(ug/m ) NO2(ug/m ) PM10(ug/m ) AQI Air quality level Air quality status 2017.6.11 12 19 46 46 Ⅰ Excellent 2017.6.12 12 22 48 65 Ⅱ Fine 2017.6.13 9 17 39 44 Ⅰ Excellent 2017.6.14 14 19 34 34 Ⅰ Excellent 2017.6.15 6 16 26 40 Ⅰ Excellent 2017.6.16 8 12 24 27 Ⅰ Excellent 2017.6.17 6 11 26 36 Ⅰ Excellent Table 2 Ambient Air Environment Monitoring Results and Statistical Analysis at the Proposed WWTP Location 3 3 Monitoring site Date of monitoring H2-S(mg/m ) Ammonia(mg/m ) 2017.05.16 ND 0.03 2017.05.17 ND 0.02~0.03 A11 Proposed site of Jiangnan WWTP Standard 0.01 0.20 Pi 0.05 0.1~0.15 Rate of noncompliance 0 0 - 510 - Table 3 Monitoring Results of Odor Concentration along the River Basin Location Monitoring time Monitoring result (dimensionless) First monitoring 13 Second monitoring 12 A1 Riverside residence at Qiaodong Street south of He River dredging section Third monitoring 12 Fourth monitoring 11 First monitoring 13 Second monitoring 15 A2 Riverside residence at Nanshan Road south of He River dredging section Third monitoring 14 Fourth monitoring 17 First monitoring 19 Second monitoring 16 A3 Riverside residence at Sanqi Bridge of Huangtian Branch Canal dredging section Third monitoring 16 Fourth monitoring 15 First monitoring 10 Second monitoring 12 A4 Riverside residence at Shizigang of Guposhan Drainage Canal dredging section Third monitoring <10 Fourth monitoring 11 First monitoring <10 Second monitoring <10 A5 Riverside residence at Xinduzhai of Taoyuan Drainage Canal dredging section Third monitoring <10 Fourth monitoring <10 First monitoring <10 Second monitoring <10 A6 Riverside residence at Fumin Street of Huangan Temple Drainage Canal dredging section Third monitoring <10 Fourth monitoring <10 First monitoring 87 Second monitoring 88 A7 Riverside residence at Xiyue Street of Huangan Temple Drainage Canal dredging section Third monitoring 82 Fourth monitoring 88 First monitoring 20 Second monitoring 23 A8 Riverside residence at Zhushan Road of Shizigang Drainage Canal dredging section Third monitoring 21 Fourth monitoring 23 First monitoring 19 A9 Riverside residence at Wangjiao Street of Shizigang Drainage Canal dredging section Second monitoring 16 - 511 - Table 3 Monitoring Results of Odor Concentration along the River Basin Location Monitoring time Monitoring result (dimensionless) Third monitoring 15 Fourth monitoring 16 First monitoring 17 Second monitoring 16 A10 Riverside residence at Yinhe Street of Shizigang Drainage Canal dredging section Third monitoring 15 Fourth monitoring 16 First monitoring 12 Second monitoring 11 A11 Proposed site of Jiangnan WWTP Third monitoring 13 Fourth monitoring 11 - 512 - Table 4 Surface Water Environment Quality Monitoring Results Location W7 W2 Cross W3 Cross W4 W5 Cross W6 Anshan W8 Cross Shizigang W9 Cross W1 Cross section at section at Tianbaotang section at Village cross section of cross section at Date of section at confluence of the origin Cross the origin of section of Jianshezhong section of the origin of sampling the origin of Lining River of section of Huangtian Huangtian Road of Huangtian Shizigang Monitoring Lining River and Huangtian Changlong Changlong Branch Branch Huangansi Branch River item Branch Canal River River Canal Canal River Canal 2016.6.6 7.85 7.91 7.85 7.76 8.05 8.03 7.76 7.62 7.98 pH 2016.6.7 7.69 7.88 7.64 7.81 7.89 7.69 7.79 7.54 7.62 2016.6.8 7.82 7.69 7.67 7.59 7.96 8.05 7.75 7.47 7.81 2016.6.6 5.5 6.4 5.5 5.1 7.0 5.1 5.8 5.4 7.2 Dissolved oxygen 2016.6.7 5.7 6.6 5.4 5.6 6.8 5.5 6.1 5.2 7.2 2016.6.8 5.6 5.9 5.2 5.5 6.7 5.4 6.0 5.3 6.9 2016.6.6 1.6 1.4 2.2 3.2 1.9 5.1 2.6 2.5 1.8 Permanganate 2016.6.7 1.7 1.6 2.2 3.2 2.0 5.2 2.6 2.4 1.8 index 2016.6.8 1.7 1.5 2.1 3.2 2.0 5.1 2.4 2.3 1.8 2016.6.6 3.6 1.6 1.1 1.7 ND 3.8 2.1 3.3 1.7 BOD5 2016.6.7 3.3 1.7 1.1 1.9 ND 3.7 2.2 3.0 1.6 2016.6.8 3.5 1.6 1.3 1.7 ND 3.9 2.2 3.1 1.6 2016.6.6 8 7 9 12 10 16 11 12 14 COD 2016.6.7 9 8 10 14 11 17 12 13 15 2016.6.8 7 6 8 11 9 15 10 11 13 2016.6.6 7 ND 6 5 7 9 10 6 5 SS 2016.6.7 8 4 6 5 6 8 ND 5 6 2016.6.8 7 ND 4 6 6 8 ND 5 6 2016.6.6 0.105 0.088 0.102 1.508 0.191 6.468 2.754 2.848 0.541 NH3-N 2016.6.7 0.110 0.091 0.102 1.519 0.177 5.788 2.0809 2.787 0.491 - 513 - Table 4 Surface Water Environment Quality Monitoring Results Location W7 W2 Cross W3 Cross W4 W5 Cross W6 Anshan W8 Cross Shizigang W9 Cross W1 Cross section at section at Tianbaotang section at Village cross section of cross section at Date of section at confluence of the origin Cross the origin of section of Jianshezhong section of the origin of sampling the origin of Lining River of section of Huangtian Huangtian Road of Huangtian Shizigang Monitoring Lining River and Huangtian Changlong Changlong Branch Branch Huangansi Branch River item Branch Canal River River Canal Canal River Canal 2016.6.8 0.099 0.080 0.113 1.463 0.185 6.135 2.837 2.798 0.477 2016.6.6 0.03 0.06 0.08 0.45 0.05 0.53 0.38 0.31 0.13 TP 2016.6.7 0.03 0.06 0.09 0.43 0.05 0.55 0.37 0.32 0.13 2016.6.8 0.03 0.06 0.08 0.44 0.06 0.54 0.38 0.31 0.14 2016.6.6 0.01 0.01 0.01 0.03. 0.02 0.03 0.03 0.02 0.02 Petroleum 2016.6.7 0.01 0.01 0.01 0.02 0.01 0.03 0.02 0.01 0.01 2016.6.8 0.01 0.01 0.01 0.02 0.02 0.03 0.02 0.02 0.01 2016.6.6 0.0033 0.0016 0.0013 0.0041 0.0031 0.0045 0.0040 0.0020 0.0022 Volatile phenol 2016.6.7 0.0031 0.0014 0.0011 0.0038 0.0033 0.0041 0.0038 0.0023 0.0025 2016.6.8 0.0029 0.0014 0.0012 0.0038 0.0029 0.0039 0.0038 0.0020 0.0021 2016.6.6 ND ND ND ND ND ND ND ND ND Cyanide 2016.6.7 ND ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND ND 2016.6.6 0.10 0.12 0.14 0.15 0.14 0.13 0.12 0.11 0.10 Anionic surfactant 2016.6.7 0.11 0.12 0.14 0.15 0.14 0.13 0.12 0.10 0.11 2016.6.8 0.10 0.11 0.15 0.13 0.13 0.12 0.10 0.11 0.11 2016.6.6 0.012 ND ND ND 0.013 0.005 ND 0.013 0.013 Sulfide 2016.6.7 0.011 ND ND ND 0.011 0.006 ND 0.012 0.013 2016.6.8 0.012 ND ND ND 0.012 0.007 ND 0.013 0.013 2016.6.6 0.00096 0.00018 ND 0.00041 0.00088 0.00694 0.00090 0.00112 0.00206 Copper (Cu) 2016.6.7 0.00108 0.00024 ND 0.00053 0.00101 0.00638 0.00076 0.00099 0.00181 - 514 - Table 4 Surface Water Environment Quality Monitoring Results Location W7 W2 Cross W3 Cross W4 W5 Cross W6 Anshan W8 Cross Shizigang W9 Cross W1 Cross section at section at Tianbaotang section at Village cross section of cross section at Date of section at confluence of the origin Cross the origin of section of Jianshezhong section of the origin of sampling the origin of Lining River of section of Huangtian Huangtian Road of Huangtian Shizigang Monitoring Lining River and Huangtian Changlong Changlong Branch Branch Huangansi Branch River item Branch Canal River River Canal Canal River Canal 2016.6.8 0.00122 0.00021 ND 0.00066 0.00079 0.00583 0.00101 0.00090 0.00156 2016.6.6 ND 0.00091 ND ND ND ND 0.00130 ND 0.00091 Zinc (Zn) 2016.6.7 ND 0.00108 ND ND ND ND 0.00102 ND 0.00080 2016.6.8 ND 0.00123 ND ND ND ND 0.00099 ND 0.00109 2016.6.6 ND ND ND ND ND ND ND ND ND Plumbum(Pb) 2016.6.7 ND ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND ND 2016.6.6 ND ND ND ND ND ND ND ND ND Cadmium 2016.6.7 ND ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND ND 2016.6.6 0.0050 0.0034 0.0023 0.0065 0.0070 0.0038 0.0085 0.0053 0.0063 Arsenic(As) 2016.6.7 0.0049 0.0035 0.0023 0.0062 0.0066 0.0039 0.0084 0.0060 0.0062 2016.6.8 0.0048 0.0034 0.0023 0.0064 0.0069 0.0038 0.0084 0.0054 0.0060 2016.6.6 ND ND ND ND ND ND ND ND ND Cr6+ 2016.6.7 ND ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND ND 2016.6.6 ND ND ND ND ND ND ND ND ND Hg 2016.6.7 ND ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND ND - 515 - Table 4 Surface Water Environment Quality Monitoring Results (Continued) Location W12 W14 Cross W10 Wangjiao W11 Dawodu Nanshetang W13 Cross W15 W16 Babu W17 Lingfeng section at the Date of cross section cross section cross section section of Jigongzhou Bridge cross Bridge cross Monitoring origin of sampling of Shizigang of Taoyuan of Guishidong Guishidong cross section section of He section of He Guishidong No. item River River No. 6 Branch Trunk Canal of He River River River 5 Branch Canal Canal 2016.6.6 7.45 7.96 8.08 8.12 8.00 8.02 8.01 8.00 pH 2016.6.7 7.50 7.74 7.93 7.91 7.93 7.86 7.77 7.89 2016.6.8 7.31 7.99 8.01 8.06 8.04 7.86 7.92 7.87 2016.6.6 5.1 8.8 8.9 6.8 7.0 7.6 7.9 7.6 Dissolved oxygen 2016.6.7 5.2 8.8 8.9 6.8 7.0 7.6 7.9 7.6 2016.6.8 5.3 8.6 8.8 7.0 7.1 7.7 8.0 7.8 2016.6.6 4.0 2.9 1.4 1.4 1.8 1.6 1.6 1.7 Permanganate 2016.6.7 3.8 3.0 1.5 1.4 1.9 1.6 1.7 1.7 index 2016.6.8 3.7 3.0 1.4 1.3 1.8 1.6 1.7 1.7 2016.6.6 3.8 1.9 0.8 ND 3.8 ND 1.4 1.3 BOD5 2016.6.7 3.4 2.0 0.9 ND 3.5 0.8 1.6 1.4 2016.6.8 3.4 1.7 0.9 ND 3.5 0.7 1.3 1.3 2016.6.6 18 13 12 11 10 9 8 10 COD 2016.6.7 17 13 11 10 9 10 9 11 2016.6.8 15 12 11 10 9 8 7 9 2016.6.6 ND ND ND 6 7 8 6 4 SS 2016.6.7 5 6 4 5 5 9 7 6 2016.6.8 4 5 4 5 6 7 7 5 2016.6.6 7.274 0.505 0.083 0.177 0.258 0.263 0.288 0.313 NH3-N 2016.6.7 6.829 0.483 0.080 0.155 0.274 0.260 0.305 0.313 2016.6.8 6.663 0.477 0.088 0.171 0.338 0.277 0.258 0.296 - 516 - Table 4 Surface Water Environment Quality Monitoring Results (Continued) Location W12 W14 Cross W10 Wangjiao W11 Dawodu Nanshetang W13 Cross W15 W16 Babu W17 Lingfeng section at the Date of cross section cross section cross section section of Jigongzhou Bridge cross Bridge cross Monitoring origin of sampling of Shizigang of Taoyuan of Guishidong Guishidong cross section section of He section of He Guishidong No. item River River No. 6 Branch Trunk Canal of He River River River 5 Branch Canal Canal 2016.6.6 0.74 0.51 0.03 0.05 0.06 0.06 0.08 0.08 TP 2016.6.7 0.72 0.49 0.03 0.05 0.07 0.06 0.07 0.09 2016.6.8 0.73 0.47 0.03 0.05 0.07 0.06 0.07 0.09 2016.6.6 0.03 0.03 0.01 0.01 0.01 0.01 0.02 0.02 Petroleum 2016.6.7 0.03 0.3 0.02 0.01 0.01 0.01 0.02 0.02 2016.6.8 0.03 0.03 0.01 0.01 0.01 0.02 0.02 0.02 2016.6.6 0.0025 0.0017 0.0028 0.0031 0.0019 0.0035 0.0031 0.0022 Volatile phenol 2016.6.7 0.0028 0.0014 0.0021 0.0024 0.0020 0.0038 0.00034 0.0020 2016.6.8 0.002 0.0014 0.0022 0.0024 0.0020 0.0032 0.0030 0.0020 2016.6.6 ND ND ND ND ND ND ND ND Cyanide 2016.6.7 ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND 2016.6.6 0.11 0.12 0.09 0.09 0.15 0.15 0.13 0.13 Anionic surfactant 2016.6.7 0.11 0.12 0.09 0.09 0.14 0.16 0.13 0.12 2016.6.8 0.13 0.09 0.10 0.13 0.15 0.14 0.13 0.13 2016.6.6 0.009 0.014 ND 0.013 0.006 0.007 0.007 0.005 Sulfide 2016.6.7 0.010 0.013 ND 0.012 0.006 0.006 0.007 0.007 2016.6.8 0.011 0.013 ND 0.013 0.007 0.007 0.006 0.006 2016.6.6 0.00049 0.00429 0.00049 ND 0.00644 0.00048 0.00052 0.00035 Copper(Cu) 2016.6.7 0.00038 0.00464 0.00052 ND 0.00575 0.00041 0.00060 0.000029 2016.6.8 0.00041 0.00399 0.00043 ND 0.00609 0.00053 0.00072 0.00041 Zinc (Zn) 2016.6.6 0.00192 0.00205 ND ND ND ND 0.00101 ND - 517 - Table 4 Surface Water Environment Quality Monitoring Results (Continued) Location W12 W14 Cross W10 Wangjiao W11 Dawodu Nanshetang W13 Cross W15 W16 Babu W17 Lingfeng section at the Date of cross section cross section cross section section of Jigongzhou Bridge cross Bridge cross Monitoring origin of sampling of Shizigang of Taoyuan of Guishidong Guishidong cross section section of He section of He Guishidong No. item River River No. 6 Branch Trunk Canal of He River River River 5 Branch Canal Canal 2016.6.7 0.00169 0.0173 ND ND ND ND 0.00093 ND 2016.6.8 0.00222 0.00186 ND ND ND ND 0.00099 ND 2016.6.6 ND ND ND ND ND ND ND ND Plumbum(Pb) 2016.6.7 ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND 2016.6.6 ND ND ND ND ND ND ND ND Cadmium 2016.6.7 ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND 2016.6.6 0.0055 0.0020 0.0016 0.0075 0.0020 0.0036 0.0031 0.0029 Arsenic(As) 2016.6.7 0.0055 0.0016 0.00144 0.0074 0.0019 0.0035 0.0032 0.0029 2016.6.8 0.0058 0.0015 0.0014 0.0072 0.0018 0.0035 0.0030 0.0028 2016.6.6 ND ND ND ND ND ND ND ND Cr6+ 2016.6.7 ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND 2016.6.6 ND ND ND ND ND ND ND ND Hg 2016.6.7 ND ND ND ND ND ND ND ND 2016.6.8 ND ND ND ND ND ND ND ND - 518 - Table 4 Surface Water Environment Quality Monitoring Results (Continued) Location W18 Cross section ahead of Monitoring time confluence of Mawei River into He Monitoring item River 2017.3.21 7.84 pH 2017.6.27 7.57 2017.3.21 9.2 Dissolved oxygen 2017.6.27 5.4 2017.3.21 2.2 Permanganate index 2017.6.27 2.08 2017.3.21 1.6 BOD5 2017.6.27 2.1 2017.3.21 ND COD 2017.6.27 12.4 2017.3.21 0.463 NH3-N 2017.6.27 0.846 2017.3.21 0.04 TP 2017.6.27 0.20 2017.3.21 0.02 Petroleum 2017.6.27 0.01 2017.3.21 0.0017 Volatile phenol 2017.6.27 ND 2017.3.21 ND Cyanide 2017.6.27 ND 2017.3.21 0.05 Anionic surfactant 2017.6.27 0.05 2017.3.21 0.013 Sulfide 2017.6.27 0.013 2017.3.21 0.00060 Copper (Cu) 2017.6.27 0.23 2017.3.21 0.00242 Zinc (Zn) 2017.6.27 ND 2017.3.21 ND Plumbum(Pb) 2017.6.27 0.0052 2017.3.21 ND Cadmium 2017.6.27 0.0001 2017.3.21 0.0063 Arsenic(As) 2017.6.27 ND 2017.3.21 ND Cr6+ 2017.6.27 ND 2017.3.21 ND Hg 2017.6.27 ND - 519 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Range of monitored 7.69~7.82 7.69~7.91 7.64~7.85 7.59~7.81 7.89~8.05 7.69~8.05 7.75~7.79 value Standard 0.345~0.4 0.345~0.52 0.345~0.455 0.32~0.425 0.295~0.405 0.445~0.525 0.375~0.395 pH Index Sij 1 5 6~9 6~9 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 5.5~5.7 5.9~6.6 5.2~5.5 5.1~5.6 6.7~7.0 5.1~5.5 5.8~6.1 value Standard Dissolved 0.51~0.55 0.35~0.47 0.55~0.60 0.53~0.62 0.27~0.33 0.55~0.62 0.44~0.49 Index Sij 3 2 oxygen Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 1.6~1.7 1.4~1.6 2.1~2.2 3.2 1.9~2.0 5.1~5.2 2.4~2.6 value Standard Permanga 0.16~0.17 0.14~0.16 0.21~0.22 0.32 0.19~0.20 0.51~0.52 0.24~0.26 Index Sij 10 15 nate index Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of BOD5 3.3~3.6 1.6~1.7 1.1~1.3 1.7~1.9 ND 3.7~3.9 2.1~2.2 6 10 monitored - 520 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal value Standard 0.55~0.60 0.27~0.29 0.18~0.22 0.28~0.32 0.04 0.62~0.65 0.35~0.37 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 7~9 6~8 8~10 11~14 9~11 15~17 10~12 value Standard 0.23~0.30 0.20~0.27 0.27~0.33 0.37~0.47 0.30~0.37 0.50~0.57 0.33~0.40 COD Index Sij 30 40 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 7~8 ND~4 4~6 5~6 6~7 8~9 ND~ 10 value Standard 0.12~0.13 0.03~0.06 0.06~0.10 0.08~0.10 0.10~0.12 0.13~0.15 0.03~0.17 SS Index Sij 60 150 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.099~0.11 monitored 0.080~0.091 0.102~0.113 1.463~1.519 0.177~0.191 5.788~6.468 2.081~2.837 NH3-N 0 1.5 2.0 value Standard 0.07~0.073 0.05~0.06 0.07~0.08 0.98~1.01 0.12~0.13 3.86~4.31 1.39~1.89 - 521 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Index Sij Noncomplia 0 0 0 0.01 0 2.86~3.31 0.39~0.89 nce multiple Noncomplia 0 0 0 66.7% 0 100% 100% nce rate Range of monitored 0.03 0.06 0.08~0.09 0.43~0.45 0.05~0.06 0.53~0.55 0.37~0.38 value Standard 0.10 0.20 0.26~0.30 1.43~1.50 0.17~0.20 1.77~1.83 1.23~1.27 TP Index Sij 0.3 0.4 Noncomplia 0 0 0 0.43~0.50 0 0.77~0.83 0.23~0.27 nce multiple Noncomplia 0 0 0 100% 0 100% 100% nce rate Range of monitored 0.01 0.01 0.01 0.02~0.03 0.01~0.02 0.03 0.02~0.03 value Standard Petroleu 0.02 0.02 0.02 0.04~0.06 0.02~0.04 0.06 0.04~0.06 Index Sij 0.5 1.0 m Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.0029~0.003 monitored 0.0014~0.0016 0.0011~0.0013 0.0038~0.0041 0.0029~0.0033 0.0039~0.0045 0.0038~0.0040 3 Volatile value 0.01 0.1 phenol Standard 0.29~0.33 0.14~0.16 0.11~0.13 0.38~0.41 0.29~0.33 0.39~0.45 0.38~0.40 Index Sij Noncomplia 0 0 0 0 0 0 0 - 522 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Cyanide Index Sij 0.2 0.2 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 0.10~0.11 0.11~0.12 0.14~0.15 0.13~0.15 0.13~0.14 0.12~0.13 0.10~0.12 value Standard Anionic 0.33~0.37 0.37~0.40 0.47~0.50 0.43~0.50 0.43~0.47 0.40~0.43 0.33~0.40 Index Sij 0.3 0.3 surfactant Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.011~0.01 monitored ND ND ND 0.011~0.013 0.005~0.007 ND 2 value Standard Sulfide 0.02 0.01 0.01 0.01 0.02~0.03 0.01 0.01 0.5 1.0 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 - 523 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal nce rate Range of 0.00096~0. 0.00018~0.000 0.00079~0.00 0.00583~0.0 0.00076~0.001 monitored ND 0.00041~0.00066 00122 24 101 0694 01 value Standard 0.00096~0. 0.00018~0.000 0.00079~0.00 0.00583~0.0 0.00076~0.001 Copper 0.00004 0.00041~0.00066 Index Sij 00122 24 101 0694 01 1.0 1.0 (Cu) Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.00091~0.001 0.00099~0.001 monitored ND ND ND ND ND 23 30 value Standard 0.0002 0.0005 0.0002 0.0002 0.0002 0.0002 0.0005~0.0007 Zinc (Zn) Index Sij 2.0 2.0 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard Plumbum 0.002 0.002 0.002 0.002 0.002 0.002 0.002 Index Sij 0.05 0.1 (Pb) Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Cadmium Range of ND ND ND ND ND ND ND 0.05 0.01 - 524 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal monitored value Standard 0.005 0.005 0.005 0.005 0.005 0.005 0.005 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.0048~0.0 0.0066~0.007 0.0038~0.00 monitored 0.0034~0.0035 0.0023 0.0062~0.0065 0.0084~0.0085 050 0 39 value Standard Arsenic 0.05 0.03~0.04 0.02 0.06~0.07 0.07 0.04 0.08~0.09 Index Sij 0.1 0.1 (As) Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Cr6+ Index Sij 0.05 0.1 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of Hg monitored ND ND ND ND ND ND ND 0.01 0.001 value - 525 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Standard 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 7.47~7.62 7.62~7.98 7.31~7.50 7.74~7.99 7.93~8.08 7.91~8.12 7.93~8.04 value Standard 0.235~0.3 0.31~0.49 0.15~0.25 0.37~0.49 0.46~0.504 0.46~0.56 0.46~0.52 pH Index Sij 1 6~9 6~9 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 5.2~5.4 6.9~7.2 5.1~5.3 8.6~8.8 8.8~8.9 6.8~7.0 7.0~7.1 value Standard Dissolved 0.56~0.60 0.24~0.29 0.58~0.62 0.02~0.05 0.05~0.07 0.27~0.31 0.25~0.27 Index Sij 3 2 oxygen Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 2.3~2.5 1.8 3.7~4.0 2.9~3.0 1.4~1.5 1.3~1.4 1.8~1.9 Permanga value 10 15 nate index Standard 0.23~0.25 0.18 0.37~0.40 0.29~0.30 0.14~0.15 0.13~0.14 0.18~0.19 Index Sij - 526 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 3.0~3.3 1.6~1.7 3.4~3.8 1.7~2.0 0.8~0.9 ND 3.5~3.8 value Standard 0.50~0.55 0.27~0.28 0.57~0.63 0.28~0.33 0.13~0.15 0.04 0.58~0.63 BOD5 Index Sij 6 10 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 11~13 10~15 15~18 12~13 11~12 10~11 9~10 value Standard 0.37~0.43 0.33~0.50 0.50~0.60 0.40~0.43 0.37~0.40 0.33~0.37 0.30~0.33 COD Index Sij 30 40 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 5~6 5~6 ND~5 ND~6 ND~4 5~6 5~7 value SS Standard 60 150 0.08~0.10 0.08~0.10 0.03~0.08 0.03~0.10 0.03~0.07 0.08~0.10 0.08~0.12 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple - 527 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Noncomplia 0 0 0 0 0 0 0 nce rate Range of 2.787~2.84 monitored 0.477~0.541 6.663~7.274 0.477~0.505 0.080~0.088 0.155~0.177 0.258~0.338 8 value Standard 1.86~1.90 0.32~0.36 4.44~4.85 0.32~0.34 0.05~0.06 0.10~0.12 0.17~0.23 NH3-N Index Sij 1.5 2.0 Noncomplia 0.86~0.90 0 3.44~3.85 0 0 0 0 nce multiple Noncomplia 100% 0 100% 0 0 0 0 nce rate Range of monitored 0.31~0.32 0.13~0.14 0.72~0.74 0.47~0.51 0.03 0.05 0.06~0.07 value Standard 1.03~1.07 0.43~0.47 2.40~2.47 1.57~1.70 0.10 0.17 0.20~0.23 TP Index Sij 0.3 0.4 Noncomplia 0.03~0.07 0 0.40~0.47 0.57~0.70 0 0 0 nce multiple Noncomplia 100% 0 100% 100% 0 0 0 nce rate Range of monitored 0.01~0.02 0.01~0.02 0.03 0.03 0.01~0.02 0.01 0.01 value Standard Petroleu 0.02~0.04 0.02~0.04 0.06 0.06 0.02~0.04 0.02 0.02 Index Sij 0.5 1.0 m Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate - 528 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Range of 0.0020~0.0 0.002~0.002 0.0021~0.002 0.0024~0.00 monitored 0.0021~0.0025 0.0014~0.0017 0.0019~0.0020 023 8 8 31 value Standard Volatile 0.20~0.23 0.21~0.25 0.20~0.28 0.14~0.17 0.21~0.28 0.24~0.31 0.19~0.20 Index Sij 0.01 0.1 phenol Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Cyanide Index Sij 0.2 0.2 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored 0.10~0.11 0.10~0.11 0.11~0.13 0.09~0.12 0.09~0.10 0.09~0.13 0.14~0.15 value Standard Anionic 0.33~0.37 0.33~0.37 0.37~0.43 0.30~0.40 0.30~0.33 0.30~0.43 0.47~0.50 Index Sij 0.3 0.3 surfactant Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.012~0.01 Sulfide 0.013 0.009~0.011 0.013~0.014 ND 0.012~0.013 0.006~0.007 0.5 1.0 monitored 3 - 529 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal value Standard 0.02~0.03 0.03 0.02 0.03 0.01 0.02~0.03 0.01 Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.00090~0. 0.00156~0.002 0.00038~0.0 0.00043~0.00 0.00575~0.006 monitored 0.00399~0.00464 ND 00112 06 0049 052 44 value Standard 0.00090~0. 0.00156~0.002 0.00038~0.0 0.00043~0.00 0.00575~0.006 Copper 0.00399~0.00464 0.00004 Index Sij 00112 06 0049 052 44 1.0 1.0 (Cu) Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.00080~0.001 0.00169~0.0 monitored ND 0.00173~0.00186 ND ND ND 09 0222 value Standard 0.0008~0.00 0.0002 0.0004~0.0005 0.0009 0.00017 0.00017 0.00017 Zinc (Zn) Index Sij 11 2.0 2.0 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of Plumbum monitored ND ND ND ND ND ND ND 0.05 0.1 (Pb) value Standard 0.002 0.002 0.002 0.002 0.002 0.002 0.002 - 530 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal Index Sij Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard 0.005 0.005 0.005 0.005 0.005 0.005 0.005 Cadmium Index Sij 0.05 0.01 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of 0.0053~0.0 0.0055~0.00 0.0014~0.001 0.0072~0.00 monitored 0.0060~0.0063 0.0015~0.0020 0.0018~0.0020 060 58 6 75 value Standard Arsenic 0.05~0.06 0.06 0.06~0.08 0.02 0.01~0.02 0.07~0.08 0.02 Index Sij 0.1 0.1 (As) Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Cr6+ 0.05 0.1 Standard 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Index Sij Noncomplia 0 0 0 0 0 0 0 - 531 - Table 5 Statistical Evaluation of Water Quality Monitoring Results W6 Location W2 Cross W3 Cross W5 Cross Anshan W1 Cross section at section at section at Village W7 Shizigang Class IV Class V section at W4 Tianbaotang Evaluation confluence of the origin the origin of cross cross section water water the origin Cross section of index Lining River of Huangtian section of of Huangtian quality quality of Lining Changlong River and Huangtian Changlong Branch Huangtian Branch Canal standard standard Monitoring River Branch Canal River Canal Branch item Canal nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate Range of monitored ND ND ND ND ND ND ND value Standard 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Hg Index Sij 0.001 0.001 Noncomplia 0 0 0 0 0 0 0 nce multiple Noncomplia 0 0 0 0 0 0 0 nce rate - 532 - Table 5 Statistical Evaluation of Water Quality Monitoring Results (Continued) Location Class III Class IV W16 Babu Bridge W17 Lingfeng W18 Cross section W15 Jigongzhou cross water water Evaluation index cross section of He Bridge cross before Mawei River Monitoring section of He River quality quality River section of He River flowing into He River item standard standard Range of monitored 7.86~8.02 7.77~8.01 7.87~8.00 7.57~7.84 value Standard Index Sij 0.43~0.51 0.385~0.505 0.44~0.5 0.285~0.42 pH 6~9 6~9 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 7.6~7.7 7.9~8.0 7.6~7.8 5.4~9.2 value Dissolved Standard Index Sij 0.27~0.3 0.19~0.24 0.26~0.3 0.053~0.876 5 3 oxygen Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 1.6 1.6~1.7 1.7 2.08~2.2 value Permanganate Standard Index Sij 0.27 0.27~0.28 0.28 0.345~0.367 6 10 index Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored ND~0.8 1.3~1.6 1.3~1.4 1.6~2.1 value Standard Index Sij 0.06~0.2 0.325~0.4 0.325~0.35 0.4~0.525 BOD5 4 6 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 9~10 7~9 9~11 ND~12.4 value Standard Index Sij 0.45~0.5 0.35~0.45 0.45~0.55 0.125~0.62 COD 20 30 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 - 533 - Table 5 Statistical Evaluation of Water Quality Monitoring Results (Continued) Location Class III Class IV W16 Babu Bridge W17 Lingfeng W18 Cross section W15 Jigongzhou cross water water Evaluation index cross section of He Bridge cross before Mawei River Monitoring section of He River quality quality River section of He River flowing into He River item standard standard Range of monitored 7~9 6~7 4~6 / value Standard Index Sij 0.23~0.3 0.2~0.23 0.13~0.2 / SS 30 60 Noncompliance 0 0 0 / multiple Noncompliance rate 0 0 0 / Range of monitored 0.260~0.277 0.258~0.305 0.296~0.313 0.463~0.846 value Standard Index Sij 0.260~0.277 0.258~0.305 0.296~0.313 0.463~0.846 NH3-N 1.0 1.5 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.06 0.07~0.08 0.08~0.09 0.04~0.20 value Standard Index Sij 0.3 0.35~0.4 0.4~0.45 0.2~1 TP 0.2 0.3 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.01~0.02 0.02 0.02 0.01~0.02 value Standard Index Sij 0.2~0.4 0.4 0.4 0.2~0.4 Petroleum 0.05 0.5 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.0032~0.0038 0.0030~0.00034 0.0020~0.0022 ND~0.0017 value Standard Index Sij 0.64~0.76 0.6~0.68 0.4~0.44 0.03~0.34 Volatile phenol 0.005 0.01 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 - 534 - Table 5 Statistical Evaluation of Water Quality Monitoring Results (Continued) Location Class III Class IV W16 Babu Bridge W17 Lingfeng W18 Cross section W15 Jigongzhou cross water water Evaluation index cross section of He Bridge cross before Mawei River Monitoring section of He River quality quality River section of He River flowing into He River item standard standard Range of monitored ND ND ND ND value Standard Index Sij 0.01 0.01 0.01 0.01 Cyanide 0.2 0.2 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.14~0.16 0.13 0.12~0.13 0.05 value Anionic Standard Index Sij 0.7~0.8 0.65 0.6~0.75 0.25 0.2 0.3 surfactant Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.006~0.007 0.006~0.007 0.005~0.007 0.013 value Standard Index Sij 0.03~0.035 0.06~0.035 0.025~0.035 0.065 Sulfide 0.2 0.5 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.00041~0.00053 0.00052~0.00072 0.00029~0.00041 0.00060~0.23 value Standard Index Sij 0.00041~0.00053 0.00052~0.00072 0.00029~0.00041 0.00060~0.23 Copper (Cu) 1.0 1.0 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored ND 0.00093~0.00101 ND ND~0.00242 value Standard Index Sij 0.00034 0.00093~0.00101 0.00034 0.00034~0.00242 Zinc (Zn) 1.0 2.0 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 - 535 - Table 5 Statistical Evaluation of Water Quality Monitoring Results (Continued) Location Class III Class IV W16 Babu Bridge W17 Lingfeng W18 Cross section W15 Jigongzhou cross water water Evaluation index cross section of He Bridge cross before Mawei River Monitoring section of He River quality quality River section of He River flowing into He River item standard standard Range of monitored ND ND ND ND~0.0052 value Standard Index Sij 0.002 0.002 0.002 0.002~0.104 Plumbum(Pb) 0.05 0.05 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored ND ND ND ND~0.0001 value Standard Index Sij 0.005 0.005 0.005 0.005~0.02 Cadmium 0.005 0.05 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored 0.0035~0.0036 0.0030~0.0032 0.0028~0.0029 ND~0.0063 value Standard Index Sij 0.07~0.072 0.06~0.062 0.056~0.058 0.003~0.126 Arsenic(As) 0.05 0.1 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored ND ND ND ND value Standard Index Sij 0.04 0.04 0.04 0.04 Cr6+ 0.05 0.05 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 Range of monitored ND ND ND ND value Standard Index Sij 0.2 0.2 0.2 0.2 Hg 0.0001 0.01 Noncompliance 0 0 0 0 multiple Noncompliance rate 0 0 0 0 - 536 - Table 6 Statistics of Noise Monitoring and Evaluation Results of the Project Standard Standard in force Location Date of monitoring Monitored value Leq [dB(A)] Compliance dB(A) Analysis 2016.6.7 Daytime 53.3 60 Compliant 2016.6.7~6.8 Nighttime 39.8 50 Compliant N1 JIGONGZHOU 2016.6.8 Daytime 54.1 60 Compliant 2016.6.8~6.9 Nighttime 40.4 50 Compliant 2016.6.7 Daytime 54.3 60 Compliant 2016.6.7~6.8 Nighttime 39.9 50 Compliant N2 Tianchongzhai 2016.6.8 Daytime 53.9 60 Compliant 2016.6.8~6.9 Nighttime 38.1 50 Compliant 2016.6.7 Daytime 52.6 60 Compliant N3 Sanjia Primary 2016.6.7~6.8 Nighttime 40.9 50 Compliant School 2016.6.8 Daytime 54.3 60 Compliant 2016.6.8~6.9 Nighttime 38.7 50 Compliant 2016.6.7 Daytime 53.6 60 Compliant 2016.6.7~6.8 Nighttime 42.3 50 Compliant N4 Hezhou Institute 2016.6.8 Daytime 54.2 60 Compliant 2016.6.8~6.9 Nighttime 40.1 50 Compliant 2016.6.7 Daytime 54.2 60 Compliant 2016.6.7~6.8 Nighttime 43.7 50 Compliant N5 Sanjia Village 2016.6.8 Daytime 54.7 60 Compliant 2016.6.8~6.9 Nighttime 41.4 50 Compliant 2016.6.7 Daytime 53.5 60 Compliant N6 Hezhou 2016.6.7~6.8 Nighttime 40.9 50 Compliant Experimental Middle 2016.6.8 Daytime 54.1 60 Compliant School 2016.6.8~6.9 Nighttime 41.1 50 Compliant 2016.6.7 Daytime 49.5 60 Compliant 2016.6.7~6.8 Nighttime 43.2 50 Compliant N7 Wenyuanhuadu 2016.6.8 Daytime 51.2 60 Compliant 2016.6.8~6.9 Nighttime 42.1 50 Compliant 2016.6.7 Daytime 54.1 60 Compliant 2016.6.7~6.8 Nighttime 43.0 50 Compliant N8 Xiyue Street 2016.6.8 Daytime 52.2 60 Compliant 2016.6.8~6.9 Nighttime 44.2 50 Compliant 2016.6.7 Daytime 52.9 60 Compliant N9 Hezhou 2016.6.7~6.8 Nighttime 41.2 50 Compliant Transportation 2016.6.8 Daytime 52.4 60 Compliant Bureau 2016.6.8~6.9 Nighttime 41.5 50 Compliant 2016.6.7 Daytime 53.8 60 Compliant N10 Xiwan Primary 2016.6.7~6.8 Nighttime 41.4 50 Compliant School 2016.6.8 Daytime 54.2 60 Compliant 2016.6.8~6.9 Nighttime 37.0 50 Compliant 2016.6.7 Daytime 53.0 60 Compliant 2016.6.7~6.8 Nighttime 36.6 50 Compliant N11 Lining Village 2016.6.8 Daytime 53.7 60 Compliant 2016.6.8~6.9 Nighttime 38.1 50 Compliant 2016.6.7 Daytime 53.5 60 Compliant N12 Changlong 2016.6.7~6.8 Nighttime 40.0 50 Compliant Village 2016.6.8 Daytime 54.0 60 Compliant 2016.6.8~6.9 Nighttime 38.7 50 Compliant N13 Huangtian 2016.6.7 Daytime 54.2 60 Compliant Town 2016.6.7~6.8 Nighttime 39.0 50 Compliant 537 Table 6 Statistics of Noise Monitoring and Evaluation Results of the Project Standard Standard in force Location Date of monitoring Monitored value Leq [dB(A)] Compliance dB(A) Analysis 2016.6.8 Daytime 53.7 60 Compliant 2016.6.8~6.9 Nighttime 37.1 50 Compliant 2016.6.7 Daytime 52.6 60 Compliant N14 Pinggui No. 3 2016.6.7~6.8 Nighttime 39.0 50 Compliant Junior Middle 2016.6.8 Daytime 53.2 60 Compliant School 2016.6.8~6.9 Nighttime 40.4 50 Compliant 2016.6.7 Daytime 54.7 60 Compliant N15 Qianjin Road 2016.6.7~6.8 Nighttime 41.2 50 Compliant Primary School 2016.6.8 Daytime 53.0 60 Compliant 2016.6.8~6.9 Nighttime 41.2 50 Compliant 2016.6.7 Daytime 50.4 60 Compliant N16 Babu District 2016.6.7~6.8 Nighttime 40.7 50 Compliant Experimental 2016.6.8 Daytime 52.3 60 Compliant Primary School 2016.6.8~6.9 Nighttime 41.4 50 Compliant 2016.6.7 Daytime 51.3 60 Compliant N17 Hezhou 2016.6.7~6.8 Nighttime 42.3 50 Compliant Renmin Hospital 2016.6.8 Daytime 53.6 60 Compliant 2016.6.8~6.9 Nighttime 42.8 50 Compliant 2016.6.7 Daytime 52.7 60 Compliant 2016.6.7~6.8 Nighttime 41.1 50 Compliant N18 Anshan Village 2016.6.8 Daytime 53.7 60 Compliant 2016.6.8~6.9 Nighttime 41.1 50 Compliant 2016.6.7 Daytime 54.6 60 Compliant N19 Guangji 2016.6.7~6.8 Nighttime 40.5 50 Compliant Maternity Hospital 2016.6.8 Daytime 53.7 60 Compliant 2016.6.8~6.9 Nighttime 43.6 50 Compliant 2016.6.7 Daytime 53.4 60 Compliant N20 Technical 2016.6.7~6.8 Nighttime 41.9 50 Compliant School 2016.6.8 Daytime 52.9 60 Compliant 2016.6.8~6.9 Nighttime 43.6 50 Compliant 2016.6.7 Daytime 54.1 60 Compliant N21 Hezhou 2016.6.7~6.8 Nighttime 44.9 50 Compliant Chinese Traditional 2016.6.8 Daytime 53.5 60 Compliant Medicine Hospital 2016.6.8~6.9 Nighttime 38.8 50 Compliant 2016.6.7 Daytime 49.6 60 Compliant 2016.6.7~6.8 Nighttime 41.4 50 Compliant N22 Baimianshan 2016.6.8 Daytime 44.9 60 Compliant 2016.6.8~6.9 Nighttime 40.2 50 Compliant 2016.6.7 Daytime 51.2 60 Compliant 2016.6.7~6.8 Nighttime 42.1 50 Compliant N23 Dawodu 2016.6.8 Daytime 50.1 60 Compliant 2016.6.8~6.9 Nighttime 40.6 50 Compliant 538 Table 7 Soil Sample Monitoring and Analysis Results Unit:(mg/kg,pH value - dimensionless Monitoring item pH Total Cr Plumbum Cadmium Arsenic Zinc Copper Hg Monitoring site (GB15618-1995) Class II standard >7.5 250 350 0.6 25 300 100 1.5 Monitored value 8.2 51 54.8 0.23 26.1 160 45 0.322 S21 500m upstream of PI index / 0.204 0.154 0.383 1.044 0.533 0.45 0.322 Lingfeng Bridge (on the right bank) Noncompliance / 0 0 0 0.044 0 0 0 multiple Monitored value 8.2 39 57.7 1.06 40.2 322 73 1.21 S22 1000m upstream of PI index / 0.156 0.165 1.767 1.608 1.073 0.73 1.21 Lingfeng Bridge (on the right bank) Noncompliance / 0 0 0.767 0.608 0.073 0 0.21 multiple Monitored value 8.2 46 66.6 0.37 35.8 393 60 1.25 S23-1 50m upstream of PI index / 0.174 0.190 0.617 1.432 1.31 0.60 1.25 Fanglin Power Station (on the left bank) Noncompliance / 0 0 0 0.432 0.31 0 0.25 multiple Monitored value 8.2 51 70.3 0.98 25.9 279 78 1.73 S23-2 50m upstream of PI index / 0.204 0.201 1.633 1.036 0.93 0.78 1.73 Fanglin Power Station (on the right bank) Noncompliance / 0 0 0.633 0.036 0 0 0.73 multiple S24-1 1000m upstream Monitored value 8.2 57 62.5 1.29 52.4 297 91 1.65 of Fanglin Power PI index / 0.228 0.179 2.15 2.096 0.99 0.91 1.65 Station(on the left Noncompliance bank) / 0 0 1.15 1.096 0 0 0.65 multiple - 539 - Table 7 Soil Sample Monitoring and Analysis Results Unit:(mg/kg,pH value - dimensionless Monitoring item pH Total Cr Plumbum Cadmium Arsenic Zinc Copper Hg Monitoring site S24-2 1000m upstream Monitored value 8.1 45 39.6 0.26 58.0 136 39 0.624 of Fanglin Power PI index / 0.18 0.113 0.433 2.32 0.453 0.39 0.624 Station(on the right Noncompliance bank) / 0 0 0 1.32 0 0 0 multiple S25-1 2000m upstream Monitored value 8.0 36 47.8 0.53 100 155 41 0.964 of Fanglin Power PI index / 0.144 0.131 0.883 4 0.517 0.41 0.964 Station(on the left Noncompliance bank) / 0 0 0 3 0 0 0 multiple S25-2 2000m upstream Monitored value 8.1 55 33.8 0.27 105 152 45 4.36 of Fanglin Power PI index / 0.22 0.097 0.45 4.2 0.506 0.45 4.36 Station(on the right Noncompliance bank) / 0 0 0 3.2 0 0 3.36 multiple - 540 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 6.9 7.1 7.1 7.3 6.9 PI index / / / / / pH >6.5 Noncompliance / / / / / multiple Monitored value 30 54 59 56 30 PI index 0.075 0.135 0.147 0.14 0.075 Copper 400 Noncompliance 0 0 0 0 0 multiple Monitored value 118 257 266 387 163 PI index 0.236 0.514 0.532 0.774 0.326 Zinc 500 Noncompliance 0 0 0 0 0 multiple Monitored value 80.3 118 116 102 90.9 PI index 0.16 0.236 0.232 0.204 0.18 Plumbum 500 Noncompliance 0 0 0 0 0 multiple Monitored value 0.45 1.25 0.81 2.17 0.44 PI index 0.45 1.25 0.81 2.17 0.44 Cadmium 1.0 Noncompliance 0 0.25 0 1.17 0 multiple Monitored value 58.0 95.6 118 115 57.4 PI index 1.45 2.39 2.95 2.875 1.435 Arsenic 40 Noncompliance 0.45 1.39 1.95 1.875 0.435 multiple - 541 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 0.249 0.445 0.335 0.272 0.196 PI index 0.166 0.296 0.223 0.181 0.13 Hg 1.5 Noncompliance 0 0 0 0 0 multiple Monitored value 64 64 71 123 67 PI index 0.213 0.213 0.237 0.41 0.223 Total Cr 300 Noncompliance 0 0 0 0 0 multiple S6 downstream S8 dredging S9 dredging of dredging S7 dredging Location section of section of section of section of East S10 dredging section of Evaluation Huangtian Guposhan (GB15618-199Cl East No. 5 No. 6 Branch Taoyuan Drainage Canal Monitoring index Branch Canal Drainage Canal ass III Branch Canal (Sampling (Sampling depth: 20m) item (Sampling depth: (Sampling depth: Canal depth: 20m) 20m) 20m) (Sampling depth: 20m) Monitored value 7.2 7.2 7.2 7.3 6.9 PI index / / / / / pH >6.5 Noncompliance / / / / / multiple Monitored value 30 62 54 71 50 PI index 0.075 0.155 0.135 0.177 0.125 Copper 400 Noncompliance 0 0 0 0 0 multiple - 542 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 138 467 334 396 328 PI index 0.276 0.934 0.668 0.792 0.656 Zinc 500 Noncompliance 0 0 0 0 0 multiple Monitored value 80.5 133 132 139 97.4 PI index 0.161 0.266 0.264 0.278 0.189 Plumbum 500 Noncompliance 0 0 0 0 0 multiple Monitored value 0.58 1.50 2.38 1.91 1.27 PI index 0.58 1.50 2.38 1.91 1.27 Cadmium 1.0 Noncompliance 0 0.5 1.38 0.91 0.27 multiple Monitored value 74.5 42.5 64.6 64.0 42.6 PI index 1.863 1.063 1.615 1.6 1.065 Arsenic 40 Noncompliance 0.863 0.063 0.615 0.6 0.065 multiple Monitored value 0.393 1.12 1.07 0.321 1.02 PI index 0.262 0.747 0.713 0.214 0.68 Hg 1.5 Noncompliance 0 0 0 0 0 multiple Monitored value 71 217 206 181 91 PI index 0.231 0.726 0.678 0.603 0.303 Total Cr 300 Noncompliance 0 0 0 0 0 multiple - 543 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) S11 Upstream of S14 Middle S12 Downstream S13 Upstream of Huangansi section of of Huangansi Shizigang Location Drainage Shizigang S15 Downstream of Shizigang Evaluation Drainage Canal Drainage Canal (GB15618-199Cl Monitoring Canal Drainage Canal Drainage Canal dredging index dredging section dredging section ass III item dredging dredging section section (Sampling depth: 20m) (Sampling depth: (Sampling depth: section (Sampling depth: 20m) 20m) (Sampling 20m) depth: 20m) Monitored value 7.1 6.9 7.3 7.2 7.1 PI index / / / / / pH >6.5 Noncompliance / / / / / multiple Monitored value 136 128 46 96 109 PI index 0.34 0.32 0.115 0.24 0.272 Copper 400 Noncompliance 0 0 0 0 0 multiple Monitored value 598 546 221 571 637 PI index 1.19 1.09 0.442 1.14 1.27 Zinc 500 Noncompliance 0.19 0.09 0 0.14 0.27 multiple Monitored value 140 159 99.3 223 191 PI index 0.28 0.318 0.198 0.446 0.382 Plumbum 500 Noncompliance 0 0 0 0 0 multiple - 544 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 2.93 2.73 0.92 2.12 2.60 PI index 2.93 2.73 0.92 2.12 2.60 Cadmium 1.0 Noncompliance 1.93 1.73 0 1.12 1.6 multiple Monitored value 56.4 62.2 51.0 85.4 85.6 PI index 1.41 1.555 1.275 2.135 2.14 Arsenic 40 Noncompliance 0.41 0.555 0.275 1.135 1.14 multiple Monitored value 0.346 0.371 0.220 1.19 2.22 PI index 0.23 0.247 0.147 0.79 1.48 Hg 1.5 Noncompliance 0 0 0 0 0.48 multiple Monitored value 129 142 69 135 150 PI index 0.43 0.473 0.23 0.45 0.5 Total Cr 300 Noncompliance 0 0 0 0 0 multiple S16 500m S18 50m upstream of Fanglin downstream S17 300m S17 300m S18 50m Power Station on the right of Lingfeng upstream of upstream of upstream of bank Location Evaluation Bridge on Lingfeng Bridge Lingfeng Bridge Fanglin Power (GB15618-199Cl Monitoring index the right on the left bank on the right bank Station on the left Sampling ass III item Sampling bank (Sampling (Sampling depth: bank (Sampling depth: depth:110cm (Sampling depth:10cm) 20m) depth: 20m) 20cm depth: 20m) - 545 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 8.3 8.1 8.3 8.1 8.1 8.3 PI index / / / / / / pH >6.5 Noncompliance / / / / / / multiple Monitored value 49 52 83 78 85 73 PI index 0.123 0.13 0.208 0.195 0.213 0.183 Copper 400 Noncompliance 0 0 0 0 0 0 multiple Monitored value 183 232 286 283 283 272 PI index 0.366 0.464 0.572 0.566 0.566 0.544 Zinc 500 Noncompliance 0 0 0 0 0 0 multiple Monitored value 41.2 59.2 49.8 61.7 56.3 59.1 PI index 0.082 0.118 0.100 0.123 0.113 0.118 Plumbum 500 Noncompliance 0 0 0 0 0 0 multiple Monitored value 0.53 0.30 1.14 1.08 1.42 2.24 PI index 0.53 0.30 1.14 1.08 1.42 2.24 Cadmium 1.0 Noncompliance 0 0 0.14 0.08 0.42 1.24 multiple Monitored value 35.6 39.2 50.0 65.2 58.8 36.7 PI index 0.89 0.98 1.25 1.63 1.463 0.918 Arsenic 40 Noncompliance 0 0 0.25 0.63 0.463 0 multiple - 546 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 0.232 0.213 0.523 0.636 0.272 0.183 PI index 0.155 0.142 0.349 0.424 0.181 0.122 Hg 1.5 Noncompliance 0 0 0 0 0 0 multiple Monitored value 37 58 45 52 42 41 PI index 0.123 0.193 0.15 0.173 0.14 0.137 Total Cr 300 Noncompliance 0 0 0 0 0 0 multiple S19 1000m S19 1000m upstream of Fanglin upstream of Power Station on the right bank S20 2000m Fanglin upstream of S20 2000m upstream of Location Evaluation Power Fanglin Power Fanglin Power Station on the (GB15618-199G Monitoring index Station on Sampling depth: Sampling depth: Station on the left right bank rade III item the left bank 20cm 100cm bank(Sampling Sampling depth: 20cm (Sampling depth: 20) depth: 20m) Monitored value 8.2 8.0 8.0 8.0 8.0 PI index / / / / / pH >6.5 Noncompliance / / / / / multiple Monitored value 56 82 82 124 63 PI index 0.14 0.205 0.205 0.31 0.158 Copper 400 Noncompliance 0 0 0 0 0 multiple - 547 - Table 8 Sediment Monitoring and Analysis Results Unit: mg/kg Location S1 100M downstream S3 100m of S2 Lingfeng downstream of S4 Dredging confluence Bridge cross confluence of section of East S5 Dredging section of East Evaluation (GB15618-199Cl of Huangansi section of He Shizigang River Trunk Canal No. 5 Branch Canal (Sampling index ass III River into He River (Sampling into He River (Sampling depth: depth: 20m) River depth: 20m) (Sampling depth: 20m) Monitoring (Sampling 20m) item depth: 20m) Monitored value 244 286 251 312 247 PI index 0.488 0.572 0.502 0.624 0.494 Zinc 500 Noncompliance 0 0 0 0 0 multiple Monitored value 65.4 57.4 54.1 59.7 64.8 PI index 0.131 0.115 0.108 0.119 0.130 Plumbum 500 Noncompliance 0 0 0 0 0 multiple Monitored value 0.82 1.32 1.79 1.91 1.98 PI index 0.82 1.32 1.79 1.91 1.98 Cadmium 1.0 Noncompliance 0 0.32 0.79 0.91 0.98 multiple Monitored value 45.2 48.2 75.2 76.2 91.8 PI index 1.13 1.205 1.88 1.905 2.295 Arsenic 40 Noncompliance 0.13 0.205 0.88 0.905 1.295 multiple Monitored value 0.212 0.182 0.183 0.220 0.188 PI index 0.141 0.121 0.122 0.147 0.125 Hg 1.5 Noncompliance 0 0 0 0 0 multiple Monitored value 48 43 23 41 22 PI index 0.16 0.143 0.077 0.137 0.073 Total Cr 300 Noncompliance 0 0 0 0 0 multiple - 548 - - 549 - Table 9 River Sediment Toxity Leaching Results Unit: mg/L Monitoring item Evaluation index Plumbum Cadmium Arsenic Hg Cr6+ Monitoring site S1 100M downstream of Monitored value ND ND ND ND 0.01 the confluence of GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Huangansi River into He standard value River (Sampling depth: Status of standard compliance Compliant Compliant Compliant Compliant Compliant 20m) Monitored value 0.51 0.014 ND ND 0.02 S2 Lingfeng Bridge cross GB5085.3-2007 Leaching toxity section of He River 5 1 5 0.1 5 standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S3100M downstream of Monitored value ND ND ND ND 0.02 the confluence of GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Shizigang River into He standard value River (Sampling depth: Status of standard compliance Compliant Compliant Compliant Compliant Compliant 20m) Monitored value ND ND ND ND 0.01 S4 Dredging section of GB5085.3-2007 Leaching toxity Donggan Canal (Sampling 5 1 5 0.1 5 standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant Monitored value ND ND ND ND 0.01 S5 dredging section of GB5085.3-2007 Leaching toxity East No. 5 Branch Canal 5 1 5 0.1 5 standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant Monitored value 0.86 0.037 ND ND 0.01 S6 downstream of GB5085.3-2007 Leaching toxity dredging section of East 5 1 5 0.1 5 standard value No. 5 Branch Canal Status of standard compliance Compliant Compliant Compliant Compliant Compliant Monitored value 0.26 0.031 ND 0.001 0.02 S7 dredging section of GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 East No. 6 Branch Canal standard value Status of standard compliance Compliant Compliant Compliant Compliant Compliant S8 dredging section of Monitored value ND ND ND ND ND - 550 - Table 9 River Sediment Toxity Leaching Results Unit: mg/L Monitoring item Evaluation index Plumbum Cadmium Arsenic Hg Cr6+ Monitoring site Huangtian Branch Canal GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 (Sampling depth: 20m) standard value Status of standard compliance Compliant Compliant Compliant Compliant Compliant S9 dredging section of Monitored value ND ND ND ND 0.01 Guposhan Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal (Sampling depth: standard value 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant Monitored value ND ND ND 0.01 0.10 S10 dredging section of GB5085.3-2007 Leaching toxity Taoyuan Drainage Canal 5 1 5 0.1 5 standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S11Upstream of Monitored value ND ND ND 0.01 0.10 Huangansi Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal dredging section standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S12Downstream of Monitored value ND ND ND 0.001 0.01 Huangansi Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal dredging section standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S13 dredging section of Monitored value 0.83 0.034 ND ND 0.02 Shizigang Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal (Sampling depth: standard value 20m) upstream Status of standard compliance Compliant Compliant Compliant Compliant Compliant S14Middle section of Monitored value ND ND ND ND 0.02 Shizigang Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal dredging section standard value (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S15Downstream of Monitored value ND ND ND ND 0.04 Shizigang Drainage GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 Canal dredging section standard value - 551 - Table 9 River Sediment Toxity Leaching Results Unit: mg/L Monitoring item Evaluation index Plumbum Cadmium Arsenic Hg Cr6+ Monitoring site (Sampling depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S16500m downstream of Monitored value ND ND 0.0014 ND ND Lingfeng Bridge on the GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 right bank(Sampling standard value depth:10cm) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S17300m upstream of Monitored value ND ND 0.0003 ND ND Lingfeng Bridge on the GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 left bank (Sampling depth: standard value 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S17300m upstream of Monitored value ND ND 0.0015 0.00004 ND Lingfeng Bridge on the GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 right bank (Sampling standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S1850m upstream of Monitored value ND ND 0.0009 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the left bank (Sampling standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S1850m upstream of Monitored value ND ND 0.0012 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the right bank (Sampling standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S1850m upstream of Monitored value ND ND 0.0019 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the right bank(Sampling standard value depth:110cm) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S191000m upstream of Monitored value ND ND 0.0005 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the left bank (Sampling standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S191000m upstream of Monitored value ND ND 0.0013 ND ND - 552 - Table 9 River Sediment Toxity Leaching Results Unit: mg/L Monitoring item Evaluation index Plumbum Cadmium Arsenic Hg Cr6+ Monitoring site Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the right bank (Sampling standard value depth: 20m) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S191000m upstream of Monitored value ND ND 0.0022 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the right bank(Sampling standard value depth: 100cm) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S202000m upstream of Monitored value ND ND 0.0017 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the left bank(Sampling standard value depth: 20) Status of standard compliance Compliant Compliant Compliant Compliant Compliant S202000m upstream of Monitored value ND ND 0.0024 ND ND Fanglin Power Station on GB5085.3-2007 Leaching toxity 5 1 5 0.1 5 the left bank(Sampling standard value depth: 20) Status of standard compliance Compliant Compliant Compliant Compliant Compliant Note: When the test result is smaller than the method detection limit, the result is indicated as ND. - 553 - Annex 2:Surface Water Impact Prediction Process I. Prediction of impacts on water environment with normal discharge He River is the only destination of effluent discharge for Jiangnan Wastewater Treatment Plant. The hydrological parameters of flow rate, river width, river depth, and slope used in the prediction are cited from "Water Environment Capacity Research Report of Guangxi Zhuang Autonomous Region" prepared by the Environmental Science Research Institute of Guangxi Zhuang Autonomous Region affiliated to China Academy of Environmental Science. The prediction models as selected are the two-dimensional steady-state mixed attenuation model for shore discharge and the S-P model for fully mixed section recommended in HJ / T2.3-93 "Technical Guidelines of Environmental Impact Assessment - Surface Water Environment", as described as follows: (1)Mixing Section Two-dimensional steady-state mixed attenuation model for shore discharge: x c pQp uy 2 u (2 B  y ) 2 c( x, y )  exp(  K1 ){ch  [exp(  )  exp(  )]} 86400u H �M y xu 4M y x 4M y x The length estimation equation for the mixing section (shore discharge) is: (0.4 B  0.6a) Bu l 。 (0.058H  0.0065B)( gHI )1 / 2 Where: c --- concentration of pollutants on the predicted cross section, mg/L; c0 --- concentration of pollutants at the initial computation point, mg/L; K1 --- self-purification (pollutant degradation) coefficient, l/d; U --- average cross-sectional flow rate, m/s; x --- distance between the upper and lower cross sections, m; y --- horizontal distance perpendicular to the river direction; m; cp --- pollutant discharge concentration, mg/L; Qp --- wastewater discharge volume, m3/s; ch --- existing pollutant concentration in the river (upper reaches), mg/L; Qh --- river flow, m3/s; I --- river gradient, m/m; H --- water depth, m; B --- river width, m; My --- horizontal mixing coefficient, m2/s; a --- distance from discharge outlet to river shore, m; g --- gravity acceleration, m/s2; - 554 - (2)Fully mixed river section S-P Model is selected: x c  c0 exp(  K1 ) 86400u c0  (c p Q p  ch Qh ) /(Q p  Qh ) See Table 1 for values and sources of the aforesaid parameters. Table 1: Values and Sources of Parameters Needed in Prediction SN Parameter Value Source K1 is valued at 0.2 for prediction of COD Surface Water Capacity 1 K1 and 0.1 for prediction of NH3-N. Research Report for Guangxi Zhuang Autonomous Region Surface Water Capacity 2 u 0.1m/s Research Report for Guangxi Zhuang Autonomous Region Class 1A discharge limit specified cp is valued at 50mg/L for prediction of in the Pollutant Discharge 3 cp COD and 5mg/L for prediction of NH3-N. Standard for Municipal WWTPs (GB18918-2002) ch is valued at 10mg/L for prediction of Maximum value of existing COD and 0.277mg/L for prediction of 4 ch environment quality monitoring NH3-N at the upper reaches of the data discharge outlet of Jiangnan WWTP. Surface Water Capacity Research Report for Guangxi Qh is valued at 20.5 m3/s at the discharge 5 Qh Zhuang Autonomous Region, outlet of Jiangnan WWTP. flow rate with an assurance rate of 90% Calculated at the design day Qp is valued at 0.1736m3/s for Jiangnan 6 Qp treatment capacity and a daily WWTP. operation time of 24h Surface Water Capacity 7 I 0.00045m/m Research Report for Guangxi Zhuang Autonomous Region Surface Water Capacity 8 H 2.5m Research Report for Guangxi Zhuang Autonomous Region 9 B 70m Surface Water Capacity - 555 - Table 1: Values and Sources of Parameters Needed in Prediction SN Parameter Value Source Research Report for Guangxi Zhuang Autonomous Region 10 My 0.063m2/s Calculated with Taylor Method Discharge outlet is located on 11 a 0m river shore; thus valued at 0 Constant value of gravity 12 g 9.8m/s2 acceleration The calculation result for the mixing section at the lower reaches of the pollutant discharge outlet of Jiangnan WWTP is 3111m. See Table 2 and Table 3 for the prediction results. Table 2: Prediction of COD Concentrations of Jiangnan WWTP in Normal Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 1 34.6786 9.9998 9.9998 9.9998 9.9998 9.9998 9.9998 9.9998 10 17.8007 10.1457 9.9982 9.9982 9.9982 9.9982 9.9982 9.9982 20 15.5123 10.7549 9.9984 9.9964 9.9964 9.9964 9.9964 9.9964 30 14.4973 11.1941 10.0173 9.9947 9.9946 9.9946 9.9946 9.9946 40 13.8914 11.4385 10.0665 9.9933 9.9928 9.9928 9.9928 9.9928 50 13.4772 11.5674 10.1368 9.9938 9.9910 9.9910 9.9910 9.9910 60 13.1709 11.6314 10.2150 9.9975 9.9893 9.9892 9.9892 9.9892 70 12.9324 11.6581 10.2924 10.0054 9.9878 9.9875 9.9875 9.9875 80 12.7398 11.6628 10.3644 10.0174 9.9867 9.9857 9.9857 9.9857 90 12.5799 11.6543 10.4289 10.0330 9.9861 9.9839 9.9839 9.9839 100 12.4443 11.6378 10.4856 10.0513 9.9864 9.9822 9.9821 9.9821 120 12.2252 11.5926 10.5770 10.0931 9.9898 9.9791 9.9785 9.9785 140 12.0540 11.5408 10.6440 10.1371 9.9972 9.9767 9.9750 9.9749 160 11.9152 11.4882 10.6922 10.1799 10.0081 9.9753 9.9716 9.9714 180 11.7996 11.4372 10.7262 10.2197 10.0216 9.9752 9.9684 9.9679 200 11.7013 11.3886 10.7497 10.2555 10.0368 9.9764 9.9656 9.9644 220 11.6161 11.3429 10.7652 10.2871 10.0530 9.9789 9.9632 9.9611 240 11.5413 11.2999 10.7748 10.3148 10.0695 9.9825 9.9612 9.9580 260 11.4749 11.2595 10.7797 10.3387 10.0858 9.9870 9.9598 9.9552 280 11.4153 11.2217 10.7812 10.3592 10.1017 9.9923 9.9590 9.9528 300 11.3614 11.1861 10.7800 10.3767 10.1168 9.9982 9.9588 9.9507 500 11.0018 10.9186 10.7051 10.4450 10.2177 10.0626 9.9803 9.9555 700 10.7933 10.7427 10.6073 10.4275 10.2492 10.1072 10.0191 9.9896 900 10.6461 10.6117 10.5171 10.3859 10.2480 10.1305 10.0529 10.0260 1100 10.5312 10.5065 10.4372 10.3387 10.2322 10.1386 10.0753 10.0529 - 556 - Table 2: Prediction of COD Concentrations of Jiangnan WWTP in Normal Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 1300 10.4362 10.4184 10.3664 10.2915 10.2092 10.1360 10.0858 10.0680 1500 10.3545 10.3420 10.3029 10.2457 10.1823 10.1255 10.0863 10.0723 1700 10.2824 10.2744 10.2452 10.2016 10.1529 10.1090 10.0786 10.0677 1900 10.2175 10.2131 10.1918 10.1589 10.1216 10.0879 10.0644 10.0561 2100 10.1580 10.1568 10.1418 10.1173 10.0890 10.0632 10.0453 10.0388 2300 10.1028 10.1043 10.0943 10.0765 10.0554 10.0359 10.0222 10.0173 2500 10.0509 10.0547 10.0489 10.0364 10.0210 10.0064 9.9961 9.9924 2700 10.0018 10.0075 10.0050 9.9968 9.9859 9.9752 9.9676 9.9649 2900 9.9548 9.9621 9.9624 9.9577 9.9503 9.9428 9.9373 9.9353 3100 9.9096 9.9182 9.9208 9.9188 9.9143 9.9094 9.9056 9.9042 3500 9.8234 9.8340 9.8398 9.8420 9.8417 9.8403 9.8390 9.8385 4000 9.7214 9.7335 9.7419 9.7472 9.7502 9.7516 9.7522 9.7523 4500 9.6239 9.6368 9.6467 9.6538 9.6587 9.6617 9.6634 9.6639 5000 9.5297 9.5429 9.5535 9.5616 9.5676 9.5716 9.5739 9.5746 - 557 - Table 3 Prediction of NH3-N Concentrations of Jiangnan WWTP in Normal Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 1 2.7449 0.2770 0.2770 0.2770 0.2770 0.2770 0.2770 0.2770 10 1.0573 0.2917 0.2770 0.2770 0.2770 0.2770 0.2770 0.2770 20 0.8287 0.3528 0.2771 0.2769 0.2769 0.2769 0.2769 0.2769 30 0.7273 0.3969 0.2792 0.2769 0.2769 0.2769 0.2769 0.2769 40 0.6669 0.4215 0.2843 0.2769 0.2769 0.2769 0.2769 0.2769 50 0.6257 0.4346 0.2914 0.2771 0.2769 0.2768 0.2768 0.2768 60 0.5952 0.4412 0.2994 0.2776 0.2768 0.2768 0.2768 0.2768 70 0.5715 0.4440 0.3073 0.2786 0.2768 0.2768 0.2768 0.2768 80 0.5524 0.4446 0.3147 0.2799 0.2769 0.2768 0.2768 0.2768 90 0.5366 0.4439 0.3213 0.2816 0.2770 0.2767 0.2767 0.2767 100 0.5232 0.4425 0.3271 0.2836 0.2771 0.2767 0.2767 0.2767 120 0.5016 0.4383 0.3366 0.2881 0.2778 0.2767 0.2766 0.2766 140 0.4848 0.4334 0.3436 0.2928 0.2788 0.2768 0.2766 0.2766 160 0.4713 0.4285 0.3487 0.2974 0.2802 0.2769 0.2765 0.2765 180 0.4600 0.4237 0.3525 0.3017 0.2819 0.2772 0.2765 0.2765 200 0.4505 0.4192 0.3551 0.3056 0.2837 0.2776 0.2765 0.2764 220 0.4423 0.4149 0.3570 0.3091 0.2856 0.2782 0.2766 0.2764 240 0.4351 0.4109 0.3583 0.3121 0.2876 0.2788 0.2767 0.2764 260 0.4288 0.4072 0.3591 0.3149 0.2895 0.2796 0.2769 0.2764 280 0.4232 0.4037 0.3596 0.3172 0.2914 0.2804 0.2771 0.2764 300 0.4181 0.4005 0.3597 0.3193 0.2932 0.2813 0.2773 0.2765 500 0.3852 0.3769 0.3554 0.3292 0.3064 0.2908 0.2825 0.2800 700 0.3674 0.3623 0.3487 0.3305 0.3126 0.2983 0.2894 0.2864 900 0.3557 0.3522 0.3427 0.3294 0.3155 0.3036 0.2958 0.2931 1100 0.3472 0.3447 0.3377 0.3277 0.3169 0.3075 0.3010 0.2988 1300 0.3407 0.3389 0.3336 0.3260 0.3177 0.3102 0.3051 0.3033 1500 0.3355 0.3342 0.3302 0.3244 0.3180 0.3122 0.3082 0.3068 1700 0.3312 0.3304 0.3274 0.3230 0.3180 0.3135 0.3104 0.3093 1900 0.3276 0.3272 0.3250 0.3216 0.3178 0.3144 0.3120 0.3111 2100 0.3246 0.3245 0.3229 0.3204 0.3175 0.3149 0.3130 0.3124 2300 0.3220 0.3221 0.3211 0.3193 0.3171 0.3151 0.3137 0.3132 2500 0.3196 0.3200 0.3194 0.3181 0.3166 0.3151 0.3140 0.3136 2700 0.3176 0.3182 0.3179 0.3171 0.3159 0.3148 0.3141 0.3138 2900 0.3157 0.3165 0.3165 0.3160 0.3153 0.3145 0.3139 0.3137 3100 0.3140 0.3149 0.3152 0.3150 0.3145 0.3140 0.3136 0.3135 3500 0.3110 0.3121 0.3128 0.3130 0.3129 0.3128 0.3127 0.3126 4000 0.3078 0.3090 0.3099 0.3105 0.3108 0.3109 0.3110 0.3110 4500 0.3049 0.3062 0.3073 0.3080 0.3085 0.3089 0.3090 0.3091 5000 0.3022 0.3036 0.3047 0.3056 0.3062 0.3067 0.3069 0.3070 11000 0.2767 0.2777 0.2785 0.2792 0.2798 0.2802 0.2804 0.2805 - 558 - II. Prediction of impacts on water environment in the scenario of accidental discharge In the prediction of the impacts on rivers by the direct discharge of untreated wastewater, He River is the destination of discharge of Jiangnan WWTP Subproject. Based on the scale of He River, the two-dimensional steady-state mixed attenuation model for shore discharge and the S-P model for fully mixed section recommended in HJ / T2.3-93 "Technical Guidelines of Environmental Impact Assessment - Surface Water Environment" are selected as the prediction models. In the accidental discharge scenario for Jiangnan WWTP, the prediction is conducted on the assumption that wastewater is discharged without prior treatment (i.e. at the design influent concentration of WWTP). (1)Fully mixed river section S-P model is adopted: x c  c0 exp(  K1 ) 86400u c0  (c p Q p  ch Qh ) /(Q p  Qh ) (2)Mixing section Two-dimensional steady-state mixed attenuation model for shore discharge: x c pQp uy 2 u (2 B  y ) 2 c( x, y )  exp(  K1 ){ch  [exp(  )  exp(  )]} 86400u H �M y xu 4M y x 4M y x (0.4 B  0.6a) Bu l ; Calculation result of the length of the mixing (0.058H  0.0065B)( gHI )1 / 2 section is 3111m. Where: c --- concentration of pollutants on the predicted cross section, mg/L; c0 --- concentration of pollutants at the initial computation point, mg/L; K1 --- self-purification (pollutant degradation) coefficient, l/d, valued at 0.2/d for COD and 0.1/d for NH3-N; U --- average cross-sectional flow rate (m/s), both valued at 0.1 m/s; x --- distance between the upper and lower cross sections (km); cp --- pollutant discharge concentration, mg/L; the discharge concentration in the accidental discharge scenario is valued at 280mg/L for COD and 32mg/L for NH3-N; Qp --- wastewater discharge volume, m3/s; valued at 0.1736m3/s at the discharge outlet of Jiangnan WWTP; ch --- existing pollutant concentration in the river (upper reaches), mg/L; valued at 11mg/L for COD and 0.313mg/L for NH3-N at the upper reaches of the discharge outlet of Jiangnan WWTP; - 559 - Qh --- river flow, m3/s; valued at 20.5m3/s at the discharge outlet of Jiangnan WWTP; I --- river gradient, m/m; valued at 0.00045/m/m; H --- water depth, m; valued at 2.5m; B --- river width, m; all valued at 70m; My --- horizontal mixing coefficient, m2/s; result of calculation in Taylor Method is 0.063m2/s; a --- distance from discharge outlet to river shore, m; valued at 0; g --- gravity acceleration, m/s2; valued at 9.8m/s2; Table 4 and Table 5 show the results of prediction for the accidental discharge scenario of Jiangnan WWTP based on the aforesaid models and parameters. Table 4 Prediction of COD Concentrations of Jiangnan WWTP in Accidental Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 1 149.2012 10.9998 10.9998 10.9998 10.9998 10.9998 10.9998 10.9998 10 54.6915 11.8236 10.9975 10.9975 10.9975 10.9975 10.9975 10.9975 20 41.8841 15.2422 11.0060 10.9949 10.9949 10.9949 10.9949 10.9949 30 36.2074 17.7097 11.1194 10.9925 10.9924 10.9924 10.9924 10.9924 40 32.8217 19.0853 11.4026 10.9927 10.9898 10.9898 10.9898 10.9898 50 30.5098 19.8152 11.8035 11.0027 10.9873 10.9873 10.9873 10.9873 60 28.8021 20.181 12.2492 11.0311 10.9852 10.9847 10.9847 10.9847 70 27.4741 20.3378 12.6901 11.0825 10.9841 10.9822 10.9822 10.9822 80 26.4028 20.3715 13.1003 11.1572 10.9852 10.9797 10.9797 10.9797 90 25.5148 20.3314 13.4691 11.2520 10.9897 10.9773 10.9771 10.9771 100 24.7631 20.2467 13.7940 11.3622 10.9987 10.9752 10.9746 10.9746 120 23.5508 20.0083 14.3212 11.6110 11.0329 10.9727 10.9696 10.9695 140 22.6070 19.7334 14.7112 11.8726 11.0893 10.9742 10.9648 10.9644 160 21.8450 19.4539 14.9959 12.1274 11.1651 10.9814 10.9608 10.9595 180 21.2126 19.183 15.2014 12.3648 11.2557 10.9957 10.9579 10.9547 200 20.6766 18.926 15.3478 12.5803 11.3559 11.0174 10.9569 10.9504 220 20.2146 18.6845 15.4498 12.7725 11.4614 11.0462 10.9582 10.9468 240 19.8107 18.4587 15.5181 12.9423 11.5687 11.0812 10.9624 10.9444 260 19.4537 18.2477 15.5608 13.0911 11.6751 11.1217 10.9695 10.9436 280 19.1349 18.0506 15.5840 13.2208 11.7788 11.1664 10.9798 10.9448 300 18.8479 17.8661 15.5922 13.3334 11.8785 11.2143 10.9933 10.9482 500 16.9830 16.5169 15.3212 13.8647 12.5916 11.7234 11.2623 11.1235 700 15.9630 15.6800 14.9216 13.9143 12.9159 12.1211 11.6275 11.4623 900 15.2858 15.0931 14.5634 13.8289 13.0564 12.3985 11.9642 11.8134 1100 14.7892 14.6509 14.2624 13.7111 13.1144 12.5906 12.2357 12.1105 1300 14.4028 14.3030 14.0117 13.5925 13.1319 12.7218 12.4407 12.3409 1500 14.0906 14.0207 13.8015 13.4814 13.1264 12.8079 12.5884 12.5102 1700 13.8314 13.7862 13.6227 13.3788 13.1060 12.8599 12.6897 12.6290 1900 13.6115 13.5871 13.4676 13.2833 13.0748 12.8856 12.7544 12.7075 - 560 - Table 4 Prediction of COD Concentrations of Jiangnan WWTP in Accidental Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 2100 13.4216 13.4149 13.3307 13.1935 13.0354 12.8909 12.7903 12.7543 2300 13.2549 13.2633 13.2076 13.1078 12.9896 12.8802 12.8036 12.7761 2500 13.1064 13.1275 13.0950 13.0251 12.9385 12.8569 12.7992 12.7785 2700 12.9723 13.0041 12.9905 12.9446 12.8832 12.8236 12.7810 12.7655 2900 12.8498 12.8906 12.8923 12.8658 12.8245 12.7825 12.7518 12.7406 3100 12.7366 12.7848 12.7990 12.7882 12.7631 12.7351 12.7139 12.7061 Table 5 Prediction of NH3-N Concentrations of Jiangnan WWTP in Accidental Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 1 16.1076 0.3130 0.3130 0.3130 0.3130 0.3130 0.3130 0.3130 10 5.3071 0.4074 0.3130 0.3130 0.3130 0.3130 0.3130 0.3130 20 3.8439 0.7984 0.3142 0.3129 0.3129 0.3129 0.3129 0.3129 30 3.1956 1.0809 0.3274 0.3129 0.3129 0.3129 0.3129 0.3129 40 2.8091 1.2385 0.3600 0.3132 0.3129 0.3129 0.3129 0.3129 50 2.5453 1.3223 0.4062 0.3146 0.3128 0.3128 0.3128 0.3128 60 2.3505 1.3645 0.4574 0.3181 0.3128 0.3128 0.3128 0.3128 70 2.1991 1.3828 0.5081 0.3242 0.3130 0.3127 0.3127 0.3127 80 2.0770 1.3871 0.5553 0.3330 0.3133 0.3127 0.3127 0.3127 90 1.9759 1.3828 0.5978 0.3441 0.3141 0.3127 0.3127 0.3127 100 1.8903 1.3735 0.6352 0.3570 0.3154 0.3127 0.3126 0.3126 120 1.7524 1.3470 0.6961 0.3860 0.3198 0.3129 0.3126 0.3126 140 1.6452 1.3163 0.7414 0.4165 0.3268 0.3136 0.3125 0.3125 160 1.5588 1.2850 0.7746 0.4462 0.3360 0.3149 0.3126 0.3124 180 1.4872 1.2547 0.7988 0.4739 0.3469 0.3171 0.3128 0.3124 200 1.4266 1.2260 0.8161 0.4991 0.3589 0.3201 0.3132 0.3124 220 1.3744 1.1991 0.8284 0.5217 0.3715 0.3239 0.3138 0.3125 240 1.3289 1.1739 0.8369 0.5417 0.3843 0.3284 0.3148 0.3127 260 1.2887 1.1504 0.8424 0.5593 0.3970 0.3336 0.3161 0.3132 280 1.2529 1.1285 0.8457 0.5748 0.4094 0.3392 0.3178 0.3138 300 1.2207 1.1081 0.8473 0.5882 0.4214 0.3452 0.3199 0.3147 500 1.0135 0.9599 0.8225 0.6550 0.5087 0.4089 0.3559 0.3399 700 0.9027 0.8701 0.7827 0.6666 0.5516 0.4600 0.4031 0.3841 900 0.8309 0.8086 0.7475 0.6626 0.5734 0.4974 0.4473 0.4299 1100 0.7796 0.7636 0.7187 0.6549 0.5858 0.5252 0.4841 0.4696 1300 0.7409 0.7294 0.6956 0.6469 0.5935 0.5459 0.5133 0.5017 1500 0.7107 0.7025 0.6770 0.6398 0.5985 0.5615 0.5360 0.5269 1700 0.6864 0.6811 0.6621 0.6336 0.6018 0.5732 0.5533 0.5463 1900 0.6666 0.6637 0.6498 0.6282 0.6039 0.5818 0.5664 0.5610 2100 0.6502 0.6494 0.6395 0.6235 0.6049 0.5880 0.5762 0.5720 - 561 - Table 5 Prediction of NH3-N Concentrations of Jiangnan WWTP in Accidental Discharge Scenario Y(m) 0 10 20 30 40 50 60 70 X(m) 2300 0.6364 0.6374 0.6308 0.6191 0.6052 0.5924 0.5834 0.5802 2500 0.6246 0.6271 0.6233 0.6151 0.6049 0.5953 0.5885 0.5861 2700 0.6145 0.6183 0.6167 0.6113 0.6040 0.5970 0.5920 0.5901 2900 0.6057 0.6105 0.6107 0.6076 0.6027 0.5977 0.5941 0.5928 3100 0.5979 0.6036 0.6053 0.6040 0.6011 0.5977 0.5952 0.5943 - 562 - Annex 3:Public Participation Questionnaire and Feedbacks 1. Feedbacks of Hezhou Municipal Press, Publication, Radio, Film and Television Bureau on Preservation of Xiyue Street Suggestions on Preservation of the Riverside Historical Heritage of Xiyue Street Xiyue Street is a well-known historical and cultural street in Hezhou. This street block took shape in late Qing Dynasty and reached its heyday in the Minguo era, when, in particular during the period of Anti-Japanese War, hosted a large group of historical and cultural elites of China. With many ancient wharves, ancient ferries and ancient bridges and ancient trees along the river, the old communities of Hebianxiang Street, Sha Street and Xiyue Street hosted historical and cultural elite, such as He Xiangning, Liu Yazi, let alone the large number of historical architectures and cultural relics, e.g. the former residence of the famous Hong Kong film director Liu Shiyu, Liujiadianpu and Liu Yazi and the Xianfeng Bookstore where Zhang Tiesheng and Chen Cisheng covered in the World Affairs used to live. Xiyue Street is a miniature of the history of city development of Hezhou City and is a museum of the fresh history of Hezhou that records in the true sense the evolution of urban history and carries the context of historical development of Hezhou. In July 2015, Hezhou initiated the declaration for national historical and cultural cities and Xiyue Street is one of the three historical and cultural blocks included in the declaration. The ancient embankment of the section of Shajie Wharf has been covered by the newly constructed flood control embankment. Hopefully, the surviving ancient wharves, bridges and embankment will be preserved to the best possibility in the project design and construction in the future. In such a context, the following recommendations are made: 1) The project design shall, to the maximum possibility, avoid the declared scope for preservation of the national historically famous city to preserve the ancient wharf, ancient embankment, ancient bridges and ancient trees along the river and protect the cultural heritage of Hezhou. 2) During the planning design of areas around Xiyue Street, the suggestions and advices proposed by Hezhou Office of Declaration of National Historical and Cultural City shall be incorporated and no construction activities shall be commenced until such planning design is reviewed and approved by the Municipal Government. Annex buildings of and new buildings to be constructed within the declared scope of national historical and cultural city shall have consistent style with the existing historical and cultural block. 3) Reference to the advanced experiences from Yongzhou City of Hunan Province and Wuzhou City of Guangxi ZAR is recommended. The flood dike to be constructed should be moved towards the waterfront area and the existing dike and ancient wharf should be preserved. Antique waterfront bridges and aisles may be constructed along the river banks to cover the sewage drainage pipelines along the river and improve cityscape. 4) The design style of Wuzhou and Guilin for flood dykes are recommended and the mining culture, money casting culture and red revolution culture unique in Hezhou should be presented in the form of reliefs on the existing flood dykes to enrich the urban cultural heritage of Hezhou. Riverside environment improvement should be integrated with the comprehensive urban development to not only create a new leisure space for Hezhou, but also revitalize this old and historical street. - 563 - Hezhou Municipal Press, Publication, Radio, Film and Television Bureau February 25, 2017 - 564 - 2. Feedbacks by Hezhou Municipal Press, Publication, Radio, Film and Television Bureau (HPPRFTB) on Measures Proposed in the Report Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project EIA Public Participation Questionnaire (for HCPPRFTB) Name of Hezhou Municipal Culture, Press, Publication, Completed by Xiong Kaikuo organization Radio, Film and Television Bureau Address of Contact No. 233, Pinganxi Road, Hezhou 5126058 organization information Nature of ■ Government Number of 28 Position Section Chief organization □ Public institution employees Project overview: □ Enterprise This Project involves Babu □ District Others and Pinggui District of Hezhou City and mainly covers the drainage basins of the urban inland river and He River flowing through the urban center of Hezhou City. The Project comprises of three components, including: (1) Component 1: He River Flood Risk Improvement, which includes: (a) improvement and rehabilitation (or demolition) of a few small runoff hydropower stations on the main watercourse of He River to enhance flood discharge capacity; (b) appropriate widening of certain sections of the main watercourse of He River to increase the flood discharge capacity and build riverside green corridors; (c) enhancing and connecting East Trunk Canal and Mawei River to divert upstream flood from the northern part of the urban area to the downstream areas and build riverside green corridor to increase flood discharge capacity and reduce waterlogging risks in the urban center of Hezhou City; (2) Component 2: Urban Drainage and Wastewater Management, which includes: (1) rehabilitation of tributaries of urban inland rivers and construction of riverside green corridors to divert regional flood; (b) construction of stormwater pipeline and pump stations in selected areas; (c) construction of Jiangnan WWTP and main sewage pipelines; (3) Component 3: institutional capacity building and project management, which includes: (a) institutional capacity strengthening and (b) project management and supervision. Impact analysis: The construction activities of He River (Guangming Bridge – Lingfeng Bridge Section) Integrated Rehabilitation Subproject, Huangan Temple Drainage Canal Pump Station Subproject and Huangan Temple Drainage Canal Integrated Rehabilitation Subproject under the Project may generate impacts on the historical and cultural street of Xiyue Street. Countermeasures to be taken: 1. The buildings (structures) in the Xiyue Street neighborhood should be designed in such a way that they have a uniform style with the existing buildings and should not be constructed until an approval has been granted by the Municipal Government. 2. The construction area included in the project design should avoid, where possible, the area of preservation of the historical and cultural street so as to preserve the ancient buildings, ancient wharf, ancient embankment, ancient bridges and ancient trees and keep the historical background of this historical and cultural street. 3. The river rehabilitation works should take account of the city style and natural background so as to create a unique cityscape. 4. The competent authorities should be consulted before construction to develop a practical and effective program for cultural relics protection. 5. A detailed construction program should be developed before construction and signs should be erected on construction sites to indicate the nature, significance, scope and measures of preservation of the respective cultural relics as well as the contact person and contact information of the cultural relics protection administration body. 6. Where construction becomes inevitable in the area of cultural relics preservation, manual excavation must be selected and no excavators, pile drivers and other mechanical equipment should be used in order to reduce vibration impacts on cultural relics in the construction process. 7. Construction camps, temporary top soil stockpiling sites must not be located in the area of protection of cultural relics. 8. Large vehicles and plants are prohibited to enter the area of preservation of cultural relics. 9. The construction contractor should provide education on protection of cultural relics to the construction workers and keep the cultural relics as far away from the construction activities as possible to avoid human damages to such cultural relics. 10. Upon the discovery of any cultural relics in the construction process, the construction activities should be suspended immediately and a report submitted to local cultural relics administration authority. The construction activities shall not resume until a notice on work resumption is received. - 565 - Does your organization agree with the measures to be taken? Do you have any other comments or suggestions? Answer: We agree with the preservation measure to be taken and propose the addition of one more measure, i.e. “10. Preservation of the historical buildings on Xiyue Historical and Cultural Street should be carried out in reference to the standards for cultural relics�. What is your organization’s attitude towards the construction of the Project from the general perspective of loca l economic development and environmental protection? Answer: Supportive. Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: - 566 - 3. Feedbacks by Hezhou Municipal Culture Press, Publication, Radio, Film and Television Bureau (HCPPRFTB) on Measures Proposed in the Report Guangxi Hezhou Urban Water Infrastructure & Environment Improvement Project EIA Public Participation Questionnaire (for HCPPRFTB) Name of Hezhou Municipal Culture, Press, Publication, Completed by Xiong Kaikuo organization Radio, Film and Television Bureau Address of Contact No. 233, Pinganxi Road, Hezhou 5126058 organization information Nature of ■ Government Number of 28 Position Section Chief organization □ Public institution employees Project overview: □ Enterprise This Project involves Babu □ District Others and Pinggui District of Hezhou City and mainly covers the drainage basins of the urban inland river and He River flowing through the urban center of Hezhou City. The Project comprises of three components, including: (1) Component 1: He River Flood Risk Improvement, which includes: (a) improvement and rehabilitation (or demolition) of a few small runoff hydropower stations on the main watercourse of He River to enhance flood discharge capacity; (b) appropriate widening of certain sections of the main watercourse of He River to increase the flood discharge capacity and build riverside green corridors; (c) enhancing and connecting East Trunk Canal and Mawei River to divert upstream flood from the northern part of the urban area to the downstream areas and build riverside green corridor to increase flood discharge capacity and reduce waterlogging risks in the urban center of Hezhou City; (2) Component 2: Urban Drainage and Wastewater Management, which includes: (1) rehabilitation of tributaries of urban inland rivers and construction of riverside green corridors to divert regional flood; (b) construction of stormwater pipeline and pump stations in selected areas; (c) construction of Jiangnan WWTP and main sewage pipelines; (3) Component 3: institutional capacity building and project management, which includes: (a) institutional capacity strengthening and (b) project management and supervision. Key problems: The CCP Babu Special Branch located in Xiadao Primary School belongs to the right of way of the Project. The former teaching building on the site was already destroyed and the only building preserved is a streetside building. In the 1980s, the “CCP Babu Sp ecial Branch Memorial� was built up on the former site. Due to urban development, it is difficult to preserve the former site and the proposed plan at present is to relocate the remaining school gate from the former site to a new location for preservation. Does your organization agree with the measures to be taken? Do you have any other comments or suggestions? Answer: We agree with the preservation measure to be taken and propose the addition of one more measure, i.e. “10. Preservation of the historical buildings on Xiyue Historical and Cultural Street should be carried out in reference to the standards for cultural relics�. Description of cultural relics: CCP Babu Special Branch Site Code: 451102805200000165 Year of construction: 1946, representative building of modern times According to Article 20 of the Cultural Relics Law, it is recommended that this site should be avoided to the best possibility. The CCP Babu Special Branch Site is a stronghold of CCP Babu Special Branch in the former Xiadao Primary School established in 1946 and served as the headquarter of the underground CCP leadership for Babu, Yongqing, Guiling, Nanxiang and Pinggui Mine District to spread revolutionary ideas to the massive teachers and students and local people and guide the youth towards the path of revolution. The Site of CCP Babu Special Branch is an important stronghold of activities in Hezhou in those years and - 567 - represents an important heritage of red revolution culture in Hezhou, thus embracing important value in development as a base of patriotism education and a destination of red culture tourism. What is your organization’s attitude towards the construction of the Project from the general perspective of local economic development and environmental protection? Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: - 568 - 4. Feedbacks by individual experts on preservation of CCP Babu Special Branch Site Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project EIA Public Participation Questionnaire (for individuals) Name of Hu Qingsheng Sex M Age 51 organization Occupation Preservation of cultural relics Education University Address Xiangyang Garden Residential Block Telephone 18077406926 Project overview: This Project involves Babu District and Pinggui District of Hezhou City and mainly covers the drainage basins of the urban inland river and He River flowing through the urban center of Hezhou City. The Project comprises of three components, including: (1) Component 1: He River Flood Risk Improvement, which includes: (a) improvement and rehabilitation (or demolition) of a few small runoff hydropower stations on the main watercourse of He River to enhance flood discharge capacity; (b) appropriate widening of certain sections of the main watercourse of He River to increase the flood discharge capacity and build riverside green corridors; (c) enhancing and connecting East Trunk Canal and Mawei River to divert upstream flood from the northern part of the urban area to the downstream areas and build riverside green corridor to increase flood discharge capacity and reduce waterlogging risks in the urban center of Hezhou City; (2) Component 2: Urban Drainage and Wastewater Management, which includes: (1) rehabilitation of tributaries of urban inland rivers and construction of riverside green corridors to divert regional flood; (b) construction of stormwater pipeline and pump stations in selected areas; (c) construction of Jiangnan WWTP and main sewage pipelines; (3) Component 3: institutional capacity building and project management, which includes: (a) institutional capacity strengthening and (b) project management and supervision. Certain environmental impacts will be generated in the construction stage of the Project, e.g. wastewater, exhaust gas, solid wastes and noises. The operation stage involves no discharge of “wastewater, exhaust gas and solid wastes� and the adverse environmental impacts will be relatively insignificant. The negative impacts to be generated in the construction stage of the Project on environment can be effectively controlled through effective pollution control measures. In order to assure successful implementation of the environmental protection activities in the Project, this EIA public participation survey is initiated for the Project under the relevant national laws and regulations on environmental protection. Please kindly complete the following questionnaire and present your valuable suggestions and comments. To us, your participation will be a powerful assurance to the success of our environmental protection activities. 1. Do you know about “Guangxi Hezhou Urban Water Infrastructure and Environment Improvement Project�? A. Yes; w about 2. Are you satisfied with the current status of water environment quality and flood drainage in Hezhou City? A. Satisfied; ■ B. Average; C. Not satisfied 3. What are the impacts that you think the Project may generate on your daily life in the construction stage? A. Environmental impact; B. employment (income); C. acquisition or occupation of homestead (farmland); D. others; ■E. insignificant impact 4. Which of the following environmental impact is, in your opinion, the most significant one from the construction of the Project? A. Air pollution; B. water pollution; C. Noise pollution; D. Solid wastes;■E. N/A 5. In which area do you think that greater efforts should be made under the Project in controlling environmental pollution (multiple choices are allowed)? A. Air pollution; ou think that greater efforts should be made under the Project in controlling enviro 6. How will the Project affect your daily life and work upon completion? - 569 - ■ow will the Project affect your daily life and work upon completion?the Pro 7. Do you think the Project will play a positive role in driving the harmonious development of economy and society? ■o you think the Project will play a positive role in 8. What is your attitude towards the construction of the Project based on the aforesaid knowledge? ■hat is your attitude towards the 9. What are your requests and suggestions on the environmental protection measures involved in the implementation process of the Project? I suggest that the CCP Babu Special Branch Site in Xiadao Primary School and the Diandengzhai Remains should be preserved on their original sites. Hezhou Research Institute of Environmental Science Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: Sept. 12, 2017 - 570 - 5. Feedbacks by Hezhou Municipal Engineering Bureau (HMEB) on Measures Proposed in the Report Guangxi Hezhou Urban Water Infrastructure & Environment Improvement Project EIA Public Participation Questionnaire (for Municipal Engineering Bureau) Name of Hezhou Municipal Engineering Bureau Completed by Zhao He organization Address of Contact No. 41, Jianshezhong Road, Babu District, Hezhou 5277701 organization information Nature of ■ Government Number of Position organization □ Public institution employees □ Enterprise Project overview: □ Others This Project involves Babu District and Pinggui District of Hezhou City and mainly covers the drainage basins of the urban inland river and He River flowing through the urban center of Hezhou City. The Project comprises of three components, including: (1) Component 1: He River Flood Risk Improvement, which includes: (a) improvement and rehabilitation (or demolition) of a few small runoff hydropower stations on the main watercourse of He River to enhance flood discharge capacity; (b) appropriate widening of certain sections of the main watercourse of He River to increase the flood discharge capacity and build riverside green corridors; (c) enhancing and connecting East Trunk Canal and Mawei River to divert upstream flood from the northern part of the urban area to the downstream areas and build riverside green corridor to increase flood discharge capacity and reduce waterlogging risks in the urban center of Hezhou City; (2) Component 2: Urban Drainage and Wastewater Management, which includes: (1) rehabilitation of tributaries of urban inland rivers and construction of riverside green corridors to divert regional flood; (b) construction of stormwater pipeline and pump stations in selected areas; (c) construction of Jiangnan WWTP and main sewage pipelines; (3) Component 3: institutional capacity building and project management, which includes: (a) institutional capacity strengthening and (b) project management and supervision. Impact analysis: 1. A certain volume of sludge will be generated from the dredging operations of He River, East Trunk Canal, Huangan Temple Drainage Canal, Shizigang Drainage Canal, Huangtian Branch Canal and Guposhan Drainage Canal; 2. Underground pipelines may be affected by the excavation activities to be conducted on the construction sites located 23m upstream of Sanjia Bridge, intersections of Huangan Temple Drainage Canal with Badaxi Road and Jianshezhong Road, intersections of Shizigang Drainage Canal with Guposhan Avenue, Wanquan Street, Zhushan Road, Badaxi Road, Yinhe Street, Jianshezhong Road, Pinganxi Road, Longshan Road, Anshanxi Road, Xingguang Road and Pinganxi Road as well as the Transportation Bureau at Jiangbeizhong Road. 3. The construction activities may generate impacts on 4 banyan trees at Xialiangzhai, 2 hackberry trees, 1 banyan tree and 1 camphor tree at Jiangbeizhong Road, 2 camphor trees and 1 banyan tree at Xinaner Street, 1 camphor tree at Jianshezhong Road, 1 camphor tree at Xinanyi Street and 1 camphor tree at Xiyue Street. Countermeasures to be taken: 1. Sludge generated from dredging of He River, Huangan Temple Drainage Canal and Shizigang Drainage Canal is dewatered to sludge cakes with a moisture content of less than 50% (in a total volume of approximately 12554m3) and then transported to Hezhou Domestic Solid Waste Landfill for treatment. Sludge generated from dredging of East Trunk Canal, Huangtian Branch Canal and Guposhan Drainage Canal is dewatered to sludge cakes with a moisture content of less than 50% (in a total volume of approximately 2058m3) and then transported to Hezhou Solid Waste Incineration Plant for disposal. 2. The following measures should be taken for excavation activities involved in underground pipeline construction: (1) communicating with and submitting construction plan to the competent authority, and finding out layout plan of underground pipelines; (2) planning the construction works in such a way that the underground pipelines are avoided where possible; (3) controlling or minimizing the construction time of pipeline construction; (4) immediately reporting the competent authority any cases of existing pipelines affected in the excavation process for emergency repair. 3. The following measures should be taken for construction activities involving famous and ancient trees: (1) minimizing the scope and construction period of construction activities; (2) making sure that the excavation operations will not affect the roots, branches and crowns of identified famous and ancient trees; (3) making sure no construction wastes, borrow fill and waste soil are stockpiled around the growing area of such trees; (4) making sure that such trees are not rolled or compacted by vehicles and construction plants. - 571 - Does your organization agree with the measures to be taken? Do you have any other comments or suggestions? We agree. Suggestion: 1) Underground pipeline survey data should be collected from housing and urban-rural development authority; a pipeline coordination team should be set up and departmental contact person defined. Construction plan should be developed based on pipeline location and depth. The owner unit of pipelines should be notified upon excavation so that on-site surveillance and emergency preparation can be facilitated (in particular with national defense and military optical cables). Formalities for temporary excavation should be fulfilled at the municipal engineering authority if any municipal roads are involved. 2) ancient trees should be protected in strict accordance with the respective measures. What is your organization’s attitude towards the construction of the Project from the general p erspective of local economic development and environmental protection? Supportive. Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: - 572 - 6. Feedbacks by Hezhou Traffic Police No. 3 Brigade on Measures Proposed in the Report Guangxi Hezhou Urban Water Infrastructure & Environment Improvement Project EIA Public Participation Questionnaire (for Traffic Police No. 3 Brigade) Name of Hezhou Traffic Police No. 3 Brigade Completed by Gao Gan organization Address of Contact 68-32, Fanglin Road, Hezhou 18677463066 organization information Nature of ■ Government Number of 26 Position Vice Chief organization □ Public institution employees □ Enterprise Project overview: □ Others This Project involves Babu District and Pinggui District of Hezhou City and mainly covers the drainage basins of the urban inland river and He River flowing through the urban center of Hezhou City. The Project comprises of three components, including: (1) Component 1: He River Flood Risk Improvement, which includes: (a) improvement and rehabilitation (or demolition) of a few small runoff hydropower stations on the main watercourse of He River to enhance flood discharge capacity; (b) appropriate widening of certain sections of the main watercourse of He River to increase the flood discharge capacity and build riverside green corridors; (c) enhancing and connecting East Trunk Canal and Mawei River to divert upstream flood from the northern part of the urban area to the downstream areas and build riverside green corridor to increase flood discharge capacity and reduce waterlogging risks in the urban center of Hezhou City; (2) Component 2: Urban Drainage and Wastewater Management, which includes: (1) rehabilitation of tributaries of urban inland rivers and construction of riverside green corridors to divert regional flood; (b) construction of stormwater pipeline and pump stations in selected areas; (c) construction of Jiangnan WWTP and main sewage pipelines; (3) Component 3: institutional capacity building and project management, which includes: (a) institutional capacity strengthening and (b) project management and supervision. Key problems: The Project is located in the urban center of Hezhou and road closure is needed for the construction of some components in the construction stage, thus generating impacts on traffic. What procedure should be followed to get permit for road closure? What are the specific requirements on traffic organization and bypass management? Countermeasures to be taken: 1. Submitting the construction plan of construction operations having impacts on public traffic to the traffic police authority for approval before the construction works commences; 2. implementing the construction activities section by section and finishing excavation and backfill in the shortest possible time; 3. providing access roads for construction areas close to public facilities such as hospitals, schools and bus stations and avoiding peak hours for material transportation to reduce pressure on urban traffic; providing special access roads for construction works in the vicinity of villages to reduce the occupation of rural roads and avoid damages by large plants and vehicles; 4. erecting bulletin boards on construction sites to disclose information on construction works and construction time to acquire public understanding of inconveniences from the construction activities and advising the public of the contact information and complaint hotlines, etc. 5. avoiding peak traffic hours upon scheduling pipeline construction or arranging traffic police for traffic diversion and dispatch so as to assure smooth flow of pedestrian and traffic and reduce traffic congestion and impacts on residents; 6. strengthening construction management and training to construction workers on environmental protection. - 573 - Do you have any other comments or suggestions? 1. Pre-construction advertisement should be well organized and implemented using the press so that announcements and rerouting notices are made public via micro blog, wechat, etc. 2. Bus rerouting should be well planned through communication with the Transportation Bureau; 3. Actions should be taken to control speed and overload of construction vehicles, which should be properly enclosed and wheels washed to reduce environmental impacts. What is your organization’s attitude towards the construction of the Project from the general perspective of local economic development and environmental protection? We agree. Guangxi Zhengze Environmental Protection Technology Co., Ltd. Date: - 574 -