Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: 22 August 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from 15 September 2017 to 30 December 2022 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Contract Value Contracts Subject to Procurement Method Threshold US$ Prior Review 1 ICB (Works) ≥ 10,000,000 All 2 NCB (Works) ˂ 10,000,000 None 3 Shopping (Works) ˂ 200,000 None 4 ICB (Goods and Non-Consultant ≥ 2,000,000 All Services) 5 NCB (Goods and Non-Consultant < 2,000,000 None Services) 6 Shopping (Goods and Non-Consultant < 100,000 None Services) 7 SSS (Goods) Not Applicable All 2. Prequalification. Bidders for Not applicable shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual to be prepared and adopted by EDM before effectiveness of the Financing Agreement 5. Any Other Special Procurement Arrangements: Not applicable. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: August 22, 2017 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preferen by Bank US$ million ce (Prior / Post) (yes/no) 1 Summary of the 118.19 2 Yes Prior ICB (Works) 2 Summary of the 11.35 6 Yes Prior ICB (Goods and Equipment) 3 Summary of the 2.47 2 No Prior SSS (Goods and Equipment) 4 Summary of the 3.5 1 No Prior ICB (Non- Consultant Services) 5 Summary of the 0.45 1 No Post NCB (Works) 6 Summary of the 0.6 2 No Post NCB (Goods and Equipment) 7 SSS (Capacity 0.15 1 No Post Building under Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Contract Value Contracts Subject to Threshold US$ Prior Review 1 QCBS (Consulting Services –Firms) ≥ 1,000,000 All 2 QCBS (Consulting Services –Firms) ≥ 300,000 - < 1,000,000 None 3 CQS/Other (QCBS/LCS) (Consulting < 300,000 None Services –Firms) 4 Individual Consultant ( ≥ 300,000 All Consulting Services – Individuals (IC)) 5 Individual Consultant ( < 300,000 None Consulting Services – Individuals (IC)) SSS (Consulting Services –Firms and Not Applicable All Individuals (IC)) August 22, 2017 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of number of 2.9 2 Prior contracts that will be let under QCBS 2 Summary of number of 0.53 1 Prior contracts that will be let under IC 3 Summary of number of 1.45 6 Post contracts that will be let under QCBS 4 Summary of number of 1.5 13 Post contracts that will be let under IC 5 Summary of number of 0.1 1 Prior contracts that will be let under SSS August 22, 2017 PROCUREMENT Mozambique : Power Efficiency and Reliability Improvement Project (PERIP) PLAN General Information Country: Mozambique Banks Approval Date of the Original Procurement Plan: 2016-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-02-14 Project ID: P158249 GPN Date: Project Name: Power Efficiency and Reliability Improvement Project (PERIP) Loan / Credit No: IDA / V0250, IDA / D2380 Executing Agency(ies): Electricity of Mozambique WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Enhancement of IV3 / Installation of Nationalwide Single Stage - One Pending IDA / V0250 EDM Operational and Post Request for Bids Open - National 450,000.00 0.00 2018-02-28 2018-03-21 2018-05-07 2018-06-21 2018-11-12 2019-12-12 Network Redesign/WAN Envelope Implementation Commercial Operations IV2 / Supply and Installation of 10,000 AMR Meters for EDM Component 2: Enhancement of Single Stage - One Pending Large Customers to improve IDA / V0250 EDM Operational and Post Request for Bids Open - International 5,600,000.00 0.00 2017-10-31 2017-11-21 2018-01-05 2018-02-19 2018-07-12 2019-07-12 Envelope Implementation performance of AMR Commercial Operations infrastructure IV1 / Supply and Installation on Redundancy in EDM substations, Reinforcement of Transmission Lines, Power Component 1: Rehabilitation and Compensation & Single Stage - One IDA / D2380 Upgrade of Network Prior Request for Bids Open - International 114,590,000.00 0.00 Under Review 2018-01-09 2018-01-30 2018-04-02 2018-05-17 2018-10-05 2020-10-07 Primary/Secundary System Envelope Infrastructure Protection/Control in Substations of Central Northern System, Rehabilitation of Distribution Systems GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G1 / Acquisition on Office Component 3: Capacity Building Request for Single Stage - One IDA / V0250 Post Open - National 10,000.00 10,777.03 Completed 2016-11-24 2017-03-28 2017-04-13 2017-05-29 2017-04-28 Equipment for the PIU Team and Implementation Support Quotations Envelope G1-1 / Laptop computers for the Component 3: Capacity Building Request for Single Stage - One IDA / V0250 Post Open - National 9,000.00 0.00 Canceled 2016-11-14 2017-01-19 2017-02-21 Project PIU members and Implementation Support Quotations Envelope G1-2 / Office Furniture for the Component 3: Capacity Building Request for Single Stage - One IDA / V0250 Post Open - National 1,000.00 0.00 Canceled 2016-11-19 2017-02-14 2017-03-29 Project PIU Members and Implementation Support Quotations Envelope Component 2: Enhancement of III1 / Supply of Maputo and Single Stage - One Under IDA / V0250 EDM Operational and Post Request for Bids Open - International 1,200,000.00 0.00 2017-09-29 2017-11-09 2017-10-20 2017-11-09 2017-12-04 2018-01-22 2018-01-03 2018-04-17 2018-12-17 Matola Network Redesign Envelope Implementation Commercial Operations III2 / Supply of National wide Component 2: Enhancement of Network Redesign/WAN and Single Stage - One Pending IDA / V0250 EDM Operational and Prior Request for Bids Open - International 4,450,000.00 0.00 2018-03-23 2018-04-13 2018-05-28 2018-06-27 2018-11-12 2020-01-31 Supply & Installation of Data Envelope Implementation Commercial Operations Center Network Redesign III3 / Supply and Installation of Component 2: Enhancement of Single Stage - One Pending the EDM Infosec Baseline IDA / V0250 EDM Operational and Post Request for Bids Open - National 200,000.00 0.00 2017-10-10 2017-10-31 2017-12-15 2018-01-14 2018-05-28 2018-11-19 Envelope Implementation Assessment Commercial Operations III4 / Supply and Installation of Component 2: Enhancement of the EDM Operational Portal Single Stage - One Pending IDA / V0250 EDM Operational and Post Request for Bids Open - International 600,000.00 0.00 2017-11-30 2017-12-21 2018-02-05 2018-03-07 2018-07-27 2018-12-28 (Corporate Service Center) and E- Envelope Implementation Commercial Operations Learning Platform III5 / Supply and Installation of Component 2: Enhancement of the DIGITAL Board and Supply & Single Stage - One Under IDA / V0250 EDM Operational and Post Request for Bids Open - National 400,000.00 0.00 2018-07-27 2018-02-07 2018-08-17 2018-02-07 2018-10-01 2018-10-31 2019-03-14 2019-12-13 Installation of the Business Envelope Implementation Commercial Operations Continuity (Email continuity) III6 / Supply and Installation of Component 2: Enhancement of Single Stage - One Pending the Data Architecture and IDA / V0250 EDM Operational and Post Request for Bids Open - International 600,000.00 0.00 2017-10-27 2017-11-17 2018-01-01 2018-01-31 2018-06-14 2019-06-14 Envelope Implementation Application Integration Commercial Operations III9 / Supply and Installation of an Asset Management System (MAS), Maintenance Component 2: Enhancement of Single Stage - One Pending management system (MMS), IDA / V0250 EDM Operational and Prior Request for Bids Open - International 4,000,000.00 0.00 2018-06-29 2018-07-20 2018-09-03 2018-10-03 2019-02-18 2020-02-18 Envelope Implementation Worforce management (WFM), Commercial Operations Processes Design and Training of EDM Staff III10 / Supply and Installation of 3 benches of 20 meter capacity, Component 2: Enhancement of Single Stage - One Pending a Meter Calibration Lab, a IDA / V0250 EDM Operational and Post Request for Bids Open - International 500,000.00 0.00 2018-02-16 2018-03-02 2018-04-16 2018-05-16 2018-09-28 2019-05-30 Envelope Implementation Special Store and 100 portable Commercial Operations meter testers III7 / Implementation of System Stabilization & End to End Component 2: Enhancement of Pending Business Process Review by the IDA / V0250 EDM Operational and Prior Direct Selection Direct 1,970,000.00 0.00 2018-07-20 2018-08-10 2019-01-11 2020-01-13 Implementation system supplier: ERP GIAF, Commercial Operations CMS and OMS III8 / Implementation of Transfer prepaid functionality to Component 2: Enhancement of Pending Comercial Management System IDA / V0250 EDM Operational and Post Direct Selection Direct 500,000.00 0.00 2017-10-25 2017-11-15 2018-04-30 2019-04-03 Implementation (CMS) as well a new appliance to Commercial Operations tokens generation Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS6 / Support from the current Component 2: Enhancement of Service Provider to conclude Pending EDM Operational and Prior Direct Selection Direct 100,000.00 0.00 2016-10-31 2016-11-30 2017-02-10 2017-10-13 implementation of the current Implementation Commercial Operations Phase 1 of the SIGEM Project CS7-1 / Technical Audit to approximately 6,000 Meters from Component 2: Enhancement of Single Stage - One HV, MV and Big LV Customers IDA / V0250 EDM Operational and Post Request for Bids Open - International 80,000.00 0.00 Canceled 2017-03-17 2017-03-29 2017-03-29 2017-03-29 2017-05-15 2017-05-10 2017-06-14 2017-06-14 2017-08-29 2018-08-29 Envelope across 16 EDM Area Service Commercial Operations Centers CS7-2 / Technical Audit to approximately 4,500 Energy Meters from HV, MV and Big LV Component 2: Enhancement of Customers across the 16 EDM Single Stage - One Under IDA / V0250 EDM Operational and Post Request for Bids Open - International 300,000.00 313,465.62 2017-08-25 2017-08-30 2017-08-30 2017-08-30 2017-10-24 2017-10-05 2017-12-13 2017-11-30 2018-02-15 2019-02-15 Area Service Centers for Envelope Implementation Commercial Operations Rebidding subsequent to reduction of Scope of Services to fit within Available Budget II1 / Supply of GIS software Component 2: Enhancement of including Survey/Data Gathering Single Stage - One Pending IDA / D2380 EDM Operational and Prior Request for Bids Open - International 3,500,000.00 0.00 2018-07-27 2018-08-17 2018-10-16 2018-11-15 2019-03-06 2020-05-06 Campaign as well as Training of Envelope Implementation Commercial Operations the EDM Staff CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS1/PERIP/PPA / Engineering design and supervision for Component 1: Rehabilitation and Quality And Cost- rehabilitation and upgrading IDA / V0250 Upgrade of Network Prior Open - International 3,000,000.00 3,738,053.54 Signed 2016-07-27 2016-08-02 2016-08-17 2016-08-03 2016-09-30 2016-08-10 2016-11-14 2016-09-23 2016-12-14 2016-10-28 2017-01-18 2016-12-12 2017-03-15 2017-03-01 2022-01-16 Based Selection transmission and distribution Infrastructure networks CS8 / Review of Feasibility Study for a National Control Component 1: Rehabilitation and Consultant Center, Review Grid Code and IDA / V0250 Upgrade of Network Prior Qualification Open - International 150,000.00 234,624.13 Signed 2016-10-19 2016-10-10 2016-11-09 2016-10-11 2017-01-06 2016-12-21 2017-02-20 2017-05-23 2017-04-21 2017-08-01 2017-10-27 Preparation of Bidding Infrastructure Selection Documents CS11 / Financial Audit for the Component 3: Capacity Building Pending Post Least Cost Selection Open - International 30,000.00 0.00 2016-10-31 2016-11-30 2017-02-13 2017-03-31 2017-04-30 2017-06-04 2017-07-28 2018-02-28 Project PPA funding and Implementation Support Implementation Component 2: Enhancement of I19 / Implementation of Inventory Quality And Cost- IDA / V0250 EDM Operational and Prior Open - International 1,600,000.00 0.00 Under Review 2017-08-25 2017-09-11 2017-08-31 2017-09-12 2017-10-14 2017-12-08 2017-11-30 2017-12-15 2018-01-18 2018-03-05 2018-07-05 and Valuation of the EDM Assets Based Selection Commercial Operations CS2 / Engineering Studies for Component 1: Rehabilitation and Quality And Cost- Preparation of reinforcement of IDA / V0250 Upgrade of Network Prior Open - International 220,000.00 0.00 Canceled 2016-08-26 2016-11-08 2016-09-16 2016-11-11 2016-10-30 2016-12-14 2017-01-13 2017-02-17 2017-04-05 2020-04-30 Based Selection Power Generation at Temane Infrastructure Component 2: Enhancement of I20 / Realization of Customer Quality And Cost- Pending IDA / V0250 EDM Operational and Post Open - International 200,000.00 0.00 2018-02-28 2018-03-28 2018-05-11 2018-06-26 2018-07-26 2018-09-10 2019-01-18 2019-07-18 Services Based Selection Implementation Commercial Operations I22 / Implementation of Staff Mapping & Allocation, Total Component 2: Enhancement of Compensation Study, Staff Quality And Cost- Pending IDA / V0250 EDM Operational and Prior Open - International 1,300,000.00 0.00 2017-10-27 2017-11-17 2017-12-31 2018-02-14 2018-03-16 2018-04-20 2018-08-06 2019-03-06 Survey, as well as Development Based Selection Implementation Commercial Operations of Learning Strategy and Pension & Health Insurance System Component 2: Enhancement of I24 / Development of Review of Quality And Cost- Pending IDA / V0250 EDM Operational and Post Open - International 200,000.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-20 2018-04-19 2018-05-31 2018-10-15 2019-12-16 the Grid Code Based Selection Implementation Commercial Operations Component 2: Enhancement of I25 / Development of Power Quality And Cost- Pending IDA / V0250 EDM Operational and Post Open - International 200,000.00 0.00 2017-11-29 2017-12-20 2018-02-02 2018-03-19 2018-04-18 2018-05-24 2018-10-08 2019-10-08 System Protection Study Based Selection Implementation Commercial Operations Component 2: Enhancement of I18 / Development of the Ten Quality And Cost- Pending IDA / V0250 EDM Operational and Post Open - International 300,000.00 0.00 2018-01-15 2018-02-05 2018-04-06 2018-05-21 2018-06-20 2018-07-25 2018-12-10 2019-12-10 Year Strategy for EDM Based Selection Implementation Commercial Operations MZ-EDM-48798-CS-CQS / Implementation of Risk Component 2: Enhancement of Consultant Assessment and preparation of Pending IDA / D2380 EDM Operational and Post Qualification Open - International 30,000.00 0.00 2018-03-02 2018-03-23 2018-05-06 2018-06-05 2018-08-20 2018-12-17 Action Plans to provide Risk Implementation Commercial Operations Selection Matrix and Annual Audit Plan for 2018 for EDM INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Enhancement of CS3 / Transformation Team for Individual Consultant Pending EDM Operational and Prior Direct 100,000.00 0.00 2016-09-30 2016-11-15 2016-12-30 2017-02-24 2017-08-23 EDM Restructuring Process Selection Implementation Commercial Operations CS10 / Preparation of Project Component 3: Capacity Building Individual Consultant IDA / V0250 Post Direct 10,000.00 18,750.00 Signed 2016-10-28 2017-06-16 2016-12-22 2017-02-06 2017-08-10 2017-03-27 2017-12-28 2017-04-27 Manual and Implementation Support Selection CS4-2 / Post Implementation Component 2: Enhancement of Individual Consultant Review of SIGEM Project for EDM Operational and Post Direct 25,000.00 0.00 Canceled 2016-09-08 2016-10-26 2016-12-09 2017-02-08 2017-08-07 Selection ERP Component Commercial Operations Page 2 CS4-22 / Post Implementation Component 2: Enhancement of Individual Consultant Review of the ERP Component IDA / V0250 EDM Operational and Post Limited 25,000.00 18,950.00 Completed 2016-09-01 2016-09-06 2016-09-30 2016-09-21 2016-11-15 2016-10-21 2017-01-09 2016-12-20 2017-01-09 2017-03-09 Selection under SIGEM Project Commercial Operations CS4-1 / Post Implementation Component 2: Enhancement of Individual Consultant Review of SIGEM Project for EDM Operational and Post Direct 25,000.00 0.00 Canceled 2016-09-08 2016-10-07 2016-11-21 2017-01-20 2017-07-20 Selection CMS Component Commercial Operations CS4-3 / Post Implementation Component 2: Enhancement of Individual Consultant Review of SIGEM Project for EDM Operational and Post Direct 25,000.00 0.00 Canceled 2016-09-09 2016-10-25 2016-12-09 2017-02-10 2017-08-09 Selection OMS & ICS Component Commercial Operations CS4-4 / Post Implementation Component 2: Enhancement of Individual Consultant Review of SIGEM Project for PM EDM Operational and Post Direct 25,000.00 0.00 Canceled 2016-09-09 2016-10-26 2016-12-11 2017-02-10 2017-08-09 Selection Component Commercial Operations CS4-11 / Post Implementation Component 2: Enhancement of Individual Consultant Review for the CMS Component IDA / V0250 EDM Operational and Post Limited 25,000.00 22,250.00 Completed 2016-09-02 2016-09-06 2016-09-22 2016-09-21 2016-11-07 2016-10-21 2017-01-09 2016-12-20 2017-01-09 2017-03-09 Selection under the SIGEM Project Commercial Operations CS4-33 / Post Implementation Component 2: Enhancement of Review of the OMS & ICS Individual Consultant IDA / V0250 EDM Operational and Post Limited 25,000.00 23,950.00 Completed 2016-09-02 2016-09-06 2016-09-22 2016-09-21 2016-11-07 2016-10-21 2017-01-09 2016-12-20 2017-01-09 2017-04-13 Component under the SIGEM Selection Commercial Operations Project CS4-44 / Post Implementation Component 2: Enhancement of Individual Consultant Review of the PM Component IDA / V0250 EDM Operational and Post Limited 25,000.00 24,250.00 Completed 2016-09-01 2016-09-06 2016-09-23 2016-09-21 2016-11-08 2016-10-21 2017-01-09 2016-12-20 2017-01-09 2017-02-17 Selection under the SIGEM Project Commercial Operations CS5 / Bidding Documents and Component 2: Enhancement of Individual Consultant Pending procurement of Contractors for EDM Operational and Post Direct 50,000.00 0.00 2016-10-09 2016-11-23 2017-01-09 2017-02-28 2017-08-27 Selection Implementation SIGEM phase 2 Commercial Operations CS9-1 / ESIA and ESMP Study covering all Investment Component 3: Capacity Building Individual Consultant Components planned to be IDA / V0250 Post Limited 80,000.00 98,190.00 Completed 2017-03-07 2016-04-01 2017-03-12 2016-05-03 2017-03-17 2016-06-01 2017-03-29 2016-10-18 2017-05-31 2017-08-31 and Implementation Support Selection implemented in eight provinces to be covered by the Project CS9-2 / RPF Study to be carried out for all Investment Components planned to be Component 3: Capacity Building Individual Consultant IDA / V0250 Post Limited 70,000.00 68,796.00 Completed 2017-03-07 2016-04-01 2017-03-10 2016-04-01 2017-03-15 2016-06-06 2017-03-24 2016-12-06 2017-05-31 2017-09-15 implemented in all the eight and Implementation Support Selection provinces to be covered by the Project. CS7 / Audit of MV & HV Component 2: Enhancement of Individual Consultant Metering and Preparation of EDM Operational and Post Limited 80,000.00 0.00 Canceled 2016-09-30 2016-10-31 2016-11-30 2017-02-14 2017-07-14 Selection Metering Policy Commercial Operations I14 / Operationalization of a Meter Calibration Lab, Special Component 2: Enhancement of Store and Redesign of Meter Individual Consultant IDA / V0250 EDM Operational and Post Open 150,000.00 188,050.00 Signed 2017-08-21 2017-08-01 2017-09-29 2017-09-29 2017-10-20 2017-12-04 2018-01-19 2018-01-23 2018-08-20 Inspection as well as Selection Commercial Operations Establishing Testing Procedures on the field I8 / Preparation of Technical & Functional Specifications and other Technical Requirements for Component 2: Enhancement of Individual Consultant Under Supply and Installation of IDA / V0250 EDM Operational and Post Open 250,000.00 0.00 2017-09-15 2017-08-27 2017-11-24 2017-12-15 2018-02-27 2020-02-28 Selection Implementation Geographical Information System Commercial Operations (GIS) as well as Worforce Management (WFM) I6 / Design and Supervision on Supply and Implementation of Component 2: Enhancement of Asset Management System Individual Consultant Under IDA / V0250 EDM Operational and Prior Open 300,000.00 0.00 2017-09-13 2017-11-23 2017-12-29 2018-02-28 2020-02-28 (AMS) as well as of the Selection Implementation Commercial Operations Maintenance Management System (MMS) C12 / Delegation of Component 3: Capacity Building Individual Consultant Accountability and Authority IDA / V0250 Post Limited 80,000.00 93,875.00 Signed 2017-08-31 2017-06-16 2017-09-11 2017-10-06 2017-10-11 2017-10-31 2017-12-11 2017-12-29 2018-03-12 and Implementation Support Selection Matrix (DAAM) for EDM I4 / Consulting Services for Monitoring and Auditing the Component 1: Rehabilitation and Individual Consultant Pending execution of the ESMP on IDA / V0250 Upgrade of Network Post Limited 200,000.00 0.00 2018-02-07 2018-02-19 2018-03-21 2018-06-11 2020-07-30 Selection Implementation Infrastructure Investment Infrastructure components of the Project I15 / Consulting services for Component 2: Enhancement of supervision on Implementation of Individual Consultant Pending IDA / V0250 EDM Operational and Prior Open 330,000.00 0.00 2017-09-29 2017-12-04 2017-12-25 2018-03-16 2019-11-18 Maputo & National wide Network Selection Implementation Commercial Operations Redesign & WAN I16 / Consulting services for supervision on implementation of Component 2: Enhancement of Individual Consultant Under Data Center Network Redesign IDA / V0250 EDM Operational and Post Open 50,000.00 0.00 2017-09-28 2017-11-24 2017-12-15 2018-03-29 2020-03-27 Selection Implementation (Redundancy, High availability, Commercial Operations High Performance) I17 / Consulting services for Component 2: Enhancement of design and supervision on Individual Consultant Pending IDA / V0250 EDM Operational and Post Open 100,000.00 0.00 2017-11-29 2018-02-09 2018-03-02 2018-07-23 2019-07-23 implementation of DIGITAL Board Selection Implementation Commercial Operations - EDM Management Portal I3 / Consulting Services for Component 1: Rehabilitation and Preparation of Compensation Individual Consultant Pending IDA / V0250 Upgrade of Network Post Direct 100,000.00 0.00 2017-09-22 2017-10-09 2017-10-30 2018-01-08 2018-06-20 Plan for Infrastructure Investment Selection Implementation Infrastructure components of the Project Page 3