Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Services) Above US$ 1,500,000 All 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of NA NA NA NA the ICB (Works) Summary of 6.69 4 No Prior the ICB (Goods) Summary of 3.8 9 No Post All the NCB (Works) Summary of 14.70 14 No Post All the NCB (Goods) Summary of NA NA NA NA the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Commentes 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.35 2 Prior number of contracts that July 9, 2010 will be let under QCBS Summary of 1.4 38 Post LCS/ IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Africa Banks Approval Date of the Original Procurement Plan: 2017-12-27 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-04-25 Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / D1200, IDA / 58320, IDA / 58210, IDA / 58330 Executing Agency(ies): Intergovernmental Authority on Development, Ministry of Agriculutre and Natural Resources Development, Office of the Prime Minister, Agence Djiboutienne de Development Social, Tirgray - Development Response to Displacement Impacts Project, AFAR - Development Response to Displacement Impacts Project, ETHIO-SOMALE - Development Response to Displacemen WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/T1/2017 / Travaux d'extension de 5 salles de Lycée Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 325,070.00 0.00 2018-02-10 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-12-01 et réhabilitation du dortoir à and Infrastructure Envelope Implementation Obock COMP1/T3/2017 / Travaux de Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 450,704.00 0.00 2017-11-20 2017-11-27 2018-01-08 2018-02-07 2018-03-14 2018-09-10 raccordement pecherie d'Obock and Infrastructure Envelope Implementation COMP1/T8/2017 / construction de locaux Social and Economic Services Request for Single Stage - One Pending IDA / 58330 Post Limited 101,408.00 0.00 2018-03-17 2018-05-12 2018-11-08 communautaire/communautaire à and Infrastructure Quotations Envelope Implementation Ali addé COMP1/T9/2017 / Réhabilitation Social and Economic Services Request for Single Stage - One Pending du local communautaire (UNFD) IDA / 58330 Post Limited 40,000.00 0.00 2018-02-17 2018-04-14 2018-10-11 and Infrastructure Quotations Envelope Implementation à Holl-Holl COMP2/T1/2017 / rénovation et renforcement de perimetres Social and Economic Services Request for Single Stage - One Pending existants d'où 5 reservoirs , 5 IDA / 58330 Post Limited 135,211.00 0.00 2017-11-01 2017-12-27 2018-06-25 and Infrastructure Quotations Envelope Implementation puits , 5 champs solaires pour Obock COMP2/T2/2017 / rénovation et renforcement de perimetres Social and Economic Services Request for Single Stage - One Pending existants d'où 5 reservoirs , 5 IDA / 58330 Post Limited 135,211.00 0.00 2017-11-01 2017-12-27 2018-06-25 and Infrastructure Quotations Envelope Implementation puits, 5 champs solaires pour Holhol COMP2/T3/2017 / rénovation et renforcement de perimetres Social and Economic Services Request for Single Stage - One Pending existants d'où 5 reservoirs , 5 IDA / 58330 Post Limited 135,211.00 0.00 2017-11-01 2017-12-27 2018-06-25 and Infrastructure Quotations Envelope Implementation puits, 5 champs solaires pour Ali Addé UG-OPM-22288-CW-RFQ / Project Management, and Single Stage - One Pending IDA / 58210 Post Request for Bids Limited 32,877.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Partitioning of offices at Kampala Monitoring and Evaluation Envelope Implementation COMP1/T5/2017 / F+P et raccordement des installations é ectriques des logements, l Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 241,392.00 0.00 2017-10-31 2017-11-07 2017-12-07 2018-01-06 2018-02-10 2018-05-11 locaux commerciaux et and Infrastructure Envelope Implementation té ablissements publics à Holl- Holl COMP1/T6/2017 / construction de collége et logement pour ali Addé et rehabilitation de salles scientifiques, reservoirs d'eau et Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 1,616,902.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-05-09 logements enseignants du and Infrastructure Envelope Implementation collége et toiture de l'école primaire Hol Hol en 2 lots séparés DJ-ADDS-29135-CW-RFB / Social and Economic Services Single Stage - One Pending Travaux extention du centre de IDA / 58330 Post Request for Bids Open - National 399,493.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-02-08 2018-06-08 and Infrastructure Envelope Implementation santé à Obock DJ-ADDS-29136-CW-RFB / rehabilitation/ extention du centre Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 436,620.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-08-07 de santé Ali addé et Hol Hol en 2 and Infrastructure Envelope Implementation lots séparés DJ-ADDS-29129-CW-DIR / Social and Economic Services Travaux d'extension Résau/ IDA / 58330 Prior Direct Selection Direct 1,188,371.09 0.00 Under Review 2017-09-19 2017-10-04 2017-10-27 2019-04-25 and Infrastructure Electricité d'Obock et Holl-Holl ET-TDRDIP-36807-CW-RFB / Construction of New Check dam Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 80,000.00 0.00 2018-01-01 2018-02-26 2018-04-27 pond for irrigation for Asgede Management Quotations Envelope Implementation Tsmbla Woreda ET-TDRDIP-36815-CW-RFB / Sustainable Environmental Request for Single Stage - One Pending Construction of Irrigation Canal IDA / 58320 Post Limited 98,182.00 0.00 2018-01-06 2018-02-12 2018-04-13 Management Quotations Envelope Implementation Expansion for Tselemti Woreda ET-TDRDIP-36821-CW-RFB / Construction of New Communal Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 36,418.00 0.00 2018-01-01 2018-02-26 2018-04-27 well for irrigation for Asgede Management Quotations Envelope Implementation Tsmbla Woreda ET-ADRDP-36827-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending pond construction for barahle IDA / 58320 Post Limited 37,000.00 0.00 2018-01-31 2018-03-28 2018-06-26 Management Quotations Envelope Implementation woreda ET-TDRDIP-36825-CW-RFB / Sustainable Environmental Request for Single Stage - One Pending Bio-gas construction for Asgede IDA / 58320 Post Limited 12,978.00 0.00 2017-12-06 2018-01-31 2018-05-01 Management Quotations Envelope Implementation Tsmbala Woreda Page 1 ET-TDRDIP-36832-CW-RFB / FTC rehabilitation by construction of Animal sheds for Asgede Tsmbla Request for Single Stage - One Pending Woreda(Construction Of Cattle IDA / 58320 Livelihoods Program Post Limited 42,622.00 0.00 2018-01-06 2018-03-03 2018-05-02 Quotations Envelope Implementation Shed,Construction Of Shoats Shed,Construction Of Bees Shed,Construction Of Poultry Shed) ET-TDRDIP-36840-CW-RFB / Maintenance of farmers training Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 28,835.00 0.00 2018-01-06 2018-03-03 2018-05-02 center, Animal Vet Clinic for Quotations Envelope Implementation Asgede Tsmbla Woreda ET-ADRDP-40066-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending small scale irrigation for only IDA / 58320 Post Limited 23,636.00 0.00 2018-01-25 2018-03-22 2018-09-18 Management Quotations Envelope Implementation aysaita wored ET-ADRDP-40070-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending gab-ion check dam at aysaiyta IDA / 58320 Post Limited 17,500.00 0.00 2018-01-13 2018-03-10 2018-09-06 Management Quotations Envelope Implementation woreda ET-ADRDP-40106-CW-RFQ / rehabilitation of two dis silting Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 34,800.00 0.00 2018-02-04 2018-04-01 2018-09-28 irrigation schemes for aysaita Management Quotations Envelope Implementation woreda ET-ADRDP-40108-CW-RFQ / Constructions of fodder grinding Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 8,700.00 0.00 2018-02-04 2018-04-01 2018-09-28 machine house for Aysaita Quotations Envelope Implementation woreda ET-TDRDIP-41226-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending Bio gas Construction for Tselemti IDA / 58320 Post Limited 14,776.00 0.00 2017-12-31 2018-02-06 2018-05-07 Management Quotations Envelope Implementation Woreda ET-TDRDIP-41228-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending Bio gas Construction for Tahtay IDA / 58320 Post Limited 11,481.00 0.00 2017-12-31 2018-02-06 2018-05-07 Management Quotations Envelope Implementation Adyabo Woreda ET-TDRDIP-41252-CW-RFQ / Construction of new Communal Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 20,247.00 0.00 2018-01-06 2018-02-17 2018-04-18 well for Irrigation for Tselemti Management Quotations Envelope Implementation Woreda ET-TDRDIP-41258-CW-RFQ / Construction of New Check dam Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 68,182.00 0.00 2017-12-31 2018-02-25 2018-05-26 pond for Irrigation for Tselemti Management Quotations Envelope Implementation Woreda ET-TDRDIP-41260-CW-RFQ / Construction of Check dam pond Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 60,000.00 0.00 2017-12-31 2018-02-25 2018-05-26 for construction for Tahtay Management Quotations Envelope Implementation Adyabo Woreda ET-TDRDIP-41304-CW-RFQ / Rehabilitation of FTC by constructing Animal Shades for Request for Single Stage - One Pending Tselemti Woreda(Construction Of IDA / 58320 Livelihoods Program Post Limited 32,000.00 0.00 2018-01-06 2018-03-03 2018-05-02 Quotations Envelope Implementation Shoats Shed,Construction Of Bees Shed,Construction Of Poultry Shed..) ET-TDRDIP-41309-CW-RFQ / Rehabilitation of FTC by construction of Animal Shade for Tahtay Adyabo Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 38,671.00 0.00 2018-01-06 2018-03-03 2018-05-02 Woreda(Construction of cattle Quotations Envelope Implementation shed , Construction of poultry shed, Construction of Bee keeping shed) ET-TDRDIP-41310-CW-RFQ / Maintenance of FTCs for Request for Single Stage - One Pending Tselemti Woreda (construction of IDA / 58320 Livelihoods Program Post Limited 54,152.00 0.00 2018-01-06 2018-03-03 2018-05-02 Quotations Envelope Implementation gate , Construction show room,Fencing of FTCs...) ET-TDRDIP-41312-CW-RFQ / Maintenance of FTCs, Nursery Request for Single Stage - One Pending site for Tahtay Adyabo IDA / 58320 Livelihoods Program Post Limited 32,026.00 0.00 2018-01-06 2018-03-03 2018-05-02 Quotations Envelope Implementation Woreda(Maintenance of roof catchment, Fencing....) ET-SDRDIP-42056-CW-RFQ / Construction of small scale dams Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 56,364.00 0.00 2018-02-11 2018-04-08 2018-10-05 for irrigation(no 1) in awbare Management Quotations Envelope Implementation woreda ET-DRDIP-42220-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending construction of three Hand dug IDA / 58320 Post Limited 8,695.00 0.00 2018-02-10 2018-04-07 2018-07-06 Management Quotations Envelope Implementation well for SSI at Bambasi woreda ET-DRDIP-42225-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending Construction of house hold pond IDA / 58320 Post Limited 15,018.00 0.00 2018-02-10 2018-04-07 2018-07-06 Management Quotations Envelope Implementation for Bambasi woreda ET-DRDIP-42251-CW-RFQ / construction of 4 hand dug well Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 11,636.00 0.00 2018-03-10 2018-05-05 2018-05-25 for demonstration for SSI on FTC Management Quotations Envelope Implementation for Homosha woreda ET-DRDIP-42260-CW-RFQ / construction of one house hold Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 15,018.00 0.00 2018-02-27 2018-04-24 2018-05-13 pond for demonstration for Management Quotations Envelope Implementation Homosha woreda Page 2 ET-DRDIP-42275-CW-RFQ / construction of one rehabilitation Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 16,948.00 0.00 2018-03-11 2018-05-06 2018-06-05 of diversion canal for Homosha Management Quotations Envelope Implementation woreda ET-DRDIP-42304-CW-RFQ / Construction of one spring Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 7,636.00 0.00 2018-02-12 2018-04-09 2018-05-07 development for Mao and Komo Management Quotations Envelope Implementation special woreda ET-DRDIP-42310-CW-RFQ / construction of 5 hand dug well Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 11,636.00 0.00 2018-02-25 2018-04-22 2018-05-22 for Mao and Komo special Management Quotations Envelope Implementation woreda ET-DRDIP-42312-CW-RFQ / construction of one house hold Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 15,018.00 0.00 2018-02-28 2018-04-25 2018-05-20 pond for Mao and Komo special Management Quotations Envelope Implementation woreda ET-SDRDIP-42329-CW-RFQ / Construction of small scale dams Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 56,364.00 0.00 2018-02-01 2018-03-29 2018-09-25 for irrigation (no 1) in k/bayah Management Quotations Envelope Implementation woreda ET-DRDIP-42672-CW-RFQ / Construction of 3 Biogass ( one Sustainable Environmental Request for Single Stage - One Pending for Bambsi,one for Mao & Komo IDA / 58320 Post Limited 14,543.00 0.00 2018-02-25 2018-04-22 2018-06-11 Management Quotations Envelope Implementation and one for Homosha woreda ) procured at Regional Level ET-SDRDIP-42120-CW-RFQ / construction of hand dug well for irrigation (no 1)and Rehabilitation Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 13,010.00 0.00 2018-02-20 2018-04-17 2018-10-14 of existing hand dug well for Management Quotations Envelope Implementation irrigation (no 1) in boqolmayo woreda ET-SDRDIP-42119-CW-RFQ / Canal construction with water pump and Rehabilitation of Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 62,350.00 0.00 2018-02-24 2018-04-21 2018-10-18 existing irrigation schemes (km Management Quotations Envelope Implementation 3) respectily (m5) 16002 in boqolmayo woreda ET-SDRDIP-42060-CW-RFQ / construction of hand dug well for Sustainable Environmental Request for Single Stage - One Pending irrigation( no 1) & Rehabilitation IDA / 58320 Post Limited 12,910.00 0.00 2018-02-24 2018-04-21 2018-10-18 Management Quotations Envelope Implementation of existing hand dug well for irrigation one in awbare woreda ET-SDRDIP-42242-CW-RFQ / Strengthening of nursery site( Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 20,826.00 0.00 2018-02-26 2018-04-23 2018-10-20 form tools and planting material) Management Quotations Envelope Implementation (no 3) in Dollo-ado woreda ET-SDRDIP-42249-CW-RFQ / Sustainable Environmental Request for Single Stage - One Pending construction Canal construction IDA / 58320 Post Limited 80,560.00 0.00 2018-02-20 2018-04-17 2018-10-14 Management Quotations Envelope Implementation (m4) 10003 in Dollo-ado woreda ET-SDRDIP-42330-CW-RFQ / construction of hand dug well for Sustainable Environmental Request for Single Stage - One Pending irrigation (no 1) & Rehabilitation IDA / 58320 Post Limited 12,910.00 0.00 2018-03-04 2018-04-29 2018-10-26 Management Quotations Envelope Implementation of existing hand dug well for irrigation (no 1 in k/bayah woreda ET-SDRDIP-42264-CW-RFQ / construction of hand dug well for Sustainable Environmental Request for Single Stage - One Pending irrigation (no 1 ) & Rehabilitation IDA / 58320 Post Limited 12,910.00 0.00 2018-02-24 2018-04-21 2018-10-18 Management Quotations Envelope Implementation of existing hand dug well for irrigation in Dollo-ado woreda ET-TDRDIP-41254-CW-RFQ / Construction of New Communal Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 66,411.00 0.00 2018-01-06 2018-02-12 2018-04-13 well for irrigation for Tahtay Management Quotations Envelope Implementation Adyabo Woreda GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOANRD-9134-GO-UN / 30 Regional Support for vehicles,(18 Double cab p/up and IDA / 58320 Coordination, Capacity and Prior UN Agencies (Direct) Direct 1,050,000.00 109,319,495.70 Signed 2017-03-06 2017-03-11 2017-04-15 2017-06-27 2017-10-12 12 Hard top Station wagon) Knowledge Regional Support for ET-MOANRD-9137-GO-UN / 160 IDA / 58320 Coordination, Capacity and Prior UN Agencies (Direct) Direct 64,000.00 560,035.80 Signed 2017-03-06 2017-03-11 2017-04-15 2017-06-27 2017-10-12 motorcycles Knowledge Regional Support for ET-MOANRD-9146-GO-RFQ / Single Stage - One Pending IDA / 58320 Coordination, Capacity and Post Request for Bids Open - National 175,000.00 0.00 2017-05-05 2017-05-10 2017-06-21 2017-07-21 2017-08-25 2018-02-21 office Equipment's Envelope Implementation Knowledge Regional Support for ET-MOANRD-9139-GO-RFQ / IT Single Stage - One Under IDA / 58320 Coordination, Capacity and Post Request for Bids Open - National 180,000.00 0.00 2017-05-05 2017-05-10 2017-06-21 2017-05-15 2017-07-21 2017-06-09 2017-08-25 2018-02-21 equipment and accessories Envelope Implementation Knowledge ET-MOANRD-14032-GO-RFB / Procurement of Stationery for the Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 15,000.00 0.00 2017-05-09 2017-05-14 2017-06-25 2017-07-25 2017-08-29 2018-02-25 use of federal, regional and Monitoring and Evaluation Quotations Envelope Implementation woredas DRDIP Office ET-MOANRD-15380-GO-RFB / procurement of furniture for Project Management, and Single Stage - One Pending IDA / 58320 Post Request for Bids Open - National 150,000.00 0.00 2017-05-06 2017-05-11 2017-06-22 2017-07-22 2017-08-26 2018-02-22 federal, region, and woreda Monitoring and Evaluation Envelope Implementation DRDIP office Page 3 ET-MOANRD-15385-GO-RFQ / Procurement of Office Supplies Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 14,000.00 0.00 2017-05-22 2017-07-17 2018-01-13 for the use of Federal, Regions Monitoring and Evaluation Quotations Envelope Implementation and woredas office of DRDIP UG-OPM-22297-GO-RFQ / Project Management, and Request for Single Stage - One Installation of Air conditioners at IDA / 58210 Post Limited 19,178.00 12,369.46 Signed 2017-10-28 2018-02-02 2017-12-23 2018-04-06 2018-06-21 Monitoring and Evaluation Quotations Envelope the DRDIP Kampala office UG-OPM-22304-GO-RFQ / Project Management, and Request for Single Stage - One Installation of Window Blinds at IDA / 58210 Post Limited 2,740.00 2,567.46 Signed 2017-10-28 2018-02-02 2017-12-23 2018-03-09 2018-06-21 Monitoring and Evaluation Quotations Envelope the Kampala offices UG-OPM-22312-GO-DIR / Project Management, and Request for Single Stage - One Pending Assorted office stationery and IDA / 58210 Post Limited 19,178.00 0.00 2017-11-05 2017-12-31 2018-06-29 Monitoring and Evaluation Quotations Envelope Implementation other office consumables COMP1/F2/2017 / achat de Matériels informatique pour les Social and Economic Services Request for Single Stage - One Pending é iciaires pour le lycées bénf IDA / 58330 Post Limited 30,000.00 0.00 2017-10-07 2017-12-02 2018-05-31 and Infrastructure Quotations Envelope Implementation compte de l'Education Informatique COMP1/F4/2017 / equipements Social and Economic Services médicaux et Mobiliers pour IDA / 58330 Prior Direct Selection Direct 1,305,900.00 0.00 Under Review 2017-10-20 2017-10-20 2017-12-01 2018-05-30 and Infrastructure Obock,Ali Addé et Hol Hol COMP1/F5/2017 / Foyers améliorés pour les 2000 Social and Economic Services Request for Single Stage - One Pending ménages Obock, 4000 ménages IDA / 58330 Post Limited 182,211.00 0.00 2017-10-27 2017-12-22 2018-06-20 and Infrastructure Quotations Envelope Implementation Ali-addé et 1200 ménages Holl- Holl COMP2/F2/2017 / achat de matériels pour périmetres Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 166,667.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 existants d'où motopompes, and Infrastructure Envelope Implementation brouettes... pour Obock COMP4/F1/2017 / acquisition Social and Economic Services Single Stage - One Pending d'une pick up et de 2 voitures IDA / 58330 Post Request for Bids Open - National 124,213.00 0.00 2017-10-02 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2018-07-23 and Infrastructure Envelope Implementation 4X4. HARD TOP COMP4/F2/2017 / acquisition de Social and Economic Services Request for Single Stage - One Pending IDA / 58330 Post Limited 30,000.00 0.00 2017-10-09 2017-12-04 2018-06-02 tablettes pour l'enquete and Infrastructure Quotations Envelope Implementation COMP4/F4/2017 / acquisition d' Social and Economic Services Single Stage - One Pending é uipement pour le centre de q IDA / 58330 Post Request for Bids Open - National 84,507.00 0.00 2017-10-03 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 and Infrastructure Envelope Implementation formation de l'ONARS UG-OPM-22310-GO-RFQ / Procurement of Assorted Office Furniture (1.No. Conference Table plus 26 Visitors Chairs, 13 No.Office Desks, 13 No. Office Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 73,973.00 33,021.06 Signed 2017-10-25 2017-11-21 2017-12-20 2018-02-28 2018-06-18 Chairs, 26 No. Visitors chairs, Monitoring and Evaluation Quotations Envelope 2No Sofa Sets, 2No. Coffee set, 1No. Round Table, 1No. Reception/ Front Desk Unit, 1No. Paper trim UG-OPM-29346-GO-RFB / Procurement of Motorvehicles (Lot 1: 1 No Station Wagon Type A (Not exceeding 3000cc), Project Management, and Single Stage - One IDA / 58210 Prior Request for Bids Open - National 1,064,600.00 0.00 Canceled 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 Station Wagon Type B (Not Monitoring and Evaluation Envelope exceeding 2800cc), Lot 2: 15 No Double Cabin Pickups, Lot 3: 17 No Motorcycles) COMP1/F3/2017 / achat de Matériels de SVT et Physique Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 135,201.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-04-09 pour le Ministère de l'Educatioon and Infrastructure Envelope Implementation Nationale COMP2/F3/2017 / achat de matériels pour périmetres Social and Economic Services Single Stage - One Pending existants d'où motopompes, IDA / 58330 Post Request for Bids Open - International 333,334.00 0.00 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-02-22 2018-06-22 and Infrastructure Envelope Implementation brouettes... pour Ali Addé et HolHol COMP3/F1BIS/2017 / Social and Economic Services Request for Single Stage - One Pending Acquisition de kits culinaires IDA / 58330 Post Limited 20,000.00 0.00 2017-11-05 2017-12-31 2018-01-20 and Infrastructure Quotations Envelope Implementation pour les GEA ET-TDRDIP-36769-GO-RFQ / IT Equipment and Accessories for Regional Project C ordination Project Management, and Request for Single Stage - One Pending Unit : ( Lap Top ,Desk top , IDA / 58320 Post Limited 2,615.00 0.00 2018-01-20 2018-03-06 2018-04-05 Monitoring and Evaluation Quotations Envelope Implementation Printer ,External hard disk , Wi Fi modem set , ADSL internet line set , 3G Modem Device ...) ET-ADRDP-36839-GO-RFQ / Sustainable Environmental Request for Single Stage - One Pending energy saving stoves for aysaita IDA / 58320 Post Limited 5,237.00 0.00 2018-01-15 2018-03-12 2018-05-11 Management Quotations Envelope Implementation woreda ET-ADRDP-36920-GO-RFQ / purchasing fodder grinding Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 30,500.00 0.00 2018-08-27 2018-10-22 2019-04-20 machine for aysaita wored at Quotations Envelope Implementation regional level ET-ADRDP-36926-GO-RFQ / Request for Single Stage - One Pending Purchasing of seeds for nursery IDA / 58320 Livelihoods Program Post Limited 4,300.00 0.00 2018-03-09 2018-05-04 2018-07-03 Quotations Envelope Implementation site for aysaita woreda at region ET-ADRDP-36932-GO-RFQ / Surface pump for small scale Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 87,000.00 0.00 2018-03-09 2018-05-04 2018-10-31 irrigation for aysaita woreda at Management Quotations Envelope Implementation regional level Page 4 ET-ADRDP-36936-GO-RFQ / Request for Single Stage - One Pending Purchasing of FTC equipment for IDA / 58320 Livelihoods Program Post Limited 11,090.00 0.00 2018-03-09 2018-05-04 2018-10-31 Quotations Envelope Implementation Aysaita wored at regional level ET-SDRDIP-37064-GO-RFQ / IT Equipment ( in Social and Economic Services Request for Single Stage - One Pending awbare,k/bayah,boqolmayo and IDA / 58320 Post Limited 49,000.00 0.00 2017-12-06 2018-01-31 2018-07-30 and Infrastructure Quotations Envelope Implementation dollo ado woredas) at regional level ET-SDRDIP-37075-GO-RFQ / tridle pumps for irrigation(Water Sustainable Environmental Request for Single Stage - One Pending Pumps) ( in awbare,k/bayah, IDA / 58320 Post Limited 27,500.00 0.00 2018-03-06 2018-05-01 2018-10-28 Management Quotations Envelope Implementation dollo-ado woredas) At regional level ET-SDRDIP-37090-GO-RFQ / Artificial Insemination( in awbare Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 53,000.00 0.00 2018-03-28 2018-05-23 2018-11-19 and k/bayah woredas) At Quotations Envelope Implementation regional level ET-TDRDIP-37741-GO-RFQ / Stationary materials, Office Equipment's and other office Project Management, and Supplies( Field Bag Monitoring and Evaluation Request for Single Stage - One Pending , Adding Machine, Telephone IDA / 58320 Regional Support for Post Limited 3,466.00 0.00 2017-12-22 2018-02-05 2018-03-07 Quotations Envelope Implementation box , Adapter/divider,Stapler, Coordination, Capacity and puncher, Computer Ink, Knowledge Computer paper, Air fresher, soft ....) for Asgede Tsmbla Woreda Livelihoods Program ET-TDRDIP-37759-GO-RFQ / Regional Support for Office Furniture's( Shelf, Desk, Coordination, Capacity and Request for Single Stage - One Pending Chair, Table, Filing Cabinets, IDA / 58320 Post Limited 21,084.00 0.00 2017-12-22 2018-02-10 2018-03-22 Knowledge Quotations Envelope Implementation Computer Stand,...) for Project Management, and AsgedeTsmbla Woreda Monitoring and Evaluation Livelihoods Program ET-TDRDIP-37766-GO-RFQ / Regional Support for Procurement of Audiovisual Coordination, Capacity and Request for Single Stage - One Pending Equipment's( Digital camera, IDA / 58320 Post Limited 1,618.00 0.00 2017-12-15 2018-01-30 2018-03-31 Knowledge Quotations Envelope Implementation DVD, GPS) for Asgede Tsmbla Project Management, and Woreda Monitoring and Evaluation ET-TDRDIP-37770-GO-RFQ / Tools for Soil and Water Conservation and Nursery Sustainable Environmental Request for Single Stage - One Pending Materials( Gabion, shovel, IDA / 58320 Post Limited 8,946.00 0.00 2017-12-08 2018-01-14 2018-02-13 Management Quotations Envelope Implementation hammer, watering cane, measuring tape, ....) for Tselemti Woreda ET-TDRDIP-37771-GO-RFQ / Purchase of Nursery and Forest Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 4,636.00 0.00 2018-01-03 2018-01-31 2018-05-01 seeds and seedlings for Tselemti Management Quotations Envelope Implementation Woreda ET-TDRDIP-37774-GO-RFQ / Procurement of motor pump for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 8,000.00 0.00 2018-02-09 2018-03-31 2018-05-30 demonstration for Asgede Management Quotations Envelope Implementation Tsmbla Woreda ET-TDRDIP-37775-GO-RFQ / Energy Saving Technologies for Demonstration Sustainable Environmental Request for Single Stage - One Pending (wood / Energy/saving stoves IDA / 58320 Post Limited 16,928.00 0.00 2017-12-30 2018-02-24 2018-04-25 Management Quotations Envelope Implementation ,Solar energy panels for Institution,Solar Light for Home) for Asgedetsmbla Woreda ET-TDRDIP-37915-GO-RFQ / Rehabilitating Animal vet clinic with Equipment's for Asgede Tsmbla woreda(Electrical Request for Single Stage - One Pending sterilizer of 2 litres,Burdizo for IDA / 58320 Livelihoods Program Post Limited 3,273.00 0.00 2017-12-29 2018-02-04 2018-04-05 Quotations Envelope Implementation large animals,Ice box of 10 litres,complete surgical kit....) , ET-TDRDIP-37916-GO-RFQ / Rehabilitate Artificial Insemination Center with Request for Single Stage - One Pending Equipment's (Funnel IDA / 58320 Livelihoods Program Post Limited 3,636.00 0.00 2017-12-29 2018-02-04 2018-04-05 Quotations Envelope Implementation large,Binocular microscope , Mother container 36 L.....)for AsgedeTsmbla Woreda ET-DRDIP-38273-GO-RFQ / Procurement of file cabinet for Bambasi ( 16), Maokoma ( 22) Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 7,200.00 0.00 2018-01-20 2018-03-17 2018-04-16 and Homosha woreda ( 26) at Quotations Envelope Implementation Regional Level total of 64 file cabinet UG-OPM-39369-GO-RFB / Procurement of Assorted Motor Project Management, and Single Stage - One Under vehicles - 6 Double cabins, 1 IDA / 58210 Post Request for Bids Open - National 1,008,705.00 0.00 2018-02-02 2018-01-18 2018-02-07 2018-03-21 2018-04-20 2018-05-25 2018-07-09 Monitoring and Evaluation Envelope Implementation station wagon and 23 motorcycles for field operations ET-ADRDP-40055-GO-RFQ / furnitures for aysaita woreda Social and Economic Services Request for Single Stage - One Pending IDA / 58320 Post Limited 6,646.00 0.00 2018-01-13 2018-03-10 2018-09-06 such as(chairs, table, shelf,gust and Infrastructure Quotations Envelope Implementation chair) ET-ADRDP-40615-GO-RFQ / Regional Support for Vehicle Parts and Accessories: ( Request for Single Stage - One Pending IDA / 58320 Coordination, Capacity and Post Limited 10,000.00 0.00 2018-01-13 2018-03-10 2018-09-06 Tyre, Tire, inner tube oil filter etc Quotations Envelope Implementation Knowledge .....) Page 5 ET-TDRDIP-41113-GO-RFQ / Energy Saving Technologies for Demonstration( Solar energy Sustainable Environmental Request for Single Stage - One Pending panels for Institution, wood / IDA / 58320 Post Limited 15,332.00 0.00 2018-01-20 2018-03-09 2018-04-23 Management Quotations Envelope Implementation Energy/saving stoves, Solar Light for Home ) for Tahtay Adyabo Woreda ET-TDRDIP-41115-GO-RFQ / Energy Saving Technologies for Demonstration ( Solar energy Sustainable Environmental Request for Single Stage - One Pending panels for Institution , Solar IDA / 58320 Post Limited 14,337.00 0.00 2018-01-20 2018-03-02 2018-04-16 Management Quotations Envelope Implementation Light for Home , wood / Energy/saving stoves ) for Tselemti Woreda Livelihoods Program ET-TDRDIP-41120-GO-RFQ / IT Regional Support for Equipment's and Accessories for Coordination, Capacity and Request for Single Stage - One Pending Asgede Tsmbla IDA / 58320 Post Limited 17,916.00 0.00 2018-01-20 2018-03-17 2018-05-01 Knowledge Quotations Envelope Implementation Woreda(Laptop,D-Link, Desktop, Project Management, and External Hard disk....) Monitoring and Evaluation Livelihoods Program ET-TDRDIP-41123-GO-RFQ / IT Regional Support for Equipment's with Accessories for Coordination, Capacity and Request for Single Stage - One Pending IDA / 58320 Post Limited 27,782.00 0.00 2018-01-20 2018-03-07 2018-04-21 Tselemti Woreda( Desktop Knowledge Quotations Envelope Implementation computer, Laptop computer...) Project Management, and Monitoring and Evaluation Livelihoods Program ET-TDRDIP-41125-GO-RFQ / IT Regional Support for Equipment's with accessories for Coordination, Capacity and Request for Single Stage - One Pending Tahtay Adyabo Woreda( Desk IDA / 58320 Post Limited 32,091.00 0.00 2018-01-20 2018-03-06 2018-04-20 Knowledge Quotations Envelope Implementation top computer, Laptop Project Management, and Computers, ........) Monitoring and Evaluation ET-TDRDIP-41130-GO-RFQ / Procurement of Motor Pumps for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 7,273.00 0.00 2018-01-20 2018-03-17 2018-05-01 Irrigation for Demonstration for Management Quotations Envelope Implementation Tselemti Woreda ET-TDRDIP-41132-GO-RFQ / Procurement of Motor Pumps for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 13,091.00 0.00 2018-01-20 2018-03-17 2018-05-01 Irrigation for Tahtay Adyabo Management Quotations Envelope Implementation Woreda for Demonstration ET-TDRDIP-41160-GO-RFQ / Procurement of Nursery, Forest Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 1,273.00 0.00 2017-12-31 2018-01-31 2018-05-01 seeds and Seedlings for Tahtay Management Quotations Envelope Implementation Adyabo Woreda ET-TDRDIP-41168-GO-RFQ / Procurement of soil and water Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 5,088.00 0.00 2017-12-31 2018-02-03 2018-03-05 conservation, Nursery tools and Management Quotations Envelope Implementation materials ET-TDRDIP-41172-GO-RFQ / Procurement of tools and Sustainable Environmental Request for Single Stage - One Pending materials for soil and water IDA / 58320 Post Limited 5,851.00 0.00 2017-12-31 2018-02-03 2018-03-05 Management Quotations Envelope Implementation conservation and Nursery for Tahtay Adyabo Woreda Livelihoods Program ET-TDRDIP-41177-GO-RFQ / Regional Support for Audiovisual Equipment's( Digital Coordination, Capacity and Request for Single Stage - One Pending IDA / 58320 Post Limited 2,491.00 0.00 2017-12-31 2018-02-25 2018-04-11 camera,GPS,microphone..) for Knowledge Quotations Envelope Implementation Tselemti Woreda Project Management, and Monitoring and Evaluation Livelihoods Program ET-TDRDIP-41180-GO-RFQ / Regional Support for Audiovisual Equipment's( Digital Coordination, Capacity and Request for Single Stage - One Pending IDA / 58320 Post Limited 1,855.00 0.00 2017-12-31 2018-02-25 2018-04-11 Camera,GPS..) for Tahtay Knowledge Quotations Envelope Implementation Adyabo Woreda Project Management, and Monitoring and Evaluation ET-TDRDIP-41189-GO-RFQ / Metro-logical Equipment's( Digital Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 56.00 0.00 2017-12-31 2018-02-25 2018-04-11 Thermometer, Rain Gage..) for Quotations Envelope Implementation Tahtay Adyabo Woreda ET-TDRDIP-41191-GO-RFQ / Regional Support for Request for Single Stage - One Pending Purchase of Generator for IDA / 58320 Coordination, Capacity and Post Limited 727.00 0.00 2017-12-31 2018-02-25 2018-04-11 Quotations Envelope Implementation Tselemti Woreda Knowledge Livelihoods Program ET-TDRDIP-41196-GO-RFQ / Regional Support for Procurement of Office Furniture's Coordination, Capacity and Request for Single Stage - One Pending for Tselemti Woreda(Metallic File IDA / 58320 Post Limited 18,371.00 0.00 2017-12-31 2018-02-06 2018-03-23 Knowledge Quotations Envelope Implementation cabinet , Table, Computer Stand Project Management, and , Shelf, Guest Chaire....) Monitoring and Evaluation ET-TDRDIP-41202-GO-RFQ / Livelihoods Program Procurement of Office Furniture's Regional Support for for Tahtay Adyabo Coordination, Capacity and Request for Single Stage - One Pending IDA / 58320 Post Limited 14,980.00 0.00 2017-12-31 2018-02-10 2018-03-27 Woreda(Wood shelf , Knowledge Quotations Envelope Implementation Chair, Shelf, Metallic File Project Management, and Rabinate, Black Board...) Monitoring and Evaluation ET-TDRDIP-41209-GO-RFQ / Purchase of Stationary , Office Project Management, and Equipment's and other supplies Monitoring and Evaluation Request for Single Stage - One Pending for Tselemti Woreda( computer IDA / 58320 Regional Support for Post Limited 10,779.00 0.00 2017-12-31 2018-02-10 2018-03-27 Quotations Envelope Implementation pepper,computer inks, pen, Coordination, Capacity and stapler, Field bag,Flesh Knowledge Memory,Air fresh.....) Page 6 ET-TDRDIP-41216-GO-RFQ / Purchase of Stationary, Other Project Management, and office Equipment's and Supplies Monitoring and Evaluation for Tahtay Adyabo Request for Single Stage - One Pending IDA / 58320 Regional Support for Post Limited 2,766.00 0.00 2017-12-31 2018-02-10 2018-03-27 Woreda(telephone box , Flash Quotations Envelope Implementation Coordination, Capacity and Memory, computer inks, Field Knowledge Bags, Divider, Computer pepper,Sizer, Charts....) ET-TDRDIP-41232-GO-RFQ / Audiovisual Equipment's for Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 3,665.00 0.00 2017-12-31 2018-02-06 2018-03-23 Regional Project Coordination Monitoring and Evaluation Quotations Envelope Implementation Unit( Digital Camera, GPS..) ET-TDRDIP-41235-GO-RFQ / Procurement of Office Furniture's( Project Management, and Request for Single Stage - One Pending File Cabinet, Computer Stand...) IDA / 58320 Post Limited 1,505.00 0.00 2018-01-06 2018-02-12 2018-03-14 Monitoring and Evaluation Quotations Envelope Implementation for Regional Project Coordination unit. ET-TDRDIP-41238-GO-RFQ / Procurement of Stationary Project Management, and Request for Single Stage - One Pending materials, Other office IDA / 58320 Post Limited 3,667.00 0.00 2018-01-06 2018-02-12 2018-03-29 Monitoring and Evaluation Quotations Envelope Implementation Equipment's and Supplie for Regional Coordination Unit ET-TDRDIP-41263-GO-RFQ / Vehicle & Motorcycle Spare Project Management, and Request for Single Stage - One Pending Parts and Accessories : ( Spare, IDA / 58320 Post Limited 4,604.00 0.00 2018-01-06 2018-02-12 2018-03-29 Monitoring and Evaluation Quotations Envelope Implementation Tyre, , inner tube .....) for Regional Coordination unit ET-TDRDIP-41267-GO-RFQ / Vehicle & Motorcycle Spare Project Management, and Request for Single Stage - One Pending Parts and Accessories : ( Spare, IDA / 58320 Post Limited 2,218.00 0.00 2018-01-06 2018-02-12 2018-03-29 Monitoring and Evaluation Quotations Envelope Implementation Tire, inner tube etc .....) for Asgede Tsmbla Woreda ET-TDRDIP-41270-GO-RFQ / Vehicle & Motorcycle Spare Project Management, and Request for Single Stage - One Pending Parts and Accessories : ( Spare, IDA / 58320 Post Limited 2,218.00 0.00 2017-12-31 2018-02-06 2018-03-08 Monitoring and Evaluation Quotations Envelope Implementation Tyre, Tire, inner tube etc .....) for Tselemti Woreda ET-TDRDIP-41272-GO-RFQ / Vehicle & Motorcycle Spare Project Management, and Request for Single Stage - One Pending Parts and Accessories : ( Spare, IDA / 58320 Post Limited 2,218.00 0.00 2017-12-31 2018-02-25 2018-04-11 Monitoring and Evaluation Quotations Envelope Implementation Tyre, , inner tube etc .....) for Tahtay Adyabo Woreda ET-TDRDIP-41280-GO-RFQ / Rehabilitating Animal vet clinic Request for Single Stage - One Pending with Equipment's for Tselemti IDA / 58320 Livelihoods Program Post Limited 3,637.00 0.00 2017-12-31 2018-02-25 2018-04-26 Quotations Envelope Implementation Woreda(microscope,large container,....) ET-TDRDIP-41283-GO-RFQ / Rehabilitate Artificial Insemination Center with Request for Single Stage - One Pending Equipment's for Tselemti IDA / 58320 Livelihoods Program Post Limited 5,090.00 0.00 2017-12-31 2018-02-25 2018-04-26 Quotations Envelope Implementation Woreda(EAI bag,fanal nitrogen liquid , Lezer jaket for EAI technicans....) ET-TDRDIP-41285-GO-RFQ / Rehabilitate Artificial Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 2,885.00 0.00 2017-12-31 2018-02-25 2018-04-26 Insemination Center with Quotations Envelope Implementation Equipment's for Tahtay Adyabo ET-TDRDIP-41296-GO-RFQ / Procurement of Livestock Production for Tselemti Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 17,855.00 0.00 2018-01-06 2018-03-03 2018-04-17 Woreda(poultry , milk cow, goat Quotations Envelope Implementation for rearing, bee hive, Oxen for fattening....) ET-TDRDIP-41298-GO-RFQ / Livestock Production for Request for Single Stage - One Pending Demonstration for Tahtay Adyabo IDA / 58320 Livelihoods Program Post Limited 1,755.00 0.00 2018-01-06 2018-03-03 2018-04-17 Quotations Envelope Implementation Woreda(Diary(heifer,),Fattening,P oultry...) ET-TDRDIP-41313-GO-RFQ / Purchase of Agricultural inputs on FTCs/PTCs for Demonstration Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 5,745.00 0.00 2018-02-05 2018-03-14 2018-04-13 for Asgede Tsmbla Woreda( Quotations Envelope Implementation Improved seeds, Fertilizers, Furska, Fruskelo...) ET-TDRDIP-41314-GO-RFQ / Purchasing of Agricultural Inputs on FTCs and PTCs for Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 8,173.00 0.00 2018-02-05 2018-03-14 2018-04-13 Demonstration for Tselemti Quotations Envelope Implementation Woreda(Fertilizer, Improved seeds, Fruska,fruskelo..) ET-TDRDIP-41315-GO-RFQ / Purchase of Agricultural Inputs for Demonstration on FTCs and Request for Single Stage - One Pending PTCs for demonstration for IDA / 58320 Livelihoods Program Post Limited 4,820.00 0.00 2018-02-05 2018-03-14 2018-04-13 Quotations Envelope Implementation Tahtay Adyabo Woreda(Improved seed, Fertlizers, Animal Feeds.....) ET-DRDIP-42019-GO-RFQ / Project Management, and Request for Single Stage - One Pending office equipment and other office IDA / 58320 Post Limited 923.00 0.00 2018-01-15 2018-03-12 2018-04-16 Monitoring and Evaluation Quotations Envelope Implementation supplies Bambasi woreda ET-DRDIP-42022-GO-RFQ / Regional Support for procurement of office equipment Request for Single Stage - One Pending IDA / 58320 Coordination, Capacity and Post Limited 848.00 0.00 2018-01-18 2018-03-15 2018-04-14 and other office supplies for Quotations Envelope Implementation Knowledge Homosha woreda Page 7 ET-DRDIP-42025-GO-RFQ / procurement of office equipment Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 912.00 0.00 2018-01-15 2018-03-12 2018-04-16 and other office supplies for Monitoring and Evaluation Quotations Envelope Implementation Maokomo woreda ET-GDRDIP-42028-GO-RFQ / Regional Support for Request for Single Stage - One Pending Poultry for demonstration for Gog IDA / 58320 Coordination, Capacity and Post Limited 740.75 0.00 2018-04-02 2018-05-28 2018-11-24 Quotations Envelope Implementation Woreda Knowledge ET-GDRDIP-42057-GO-RFQ / Project Management, and Request for Single Stage - One Pending IDA / 58210 Post Limited 727.27 0.00 2018-03-05 2018-04-30 2018-10-27 Printer for Gog Woreda Monitoring and Evaluation Quotations Envelope Implementation ET-DRDIP-42049-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of Stationary items IDA / 58320 Post Limited 6,385.00 0.00 2018-01-10 2018-03-07 2018-03-27 Monitoring and Evaluation Quotations Envelope Implementation for regional unit ET-DRDIP-42062-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of stationary items IDA / 58320 Post Limited 3,435.00 0.00 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Implementation for Homosha woreda ET-DRDIP-42065-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of stationary for IDA / 58320 Post Limited 3,219.00 0.00 2018-01-15 2018-03-12 2018-04-16 Monitoring and Evaluation Quotations Envelope Implementation Bambasi woreda ET-DRDIP-42069-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of stationary for IDA / 58320 Post Limited 3,185.00 0.00 2018-01-15 2018-03-12 2018-04-06 Monitoring and Evaluation Quotations Envelope Implementation Mao and Komo special woreda ET-GDRDIP-42068-GO-RFQ / Project Management, and Request for Single Stage - One Pending Office Supplies for Dimma IDA / 58210 Post Limited 765.00 0.00 2018-03-05 2018-04-30 2018-10-27 Monitoring and Evaluation Quotations Envelope Implementation Woreda such as Ventilator ET-DRDIP-42072-GO-RFQ / Project Management, and Request for Single Stage - One Pending cleaning materials for Regional IDA / 58320 Post Limited 786.00 0.00 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Implementation Units ET-DRDIP-42074-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of cleaning IDA / 58320 Post Limited 526.00 0.00 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Implementation materials for Bambaso woreda ET-DRDIP-42076-GO-RFQ / procurement of cleaning Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 428.00 0.00 2018-01-15 2018-03-12 2018-04-01 materials for Mao komo special Monitoring and Evaluation Quotations Envelope Implementation woreda ET-DRDIP-42079-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of cleaning IDA / 58320 Post Limited 537.00 0.00 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Implementation materials for Homosha woreda ET-DRDIP-42083-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of printing materials IDA / 58320 Post Limited 1,756.00 0.00 2018-01-25 2018-03-22 2018-04-11 Monitoring and Evaluation Quotations Envelope Implementation and brochers for Regional Units ET-SDRDIP-42087-GO-RFQ / Support the supply of improved Sustainable Environmental Request for Single Stage - One Pending Cooking Stoves for promotion IDA / 58320 Post Limited 14,077.00 0.00 2018-01-31 2018-03-28 2018-09-24 Management Quotations Envelope Implementation and demonstration (no 400)in awbare woreda ET-DRDIP-42110-GO-RFQ / procurement of Demonstration of Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 15,516.00 0.00 2018-01-15 2018-03-12 2018-04-01 improved technologies for Management Quotations Envelope Implementation Bambasi worda ET-DRDIP-42124-GO-RFQ / procurement of Sustainable Environmental Request for Single Stage - One Pending demonistrationimproved IDA / 58320 Post Limited 16,186.00 0.00 2018-01-30 2018-03-27 2018-04-26 Management Quotations Envelope Implementation technologies for Homosh woredas ET-DRDIP-42126-GO-RFQ / procurement of demonstration Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 14,216.00 0.00 2018-01-20 2018-03-17 2018-04-11 technologies for Mao and komo Management Quotations Envelope Implementation special woredas ET-SDRDIP-42127-GO-RFQ / Support the supply of improved Sustainable Environmental Request for Single Stage - One Pending Cooking Stoves for promotion IDA / 58320 Post Limited 8,446.00 0.00 2018-02-26 2018-04-23 2018-10-20 Management Quotations Envelope Implementation and demonstration (no 240) in boqolmayo woreda ET-DRDIP-42128-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of vehicle spar parts IDA / 58320 Post Limited 7,654.00 0.00 2018-01-15 2018-03-12 2018-04-11 Monitoring and Evaluation Quotations Envelope Implementation for Regional Unit ET-DRDIP-42132-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of vehicle spar parts IDA / 58320 Post Limited 6,278.00 0.00 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Implementation for bambasi woreda ET-DRDIP-42134-GO-RFQ / Project Management, and Request for Single Stage - One Pending procurement of vehicle sparpart IDA / 58320 Post Limited 4,567.00 0.00 2018-01-29 2018-03-26 2018-04-25 Monitoring and Evaluation Quotations Envelope Implementation for Homosha woreda ET-DRDIP-42135-GO-RFQ / procurement of vehicle sparpart Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 5,654.00 0.00 2018-01-29 2018-03-26 2018-04-30 for Mao and komo special Monitoring and Evaluation Quotations Envelope Implementation woreda ET-SDRDIP-42133-GO-RFQ / Support Biogas Development for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 9,455.00 0.00 2018-03-05 2018-04-30 2018-10-27 demonstration( no 2) boqolmayo Management Quotations Envelope Implementation woreda ET-DRDIP-42248-GO-RFQ / procurement of one rope and Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 654.00 0.00 2018-01-30 2018-03-27 2018-04-28 washer for demonstration for Management Quotations Envelope Implementation Bambasi woreda Page 8 ET-SDRDIP-42254-GO-RFQ / Support the supply of improved Sustainable Environmental Request for Single Stage - One Pending Cooking Stoves for promotion IDA / 58320 Post Limited 14,077.00 0.00 2018-03-04 2018-04-29 2018-10-26 Management Quotations Envelope Implementation and demonstration( no 400) in Dollo-ado woreda ET-DRDIP-42288-GO-RFQ / procurement of 42 treadle pump Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 7,172.00 0.00 2018-01-22 2018-03-19 2018-04-15 for demonstration for Mao and Management Quotations Envelope Implementation Komo special woreda ET-DRDIP-42290-GO-RFQ / procurement of one rope and Sustainable Environmental Request for Single Stage - One Pending washer pump for demonstration IDA / 58320 Post Limited 545.00 0.00 2018-02-18 2018-04-15 2018-05-15 Management Quotations Envelope Implementation for Mao and Komo special woreda ET-SDRDIP-42332-GO-RFQ / Support the supply of improved Sustainable Environmental Request for Single Stage - One Pending Cooking Stoves for promotion IDA / 58320 Post Limited 7,039.00 0.00 2018-03-04 2018-04-29 2018-10-26 Management Quotations Envelope Implementation and demonstration(no 200) in k/bayah woreda ET-ADRDP-42472-GO-RFQ / Sustainable Environmental Request for Single Stage - One Pending energy saving stoves for barahle IDA / 58320 Post Limited 4,364.00 0.00 2018-01-15 2018-03-12 2018-09-08 Management Quotations Envelope Implementation woreda ET-ADRDP-42482-GO-RFQ / furniture for barahle woreda such Social and Economic Services Request for Single Stage - One Pending IDA / 58320 Post Limited 6,500.00 0.00 2018-01-10 2018-03-07 2018-09-03 as(chair,table, gust chair and and Infrastructure Quotations Envelope Implementation shelf) ET-ADRDP-42485-GO-RFQ / IT- Equipment's for barahle woreda Social and Economic Services Request for Single Stage - One Pending IDA / 58320 Post Limited 9,910.00 0.00 2018-01-10 2018-03-07 2018-09-03 such as(desk top, lab top, and Infrastructure Quotations Envelope Implementation printer) ET-ADRDP-42493-GO-RFQ / Office stationery for barahle Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 1,164.00 0.00 2018-01-15 2018-03-12 2018-09-08 woereda such as(printing papers, Monitoring and Evaluation Quotations Envelope Implementation pen etc) ET-DRDIP-42136-GO-DIR / procurement of uniform for drivers Project Management, and Request for Single Stage - One Pending and safety shoes for CIF IDA / 58320 Post Limited 4,365.00 0.00 2018-02-20 2018-04-17 2018-05-22 Monitoring and Evaluation Quotations Envelope Implementation employees for Regional staffs only ET-DRDIP-42277-GO-RFQ / procurement of 89 motor pump for ( 13 for Homosha woreda ,60 Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 97,090.00 0.00 2018-02-11 2018-04-08 2018-05-28 for Bambasi woreda and 16 for Management Quotations Envelope Implementation Homosha ) procured at Regional level ET-DRDIP-42282-GO-RFQ / procurement of 3 rope and washer pump for Irrigation for demonstration, 1for Homosha Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 2,120.00 0.00 2018-01-13 2018-03-10 2018-04-24 woreda ,1 for Bambasi woreda Management Quotations Envelope Implementation and 1 for Mao Komo Special woreda ) procured at Regional Level ET-DRDIP-42098-GO-RFQ / procurement of 1040 wood saving stoves ( 320 for Bambasi , 330 Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 17,698.00 0.00 2018-01-30 2018-03-27 2018-05-01 for Homosha and 390 for Mao Management Quotations Envelope Implementation and Komo special woreda procured at Regional Level ET-DRDIP-42103-GO-RFQ / procurement of 156 solar light ( 40 for Bambasi ,51 for Mao & Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 39,709.00 0.00 2018-01-30 2018-03-27 2018-04-22 komo and 65 for Homosha Management Quotations Envelope Implementation woreda ) procured at Regional Level ET-DRDIP-42106-GO-RFQ / procurement of 10 solar energy Sustainable Environmental Request for Single Stage - One Pending panel ( 3 for Bambasi woreda,3 IDA / 58320 Post Limited 25,820.00 0.00 2018-01-27 2018-03-24 2018-04-14 Management Quotations Envelope Implementation for Homosha woreda and 4 Mao and komo special woreda ET-DRDIP-42239-GO-RFQ / procurement of 115 treadle pump(43 for Homoshaworeda ,30 Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 33,454.00 0.00 2018-02-25 2018-04-22 2018-06-01 for Bambasi woreda and 42 for Management Quotations Envelope Implementation Mao Komo special woreda )at Regional Level UG-OPM-22084-GO-RFB / Procurement of ICT Hardware/ Equipment (31 Laptops, 3 Desktop Computers, 17 Small Project Management, and Single Stage - One Under IDA / 58210 Post Request for Bids Open - National 170,693.00 0.00 2018-02-05 2018-02-12 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 and Medium Duty Photocopiers, Monitoring and Evaluation Envelope Implementation 2 Printers, 15 Scanners, 1 Projector, 17 Internet Modems, 29 computer Tablets) ET-ADRDP-42470-GO-RFQ / Sustainable Environmental Request for Single Stage - One Pending Solar lanterns and solar panel for IDA / 58320 Post Limited 18,182.00 0.00 2018-01-15 2018-03-12 2018-09-08 Management Quotations Envelope Implementation barahle woreda ET-ADRDP-36833-GO-RFQ / Sustainable Environmental Request for Single Stage - One Pending solar lanterns and solar panel for IDA / 58320 Post Limited 21,820.00 0.00 2017-12-06 2018-01-31 2018-07-30 Management Quotations Envelope Implementation aysaita woreda ET-ADRDP-36799-GO-RFQ / IT- equipment's for aysaita Project Management, and Request for Single Stage - One Pending woreda(desktop,laptop,printer) IDA / 58320 Post Limited 10,900.00 0.00 2018-01-08 2018-03-05 2018-09-01 Monitoring and Evaluation Quotations Envelope Implementation and one laptop computer for the region Page 9 ET-ADRDP-36915-GO-RFQ / Electric transformer for fodder grinding machine for aysaita woreda at region Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 21,500.00 0.00 2018-05-29 2018-07-24 2018-10-22 it is considered as income Quotations Envelope Implementation generating and the operating cost will be covered by the beneficiary body ET-ADRDP-40433-GO-RFQ / office stationery for the region Project Management, and Request for Single Stage - One Pending IDA / 58320 Post Limited 4,200.00 0.00 2018-01-23 2018-03-20 2018-09-16 and aysita woreda such as Monitoring and Evaluation Quotations Envelope Implementation (paper, pen etc) ET-SDRDIP-37069-GO-RFQ / Office furniture ( in Social and Economic Services Request for Single Stage - One Pending awbare,k/bayah,boqolmayo and IDA / 58320 Post Limited 44,500.00 0.00 2017-12-06 2018-01-31 2018-07-30 and Infrastructure Quotations Envelope Implementation dolo-ado woredas ) At regional level ET-SDRDIP-42090-GO-RFQ / Supply of Solar energy panel for Sustainable Environmental Request for Single Stage - One Pending institutions ( n0 3) and Solar IDA / 58320 Post Limited 33,000.00 0.00 2018-02-05 2018-04-02 2018-09-29 Management Quotations Envelope Implementation Lighting for demonstration (20 per kebele ) in awbare woreda ET-SDRDIP-42092-GO-RFQ / Establishing and strengthening Request for Single Stage - One Pending Horticultural Nurseries(farm IDA / 58320 Livelihoods Program Post Limited 20,830.00 0.00 2018-01-31 2018-03-28 2018-09-24 Quotations Envelope Implementation tools& planting material..) (no 2) in awbare woreda ET-SDRDIP-42130-GO-RFQ / Supply of Solar energy panel for institutions and Solar Lighting for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 20,188.00 0.00 2018-02-25 2018-04-22 2018-10-19 demonstration (20 per kebele) Management Quotations Envelope Implementation (no 100) (no 2) in boqolmayo woreda ET-SDRDIP-42223-GO-RFQ / Establishing and strengthening Request for Single Stage - One Pending Horticultural Nurseries( farm IDA / 58320 Livelihoods Program Post Limited 17,338.00 0.00 2018-02-01 2018-03-29 2018-09-25 Quotations Envelope Implementation tools& planting material..) in boqolmayo woreda ET-SDRDIP-42335-GO-RFQ / Supply of Solar energy panel for institutions (no 2) and Solar Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 17,490.00 0.00 2018-03-02 2018-04-27 2018-10-24 Lighting for demonstration (20 per Management Quotations Envelope Implementation kebele) (no 100) in k/bayah woreda ET-SDRDIP-42336-GO-RFQ / Support Biogas Development for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 4,728.00 0.00 2018-02-05 2018-04-02 2018-09-29 demonstration(biogas) (no 1) in Management Quotations Envelope Implementation k/bayah woreda ET-SDRDIP-42344-GO-RFQ / Establishing and strengthening Sustainable Environmental Request for Single Stage - One Pending Horticultural Nurseries(farm IDA / 58320 Post Limited 12,159.00 0.00 2018-01-29 2018-03-26 2018-09-22 Management Quotations Envelope Implementation tools& planting material (no 1) in k/bayah woreda ET-SDRDIP-42259-GO-RFQ / Supply of Solar energy panel for Sustainable Environmental Request for Single Stage - One Pending institutions( no 3) &Solar Lighting IDA / 58320 Post Limited 32,980.00 0.00 2018-02-23 2018-04-20 2018-10-17 Management Quotations Envelope Implementation for demonstration (20 per kebele) (no 200) in Dollo-ado woreda ET-SDRDIP-42262-GO-RFQ / Support Biogas Development for Sustainable Environmental Request for Single Stage - One Pending IDA / 58320 Post Limited 9,455.00 0.00 2018-02-26 2018-04-23 2018-10-20 demonstration(biogas) (no 2) in Management Quotations Envelope Implementation Dollo-ado woreda COMP1/F2/2017 / achat de Social and Economic Services Single Stage - One Pending Matériels informatique pour les IDA / 58330 Post Request for Bids Open - National 135,000.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 and Infrastructure Envelope Implementation é iciaires/ Education lycées bénf COMP3/F1/2017 / acquisition de matériels et consommables pour Social and Economic Services Single Stage - One Pending IDA / 58330 Post Request for Bids Open - National 180,000.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-04-09 les groupements de femmes et and Infrastructure Envelope Implementation jeunes COMP4/F3/2017 / acquisition de Social and Economic Services Request for Single Stage - One Pending logiciel pour l'analyse des IDA / 58330 Post Limited 25,000.00 0.00 2017-11-17 2018-01-12 2018-07-11 and Infrastructure Quotations Envelope Implementation données des enquetes COMP1/F1/2017 / Equipements chauds et Froid pour les lycés Social and Economic Services Single Stage - One Pending techniques d' Ali Sabieh et IDA / 58330 Post Request for Bids Open - International 428,391.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 and Infrastructure Envelope Implementation Obock pour le Ministère de l' Education Nationale DJ-IGAD-55119-GO-DIR / Regional Support for Pending Procurement of GIS Application ( IDA / D1200 Coordination, Capacity and Post Direct Selection Direct 10,000.00 0.00 2018-03-28 2018-04-02 2018-05-07 2018-11-03 Implementation ArcGIS) Knowledge DJ-IGAD-55145-GO-RFQ / Regional Support for Procurement of GIS tools (Adobe Request for Single Stage - One Pending IDA / D1200 Coordination, Capacity and Post Limited 2,500.00 0.00 2018-04-03 2018-05-29 2018-11-25 Creative Crowd and GPSMAP Quotations Envelope Implementation Knowledge 64s (Handheld GPS Kits)) ET-TDRDIP-57977-GO-RFQ / Physical capacity building with office Furniture for Multipurpose Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 6,546.00 0.00 2018-04-25 2018-06-20 2018-12-17 Cooperatives( F Iron shelf, safe Quotations Envelope Implementation box, Table,Rope chair....) for Tahtay Adyabo Woreda Page 10 ET-TDRDIP-57994-GO-RFQ / Purchase of Industrial Materials FOR maintenance of offices for Request for Single Stage - One Pending Multipurpose Cooperatives in IDA / 58320 Livelihoods Program Post Limited 8,364.00 0.00 2018-04-25 2018-06-20 2018-12-17 Quotations Envelope Implementation Tahtay Adyabo Woreda( Cement, Iron Sheet, Iron Bar, Paintings, door...) ET-TDRDIP-58289-GO-RFQ / Physical Capacity Building of Multipurpose Cooperatives by Request for Single Stage - One Pending Providing Office Furniture's and IDA / 58320 Livelihoods Program Post Limited 10,352.72 0.00 2018-04-25 2018-06-20 2018-12-17 Quotations Envelope Implementation Equipment's in Asgede- Tsmbla Woreda( Shelf, Cash box, Tables...) ET-TDRDIP-58293-GO-RFQ / Physical Capacity building by Providing Industrial materials for Maintenance of office services Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 823.00 0.00 2018-04-25 2018-06-20 2018-12-17 for Multipurpose Cooperatives in Quotations Envelope Implementation Asgede Tsmbla Woreda( Cement, Reinforcement bar, nail, nail, Eucalyptus tree,... ) ET-TDRDIP-58299-GO-RFQ / Physical Capacity Building for Multipurpose Cooperatives by Request for Single Stage - One Pending providing Office Equipment's and IDA / 58320 Livelihoods Program Post Limited 3,199.00 0.00 2018-04-25 2018-06-20 2018-12-17 Quotations Envelope Implementation IT materials for Asgede - Tsmbla Woreda( Printers, Desktop, Photocopier ..) ET-TDRDIP-58312-GO-RFQ / Physical Capacity building of Multipurpose Cooperatives by Request for Single Stage - One Pending IDA / 58320 Livelihoods Program Post Limited 1,011.00 0.00 2018-04-25 2018-06-20 2018-12-17 providing Office furniture's in Quotations Envelope Implementation Tselemti Woreda( Guest Chair, Table, Window gate......) ET-TDRDIP-58309-GO-RFQ / Physical Capacity Building by Providing Industrial materials for Request for Single Stage - One Pending Maintenance of office buildings IDA / 58320 Livelihoods Program Post Limited 24,047.00 0.00 2018-04-25 2018-06-20 2018-12-17 Quotations Envelope Implementation of the Multipurpose Cooperatives in Tselemti Woreda( Cement,Iron sheet, Iron bar, nail.....) ET-TDRDIP-60345-GO-RFQ / physical capacity building of Multipurpose cooperatives for Request for Single Stage - One Pending office maintenance by providing IDA / 58320 Livelihoods Program Prior Limited 2,986.00 0.00 2018-05-05 2018-06-30 2018-12-27 Quotations Envelope Implementation Local construction materials at Tselemti Woreda( sand, Gravel......) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22095-NC-DIR / LAN Project Management, and Under set up/ extension to the DRDIP IDA / 58210 Prior Direct Selection Direct 10,959.00 0.00 2017-08-21 2018-02-13 2017-08-26 2018-02-23 2017-09-30 2018-03-29 Monitoring and Evaluation Implementation Offices UG-OPM-22307-NC-DIR / Procurement of Additional Office Project Management, and Under IDA / 58210 Prior Direct Selection Direct 68,493.00 0.00 2017-08-14 2017-08-19 2017-10-30 2017-09-23 2018-03-22 Space for DRDIP TST at Ruth Monitoring and Evaluation Implementation Towers (One years Contract) UG-OPM-22306-NC-RFQ / Project Management, and Request for Single Stage - One Pending Office Branding for the Kampala IDA / 58210 Post Limited 548.00 0.00 2017-10-28 2017-12-23 2018-06-21 Monitoring and Evaluation Quotations Envelope Implementation Offices UG-OPM-22104-NC-RFQ / Project Management, and Request for Single Stage - One Pending PABX Upgrade/ extension to the IDA / 58210 Post Limited 13,699.00 0.00 2017-10-28 2017-12-23 2018-06-21 Monitoring and Evaluation Quotations Envelope Implementation refugees office UG-OPM-22287-NC-DIR / Development of a Project Project Management, and Under IDA / 58210 Prior Direct Selection Direct 300,905.00 0.00 2017-12-08 2017-12-13 2018-02-06 2018-01-17 2018-07-16 Management Information System Monitoring and Evaluation Implementation (MIS) ET-TDRDIP-37918-NC-RFQ / Project Management, and Request for Single Stage - One Pending Printing for Regional Project IDA / 58320 Post Limited 832.00 0.00 2018-01-20 2018-02-23 2018-04-09 Monitoring and Evaluation Quotations Envelope Implementation Coordination unit ET-TDRDIP-41108-NC-RFQ / Regional Support for Request for Single Stage - One Pending Printing Service for Asgede IDA / 58320 Coordination, Capacity and Post Limited 832.00 0.00 2018-01-20 2018-03-06 2018-04-20 Quotations Envelope Implementation Tsmbla Woreda Knowledge Project Management, and ET-TDRDIP-41111-NC-RFQ / Monitoring and Evaluation Request for Single Stage - One Pending Printing Services for Tselemti IDA / 58320 Regional Support for Post Limited 832.00 0.00 2018-01-20 2018-03-06 2018-04-20 Quotations Envelope Implementation Woreda Coordination, Capacity and Knowledge Project Management, and ET-TDRDIP-41112-NC-RFQ / Monitoring and Evaluation Request for Single Stage - One Pending Printing Services for Tahtay IDA / 58320 Regional Support for Post Limited 832.00 0.00 2018-01-20 2018-03-06 2018-04-20 Quotations Envelope Implementation Adyabo Woreda Coordination, Capacity and Knowledge UG-OPM-45668-NC-DIR / Purchase and Installation of Project Management, and IDA / 58210 Prior Direct Selection Direct 9,642.00 0.00 Under Review 2018-02-05 2018-03-04 2018-02-10 2018-03-09 2018-03-17 2018-09-13 Wireless internet for DRDIP Monitoring and Evaluation Offices CONSULTING FIRMS Page 11 Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IGAD/ DRDIP/CS/8 / Regional Support for Consultancy for the Quality And Cost- Pending IDA / D1200 Coordination, Capacity and Post Open - International 100,000.00 0.00 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Commissioning of Joint Research Based Selection Implementation Knowledge On Displacement & Development IGAD/ DRDIP/CS/9 / Consultancy to strengthen Monitoring Mechanism on Mixed Regional Support for Migration, Migration Trends and Quality And Cost- Pending IDA / D1200 Coordination, Capacity and Prior Open - International 500,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2019-03-13 the Assessment of the impact of Based Selection Implementation Knowledge intervention in the 3 Project Countries on Forced Displacement & Mixed Migration IGAD/ DRDIP/CS/10 / Regional Support for Consultant Consultancy for the Development Pending IDA / D1200 Coordination, Capacity and Post Qualification Open - National 5,000.00 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-06 2017-11-10 2018-05-09 of DRDIP Regional Secretariat Implementation Knowledge Selection Website ET-MOANRD-9153-CS-QCBS / Base line survey consultancy Project Management, and Quality And Cost- Under IDA / 58320 Post Open - International 200,000.00 0.00 2017-03-19 2017-08-14 2017-04-09 2017-05-23 2017-11-14 2017-06-20 2017-07-20 2017-08-24 2017-09-28 2018-09-28 (before the implementation of the Monitoring and Evaluation Based Selection Implementation project). ET-MOANRD-15793-CS-LCS / procurement of independent Project Management, and Under IDA / 58320 Post Least Cost Selection Open - National 100,000.00 0.00 2017-05-30 2017-08-15 2017-06-20 2017-08-03 2017-08-21 2017-08-31 2017-09-21 2017-09-30 2017-10-23 2017-11-04 2017-11-07 2017-12-09 2018-06-07 external financial audit for the Monitoring and Evaluation Implementation year 2016/17 june. ET-MOANRD-15796-CS-LCS / Project Management, and Pending procurement of consultancy for IDA / 58320 Post Least Cost Selection Open - National 50,000.00 0.00 2017-05-29 2017-06-19 2017-08-02 2017-08-30 2017-09-29 2017-11-03 2017-12-08 2018-06-06 Monitoring and Evaluation Implementation PIM translation in to 'Amharic ' ET-MOANRD-15794-CS-LCS / Procurement of independent Project Management, and Pending IDA / 58320 Prior Least Cost Selection Open - National 100,000.00 0.00 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2018-06-07 external procurement audit for Monitoring and Evaluation Implementation the year 2016/17 June. ET-MOANRD-18835-CS-LCS / Project Management, and Pending PIM and manuals translation with IDA / 58320 Post Least Cost Selection Open - National 21,700.00 0.00 2017-06-19 2017-07-10 2017-08-23 2017-09-20 2017-10-20 2017-11-24 2017-12-29 2018-06-27 Monitoring and Evaluation Implementation different local language COMP1/C1/2017 / Recrutement d'un Bureau d'Etudes et de supervision pour les travaux Social and Economic Services Quality And Cost- Pending d'extension, construction, IDA / 58330 Post Open - National 252,234.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 and Infrastructure Based Selection Implementation é ablissements réhabilitation des t scolaires , le local communautaire COMP1/C2/2017 / Recrutement d'un Bureau d'Etudes pour la Consultant Social and Economic Services Pending supervision des travaux IDA / 58330 Post Qualification Open - National 83,611.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 and Infrastructure Implementation d'extension de centres de santé Selection pour obock, ali addé et Hol hol COMP1/C3/2017 / Récrutement d'un consultant individuel pour les é udes et la supervision les t Consultant Social and Economic Services Pending travaux d'installations dans les IDA / 58330 Post Qualification Open - National 30,000.00 0.00 2017-10-30 2017-11-20 2018-01-03 2018-02-02 2018-03-09 2018-09-05 and Infrastructure Implementation logements, locaux commerciaux Selection é ablissement publics à Holl- et t Holl COMP1/C4/2017 / Recrutement Consultant Social and Economic Services Pending d'un bureau d'etudes pour IDA / 58330 Post Qualification Open - National 45,070.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 and Infrastructure Implementation raccordement Pecherie (Obock) Selection COMP1/C5/2017 / Recrutement d'un BE pour les travaux de Social and Economic Services Quality And Cost- Pending forrage de Hol hol et Ali Addé et IDA / 58330 Post Open - National 188,732.00 0.00 2017-12-15 2018-01-05 2018-02-18 2018-03-18 2018-04-17 2018-05-22 2018-06-26 2019-06-26 and Infrastructure Based Selection Implementation du reseau d'adduction d'eau à Obock et Holl-Holl COMP2/C1/2017 / Recrutement Consultant d'un bureau d'etudes pour la la Social and Economic Services Pending IDA / 58330 Post Qualification Open - National 40,564.00 0.00 2017-10-05 2017-10-26 2017-12-09 2018-01-08 2018-02-12 2018-08-11 rénovation et renforcement des and Infrastructure Implementation Selection perimetres existants COMP2/C2/2017 / Recrutement d'un bureau d'etudes pour Social and Economic Services Quality And Cost- Pending IDA / 58330 Post Open - National 152,369.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 l'extension de la centrale solaire and Infrastructure Based Selection Implementation et le forage d'Ali-Addé COMP4/C10/2017 / recrutement Social and Economic Services Pending d 'un cabinet pour l'Audit IDA / 58330 Post Least Cost Selection Open - National 10,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2018-10-10 and Infrastructure Implementation Financier COMP4/C11/2017 / Recrutement d'un consultant Consultant Social and Economic Services Pending pour la collecte de donnée IDA / 58330 Post Qualification Open - National 8,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 and Infrastructure Implementation administratives de toutes les Selection infrastructures sociales de base INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22319-CS-CDS / Project Management, and Pending IDA / 58210 Prior Direct Selection Direct 164,383.56 0.00 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Baseline survey Monitoring and Evaluation Implementation UG-OPM-22326-CS-INDV / M & Project Management, and Individual Consultant Pending IDA / 58210 Post Open 76,010.88 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 E Officer Monitoring and Evaluation Selection Implementation Page 12 UG-OPM-22332-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 98,367.12 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Project Engineer Monitoring and Evaluation Selection Implementation UG-OPM-22344-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 76,010.88 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Livelihood Officer Monitoring and Evaluation Selection Implementation UG-OPM-22345-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 76,010.88 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Environment Officer Monitoring and Evaluation Selection Implementation UG-OPM-22347-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 76,010.88 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Officer Monitoring and Evaluation Selection Implementation UG-OPM-22349-CS-INDV / Project Management, and Individual Consultant IDA / 58210 Post Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Communication Assistant Monitoring and Evaluation Selection UG-OPM-22352-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 43,651.20 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Administrative Assistant Monitoring and Evaluation Selection Implementation UG-OPM-22355-CS-INDV / Project Management, and Individual Consultant Pending Engineering Assistant 1 IDA / 58210 Post Open 43,651.20 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Selection Implementation (Kampala Office) UG-OPM-22357-CS-INDV / Project Management, and Individual Consultant Pending Engineering Assistant 2 IDA / 58210 Post Open 43,651.20 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Selection Implementation (Kampala Office) UG-OPM-22360-CS-INDV / Project Management, and Individual Consultant IDA / 58210 Post Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Assistant 1 Monitoring and Evaluation Selection UG-OPM-22361-CS-INDV / Project Management, and Individual Consultant IDA / 58210 Post Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Assistant 2 Monitoring and Evaluation Selection UG-OPM-22362-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 43,651.20 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Accounts Assistant Monitoring and Evaluation Selection Implementation UG-OPM-22363-CS-INDV / Project Management, and Individual Consultant IDA / 58210 Post Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Executive Assistant Monitoring and Evaluation Selection UG-OPM-22367-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 1 Monitoring and Evaluation Selection Implementation UG-OPM-22368-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 2 Monitoring and Evaluation Selection Implementation UG-OPM-22369-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 3 Monitoring and Evaluation Selection Implementation UG-OPM-22372-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 4 Monitoring and Evaluation Selection Implementation UG-OPM-22373-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 5 Monitoring and Evaluation Selection Implementation UG-OPM-22374-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 6 Monitoring and Evaluation Selection Implementation UG-OPM-22377-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 7 Monitoring and Evaluation Selection Implementation UG-OPM-22379-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 8 Monitoring and Evaluation Selection Implementation UG-OPM-22382-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 9 Monitoring and Evaluation Selection Implementation UG-OPM-22384-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 10 Monitoring and Evaluation Selection Implementation UG-OPM-22387-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 13,150.56 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 District Engineering Assistant 11 Monitoring and Evaluation Selection Implementation UG-OPM-22505-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 1 Monitoring and Evaluation Selection Implementation UG-OPM-22509-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 2 Monitoring and Evaluation Selection Implementation UG-OPM-22515-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 1 Monitoring and Evaluation Selection Implementation UG-OPM-22517-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 2 Monitoring and Evaluation Selection Implementation UG-OPM-22519-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 3 Monitoring and Evaluation Selection Implementation UG-OPM-22524-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 4 Monitoring and Evaluation Selection Implementation UG-OPM-22527-CS-INDV / Project Management, and Individual Consultant Pending IDA / 58210 Post Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 5 Monitoring and Evaluation Selection Implementation IGAD/ DRDIP/CS/7 / Regional Support for Recruitment of Consultant for Individual Consultant Pending IDA / D1200 Coordination, Capacity and Prior Open 70,000.00 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Capacity Support to Project Selection Implementation Knowledge Countries UG-OPM-22316-CS-CDS / Project Management, and Pending IDA / 58210 Prior Direct Selection Direct 120,723.12 0.00 2017-10-02 2017-10-12 2017-12-16 2018-06-14 Project Manager - DRDIP Monitoring and Evaluation Implementation Page 13 COMP4/C1/2017 / coordinateur Social and Economic Services Individual Consultant Under IDA / 58330 Post Open 30,000.00 0.00 2017-10-02 2016-10-25 2017-11-20 2017-12-11 2018-01-15 2018-07-14 de projet and Infrastructure Selection Implementation COMP4/C2/2017 / recrutement Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 d'ingénieur en Infrastructures and Infrastructure Selection Implementation COMP4/C3/2017 / recrutement Social and Economic Services Individual Consultant Pending de 4 techniciens supérieurs pour IDA / 58330 Post Open 62,400.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure Selection Implementation les régions et Djibouti ville COMP4/C5/2017 / recrutement Social and Economic Services Individual Consultant Pending d'un spécialiste en sauvegardes IDA / 58330 Post Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure Selection Implementation environnementales et sociales COMP4/C6/2017 / recrutement Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 d'un responsable Suivi evaluation and Infrastructure Selection Implementation COMP4/C7/2017 / recrutement Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 d'un comptable and Infrastructure Selection Implementation COMP4/C8/2017 / recrutement Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 12,000.00 0.00 2017-11-05 2017-12-24 2018-01-14 2018-02-18 2018-08-17 d'un assistant de projet and Infrastructure Selection Implementation COMP4/C9/2017 / recrutement Social and Economic Services Individual Consultant Pending d'un spécialiste Passation des IDA / 58330 Post Open 24,000.00 0.00 2017-10-05 2017-11-23 2017-12-14 2018-01-18 2018-07-17 and Infrastructure Selection Implementation marchés COMP4/C12/2017 / Enquette Social and Economic Services Pending sur les migrants à Balbala et à IDA / 58330 Prior Direct Selection Direct 71,967.00 0.00 2017-10-02 2017-10-07 2017-11-11 2018-05-10 and Infrastructure Implementation Djibouti-Ville COMP4/C16/2017 / Récrutement d'un expert Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 30,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 international pour la préparation and Infrastructure Selection Implementation de la stratégie de l'ONARS COMP4/C17/2017 / Récrutement d'un consultant Social and Economic Services Individual Consultant Pending individuel pour l'appui de l'expert IDA / 58330 Post Open 11,268.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure Selection Implementation en charge de la préparation de la stratégie de l'ONARS COMP4/C17/2017_1 / recrutement d'un expert Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 85,000.00 0.00 2017-11-15 2018-01-03 2018-01-24 2018-02-28 2018-08-27 international en manuel de and Infrastructure Selection Implementation procédures ONARS UG-OPM-30462-CS-CDS / Procurement of Consulting services for Updating of the Environmental and Social Project Management, and Under IDA / 58210 Prior Direct Selection Direct 41,551.00 0.00 2017-10-05 2017-10-17 2017-10-09 2017-10-19 2017-10-27 2017-11-24 Management Framework and Monitoring and Evaluation Implementation Resettlement Policy Framework for the Development Response to Displacement Impact Project. UG-OPM-22353-CS-CDS / Project Management, and IDA / 58210 Prior Direct Selection Direct 43,651.20 0.00 Canceled 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Procurement Assistant Officer Monitoring and Evaluation UG-OPM-22343-CS-CDS / Project Management, and Individual Consultant Pending IDA / 58210 Post Limited 76,010.88 0.00 2017-10-20 2017-10-25 2017-11-15 2017-12-20 2018-06-18 Project Accountant Monitoring and Evaluation Selection Implementation UG-OPM-22350-CS-CDS / ICT Project Management, and Individual Consultant IDA / 58210 Post Limited 43,651.20 0.00 Canceled 2017-10-27 2017-11-01 2017-11-22 2017-12-27 2018-06-25 Assistant Officer Monitoring and Evaluation Selection COMP4/C4/2017 / recrutement Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2019-01-15 d'un spécialiste en agriculture and Infrastructure Selection Implementation DJ-IGAD-37530-CS-INDV / Regional Support for Renewal of contract for Senior Individual Consultant Under IDA / D1200 Coordination, Capacity and Prior Direct 504,000.00 0.00 2017-11-22 2017-11-29 2017-12-02 2017-12-23 2018-01-27 2018-07-26 Programme Coordinator-IGAD/ Selection Implementation Knowledge DRDIP DJ-IGAD-37531-CS-INDV / Regional Support for Individual Consultant Under Renewal of the contract for the IDA / D1200 Coordination, Capacity and Prior Direct 192,500.00 0.00 2017-11-22 2018-02-28 2017-12-02 2017-12-23 2018-01-27 2018-07-26 Selection Implementation Project Accountant-IGAD/ DRDIP Knowledge DJ-IGAD-38100-CS-INDV / Selection of Consultant to undertake the Study to assess Regional Support for Individual Consultant Pending the socio-economic impact on IDA / D1200 Coordination, Capacity and Post Open 20,000.00 0.00 2017-11-24 2018-01-12 2018-02-02 2018-03-09 2018-09-05 Selection Implementation the migrant and refugee hosting Knowledge communities in Balbala, Djibouti Ville, Djibouti COMP4/C13/2017 / recrutement Social and Economic Services Individual Consultant Pending d'un consultant pour l'enquête IDA / 58330 Post Open 29,734.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 and Infrastructure Selection Implementation quantitative ménage COMP4/C14/2017 / recrutement d'un consultant pour l'enquête Social and Economic Services Individual Consultant Pending IDA / 58330 Post Open 26,133.00 0.00 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 quantitative jeunes femmes et and Infrastructure Selection Implementation périmètres agro pastoraux COMP4/C15/2017 / recrutement Social and Economic Services Individual Consultant Pending d'un consultant pour l'enquete IDA / 58330 Post Open - National 50,000.00 0.00 2018-01-30 2018-02-27 2018-03-13 2018-03-27 2018-05-26 and Infrastructure Selection Implementation qualitatif (focus groupe) COMP4/C16/2017 / Recrutement d'un consultant Social and Economic Services Individual Consultant Pending IDA / 58330 Post Limited 34,000.00 0.00 2018-03-14 2018-03-19 2018-04-09 2018-05-14 2018-06-28 pour l'enquête de suivi des and Infrastructure Selection Implementation indicateurs UG-OPM-52236-CS-INDV / Project Management, and Individual Consultant Pending Consulting Services for IDA / 58210 Post Open 95,589.00 0.00 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Monitoring and Evaluation Selection Implementation Communications Officer Page 14 UG-OPM-52238-CS-INDV / Project Management, and Individual Consultant Pending Consultant services for ICT IDA / 58210 Post Open 95,589.00 0.00 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Monitoring and Evaluation Selection Implementation Officer DJ-ADDS-54279-CS-INDV / recrutement d'un consultantpour Social and Economic Services Individual Consultant Pending IDA / 58330 Post Limited 20,000.00 0.00 2017-10-05 2017-10-10 2017-10-31 2017-12-05 2018-06-03 la sensibilisation,étude de and Infrastructure Selection Implementation marchés, mise a jour du listing COMP4/C17/2017_2 / Social and Economic Services Individual Consultant Pending recrutement d'un consultant pour IDA / 58330 Post Limited 80,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-06-29 and Infrastructure Selection Implementation é ence l'enquete de réfr 40000 / recrutement d'un Social and Economic Services Individual Consultant Pending consultant pour la IDA / 58330 Post Limited 40,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 and Infrastructure Selection Implementation communication COMP3/C1/2017 / recrutement Social and Economic Services Individual Consultant Pending d'un consultant pour l'analyse IDA / 58330 Post Limited 20,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 and Infrastructure Selection Implementation complémentaire de l'enquete Page 15