Document of The World Bank Report No: ICR0000443 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-31560 GEF TF-21598) ON A CREDIT IN THE AMOUNT OF 3.2 MILLION SDR (US$ 4.6 MILLION EQUIVALENT) AND ON A GLOBAL ENVIRONMENT FACILITY GRANT IN THE AMOUNT OF 1.3 MILLION SDR (US$ 1.3 MILLION EQUIVALENT) TO GEORGIA FOR AN INTEGRATED COASTAL MANAGEMENT PROJECT August 31, 2007 ECSSD South Caucasus Country Unit ICA Region CURRENCY EQUIVALENTS (Exchange Rate Effective December 31, 2007) Currency Unit = GEL GEL 1.00 = US$ 1.72 US$ 1.00 = GEL 0.58 FISCAL YEAR January 1 ­ December 31 ABBREVIATIONS AND ACRONYMS BSEP Black Sea Environmental Program CAS Country Assistance Strategy CPS Country Partnership Strategy DPA Department of Protected Areas of Georgia ETIB Project Energy Transit Institution Building Project EU TACIS European Union Technical Assistance to the CIS FMS Financial Management System GEF Global Environment Facility GEO Global Environment Objective GICM Project Georgia Integrated Coastal Management Project GIS Geographic Information System ICZM Integrated Coastal Zone Management IDA International Development Association ISR Implementation Status and Results KNP Kolkheti National Park KNR Kobuleti State Nature Reserve MoEPNR Ministry of Environment Protection and Natural Resources of Georgia MTR Mid Term Review NEAP National Environmental Action Plan NGO Non Governmental Organization OD Operational Directive OP Operational Policy PDO Project Development Objective PIU Project Implementation Unit PMR Project Management Report TA Technical Assistance TF Trust Fund WWF World Wildlife Fund Vice President: Shigeo Katsu Country Director: Donna Dowsett-Coirolo Sector Manager: Juergen Voegele Project Team Leader: Darejan Kapanadze ICR Team Leader: Darejan Kapanadze GEORGIA Integrated Coastal Management Project CONTENTS Data Sheet A. Basic Information B. Key Dates C. Ratings Summary D. Sector and Theme Codes E. Bank Staff F. Results Framework Analysis G. Ratings of Project Performance in ISRs H. Restructuring I. Disbursement Graph 1. Project Context, Development and Global Environment Objectives Design............. 1 2. Key Factors Affecting Implementation and Outcomes .............................................. 5 3. Assessment of Outcomes.......................................................................................... 11 4. Assessment of Risk to Development Outcome and Global Environmet Outcome .. 18 5. Assessment of Bank and Borrower Performance ..................................................... 19 6. Lessons Learned ....................................................................................................... 22 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners.........25 Annex 1. Project Costs and Financing.......................................................................... 26 Annex 2. Outputs by Comonent...........................................................................28 Annex 3. Economic and Financial Analysis .....................................................32 Annex 4. Bank Lending and Implementation Support/Supervision Processes ..........35 Annex 5. Beneficiary Survey Results.........................................................................37 Annex 6. Stakeholder Workshop Report and Results...............................................45 Annex 7. Summary of Borrower's ICR and /or Comments on Draft ICR....................46 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders....................... 54 Annex 9. List of Supporting Documents ...................................................................... 57 MAP A. Basic Information Integrated Coastal Country: Georgia Project Name: Management Project IDA-31560,JPN- Project ID: P050911,P060009 L/C/TF Number(s): 50946,WBTF-21598 ICR Date: 11/29/2007 ICR Type: Core ICR REPUBLIC OF Lending Instrument: SIL,SIL Borrower: GEORGIA Original Total XDR 3.2M,USD 1.3M Disbursed Amount: XDR 3.2M,USD 1.3M Commitment: Environmental Category: B,B Focal Area: B Implementing Agencies: Ministry of Environment Protection and Natural Resources Cofinanciers and Other External Partners: Senter, the Agency of the Ministry of Economic Affairs B. Key Dates Integrated Coastal Management Project - P050911 Process Date Process Original Date Revised / Actual Date(s) Concept Review: 04/10/1997 Effectiveness: 05/21/1999 05/21/1999 Appraisal: 05/18/1998 Restructuring(s): 12/26/2002 Approval: 12/17/1998 Mid-term Review: 12/26/2002 Closing: 12/31/2004 02/28/2007 Integrated Coastal Management (GEF) Project - P060009 Process Date Process Original Date Revised / Actual Date(s) Concept Review: 05/01/1998 Effectiveness: 05/21/1999 05/21/1999 Appraisal: 05/18/1998 Restructuring(s): 12/26/2002 Approval: 12/17/1998 Mid-term Review: 12/26/2002 Closing: 12/31/2004 10/31/2006 C. Ratings Summary C.1 Performance Rating by ICR Outcomes Moderately Unsatisfactory GEO Outcomes Satisfactory i Risk to Development Outcome Substantial Risk to GEO Outcome Low or Negligible Bank Performance Moderately Satisfactory Borrower Performance Moderately Unsatisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Bank Ratings Borrower Ratings Quality at Entry Satisfactory Government: Moderately Unsatisfactory Quality of Supervision: Moderately SatisfactoryImplementing Agency/Agencies: Moderately Satisfactory Overall Bank Moderately SatisfactoryOverallBorrower Moderately Performance Performance Unsatisfactory C.3 Quality at Entry and Implementation Performance Indicators Integrated Coastal Management Project - P050911 Implementation QAG Assessments Performance Indicators (if any) Rating: Potential Problem Project Quality at Entry at any time (Yes/No): Yes (QEA) None Problem Project at any Quality of time (Yes/No): Yes Supervision (QSA) None DO rating before Moderately Closing/Inactive status Satisfactory Integrated Coastal Management (GEF) Project - P060009 Implementation QAG Assessments Performance Indicators (if any) Rating: Potential Problem Project Quality at Entry at any time (Yes/No): No (QEA) None Problem Project at any Quality of time (Yes/No): No Supervision (QSA) None GEO rating before Closing/Inactive Status Satisfactory D. Sector and Theme Codes Integrated Coastal Management Project - P050911 Original Actual Sector Code (as % of total Bank financing) Central government administration 50 50 ii General agriculture, fishing and forestry sector 32 44 Other social services 9 3 Sub-national government administration 9 3 Theme Code (Primary/Secondary) Biodiversity Primary Primary Environmental policies and institutions Primary Primary Participation and civic engagement Secondary Secondary Pollution management and environmental health Primary Primary Water resource management Primary Primary Integrated Coastal Management (GEF) Project - P060009 Original Actual Sector Code (as % of total Bank financing) Central government administration 3 10 General agriculture, fishing and forestry sector 91 84 Other social services 3 3 Sub-national government administration 3 3 Theme Code (Primary/Secondary) Biodiversity Primary Primary Environmental policies and institutions Primary Primary Participation and civic engagement Secondary Secondary Pollution management and environmental health Primary Primary Water resource management Primary Primary E. Bank Staff Integrated Coastal Management Project - P050911 Positions At ICR At Approval Vice President: Shigeo Katsu Johannes F. Linn Country Director: D-M Dowsett-Coirolo Judy M. O'Connor Sector Manager: Juergen Voegele Michele E. de Nevers Project Team Leader: Darejan Kapanadze Rita E. Cestti ICR Team Leader: Darejan Kapanadze ICR Primary Author: Ulrich Zeidler iii Integrated Coastal Management (GEF) Project - P060009 Positions At ICR At Approval Vice President: Shigeo Katsu Johannes F. Linn Country Director: D-M Dowsett-Coirolo Judy M. O'Connor Sector Manager: Juergen Voegele Michele E. de Nevers Project Team Leader: Darejan Kapanadze Rita E. Cestti ICR Team Leader: Darejan Kapanadze ICR Primary Author: Ulrich Zeidler F. Results Framework Analysis Project Development Objectives (from Project Appraisal Document) The project aims to strengthen institutions in Georgia to manage the coastal resources of the Black Sea by developing, testing and evaluating methods to effectively integrate environmental concerns into sustainable coastal development planning at the national, regional, and local levels. Revised Project Development Objectives (as approved by original approving authority) Global Environment Objectives (from Project Appraisal Document) The project aims to assist Georgia in meeting its international commitments under the Black Sea Environmental Program (BSEP) and to implement priority actions outlined in the Georgia Biodiversity Strategy/Action Plan. These priorities include conservation of biodiversity at sites of international significance on Georgia's Black Sea coast, such as the Kolkheti and Kobuleti wetland Ramsar sites; restoration of degraded habitats and resources within the Black Sea Large Marine Ecosystem; and participation in regional efforts to manage and sustain public goods of a transnational character. Revised Global Environment Objectives (as approved by original approving authority (a) PDO Indicator(s) Original Target Formally Actual Value Indicator Baseline Value Values (from Revised Achieved at approval Target Completion or documents) Values Target Years Indicator 1 : Coordination mechanism for intersectoral planning and management of coastal resources established at national and local level s. Value National and local ICZM unit of the (quantitative orNo formal mechanism in level coordination Monitoring and Qualitative) place mechanisms Forecasting Center established under the Ministry iv through legislation of Environment established as an information and knowle dge base for integrated planning and management of coastal resources. Date achieved 05/21/1999 06/30/2006 02/28/2007 Comments 30% achieved. No local coordination mechanisms were established and the (incl. % central ICZM unit is not a representative body manda ted to reconcile multiple achievement) interests, but rather a ministerial division to advise Government on coastal planning and management Indicator 2 : Local stakeholder participation facilitated in coastal development management decisions Involvement of Involvement of No precedents of local stakeholders in stakeholders in Value stakeholders' true decision-making decision-making on (quantitative or involvement in decision- on coastal matters coastal resource use Qualitative) making on coastal facilitated by matters by development national and local administrations of authorities protected areas Date achieved 05/21/1999 06/30/2006 02/28/2007 Comments 30% achieved. An organized and meaningful involvement of stakeholders by the (incl. % national and local authorities has not become a common pattern, but rather achievement) happens occasionally and mostly if demanded by international development institutions/donors. Indicator 3 : Specialists trained in coastal resource planning and management tools and environmental education. Value (quantitative or 0 35 48 Qualitative) Date achieved 05/21/1999 06/30/2006 02/28/2007 Comments (incl. % 100% achieved. achievement) (b) GEO Indicator(s) Original Target Formally Actual Value Indicator Baseline Value Values (from Revised Achieved at approval Target Completion or documents) Values Target Years Indicator 1 : Information node for Black Sea regional coastal environmental monitoring network established in Georgia Value The national The information (quantitative or No node in place information node for coastal Qualitative) network put in environment place, database monitoring network v created, and established under connection with the Ministry of the regional Environment; network connection wit h established regional points of data entry established; databases designed and available data entered. Date achieved 05/21/1999 06/30/2006 02/28/2007 Comments 80% achieved. Institutions, hardware, and software are all in place. With (incl. % arrangements have been made and some restructuring still ongoing, the network achievement) is just starting operation. The information flow is not well established. Indicator 2 : Provision made for introducing and retaining user fees for protected areas Legislation providing for generation, retention, and Value Provision enacted reinvestment of (quantitative or No provision in place through adopted revenues (including Qualitative) legislation user fees) by protected areas adopte d and arrangements made for its enforcement. Date achieved 05/21/1999 06/30/2006 02/28/2007 Comments (incl. % 100% achieved achievement) Indicator 3 : National park staff trained Value (quantitative or 0 20 21 Qualitative) Date achieved 05/21/1999 06/30/2006 02/02/2007 Comments (incl. % 100% achieved achievement) (c) Intermediate Outcome Indicator(s) Original Target Formally Actual Value Indicator Baseline Value Values (from Achieved at approval Revised Completion or documents) Target Values Target Years Indicator 1 : The first elements of a cohesive institutional and legislative framework in place; consultative commissions in place and func tioning effectively Value No institutional and legal Interim ICZM unit created vi (quantitative or framework in place consultative within the Qualitative) commissions in Monitoring and place; legislation Forecasting Center drafted and passed under the Ministry on to the of Environment. Parliament for ICZM Guidelines approval issued by t he Ministry of Environment. Date achieved 05/21/1999 12/31/2005 02/28/2007 Comments 30% achieved. Permissive environment has been provided for ICZM though the (incl. % Law on Spatial Planning and Urbanization, though ICZM has not been made achievement) mandatory. Consultative commissions recommended in the ICZM Guidelines, but not required or established. Indicator 2 : Hardware and software effectively used in collaborating institutions; effective warning systems implemented. Renovation of premises of collaborating No adequate institutions A full set of completed; hardware and Value IT/laboratory hardware IT/laboratory software installed in (quantitative or and software available in hardware and laboratories and Qualitative) collaborating institutions; no warning systems software supplied mostly functional. implemented and being instal Warning systems led; warning designed. systems designed and ready for launching in 2006 Date achieved 05/21/1999 12/31/2005 02/28/2007 Comments 60% completed. Out of 3 laboratories, 1 is fully operational, 1 is liquidated, and (incl. % 1 is operating below capacity due to lack of funding and continuous changes in achievement) management. The monitoring program is not fully operational due to scarce funding. vii G. Ratings of Project Performance in ISRs - Actual Disbursements No. Date ISR Archived DO GEO IP (USD millions) Project 1 Project 2 1 02/01/1999 S S S 0.00 0.00 2 06/24/1999 S S S 0.00 0.00 3 12/23/1999 S S S 0.10 0.00 4 12/30/1999 S S S 0.10 0.00 5 06/28/2000 S S S 0.38 0.09 6 07/18/2000 S S S 0.39 0.09 7 09/06/2000 S S S 0.39 0.09 8 01/03/2001 S S S 0.39 0.09 9 06/29/2001 S S S 0.45 0.10 10 12/17/2001 S S S 0.45 0.10 11 01/18/2002 U U U 0.49 0.13 12 08/09/2002 U U U 0.69 0.13 13 11/21/2002 U U S 0.76 0.14 14 01/31/2003 S U S 0.98 0.22 15 02/07/2003 S S S 0.98 0.22 16 08/06/2003 S S S 1.19 0.23 17 03/04/2004 S S S 1.60 0.28 18 07/15/2004 S S S 1.84 0.36 19 08/25/2004 S S S 1.91 0.38 20 02/24/2005 MU MS MU 2.77 0.46 21 06/28/2005 S S S 2.92 0.52 22 02/07/2006 MS S S 3.54 0.68 23 02/22/2007 MS MS S 4.56 1.30 viii H. Restructuring (if any) ISR Ratings atAmount Disbursed RestructuringBoard ApprovedRestructuring at Restructuring in Reason for Date(s) USD millions Restructuring & Key PDO GEO Changes Made Change Change DO GEO IP Project1 Project 2 A significant conclusion made at MTR was that the Integrated Coastal Management Project had been mostly directed from the cap ital city of Georgia located far outside the coastal zone, and there was little participation in project implementation at the local level (rural communities and coastal municipalities). The PDO did not change at 12/26/2002 N U S 0.87 restructuring. In response to the above finding, ho wever, an additional output was added to the project design - the development and implementation of an effective communications str ategy for integrating of project components and maximizing the impact of its deliverables. Six performance indicators were designed for measuring progress in achieving the mentioned output. ix An important lesson learned at MTR was that local communities had been not sufficiently involved in the planning of Kolkheti protected areas and continued to have little awareness of their implications. While the GEO had not changed at restructuring, the co 12/26/2002 N U 0.14mponent output was revised to include presence of fully operational protected area management plans. Also, the previous single perf ormance indicator was replaced with six new ones, all with emphasis on measuring progress in mainstreaming local community participa tion. x I. Disbursement Profile P050911 P060009 xi 1. Project Context, Development and Global Environment Objectives Design 1.1 Context at Appraisal The Black Sea plays a crucial role in the welfare of Georgia's population. Not only does it provide essential goods and crucial links to markets for oil and other products, but it has intrinsic ecological value and deeply rooted cultural and historic significance. Over the past decades, uncontrolled pollution, coastal erosion intensified by human intervention, over-fishing, intervention of alien species, and off-shore dumping have devastated the Black Sea and its littoral zone. Ongoing economic development, including construction of oil terminals, creates a substantial new risk from oil spills to the wetlands and nearshore marine environment of Georgia. With the change to a parliamentary democracy, Georgia has entered a new phase of environmental activism. The Ministry of Environment, responsible for coordinating government efforts to protect and conserve the country's environment, has made important progress toward strengthening legal and regulatory instruments for improved environmental management and produced major pieces of environmental legislation. Georgia has become a party to the Bucharest Convention for the Protection of the Black Sea Against Pollution (1992), Convention on Biological Diversity (1994), Ramsar Convention on the Wetlands of International Importance (1996), and signed the Strategic Action Plan for the Rehabilitation of Protection of the Black Sea (1996). The first National Environmental Action Plan (NEAP) was also prepared. In line with the NEAP and the recent development in environmental legislation, the Georgia Integrated Coastal Management (GICM) project was designed to support the government's interests in strengthening institutional capacity for environmental management and ensuring that development along the Black Sea coast is consistent with principles of environmentally and socially sustainable development. An integrated approach to coastal management is essential for ensuring Georgia's biodiversity conservation. Increasing public awareness through information collection and dissemination, environmental education and participation of local communities and NGOs was an underlying theme in all components of the project, which was intended to increase project ownership by stakeholders and to improve prospects for sustainability of integrated coastal management beyond the life of the project. 1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved) The project aimed to strengthen institutions in Georgia to manage the coastal resources of the Black Sea by developing, testing and evaluating methods to effectively integrate environmental concerns into sustainable coastal development planning at the national, regional and local levels. Key performance indicators included: 1 - intersectoral consultative commissions for integrated coastal zone management (ICZM) established and functioning according to agreed objectives and procedures at national and local levels, - Georgians trained in coastal resource planning and management tools and public awareness and conflict resolution techniques, - draft legislation outlining mandate and responsibilities of a coastal authority and codes of conduct for coastal resource/landscape use prepared, - oil spill contingency plan and financing plan developed and approved by the government, - significant private sector involvement in oil pollution fund capitalization, - cost-effective options to address coastal erosion and municipal water use priorities identified. 1.3 Original Global Environment Objectives (GEO) and Key Indicators (as approved) The project aimed to assist Georgia in meeting its international commitments under the Black Sea Environmental Program (BSEP) and to implement priority actions outlined in the Georgia Biodiversity Strategy/Action Plan. These priorities comprised conservation of biodiversity at sites of international significance on Georgia's Black Sea coast; restoration of degraded habitats and resources within the Black Sea Large Marine Ecosystem; and participation in regional efforts to manage and sustain public goods of a transnational character. Key performance indicators included: - establishment of legal status of the Kolkheti National Park (KNP) and Kobuleti State Nature Reserve (KNR) and demarcation of their boundaries, - encroachment, illegal poaching and harvesting rates reduced over baseline conditions, - information node for the Black Sea regional environmental monitoring network established in Georgia, - computer links and information sub-nodes in collaborating institutions up and running. 1.4 Revised PDO (as approved by original approving authority) and Key Indicators, and reasons/justification The original development objectives were maintained throughout the project life. Key indicators were slightly revised at the project mid term to better measure institutionalization of the ICZM principles and public outreach of the project. 1.5 Revised GEO (as approved by original approving authority) and Key Indicators, and reasons/justification The original global environmental objectives were maintained throughout the project life. 2 Key indicators were revised at the project mid term to address concerns about post- project sustainability of the beneficiary protected areas and insufficient involvement of local communities in planning and managing the protected areas of Kolkheti. 1.6 Main Beneficiaries The primary target groups of project beneficiaries included the communities living within the coastal zone of Georgia, communities living in and around the protected areas of Kolkheti, and the communities located in the port cities of Poti and Batumi. In reaching these ultimate beneficiaries, the project delivered technical assistance to: (i) the laboratory for water quality monitoring of the Batumi Institute of Marine Ecology and Fisheries, now absorbed by the Monitoring and Forecasting Center under the Ministry of Environmental Protection and Natural Resources (MoEPNR); (ii) the Central Laboratory of the Ministry of Health of the Autonomous Republic of Achara; (iii) the laboratory for water quality monitoring under the Poti Municipality; (iv) the Coastal Dynamics Institute, now absorbed by the Monitoring and Forecasting Center under the MoEPNR; (v) the Integrated Coastal Zone Management Center, now absorbed by the Monitoring and Forecasting Center under the MoEPNR; (vi) the administrations of the Kolkheti protected areas under the Department of Protected Areas, MoEPNR; (vii) the Convention Inspection for the Protection of the Black Sea under the MoEPNR, and (viii) the Maritime Transport Administration and Marine Rescue and Coordination Center of the Ministry of Transport, now absorbed by the Ministry of Economic Development. The coast-based laboratories would benefit from the increased capacity to monitor quality of drinking water, surface water in the sea, rivers, lakes and reservoirs, bathing water at beaches, marine water off-shore, as well as to track key marine biodiversity (Batumi lab). The Coastal Dynamics Institute would gain capacity to monitor, model and forecast coastal dynamics using coastline and river modeling software. The ICZM Center would accumulate a set of informative and reliable quantitative and qualitative information on the coastal zone, including reports, photos, satellite imagery, GIS database, maps, etc. Administrations of the Kolkheti protected areas would become sustainable, modern, and viable institutions with legally and administratively sound basis, capable of delivering mandated responsibilities for conservation and sustainable use of natural resources within these protected areas. 1.7 Original Components The overall program comprised five components. The World Bank financed the first and the third components and administered the GEF grant financing for the second component. The government of the Netherlands provided parallel financing for the fourth and fifth components of the project. Component 1. Integrated Coastal Zone Management Institutional Capacity-Building. This component aimed to establish an institutional and legal framework for ICZM in Georgia through the development of institutional arrangement to facilitative intersectoral planning and the participation of key stakeholder groups in coastal resource decision making. This would be achieved through the creation of: (i) a State Consultative Commission for ICZM, (ii) the Working Group for the Advancement of ICZM; and (iii) three local ICZM Consultative Commissions along the Black Sea Coast. 3 Component 2. Establishment of Kolkheti National Park and Kobuleti Nature Reserve This component sought to improve the protection and management of threatened forest and wetland natural habitats within the Kolkheti coastal region through: (a) creation of the Kolkheti National Park and the Kobuleti Nature Reserve; (b) support to protected area administration and management; (c) establishment of infrastructure for improved biodiversity protection and development of nature-based tourism; and (d) improved monitoring and applied research on biodiversity and the effectiveness of conservation efforts. Component 3. Establishment of a Coastal Environmental Quality Monitoring and Information System. This component was intended to facilitate establishment of an environmental quality monitoring system and information network through: (a) development of new monitoring standards and regulations; (b) delivery of necessary measurement, sampling, and analysis equipment to selected monitoring laboratories and agencies; (c) organization of training programs; and (d) building a system of coastal information exchange between the central ICZM node and collaborating institutions located in Tbilisi as well as in Kolkheti (Poti, Batumi, and Kobuleti). Component 4. Evaluation of Coastal Erosion and Municipal Water Use. To assess the factors contributing to coastal erosion, particularly in the risk-exposed areas of Poti (Rioni River-Mouth) and Batumi (Chorokhi River-Mouth), this component was to finance comprehensive analysis of municipal water use and associated infrastructure in Poti and Batumi. Based on these studies a plan for integrated municipal water management would be developed for each locality, including analysis of cost effectiveness of interventions to control erosion, and feasibility of proposed options to sustainability address the most serious aspects of coastal erosion. Component 5. Development of a National Oil Spill Contingency and Marine Pollution Control Plan. This component aimed to increase Georgia's capacity to implement the regional Black Sea Strategic Action Plan and to deal with existing and future risks of oil pollution through providing support in preparation, according to the International Maritime Organization's guidelines, of a national oil spill contingency plan and emergency response program. It would also facilitate identification of future investment opportunities for prevention and abatement of oil pollution through contingency and operational spills. 1.8 Revised Components There was no revision of the initial project components. 1.9 Other significant changes At the project mid term revisions were made to the formulation of the expected outputs and key performance indicators. These changes introduced more emphasis on 4 communicating project objectives and activities to stakeholders and on mainstreaming the interests of local communities in the planning and management of protected areas. During project implementation some reallocation of funds increased the amount of credit resources as well as government co-financing for components 1 and 3 to cover staff salaries and operating costs for two additional years of project implementation, to afford a fuller set of equipment for the project beneficiary laboratories, to renovate some office space of the MoEPNR (including space for PIU) after the Ministry's move to the new premises, and to address a few more minor needs that had emerged under these components during implementation. The project required three extension of the closing date for the IDA Credit and two extensions of the closing date for the GEF TF Grant that moved these dates from the planned December 31, 2004, to October 31, 2006, and February 28, 2007, respectively. These extensions became necessary due to several reasons: project effectiveness 5 months past approval, poor government co-financing of the project at early stages of its implementation, little commitment to and slow action on the GEF-financed component at an earlier phase of project implementation, and persisting institutional changes in the administrations of all key involved institutions: the MoEPNR, the DPA, the KNP, coast- based laboratories, and the PIU. 2. Key Factors Affecting Implementation and Outcomes Quality at entry was satisfactory. The project was relevant, because it directly responded to the government's objective to protect the environment and support sustainable natural resource management through integrating environment into economic policies and strengthening institutional framework for mainstreaming of environmental planning and management into economic sectors. The project idea was conceived during implementation of the GEF-financed component of an earlier Municipal Infrastructure Rehabilitation project, under which many of the key elements of the future GICM project were identified. For better formulation of needs, some participatory workshops and consultation were held with local authorities. The project component for the establishment of Kolkheti protected areas was designed in collaboration with regional support groups, facilitated by the conservation program of WWF in Georgia. A dozen NGOs, actively involved with environmental and social issues, were consulted to help shape the package of assistance to be delivered to the beneficiary protected areas and to plan activities in their support zones. While participatory processes at the project preparation stage looked adequate, difficulties encountered at the implementation phase revealed a deficiency in community outreach, because the local authorities, interest groups, and NGOs did not prove to be fully representative of the affected communities. The project design was based on comprehensive analysis that included cost effectiveness, fiscal impact, technical, institutional, social, and environmental implications. Potential 5 risks and expected sustainability of the project outcomes were also considered. The overall rating of risks was modest and the identified potential threats included loss of the government's commitment, political instability, delay in adoption of the Kolkheti protected areas legislation, lack of incentives to encourage compliance with coastal zone management regulation, lack of cooperation between public and private sectors in development capacity to respond to oil spills, and inability to recruit and retain qualified staff for project implementation purposes. The risk analysis proved to be mostly realistic and the identified measures for risk minimization have been applied during the project implementation. The lessons from other Bank projects in the region underscore the need to (i) obtain support at the highest levels to ensure commitment to project objectives and the necessary allocation of resources for the project; and (ii) focus on institutional strengthening and capacity building in the technical and policy areas (this is particularly true for integrated coastal zone management, which requires an interdisciplinary approach). Lessons also suggest that (iii) simple focused projects tend to be more successful than complex and comprehensive undertakings; and finally, (iv) building on existing PIUs to take advantage of knowledge and networks formed earlier can advance project design while institutionalizing expertise. Other valuable lessons for establishing integrated coastal management in Georgia come from experience beyond the Black Sea, namely, from regional environmental programs in the Baltic and Mediterranean Seas. These include the need to integrate coastal management planning into national development plans; the need to build ownership of the project locally through public awareness and involvement in project design and implementation; and the need to focus on project sustainability and resource mobilization to ensure continuity beyond the project implementation period. The GICM project design reflected these lessons in the project's incremental approach aimed at building a sound foundation for ICZM through institutional strengthening and local participation. However, the principles of ICZM do not allow a simple focus approach and, therefore, the risk of being dependant upon the support of many institutions could have not been significantly minimized. 2.2 Implementation Implementation in general was moderately satisfactory. The project had been at risk at its mid term mostly due to failure of the government to manage conflicting interests of Kolkheti wetland protection and the development of a large scale oil terminal in the same area. After receiving strong signals from the Bank and whistleblower NGOs, the government took several remedial actions, the most important of which was the MoEPNR's engagement with the Ramsar Bureau for getting advice and guidance on approaches to compensation for the lost wetlands. In the course of this cooperation some 1,300 hectares of land have already been added to the park area. Significant delays in the implementation of the GEF-financed component around mid term of the project were caused by slow decision-making and processing of the transfer of user rights to a building allocated to host the administration of the KNP. Eventually this issue was resolved and 6 fully adequate premises were delivered to the park administration. Government co- financing had been poor at the earlier stage of implementation, but later improved and has not been an issue thereafter. Institutional arrangements for project administration were generally satisfactory. Estimates of project costs were reasonable. Changes in country context and project clients/beneficiates During the project life some major political, policy and administrative shifts occurred in Georgia, including the national Rose Revolution, revolution in the Autonomous Republic of Achara (that comprises a good part of Georgia's coastal zone), four changes in the Minister of Environment in charge of the project implementing agency, three changes in the head of the Department of Protected Areas, three changes in the director of the project beneficiary KNP, and a major restructuring of the project implementation unit within the MoEPNR, including a high rate of staff turnover. These events caused delays in project implementation due to changing political priorities, policy trends, institutional set-up, and staffing of key institutions involved, and also due to varying security situation and accessibility of some project implementation sites. Altered political/policy framework The ICZM capacity building component of the project is the one mostly influenced by the altered national policy trends. Although improvement of the coastal resource management remained high on the government's agenda, the national and local consultative bodies for ICZM were considered an additional institutional layer and their establishment found redundant in the context of the overwhelming trend of liberalization and de-regulation. A legal framework for ICZM is now established, though its mechanism is different from what had been initially conceived. The Law of Georgia on Spatial Planning and Urban Development was passed by the Parliament in 2005. It provides for integrated planning of development at the local, regional and national levels. The Law requires that planning is based on consideration of interests of the affected legal and physical bodies, local governing / self-governing bodies and the State, and also obligates that ecosystems as well as natural and cultural resources are sustained. With such Law in force, the government saw no need for specialized ICZM legislation. The draft ICZM law was, therefore, re-worked into the Guidelines for ICZM and issued by the MoEPNR as a supplement to the Law on Spatial Planning and Urban Development. The Guidelines add some specific costal zone dimensions to this legislation. An ICZM Center was established at the project start-up and it functioned as a PIU for several years. Later several PIUs under the MoEPNR were merged and the ICZM Center, as a self standing legal body, was abolished. A new institutional unit for ICZM was then created in January 2007 as a part of the Monitoring and Forecasting Center under the MoEPNR. This unit is not a consultative body representing various interest groups of the coastal zone - as originally envisaged - though it can contribute much to the improved planning and decision making on coastal matters while acting as an information and knowledge base. All studies, reports, maps, images, and databases accumulated during GICM project implementation are being transferred to the Monitoring and Forecasting Center. The ICZM unit of the Center is designated and equipped to accumulate the flows of monitoring data and other incoming information on the quality of coastal environment. 7 Therefore, the Center has been given a mandate to facilitate ICZM process through provision of empirical data, professional judgment, and technical tools for planning, managing, and monitoring developments in the coastal zone. However, capacity of the young ICZM unit still needs to be built up to a point that is adequate to its role and responsibilities. Overall, the institutional and legal framework for ICZM established as a result of the GICM project is weaker than targeted at the project design stage. Kulevi oil terminal The construction of the Kulevi Oil Terminal, causing a loss of 90 ha of wetlands protected under Ramsar Convention on the Protection of Wetlands, was on the Bank's radar screen throughout the project life for several reasons: (i) this large infrastructure project had major environmental and social impacts within the coastal zone; (ii) it had significant implications for the outcomes of the GEF-financed second component of the GICM project; and (iii) the Bank's top management was approached by international and Georgian environmental NGOs with a plea to exercise sanctions against Georgia due to negative global externalities of Kulevi oil terminal. Kulevi oil terminal was declared to be of paramount economic and geopolitical importance by both pre- and post-revolution governments and the Bank has never disputed that. The Bank repeatedly flagged to the government its concerns about the non-compliance of Kulevi project with national legislation and the international Ramsar Convention, and emphasized the need to mitigate environmental impacts of the terminal. Construction commenced without an environmental permit and without formal de-listing of the construction site from the Ramsar Convention on the Protected of Wetlands of International Importance. Later the permit was issued contingent on meeting several requirements. At present they are met partially. The developer has produced an additional study on biodiversity (including a monitoring plan) and shared with the MoEPNR the first draft contingency action plan for addressing oil spills in the terminal, including its marine part and the railway access road. The Ministry's comments are now being incorporated. The developer, through a sub-contractor, has also produced a study with valuation of damage caused to the ecosystem due to construction and future operation of the terminal, along with a proposed compensation package. Communication with Ramsar Bureau on de-listing of the former site and allocating the new ones will be made by the MoEPNR once the compensation parcel is internally agreed upon. Overall, commencement of the Kulevi oil terminal construction without addressing environmental issues was a bad environmental practice and inconsistent with the ICZM principles. Later the new government of Georgia took several steps towards restoring environmental compliance of the Kulevi project, including partial compensation of the loss through allocation of alternative wetland sites for restoration and conservation, and including them into the Kolkheti protected areas. At the same time, the operation of Kulevi oil terminal will require taking some area out of the marine part of the KNP, or at least re-alignment of its present boundaries. 8 Some environmental NGOs argued that the co-existence of the KNP and the Kulevi oil terminal was impossible and requested the Bank to terminate the GICM project financing unless the terminal construction was discontinued. It was evident that the possibility of project closure would not stop construction in Kulevi, but it might be interpreted as proof of the low importance of Kolkheti wetlands and bring about additional environmental damage. Furthermore, stopping project financing half way through would waste most of the investments already made. At the same time, continuing project implementation would be pointless if the construction in Kulevi could wipe out its outcomes. The decision to keep the project in the Bank's portfolio was made as a result of careful consideration of these factors. By the time of the present ICR, outcomes of the GEF- financed component of the project prove that the wetland ecosystems of Kolkheti are far better off as a result of project implementation than they would have been otherwise and the project's environmental objective has been met. Project outreach and local involvement Stakeholder workshops during the MTR identified certain shortcomings in project outreach and communication at the local level. In particular the following deficiencies were noted: (i) a lack of information about the project for stakeholder communities, local government, and NGOs; (ii) weak public awareness and involvement in the project work; (iii) limited tangible positive impact of the project at the local level; and (iv) insufficient participation of local communities in the planning of protected areas' management. The main message from the MTR mission was a call for shifting emphasis to the local level in all aspects: project administration, public outreach, community empowerment, stakeholder involvement, etc. In response to the mission's recommendations: (a) a communication strategy was developed and implemented in cooperation with the administrations of the project beneficiary protected areas; (b) one PIU staff unit began to function as Public Relations Officer; (c) one new PIU staff unit was created with a duty station in the coastal zone; (d) additional funds were obtained from the Japanese Social Development Fund for the implementation of a Small Grants Program aiming Kolkheti lowland communities, (e) a number of key output indicators and PDO indicators were reformulated to measure progress in enhancement of the project work at local level. 2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization Monitoring and evaluation of the project implementation progress was based on the logical framework provided in the PAD that carried a set of goals, objectives, outputs, and outcomes organized in a hierarchical order and the respective key performance indicators, as approved. The project outcome indicators included: · Coordination mechanism for intersectoral planning and management of coastal resources established at national and local levels, · Provision made for introducing and retaining user fees for protected areas, · User based financing mechanism(s) for control of oil pollution piloted, · Specialists trained in coastal resource planning and management tools and environmental education, 9 · Information node for Black Sea regional coastal environmental monitoring network established, · Black Sea environmental education materials developed for formal and informal sectors, · National park staff trained, · Local stakeholder participation facilitated in coastal development management decisions. Some of these indicators, though, would have been more suitable to measure project outputs, rather than outcomes (especially, development of training materials and training of park staff). During the MTR, the logical framework and key performance indicators were revised and upgraded to reflect some lessons learned and to strengthen the logical links between the project objectives, outputs, and monitoring indicators. Overall, the vast majority of performance indicators before as well as after revision at the MTR have been qualitative. A few quantitative indicators lacked baseline numerical data where no relevant monitoring had been carried out in the country prior to the project launch. Several tracking tools were used to measure project progress against the established indicators. The World Bank's monitoring tool, applied regularly throughout the project life, was the conduct of bi-annual supervision missions of the task team, that included extensive field work in the project implementation sites, meetings with the project clients, beneficiaries, and stakeholders. Analysis of the missions' work was regularly documented in Aide Memoires and ISR Reports. Advancement of project implementation was reported annually by the PIU through comprehensive progress reports. However, the PIU ceased submitting progress reports after the MTR, which created a gap in the borrower's reporting between the project MTR and completion. The PIU explained this by being overloaded with the government's frequent, multiple, and sometimes ad hoc requests to report on various project parameters in a variety of formats. While this argument was not groundless, general progress reporting to the Task Team should have not been compromised and more attention should have been paid to the improvement of time management and delegation of responsibilities within the PIU. The development progress of the protected areas of Kolkheti was tracked by applying the WB/WWF Management Effectiveness Tracking Tool. Information obtained through application of this tracking tool contributed to monitoring of the outputs and outcomes of component 2 of the project and worked as an additional incentive for protected area administrations for improvement. Tracking project-related developments of Georgia's national legislation was also an indicator for evaluating the project's progress in meeting its development and global objectives. 10 Overall, the monitoring framework carried a decent mix of qualitative and quantitative indicators that were measured in the course of the project implementation. 2.4 Safeguard and Fiduciary Compliance Implementation of the project was monitored to track compliance with four triggered safeguards: Environmental Assessment (OD 4.01), Natural Habitats (OP 4.04), Forestry (OP 4.36), and Projects in International Waters (OP 7.60). Compliance with OP 4.36 and OP 7.60 has been satisfactory throughout the project life. Compliance with OD 4.01 and OP 4.04 was considered unsatisfactory during three years of project implementation (2002 through 2004). The rationale for that was the construction of Kulevi oil terminal in the wetland area protected under the Ramsar Convention and in immediate proximity to the KNP. Later the task team reconsidered the rationale for reflecting activities not funded from the project proceeds in rating of the project's compliance with the safeguards and found it more relevant to apply ratings primarily with reference to the activities within the project scope. Therefore, compliance of project implementation with all triggered safeguards has been rated satisfactory since 2005. Fiduciary compliance was monitored on a regular basis through financial management supervision. Findings and recommendations of supervision were documented in FMS reports. The Borrower submitted to the Bank Project Management Reports (PMRs) on a quarterly basis, as well as annual independent audit reports on the project's books and accounts. No major issues have been encountered in the financial management of the project. 2.5 Post-completion Operation/Next Phase The government recently created a knowledge and information basis for ICZM by setting up the new ICZM unit within the Monitoring and Forecasting Center under the MoEPNR. It is now of the pivotal importance that this new unit is built up to be able to perform as a potent and viable national node of the coastal environment monitoring network where all existing studies, reports, maps, images, and databases are combined and all monitoring data from the coastal areas are further collected and evaluated. The government of the Autonomous Republic of Achara has taken the first steps to integrate principles of ICZM into their coastal development plans. These include: (i) application for funds and TA for the development of landscape master plans for the territory of the Autonomous Republic, (ii) designation of a new National Park of Mount Mtirala and ongoing work to establish two more protected areas, including a trans- boundary one with Turkey, (iii) introduction of pollution hotspot monitoring along the coast, that implies tracking of point sources of industrial pollution, and (v) improvement of beach management practices utilizing good and bad experience from the pilot activity launched in Kobuleti under the GICM project. Successful implementation of these initiatives would result in a tangible and sustainable improvement of the quality of coastal environment in Achara. 11 The government of Georgia, using technical assistance from EU TACIS financed Black Sea Investment Facility (BSIF): Georgia, Moldova, Russia, Ukraine developed a number of infrastructure project ideas, all dealing with the environmental health of the Black Sea. These include projects for water supply and waste water treatment in the port city of Poti and the seaside resort Kobuleti, as well as waste management and disposal projects for Kobuleti and the port city of Batumi. Feasibility studies for these projects are completed and investments for the detailed engineering design and implementation of these projects are being secured by the government. Implementation of these projects would contribute much to decreasing pollution of marine and terrestrial environment in the coastal zone. The GICM project helped to establish two coastal protected areas. The KNR has already become an important international destination for wetland studies. The KNP, along with a major conservation value, carries considerable potential for nature tourism. With an excellent visitor center, interpretation facilities, and other tourist infrastructure it is ready to receive and service visitors. Proper marketing of the KNP, possibly in a package with other natural and as well as cultural attractions of the Georgia's coastal zone, is of crucial importance. Some amendments to the Law on Establishment and Management of Kolkheti Protected Areas are expected to deal with issues arising from (i) social tensions in the Lanchkhuti district area within the KNP, (ii) compensation for wetlands lost to Kulevi oil terminal, and (iii) entry of the Kulevi terminal into operation. One legally designated part of the KNP, which falls under administrative district of Lanchkhuti district, de-facto is not yet delivered to the jurisdiction of the Park administration, as the authorities have not come up with acceptable alternatives for community forest use within this area. The Department of Protected Areas (DPA) under the MoEPNR is working with local government, the Department of Forestry, and communities to resolve this matter. The three laboratories supported under the GICM project have received a comprehensive package of assistance to bring them up to international standards of environmental quality monitoring. One of the laboratories, however, was closed shortly after project completion. Due to still ongoing institutional changes, the system of agreed-upon water quality monitoring data generation as well as their compilation, processing, and publishing in the ICZM unit of the Monitoring and Forecasting Center is not yet operating smoothly. Available funding is insufficient for full operation and proper maintenance of the coastal laboratories. Therefore, their technical capacity is underutilized. The MoEPNR should promptly address the above issues and come up with adequate solutions, allowing them to take full advantage of the high-tech laboratory facilities obtained as a result of the GICM project implementation. Erosion of Georgia's Black Sea coastline continues to be a pressing problem, originating from natural as well as anthropogenic sources both within and outside the country's territory. The GICM project brought in the best international expertise for analyzing nature of erosion, understanding coastal dynamics and proposing a range of possible technical solutions. Human capacity, hardware and software for coastal modeling were 12 delivered to the Institute of Coastal Dynamics, which recently was absorbed by the Monitoring and Forecasting Center of the MoEPNR. This provides good institutional grounds for the ICZM unit and the coastal dynamics team to work jointly under the umbrella of this Center and to provide valuable advice to a recently created inter-agency commission on coastal erosion. The marine oil spill contingency action plan was drafted under the GICM project in 2000. The document was not adopted by the government due to lack of consent between stakeholders on the roles of various agencies in reacting to possible spills. Neither had the final decision been reached on the mechanism of financing the response actions. Later the Bank-supported Energy Transit Institutional Development project picked up the draft action plan to reflect the recent administrative changes and to include a fresh set of comments from the stakeholders. The new iteration of the marine oil spill contingency action plan is now delivered to the MoEPNR. The next step would be for the MoEPNR to circulate it to the Cabinet and facilitate formal adoption by the government. The World Bank, through its continued sector dialogue with the MoEPNR, will keep track of the government's next steps and actions on the above issues that remain important for the purpose of the GICM project developmental and global objectives beyond its lifetime. An analytical and advisory activity of the Bank, as planned in the current CPS, around legal and policy issues of resource use in the KNP would be highly beneficial for continuing cooperation with the government on long term sustainability of protected areas. 3. Assessment of Outcomes 3.1 Relevance of Objectives, Design and Implementation The GICM project was designed during the period of the CAS dated September 12, 1997. Protecting the environment and supporting sustainable natural resource management was one of four main objectives of that CAS. Among the associated issues identified in the CAS were that environmental concern had not been effectively integrated into economic policies and that institutional arrangement to facilitate the mainstreaming of environmental planning and management into economic sections were weak. The design of the GICM project was highly appropriate to the above CAS objective and the issues identified therein. The GICM project objectives and the design of its component financed from GEF were also fully relevant to the priorities of the GEF Biodiversity focal area under operational programs for the Coastal, Marine and Freshwater Ecosystems as well as for the Forest Ecosystems. The project activities concentrated on the conservation and sustainable use of biodiversity in coastal forest wetlands and nearshore waters of Georgia which are of international importance. At the same time, they were designed to support Georgia in meeting its commitments under the BSEP and to implement priority actions outlined in the NEAP. The integrated approach chosen in the project design for the management of coastal resources reflects actual trends of international environmental legislation. 13 While the project was prepared and approved by the end of 1998, it became effective in May 1999 and implementation finished in 2006. This period of time was very intense in terms of political developments in Georgia. After an initial starting period, the project was affected by the country-wide deteriorating situation in 2002-2003. The project was successful during this period in ringfencing specific coastal protection activities from the external situation, including maintaining a positive dialogue with the Autonomous Republic of Achara during a tense period between Tbilisi and the Achara government. It was appropriate during this period that the MTR confirmed the validity of the PDOs, with an increased focus on the need to strengthen communication and local participation. Following the Rose Revolution in 2004 until present, the government consolidated its political and economic situation, and began to move in a direction towards more de- regulation and less interference with the private sector. This resulted in a tension between the earlier approach and the new one, but no further effort at restructuring took place to adjust to this new situation, initiated by either the Bank or the Borrower. The reluctance of the Cabinet to pass the ICZM legislation and to establish representative consultative bodies for ICZM decision-making at the national and local levels became apparent in early 2006. The work under ICZM component of the project was then shifted promptly and efforts were re-directed towards development of ICZM Guidelines. This non-discretionary document of advisory nature was issued by the MoEPNR in the last year of the project implementation. While protection of the environment and of natural resources dropped on the government's priority list over the project's lifetime, the development of Georgia's tourism potential has been declared one of the vehicles for the country's economic growth. In this light strengthening and expanding of the protected area network for nature tourism is getting high level political support. While the project was at risk in the past due to failure of the former government to allocate an adequate building for the administration of the KNP and the limited ownership of the park by its local administration as well as the DPA, the situation changed significantly under the new government. With adequate leadership at both central and local levels and the increasing public funding to the protected areas of Kolkheti, implementation progress of the GEF - funded protected areas component of the GICM project improved tangibly towards the end. 3.2 Achievement of Project Development Objectives and Global Environment Objectives Achievement of PDO: The project partially met its development objective. Key indicators of PDO achievement were (i) creation of a mechanism for inter-sectoral planning and management of coastal resource use, (ii) ensuring stakeholder participation in coastal management, and (iii) training a critical number of specialists in the ICZM A legal framework for ICZM has been established, though through the instruments different from what was planned initially. The Law on Spatial Planning and Urban Development was passed by the Parliament in 2005, which provides for integrated planning of development at the local, 14 regional and national levels. This Law requires that planning is based on consideration of interests of the affected legal and physical bodies, local governing / self-governing bodies, and the State, and also obligates to ensure sustainability of ecosystems as well as conservation of natural and cultural resources. With such law in force, the government saw no need in a specialized ICZM legislation. Instead, the Law on Spatial Planning and Urban Development was supplemented with the Guidelines for ICZM, issued by the MoEPNR, that add some specific costal zone dimensions to this legislation. The project was not able to ensure meaningful participation of stakeholders in coastal management. Institutional mechanisms for stakeholder involvement should have been created by setting up representative bodies in several locations of the coastal zone as well as having one once central body in Tbilisi. However, the project did not result in the establishment of consultative commissions for ICZM, as such institutions had been considered a redundant additional layer of decision-making which could restrict the smooth flow of investments and economic growth. A conceptually different ICZM unit was set up under the MoEPNR as a knowledge base, rather than a forum for participatory intersectoral planning of coastal development. The ICZM unit is fully mandated and well equipped to operate as an information node for the Black Sea coastal environment monitoring network. Though, due to continuous restructuring of both central and coast- based institutions that comprise the monitoring network, the ICZM unit is not currently operating at full capacity and has yet to establish a strong ownership of the system. A sufficient number of specialists received training in the field of ICZM, which allowed them to acquire relevant knowledge and skills. Therefore, the project succeeded in creating human resources for ICZM at the national level. In summary, out of three PDO indicators one was fully met, while two indicators were achieved by about 30%. With this status towards the end of the project implementation, the overall outcome was found moderately satisfactory, because even without the ICZM law and inter-sectoral ICZM commissions, the project-assisted developments in the legal and institutional framework allowed for tangible improvement of coastal planning and management practices. However in the period between the project closure and the time of this ICR the government showed little interest in promoting integrated planning of development within the framework established under the project based on the Law on Spatial Planning and Urban Development and the ICZM guidelines. Furthermore, while all three beneficiary laboratories for water quality monitoring had been operational by the project completion and the ICZM unit had been created within the Monitoring and Forecasting Center for the MoEPNR, at present one of the laboratories is abolished, the second one has developed problems due to poor management, and the central ICZM unit is not performing effectively its mandate. Therefore, the ICR rates achievement of PDO moderately unsatisfactory. Achievement of GEO: Overall outcome of the GEF-financed component for the establishment of the KNP and the KNR is satisfactory and the project met its global environmental objective. Key indicators of achieving GEO were (i) creation of an information node to accumulate 15 coastal monitoring data, (ii) establishment of use fee collection and retention system in the protected areas of Kolkheti, and (iii) increasing capacity of the protected areas' staff. Starting from scratch by designating these protected areas, towards the project completion their management plans have been approved and operational, the area under protection has been registered and physically benchmarked, capable administration units built, effective system of patrolling introduced, high quality administrative and visitor servicing infrastructure installed, user fee collection and retention by administrations ruled in, and a strong basis laid for biodiversity monitoring and research. Both beneficiary protected areas are well established now, with their management structure on firm footing. Much effort has been invested in regulating natural resource use within the protected areas and reconciliation of local community interests with the goals of conservation and nature tourism development. Though this process is still ongoing and calls for further improvements at the national level, beyond the scope of GICM project. Issues around marine part of the KNP are not yet resolved. The boundaries of the marine part must be legally revised due to Kulevi oil terminal entering into operation in 2007, and its patrolling should be organized. Without undermining magnitude of this problem the achievement of GEO is still rated satisfactory to reflect a huge difference that the establishment of the KNP and the KNR made for the Georgia's coastal zone in terms of formalizing wetland conservation values as well as physically protecting wetlands from eradication through draining, timber and peat extraction, and other forthcoming threats. An information node for accumulation of the coastal information was created within the Monitoring and Forecasting Center of the MoEPNR. It holds valuable sets of baseline data, as well as analytical reports on the state of environment in the coastal zone, and a rich gallery of images. Collecting current information and keeping the databases up-to- date is a challenge faced by the Center. By and large, the project succeeded in the improvement of the protection and management of threatened forest and wetland natural habitats within the Kolkheti region and in integrating these protected areas into the broader objectives of development in the coastal zone. Achievements in conservation of Kolkheti wetlands is a major contribution to the implementation of the Georgia Biodiversity Strategy and Action Plan (BSAP), as preserving biodiversity sites of international significance on Georgia's Black Sea coast is among the priorities outlined in the BSEP. 3.3 Efficiency Costs incurred for implementing the GICM project were US$ 7.9 million along with potential costs of foregone economic activity as a result of establishing protected areas of Kolkheti. Out of the total project cost, financing of the GEF component was US$ 1.3 million, which represents the incremental cost for achieving sustainable global environmental benefits from conservation of Kolkheti wetlands carrying international importance. The types of foregone economic activities due to establishment of Kolkheti protected areas comprise hunting and peat mining, none of which would have any major economic importance. Potential costs of foregone fishing and firewood extraction had been minimized to negligible level, as the amendment introduced to the Law on the Establishment and Management of Kolkheti Protected Areas provided for the traditional 16 use zone within the park, where regulated extraction of fish and wood is permitted and meets the basic needs of the gateway communities. Overall benefits from the establishment and development of the Kolkheti protected areas are numerous. Although most of these benefits cannot be quantified, their importance is well justified. Benefits were secured in public health, tourism, preservation of ecological resources - including the functional values of wetlands for flood protection, pollution filtration and habitat values, including habitats for migratory birds. Project supported research of Kobuleti peat bogs led to the remarkable scientific finding that dramatically increases the value of Global benefit from their conservation. Namely, peat bogs of Kobuleti turned out to be of a rain-fed percolating type, which is a unique combination. Kobuleti bogs also have been proven to have an outstanding growing rate. Ongoing research may lead to the development of peat bog farming technology for environmentally harmless production of peat in future. Investments into the establishment and development of Kolkheti wetlands had an important positive spillover to the Georgia's national network of protected areas. The GICM project supported debates over the legal instruments for protected areas zoning and administration, that have directly resulted in upgrading the national legislation on protected areas. Also, the GEF component of the GICM project increased awareness of the importance of wetland ecosystems that had been almost non-existent by the time of the project start-up. 3.4 Justification of Overall Outcome and Global Environment Outcome Rating The project development objective was highly relevant at the time of preparation and remained so throughout the project life. With the increasing magnitude of energy transit through Georgia's seaports and booming investment in coastal infrastructure, the importance of the project's development objective even grew during its implementation. At the same time the overriding political trend of creating a welcoming environment for investment and the tendency towards deregulation altered the government's vision of what they would like to achieve through introduction of ICZM in this country. The project adapted to the changing demands of the client and, overall, succeeded in laying foundation for Georgia's ICZM capacity. However, without proper institutions or forums for meaningful involvement of local stakeholders in planning of coastal development and with limited indication of the government's ownership of ICZM principles towards the project completion and post project phase, the overall outcome rating of the Bank project is moderately unsatisfactory. The Global environmental objective of the project has been fully relevant throughout the project life. The government's ownership of the GEF Component of the GICM project has considerably increased towards the end of project implementation, which allowed achieving much despite significant delays and problems encountered earlier in the project life. Investing a modest amount of US$1.3 million in the GEF-financed component of the project generated significant benefits at the local, national, and international level and produced sustainable, irreversible outcomes. With the excellent results and prospects for wetland conservation in the KNR and in the terrestrial part of the KNP, but little 17 achievements in the marine part of the park due to the compromising decisions on Kulevi oil terminal, the overall environmental impact of the project is satisfactory. 3.5 Overarching Themes, Other Outcomes and Impacts Institutional Change/Strengthening The process of developing, discussing, and approving management plans for Kolkheti protected areas has been a learning process for several involved institutions. This exercise contributed much to the development of in-country capacity of protected area planning. A team of professionals that had contributed to the management plans of the KNP and the KNR is currently involved in planning of other protected areas and their expertise is in high demand. Experience with Kolkheti protected areas demonstrated certain weaknesses of the public consultation process previously believed to be good enough and applied to planning of these protected areas. Lessons learned are fully applied to the process of planning new protected areas in the country. A lengthy process of adopting management plans for Kolkheti protected areas led to the identification of some procedural glitches. As a result, the government amended the procedure of approving protected area management plans and made it less cumbersome. Through the building of a new visitor center in the KNP, the project helped to introduce the concept and principles of "green architecture" to the country. The architect of this building got the initial inspiration for this approach through one of the project's study tours to the US National Parks and is now successfully promoting the ideas of green architecture within Georgia. 4. Assessment of Risk to Development Outcome and Global Environment Outcome The overall rating for the risk to project development outcomes is significant. The main background behind this rating is the persisting institutional changes in combination with a powerful trend of deregulation and liberalization in support of ambitious goals as regards attracting investments to the country and achieving strong economic growth. With respect to ICZM institutional capacity building this means that the integrated and participatory planning approach, as envisaged in the project design, is not well supported by the government. It decided against creating participatory consultative institutional bodies for planning coastal development at the national and local levels. The ICZM Guidelines, developed under the project, represent a somewhat weaker, non-binding planning tool that leaves the introduction of stronger coastal zone specific regulations and legal instruments for the future. The newly established ICZM unit under the Monitoring and Forecasting Center within the MoEPNR was established very recently. Its new staff has to build up their ICZM capacity from a basic level. The central ICZM database established under the project 18 (GIS, protocols of data exchange) is currently unattended. Therefore, there is no firm assurance of having a successful ICZM unit in place any time soon. It should be noted though, that the approval of the Law on Spatial Planning and Urban Development in 2005 has created a permissive environment for stakeholder participation and consideration of different interests in planning of coastal development. With respect to the establishment of coastal environment quality monitoring and evaluation system, the institutional sustainability of project outcome is questionable. Out of the three laboratories that received equipment and training under the project, one is fully functional, one has been abolished with currently unclear arrangements for absorption of its functions by other institutions, and for one - staff turnover has already contributed to some loss of the acquired capacity. The overall rating of the risk to GEO outcome is low. The main reasons for this evaluation are impressive results from the GEF component of the project. The KNP and the KNR have been successfully established. The major part of designated territories is legally transferred to the protected area administrations, border demarcation is completed, functioning administration units and high quality administrative and visitor servicing infrastructure are in place. Considerable effort has been made to regulate natural resources use within the protected areas with tangible results regarding forest management, fishery and hunting. Both administrations of the project beneficiary protected areas are continuously working on further improvement of their law enforcement measures. Ownership of and support to the KNP and the KNR demonstrated by the Department of Protected Areas is fully adequate. Public funding from the State budget of these protected areas has been increasing for the last couple of years. With the current management structure on firm footing, prospects for conservation of internationally important coastal wetlands and biodiversity are generally good. It is also expected that the development of nature tourism will contribute to stabilize the protected areas. 5. Assessment of Bank and Borrower Performance 5.1 Bank Performance Bank Performance in Ensuring Quality at Entry The Bank's overall performance in the identification, preparation assistance, and appraisal of the project is rated satisfactory. An Environment Specialist with extensive worldwide experience in marine biology and coastal matters was in charge of the team at the early stage of the project identification and preparation. The preparation was adequately performed in a reasonable time, resulting in a well-designed project addressing government priorities as outlined in the CAS as well as the Global objectives of conserving wetland ecosystems and their biodiversity. For shaping up the GEF- financed component, the outputs of the WWF's Conservation Program in Georgia were plugged into the project planning. Using of this resource was highly relevant, as the WWF's work had identified the Kolkheti wetlands as a location for one of the seven 19 potential national park sites in Georgia and produced guidelines for the development of protected areas in Kolkheti. All key arrangements for project implementation, including placement of a PIU within the MoEPNR as well as establishment of accounting, financial reporting, and auditing systems, had been made on time and with due consideration. The Bank got assurance in the government's commitment to the introduction of ICZM policies and principles through the establishment of a central consultative body on ICZM prior to the project start-up. The State Consultative Commission for Integrated Coastal Zone Management was indeed set up through a presidential decree in October 1998. Quality of Supervision The Bank's supervision performance was moderately satisfactory. In the course of implementation, the Bank conducted 17 supervision missions (about two a year) and a MTR. The Sector Manager made important contribution to the MTR by visiting project implementation sites and participating in the discussions with the project clients, beneficiaries, and other stakeholders. In general, the composition of the Bank missions in terms of appropriate skill mix, expertise and staff continuity was assured, with consultants mobilized for specific areas when needed. In response to the findings of MTR, a key message of which was the lack of local community involvement in and ownership of the project, the Bank's task team provided strong follow up on the development and implementation of a public awareness program. Furthermore, the task team raised Japanese Social Development Fund financing for carrying out a project for Improving Livelihood Security in Kolkheti Lowlands, as a supplemental activity to the GICM project. The project implementation progress was carefully monitored by the supervision team and was recorded in the ISRs. The Bank systematically tracked financial management and procurement under the project through regular oversight of the financial management system of PIU, commenting on and clearing procurement documents pertaining prior review contracts and conducting regular post-reviews of other procurement. Safeguard compliance was also monitored throughout the project implementation and recorded in all ISRs. The supervision team has been cooperative and helpful to the project implementing agency. This implied, inter alia, working closely with four different administrations of the MoEPNR and three administrations of the DPA that were in office during the project lifetime, to discuss relevance of the project concept, brief on the implementation history, explain the Bank expectations of the Borrower performance, and achieve synergy. The Bank team also maintained constructive dialogue on project related issues with the environment protection and natural resources agency of the Autonomous Republic of Achara. One shortfall in project supervision was that the project team kept its cooperation on project matters confined to the implementing agency, and within this agency talked 20 mostly with one high ranking focal point designated for overseeing the Bank-assisted operations. In regular circumstances this could have been sufficient, but in a highly dynamic political environment and during a period of major policy changes the supervision team should have sought broader views on the developments which had been of multi-sectoral interest. With that the Bank could have diagnosed a need for restructuring elements of the project related to integrated planning process and could have taken initiative in discussing this matter with the government. Justification of Rating for Overall Bank Performance The Bank's performance was fully satisfactory at the early stage of the project identification and preparation. Supervision was also well organized and highly professional, through its efforts were affected by nation-wide political developments which raised issues of a cross-sectoral nature and, therefore, stronger higher level management attention might have been warranted at times. The rating of the overall Bank performance is, therefore, moderately satisfactory. 5.2 Borrower Performance Government Performance The government was highly committed to the project idea at the preparation stage and acted proactively on a few matters. For instance, the State Consultative Commission for ICZM was established through the Presidential Decree in October 1998, preceding the project effectiveness in May 1999. The ICZM Center was established in the capacity of the GICM PIU in April 1999, also prior to the date of effectiveness. Shortly after the project start-up the issue of Kulevi oil terminal construction emerged. Important decisions and rulings made by the government pertaining to this construction project deviated from national legislation and the provisions of the Ramsar Convention, which certainly was not in harmony with the ICZM spirit and the best practice. Later political and policy trends emerging in Georgia caused further weakening of the government's ownership of the ICZM approach, though no formal request was made for restructuring or dropping any of the GICM project components. Towards the end of the project life the government did not adopt ICZM legislation opting rather for non-biding ICZM guidelines, and did not establish ICZM consultative bodies. This reduced commitment was exacerbated by numerous changes in environmental and project management over the project life. Unlike their mixed attitude towards the ICZM principles, the government's commitment to the GEF financed component of the GICM project increased substantially over the time. Significant hindrances were experienced with implementation of this component at the earlier stage of implementation due to lack of the government's commitment and delayed decision-making. Later the new administration of the MoEPNR turned things around and provided excellent cooperation on all major aspects. The strong leadership of the MoEPNR's central administration and the DPA in achieving sustainability of protected areas of Kolkheti continues post-project and is remarkable. 21 Delays in co-financing of the GICM project from the State budget was a major issue early in project implementation. Significant improvement of the country's financial systems and institutions after the Rose Revolution has eradicated the glitches in co- financing and it has been smooth ever since. Overall, the Borrower's performance is rated moderately unsatisfactory. Implementing Agency or Agencies Performance The MoEPNR provided good leadership and oversight during the preparation and implementation of the GICM project. The ICZM Center under the MoEPNR acted as a GICM PIU for the considerable period of implementation. Closer to project completion a new legal body was established as a PIU for all Bank assisted operations being implemented by the MoEPNR. While the ICZM Center demonstrated full dedication to the project goals and objectives and carried good technical staff, it was weaker in contract management and in meeting established deadlines. Restructuring of the PIU resulted in a stronger management and closer integration of its work with the MoEPNR mainstream activities, though the skill mix deteriorated somewhat with the loss of technical professionals. Reporting progress on the project implementation was inadequate since the MTR. Eventually, the Implementing Agency with its PIU managed to deliver majority of the project outputs that had been under its control and discretion, disbursed all but negligible proceeds of the project and properly accounted for them. Performance of the implementing agency is, therefore, rated moderately satisfactory. Justification of Rating for Overall Borrower Performance Considering performance of the Borrower, the project implementing Ministry, and the Project Implementation Unit in general during all stages of the project cycle, the rating is moderately unsatisfactory. 6. Lessons Learned Community awareness and participation in a project may not always be achievable through adequate involvement of local NGOs. Community outreach is a big challenge, as that implies extensive work with a great number of diverse people. Therefore, it is logical to try reaching communities through their representative bodies, such as elective bodies of local government and more so ­ local NGOs. But that may not always be a sufficient tool for public outreach in Georgia. Membership of many NGOs in this country is based on belonging to a professional field. Some are being created to set up bodies eligible for receiving grants or for selling variety of services. Such NGOs are usually good policy promoters, fundraisers or watchdogs, but they may not be reliable conduit for community preferences and concerns. Therefore, the extent to which local NGOs could be used as agents for community involvement calls for cautious consideration on case-by-case basis. 22 Consultative councils of protected areas in Georgia are actually dysfunctional at present and their concept needs to be rethought. An example with the KNP and the KNR illustrated a problem with setting-up and operating consultative councils to the protected area administrations, with is a generic issue for the national network of protected areas. The Law of Georgia on the Protected Areas System calls for having such councils in place and this legal requirement is being concurred with by formal establishment of the councils, but there is no example of an effectively functioning council for any of the protected areas. Therefore, revisions are required to make the councils viable, as they are in other countries. This could imply altering the existing mandate of the councils, changing the current pattern of member composition, and/or other measures. For biodiversity conservation projects it is advisable to plan development of biodiversity/protected area management plans as early in the project cycle as possible. The timeframe necessary for the development of management plans for Kolkheti protected areas under the GICM project had been dramatically underestimated, and later it turned out not to be an exceptional case for projects being implemented in Georgia. Delays with development of management plans resulted in a lesser time and resources available for their implementation within the project life and with project's assistance. The lesson drawn from this experience is that preparation of management plans should be scheduled within a realistic timeframe and as early in the project cycle as possible ­ preferably during project preparation. Efficiency of capacity building of institutions though short term training of staff is limited within the systems with high level of staff turnover. Capacity building activities conducted under the GICM project could have only a limited effect. One reason is the high rate of staff turnover and institutional instability which affects all levels of public sector management. The second reason is the general lack of adequate professional staff in the beneficiary public institutions due to modest salaries compared to the private sector. The short term training that is possible through a project could only supplement or improve existing skills but not replace professional education. Furthermore, investing too much in staff training carries a risk of not getting an adequate outcome, as there are no guarantees that majority of trained staff will stay in their current positions through the project life and beyond. Therefore, it is advisable to carefully balance between staff training and introduction of systemic changes in institutional/managerial patterns, which are less dependant on staff turnover. For medium term perspective projects should not focus on introduction of ambitious environmental legislation, but rather on achieving good environmental performance under current legal framework. Provided the assumption that the trend of de-regulation and market liberalization continues in Georgia, projects would most likely not succeed in fostering establishment of overarching environmental legislation. Instead, projects should concentrate on building awareness and capacity for good environmental performance at the level of 23 individual institutions, administrations, and communities. This recommendation is based on the fact, that current environmental legislation is being applied to full extent and it is actually permissive for much better performance, provided that there is willingness and adequate capacity in respective institutions. Management of protected area projects needs strong presence both centrally and locally. Establishment of new protected areas and other conservation efforts in most cases carry implications for local businesses and gateway communities. Their sensitivity to projects supporting protected areas calls for strong local presence of project proponents and implementing agencies from the very early phase of the project cycle. In case of the GICM project this lesson was drawn during the MTR and corrective measures were taken afterwards. If the project implementation unit had had local liaison officers in place right from the beginning, some shortfalls in cooperation with local communities may have been avoided. On the other hand, a project team's role in maintaining dialogue with relevant government agencies at the central level is equally important. This is instrumental for keeping up-to-date on policy trends and political developments, which may have direct influence on project implementation and may require some fine-tuning of project activities with the evolving country context. Success of a project under any line agency would depend on its ownership by a focal point in a politically strong branch of the government. The GICM project implementing agency, as well as the main cooperation partner during implementation, has been the MoEPNR. Since the key decisions on urban and coastal planning are taken by other line ministries, the project could have benefited from establishing more intensive cooperation with the (former) Ministry of Urbanization and Construction and the Ministry of Economy from an early stage of implementation. The conclusion from this example is that projects, which are complex by nature and carry development objectives that could be successfully achieved only through multi-sectoral approach, should be implemented with permanent involvement of all key players. Managing project implementation in a politically dynamic country should imply regular scanning of political trends and flexibility in adjusting to changing times. During the lifetime of the GICM project political environment in Georgia had changed significantly, which made the Borrower out of need for some of the project's expected outputs (ICZM law, national and local ICZM consultative bodies). Though the Borrower`s altered expectations of the project were not formally communicated to the Bank and no changes to the implementation plan were formally requested by the implementing agency. Under these circumstances, timely corrective actions could have been taken and a better outcome achieved if the importance of ongoing political changes for the project's success had been accurately diagnosed and sensitive components had been discussed and agreed upon with a broader group of key decision-makers in the government. 24 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/implementing agencies See annex 7. (b) Cofinanciers (c) Other partners and stakeholders See annex 8. 25 Annex 1. Project Costs and Financing (a) Project Cost by Component (in USD Million equivalent) INTGD COASTAL MGMT - P050911 Actual/Latest Components Appraisal Estimate Percentage of (USD millions) Estimate (USD millions) Appraisal ICZM INSTITUTIONAL CAPACITY-BLDG 1.20 2.02 1.35 EST. KOLKHETI NAT'L PARK & KOBULETI 2.69 2.54 0.79 NATURE RESERVE EST. COASTAL ENV. QUALITY MONITORING & 1.70 2.43 1.28 INFORMATION SYSTEM EVALUATION OF COASTAL EROSION 0.50 0.65 1.30 DEV. OF NAT'L OIL SPILL CONTINGENCY PLAN & MARINE POLLUTION 0.50 0.50 1.00 CONTROL PLAN Total Baseline Cost 6.59 Physical Contingencies 0.39 Price Contingencies 0.67 Total Project Costs 7.65 PPF 0.00 Front-end fee IBRD 0.00 Total Financing Required 7.65 INTGD COASTAL MGMT (GEF) - P060009 Actual/Latest Components Appraisal Estimate Percentage of (USD millions) Estimate (USD millions) Appraisal ICZM INSTITUTIONAL CAPACITY-BLDG 1.20 2.02 1.35 EST. KOLKHETI NAT'L PARK & KOBULETI 2.69 2.54 0.79 NATURE RESERVE EST. COASTAL ENV. QUALITY MONITORING & 1.70 2.43 1.28 INFORMATION SYSTEM EVALUATION OF COASTAL EROSION 0.50 0.65 1.30 DEV. OF NAT'L OIL SPILL CONTINGENCY PLAN & 0.50 0.50 1.00 MARINE POLLUTION 26 CONTROL PLAN Total Baseline Cost 6.59 Physical Contingencies 0.39 Price Contingencies 0.67 Total Project Costs 7.65 PPF 0.00 Front-end fee IBRD 0.00 Total Financing Required 7.65 (b) Financing P050911 - INTGD COASTAL MGMT Appraisal Actual/Latest Source of Funds Type of Estimate Estimate Percentage of Financing (USD (USD Appraisal millions) millions) Borrower Joint financing 0.90 1.10 1.22 International Development Association (IDA) Credit 4.40 4.58 1.04 NETHERLANDS: Min. of Foreign Parallel Affairs / Min. of Dev. Coop. financing 1.00 1.15 1.15 P060009 - INTGD COASTAL MGMT (GEF) Appraisal Actual/Latest Source of Funds Type of Estimate Estimate Percentage of Financing (USD (USD Appraisal millions) millions) Global Environment Facility (GEF) Grant 1.30 1.31 1.01 27 Annex 2. Outputs by Component Actual Value Baseline Original Target Values Achieved at Completion Project Outputs 1a. Effective Institutional arrangements for ICZM established at national and local levels 1b. ICZM legislation and implementation plans developed and harmonized for regulation of development activities in the coastal zone (a) The first elements of a cohesive No elements of Basic elements of Basic elements of institutional and legislative framework in institutional and institutional and legislative framework place; consultative commissions in place legislative legislative created. Creation of and functioning effectively framework for framework for ICZM-specific ICZM in place. No ICZM created. institutions found consultative Consultative redundant by the commissions exist commissions government. established and functional (b)* The most appropriate structure and No structure and Structure and National ICZM functions for national and local ICZM functions for ICZM functions for consultative council consultative commissions identified consultative ICZM consultative not found relevant by commissions commissions the government. identified identified and Structure and agreed between functions of local stakeholders ICZM councils recommended in the ICZM Guidelines (c)* Intersectoral consultative commissions No intersectoral Intersectoral ICZM Intersectoral ICZM for ICZM established and functioning consultative consultative consultative according to objectives and procedures commissions for commissions commissions not agreed through consultation at national, ICZM in place established and found relevant by the regional and local levels functional government (d)* Linkages established with national No specialized land ICZM-specific General ICZM cadastral survey project to facilitate use planning guidelines for land guidelines, including development of appropriate land use guidelines for use planning basic principles of land planning guidelines for ICZM ICZM exist developed and use planning, made available for developed and widely users disseminated. (e)* A cohesive and harmonized legislative No legislative Legislative Legislative framework framework for land use planning and ICZM framework for framework for harmonized land developed and operational harmonized land provided for use planning provided. use planning and harmonized land ICZM not enforced, ICZM in place use planning and but recommended ICZM 28 2. Protected areas clearly demarcated, and protected area management plans fully operational (a) Poaching and harvesting rates reduced Encroachment No plot of the KNP boundaries compared to baseline conditions; no new within Park protected areas expanded in May 2006 encroachment within Park boundaries boundaries taken away for to include additional being attempted alternative use 1300 ha of wetlands Note: No reliable baseline data existed on poaching and illegal forest harvesting rates and no quantitative target was set for reducing poaching and forest harvesting. Towards the project completion KNP administration has been reporting dramatic decrease in poaching and significant shift towards legalized forest use within the traditional use zone. (b)* Regulations respected, and Park Park administration Park administration environmental degradation trends stabilized administration successful in successful in enforcing within the park through partnership between ineffectively enforcing forest use regime park administration and local communities enforcing regulations in through offering regulations. result of permitted alternative Extreme cases established to local communities. of violation community Extreme cases of being reported partnership. poaching excluded (e.g. fishing Extreme cases of through improved with electric violation excluded. patrolling. shock devices) Regulations for managing Lake Paliastomi fishery in the process of formulation (c)* Local advisory councils established to No advisory KNP and KNR KNP and KNR have ensure the participation of communities in councils in have effectively formally established decision making with respect to protected place functioning but not effectively area management advisory councils functioning advisory councils (d)* A specific community outreach staff No community Community Community outreach post established within KNP administration outreach staff post outreach staff post staff post exists and an to be responsible for engendering awareness present within KNP exists and an incumbent performs and partnership, and to facilitate conflict administration incumbent mandated duties resolution performs mandated duties (e)* The Community Grant Scheme No Community KNP gateway 29 grants in total developed and managed as an effective and Grant Scheme in communities amount of USD transparent means of support to place supported through 942,650 equivalent communities whose livelihoods are the Community were given out to the negatively affected by the establishment of Grant Scheme KNP gateway the KNP communities through the Community Grant Scheme Note: The Community Grant Scheme for the KNP gateway community was provided through a supplemental project for Improving Livelihood Security in Kolkheti Lowland (ILSKL), financed with the Japanese Social Development Grant. 29 (f)* Local communities empowered by Local communities Local communities Local communities development of capacity to plan, and isolated, carrying capable of experienced in priority capture funds to improve and diversify their no capacity to plan organizing around setting, planning, and livelihoods ahead and to new initiatives, implementing common organize around planning, and initiatives through new initiatives jointly participation in the implementing project for ILSKL activities aimed at improving community livelinhood (g)* Linkages developed with other projects Protected areas Protected areas of Linkages with private and institutions, to avoid conflict of of Kolkheti not Kolkheti engaged sector yet in embryonic interests, to capitalize on lessons learned having any in alliances with phase. KNP engaged in and to add value from private sector alliances with other projects and a partnership agreement other projects institutions and with a sister protected and institutions benefiting from area of Point Reyes, which would developed USA, and Lake allow to avoid partnerships / Paliastomi got involved conflicts and synergies in the Living Lakes develop alliance. synergies (h)* Amendments to KNP legislation KNP legislation not KNP legislation Traditional use zone identified and formally adopted to clearly permissive for provides for established within KNP define the rights of access of local resource use by regulated access of through a legal communities local communities local communities amendment to park resources 3. Coastal Zone Monitoring and Information System activated and functioning for protection of public health and natural systems (a) High demand for information from user Negligible High demand for Demand for groups; effective warning systems demand for coastal information mostly implemented; hardware and software coastal information. from media. effectively used in collaborating institutions information. Effective warning Information on beach No effective system on beach water quality not warning system water quality disclosed to public in a on beach water operational. systematic manner. quality. ICZM Collaborating No relevant collaborating institutes equipped hardware and institutions with relevant hardware software present exchanging and software, but have in collaborating information not started to regularly institutions effectively. generate and exchange information. (b)* An information node for the Black Sea No information An information ICZM unit established regional environmental monitoring network node in place node institutionally under the MoEPNR, established in Georgia formed, equipped equipped, but not yet and functional functional (c)* Web site developed to provide access Monitoring data Monitoring data Web site for posting to the monitoring data not posted on the being regularly monitoring data not Web posted on the Web developed 30 4. Future investment program to control coastal erosion prioritised and associated risks quantified (a) Favourable response and follow-up by No significant Government Government the government and donors action on behalf of giving high established an Inter- government and priority to sectoral commission on donors in response addressing erosion problems for to the problems of coastline participatory planning coastline erosion erosion and and decision-making donors willing to assist (b)* Fundable small scale options for No small scale Small scale Artificial spreading of addressing erosion problems at a local level options developed options worked inert materials over the developed for addressing out for addressing eroded beaches has erosion at local erosion at local been offered as a small level level scale option for addressing most pressing erosion problems at the selected segments of coastline (c)* Coastal erosion control mechanisms Coastal erosion Government Government, through enforced control enforcing environmental mechanisms not regulations aimed inspectorate of being enforced at decreasing MoEPNR, strictly coastal erosion enforcing regulations on mining gravel from river beds 5. Tiered response strategy and implementation plan developed for oil spills and tested (a) Contingency plan and financing plan No contingency Contingency plan Contingency plan and developed and approved by government; plan and financing and financing plan financing plan private sector participation forthcoming plan in place. The approved. Private developed, but not role of private sector's approved yet. The role sector not defined participation of private sector not pledged clearly defined as the financing plan is pending approval (b)* Oil spill response strategy and No response Response strategy Response strategy equipment tested under field conditions strategy in place endorsed and developed, but not yet and no field test of equipment tested endorsed formally. equipment carried out under field Equipment successfully out for more than a conditions tested out under field decade conditions in Batumi harbor Note: Out put indicators marked with a star (*) were added to the results framework at mid term review of the project. 31 Annex 3. Economic and Financial Analysis Cost Effectiveness The economic assessment of the project, carried out as a part of its preparation, included analysis of costs and benefits which had been likely to result from project implementation. The identified costs included the total project costs (USD 7.6 million) and potential costs of foregone economic activity as a result of establishing the KNP and the KNR. While the types of foregone economic activities had been well known at project preparation stage, the associated costs had not been found quantifiable. The expected benefits included public health benefits; tourism benefits; institutional benefits, or benefits gained through setting up more effective means for cooperation and decision making; benefits from preservation of ecological resources; benefits from establishing of an oil spill prevention program, and non-use values of nature protection such as existence values and bequest values. The actual total project cost made USD 8.1 million, which is USD 0.5 million over the appraisal estimate. The reasons for this are several: one is the fluctuation of the rate of SDR exchange for USD; second is reallocation of the project proceeds from the categories of expenditure to be financed 100% from the Bank credit/grant to the categories financed at a lower % from the Bank credit/grant, which increased the need for government co-financing; and lastly, the government of the Netherlands increased the amount of their parallel financing of the project by USD 0.15 million equivalent during the project implementation period. The expected types of economic activity foregone due to establishing of the KNP and the KNR had been hunting, fishing, firewood collection, reed collection, and peat and gravel mining. Hunting for game indeed dropped in result of establishing the projected areas and this carries certain economic cost, through decreased hunting and the associated economic impact can not be attributed exclusively to the enforcement of the protection regime in the protected areas of Kolkheti. An outbreak of the Avian Influenza and a few incidences of the disease in wild avifauna registered in West Georgia resulted in a significant impact on bird hunting, which had been even banned throughout the country for a while. Establishment of the KNP resulted in altered patterns of fishing in Lake Paliastomi and small rivers flowing through the park. Fishing with illegal devices (electric shock) has been generally eliminated and some effort limitation has been applied through regulating fishing equipment (specifications of fishing nets). Subsistence fishing is allowed in the traditional use zone of the KNP, which significantly decreases the cost of foregone economic activity. Regulations for the use of Lake Paliastomi fishery are not fully worked out yet and may require certain legislative changes. The economic impact of restricted forest use due to enforcement of the KNP protective regime has been significantly mitigated through the establishment of the traditional use zone within the park. Local communities are allowed to collect 32 a pre-defined volume of firewood in the especially designated forest stands seasonally, which ensures that subsistence needs of rural households around the park are met. The project implementation did not cause any cost for resettlement, as the protected area boundaries had been drawn through an intense consultation process and avoided any change in land tenure. Most of the expected project benefits have materialized in result of its implementation. Economically the most significant benefits are those received from preservation of ecological resources, including the functional values of wetlands for flood protection, pollution filtration, and habitat values. Tourism benefits from the project are also quite significant, as the wetlands that had been actually a no-go area prior to the project implementation, are now being advertised as a tourist destination, well suited for receiving variety of visitors, and protected area administrations are institutionally capable of selling their services and managing visitation. One indirect economic benefit for local communities coming from the establishment of the KNP is that the market prices for real estate around the park's visitor center have increased in anticipation of increasing inflow of visitors and associated job/income opportunities. Establishment of the protected areas of Kolkheti had been decisive for the fate of wetland habitats and, therefore, for the existence of numerous floral and animal populations of this ecosystem, which would have otherwise become extinct in Georgia. Furthermore, the project intervention allowed to document the existence of unique type of pit bogs in Kobuleti and to conserve them, which is a significant gain at the regional level. Therefore, the project fully met expectations pertaining benefits from non-use values, namely, the existence value as well as the scientific value of the coastal wetland ecosystem. Institutional benefits from the project implementation are also tangible. Administrations of the two wetland protected areas have been established and their institutional capacity built from scratch to the highest national standard. The Department of Protected Areas under the MoEPNR of Georgia got vast experience in planning, organizing, and managing protected areas at the international quality standard level. The project achieved increase in the awareness of the importance of wetlands among several key governmental and non-governmental institutions. The public health benefits from the improved water quality monitoring and introducing of an effective warning system, as well as the benefits from increased preparedness for preventing and addressing marine oil spills are yet to be received from the project investments. All necessary inputs are provided and the end results are mostly a function of upcoming managerial decisions. The below table carries the project cost benefit analysis summary. 33 COSTS BENEFITS INVESTMENT COSTS ECOLOGICAL VALUES Waterfowl/bird habitat and migration route COST OF FOREGONE ECONOMIC preserved; ACTIVITY Natural buffer for flood protection preserved; Natural filtration of pollution maintained; Loss of hunting and peat mining Rare and highly endemic species conserved; activities; Pit bogs of a unique type discovered and conserved. Limitation in fishing and firewood extraction activities. INSTITUTIONAL BENEFITS Two wetland protected areas established, their institutional capacity built from scratch to the highest national standard, a model of a modern and fully functional protected area administration set up; The Department of Protected Areas under the Ministry of Environment Protection and Natural Resources of Georgia got vast experience in planning, organizing, and managing protected areas at the international quality standard level; Awareness of the importance of wetlands increased among several key Governmental and non- Governmental institutions through study tours and training delivered to their key staff. TOURISM BENEFITS Nature tourism benefit due to the Kolkheti National Park; Visitor fees generated and reinvested in the Park facilities; Research and other user fees generated and reinvested in Kolkheti protected area facilities NON-USE VALUES Existence Value to society ­ knowledge that one of Georgia's important natural resources has been preserved; Bequest value to society ­ knowledge that society today has done something to help preserve the environment for future generations 33 Fiscal Impact Total government financing of the project during its implementation period was estimated to be $0.9 million USD equivalent over the six year period. The actual amount of government financing made $1.1 million USD equivalent over an eight year period, which brought the annual fiscal impact lower than expected. The project was co-financed with the GEF grant of 1.3 million USD and the Netherlands government grant of $1.15 million USD equivalent (exceeding the appraisal estimate by $0.15 million USD equivalent) that helped to reduce the fiscal burden of borrowing. Establishment of the KNP and the KNR did not result in a significant increase of the number of public servants hired by the government, as the administrations of these protected areas are relatively small, and because a good part of staff units of park rangers had been creased through converting staff units of forest rangers under the forest district administrations. Public funding of operation and maintenance of the KNP and the KNR has been on an ascending trend towards the end of project implementation, while the project financing of their incremental operating costs started to drop. It happened in tune with an agreed upon strategy for a smooth phase-out of the project assistance to protected area administrations. During the project life the protected areas of Kolkheti were granted a legal status allowing them to generate their own income through collection of use fees and selling services. Such diversification of income sources certainly adds to the financial sustainability of the beneficiary protected areas and provides healthy economic incentives for their administrations (at least in the medium term, while visitation to the protected areas of Kolkheti is not expected to exceed their carrying capacity). 34 Annex 4. Bank Lending and Implementation Support/Supervision Processes (a) Task Team members Names Title Unit Responsibility/ Specialty Lending Darejan Kapanadze Operations Officer ECSSD Environment Specialist Frances Rosenthal Operations Analyst ECSPE Bank Project Processor Karin Shepardson Sr. Operations Officer ECSSD Environment Specialist Maria Eleni Hatziolos Sr. Environmental Specialist ENV Task Team Leader Supervision/ICR Anne N. Ranasinghe Procurement Assistant ECSPS Procurement Specialist Arman Vatyan Sr. Financial Management Specialist ECSPS FMS Supervisor Natural Resource Christian Gonner Consultant ECSSD Management and Social Specialist Darejan Kapanadze Operations Officer ECSSD Task Team Leader Elmas Arisoy Sr. Procurement Specialist EAPCO Procurement Specialist Nature Tourism Emanuela Montanari Development and Stephens Consultant ECSSD Public Relations Specialist Guranda Elashvili Procurement Assistant ECCGE Procurement Specialist Karl Skansing Consultant ECSPS Procurement Specialist Protected Areas and Kathleen S. Mackinnon Lead Biodiversity Specialist ENV Conservation Specialist Coastal Milen F. Dyoulgerov Operations Officer SDNVP Management Specialist Phillip Brylski Environmental Specialist ECSSD Biodiversity and Forest Specialist Rita E. Cestti Sr. Water Resources Econ. ECSSD Task Team Leader 35 b) Staff Time and Cost Staff Time and Cost (Bank Budget Only) Stage of Project Cycle No. of staff weeks USD Thousands (including travel and consultant costs) Lending 0097 0 36.21 0098 0 124.38 0099 0 55.75 0000 1.3 2.29 Total: 1.3 218.63 Supervision/ICR 0099 0 15.89 0000 32.60 116.56 0001 21.14 104.68 0002 25.09 82.35 0003 23.63 112.92 0004 24.04 63.55 0005 24.38 78.05 0006 25.79 96.43 0007 13.95 47.38 Total: 190.62 717.81 36 Annex 5. Beneficiary Survey Results The KNP - a key beneficiary institution of the GEF-financed component of the project - has been periodically surveyed using a simple site-level tracking tool developed for the World Bank and WWF and intended for reporting progress at protected area sites. The first time this tool had been used in 2002 to document the baseline in terms of legal and institutional status of the KNP as well as its functionality and effectiveness of management. Based on the scores, the KNP was found 26.5% successful in August 2002. In December 2004 the evaluation outcome was 36.6 %. The last evaluation was carried out in December 2005, which found the KNP 64.5% successful. Therefore, the progress over the evaluation period made 38%. Below provided is an evaluation sheet from the last survey of the KNP. According to the instruction on the use of this tracking took, the evaluation has been done by the KNP administration under the professional guidance provided by the Bank consultant. Issue Criteria Score Comments 1. Legal status The protected area is not gazetted 0 The government has agreed that the protected area 1 Does the protected should be gazetted but the process has not yet begun area have legal status? The protected area is in the process of being gazetted 2 but the process is still incomplete Context The protected area has been legally gazetted (or in the 3 case of private reserves is owned by a trust or similar) 2. Protected area There are no mechanisms for controlling 0 No law enforcement in Gurian regulations inappropriate land use and activities in the protected part of KNP. area Illegal wood-cutting is better Are inappropriate Mechanisms for controlling inappropriate land use 1 controlled now (by various land uses and and activities in the protected area exist but there are cooperating government activities (e.g. major problems in implementing them effectively bodies: Sakrebulo, KNP, poaching) controlled? environmental inspectorate, Mechanisms for controlling inappropriate land use 2 police). and activities in the protected area exist but there are some problems in effectively implementing them Context Mechanisms for controlling inappropriate land use 3 and activities in the protected area exist and are being effectively implemented 3. Law The staff have no effective capacity/resources to 0 Follow-up by courts often enforcement enforce protected area legislation and regulations unclear. In one case large group of fishermen demanded back There are major deficiencies in staff 1 Can staff enforce confiscated illegal equipment. capacity/resources to enforce protected area protected area rules Occasional intervention by legislation and regulations (e.g. lack of skills, no well enough? high authorities. patrol budget) In marine part, coast guard The staff have acceptable capacity/resources to 2 conducts patrol. enforce protected area legislation and regulations but some deficiencies remain Context The staff have excellent capacity/resources to enforce 3 protected area legislation and regulations 37 Issue Criteria Score Comments 4. Protected area No firm objectives have been agreed for the protected 0 Systematic planning started in objectives area May/June 2005. Activities follow identified priorities. Have objectives been The protected area has agreed objectives, but is not 1 agreed? managed according to these objectives The protected area has agreed objectives, but these are 2 only partially implemented Planning The protected area has agreed objectives and is 3 managed to meet these objectives 5. Protected area Inadequacies in design mean achieving the protected 0 New zoning is reflecting socio- design areas major management objectives of the protected economic situation and area is impossible previous conflicts. However, Does the protected Inadequacies in design mean that achievement of 1 new problems arose with area need enlarging, major objectives are constrained to some extent Kulevi railway route which corridors etc to meet overlaps with KNP. its objectives? Design is not significantly constraining achievement 2 of major objectives, but could be improved Reserve design features are particularly aiding 3 Planning achievement of major objectives of the protected area 6. Protected area The boundary of the protected area is not known by 0 No demarcation in Guria; boundary the management authority or local changes required along Kulevi demarcation residents/neighboring land users railway. Is the boundary The boundary of the protected area is known by the 1 known and management authority but is not known by local demarcated? residents/neighboring land users The boundary of the protected area is known by both 2 the management authority and local residents but is not appropriately demarcated The boundary of the protected area is known by the 3 Context management authority and local residents and is appropriately demarcated 7. Management plan There is no management plan for the protected area 0 Management plan has been finalized but not yet approved Is there a A management plan is being prepared or has been 1 by the government of Georgia. management plan and prepared but is not being implemented A forthcoming new law will is it being allow MoEPNR to approve implemented? An approved management plan exists but it is only 2 management plans. being partially implemented because of funding constraints or other problems An approved management plan exists and is being 3 Planning implemented Additional points The planning process allows adequate opportunity for +1 Since this is the first key stakeholders to influence the management plan management plan, no periodic review process has been There is an established schedule and process for +1 established yet. periodic review and updating of the management plan Planning The results of monitoring, research and evaluation are +1 routinely incorporated into planning 38 Issue Criteria Score Comments 8. Regular work plan No regular work plan exists 0 Is there an annual A regular work plan exists but activities are not 1 work plan? monitored against the plan's targets A regular work plan exists and actions are monitored 2 against the plan's targets, but many activities are not completed A regular work plan exists, actions are monitored 3 against the plan's targets and most or all prescribed Planning/Outputs activities are completed 9. Resource There is little or no information available on the 0 Baseline information is inventory critical habitats, species and cultural values of the available, but not fully protected area sufficient (e.g. no forest Do you have enough inventory in TUZ). Only information to Information on the critical habitats, species and 1 limited monitoring is done so manage the area? cultural values of the protected area is not sufficient to far (waterbirds, mire ecology). support planning and decision making Information on the critical habitats, species and 2 cultural values of the protected area is sufficient for key areas of planning/decision making but the Context necessary survey work is not being maintained Information concerning on the critical habitats, 3 species and cultural values of the protected area is sufficient to support planning and decision making and is being maintained 10. Research There is no survey or research work taking place in 0 the protected area Is there a program of There is some ad hoc survey and research work 1 management- orientated survey and There is considerable survey and research work but it 2 research work? is not directed towards the needs of protected area management There is a comprehensive, integrated programme of 3 Inputs survey and research work, which is relevant to management needs 11. Resource Requirements for active management of critical 0 Greifswald University research management ecosystems, species and cultural values have not been on plant and mire assessed ecology/hydrology. Is the protected area Requirements for active management of critical 1 adequately managed ecosystems, species and cultural values are known but (e.g. for fire, invasive are not being addressed species, poaching)? Requirements for active management of critical 2 ecosystems, species and cultural values are only being partially addressed Requirements for active management of critical 3 Process ecosystems, species and cultural values are being substantially or fully addressed 39 Issue Criteria Score Comments 12. Staff numbers There are no staff 0 Are there enough Staff numbers are inadequate for critical management 1 people employed to activities manage the protected Staff numbers are below optimum level for critical 2 area? management activities Staff numbers are adequate for the management needs 3 Inputs of the site 13. Personnel Problems with personnel management constrain the 0 New director delegates tasks management achievement of major management objectives and makes best use of existing expertise. Staff is far more Problems with personnel management partially 1 Is the staff managed motivated than in the past. constrain the achievement of major management well enough? objectives Personnel management is adequate to the 2 achievement of major management objectives but could be improved Process Personnel management is excellent and aids the 3 achievement major management objectives 14. Staff training Staff are untrained 0 Is there enough Staff training and skills are low relative to the needs 1 training for staff? of the protected area Staff training and skills are adequate, but could be 2 further improved to fully achieve the objectives of management Inputs/Process Staff training and skills are in tune with the 3 management needs of the protected area, and with anticipated future needs 15. Current budget There is no budget for the protected area 0 There will be far less budget from June 2006 onwards! Is the current budget The available budget is inadequate for basic 1 Possibly additional TA can be sufficient? management needs and presents a serious constraint provided, and there discussions to the capacity to manage on a future USAID project for supporting tourism The available budget is acceptable, but could be 2 development and further improved to fully achieve effective environmental education in the management national parks of Georgia. Inputs The available budget is sufficient and meets the full 3 management needs of the protected area 16. Security of There is no secure budget for the protected area and 0 There is some uncertainty budget management is wholly reliant on outside or year by associated with the year funding establishment of KNP as a Is the budget secure? There is very little secure budget and the protected 1 legal body of public law. area could not function adequately without outside funding There is a reasonably secure core budget for the 2 protected area but many innovations and initiatives are reliant on outside funding Inputs There is a secure budget for the protected area and its 3 management needs on a multi-year cycle 40 Issue Criteria Score Comments 17. Management of Budget management is poor and significantly 0 budget undermines effectiveness Is the budget Budget management is poor and constrains 1 managed to meet effectiveness critical management Budget management is adequate but could be 2 needs? improved Process Budget management is excellent and aids 3 effectiveness 18. Equipment There is little or no equipment and facilities 0 Safety equipment for marine boat is being procured. Is equipment There is some equipment and facilities but these are 1 Equipment is used according to adequately wholly inadequate needs. Buildings have been maintained? designed and will be constructed in the next months. There is equipment and facilities, but still some major 2 In situ infrastructure will be gaps that constrain management Process developed for priority sites. There is adequate equipment and facilities 3 19. Maintenance of There is little or no maintenance of equipment and 0 Boat propeller has been equipment facilities repaired. Cars and boats are well maintained. Is equipment There is some ad hoc maintenance of equipment and 1 adequately facilities maintained? There is maintenance of equipment and facilities, but 2 there are some important gaps in maintenance Process Equipment and facilities are well maintained 3 20. Education and There is no education and awareness program 0 Multiple relevant activities awareness program have been implemented. Is there a planned There is a limited and ad hoc education and 1 education program? awareness program, but no overall planning for this There is a planned education and awareness program 2 but there are still serious gaps There is a planned and effective education and 3 Process awareness program fully linked to the objectives and needs of the protected area 21. State and There is no contact between managers and 0 commercial neighboring official or corporate land users neighbours Is there co-operation There is limited contact between managers and 1 with adjacent land neighboring official or corporate land users users? There is regular contact between managers and 2 neighboring official or corporate land users, but only limited co-operation There is regular contact between managers and 3 neighboring official or corporate land users, and Process substantial co-operation on management 41 Issue Criteria Score Comments 22. Indigenous Indigenous and traditional peoples have no input into 0 Irrelevant people decisions relating to the management of the protected area Do indigenous and traditional peoples Indigenous and traditional peoples have some input 1 resident or regularly into discussions relating to management but no direct using the PA have involvement in the resulting decisions input to management decisions? Indigenous and traditional peoples directly contribute 2 to some decisions relating to management Indigenous and traditional peoples directly participate 3 Process in making decisions relating to management 23. Local Local communities have no input into decisions 0 Local communities were communities relating to the management of the protected area consulted for allocating forest stands from the traditional use Do local Local communities have some input into discussions 1 zone and for establishing communities resident relating to management but no direct involvement in fishery regime. or near the protected the resulting decisions area have input to management decisions? Local communities directly contribute to some 2 decisions relating to management Local communities directly participate in making 3 Process decisions relating to management Additional points There is open communication and trust between local +1 Trust only with some stakeholders and protected area managers communities, not with Guria. Programs to enhance local community welfare, while +1 conserving protected area resources, are being Outputs implemented 24. Visitor facilities There are no visitor facilities and services 0 Are visitor facilities Visitor facilities and services are inappropriate for 1 (for tourists, pilgrims current levels of visitation or are under construction etc) good enough? Visitor facilities and services are adequate for current 2 levels of visitation but could be improved Visitor facilities and services are excellent for current 3 Outputs levels of visitation 25. Commercial There is little or no contact between managers and 0 Initial contacts were made tourism tourism operators using the protected area during tourism fair. There is contact between managers and tourism 1 Do commercial tour operators but this is largely confined to administrative operators contribute or regulatory matters to protected area management? There is limited co-operation between managers and 2 tourism operators to enhance visitor experiences and maintain protected area values There is excellent co-operation between managers and 3 tourism operators to enhance visitor experiences, Process protect values and resolve conflicts 26. Fees Although fees are theoretically applied, they are not 0 Only fees for woodcutting in If fees (tourism, collected the traditional use zone are 42 Issue Criteria Score Comments fines) are applied, do The fee is collected, but it goes straight to central 1 collected and transferred to they help protected government and is not returned to the protected area Sakrebulo account. area management? or its environs The fee is collected, but is disbursed to the local 2 authority rather than the protected area There is a fee for visiting the protected area that helps 3 Outputs to support this and/or other protected areas 27. Condition Important biodiversity, ecological and cultural values Bronze-age settlement has been assessment are being severely degraded 0 destroyed (though partially Some biodiversity, ecological and cultural values are excavated) by Kulevi; illegal Is the protected area being severely degraded 1 fishing, poaching, woodcutting, being managed grazing. consistent to its Some biodiversity, ecological and cultural values are objectives? being partially degraded but the most important 2 values have not been significantly impacted Biodiversity, ecological and cultural values are Outcomes predominantly intact 3 Additional points There are active programs for restoration of degraded areas within the protected area and/or the protected +1 Outputs area buffer zone 28. Access Protection systems (patrols, permits etc) are 0 Control of woodcutting has assessment ineffective in controlling access or use of the reserve improved. Some success with in accordance with designated objectives illegal fishing, but see above. Are the available management Protection systems are only partially effective in 1 mechanisms working controlling access or use of the reserve in accordance to control access or with designated objectives use? Protection systems are moderately effective in 2 controlling access or use of the reserve in accordance with designated objectives Outcomes Protection systems are largely or wholly effective in 3 controlling access or use of the reserve in accordance with designated objectives 29. Economic benefit The existence of the protected area has reduced the 0 Due to high unemployment and assessment options for economic development of the local persisting socio-economic communities constraints many people have Is the protected area extracted resources from KNP providing economic The existence of the protected area has neither 1 (wood, fish, game, pasture). benefits to local damaged nor benefited the local economy JSDF grant has created some communities? There is some flow of economic benefits to local 2 economic development. communities from the existence of the protected area but this is of minor significance to the regional economy Outcomes There is a significant or major flow of economic 3 benefits to local communities from activities in and around the protected area (e.g. employment of locals, locally operated commercial tours etc) 43 Issue Criteria Score Comments 30. Monitoring and There is no monitoring and evaluation in the protected 0 evaluation area There is some ad hoc monitoring and evaluation, but 1 no overall strategy and/or no regular collection of results Planning/Process There is an agreed and implemented monitoring and 2 evaluation system but results are not systematically used for management A good monitoring and evaluation system exists, is 3 well implemented and used in adaptive management TOTAL SCORE 60 out of 93 = 64.5% 44 Annex 6: Stakeholder Workshop Report and Results A stakeholder workshop was not carried out as part of the ICR. However, the team carried out a beneficiary assessment (see annex 5) and met with key stakeholders to discuss the results of the project (see annex 8). 45 Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR Sustainable Development Projects Implementation Agency, acting as a PIU for the GICM Project, submitted Borrower's ICR on behalf of the MoEPNR to the Bank. Below is the summary of this document: Introduction Georgia's coastline stretches approximately 310 km along the Black Sea. The coastal zone is dominated by wetland ecosystems. Steep cliffs and mountains appear at its north and south edges. Up-stream human activities have put increasing pressure on coastal zone ecosystems along the Black Sea, while further downstream, over-fishing and off- shore dumping have devastated marine resources. In general, fragmented and weak management of natural resources at the regional, national, and international levels has resulted in uncontrolled pollution, unsustainable exploitation and loss of productive habitats in the coastal zone. In 1996 a regional Strategic Action Plan for the Rehabilitation and Protection of the Black Sea was signed by all six littoral states and the process of implementing this regional strategy begun. Its major targets for advancing the ICZM process within each country include: (i) preparation of national ICZM strategies and guidelines, (ii) establishment of inter-sectoral ICZM committees, and (iii) adoption of legal and other instruments for facilitating ICZM. The GICM project was designed to help Georgia with implementation of the regional Black Sea Strategic Action Plan through building a strong institutional base for ICZM, and creating enabling environment for the introduction of improved management techniques and investments in the coastal zone. Project Achievements Building Legal and Institutional Framework for ICZM The State Consultative Commission for ICZM was established through the Presidential Decree No. 608 on October 25, 1998 to develop institutional framework for integrated planning and management of coastal resources in Georgia. This inter-agency representative body, co-chaired by the Minister of Environment and the Minister of Urbanization and Construction, served as the forum for interpreting and coordinating existing policies among the various sectors/stakeholders involved in coastal and marine resource use along Georgia's Black Sea Coast. From April 2002 an international consulting firm had been providing assistance to Georgia through the GICM project in building ICZM capacity, which resulted in the development of a draft ICZM law and an explanatory note to it. The key features of this draft legislation included inter-sectoral cooperation and consultation, as well as public consultation and stakeholder involvement. It provided a coordination mechanism for participatory panning and management of coastal resources at national and local levels. Though, the ICZM legislation had not been passed as it was found not in tune with the government's strong fortitude towards improving investment climate through curtailing 46 time required for clearing business initiatives. No ICZM councils had been founded either. The draft ICZM law was re-worked into Guidelines for ICZM. This document was formally endorsed and issued by the MoEPNR in 2006. Guidelines were circulated to local governing bodies in the coastal zone as well as to relevant units in the central government, government of the Autonomous Republic of Achara, NGOs, and other stakeholders. Guidelines are also posted on the web page of the Aarhus Center Georgia. ICZM Guidelines recommend creation of temporary consultative commissions upon need during elaboration of development plans for local or regional administrative units of the coastal zone. A knowledge and information basis for ICZM was created within the MoEPNR in January 2007. The ICZM division of the Monitoring and Forecasting Center under the MoEPNR is mandated to contribute to planning and decision making on the coastal matters through provision of data and advice. Establishment of Kolkheti Protected Areas (KNP & KNR) The KNP was established around an area within the larger Kolkheti wetlands lowland that had been designated as a Ramsar site in 1996. The KNR is located inland from the Black Sea coast near the city of Kobuleti and also represents a Ramsar site. Both proposed protected areas support rare and relic plant communities such as peat bogs and forests from the Tertiary period. These protected areas provide critical habitat for numerous species of migratory and wintering birds. Land Transfer and Demarcation. The work that preceded legal enactment of the KNP apparently lacked public consultation. It resulted in a lengthily and heavy process of land transfer. Eventually, the protected areas are now registered with their administrative bodies under the Department of Protected Areas and their physical demarcation is also completed. Adoption of Management Plans. After rounds of reviews by the Bank consultants and the key government agencies, the management plans for the KNP and the KNR were approved in February 2006 and June 2006 respectively. These documents carry important factual information, provide good guidance for protected area administrations, and are of a high quality by international standards. Building Capacity of Protected Area Administrations. The KNP administration, established in the capacity of a legal body of Public Law, is granted the right to generate, retain, and re-invest its own revenues in the not-for-profit areas of activity that are specified in its charter. The GICM project provided good training opportunities for the staff of the KNP and the KNR. Due to significant turnover, some of the trained staff is no longer employed in these protected areas. Development of Protected Area Infrastructure. Under the GICM project the administration buildings were constructed/refurbished for the protected areas of Kolkheti. A visitor center for the KNP has been constructed following the principles of green architecture and this building is the first example of such environment- friendly construction in Georgia. Some limited infrastructure for nature-based 47 tourism such as boardwalks, shelters, a bird ringing station, hiking trails, observation towers for bird watching, etc. were provided to the KNP and the KNR. Top quality bi-lingual interpretation materials on the history, culture, and ecology of the Kolkheti lowland were developed in cooperation with the US Park Service and installed in these protected areas. Raising Public Awareness of Kolkheti Protected Areas. The project assisted administrations of the KNP and the KNR with a startup of environmental education and awareness activities. During the project life the beneficiary protected areas organized children excursions, environmental lectures in local elementary and high schools, published articles on the regional and international importance of Kolkheti wetlands, facilitated community discussions on the local hot issues pertaining conflicts between nature conservation and commercial interests. A number of radio programs and video materials on wetlands and their protection have also been aired. The project sponsored participation of the KNP in several tourism fairs. Establishment of Coastal Environmental Quality Monitoring and Information Systems An urgent need to monitor the quality of near-shore and off-shore waters, rivers and estuaries, as well as ports and sources of pollution was identified in a regional study commissioned by EU TACIS in 1994. Untreated sewage, municipal waste, pollution from dilapidated oil facilities, vessel waste, industrial pollution, and agricultural runoff represented a well known but insufficiently measured threat to both public health and coastal ecosystems, with negative impacts to tourism development. A feasibility study and design for the coastal environment quality monitoring and information system were developed by an international consulting firm under the GICM project and groundwork was laid for its implementation. This implied refurbishment of three beneficiary coastal monitoring laboratories; delivery of sampling, measurement, and analytic equipment to them; improvement of monitoring standards and data protocols; provision of training and technical assistance; and establishment of a basic structure for an effective information system. More specifically, the key elements of the developed monitoring and information system are: (i) the design and implementation arrangements for the monitoring and computer-based information systems; (ii) re- establishment of an off-shore water quality monitoring program with selected biodiversity monitoring; (iii) strengthening of pollution monitoring in the coastal zone, including rivers and estuaries; and (iv) creating foundation for a computer based ICZM information system. Institutional set-up of the entities responsible for coastal environment quality monitoring and data management had been changing during the GICM Project life. Due to uncertainty and a persisting process of restructuring of institutional affiliation and set-up, the current structure of coastal information system is yet to enter into operation. Batumi laboratory of the Institute of Marine Ecology and Fisheries has not fully settled in its new capacity under the Monitoring and Forecasting Center, and a recently established ICZM section of this Center is yet in the process of formation. On the other hand, the outcome of the above institutional reforms is fully justifiable and permissive for effective 48 operation of the ICZM function. The main chemical and biological facility for marine ecosystem research and monitoring ­ which is the laboratory in Batumi, as well as the main geological and engineering facility for researching and managing coastal dynamics are now both consolidated within the Monitoring and Forecasting Center under MoEPNR. All hardware, software, databases and intellectual property, accumulated under the GICM Project, also belong there. Therefore, there is a permissive environment for successful operation of the coastal quality monitoring and information system, conditional to the strong ownership and management provided from MoEPNR. Coastal Erosion and Municipal Water Management Study A comprehensive study of coastal erosion in Poti and Batumi regions, morphology of main rivers draining into the Black Sea (including patterns of sediment transport), as well as an overview of water supply systems in the main coastal municipalities, their drainage and sewer systems, waste water disposal and solid waste management delivered important information which had been used for pre-feasibility studies of possible interventions and identification of investment priorities. The project helped to develop a coastline dynamics model and to transfer of the Dutch experience in this filed to the specialists of the Georgia's Coastal Dynamics Institute. A workshop on coastal modelling was delivered in 2000 to train local staff in the use of the coastline and river modelling software (products of the Delft Hydraulics). Hands-on experience was gained through a joint assessment of erosion processes for Batumi and Poti by the Dutch and Georgian specialists. The updated beach profile measurements and historical data to run the model were obtained and its validation was also carried out. Capacity building of the Coastal Dynamics Institute (currently under the MoEPNR) included provision of PCs, portable radio transmitters, river and coastal modelling software, an echo-sounder, and a tachometer. Preparation of a National Oil Spill Contingency Plan Preparation of a contingency plan for accidental offshore oil spills, as well as assessment of port waste reception facilities and development of an investment plan for the control of marine pollution were carried out by an international consulting company in cooperation with the Maritime Administration and the Convention Inspection for the Protection of the Black Sea. The work resulted in a report which contains two volumes of background information, and a draft National Oil Spill Contingency Plan for Georgia. It was reviewed by relevant line agencies and stakeholders in Georgia and was also commented by the International Maritime Organization. The Oil Spill Contingency Plan has not been adopted by the government so far. Its new iteration is being circulated to the government's line agencies again. The Convention Inspection received a set of portable and stationary monitoring equipment for confirmation measurements of chemicals, oil identification spectroscopy, etc. 49 In 2001 an oil spill response exercise was conducted in the Batumi harbour for the first time in more than a decade. The Georgian public agencies as well as international oil transporting companies involved in Georgia participated in this exercise. It demonstrated ability of the Georgian authorities to manage complex activities of multiple actors on the scene of emergency. The exercise had been a unique opportunity for sharpening response action skills and for checking out reliability of the available equipment. Recommendations were produced for the creation of a funding instrument enabling coverage of maintenance costs of the oil spill preparedness and response. Training and Capacity Building Project has contributed to the capacity building of the Ministry of Environment and State Department of Protected Ares and other agencies through training and sponsoring attendance at various international meetings related to the protection of marine environment and protected areas management. A few most important training events attended with the GICM project support by the Georgian public servants and members of NGOs include: the ICZM Law meeting for the Black Sea country representatives, Bucharest, Romania, 2000, 1st Black Sea Conference on Ballast Waters Management and Control, Odessa, Ukraine, 2001, international seminar on watershed management, Izmir, Turkey, 2001, international course on wetlands restoration, Lelystad, the Netherlands, 2002, 1st Meeting of the Contracting Parties to ACCOBAMS (Agreement on the Conservation of Cetaceans of the Black Sea, Mediterranean Sea and Contiguous Atlantic Area), Monaco, 2002, 5th International Symposium on GIS and Computer Cartography for Coastal Zone Management, Genoa, Italy, 2003, 4th East-West Fisheries Conference, Tallinn, Estonia, 2003, study tour on park infrastructure, USA, 2004 international conference on the Management Challenges for Wetlands, Mires, and Peatlands in the 21th Century, Argentina, 2004, 10th International Living Lakes Conference on Responsible Stewardship by Lake Communities, Tagaytay City, Philippines, 2005 workshop on Laboratory measurement of salinity, Hampshire, UK, 2005 Achievement of Project Objectives and Rating of Key Performance Indicators Project development objective: The project aimed to strengthen institutions in Georgia to manage the coastal resources of the Black Sea by developing, testing and evaluating methods to effectively integrate environmental planning and management into economic development activities along the Black Sea coast. The development objective is partially achieved by the project. Global development objective: The project also aimed to assist Georgia in meeting its international commitments under the Black Sea Environmental Program (BSEP) and to 50 implement priority actions outlined in the Georgia Biodiversity Strategy/Action Plan. These priorities included conservation of biodiversity at sites of international significance on Georgia's Black Sea coast, such as the Kolkheti and Kobuleti wetland Ramsar sites; restoration of degraded habitats and resources within the Black Sea Large Marine Ecosystem; and participation in regional efforts to manage and sustain public goods of a transnational character. The global development objective is achieved by the project. (a) Intersectoral consultative commissions for ICZM established and functioning according to agreed objectives and procedures at national and local levels Unsatisfactory. The State Consultative Commission for ICZM that has been established for interpreting and coordinating existing policies among the various sectors/stakeholders involved in coastal and marine resource use along Georgia's Black Sea Coast is not functioning any more. (b) Georgians trained in coastal resource planning and management tools (EA, land use planning/zoning; protected area management; GIS) and public awareness and conflict resolution techniques Moderately Satisfactory. Training efforts in land use planning and zoning failed, but there were several successful trainings delivered in protected areas management. These were study tours to the neighbouring Turkey, Ukraine, Romania, and the USA. Five individuals were trained on wetland management and restoration in the Netherlands. The GIS capacity of the ICZM Center had been highly recognized by users, but this Center has been dissolved upon project completion. The GIS database of ICZM information is now owned by the Monitoring and Forecasting Center under the MoEPNR, which comprises the newly established ICZM unit. (c) Draft legislation outlining mandate and responsibilities of a coastal authority and codes of conduct for coastal resource/landscape use prepared Moderately Unsatisfactory. ICZM draft law has been developed, but not adopted by the government of Georgia. A law on Spatial Planning and Urban Development, adopted in 2005, provides a permissive legal environment for ICZM, though it does not carry legally binding requirements for participatory planning of coastal resource use. (d) Legal status of KNP and KNR established and boundaries demarcated Highly Satisfactory. Legislation is in place. It has been amended with acknowledgement of subsistence needs of local communities. Boundaries of the KNP and the KNR are digitally and physically demarcated. (e) Encroachment, illegal poaching and harvesting rates reduced over baseline conditions N/A. This indicator could have not been used in a meaningful manner due to difficulty of determining baseline conditions, as many uncertainties were involved. 51 (f) Information node for Black Sea regional environmental monitoring network established in Georgia Moderately Satisfactory. The sampling, measurement, and analytic equipment for the selected monitoring laboratories were procured; monitoring standards and data protocols improved; training and technical assistance provided; and a basic structure for an effective information system put in place. There are sufficient prerequisites for the monitoring and information network to operate successfully, but it is not fully functioning to date. (g) Computer links and information sub-nodes in collaborating institutions up and running Satisfactory. Many partner institutions developed simple internet nodes in line with the overall technical development in the country. The Internet dial-up connection is available now many coastal zone cities ­ Batumi, Poti, Zugdidi, Ozurgeti, etc. The project provided Internet connectivity to the KNP through equipping it with strong computers, internet node with institutional email address, and a homepage. Relevant hardware and software has also been delivered to a number of institutions in the coastal zone as well as in Tbilisi which handle the coastal information. (h) Oil spill contingency plan and financing plan developed and approved by government Moderately Satisfactory. A high quality draft contingency plan developed, combined with a field testing through a high-seas equipment deployment exercise. The government's continued interest in the development of the national capacity for oil spill response is evident from the approval of the non-pipeline component of the Energy Transit Institutional Building project. An approval of the draft plan is still pending. Lessons Learned The critical lesson from the GICM project is that it had been overly ambitious to expect that Georgia would have a fully-fledged functioning ICZM system by project completion. It should be recognized that the ICZM is a long term process and outcomes of the component A of the project would be a platform for further development over the years to come. The international experience from the Mediterranean, Baltic, and Black Sea Programmes also indicates that the process of implementing change requires long time and much effort. Many institutions in Georgia are yet in a young stage and considerable work is needed at all levels of the government to create the structure for and the culture of cross-sectoral functions. Somewhat similar conclusions could be driven from the attempts to lay a foundation for coastal environment quality monitoring system. The general institutional constraints are affecting its functionality as well and it would be a major challenge to achieve flawless operation of mechanisms for receiving and communicating data and information across ministerial and regional boundaries. 52 The project faced difficulties under the protected areas component in localities with high occurrence and much depth of poverty. Social environment and the magnitude of problems associated with communities' dependence on the natural resource extraction should be fully recognized under conservation projects. The other critical issue to find effective means for communicating project objectives and offered solutions to a variety of stakeholders that may significantly vary in terms of their social and material status, vested interests, and aspirations. 53 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders Comments on the project outcomes, their importance, and lessons learned were obtained from several key stakeholders through meetings and discussions held several months past completion. Department of Environment Protection and Natural Resources of the Autonomous Republic of Achara. On March 28, 2007 the ICR mission met with Mr. I. Goradze, Head of the Department of Environment Protection and Natural Resources of Achara, to discuss how the Autonomous Republic, covering about one third of Georgia's coastline, has benefited from the implementation of the GICM project. The Head of Achara's environment agency told the mission that he sees particular importance of the GICM project is catalyzing numerous initiatives for sustainable management of the coastal zone. A package of assistance delivered to the KNR is highly valuable for conserving a particular unique wetland ecosystem. Furthermore, the positive experience with the KNR stimulated the new similar initiatives in the Autonomous Republic. With the assistance of the WWF the first national park had been planned and legally established in Achara in 2005. Protected area planning gained indeed a strong momentum and work has commenced towards establishment of two more, one of which is conceived as a trans- boundary protected area to be co-managed by Georgia and Turkey. Assistance delivered under the GICM project for strengthening water quality monitoring in the coastal zone and identification of challenges associated with an ambition to introduce the Blue Flag Program to Georgia's Black Sea beaches has sensitized the environmental agency of Achara to water pollution problems. It led to an initiative to introduce of program for point source pollution control. The government of Achara financed inventory of water pollution hotspots and is supporting regular monitoring of discharge at the selected high risk sites. The GICM project helped to test a model for improved management of public beaches through a pilot activity in Kobuleti, Achara. It implied delivery of beach equipment to the local government for leasing it to a concessionaire under the condition of quality maintenance of the concession area, including adherence to high standards of sanitation and waste management. Due to institutional and staff changes in the beneficiary local government unit, this pilot activity had not been sustained beyond one season, through it actually produced the intended outcome. The Prime Minister of Georgia and the Minister of Environment of Georgia, both attending the season opening event at the pilot beach, found the proposed model of its management highly relevant and called for applying it throughout the coastline. Currently concessions are being issued for segments of public beaches along great part of Achara's coastline, which allowed to improve service delivery and to increase public health and environment standards of beach maintenance. IUCN Programme for Southern Caucasus. On March 22, 2007 the ICR mission met Mr. R. Gokhelashvili, Director of the IUCN Programme Office for the Southern Caucasus, to hear his opinion on the GICM project outcomes. Mr. Gokhelashvili noted the importance of the assistance delivered through the project with conservation of wetland ecosystems, 54 including those representing habitat for migratory birds. The project provided some infrastructure and equipment for birdwatching in the beneficiary projected areas and sponsored a publication on avifauna of Kolkheti, which is an excellent educational material and a guide for birdwatches. Speaking of the challenges of managing protected areas, Mr. Gokhelashvili mentioned that the consultative board established for the KNP, alike similar bodies set for other protected areas in Georgia, did not succeed in becoming a functional and a meaningful tool for the park management. The generic reason for that could be the composition of the consultative boards, which mostly comprises pretty high level officials, many of them based in the capital city of Tbilisi. Furthermore, the entire institutional concept and status of consultative boards may need rethinking. There should be much more emphasis on local participation, all way through creation of a forum for community co-management of protected areas. WWF Caucasus Programme. On June 27, 2007 the ICR Team discussed impact of the GICM project with Mr. Nugzar Zazanashvili, Conservation Director, WWF Caucasus Programme. He noted, that the support provided through the project to the KNP is highly valuable, as this Park is a key instrument for preserving ecological balance in the Priority Conservation Area #26 of the Caucasus Ecoregion, as identified by experts from six countries of the region (Ecoregional Conservation Plan for the Caucasus. WWF, KfW, BMZ, CEPF, MacArthur Foundation, May 2006). Also, the KNP protects the last remaining sections of unique lowland swamp forests and wetlands in the Caucasus. It plays a crucial role in conservation of globally threatened species of sturgeon, including critically endangered Atlantic (Baltic) sturgeon (Acipenser sturio), which spawns only in the rivers in the Kolkheti Lowlands. Establishment of the Kolkheti protected areas is instrumental for preservation of the most significant bird habitats of the Black Sea coastal zone. The KNP is the only protected area in the Black Sea basin with a formally designated marine park. This directly contributes to one of the main goals and the respective suggested action of the Convention on Biological Diversity (CBD) Programme of Work on Protected Areas: "1.1.3. As a matter of urgency, by 2006 terrestrially and by 2008 in the marine environment, take action to address the under-representation of marine and inland water ecosystems in existing national and regional systems of protected areas..." Though management of the marine part of the KNP calls for further refining and strengthening. Mr. Zazanashvili mentioned, that while the GICM project successfully met the main conservation objectives, it had some shortfalls as well, including a weakness in guiding the protected area proponents around the conflict of interests with local population. Despite later measures aimed at problem shooting, long term solutions are still to be worked out. Implementation of alternative livelihood programs for local communities could be among further measures for sustaining co-existence of the protected areas of Kolkheti and their gateway communities. 55 Mr. Zazanashvili shared with the ICR mission his concerns about potential threats to the KNP that come from its neighboring Kulevi oil terminal. He expressed a hope that proper monitoring and mitigation plans are applied to address sensitivity of the western sections of the KNP to an ongoing construction of railway access to the terminal. Achara-based NGO Chaobi. On June 27, 2007 the ICR team received feedback on the GICM project outcomes from Ms. I. Machutadze, Head of an NGO Chaobi (mire), which advocates for conservation of Kolkheti wetlands. The main point made by Ms. Machitadze is that the project had an outstanding impact in terms of raising awareness of wetlands among diverse parts of society, ranging from the local communities all way up to the government. During the Soviet epoch wetlands had no other interpretation than being wasted areas that also carried venomous wildlife and disease vectors. Therefore, the State policy called for draining as much wetlands as physically possible for converting them to agricultural plots. Huge public funding had been spent on this drainage campaign. With such historical background, it is difficult to overestimate difficulties associated with educating society on the functions and value of wetlands and altering perceptions strongly entrenched in public mentality. Establishing protected areas with a mandate to conserve wetlands has been a strong signal and became pivotal in altering attitude towards peat bogs of Kolkheti. Furthermore, during the project life and with its support the KNR became an object for international research and unique nature of its ecosystem has been scientifically proven. Ms. Machutadze also mentioned difficulties of reconciling conservation objectives with the social needs of local poor rural communities. Allocating areas for nature protection usually carries potential conflicts of economic/social character, which should not be underestimated or ignored from the very early stages of planning. In case of the KNP, a good part of the social tension, associated with limiting of the natural resource use, could have been avoided through including the traditional use zone in the KNP at the time of its establishment. 56 Annex 9. List of Supporting Documents 1. Project Information Document, PID5864, July 1998 2. Project Appraisal Document, Report No. 17131-GE, November 1998 3. Development Credit Agreement, Credit No. 3156 GE, January 1999 4. GEF TF Grant Agreement, GEF TF No. 021598, January 1999 5. Environmental Assessment, E469, January 2001 5. ISRs filed, along with the attached Aide Memoires, in the World Bank Project Portal 57 GEORGIA 40°E 42°E 44°E 44°N 44°N SELECTED CITIES AND TOWNS AUTONOMOUS OBLAST (AO) CENTER R U S S I A N F E D E R A T I O N AUTONOMOUS REPUBLIC (ASSR) CENTERS To NATIONAL CAPITAL Soai GEORGIA RIVERS C a MAIN ROADS Gagra u RAILROADS c AUTONOMOUS OBLAST (AO) BOUNDARY a A B K H A Z I A s AUTONOMOUS REPUBLIC (ASSR) BOUNDARIES Mestia u To INTERNATIONAL BOUNDARIES Suhumi Vladikavkaz s This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other information Ochamchira K o l k h i d a Tkvarceli M Dzvari o Mqinvartsveri shown on this map do not imply, on the part of The World Bank (5047 m) Group, any judgment on the legal status of any territory, or any Low u Kazbegi endorsement or acceptance of such boundaries. Inguri Oni n land Zugdidi Ambrolauri t South a Sachkhere Ossetia SenakiTskenisckali Rioni Tkibuli i Kvirilk Black Sea Kutaisi n Ts'khinvali Chinvali Poti Iori Rioni Samtredia s 42°N Akhmeta 42°N Gori Khashuri Telavi Ozurgeti Mtkvari(Kura) Mtskheta Kobuleti Alazani Lagodehi AADJJAARRAA T'BLISI Gurjaani Batumi Akhaltsikhe Iori To Rustavi Zagatala Marneuli Ahalkalaki Tsiteli- Kazreti Tskaro Ninocminda Mtkvari Iori To Trabzon (Kura) T U R K E Y To Yevlax Mingechevir 0 20 40 60 Kilometers Reservoir NOVEMBER To A Z E R B A I J A N IBRD 0 10 20 30 40 50 Miles Erzurum To A R M E N I A Erzurum To 33410 Armavir Lake 2004 Sevan 40°E 42°E 44°E 46°E