E2068 v17 ---- ----.-~ --= - -.::::::::-~- -----1111'00 YEARS® AN ENVIRONMENTAL MANAGEMENT PLAN BY: PARSONS BRINCKERHOFF AFRICA (PTY) LTD. Environmental and Social Division SUBMITTED TO: Botswana Power Corporation FOR: BPC 400 kV Transmission Line from the Morupule B Power Station to the Phokoje Substation, Botswana PB Reference: ZA2155302 Date: 23 April 2009 Status: Final for Client PARSONS BRINCKERHOFF AFRICA (PTY) LTD JOHANNESBURG, SOUTH AFRICA 12 BURNSIDE ISLAND, 410 JAN SMUTS AVE PO BOX 41927, CRAIGHALL, 2024 TEL: +27-11-787-4141 FAX: +27-11-886-0359 EMAIL: pbafrica@pbworld.com ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation APPROVED BY: DATE: SIGNATURE: A. Williamson 30104/2009 ~~~~ © Parsons Brinckerhoff Africa (Pty) Ltd. Copyright in the drawings, information and data recorded in this document ("the information") is the property of PB. This document and the information are solely for the use of the authorised recipient and this document may not be used, copied or reproduced in whole or part for any purpose other than that for which it was supplied by PB. PB QUALITY SYSTEM: PB REFERENCE ZA2155302 YOUR REFERENCE ZA2155302 REPORT STATUS Draft for Internal Review PREPARED BY AS Bodasing, R Kruger REVIEWED BY R Thomas APPROVED BY A Williamson DATE CREATED 23 April 2009 DATE ISSUED 30 April 2009 Quality Management System Certified to ISO 9001 :1994 Parsons Brinckerhoff Africa (Pty) Ltd ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation TABLE OF CONTENTS 1. INTRODUCTION .....................................................................................................................1 2. Terms of reference.................................................................................................................1 3. AIM OF THIS DOCUMENT .....................................................................................................2 4. GLOSSARY OF TERMS AND ABBREVIATIONS .................................................................3 5. PROJECT DESCRIPTION ......................................................................................................8 5.1. Proposed Project ..........................................................................................................8 5.1.1. Construction Details.........................................................................................8 5.1.2. Dismantling ......................................................................................................9 5.1.3. Tower Construction..........................................................................................9 5.1.4. Stringing of Conductors ...................................................................................9 5.1.5. Earthworks.....................................................................................................10 5.1.6. Equipment and Materials Storage .................................................................10 5.2. Site Description...........................................................................................................10 5.2.2 Topography....................................................................................................11 5.2.3 Water Resources ...........................................................................................12 5.2.4 Geology and Soils..........................................................................................12 5.2.5 Flora...............................................................................................................13 5.2.6 Fauna.............................................................................................................15 5.2.7 Avifauna.........................................................................................................16 5.2.8 Archaeology and Historical Sites...................................................................17 6. ENVIRONMENTAL MANAGEMENT PLAN .........................................................................18 6.1. General Focus ............................................................................................................18 6.2. Purpose.......................................................................................................................18 7. ENVIRONMENTAL AWARENESS AND COMPLIANCE.....................................................19 7.1. Introduction .................................................................................................................19 7.2. Responsibilities for Environmental Management........................................................19 7.3. Training and Induction of Employees .........................................................................20 7.4. Complaints Register and Environmental Incidents Book............................................20 7.5. Environmental Monitoring ...........................................................................................21 7.6. Dealing with Non-Compliance with the EMP (Penalties/Incentives for Staff).............21 7.7. Roles and Responsibilities of Key Personnel during Construction Phase .................21 7.8. EMP Amendments / EMP Instructions........................................................................22 8. MITIGATION MEASURES ....................................................................................................23 8.1. Construction Initiation / Site Establishment ................................................................23 8.1.1 Potential Significant Impacts..........................................................................23 8.1.2 Sources of Potential Impacts.........................................................................23 Parsons Brinckerhoff Africa (Pty) Ltd i ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.1.3 Objectives ......................................................................................................23 8.1.4 Performance Indicators..................................................................................23 8.1.5 Monitoring Programme ..................................................................................23 8.1.6 Mitigation Measures.......................................................................................23 8.2. Site Clearing / Earthworks / Establishment & Maintenance of Roads and Tracks.....30 8.2.1 Potential Significant Impacts..........................................................................30 8.2.2 Sources of Potential Impacts.........................................................................30 8.2.3 Objectives ......................................................................................................31 8.2.4 Performance indicators..................................................................................31 8.2.5 Monitoring Programme ..................................................................................31 8.2.6 Mitigation Measures.......................................................................................31 8.3. Pollution Control..........................................................................................................34 8.3.1 Potential Significant Impacts..........................................................................34 8.3.2 Sources of Potential Impacts.........................................................................34 8.3.3 Objectives ......................................................................................................34 8.3.4 Performance indicators..................................................................................35 8.3.5 Monitoring Programme ..................................................................................35 8.3.6 Mitigation Measures.......................................................................................35 8.4. Waste Management....................................................................................................39 8.4.1 Potential Significant Impacts..........................................................................39 8.4.2 Sources of Potential Impacts.........................................................................39 8.4.3 Objectives ......................................................................................................39 8.4.4 Performance indicators..................................................................................40 8.4.5 Monitoring Programme ..................................................................................40 8.4.6 Mitigation Measures.......................................................................................40 8.5. Protecting the Biophysical Environment .....................................................................41 8.5.1 Potential Significant Impacts & Impact Sources:...............................................41 8.5.2 Objectives ..........................................................................................................41 8.5.3 Performance Indicators..................................................................................42 8.5.4 Monitoring Programme ..................................................................................42 8.5.5 Mitigation Measures.......................................................................................42 8.6. Protecting Heritage Sites and Artefacts......................................................................48 8.6.1 Potential Significant Impacts..........................................................................48 8.6.2 Sources of Potential Impacts.........................................................................48 8.6.3 Objectives ......................................................................................................48 8.6.4 Performance Indicators..................................................................................48 8.6.5 Mitigation Measures.......................................................................................48 8.7. Infrastructure / Development.......................................................................................49 Parsons Brinckerhoff Africa (Pty) Ltd ii ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.7.1 Potential Significant Impacts and Impact Sources ........................................49 8.7.2 Objectives ......................................................................................................49 8.7.3 Performance Indicators..................................................................................49 8.7.4 Monitoring Programme ..................................................................................50 8.7.5 Mitigation Measures.......................................................................................50 8.8. Socio ­ Economic Environment..................................................................................50 8.6.1 Potential Significant Impacts and Sources of Impacts...................................50 8.6.2 Objectives ......................................................................................................50 8.6.4 Performance Indicators..................................................................................50 8.6.5 Mitigation Measures.......................................................................................51 8.9. Rehabilitation ..............................................................................................................52 8.10.1 Potential Impacts and Impact Sources ..........................................................52 8.10.2 Objectives ......................................................................................................52 8.10.3 Principle .........................................................................................................52 8.10.4 Performance Indicators..................................................................................52 8.10.5 Monitoring Programme ..................................................................................53 8.10.6 Mitigation Measures.......................................................................................53 8.10. Post Construction Activities ........................................................................................55 9. CONCLUSION.......................................................................................................................58 LIST OF APPENDICES APPENDIX A - Maps APPENDIX B - Botswana National Museum Conditional Permit Parsons Brinckerhoff Africa (Pty) Ltd iii ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 1. INTRODUCTION The BPC propose to construct a new 400 kV Overhead Transmission Line (OHTL) which will be located between the proposed Morupule B Power Station, located near Palapye, and Phokoje Substation, near Selebi - Phikwe. Digby Wells and Associates (DWA) were appointed as consultants to undertake the EIA for the proposed 400 kV line as part of the MEP. The proposed MEP includes the construction of a coal fired Power Station and the construction of a 400 kV Transmission line from Mmamabula Power Station to Palapye and then to Selebi ­ Phikwe. The 400 kV line between Morupule B and Phokoje is expected to provide a firm 400 kV supply at Phokoje Substation. The estimated length of the line is 105km. At the Morupule Power Station, the existing 220 kV lines from Morupule to Selebi-Phikwe and Serule are required to be deviated as part of the scope for the 400 kV line project. The estimated length of the deviations is 5km per line. The deviations will eliminate multiple line crossings by the new 400 kV feeders to be built at the proposed Morupule B Power Station. The proposed line route from Morupule B will follow the route of the existing 220 kV line between Morupule Power Station and Phokoje Substation. At Phokoje substation, there will be a realignment of feeders and feeder bays. The new Morupule B ­ Phokoje 400kV line will occupy the existing feeder bay for the Matimba ­ Phokoje 400kV line, including the last two towers into Phokoje 400kV substation. The Matimba ­ Phokoje 400kV line will then be shifted to occupy a vacant feeder bay which had been reserved for a future Matimba ­ Phokoje 400kV line which will no longer be built. This vacant feeder bay (Matimba East) will then need to be fully equipped under this contract. A new short section of 400kV line (approximately 1km) will also be built under this contract for the Matimba ­ Phokoje 400kV line to replace the section of line occupied by the Morupule B ­ Phokoje 400kV line. The DEA approved the draft EMP for the proposed project submitted together with the MEP EIA Report. In order for construction to commence, a project specific, detailed EMP needs to be compiled and submitted to the DEA for approval. 2. TERMS OF REFERENCE The Environmental Impact Statement (EIS) for the 400 kV Transmission line for the Mmamabula Energy Project (MEP) was submitted to the Department of Environmental Affairs (DEA) for consideration. The EIS was in accordance with Section 14 (1a) of the Environmental Impact Assessment (EIA) Act, No. 6 of 2005, authorised by DEA on the following conditions: · The Botswana Power Corporation (BPC) should notify Interested and Affected Parties (I&APs) living along the Transmission line corridors and whose properties will be affected, prior to commencement of construction work; Parsons Brinckerhoff Africa (Pty) Ltd 1 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · The mitigation measures and impact management / monitoring recommendations that are outlined in the EIS should be implemented totally; · Planning permission is granted by relevant authorities before construction of the Transmission line; · All electrical equipment or appliances are Polychlorinated Biphenyl (PCB) free and proof to that effect should be available during monitoring and auditing of the project. It is, amongst others, these conditions with which this EMP seeks to ensure contractor's compliance. The BPC appointed PB Africa (Pty) Ltd for the Consultancy Service for the proposed Morupule B ­ Phokoje 400 kV single circuit OHTL. The Environmental and Social Division of PB Africa was responsible for the compilation of the site specific EMP. A site visit was conducted by PB Africa on 21 and 22 August 2008. The site visit included an inspection of the proposed line route between Morupule B Power Station and Phokoje Substation. A map indicating the location of the 400 kV Transmission line is included in Appendix A. The map shows the line routing in relation to Morupule `B' Power Station, Phokoje Substation and the surrounding area. Furthermore, sensitive areas in terms of biodiversity are highlighted and particular attention to biodiversity mitigation measures need to be employed along those sections of the line. Zoomed in maps of the sensitive zones are provided in Appendix B for further guidance. The DEA will undertake an environmental audit of the project. 3. AIM OF THIS DOCUMENT The aim of this Environmental Management Plan (EMP) is to highlight the potential impacts associated with the construction of the 400 kV Transmission Line and provides suitable mitigation measures to prevent or minimise those impacts. Furthermore, it aims to incorporate the costs of mitigation measures and rehabilitation activities into the tender budget. The long term objectives of the EMP are: · To ensure that, first and foremost, the RoD and regulatory requirements are adhered to; · To ensure that necessary precautions are taken to avoid unnecessary damage or potential future damage to the environment during the construction phase of the project; · To ensure that all personal involved in the construction phase of the project are committed to sound environmental best practices, as described within this EMP; · To preserve the natural environment through all possible implementable measures where possible. Parsons Brinckerhoff Africa (Pty) Ltd 2 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 4. GLOSSARY OF TERMS AND ABBREVIATIONS PARTIES INVOLVED Contractor (CT) For the purpose of this EMP, `contractor" refers to the main contractor (s) appointed by the client for the construction of the overhead Transmission line, or portion of the project. The main contractor (s) are required to adhere to the EMP and are responsible to ensure that all sub-contractors, suppliers, and staff appointed by them also adhere to the EMP. All Staff The entire workforce. Workers employed by the contractor, persons involved with the activities related to the project, or persons present or visiting the construction, including permanent, contract and casual labour. Environmental A qualified, independent environmental expert appointed by the client and / or the Control Officer contractor. It is the Environmental Control Officer's (ECO) responsibility to (ECO) monitor the contractor's performance in matters concerning the day to day implementation of the EMP, and for liaison with the DEA and other authorising institutions. Where required the ECO will be responsible for consultation with the public and owners or managers of properties affected by the construction. DEA Department of Environmental Affairs. Local Community People residing or present in the region and near the construction activities, including owners and / or managers of land affected by construction, workers on the land and people in nearby towns or villages. Public Community Any individual or group concerned with or affected by the project and its consequences, including the local community, regional and national authorities, investors, workforce, customers, consumers, environmental interest groups and the general public. ABOUT THE CONSTRUCTION ACTIVITIES Construction The land on which the project will be located. It includes the power line route, Area/Site campsites, access roads and tracks as well as any other area affected or disturbed by construction activities. The EMP (particularly the specifications for rehabilitation) is relevant for all areas disturbed during construction. Service Track The track (graded only where necessary) along the length of the power line to Parsons Brinckerhoff Africa (Pty) Ltd 3 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation facilitate transportation of the construction workforce, equipment, material and to provide access to and from proposed power line towers for maintenance. Access Roads All existing and newly established roads and tracks, and areas cleared or driven and Tracks over to provide access to and from the construction areas, and for the transportation of the construction workforce, equipment and materials. Route Clearing / Clearing of a linear area with a grader. It usually implies skimming the soil Blading surface to remove rocks, vegetation and other obstacles likely to interfere with the safe construction. Disturbances associated with blading (and subsequent skimming of the soil surface) can be significantly reduced if the blade is kept approximately five centimetres from the soil surface. By doing this, larger obstacles will be removed but the integrity of the protective top layer of the soil will be left intact. Gravel, pebbles and small stones on the soil surface, and small plants will be left in place, and larger plants will be `pruned' five centimetres above ground. ABOUT THE ENVIRONMENT Commercially A species of animal or plant having desirable human uses (food, fuel, shelter, Important Species clothing, medicine, etc.) present in sufficient numbers to make commercial collection or harvesting economically viable. Environment The surroundings within which people exist. The environment is made up of: the soil; water and atmosphere; fauna; flora; any part, combination or interrelationships among these; and all the physical, chemical, aesthetic and cultural properties and conditions of the foregoing that influence human health and well being. Environmental A detailed plan of action prepared to organise and co-ordinate environmental Management Plan mitigation, rehabilitation and monitoring so that positive impacts are enhanced (EMP) and negative impacts and damage to the environment are avoided, minimised or rectified where required. Environmental The effect of an activity on the environment, whether desirable or undesirable. Impact Undesirable or negative environmental impacts will result in damage and / or pollution of, or detriment to the environment or in danger to the public, whether immediate or delayed. Environmental An unexpected or sudden occurrence related to the project, including major Incident emissions, spills, fires, explosions, floods or erosion leading to serious or Parsons Brinckerhoff Africa (Pty) Ltd 4 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation potentially serious negative environmental impacts. Fugitive Dust Natural and / or human associated dust becoming airborne due to the forces of wind or human activity. Flora and Fauna Any individual or group of micro-organisms, plants or animals. General Waste It includes waste paper, board, cardboard, benign organic and domestic waste and Construction and uncontaminated construction debris such as used paint tins, unused Rubble conductors and earth wires, insulator sets, nuts, bolts and unused subsoil. Heritage Sites Heritage sites and artefacts can be defined as any object or site of cultural, and Artefacts historical, archaeological or paleontological significance found in or on the land. Historical objects with architectural, historical, scientific, cultural, social, spiritual, linguistic, technological or aesthetic value. For example, buildings or parts thereof, graves or burial sites, milestones, numismatic and military objects. Archaeological objects include material remains resulting from human activity which are over 100 years old and which are in a state of disuse, such as tools, artefacts, human and hominoid remains and artificial features and structures. Paleontological objects include any fossilised remains of animals or plants Hazardous Potentially dangerous substances that may affect human health and / or Substances environmental health and / or have inherent chemical and physical composition, which could be toxic, poisonous, flammable, explosive, carcinogenic or radioactive. Hazardous waste includes, but are not limited to: human excrement, the by products and wastes associated with the use of hazardous substances (i.e. used fuel, oil, lubricant and solvents), as well as items such as spent batteries, old oil filters, light bulbs, tyres, circuit boards, etc. which require special collection and handing. When left abandoned, even substances such as scrap metal, wire, tins, broken glass and plastic could be harmful to people, wild and domestic animals. For example: plastic could be ingested by animals; people and animals could be injured by broken glass or metal objects; and animals could get trapped in drums, tins and bottles and get entangled in plastic or metal wiring. Even if buried, such objects may become exposed over time due to wind erosion, scavengers or future human activities. Because of the sensitive nature of the area, these substances are all regarded as `hazardous waste' for the purposes of Parsons Brinckerhoff Africa (Pty) Ltd 5 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation this EMP. Hydrological For the purposes of this EMP, hydrological features include, but are not limited Features to: wetlands; open water; vegetated drainage channels; subterranean water; marine environments and estuarine environments. Life Support Life support systems include, but are not limited to: an ecological system in which Systems outputs are vital for sustaining specialised habitats; an ecological system in which its outputs are vital for sustaining human life (e.g. water purification). Mitigation Environmental management measures designed to avoid, limit or remedy undesirable environmental impacts. Monitoring Structured observation, measurement and evaluation of environmental data over a period of time to assess the efficiency of environmental mitigation and rehabilitation measures. Rehabilitation Measures implemented to restore a damaged environment. Sensitive Sites Environmentally sensitive sites include but are not limited to: · Areas with high conservation value due to the presence of important plant specimens, pristine habitats, high biodiversity, important water resources or heritage features and artefacts; · Areas particularly prone to erosion once disturbed (steep slopes); · Vulnerable areas with low potential for rehabilitation / slow rate of recovery (rock outcrops, steep slopes); and · Areas in close proximity of sensitive receptors, such as farm homesteads, viewpoints or tourist stopovers. Specialised Specialised habitats include, but are not limited to, areas which are: Habitats · Priority breeding habitats; · Refuge areas; · Vital for species survival (important for all / or part of its life cycle); · Essential for species performance; and, Parsons Brinckerhoff Africa (Pty) Ltd 6 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Cryptic habitats, etc. Parsons Brinckerhoff Africa (Pty) Ltd 7 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 5. PROJECT DESCRIPTION 5.1. Proposed Project BPC propose to construct a new 400 kV Transmission line between the proposed Morupule B Power Station and existing Phokoje Substation. This will involve the following activities: · Deviations of part of the existing 220kV lines from Morupule to Selebi-Phikwe and Serule, respectively, to prevent multiple line crossings by the new 400kV lines emanating from the new Morupule B Power Station. This will involve the construction of new towers and stringing of conductors and earthwires on the deviated portions of the 220kV lines; · Dismantling of some of the existing towers on the 220 kV lines between the deviation points; · The construction of new towers and stringing of conductors and earthwires on the new 400kV OHTL. The following project specific information has been incorporated into applicable sections of the EMP. 5.1.1. Construction Details The scope of work for the construction will consist inter alia of the following activities: · Ground line survey of the final routes selected for the overhead lines; · Production of line profiles; · Detailed geotechnical investigations; · Tower plotting and optimisation; · Design of tower foundations; · Tower earthing design; · Material supply to include: conductors, earthwires, composite insulators; line hardware and fittings; vibrations dampers; arcing horns; complete towers; foundation materials; aircraft warning markers; anti climbing devices; bird guards / diverters; etc; · Supply of all plant and equipment for line construction; · Site establishment; · Bush clearing; · Tower pegging; · Foundation excavations; · Tower base setting and concreting; · Backfilling of foundations; · Tower erection; · Stringing; and, · Dismantling of redundant 220 kV lines. Parsons Brinckerhoff Africa (Pty) Ltd 8 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 5.1.2. Dismantling · Several towers along the existing 220 kV line routes between Morupule to Phokoje and Serule, respectively, will need to be removed. This will involve the dismantling of the tower structures and demolition, excavation and removal of the concrete foundations to 600 mm below ground level. · The dismantling contractor will be required to dispose of all dismantled material (steel, concrete, insulators, conductors etc.) to the appointed BPC depot. Disposal waybills will need to be forwarded to the project consultant for confirmation. 5.1.3. Tower Construction · Material required for each tower will be transported to the tower site and constructed on site. · Cranes will be used to lift and place the tower structures in position. In places where cranes are not suitable, manual means using a ginpole may be utilised for self-supporting tower positions. 5.1.4. Stringing of Conductors · Once the towers have been erected, the conductors and earthwires will need to be strung between each tower. In order to extend the conductors and earthwires along the route, a vehicle will be used to drive along the servitude to pull out a pilot wire to be used for pulling the conductors and earthwires between pulling sections, including the placement of rollers at each suspension tower. The conductors and earthwires will then be strung by a tensioner and a puller between stringing sections and then clamped into position at each tower site. · Obstructions such as trees may be present on the servitude. BPC generally requires the servitude to be cleared of all trees that may cause a flashover. The width of the strip to be cleared of trees is not more than 40m, and will vary according to the mean height of the bush or forest and shall be determined by ensuring that any tree after falling shall not be less than 5m clear of the maximum deflected position of the conductor, or standing trees would not cause flashover from a conductor deflected up to 55o from the vertical. In determining the flashover clearance and in estimating the mean height of the bush or forest due allowance shall be made for seasonal growth. The strip of land determined for tree clearance above shall be completely cleared of all trees, scrub and undergrowth by felling not more than 150 mm above ground. · No bush clearing in the form of de-stumping, scalping and uprooting is allowed on river and stream banks. No bush clearing is allowed in or across bush filled ravines and gullies. No protected or endangered plant species shall be removed without a PERMIT from Nature Conservation, the landowner or BPC. The use of herbicides is strictly prohibited in Botswana Parsons Brinckerhoff Africa (Pty) Ltd 9 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · A botanist is to be engaged before the bush clearing to identify the protected species. The contractor to provide a botanist and will be responsible for such costs. · Only an 8m corridor may be cleared flush with the ground to allow vehicular access. No scalping is allowed on any part of the servitude road unless absolutely necessary. 5.1.5. Earthworks · Cut to fill activities will be employed to ensure that excavated material (removed from the bases of the towers during foundation excavation) is utilised for the backfilling of the holes following construction of the tower foundation. · Topsoil excavated from each tower position will be kept to a minimum and will be limited to the immediate area surrounding the base of the tower. Any shortfalls required for rehabilitation / landscaping purposes will be addressed during the landscaping contract. 5.1.6. Equipment and Materials Storage The contractor will make use of an area to set up storage and administration area for the duration of the contract. This will need to be located at a suitable existing site and must not be located on the servitude. 5.2. Site Description The following section details the findings and recommendations of specialist studies undertaken for the MEP as well as observations during various sites visits undertaken by PB Power. 5.2.1 Existing and Surrounding Land-use Description The majority of the Transmission line will pass through tribal land utilised by a number of different farmers between the towns of Palapye and Selebi ­ Phikwe. There are a number of cattle kraals, posts and dwellings that exist within the servitude of the Transmission line. The line will cross over at the point where the A1 crosses Mogapinyana Road and a railway line. The Transmission line passes over a number of non perennial rivers in the Palapye area. A noise and social impact assessment was conducted as part of the greater MEP. The recommendations of these specialist reports are included as part of this project and EMP. Parsons Brinckerhoff Africa (Pty) Ltd 10 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Implications · Dismantling activities will generate large volumes of steel and foundation rubble waste, which will need to be disposed of or recycled in an appropriate manner. · The site is situated in close proximity to sensitive receptors (people, animals, etc) which may be affected by noise and dust associated with dismantling and construction activities. · Dismantling, construction and stringing activities are potentially dangerous to road users, residents and the general public. Recommendations · Construction activities must take place during daylight hours on week days (between 07h00 and 17h00). · Construction activities outside of daylight hours must be communicated accordingly in advance. · There must be regular dampening of the ground to avoid dust in the working areas. · Signage must be put in place in public places prior to any potential dangerous activities, to alert the public of construction activities. · Keep all equipment / machinery and vehicles in good working order and well maintained. · Construction activities must be restricted to demarcated areas. · All areas outside designated construction areas, shall be regarded `no go' areas. · Aircraft warning balls need to be put on the OHTL, on the span of transmission line that crosses over the road. 5.2.2 Topography Description The area comprises low relief plain and featureless veld. The proposed line route crosses a number of seasonal rivers and streamlets. The major rivers that will be crossed are the Lotsane, Dikabeya, Tshokana and Mahunwane Rivers. Implications · Rivers could pose access problems during the construction and maintenance of the OHTL. · There is the potential for erosion to occur on the banks of rivers and streams. Recommendations · Erosion control measures must be put in place prior to construction activities commencing. Parsons Brinckerhoff Africa (Pty) Ltd 11 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Minimise loss of topsoil at any one site. 5.2.3 Water Resources Description The servitude crosses a number of water courses between Palapye and Selebi ­ Phikwe. The major rivers that will be crossed are Lotsane, Dikabeya, Tshokana and Mahunwane Rivers. Implications The following will be addressed in the applicable sections of the EMP: · Stormwater emanating from access roads to the tower sites; · Prevention of erosion and sedimentation of watercourses through the construction of berms; · Disturbance of water courses from servitude construction; · Sedimentation of local streams; · Sewage and waste disposal; and, · Hydrocarbon spillage. Recommendations · Plan and implement appropriate water monitoring and management plans; · All roads need to be planned to minimise erosion; · Chemicals and hydrocarbons capable of causing water pollution should be appropriately transported, loaded and unloaded and stored and the necessary precautions taken when refuelling onsite. · Precaution must be taken when working close to such rivers in that they are not polluted with oils, fuels and other toxic materials. · Design and implement an appropriate waste management plan. · Minimise construction impacts at all river crossing points through appropriate mitigation measures where relevant. · Avoid wet areas at any cost. · No access roads through rivers and stream banks. · Minimise erosion of embankments and subsequent siltation of rivers and streams. · Warning balls need to be placed on the OHTL when it crosses rivers. 5.2.4 Geology and Soils Description Parsons Brinckerhoff Africa (Pty) Ltd 12 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation A detailed geotechnical assessment will be conducted prior to the commencement of construction. The major soil groups that will be crossed by the proposed Transmission routes are mostly Arenosols and Luvisols, with small areas of Lixisols. They are mostly found on fine-grained and coarse-grained sedimentary rocks e.g. .sandstone. Luvisols have an accumulation of clay (15-25%) and a higher fertility, while Arenosols are coarse, sandy soils with weak structure and low fertility. In general the soils are sandy with a low clay content (<10%); this results in high water infiltration rates, low water holding capacity and fairly poor fertility. Lixisols are highly weathered and strongly leached soils and they also have a zone of clay accumulation which may occur at some depth below soil surface. Implications · It is anticipated that excavations will be fairly easy; · The low clay content and loose soils, has the potential to cause erosion; · Soil compaction; and · Soil pulverisation. Recommendations · Berms should be placed around stockpiled soil to prevent soil loss due to erosion. · Roads that are frequently used should also be built up using ferricrete or calcrete that can be obtained from an authorized local source. · Storage and use of fuels and lubricants should be strictly confined to bunded areas. Fuels and lubricants stored on site should be stored on an impermeable surface, such as heavy gauge plastic sheeting. The bunded area should have a volume of 110% volume of the stored fuels and lubricants. · Temporary storage of fuels and lubricants may not exceed the duration of the works. · Areas cleared of topsoil should be kept to a minimum in order to limit possible erosion problems. 5.2.5 Flora Description The Vegetation Map of the Republic of Botswana (1991) was used to give an indication of the general vegetation types occurring along the proposed routes of the Transmission line. Information about Botswana in general was also obtained from the internet (Global Terrestrial Observing Systems, 2001 & Bose, 2002). According to White (1983), the area of concern falls within the Kalahari thornveld and the transition to Zambezian broad-leaved woodland. This vegetation type is characterized by wooded grassland. The Parsons Brinckerhoff Africa (Pty) Ltd 13 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation area falls on the transition between the Zambezian Regional Centre of Plant Endemism (also referred to as the Zambezian Region) and the Kalahari-Highveld Regional Transitional Zone as described by White (1983). The area of the proposed development show strong similarities to Vegetation Type 17, namely the Sweet Bushveld, as described by Van Rooyen & Bredenkamp (In Low and Rebelo, 1996) and the Arid Sweet Bushveld (Veld Type 14) as described by Acocks (1988) within the adjacent boundaries of South Africa. The Sweet Bushveld and Arid Sweet Bushveld show similarities and correspond in vegetation composition, dominant trees, shrubs, climate and soils. The typical vegetation in this region is savanna, containing both a tree and shrub layer and a grass layer. Due to the extensive grazing by livestock in some areas, the relationship between these two layers has been unbalanced, resulting in the tree and shrub layer becoming dominant over the grass layer. This then allows the tree and shrub layer to continually out-compete the grass layer, resulting in a dense tree and shrub layer and limited grass cover. Because the area of interest consists predominantly of tribal grazing lands, there are no areas officially protected, such as game reserves, for conservation value in the area of interest. Implications · Removal of vegetation and topsoil for servitude, towers and access roads; · Introduction or encroachment of alien invasive species due to disturbance; · Disturbance of animal nesting and foraging sites. Recommendations · Any individual plants that have Red Data Status that are found growing in an area where the vegetation will need to be removed, must be removed by an authorised individual and should be relocated to a safe place to avoid destruction. A nursery will be developed on site for this purpose. · Only the cutting of trees is permitted, no trees can be uprooted except if they fall within a planned access or service road. · The people involved in the construction phase should be educated on which plants have Red Data Status so they can notify the Environmental Control Officer (ECO) should they see these plants in vulnerable areas. · Vegetation monitoring will include alien invasive status, should such species be encountered, an alien invasive control programme will be developed and implemented. · All persons involved in the construction phase should be prevented from entering areas of vegetation that are not included as part of the project. · All construction vehicles must be restricted to designated roads and lay down sites to prevent unnecessary destruction of vegetation. Parsons Brinckerhoff Africa (Pty) Ltd 14 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Appropriate measures should be implemented to prevent erosion. · Alien species encountered during construction activities must be removed. · Ensure no unnecessary removal of trees or vegetation. 5.2.6 Fauna Description Due to the fact that the land use in this region is primarily tribal grazing land, the potential for wild animals to occur here is very low. The identification of areas of importance that could support natural wildlife, especially red data species, was difficult due to the fact that the majority of the land is disturbed. The natural vegetation is disturbed due to human interference and the grazing and browsing of domestic animals. The local people also hunt in these areas. As a result very few wild animals were expected to occur here. The very low numbers of actual wild animal sightings confirmed this. The wetland areas would provide watering points for the existing wildlife but due to the climate and surface water patterns in this region these are not permanent water sources. These small wetlands were generally located in areas utilised by humans and livestock so did not support a large variety or abundance of wildlife. No red data mammals were observed during the site visit, no reptiles or frogs were recorded during the specialist study investigations. There is the possibility of wild bucks, hares and tortoises occurring in the project area. These were observed during initial site investigations. Implications · Construction phase will increase local dust levels and noise levels in the area. · The increased traffic of heavy duty vehicles and machinery will pose a threat to animals in the area. · The removal of vegetation during the construction phase, less food items will be available to animals in the area and the risk of erosion will make the area even less desirable for animals especially the browsing/grazing species. Recommendations · Workers should be made aware of the importance of maintaining the animal life. · Hunting by construction workers is prohibited. · Areas of importance, such as pans and stream banks, must be marked as no-go areas, so as to preserve the necessary habitats. · The destruction of the vegetative cover should be kept to a minimum, and limited to those areas allocated for infrastructure development. Parsons Brinckerhoff Africa (Pty) Ltd 15 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Access gates must be installed where fences are opened for access roads and game gates must be installed where necessary, these need to be approved by the ECO. · Heavy vehicles should be given a strict speed limit that should be adhered to at all times in order to minimise the potential for road related deaths. · Minimise disruption of farming activities. · Minimise disturbance of animals. · Minimise breeding patterns of birds. 5.2.7 Avifauna Description The study area, broadly speaking can be described as arid woodland, having a grassy under storey and a distinct woody upper storey of trees and tall shrubs. The vegetation structure is one of the most important factors influencing bird distribution. With the vegetation zones in the study area, several distinct bird micro-habitats are found. The current proposed alignments do not impact on the vulture colonies in Tswanpong, as they avoid the hills completely. According to the report, the Transmission line alignment should have no direct impacts on the birds. Implications · Electrocutions ­ Due to the large size of the clearances on most overhead lines greater than 132kV, electrocutions are generally ruled out as even the largest birds can not physically bridge the gap between dangerous components. Transmission lines have proven to be beneficial to many birds, by providing safe nesting and roosting sites in areas where suitable natural alternatives are scarce. · Collisions ­ Collisions are the biggest single threat posed by Transmission lines to birds in southern Africa. Species most likely to be impacted are various water birds (wetlands and river crossings), storks (wetlands, river crossings and agricultural lands), Secretary birds and Kori bustard. · Habitat Destruction - During the construction phase and the maintenance of power lines, some habitat destruction and transformation inevitably takes place. This happens with the construction of access roads, the clearing of servitudes. Servitudes have to be cleared of excess vegetation at regular intervals in order to allow access to the line for maintenance, to prevent vegetation from intruding into the legally prescribed clearance gap between the ground and the conductors. These activities have an impact on birds breeding, foraging and roosting in or in close proximity to the servitude through modification of habitat. Recommendations Parsons Brinckerhoff Africa (Pty) Ltd 16 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Mark the earth wire of the line with anti-collision devices. There are several devices available in southern Africa for the marking of power lines. Some are dynamic devices (usually called bird flappers) and some are static. Dynamic devices are more effective in reducing collisions. · Construction methods should minimise the impact on vegetation and the removal of large trees should be avoided if the trees pose no risk of flashovers. 5.2.8 Archaeology and Historical Sites Description An Archaeological Impact Assessment (AIA) was conducted for the proposed transmission line and a conditional permit awarded by the Botswana National Museum (Appendix B). The awarded permit lists the following conditions: · That an introduction course be performed for those involved in the construction; · That an archaeological inspection be carried out after bush clearing; · That monitoring is conducted during the construction of the power line, with specific reference to those areas where archaeological remains were identified; · That a test excavation be carried out, prior to any development, for identified sites with a significance ranking of 2 ­ 3; · Where possible, site 10 ­ foothill site, be preserved at all costs, and; · That the Department of National Museum be informed of any further and/or additional archaeological finds. Parsons Brinckerhoff Africa (Pty) Ltd 17 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 6. ENVIRONMENTAL MANAGEMENT PLAN 6.1. General Focus This EMP outlines measures to be implemented in order to minimise adverse environmental degradation associated with the construction of the propose Transmission power line. It serves as a guide to the contractor and the construction workforce on their roles and responsibilities concerning environmental management on site, and provides a framework for environmental monitoring throughout the construction period. 6.2. Purpose The purpose of the EMP is to: · Encourage good management practices through planning and commitment to environmental issues; · Define how the management of the environment is reported and performance evaluated; · Provide rational and practical environmental guidelines to: Prevent pollution of land, air and water; Protect indigenous flora and fauna; Prevent soil erosion and facilitate revegetation; Comply with applicable laws, regulations, standards, and guidelines for the protection of the environment; and Adopt the best practicable means available to prevent or minimise adverse environmental impacts. · Develop waste management practices based on prevention, minimisation, recycling, treatment or disposal of wastes; · Describe all monitoring procedures required to identify impacts on the environment; and, · Train employees and contractors with regard to environmental obligations. Parsons Brinckerhoff Africa (Pty) Ltd 18 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 7. ENVIRONMENTAL AWARENESS AND COMPLIANCE 7.1. Introduction The philosophy adopted in this management plan is derived from the principles of sustainable development. Sustainable development requires that: · The disturbance of ecosystems and loss of biological diversity are avoided, or, where they cannot be altogether avoided, are minimised and remedied; · Pollution and degradation of the environment are avoided, or, where they cannot be altogether avoided, are minimised and remedied; · That the disturbance of landscapes and sites that constitute the nation's cultural heritage is avoided, or where it cannot be altogether avoided, is minimised and remedied; · That waste is avoided, or where it cannot be altogether avoided, is minimised and re-used or recycled where possible and otherwise disposed of in a responsible manner; · That a risk-averse and cautious approach is applied, which takes into account the limits of current knowledge about the consequences of decisions and actions; · Negative impacts on the environment and on people's environmental rights be anticipated; and, prevented and where they cannot altogether be prevented, are minimised and remedied. 7.2. Responsibilities for Environmental Management In addition to the appointed Environmental Consultant, the DEA may need to provide input (review, authorise, provide feedback or advice) on certain aspects of the EMP. Their prompt reaction is required to avoid unnecessary delays during the construction period. They shall respond promptly (within 10 working days) in writing to: · Applications for approval of access plans and the construction campsite layout; · Applications for approval of amendments to any EMP clauses; · Environmentally related complaints or claims received; · Requests to provide input on the specifications of bird mitigation devices used; · Requests for advice on rehabilitation measures, or other environmental matter related tot eh EMP and the project in general. The appointed ECO will arrange for inspections of the construction activities and the EMP implementation throughout the construction phase. The ECO will produce monthly reports (depending Parsons Brinckerhoff Africa (Pty) Ltd 19 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation on the amount of activity) that will be submitted to the client (BPC) and the DEA. Upon completion of the project, the ECO will produce a final report, which will be submitted to the client and DEA. The contractor and BPC or its agents shall be responsible for environmental control on site during the construction period. The ECO or the person/s nominated by the client must notify surrounding residents in advance of any potentially disturbing activities. 7.3. Training and Induction of Employees The contractor and BPC have the responsibility to ensure that all those people involved in the project are aware of and familiar with the environmental requirements for the project (includes sub contractors, casual labourers, etc). The EMP shall be part of the terms of reference for all contractors, sub contractors and suppliers. All contractors, sub contractors and suppliers have to give some assurance that they understand the EMP and that they will comply with the conditions therein. All senior and supervisory staff members shall familiarise themselves with the full contents of the EMP. They shall know and understand the specifications of the EMP and shall be able to assist other staff members in matters relating to the EMP. An environmental awareness training programme for all staff members shall be put in place by BPC. Before commencing with any work, all staff members shall be appropriately briefed about the EMP and relevant occupational health and safety issues. 7.4. Complaints Register and Environmental Incidents Book The contractor must record any complaints received from the community, the complaint should be brought to the attention of the site manager and ECO, who will respond accordingly. The following information will be recorded: · Time, date and nature of complaint; · Response and investigation undertaken; and · Actions taken and by whom. All complaints received will be investigated and a response (even if pending further investigation) should be given to the complainant with 7 days. Parsons Brinckerhoff Africa (Pty) Ltd 20 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation All environmental incidents occurring on the site will be recorded. The following information will be provided: · Time, date and nature of the incident; · Actions taken and by whom. The complaints register and Environmental Incidents book must remain on site / site offices at all times. 7.5. Environmental Monitoring An independent environmental consultant who will act as the ECO must undertake environmental audits at a frequency that is deemed necessary by the ECO in order to ensure compliance of all aspects of the EMP. This can be done by means of completing the EMP checklist which forms part of the mitigation measures included in this EMP. In order to facilitate communication between the ECO and the resident engineer and contractor, it is vital that a suitable chain of command is structured that will ensure that the ECO's recommendations have the full backing of the project team before being conveyed to the contractor. In this way, penalties as a result of non-compliance with the EMP may be justified as failure to comply with instruction from the highest authority. 7.6. Dealing with Non-Compliance with the EMP (Penalties/Incentives for Staff) BPC may put in place in the contractors contract, procedures to motivate the contractor and staff members to comply with the EMP and to deal with acts of non-compliance, or deliberate malicious damage to the environment by any staff member. It is suggested that fines / penalties be set according to the cost required to rehabilitate the area, to the satisfaction of the ECO, should the rehabilitation be required as a consequence of the contractor's non-compliance with the EMP. 7.7. Roles and Responsibilities of Key Personnel during Construction Phase In order to ensure that there is a chain of command and that key personnel are aware of their roles and responsibilities during the construction phase of the project the following table has been developed (to also be read in conjunction with Section 3 ­ Glossary of Terms). Parsons Brinckerhoff Africa (Pty) Ltd 21 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Function Name / Cell Number Responsibility Project Manager (PM) ­ from Overall management of the Project and BPC EMP implementation. Site Supervisor / Contractor Oversees site works, liaison with contractor, Manager (CM) PM and ECO. Environmental Control Officer Implementation of EMP and liaison between (ECO) BPC and the Contractor. Contractor (CT) Implementation and compliance with recommendations and conditions of the EMP. 7.8. EMP Amendments / EMP Instructions No EMP amendment (relaxation or revision of any EMP mitigation measure) shall be allowed without approval from the relevant authority (DEA). Motivations for the EMP amendments must be discussed with the appointed ECO and other relevant authorising bodies. Parsons Brinckerhoff Africa (Pty) Ltd 22 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8. MITIGATION MEASURES This section forms the core of the EMP. Potential environmental impacts, impact sources and objectives are described, and environmental management mitigation measures to be implemented during construction are specified. The Contractor shall adhere to these measures at all times. 8.1. Construction Initiation / Site Establishment 8.1.1 Potential Significant Impacts · Unnecessary damage to sensitive sites, potentially affecting biodiversity protection; · Potential disturbance to traffic flow. 8.1.2 Sources of Potential Impacts · Indiscriminate siting of construction workings such as access roads and tracks, etc.; · Heavy vehicles delivering construction materials. 8.1.3 Objectives · Carefully plan construction activities to minimise environmental damage and to minimise the overall area of impact. 8.1.4 Performance Indicators · Proactive attention to the mitigation of impacts, the effectiveness determined by the number of community complaints received and the number of incidences compared to the norm, prior to the construction activities. 8.1.5 Monitoring Programme · Draw up a Project Layout and Access Plan in conjunction with PB Power; · Monitor construction against the Project Layout and Access Plan. · Have the Project Layout and Access Plan, and all amendments thereto, checked by the ECO and approved by DEA. 8.1.6 Mitigation Measures Parsons Brinckerhoff Africa (Pty) Ltd 23 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Project Layout and Access Plan Before commencing with construction, carefully plan the siting and use of the construction activities and all workings. Develop a Project Layout and Access Plan to show the intended use of the area. The plan shall clearly indicate and/or describe the location and details of: · Servitudes; · Areas and routes to be cleared ­ including the size / width of the cleared areas; · The construction campsite and rest areas to be used during construction; Engineers, · Waste disposal sites to be used during construction; Architects, CT · Sources of construction materials; and BPC to · Sources and procedures for water abstraction and provision; develop, ECO · Power supply during construction; to advise and · Existing roads and tracks to be used as transportation routes, and routes to DEA to approve gain access to construction areas; · New tracks deemed necessary to provide access to construction activities; · Any informal residential structures found within the property; · Affected land use, 1:50 year flood lines; · Sensitive areas; and · Topsoil management, i.e. indicate areas where topsoil will be removed, stockpiled and later used. Access to Site Routing: · The contractor must take into account any limitations identified and recommendations made during the environmental studies when deciding on an access route to the construction site. Resident · The location of all underground services and servitudes must be identified and Engineer (RE) / confirmed before construction commences. ECO / CT and · Choice of access routes and timing of access should take into account minimum All drivers disturbance to neighbouring residents and surrounding land uses. · Access roads should be photographed prior to construction to ensure that they are rehabilitated to their former state following construction. · Vehicles must keep to single tracks on the servitude. Parsons Brinckerhoff Africa (Pty) Ltd 24 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Haulage Roads: · All roads for construction access must be planned and approved by the RE and ECO ahead of construction activities and must not be created on an ad hoc basis. · Roads must follow natural contours to reduce storm water erosion. · Roads must have as little cut and fill as possible. · Road widths and the radii of curves are to be reduced to the minimum required. · No trees / shrubs / groundcover may be removed or vegetation stripped without the prior permission of the RE / ECO. · Contractors shall construct formal drainage structures / berms on all temporary haulage roads in the form of side drains and mitre drains to prevent erosion and point source discharge of run-off. RE / ECO / CT · Scour check walls must be constructed in the side drains as follows: Gradient of Road Scour Check Spacing. <4% Not required 5% 20m 8% 10m 10% 5m · Scour checks can be constructed from rocks available on site or using driven wooden pegs. · Haulage roads must allow for the natural flow of water where required. · All stream / river crossings and temporary bridges shall be built to the RE's approval. Survey points: · Roads or trails that are cut to provide temporary access for survey work must be RE / ECO / CT minimised. · Marking of survey points must be done to / with the RE's approval. · Vegetation clearing must be kept to a minimum during survey operations. Construction Campsite Plan Before establishing the construction campsite, carefully plan the layout and Engineers, develop a Construction Campsite Plan1. The Construction Campsite Plan shall Architects, CT provide a description of the site and shall show, on a reasonably scaled map, the and BPC to intended use of the site. Indicate and / or describe the location, size / quantity / develop, ECO capacity and design of: to advise DEA · Access routes; to approve. · Ablution facilities (including details on the handling of sewage and 1To form part of the Project Layout and Access Plan. Parsons Brinckerhoff Africa (Pty) Ltd 25 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility wastewater); · On-site waste management facilities (waste containers, etc.); · Design of bunds and other structures for containment of hazardous substances; · Fencing; · Water storage and supply; · Power supply (for cooking, space heating, lighting, etc.); · Fire extinguishers, first aid kit and any other relevant safety equipment; · Accommodation facilities (where necessary); · Other structures and buildings (offices, storerooms, workshops, etc.); · Other storage areas and stockpiles (i.e. topsoil, construction materials, equipment, etc.); · Location of areas to be reinstated upon completion of the construction period, providing measures to be used for reinstatement. Setting up the Construction Camp The construction / Contractors camp must not be located on the servitude. Rather it should be located at a previously established site in a suitable location. Layout: · No accommodation for construction staff (temporary or permanent) is to be provided on site. Only security personnel will be allowed to stay on site overnight. · The Contractor is to adhere to the following when selecting an alternative site for the Contractor's Camp: - Choose as level an area as possible (gradients must not exceed 1:3); - Avoid locating the camp within 50m of a hydrological feature; - Locate the Contractor's Camp within an already disturbed area; RE / CT / ECO · The site selected must be approved by the ECO. If the ECO is not satisfied to advise with the proposed site, alternative sites must be proposed and discussed with the ECO until a compromise is reached that is mutually acceptable to both parties. · Where possible cut to fill must be avoided during the establishment of the Contractor's Camp. · The Contractor's Camp should not exceed an area of 0.5ha. · The extent of the Contractor's Camp must be defined and fenced off and all activities must be confined within this area. Any extension or change in location of the Contractor's Camp must be authorised by the ECO. · The camp layout must be orderly and planned beforehand. · The camp area is to be maintained in a neat and orderly state at all times. Parsons Brinckerhoff Africa (Pty) Ltd 26 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · Provision must be made for adequate cooking and ablution facilities. · Gas or electricity must be used for cooking purposes to avoid the use of fires and potential stripping of the surrounding vegetation for fuel. · Adequate parking must be provided for site staff and visitors. Ablutions: · Potable water must be available at all times at various points within the Contractor's Camp. · Where waterborne sewerage is not available a reputable company approved by the RE must provide portable chemical toilets. Such toilets must be RE / CT available for all site staff. · Toilets must be no closer than 50m from any natural water body watercourses. · The construction of long drop toilets is forbidden. Provision for Camp Waste Disposal: · An adequate number of waste receptacles must be available at strategic locations around the Contractor's Camp for gathering all domestic refuse, and to minimise littering. · Bins must be lined for efficient control and safe disposal of waste. · Recycling and the provision of separate waste receptacles for different types RE / ECO of water must be encouraged. · The excavation and use of rubbish pits on site is forbidden. · A fenced area must be allocated for waste sorting and disposal. Establishing Storage Facilities General Substances and Materials: · Choice of location for storage areas must take into account prevailing winds, distance from water bodies and general on-site topography. · Storage areas must be designated, demarcated and adequately fenced if necessary. · A lockable, mobile structure must be erected on an impermeable surface for storing materials, equipment, chemicals, etc. · All fuel required on site is to be stored at the Contractor's Camp within an adequately sized bund wall that has an impermeable base. The ECO must ensure that the capacity of the bund wall is adequate to cope with a spill / leak of the fuel storage container. · An overflow pipe to the grease trap must be fitted to the concrete bund wall in RE / ECO case of the tank rupturing. · A designated working area must be constructed and must be underlain by an impermeable surface (e.g. a concrete slab or plastic lining). · All handling of potentially toxic or hazardous material, and the repair, Parsons Brinckerhoff Africa (Pty) Ltd 27 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility maintenance and storage of vehicles and equipment must be undertaken on the impermeable working surface in accordance with the Materials Safety Data Sheets (MSDS). · Fire prevention facilities must be present and easily accessible at all storage facilities. · Burning of firebreaks, if required, is to be carefully planned and managed. Safety and Security Fencing: · The Contractors camp must be adequately fenced with bonnox type fencing (approximately 2m high, topped with razor wire) to discourage the theft of materials and equipment from the construction site. RE / CT · Contractors' camps within residential / commercial areas should be fenced and manned to control access to the site. Gate Installation and Gate Control · Gates shall be installed where necessary. · All gates installed in electrified fencing shall be electrified as well. · All gate positions shall be 3m off centre to allow for continued access when stringing takes place. · All gates shall be fitted with locks and be kept locked at all times during the construction phase. · Once the contractor has left site gates are to be fitted with BPC locks. Risks Associated with Materials on Site: · Material stockpiles must be stable and well secured to avoid collapse and possible injury to workers / local residents. · Flammable materials should be stored as far as possible from adjacent residential / commercial / informal areas. · Fire fighting equipment is to be present on site at all times. RE / ECO · Obstruction to drivers' line of sight as a result of stockpiles must be avoided, especially at intersections and sharp corners. · No materials are to be stored in unsuitable or high-risk areas such as floodplains or on steep slopes. · All I&AP's are to be notified in advance of any known potential risks associated with the construction site and associated activities. Hazardous Substances and Materials: (See Section 3 for a definition of hazardous substances and materials) · Material Safety Data Sheets (MSDS's) shall be readily available on site for all chemicals and hazardous substances to be used on site. Where possible and available, MSDS's should include additional information on ecological impacts Parsons Brinckerhoff Africa (Pty) Ltd 28 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility and measures to minimise and mitigate against any negative environmental impacts in the result of an accidental spill. RE / CT and · Hazardous storage and refuelling areas must be bunded with an impermeable ECO to advise liner to protect groundwater quality. The contractor shall submit a methods statement to the RE for approval. · Storage areas containing hazardous substances / materials must be clearly signed. · Residents living adjacent to the Contractors Camp must be notified of the existence of the hazardous substances / materials storage area. · Staff handling hazardous substances / materials must be aware of their potential impacts and follow appropriate safety measures. · The Contractor must submit a method statement and plans for the storage of hazardous materials and emergency procedures. Materials Management: · Contractors shall prepare a source statement indicating the sources of all materials (including topsoil, sands, natural gravels, crushed stone etc.) and submit these to the RE for approval prior to the commencement of any work. RE / CT · A signed document from the supplier of natural materials must be obtained confirming that they have been obtained in a sustainable manner and in compliance with relevant legislation. Education of Site Staff on General and Environmental Conduct Environmental Education and Awareness: Ensure that all site personnel have a basic level of environmental awareness training. This training will be done by the ECO. Topics covered should include: - What is meant by "environment"; - Why the environment needs to be protected and conserved; - How construction activities can impact on the environment; - What can be done to mitigate against such impacts; and ECO / RE / CT - Awareness of emergency spills response provisions. It is the contractors' responsibility to provide the site foreman with no less than 1 hour's environmental training and to ensure that the foreman has sufficient understanding to pass this information onto the construction staff. · Translators are to be used if necessary. · The RE / ECO must be on hand to explain any technical issues and to answer questions. · Construction workers must be made aware that they are not to make excessive noise (shouting, hooting etc.). Worker Conduct on Site: A general regard for the social and ecological well being of the site and adjacent Parsons Brinckerhoff Africa (Pty) Ltd 29 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility areas is expected of the site staff. Workers need to be made aware of the following rules: · No alcohol / drugs to be allowed on site; · No misuse of firearms will be allowed on or near the site; · Prevent excessive / unnecessary noise such as hooting of shouting; RE / ECO/CT · No harvesting of firewood from the site or from areas adjacent to it; · Construction staff is to make use of the facilities provided for them, as apposed to ad hoc alternatives; · Trespassing on private / commercial properties adjoining the site is forbidden; and · Driving under the influence of alcohol is prohibited. Implementation · Throughout the period of construction, restrict activities to within the CT, BPC and designated areas as indicated during the Project Plan phase. ECO. · Have all amendments checked by the ECO. Restrict heavy vehicles from travelling to and from the site during peak traffic CT & BPC. periods. 8.2. Site Clearing / Earthworks / Establishment & Maintenance of Roads and Tracks 8.2.1 Potential Significant Impacts · Potential damage to the soil structure, soil compaction and loss of soil fertility. · Loss of the vegetation cover and increased erosion risks. · Dust related problems. · Safety hazards to the public, workers and animals in the area. · Disruption or destruction of archaeological remains. 8.2.2 Sources of Potential Impacts · Blading takes place when a grader is used for construction earthworks, vegetation clearing, grading platforms, cut and fill activities. The soil surface is skimmed and the vegetation cover, including the root systems of plants, is removed. · Tracks are created when vehicles, equipment, and even pedestrians simply move over an area. Haphazard and off-road driving and people wandering off into the adjacent areas (especially the river area) can easily result in the proliferation of tracks. Parsons Brinckerhoff Africa (Pty) Ltd 30 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.2.3 Objectives · Carefully plan construction activities and transportation of people and equipment with the intention to: Avoid clearing where it is not absolutely called for; Minimise secondary impacts such as dust and erosion; and, Avoid compromising the safety of the public, workers and animals in the area. Ensure that an archaeological inspection has been carried out on cleared areas. 8.2.4 Performance indicators · Minimal erosion evident; · No areas unnecessarily disturbed; · No fines/penalties issued. 8.2.5 Monitoring Programme · Visual assessment supported by photographic records of the site. 8.2.6 Mitigation Measures Mitigation Measure Responsibility Route and Area Clearing Off-road driving and the creation of new tracks, other than those described during Project Layout and Access Plan, are prohibited and will be regarded as CT liable, Drivers, unwanted tracks or unwarranted disturbed areas. All unwanted tracks or All Staff. unwarranted disturbed areas shall be properly rehabilitated (see Section 8.10 and 8.11). Parsons Brinckerhoff Africa (Pty) Ltd 31 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · When a new path is created: - Carefully plan the route and have it clearly marked out so that drivers exactly know where to drive. · Establish the track by simply driving over the ground if there are no obvious obstacles (i.e. large rocks, high plants or rough terrain). · Keep tracks as narrow as possible and only drive on marked out routes (as per the Layout and Access Plan). · No bulldozers will be used in bush clearing outside of the construction footprint. Only inflatable tyre earthmoving equipment must be used to reduce damage to vegetation. · If obstacles are far enough apart, divert the track around obstacles. Only ECO supervise, obstacles that could interfere with the safe construction and operation of the CT, Drivers. development need to be removed. · Where possible, remove obstacles by hand. Shrubs are to be cut or crushed rather than being completely uprooted in areas where landscaping will be undertaken on completion of the project · Leave vegetation in place wherever possible, especially around the perimeter of the site (even if they are exotic) to provide screening and habitat. Indigenous plants can be planted to replace these exotics over time. · Only undertake earthworks in an area if it is unavoidable, and keep the size of platforms (if they are necessary) as small as possible. · Before driving over any area: · Rather keep to existing roads and tracks. ECO supervise, · Carefully examine the area to determine if there are any sensitive sites in Drivers. harms way. Clearly mark, or demarcate with plastic tape, these sites and work around them. · Care must be taken along riverbanks to ensure that the bank vegetation is not disturbed as these areas have a high erosion potential. · Minimise erosion and drainage problems by avoiding tracks crossing contours at right angles, thereby avoiding steep slopes. ECO supervise, · Implement measures to manage storm water runoff from the platform banks Engineers, CT, so that run off and sediment loads are contained and carried in temporary drivers, and all drains. staff. · Put in place measures to avoid erosion at river and stream channel crossings, and at places where existing erosion scars and dongas are encountered to avoid any further erosion at these points. Parsons Brinckerhoff Africa (Pty) Ltd 32 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Clearly mark with paint important trees that may not be disturbed in the RE /CT/ ECO construction footprint area. · Relocate important indigenous plant specimens. · Plan the development around important specimens on the boundaries of the CT, ECO, BPC, site. Incorporate these into open space areas within the development, or engineers, etc. parking areas etc. Appropriate fines/penalties will be set for the disturbance of areas outside of ECO / DEA those agreed to on the project layout plan. Use and Maintenance of Roads and Tracks outside the development area Limit all construction activity as far as possible within the confines of the site CT liable, ECO area. supervise, Drivers, Prohibit vehicles from leaving designated paths and existing tracks. All Staff. Keep all existing and new roads in an acceptable condition: · Repair erosion damage and put in place measures to avoid erosion over the CT long-term. The Contractor shall be responsible for rehabilitation of all unwanted tracks or unwarranted disturbed areas formed by themselves or their staff members, sub- CT contractors or suppliers. The primary aim is to avoid all unnecessary tracks. Address road safety issues: · Make sure all drivers are properly trained and in possession of a valid licence for the specific vehicle. ECO supervise, · No one shall drive when under the influence of alcohol. CT, Drivers. · Vehicles must not be overloaded. · Encourage safe and responsible driving. Adhere to speed limits. Access must be prohibited during rainy, wet and muddy conditions. Access ECO supervise, during these conditions will cause damage and is also dangerous. CT, Drivers. Clearing of / Excavating Areas When an area is cleared: · Minimise the size of the area to be disturbed and adhere to the guidelines for excavation as described above. · Contain all disturbances within the confines of the site area. This includes ECO supervise, all stockpiles, storage of construction material and equipment, excavations CT, Drivers. and parking of construction vehicles. · Cordon off excavating areas with danger tape in order to keep the disturbance within a limited to the area. · Keep to already disturbed areas as far as possible. Parsons Brinckerhoff Africa (Pty) Ltd 33 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · Topsoil must be stripped to a depth of at least 150mm and placed in a separate stockpile to that of the subsoil and bedrock. This will aid CT, Drivers and rehabilitation later on. BPC · Topsoil stockpiles must be kept free from infestation by alien vegetation. · Avoid excavation of areas during high winds. · Areas of indigenous vegetation identified as sensitive may not be disturbed or destroyed. If the vegetation is interfering with construction activities in any way and needs to be lopped or removed then this must be done under CT and BPC, ECO supervision of a qualified indigenous nurseryman. supervise. · The obstructing branches of indigenous trees and bushes and well- established non-invasive exotics will only be trimmed rather than the entire tree, felled. 8.3. Pollution Control 8.3.1 Potential Significant Impacts · The accidental, negligent, or deliberate spillage or inappropriate disposal of hazardous substances could result in air, soil and water pollution and may affect the health and well being of people, plants and animals. · Excessive noise could be made by the construction activity which would affect neighbouring communities. 8.3.2 Sources of Potential Impacts · Substances such as sewage, fuels, lubrication oils, hydraulic and brake fluid, solvents, paints and anti-corrosives, insecticides and pesticides, as well as the by-products and waste associated with use of these products will be present on construction areas. · Typical problem areas on site include, but are not limited to ablution facilities and waste storage. · Raucous workers and machinery (diesel-driven winches from the mobile crane, jackhammers when breaking up the existing buildings and foundations). 8.3.3 Objectives · Minimise the risk of pollution and health impacts. · Prevent polluted water from entering stream channels or underground aquifers. · Minimise the disturbance to surrounding residents. Parsons Brinckerhoff Africa (Pty) Ltd 34 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.3.4 Performance indicators · No significant chemical spills on the site or in the adjacent water courses; · No release of chemicals into the environment; · Good housekeeping prevents refuse or contaminants from entering the water course; · The number of complaints received from the public regarding noise. 8.3.5 Monitoring Programme · A list of all chemicals, paints and cleaning products is to be produced and approved by DEA; · Chemical storage areas will be visually inspected; · Adequacy of bunding will be assessed; · Records of spills will be examined in the environmental incident book; · Staff will be questioned regarding their understanding of chemical management; · Regular visual assessment of all storage containers and areas for capacity, potential for recycling and evidence of spillage etc.; · General housekeeping will be examined to ensure storm water runoff does not contain refuse or contaminants; · An assessment of `excessive' noise will be undertaken by the ECO. 8.3.6 Mitigation Measures Mitigation Measure Responsibility Sanitation Toilets must be provided to prevent staff from urinating or defecating in or near CT, All Staff. any river, stream channel, pan, dam or borehole. Parsons Brinckerhoff Africa (Pty) Ltd 35 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Ablution Facilities: · An adequate number of self-contained chemical toilets must be established at the Contractor's Camp and active working area. Contractors must supply toilet paper at all toilets, and will be responsible for their maintenance and servicing. · The ablution facilities must conform to the requirements stipulated by the DEA and Local Authorities. · Toilets must be placed outside areas susceptible to standing or flowing water and siting must be done in consultation with the ECO. · The ablution facilities must be maintained in a clean and orderly state and are CT / RE / ECO to be regularly cleared to prevent odour and pest problems. · A contingency plan for spills from toilets must be supplied by the Contractor and approved by the ECO. · Contractors must ensure that no spillage occurs when chemical toilets are cleaned and cleared, and that the contents are carefully stored and transported when removing it off-site. All spills must be recorded in the Environmental Incident Record Book. · No pit latrines are to be used. · Performing ablutions outside toilet facilities will be strictly prohibited. Hazardous Substances Ensure that all staff are adequately protected and educated about the safe and CT and BPC proper handling and disposal of hazardous substances. · Keep a register of hazardous substances present on site, and have information pertaining to the management of spills or ingestion available. · The Contractor must compile an inventory of all fuels and hazardous CT and BPC, substances to be used and stored on the site, and must ensure that they ECO supervise. know the effects of these substances on their staff and the environment. · A copy of the fuels and hazardous substance inventory must be supplied to the ECO Use `environmental friendly' chemicals, paints and cleaning products and avoid CT to list. List to persistent, harmful substances. If required, specific control and mitigation be approved by measures are to be developed to ensure no pollution to ground and water ECO and DEA resources. Always use a bunded area when washing, refuelling or doing emergency maintenance work on vehicles, machinery or equipment (i.e. generators) or when CT and BPC, All transferring hazardous substances from one container to another. These activities Staff. are not allowed outside the construction campsite, in the veld or along roads and tracks. No routine maintenance of vehicles is to be conducted on site. Parsons Brinckerhoff Africa (Pty) Ltd 36 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Hazardous substances must be stored in a well-ventilated area, and behind lock CT and BPC and key. · In the event of a hazardous spill, whether accidental, deliberate or through negligence, on site or during transportation of these substances to/from the site: - Immediately implement actions to stop or reduce and contain the spill. - Report the spill to the ECO and arrange implementation of the necessary clean up procedures. CT and BPC, - Collect contaminated soil, water and other materials and dispose of it at an ECO supervise. appropriate site. · Used fuel, oils, hydraulic fluids, paints and solvents and grease will be stored in drums or other suitable containers. These must be labelled, sealed and removed from the site to an appropriate disposal site or recycling facility. · Use the least polluting, most rapidly biodegradable products for cleaning purposes. Concrete Mixing: · Concrete mixing is to take place at a site approved by the ECO. Concrete mixing areas need to be strategically placed so as to service as large an area as possible and compact so that the area of contamination is consolidated. Ad hoc mixing at the active working area should be avoided where possible. · It will be necessary to transfer the concrete from the mixing site to the active working area. The Contractor is to propose methods of transferring the concrete that must be approved by the ECO. RE / ECO / CT · If small volumes of concrete are to be mixed (manually), mixing is to be undertaken on a hard surface covered in plastic sheeting so that concrete waste and runoff can be contained. · If large volumes are generated the following requirements must be met: - Mixing area must be underlain by an impermeable surface that is sufficiently large to trap spills; - Runoff from the concrete mixing area is to be contained and channelled into a wastewater sump. · All concrete waste is to be collected and removed from the site for disposal at an appropriate disposal site. Parsons Brinckerhoff Africa (Pty) Ltd 37 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Contaminated Water and Soils · All soil that is contaminated must be removed and stored in a skip until it can be disposed of at an appropriate disposal site. · All wastewater and polluted runoff from contaminated areas must be channelled into appropriately sized, designed and located collection sumps. · The size, design and location of the polluted runoff capture system must be RE / ECO / CT assessed and approved by the ECO. · The collection sumps must be properly managed and regularly cleared to prevent overflows. · Contaminated water / sediment from the sumps must be disposed of at an appropriate disposal site. Fuel Tanks · All liquid fuels (e.g. diesel and petrol) which are stored in tanks or drums must RE / ECO / CT have a bund wall around the tanks to prevent liquids from escaping in the event of a spill or leak. · The volume of the bund must be 110% of the volume of the storage tanks. · The fuels dispenser must be hung within the bunded area with an impermeable surface, such as heavy gauge plastic sheeting, while not in use. · The tank(s) must be located in an area, which is easily accessible for vehicles. · The Contractor will be responsible for ensuring that any party delivering fuels or other chemicals to the site is aware of the appropriate storage / drop-off locations and the environmental controls that apply. Equipment / Machinery · The Contractor must store all equipment that may leak on an impermeable RE / ECO / CT surface, with watertight drip trays to catch any pollutants. · The drip trays must be cleaned regularly, and must not be allowed to overflow. · Chemicals collected in the drip trays must be collected and disposed of in an appropriate manner (MSDS). Dust Control Parsons Brinckerhoff Africa (Pty) Ltd 38 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · Exposed surfaces must be revegetated as soon as possible. · Excavation, handling and transport of erodible materials must be avoided under high wind conditions or when a visible dust plume is present. · During high wind conditions, dust suppression measures will be required. · Soils must either be covered with a biomatting or revegetated, and stockpiles are to be located in sheltered areas where they will not be exposed to the RE / ECO/CT erosive effects of the wind. · Vehicle speeds must not exceed 30km/h along dust roads or 20km/h when traversing unconsolidated and un-vegetated surfaces. · Appropriate dust suppression measures must be used when dust generation is unavoidable (dampening with water). Noise Pollution Access to the site must be limited to normal working hours (5 day working week, Monday to Friday between the hours of 07h00 and 17h00) ­ exceptions to this All Staff must be communicated to the potentially affected surrounding landowners. It is not permissible to generate unnecessary noise whilst on site e.g. hooting and All Staff shouting. Vehicles and other machinery must be maintained in a good working order and CT, BPC and excessive noise must be controlled. drivers Air Pollution BPC / RE / CT / No burning of refuse will be permitted on the site. ECO 8.4. Waste Management 8.4.1 Potential Significant Impacts · Visual degradation. · Pollution and potential harm to people and animals. 8.4.2 Sources of Potential Impacts · Litter and inappropriately disposed waste. · Waste carried around by the wind or by scavengers. 8.4.3 Objectives Parsons Brinckerhoff Africa (Pty) Ltd 39 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Implement all reasonable measures to prevent inappropriate disposal of waste and to prevent litter from becoming windblown or carried around by scavengers. · Always maintain a clean and tidy site. 8.4.4 Performance indicators No breaches associated with transport, collection, storage and disposal/re-use of solid wastes. 8.4.5 Monitoring Programme · Regular visual assessment of all storage containers and areas for capacity, potential for recycling and evidence of spillage etc.; · General housekeeping will be examined to ensure storm water runoff does not contain refuse or contaminants 8.4.6 Mitigation Measures Mitigation Measure Responsibility Solid Waste · For all waste (general and hazardous), the principle of `what gets taken in shall be taken out' shall apply. No waste shall be buried or burned anywhere in the veld or at the construction campsite. · Arrange for the daily removal of all waste. Verify the final destination and method of disposal or recycling. Keep in mind that the producer of the waste is CT and BPC liable, All ultimately responsible for its proper disposal. Remember that rubbish will attract Staff, ECO supervise. animal pests. · Littering (either at the construction campsite, construction areas, along public roads, or in surrounding areas) shall not be tolerated. · Ensure that the construction campsite, all construction areas and the surroundings are kept in a clean and neat condition at all times and that windblown litter is cleared on a daily basis. Strictly prohibit, and put in place fines/penalties for illegal dumping. CT, BPC, ECO Parsons Brinckerhoff Africa (Pty) Ltd 40 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.5. Protecting the Biophysical Environment 8.5.1 Potential Significant Impacts & Impact 8.5.2 Objectives Sources: Managing Surface Water · Disturbance to local hydrology from · Minimise water use wherever possible. construction activities. · Minimise disturbances to local hydrology. · Pollution of surface water bodies. · Prevent pollution of surface water bodies. Soil Management and Dust Control · Dust can be a nuisance to the construction · Minimise the damage to the fragile surface workforce and to the public and can soil layer through careful planning of negatively affect the growth and recovery rate construction activities. of plants. Potential sources of fugitive dust · Implement measures to preserve topsoil in include, but are not limited to: areas where disturbances occur. - Demolition of concrete foundations and · Implement the best practicable means to existing buildings; prevent dust from becoming so dispersed in - Grading / movement of soil; the atmosphere as to be harmful or cause - Transportation and unloading of nuisance to people, plants and animals. construction materials; - Vehicular movement over unsurfaced roads and tracks; and, - Wind erosion of stockpiles. · Construction activities will result in the exposure of the soil to erosive factors, i.e. wind and water, and the compaction of the soil in other areas; Plants and Animals · Illegal poaching and collection of animals and · Avoid unnecessary damage and destruction plant material. of the vegetation cover. · Loss of established indigenous and exotic · Relocate species wherever possible habitat · Leave exotic species and interplant with · Unnecessary trampling of vegetation and indigenous species harm to animals. · Design the construction planning around the identified sensitive areas · Prevent veld fires. · Avoid poaching and collection of animals and plants material. Landscape Quality Parsons Brinckerhoff Africa (Pty) Ltd 41 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Degradation of the scenic quality due to the · Implement all reasonable measures to major earthworks and any unsightly minimise the visual impacts and keep the structures. area as natural looking as possible. · Ensure that the controlling body issues specifications for buildings on the site which will reduce construction and long term impacts (such as pollution and visual quality). 8.5.3 Performance Indicators · No breaches in surfacing, bunds or water channels; · Erosion avoided or minimized using standard erosion and sediment control techniques; · No compaction as a result of construction activities; · No recorded incidents of unnecessary plant or animal destruction; · No disturbance of sensitive areas; · Planting with indigenous species undertaken; and · The occurrence of uncontrolled veld fires. 8.5.4 Monitoring Programme · Water control bunds, drains, ponds and channels will be checked to ensure they are functioning correctly; · General housekeeping will be examined to ensure stormwater runoff does not contain refuse or contaminants; · Stormwater discharge points will be examined for erosion; · Inspection of all erosion and sediment control devices on a regular basis, particularly after heavy rains; · Inspection of the adjacent river to assess pollution situation; · Inspection of all steep slopes created and rehabilitated areas. 8.5.5 Mitigation Measures Mitigation Measure Responsibility General Adhere to the specifications for route clearing / establishment and maintenance CT and BPC, ECO of roads and tracks (see above). supervise. Throughout the period of construction, restrict activities to within the designated CT and BPC, ECO areas as indicated during the initial Project Layout Plan. supervise. Appropriate fines/penalties will be set for the disturbance of areas outside of ECO / BPC/ CT those agreed to on the layout plan. Parsons Brinckerhoff Africa (Pty) Ltd 42 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Managing Surface Water Discuss water provision for construction purposes. CT and BPC CT, BPC and Do not drive any vehicle through any watercourse or water body. drivers. · Do not impede or deviate the flow of any surface water body. · Do not dispose of any waste into surface water bodies. · Adequate bunding must be designed around the business park to prevent CT and BPC, ECO any spillages contaminating the ground/surface water system. supervise · Do not use any surface water bodies for domestic purposes including bathing, washing and drinking water. · The Contractor may not cause the pollution of any watercourses, whether flowing or not, along the OHTL route. · To control and minimise the washing of soil into watercourses, the Contractor must implement the following: - Appropriate soil management strategies; - Prompt rehabilitation to protect and stabilise exposed soil surfaces. - Follow the requirements for soil stockpiling and management. · To prevent the contamination of water by materials used during construction, the Contractor must ensure the following: - Materials are prepared and stored away from watercourses; - Measures must be implemented to prevent seepage of liquid materials into the ground where it could contaminate groundwater; - Ensure prompt cleaning up of accidental spillages · To prevent the contamination of watercourses by diesel, grease, oil, etc. RE / CT / ECO derived from the camp and working area, the Contractor must ensure that: - The machinery / equipment is maintained in a good operating condition; - Specially designated areas for vehicle maintenance are created; - Accidental spillages are cleaned up promptly. - No servicing of vehicles / machinery / equipment in the field. · No water is to be abstracted from any watercourses for use during the construction phase unless approved by the ECO, provided that an appropriate licence is obtained. · No members of the construction team will be permitted to use any watercourses or water bodies for domestic purposes such as washing or bathing. · The watercourses and water bodies are not to be used for the rinsing and cleaning of construction equipment. This is to be done at the Contractor's Camp in an appropriate work area. Parsons Brinckerhoff Africa (Pty) Ltd 43 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Soil Management / Topsoil / Dust Control · Implement measures to prevent dust from becoming problematic. These measures shall include, but are not limited to: - Restricting excessive vehicular movement. · Limit vehicle speeds on un-surfaced roads and tracks to 30km/h along dust roads and 20km/h along the steep or difficult tracks. · During periods of prolonged use, un-surfaced roads must be dampened if CT and BPC, ECO dust becomes a problem. supervise. · Disturb as small an area as possible. · Vehicles will be kept to a single path, and soils ripped and replanted with indigenous species upon completion of all construction phases. · All construction activity near the rivers will be kept to a minimum, and erosion prevention mechanisms must be employed before the commencement of construction. Soil Stripping: For the purposes of this report, topsoil is considered to be the top 200mm of soil: · All topsoil is to be stripped at the tower sites to a minimum depth of 200mm. RE / ECO Where there is less than 200mm of soil, the maximum available topsoil must be stripped. · At tower sites, topsoil will need to be stripped by hand (either with or without sods). The soil may be stripped mechanically at sites approved by the ECO. Soil Handling: · Soil must not be handled when it is wet as this will result in unnecessary compaction; however this needs to be balanced against the high erosion potential of soils when they are dry. · Repeated handling of soil must be avoided, as it results in compaction and the loss of soil structure. Planning the soil stripping and stockpiling process and allocating formal stockpile areas will minimise the chance of repeated handling. RE / CT / ECO · If the soil stockpiles are to remain unused for more than two months they will need to be vegetated with a suitable grass / legume mix. · Soil must not be handled during windy conditions to minimise soil loss through wind erosion. · In order to minimise the risk of spillage and loss through wind erosion, trucks transporting soil must not be overloaded when conveying soil to, from and around the site. · Soils being transported long distances must be covered with a tarpaulin. Parsons Brinckerhoff Africa (Pty) Ltd 44 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility Soil Stockpiling and Management: General Guidelines · All stripped soil (topsoil and subsoil) is to be stockpiled so that it can be used in the rehabilitation process. · Soil that is to be stockpiled for an extended period must be stored: - At a sheltered site where it will not be exposed to the effects of wind RE / CT / ECO to erosion; supervise - Outside the working area where it will not be disturbed or contaminated; - Away from drainage lines so as to avoid the risk of erosion; - Away from areas of valuable indigenous vegetation. · Topsoil (top 200 mm) is not to be mixed with subsoil. · Soil is not to be stockpiled against tree trunks, as this will encourage ant infestations. · Topsoil is not to be used as a bedding material. Location of Soil Stockpiles · Stockpiles must not be situated such that they obstruct natural waterways and drainage lines. · Soil stripped from the tower sites will be placed upslope of the excavated hole (if possible) to prevent erosion. RE / CT / ECO to · Topsoil and subsoil stockpiles will need to be contained to prevent mixing. supervise · The stockpiling period is not to exceed 3 weeks. · Soil is to be stockpiled in small manageable piles not exceeding 2 m in height. Stockpile Maintenance · Stockpiles are to be protected from wind and water erosion: · Short-term stockpiling (less than 3 weeks) erosion control measures will not need to be implemented; however, limitations on the area to be cleared will apply. · Medium-term stockpiling (more than 3 weeks), stockpiles must be covered with biomatting. · Long-term stockpiling (more than 2 months), stockpiles must be RE / CT / ECO to revegetated by hydroseeding or sowing with an appropriate grass / legume supervise mix. · The colonisation of stockpiles by invasive plants must be controlled by removing the plants when they germinate. The purpose of this is to reduce the risk of developing a seedbank of invasive species within the stockpiled soil. Plants and Animals Parsons Brinckerhoff Africa (Pty) Ltd 45 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility With regards to sensitive sites strictly enforce the following mitigation measures: · Get to know which sites are sensitive and mark or demarcate these with plastic tape to increase their visibility, thus helping to prevent accidental destruction and avoid unnecessary damage. CT and BPC, ECO · Prevent people from going to, or driving over, these areas. supervise. · Where they cannot be avoided altogether, minimise impacts by removing as little vegetation as possible. · Avoid clearing of sensitive areas. Remove vegetation by hand. Feather-back the vegetation and avoid removal of large tracts of vegetation. Identify areas identified as `sensitive sites' on the Project Layout Plan for ECO and PB comment and review by DEA. · The following must be done to ensure the protection of the vegetation: - Indigenous trees along the OHTL route are to be protected and painted with `anti-muthi' paint (e.g. brown coloured PVA). - Steps must be taken to ensure that the poaching of fauna or removal of flora does not occur, and the following steps must be implemented: - All staff members are required to attend the environmental awareness meeting; - Employees will be subject to fines, should they be caught poaching fauna or removing flora from the site or immediate surrounds. - No member of the construction team may harvest, damage or remove plants, especially those in designated `out of bounds' areas. - Confine the disturbance to a narrow, clearly defined corridor. - Use only plant species endemic to the site for rehabilitation purposes in RE / CT and ECO order to recreate animal habitats, as they were pre-construction (using other species will alter the habitat, especially for birds, and render it unsuitable). - Revegetate the disturbed area as quickly as possible. - The Client is to ensure that follow-up work / monitoring is scheduled over a suitable time period (at least six months) to ensure that the planted vegetation establishes itself, that the natural re-colonisation by indigenous, pioneer plants is successful and that alien plants are controlled. - Before construction proceeds in any section, the ECO is to assess the proposed OHTL route to determine the presence of nesting or refuge sites. Should any such sites be found, an appropriately qualified person is to be appointed to determine the best course of action. Parsons Brinckerhoff Africa (Pty) Ltd 46 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · Strictly prohibit, and put in place penalties for: - Collection, picking, removing, unearthing, cutting, chopping down, or wilful damage to any plant or dry plant material outside of the areas demarcated for clearing. - Feeding, teasing, playing with, attempting to tame, catching, hunting, shooting, or setting devices to trap or kill any wild or domesticated CT and BPC, ECO animal. supervise. - Disturbing / destroying any animal habitats e.g. bird nests and animal burrows. - Going to, driving over, or wilful damage to any area that is barricaded, cordoned off or marked as a sensitive site (including the river and its floodplain). The occurrence of alien invasive plants throughout the property must be Maintenance and documented and reported and steps taken to eliminate these plants during inspection staff. construction. Non-invasive exotics can be retained and phased out over a five year period by CT and BPC, ECO replanting with indigenous alternatives. This will reduce the risk of erosion and supervise. act as a sound and visual buffer during construction. Implement measures to minimise the risk of veld fires. · No fires will be allowed in the veld or anywhere on the property. · Prohibit smoking near any flammable substance. Instruct staff members to CT and BPC, ECO put out cigarette butts before throwing them into a waste container. supervise. · Have sufficient fire fighting equipment available. Landscape and Aesthetic Quality · Pay attention to the appearance of the any temporary fencing and buildings. BPC / ECO · Ensure that that any signage is visible but not visually intrusive. supervise. Adhere to waste management guidelines. Ensure good `housekeeping' on site Building CT, BPC/ and control litter and general site cleanliness. ECO supervise. Annotate the Project Layout and Access Plan to indicate the proposed location of vegetation nodes and corridors suitable for Red Data species habitat outside PB to compile of the construction footprint. The use of muted, non-reflective colours on all painted surfaces will be encouraged. BPC / ECO Discuss the layout of the site with the environmental team to ensure the design supervise. is optimal. Parsons Brinckerhoff Africa (Pty) Ltd 47 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.6. Protecting Heritage Sites and Artefacts 8.6.1 Potential Significant Impacts · Damage or loss of important cultural, historical or pre-historical sites and artefacts. 8.6.2 Sources of Potential Impacts Impacts to heritage sites and artefacts may occur because of: · Earthworks; · Positioning of buildings; · People tampering with, or removal of, potential heritage sites and artefacts. 8.6.3 Objectives · No heritage objects may be moved without a permit from the National Museum, Botswana and any permitted removal of heritage objects must be done under the supervision of a qualified specialist. The National Museum should be notified of any additional archaeological finds. 8.6.4 Performance Indicators · Implement all reasonable measures to avoid disturbance or loss of important heritage sites and artefacts, those recorded during the archaeological survey as well as any new sites found during construction ­ especially to stone walls, graves and other `heaps of stones' throughout the area. 8.6.5 Mitigation Measures Mitigation Measure Responsibility Unrecorded Heritage Sites and Artifacts · Be aware of the possibility that currently unrecorded heritage sites and artefacts may be found during construction. · Adhere to the specifications for route clearing / excavation / establishment CT, All Staff, ECO and maintenance of roads and tracks. supervise. · Treat any `heap of stones', dry-stone walling or other suspicious stone structure as if it may be a grave or other important heritage feature ­ and strictly leave them alone. Parsons Brinckerhoff Africa (Pty) Ltd 48 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility When a possible heritage site or artefact are found: - Immediately report the find to the Archaeological specialist and/or National Museum; - Carefully work around the site to avoid damage; CT, All Staff, ECO - Do not remove any object from the site; supervise. - Document the nature and location of the site; · If damage to the site cannot be avoided, report the discovery to the National Museum, Botswana or an Archaeological Specialist to obtain their advice, and do not damage or destroy the site without their permission. Strictly prohibit, and put in place penalties for: - Wilful damage, removal or collection of any stone structure or wall, heap CT, ECO of stones, grave, clay shard, stone tools, beads, shells, or any other supervise. heritage site or artefact. 8.7. Infrastructure / Development 8.7.1 Potential Significant Impacts and Impact Sources · Damage to existing roads and tracks, power lines, pipelines, etc. · Dangerous conditions near road. · Trespassing and illegal access onto land. 8.7.2 Objectives · Impacts to heritage sites and artefacts may occur because of: · Minimise impacts on developments and infrastructure in the area. · Implement measures to avoid safety hazards near roads, pipelines and other infrastructure. · Prevent trespassing onto land. 8.7.3 Performance Indicators · Recurrence of incidents prevented; · Incident reported internally and to the relevant authority; · Incident documented; · Appropriate action taken. Parsons Brinckerhoff Africa (Pty) Ltd 49 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.7.4 Monitoring Programme · Incident reports will be checked to ensure that there was appropriate follow up; · Where necessary, relevant environmental monitoring will be conducted to determine impacts. 8.7.5 Mitigation Measures Mitigation Measure Responsibility CT and BPC, Consult with the relevant authorities, and adhere to safety standards near Official Project roads, pipelines and other infrastructure. The relevant authorities must approve Surveyor, ECO any relaxation of safety standards. supervise. Avoid unnecessary damage to infrastructures such as roads, telephone lines, CT and BPC, ECO dwellings and fence lines. Repair damage, reinstate, relocate or replace supervise. infrastructure as required. 8.8. Socio ­ Economic Environment 8.6.1 Potential Significant Impacts and Sources of Impacts · Visual impact of powerline and construction activities on sensitive receptors. · Introduction of migrant workers. · Damage to private properties through which the power line traverses. · Sanitation 8.6.2 Objectives · Limit impact on affected and surrounding landowners. 8.6.4 Performance Indicators · Implement all reasonable measures to avoid disturbance to affected and surrounding landowners as detailed in section 8.6.5 below. All incidents that occur must be recorded within the incidents register kept on site. Achievements of objectives will be measured by number of complaints received or incidents logged. Parsons Brinckerhoff Africa (Pty) Ltd 50 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.6.5 Mitigation Measures Mitigation Measures Responsibility Socio-Economic Environment Visual Aspect · Any areas that are disturbed by the construction or dismantling of towers ECO will need to be rehabilitated as soon as possible after the completion of construction so as to conceal the linear scar created during construction. Employment · The Contractor is to employ local labour (both male and female, skilled and RE unskilled) as a priority especially for labour intensive tasks such as hand stripping of soil, removal or sods, planting, etc. · Workers are to be made aware that employment is only temporary and will cease at the end of the Contract period. Where possible, employment of local persons must be used for capacity building and the imparting of new skills. Damage to Property and Structures · Damage to houses, structures, fences, crops and grazing land on private property must be avoided as far as possible. · Should damage to the aforementioned occur, the Contractor will be responsible for repairing the damage caused or compensating the property owner accordingly. RE / ECO · Any fencing removed to enable construction to proceed must be replaced on completion of work in that area. · The Contractor will be responsible for providing an alternative fenced off area (e.g. for keeping of livestock) if required by the property owner. Sanitation · The contractor shall install mobile chemical toilets and ensure staff are sensitised to the fact that these toilets shall be used at all times during the CT construction period Communication with Interested and Affected Parties (I&AP's): · The RE and Contractor are responsible for ongoing communication with those people that are interested in or affected by the project. · A complaints register is to be housed at the site office. This must be in carbon copy format, with numbered pages. The Contractor must account for any missing pages. This register is to be tabled during monthly site meetings. · I&AP's need to be made aware of the existence of the complaints register and the methods of communication available to them. Parsons Brinckerhoff Africa (Pty) Ltd 51 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation · Queries and complaints are to be handled by: RE / ECO - Documenting details of such communications; - Submitting these for inclusion into the complaints register; - Bringing issues to the immediate attention of the RE; and - Taking remedial action as per the RE and / or ECO's instructions. · Selected staff are to be made available for formal consultation with I&AP's in order to: - Explain the construction process; and - To answer any questions. 8.9. Rehabilitation 8.10.1 Potential Impacts and Impact Sources · Permanent scarring of the landscape if tracks or disturbed areas are not repaired, and if the construction campsite is not properly reinstated. · Inadequate rehabilitation due to insufficient budget allocations. · Destruction of indigenous vegetation by the colonisation of alien exotic species. 8.10.2 Objectives · Make sure there are sufficient budget allocations for environmental rehabilitation. · Rehabilitate unwanted tracks or unwarranted disturbed areas as best as possible. · Remove potential `eyesores' and leave the construction campsite and entire construction area in a neat and safe condition (before final hand-over of the site). 8.10.3 Principle · Rehabilitation will be done as soon as possible after completion of construction activities in any one area. 8.10.4 Performance Indicators · Adequate soil available for rehabilitation; · The increase in occurrence, density and diversity of exotic by indigenous species; · A reduction in the incidence and spread of alien invasive species; · Leaving of a clean and tidy site at the end of construction. Parsons Brinckerhoff Africa (Pty) Ltd 52 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 8.10.5 Monitoring Programme · Inspection of all rehabilitated areas. 8.10.6 Mitigation Measures Mitigation Measure Responsibility Tender Process This EMP is to form part of the tender document. BPC With the awarding of the tender, the Contractor is to be informed of any intention to impose fines/penalties for transgressions to the contents of this EMP so that the Contractor is able to assess the impact that the associated BPC & CT. restrictions might have on his normal way of working and justify additional costs, where necessary. The Contractor may not be geared up to carry out some of the rehabilitation activities which are specified during the construction phase, i.e. spreading of stockpiled topsoil, the replanting of vegetation, seeding, watering and invasive plant control. These activities will have to be done by a firm of specialists, ideally appointed and managed by an independent consultant. Nevertheless, there must be sufficient budget allocations for environmental compliance. The following list is presented as a sample of potential cost items. It is not exhaustive. · Staff training; · Stormwater control facilities; · Alien plant control; BPC, CT, ECO and · Relocation of plants; DEA · Working around sensitive areas; · Revegetation; · Pollution control facilities; · Waste control and recycling; · Dust suppression; · Use of `environmental friendly' chemicals/cleaning products; · General Housekeeping; · Undertake noisy activities during the day; · Demarcation of the working area; and · Restriction of speed of vehicles on unsurfaced roads Throughout the Construction Phase Parsons Brinckerhoff Africa (Pty) Ltd 53 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility In consultation with the ECO, identify all areas requiring rehabilitation, including unwanted tracks, unwarranted disturbed areas and areas of excessive alien invasive plant infestation and develop the best practical rehabilitation measures for the specific areas in question. Measures include, but are not limited to: · Hand-raking the ground in sandy areas to remove tracks or scars. Rehab. CT and · Ripping of compacted soils and breaking up the clods to ensure proper BPC, ECO advise. drainage and water infiltration. · Tilling the topsoil layer to establish a smooth surface. · Sweeping or dragging a heavy cloth over an area. · Scattering pebbles and rocks over an area to make it blend in with the surroundings. · Topsoil (containing the valuable seedbed) that has been stockpiled for excavation of tower foundations will be spread over the subsoil and bedrock in areas requiring rehabilitation for the facilitation of vegetation establishment. Rehab. CT, ECO to · Where compaction by vehicular or construction activity has occurred, soils advise. will be ripped immediately following completion of construction and rehabilitated by planting, hydroseeding, or both. · Vegetation will also be planted in clumps in order to resemble the natural vegetation as much as possible. · Water the revegetated areas thoroughly after seeding/planting and for the first dry season, in particular. · Ensure that when final rehabilitation is complete, all invasive plants have Rehab. CT, ECO to been removed and destroyed. advise. · Appoint a responsible community member (who is familiar with the procedures) to continue with the invasive plant control programme. · Instigate an alien replacement programme on the site (and monitor). · Inform and educate residents and contract staff as to the correct procedures for encouraging the growth of indigenous vegetation, the removal of exotic Rehab. CT, ECO, vegetation and the prevention of its spread. DEA to advise. · Monitor the success of rehabilitation measures and revise the measures if they were proved to be unsuccessful. Before Closure Parsons Brinckerhoff Africa (Pty) Ltd 54 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation Mitigation Measure Responsibility · Remove all construction equipment, surplus materials and temporary structures, fences and works of every kind. · Clear windblown litter and other waste from surrounding areas. · Remove all remaining waste to a recognised dump All CTs and BPC. · Repair damage to roads, fence lines, telephone lines, etc. caused by construction. · Ensure there are no bare areas. Platforms must be grassed if they are not to be developed immediately. 8.10. Post Construction Activities Site rehabilitation is an essential component of this EMP and must be carried out in conjunction with the ECO. The guideline is to be used as the basic structure for the site rehabilitation; the specific details must be decided by the Rehabilitation Contractor in conjunction with the ECO. This applies most specifically to the soil replacement, amelioration and revegetation components. · The requirements for the control of soil, water, dust and noise pollution stipulated in this EMP still apply during the site rehabilitation phase of the project. · Similarly, the requirements for soil management, erosion control, alien vegetation removal and vegetation and fauna protection also apply. · Livestock must be kept away from the rehabilitated areas for a sufficient period to allow the plants to become sufficiently well established before being exposed to trampling or grazing. Activity Monitor Rehabilitation Infrastructure · Disassemble all infrastructure units and remove components from the working areas and Contractors Camp. This will include storage structures and containers, water storage containers, power supply, etc. · Drain all portable chemical toilets, being careful not to spill the contents. Transfer the contents to an appropriate disposal site. · Drain all wastewater and sewage associated with the temporary ablution facilities and transfer the waste to an appropriate disposal site. RE / ECO · Disassemble all fencing around the camp and either sell, auction or donate the components to the local community or transfer the waste components to a disposal site or the Contractors base. · Do not leave any components, waste or infrastructure units within the working area and camp unless specifically required for the operational and Parsons Brinckerhoff Africa (Pty) Ltd 55 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation maintenance phases and as agreed by the ECO. Contaminated Substrates and Pollution Control Structures · Excavate all areas of contaminated substrate, transfer the contaminated substrate to an appropriate disposal site and treat the affected areas with appropriate ameliorants. · Remove all plastic linings used for pollution control and transfer to an RE / ECO appropriate disposal site. · Break up all concrete structures that have been created (e.g. working and parking surfaces) and remove concrete waste to an appropriate disposal site. Waste · Remove all remaining construction materials from the camp and working areas and either sell, auction, donate to the local community or transfer to the Contractor's base. RE · Remove all construction debris, litter and domestic waste from the camp and working areas and transfer to an appropriate disposal site. Remove all waste receptacles from the camp and working area either donate to the local community, auction, or transfer to Contractor's base. · Do not burn or bury any waste at the Contractors Camp or in the working area ­ all waste is to be transferred to a permitted disposal site. Collection Sumps · Drain all collection sumps and dispose of the contaminated liquid and solids at an appropriate disposal site. · Remove the tanks or plastic linings or similar and transfer to a permitted site RE / ECO for disposal. Access Routes · For those roads that are to remain in place, the Contractor is to ensure that the parallel and side drains are in a satisfactory condition on completion of the construction phase and that the roads are rehabilitated to their former state. · For those roads and other hardened surfaces that are to be decommissioned the following is required: - Rip the compacted surface using a disc harrow or mechanical plough; RE / ECO - Fill any cuts with spoil and subsoil (where applicable); - Replace topsoil; - Peg biomatting onto those areas where backfilled / capped surfaces are steep (Identified by ECO); - Plant or seed with a suitable rehabilitation plant species mix. Revegetation · It is important that the revegetation activities be planned in advance to ensure that seed and plant stockists are able to supply the required volume when Parsons Brinckerhoff Africa (Pty) Ltd 56 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation required. · All revegetated areas will need to be watered to ensure plant growth and development. The volume and frequency of watering will be left to the CT / RE / ECO discretion of the Rehabilitation Contractor and ECO. · All areas within the camp or along / adjacent to the OHTL route, where soil has been stripped, disturbed and replaced will need to be revegetated. · This may include: - Contractor's Camp; - Additional infrastructure; - Access routes; - Other area disturbed during the construction phase. Parsons Brinckerhoff Africa (Pty) Ltd 57 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation 9. CONCLUSION Due to the power line servitude traversing agricultural land, grazing land and several drainage lines, the dismantling and construction of towers and associated stringing of conductors has the potential to cause significant impacts on both the biophysical and socio-economic environment in the area. If the above-mentioned management recommendations are adopted, however, it is anticipated that most of the negative environmental impacts of dismantling and construction can be prevented or at least minimised. An appointed Environmental Control Officer (ECO) will monitor the site throughout construction to ensure that the required environmental controls are in place and are functioning effectively. Parsons Brinckerhoff Africa (Pty) Ltd 58 ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation APPENDIX A Parsons Brinckerhoff Africa (Pty) Ltd 20000 40000 60000 80000 TITLE 0000242- 27°15'0"E 27°30'0"E 27°45'0"E !(Mmadinare 0000242- ARMS SITES Damochojenaa !( Serule PROJECT !( 400kV Transmission Line Morupule-B PS - Phokoje SS Phokoje ! ! SS ! ! ! !10 . LEGEND: ! S"0'0°22 ! .8 ! ! !9 . ARMS Site ! S"0'0°22 ! . ! Proposed Transmission Line ! ! ! ! !( Settlement ! ! Railroad 0000442- Moreomabele ! !( Road ! ! Drainage Line ! 0000442- ! ! ! ! ! ! ! ! ! ! ! Topisi ! !( ! ! !6 .! ! !! .5 ! ! ! ! ! ! ! 0000642- ! ! S"0'51°22 ! 00006 ! ! ! Maope ! S"0'51°22 42- !( ! ! ! ! ! ! ! ! ! ! ! ! ! NOTE: ! !! .7 Thangwane Diloro ! !( !( !! .4 ARMS =Archaeological Resources Management Services ! Identified Site ! ! ! Kgagodi !( ! !( ! Mogapinyana ! ! SCALE 0000842- ¹ ! ! Tamasane ! !( 0000842- DATUM: WGS84 PROJECTION: Transverse Mecator MERIDIAN: 27.000000 ! ! .3 Dikabeya DATE: 23-04-2009 ! ! .2 !( ! 1:300,000 ! ! 1 centimeter = 3,000 meters ! ! 0 2.5 5 10 15 20 ! S"0'03°22 ! ! ! ! ! ! S"0'03°22 Kilometres ! Morupule-B !1 . ! SS! ! (Proposed) Palapye Moremi PARSONS BRINCKERHOFF AFRICA (PTY) LTD. !( !( Block 12 Burnside Island P.O. Box 41927 Lesenepole 410 Jan Smuts Avenue Craighall, 2024 !( Johannesburg Republic of South Africa 0000052- Maunatlala 2196 !( 0000052- Republic of South Africa Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°15'0"E 27°30'0"E 27°45'0"E www.pbworld.com/ea 20000 40000 60000 80000 Copyright Parsons Brinckerhoff 20000 40000 60000 80000 TITLE 0000242- 27°15'0"E 27°30'0"E 27°45'0"E ARMS SITES E E E E Rank 2 & 3 Sites !(Mmadinare 0000242- Damochojenaa (Require test excavation prior to development) !( Serule PROJECT !( 400kV Transmission Line Morupule-B PS - Phokoje SS Phokoje ! ! SS ! ! ! ! .10 LEGEND: ! S"0'0°22 ! .8 ! ! ! .9 ARMS Site ! S"0'0°22 ! . Proposed Transmission Line ! ! ! ! Settlement ! !( ! ! Railroad 0000442- Moreomabele ! !( ! E E E Road ! E ! 0000442- ! Drainage Line ! ! ! ! ! ! ! ! ! ! Topisi ! !( ! ! ! ! ! ! ! ! ! ! ! ! 0000642- ! ! S"0'51°22 E E ! E E 00006 ! ! ! Maope ! S"0'51°22 42- !( ! ! ! ! ! ! ! ! ! ! ! ! ! NOTE: ! !! .7 Thangwane Diloro ! !( !( ! ARMS =Archaeological Resources Management Services ! Identified Site ! ! ! Kgagodi !( ! !( ! Mogapinyana ! ! SCALE 0000842- ¹ ! ! E E PROJECTION: Transverse Mecator Tamasane E E ! !( 0000842- DATUM: WGS84 MERIDIAN: 27.000000 ! Dikabeya DATE: 23-04-2009 ! !( ! 1:300,000 ! ! 1 centimeter = 3,000 meters ! ! 0 2 4 8 12 16 ! S"0'03°22 ! ! ! ! ! ! S"0'03°22 Kilometres ! Morupule-B ! SS! ! (Proposed) Palapye Moremi PARSONS BRINCKERHOFF AFRICA (PTY) LTD. !( !( Block 12 Burnside Island P.O. Box 41927 Lesenepole 410 Jan Smuts Avenue Craighall, 2024 !( Johannesburg Republic of South Africa 0000052- Maunatlala 2196 !( E E E E 0000052- Republic of South Africa Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°15'0"E 27°30'0"E 27°45'0"E www.pbworld.com/ea 20000 40000 60000 80000 Copyright Parsons Brinckerhoff 0 20000 40000 60000 80000 TITLE 27°0'0"E 27°15'0"E 27°30'0"E 27°45'0"E NSCP SITES 0000242- Mmadinare !( 0000242- PROJECT 400kV Transmission Line Damochojenaa !( Morupule-B PS - Phokoje SS Serule !( LEGEND: Phokoje ! Selebi-Phikwe ! SS ! !( A77 ! $1 NSCP Site ! $ 1 S"0'0°22 ! !Proposed Transmission Line ! ! !( Settlement ! S"0'0°22 ! ! Railroad ! A68 ! Road 0000442- Moreomabele $ 1 ! !( ! ! ! 0000442- Drainage Line ! A67 ! $ 1! ! ! ! ! ! ! Topisi ! !( ! A69 ! A69_2 $ 1 ! ! ! ! Pressure Tank 3 ! A78 220kV! Site $ 1 $ 1 ! ! 0000642- ! ! S"0'51°22 ! ! ! Maope ! S"0'51°22 0000642- !( ! ! ! ! ! ! ! ! Mogapi ! !( ! ! ! ! Thangwane Diloro ! !( !( ! ! ! NOTE: ! Kgagodi ! !( !( ! Mogapinyana ! ARMS =Archaeological Resources Management Services ! 0000842- ! ! Tamasane !( ! 0000842- Identified Site Dikabeya SCALE ! !( ¹ ! DATUM: WGS84 PROJECTION: Transverse Mecator ! MERIDIAN: 27 Degrees East ! ! DATE: Day/Month/Year ! S"0'03°22 ! ! ! 1:350,000 ! ! ! Morupule-B S"0'03°22 1 centimeter = 3,500 meters ! ! SS ! (Proposed) 0 2.5 5 10 15 20 Palapye Moremi Kilometres !( !( Lesenepole !( 0000052- Maunatlala !( 0000052- PARSONS BRINCKERHOFF AFRICA (PTY) LTD. Block 12 Burnside Island P.O. Box 41927 Malaka !( Mokokwana 410 Jan Smuts Avenue Craighall, 2024 !( Mosweu Seolwane Johannesburg Republic of South Africa Letsheng !( !( 2196 !( Republic of South Africa Moeng !( Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°0'0"E 27°15'0"E 27°30'0"E 27°45'0"E www.pbworld.com/ea 0 20000 40000 60000 80000 Copyright Parsons Brinckerhoff S"04'02°22 31100 31200 31300 27°18'10"E 27°18'15"E S"04'02°22 TITLE ARMS SITE 7 PROJECT 400kV Transmission Line 0002742- E E E 0002742- Morupule-B PS - Phokoje SS LEGEND: ! . ARMS Site Existing 200kV Transmission Line Proposed Transmission Line ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! 0012742- ! E E ! ! E ! 0012742- ! ! ! ! ! ! ! ! ! S"54'02°22 ! ! .7 ! ! ! ! ! S"54'02°22 ! ! ! ! ! ! ! NOTE: ! ! ! ! ARMS =Archaeological Resources Management Services ! ! Identified Site ! ! ! ! ! ! SCALE ¹ ! ! DATUM: WGS84 ! PROJECTION: Transverse Mecator ! MERIDIAN: 27.000000 ! ! ! DATE: 23-04-2009 ! ! ! 1:1,000 ! ! ! 1 centimeter = 10 meters ! ! 0022742- ! 40 60 80 ! ! E E E Metres ! ! 0022742- 0 10 20 ! ! ! ! ! PARSONS BRINCKERHOFF AFRICA (PTY) LTD. Block 12 Burnside Island P.O. Box 41927 410 Jan Smuts Avenue Craighall, 2024 Johannesburg Republic of South Africa 2196 Republic of South Africa Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°18'10"E 27°18'15"E www.pbworld.com/ea 31100 31200 31300 Copyright Parsons Brinckerhoff 76900 77000 77100 TITLE 27°44'40"E 27°44'45"E ! ARMS SITE 8 ! ! ! ! ! PROJECT ! 400kV Transmission Line ! Morupule-B PS - Phokoje SS ! ! ! ! ! ! LEGEND: ! ! ! . ARMS Site ! ! Existing 220kV Line ! Proposed Transmission Line ! ! ! ! ! ! ! ! ! ! ! ! 0042342- ! ! ! 0042342- ! ! ! ! ! ! ! ! ! ! ! ! ! ! S"01'95°12 ! ! ! ! S"01'95°12 ! !8 . ! ! ! ! ! ! ! ! ! NOTE: ! ! ! ARMS =Archaeological Resources Management Services ! 0052342- Identified Site ! ! ! 0052342- ! SCALE ¹ ! DATUM: WGS84 ! PROJECTION: Transverse Mecator ! MERIDIAN: 27.000000 ! ! DATE: 23-04-2009 ! 1:1,000 ! ! ! 1 centimeter = 10 meters ! 0 5 10 20 30 40 ! ! Metres ! ! ! ! ! ! ! ! PARSONS BRINCKERHOFF AFRICA (PTY) LTD. ! Block 12 Burnside Island P.O. Box 41927 ! 410 Jan Smuts Avenue Craighall, 2024 ! Johannesburg Republic of South Africa ! 2196 ! Republic of South Africa ! ! Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 ! Email: pbafrica@pbworld.com 27°44'40"E 27°44'45"E www.pbworld.com/ea 76900 77000 77100 Copyright Parsons Brinckerhoff 75900 76000 76100 TITLE 27°44'5"E 27°44'10"E ! ARMS SITE 9 ! ! ! ! ! PROJECT ! 400kV Transmission Line ! Morupule-B PS - Phokoje SS ! ! ! ! ! ! LEGEND: ! ! ! ARMS Site ! . ! Existing 220kV Line ! Proposed Transmission Line ! ! ! ! 0083342- ! ! ! 0083342- ! ! ! ! ! ! ! ! S"55'95°12 ! ! ! ! ! S"55'95°12 ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! .9 ! ! ! ! ! ! ! ! ! 0093342- ! ! ! ! 0093342- ! ! ! NOTE: ! ! ARMS =Archaeological Resources Management Services ! ! Identified Site ! ! ! ! SCALE ¹ ! ! DATUM: WGS84 ! PROJECTION: Transverse Mecator ! MERIDIAN: 27.000000 ! ! DATE: 23-04-2009 ! ! ! 1:1,000 ! 1 centimeter = 10 meters ! 0 5 10 20 30 40 Metres S"0'0°22 S"0'0°22 PARSONS BRINCKERHOFF AFRICA (PTY) LTD. Block 12 Burnside Island P.O. Box 41927 410 Jan Smuts Avenue Craighall, 2024 0004342- 0004342- Johannesburg Republic of South Africa 2196 Republic of South Africa Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°44'5"E 27°44'10"E www.pbworld.com/ea 75900 76000 76100 Copyright Parsons Brinckerhoff 77400 77500 77600 77700 77800 TITLE 27°45'0"E 27°45'5"E 27°45'10"E S"04'85°12 ! ARMS SITE 10 ! ! ! S"04'85°12 ! ! PROJECT ! 400kV Transmission Line ! Morupule-B PS - Phokoje SS ! ! ! ! ! ! LEGEND: ! ! ARMS Site 0061342- ! ! ! Existing 220kV Line ! 0061342- . Proposed Transmission Line ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! S"54'85°12 ! ! ! ! ! S"54'85°12 0071342- ! ! ! 0071342- ! ! ! ! ! ! ! ! ! .10 ! ! ! ! ! ! ! ! ! ! NOTE: ! ! 0081342- ARMS =Archaeological Resources Management Services ! Identified Site ! ! 0081342- ! ! SCALE ¹ ! DATUM: WGS84 ! PROJECTION: Transverse Mecator ! MERIDIAN: 27.000000 S"05'85°12 ! ! ! ! 1:1,500 ! S"05'85°12 DATE: 23-04-2009 ! 1 centimeter = 15 meters ! ! 0 12.5 25 50 75 100 ! Metres ! ! ! ! ! ! 0091342- ! ! ! ! 0091342- PARSONS BRINCKERHOFF AFRICA (PTY) LTD. Block 12 Burnside Island P.O. Box 41927 ! 410 Jan Smuts Avenue Craighall, 2024 ! Johannesburg Republic of South Africa 2196 Republic of South Africa Tel: +27 (0)11 787 4141 Fax: +27 (0)11 886 0359 Email: pbafrica@pbworld.com 27°45'0"E 27°45'5"E 27°45'10"E www.pbworld.com/ea 77400 77500 77600 77700 77800 Copyright Parsons Brinckerhoff ENVIRONMENTAL MANAGEMENT PLAN 400 kV Line Morupule B Power Station - Phokoje Substation APPENDIX B Parsons Brinckerhoff Africa (Pty) Ltd · BOTSWANA national museum D"panm,,"u of National Munum, Monum"n" and An Gallery 331 Independence Avenue Gaborone, Botswana Private Bag 00 I 14 enq +2673974616 +26736 10400 18 November 2008 fu +267 3902797 email Illiltional.muscum@gov.bw www n:l.!ional-museum.gov.bw To: AR.M.S POBox 601271 Our r(for~"u: Gaborone NlII6/3/1/ 1II (157) RE: CONDiTIONAL PERMiT: PROPOSED 400KY POWER LINE: MORl1PULE- PHOKOTE STATION . A conditional permit is given to Botswana Power Corporation for the above- proposed development in Central District. This pennit can only be valid if the following are adhered to: I. An induction course is performed for the constructors. 2. Archaeological inspection done after bush clearing. 3. Monitoring is done during construction of the power line more especially in areas where there were archaeological remains. 4. Test excavation is done for the sites ranked 2-3 prior to any development. 5. Where possible the site on the foothill (site 10) is preserved at all costs. 6. In case of chance finds, the Department of National Museum IS informed. \Ve advice that, the developer here being Botswana Power Corporation, observe and commit themselves to the above recommendations. Thank you ~ O. Ntebang