The World Bank Implementation Status & Results Report Integrated Transport (P102368) Integrated Transport (P102368) AFRICA EAST | Botswana | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2009 | Seq No: 25 | ARCHIVED on 28-Jun-2021 | ISR47035 | Implementing Agencies: Ministry of Finance and Economic Development, Ministry of Transport and Communications Key Dates Key Project Dates Bank Approval Date: 28-May-2009 Effectiveness Date: 17-May-2010 Planned Mid Term Review Date: 22-Aug-2016 Actual Mid-Term Review Date: 29-Aug-2016 Original Closing Date: 31-Jan-2020 Revised Closing Date: 31-Dec-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The primary development objective of the project is to enhance the efficiency of the transport system by building modern businessmanagement capacity and improving the strategic planning aspects of inter-regional and critical transport infrastructure. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A: Capacity Building, Institutional Strengthening and Training:(Cost $8.50 M) Component B: Road Sector Investment:(Cost $236.80 M) Component C: Urban Roads Infrastructure Investment:(Cost $81.40 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Overall Progress: The project has continued at slow pace since the last mission in the two key components namely OPRC works and urban infrastructure improvement. The project needs to increase the pace to complete all activities before the closing date in December 2021. OPRC Works Contracts: Out of about total 335km of road section for rehabilitation and improvement, 328km (98%) of the total length) road sections have been completed and paid for. This represents an increase of only 12 km (3.6%) since the last implementation mission in October 2020. Current target completion dates for rehabilitation and improvement phase is expected to be end of July 2021. Urban Infrastructure Improvements: Traffic Signaling works progressed notably since October 2020. Out of 129 intersections, 105 are completed. and the construction of the centralized traffic control center (CTC) has been at 68%. The whole system is expected to be completed by March 2022. The construction works to improve the layouts of some key intersections in Gaborone has completed 13 intersections. 6/28/2021 Page 1 of 5 The World Bank Implementation Status & Results Report Integrated Transport (P102368) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Low Low Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Substantial Substantial Sustainability Fiduciary -- Low Low Environment and Social -- Moderate Moderate Stakeholders -- Moderate Substantial Other -- Moderate Moderate Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes To enhance the efficiency of Botswana's transport system IN01002226 ►Length of roads under successful long term OPRCs for rehabilitation and maintenance (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 316.00 328.00 335.00 Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 IN01002227 ►Average vehicle operating costs per vehicle-km on OPRC roads (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.26 0.00 0.23 0.18 Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 Baseline: Car - 26 US Cents; Bus - 48 US Cents; Heavy Truck - 79 US Cents Comments: End target: Car - <18 US Cents; Bus - <38 US Cents; Heavy Truck - <68 US Cents 6/28/2021 Page 2 of 5 The World Bank Implementation Status & Results Report Integrated Transport (P102368) Project collected traffic and other pertinent information required to compute VOC in December 2020 when 94% of the works were completed. Draft VOC analysis report was prepared and initial VOC values were populated as follows: Car 23 Bus - - - - - 40 Heavy Truck 69 IN01002228 ►Decrease in number of annual road accidents on project roads as related to road conditions (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 59.70 74.20 20.00 Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 The reduction is significant, and MTC attributes this partly to the reduction of traffic as a result of movement restrictions following government's order to curb COVID-19 pandemic Comments: IN01002229 ►Average travel time reduction (Gaborone City) per 10 kms travel (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 Project interventions commenced in November 2019; baseline data collected – update to be provided Comments: after implementation of works and results start to materialize. IN01002230 ►Completion of Sector Studies (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 75.00 75.00 100.00 Date 12-Nov-2009 30-Sep-2020 30-Sep-2020 31-Dec-2021 81% reported earlier was an error Comments: Intermediate Results Indicators by Components Component B: Road Sector Investment IN01002231 ►First OPRC contract awarded successfully (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes 6/28/2021 Page 3 of 5 The World Bank Implementation Status & Results Report Integrated Transport (P102368) Date 12-Nov-2009 01-May-2014 01-May-2014 31-Dec-2012 IN01002232 ►Number of contracts successfully awarded within the bid/proposal validity period (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 100.00 Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 IN01002233 ►Number of complaints on procurement processes determined to be justified by the Bank (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value None None None None Date 30-Jun-2009 30-Sep-2020 10-May-2021 31-Dec-2021 IN01002234 ►Satisfactory financial management reporting (%) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0% 100% 100% 100% Date 12-Nov-2009 30-Sep-2020 10-May-2021 31-Dec-2021 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P102368 IBRD-77130 Effective USD 186.00 186.00 0.00 135.02 50.98 73% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P102368 IBRD-77130 Effective 28-May-2009 16-Nov-2009 17-May-2010 31-Jan-2020 31-Dec-2021 Cumulative Disbursements 6/28/2021 Page 4 of 5 The World Bank Implementation Status & Results Report Integrated Transport (P102368) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History Level 2 Approved on 26-Oct-2017 ,Level 2 Approved on 25-Jun-2019 ,Level 2 Approved on 29-Sep-2020 ,Level Approved on 27-Oct-2020 Related Project(s) There are no related projects. 6/28/2021 Page 5 of 5