PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic of Congo, Transport and Connectivity Support Project(P161877) Project Implementation agency: Cellule Infrastructures Date of the Procurement Plan: January 10, 2020 Period covered by this Procurement Plan: January 2020 – June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Congo, Democratic Republic of : DRC Transport and Connectivity Support Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2020-01-12 2021-10-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161877 GPN Date: Project Name: DRC Transport and Connectivity Support Project Loan / Credit No: / , IDA / V2970 Cellule Infrastructures Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151794-NC-DIR / Passation de En attente Mise à jour du logiciel / Monitoring and evaluation A posteriori marché de gré à Direct 50,000.00 0.00 2020-10-01 2020-10-06 2020-11-10 2020-11-25 d'exécution TOMPRO par TOMATE gré CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-152090-CS-CQS / Etudes techniques et Sélection fondée économiqes et préparation du Support to road sector sur les En attente / A posteriori Open - International 100,000.00 0.00 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 DAO pour le bitumage de la governance qualifications des d'exécution RN2, tronçon Bukavu - consultants Walungu (38 km) ZR-CI-152092-CS-QCBS / Etudes techniques et Sélection fondée économiqes et préparation du Support to road sector / A posteriori sur la qualité et le Open - International 425,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-02-07 DAO pour le bitumage de la governance coût RN2, tronçon Mbuji Mayi - Kabinda (159 km) ZR-CI-152088-CS-CQS / Etudes techniques et Sélection fondée économiqes ainsi que la Support to road sector sur les préparation du DAO pour la / A posteriori Open - International 120,000.00 0.00 Annulé 2020-01-30 2020-02-20 2020-04-04 2020-05-04 2020-06-08 2020-11-07 governance qualifications des réhabilitation et l'entretien de consultants la RN2, tronçon Walungu- Kamituga (142 km) ZR-CI-152139-CS-CQS / Etudes techniques et Sélection fondée économiqes et préparation du Support to road sector sur les / A posteriori Open - International 125,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 DAO pour le bitumage de la governance qualifications des RN2, tronçon Butembo - Beni consultants (55 km) ZR-CI-152097-CS-QCBS / Etudes techniques et économiques ainsi que la Sélection fondée Support to road sector En cours préparation du DAO pour la IDA / V2970 A posteriori sur la qualité et le Open - International 300,000.00 0.00 2020-03-27 2020-04-24 2020-04-17 2020-05-20 2020-05-31 2020-07-24 2020-06-28 2020-11-03 2020-07-28 2020-11-03 2020-09-01 2020-11-03 2020-10-06 2021-03-07 governance d'exécution réhabilitation de la RN2, coût tronçon Beni-Butembo- Rutshuru (306 km) ZR-CI-152087-CS-QCBS / Etudes de sauvegardes (EIES, Sélection fondée Airport emergency PAR et PPA) des travaux de IDA / V2970 A posteriori sur la qualité et le Open - International 450,000.00 0.00 Annulé 2020-03-27 2020-07-27 2020-04-17 2020-05-31 2020-06-28 2020-07-28 2020-09-01 2020-10-06 2021-03-07 improvement réhabilitation du tronçon Beni- coût Butembo-Rutshuru ZR-CI-151795-CS-CQS / Evaluation des risques VBG Sélection fondée liés aux travaux de Airport emergency sur les IDA / V2970 A posteriori Limited 200,000.00 149,160.00 Achevé 2020-04-12 2020-05-29 2020-04-26 2020-08-07 2020-05-26 2020-09-04 2020-06-30 2020-09-28 2020-09-29 2021-07-13 réhabilitation de la RN2, improvement qualifications des tronçon Mbuji Mayi-Kabinda- consultants Lubao ZR-CI-164527-CS-QCBS / Elaboration des cadres de Sélection fondée sauvegardes (CGES y compris Airport emergency En attente IDA / V2970 A posteriori sur la qualité et le Open - International 300,000.00 0.00 2020-04-06 2020-04-27 2020-06-10 2020-07-08 2020-08-07 2020-09-11 2020-10-16 2021-03-17 les risques VBG, CPR et CPPA) improvement d'exécution coût des travaux des routes prioritaires ZR-CI-164534-CS-QCBS / Sélection fondée Préparation des documents de Airport emergency En attente IDA / V2970 A posteriori sur la qualité et le Open - International 200,000.00 0.00 2020-04-10 2020-05-01 2020-06-14 2020-07-12 2020-08-11 2020-09-15 2020-10-20 2021-03-21 sauvegardes (EIES et PAR) des improvement d'exécution coût travaux aéroportuaires de Beni Page 1 ZR-CI-164532-CS-CQS / Analyse technique et Sélection fondée économique pour Support to road sector sur les En cours IDA / V2970 A posteriori Open - International 100,000.00 0.00 2020-04-30 2020-05-13 2020-05-21 2020-06-23 2020-07-04 2020-08-03 2020-09-07 2021-01-06 l'aménagement de la RP governance qualifications des d'exécution 1029 Sake-Masisi-Walikale consultants (287 km) ZR-CI-164603-CS-QCBS / Etudes techniques et Sélection fondée Support to road sector En attente préparation du DAO des IDA / V2970 A posteriori sur la qualité et le Open - International 350,000.00 0.00 2020-03-30 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-03-10 governance d'exécution travaux aéroportuaires (Goma coût et Beni) ZR-CI-164588-CS-CQS / Etude de faisabilité et Sélection fondée assistance technique sur Support to road sector sur les En attente IDA / V2970 A posteriori Limited 200,000.00 0.00 2020-04-13 2020-04-27 2020-05-27 2020-07-01 2020-12-28 l'intégration et la gestion de la governance qualifications des d'exécution fibre optique dans les routes consultants du projet Sélection fondée ZR-CI-173044-CS-QCBS / En cours IDA / V2970 Monitoring and evaluation A posteriori sur la qualité et le Open - International 45,000.00 0.00 2020-08-03 2020-09-10 2020-08-24 2020-10-09 2020-10-07 2021-01-13 2020-11-04 2020-12-04 2021-01-08 2021-02-12 2022-02-12 Audit externe des comptes d'exécution coût ZR-CI-152089-CS-CQS / Sélection fondée Audit organisationnel et sur les IDA / V2970 Road improvement program A posteriori Open - International 90,000.00 0.00 En cours d'examen 2020-10-05 2020-11-13 2020-10-26 2020-12-09 2021-01-08 2021-02-12 2021-04-14 technique du Fonds National qualifications des d'Entretien Routier (FONER) consultants ZR-CI-190167-CS-QCBS / Elaboration des cadres de Sélection fondée Airport emergency sauvegardes (CGES y compris IDA / V2970 A posteriori sur la qualité et le Open - International 350,000.00 0.00 En cours d'examen 2020-09-11 2020-11-09 2020-10-02 2020-11-15 2020-12-13 2021-01-12 2021-02-16 2021-03-23 2021-07-23 improvement les risques VBG, CPR et CPPA) coût du PACT (routes et aéroports) ZR-CI-190169-CS-LCS / Sélection au En cours Audit financier de la RVA, IDA / V2970 Road improvement program A posteriori Open - International 60,000.00 0.00 2020-09-04 2020-08-27 2020-09-25 2020-10-07 2020-11-08 2021-03-09 2020-12-06 2021-04-20 2021-01-05 2021-02-09 2021-03-16 2021-08-13 moindre coût d'exécution exercices 2019 et 2020 ZR-CI-190170-CS-LCS / Sélection au En cours audit financier du FONER, IDA / V2970 Road improvement program A posteriori Open - International 60,000.00 67,000.00 2020-09-04 2020-09-01 2020-09-25 2020-10-07 2020-11-08 2021-01-20 2020-12-06 2021-03-09 2021-01-05 2021-04-20 2021-02-09 2021-05-25 2021-03-16 2021-08-13 moindre coût d'exécution exercices 2019 et 2020 ZR-CI-190171-CS-CQS / Etude d'impact Sélection fondée environnemental et social Airport emergency sur les En cours (EIES) des travaux de IDA / V2970 A posteriori Open - International 150,000.00 0.00 2020-09-04 2021-05-07 2020-09-25 2020-11-08 2020-12-08 2021-01-12 2021-03-14 improvement qualifications des d'exécution réhabilitation du tronçon consultants routier Beni-Butembo- Rutshuru ZR-CI-205399-CS-CQS / Elaboration du Plan d'Action Sélection fondée de Réinstallation (PAR) et du Airport emergency sur les Plan en faveur des Populations IDA / V2970 A posteriori Open - International 183,000.00 0.00 En cours d'examen 2020-11-27 2020-12-21 2020-12-18 2021-01-31 2021-03-02 2021-04-06 2021-08-04 improvement qualifications des Autochtones (PPA) liés aux consultants travaux de bitumage de la RN2, tronçon Beni-Butembo ZR-CI-230037-CS-CQS / Elaboration du Plan en faveur Sélection fondée des Populations Autochtones Airport emergency sur les En attente IDA / V2970 A posteriori Open - International 130,340.00 0.00 2021-05-21 2021-06-11 2021-07-25 2021-08-24 2021-09-28 2022-02-25 (PPA) lié aux travaux de improvement qualifications des d'exécution bitumage de la RN2, tronçon consultants Beni-Butembo ZR-CI-230401-CS-CQS / Sélection fondée Elaboration du Plan d'Action Airport emergency sur les En attente de Réinstallation (PAR) lié aux IDA / V2970 A posteriori Limited 103,448.00 0.00 2021-05-14 2021-05-28 2021-06-27 2021-08-01 2021-11-29 improvement qualifications des d'exécution travaux de bitumage de la consultants RN2, tronçon Beni-Butembo ZR-CI-230619-CS-CQS / Sélection fondée Actualisation du PAR des Airport emergency sur les En cours travaux de réhabilitation de la IDA / V2970 A posteriori Limited 110,000.00 0.00 2021-05-14 2021-06-27 2021-05-28 2021-06-27 2021-08-01 2021-08-11 improvement qualifications des d'exécution RN2, tronçon Mbuji Mayi- consultants Kabinda Sélection fondée ZR-CI-230067-CS-CQS / Airport emergency sur les En cours Elaboration du CPR du PACT IDA / V2970 A posteriori Open - International 285,110.00 0.00 2021-07-12 2021-07-09 2021-08-02 2021-07-15 2021-09-15 2021-10-15 2021-11-19 2022-04-03 improvement qualifications des d'exécution (routes et aéroports) consultants ZR-CI-254724-CS-CQS / Actualisation des études Sélection fondée techniques pour la Airport emergency sur les IDA / V2970 A posteriori Limited 178,850.00 0.00 En cours d'examen 2021-09-30 2021-10-18 2021-10-14 2021-11-13 2021-12-18 2022-05-17 construction des ouvrages de improvement qualifications des drainage et étude économique consultants de l’aéroport de Goma ZR-CI-254725-CS-CQS / Elaboration du schéma de Sélection fondée principe de plan masse Airport emergency sur les (SPPM), études de IDA / V2970 A posteriori Limited 199,650.00 0.00 En cours d'examen 2021-09-30 2021-10-18 2021-10-14 2021-11-13 2021-12-18 2022-05-17 improvement qualifications des construction du mur de consultants clôture et études techniques et économiques de l’aéroport de Beni-Mavivi INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151569-CS-INDV / Mise à jour du manuel de En attente procédures administratives, / Road improvement program A posteriori Individuel Limited 35,000.00 0.00 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2020-10-28 d'exécution comptables, financières, et de passation des marchés Page 2 ZR-CI-152128-CS-INDV / En cours Mise à jour du manuel / Monitoring and evaluation A posteriori Individuel Limited 35,000.00 0.00 2020-04-01 2020-11-23 2020-04-06 2020-04-27 2020-06-01 2020-08-31 d'exécution d'exécution du projet ZR-CI-164594-CS-CDS / Actualisation des études techniques et économiques Sélection de ainsi que du DAO pour la Support to road sector IDA / V2970 A posteriori consultants par Direct 200,000.00 349,200.00 Signé 2020-03-30 2020-05-20 2020-04-09 2020-07-29 2020-06-13 2020-09-10 2020-09-13 réhabilitation de la RN2, governance entente directe tronçon Mbuji Mayi - Kabinda - Lubao (332 km) par AIC PROGETTI ZR-CI-164593-CS-INDV / Analyse sécuritaire du projet Airport emergency En attente IDA / V2970 A posteriori Individuel Open 200,000.00 0.00 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2021-02-06 et élaboration du plan de improvement d'exécution gestion de la sécurité ZR-CI-164587-CS-INDV / Etudes économiques des Support to road sector En attente IDA / V2970 A posteriori Individuel Limited 40,000.00 0.00 2020-04-06 2020-04-11 2020-05-02 2020-06-06 2020-12-03 activités aéroportuaires (Goma governance d'exécution et Beni) ZR-CI-164590-CS-INDV / Actualisation du PPA des travaux de rehabilitation de la Airport emergency En cours IDA / V2970 A posteriori Individuel Direct 50,000.00 0.00 2020-05-26 2020-06-18 2020-06-05 2020-06-26 2020-07-31 2020-10-29 RN2, tronçon Mbuji Mayi- improvement d'exécution Kabinda-Lubao par Bruno BOLEKYMO ZR-CI-164605-CS-INDV / Actualisation du PAR des travaux de réhabilitation de la Airport emergency En cours IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 2020-05-26 2020-08-10 2020-06-05 2020-06-26 2020-07-31 2020-10-29 RN2, tronçon Mbuji Mayi- improvement d'exécution Kabinda-Lubao par Mamadou DIEDHIOU ZR-CI-164586-CS-INDV / Actualisation et préparation des documents de Airport emergency En attente IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 2020-05-28 2020-06-07 2020-06-28 2020-08-02 2020-10-31 sauvegardes (EIES et PAR) des improvement d'exécution travaux aéroportuaires de Goma par André TURCOTTE ZR-CI-164585-CS-INDV / Actualisation des EIES des travaux de réhabilitation de Airport emergency IDA / V2970 A posteriori Individuel Direct 120,000.00 143,236.00 Signé 2020-05-26 2020-06-18 2020-06-05 2020-07-29 2020-06-26 2020-08-20 2020-07-31 2020-09-10 2020-10-29 la RN2, tronçon Mbuji Mayi- improvement Kabinda-Lubao par Adama ZARE ZR-CI-173049-CS-INDV / Chef de Section Routes au En cours IDA / V2970 Monitoring and evaluation A posteriori Individuel Open 60,000.00 0.00 2020-05-26 2020-05-27 2020-07-14 2020-08-04 2020-09-08 2021-09-08 sein de la Cellule d'exécution Infrastructures ZR-CI-181740-CS-INDV / Prestations de service au poste de Coordonnateur de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 55,825.00 183,425.00 Signé 2020-06-26 2020-07-14 2020-06-28 2020-07-14 2020-06-29 2020-09-30 2020-07-01 2020-12-02 2021-01-31 Cellule Infrastructures par Théophile NTELA LUNGUMBA ZR-CI-181736-CS-INDV / Prestations de service au poste de Chef de Section Administration et Finances au IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 35,000.00 55,000.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-29 2020-07-01 2020-11-05 2021-01-31 sein de la Cellule Infrastructures par Pierre BUNDOKI NDONGALA ZR-CI-181744-CS-INDV / Prestations de service au poste de Comptable au sein IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 18,900.00 18,900.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 de la Cellule Infrastructures par Jean-Jacques MAKUNZA ZR-CI-181742-CS-INDV / Prestations de service au poste de Gestionnaire de Projet Transport au sein de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,920.00 39,160.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Cellule Infrastructures par Théodore NGAMBILA VAN MAZIREL ZR-CI-181732-CS-INDV / Prestations de service au poste de Responsable de Passation des Marchés de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 31,990.00 50,270.00 Signé 2020-06-26 2020-07-30 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Cellule Infrastructures par Damien MANYAMALA MAKANDAKELE ZR-CI-181739-CS-INDV / Prestations de service au poste de Chargé de Passation IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,570.00 38,610.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-10-30 2020-07-01 2020-11-05 2021-01-31 des Marchés au sein de la Cellule Infrastructures par Godefroid KASENDE MESO ZR-CI-181735-CS-INDV / Prestations de service au poste de Spécialiste en Airport emergency sauvegardes IDA / V2970 A posteriori Individuel Direct 28,560.00 95,900.00 Achevé 2020-06-26 2020-08-03 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 2021-08-15 improvement environnementales au sein de la Cellule Infrastructures par Aimé KABAMBA ZR-CI-181731-CS-INDV / Prestations de service au poste de Spécialiste en Airport emergency IDA / V2970 A posteriori Individuel Direct 23,450.00 36,850.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 sauvegardes sociales au sein improvement de la Cellule Infrastructures par Félix TSHIABA Page 3 ZR-CI-181737-CS-INDV / Prestations de service au poste d'Expert Senior SIG au IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 28,560.00 44,880.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 sein de la Cellule Infrastructures par Patrick MBUY'A SAKAFUKU ZR-CI-181734-CS-INDV / Prestations de service au poste d'Assistante à la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 15,120.00 23,760.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Coordination de la Cellule Infrastructures par Marianne IKOBO ZR-CI-181743-CS-INDV / Prestations de service au poste de Chauffeur à la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,540.00 13,420.00 Signé 2020-06-26 2020-09-29 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Coordination de la Cellule Infrastructures par Noël MATUNGULU ZR-CI-181741-CS-INDV / Prestations de service au poste d'Assistante au projet IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 12,390.00 19,470.00 Signé 2020-06-26 2020-07-10 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 au sein de la Cellule Infrastructures par Mélanie KAYIBA ZR-CI-181738-CS-INDV / Prestations de service au poste de Chauffeur au sein de IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,260.00 12,980.00 Signé 2020-06-26 2020-08-20 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 la Cellule Infrastructures par Jean-Pierre KILONGOKELE ZR-CI-182253-CS-INDV / Prestations de service au poste d'Ingénieur Assistant 1 IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-05 2021-01-31 à la Section Routes de la Cellule Infrastructures par Cyrille KIBULU ZR-CI-182250-CS-INDV / Prestations de service au poste d'Ingénieur Assistant 2 IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-05 2021-01-31 à la Section Routes de la Cellule Infrastructures par Ange MUSHIGO ZR-CI-186421-CS-INDV / Appuis ponctuels à En cours l'évaluation des offres des IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 42,000.00 0.00 2020-08-14 2020-09-01 2020-08-19 2020-09-09 2020-10-14 2021-04-12 d'exécution marchés prévus au PPA du PACT ZR-CI-152119-CS-INDV / Etude de marchés du projet et IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 75,000.00 0.00 Annulé 2020-06-15 2020-06-20 2020-07-11 2020-08-15 2020-10-15 préparation de la stratégie de passation de marchés ZR-CI-151728-CS-INDV / Airport emergency Elaboration des procédures de IDA / V2970 A posteriori Individuel Open 150,000.00 0.00 Annulé 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2020-11-08 improvement gestion de la main d'oeuvre ZR-CI-215461-CS-INDV / Prestations de services de Support to road sector En cours Comptable du projet PACT au IDA / V2970 A posteriori Individuel Open 42,000.00 0.00 2021-01-29 2021-02-15 2021-03-22 2021-03-26 2021-04-12 2022-04-12 governance d'exécution sein de la Cellule Infrastructures ZR-CI-215454-CS-CDS / Réalisation des études diachroniques, durant la période de 10 dernières Sélection de années, de l’évolution Airport emergency En attente IDA / V2970 A posteriori consultants par Direct 54,000.00 0.00 2021-01-29 2021-02-01 2021-02-26 2021-05-17 environnementale et sociale improvement d'exécution entente directe par télédétection dans la bande de 10 km centrée sur les axes routiers Mbuji-Mayi – Lubao et Goma – Beni ZR-CI-230075-CS-INDV / Expert en fibre optique et Support to road sector En attente développement numérique au IDA / V2970 A posteriori Individuel Open 48,000.00 0.00 2021-05-07 2021-06-25 2021-07-16 2021-08-20 2022-08-20 governance d'exécution sein de la Cellule Infrastructures ZR-CI-230031-CS-CDS / Actualisation des EIES des Sélection de travaux de réhabilitation de la Airport emergency IDA / V2970 A posteriori consultants par Direct 227,490.00 216,171.00 Signé 2021-05-07 2021-04-16 2021-05-17 2021-05-25 2021-07-21 2021-07-22 2021-11-18 RN2, tronçon Mbuji Mayi- improvement entente directe Kabinda-Lubao par la firme SERF BURKINA ZR-CI-241060-CS-INDV / Prestations de services au poste d'Expert Violences Airport emergency En cours Basées sur le Genre au sein de IDA / V2970 A posteriori Individuel Direct 38,500.00 0.00 2021-06-28 2021-08-19 2021-07-04 2021-07-07 2021-07-31 2022-05-31 improvement d'exécution la Cellule Infrastructures par Madame Liliane MUSAU KAZADI ZR-CI-241107-CS-INDV / Elaboration du Cadre de Airport emergency En cours planification en faveur des IDA / V2970 A posteriori Individuel Limited 195,241.00 0.00 2021-07-14 2021-06-03 2021-07-19 2021-06-21 2021-08-09 2021-09-13 2022-01-26 improvement d'exécution Populations Autochtones (CPPA) du Projet ZR-CI-241053-CS-INDV / Elaboration du Cadre de Airport emergency IDA / V2970 A priori Individuel Limited 304,250.00 0.00 Annulé 2021-07-12 2021-07-17 2021-08-07 2021-09-11 2022-02-08 gestion environnementale et improvement sociale (CGES) du Projet Page 4 ZR-CI-254730-CS-INDV / Prestations de service au poste d'Expert en Sauvegarde Support to road sector En cours Environnementale et IDA / V2970 A posteriori Individuel Open 31,500.00 0.00 2021-09-30 2021-10-12 2021-11-09 2021-11-23 2021-12-02 2022-05-31 governance d'exécution Responsable de l’Unité Environnementale et Sociale de la CI ZR-CI-254728-CS-INDV / Consultant individuel Ingénieur routier en appui à IDA / V2970 Road improvement program A posteriori Individuel Direct 30,000.00 0.00 En cours d'examen 2021-09-30 2021-10-19 2021-10-10 2021-10-24 2021-11-16 2022-04-15 l’équipe du projet PACT, par Billy TSHIBAMBE ZR-CI-258766-CS-INDV / Prestation de service d’élaboration du cadre de En attente Gestion Environnementale et IDA / V2970 Road improvement program A posteriori Individuel Direct 54,033.00 0.00 2021-10-19 2021-10-20 2021-10-22 2021-10-25 2021-11-24 d'exécution Sociale (CGES) du Projet d’Appui à la Connectivité et au Transport (PACT). Page 5