PROCUREMENT PLAN (Textual Part) Project information: Bangladesh, Project Preparation Advance (PPA) for Livestock Development-based Dairy Revolution and Meat Productions (DRMP), PPA No. IDA V104-BD Project Implementation agency: Department of Livestock Date of the Procurement Plan: October 2017 Period covered by this Procurement Plan: October 2017 - August 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank; b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory; f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable/ Other Relevant Procurement Information. Procurement Responsibility: Department of Livestock (DLS) is the implementing agency (IA) who will be responsible for all procurements Procurement Threshold Bank-financed all contracts at or above the thresholds set out in the below table 1 are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Substantial Moderate Low Type of procurement High risk risk risk risk Works (including turnkey, supply & 5 10 15 20 installation of plant and equipment, and PPP) Goods, information technology and non- 1.5 2 4 6 consulting services Consultants: firms 0.5 1 2 4 Consultants: individuals 0.2 0.3 0.4 0.5 Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract, including all taxes and duties payable under the contract. PROCUREMENT Bangladesh : Livestock and Dairy Development Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2018-05-26 2020-03-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161246 GPN Date: 2019-04-22 Project Name: Livestock and Dairy Development Project Loan / Credit No: IDA / V1040, IDA / 63300 Executing Agency(ies): Department of Livestock Services for DRMP WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DLS/DRMP/PPA/W-01 / Pending Civil Construction of office Project Management Single Stage - One IDA / V1040 Post Request for Bids Open - National 131,916.00 0.00 Implementati 2018-09-05 2018-09-08 2018-09-19 2018-09-24 2018-10-02 2018-12-31 building: vertical extension Monitoring and Evaluation Envelope on of Nutrition Building, DLS DLS/LDDP/WD-40 / Earth Filling, construction of new boundary wall and vertical Improving Risk Management extension of existing Pending and Climate Resilience of Single Stage - One boundary wall at Tangail IDA / 63300 Post Request for Bids Open - National 115,747.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-02-01 Livestock Production Envelope and Jamalpur districts AI on Systems premises, repair of Tangail and Jamalpur AI offices, quarter etc DLS/LDDP/WD-88A / Repair and renovation of Under Market Linkages and Value Single Stage - One auditorium (+/- 350 Sq M) IDA / 63300 Post Request for Bids Open - National 109,157.00 0.00 Implementati 2019-05-07 2019-08-18 2019-05-15 2019-06-10 2019-09-23 2019-06-24 2019-09-30 2019-08-01 2020-05-01 Chain Development Envelope at Officers Training Institute on (OTI) Savar, Dhaka DLS/LDDP/WD-90 / Construction of Existing DLS Under Building no-02 6th and 7th Project Management Single Stage - One IDA / 63300 Post Request for Bids Open - National 805,000.00 0.00 Implementati 2019-04-25 2019-04-30 2019-05-13 2019-05-27 2019-07-11 2020-07-11 floor including substation, Monitoring and Evaluation Envelope on lift, furniture, decoration etc for PMU DLS/LDDP/WD-108 / Improving Risk Management Pending Renovation and Repairing and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 273,048.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-05-01 works at Rajshahi Dairy Livestock Production Envelope on Farm Systems DLS/LDDP/WD-109 / Improving Risk Management Pending Renovation and Repairing and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 106,795.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-02-01 works at Bogura Dairy Livestock Production Envelope on Farm Systems DLS/LDDP/WD-110 / Improving Risk Management Pending Renovation and Repairing and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 109,217.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-02-01 works at Barishal Dairy Livestock Production Envelope on Farm Systems Improving Risk Management DLS/LDDP/WD-111 / Pending and Climate Resilience of Single Stage - One Renovation and Repairing IDA / 63300 Post Request for Bids Open - National 109,217.00 0.00 Implementati 2019-05-07 2019-05-21 2019-06-10 2019-06-24 2019-08-01 2020-02-01 Livestock Production Envelope works at Sylhet Dairy Farm on Systems DLS/LDDP/WD-112 / Improving Risk Management Pending Renovation and Repairing and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 109,627.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-02-01 works at Faridpur Dairy Livestock Production Envelope on Farm Systems Page 1 DLS/LDDP/WD-113 / Improving Risk Management Pending Renovation and Repairing and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 117,819.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-02-01 works at Chattogram Dairy Livestock Production Envelope on Farm Systems DLS/LDDP/WD-23 / Construction of Vertical Expansion of 26 (twenty Six) Existing Upazila Livestock Under Development Centers (ULDC) Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-05-07 2019-05-15 2019-06-10 2019-06-24 2019-08-01 2020-08-01 for Training and service Chain Development Envelope on Facilities Panchagor-03 nos, Thakurgaon-02 nos, Dinajpur- 10 nos, Lalmonirhat-05 nos, Nilphamari-06 nos DLS/LDDP/WD-24 / Construction of Vertical Extension of 26 (twenty six) existing Upazila Livestock Pending Development Centers (ULDC) Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-05-26 2019-06-03 2019-06-30 2019-07-14 2019-08-21 2020-08-21 for Training and Service Chain Development Envelope on Facilities Kurigram=07 nos, Gaibandha= 03 nos, Rangpur=04 nos, Bogra=08 nos and Natore=04 nos DLS/LDDP/WD-25 / Construction of Vertical Extension of 26 (twenty six) existing Upazila Livestock Pending Development Centers (ULDC) Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-06-13 2019-06-23 2019-07-18 2019-08-01 2019-09-09 2020-09-09 for Training and Service Chain Development Envelope on Facilities Rajshahi=06, Nawgaon=07 nos, Pabna=06 nos, Sirajgonj=05 nos and Joypurhat=02 nos DLS/LDDP/WD-26 / Construction of Vertical Extension of 26 (twenty six) existing ULDC for Training and Service Facilities Pending Dhaka=04 nos, Manikgonj=04 Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-06-27 2019-07-07 2019-08-01 2019-08-14 2019-09-19 2020-09-19 nos, Narrayongonj=02 nos, Chain Development Envelope on Gazipur=02 nos, Munshigonj=03 nos, Narshingdi=03 nos, Shariatpur=04 nos and Madaripur=04 nos DLS/LDDP/WD-31 / Construction of Vertical Extension of 30 (thirty) existing ULDC for Training Pending and Service Facilities Market Linkages and Value Single Stage - One IDA / 63300 Prior Request for Bids Open - National 840,000.00 0.00 Implementati 2019-08-13 2019-08-21 2019-09-16 2019-09-30 2019-10-28 2020-10-28 Chapainababgonj=03, Chain Development Envelope on Mymensingh=06, Netrokona=07, Jamalpur=01, Sherpur=04, Tangail=06 and Gopalgonj=03 nos DLS/LDDP/WD-27 / Construction of Vertical Extension of 26 (twenty six) existing ULDC for Training Pending Market Linkages and Value Single Stage - One and Service Facilities IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-08-27 2019-09-04 2019-09-30 2019-10-14 2019-11-11 2020-11-11 Chain Development Envelope Faridpur=06 nos, on Kishorgonj=07 nos, Khulna=06 nos, Satkhira=05 nos and Feni=02 nos Page 2 DLS/LDDP/WD-28 / Construction of Vertical Extension of 26 (twenty six) existing ULDC for Training and Service Facilities Rajbari=02 nos, Pending Market Linkages and Value Single Stage - One Chottogram=05, Kustia=02 IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-09-30 2019-10-07 2019-10-28 2019-11-11 2019-12-17 2020-12-17 Chain Development Envelope nos, Meherpur=01, on Chuadanga=02 nos, Jhenaidah=04 nos, Magura=03, Narail=02, Jessore=03 and B. Baria=02 nos DLS/LDDP/WD-29 / Construction of Vertical Extension of 26 (twenty six) existing ULDC for Training Pending and Service Facilities Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-10-14 2019-10-21 2019-11-11 2019-11-25 2019-12-23 2020-12-23 Barishal=04, Barguna=02, Chain Development Envelope on Patuakhali=03, Jhalkhati=02, bhola=03, Pirojpur=03, Bagerhat=04, Lakhipur=03 and Noakhali=02 nos DLS/LDDP/WD-30 / Construction of Vertical Extension of 26 (twenty six) existing ULDC for Training Pending Market Linkages and Value Single Stage - One and Service Facilities IDA / 63300 Post Request for Bids Open - National 728,000.00 0.00 Implementati 2019-11-12 2019-11-19 2019-12-10 2019-12-25 2020-01-22 2021-01-22 Chain Development Envelope Sylhet=04, Moulbai on Bazar=04, Sunamgonj=02, Hobogonj=03, Cumilla=05, Chadpur=04 and Coxes Bazar=04 WD-32 / Construction of Improving Risk Management Pending District AI center at and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 282,975.90 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Noakhali 3 storied Livestock Production Envelope on Foundation Systems WD-33 / Construction of Improving Risk Management District AI centre at Pabna Pending and Climate Resilience of Single Stage - One with 3 storied Foundation & IDA / 63300 Post Request for Bids Open - National 274,987.95 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Livestock Production Envelope drain, Repairing of Road, on Systems Shed Floors etc. WD-34 / Construction of Improving Risk Management Pending District AI center at and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 268,048.19 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Rangpur with 3 storied Livestock Production Envelope on Foundation Systems WD-35 / Construction of Improving Risk Management Pending District AI center at and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 273,481.93 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Thakurgaon with 3 storied Livestock Production Envelope on Foundation Systems WD-36 / Construction of District AI center at Improving Risk Management Pending Barishal with 3 storied and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 257,469.88 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Foundation & drain, Livestock Production Envelope on Repairing of Road, Shed Systems Floors etc. WD-37 / Construction of District AI center at Improving Risk Management Pending Sylhet with 3 storied and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 270,060.24 0.00 Implementati 2019-09-15 2019-09-25 2019-10-16 2019-11-07 2019-12-12 2020-02-27 Foundation and Training Livestock Production Envelope on Center at Sylhet Dairy Systems Farm Page 3 WD-38 / Construction of Improving Risk Management Pending District AI center at and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 285,048.19 0.00 Implementati 2019-09-19 2019-09-25 2019-10-16 2019-11-07 2019-12-12 2020-02-27 Faridpur with 3 storied Livestock Production Envelope on Foundation & drain Systems WD-41 / Construction of District AI center at Improving Risk Management Pending Chattogram with 3 and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 232,602.41 0.00 Implementati 2019-09-10 2019-09-25 2019-10-16 2019-11-07 2019-12-12 2020-02-27 storied Foundation & Livestock Production Envelope on drain, Repairing of Road, Systems Shed Floors etc WD-85 / Modern Semi Pending Automatic Slaughter House Market Linkages and Value Open - Single Stage - One IDA / 63300 Prior Request for Bids 10,000,000.00 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 with Drainage system at Chain Development International Envelope on Divisional HQ in Chottogram WD-86 / Modern Semi Pending Automatic Slaughter House Market Linkages and Value Open - Single Stage - One IDA / 63300 Prior Request for Bids 10,000,000.00 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 with Drainage system at Chain Development International Envelope on Divisional HQ in Khulna WD-87 / Modern Semi Pending Automatic Slaughter House Market Linkages and Value Open - Single Stage - One IDA / 63300 Prior Request for Bids 10,000,000.00 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 with Drainage system at Chain Development International Envelope on Divisional HQ in Rajshahi WD-88 (1) / Construction works for 7 storied Pending Market Linkages and Value Single Stage - One Dormitory bldg. Main gate, IDA / 63300 Post Request for Bids Open - National 968,674.70 0.00 Implementati 2019-09-01 2019-09-12 2019-10-03 2019-10-24 2019-11-28 2020-02-13 Chain Development Envelope B/W, Entry Road from on Dhaka Aricha High way WD-101 / Construction of Bio Gas plant, with distribution line, Mechanical System for drying the Pending slurry, Liquid extractor, shed Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 843,373.49 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 for dryers Manure Plant Chain Development Envelope on Manure Plant-20 ton at Savar CCDBF including remodeling and activation of existing 4 nos WD-102 / 1 Storied Training Center, Cattle shed, Improving Risk Management Pending at Rajshahi -5 nos each and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 926,783.13 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 =868 SqM + Vetting for Livestock Production Envelope on shed and Training centers Systems all Farms-2.00 Lac Taka Improving Risk Management WD-103 / Construction of Pending and Climate Resilience of Single Stage - One Training center at Bogura IDA / 63300 Post Request for Bids Open - National 111,746.99 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 Livestock Production Envelope Dairy Farm on Systems WD-104 / 1 Storied Improving Risk Management Pending Training Center, Cattle shed and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 306,710.84 0.00 Implementati 2019-09-01 2019-09-12 2019-10-03 2019-10-24 2019-11-28 2019-12-05 at Barishal Prefabricated Livestock Production Envelope on MS steel section as Column. Systems WD-105 / 1 Storied Improving Risk Management Pending Training Center -185 Sqm and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 164,662.65 0.00 Implementati 2019-09-01 2019-09-12 2019-10-03 2019-10-24 2019-11-28 2020-02-13 ,Godown at Sylhet Dairy Livestock Production Envelope on farm Systems Page 4 WD-106 / 1 Storied Improving Risk Management Pending Training Center -185 Sqm , and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 355,180.72 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 Cattle shed at Faridpur -2 Livestock Production Envelope on nos each =576.50 Sqm Systems WD-107 / Construction of Improving Risk Management Pending Training Center,Boundary and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 215,819.28 0.00 Implementati 2020-03-01 2020-03-15 2020-04-05 2020-04-26 2020-05-31 2020-08-16 wall and mini deep tube Livestock Production Envelope on well at Chattogram Systems WD-84 / Construction of Pending District level Hygienic Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 3,174,987.95 0.00 Implementati 2019-11-10 2019-11-20 2019-12-11 2020-01-03 2020-02-07 2020-04-24 Slaughter house within with Chain Development Envelope on necessary Drainage system WD-83 / Construction of Pending District level Hygienic Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 3,174,987.95 0.00 Implementati 2019-11-10 2019-11-20 2019-12-11 2020-01-03 2020-02-07 2020-04-24 Slaughter house within with Chain Development Envelope on necessary Drainage system. WD-81 / Construction of Pending District level Hygienic Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 3,174,987.95 0.00 Implementati 2019-11-10 2019-11-20 2019-12-11 2020-01-03 2020-02-07 2020-04-24 Slaughter house within with Chain Development Envelope on necessary Drainage system WD-82 / Construction of Pending District level Hygienic Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 3,174,987.95 0.00 Implementati 2019-11-10 2019-11-20 2019-12-11 2020-01-03 2020-02-07 2020-04-24 Slaughter house within with Chain Development Envelope on necessary Drainage system GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DLS/DRMP/PPA/G-06 / 16 sets of Desktop Computers/ Project Management Single Stage - One IDA / V1040 Post Request for Bids Open - National 34,579.12 28,014.20 Signed 2018-04-03 2018-04-01 2018-04-08 2018-06-27 2018-05-20 2018-04-16 2018-06-19 2018-05-15 2018-07-24 2018-05-28 2019-01-20 Laptop Computers, Printers, Monitoring and Evaluation Envelope UPS and accessories DLS/DRMP/PPA/G-07 / 1 no. Digital Camera, 5 nos. Digital Photocopiers, 2 nos. Project Management Single Stage - One Fax Machine , 2 nos. IDA / V1040 Post Request for Bids Open - National 23,565.58 12,745.56 Signed 2018-04-19 2018-04-01 2018-04-24 2018-06-27 2018-06-05 2018-04-16 2018-07-05 2018-05-17 2018-08-09 2018-06-12 2019-02-05 Monitoring and Evaluation Envelope Scanner, and 2 nos. Digital Multimedia Projector with Screens DLS/DRMP/PPA/G-08 / 4 nos. split type 2 ton capacity Air Conditioners, 1 Project Management Single Stage - One no. Water Heater, 2 nos. IDA / V1040 Post Request for Bids Open - National 11,526.15 0.00 Canceled 2018-04-09 2018-04-14 2018-06-27 2018-05-26 2018-04-16 2018-06-25 2018-05-09 2018-07-30 2019-01-26 Monitoring and Evaluation Envelope Microwave Oven, 2 nos. Water Purifier, Electronic Appliances DLS/DRMP/PPA/G-12 / Office Furniture, Fixture, Project Management Single Stage - One IDA / V1040 Post Request for Bids Open - National 12,806.72 8,785.69 Signed 2018-04-23 2018-05-08 2018-04-28 2018-06-27 2018-06-09 2018-05-24 2018-07-09 2018-05-29 2018-08-13 2018-06-07 2019-02-09 File Cabinet, helves, Closet, Monitoring and Evaluation Envelope Almirah DLS/DRMP/PPA/G-01 / Project Management Request for Single Stage - One Procurement of Office IDA / V1040 Post Limited 3,842.61 3,515.98 Signed 2018-04-03 2018-04-16 2018-05-29 2018-04-25 2018-11-25 Monitoring and Evaluation Quotations Envelope Supplies, and Consumables Page 5 DLS/DRMP/PPA/G-03 / Procurement of Biding Project Management Request for Single Stage - One Machine, Shredder, Vacuum IDA / V1040 Post Limited 3,842.61 3,538.46 Signed 2018-04-16 2018-05-08 2018-06-11 2018-05-17 2018-12-08 Monitoring and Evaluation Quotations Envelope Cleaner, Water Dispenser, etc. DLS/DRMP/PPA/G-08A / Split type air conditioner 3 Project Management Request for Single Stage - One IDA / V1040 Post Limited 5,763.00 5,336.11 Signed 2018-06-15 2018-06-13 2018-08-10 2018-06-18 2019-02-06 nos. for immediate Monitoring and Evaluation Quotations Envelope requirement DLS/DRMP/PPA/G-08B / 1 no. Water Heater, 2 nos. Microwave Oven, 2 nos. Pending Project Management Request for Single Stage - One Water Purifier, Electronic IDA / V1040 Post Limited 5,763.15 0.00 Implementati 2018-06-19 2018-08-14 2019-02-10 Monitoring and Evaluation Quotations Envelope Appliances and 1 no. split on type 2 ton capacity Air Conditioner DLS/DRMP/PPA/G-09 / Office Refurbishing for the Project Management Request for Single Stage - One offices of the Project IDA / V1040 Post Limited 3,842.61 3,422.28 Signed 2018-04-06 2018-03-18 2018-06-01 2018-03-28 2018-11-28 Monitoring and Evaluation Quotations Envelope Director and Deputy Project Director DLS/DRMP/PPA/G-10 / Repair & reconstruction of civil works, sanitary & Project Management Single Stage - One IDA / V1040 Post Request for Bids Open - National 19,209.68 16,093.48 Signed 2018-05-24 2018-04-08 2018-05-29 2018-06-27 2018-07-10 2018-04-23 2018-08-09 2018-05-10 2018-09-13 2018-06-06 2019-03-12 water supply line, electrical Monitoring and Evaluation Envelope & thai glass fitting -Office Refurbishing DLS/DRMP/PPA/G-13 / Pending Project Management Request for Single Stage - One Computer Accessories and IDA / V1040 Post Limited 5,520.00 0.00 Implementati 2018-09-10 2018-09-23 2018-10-08 Monitoring and Evaluation Quotations Envelope software. MS office & etc. on Pending DLS/DRMP/PPA/G-14 / Split Project Management Request for Single Stage - One IDA / V1040 Post Limited 6,404.00 0.00 Implementati 2018-09-11 2018-09-23 2018-10-08 type Air-Conditioner -3 nos. Monitoring and Evaluation Quotations Envelope on Pending DLS/DRMP/PPA/G-15 / Project Management Request for Single Stage - One IDA / V1040 Post Limited 4,265.00 0.00 Implementati 2018-09-07 2018-09-18 2018-10-02 Procurement of 3 nos. laptop Monitoring and Evaluation Quotations Envelope on DLS/DRMP/PPA/G-16 / Water Heater, Microwave Pending Project Management Request for Single Stage - One Oven, Freezer, Water IDA / V1040 Post Limited 5,123.00 0.00 Implementati 2018-09-11 2018-09-25 2018-10-10 Monitoring and Evaluation Quotations Envelope Purifier, Electronic on Appliances, etc. DLS/DRMP/PPA/G-17 / Phone set (land ph 02 nos, Pending Project Management Request for Single Stage - One Cell phone 2 nos, Tab 2 IDA / V1040 Post Limited 2,945.00 0.00 Implementati 2018-09-06 2018-09-17 2018-10-04 Monitoring and Evaluation Quotations Envelope Nos, LED Pocket/Mini on Projector-01) DLS/LDDP/GD-78A / Pending Project Management Request for Single Stage - One Furniture for Project IDA / 63300 Post Limited 2,410.00 0.00 Implementati 2019-04-23 2019-05-21 2019-05-28 Monitoring and Evaluation Quotations Envelope Management Unit (PMU) on DLS/LDDP/GD-102 / A) Intercom for Project Pending Project Management Request for Single Stage - One Management unit (50 user), IDA / 63300 Post Limited 8,434.00 0.00 Implementati 2019-04-23 2019-05-21 2019-06-11 Monitoring and Evaluation Quotations Envelope B) Surveillance System on (Camera-minimum 10 nos) Improving Risk Management Pending GD-40 / Consumables item and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 202,409.64 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-20 2019-11-03 2019-12-01 for research Laboratories Livestock Production Envelope on Systems Page 6 Pending Project Management Request for Single Stage - One GD-43 / Books & Journal IDA / 63300 Post Limited 6,024.10 0.00 Implementati 2019-10-15 2019-11-01 2019-11-21 Monitoring and Evaluation Quotations Envelope on Improving Risk Management Pending GD-44 / Hardware & and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 48,192.77 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-20 2019-11-03 2019-12-01 software for Laboratories Livestock Production Envelope on Systems Improving Risk Management GD-45 / Equipment for Pending and Climate Resilience of Single Stage - One improvement of Food Safety IDA / 63300 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2019-08-19 2019-08-28 2019-09-11 2019-09-18 2019-10-23 2020-01-08 Livestock Production Envelope lab. (BLRI) on Systems GD-47 / Printing of leaflet Pending Single Stage - One & vaccine card for FMD, IDA / 63300 Productivity Improvement Post Request for Bids Open - National 325,000.00 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-20 2019-11-03 2019-12-01 Envelope PPR & ND on GD-51 / Procurement of Pending Syringe, cool box etc for Single Stage - One IDA / 63300 Productivity Improvement Post Request for Bids Open - National 266,915.67 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-20 2019-11-03 2019-12-01 FMD, PPR & ND Envelope on vaccination program GD-55 / Printing of leaflet Pending for progressive management Single Stage - One IDA / 63300 Productivity Improvement Post Request for Bids Open - National 102,409.64 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-20 2019-11-03 2019-12-01 of Ruminant & Poultry Envelope on diseases Pending GD-56 / Drug for Dairy Single Stage - One IDA / 63300 Productivity Improvement Post Request for Bids Open - National 216,867.47 0.00 Implementati 2019-08-19 2019-08-28 2019-09-11 2019-09-18 2019-10-23 2020-01-08 cattle deworming program Envelope on Pending GD-57 / Drug for Beef Single Stage - One IDA / 63300 Productivity Improvement Post Request for Bids Open - National 216,867.47 0.00 Implementati 2019-08-19 2019-08-28 2019-09-11 2019-09-18 2019-10-23 2020-01-08 cattle deworming program. Envelope on Improving Risk Management GD-60 / Equipment’s early Pending and Climate Resilience of Single Stage - One pregnancy diagnosis etc for IDA / 63300 Prior Request for Bids Open - National 1,891,566.27 0.00 Implementati 2019-10-01 2019-10-15 2019-11-05 2019-11-19 2019-12-03 2019-12-31 Livestock Production Envelope FDIL & CDIL on Systems Improving Risk Management GD-62 / Equipment for Pending and Climate Resilience of Single Stage - One mini diagnostic lab. At IDA / 63300 Prior Request for Bids Open - National 4,481,927.71 0.00 Implementati 2019-12-15 2020-01-01 2020-01-22 2020-02-05 2020-02-19 2020-03-18 Livestock Production Envelope Upazila level on Systems Improving Risk Management GD-63 / Consumable item Pending and Climate Resilience of Single Stage - One for mini diagnostic lab. and IDA / 63300 Post Request for Bids Open - National 366,024.10 0.00 Implementati 2019-08-19 2019-08-28 2019-09-11 2019-09-18 2019-10-23 2020-01-08 Livestock Production Envelope FDIL & CDIL on Systems GD-74 / Procurement of Pending Project Management Single Stage - One Computer and associated IDA / 63300 Post Request for Bids Open - National 120,481.93 0.00 Implementati 2019-08-19 2019-08-29 2019-09-12 2019-09-19 2019-10-24 2020-01-09 Monitoring and Evaluation Envelope equipment's on Pending GD-76 / Procurement of Project Management Request for Single Stage - One IDA / 63300 Post Limited 4,939.76 0.00 Implementati 2019-10-15 2019-11-04 2019-11-24 Photocopier Monitoring and Evaluation Quotations Envelope on Pending GD-79 / Printing materials Market Linkages and Value Single Stage - One IDA / 63300 Post Request for Bids Open - National 120,481.93 0.00 Implementati 2019-10-01 2019-10-15 2019-11-05 2019-11-26 2019-12-31 2020-03-17 for different program Chain Development Envelope on Improving Risk Management Pending GD-80 / Goods for Farmers and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 120,481.93 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 on Food Safety Livestock Production Envelope on Systems Page 7 Pending GD-87 / Procurement of Bi- Project Management Single Stage - One IDA / 63300 Post Request for Bids Open - National 759,036.14 0.00 Implementati 2019-09-01 2019-09-15 2019-10-06 2019-10-27 2019-12-01 2020-02-16 Cycle for LSP Monitoring and Evaluation Envelope on Pending GD-88 / Procurement of Project Management Single Stage - One IDA / 63300 Post Request for Bids Open - National 1,113,253.01 0.00 Implementati 2019-10-01 2019-10-15 2019-11-05 2019-11-26 2019-12-31 2020-03-17 Tab for LSP Monitoring and Evaluation Envelope on Pending GD-89 / Procurement of Kit Project Management Single Stage - One IDA / 63300 Post Request for Bids Open - National 354,216.87 0.00 Implementati 2019-10-01 2019-10-15 2019-11-05 2019-11-26 2019-12-31 2020-03-17 Box for LSP Monitoring and Evaluation Envelope on WD-39 / Construction of Improving Risk Management Pending District AI center at and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 239,554.22 0.00 Implementati 2019-09-10 2019-09-25 2019-10-16 2019-11-07 2019-12-12 2020-02-27 Mymenshingh with 3 Livestock Production Envelope on storied Foundation Systems GD-66 (2) / Consumable Improving Risk Management Pending items such as emergency and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 397,241.38 0.00 Implementati 2019-09-22 2019-09-27 2019-11-08 2019-12-08 2020-01-12 2023-12-31 drug, antiseptic etc 180 Livestock Production Envelope on UNIT Systems GD-66 (1) / Procurement of Improving Risk Management Pending equipment's including and Climate Resilience of Single Stage - One IDA / 63300 Post Request for Bids Open - National 1,355,421.69 0.00 Implementati 2019-10-31 2019-11-21 2019-12-05 2019-12-12 2020-01-16 2020-04-02 installation within the Livestock Production Envelope on Mobile Veterinary Clinic Systems Pending GD-48 / Procurement of IDA / 63300 Productivity Improvement Post Direct Selection Direct 120,481.93 0.00 Implementati 2019-12-22 2019-12-27 2020-01-31 2023-12-31 FMD Vaccine on Improving Risk Management GD 66 / Procurement of and Climate Resilience of Open - Single Stage - One Under Mobile Veterinary Clinic IDA / 63300 Prior Request for Bids 11,934,216.87 0.00 2020-02-09 2020-03-05 2020-04-16 2020-05-16 2020-06-27 2021-06-22 Livestock Production International Envelope Review with Registration Systems Improving Risk Management GD-66 / Procurement of and Climate Resilience of Single Stage - One Mobile Veterinary Clinic IDA / 63300 Prior Request for Bids Open - National 11,934,216.87 0.00 Canceled 2019-08-19 2019-09-09 2019-09-23 2019-09-30 2019-11-04 2020-01-20 Livestock Production Envelope with Registration Systems NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DLS/DRMP/PPA/NC-03A / Pending Study tour in India for Project Management IDA / V1040 Prior Direct Selection Direct 32,017.81 0.00 Implementati 2018-06-10 2018-06-15 2018-07-20 2019-01-16 Insurance, co-operative and Monitoring and Evaluation on Dairy Hub model in India DLS/DRMP/PPA/NC-01C / Pending Project Management Request for Single Stage - One Workshop, Conference, IDA / V1040 Post Limited 6,300.00 0.00 Implementati 2018-09-04 2018-10-30 2019-04-28 Monitoring and Evaluation Quotations Envelope Meeting, FGD on DLS/DRMP/PPA/NC-01 / Workshop, Conference, Meeting, FGD: In some Project Management Request for Single Stage - One cases Direct Procurement IDA / V1040 Post Limited 6,300.00 5,917.16 Signed 2018-06-25 2018-03-12 2018-08-20 2018-03-19 2019-02-16 Monitoring and Evaluation Quotations Envelope and in some cases Request for Quotation, as and when required basis. Page 8 DLS/DRMP/PPA/ NC-03 / Foreign Study tour on Food Pending safety value chain practices Project Management IDA / V1040 Post Direct Selection Direct 64,036.00 0.00 Implementati 2018-09-17 2018-09-22 2018-10-05 2018-11-19 in USA/Canada/Europe for Monitoring and Evaluation on DG, DLS, Secretary, MOFL including govt. team DLS/LDDP/S-72 / Vehicle Rent for PMU (12 Months, Pending Effective from January, Project Management IDA / 63300 Post Direct Selection Direct 11,566.00 0.00 Implementati 2019-04-18 2019-04-22 2019-05-09 2019-12-31 2019). The Agreement Monitoring and Evaluation on signing date between 2 parties is 19/12/2018 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DLS/DRMP/PPA/S-17 / Designing and Costing of Integrated Livestock Manure Project Management Quality And Cost- Pending IDA / V1040 Post Open - National 6,403.00 0.00 2018-09-16 2018-09-19 2018-09-26 2018-09-30 2018-10-05 2018-10-14 2018-10-30 2018-12-04 Management Plant for Monitoring and Evaluation Based Selection Implementation Central Cattle Breeding & Dairy Firm - CCDF DLS/LDDP/S-40 / Website Project Management Quality And Cost- Pending Development and Operation IDA / 63300 Post Open - National 120,482.00 0.00 2019-04-18 2019-04-22 2019-05-12 2019-05-16 2019-05-20 2019-05-30 2019-06-20 2023-12-31 Monitoring and Evaluation Based Selection Implementation for PMU DLS/LDDP/S-41 / Developed Project Management Project Management Quality And Cost- Pending IDA / 63300 Post Open - National 100,000.00 0.00 2019-06-30 2019-07-14 2019-08-04 2019-08-18 2019-08-25 2019-09-22 2019-10-06 2020-10-05 Information System (PMIS) Monitoring and Evaluation Based Selection Implementation and Accounting Software DLS/LDDP/S-67 / Agro- Business Planning, Technology and Marketing Quality And Cost- Open - Under Advice and Implementation IDA / 63300 Productivity Improvement Prior 6,000,000.00 0.00 2019-07-25 2020-01-29 2019-08-15 2020-02-03 2019-09-28 2019-10-26 2019-11-25 2019-12-30 2020-02-03 2021-02-02 Based Selection International Implementation Support Livestock and Dairy Development Project (LDDP) LDDP/S-39 / Consulting Services for Design and Supervision of Civil, Project Management Quality And Cost- Open - Under IDA / 63300 Prior 3,750,000.00 0.00 2019-07-21 2019-08-08 2019-08-11 2019-08-09 2019-09-15 2020-03-08 2019-10-06 2019-11-05 2019-12-10 2020-01-14 2021-01-13 Electrical & Mechanical Monitoring and Evaluation Based Selection International Implementation works and other procurement SD-73 / PMU will hired Computerized Project Management and Information Project Management Quality And Cost- Pending System (CPMIS) firm to IDA / 63300 Post Open - National 100,000.00 0.00 2019-09-01 2019-09-15 2019-10-13 2019-10-20 2019-10-27 2019-11-10 2019-12-01 2023-12-31 Monitoring and Evaluation Based Selection Implementation design and develop computerized data entry and reporting system software DLS/LDDP/S-39 / Engineering Consulting Firm Selection for site survey, Project Management Quality And Cost- Open - IDA / 63300 Prior 3,750,000.00 0.00 Canceled 2019-04-18 2019-04-22 2019-05-12 2019-05-16 2019-05-20 2019-05-27 2019-06-17 2023-12-31 Drawing, Design and Monitoring and Evaluation Based Selection International Supervision of construction works Page 9 S-7 / The PMU will hire Environmental and Social Project Management Quality And Cost- Pending IDA / 63300 Post Open - National 361,445.78 0.00 2020-03-22 2020-04-12 2020-05-26 2020-06-23 2020-07-23 2020-08-27 2020-10-01 2023-12-31 Impact Assessment (ESIA) Monitoring and Evaluation Based Selection Implementation firm for 06 (six) Months INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DLS/DRMP/PPA/S-03 / Individual Project Management Pending Project Management IDA / V1040 Post Consultant Open 44,183.56 0.00 2018-04-25 2018-06-13 2018-07-04 2018-08-08 2019-02-04 Monitoring and Evaluation Implementation Consultant (Team Leader) Selection DLS/DRMP/PPA/S-05 / Individual Development Project Proposal Project Management Pending IDA / V1040 Post Consultant Limited 22,091.78 0.00 2018-04-09 2018-04-14 2018-05-05 2018-06-09 2018-12-06 (DPP) Preparation Monitoring and Evaluation Implementation Selection Specialist DLS/DRMP/PPA/S-07 / Individual Project Management Pending Monitoring & Evaluation IDA / V1040 Post Consultant Limited 22,091.78 0.00 2018-04-26 2018-05-01 2018-05-22 2018-06-26 2018-12-23 Monitoring and Evaluation Implementation Specialist Selection Individual DLS/DRMP/PPA/S-08 / Project Management Pending IDA / V1040 Post Consultant Limited 14,727.85 0.00 2018-06-03 2018-06-08 2018-06-29 2018-08-03 2019-01-30 Gender Specialist Monitoring and Evaluation Implementation Selection DLS/DRMP/PPA/S-12 / Individual Project Management Pending Market Development and IDA / V1040 Post Consultant Limited 29,455.71 0.00 2018-05-08 2018-05-13 2018-06-03 2018-07-08 2019-01-04 Monitoring and Evaluation Implementation Value Chain Specialist Selection Individual DLS/DRMP/PPA/S-15 / Project Management Pending IDA / V1040 Post Consultant Limited 22,091.78 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 Cattle Insurance Specialist Monitoring and Evaluation Implementation Selection DLS/DRMP/PPA/S-16 / Other Specialist in the areas Individual of (i) Engineer Consultant Project Management Pending IDA / V1040 Post Consultant Limited 36,819.64 0.00 2018-06-28 2018-07-03 2018-07-24 2018-08-28 2019-02-24 and (ii) Project Monitoring and Evaluation Implementation Selection Implementation and Management DLS/LDDP/SD-22 / PMU Individual Project Management Under will hire engineering Expert IDA / 63300 Post Consultant Open 202,409.00 0.00 2019-04-23 2019-07-03 2019-07-05 2019-08-09 2023-01-20 Monitoring and Evaluation Implementation (01 Person) for 42 month Selection DLS/LDDP/S-36A / PMU Individual will hired Procurement Project Management IDA / 63300 Prior Consultant Open 202,409.00 0.00 Canceled 2019-04-18 2019-05-16 2019-05-23 2019-06-27 2023-12-31 Specialist (1 nos) for 48 Monitoring and Evaluation Selection month DLS/LDDP/S-36B / PMU Individual Project Management will hire 01 procurement IDA / 63300 Prior Consultant Open 202,409.00 0.00 Canceled 2019-04-18 2019-05-16 2019-05-23 2019-06-27 2023-12-31 Monitoring and Evaluation specialist for 48 MM Selection DLS/LDDP/S-38A / PMU Individual will hired Financial Project Management IDA / 63300 Post Consultant Open 180,723.00 0.00 Canceled 2019-04-18 2019-05-16 2019-05-30 2019-06-27 2023-12-31 Management Specialist (1 Monitoring and Evaluation Selection nos) for 50 month DLS/LDDP/S-38B / PMU Individual will hired Financial Project Management IDA / 63300 Post Consultant Open 180,723.00 0.00 Canceled 2019-04-18 2019-05-16 2019-05-30 2019-06-27 2023-12-31 Management Specialist (1 Monitoring and Evaluation Selection nos) for 50 month Page 10 SD-15 / PMU will hired Individual Project Management Under Junior Monitoring Specialist IDA / 63300 Post Consultant Open 151,807.23 0.00 2019-09-15 2019-10-29 2019-10-13 2019-10-20 2019-11-24 2023-12-31 Monitoring and Evaluation Implementation 01 (One) for 36 Months Selection SD-64 / PMU will hired Consulting services for Individual Project Management Pending preparing vaccination card, IDA / 63300 Post Consultant Open 6,506.02 0.00 2019-09-15 2019-10-13 2019-10-20 2019-11-24 2023-12-31 Monitoring and Evaluation Implementation training manual, and leaflets Selection etc SD-24 / Project Individual Project Management Management Expert: PMU IDA / 63300 Prior Consultant Open 231,325.30 0.00 Canceled 2019-10-13 2019-11-13 2019-12-01 2019-12-22 2020-01-26 2023-12-31 Monitoring and Evaluation will hired expert for 48 MM Selection SD-27 / Junior Agribusiness Individual Project Management Under Specialist: PMU will hired IDA / 63300 Post Consultant Open 86,746.99 0.00 2019-10-20 2019-10-29 2019-12-08 2019-12-29 2020-02-02 2023-12-31 Monitoring and Evaluation Implementation expert for 24 MM Selection SD-34 / Environment and Individual Social Safeguard Specialist: Project Management Under IDA / 63300 Prior Consultant Open 231,325.30 0.00 2019-11-03 2019-11-27 2019-12-22 2020-01-12 2020-02-16 2023-12-31 PMU will hired expert for Monitoring and Evaluation Implementation Selection 48 MM SD-35 / Senior Procurement Individual Project Management Under Specialist: PMU will hired IDA / 63300 Prior Consultant Open 231,325.30 0.00 2019-09-22 2020-02-24 2019-11-10 2019-12-01 2020-01-05 2023-12-31 Monitoring and Evaluation Implementation expert for 48 MM Selection SD-37 / Senior Financial Individual Management Specialist Project Management Under IDA / 63300 Prior Consultant Open 289,156.63 0.00 2019-09-22 2019-11-27 2019-11-10 2019-12-01 2020-01-05 2023-12-31 (SFMS): PMU will hired Monitoring and Evaluation Implementation Selection expert for 60 MM SD-38 (A) / Junior Individual Financial Management Project Management Pending IDA / 63300 Post Consultant Open 180,722.89 0.00 2019-09-22 2019-11-10 2019-12-01 2020-01-05 2023-12-31 Specialist: PMU will hired Monitoring and Evaluation Implementation Selection expert for 50 MM SD-38 (B) / Junior Individual Financial Management Project Management Pending IDA / 63300 Post Consultant Open 180,722.89 0.00 2019-09-22 2019-11-10 2019-12-01 2020-01-05 2023-12-31 Specialist: PMU will hired Monitoring and Evaluation Implementation Selection expert for 50 MM SD-12 / PMU will hired 01 Individual Position of Senior Monitoring Project Management Under IDA / 63300 Post Consultant Open 231,325.30 0.00 2019-10-20 2020-01-30 2019-12-08 2019-12-29 2020-02-02 2020-07-31 $ Evaluation Specialist (48 Monitoring and Evaluation Implementation Selection Month) SD-30 / Food Safety and Individual Quality Control Expert: Project Management Under IDA / 63300 Post Consultant Open 202,409.64 0.00 2019-11-03 2020-01-30 2019-12-22 2020-01-12 2020-02-16 2023-12-31 PMU will hired expert for Monitoring and Evaluation Implementation Selection 42 MM SD-20 / PMU will hired Individual Project Management Under Animal Health Expert 01 IDA / 63300 Post Consultant Open 202,409.64 0.00 2019-10-24 2020-01-30 2019-11-21 2019-11-28 2020-01-02 2024-02-21 Monitoring and Evaluation Implementation (One) for 42 Months Selection SD-17 / PMU will hire Individual Project Management Under Training & Extension Expert IDA / 63300 Post Consultant Open 231,325.30 0.00 2019-10-20 2020-01-30 2019-11-17 2019-11-24 2019-12-29 2024-01-28 Monitoring and Evaluation Implementation 01 (One) for 48th months Selection SD-14 / PMU will hired 01 Individual Project Management Under Position of ICT Expert (48 IDA / 63300 Post Consultant Open 231,325.30 0.00 2019-10-24 2020-01-30 2019-12-12 2020-01-02 2020-02-06 2020-08-04 Monitoring and Evaluation Implementation Month) Selection Page 11 SD-26 / Senior Agri- Individual Project Management Pending Business Specialist: PMU IDA / 63300 Post Consultant Open 231,325.30 0.00 2019-10-20 2019-12-08 2019-12-29 2020-02-02 2023-12-31 Monitoring and Evaluation Implementation will hired expert for 48 MM Selection SD-18 / National Dairy Individual Project Management Under Expert: PMU will hired IDA / 63300 Post Consultant Open 231,325.30 0.00 2019-10-24 2020-01-30 2019-12-12 2020-01-02 2020-02-06 2020-08-04 Monitoring and Evaluation Implementation Expert for 48 MM Selection SD-36 (A) / Junior Individual Project Management Pending Procurement Specialist: PMU IDA / 63300 Post Consultant Open 202,409.64 0.00 2019-09-22 2019-12-08 2019-12-12 2019-12-22 2023-12-31 Monitoring and Evaluation Implementation will hired expert for 48 MM Selection SD-36 (B) / Junior Individual Project Management Pending Procurement Specialist: PMU IDA / 63300 Post Consultant Open 202,409.64 0.00 2019-09-22 2019-12-08 2019-12-15 2019-12-29 2023-12-31 Monitoring and Evaluation Implementation will hired expert for 48 MM Selection LDDP_SD-24 / Project Individual Project Management Under Management Expert: PMU IDA / 63300 Post Consultant Open 231,325.30 0.00 2020-01-20 2019-11-19 2020-03-09 2020-03-30 2020-05-04 2020-09-01 Monitoring and Evaluation Implementation will hired expert for 48 MM Selection S-29 / International Individual Project Management Under Slaughter/Meat Processing IDA / 63300 Post Consultant Open 173,493.98 0.00 2020-02-16 2020-01-30 2020-04-27 2020-05-11 2020-06-15 2023-12-31 Monitoring and Evaluation Implementation Expert 12 person-months Selection SD-21 / PMU will hire Individual Project Management Under Animal Reproductive Health IDA / 63300 Post Consultant Open 202,409.64 0.00 2020-02-16 2020-01-30 2020-03-22 2020-04-05 2020-05-10 2023-12-31 Monitoring and Evaluation Implementation Expert 42 person/months Selection SD-23 / Ruminant Nutrition Individual Project Management Under expert: PMU will hired IDA / 63300 Post Consultant Open 202,409.64 0.00 2020-02-16 2020-01-30 2020-03-23 2020-04-13 2020-05-18 2024-04-22 Monitoring and Evaluation Implementation expert for 42 MM Selection SD-25 / PMU will hired Individual Climate Smart Livestock Project Management Under IDA / 63300 Post Consultant Open 202,409.64 0.00 2020-02-16 2020-01-30 2020-03-22 2020-04-05 2020-05-10 2023-12-31 Husbandry Expert (National) Monitoring and Evaluation Implementation Selection for 42 person/months SD-13 / PMU will hire Individual Knowledge Management Project Management Pending IDA / 63300 Post Consultant Open 202,409.64 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2023-12-31 Specialist 42 person/Months Monitoring and Evaluation Implementation Selection (01 Position) SD-19 / PMU will hire Individual Project Management Pending Poultry Nutrition Expert 42 IDA / 63300 Post Consultant Open 202,409.64 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2023-12-31 Monitoring and Evaluation Implementation person/Months (01 Position) Selection SD-28 / PMU will hire Individual International Dairy Project Management Pending IDA / 63300 Post Consultant Open 173,493.98 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2023-12-31 Processing Expert for 12 Monitoring and Evaluation Implementation Selection Months (01 Position) SD-31 / PMU will hire Individual Project Management Pending AMR Surveillance Expert for IDA / 63300 Post Consultant Open 173,493.98 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2023-12-31 Monitoring and Evaluation Implementation 36 months (01 Position) Selection SD-32 / PMU will hire Individual Project Management Pending Social and Gender Specialist IDA / 63300 Post Consultant Open 86,746.99 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2023-12-31 Monitoring and Evaluation Implementation for 18 Months (01 Position) Selection SD-33 / PMU will hire Individual Communication and Public Project Management Pending IDA / 63300 Post Consultant Open 115,662.65 0.00 2020-03-01 2020-04-19 2020-05-10 2020-06-14 2023-12-31 Relation Expert for 24 Monitoring and Evaluation Implementation Selection months (01 Position) Page 12