Tianjin Urban Transport Improvement Project Procurement Plan The procurement plan will cover the whole period of the project implementation. The PMO shall update the procurement plan throughout the duration of the project at least annually by including contracts previously awarded. All procurement plans, their updates or modifications shall be subject to Bank’s prior review and no objection before implementation. I. General 1. Project information: Country供 China Borrower: The People’s Republic of China Project Name: Tianjin Urban Transport Improvement Project Loan No: IBRD 85650-CN Project Code: P148129 Project Implementation Agency (PIA): The Project Management Office, Tianjin Urban & Rural Construction Committee (PMO) 2. Bank’s approval Date of the procurement Plan: Original: October 16, 2015 3. Date of General Procurement Notice: Oct供2015 4. Period covered by this procurement plan: 2016-2021 II. Goods and Works and Non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Category Contract Value (US$) Procurement Method Bank Prior Review Goods/IT Systems and 咨=10 million ICB Non-Consulting All contracts >= USD 4 million. Services 咨=500k - < 10 million NCB 1 Remarks: Where goods are not normally available within China, the method of procurement will be ICB even if the contract value is less than USD 10 million. < 500 K Shopping None All DC contracts>= US$ 4 N/A DC million. >=40 million ICB All contracts >= USD 15 million. 咨=500k - < 40 million NCB Works/ Supply & Installation < 500 K Shopping None 供供供供/供供供供供 N/A DC All contracts >= USD 15 million. ICB: International Competitive Bidding NCB: National Competitive Bidding Notes: DC: Direct Contracting NA: Not Applicable 2. Prequalification. Bidders for all ICB works contracts shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: NA. 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: Retroactive financing will be agreed under this project. . Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures. III. Selection of Consultants 2 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditure Category Contract Value (US$) Selection Method Bank Prior Review >= 300,000 QCBS, QBS Firms: All contracts >=USD 2 million; < 300,000 QCBS, QBS, CQS Firms: All SSS contracts >= USD 1 million; Consultants N/A SSS Individual Consultant : All contracts >=USD 400,000; 咨咨 SSS for individual consultant: >=USD 400,000 N/A IC QCBS: Quality- and Cost-Based Selection QBS: Quality-Based Selection CQS: Selection Based on the Consultants’ Qualifications Notes: SSS: Single-Source Selection IC: Individual Consultant selection procedure NA: Not Applicable 1. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD500, 000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 2. Any Other Special Selection Arrangements: Retroactive financing will be agreed under this project. Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures. 3. Consultancy Assignments with Selection Methods and Time Schedule 3 PROCUREMENT China : China: Tianjin Urban Transport Improvement Project PLAN General Information Country: China Banks Approval Date of the Original Procurement Plan: 2017-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-07-11 Project ID: P148129 GPN Date: 2017-07-09 Project Name: China: Tianjin Urban Transport Improvement Project Loan / Credit No: IBRD / 85650 Executing Agency(ies): Tianjin Urban Transport PMO WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A-1 / China Tianjin NMT demonstration Part (Heping) Green Transport Improvement in Single Stage - One IBRD / 85650 Prior Request for Bids Open - National 17,448,185.00 13,952,999.96 Signed 2017-12-25 2018-02-01 2017-12-30 2018-02-24 2018-02-10 2018-03-29 2018-03-12 2018-04-09 2018-04-16 2018-04-27 2018-10-13 including Binjiang Road, Haerbin Heping and Nankai Districts Envelope Road, and Chifeng Road A-2 / China Tianjin NMT demonstration Part (Nankai) Green Transport Improvement in Single Stage - One Under IBRD / 85650 Post Request for Bids Open - National 5,832,710.00 3,919,666.17 2017-07-31 2018-04-25 2017-08-05 2017-09-16 2018-06-06 2017-10-16 2018-06-15 2017-11-20 2018-05-19 including Dongmennei Road Heping and Nankai Districts Envelope Implementation Shuige Road D-1 / China Tianjin Nankai Request for Single Stage - One Under IBRD / 85650 Bus Terminal Development Post Limited 483,200.00 0.00 2017-08-05 2017-09-30 2018-03-29 People's Hospital Bus Terminal Quotations Envelope Implementation B-1 / Metro Stations connection Single Stage - One Under IBRD / 85650 Metro Access Improvement Post Request for Bids Open - National 1,371,886.00 1,171,152.15 2018-05-08 2018-05-07 2018-05-08 2018-06-19 2018-06-06 2018-07-19 2018-06-11 2018-08-23 2019-02-19 project in Nankai District Envelope Implementation Green Transport Improvement in Single Stage - One Pending A-3 / Heping NMT Phase II IBRD / 85650 Prior Request for Bids Open - National 26,813,830.00 0.00 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 2019-11-26 Heping and Nankai Districts Envelope Implementation Green Transport Improvement in Single Stage - One Pending A-4 / Nankai NMT Phase II IBRD / 85650 Prior Request for Bids Open - National 19,500,750.00 0.00 2018-11-28 2018-12-03 2019-01-14 2019-02-13 2019-03-20 2020-01-14 Heping and Nankai Districts Envelope Implementation Green Transport Improvement in Single Stage - One Pending A-5 / Heping NMT Phase III IBRD / 85650 Post Request for Bids Open - National 9,480,310.00 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 Heping and Nankai Districts Envelope Implementation Green Transport Improvement in Single Stage - One Pending A-6 / Nankai NMT Phase III IBRD / 85650 Post Request for Bids Open - National 7,055,120.00 0.00 2020-04-09 2020-04-14 2020-05-26 2020-06-25 2020-07-30 2021-01-26 Heping and Nankai Districts Envelope Implementation B-2 / Meter Connection Hebei Single Stage - One Pending IBRD / 85650 Metro Access Improvement Prior Request for Bids Open - National 26,816,880.00 0.00 2018-12-19 2018-12-19 2019-01-30 2019-03-01 2019-04-05 2020-01-30 District Envelope Implementation B-3 / Metro Connection Heping, Single Stage - One Pending Hexi, Hongqiao, and Hedong IBRD / 85650 Metro Access Improvement Post Request for Bids Open - National 2,971,810.00 0.00 2019-06-13 2019-06-13 2019-07-25 2019-08-24 2019-09-28 2020-03-26 Envelope Implementation Districts B-4 / Metro Connection in Single Stage - One Pending Dongli, Beichen, Jinnan, Xiqing IBRD / 85650 Metro Access Improvement Post Request for Bids Open - National 3,116,430.00 0.00 2020-04-16 2020-04-16 2020-05-28 2020-06-27 2020-08-01 2021-01-28 Envelope Implementation Districts D-2 / Nankai District Qingnian Request for Single Stage - One Pending IBRD / 85650 Bus Terminal Development Post Limited 314,230.00 0.00 2020-06-15 2020-08-10 2021-02-06 Road Station Quotations Envelope Implementation GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Bus Terminal Development Technical Assistance E-2 / Research on car parking Public Bike Sharing System Consultant mechanism of core area of IBRD / 85650 (PBS) Pilot Prior Qualification Open - International N 200,000.00 227,839.24 Signed 2015-11-23 2016-02-21 2016-03-22 2016-05-11 2016-05-21 2016-05-05 2017-05-16 central city Metro Access Improvement Selection Green Transport Improvement in Heping and Nankai Districts Bus Terminal Development Technical Assistance E-1A / Research on the green Public Bike Sharing System transportation development Quality Based IBRD / 85650 (PBS) Pilot Prior Open - International N 1,500,000.00 1,734,769.74 Signed 2015-11-23 2016-02-21 2016-05-21 2016-06-20 2016-07-20 2016-05-30 2016-09-18 2016-05-30 2017-09-13 strategy on Tianjin urban (Phase Selection Metro Access Improvement I) Green Transport Improvement in Heping and Nankai Districts INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Page 2