PROCUREMENT PLAN (Textual Part) Project information: Mali, Strengthening Climate Resilience in Mali, P161406 Project Implementation agency: Ministry of security and Civil Protection Date of the Procurement Plan: February 1st, 2020 Period covered by this Procurement Plan: January 1 to December 31, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. - When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree N °2015-0604 / P-RM of September 25, 2015 relating to the Code of Public Procurement and Public Service Delegations and the decree N ° 2015-3731 / MEF-SG of October 22, 2015 setting the terms of application of the Decree N °2015-0604 / P-RM, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. 1 - To avoid any risk of non-compliance of national procedures with the principles and standards of the World Bank, when they are used in the context of procurement for this project, the standard World Bank procurement documents will be given priority used in the national circuit for the acquisition of goods, works and services. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as specified below :  Goods: not applicable for the contracts in the Procurement Plan;  Works: applicable for the contracts in the Procurement Plan. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. The project is in the start-up phase and benefits from the support of the Bank for certain consulting services activities directly implemented by the Bank in CREWS. (Paragraph 3.10-b of the Procurement Regulations). Other Relevant Procurement Information. This manual includes eligible activities, services and work approved by the World Bank. This is emergency support to save people and their property in the event of a natural disaster. The activities to be carried out on this component are endowed with financial resources drawn from the other components of the project on the basis of an official declaration of crisis by the Government. Contracts for these activities follow standard procurement principles and are carried out as an emergency project. Contingency Emergency Response Component (CERC) Operational Manuel has been established to guide the implementation of these activities. 2 PROCUREMENT Mali : Strengthening Climate Resilience in Mali Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2020-03-21 2021-03-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161406 GPN Date: Project Name: Strengthening Climate Resilience in Mali Project Loan / Credit No: IDA / D4730 Strengthening Climate Resilience Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ML-HYDROMET-160015-CW- Improvement of Hydromet RFB / Travaux de Single Stage - One En attente 2021-07- IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 314,135.00 0.00 2020-09-17 2020-09-22 2020-11-03 2020-12-03 2021-01-07 réhabilitation du bâtiment de Envelope d'exécution 06 Infrastructure la DSGRE de l'Hydraulique ML-HYDROMET-160458-CW- Improvement of Hydromet RFB / Travaux de Single Stage - One En attente 2023-01- IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 680,000.00 0.00 2020-09-30 2020-10-09 2020-11-20 2020-12-10 2021-01-14 modernisation du Centre de Envelope d'exécution 14 Infrastructure Prévisions et de calcul ML-HYDROMET-160235-CW- Improvement of Hydromet RFB / Travaux d'aménagement Single Stage - One En attente 2021-08- IDA / D4730 and Early Warning A posteriori Demande de prix Open 127,500.00 0.00 2020-10-27 2020-12-22 de la salle des archives de la Envelope d'exécution 19 Infrastructure météo ML-HYDROMET-160196-CW- RFB / Travaux de construction Improvement of Hydromet Single Stage - One En attente 2022-06- du bâtiment du Centre IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 1,458,000.00 0.00 2020-08-27 2020-09-01 2020-10-13 2020-11-12 2020-12-17 Envelope d'exécution 10 National des Opérations Infrastructure d'Urgences ML-HYDROMET-160474-CW- Improvement of Hydromet RFB / Travaux d'électrification Single Stage - One En attente 2021-08- IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 255,000.00 0.00 2020-09-08 2020-09-15 2020-10-27 2020-11-16 2020-12-14 du bâtiment de la météo par Envelope d'exécution 11 Infrastructure de l’énergie solaire ML-HYDROMET-160463-CW- RFQ / Travaux de Single Stage - One En attente 2021-04- IDA / D4730 Project Management A posteriori Demande de prix Limited 41,400.00 0.00 2020-08-25 2020-10-13 réhabilitation des bureaux de Envelope d'exécution 11 l'UCP ML-HYDROMET-171247-CW- Enhancement of Service Single Stage - One En attente 2021-01- RFQ / Travaux de curage des IDA / D4730 Delivery and Warnings to A posteriori Demande de prix Limited 68,611.00 0.00 2020-05-20 2020-07-15 Envelope d'exécution 11 caniveaux Communities ML-HYDROMET-189220-CW- Enhancement of Service Passation de DIR / Travaux d'extension du En attente 2020-12- IDA / D4730 Delivery and Warnings to A posteriori marché de gré à Direct 68,610.00 0.00 2020-08-20 2020-08-25 2020-09-11 curage des collecteurs à d'exécution 10 Communities gré Bamako ML-HYDROMET-189221-CW- Enhancement of Service Passation de DIR / Travaux d'extension de En attente 2020-12- IDA / D4730 Delivery and Warnings to A posteriori marché de gré à Direct 34,305.00 0.00 2020-08-20 2020-08-25 2020-09-02 curage des caniveaux à d'exécution 01 Communities gré Bamako ML-HYDROMET-171241-CW- Enhancement of Service Single Stage - One En attente 2021-01- RFQ / Travaux de curage des IDA / D4730 Delivery and Warnings to A posteriori Demande de prix Limited 34,305.00 0.00 2020-05-17 2020-07-12 Envelope d'exécution 08 collecteurs Communities GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160028-GO- Improvement of Hydromet Single Stage - One En attente RFB / Véhicules de secours IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 475,000.00 0.00 2020-03-03 2020-03-08 2020-04-19 2020-05-19 2020-06-23 2020-08-22 Envelope d'exécution spécialisés Infrastructure ML-HYDROMET-160467-GO- Improvement of Hydromet Single Stage - One En attente RFB / Installation de données IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 200,000.00 0.00 2020-09-09 2020-09-18 2020-10-30 2020-11-19 2020-12-17 2021-04-16 Envelope d'exécution de detétection de foudre Infrastructure ML-HYDROMET-160445-GO- Improvement of Hydromet Single Stage - One En cours RFQ / Engin à deux roues IDA / D4730 and Early Warning A posteriori Demande de prix Limited 29,800.00 0.00 2020-03-25 2020-05-08 2020-05-22 Envelope d'exécution pour la météo et l'UCP Infrastructure ML-HYDROMET-160426-GO- Improvement of Hydromet RFB / Équipements en moyens Single Stage - One En attente IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 250,000.00 0.00 2020-03-03 2020-03-08 2020-04-19 2020-05-19 2020-06-10 2020-09-08 de transmissions pour Envelope d'exécution Infrastructure véhicules et postes fixes ML-HYDROMET-160476-GO- Improvement of Hydromet RFQ / Equipements en Single Stage - One En cours IDA / D4730 and Early Warning A posteriori Demande de prix Limited 40,300.00 0.00 2020-04-06 2020-05-05 2020-05-15 2020-06-14 mobiliers pour la gestion de Envelope d'exécution Infrastructure projet ML-HYDROMET-160223-GO- Improvement of Hydromet Single Stage - One En attente RFB / Equipements IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 950,000.00 0.00 2020-03-12 2020-03-24 2020-05-05 2020-06-04 2020-07-09 2020-09-07 Envelope d'exécution informatiques - SAP Infrastructure ML-HYDROMET-160393-GO- Improvement of Hydromet Single Stage - One En attente RFB / Equipements divers IDA / D4730 and Early Warning A posteriori Demande de prix Limited 39,400.00 0.00 2020-04-28 2020-06-23 2020-12-20 Envelope d'exécution pour la gestion de projet. Infrastructure ML-HYDROMET-160421-GO- RFB / Installation des stations Capacity Building and Single Stage - One En attente automatiques synoptiques et IDA / D4730 A priori Appel d'offres Open - National 1,900,000.00 0.00 2020-07-08 2020-07-16 2020-08-27 2020-09-26 2020-10-31 2021-02-28 Institutional Development Envelope d'exécution agro-météorologiques et d’alimentation solaire (2 lots) Page 1 ML-HYDROMET-160185-GO- Improvement of Hydromet Single Stage - One En cours RFB / Véhicules pour les IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 435,000.00 0.00 2020-02-21 2020-04-15 2020-03-02 2020-04-01 2020-05-01 2020-06-05 2020-12-02 Envelope d'exécution services techniques et l'UCP Infrastructure ML-HYDROMET-160454-GO- Improvement of Hydromet Single Stage - One En cours RFB / Matériels informatiques IDA / D4730 and Early Warning A posteriori Appel d'offres Open - National 72,550.00 0.00 2020-04-16 2020-06-10 2020-04-21 2020-06-18 2020-06-02 2020-07-02 2020-08-06 2021-02-02 Envelope d'exécution pour la gestion du projet Infrastructure ML-HYDROMET-171164-GO- Enhancement of Service RFQ / Acquisition et Single Stage - One En cours IDA / D4730 Delivery and Warnings to A priori Demande de prix Limited 38,593.00 0.00 2020-05-09 2020-07-04 2020-12-31 installation de dispositifs de Envelope d'exécution Communities lavage de fabrication locale ML-HYDROMET-171159-GO- Enhancement of Service RFQ / Acquisition et Single Stage - One En cours IDA / D4730 Delivery and Warnings to A posteriori Demande de prix Limited 85,763.00 0.00 2020-05-05 2020-04-29 2020-06-30 2020-12-27 distribution gratuite de Envelope d'exécution Communities masques de confection locale NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160464-NC- RFQ / Etablissement d'un Improvement of Hydromet Single Stage - One En attente contrat formel avec les IDA / D4730 and Early Warning A posteriori Demande de prix Limited 10,000.00 0.00 2020-04-09 2020-05-14 2021-05-09 Envelope d'exécution fournisseurs d'images Infrastructure satellitaires ML-HYDROMET-160441-NC- RFP / Développement Enhancement of Service Passation de En cours d’informations agro- IDA / D4730 Delivery and Warnings to A priori marché de gré à Direct 95,000.00 0.00 2020-11-27 2020-12-02 2021-01-06 2021-06-05 d'examen météorologiques (mise à jour Communities gré de l'AGROMET TOOLBOX) ML-HYDROMET-160444-NC- RFQ / Installation d'un logiciel Single Stage - One En attente IDA / D4730 Project Management A posteriori Demande de prix Limited 24,014.00 0.00 2020-07-20 2020-09-14 2021-03-13 de gestion informatique du Envelope d'exécution système de Suivi-Evaluation ML-HYDROMET-160243-NC- Passation de En cours DIR / Installation de logiciels IDA / D4730 Project Management A priori marché de gré à Direct 41,165.00 0.00 2020-03-24 2020-03-29 2020-04-15 2021-04-10 d'examen pour la gestion de projet gré ML-HYDROMET-160241-NC- DIR / Développement Enhancement of Service Demande de Single Stage - Two En cours d'application d'alerte et de IDA / D4730 Delivery and Warnings to A posteriori Limited 355,000.00 0.00 2020-07-30 2020-05-10 2020-10-15 2020-07-29 2020-10-15 2020-07-29 2020-12-24 2020-08-30 2021-03-08 2020-11-26 2021-04-12 2021-08-10 propositions Envelope d'exécution collecte/partage Communities d'informations ML-HYDROMET-160012-NC- RFQ / Mise en place d'un SIG et d'une base de données par Enhancement of Service les stations de mesures. Après Single Stage - One En attente IDA / D4730 Delivery and Warnings to A posteriori Demande de prix Limited 50,000.00 0.00 2020-11-17 2021-01-12 2021-07-11 discussion avec le SGF, il est Envelope d'exécution Communities indiqué de répartir le financement de ce marché sur IDA à 40% et sur GCF à 60%. ML-HYDROMET-169012-NC- DIR / Montage de sketchs de sensibilisation en langues Single Stage - One En cours IDA / D4730 Project Management A posteriori Demande de prix Limited 13,700.00 0.00 2020-05-02 2020-06-02 2020-06-01 2020-07-15 locales des communautés sur Envelope d'exécution les risques, mécanismes et systèmes d'alerte précoce ML-HYDROMET-169002-NC- DIR / Montage de bandes dessinées pour la Single Stage - One En attente IDA / D4730 Project Management A posteriori Demande de prix Limited 13,700.00 0.00 2020-05-05 2020-06-10 2020-07-31 sensibilisation des enfants et Envelope d'exécution des adultes sur les systèmes d'alerte précoce ML-HYDROMET-171250-NC- Enhancement of Service RFQ / Service de diffusion de Single Stage - One En cours IDA / D4730 Delivery and Warnings to A posteriori Demande de prix Limited 30,875.00 0.00 2020-05-12 2020-04-29 2020-07-07 2020-12-31 message sur radio, télé et Envelope d'exécution Communities autres médias ML-HYDROMET-160448-NC- Improvement of Hydromet Single Stage - One RFQ / Fournir la connexion IDA / D4730 and Early Warning A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2020-03-15 2020-04-22 2021-04-17 Envelope internet à la DNH Infrastructure ML-HYDROMET-189222-NC- Capacity Building and Single Stage - One En attente RFQ / Développement d’un IDA / D4730 A posteriori Demande de prix Limited 24,500.00 0.00 2020-10-05 2020-11-30 2021-02-28 Institutional Development Envelope d'exécution site web pour le SAP ML-HYDROMET-189533-NC- Passation de En attente DIR / Acquisition de logiciel IDA / D4730 Project Management A posteriori marché de gré à Direct 24,014.00 0.00 2020-08-31 2020-09-05 2020-10-10 2021-04-08 d'exécution de suivi-évaluation gré CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160630-CS- Enhancement of Service Sélection fondée QCBS / Etude diagnostic de En cours IDA / D4730 Delivery and Warnings to A posteriori sur la qualité et le Open - National 80,000.00 0.00 2020-05-13 2020-05-30 2020-05-20 2020-08-16 2020-06-26 2020-07-24 2020-08-14 2020-09-11 2020-10-09 2020-10-21 l’outil d’enquête de d'exécution Communities coût vulnérabilité urbaine du SAP ML-HYDROMET-160652-CS- Sélection fondée CQS / Etude et suivi des Improvement of Hydromet sur les En attente travaux d'électrification du IDA / D4730 and Early Warning A posteriori Limited 45,000.00 0.00 2020-06-30 2020-07-14 2020-08-13 2020-09-17 2021-09-12 qualifications des d'exécution bâtiment de la Météo en Infrastructure consultants Energie solaire Page 2 ML-HYDROMET-160563-CS- Sélection fondée En cours QCBS / Audit des comptes du IDA / D4730 Project Management A posteriori sur la qualité et le Open - National 41,166.00 0.00 2020-11-19 2020-02-24 2020-12-03 2020-06-18 2021-01-07 2021-02-04 2021-03-05 2021-04-01 2021-04-29 2022-04-29 d'exécution Projet pour 2020 - 2022 coût ML-HYDROMET-160635-CS- QCBS / Etude sur l'hydrologie Sélection fondée Capacity Building and En cours des petits cours d'eau et cours IDA / D4730 A posteriori sur la qualité et le Open - National 150,000.00 0.00 2020-12-16 2020-05-30 2020-12-31 2020-08-16 2021-02-05 2021-03-08 2021-03-31 2021-05-05 2021-06-03 2021-10-08 Institutional Development d'exécution d'eau non pérennes sur 3 coût sites pilotes ML-HYDROMET-160647-CS- Improvement of Hydromet Sélection fondée QCBS / Etude technique et En cours IDA / D4730 and Early Warning A posteriori sur la qualité et le Open - National 100,000.00 0.00 2020-04-30 2020-05-12 2020-05-07 2020-06-11 2020-07-10 2020-07-31 2020-09-04 2020-10-02 2021-10-02 suivi des travaux de d'exécution Infrastructure coût construction du siège de SAP ML-HYDROMET-160566-CS- Improvement of Hydromet Sélection fondée QCBS / Etude et suivi des IDA / D4730 and Early Warning A posteriori sur la qualité et le Open - National 120,000.00 0.00 En cours d'examen 2020-07-23 2020-05-10 2020-08-13 2020-09-11 2020-10-12 2020-11-11 2020-12-09 2021-01-06 2021-03-07 travaux du Centre de Infrastructure coût Previsions et de calcul ML-HYDROMET-160649-CS- QCBS / Etude qualitative Sélection fondée Capacity Building and En cours globale pou un suivi potentiel IDA / D4730 A posteriori sur la qualité et le Open - National 100,000.00 0.00 2020-12-26 2020-05-30 2021-01-16 2021-02-12 2021-03-15 2021-04-14 2021-05-19 2021-06-16 2021-09-14 Institutional Development d'exécution de la qualité des cours d'eau coût (Niger, Sénégal et Volta) ML-HYDROMET-160675-CS- Improvement of Hydromet Sélection fondée QCBS / Etude architecturale et En attente IDA / D4730 and Early Warning A posteriori sur la qualité et le Open - National 162,000.00 0.00 2020-06-18 2020-07-02 2020-08-07 2020-08-27 2020-09-26 2020-10-31 2020-11-27 2022-11-27 suivi des travaux du bâtiment d'exécution Infrastructure coût du CNOU ML-HYDROMET-189525-CS- Sélection fondée CQS / Formation de 15 cadres Capacity Building and sur les En attente IDA / D4730 A posteriori Limited 25,500.00 0.00 2020-09-09 2020-09-23 2020-10-23 2020-11-27 2021-05-26 du SAP en analyse de données Institutional Development qualifications des d'exécution qualitatives consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160688-CS- Capacity Building and En attente INDV / Elaboration du plan IDA / D4730 A posteriori Individuel Limited 20,000.00 0.00 2020-05-21 2020-05-28 2020-06-11 2020-07-02 2020-07-08 Institutional Development d'exécution d'Affaire pour Mali-Meteo ML-HYDROMET-160685-CS- Improvement of Hydromet INDV / Etudes et suivi des En attente IDA / D4730 and Early Warning A posteriori Individuel Limited 22,500.00 0.00 2020-08-25 2020-09-01 2020-09-22 2020-10-13 2021-10-08 travaux aménagement de la d'exécution Infrastructure salle des archives de la Météo ML-HYDROMET-160567-CS- INDV / Élaboration du manuel En attente IDA / D4730 Project Management A posteriori Individuel Limited 42,880.00 0.00 2020-05-29 2020-06-03 2020-06-24 2020-07-15 2020-09-14 de procédures suivi évaluation d'exécution et formation des acteurs ML-HYDROMET-160670-CS- Enhancement of Service INDV / Elaboration du En attente IDA / D4730 Delivery and Warnings to A posteriori Individuel Limited 10,300.00 0.00 2020-12-02 2020-12-09 2020-12-30 2021-01-20 2021-05-20 mécanisme alerte spécifique à d'exécution Communities la protection civile ML-HYDROMET-160690-CS- Improvement of Hydromet INDV / Etude et suivi de la IDA / D4730 and Early Warning A posteriori Individuel Limited 23,000.00 0.00 En cours d'examen 2020-07-30 2020-05-10 2020-08-06 2020-08-27 2020-09-10 2021-09-10 réhabilitation du bâtiment de Infrastructure la DSGRE de l'Hydraulique ML-HYDROMET-158771-CS- En attente INDV / Un spécialiste IDA / D4730 Project Management A posteriori Individuel Open 33,242.00 0.00 2019-10-10 2019-12-06 2019-12-27 2020-01-06 2020-12-31 d'exécution Passation des marchés ML-HYDROMET-160230-CS- En attente INDV / Un spécialiste en IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 0.00 2019-11-14 2020-03-27 2020-05-05 2020-05-22 2021-05-17 d'exécution Sauvegarde Environnementale ML-HYDROMET-160203-CS- INDV / Un spécialiste en En attente IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 0.00 2019-11-14 2020-03-13 2020-04-03 2020-04-21 2021-04-16 Développement/Sauvegarde d'exécution sociale ML-HYDROMET-160189-CS- En attente INDV / Un spécialiste de Suivi IDA / D4730 Project Management A posteriori Individuel Open 28,820.00 0.00 2019-12-16 2020-02-03 2020-02-13 2020-02-23 2021-02-17 d'exécution Évaluation ML-HYDROMET-160234-CS- En attente IDA / D4730 Project Management A posteriori Individuel Open 28,820.00 0.00 2019-12-16 2020-02-03 2020-02-18 2020-03-02 2021-02-25 INDV / Un auditeur Interne d'exécution ML-HYDROMET-160232-CS- En attente INDV / Un Chargé de IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 0.00 2020-03-12 2020-05-11 2020-05-29 2020-06-09 2021-06-04 d'exécution communication du Projet ML-HYDROMET-158769-CS- En attente INDV / Specialiste en gestion IDA / D4730 Project Management A posteriori Individuel Open 33,242.00 0.00 2020-02-17 2020-02-17 2020-02-17 2020-02-17 2020-02-17 d'exécution financiere ML-HYDROMET-160568-CS- INDV / Développement des Capacity Building and En attente SOP (Manuel des procédures IDA / D4730 A posteriori Individuel Limited 50,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2020-12-15 2021-02-13 Institutional Development d'exécution administratives, financières et comptables) ML-HYDROMET-160640-CS- INDV / Elaboration des En attente manuels de gestion IDA / D4730 Project Management A posteriori Individuel Limited 9,520.00 0.00 2020-11-30 2020-12-07 2020-12-28 2021-01-11 2021-03-12 d'exécution Environnementale et Sauvegarde sociale Page 3 ML-HYDROMET-160693-CS- INDV / Etudes et suivi des En attente IDA / D4730 Project Management A posteriori Individuel Limited 7,720.00 0.00 2020-06-02 2020-06-09 2020-06-30 2020-07-14 2021-07-14 travaux de réhabilitation des d'exécution bureaux UCP ML-HYDROMET-172810-CS- Contingent Emergency En attente INDV / Recrutement d'un IDA / D4730 A posteriori Individuel Limited 17,150.00 0.00 2020-05-08 2020-05-13 2020-05-27 2020-06-10 2021-02-05 Response Component d'exécution Communicateur Traditionnel ML-HYDROMET-160031-CS- INDV / Assistance à maîtrise Capacity Building and IDA / D4730 A priori Individuel Direct 115,270.00 0.00 Annulé 2020-04-01 2020-04-10 2020-04-20 2020-04-30 2020-10-27 d'ouvrage pour la Institutional Development l'hydraulique Page 4