Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: December, 2016 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Jan 2017 to June 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 1.5 High risk Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual Consultants) 0.2 High risk 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. January 11, 2018 PROCUREMENT Kenya : Kenya Climate Smart Agriculture Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2018-01-11 2019-10-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154784 GPN Date: 2018-02-08 Project Name: Kenya Climate Smart Agriculture Project Loan / Credit No: IDA / 59450 Executing Agency(ies): MINISTRY OF AGRICULTURE, LIVESTOCK AND FISHERIES WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening KE-MOALF-117988-CW-RFB Climate-Smart Agricultural Pending / Electrical Works for Research and Seed Systems Single Stage - One IDA / 59450 Post Request for Bids Open - National 347,798.18 0.00 Implementati 2019-06-25 2019-06-30 2019-08-11 2019-09-10 2019-10-15 2020-01-13 proposed Wajir Livestock (US$53.7 million equivalent, Envelope on Training Institute of which IDA US$50.0 million equivalent) Component 2: Strengthening KE-MOALF-117990-CW-RFB Climate-Smart Agricultural / PROPOSED WAJIR Pending Research and Seed Systems Single Stage - One LIVESTOCK TRAINING IDA / 59450 Post Request for Bids Open - National 807,034.54 0.00 Implementati 2019-07-28 2019-08-02 2019-08-30 2019-09-16 2019-10-07 2020-10-01 (US$53.7 million equivalent, Envelope INSTITUTE (BUILDING on of which IDA US$50.0 WOKS) million equivalent) KE-MOALF-35272-CW-RFB Component 4: Project / RENOVATION AND Coordination and REFURBISHMENT OF 24 Management (US$29.3 Single Stage - Two IDA / 59450 Post Request for Bids Open - National 308,600.00 0.00 Canceled 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 COUNTY PROJECT million equivalent, of which Envelope OFFICES AND KCSAP IDA US$20.0 million SECRETARIAT equivalent) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening KE-MOALF-35233-GO-RFB / Climate-Smart Agricultural Pending PURCHASE OF Research and Seed Systems Single Stage - One IDA / 59450 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2017-11-23 2017-11-28 2018-01-09 2018-02-08 2018-03-15 2018-09-11 GLASSWARE/CONSUMABLE (US$53.7 million equivalent, Envelope on S of which IDA US$50.0 million equivalent) Component 3: Supporting Agro-weather, Market, Pending KE-MOALF-35261-GO-RFB / Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 92,800.00 0.00 Implementati 2017-11-23 2017-11-28 2018-01-09 2018-02-08 2018-03-15 2018-09-11 PROTECTIVE CLOTHING Services (US$32.9 million Envelope on equivalent, of which IDA US$ 30.0 million equivalent) Page 1 Component 2: Strengthening KE-MOALF-35230-GO-RFB / Climate-Smart Agricultural Pending PROCUREMENT OF Research and Seed Systems Single Stage - One IDA / 59450 Post Request for Bids Open - National 308,600.00 0.00 Implementati 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 RESEARCH FACILITIES (US$53.7 million equivalent, Envelope on LOT 5 of which IDA US$50.0 million equivalent) Component 3: Supporting KE-MOALF-35304-GO-RFB / Agro-weather, Market, Pending Purchase and Dissemination Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 443,000.00 0.00 Implementati 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 of market information 1.2m Services (US$32.9 million Envelope on SMS equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting Agro-weather, Market, KE-MOALF-48128-GO-RFB / Pending Climate, and Advisory Single Stage - One PURCHASE OF IDA / 59450 Post Request for Bids Open - National 702,790.00 0.00 Implementati 2018-02-21 2018-02-26 2018-04-09 2018-05-09 2018-06-13 2018-12-10 Services (US$32.9 million Envelope MOTORBIKES on equivalent, of which IDA US$ 30.0 million equivalent) Component 2: Strengthening Climate-Smart Agricultural KE-MOALF-48138-GO-RFB / Pending Research and Seed Systems Single Stage - One PURCHASE OF RESEARCH IDA / 59450 Post Request for Bids Open - National 950,000.00 0.00 Implementati 2018-02-21 2018-02-26 2018-04-09 2018-05-09 2018-06-13 2018-12-10 (US$53.7 million equivalent, Envelope EQUIPMENT on of which IDA US$50.0 million equivalent) KE-MOALF-48137-GO-RFB / PURCHASE OF MANUAL Component 3: Supporting WEATHER INSTRUMENTS Agro-weather, Market, AND PURCHASE OF 120 Under Climate, and Advisory Open - Single Stage - One (SETS) AWS,HYDRO MET IDA / 59450 Prior Request for Bids 3,002,400.00 0.00 Implementati 2018-02-21 2018-02-26 2018-04-09 2018-05-09 2018-06-13 2018-12-10 Services (US$32.9 million International Envelope 17 (SET),17 (SET) AGRO on equivalent, of which IDA MET STATIONS,1 (SET) US$ 30.0 million equivalent) BASE STATION AND 24 (SET) WORK STATION Component 3: Supporting KE-MOALF-48135-GO-RFB / Agro-weather, Market, UPGRADING THE Pending Climate, and Advisory Open - Single Stage - One NETWORK OF AGRO MET IDA / 59450 Prior Request for Bids 3,408,800.00 0.00 Implementati 2018-02-21 2018-02-26 2018-04-09 2018-05-09 2018-06-13 2018-12-10 Services (US$32.9 million International Envelope AND HYDRO MET on equivalent, of which IDA STATIONS US$ 30.0 million equivalent) KE-MOALF-62658-GO-RFB / PROCUREMENT OF ICT Component 3: Supporting EQUIPMENT,SUPPLY AND Agro-weather, Market, INSTALLATION OF Climate, and Advisory Single Stage - One INFORMATION SYSTEMS IDA / 59450 Post Request for Bids Open - National 130,000.00 0.00 Canceled 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 Services (US$32.9 million Envelope BIG DATA ANALYTICS equivalent, of which IDA SYSTEMS WITH HIGH US$ 30.0 million equivalent) PERFORMANCE COMPUTING (HPC) QTY 1 KE-MOALF-62660-GO-RFB / Component 3: Supporting PROCUREMENT,SUPPLY Agro-weather, Market, Under AND INSTALLATION OF Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 INFORMATION SYSTEMS Services (US$32.9 million Envelope on QTY 1 AGRO-WEATHER equivalent, of which IDA SYSTEM US$ 30.0 million equivalent) KE-MOALF-62662-GO-RFB / Component 3: Supporting PROCUREMENT,SUPPLY Agro-weather, Market, Under AND INSTALLATION OF Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 500,000.00 0.00 Implementati 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 INFORMATION SYSTEMS Services (US$32.9 million Envelope on QTY 1 CALL MANAGER equivalent, of which IDA SYSTEM AND SOLUTIONS US$ 30.0 million equivalent) Page 2 KE-MOALF-62666-GO-RFB / Component 3: Supporting PROCUREMENT,SUPPLY Agro-weather, Market, AND INSTALLATION OF Pending Climate, and Advisory Single Stage - One INFORMATION SYSTEMS IDA / 59450 Post Request for Bids Open - National 370,000.00 0.00 Implementati 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 Services (US$32.9 million Envelope QTY 1 INTERNET on equivalent, of which IDA CONNECTIVITY AND WIDE US$ 30.0 million equivalent) AREA NETWORK KE-MOALF-35228-GO-RFB / PURCHASE OF OFFICE EQUIPMENT 26 Photocopiers 63 Desktop computers Component 1: Upscaling 183 Laptops Climate-Smart Agricultural 566 Ups, Under Practices (US$163.8 million Single Stage - One 26 Photocopiers, IDA / 59450 Post Request for Bids Open - National 889,900.00 0.00 Implementati 2018-10-31 2018-11-05 2018-12-17 2019-01-16 2019-02-20 2019-08-19 equivalent, of which IDA Envelope 58 Printers on US$150.0 million eq 1 Servers uivalent) 1 Anti-Spam Messaging Gate Way 1 GPS 2 Routers 10 Lan Switches Component 4: Project KE-MOALF-82631-GO-RFB / Coordination and Procurement of 61 Motor Under Management (US$29.3 Open - Single Stage - One Vehicles - 3- NPCU IDA / 59450 Prior Request for Bids 4,288,360.00 0.00 Implementati 2018-11-07 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 million equivalent, of which International Envelope - 48- (24 Counties) on IDA US$20.0 million - 10- KALRO equivalent) Component 1: Upscaling KE-MOALF-62321-GO-RFB / Climate-Smart Agricultural Procurement of 59 Vehicles Practices (US$163.8 million Open - Single Stage - One IDA / 59450 Prior Request for Bids 4,225,160.00 0.00 Canceled 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 for 3-NCPU, 48- CPCU and equivalent, of which IDA International Envelope 8- KALRO US$150.0 million eq uivalent) KE-MOALF-62645-GO-RFB / Component 1: Upscaling PROCUREMENT OF AWS Climate-Smart Agricultural 120 (SETS), AGROMET Practices (US$163.8 million Single Stage - One STATIONS 34 (SETS), BASE IDA / 59450 Post Request for Bids Open - National 123,600.00 0.00 Canceled 2018-05-31 2018-06-05 2018-07-17 2018-08-16 2018-09-20 2019-03-19 equivalent, of which IDA Envelope STATION 75 (SETS), US$150.0 million eq HYDRO-MET STATIONS 17 uivalent) (SETS) Component 1: Upscaling Climate-Smart Agricultural KE-MOALF-35229-GO-RFB / Practices (US$163.8 million Single Stage - One PURCHASE OF OFFICE IDA / 59450 Prior Request for Bids Open - National 3,178,200.00 0.00 Canceled 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 equivalent, of which IDA Envelope FURNITURE US$150.0 million eq uivalent) KE-MOALF-86699-GO-RFQ / Procurement of Office Furniture for the NPCU,- 8 Component 4: Project Executive Office Table, 12 Coordination and Executive Office Chair, 45 Pending Management (US$29.3 Request for Single Stage - One Visitor Chair, 1 Conference IDA / 59450 Post Open - National 50,000.00 0.00 Implementati 2018-12-04 2019-01-29 2019-02-28 million equivalent, of which Quotations Envelope Table-(30 pax), 30 on IDA US$20.0 million Conference Chair, 10 Coat equivalent) Hunger, 10 Bookshelves, 1 Reception Desk and 10 filling cabinets Component 4: Project KE-MOALF-86755-GO-RFQ / Coordination and Pending Procurement and Installation Management (US$29.3 Request for Single Stage - One IDA / 59450 Post Limited 6,435.60 0.00 Implementati 2018-12-10 2019-02-04 2019-03-06 of Smart LED screen 55 million equivalent, of which Quotations Envelope on inch Quantity 5 IDA US$20.0 million equivalent) Page 3 KE-MOALF-86750-GO-RFQ / Component 4: Project Long Range Wireless Access Coordination and Point Quantity 5 (4 at Under Management (US$29.3 Request for Single Stage - One Kilimo and 1 at KMD), IDA / 59450 Post Limited 15,450.00 0.00 Implementati 2018-12-10 2019-02-04 2019-03-06 million equivalent, of which Quotations Envelope LAN Routers Qty 2 at on IDA US$20.0 million Kilimo and KMD, LAN equivalent) Switches Qty 2 KE-MOALF-95865-GO-RFB / SUPPLY AND Component 3: Supporting INSTALLATION OF Agro-weather, Market, Under INFORMATION SYSTEM Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 1,300,000.00 0.00 Implementati 2018-08-13 2018-08-18 2018-09-29 2018-10-29 2018-12-03 2019-03-03 BIG DATA ANALYTICS Services (US$32.9 million Envelope on SYSTEM WITH HIGH equivalent, of which IDA PERFORMANCE US$ 30.0 million equivalent) COMPUTING Component 2: Strengthening Climate-Smart Agricultural KE-MOALF-35231-GO-RFB / Research and Seed Systems Single Stage - One PROCUREMENT OF IDA / 59450 Prior Request for Bids Open - National 2,561,200.00 0.00 Canceled 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 (US$53.7 million equivalent, Envelope MOTOR VEHICLES of which IDA US$50.0 million equivalent) KE-MOALF-117995-GO-RFB / PROPOSED WAJIR Component 3: Supporting LIVESTOCK TRAINING Agro-weather, Market, Pending INSTITUTE (PROJECT Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 115,553.40 0.00 Implementati 2019-07-01 2019-07-06 2019-08-05 2019-08-27 2019-09-17 2019-10-18 VEHICLES) TO BE Services (US$32.9 million Envelope on DELIVERED AT STATE equivalent, of which IDA DEPARTMENT OF US$ 30.0 million equivalent) LIVESTOCK. KE-MOALF-117992-CW-RFB / PROPOSED WAJIR LIVESTOCK TRAINING INSTITUTE LOOSE FIXTURES (CHICKEN Component 2: Strengthening CAGES ,LIBRARY TABLES Climate-Smart Agricultural AND CHAIRS,COMPUTER Pending Research and Seed Systems Request for Single Stage - One LAB WORKSTATIONS AND IDA / 59450 Post Limited 88,058.25 0.00 Implementati 2019-08-10 2019-10-05 2020-04-02 (US$53.7 million equivalent, Quotations Envelope CHAIRS,LECTURE ROOM on of which IDA US$50.0 CHAIRS WITH WRITING million equivalent) PADS,LECTURE ROOM ROSTRUM,LECTURE ROOM WHITE NOTICE BOARDS,DINNING HALL TABLES) Component 3: Supporting KE-MOALF-140962-GO-RFQ Agro-weather, Market, Pending / Procurement of Qty 23 Climate, and Advisory Single Stage - One IDA / 59450 Post Request for Bids Open - National 142,000.00 0.00 Implementati 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-21 2020-08-19 smart phones and Qty 80 Services (US$32.9 million Envelope on Tablets. equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting Agro-weather, Market, KE-MOALF-140966-GO-RFB Pending Climate, and Advisory Single Stage - One / Procurement of Qty 26 IDA / 59450 Post Request for Bids Open - National 260,000.00 0.00 Implementati 2019-11-01 2019-11-06 2019-12-06 2019-12-27 2020-01-24 2020-04-23 Services (US$32.9 million Envelope Photocopier Machines on equivalent, of which IDA US$ 30.0 million equivalent) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 Component 4: Project KE-MOALF-86813-NC-RFQ / Coordination and Pending Procurement of Internet Management (US$29.3 Request for Single Stage - One IDA / 59450 Post Open - National 43,200.00 0.00 Implementati 2018-12-04 2019-01-29 2019-02-28 bandwidth-20Mbps per million equivalent, of which Quotations Envelope on month 20x3x12 IDA US$20.0 million equivalent) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Supporting Agro-weather, Market, Consultant KE-MOALF-35273-CS-CQS / Climate, and Advisory IDA / 59450 Post Qualification Open - National 200,000.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 BASELINE SURVEYS Services (US$32.9 million Selection equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting Agro-weather, Market, Consultant KE-MOALF-35279-CS-CQS / Climate, and Advisory Pending IDA / 59450 Post Qualification Open - National 10,000.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 KCSAP WEBSITE Services (US$32.9 million Implementation Selection equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-35289-CS-CQS / Agro-weather, Market, DEVELOPMENT OF Consultant Climate, and Advisory Pending STANDARD TRAINING IDA / 59450 Post Qualification Open - National 100,000.00 0.00 2017-11-23 2017-12-14 2018-01-27 2018-02-26 2018-04-02 2018-09-29 Services (US$32.9 million Implementation MANUALS AND IEC Selection equivalent, of which IDA MATERIALS US$ 30.0 million equivalent) Component 3: Supporting Agro-weather, Market, KE-MOALF-35298-CS-CQS / Consultant Climate, and Advisory Pending Review of the VC IDA / 59450 Post Qualification Open - National 50,000.00 0.00 2017-11-23 2017-12-14 2018-01-27 2018-02-26 2018-04-02 2018-09-29 Services (US$32.9 million Implementation development/strategy/adoption Selection equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting Agro-weather, Market, Consultant KE-MOALF-35299-CS-CQS / Climate, and Advisory Pending IDA / 59450 Post Qualification Open - National 50,000.00 0.00 2017-11-23 2017-12-14 2018-01-27 2018-02-26 2018-04-02 2018-09-29 communication strategy Services (US$32.9 million Implementation Selection equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-35295-CS-CQS / Agro-weather, Market, Consultant UPDATING KEY Climate, and Advisory Pending IDA / 59450 Post Qualification Open - National 50,000.00 0.00 2018-01-31 2018-02-21 2018-04-06 2018-05-06 2018-06-10 2018-12-07 INFORMATION OF THE Services (US$32.9 million Implementation Selection TARGETED VC's equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-48124-CS-QCBS Agro-weather, Market, / ICT-BASED Climate, and Advisory Quality And Cost- Open - Under IDA / 59450 Post 307,600.00 0.00 2018-02-21 2018-03-14 2018-04-27 2018-05-25 2018-06-24 2018-07-29 2018-09-02 2019-09-02 AGRICULTURAL Services (US$32.9 million Based Selection International Implementation INFORMATION PLATFORM equivalent, of which IDA US$ 30.0 million equivalent) Page 5 KE-MOALF-48127-CS-QCBS / DEVELOPMENT OF STANDARDIZED TRAINING FOR PARTICIPATORY Component 3: Supporting INTEGRATED COMMUNITY Agro-weather, Market, DEVELOPMENT,VALUE Climate, and Advisory Quality And Cost- Open - CHAIN ANALYSIS AND IDA / 59450 Post 350,000.00 0.00 Canceled 2018-02-21 2018-03-14 2018-04-27 2018-05-25 2018-06-24 2018-07-29 2018-09-02 2019-09-02 Services (US$32.9 million Based Selection International DEVELOPMENT equivalent, of which IDA ,FIDUCIARY US$ 30.0 million equivalent) MANAGEMENT AND SOCIAL SAFEGUARDS AND AGRI-BUSINESS AND FINANCE SERVICES Component 3: Supporting Agro-weather, Market, KE-MOALF-48141-CS-QCBS Climate, and Advisory Quality And Cost- Open - IDA / 59450 Post 434,700.00 0.00 Canceled 2018-02-21 2018-03-14 2018-04-27 2018-05-25 2018-06-24 2018-07-29 2018-09-02 2019-09-02 / MIS FOR M&E Services (US$32.9 million Based Selection International equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-108769-CS-CQS Agro-weather, Market, / Consultant Service for Climate, and Advisory Quality And Cost- Open - Pending IDA / 59450 Post 309,100.00 0.00 2019-06-11 2019-07-02 2019-08-15 2019-09-12 2019-10-12 2019-11-16 2019-12-21 2020-06-08 Market Information System Services (US$32.9 million Based Selection International Implementation Development equivalent, of which IDA US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-108771-CS-CQS Agro-weather, Market, / Consultant service for Climate, and Advisory Quality And Cost- Open - Under segmentation and IDA / 59450 Post 300,000.00 0.00 2019-06-11 2019-07-02 2019-08-15 2019-09-12 2019-10-12 2019-11-16 2019-12-21 2020-06-08 Services (US$32.9 million Based Selection International Implementation registration of value chain equivalent, of which IDA stakeholders US$ 30.0 million equivalent) KE-MOALF-35284-CS-CQS / Component 3: Supporting DEVELOPMENT OF Agro-weather, Market, PERATIONAL MANUALS Consultant Climate, and Advisory FOR IDA / 59450 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-11-23 2017-12-14 2018-01-27 2018-02-26 2018-04-02 2018-09-29 Services (US$32.9 million FINANCE,PROCUREMENT Selection equivalent, of which IDA AND COMMUNITY DRIVEN US$ 30.0 million equivalent) DEVELOPMENT INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project Coordination and KE-MOALF-84065-CS-CDS / Management (US$29.3 Under CONSULTANCY SERVICES IDA / 59450 Post Direct Selection Direct 434,700.00 0.00 2018-11-14 2018-11-24 2019-01-28 2019-07-27 million equivalent, of which Implementation FOR MIS FOR M&E IDA US$20.0 million equivalent) Component 4: Project KE-MOALF-83738-CS-CDS / Coordination and CONSULTANCY SERVICES Management (US$29.3 FOR BASELINE SURVEY IDA / 59450 Prior Direct Selection Direct 1,000,000.00 0.00 Under Review 2018-11-14 2018-11-24 2019-01-28 2019-07-27 million equivalent, of which AND IMPACT IDA US$20.0 million EVALUATION equivalent) Component 3: Supporting KE-MOALF-138399-CS-CDS Agro-weather, Market, / Lead Consultant for Climate, and Advisory Pending National Cereal and Produce IDA / 59450 Post Direct Selection Direct 18,013.00 0.00 2019-11-01 2019-11-11 2019-12-23 2020-02-21 Services (US$32.9 million Implementation Board and Strategic Food equivalent, of which IDA Reserve Trust Fund US$ 30.0 million equivalent) Page 6 Component 3: Supporting KE-MOALF-140372-CS-CDS Agro-weather, Market, / Senior Consultant for Climate, and Advisory Pending National Cereal and Produce IDA / 59450 Post Direct Selection Direct 13,911.00 0.00 2019-11-01 2019-11-11 2019-12-23 2020-02-21 Services (US$32.9 million Implementation Board and Strategic Food equivalent, of which IDA Reserve Trust Fund US$ 30.0 million equivalent) Component 3: Supporting KE-MOALF-140378-CS-CDS Agro-weather, Market, / Junior Consultant for Climate, and Advisory Pending National Cereal and Produce IDA / 59450 Post Direct Selection Direct 6,064.00 0.00 2019-10-22 2019-11-01 2019-12-13 2020-02-11 Services (US$32.9 million Implementation Board and Strategic Food equivalent, of which IDA Reserve Trust Fund US$ 30.0 million equivalent) Page 7