Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Revision of Updated Procurement Plan, August 2017 2. Date of General Procurement Notice: October 10, 2016 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Category Prior Review Comments Threshold US$ 1. Goods and >= US$2 million All 2. Works >= US$ 10 million All 3. (Non-Consultant Services) >= US$2 million All 2. Prequalification. _Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: At sub-national levels (Commune/Sangkat and Community), provisions of the Project Implementation Manual (PIM) dated March 30, 2016 which has been agreed by the Bank will apply. The PIM provides for processes and procedures for procurement at sub-national levels. 4. Reference to (if any) Project Operational/Procurement Manual: the Project Implementation Manual (PIM) dated March 30, 2016 has been agreed by the Bank. 5. Summary of the Procurement Packages 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) LASE Upgrade 1.5 1 No Post NCB D/NC Earth Road DDS/ to Late- W/NC Rite Roads B/05/ (106.96Km 17 ) LASE Constructio 1.3 1 No Post NCB D/NC n of Late- DDS/ Rite Roads W/NC = 29km B/03/ 17 LASE Land 2.4 1 No Post NCB D/NC Preparation DDS/ Agriculture W/NC - B/02/ Bulldozing, 17 Leveling. Total:2,355 .50Ha LASE Constructio 1.1 1 No Post NCB D/NC n of 11 DDS/ small W/NC dams. B/06/ 17 LASE Constructio 2.86 1 No Post NCB D/NC n of earth DDS/ roads W/NC (130Km) B/04/ 17 LASE Household 0.12 1 No Post NCB D/NC Start-Up DDS/ Packages G/NC for Daung B/12/ 700 HH 17 (Solar lamp, Tent plastic, mat, blanket, water jar, water filter) LASE Office 0.18 1 No Post NCB D/NC equipment DDS/ (computers G/NC & B/03/ Photocopy 16 Machines) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2.Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) >= US$1,000,000 2. Individual >= US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million LASED/N Consulting 0.12 1 Post CQS CDDS/F/ firm for 35/17 Irrigation Design (8 sites) LASED/N Baseline 0.07 1 Post CQS CDDS/IC Survey in /30/17 year 2017 (Local Firm) LASED/N Impact 0.05 1 Post CQS CDDS/IC Survey for /31/18 2nd year of the project/Mi d-term review (Local Firm) LASED/N Final 0.12 1 Post CQS CDDS/IC Impact /32/21 Survey PROCUREMENT Cambodia : KH-Land Allocation for Social and Economic Development Project II PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2016-08-18 2020-12-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150631 GPN Date: 2016-10-10 Project Name: KH-Land Allocation for Social and Economic Development Project II Loan / Credit No: IDA / 58070 National Committee for Sub-National Democratic Development Secretariat Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Document Amount Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion Type (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned COMMUNE NO 07/17 / Water Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-12- 2018-08- well (Afredes) for Thmey 19 IDA / 58070 Preparation and Post Open - National 63,333.33 62,890.00 Signed Quotations Envelope 06 01 26 01 Units Infrastructure Development COMMUNE NO 08/17 / Water Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- well (Afredes) for Chambak 6 IDA / 58070 Preparation and Post Open - National 20,000.00 9,900.00 Signed Quotations Envelope 06 01 30 01 Units Infrastructure Development COMMUNE NO 10/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,750.00 Signed Quotations Envelope 06 31 13 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Tipo 1 QTY 1 Unit COMMUNE NO 11/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,750.00 Signed Quotations Envelope 06 31 13 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Tipo 2 QTY 1 Unit COMMUNE NO 12/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,400.00 Signed Quotations Envelope 06 31 12 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Choamkravien QTY 1 Unit COMMUNE NO 13/17 / House for Nurses & Teachers Sub-component 1.2: Land (8mx 20m x4Rooms, each Request for Single Stage - One 2017-07- 2017-08- 2017-11- 2018-08- IDA / 58070 Preparation and Post Open - National 35,000.00 32,400.00 Signed room equipped with internal Quotations Envelope 06 31 30 31 Infrastructure Development kitchen & bathroom) for Chambak QTY 1 Unit COMMUNE NO 14/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 31,500.00 Signed Quotations Envelope 06 31 04 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Sambok QTY 1 Unit COMMUNE NO 15/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,850.00 Signed Quotations Envelope 06 31 04 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Changkrang QTY 1 Unit COMMUNE NO 16/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-09- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,700.00 Signed Quotations Envelope 06 31 11 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Thmey QTY 1 Unit COMMUNE NO 17/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-09- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 30,400.00 Signed Quotations Envelope 06 31 06 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Dar QTY 1 Unit COMMUNE NO 18/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,886.00 Signed Quotations Envelope 06 31 13 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Ksach Sar QTY 1 Unit COMMUNE NO 19/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,720.00 Signed Quotations Envelope 06 31 06 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Sambok Kriel QTY 1 Unit COMMUNE NO 20/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 34,869.00 Signed Quotations Envelope 06 31 13 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Peam QTY 1 Unit COMMUNE NO 21/17 / House for Nurses & Teachers Sub-component 1.2: Land (8mx 20m x4Rooms, each Request for Single Stage - One 2017-07- 2017-08- 2017-10- 2018-08- IDA / 58070 Preparation and Post Open - National 35,000.00 34,800.00 Signed room equipped with internal Quotations Envelope 06 31 13 31 Infrastructure Development kitchen & bathroom) for Chhean Loeung QTY 1 Unit COMMUNE NO 22/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2017-07- 2017-08- 2017-08- 2018-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 33,942.00 Signed Quotations Envelope 06 31 29 31 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Raksmey Samaki QTY 1 Unit COMMUNE NO 23/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-07- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 28,900.00 Signed Quotations Envelope 06 01 15 31 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Dar (1). Total: 1 Unit COMMUNE NO 24/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-07- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 28,950.00 Signed Quotations Envelope 06 01 15 31 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Thmey (1). Total: 1 Unit COMMUNE NO 25/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-07- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 27,400.00 Signed Quotations Envelope 06 01 20 31 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Chambak (1). Total: 1 Unit Page 1 COMMUNE NO 26/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land (W=7.2m, L=17.2m, Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-07- IDA / 58070 Preparation and Post Open - National 29,000.00 28,800.00 Signed H=6.62m, Warehouse, 2 Quotations Envelope 06 01 06 31 Infrastructure Development rooms's W.C) for Choamkravien (1). Total: 1 Unit COMMUNE NO 27/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 25,400.00 Signed Quotations Envelope 06 01 11 01 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Tipo 2 (1). Total: 1 Unit COMMUNE NO 29/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 26,400.00 Signed Quotations Envelope 06 01 24 01 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Peam (1). Total: 1 Unit COMMUNE NO 30/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 28,850.00 Signed Quotations Envelope 06 01 24 31 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Chean Loeung (1). Total: 1 Unit COMMUNE NO 31/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 28,780.00 Signed Quotations Envelope 06 01 29 01 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Ksach Sor (1). Total: 1 Unit COMMUNE NO 32/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 26,300.00 Signed Quotations Envelope 06 01 24 01 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Chum Kreal (1). Total: 1 Unit COMMUNE NO 33/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2017-06- 2017-08- 2017-11- 2018-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 27,565.00 Signed Quotations Envelope 06 01 01 01 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Prey Thom (1). Total: 1 Unit LASED/NCDDS/W/NCB/02/17 / Land Preparation Agriculture- Buldozing, Leveling:LOT1: S.Kriel(100), Ksa.Sar(126.50),Peam(116.50) Sub-component 1.2: Land , Chh.loeung(103), Single Stage - One 1,913,405.7 2017-02- 2017-08- 2017-02- 2017-03- 2017-10- 2017-04- 2017-11- 2017-05- 2017-12- 2017-11- IDA / 58070 Preparation and Post Request for Bids Open - National 2,355,500.00 Signed Ra.Samaki(200), TP1(276), Envelope 5 01 24 06 20 05 19 20 24 28 20 Infrastructure Development TP2 (226.50), S.bok(100), Ch.Krang(59), Dar(97), Thmey(174)&Chambak(277). LOT2:Daung (500).Grand Total:2,355.50Ha LASED/NCDDS/W/NCB/07/17 / Construction of Primary Schools (5Rooms, 4WCs, 1Well, 1Flag Pole) Incl. 250chairs connected with Sub-component 1.2: Land Single Stage - One 2017-09- 2017-10- 2017-09- 2017-11- 2017-11- 2017-12- 2018-01- 2018-01- 2018-02- 2018-07- tables, 5Tables & 5Chairs and IDA / 58070 Preparation and Post Request for Bids Open - National 711,111.11 693,314.40 Signed Envelope 15 09 20 01 15 01 15 05 09 04 Whiteboards for: Tipo1, Infrastructure Development Chambak, Sambok, Raksmey Samaki (KSP), Ksach Sar (KCH), Choamkravien and Daung (2units) Total:8Units LASED/NCDDS/W/SP/01/17 / "Upgrade Earth Road to Late- Sub-component 1.2: Land Request for Single Stage - One 2017-12- 2018-02- 2018-02- 2018-08- Rite Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Post Open - National 158,888.89 127,836.37 Signed Quotations Envelope 20 14 09 13 Main Road, KPT Infrastructure Development Tipo 1 and 2 = 11km. " COMMUNE/KPT/W/37/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m):, Sub-component 1.2: Land Request for Single Stage - One 2018-08- 2018-10- 2018-07- 2019-03- Tipo 1 (AR3=0.95km, IDA / 58070 Preparation and Post Open - National 61,677.78 36,917.00 Signed Quotations Envelope 06 01 02 30 ART=0.71km, AR2=1.26km, Infrastructure Development AR4=1,35) Total= 4.27km. (Package1) LASED/NCDDS/W/NCB/05/17 / Upgrade Earth Road to Late- Rite Roads(W4.5mxT0.15m):LOT 1: Tipo1(9.47km), Tipo2 (10.53km) and Main Road Sub-component 1.2: Land Single Stage - One 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- (11km). Total 31km. LOT 2: IDA / 58070 Preparation and Post Request for Bids Open - National 1,544,977.78 0.00 Canceled Envelope 01 06 18 17 22 20 S.Kriel(19km), Infrastructure Development K.Sar(10.80km), Peam(11.44km), Chh.Loeung(13.72km) & Ra.Samaki(21km). Total: 75.96km. Grand Total 106.96Km LASED/NCDDS/W/NCB/03/17 / Construction of Lot 1. Late- Sub-component 1.2: Land Rite Roads (W5xT0.15xE0.5m) Single Stage - One 1,244,944.1 2019-01- 2019-09- 2019-01- 2019-02- 2019-10- 2019-03- 2019-11- 2019-04- 2019-11- 2019-10- IDA / 58070 Preparation and Post Request for Bids Open - National 1,342,000.00 Completed = 22km. Lot 2. Earth Roads Envelope 4 01 09 06 17 17 19 01 23 13 20 Infrastructure Development (W5xT0.15xE0.5m) for Daung = 29km LASED/NCDDS/W/SP/09/17 / Build board Construction, Installation and Renew Banner Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2019-02- 2018-11- (New bill board 3 sites at KSP, IDA / 58070 Preparation and Post Open - National 116,666.67 107,060.85 Signed Quotations Envelope 07 02 28 29 KPT and KCH) and Renews Infrastructure Development banner for existing bill board 9 sites. COMMUNE/KRT/W/54/18 / Construction of Health Posts (3 rooms, fense 400m, gate 1, Sub-component 1.2: Land Request for Single Stage - One 2018-03- 2018-05- 2018-04- 2018-10- well1, WC 2rooms, pipe IDA / 58070 Preparation and Post Open - National 36,666.67 34,900.00 Signed Quotations Envelope 06 01 30 28 culvert 1, incinerator 1, 200m Infrastructure Development of laterite road). 1 Unit for Da, KRT COMMUNE/KRT/W/55/18 / Construction of Health Posts (3 rooms, fense 400m, gate 1, Sub-component 1.2: Land Request for Single Stage - One 2018-03- 2018-05- 2018-04- 2018-10- well1, WC 2rooms, pipe IDA / 58070 Preparation and Post Open - National 36,666.67 36,200.00 Signed Quotations Envelope 06 01 18 28 culvert 1, incinerator 1, 200m Infrastructure Development of laterite road). 1 Unit for Thmey, KRT. LASED/NCDDS/W/NCB/08/17 / Construction of Health Posts (3 rooms, fense 400m, gate 1, well1, WC 2rooms, pipe Sub-component 1.2: Land culvert 1, incinerator 1, 200m Request for Single Stage - One 2017-02- 2017-04- 2018-04- IDA / 58070 Preparation and Post Open - National 183,333.33 0.00 Canceled of laterite road). Da (1 Unit), Quotations Envelope 06 03 03 Infrastructure Development Thmey (1 Unit) Ksach Sar (1 Unit), Chhean Loeung (1 Unit) and Daung (1 Unit). Total 5 Units. Page 2 LASED/NCDDS/W/NCB/01/17 / 1) Concrete Poles in Agriculture & Residential Lands (0.12 x 0.12 x 0.75m) = (5000 Poles), 2) Concrete Sub-component 1.2: Land Request for Single Stage - One 2017-10- 2017-12- 2018-05- Poles in Forestry & in SLC IDA / 58070 Preparation and Post Open - National 160,555.56 0.00 Canceled Quotations Envelope 07 02 31 Sites (0.3x0.3x0.4x1.5m) Infrastructure Development (150 Poles) and 3) Concrete Poles in Stream and Canal (0.2x0.2x1.5m) for Daung (200 Poles). LASED/NCDDS/W/NCB/09/18 / Upgrade Earth Road to Late- Rite Road(W4.5mxT0.15m):LOT1:K PT,Tipo=15 lines=15.73km,LOT2: KCH A) Sub-component 1.2: Land KrangLvea =22 Lines Single Stage - One 2018-08- 2018-10- 2018-08- 2018-10- 2018-01- 2018-11- 2018-12- 2018-12- 2018-12- 2019-12- IDA / 58070 Preparation and Post Request for Bids Open - National 1,128,544.44 946,643.43 Signed 25.14km),B)Peam =17 Envelope 22 04 27 08 04 07 14 12 25 12 Infrastructure Development Lines(11.44km),C)Chhean Loeung=10 Lines (9.57km)=46.15km & LOT3: KSP,RaksmeySamaki=5 Lines= 16.25km. GrandTotal=78.13Km. COMMUNE/KCH/W/42/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads (W4.5mxT0.15m): Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 67,311.11 63,500.00 Signed Sambok Kriel, Krang Lvea Quotations Envelope 23 18 18 14 Infrastructure Development Commune, KCH = (URR/5lines = 4.66km). (Package 2). COMMUNE/KCH/W/46/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads (W4.5mxT0.15m): Request for Single Stage - One 2018-05- 2018-07- 2018-08- 2018-12- IDA / 58070 Preparation and Post Open - National 59,944.44 29,400.00 Signed Chhean Loeung Commune, Quotations Envelope 09 04 21 31 Infrastructure Development KCH = (URR/12lines) = 4.15km. (Package 1). COMMUNE/KCH/W/56/18 / Construction of Health Posts (3 rooms, fense 400m, gate 1, Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-04- 2018-12- well1, WC 2rooms, pipe IDA / 58070 Preparation and Post Open - National 36,666.67 29,967.00 Signed Quotations Envelope 22 17 25 14 culvert 1, incinerator 1, 200m Infrastructure Development of laterite road). 1 Unit for Ksach Sar, KCH. COMMUNE/KCH/W/57/18 / Construction of Health Posts (3 rooms, fense 400m, gate 1, Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-04- 2018-12- well1, WC 2rooms, pipe IDA / 58070 Preparation and Post Open - National 36,666.67 28,967.00 Signed Quotations Envelope 22 17 24 14 culvert 1, incinerator 1, 200m Infrastructure Development of laterite road). 1 Unit for Chhean Loeung, KCH. COMMUNE/KCH/W/59/18 / Ploughing (2 Times) for Peam Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-08- 2019-01- Commune (116.5Ha), Samaki IDA / 58070 Preparation and Post Open - National 12,944.44 10,718.00 Signed Quotations Envelope 23 18 09 14 Meanchey District, Kg. Infrastructure Development Chhnang COMMUNE/KCH/W/60/18 / Ploughing (2 Times) for Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-08- 2019-01- Chheanloeurng Commune IDA / 58070 Preparation and Post Open - National 11,444.44 9,476.00 Signed Quotations Envelope 23 18 09 14 (103Ha), Samaki Meanchey Infrastructure Development District, Kg. Chhnang. COMMUNE/KSP/W/49/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Raksmey Samaki, KSP = Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-06- 2018-12- (Up1=3.40km, Up2=0.30 km, IDA / 58070 Preparation and Post Open - National 68,611.11 67,345.00 Signed Quotations Envelope 14 09 05 06 Up3=0.15 km, Up4=0.30 km, Infrastructure Development Up5=0.30 km, and Up6=0.30km) = 4.75km. (Package 1) COMMUNE/KPT/W/53/18 / Construction of Health Posts (3 rooms, fense 400m, gate 1, Sub-component 1.2: Land Request for Single Stage - One 2018-11- 2019-01- 2019-11- 2019-07- well1, WC 2rooms, pipe IDA / 58070 Preparation and Post Open - National 36,666.67 30,000.00 Signed Quotations Envelope 20 15 14 14 culvert 1, incinerator 1, 200m Infrastructure Development of laterite road). 1 Unit for Daung, KPT. COMMUNE NO 05/17 / Water Sub-component 1.2: Land Request for Single Stage - One 2018-09- 2018-11- 2019-12- 2019-05- well (Afredes) for Daung (Site IDA / 58070 Preparation and Post Open - National 54,000.00 29,700.00 Signed Quotations Envelope 19 14 02 13 I) : Total: 18 Units Infrastructure Development COMMUNE/KSP/W/61/18 / Ploughing (2 Times) for Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- Reaksmey Samaki Commune IDA / 58070 Preparation and Post Open - National 22,222.22 21,600.00 Signed Quotations Envelope 23 18 04 14 (200Ha), Oral District, Kg. Infrastructure Development Speu. COMMUNE/KPT/W/62/18 / Ploughing (2 Times) Tipo 1 = Sub-component 1.2: Land 354.44Ha & Tipo 2 =226.5Ha, Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 64,548.89 46,075.20 Signed Total = 580.94Ha for Tipo Quotations Envelope 23 18 02 14 Infrastructure Development Commune, Suntuk District, Kg. Thom. COMMUNE/KRT/W/67/18 / Sub-component 1.2: Land Pending Ploughing (2 Times) for Request for Single Stage - One 2018-05- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 19,333.33 0.00 Implementa Thmey Commune (174Ha), Quotations Envelope 23 18 14 Infrastructure Development tion Chetr Borey, Kratie. COMMUNE/KRT/W/68/18 / Sub-component 1.2: Land Pending Ploughing (2 Times) for Request for Single Stage - One 2018-05- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 30,777.78 0.00 Implementa Chambak Commune (277Ha), Quotations Envelope 23 18 14 Infrastructure Development tion Prek Prasab, Kratie. COMMUNE/KPT/W/63/18 / Sub-component 1.2: Land Ploughing (2 Times) for Request for Single Stage - One 2019-02- 2019-04- 2019-07- 2019-09- IDA / 58070 Preparation and Post Open - National 55,555.56 55,300.00 Signed Daung Commune (500Ha), Quotations Envelope 06 03 23 30 Infrastructure Development Suntuk District, Kg. Thom. COMMUNITY/KCH/W/45/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 2,777.78 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Sambok Kriel (100Ha), KCH. COMMUNITY/KCH/W/46/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 3,513.89 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Ksach Sar (126.50Ha), KCH. COMMUNITY/KCH/W/47/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 3,236.11 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Peam (116.50Ha), KCH. COMMUNITY/KCH/W/48/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 2,861.11 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Chheanloeung (103Ha), KCH. Page 3 COMMUNITY/KSP/W/49/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 5,555.56 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Raksmey Samaki (200Ha), KSP. COMMUNITY/KPT/W/42/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 9,845.56 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Tipo 1, KPT (354.44Ha) COMMUNITY/KPT/W/43/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 6,291.67 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Tipo 2 , KPT (226.50Ha) COMMUNITY/KRT/W/50/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 6,111.11 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Sambok, KRT (100Ha+120Ha=220Ha). COMMUNITY/KRT/W/51/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 3,861.11 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Changkrang, KRT (59Ha+80Ha=139Ha) COMMUNITY/KRT/W/52/18 / Planting in Agriculture Land Sub-component 1.2: Land Community Driven 2018-06- 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- (Sowing Seed or Planting IDA / 58070 Preparation and Post Open - National 2,694.44 0.00 Canceled Development 08 20 13 25 24 28 27 Seedling cover crop) for Infrastructure Development community in Dar, KRT (97Ha) COMMUNITY/KRT/W/53/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 4,833.33 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Thmey, KRT (174Ha) COMMUNITY/KRT/W/54/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 7,694.44 0.00 Canceled Seedling cover crop) for Development 08 13 25 24 28 27 Infrastructure Development community in Chambak, KRT (277Ha) COMMUNITY/KPT/W/44/18 / Planting in Agriculture Land Sub-component 1.2: Land (Sowing Seed or Planting Community Driven 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2020-02- IDA / 58070 Preparation and Post Open - National 13,888.89 0.00 Canceled Seedling cover crop) for Development 08 13 24 24 28 24 Infrastructure Development community in Daung, KPT (500Ha) COMMUNE NO 06/17 / Water Sub-component 1.2: Land Request for Single Stage - One 2019-01- 2019-03- 2019-12- 2019-09- well (Afredes) for Daung (Site IDA / 58070 Preparation and Post Open - National 51,000.00 28,050.00 Signed Quotations Envelope 20 17 02 13 II): Total: 17 Units Infrastructure Development COMMUNE/KPT/W/34/18 / Sub-component 1.2: Land Concrete Poles in Agriculture Request for Single Stage - One 2019-01- 2019-03- 2018-09- 2019-09- IDA / 58070 Preparation and Post Open - National 72,000.00 28,800.00 Signed Lands (0.12 x 0.12 x 0.75m) Quotations Envelope 20 17 20 13 Infrastructure Development = (3600 Poles) for Daung, KPT. COMMUNE/KPT/W/35-36/18 / Concrete Poles in Residential Lands (0.12 x 0.12 x 0.75m= 1400 Poles) Sub-component 1.2: Land and Concrete Poles in Forestry Request for Single Stage - One 2018-09- 2018-11- 2018-09- 2019-05- IDA / 58070 Preparation and Post Open - National 44,600.00 21,300.00 Signed (0.3x0.3x0.4x1.5m = 150 Quotations Envelope 22 17 20 16 Infrastructure Development Poles) and Concrete Poles in Stream and Canal (0.2x0.2x1.5m = 200 Poles) for Daung, KPT. COMMUNITY/KPT/W/39/18 / Instalation Concrete Poles in Sub-component 1.2: Land Pending Community Driven 2019-01- 2019-01- 2019-03- 2019-04- 2019-05- 2019-11- Agriculture Lands (0.12 x IDA / 58070 Preparation and Post Open - National 18,000.00 0.00 Implementa Development 15 20 03 02 07 03 0.12 x 0.75m) = (3600 Poles) Infrastructure Development tion for Daung, KPT. COMMUNE NO 09/17 / House for Nurses & Teachers Ceramic tile floor (W=9.2m, Sub-component 1.2: Land Request for Single Stage - One 2018-12- 2019-02- 2019-11- 2019-08- L=16.2m, H=6.82m, 4 bed IDA / 58070 Preparation and Post Open - National 35,000.00 29,000.00 Signed Quotations Envelope 19 13 14 12 room, 4 rooms's W.C & 4 Infrastructure Development places of kitchend) for Daung QTY 1 Unit COMMUNE NO 28/17 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Request for Single Stage - One 2019-01- 2019-02- 2019-11- 2019-08- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 29,000.00 24,300.00 Signed Quotations Envelope 02 27 14 26 H=6.62m, Warehouse, 2 Infrastructure Development rooms's W.C) for Daung (1). Total: 1 Unit COMMUNE NO 01/17 / Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-05- 2019-07- Repair Earth Roads for IDA / 58070 Preparation and Post Open - National 22,000.00 21,614.12 Signed Quotations Envelope 29 24 28 24 Sambok (6.6km). Total: Infrastructure Development 6.6Km COMMUNE NO 02/17 / Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-06- 2019-07- Repair Earth Roads for IDA / 58070 Preparation and Post Open - National 22,000.00 21,576.00 Signed Quotations Envelope 29 24 08 24 Changkrang (6.6km) Total: Infrastructure Development 6.6Km COMMUNE NO 03/17 / Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-05- 2019-07- Repair Earth Roads for Thmey IDA / 58070 Preparation and Post Open - National 13,333.33 9,934.00 Signed Quotations Envelope 29 24 21 24 (4km). Total: 4Km Infrastructure Development COMMUNE NO 04/17 / Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-05- 2019-07- Repair Earth Roads for Dar IDA / 58070 Preparation and Post Open - National 26,000.00 25,497.00 Signed Quotations Envelope 29 24 09 24 (7.8km). Total: 7.8 Km Infrastructure Development COMMUNE/KRT/W/64/18 / Ploughing (2 Times) for Sub-component 1.2: Land Pending Request for Single Stage - One 2018-05- 2018-07- 2019-01- Sambok Commune IDA / 58070 Preparation and Post Open - National 24,444.44 0.00 Implementa Quotations Envelope 23 18 14 (100Ha+120Ha=220Ha), Infrastructure Development tion Chetr Borey, Kratie. COMMUNE/KRT/W/65/18 / Ploughing (2 Times) for Sub-component 1.2: Land Pending Request for Single Stage - One 2018-05- 2018-07- 2019-01- Changkrang Commune IDA / 58070 Preparation and Post Open - National 15,444.44 0.00 Implementa Quotations Envelope 23 18 14 (59Ha+80Ha=139Ha), Chetr Infrastructure Development tion Borey, Kratie. COMMUNE/KRT/W/66/18 / Sub-component 1.2: Land Pending Ploughing (2 Times) for Dar Request for Single Stage - One 2018-05- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 10,777.78 0.00 Implementa Commune (97Ha), Chetr Quotations Envelope 23 18 14 Infrastructure Development tion Borey, Kratie. COMMUNITY/KCH/W/07A/18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Lands (0.12x0.12x0.75m) = Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 18,900.00 12,936.00 Signed (700 Poles) and 2) Concrete Development 08 27 13 25 27 24 27 28 27 27 Infrastructure Development Poles in Forestry & in SLC Sites (0.3x 0.3x 0.4x 1.5m) for Sambok Kriel (20 Poles). Page 4 COMMUNITY/KCH/W/08A/18 / Concrete Poles in Sub-component 1.2: Land Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-09- 2018-09- 2019-05- 2019-03- Agriculture & Residential IDA / 58070 Preparation and Post Open - National 10,000.00 17,027.85 Signed Development 08 27 13 25 27 24 27 28 27 27 Lands (0.12x0.12x0.75m) for Infrastructure Development Ksach Sar (400 Poles). COMMUNITY/KCH/W/09A/18 / 1) Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Lands (0.12x0.12x0.75m) = Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 12,100.00 12,096.00 Signed (400 Poles) and Concrete Development 08 17 13 25 25 24 25 28 25 27 Infrastructure Development Poles in Forestry & in SLC Sites (0.3x0.3x0.4x1.5m) for Peam (30 Poles). COMMUNITY/KCH/W/34A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 25,000.00 24,994.00 Signed Culverts (H1xL6m) for Development 08 27 13 25 27 24 27 28 27 27 Infrastructure Development Sambok Kriel: 10 Units. COMMUNITY/KCH/W/35A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 37,500.00 37,487.00 Signed Culverts (H1xL6m) for Ksach Development 08 27 13 25 27 24 27 28 27 27 Infrastructure Development Sar: 15 Units COMMUNITY/KCH/W/36A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 12,500.00 12,487.00 Signed Culverts (H1xL6m) for Peam: Development 08 28 13 25 28 24 28 28 28 27 Infrastructure Development 5 Units COMMUNITY/KCH/W/37A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 25,000.00 24,990.00 Signed Culverts (H1xL6m) for Chhean Development 06 28 11 23 28 22 28 26 28 25 Infrastructure Development Loeun: 10 Units. COMMUNITY/KSP/W/10A/18 / 1) Concrete Poles in Forestry & in SLC Sites Sub-component 1.2: Land (0.3x0.3x0.4x1.5m) (20 Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2018-12- IDA / 58070 Preparation and Post Open - National 2,570.00 2,569.35 Signed Poles) and 2) Concrete Poles Development 08 23 13 25 23 24 23 28 23 27 Infrastructure Development in Stream and Canal (0.2x0.2x1.5m) for Raksmey Samaki (26 Poles). COMMUNITY NO 10/18 / 1) Concrete Poles in Forestry & in SLC Sites Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-08- (0.3x0.3x0.4x1.5m) (20 IDA / 58070 Preparation and Post Open - National 2,570.00 0.00 Canceled Quotations Envelope 06 01 01 Poles) and 2) Concrete Poles Infrastructure Development in Stream and Canal (0.2x0.2x1.5m) for Raksmey Samaki (26 Poles) COMMUNITY/KSP/W/38A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-08- 2019-05- 2018-08- 2019-05- 2018-10- 2019-05- 2019-01- IDA / 58070 Preparation and Post Open - National 37,500.00 37,495.00 Signed Culverts (H1xL6m) for Development 15 23 20 01 23 31 23 05 23 03 Infrastructure Development Raksmey Samaki: 15 Units COMMUNITY NO 38/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 37,500.00 0.00 Canceled (H1xL6m) for Raksmey Quotations Envelope 06 01 28 Infrastructure Development Samaki: 15 Units COMMUNITY NO 17/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 18,750.00 0.00 Canceled (W5xT0.15xE0.5m) for Tipo 1 Quotations Envelope 06 01 28 Infrastructure Development (15Km) COMMUNITY/KPT/W/17A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2019-03- 2019-03- 2019-05- 2019-05- 2019-07- 2019-10- IDA / 58070 Preparation and Post Open - National 18,750.00 0.00 Implementa Roads (W5xT0.15xE0.5m) for Development 15 20 01 31 05 03 Infrastructure Development tion Tipo 1 (15Km) COMMUNITY NO 18/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 15,000.00 0.00 Canceled (W5xT0.15xE0.5m) for Tipo 2 Quotations Envelope 06 01 28 Infrastructure Development (12Km) COMMUNITY/KPT/W/18A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2019-03- 2019-03- 2019-05- 2019-05- 2019-07- 2019-10- IDA / 58070 Preparation and Post Open - National 15,000.00 0.00 Implementa Roads (W5xT0.15xE0.5m) for Development 15 20 01 31 05 03 Infrastructure Development tion Tipo 2 (12Km) COMMUNITY NO 32/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 27,500.00 0.00 Canceled (H1xL6m) for Tipo 1 (10), Kg. Quotations Envelope 06 01 28 Infrastructure Development Thom: 11 Units. COMMUNITY/KPT/W/32A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- IDA / 58070 Preparation and Post Open - National 27,500.00 19,473.30 Signed Culverts (H1xL6m) for Tipo 1 Development 08 27 13 25 27 24 27 28 27 27 Infrastructure Development (10), Kg. Thom: 11 Units. COMMUNITY/KPT/W/33A/18 / Construction of Pipe Sub-component 1.2: Land Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-08- 2018-08- 2019-05- 2018-09- 2019-05- 2019-03- Culverts (H1xL6m) for Tipo 2 IDA / 58070 Preparation and Post Open - National 27,500.00 19,473.30 Signed Development 08 27 13 25 27 24 27 28 27 27 (10), Kg. Thom. Total: 11 Infrastructure Development Units. COMMUNITY NO 01/18 / Concrete Poles and Sub-component 1.2: Land Installation in Agriculture & Request for Single Stage - One 2018-06- 2018-08- 2019-08- IDA / 58070 Preparation and Post Open - National 17,700.00 0.00 Canceled Residential Lands Quotations Envelope 06 01 01 Infrastructure Development (0.12x0.12x0.75m) for Sambok, Kratie (708 Poles). COMMUNITY/KRT/W/01A/18 / Concrete Poles and Sub-component 1.2: Land Installation in Agriculture & Community Driven 2018-06- 2019-09- 2018-06- 2018-07- 2019-09- 2018-08- 2019-09- 2018-09- 2019-11- 2019-03- IDA / 58070 Preparation and Post Open - National 17,700.00 17,699.08 Signed Residential Lands Development 08 12 13 25 12 24 12 28 12 27 Infrastructure Development (0.12x0.12x0.75m) for Sambok, Kratie (708 Poles). COMMUNITY NO 02/18 / Concrete Poles in Agriculture Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-08- & Residential Lands IDA / 58070 Preparation and Post Open - National 17,500.00 0.00 Canceled Quotations Envelope 06 01 01 (0.12x0.12x0.75m) for Infrastructure Development Changkrang (700 Poles). COMMUNITY/KRT/W/02A/18 / Concrete Poles in Sub-component 1.2: Land Community Driven 2018-06- 2019-09- 2018-06- 2018-07- 2019-09- 2018-08- 2019-09- 2018-09- 2019-09- 2019-03- Agriculture & Residential IDA / 58070 Preparation and Post Open - National 17,500.00 17,473.88 Signed Development 08 11 13 25 11 24 11 28 11 27 Lands (0.12x0.12x0.75m) for Infrastructure Development Changkrang (700 Poles). COMMUNITY NO 05/18 / Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land (0.12x0.12x0.75m) = (250 Request for Single Stage - One 2018-06- 2018-08- 2019-08- IDA / 58070 Preparation and Post Open - National 6,950.00 0.00 Canceled Poles) and Concrete Poles in Quotations Envelope 06 01 01 Infrastructure Development Forestry & in SLC Sites (0.3x0.3x0.4x1.5m) for Thmey (10 Poles) COMMUNITY/KRT/W/05A/18 / Concrete Poles in Agriculture & Residential Sub-component 1.2: Land Pending Lands (0.12x0.12x0.75m) = Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 58070 Preparation and Post Open - National 6,950.00 0.00 Implementa (250 Poles) and Concrete Development 08 13 25 24 28 27 Infrastructure Development tion Poles in Forestry & in SLC Sites (0.3x0.3x0.4x1.5m) for Thmey (10 Poles) COMMUNITY NO 06/18 / Concrete Poles in Agriculture Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-08- & Residential Lands IDA / 58070 Preparation and Post Open - National 6,750.00 0.00 Canceled Quotations Envelope 06 01 01 (0.12x0.12x0.75m) for Infrastructure Development Chambak (270 Poles). Page 5 COMMUNITY/KRT/W/06A/18 / Concrete Poles in Sub-component 1.2: Land Community Driven 2018-06- 2019-09- 2018-06- 2018-07- 2019-09- 2018-08- 2019-09- 2018-09- 2019-09- 2019-03- Agriculture & Residential IDA / 58070 Preparation and Post Open - National 6,750.00 6,733.21 Signed Development 08 02 13 25 12 24 12 28 12 27 Lands (0.12x0.12x0.75m) for Infrastructure Development Chambak (270 Poles). COMMUNITY NO 07/18 / 1) Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land (0.12x0.12x0.75m) = (700 Request for Single Stage - One 2018-06- 2018-08- 2019-08- IDA / 58070 Preparation and Post Open - National 18,900.00 0.00 Canceled Poles) and 2) Concrete Poles Quotations Envelope 06 01 01 Infrastructure Development in Forestry & in SLC Sites (0.3x 0.3x 0.4x 1.5m) for Sambok Kriel (20 Poles) COMMUNITY NO 08/18 / Concrete Poles in Agriculture Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-08- & Residential Lands IDA / 58070 Preparation and Post Open - National 10,000.00 0.00 Canceled Quotations Envelope 06 01 01 (0.12x0.12x0.75m) for Ksach Infrastructure Development Sar (400 Poles). COMMUNITY NO 09/18 / 1) Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land (0.12x0.12x0.75m) = (400 Request for Single Stage - One 2018-06- 2018-08- 2019-08- IDA / 58070 Preparation and Post Open - National 12,100.00 0.00 Canceled Poles) and Concrete Poles in Quotations Envelope 06 01 01 Infrastructure Development Forestry & in SLC Sites (0.3x0.3x0.4x1.5m) for Peam (30 Poles). COMMUNITY/KRT/W/13A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2019-01- 2019-01- 2019-02- 2019-03- 2019-04- 2019-07- IDA / 58070 Preparation and Post Open - National 7,500.00 0.00 Implementa Roads (W5xT0.15xE0.5m). for Development 08 13 24 26 30 29 Infrastructure Development tion Sambok (6km). COMMUNITY NO 13/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 7,500.00 0.00 Canceled (W5xT0.15xE0.5m). for Quotations Envelope 06 01 28 Infrastructure Development Sambok (6km). COMMUNITY NO 14/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 7,500.00 0.00 Canceled (W5xT0.15xE0.5m) for Quotations Envelope 06 01 28 Infrastructure Development Changkrang (6km). COMMUNITY/KRT/W/15A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2019-01- 2019-01- 2019-02- 2019-03- 2019-04- 2019-07- IDA / 58070 Preparation and Post Open - National 10,000.00 0.00 Implementa Roads (W5xT0.15xE0.5m) for Development 08 13 24 26 30 29 Infrastructure Development tion Da (8km). COMMUNITY/KRT/W/19A/18 Sub-component 1.2: Land Community Driven 2018-06- 2019-10- 2018-06- 2018-07- 2019-10- 2018-08- 2019-10- 2018-09- 2019-10- 2018-12- / Construction of Box IDA / 58070 Preparation and Post Open - National 16,000.00 15,999.11 Signed Development 08 14 13 25 14 24 14 28 14 27 Culverts (2x3x6m) for Infrastructure Development Sambok (1 Unit) COMMUNITY/KRT/W/20A/18 Sub-component 1.2: Land / Construction of Box Community Driven 1,599,750.0 2018-06- 2019-10- 2018-06- 2018-07- 2019-10- 2018-08- 2019-10- 2018-09- 2019-10- 2018-12- IDA / 58070 Preparation and Post Open - National 16,000.00 Signed Culverts (2x3x6m) for Development 0 08 31 13 25 31 24 31 28 31 27 Infrastructure Development Changkrang (1 Unit) COMMUNITY/KRT/W/21A/18 Sub-component 1.2: Land Community Driven 2018-06- 2019-10- 2018-06- 2018-07- 2019-10- 2018-08- 2019-10- 2018-09- 2020-02- 2018-12- / Construction of Box IDA / 58070 Preparation and Post Open - National 16,000.00 15,999.10 Signed Development 08 14 13 25 14 24 14 28 14 27 Culverts (2x3x6m) for Dar (1 Infrastructure Development Unit) COMMUNITY/KRT/W/22A/18 Sub-component 1.2: Land Community Driven 2018-06- 2020-03- 2018-06- 2018-07- 2020-04- 2018-08- 2020-04- 2018-09- 2020-04- 2018-12- / Construction of Box IDA / 58070 Preparation and Post Open - National 32,000.00 31,996.00 Signed Development 08 22 13 25 04 24 04 28 04 27 Culverts (2x3x6m) for Thmey Infrastructure Development (2 Units) COMMUNITY/KRT/W/23A/18 Sub-component 1.2: Land Pending / Construction of Box Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- IDA / 58070 Preparation and Post Open - National 32,000.00 0.00 Implementa Culverts (2x3x6m) for Development 08 13 25 24 28 27 Infrastructure Development tion Chambak. Phase 1 (2 Units) COMMUNITY/KRT/W/24A/18 Sub-component 1.2: Land / Construction of Box Community Driven 2018-06- 2019-11- 2018-06- 2018-07- 2019-11- 2018-08- 2019-11- 2018-09- 2019-11- 2018-12- IDA / 58070 Preparation and Post Open - National 32,000.00 31,990.29 Signed Culverts (2x3x6m) for Development 08 08 13 25 18 24 18 28 18 27 Infrastructure Development Chambak. Phase 2 (2 Units) COMMUNITY/KRT/W/25A/18 Sub-component 1.2: Land / Construction of Box Community Driven 2018-06- 2019-11- 2018-06- 2018-07- 2019-11- 2018-08- 2019-11- 2018-09- 2019-11- 2018-12- IDA / 58070 Preparation and Post Open - National 32,000.00 31,990.29 Signed Culverts (2x3x6m) for Development 08 17 13 25 21 24 28 28 28 27 Infrastructure Development Chambak. Phase 3 (2 Units) COMMUNITY/KRT/W/26A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-03- 2018-06- 2018-07- 2019-03- 2018-08- 2019-03- 2018-09- 2019-03- 2018-12- IDA / 58070 Preparation and Post Open - National 20,000.00 19,985.00 Signed Culverts (H1xL6m) for Development 08 06 13 25 06 24 06 28 06 27 Infrastructure Development Sambok, Kratie: 8 Units COMMUNITY/KRT/W/27A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-03- 2018-06- 2018-07- 2019-03- 2018-08- 2019-03- 2018-09- 2019-03- 2018-12- IDA / 58070 Preparation and Post Open - National 20,000.00 19,985.00 Signed Culverts (H1xL6m) for Development 08 06 13 25 06 24 06 28 06 27 Infrastructure Development Changkrang, Kratie: 8 Units COMMUNITY/KRT/W/28A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-05- 2018-06- 2018-07- 2019-05- 2018-08- 2019-05- 2018-09- 2019-05- 2018-12- IDA / 58070 Preparation and Post Open - National 15,000.00 14,998.00 Signed Culverts (H1xL6m) for Dar, Development 08 06 13 25 06 24 06 28 06 27 Infrastructure Development Kratie: 6 Units COMMUNITY/KRT/W/29A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-03- 2018-06- 2018-07- 2019-03- 2018-08- 2019-03- 2018-09- 2019-03- 2018-12- IDA / 58070 Preparation and Post Open - National 17,500.00 14,998.00 Signed Culverts (H1xL6m) for Thmey, Development 08 06 13 25 06 24 06 28 06 27 Infrastructure Development Kratie: 7 Units COMMUNITY/KRT/W/30A/18 Sub-component 1.2: Land / Construction of Pipe Community Driven 2018-06- 2019-03- 2018-06- 2018-07- 2019-03- 2018-08- 2019-05- 2018-09- 2019-03- 2018-12- IDA / 58070 Preparation and Post Open - National 10,000.00 9,955.00 Signed Culverts (H1xL6m) for Development 08 03 13 25 06 24 06 28 06 27 Infrastructure Development Chambak, Kratie: 4 Units COMMUNITY/KTM/W/11A/18 Sub-component 1.2: Land / Concrete Poles in Stream Community Driven 2018-06- 2019-07- 2018-06- 2018-07- 2019-07- 2018-08- 2020-02- 2018-09- 2019-07- 2019-03- IDA / 58070 Preparation and Post Open - National 15,750.00 12,579.89 Signed and Canal (0.2x0.2x1.5m) for Development 08 11 13 25 11 24 11 28 11 27 Infrastructure Development Chaomkravien (350 Poles). COMMUNITY/KTM/W/16A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- IDA / 58070 Preparation and Post Open - National 6,250.00 0.00 Implementa Roads (W5xT0.15xE0.5m) for Development 08 13 25 24 28 27 Infrastructure Development tion Choamkravien (5Km) COMMUNITY/KTM/W/31A/18 / Construction of Pipe Sub-component 1.2: Land Community Driven 2018-06- 2019-11- 2018-06- 2018-07- 2019-11- 2018-08- 2019-11- 2018-09- 2019-11- 2018-12- Culverts (H1xL6m) for IDA / 58070 Preparation and Post Open - National 20,000.00 19,919.69 Signed Development 08 25 13 25 25 24 25 28 25 27 Choamkravien, Kg. Cham: 8 Infrastructure Development Units COMMUNE/KCH/W/58/18 / Ploughing (2 Times) for Sambok Kriel (100Ha) and for Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-08- 2019-01- Ksach Sar (126.50Ha), Total IDA / 58070 Preparation and Post Open - National 25,166.67 20,838.00 Signed Quotations Envelope 23 18 13 14 226.50 Ha, Kranglovea Infrastructure Development Commune, Samaki Meanchey District, Kg. Chhnang. COMMUNITY/KPT/W/41/18 / Instalation Concrete Poles in in Residential Lands (0.12 x 0.12 x 0.75m = 1400 Poles) Sub-component 1.2: Land Pending and Concrete Poles in Forestry Community Driven 2018-09- 2018-09- 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58070 Preparation and Post Open - National 9,900.00 0.00 Implementa (0.3x0.3x0.4x1.5m = 150 Development 17 22 03 03 07 06 Infrastructure Development tion Poles) and Concrete Poles in Stream and Canal (0.2x0.2x1.5m = 200 Poles) for Daung, KPT. Page 6 COMMUNE/KPT/W/38/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Request for Single Stage - One 2018-08- 2018-10- 2019-03- Tipo 1 (AR6=1.30km, IDA / 58070 Preparation and Post Open - National 75,111.11 0.00 Canceled Quotations Envelope 06 01 30 AR=14km, AR16=0.85km, Infrastructure Development AR18=0.46, and AA1= 1.42) Total= 5.2km. (Package2) COMMUNE/KPT/W/39/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Tipo 2 (AR01=1.10km, Sub-component 1.2: Land Request for Single Stage - One 2018-07- 2018-09- 2019-02- AR02=1.20km, IDA / 58070 Preparation and Post Open - National 84,933.33 0.00 Canceled Quotations Envelope 07 01 28 AR03=1.20km, Infrastructure Development AR04=1.13km, ARAR05=1.25km)= Total:5.88km (Package 1) COMMUNE/KPT/W/40/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Tipo 2 (AR06=1.10km, Sub-component 1.2: Land Request for Single Stage - One 2018-07- 2018-09- 2019-02- AR07=1.15km, IDA / 58070 Preparation and Post Open - National 67,166.67 0.00 Canceled Quotations Envelope 07 01 28 AR08=1.00km, Infrastructure Development AR09=0.60km, AR10=0.80km)= Total:4.65km (Package 2) COMMUNE/KCH/W/41/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-11- Rite Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Post Open - National 77,133.33 0.00 Canceled Quotations Envelope 07 02 29 Sambok Kriel = (URR/7lines = Infrastructure Development 5.34km). (Package 1) COMMUNE/KCH/W/43/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-11- Rite Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Post Open - National 69,333.33 0.00 Canceled Quotations Envelope 07 02 29 Ksach Sar = (URR/2lines & Infrastructure Development UAR/6lines = 4.8km). COMMUNE/KCH/W/44/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Request for Single Stage - One 2018-04- 2018-06- 2018-11- Rite Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Post Open - National 81,900.00 0.00 Canceled Quotations Envelope 07 02 29 Peam = (URR/9lines) = Infrastructure Development 5.67km. (Package 1) COMMUNE/KCH/W/45/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads (W4.5mxT0.15m): Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 83,344.44 0.00 Canceled Peam = (URR/5lines & Quotations Envelope 06 01 28 Infrastructure Development UAR/3lines). Total = 5.77km. (Package 2) COMMUNE/KCH/W/47/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads Request for Single Stage - One 2018-07- 2018-09- 2019-02- IDA / 58070 Preparation and Post Open - National 63,555.56 0.00 Canceled (W4.5mxT0.15m):Chhean Quotations Envelope 07 01 28 Infrastructure Development Loeung = (UAR/4lines). Total = 4.40km. (Package 2) COMMUNE/KCH/W/48/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads Request for Single Stage - One 2018-07- 2018-09- 2019-02- IDA / 58070 Preparation and Post Open - National 74,677.78 0.00 Canceled (W4.5mxT0.15m):Chhean Quotations Envelope 07 01 28 Infrastructure Development Loeung = (UAR/6lines). Total = 5.17km. (Package 3) COMMUNE/KSP/W/50/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Request for Single Stage - One 2018-02- 2018-04- 2018-09- Raksmey Samaki, KSP = IDA / 58070 Preparation and Post Open - National 75,833.33 0.00 Canceled Quotations Envelope 06 03 30 (Up7=3.50 km, and Infrastructure Development Up9=1.75km) = 5.25km. (Package 2) COMMUNE/KSP/W/51/18 / Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Request for Single Stage - One 2018-02- 2018-04- 2018-09- Raksmey Samaki, KSP = IDA / 58070 Preparation and Post Open - National 74,388.89 0.00 Canceled Quotations Envelope 06 03 30 (Up8=1.65 km, and Infrastructure Development Up10=3.50km) = 5.15km. (Package 3) COMMUNE/KSP/W/52/18 / Upgrade Earth Road to Late- Sub-component 1.2: Land Rite Roads (W4.5mxT0.15m): Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 84,500.00 0.00 Canceled Raksmey Samaki, KSP - Main Quotations Envelope 06 01 28 Infrastructure Development = (Up11=5.85km) = 5.85km. (Package 4) LASED/NCDDS/W/SP/02/18 / "Upgrade Earth Road to Late- Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Request for Single Stage - One 2018-08- 2018-10- 2019-03- Main Road KCH IDA / 58070 Preparation and Post Open - National 216,666.67 0.00 Canceled Quotations Envelope 06 01 30 Sambokreal = 9km and Infrastructure Development Khsach Sor = 6km. (Total = 15km)" COMMUNITY NO 33/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 27,500.00 0.00 Canceled (H1xL6m) for Tipo 2 (10), Kg. Quotations Envelope 06 01 28 Infrastructure Development Thom. Total: 11 Units COMMUNITY NO 15/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 58070 Preparation and Post Open - National 10,000.00 0.00 Canceled (W5xT0.15xE0.5m) for Da Quotations Envelope 06 01 28 Infrastructure Development (8km). COMMUNITY NO 19/18 / Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-01- Construction of Box Culverts IDA / 58070 Preparation and Post Open - National 16,000.00 0.00 Canceled Quotations Envelope 06 01 28 (2x3x6m) for Sambok (1) Infrastructure Development COMMUNITY NO 20/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 16,000.00 0.00 Canceled (2x3x6m) for Changkrang (1 Quotations Envelope 06 01 28 Infrastructure Development Unit) COMMUNITY NO 21/18 / Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-01- Construction of Box Culverts IDA / 58070 Preparation and Post Open - National 16,000.00 0.00 Canceled Quotations Envelope 06 01 28 (2x3x6m) for Dar (1 Unit) Infrastructure Development COMMUNITY NO 22/18 / Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-01- Construction of Box Culverts IDA / 58070 Preparation and Post Open - National 32,000.00 0.00 Canceled Quotations Envelope 06 01 28 (2x3x6m) for Thmey (2 Units) Infrastructure Development COMMUNITY NO 23/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 32,000.00 0.00 Canceled (2x3x6m) for Chambak. Phase Quotations Envelope 06 01 28 Infrastructure Development 1 (2 Units) COMMUNITY NO 24/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 32,000.00 0.00 Canceled (2x3x6m) for Chambak. Phase Quotations Envelope 06 01 28 Infrastructure Development 2 (2 Units) COMMUNITY NO 25/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 32,000.00 0.00 Canceled (2x3x6m) for Chambak. Phase Quotations Envelope 06 01 28 Infrastructure Development 3 (2 Units) COMMUNITY NO 26/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 20,000.00 0.00 Canceled (H1xL6m) for Sambok, Kratie: Quotations Envelope 06 01 28 Infrastructure Development 8 Units COMMUNITY NO 27/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 20,000.00 0.00 Canceled (H1xL6m) for Changkrang, Quotations Envelope 06 01 28 Infrastructure Development Kratie: 8 Units Page 7 COMMUNITY NO 28/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 15,000.00 0.00 Canceled (H1xL6m) for Dar, Kratie: 6 Quotations Envelope 06 01 28 Infrastructure Development Units COMMUNITY NO 29/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 17,500.00 0.00 Canceled (H1xL6m) for Thmey, Kratie: 7 Quotations Envelope 06 01 28 Infrastructure Development Units COMMUNITY NO 30/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 10,000.00 0.00 Canceled (H1xL6m) for Chambak, Quotations Envelope 06 01 28 Infrastructure Development Kratie: 4 Units COMMUNITY NO 31/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 20,000.00 0.00 Canceled (H1xL6m) for Choamkravien, Quotations Envelope 06 01 28 Infrastructure Development Kg. Cham: 8 Units COMMUNITY NO 16/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One 2018-08- 2018-10- 2019-03- IDA / 58070 Preparation and Post Open - National 6,250.00 0.00 Canceled (W5xT0.15xE0.5m) for Quotations Envelope 06 01 30 Infrastructure Development Choamkravien (5Km) COMMUNITY NO 11/18 / Sub-component 1.2: Land Concrete Poles in Stream and Request for Single Stage - One 2018-06- 2018-08- 2019-08- IDA / 58070 Preparation and Post Open - National 15,750.00 0.00 Canceled Canal (0.2x0.2x1.5m) for Quotations Envelope 06 01 01 Infrastructure Development Chaomkravien (350 Poles). COMMUNITY NO 34/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 25,000.00 0.00 Canceled (H1xL6m) for Sambok Kriel: Quotations Envelope 06 01 28 Infrastructure Development 10 Units COMMUNITY NO 35/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 37,500.00 0.00 Canceled (H1xL6m) for Ksach Sar: 15 Quotations Envelope 06 01 28 Infrastructure Development Units COMMUNITY NO 36/18 / Sub-component 1.2: Land Request for Single Stage - One 2018-06- 2018-08- 2019-01- Construction of Pipe Culverts IDA / 58070 Preparation and Post Open - National 12,500.00 0.00 Canceled Quotations Envelope 06 01 28 (H1xL6m) for Peam: 5 Units Infrastructure Development COMMUNITY NO 37/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 25,000.00 0.00 Canceled (H1xL6m) for Chhean Loeun: Quotations Envelope 06 01 28 Infrastructure Development 10 Units COMMUNITY/KRT/W/14A/18 Sub-component 1.2: Land Pending / Planting Grass of Earth Community Driven 2019-01- 2019-01- 2019-02- 2019-03- 2019-04- 2019-07- IDA / 58070 Preparation and Post Open - National 7,500.00 0.00 Implementa Roads (W5xT0.15xE0.5m) for Development 08 13 24 26 30 29 Infrastructure Development tion Changkrang, KRT (6km). COMMUNE/TKM/W/69/19 / Construction of community Sub-component 1.2: Land market (size 5m x 6m roof Request for Single Stage - One 2019-03- 2019-05- 2019-11- 2019-10- IDA / 58070 Preparation and Post Open - National 15,000.00 15,000.00 Signed zine and concrete basement) Quotations Envelope 06 01 14 28 Infrastructure Development in Choamkravien, TKM. Toatl: 1 Unit COMMUNE/KCH/W/70/19 / Construction of community Sub-component 1.2: Land Request for Single Stage - One 2019-03- 2019-05- 2019-08- 2019-10- market (size 5m x 6m roof IDA / 58070 Preparation and Post Open - National 15,000.00 15,000.00 Signed Quotations Envelope 06 01 27 28 zine and concrete basement) Infrastructure Development in Peam, KCH. Total: 1 Unit COMMUNE/KPT/W/71/19 / Construction of community Sub-component 1.2: Land Request for Single Stage - One 2019-03- 2019-05- 2019-10- 2019-10- market (size 5m x 6m roof IDA / 58070 Preparation and Post Open - National 15,000.00 15,160.00 Signed Quotations Envelope 06 01 28 28 zine and concrete basement) Infrastructure Development in Tipo, KPT. Total: 1 Unit COMMUNE/KRT/W/72/19 / Construction of community Sub-component 1.2: Land Request for Single Stage - One 1,490,000.0 2019-03- 2019-05- 2019-10- 2019-10- market (size 5m x 6m roof IDA / 58070 Preparation and Post Open - National 15,000.00 Signed Quotations Envelope 0 06 01 02 28 zine and concrete basement) Infrastructure Development in Dar, KRT. Total: 1 Unit COMMUNE/KRT/W/73/19 / Repair Existing Earth Road in SAMBOK (A006 (AT001)=0.70km, A004b=0.48km, Sub-component 1.2: Land A010=1.26km, Request for Single Stage - One 2019-03- 2019-05- 2019-06- 2019-11- IDA / 58070 Preparation and Post Open - National 30,099.97 29,484.17 Signed A001b=1.55km, Quotations Envelope 15 10 20 06 Infrastructure Development S007=1.940km, A007=0.780km, A024=1.015km, A034=1.300km) in KRT- Total=9.03Km COMMUNE/KRT/W/74/19 / Repair Existing Earth Road in CHANGKRANG (La Or Sub-component 1.2: Land village=4.10km, Request for Single Stage - One 2019-03- 2019-05- 2019-06- 2019-11- IDA / 58070 Preparation and Post Open - National 23,266.64 23,125.96 Signed S029=0.650km, Quotations Envelope 16 11 21 07 Infrastructure Development A013b=1.13km, A15b=1.10km) in KRT- Total=6.98Km COMMUNE/KRT/W/75/19 / Repair Existing Earth Road in Sub-component 1.2: Land Request for Single Stage - One 2019-03- 2019-05- 2019-06- 2019-11- DAR (S004=1.32km, IDA / 58070 Preparation and Post Open - National 9,066.66 7,727.50 Signed Quotations Envelope 25 20 13 16 A007=1.00km, Infrastructure Development S012=0.40km) - in KRT. Total=2.72Km COMMUNE/KRT/W/76/19 / Repair Existing Earth Road in THMEI (A002a=1.07km, Sub-component 1.2: Land A012a=1.39km, S006A = Request for Single Stage - One 2019-03- 2019-05- 2019-06- 2019-11- IDA / 58070 Preparation and Post Open - National 28,633.30 18,900.00 Signed 0.467 KM, A006a=1.703, Quotations Envelope 25 20 27 16 Infrastructure Development S004a=0.467km, Boeung Svay Chrum road=3.50km) - in KRT. Total= 8.59Km LASED/NCDDS/W/NCB/04/17 / Construction Earth Roads(W5xT0.15xE0.5m):LOT 1:Sambok(14.975),Ch.krang(6 ),Dar(8),Thmey(10), Sub-component 1.2: Land Chambak(29.091),Choamkravi Single Stage - One 2,404,574.4 2019-02- 2019-04- 2019-02- 2019-04- 2019-05- 2019-05- 2019-08- 2019-06- 2019-08- 2019-12- IDA / 58070 Preparation and Post Request for Bids Open - National 2,860,000.00 Completed en- Envelope 5 20 24 25 08 30 08 09 12 26 09 Infrastructure Development TKM(5),TP1(15),TP2(12).Total: 100.410km.LOT2:S.Kriel(14), Ks.Sar(14),Peam(14),Chh.Loeu ng(7),Ra.Samaki(7).Total:29.5 90km.GrandTotal:130Km LASED/NCDDS/W/NCB/10/19 / Construction of Community Rain Water Storage at Thmey 1 line (L:600m, TW:5m, Laterite Layer, 1 Double Box Sub-component 1.2: Land Single Stage - One 2019-02- 2019-09- 2019-02- 2019-04- 2019-10- 2019-05- 2019-11- 2019-06- 2019-12- 2019-12- Culvert with lifting Gates) and IDA / 58070 Preparation and Post Request for Bids Open - National 294,776.67 249,916.88 Signed Envelope 15 09 20 03 24 03 27 07 27 04 Chambak 1 line (L:160m, Infrastructure Development TW:5m,Laterite Layer, 1 Double Box Culvert with Lifting Gates) in KRT. Total: 2 lines. LASED/NCDDS/W/NCB/11/19 / Construction of Community Natural Live Stream Storage at Tipo Commune 1 line Sub-component 1.2: Land Single Stage - One 2019-02- 2019-09- 2019-02- 2019-04- 2019-10- 2019-05- 2019-11- 2019-06- 2019-12- 2019-12- (L:600m, TW:5m, Laterite IDA / 58070 Preparation and Post Request for Bids Open - National 322,493.33 350,896.09 Signed Envelope 20 09 25 08 31 08 27 12 27 09 Layer, Double Box Culvert Infrastructure Development with lifting Gates, and One line of Spillway structure of 45 m) in KPT. Total: 1 line Page 8 LASED/NCDDS/W/NCB/12/19 / Construction of Community Natural Live Stream Storage 1 line: Dyke (L:200m, TW:5m, Sub-component 1.2: Land Single Stage - One 2019-06- 2019-12- 2019-07- 2019-08- 2020-02- 2019-09- 2020-04- 2019-10- 2020-04- 2020-04- Laterite Layer, Double Box IDA / 58070 Preparation and Post Request for Bids Open - National 338,888.89 330,749.03 Signed Envelope 30 16 05 16 06 15 26 20 29 17 Culvert with lifting Gates, One Infrastructure Development line of Spillway structure of 45m) at Prey Thom, KSP, Total: 1 line LASED/NCDDS/W/NCB/13/19 / Construction of Community Rain Water Storage at 1)Ksach Sar 1 line(L:200m, TW:5m), 2) Sub-component 1.2: Land Kiri Aphivath 1 line Single Stage - One 2019-06- 2019-12- 2019-06- 2019-08- 2020-02- 2019-09- 2020-03- 2019-10- 2020-03- 2020-04- IDA / 58070 Preparation and Post Request for Bids Open - National 416,222.22 320,000.02 Signed (L:150m,TW:5m), 3) Sambok Envelope 20 16 25 06 05 05 02 10 18 07 Infrastructure Development Kreal 1 line (Dyke L:80m, TW:5m) and 4) Pond at Sok Senchey (80mx50m) in KCH. Total: 3 lines & 1 Pond. LASED/NCDDS/W/NCB/06/17 / Small Dam(W4xSite Slop1:2, average embankment, length depends on each site,1spill way 20m,water double gates Sub-component 1.2: Land Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- (2x2m=4m):Lot IDA / 58070 Preparation and Post Request for Bids Open - National 980,000.00 0.00 Canceled Envelope 03 08 20 19 24 22 1:S.bok(1),Ch.krang(1), Infrastructure Development Thmey(1),Chambak(1),TP1(1), TP2(1)&Daung(1).Lot 2:Sb.Kriel(1),Ks.Sar(1),Peam(1) and R.Samaki(1).Total: 11Unit COMMUNITY/KRT/W/55/19 / Sub-component 1.2: Land Pending Planting Grass of Earth Roads 2019-06- 2019-06- 2019-07- 2020-01- IDA / 58070 Preparation and Post Direct Selection Direct 11,287.50 0.00 Implementa (W5xT0.15xE0.5m). for 17 22 27 23 Infrastructure Development tion SAMBOK, (9.03km) COMMUNITY/KRT/W/56/19 / Sub-component 1.2: Land Pending Planting Grass of Earth Roads 2019-03- 2019-03- 2019-04- 2019-10- IDA / 58070 Preparation and Post Direct Selection Direct 8,725.00 0.00 Implementa (W5xT0.15xE0.5m) for 20 25 29 26 Infrastructure Development tion CHANGKRANG (6.98km) COMMUNITY/KRT/W/57/19 / Sub-component 1.2: Land Pending Planting Grass of Earth Roads 2019-06- 2019-06- 2019-07- 2020-01- IDA / 58070 Preparation and Post Direct Selection Direct 3,400.00 0.00 Implementa (W5xT0.15xE0.5m) for DAR 20 25 30 26 Infrastructure Development tion (2.72km) COMMUNITY/KRT/W/59/19 / Sub-component 1.2: Land Pending Repair health post in 2019-03- 2019-03- 2019-04- 2019-10- IDA / 58070 Preparation and Post Direct Selection Direct 3,000.00 0.00 Implementa CHAMBAK which was built 20 25 29 26 Infrastructure Development tion during LASED I COMMUNITY/KRT/W/60/19 / Sub-component 1.2: Land 2019-03- 2019-03- 2019-04- 2019-10- Fence for health post in IDA / 58070 Preparation and Post Direct Selection Direct 3,000.00 0.00 Canceled 15 20 24 21 CHAMBAK 300m Infrastructure Development COMMUNE/KRT/W/80/20 / Construction of Community Centre Ceramic tile floor Sub-component 1.2: Land Pending Request for Single Stage - One 2020-04- 2020-06- 2020-12- (W=7.2m, L=17.2m, IDA / 58070 Preparation and Post Open - National 30,000.00 0.00 Implementa Quotations Envelope 15 10 07 H=6.62m, Warehouse, 2 Infrastructure Development tion rooms's W.C) for CHANGKRANG 1 Unit, KRT COMMUNITY/KRT/W/58/19 / Sub-component 1.2: Land Planting Grass of Earth Roads 2019-06- 2019-06- 2019-07- 2020-01- IDA / 58070 Preparation and Post Direct Selection Direct 10,737.50 0.00 Canceled (W5xT0.15xE0.5m) for THMEI 20 25 30 26 Infrastructure Development (8.59km) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/G/NCB/07/16 / OfficeFurniture:Nat.+3NewPro vi:(30MeetChr, 28Desks, 58Chr, 4MeetTab, 2Filingcabi,3SlidingCabi,6Filin Component 2: Project Request for Single Stage - One 2017-02- 2017-04- 2017-11- 2018-04- gCabi). 3Distr:(15Des, 45Chr, IDA / 58070 Post Open - National 40,110.00 37,270.50 Signed Management Quotations Envelope 06 03 28 03 3SlidingCabi, 3FilingCabi, 3MeetTab) 5NewHP:(10Des,10Char,5Slidi ngCabi,5FilingCabi+4Draw, 5Connected 3Cha,10Bed,5WaterFilter) LASED/NCDDS/G/SP/10/17 / GPS Mapping+Licenses: NCDDS 2, GSSLC 4, GDA 5, (KCH,KSP,TBM) 3, Total GPS:14 units. Concrete Test Sub-Component 1.1: Social Request for Single Stage - One 2017-02- 2017-04- 2017-12- 2017-09- Hammer for 3 new provinces IDA / 58070 Land Concession Investment Post Open - National 44,311.11 42,260.00 Signed Quotations Envelope 06 03 15 30 3 & for NCDDS 1. Dynamic Planning and Prioritization Cone Penetrometer(DCP) for new provinces 3 and NCDDS 1. Topography Survey for new provinces 3 &NCDDS 1. LASED/NCDDS/G/NCB/01/16 Sub-component 1.3: / Vehicles : 9 Pickup Trucks Single Stage - One 2016-11- 2016-11- 2016-12- 2017-01- 2017-01- 2017-02- 2017-03- 2017-02- 2017-09- IDA / 58070 Agriculture and Livelihood Post Request for Bids Open - National 270,000.00 243,531.00 Signed for National Level and Sub- Envelope 14 19 31 12 30 09 06 16 02 Development National. LASED/NCDDS/G/SP/06/16 / Component 2: Project Request for Single Stage - One 2016-11- 2017-01- 2017-09- 2018-01- Software (GIS, Accounting) for IDA / 58070 Post Open - National 24,200.00 15,760.00 Signed Management Quotations Envelope 26 21 15 21 NCDDS, GSSLC & GDA LASED/NCDDS/G/NCB/02/16 / Motorcycles: for Province(KSP: 10, KCH: 10, TBK: 10), for District: (SMC: 5, Sub-component 1.2: Land Single Stage - One 2016-12- 2016-12- 2017-01- 2017-02- 2017-02- 2017-03- 2017-03- 2017-04- 2017-05- 2018-04- OR: 5, PBL:5), for Communes: IDA / 58070 Preparation and Post Request for Bids Open - National 115,500.00 100,170.00 Signed Envelope 31 26 05 16 02 18 21 22 02 22 (CL:1, PM:1, RSMSK:1, DG:1, Infrastructure Development KLV:1), for NCDDS: 3 Units, GSSLC: 3 Units, GDA: 7 Units. Total 63 Units LASED/NCDDS/G/NCB/03/16 / Computer&Photocopy Machine: Lot 1: Nat.: 37Laptops,3LaserJet Printers, 4Scaners. Provi.: 49Laptops, 5LaserJet Printer & 5Scaner. Component 2: Project Single Stage - One 2016-11- 2017-04- 2016-12- 2017-01- 2017-06- 2017-02- 2017-08- 2017-03- 2017-09- 2018-03- IDA / 58070 Post Request for Bids Open - National 177,460.00 191,151.40 Signed Distr.:14Laptops, 7LaserJet Management Envelope 30 12 05 16 08 15 08 22 12 22 Printers.Lot 2: Nat.: 3Photocopy, 4LCD Projector+Screen, Provi.:5Photocopy & 5LCD Projector+Screen Sub-Component 1.1: Social LASED/NCDDS/G/SP/08/16 / Request for Single Stage - One 2017-02- 2017-04- 2017-10- IDA / 58070 Land Concession Investment Post Limited 2,720.00 0.00 Canceled Soil Testing Kits (16 kits) Quotations Envelope 06 03 03 Planning and Prioritization LASED/NCDDS/G/SP/01A/17 Sub-component 1.3: Request for Single Stage - One 2017-10- 2017-12- 2017-11- 2018-04- / 1 Pickup Trucks for National IDA / 58070 Agriculture and Livelihood Post Open - National 30,000.00 27,000.00 Signed Quotations Envelope 06 01 16 03 Level. Development LASED/NCDDS/G/SP/05/16 / Building new networking data center for LASED-NCDDS (1 Component 2: Project Request for Single Stage - One 2016-12- 2017-01- 2018-01- IDA / 58070 Post Open - National 36,000.00 0.00 Canceled server machine, fiber optic Management Quotations Envelope 06 31 31 cable, and network accessory) and Internet Service Provider Page 9 LASED/NCDDS/G/NCB/03A/1 8 / Laptop for National and Sub-National Level (4 for Component 2: Project Request for Single Stage - One 2018-03- 2018-05- 2018-05- 2018-07- GDH, 2 for GDA and 27 for IDA / 58070 Post Open - National 54,400.00 55,220.00 Signed Management Quotations Envelope 06 01 31 30 NCDDS and 5 Provinces) and 1 Desktop for (Large Monitor) for GDH. Total: 34 units LASED/NCDDS/G/SP/04/16 / Camera Equipment. A) National level: 1) Professional Camera (3 units) and Sub-Component 1.1: Social Professional Video Camera (3 Request for Single Stage - One 2018-04- 2018-06- 2018-05- 2018-08- IDA / 58070 Land Concession Investment Post Open - National 32,000.00 16,900.00 Signed units) for LASED-GSSLC Quotations Envelope 07 02 31 31 Planning and Prioritization Communication, LASED- NCDDS & GDA. B) Provincial: 1) Camera (5 units); 2) Aircon (6 units). LASED/NCDDS/G/SP/05A/16 / Building new networking data center for LASED-NCDDS Component 2: Project Request for Single Stage - One 2018-05- 2018-07- 2019-04- 2018-09- (1 server, Back up Storage IDA / 58070 Post Open - National 48,650.00 46,840.80 Signed Management Quotations Envelope 06 01 19 29 4TB, UPS, Other Software license, Internet service 4 years) and Android Tablet (50 Tablets) LASED/NCDDS/G/SP/09/17 / 1). Mobile loud speaker (Loud Speaker, Stand, Transmitter and Receiver) for LASED Sub-component 1.3: GSSLC, NCDDS and GDA. Toal: Request for Single Stage - One 2018-04- 2018-06- 2018-08- 2018-11- IDA / 58070 Agriculture and Livelihood Post Limited 11,500.00 11,950.00 Signed 3 sets. 2). Loud Speaker ( Quotations Envelope 07 02 28 29 Development Loud Speaker, Microphone, Ampli, Battery and Electrical line) for 12 SLC Community Toal: 14 sets. LASED/NCDDS/G/NCB/11/17 / Agriculture Start-Up Sub-component 1.2: Land Packages for Daung 700 HH Single Stage - One 2018-06- 2019-03- 2018-06- 2018-07- 2019-05- 2018-08- 2019-06- 2018-09- 2019-07- 2019-09- IDA / 58070 Preparation and Post Request for Bids Open - National 280,000.00 206,229.76 Signed (Agri kits 8 items, rice Envelope 01 26 06 18 08 17 25 21 19 21 Infrastructure Development 200kg/HH, vegetable seeds 6 items, plants 5 items) LASED/NCDDS/G/NCB/12/17 / Household Start-Up Sub-component 1.2: Land Single Stage - One 2018-07- 2019-11- 2018-07- 2018-08- 2019-12- 2018-09- 2020-01- 2018-10- 2020-02- 2019-04- Packages for Daung 700 HH IDA / 58070 Preparation and Post Request for Bids Open - National 116,666.67 121,213.95 Signed Envelope 02 08 07 18 26 17 23 22 03 20 (Solar lamp, Tent plastic, mat, Infrastructure Development blanket, water jar, water filter) LASED/NCDDS/G/NCB/13/17 Sub-component 1.2: Land / Shelter Construction Single Stage - One 2018-05- 2019-03- 2018-05- 2018-06- 2019-05- 2018-07- 2019-06- 2018-08- 2019-07- 2019-02- IDA / 58070 Preparation and Post Request for Bids Open - National 217,777.78 223,080.00 Signed Materials (40 Zincs/HH) for Envelope 01 26 06 17 02 17 25 21 19 17 Infrastructure Development Daung 700HH COMMUNE/KCH/G/03A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Cashew Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2018-10- = 210 Seedlings/Ha) for Peam IDA / 58070 Preparation and Post Open - National 19,416.67 18,873.00 Signed Quotations Envelope 23 18 05 16 Commune (116.5Ha), Samaki Infrastructure Development Meanchey District, Kg. Chhnang. COMMUNE/KCH/G/04A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Cashew Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2018-10- = 210 Seedlings/Ha) for IDA / 58070 Preparation and Post Open - National 17,166.67 16,789.00 Signed Quotations Envelope 23 18 05 16 Chheanloeurng Commune Infrastructure Development (103Ha), Samaki Meanchey District, Kg. Chhnang. COMMUNE/KSP/G/05- 06A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- Cashew = 210 Seedlings/Ha) IDA / 58070 Preparation and Post Open - National 33,333.33 33,120.00 Signed Quotations Envelope 23 18 23 14 for Reaksmey Samaki Infrastructure Development Commune (200Ha), Oral District, Kg. Speu. COMMUNE/KPT/G/07- 11A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Sub-component 1.2: Land Cashew = 210 Seedlings/Ha) Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 96,823.33 923,804.64 Signed Tipo 1 = 354.44Ha & Tipo 2 Quotations Envelope 23 18 02 14 Infrastructure Development =226.5Ha, Total = 580.94Ha for Tipo Commune, Suntuk District, Kg. Thom. COMMUNE/KRT/G/12A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Cashew Sub-component 1.2: Land Pending Request for Single Stage - One 2018-05- 2018-07- 2019-01- = 210 Seedlings/Ha) for IDA / 58070 Preparation and Post Open - National 36,666.67 0.00 Implementati Quotations Envelope 23 18 14 Sambok Commune Infrastructure Development on (100Ha+120Ha=220Ha), Chetr Borey, Kratie. COMMUNE/KRT/G/15- 16A/18 / Supply Cover Crops Sub-component 1.2: Land ( Mug bean = 20kgs/Ha and Request for Single Stage - One 2018-05- 2018-07- 2018-08- 2019-01- IDA / 58070 Preparation and Post Open - National 29,000.00 28,779.60 Signed Cashew = 210 Seedlings/Ha) Quotations Envelope 23 18 06 14 Infrastructure Development for Thmey Commune (174Ha), Chetr Borey, Kratie. COMMUNE/KRT/G/17- 19A/18 / Supply Cover Crops Sub-component 1.2: Land Pending ( Mug bean = 20kgs/Ha and Request for Single Stage - One 2018-05- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 46,166.67 0.00 Implementati Cashew= 210 Seedlings/Ha) Quotations Envelope 23 18 14 Infrastructure Development on for Chambak Commune (277Ha), Prek Prasab, Kratie. COMMUNE/KPT/G/20- 24A/18 / Supply Cover Crops Sub-component 1.2: Land Pending ( Mug bean = 20kgs/Ha and Request for Single Stage - One 2019-02- 2019-04- 2019-09- IDA / 58070 Preparation and Post Open - National 83,333.33 0.00 Implementati Cashew= 210 Seedlings/Ha) Quotations Envelope 06 03 30 Infrastructure Development on for Daung Commune (500Ha), Suntuk District, Kg. Thom. COMMUNE/KCH/G/01- 02A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Cashew = 210 Seedlings/Ha) Sub-component 1.2: Land Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2018-10- for Sambok Kriel (100Ha)and IDA / 58070 Preparation and Post Open - National 37,750.00 38,590.00 Signed Quotations Envelope 23 18 05 16 for Ksach Sar (126.50Ha), Infrastructure Development Total 226.50 Ha, Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/02/18 / Planting in Agriculture Land (Ploughing and Seedling for Sub-component 1.2: Land Request for Single Stage - One 2018-01- 2018-03- 2018-08- Cover Crop) for Ksach Sar IDA / 58070 Preparation and Post Open - National 35,138.89 0.00 Canceled Quotations Envelope 06 03 30 (126.50Ha), Kranglovea Infrastructure Development Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/23/18 / Planting in Agriculture Land (Ploughing and Seedling for Sub-component 1.2: Land Request for Single Stage - One 2018-01- 2018-03- 2018-08- Cover Crop) for Daung IDA / 58070 Preparation and Post Open - National 27,777.78 0.00 Canceled Quotations Envelope 06 03 30 Commune, Prasad Balang, Kg. Infrastructure Development Thom. PHASE 4 (100Ha) of 500Ha COMMUNE/KRT/G/13A/18 / Supply Cover Crops ( Mug bean = 20kgs/Ha and Sub-component 1.2: Land Pending Request for Single Stage - One 2018-05- 2018-07- 2019-01- Cashew= 210 Seedlings/Ha) IDA / 58070 Preparation and Post Open - National 23,166.67 0.00 Implementati Quotations Envelope 23 18 14 for Changkrang Commune Infrastructure Development on (59Ha+80Ha=139Ha), Chetr Borey, Kratie Page 10 COMMUNE/KRT/G/14A/18 / Supply Cover Crops ( Mug Sub-component 1.2: Land bean = 20kgs/Ha and Cashew Request for Single Stage - One 2018-05- 2018-07- 2018-07- 2019-01- IDA / 58070 Preparation and Post Open - National 16,166.67 15,729.52 Signed = 210 Seedlings/Ha) for Dar Quotations Envelope 23 18 06 14 Infrastructure Development Commune (97Ha), Chetr Borey, Kratie. LASED/NCDDS/G/UN/01/19 Sub-component 1.3: UN Agencies 2019-02- 2019-04- 2019-02- 2019-06- 2019-03- 2019-08- 2019-09- / Vehicles (SUV) for GDH, IDA / 58070 Agriculture and Livelihood Post Direct 108,000.00 119,011.49 Signed (Direct) 01 25 06 26 13 14 09 NCDDS & GDA, total = 3 units Development LASED/NCDDS/G/SP/11/19 / Sub-component 1.2: Land Request for Single Stage - One 2019-03- 2019-05- 2019-08- 2019-10- 2019-10- Solar Panel for teacher and IDA / 58070 Preparation and Post Open - National 14,400.00 14,193.00 Completed Quotations Envelope 06 01 28 28 08 nurse house, total = 9 sets Infrastructure Development LASED/NCDDS/G/SP/12/19 / DGPS for KRT and KPT, total = 2 units Sub-component 1.2: Land Request for Single Stage - One 2019-03- 2019-05- 2019-11- 2019-11- 2019-11- GPS for GDH (2 units), GDA (4 IDA / 58070 Preparation and Post Open - National 61,000.00 52,950.00 Completed Quotations Envelope 20 15 08 11 21 units) , and 5 units for KCH, Infrastructure Development KRT, KPT, KSP and TKM), toal = 11 units LASED/NCDDS/G/SP/13/19 / Tape Recorder (3 units for Sub-Component 1.1: Social Request for Single Stage - One 2019-03- 2019-05- 2019-07- 2019-11- NCDDS, GDH, and GDA and 5 IDA / 58070 Land Concession Investment Post Open - National 3,200.00 3,160.00 Signed Quotations Envelope 25 20 12 16 units for 5 provinces), total = Planning and Prioritization 8 units LASED/NCDDS/G/SP/14/19 / Agriculture Materials:Lot 1: So il Auger (§ ” € š Ž Ì • ½ „ Š ¸ ) for GDA, Total = 2 units Lot 2: Hatchery Machine (˜ É ¶ Sub-component 1.3: Request for Single Stage - One 2019-04- 2019-06- 2019-10- 2019-12- Ÿ Ê ¸ “ — Ò ‰ ¶ Ÿ Ë – „ ˜ ¶ “ Ë ) (2 u IDA / 58070 Agriculture and Livelihood Post Open - National 14,277.78 13,500.00 Signed Quotations Envelope 15 10 14 07 nits for Sambok, 2 units for C Development hangkrang, 2 units of Chamkr avien, 2 units for Tipo, 2 units for Rasmey Samaki) Total = 1 0 units COMMUNE/KSP/G/20/19 / Sub-component 1.2: Land Water tank with supporter and Request for Single Stage - One 2019-03- 2019-05- 2019-09- 2019-07- IDA / 58070 Preparation and Post Open - National 10,500.00 9,998.00 Signed tube (Rasmey Samaki, KSP), Quotations Envelope 06 01 02 30 Infrastructure Development Total = 3 units COMMUNE/KPT/G/21/19 / Sub-component 1.2: Land Pending Request for Single Stage - One 2019-04- 2019-06- 2019-09- Water tank for health post in IDA / 58070 Preparation and Post Open - National 2,000.00 0.00 Implementati Quotations Envelope 15 10 08 Dong SLC, KPT, total = 1 Infrastructure Development on units LASED/NCDDS/G/SP/17/20 / Sub-component 1.2: Land Drone 1 set and extra Request for Single Stage - One 2020-03- 2020-05- 2020-04- 2020-11- IDA / 58070 Preparation and Post Open - National 7,132.00 6,980.00 Signed accessories (1 Battery & 1 Quotations Envelope 11 06 10 02 Infrastructure Development Charger) for GDH. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/35/17 / Insurance (Group Personal Pending Accident and Health Insurance Component 2: Project Single Stage - One 2017-03- 2017-03- 2017-04- 2017-05- 2017-06- 2021-12- IDA / 58070 Post Request for Bids Open - National 108,900.00 0.00 Implementati and Vehicle Insurance (Third Management Envelope 01 06 17 17 21 31 on Party Liability Driver and Passenger) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/30/17 / Sub-Component 1.1: Social Consultant 2017-09- 2017-02- 2017-04- 2017-12- 2017-05- 2018-03- 2017-06- 2018-03- 2018-06- Baseline Survey in year 2017 IDA / 58070 Land Concession Investment Post Qualification Open - National 70,000.00 69,998.05 Signed 2017-01-31 25 21 06 19 06 28 10 30 10 (Local Firm) Planning and Prioritization Selection LASED/NCDDS/F/35/17 / Sub-Component 1.1: Social Consultant 2017-08- 2017-10- 2017-11- 2017-12- 2017-12- 2018-03- 2018-01- 2018-03- 2018-06- Consulting firm for Irrigation IDA / 58070 Land Concession Investment Post Qualification Open - National 120,000.00 119,997.50 Signed 2017-09-15 08 06 19 19 19 28 23 30 12 Design (8 sites) Planning and Prioritization Selection Sub-component 1.2: Land Consultant LASED/NCDDS/IC/32/21 / Open - Pending 2021-08- 2021-09- 2021-10- 2021-11- 2022-07- IDA / 58070 Preparation and Post Qualification 90,000.00 0.00 2021-07-13 Final Impact Survey International Implementation 03 16 16 20 12 Infrastructure Development Selection LASED/NCDDS/IC/34/17 / Service Provider for Sub-component 1.3: Quality Based Open - 2018-04- 2018-06- 2018-04- 2018-08- 2018-10- 2018-09- 2018-11- 2018-10- 2019-03- 2018-11- 2019-03- 2018-12- 2019-03- 2023-04- Implementation Community IDA / 58070 Agriculture and Livelihood Post 514,100.00 589,967.25 Signed 2018-06-01 Selection International 25 22 30 05 04 02 27 02 14 01 21 06 29 30 Development Fund (for 5 Development years) LASED/NCDDS/IC/31/18 / Sub-Component 1.1: Social Consultant Impact Survey for 2nd year of 2018-07- 2018-09- 2018-10- 2018-11- 2019-11- IDA / 58070 Land Concession Investment Post Qualification Open - National 50,000.00 0.00 Canceled 2018-07-10 the project/Mid-term review 31 13 13 17 17 Planning and Prioritization Selection (Local Firm) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/10/17 / Individual Component 2: Project 2017-11- 2017-02- 2018-02- 2017-03- 2018-02- 2017-04- 2018-03- 2021-12- Admin and Finance Assistant IDA / 58070 Post Consultant Open 56,470.59 35,209.47 Signed 2017-01-01 Management 21 19 20 12 28 16 01 31 at NCDDS Selection LASED/NCDDS/IC/11/17 / Individual Component 2: Project 2017-11- 2017-02- 2018-02- 2017-03- 2018-02- 2017-04- 2018-03- 2021-12- Admin and Finance Assistant IDA / 58070 Post Consultant Open 56,470.59 35,209.37 Terminated 2017-01-01 Management 21 19 20 12 28 16 01 31 at GDA-MAFF Selection LASED/NCDDS/IC/12/17 / Individual Component 2: Project 2017-11- 2017-02- 2018-02- 2017-03- 2018-02- 2017-04- 2018-03- 2021-12- Admin and Finance Assistant IDA / 58070 Post Consultant Open 56,470.59 34,126.12 Terminated 2017-01-01 Management 21 19 20 12 28 16 01 31 at GSSLC Selection LASED/NCDDS/IC/04/16 / Sub-component 1.2: Land Individual 2016-09- 2016-10- 2016-11- 2016-12- 2021-08- Project Finance Consultant at IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 16 20 10 15 31 GSSLC & GDA Infrastructure Development Selection LASED/NCDDS/IC/01/16 / Sub-component 1.2: Land Individual 2016-10- 2016-10- 2016-11- 2021-08- National Operation and M&E IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-08-16 04 25 29 31 Advisor at NCDDS Infrastructure Development Selection LASED/NCDDS/IC/05/16 / Sub-component 1.2: Land Individual 2016-10- 2016-10- 2016-11- 2016-12- 2020-11- National Infrastructure IDA / 58070 Preparation and Prior Consultant Open 118,588.24 0.00 Canceled 2016-09-01 03 20 10 15 30 Advisor at GSSLC Infrastructure Development Selection LASED/NCDDS/IC/06/16 / Sub-component 1.2: Land Individual 2016-10- 2016-11- 2016-12- 2021-08- National Operation and M&E IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 20 10 15 31 Advisor at GSSLC Infrastructure Development Selection LASED/NCDDS/IC/07/16 / Sub-component 1.3: Individual National Agriculture & Rural 2016-09- 2016-10- 2016-11- 2016-12- 2021-08- IDA / 58070 Agriculture and Livelihood Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 Development Advisor at GDA 19 20 10 15 31 Development Selection - MAFF LASED/NCDDS/IC/08/16 / Sub-component 1.2: Land Individual 2017-01- 2017-02- 2017-03- 2020-11- National Communication & IDA / 58070 Preparation and Prior Consultant Open 118,588.24 0.00 Canceled 2016-12-01 19 09 16 30 Strategy Advisor at NCDDS Infrastructure Development Selection Page 11 LASED/NCDDS/IC/13/17 / Sub-Component 1.1: Social Individual One Provincial GIS, Safeguard 2017-03- 2017-02- 2017-10- 2017-03- 2017-11- 2017-04- 2017-12- 2021-04- IDA / 58070 Land Concession Investment Post Consultant Open 101,647.06 56,587.00 Signed 2016-12-31 and Environemental Advisor 16 18 31 11 13 15 07 15 Planning and Prioritization Selection at LASED Kratie LASED/NCDDS/IC/14/17 / One Provincial GIS, Safeguard Sub-Component 1.1: Social Individual 2017-03- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-10- 2021-04- and Environemental Advisor IDA / 58070 Land Concession Investment Post Consultant Open 101,647.06 75,689.25 Signed 2016-12-31 16 18 15 11 15 15 16 15 for LASED Kg. Thom and Planning and Prioritization Selection Thbong Khmum LASED/NCDDS/IC/15/17 / One Provincial GIS, Safeguard Sub-Component 1.1: Social Individual 2017-03- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-10- 2021-04- and Environmental Advisor for IDA / 58070 Land Concession Investment Post Consultant Open 101,647.06 72,085.00 Signed 2016-12-31 16 18 15 11 15 15 16 15 LASED Kampong Speu and Planning and Prioritization Selection Kampong Chhnang. LASED/NCDDS/IC/16/17 / Sub-component 1.2: Land Individual 2017-03- 2017-02- 2017-10- 2017-03- 2017-10- 2017-04- 2017-12- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 109,411.76 64,876.50 Signed 2016-12-31 16 18 13 11 28 15 01 31 for LASED Kratie. Infrastructure Development Selection LASED/NCDDS/IC/17/17 / Sub-component 1.2: Land Individual 2017-03- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-10- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 109,411.76 54,064.00 Terminated 2016-12-31 16 18 15 11 15 15 16 31 for LASED Tbong Khmum. Infrastructure Development Selection LASED/NCDDS/IC/18/17 / Sub-component 1.2: Land Individual 2017-10- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-12- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 109,411.76 58,749.00 Signed 2016-12-31 16 18 15 11 28 15 01 31 for LASED Kg. Thom. Infrastructure Development Selection LASED/NCDDS/IC/19/17 / Sub-component 1.2: Land Individual 2017-03- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-12- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 109,411.76 58,668.00 Terminated 2016-12-31 16 18 15 11 29 15 01 31 for LASED Kg. Speu. Infrastructure Development Selection LASED/NCDDS/IC/20/17 / Sub-component 1.2: Land Individual 2017-03- 2017-02- 2017-09- 2017-03- 2017-10- 2017-04- 2017-12- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 109,411.76 64,876.50 Signed 2016-12-31 16 18 15 11 28 15 01 31 for LASED Kg. Chhnang. Infrastructure Development Selection LASED/NCDDS/IC/21/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-11- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 109,411.76 52,262.00 Terminated 2016-11-30 16 18 22 08 28 15 01 31 for LASED Kratie. Infrastructure Development Selection LASED/NCDDS/IC/22/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-11- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 109,411.76 64,876.50 Terminated 2016-11-30 16 18 15 08 28 15 01 31 for LASED Thbong Khmum. Infrastructure Development Selection LASED/NCDDS/IC/23/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-10- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 109,411.76 37,845.00 Terminated 2016-11-30 16 18 15 08 15 15 16 31 for LASED Kg. Thom. Infrastructure Development Selection LASED/NCDDS/IC/24/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-10- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 109,411.76 46,855.00 Terminated 2016-11-30 16 18 15 08 18 15 24 31 for LASED Kg. Speu. Infrastructure Development Selection LASED/NCDDS/IC/25/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-10- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 109,411.76 46,855.00 Terminated 2016-11-30 16 18 15 08 15 15 16 31 for LASED Kg. Chhnang. Infrastructure Development Selection LASED/NCDDS/IC/01A/16 / Sub-component 1.2: Land Individual Senior Sub-National Project 2016-12- 2017-01- 2017-04- 2017-02- 2017-03- 2017-05- 2021-12- IDA / 58070 Preparation and Post Consultant Open 155,294.12 134,747.00 Signed 2016-11-30 Management Advisor at 05 18 03 08 15 30 31 Infrastructure Development Selection NCDDS LASED/NCDDS/IC/05A/16 / Sub-component 1.2: Land Individual 2016-11- 2017-01- 2017-04- 2017-02- 2017-05- 2017-03- 2017-05- 2021-03- Senior National Infrastructure IDA / 58070 Preparation and Post Consultant Open 118,588.24 113,262.00 Signed 2016-11-30 21 18 03 08 02 15 03 15 Advisor at GSSLC Infrastructure Development Selection LASED/NCDDS/IC/06A/16 / Sub-component 1.2: Land Individual 2016-12- 2017-01- 2017-04- 2017-02- 2017-05- 2017-03- 2017-05- 2021-12- Senior National Operation and IDA / 58070 Preparation and Post Consultant Open 176,470.59 154,680.00 Terminated 2016-11-30 06 18 03 08 02 15 02 31 M&E Advisor at GSSLC Infrastructure Development Selection LASED/NCDDS/IC/07A/16 / Sub-component 1.3: Individual Senior National Agriculture & 2016-12- 2017-01- 2017-04- 2017-02- 2017-05- 2017-03- 2017-05- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 148,235.29 106,605.00 Signed 2016-11-30 Rural Development Advisor at 06 18 03 08 05 15 08 31 Development Selection GDA - MAFF LASED/NCDDS/IC/08A/16 / Sub-component 1.2: Land Individual 2017-12- 2017-01- 2018-03- 2017-02- 2018-03- 2017-03- 2018-03- 2021-03- National Communication & IDA / 58070 Preparation and Post Consultant Open 118,588.24 105,626.91 Signed 2016-11-30 25 18 16 08 20 15 21 15 Strategy Advisor at NCDDS Infrastructure Development Selection LASED/NCDDS/IC/26/16 / Sub-component 1.2: Land Individual 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-10- 2021-03- Provincial Infrastructure IDA / 58070 Preparation and Post Consultant Open 87,529.41 64,876.50 Signed 2016-11-30 16 18 15 08 15 15 16 15 Engineer at LASED Kratie Infrastructure Development Selection LASED/NCDDS/IC/27/16 / Sub-component 1.2: Land Individual Provincial Infrastructure 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-11- 2021-03- IDA / 58070 Preparation and Post Consultant Open 87,529.41 64,876.50 Signed 2016-11-30 Engineer for LASED Kg. Thom 16 18 15 08 28 15 15 15 Infrastructure Development Selection and Thbong Khmum LASED/NCDDS/IC/28/16 / Sub-component 1.2: Land Individual Provincial Infrastructure 2017-03- 2017-01- 2017-09- 2017-02- 2017-10- 2017-03- 2017-12- 2021-03- IDA / 58070 Preparation and Post Consultant Open 87,529.41 66,679.00 Signed 2016-11-30 Engineer for LASED Kampong 16 18 15 08 28 15 15 15 Infrastructure Development Selection Speu and Kampong Chhnang. LASED/NCDDS/IC/29/17 / Sub-Component 1.1: Social Individual International Short-Term 2018-07- 2017-05- 2019-01- 2017-06- 2019-01- 2017-07- 2019-01- 2018-01- IDA / 58070 Land Concession Investment Post Consultant Open 100,000.00 83,720.93 Signed 2017-03-31 Consultant for Internal Review 06 19 03 09 15 14 15 10 Planning and Prioritization Selection and Report (1month x 6times) LASED/NCDDS/IC/33/21 / Sub-Component 1.1: Social Individual National Consultant for 2021-02- 2021-03- 2021-04- 2021-12- IDA / 58070 Land Concession Investment Post Consultant Open 65,000.00 0.00 Canceled 2020-12-31 Preparing Project Completion 18 11 15 31 Planning and Prioritization Selection Report. LASED/NCDDS/IC/37/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-09- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 27,748.65 Signed 2017-02-28 Agriculture Facilitator for 18 18 21 09 28 13 01 31 Development Selection Sambok, KRT LASED/NCDDS/IC/38/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-09- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 21,473.38 Signed 2017-02-28 Agriculture Facilitator for 19 18 14 09 27 13 01 31 Development Selection ChangKrang, KRT LASED/NCDDS/IC/39/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 34,688.25 Signed 2017-02-28 Agriculture Facilitator for Da, 18 18 14 09 11 13 18 31 Development Selection KRT LASED/NCDDS/IC/40/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-09- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 21,473.38 Terminated 2017-02-28 Agriculture Facilitator for 18 18 14 09 27 13 01 31 Development Selection Thmey, KRT LASED/NCDDS/IC/41/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-09- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 16,076.32 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 27 13 01 31 Development Selection Chambak, KRT LASED/NCDDS/IC/42/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-10- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 29,346.23 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 11 13 22 31 Development Selection Choamkravien, TKM LASED/NCDDS/IC/43/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 31,329.12 Signed 2017-02-28 Agriculture Facilitator for 18 18 21 09 22 13 01 31 Development Selection Tipo, KPT LASED/NCDDS/IC/44/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 38,205.00 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 22 13 13 31 Development Selection Dong, KPT Page 12 LASED/NCDDS/IC/45/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 30,434.00 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 22 13 01 31 Development Selection Kraing Lavea, KCH LASED/NCDDS/IC/46/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 29,091.32 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 22 13 01 31 Development Selection Chheanloeung, KCH LASED/NCDDS/IC/47/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 31,329.12 Terminated 2017-02-28 Agriculture Facilitator for 18 18 14 09 22 13 01 31 Development Selection Peam, KCH LASED/NCDDS/IC/48/17 / Sub-component 1.3: Individual Community Development and 2018-04- 2017-04- 2018-09- 2017-05- 2018-10- 2017-06- 2018-11- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 48,000.00 26,853.53 Signed 2017-02-28 Agriculture Facilitator for 18 18 14 09 22 13 01 31 Development Selection Raksmeysamaki, Oral, KSP LASED/NCDDS/IC/09/16 / Sub-component 1.2: Land Individual Procurement and Contract 2016-09- 2016-10- 2016-10- 2016-12- 2021-07- IDA / 58070 Preparation and Prior Consultant Open 104,470.59 0.00 Canceled 2016-08-22 Management Assistant at 02 10 31 05 31 Infrastructure Development Selection NCDDS LASED/NCDDS/IC/02/16 / Sub-component 1.2: Land Individual National Procurement and 2016-09- 2016-10- 2016-10- 2016-12- 2020-07- IDA / 58070 Preparation and Prior Consultant Open 158,117.65 0.00 Canceled 2016-08-22 Contract Management Advisor 01 10 31 05 31 Infrastructure Development Selection at NCDDS LASED/NCDDS/IC/03/16 / Sub-component 1.2: Land Individual 2016-09- 2016-10- 2016-11- 2016-12- 2021-08- Project Finance Consultant at IDA / 58070 Preparation and Prior Consultant Open 148,235.29 0.00 Canceled 2016-09-01 16 20 10 15 31 NCDDS Infrastructure Development Selection LASED-NCDDS-IC-02A-16 / Sub-component 1.2: Land Individual Senior National Procurement 2016-09- 2016-10- 2017-07- 2016-11- 2017-07- 2016-12- 2017-07- 2020-12- IDA / 58070 Preparation and Post Consultant Open 158,117.65 158,258.00 Signed 2016-08-31 and Contract Management 02 19 12 09 25 14 27 13 Infrastructure Development Selection Advisor at NCDDS LASED-NCDDS-IC-03A-16 / Senior National Project Sub-component 1.2: Land Individual 2016-09- 2016-12- 2017-03- 2016-12- 2017-05- 2017-02- 2017-05- 2021-12- Financial Management IDA / 58070 Preparation and Post Consultant Open 176,470.59 70,400.00 Signed 2016-09-11 16 07 21 28 18 01 25 31 Consultant at NCDDS, GSSLC Infrastructure Development Selection and GDA LASED-NCDDS-IC-09A-16 / Sub-component 1.2: Land Individual Procurement and Contract 2016-09- 2016-10- 2017-01- 2016-11- 2016-12- 2017-02- 2021-12- IDA / 58070 Preparation and Post Consultant Open 104,470.59 66,375.00 Signed 2016-09-01 Management Assistant at 01 20 18 10 15 06 31 Infrastructure Development Selection NCDDS LASED/NCDDS/IC/36A/17 / One Consultant for Develop Individual Component 2: Project 2017-05- 2017-10- 2017-12- 2017-11- 2018-01- 2017-12- 2018-01- 2019-02- and Upgrade of Management IDA / 58070 Post Consultant Open 86,000.00 82,950.00 Signed 2017-08-28 Management 30 16 14 06 12 11 15 04 Information System (MIS) for Selection District LASED/NCDDS/IC/36/17 / One Consultant for Develop Individual Component 2: Project 2017-07- 2017-08- 2017-09- 2019-05- and Upgrade of Management IDA / 58070 Post Consultant Open 40,000.00 0.00 Canceled 2017-05-31 Management 19 09 13 13 Information System (MIS) for Selection District LASED/NCDDS/IC/50/17 / Sub-Component 1.1: Social Individual 2017-10- 2017-12- 2018-01- 2018-01- 2018-03- 2018-02- 2018-03- 2021-12- One Consultant for Annual IDA / 58070 Land Concession Investment Post Consultant Open 23,760.00 63,300.00 Signed 2017-11-01 24 20 29 10 02 14 05 31 Progress Survey Planning and Prioritization Selection Individual LASED/NCDDS/IC/49/17 / IT Component 2: Project 2017-12- 2018-02- 2018-03- 2018-03- 2018-03- 2018-04- 2018-03- 2021-12- IDA / 58070 Post Consultant Open 112,941.18 108,335.29 Signed 2018-01-01 Adviser Management 25 19 16 12 20 16 21 31 Selection LASED/NCDDS/IC/55/18 / Individual Component 2: Project 2018-07- 2018-09- 2019-03- 2018-10- 2019-03- 2018-11- 2019-03- 2021-11- M&E and Training Assistant IDA / 58070 Post Consultant Open 33,882.35 31,218.35 Signed 2018-08-06 Management 12 24 01 15 04 19 29 18 (MTA) Selection LASED/NCDDS/IC/25A/18 / Sub-component 1.2: Land Individual 2018-08- 2018-10- 2019-07- 2018-11- 2019-08- 2018-12- 2019-08- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 96,411.76 52,451.47 Signed 2018-08-24 20 12 22 02 08 07 14 31 for LASED Kg. Chhnang. (New) Infrastructure Development Selection LASED/NCDDS/IC/56/19 / Sub-component 1.3: Individual 2019-03- 2019-04- 2019-06- 2019-04- 2019-07- 2019-05- 2019-07- 2021-12- Senior Agronomist and Value IDA / 58070 Agriculture and Livelihood Post Consultant Open 94,823.53 92,510.29 Signed 2019-02-15 14 05 25 26 08 31 10 31 Chain Adviser for GDA Development Selection LASED/NCDDS/F/36/19 / Contract with NGOs to form Sub-component 1.3: and strengthen the Pending 2019-05- 2019-07- 2021-12- IDA / 58070 Agriculture and Livelihood Post Direct Selection Direct 40,000.00 0.00 2019-05-01 community forestry Implementation 11 15 31 Development conservation in project target sites. LASED/NCDDS/IC/17A/19 / Sub-component 1.2: Land Individual 2019-02- 2019-05- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 54,705.88 56,130.88 Signed 2019-03-15 13 03 23 24 16 28 23 31 for LASED Thbong Khmum. Infrastructure Development Selection LASED/NCDDS/IC/23A/19 / Sub-component 1.2: Land Individual 2019-03- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 56,529.41 52,451.47 Signed 2019-03-25 15 13 22 03 30 08 31 31 for LASED Kg. Thom. (New) Infrastructure Development Selection LASED/NCDDS/IC/06B/19 / Sub-component 1.2: Land Individual 2019-03- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-06- 2021-12- New Senior National IDA / 58070 Preparation and Post Consultant Open 91,176.50 90,485.29 Terminated 2019-04-01 27 20 03 10 20 15 27 31 Operation and M&E Advisor at Infrastructure Development Selection GDH LASED/NCDDS/IC/59/19 / National Short-Term Sub-component 1.2: Land Consultant for Social Risk 2019-10- 2019-09- 2019-10- 2019-11- 2019-10- 2020-02- IDA / 58070 Preparation and Post Direct Selection Direct 13,500.00 22,500.00 Signed 2019-08-29 Management Framework 08 08 09 12 21 10 Infrastructure Development Development for LASED III Preparation LASED/NCDDS/IC/60/19 / National Short-Term Sub-component 1.2: Land Consultant for Environmental 2019-10- 2019-09- 2019-10- 2019-11- 2019-10- 2019-11- IDA / 58070 Preparation and Post Direct Selection Direct 13,500.00 18,000.00 Signed 2019-08-29 Risk Management Framework 08 08 09 12 21 21 Infrastructure Development Development for LASED III Preparation LASED/NCDDS/IC/61/19 / Sub-component 1.2: Land National Monitoring and 2019-10- 2019-09- 2019-10- 2019-11- 2019-10- 2021-12- IDA / 58070 Preparation and Post Direct Selection Direct 78,400.00 75,925.50 Signed 2019-08-29 Evaluation Consultant for 08 08 09 12 18 31 Infrastructure Development LASED II at NCDDS LASED/GDH/IC/62/19 / Sub-component 1.2: Land National Monitoring and 2019-10- 2019-09- 2019-10- 2019-11- 2019-10- 2021-12- IDA / 58070 Preparation and Post Direct Selection Direct 78,400.00 74,466.00 Signed 2019-08-29 Evaluation Consultant for 08 08 09 12 21 31 Infrastructure Development LASED II at GDH LASED/NCDDS/IC/58/19 / Sub-component 1.2: Land International Short-Term 2019-10- 2019-10- 2019-10- 2019-12- 2019-10- 2020-01- IDA / 58070 Preparation and Post Direct Selection Direct 18,750.00 20,930.23 Signed 2019-09-26 Consultant for Environmental 08 06 09 10 21 04 Infrastructure Development Management LASED/NCDDS/IC/47A/19 / Sub-component 1.3: Individual Community Development and Pending 2019-11- 2019-12- 2020-01- 2021-12- IDA / 58070 Agriculture and Livelihood Post Consultant Open 22,400.00 0.00 2019-09-26 Agriculture Facilitator for Implementation 14 05 09 31 Development Selection Peam, KCH (New) KH-NCDDS-135175-CS-CDS Sub-component 1.2: Land / International Short Term 2019-10- 2019-10- 2019-10- 2019-12- 2019-10- 2020-01- IDA / 58070 Preparation and Post Direct Selection Direct 30,000.00 22,000.00 Terminated 2019-09-26 Consultant for Social Risk 08 06 09 10 21 19 Infrastructure Development Management LASED/NCDDS/IC/21A/19 / Sub-component 1.2: Land Individual 2019-10- 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 45,588.00 42,333.09 Signed 2019-11-01 29 20 17 10 23 14 31 31 for LASED Kratie (New) Infrastructure Development Selection Page 13 LASED/NCDDS/IC/22A/19 / Sub-component 1.2: Land Individual Provincial Finance Consultant 2019-10- 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2021-12- IDA / 58070 Preparation and Post Consultant Open 45,588.00 43,345.85 Signed 2019-11-01 for LASED Tbong Khmum 29 20 17 10 23 14 31 31 Infrastructure Development Selection (New) LASED/NCDDS/IC/24A/19 / Sub-component 1.2: Land Individual 2019-10- 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2021-12- Provincial Finance Consultant IDA / 58070 Preparation and Post Consultant Open 45,588.00 46,136.47 Signed 2019-11-01 29 20 17 10 23 14 31 31 for LASED Kg. Speu. (New) Infrastructure Development Selection LASED/GDH/IC/12A/19 / Individual Component 2: Project 2019-10- 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2021-12- Admin and Finace Assistant at IDA / 58070 Post Consultant Open 23,529.00 19,319.65 Signed 2019-11-01 Management 28 20 18 10 24 14 27 31 GDH (New) Selection LASED/GDH/IC/63/19 / Sub-Component 1.1: Social Individual Short-term consultant to Pending 2019-12- 2020-01- 2020-02- 2020-08- IDA / 58070 Land Concession Investment Post Consultant Open 7,600.00 0.00 2019-11-05 produce Orthophoto for Land Implementation 24 14 18 16 Planning and Prioritization Selection Activities in Daung Site, KPT LASED/GDH/IC/64/19 / Short-term Consultant to Sub-Component 1.1: Social Individual Pending 2020-01- 2020-01- 2020-02- 2020-08- Update, Revised PIM / COM IDA / 58070 Land Concession Investment Post Consultant Open 30,000.00 0.00 2019-11-15 Implementation 03 24 28 26 for LASED III, Including ICLT Planning and Prioritization Selection chapter. LASED/NCDDS/IC/19A/19 / Sub-component 1.2: Land Individual Pending 2020-01- 2020-01- 2020-03- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 41,941.18 0.00 2019-11-20 Implementation 08 29 04 31 for LASED Kg. Speu (New). Infrastructure Development Selection LASED/GDH/IC/65/19 / Sub-component 1.2: Land 2019-11- 2019-11- 2019-11- 2020-01- 2019-11- 2021-01- Project Management Support IDA / 58070 Preparation and Post Direct Selection Direct 26,470.59 22,500.00 Signed 2019-11-14 07 24 08 28 18 27 Consultant at GDH Infrastructure Development LASED/NCDDS/IC/66/19 / International Short-Term Sub-component 1.2: Land Consultant for Support the 2019-12- 2019-12- 2019-12- 2020-03- 2020-01- 2020-03- IDA / 58070 Preparation and Post Direct Selection Direct 18,442.00 13,588.24 Signed 2019-12-20 formulation of an Agricultural 17 30 24 04 03 29 Infrastructure Development Service Strategy for LASED III (21 days) LASED/NCDDS/IC/18A/19 / Sub-component 1.2: Land Individual Pending 2020-03- 2020-03- 2020-04- 2021-12- Provincial Operation Advisor IDA / 58070 Preparation and Post Consultant Open 40,117.65 0.00 2020-01-15 Implementation 04 25 29 31 for LASED Kg. Thom. (New) Infrastructure Development Selection LASED/NCDDS/IC/71/20 / Sub-component 1.2: Land Individual 2020-05- 2020-05- 2020-06- 2021-12- Finance Assistant for LASED II IDA / 58070 Preparation and Post Consultant Open 16,941.18 0.00 Canceled 2020-03-16 04 25 29 31 - GDH Infrastructure Development Selection LASED/NCDDS/IC/72/20 / Sub-component 1.2: Land Individual Pending 2020-05- 2020-05- 2020-06- 2021-12- Administrative Assistant for IDA / 58070 Preparation and Post Consultant Open 16,941.18 0.00 2020-03-15 Implementation 03 24 28 31 LASED II - NCDDS Infrastructure Development Selection LASED/NCDDS/IC/40A/20 / Sub-component 1.3: Individual Community Development and 2020-08- 2020-08- 2020-09- 2021-06- IDA / 58070 Agriculture and Livelihood Post Consultant Open 8,000.00 0.00 Canceled 2020-07-13 Agriculture Facilitator for 24 28 01 30 Development Selection Thmey, KRT (New) LASED/NCDDS/IC/57/19 / Consultant for Measurement Sub-Component 1.1: Social Individual the awareness and 2019-06- 2019-06- 2019-08- 2020-01- IDA / 58070 Land Concession Investment Post Consultant Open 20,000.00 0.00 Canceled 2019-04-19 understanding of LRs and 07 28 02 31 Planning and Prioritization Selection project team on the LASED II and SLC. LASED/NCDDS/IC/51/18 / One National Consultant for Sub-Component 1.1: Social Individual PIM revision of LASEDII 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58070 Land Concession Investment Post Consultant Open 16,000.00 0.00 Canceled 2018-11-01 (Lumpsum Contract external 20 10 14 13 Planning and Prioritization Selection short term consultant out put base) LASED/NCDDS/IC/52/18 / One National Consultant for Small scale Solar-irrigation Sub-Component 1.1: Social Individual system study in 2 sites in Dar 2018-10- 2018-11- 2018-12- 2019-06- IDA / 58070 Land Concession Investment Post Consultant Open 30,000.00 0.00 Canceled 2018-09-03 and Choam krovien 22 12 17 15 Planning and Prioritization Selection (Lumpsum Contract external short term consultant out put base for study (2 sites) for LASED II. LASED/NCDDS/IC/53/18 / One National Consultant for Sub-Component 1.1: Social Individual Socio Economic baseline 2018-09- 2018-10- 2018-11- 2019-05- IDA / 58070 Land Concession Investment Post Consultant Open 20,000.00 0.00 Canceled 2018-08-01 survey (Lumpsum Contract 19 10 14 13 Planning and Prioritization Selection external short term consultant out put base for LASED II LASED/NCDDS/IC/54/18 / One National Consultant for Effectiveness application of Sub-Component 1.1: Social Individual 2018-11- 2018-12- 2019-01- 2019-07- safeguard assessment IDA / 58070 Land Concession Investment Post Consultant Open 25,000.00 0.00 Canceled 2018-10-01 19 10 14 13 (Lumpsum Contract short Planning and Prioritization Selection term consultant out put base) for LASED II LASED/NCDDS/IC/34/21 / Sub-Component 1.1: Social Individual International Consultant for Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58070 Land Concession Investment Post Consultant Open 65,000.00 0.00 2020-12-28 Preparing Project Completion Implementation 15 08 12 09 Planning and Prioritization Selection Report Page 14