Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Above US$ 1,500,000 All Services) 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive July 9, 2010 financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary NA NA NA NA of the ICB (Works) Summary 6.69 4 No Prior of the ICB (Goods) Summary 3.8 9 No Post All of the NCB (Works) Summary 14.70 14 No Post All of the NCB (Goods) Summary NA NA NA NA of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Commentes Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 0.35 2 Prior of number of contracts that will be let under QCBS Summary 1.4 38 Post LCS/ IC of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Eastern Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-10-26 2021-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58330 Agence Djiboutienne de Development Social Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned COMP1/T1/2017 / Travaux d'extension de 5 salles de Social and Economic Services Single Stage - One 2018-12- IDA / 58330 A posteriori Appel d'offres Open - National 325,070.00 375,984.42 Signé 2018-02-10 2018-09-24 2018-02-17 2018-03-31 2018-11-07 2018-04-30 2018-12-04 2018-06-04 2018-12-13 Lycée et réhabilitation du and Infrastructure Envelope 01 dortoir à Obock COMP1/T3/2017 / Travaux Social and Economic Services Single Stage - One En attente 2018-09- de raccordement pecherie IDA / 58330 A posteriori Appel d'offres Open - National 450,704.00 0.00 2017-11-20 2017-11-27 2018-01-08 2018-02-07 2018-03-14 and Infrastructure Envelope d'exécution 10 d'Obock COMP1/T8/2017 / construction de locaux Social and Economic Services Single Stage - One 2018-11- IDA / 58330 A posteriori Demande de prix Limited 101,408.00 95,992.16 Signé 2018-03-17 2018-10-22 2018-05-12 2019-01-13 communautaire/communautai and Infrastructure Envelope 08 re à Ali addé COMP1/T9/2017 / Réhabilitation du local Social and Economic Services Single Stage - One En attente 2018-10- IDA / 58330 A posteriori Demande de prix Limited 40,000.00 0.00 2018-02-17 2018-04-14 communautaire (UNFD) à Holl- and Infrastructure Envelope d'exécution 11 Holl COMP2/T1/2017 / rénovation et renforcement de Social and Economic Services Single Stage - One En attente 2018-06- perimetres existants d'où 5 IDA / 58330 A posteriori Demande de prix Limited 135,211.00 0.00 2017-11-01 2017-12-27 and Infrastructure Envelope d'exécution 25 reservoirs , 5 puits , 5 champs solaires pour Obock DJ-ADDS-29135-CW-RFB / Social and Economic Services Single Stage - One En attente 2018-06- Travaux extention du centre IDA / 58330 A posteriori Appel d'offres Open - National 399,493.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-02-08 and Infrastructure Envelope d'exécution 08 de santé à Obock DJ-ADDS-29136-CW-RFB / rehabilitation/ extention du Social and Economic Services Single Stage - One En attente 2018-08- IDA / 58330 A posteriori Appel d'offres Open - National 436,620.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 centre de santé Ali addé et and Infrastructure Envelope d'exécution 07 Hol Hol en 2 lots séparés DJ-ADDS-29129-CW-DIR / Passation de Travaux d'extension Résau/ Social and Economic Services 1,188,375.0 2019-04- IDA / 58330 A priori marché de gré à Direct 1,188,371.09 Signé 2017-09-19 2019-05-14 2017-10-04 2020-09-23 2017-10-27 2017-12-21 Electricité d'Obock et Holl- and Infrastructure 0 25 gré Holl 004/2017/TVX/IDA- PRDDCA/ADDS / avenant n°1 Passation de au marché des travaux Social and Economic Services 210,936,565. 2019-09- IDA / 58330 A priori marché de gré à Direct 0.00 Annulé 2019-02-21 2019-02-26 2019-04-02 d'électrification Holhol et and Infrastructure 00 29 gré extension réseau electrique d'Obock COMP1/T5/2017 / F+P et raccordement des installations électriques des Social and Economic Services Single Stage - One 2018-05- logements, locaux IDA / 58330 A posteriori Appel d'offres Open - National 241,392.00 324,046.72 Signé 2017-10-31 2018-03-29 2017-11-07 2017-12-07 2018-05-02 2018-01-06 2018-06-20 2018-02-10 2018-06-25 and Infrastructure Envelope 11 commerciaux et établissements publics à Holl- Holl COMP4/T1/2019 / Travaux Project Management, and Single Stage - One 2020-06- de construction d'une salle IDA / 58330 A posteriori Appel d'offres Open - National 185,915.00 143,370.91 Signé 2019-09-08 2019-10-21 2019-09-13 2019-10-25 2019-12-11 2019-11-24 2020-01-27 2019-12-29 2020-02-02 Monitoring and Evaluation Envelope 26 d'archives COMP1/T7/2017 / Travaux Social and Economic Services Single Stage - One En cours 2020-06- de construction d'une piste en IDA / 58330 A posteriori Appel d'offres Open - National 662,423.00 0.00 2019-09-08 2018-11-01 2019-09-13 2021-01-19 2019-10-25 2019-11-24 2019-12-29 and Infrastructure Envelope d'exécution 26 pierres taillées (voiries Obock) COMP1/T6/2017 / Travaux de construction de logements Social and Economic Services Single Stage - One En attente 2018-05- de fonction et réhabilitation IDA / 58330 A posteriori Appel d'offres Open - National 1,616,902.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 and Infrastructure Envelope d'exécution 09 de l’école primaire et collège de Holl Holl. COMP2/T2/2017 / Social and Economic Services Single Stage - One En attente 2018-06- rénovation et renforcement de IDA / 58330 A posteriori Demande de prix Limited 186,183.00 0.00 2017-11-01 2017-12-27 and Infrastructure Envelope d'exécution 25 perimetres existants pour Holhol COMP2/T3/2017 / rénovation et renforcement de Social and Economic Services Single Stage - One En attente 2018-06- perimetres existants d'où 5 IDA / 58330 A posteriori Demande de prix Limited 149,000.00 0.00 2017-11-01 2017-12-27 and Infrastructure Envelope d'exécution 25 reservoirs , 5 puits, 5 champs solaires pour Ali Addé COMP1/T1/2019 / Travaux Passation de de réhabilitation et Social and Economic Services En attente 2020-04- IDA / 58330 A posteriori marché de gré à Direct 87,417.00 0.00 2019-09-08 2019-09-13 2019-10-18 d'extension du Centre de and Infrastructure d'exécution 15 gré Santé de Holl Holl.. COMP1/T6/2019 / petits Social and Economic Services Single Stage - One En attente 2020-07- travaux de raccordement eau IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2019-11-25 2020-01-20 and Infrastructure Envelope d'exécution 18 et électricité pour la pêcherie.. COMP1/T7/2019 / Travaux de rénovation d'électricité Social and Economic Services Single Stage - One 2020-06- pour la salle d'urgence et salle IDA / 58330 A posteriori Demande de prix Limited 13,000.00 12,299.96 Signé 2019-11-02 2019-10-15 2019-12-28 2019-11-05 and Infrastructure Envelope 25 d'hospitalisation du CMH d'Obock Page 1 COMP1/T5/TVX/2019 / Social and Economic Services Single Stage - One 2020-09- Rénovation des locaux de IDA / 58330 A posteriori Appel d'offres Open - National 107,042.00 102,232.86 Signé 2019-11-19 2019-11-10 2019-11-24 2020-08-24 2020-01-05 2020-01-29 2020-02-04 2020-03-08 2020-03-10 2020-03-12 and Infrastructure Envelope 06 l'UNFD à Obock COMPT1/T3/2010 / travaux de raccordement de nouveaux forages, réalisation de Passation de Social and Economic Services 1,335,723.2 2020-06- conduite d'adduction d'eau et IDA / 58330 A posteriori marché de gré à Direct 1,339,674.00 Signé 2020-02-04 2020-02-19 2020-02-09 2015-11-01 2020-03-15 2020-06-10 and Infrastructure 8 13 changements des conduites gré vétustes de distribution d'eau à Obock COMP1/T5/2019 / Travaux Social and Economic Services Single Stage - One 2021-07- de rénovation des locaux de IDA / 58330 A posteriori Appel d'offres Open - National 107,042.00 102,232.86 Signé 2020-10-11 2019-11-21 2020-10-16 2020-11-15 2020-11-27 2019-12-25 2020-12-27 2020-03-18 2021-01-31 2020-03-20 and Infrastructure Envelope 30 l'UNFD à Obock COMP1/T3/2019 / Réalisation à Obock des travaux de raccordement de 05 forages, de changement de Passation de la conduite principale reliant Social and Economic Services 1,335,723.2 2020-04- IDA / 58330 A posteriori marché de gré à Direct 1,339,674.00 Signé 2019-09-08 2019-10-19 2019-09-13 2019-10-14 2019-10-18 2020-07-05 les forages au réservoir and Infrastructure 8 15 gré existant de la ville et de changement d'une partie vetuste du réseau de distribution COMPT1/T7/2019 / Fourniture +Pose et raccordement des Social and Economic Services Single Stage - One 2020-07- IDA / 58330 A posteriori Demande de prix Open - National 164,380.00 146,159.28 Signé 2020-02-09 2020-11-15 2020-04-05 2020-07-23 installations électriques des and Infrastructure Envelope 04 logements, mis en conformité de 200 logements à obock COMP2/T4/2020 / Travaux d’extension de la centrale Sustainable Environmental Single Stage - One En cours 2021-10- IDA / 58330 A posteriori Appel d'offres Open - International 3,500,000.00 0.00 2021-01-03 2020-10-25 2021-01-07 2021-01-14 2021-02-18 2021-03-20 2021-04-24 solaire et du réseau de ALI Management Envelope d'exécution 21 ADDE DJIBOUTI GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/F2/2017 / achat de Matériels informatique pour Social and Economic Services Single Stage - One En attente les lycées bénéficiaires pour le IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2017-10-07 2017-12-02 2018-05-31 and Infrastructure Envelope d'exécution compte de l'Education Informatique COMP1/F4/2017 / Passation de equipements médicaux et Social and Economic Services IDA / 58330 A priori marché de gré à Direct 1,305,900.00 650,947.00 Signé 2017-10-20 2018-05-31 2017-10-20 2020-06-24 2017-12-01 2018-02-07 2018-05-30 Mobiliers pour Obock,Ali and Infrastructure gré Addé et Hol Hol COMP2/F2/2017 / achat de matériels pour périmetres Social and Economic Services Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 166,667.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 existants d'où motopompes, and Infrastructure Envelope d'exécution brouettes... pour Obock COMP4/F1/2017 / Social and Economic Services Single Stage - One En attente acquisition d'une pick up et IDA / 58330 A posteriori Appel d'offres Open - National 124,213.00 0.00 2017-10-02 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2018-07-23 and Infrastructure Envelope d'exécution de 2 voitures 4X4. HARD TOP COMP4/F2/2017 / Social and Economic Services Single Stage - One En attente acquisition de tablettes pour IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2017-10-09 2017-12-04 2018-06-02 and Infrastructure Envelope d'exécution l'enquete COMP4/F4/2017 / acquisition d' équipement Social and Economic Services Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 84,507.00 0.00 2017-10-03 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 pour le centre de formation and Infrastructure Envelope d'exécution de l'ONARS COMP1/F3/2017 / achat de Matériels de SVT et Physique Social and Economic Services Single Stage - One IDA / 58330 A posteriori Appel d'offres Open - National 135,201.00 91,577.55 Signé 2017-10-31 2019-10-16 2017-11-05 2017-12-05 2019-11-20 2018-01-04 2020-01-29 2018-02-08 2020-06-08 2018-04-09 pour le Ministère de and Infrastructure Envelope l'Educatioon Nationale COMP2/F3/2017 / achat de matériels pour périmetres Social and Economic Services Single Stage - One En attente existants d'où motopompes, IDA / 58330 A posteriori Appel d'offres Open - International 333,334.00 0.00 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-02-22 2018-06-22 and Infrastructure Envelope d'exécution brouettes... pour Ali Addé et HolHol COMP3/F1BIS/2017 / Social and Economic Services Single Stage - One En attente Acquisition de kits culinaires IDA / 58330 A posteriori Demande de prix Limited 20,000.00 0.00 2017-11-05 2017-12-31 2018-01-20 and Infrastructure Envelope d'exécution pour les GEA COMP3/F1/2017 / acquisition de matériels et Social and Economic Services Single Stage - One En attente consommables pour les IDA / 58330 A posteriori Appel d'offres Open - National 180,000.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-04-09 and Infrastructure Envelope d'exécution groupements de femmes et jeunes COMP4/F3/2017 / acquisition de logiciel pour Social and Economic Services Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 25,000.00 0.00 2017-11-17 2018-01-12 2018-07-11 l'analyse des données des and Infrastructure Envelope d'exécution enquetes COMP1/F1/2017 / Equipements chauds et Froid pour les lycés techniques d' Social and Economic Services Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - International 428,391.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 Ali Sabieh et Obock pour le and Infrastructure Envelope d'exécution Ministère de l' Education Nationale COMP1/F4/2019 / acquisition de chambres Project Management, and Single Stage - One IDA / 58330 A posteriori Appel d'offres Open - National 123,944.00 78,248.74 Signé 2019-09-08 2019-06-20 2019-09-13 2019-10-25 2019-08-07 2019-11-24 2019-09-17 2019-12-29 2019-10-03 2020-06-26 froides positives pour la Monitoring and Evaluation Envelope pecherie Page 2 COMP1/F5/2019 / Regional Support for Acquisition de boutres, et Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 275,000.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 autres matériels etc.. pour les Envelope d'exécution Knowledge pecheurs d'obock COMP1/F6/2019 / Regional Support for Acquisition d'équipements Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 56,338.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pours les dortoirs et Envelope d'exécution Knowledge réfectoires d'Obock COMP1/F1/2019 / Acquisition d'équipements Project Management, and Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 54,995.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pour le collège de Alli Addé Monitoring and Evaluation Envelope d'exécution (tables, chaises,...) COMP1/F2/2019 / Regional Support for Acquisition d'équipements Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 99,000.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pour l'UNFD à Holhol, Ali addé Envelope d'exécution Knowledge et Obock COMP1/F2/2017 / achat de Matériels informatique pour Social and Economic Services Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 169,000.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 les lycées bénéficiaires/ and Infrastructure Envelope d'exécution Education COMP1/F5/2017 / Passation de Social and Economic Services acquisition de 10 200 foyers IDA / 58330 A priori marché de gré à Direct 229,859.00 183,345.08 Signé 2019-11-15 2020-06-18 2019-11-20 2020-06-24 2019-12-16 2020-01-08 2020-03-15 and Infrastructure améliorés pour les 3 sites gré COMP1/F1/2020 / Regional Support for Passation de acquisition d'équipements et IDA / 58330 Coordination, Capacity and A posteriori marché de gré à Direct 650,374.00 650,734.00 Signé 2020-10-07 2020-05-26 2020-10-12 2020-10-01 2020-11-16 2020-11-12 2021-05-15 matériels médicaux pour la Knowledge gré CAMME. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/NCS1/2019 / séminaire Management de Passation de projets et programmes par Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 12,435.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 indicateurs, résultats et Monitoring and Evaluation d'exécution gré tableaux de bord COMP4/NCS2/2019 / Formation: cycle FI05 intitulé "La passation et l'exécution des marchés selon les Passation de Project Management, and En attente nouvelles procédures IDA / 58330 A posteriori marché de gré à Direct 15,000.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 Monitoring and Evaluation d'exécution nationales et des bailleurs gré (Banque Mondiale, Banque Africaine de Développement, Union Européenne...)" COMP4/CSC3/2019 / Formation de la responsable Passation de gestion financière en gestion Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 15,000.00 0.00 2019-09-24 2019-09-29 2019-11-03 2020-05-01 administrative et financière, la Monitoring and Evaluation d'exécution gré clôture et l'audit des programmes et projets COMP4/NCS4/2019 / formation du chef de projet Passation de en " préparation ala Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 15,171.00 0.00 2019-11-17 2019-11-22 2019-12-27 2019-12-30 certification en gestion de Monitoring and Evaluation d'exécution gré projet PMP (project Managment professionnal) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/C1/2017 / Recrutement d'un Bureau d'Etudes et de supervision Sélection fondée Social and Economic Services pour les travaux d'extension, IDA / 58330 A posteriori sur la qualité et le Open - National 252,234.00 332,425.00 Signé 2017-10-02 2017-07-26 2017-10-23 2017-12-06 2018-01-08 2018-01-03 2018-01-31 2018-02-02 2018-03-07 2018-03-09 2018-04-04 2018-04-13 2018-04-05 2019-04-13 and Infrastructure construction, réhabilitation coût des établissements scolaires , le local communautaire COMP1/C2/2017 / Recrutement d'un Bureau Sélection fondée d'Etudes pour la supervision Social and Economic Services sur les En attente IDA / 58330 A posteriori Open - National 83,611.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 des travaux d'extension de and Infrastructure qualifications des d'exécution centres de santé pour obock, consultants ali addé et Hol hol COMP1/C3/2017 / Récrutement d'un consultant individuel pour les études et Sélection fondée la supervision les travaux Social and Economic Services sur les En attente IDA / 58330 A posteriori Open - National 30,000.00 0.00 2017-10-30 2017-11-20 2018-01-03 2018-02-02 2018-03-09 2018-09-05 d'installations dans les and Infrastructure qualifications des d'exécution logements, locaux consultants commerciaux et établissement publics à Holl-Holl COMP1/C4/2017 / Sélection fondée Recrutement d'un bureau Social and Economic Services sur les En attente IDA / 58330 A posteriori Open - National 45,070.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 d'etudes pour raccordement and Infrastructure qualifications des d'exécution Pecherie (Obock) consultants Page 3 COMP1/C5/2017 / Recrutement d'un BE pour les Sélection fondée travaux de forrage de Hol hol Social and Economic Services En attente IDA / 58330 A posteriori sur la qualité et le Open - National 188,732.00 0.00 2017-12-15 2018-01-05 2018-02-18 2018-03-18 2018-04-17 2018-05-22 2018-06-26 2019-06-26 et Ali Addé et du reseau and Infrastructure d'exécution coût d'adduction d'eau à Obock et Holl-Holl COMP2/C1/2017 / Sélection fondée Recrutement d'un bureau Social and Economic Services sur les En attente d'etudes pour la la rénovation IDA / 58330 A posteriori Open - National 40,564.00 0.00 2017-10-05 2017-10-26 2017-12-09 2018-01-08 2018-02-12 2018-08-11 and Infrastructure qualifications des d'exécution et renforcement des consultants perimetres existants COMP2/C2/2017 / Recrutement d'un bureau Sélection fondée Social and Economic Services d'etudes pour l'extension de IDA / 58330 A posteriori sur la qualité et le Open - National 152,369.00 228,500.00 Signé 2017-10-02 2018-07-12 2017-10-23 2017-12-06 2018-08-29 2018-01-03 2018-10-24 2018-02-02 2018-12-26 2018-03-09 2019-01-09 2018-04-13 2019-01-19 2019-04-13 and Infrastructure la centrale solaire et le forage coût d'Ali-Addé COMP4/C10/2017 / Social and Economic Services Sélection au En attente recrutement d 'un cabinet IDA / 58330 A posteriori Open - National 10,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2018-10-10 and Infrastructure moindre coût d'exécution pour l'Audit Financier COMP4/C11/2017 / Recrutement d'un consultant Sélection fondée pour la collecte de donnée Social and Economic Services sur les En attente IDA / 58330 A posteriori Open - National 8,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 administratives de toutes les and Infrastructure qualifications des d'exécution infrastructures sociales de consultants base COMP1/C2/2019 / Recrutement d'un cabinet Sélection fondée Social and Economic Services En attente pour l'étude topographique de IDA / 58330 A posteriori sur la qualité et le Open - National 30,000.00 0.00 2019-09-23 2019-10-14 2019-11-27 2019-12-25 2020-01-24 2020-02-28 2020-04-03 2021-04-03 and Infrastructure d'exécution l'adduction d'eau potable a coût partir d'Ali sabieh COMP1/C5/2017 / Recrutement d'un BE pour les Sélection fondée Social and Economic Services En cours travaux de raccordements de IDA / 58330 A posteriori sur la qualité et le Open - International 500,000.00 0.00 2020-02-20 2020-01-09 2020-03-12 2020-08-16 2020-04-25 2020-05-23 2020-06-22 2020-07-27 2020-08-31 2021-08-31 and Infrastructure d'exécution Hol hol et Ali Addé au coût reservoir d'eau d'Ali-Sabieh INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/C1/2017 / Social and Economic Services IDA / 58330 A posteriori Individuel Open 30,000.00 29,911.54 Signé 2017-10-02 2016-10-25 2017-11-20 2017-03-02 2017-12-11 2017-03-02 2018-01-15 2017-04-01 2018-07-14 coordinateur de projet and Infrastructure COMP4/C2/2017 / Social and Economic Services recrutement d'ingénieur en IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-02 2016-10-25 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure Infrastructures COMP4/C3/2017 / recrutement de 4 techniciens Social and Economic Services IDA / 58330 A posteriori Individuel Open 62,400.00 0.00 En cours d'examen 2017-10-02 2017-03-20 2017-11-20 2017-12-11 2018-01-15 2018-07-14 supérieurs pour les régions et and Infrastructure Djibouti ville COMP4/C5/2017 / recrutement d'un spécialiste Social and Economic Services IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-02 2016-11-08 2017-11-20 2017-12-11 2018-01-15 2018-07-14 en sauvegardes and Infrastructure environnementales et sociales COMP4/C6/2017 / Social and Economic Services recrutement d'un responsable IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-02 2016-11-08 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure Suivi evaluation COMP4/C7/2017 / Social and Economic Services IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-02 2016-11-15 2017-11-20 2017-12-11 2018-01-15 2018-07-14 recrutement d'un comptable and Infrastructure COMP4/C8/2017 / Social and Economic Services En attente recrutement d'un assistant de IDA / 58330 A posteriori Individuel Open 12,000.00 0.00 2017-11-05 2017-12-24 2018-01-14 2018-02-18 2018-08-17 and Infrastructure d'exécution projet COMP4/C9/2017 / Social and Economic Services recrutement d'un spécialiste IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-05 2018-01-08 2017-11-23 2017-12-14 2018-01-18 2018-07-17 and Infrastructure Passation des marchés COMP4/C12/2017 / Enquette Sélection de Social and Economic Services En attente sur les migrants à Balbala et à IDA / 58330 A priori consultants par Direct 71,967.00 0.00 2017-10-02 2017-10-07 2017-11-11 2018-05-10 and Infrastructure d'exécution Djibouti-Ville entente directe COMP4/C16/2017 / Récrutement d'un expert Social and Economic Services En cours international pour la IDA / 58330 A posteriori Individuel Open 30,000.00 0.00 2017-10-02 2017-09-14 2017-11-20 2017-12-11 2018-01-15 2018-07-14 and Infrastructure d'exécution préparation de la stratégie de l'ONARS COMP4/C17/2017 / Récrutement d'un consultant individuel pour l'appui de Social and Economic Services En cours IDA / 58330 A posteriori Individuel Open 11,268.00 0.00 2017-10-02 2017-09-14 2017-11-20 2017-12-11 2018-01-15 2018-07-14 l'expert en charge de la and Infrastructure d'exécution préparation de la stratégie de l'ONARS COMP4/C17/2017_1 / recrutement d'un expert Social and Economic Services En cours IDA / 58330 A posteriori Individuel Open 85,000.00 0.00 2017-11-15 2017-09-18 2018-01-03 2018-01-24 2018-02-28 2018-08-27 international en manuel de and Infrastructure d'exécution procédures ONARS COMP4/C4/2017 / Social and Economic Services recrutement d'un spécialiste IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 En cours d'examen 2017-10-02 2016-11-08 2017-11-20 2017-12-11 2018-01-15 2019-01-15 and Infrastructure en agriculture Page 4 COMP4/C13/2017 / recrutement d'un consultant Social and Economic Services En attente IDA / 58330 A posteriori Individuel Open 29,734.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 pour l'enquête quantitative and Infrastructure d'exécution ménage COMP4/C14/2017 / recrutement d'un consultant Social and Economic Services En attente pour l'enquête quantitative IDA / 58330 A posteriori Individuel Open 26,133.00 0.00 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 and Infrastructure d'exécution jeunes femmes et périmètres agro pastoraux COMP4/C16/2017 / Recrutement d'un consultant Social and Economic Services En attente IDA / 58330 A posteriori Individuel Limited 34,000.00 0.00 2018-03-14 2018-03-19 2018-04-09 2018-05-14 2018-06-28 pour l'enquête de suivi des and Infrastructure d'exécution indicateurs DJ-ADDS-54279-CS-INDV / recrutement d'un consultantpour la Social and Economic Services En attente IDA / 58330 A posteriori Individuel Limited 20,000.00 0.00 2017-10-05 2017-10-10 2017-10-31 2017-12-05 2018-06-03 sensibilisation,étude de and Infrastructure d'exécution marchés, mise a jour du listing COMP4/C17/2017_2 / Social and Economic Services En attente recrutement d'un consultant IDA / 58330 A posteriori Individuel Limited 80,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-06-29 and Infrastructure d'exécution pour l'enquete de référence 40000 / recrutement d'un Social and Economic Services En attente consultant pour la IDA / 58330 A posteriori Individuel Limited 40,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 and Infrastructure d'exécution communication COMP3/C1/2017 / recrutement d'un consultant Social and Economic Services En attente IDA / 58330 A posteriori Individuel Limited 20,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 pour l'analyse and Infrastructure d'exécution complémentaire de l'enquete 022/2018/CO/IDA- Sélection de PRDDCA/ADDS / recrutement IDA / 58330 Livelihoods Program A posteriori consultants par Direct 8,400.00 0.00 En cours d'examen 2019-01-16 2018-12-04 2019-01-26 2019-04-01 2019-09-28 d'une chargée des GEA pour la entente directe rgion OBOCK 023/2018/CO/IDA- Sélection de PRDDCA/ADDS / recrutement IDA / 58330 Livelihoods Program A posteriori consultants par Direct 8,400.00 0.00 En cours d'examen 2019-01-16 2018-12-04 2019-01-26 2019-04-01 2019-09-28 d'une chargée des GEA pour la entente directe région d'Ali sabieh 024/2018/CO/IDA- PRDDCA/ADDS / Recrutement Sélection de En attente d'une facilitatrice du IDA / 58330 Livelihoods Program A posteriori consultants par Direct 7,200.00 0.00 2019-01-30 2019-02-09 2019-04-15 2019-10-12 d'exécution programme de moyens de entente directe subsistance des jeunes. 004/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'un facilitateur à Holl-Holl Sélection de Project Management, and En attente pour le Renforcement de IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Monitoring and Evaluation d'exécution capacités des jeunes et pour entente directe la Préparation au concours de Microprojets 005/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'une facilitatrice à Holl-Holl Sélection de Project Management, and En attente pour le Renforcement de IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Monitoring and Evaluation d'exécution capacités des jeunes et pour entente directe la Préparation au concours de Microprojets. 006/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'une facilitatrice à Holl-Holl Sélection de Project Management, and En attente pour le Renforcement de IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Monitoring and Evaluation d'exécution capacités des jeunes et pour entente directe la Préparation au concours de Microprojets. 007/2019/CO/IDA- PRDDCA/ADDS / Recrutement d’un facilitateur à Ali-Addeh Sélection de Project Management, and En attente pour le Renforcement de IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Monitoring and Evaluation d'exécution capacités des jeunes et pour entente directe la Préparation au concours de Microprojets. 020/2019/CO/IDA- PRDDCA/ADDS / recrutement Sélection de Project Management, and En attente d'un consultant pour IDA / 58330 A posteriori consultants par Direct 4,250.00 0.00 2019-04-02 2019-04-12 2019-06-16 2019-12-13 Monitoring and Evaluation d'exécution l'actualisation des indicateurs entente directe DRIPDIP COMP4/C19/2019 / Project Management, and recrutement d'un consultant IDA / 58330 A posteriori Individuel Open 15,000.00 23,000.00 Signé 2019-07-15 2019-06-09 2019-09-02 2019-07-18 2019-09-23 2019-07-29 2019-10-28 2019-07-30 2020-04-25 Monitoring and Evaluation pour la revue mi-parcours COMP4/C20/2019 / Sélection de Project Management, and En cours recrutement d'un coordinateur IDA / 58330 A posteriori consultants par Direct 30,000.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 Monitoring and Evaluation d'exécution pour la composante III entente directe COMP4/C21/2019 / Sélection de Project Management, and En cours recrutement d'un expert micro IDA / 58330 A posteriori consultants par Direct 24,000.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 Monitoring and Evaluation d'exécution entreprise entente directe COMP4/C22/2019 / Sélection de Project Management, and En cours recrutement d'une assistante IDA / 58330 A posteriori consultants par Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 Monitoring and Evaluation d'exécution pour le coordinateur du projet entente directe COMP4/C23/2019 / Sélection de recrutement d'une assistante Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 pour le coordinateur de la Monitoring and Evaluation d'exécution entente directe composante III Page 5 COMP4/C24/2019 / Sélection de recrutement d'une facilitatrice Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 4,733.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 communautaire des femmes Monitoring and Evaluation d'exécution entente directe à Holhol COMP4/C25/2019 / Sélection de recrutement d'une facilitatrice Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 communautaire pour les Monitoring and Evaluation d'exécution entente directe femmes à obock COMP4/C26/2019 / Sélection de recrutement d'une facilitatrice Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 communautaire pour les Monitoring and Evaluation d'exécution entente directe femmes a Obock COMP4/C27/2019 / Sélection de recrutement d'une facilitatrice Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 communautaire pour les Monitoring and Evaluation d'exécution entente directe femmes a Obock COMP4/C28/2019 / Sélection de recrutement d'une facilitatrice Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 communautaire pour les Monitoring and Evaluation d'exécution entente directe femmes a Obock COMP1/C1/2019 / Regional Support for Recrutement d'un consultant En attente IDA / 58330 Coordination, Capacity and A posteriori Individuel Limited 32,000.00 0.00 2019-11-12 2019-11-17 2019-12-08 2020-01-12 2020-02-26 pour l'étude topographique d'exécution Knowledge dédiée a la DHR... COMP3/C4/2019 / recrutement d'un spécialiste Project Management, and En cours IDA / 58330 A posteriori Individuel Limited 15,000.00 0.00 2019-11-26 2019-10-09 2019-12-01 2019-12-22 2020-01-26 2020-01-30 en développement Monitoring and Evaluation d'exécution agropastorale COMP4/C15/2017 / recrutement d'un consultant Social and Economic Services En attente IDA / 58330 A posteriori Individuel Open - National 50,000.00 0.00 2017-10-31 2017-11-28 2017-12-12 2017-12-26 2018-02-24 pour l'enquete qualitatif and Infrastructure d'exécution (focus groupe) .. COMP3/C3/2019 / Recrutement de deux consultant hydrolaugue et Project Management, and IDA / 58330 A posteriori Individuel Limited 30,000.00 29,911.54 Signé 2019-11-12 2019-10-15 2019-11-17 2019-10-29 2019-12-08 2020-04-29 2020-01-12 2020-06-30 2020-02-26 énergeticien pour la la Monitoring and Evaluation renovation/renforcement des perimetres existants COMPR1/C2/2019 / Recrutement d'un consultant individuel pour la supervision Social and Economic Services les travaux d'installations IDA / 58330 A posteriori Individuel Limited 27,000.00 26,400.79 Signé 2020-02-05 2020-02-24 2020-02-10 2020-03-23 2020-03-02 2020-03-25 2020-04-06 2020-06-01 2020-06-05 and Infrastructure dans les logements et mis en conformité de 200 logment à obock COMP4/C2/2017 / expert Project Management, and En attente international en manuel de IDA / 58330 A posteriori Individuel Limited 85,000.00 0.00 2020-02-04 2020-02-09 2020-03-01 2020-04-05 2020-07-04 Monitoring and Evaluation d'exécution procédures /ONARS (3) COMP1/C1/2020 / recrutement du BE d'études assurant la continuité du Sélection de contrôle des travaux de Social and Economic Services En cours IDA / 58330 A posteriori consultants par Direct 121,025.00 0.00 2020-08-24 2020-03-12 2020-09-03 2020-11-07 2021-05-06 construction et réhabilitation and Infrastructure d'exécution entente directe (ecole, local communautaire, maison de fonction, route pierres taillées...) COMP4/C11/2019 / Mise a Regional Support for Sélection de jour du logiciel de gestion du IDA / 58330 Coordination, Capacity and A posteriori consultants par Direct 94,000.00 117,075.91 Signé 2019-09-08 2020-11-07 2019-09-18 2019-09-20 2019-11-22 2020-05-25 2020-05-20 projet Knowledge entente directe COMP1/C2/2020 / Regional Support for Sélection de En cours Recrutement d'un consultant IDA / 58330 Coordination, Capacity and A posteriori consultants par Direct 24,000.00 0.00 2020-12-22 2020-12-11 2021-01-01 2021-03-07 2021-09-03 d'exécution ingénieur en HYDRAULIQUE Knowledge entente directe COMP1/C3/2020 / Regional Support for Sélection de En cours Recrutement d'un consultant IDA / 58330 Coordination, Capacity and A posteriori consultants par Direct 24,000.00 0.00 2020-12-22 2020-12-11 2021-01-01 2021-03-07 2021-09-03 d'exécution Ingénieur en Genie Civil Knowledge entente directe COMP3/C2/2020 / Sélection de recrutement d'un expert en En cours IDA / 58330 Livelihoods Program A posteriori consultants par Direct 24,000.00 15,554.00 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2021-09-03 micro entreprise pour la d'exécution entente directe composante III COMP3/C3/2020 / Sélection de En cours recrutement d'une assistante IDA / 58330 Livelihoods Program A posteriori consultants par Direct 13,200.00 13,161.08 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2021-09-03 d'exécution pour la composante III entente directe COMP3/C1/2020 / Sélection de Project Management, and En cours recrutement d'un coordinateur IDA / 58330 A posteriori consultants par Direct 30,000.00 23,929.23 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2021-09-03 Monitoring and Evaluation d'exécution pour la composante III entente directe COMP3/C2/2017 / Regional Support for recrutement d'une facilitatrice En attente IDA / 58330 Coordination, Capacity and A posteriori Individuel Limited 7,200.00 0.00 2021-02-09 2021-02-14 2021-03-07 2021-04-11 2021-10-08 pour le programme de d'exécution Knowledge moyens de subsistances a Obock Page 6