The World Bank Report No: ISR11362 Implementation Status & Results China Urban Scale Building Energy Efficiency and Renewable Energy (P130786) Public Disclosure Copy Operation Name: Urban Scale Building Energy Efficiency and Renewable Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Archive Date: 24-Oct-2013 Energy (P130786) Country: China Approval FY: 2013 Product Line: Global Environment Project Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ministry of Housing and Urban-Rural Development, Beijing Housing and Urban-Rural Development Commission, Beijing Development and Reform Commission, Ningbo Housing and Urban-Rural Development Commission Key Dates Board Approval Date 26-Apr-2013 Original Closing Date Planned Mid Term Review Date Last Archived ISR Date Effectiveness Date Revised Closing Date Actual Mid Term Review Date Global Environmental Objectives Global Environmental Objective (from Project Appraisal Document) The proposed project development objective is to improve selected national and city-level policies for (1) the promotion of low-carbon, adaptive and livable urban forms; (2) an increase in energy efficiency in public and commercial buildings; and, (3) the scale-up of commercially viable rooftop solar PV deployment. The global environment objective of the proposed project is to reduce carbon dioxide emissions from buildings in selected Chinese cities by supporting improved policy making and implementation in promoting low-carbon, adaptive and livable urban forms, increasing energy efficiency in public and commercial buildings, and scaling up commercially viable rooftop solar PV deployment. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost 1. Promoting the Development of Low-Carbon, Adaptive and Livable Urban Forms 8.76 Public Disclosure Copy 2. Improving Energy Efficiency in Public and Commercial Buildings 18.53 3. Scaling up Commercially Viable Rooftop Solar PV Deployment 2.00 4. Project Management 1.50 Overall Ratings Previous Rating Current Rating Progress towards achievement of GEO Satisfactory Overall Implementation Progress (IP) Satisfactory Overall Risk Rating Substantial Page 1 of 5 The World Bank Report No: ISR11362 Implementation Status Overview The grant and project agreements became effective on August 26, 2013. Most of the activities planned for the first year are already mobilized and at different stages of implementation. But the project is still in too early a stage for meaningful progress. Public Disclosure Copy Locations Country First Administrative Division Location Planned Actual China Zhejiang Sheng Ningbo ✔ China Beijing Beijing ✔ China Beijing Beijing ✔ Results Global Environmental Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target LOCAL urban planning and design principles Yes/No Value Yes recommended for inclusion in statutory urban Date 01-May-2013 30-Jun-2018 planning standards and regulations Comments • Draft national guidelines on development of LOCAL urban forms prepared Energy performance benchmarking and Yes/No Value Yes disclosure (EPB&D) program for large public Date 01-May-2013 30-Jun-2018 and commercial buildings developed at the Comments • Official national national level and mandatory adoption by select cities. guidelines on EPB&D for public and commercial buildings issued • Beijing, Ningbo and two additional cities issued official ordinance on adopting Public Disclosure Copy mandatory EPB&D for large public and commercial buildings Number of renewable energy service contracts Number Value 0.00 765.00 signed Date 01-May-2013 30-Jun-2018 Comments CO2 emissions reduction associated with GEF Tones/year Value 0.00 85120.00 assistance Date 01-May-2013 30-Jun-2018 Comments Page 2 of 5 The World Bank Report No: ISR11362 Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Urban form studies completed Number Value 0.00 4.00 Public Disclosure Copy Date 01-May-2013 30-Jun-2016 Comments Mayors and city planning officials trained Number Value 0.00 150.00 Date 01-May-2013 30-Jun-2018 Comments City pilots of Local urban planning and design Number Value 0.00 3.00 completed Date 01-May-2013 30-Jun-2018 Comments National and city BEP&D pilot programs Number Value 0.00 3.00 implemented Date 01-May-2013 30-Jun-2018 Comments • Ningbo pilots completed • The two additional city pilots completed Selected building EE and green building Yes/No Value Yes policies in Beijing improved and new policies Date 01-May-2013 30-Jun-2018 informed Comments One or two additional relevant policy studies completed Outreach to local stakeholders and training of Number Value 0.00 1000.00 local trades in Beijing (number of people Date 01-May-2013 30-Jun-2018 trained) Comments Floor area of green buildings in Beijing Square Meter(m2) Value 3000000.00 15000000.00 received certificates Date 01-Jan-2013 30-Jun-2018 Comments Public Disclosure Copy Bioclimatic and cost-optimal green building Yes/No Value Yes designs demonstrated in Ningbo Date 01-May-2013 30-Jun-2018 Comments New green building demonstration completed and certified Green retrofit demonstration project completed and certified Page 3 of 5 The World Bank Report No: ISR11362 Green building policies in Ningbo improved and Yes/No Value Yes new policies informed Date 01-May-2013 30-Jun-2017 Comments Ningbo green building design Public Disclosure Copy guidelines issued Outreach to local stakeholders and training of Number Value 0.00 800.00 local trades in Ningbo (number of people Date 01-May-2013 30-Jun-2018 tranined) Comments Installed rooftop solar PV capacity under the Megawatt Value 0.00 100.00 Beijing Rooftop Solar PV Scale-up Project Date 01-Jan-2013 30-Jun-2018 Comments Improved knowledge of local grid company Yes/No Value Yes about handling grid-connected rooftop PV Date 01-May-2013 30-Jun-2017 systems Comments Two-way metering pilot, final results shared in workshop Establishment of Beijing solar energy Yes/No Value Yes information portal Date 01-May-2013 30-Jun-2018 Comments Beijing solar energy information portal operational with a website for public information access Renewable energy education delivery in public Number Value 0.00 20.00 schools enhanced (number of demonstration Date 01-May-2013 30-Jun-2016 laboratories established) Comments Data on Financial Performance (as of 00000000) Financial Agreement(s) Key Dates Public Disclosure Copy Disbursements (in Millions) 0.00 0.00 0.00 0.00 0.00 Disbursement Graph Page 4 of 5 The World Bank Report No: ISR11362 Public Disclosure Copy Key Decisions Regarding Implementation None at this time. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 5 of 5