Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and 1.5 non-consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Estimated Review July 9, 2010 Ref. Descriptio Cost Package Domestic by Bank Com No. n US$ million s Preference (Prior / ment (yes/no) Post) s 1 Summary 32 2 To be Prior of the ICB Determine (Works) d 2 Summary 10.2 6 To be Prior of the ICB Determine (Goods) d 3 Summary 19.4 5 No Post of the NCB (Works) 4 Summary 0.28 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimate Packages Review Comments No. Assignment d by Bank Cost (Prior / US$ Post) million 1 Summary of 3.5 3 Prior number of contracts that July 9, 2010 will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2018-01-15 2021-02-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 Ministry of Water Irrigation and Electricity, WSS Program Management Unit Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOWIE-77733-CW-DIR / Component 2: Sanitation and Pending Pipe laying for Dire Dewa water supply services 2018-11- 2018-12- 2019-01- 2019-05- IDA / 60070 Post Direct Selection Direct 458,379.00 0.00 Implementat town water supply project by improvement in secondary 28 03 07 07 ion Dire Dewa town cities ET-MOWIE-143512-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Asosa IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Asosa Water Supply ion cities and Sewerage Authority ET-MOWIE-143682-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-01- 2020-03- 2021-05- communal latrines for IDA / 60070 Post Request for Bids Open - National 1,626,000.00 0.00 Implementat improvement in secondary Envelope 27 02 01 31 06 30 Bahirdar town by Bahirdar ion cities town Water Supply Project ET-MOWIE-143697-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,002,000.00 0.00 Implementat Adama Town By Adama improvement in secondary Envelope 28 03 02 01 07 31 ion Town Waste Water cities Management Project ET-MOWIE-143699-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,192,000.00 0.00 Implementat Diredewa Town by Diredewa improvement in secondary Envelope 28 03 02 01 07 31 ion Town Water Supply and cities Sewerage Enterprise ET-MOWIE-143701-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 834,000.00 0.00 Implementat Mekelle Town by Mekelle improvement in secondary Envelope 28 03 02 01 07 31 ion Town Water Supply and cities Sewerage Enterprise ET-MOWIE-143704-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,436,000.00 0.00 Implementat Hawasa Town by Hawasa improvement in secondary Envelope 28 03 02 01 07 31 ion Town Water supply and cities sewerage service ET-MOWIE-143535-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Dessie IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Water Supply and ion cities Sewerage Authority ET-MOWIE-143530-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Deghabur water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat town by Deghabur Water improvement in secondary Envelope 20 25 25 24 28 26 ion Supply and Sewerage cities Enterprise ET-MOWIE-143532-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- communal toilet for Sodo IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 28 03 02 01 07 03 town by Sodo Water Supply ion cities and Sewerage Authority ET-MOWIE-142793-CW-RFB / Construction of FSM (fecal Component 2: Sanitation and sludge management) for water supply services Open - Single Stage - One 2019-12- 2019-12- 2020-02- 2020-03- 2020-04- 2021-11- IDA / 60070 Post Request for Bids 8,610,620.78 0.00 Canceled Bahirdar and Hawasa Towns improvement in secondary International Envelope 25 30 10 11 15 06 by water development cities commission ET-MOWIE-143521-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Semera water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat towns by Semera Water improvement in secondary Envelope 20 25 25 24 28 26 ion Supply and Sewerage cities Authority ET-MOWIE-143537-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Debrebirhan town by improvement in secondary Envelope 28 03 02 01 07 03 ion Debrebirhan Water Supply and cities Sewerage Authority ET-MOWIE-143510-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Asella IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 Town by Asella Water Supply ion cities and Sewerage Enterprise ET-MOWIE-143522-CW-RFB Component 2: Sanitation and / Construction of public and water supply services Single Stage - One 2019-11- 2020-02- 2019-11- 2019-12- 2020-04- 2020-01- 2020-05- 2020-02- 2020-06- 2020-08- communal toilet for Adigrat IDA / 60070 Post Request for Bids Open - National 2,000,000.00 490,071.10 Signed improvement in secondary Envelope 20 13 25 25 28 24 12 28 30 26 towns by Adigrat Water cities Supply and Sewerage service ET-MOWIE-143528-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Jigjiga IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Jigjiga Water Supply ion cities and Sewerage Enterprise ET-MOWIE-143501-CW-RFB Component 2: Sanitation and / construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- communal toilet for Bishoftu IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 28 03 14 13 19 15 town by Bishoftu Water ion cities Supply and Sewerage Authority ET-MOWIE-143272-CW-RFB / construction of public and Component 2: Sanitation and Pending communal toilet for Nekemte water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Town By Nekemte Water improvement in secondary Envelope 20 25 25 24 28 26 ion supply and Sewerage cities Enterprise . ET-MOWIE-143519-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Gambella water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat towns by Gambella Water improvement in secondary Envelope 28 03 02 01 07 03 ion Supply and Sewerage cities Authority ET-MOWIE-143478-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Jima town IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 by Jima Water Supply and ion cities Sewerage Authority ET-MOWIE-143524-CW-RFB Component 2: Sanitation and / Construction of public and Under water supply services Single Stage - One 2019-11- 2020-05- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Harar IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 20 25 25 24 28 26 town by Harar Water Supply ion cities and Sewerage Authority Page 1 ET-MOWIE-143531-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Arbaminch town by improvement in secondary Envelope 20 25 25 24 28 26 ion Arbaminch Water Supply and cities Sewerage Authority ET-MOWIE-143536-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Gonder IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Gonder Water Supply ion cities and Sewerage Authority ET-MOWIE-143503-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Shashamene town by improvement in secondary Envelope 20 25 25 24 28 26 ion Shashamene Water Supply cities and Sewerage Enterprise ET-MOWIE-139087-CW-RFB / Design, Construction and Operation of Five Cities Faecal Component 2: Sanitation and Sludge Treatment Plant (FSTP) Pending water supply services Open - Single Stage - One 21,643,000.0 2020-03- 2020-04- 2020-06- 2020-07- 2020-08- 2020-10- under two lots ( Lot I Adama, IDA / 60070 Prior Request for Bids 0.00 Implementat improvement in secondary International Envelope 0 13 17 01 02 24 17 Dire Dewa and Mekelle and ion cities Lot II Bahir Dar and Hawasa). Implementing Agency: Water Development Commission. ET-MOWIE-172250-CW-RFQ / construction of civil work, Component 2: Sanitation and supply and installation of Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- pipes and fittings for IDA / 60070 Post Limited 73,970.00 0.00 Implementat improvement in secondary Quotations Envelope 25 20 18 Shashamene town WSSE low ion cities income are by Shashamene town WSSE ET-MOWIE-172255-CW-RFQ / Civil work and supply and Component 2: Sanitation and Pending installation of water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- IDA / 60070 Post Limited 90,640.00 0.00 Implementat electromagnetical equipment improvement in secondary Quotations Envelope 25 20 18 ion for Nekemte town low income cities are by Nekemte town WSSE ET-MOWIE-172258-CW-RFQ Component 2: Sanitation and / Expansion of Water Supply Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- system for Adigrat town low IDA / 60070 Post Limited 75,260.00 0.00 Implementat improvement in secondary Quotations Envelope 25 20 18 income area by Adigrat town ion cities WSSE ET-MOWIE-172259-CW-RFQ / Earth Work, supply and Component 2: Sanitation and installation of pipes and water supply services Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-04- 2020-10- IDA / 60080 Post Limited 75,800.00 29,363.01 Completed fitting for Jigjiga town low improvement in secondary Quotations Envelope 25 18 20 30 18 income are by Jigijiga town cities WSSE ET-MOWIE-172260-CW-RFQ / Earth work and supply and Component 2: Sanitation and installation of pipes and water supply services Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-04- 2020-09- fitting for Degahabur town IDA / 60070 Post Limited 75,800.00 16,028.61 Signed improvement in secondary Quotations Envelope 25 09 20 27 18 low income area water supply cities project by Deghabur town WSSE ET-MOWIE-172944-CW-RFP / Design, Construction and Operation of Five Cities Faecal Component 2: Sanitation and Sludge Treatment Plant (FSTP) Under water supply services Request for Open - Single Stage - Two 21,643,000.0 2020-06- 2020-08- 2020-08- 2020-08- 2020-06- 2020-09- 2020-10- 2021-01- 2021-02- 2022-08- under two lots ( Lot I Adama, IDA / 60070 Prior 0.00 Implementat improvement in secondary Proposals International Envelope 0 05 21 21 21 10 08 30 12 16 10 Dire Dewa and Mekelle and ion cities Lot II Bahir Dar and Hawasa). Implementing Agency: Water Development Commission. ET-MOWIE-208763-CW-RFB / Procurement of construction and rehabilitation 20 public Component 2: Sanitation and Pending and communal latrines (10 water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60070 Post Request for Bids Open - National 488,000.00 0.00 Implementat new construction and 10 improvement in secondary Envelope 25 30 29 13 20 16 ion existing latrines cities rehabilitation) for Bahir Dar Town by Bahir Dar Town WSSA ET-MOWIE-208771-CW-RFB / Construction of 22 public Component 2: Sanitation and and communal latrines for Pending water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-08- Dire Dewa town Under two IDA / 60070 Post Request for Bids Open - National 816,000.00 0.00 Implementat improvement in secondary Envelope 15 20 19 03 03 30 lots (lot I 11 public and lot II ion cities 11 communal) by Dire Dewa WSSE ET-MOWIE-208775-CW-RFB / Construction of civil works Component 2: Sanitation and Pending for completing the sludge water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60070 Post Request for Bids Open - National 369,000.00 0.00 Implementat drying bed for fecal sludge improvement in secondary Envelope 22 27 26 10 17 13 ion management for Arbaminch cities town by Arbaminch town WSS GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43004-GO-DIR / Component 2: Sanitation and Supply of pipes and fittings Under water supply services 2018-01- 2018-01- 2018-02- 2018-05- for the remaining work of Dire IDA / 60070 Prior Direct Selection Direct 1,897,466.00 0.00 Implementati improvement in secondary 12 17 24 25 Dewa City Water Supply and on cities Sanitation Project ET-MOWIE-43329-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Gambella City Water Supply and Sewerage Service ET-MOWIE-43286-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-09- 2018-05- 2020-03- 2018-06- 2020-04- IDA / 60070 management & institutional Post Limited 10,000.00 5,098.59 Completed copy machines and lap top Quotations Envelope 22 10 03 21 02 10 strengthening computers)for Deghabur Town Water Supply and Sewerage Service ET-MOWIE-43289-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project Under computers, scanners, photo Request for Single Stage - One 2018-03- 2020-09- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 22 17 03 02 strengthening on computers) for Arbaminch Town Water Supply and Sewerage Service ET-MOWIE-43291-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 22 03 02 strengthening on computers) for Harar Town Water Supply and Sewerage Service ET-MOWIE-43294-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-11- 2018-05- 2020-06- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 6,182.79 Signed copy machines and lap top Quotations Envelope 29 25 10 23 09 strengthening computers) for Bishoftu Town Water Supply and Sewerage Service Page 2 ET-MOWIE-43297-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Shashemane City Water Supply and Sewerage Service ET-MOWIE-43299-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2017-09- 2018-05- 2020-04- 2018-06- 2020-04- IDA / 60070 management & institutional Post Limited 10,000.00 11,105.57 Completed copy machines and lap top Quotations Envelope 29 11 17 02 16 02 strengthening computers) for Jigjiga City Water Supply and Sewerage Service ET-MOWIE-43300-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Hawassa City Water Supply and Sewerage Service ET-MOWIE-43035-GO-RFQ / Procurement of IT equipment Component 3: Project Pending (printers, desk top computers, Request for Single Stage - One 2018-04- 2018-06- 2018-07- IDA / 60070 management & institutional Post Limited 50,000.00 0.00 Implementati scanners, photo copy Quotations Envelope 14 09 09 strengthening on machines and lap top computers) for Ministry PIU ET-MOWIE-43317-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Assosa City Water Supply and Sewerage Service ET-MOWIE-43319-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Asella City Water Supply and Sewerage Service ET-MOWIE-43322-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Sodo City Water Supply and Sewerage Service ET-MOWIE-43324-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-12- 2018-05- 2019-02- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 3,436.18 Signed copy machines and lap top Quotations Envelope 29 27 10 07 09 strengthening computers) for Debre Berhan City Water Supply and Sewerage Service ET-MOWIE-43326-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Dessie City Water Supply and Sewerage Service ET-MOWIE-43328-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Gonder City Water Supply and Sewerage Service ET-MOWIE-43331-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-09- 2018-05- 2018-09- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 3,362.55 Signed copy machines and lap top Quotations Envelope 29 06 10 29 09 strengthening computers) for Nekmte City Water Supply and Sewerage Service ET-MOWIE-43333-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-09- 2018-05- 2018-11- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 1,386.08 Signed copy machines and lap top Quotations Envelope 29 19 10 03 09 strengthening computers) for Jimma City Water Supply and Sewerage Service ET-MOWIE-43303-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-09- 2018-05- 2019-10- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 8,151.84 Signed copy machines and lap top Quotations Envelope 29 26 10 19 09 strengthening computers) for Adama City Water Supply and Sewerage Service ET-MOWIE-43304-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Mekelle City Water Supply and Sewerage Service ET-MOWIE-43307-GO-RFQ / Procurement of office equipment(printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Bahir Dar City Water Supply and Sewerage Service ET-MOWIE-43310-GO-RFQ / Procurement of office equipment for Dire Dawa City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service(Printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-43311-GO-RFQ / Procurement of office equipment for Semera City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service(Printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-43313-GO-RFQ / Procurement of office equipment for Adegrat City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service (printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) Page 3 ET-MOWIE-50407-GO-DIR / Component 2: Sanitation and Procurement of Bulk Flow water supply services 2018-02- 2018-04- 2018-03- 2018-04- 2018-07- meter for Mekelle Town Water IDA / 60070 Prior Direct Selection Direct 433,013.00 0.00 Canceled improvement in secondary 28 05 05 06 05 Supply and Sewerage Service cities by Mekelle town WSSS Component 2: Sanitation and ET-MOWIE-55837-GO-RFB / Pending water supply services Single Stage - One 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- Procurement of Automatic IDA / 60070 Post Request for Bids Open - National 250,000.00 0.00 Implementati improvement in secondary Envelope 20 25 25 24 28 27 Water Meter Test Bench on cities ET-MOWIE-75633-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending Request for Single Stage - One 2018-09- 2018-11- 2018-12- laptop computers for Amhara IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Quotations Envelope 15 10 10 Region Water,Irrigation and strengthening on Energy Development Bureau by Amhara Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75634-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Oromia Quotations Envelope 15 10 10 strengthening on Region Water,Mineral and Energy Bureau by Oromia Region Water,Mineral and Energy Bureau. ET-MOWIE-75635-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending Request for Single Stage - One 2018-09- 2018-11- 2018-12- laptop computers for SNNPR IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Quotations Envelope 15 10 10 Region Water,Irrigation and strengthening on Energy Development Bureau by SNNPR Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75636-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Afar Quotations Envelope 15 10 10 strengthening on Region Water Resource Development Bureau by Afar Region Water Resource Development Bureau ET-MOWIE-75637-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Somali Quotations Envelope 15 10 10 strengthening on Region Water Resource Development Bureau by Somali Region Water Resource Development Bureau ET-MOWIE-75641-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending laptop computers for Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Gambella Region Quotations Envelope 15 10 10 strengthening on Water,Irrigation and Energy Development Bureau by Gambella Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75643-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending laptop computers for Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Benshangul Gumuz Region Quotations Envelope 15 10 10 strengthening on Water,Irrigation and Energy Development Bureau by Benshangul Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75646-GO-RFQ / Procurement of Office Equipment (printers, desktop Component 3: Project Pending computers, scanners, Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati photocopy machines and Quotations Envelope 15 10 10 strengthening on laptop computers) for Tigray Region Water Bureau by Tigray Region Water Bureau ET-MOWIE-84615-GO-RFB / Procurement of 44 Double Component 3: Project Open - Single Stage - One 2018-11- 2019-02- 2018-11- 2019-02- 2019-01- 2019-04- 2019-01- 2019-07- 2019-03- 2019-09- 2019-09- 2020-06- Cup vehicles for 22 Secondary IDA / 60080 management & institutional Prior Request for Bids 1,800,000.00 1,412,937.01 Completed International Envelope 15 02 20 27 01 15 31 10 07 05 03 29 Cities, Regional Water Bureaus strengthening PMU, and Federal PMU ET-MOWIE-98176-GO-RFB / Supply and Installation Component 2: Sanitation and Equipment for Water Quality Pending water supply services Open - Single Stage - One 2019-03- 2019-03- 2019-04- 2019-05- 2019-07- 2019-11- Laboratory and Training IDA / 60070 Post Request for Bids 1,000,000.00 0.00 Implementati improvement in secondary International Envelope 14 19 30 30 04 01 Center for Mekelle Town on cities Water Supply Project by Mekelle Town Water Supply Office ET-MOWIE-143211-GO-RFB / Procurement of 25 (twenty five ) 10m3 and 8m3 size Component 2: Sanitation and vacuum track for 5 towns( water supply services Open - Single Stage - One 2019-11- 2020-08- 2019-11- 2020-09- 2020-01- 2020-11- 2020-02- 2020-03- 2020-09- IDA / 60070 Prior Request for Bids 5,500,000.00 0.00 Under Review Adama,Mekele,Diredewa, improvement in secondary International Envelope 29 19 30 01 14 22 13 19 15 Bahirdar ,and Hawasa) of cities UWSSP-2 By Water Development Commission . ET-MOWIE-156913-GO-RFB / procurement of 44 (forty- Component 2: Sanitation and four) Motorcycles for 22 Under water supply services Single Stage - One 2020-02- 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- Towns of Urban Water Supply IDA / 60070 Post Request for Bids Open - National 180,000.00 0.00 Implementati improvement in secondary Envelope 12 13 12 12 16 13 and Sanitation project II on cities (UWSSP-2) by Water Development Commission ET-MOWIE-166460-GO-DIR / Procurement of IT Equipment (E-video (ten in number) Modem with Component 3: Project Pending subscription 4GB and Fixed 2020-03- 2020-04- 2020-05- 2020-06- IDA / 60070 management & institutional Post Direct Selection Direct 3,600.00 0.00 Implementati Wireless Broadband (WIFI) (3) 30 04 09 18 strengthening on three apparatuses for water Development Commission offices and Staffs will be implemented by WDC ET-MOWIE-166453-GO-RFQ / Procurement of Core i7 7 Component 3: Project Pending (seven) Laptops for Water Request for Single Stage - One 2020-04- 2020-05- 2020-07- IDA / 60070 management & institutional Post Limited 10,937.50 0.00 Implementati Development commission Quotations Envelope 04 30 29 strengthening on Staffs which will be implemented by WDC. ET-MOWIE-168265-GO-RFB / procurement of pipes and Component 2: Sanitation and fittings, water meters and leak Under water supply services Open - Single Stage - One 2020-04- 2020-01- 2020-05- 2020-06- 2020-07- 2020-08- 2020-12- detection equipment for IDA / 60070 Post Request for Bids 907,000.00 0.00 Implementati improvement in secondary International Envelope 30 29 05 04 04 08 06 Gonder town Water Supply on cities and Sewerage service enterprise by Gonder town WSSE Page 4 ET-MOWIE-172211-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- 2020-07- 2020-08- fittings and water meters for IDA / 60070 Post Limited 75,800.00 60,209.31 Signed improvement in secondary Quotations Envelope 20 06 15 22 14 Arbaminch Town WSSE by cities Arbaminch town WSSE ET-MOWIE-172215-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-06- 2020-07- 2020-07- 2020-08- fittings and water meters for IDA / 60070 Post Limited 75,700.00 61,772.81 Signed improvement in secondary Quotations Envelope 20 29 15 03 14 Wolaita Sodo Town WSSE by cities Wolaita town WSSE ET-MOWIE-172221-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings Hawasa Town WSSE IDA / 60070 Post Limited 75,800.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 by Hawasa town WSSE for low on cities income area ET-MOWIE-172233-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 75,800.00 0.00 Implementati for Debre Brerhan Town WSSE improvement in secondary Quotations Envelope 20 15 14 on by DebreBerhan town WSSE cities for low income area ET-MOWIE-172236-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings for Dessie Town WSSE IDA / 60070 Post Limited 75,700.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 by Dessie town WSSE for low on cities income area ET-MOWIE-172241-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-01- 2020-07- 2020-03- 2020-08- fittings for Gonder Town WSSE IDA / 60070 Post Limited 75,800.00 39,738.87 Signed improvement in secondary Quotations Envelope 23 29 18 17 17 by Gonder town WSSE for low cities income area ET-MOWIE-172244-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings for Bahir Dar Town IDA / 60070 Post Limited 75,800.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 low income area WSSE by on cities Bahir Dar town WSSE ET-MOWIE-172245-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 75,690.00 0.00 Implementati for Bishftu Town WSSE by improvement in secondary Quotations Envelope 25 20 19 on Bishftu town WSSE for low cities income area ET-MOWIE-172248-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and Water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 74,980.00 0.00 Implementati for Jimma Town WSSE by improvement in secondary Quotations Envelope 25 20 19 on Jimma town WSSE for low cities income area ET-MOWIE-172256-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings, leak detection and water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati water quality test equipment improvement in secondary Quotations Envelope 25 20 18 on for Assela town low income cities area by Assela town WSSE ET-MOWIE-172257-GO-RFQ / Supply and installation of Component 2: Sanitation and Pending pipes and fittings for Mekelle water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- IDA / 60070 Post Limited 75,800.00 0.00 Implementati town low income area water improvement in secondary Quotations Envelope 20 15 13 on supply project by Mekelle cities town WSSP ET-MOWIE-172262-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings for Gambella town water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati town low income area water improvement in secondary Quotations Envelope 25 20 18 on supply project by Gambella cities town WSSP ET-MOWIE-172263-GO-RFQ Component 2: Sanitation and / Procurement of pipe fittings Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- for Asosa town low income IDA / 60070 Post Limited 5,000.00 0.00 Implementati improvement in secondary Quotations Envelope 25 20 19 area water supply project by on cities Asosa WSSE ET-MOWIE-172265-GO-RFQ Component 2: Sanitation and / procurement of pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- fittings for Harar town low IDA / 60070 Post Limited 69,500.00 0.00 Implementati improvement in secondary Quotations Envelope 25 20 18 income area water supply on cities project by Harar town WSSE ET-MOWIE-172275-GO-RFQ Component 2: Sanitation and / supply of pipes and fittings Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- for Semera Logia town low IDA / 60070 Post Limited 72,500.00 0.00 Implementati improvement in secondary Quotations Envelope 31 26 24 income area water supply on cities project by Semera Logia WSSE ET-MOWIE-172933-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings for Dire Dewa town water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati low income area water supply improvement in secondary Quotations Envelope 30 25 23 on project by Dire Dewa Town cities WSSE ET-MOWIE-168264-GO-RFB / Procurement of Water meters, Bulk flow meters, Component 2: Sanitation and Pending pipes and fittings and leak water supply services Open - Single Stage - One 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2021-01- IDA / 60070 Post Request for Bids 1,565,000.00 0.00 Implementati detection Equipments for Jima improvement in secondary International Envelope 28 02 02 01 05 03 on Town Water Supply and cities Sewerage Enterprise by Jima town WSSE ET-MOWIE-174562-GO-RFQ / Procurement of Aluminium sulfate for covid-19 Component 2: Sanitation and intervention in Gmbella water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 60070 Post Limited 46,154.00 0.00 Canceled towns health stations, improvement in secondary Quotations Envelope 31 05 19 hospitals, isolation centers cities and areas with acute waster supply shortage by WDC ET-MOWIE-174573-GO-RFQ Component 2: Sanitation and / Procurement of filter media water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- Sand for Gambella town Water IDA / 60070 Post Limited 46,154.00 0.00 Canceled improvement in secondary Quotations Envelope 31 05 19 Treatment plant by Gambella cities Town Water Utility ET-MOWIE-175708-GO-RFQ / Procurement of Pipes and Component 2: Sanitation and Pending fittings for Adama town low water supply services Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 60070 Post Limited 76,900.00 0.00 Implementati income area water supply improvement in secondary Quotations Envelope 10 15 14 on project by Adama town Water cities Utility ET-MOWIE-43018-GO-RFB / Procurement of 44 vehicles(double Cabins) for secondary city utilities, Component 3: Project 2018-06- 2018-06- 2018-07- 2018-11- Regional Water Bureaus and 2 IDA / 60070 management & institutional Prior Direct Selection Direct 1,800,000.00 0.00 Canceled 20 25 30 27 Vehicles( double Cabins) for strengthening Ministry PIU by the Ministry of Water Irrigation and Electricity through UNOPS ET-MOWIE-181638-GO-RFB / Procurement of Pipes and Fittings for covid-19 Component 2: Sanitation and Under intervention in 13 towns water supply services Open - Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-08- 2020-09- 2020-12- IDA / 60070 Post Request for Bids 573,766.00 0.00 Implementati health stations, hospitals, improvement in secondary International Envelope 06 04 11 08 01 15 05 04 on isolation centers and areas cities with acute waster supply shortage by WDC Page 5 ET-MOWIE-174564-GO-RFQ / Procurement of Water Component 2: Sanitation and treatment Chemicals and water supply services Request for Single Stage - One 2020-07- 2020-08- 2020-08- Reagents for covid-19 IDA / 60070 Post Limited 110,769.00 0.00 Canceled improvement in secondary Quotations Envelope 11 15 29 intervention in Bonga town cities to areas with acute waster supply shortage by WDC ET-MOWIE-181653-GO-RFQ Component 2: Sanitation and Pending / Procurement of pipe fittings water supply services Request for Single Stage - One 2020-07- 2020-08- 2020-09- IDA / 60070 Post Limited 2,700.00 0.00 Implementati for Harar town water supply improvement in secondary Quotations Envelope 11 29 12 on project by Harar town cities ET-MOWIE-181625-GO-RFB / Procurement of Electromechanical Equipment (59 submersible water pumps Component 2: Sanitation and (lot I) ,11 surface pumps (lot Under water supply services Open - Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-10- 2020-08- 2020-09- 2020-12- II) ,2 Surge Vessels (Lot III) IDA / 60070 Post Request for Bids 4,139,530.00 0.00 Implementati improvement in secondary International Envelope 08 04 13 08 03 21 17 07 06 and 29 Generators (lot IV) for on cities 25 towns covid-19 intervention in acute water supply shortage areas by WDC. ET-MOWIE-183159-GO-DIR Component 2: Sanitation and / Procurement of filter media Pending water supply services 2020-07- 2020-07- 2020-08- 2020-09- Sand for Gambella town Water IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 Implementati improvement in secondary 15 20 10 09 Treatment plant by Gambella on cities Town Water Utility ET-MOWIE-185679-GO-RFQ / Procurement of Office Equipment (#12 laptop Component 3: Project Pending computers, #1 Led Projector, Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 60070 management & institutional Post Limited 50,000.00 0.00 Implementati #2 Heavy duty color printers, Quotations Envelope 10 05 20 strengthening on #1 scanner and #1 heavy duty photo copy machine) for WDC PIU by WDC ET-MOWIE-208762-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fitting for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system to low income improvement in secondary Envelope 21 26 25 09 02 01 on area of Mekelle town by cities Mekelle town WSS ET-MOWIE-208765-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fitting for expansion of water water supply services Request for Single Stage - One 2021-01- 2021-03- 2021-03- IDA / 60070 Post Limited 65,000.00 0.00 Implementati supply system for unserved improvement in secondary Quotations Envelope 04 01 31 on low income area by Bahir Dar cities WSS ET-MOWIE-208767-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 21 26 25 09 02 01 on low income are for Adama cities town by Adama town WSSE ET-MOWIE-208769-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 22 27 26 10 03 02 on low income area of Hawasa cities town by Hawasa town WSSE ET-MOWIE-208770-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 22 27 26 10 03 02 on low income area of Dire Dewa cities town by Dire Dewa town WSSE ET-MOWIE-208774-GO-RFQ / procurement of pumps and Component 2: Sanitation and Pending generators for Debre Birhan water supply services Request for Single Stage - One 2021-01- 2021-02- 2021-03- IDA / 60070 Post Limited 79,000.00 0.00 Implementati town Water Supply Project by improvement in secondary Quotations Envelope 10 21 23 on Debre Birhan town Dar Town cities WSSE ET-MOWIE-220715-GO-RFB / Procurement of operational service improvement equipment's under two lots ( Component 2: Sanitation and Pending lot I Water Meters, lot II leak water supply services Open - Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-11- IDA / 60070 Prior Request for Bids 8,900,000.00 0.00 Implementati detection equipment, welding improvement in secondary International Envelope 10 15 26 26 30 27 on machines, Bulk flow meters, cities and test bench) for improvement of 22 town Water supply projects by WDC ET-MOWIE-220716-GO-RFB / procurement of pipes and Component 2: Sanitation and Pending fittings for 22 towns water water supply services Open - Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-11- IDA / 60070 Prior Request for Bids 2,800,000.00 0.00 Implementati supply projects operational improvement in secondary International Envelope 10 15 26 26 30 27 on efficiency improvement by cities WDC ET-MOWIE-221971-GO-DIR / Procurement of Water Component 2: Sanitation and treatment Chemicals and Pending water supply services 2021-03- 2021-03- 2021-04- 2021-06- Reagents for covid-19 IDA / 60070 Post Direct Selection Direct 110,769.00 0.00 Implementati improvement in secondary 01 06 10 09 intervention in Bonga town on cities to areas with acute waster supply shortage by WDC ET-MOWIE-221972-GO-DIR / Procurement of Aluminium sulfate for covid-19 Component 2: Sanitation and Pending intervention in Gmbella towns water supply services 2021-03- 2021-03- 2021-04- 2021-06- IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 Implementati health stations, hospitals, improvement in secondary 01 06 10 09 on isolation centers and areas cities with acute waster supply shortage by WDC ET-MOWIE-221973-GO-UN / Procurement of Electromechanical Equipment Component 2: Sanitation and Pending (59 submersible water pumps water supply services UN Agencies 2021-03- 2021-03- 2021-04- 2021-07- IDA / 60070 Post Direct 1,500,000.00 0.00 Implementati (lot I) and 11 surface pumps improvement in secondary (Direct) 02 07 11 10 on (lot II) ) for 25 towns covid- cities 19 intervention in acute water supply shortage NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-174570-NC-RFQ Component 2: Sanitation and / Procurement of maintenance Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- service of Generators and IDA / 60070 Post Limited 30,769.00 0.00 Implementati improvement in secondary Quotations Envelope 31 05 19 transformer for shire town by on cities shire town Water Utility CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43244-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-07- 2018-05- 2018-07- 2018-03- 2018-07- 2018-12- 2018-09- 2018-01- 2018-11- 2019-04- 2018-12- 2019-07- 2019-09- Feasibility Study and Detail IDA / 60070 Post Open - National 250,000.00 214,456.00 Signed 2018-04-20 improvement in secondary Based Selection 17 11 01 03 29 31 27 15 08 27 20 04 16 Design of Waste Water cities Management System for Harari town by Harari Town water supply and sewerage service Page 6 ET-MOWIE-50559-CS-QCBS / Consultancy Service for Establishment of Urban Water Component 2: Sanitation and Supply and Waste Water water supply services Quality And Cost- Under 2018-07- 2018-09- 2018-09- 2018-10- 2018-12- 2019-01- 2020-01- IDA / 60070 Post Open - National 200,000.00 0.00 2018-06-20 Management Service improvement in secondary Based Selection Implementation 20 02 30 30 04 08 08 Regulation in Ethiopia by cities Ministry of Water Irrigation and Electricity ET-MOWIE-43193-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-08- 2019-06- 2018-09- 2019-09- 2018-10- 2020-02- 2018-11- 2020-09- 2018-12- 2020-10- 2019-09- IDA / 60070 Prior 600,000.00 995,043.88 Signed 2018-06-20 Design of Waste Water improvement in secondary Based Selection International 10 11 03 24 27 21 02 21 12 25 03 30 01 26 Management System for cities Jimma and Nekemte Towns by Oromia Water Mineral and Energy Bureau ET-MOWIE-43212-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail improvement in secondary Based Selection 11 01 29 27 08 20 16 Design for Asella Town WSSS cities by Asella Town water supply and sewerage service ET-MOWIE-43209-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- Under 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 60070 Post Open - National 500,000.00 0.00 2018-03-20 Feasibility Study and Detail improvement in secondary Based Selection Implementation 10 31 28 27 08 19 16 Design for Sodo and cities Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-43208-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-03-20 Feasibility Study and Detail improvement in secondary Based Selection 10 31 28 27 01 12 09 Design for Sodo Town WSSS cities by Sodo Town water supply and sewerage service ET-MOWIE-43214-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-08- 2018-05- 2018-07- 2018-08- 2018-07- 2019-03- 2018-09- 2019-06- 2018-11- 2019-09- 2018-12- 2019-09- 2019-09- Feasibility Study and Detail IDA / 60070 Post Open - National 250,000.00 217,285.63 Signed 2018-04-20 improvement in secondary Based Selection 01 11 01 01 29 09 27 03 08 18 20 27 16 Design of Waste Water cities Management System for Adegrat town by Tigray Region Water Bureau ET-MOWIE-43206-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Dessie town by Dessie Town water supply and sewerage service ET-MOWIE-43200-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Gambella town by Gambella Town water supply and sewerage service ET-MOWIE-43198-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-06- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 24 22 20 01 13 09 Management System for cities Nekemet town by Nekemet Town water supply and sewerage service ET-MOWIE-43237-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Jigjiga town by Jigijiga Town water supply and sewerage service ET-MOWIE-43239-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Shashemene town by Shashemene Town water supply and sewerage service ET-MOWIE-43216-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Semera town by Semera Town water supply and sewerage service ET-MOWIE-43241-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Bishoftu town by Bishoftu Town water supply and sewerage service ET-MOWIE-43059-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Deghabur town by Deghabur Town water supply and sewerage service ET-MOWIE-43248-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Arbaminch town by Arbaminch Town water supply and sewerage service ET-MOWIE-43203-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Gonder town by Gonder Town water supply and sewerage service Page 7 ET-MOWIE-65731-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-09- 2018-08- 2019-01- 2018-09- 2019-03- 2018-10- 2019-08- 2018-11- 2019-12- 2018-12- 2019-12- 2019-09- IDA / 60080 Prior 900,000.00 1,246,690.99 Signed 2018-06-20 Design of Waste Water improvement in secondary Based Selection International 06 11 04 24 14 21 05 21 30 25 08 30 18 26 Management System for cities Gambella, Semera and Asosa Towns by Ministry of Water Irrigation and Electricity ET-MOWIE-65735-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - Under 2018-08- 2018-07- 2018-10- 2018-09- 2019-08- 2018-09- 2019-11- 2018-10- 2020-02- 2018-12- 2020-09- 2019-01- 2019-10- Design of Waste Water IDA / 60080 Prior 900,000.00 0.00 2018-06-28 improvement in secondary Based Selection International Implementation 10 19 05 01 14 29 12 29 26 03 22 07 04 Management System for cities Asella, Shashemene and Bishoftu towns by Oromia Water, Mineral and Energy Bureau ET-MOWIE-65737-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-09- 2019-06- 2018-09- 2019-09- 2018-10- 2019-12- 2018-12- 2020-06- 2019-01- 2020-08- 2019-10- IDA / 60080 Prior 900,000.00 1,163,667.22 Signed 2018-06-28 Design of Waste Water improvement in secondary Based Selection International 10 19 14 01 27 29 17 29 08 03 02 07 21 04 Management System for cities Gonder, Dessie and Debreberhan towns by Amehara Water Bureau ET-MOWIE-65751-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- Open - Under 2018-08- 2018-07- 2018-10- 2018-08- 2020-02- 2018-09- 2020-05- 2018-10- 2020-12- 2018-11- 2021-02- 2018-12- 2019-09- Feasibility Study and Detail IDA / 60080 Prior 600,000.00 0.00 2018-06-20 improvement in secondary Based Selection International Implementation 10 11 17 24 16 21 21 21 16 25 22 30 26 Design of Waste Water cities Management System for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-65753-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-08- 2019-07- 2018-09- 2019-09- 2018-10- 2019-10- 2018-12- 2020-05- 2019-01- 2020-06- 2019-10- IDA / 60080 Prior 600,000.00 1,279,278.48 Signed 2018-06-26 Design of Waste Water improvement in secondary Based Selection International 06 17 05 30 16 27 05 27 31 01 30 05 30 02 Management System for Jijiga cities and Deghabur Towns by Somali Region Water Resource Development Bureau ET-MOWIE-43213-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail improvement in secondary Based Selection 11 01 29 27 08 20 16 Design for Aossosa Town cities WSSS by Assosa Town water supply and sewerage service ET-MOWIE-55840-CS-QCBS / Procurement of re- Component 2: Sanitation and innovation of Enterprise level water supply services Quality And Cost- Pending 2018-07- 2018-08- 2018-09- 2018-10- 2018-11- 2018-12- 2019-12- IDA / 60070 Post Open - National 250,000.00 0.00 2018-06-20 Information Management improvement in secondary Based Selection Implementation 11 24 21 21 25 30 30 System by Mekele Town Water cities Supply and Sewerage Service ET-MOWIE-43218-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for Dire IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 08 19 16 Dewa town by Dire Dawa cities Town water supply and sewerage service ET-MOWIE-43231-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 01 12 09 Adama town by Adama Town cities water supply and sewerage service ET-MOWIE-43234-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 01 12 09 Hawassa town by Hawassa cities Town water supply and sewerage service ET-MOWIE-43227-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 08 19 16 Mekelle town by Mekelle Town cities water supply and sewerage service ET-MOWIE-43222-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-08- City Wide Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-04-20 improvement in secondary Based Selection 11 01 29 28 09 20 17 Bahir Dar town by Bahir Dar cities Town water supply and sewerage service ET-MOWIE-77764-CS-QCBS / consultancy service for Component 2: Sanitation and preparation of business plan water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- for Jima, Nekemte and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 06 Bishoftu Towns Water Supply cities project by Oromia Water, Mineral and Energy Bureau ET-MOWIE-75929-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 of NRW reduction and improvement in secondary Based Selection 18 01 29 28 04 08 06 management interventions for cities Jigjiga and Deghabur towns by Somali Region Water Bureau ET-MOWIE-75924-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-10- of NRW reduction and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 05 management interventions for cities Bahirdar, D/berhan and Dessie towns by Amhara Water Bureau ET-MOWIE-77752-CS-QCBS / Consultancy service for Component 2: Sanitation and preparation of business plan water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- for Mekele and Adegrat towns IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 06 Water supply and Sewerage cities authorities by Tigray Region Water Bureau ET-MOWIE-75935-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-07- IDA / 60070 Post Open - National 50,000.00 0.00 Canceled 2018-10-02 of NRW reduction and improvement in secondary Based Selection 23 06 03 02 09 13 12 management interventions for cities Harari town by Harari water supply and sewerage service ET-MOWIE-77885-CS-QCBS / Consultancy Service for Component 2: Sanitation and preparation of Business plan water supply services Quality And Cost- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-08- for Adama, Asella and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-10-05 improvement in secondary Based Selection 26 09 06 05 12 16 14 Shashamene towns by Oromia cities Water Mineral and Energy Bureau Page 8 ET-MOWIE-75932-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- Pending 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- IDA / 60070 Post Open - National 130,000.00 0.00 2018-11-15 Reduction strategic plan and improvement in secondary Based Selection Implementation 06 19 16 18 22 27 24 implementation mechanisms cities for Soda, Hawasa and Arbamich towns by SNNP reginal water bureaus ET-MOWIE-75927-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-10- IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 of NRW reduction and improvement in secondary Based Selection 18 01 29 28 04 08 05 management interventions for cities Gambella, Semera and Asosa towns by MoWIE ET-MOWIE-84640-CS-QCBS Component 2: Sanitation and / Consultancy Service for water supply services Quality And Cost- Open - Under 2018-12- 2018-12- 2019-02- 2019-02- 2019-11- 2019-03- 2020-04- 2019-04- 2020-06- 2019-05- 2019-06- 2020-06- Preparation of Urban Water IDA / 60080 Prior 540,000.00 0.00 2018-11-30 improvement in secondary Based Selection International Implementation 05 21 14 03 27 03 03 02 09 07 11 10 Supply Study and Design cities Criteria ET-MOWIE-77886-CS-QCBS Component 2: Sanitation and / Consultancy Service for water supply services Quality And Cost- Under 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-06- 2019-09- preparation of Business plan IDA / 60070 Post Open - National 50,000.00 0.00 2018-11-20 improvement in secondary Based Selection Implementation 04 11 24 21 23 27 01 29 for Dire Dewa town by cities Diredewa town water utility ET-MOWIE-75898-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- Care, FM improvement, IDA / 60070 management & institutional Post Open - National 51,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 23 network management and and strengthening capacity Building for Deghabur and Jigjiga towns by Somali Region Water Resource Development Bureau ET-MOWIE-75900-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Accounting System, Customer Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 51,000.00 0.00 Canceled 2018-11-15 Care, FM improvement, Based Selection 06 19 16 18 22 27 23 strengthening network management and and capacity Building for Adegrat and Mekelle towns by Tigray Region Water Bureau ET-MOWIE-75896-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- Care, FM improvement, IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 23 network management and and strengthening capacity Building for Bahirdar, Gonder, Debrebrihan and Dessie towns by Amahara Water Bureau ET-MOWIE-75897-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Accounting System, Customer Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 Care, FM improvement, Based Selection 06 19 16 18 22 27 23 strengthening network management and and capacity Building for Gambella, Semera, and Asosa towns by MoWIE ET-MOWIE-75892-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Accounting System, Customer Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 Care, FM improvement, Based Selection 06 19 16 18 22 27 23 strengthening network management and and capacity Building for Nekemte and Jimma towns by by Oromia WMEB ET-MOWIE-75903-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Accounting System, Customer Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-14 Care, FM improvement, Based Selection 05 18 15 17 21 26 22 strengthening network management and and capacity Building for Hawassa, Sodo, and Arbaminch towns by SNRPR Water Bureau ET-MOWIE-75888-CS-INDV / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and Capacity Building for Adama, Assela, Bishoftu and Shashamene towns by Oromia WMEB ET-MOWIE-75899-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-08- Accounting System, Customer IDA / 60070 management & institutional Post Open - National 75,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 25 Care, FM improvement, strengthening network management and and capacity Building for Harar town by by Harar WMEB ET-MOWIE-75905-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Component 3: Project Accounting System, Customer Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-08- IDA / 60070 management & institutional Post Open - National 100,000.00 0.00 Canceled 2018-11-15 Care, FM improvement, Based Selection 06 19 16 18 22 27 25 strengthening network management and and capacity Building for Diredewa town WSSS by diredewa town WSSS ET-MOWIE-107046-CS-QCBS / Consultancy Service for Design and Implementation of Component 2: Sanitation and an Integrated Management water supply services Quality And Cost- Open - Under 2019-09- 2019-09- 2019-11- 2019-10- 2020-05- 2019-12- 2020-06- 2020-01- 2020-11- 2020-02- 2020-03- 2021-09- IDA / 60070 Prior 4,067,243.00 0.00 2019-08-20 Information System for Urban improvement in secondary Based Selection International Implementation 16 10 07 24 07 05 26 04 17 08 14 05 Water Utilities in Ethiopia, by cities Water Development Commission ET-MOWIE-139130-CS-QCBS / consultancy service on the construction supervision of Component 2: Sanitation and FSM (fecal sludge water supply services Quality And Cost- Open - 2020-06- 2019-12- 2020-07- 2020-01- 2020-02- 2020-03- 2020-04- 2020-06- 2022-01- IDA / 60070 Prior 1,400,000.00 0.00 Under Review 2019-11-21 management ) for Adama, improvement in secondary Based Selection International 12 12 14 25 24 25 29 03 24 Bahirdar, Hawasa, DireDewa, cities and Mekele Towns by Water Development Comision. ET-MOWIE-143194-CS-QCBS / Selection and Employment of Independent procurement Audit service for multi Component 2: Sanitation and years procurement Audit water supply services Quality And Cost- Under 2020-01- 2020-01- 2020-01- 2020-03- 2020-05- 2020-04- 2020-07- 2020-05- 2020-11- 2020-06- 2020-07- 2022-02- IDA / 60070 Prior Open - National 300,000.00 0.00 2019-12-25 (2009-2013 EFY) for 23 improvement in secondary Based Selection Implementation 01 08 27 08 12 07 14 07 09 11 16 06 towns o f Urban Water and cities Sanitation Project II (UWSSP- 2) by Water Development Commission Page 9 ET-MOWIE-152576-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic Component 2: Sanitation and plan and implement for water supply services Quality And Cost- Open - Under 2020-03- 2020-02- 2020-06- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2022-01- IDA / 60070 Prior 3,105,582.00 0.00 2020-01-23 Adama, Asela, Shashamene, improvement in secondary Based Selection International Implementation 13 13 08 28 25 25 29 03 25 Nekemete, Jima and Bishoftu cities towns Water supply and Sewerage authorities by Oromia Region Water Bureau ET-MOWIE-152577-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-03- 2020-02- 2020-05- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2021-11- plan and implement for Bhir IDA / 60070 Prior 2,552,791.00 0.00 2020-01-23 improvement in secondary Based Selection International Implementation 13 13 28 28 25 25 29 03 26 Dar, Gonder, Dessie and cities Debre-birhan towns Water supply and Sewerage authorities by Amhara Region Water Bureau ET-MOWIE-152580-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2021-02- 2020-02- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2021-09- plan and implement for IDA / 60070 Prior 2,258,370.00 0.00 2020-01-23 improvement in secondary Based Selection International Implementation 26 13 28 25 25 29 03 27 Gambella, Semera and Asosa cities towns Water supply and Sewerage authorities by Water Development Commission ET-MOWIE-77756-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- plan and implementation for IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-15 improvement in secondary Based Selection 04 06 19 16 18 22 27 24 JIjiga and Deghabur towns cities Water supply and Sewerage authorities by Somali Region Water Bureau ET-MOWIE-77754-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- plan and implement for IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-14 improvement in secondary Based Selection 04 05 18 15 17 21 26 23 A/Minch, Sodo and Hawassa cities towns Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-75930-CS-QCBS / Selection and employment of consultant for Consultancy Component 2: Sanitation and service for preparation of water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- business plan and NRW IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-30 improvement in secondary Based Selection 04 21 03 03 02 07 11 09 Reduction strategic plan and cities implementation mechanisms Mekele and Adigrat towns by Tigray regional water bureau ET-MOWIE-77755-CS-QCBS / Consultancy service service for preparation of business plan and NRW Reduction Component 2: Sanitation and strategic plan and water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- implementation m for IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-29 improvement in secondary Based Selection 04 20 02 02 01 06 10 08 Gambella, Semera and Asosa cities towns Water supply and Sewerage authorities by Ministry of Water Irrigation and Electricity ET-MOWIE-107044-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- 2019-09- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-04- Reduction strategic plan and IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2019-04-10 improvement in secondary Based Selection 04 01 14 12 11 15 20 17 implementation mechanisms cities for Adama, Asella, Shashamene, Nekemte, Jimma and Bishoftu towns by Oromia WMEB ET-MOWIE-75921-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-06- 2019-11- IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-22 Reduction strategic plan and improvement in secondary Based Selection 13 26 23 25 29 03 30 implementation mechanisms cities for for Adama, Asella, Shashamene and Bishoftu towns by Oromia WMEB ET-MOWIE-77757-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic Component 2: Sanitation and plan and implementation water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- IDA / 60070 Post Open - National 60,000.00 0.00 Canceled 2018-11-30 mechanisms for Harar town improvement in secondary Based Selection 04 21 03 03 02 07 11 09 Water supply and Sewerage cities authorities by Harar town Water supply and Sewerage authorities ET-MOWIE-75919-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 3: Project Quality And Cost- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- business plan and NRW IDA / 60070 management & institutional Post Open - National 110,000.00 0.00 Canceled 2018-11-30 Based Selection 21 03 03 02 07 11 08 Reduction strategic plan and strengthening implementation mechanisms for Jimma and Nekemte towns by Oromia WMEB ET-MOWIE-77761-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strafor water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- Gonder, Dessie, Debreberhan IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-15 improvement in secondary Based Selection 04 06 19 16 18 22 27 24 and Bahirdar towns Water cities supply and Sewerage authorities by Amhara Region Water Bureau ET-MOWIE-152586-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-07- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- plan and implement for Jigjiga IDA / 60070 Post 1,505,580.00 0.00 2020-02-19 improvement in secondary Based Selection International Implementation 13 11 24 22 21 26 30 30 and Degnabur towns Water cities supply and Sewerage authorities by somali Region Water Bureau ET-MOWIE-152559-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-03- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-10- plan and implement for IDA / 60070 Post 1,700,000.00 0.00 2020-02-20 improvement in secondary Based Selection International Implementation 16 12 25 23 22 27 31 25 A/Minch, Sodo and Hawassa cities towns Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-152583-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-07- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- plan and implement for IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 improvement in secondary Based Selection International Implementation 13 12 25 23 22 27 31 31 Adegrat and Mekelle towns cities Water supply and Sewerage authorities by Tigray Region Water Bureau ET-MOWIE-152591-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-04- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 plan and implement for Harar improvement in secondary Based Selection International Implementation 15 12 25 23 22 27 31 31 town Water supply and cities Sewerage authority by Harar Region Water Bureau Page 10 ET-MOWIE-146021-CS-QBS / Selection and Employment Component 2: Sanitation and Consultant of Environmental & Social water supply services 2020-02- 2020-03- 2020-04- 2020-05- 2020-11- IDA / 60070 Post Qualification Open - National 29,100.00 0.00 Canceled 2020-01-14 Impact Assessment for Arba improvement in secondary 04 19 18 23 19 Selection Minch & Wolaita Sodoby water cities Development commission ET-MOWIE-146020-CS-QBS / Selection and Employment Component 2: Sanitation and of Environmental & Social Consultant water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- Impact Assessment for IDA / 60070 Post Qualification Open - National 60,000.00 0.00 2020-02-28 improvement in secondary Implementation 03 13 02 01 06 03 Gondar, Dessie, Debre Berhan, Selection cities Jigjiga and Degehabur by water Development commission. ET-MOWIE-146016-CS-QBS / Selection and Employment of Environmental & Social Component 2: Sanitation and Consultant Impact Assessment for water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- IDA / 60070 Post Qualification Open - National 91,300.00 0.00 2020-02-28 Jimma, Nekemte, Bishoftu, improvement in secondary Implementation 03 13 02 01 06 03 Selection Shashemene, Assela, W/Sodo cities and Arba Minch by water Development commission ET-MOWIE-146024-CS-QBS / Selection and Employment Component 2: Sanitation and of Environmental & Social Consultant water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- Impact Assessment for Harar, IDA / 60070 Post Qualification Open - National 52,200.00 0.00 2020-02-28 improvement in secondary Implementation 03 13 02 01 06 03 Adigrat, Gambella, Semera- Selection cities Logia and, Assosa by water Development commission ET-MOWIE-205117-CS-QCBS / Consultancy Service for Component 2: Sanitation and Preparing Technical Design water supply services Quality And Cost- Open - 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- 2021-06- 2022-11- IDA / 60080 Prior 1,700,000.00 0.00 Under Review 2020-11-25 Manual, Operation, improvement in secondary Based Selection International 16 29 26 28 02 06 28 Maintenance and Management cities for Urban Sanitation by WDC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-55842-CS-INDV / Selection and Employment of Component 3: Project Individual Pending 2018-07- 2018-08- 2018-09- 2024-08- Procurement Specialist for IDA / 60070 management & institutional Post Consultant Open 54,000.00 0.00 2018-06-18 Implementation 22 12 16 15 Mekelle Town Water Utility by strengthening Selection Mekelle Town Utility ET-MOWIE-63893-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for Adama 2020-06- 2018-07- 2018-07- 2018-07- 2019-07- 2018-08- 2018-07- 2019-08- IDA / 60080 management & institutional Post Consultant Open 5,185.00 3,908.81 Signed 2018-06-14 Town Waste Water 16 13 26 27 27 31 27 26 strengthening Selection Management project by Adama Town Utility office. ET-MOWIE-70084-CS-INDV / Selection and employment of Component 3: Project Individual 2018-12- 2018-09- 2019-03- 2018-09- 2019-03- 2018-10- 2019-03- 2019-10- Technical specialist for IDA / 60070 management & institutional Post Consultant Open 7,500.00 6,474.26 Signed 2018-08-07 02 05 07 15 10 13 10 13 Amhara regional bureau by strengthening Selection Amhara regional bureau ET-MOWIE-70090-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Oromia Region Water Mineral Implementation 05 15 13 13 strengthening Selection and Energy Bureau by Oromia OWMEB ET-MOWIE-70097-CS-INDV / selection and employment of Component 3: Project Individual 2018-12- 2018-09- 2019-02- 2018-09- 2019-03- 2018-10- 2019-03- 2019-10- Technical specialist for IDA / 60070 management & institutional Post Consultant Open 7,500.00 6,470.41 Signed 2018-08-07 03 05 20 12 10 10 10 10 Amhara regional bureau by strengthening Selection Amhara regional bureau ET-MOWIE-70098-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Oromia Region Water Mineral Implementation 05 26 24 24 strengthening Selection and Energy Bureau by Oromia OWMEB ET-MOWIE-70101-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for SNNPR 2019-02- 2018-09- 2020-04- 2018-09- 2019-04- 2018-10- 2019-04- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 5,366.75 Signed 2018-08-07 Region Water Resource 18 05 11 26 15 24 15 24 strengthening Selection Development Bureau by SNNPR Water Resource Bureau ET-MOWIE-70102-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for SNNPR Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Region Water Mineral and Implementation 05 19 24 24 strengthening Selection Energy Bureau by SNNPR Water Resource Bureau ET-MOWIE-70104-CS-INDV / Selection and Employment of Technical specialist for Component 3: Project Individual Ethiopian Somali Region Water Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Resource Development Bureau Implementation 05 26 31 31 strengthening Selection by Ethiopian Somali Region Water Resource Development Bureau ET-MOWIE-70107-CS-INDV / Selection and Employment of Technical specialist for Component 3: Project Individual Pending 2018-09- 2018-09- 2018-10- 2019-10- Benishangulegumuz Region IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Implementation 05 26 31 31 Water Mineral and Energy strengthening Selection Bureau by Benshangulgumuz Region Water Bureau ET-MOWIE-70109-CS-INDV / Selection and Employment of Project Coordinator for Adama Component 3: Project Individual 2018-12- 2018-09- 2018-12- 2018-09- 2018-08- 2018-11- 2018-08- 2019-11- Town Waste Water IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,556.55 Signed 2018-08-08 07 06 28 27 28 01 28 01 Management Project by strengthening Selection Adama Town Water Supply and Sewerage Authority ET-MOWIE-70111-CS-INDV / Selection and employment of financial specialist for Mekele Component 3: Project Individual Pending 2018-09- 2018-09- 2018-10- 2019-10- Town Water supply and IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-08 Implementation 06 13 18 18 sewerage service by mekele strengthening Selection town water supply and sewerage Authority ET-MOWIE-70119-CS-INDV / Selection and Employment of Component 3: Project Individual Project coordinator for 2018-11- 2018-09- 2019-03- 2018-09- 2019-03- 2018-11- 2019-03- 2019-11- IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,364.91 Signed 2018-08-15 Hawasa Town by Hawasa 06 13 18 27 19 01 19 01 strengthening Selection Town Water Supply and Sewerage Service ET-MOWIE-70125-CS-INDV / Selection and employment of financial specialist for Hawasa Component 3: Project Individual Pending 2018-09- 2018-09- 2018-11- 2019-11- Town Water supply and IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 Implementation 13 27 01 01 sewerage service by Hawasa strengthening Selection town water supply and sewerage Authority ET-MOWIE-70129-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Asela 2018-07- 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,509.16 Signed 2018-08-06 town by Asela town Water 15 04 02 18 12 23 12 23 strengthening Selection Supply and Sewerage Authority Page 11 ET-MOWIE-70150-CS-INDV / Selection and Employment of Project Coordinator for Component 3: Project Individual 2019-12- 2018-09- 2019-12- 2018-09- 2020-06- 2018-11- 2020-06- 2019-11- Shashamene town by IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,514.68 Signed 2018-08-15 01 13 20 27 08 01 08 01 Shashamene town Water strengthening Selection Supply and Sewerage Authority ET-MOWIE-70157-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-06- 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 7,801.64 Signed 2018-08-10 Nekemte town by Nekemte 17 08 03 22 03 27 03 27 strengthening Selection town Water Supply and Sewerage Authority ET-MOWIE-70166-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-07- 2018-09- 2018-09- 2018-09- 2018-09- 2018-11- 2018-09- 2019-11- IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,530.78 Signed 2018-08-15 Arbaminch town by 01 13 02 27 11 01 11 01 strengthening Selection Arbaminch town Water Supply and Sewerage Authority ET-MOWIE-70176-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-13 Gambella town by Gambella Implementation 11 25 30 30 strengthening Selection town Water Supply and Sewerage Autrity ET-MOWIE-70184-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Asosa Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-14 town by Asosa town Water Implementation 12 26 31 31 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70191-CS-INDV / Selection and employment of Component 3: Project Individual project coordinator for Under 2018-12- 2018-09- 2019-12- 2018-09- 2020-01- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-07 Adigrat town by Adigrat town Implementation 06 05 02 19 12 24 24 strengthening Selection water supply and sewerage service ET-MOWIE-70193-CS-INDV / Selection and Employment of Component 3: Project Individual Procurement Specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,921.00 0.00 2018-08-13 Asosa town by Asosa town Implementation 11 25 30 30 strengthening Selection Water Supply and Sewerage Authority ET-MOWIE-70194-CS-INDV / Selection and Employment of Component 3: Project Individual financial spcialist for Asosa Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-13 town by Asosa town Water Implementation 11 25 30 30 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70198-CS-INDV / Selection and Employment of Component 3: Project Individual Procurement Specialist for Pending 2018-09- 2018-09- 2018-11- 2019-11- IDA / 60070 management & institutional Post Consultant Open 7,921.00 0.00 2018-08-15 Adigrat town by Adigerat town Implementation 13 27 01 01 strengthening Selection Water Supply and Sewerage Authority ET-MOWIE-70199-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Adigrat Under 2018-09- 2018-09- 2018-11- 2019-11- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 town by Adigerat town Water Implementation 13 27 01 01 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70202-CS-INDV / Selection and Employment of Component 3: Project Individual financial Specialist for Jijiga Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 town by Jijiga town Water Implementation 13 20 18 18 strengthening Selection Supply and Sewerage Authority ET-MOWIE-75716-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for 2019-01- 2018-11- 2019-02- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,713.49 Signed 2018-09-14 Bahirdar town Water Supply 10 02 12 23 12 28 16 28 strengthening Selection and Sewerage Authority by Bahirdar Town ET-MOWIE-75723-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Gonder 2018-05- 2018-11- 2018-05- 2018-11- 2018-05- 2018-12- 2019-05- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,884.75 Signed 2018-09-13 town Water Supply and 01 01 01 22 01 27 01 27 strengthening Selection Sewerage Authority by Gonder Town ET-MOWIE-75730-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Dessie 2018-09- 2018-11- 2019-04- 2018-11- 2019-04- 2018-12- 2019-04- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,716.23 Signed 2018-09-14 town Water Supply and 10 02 25 23 26 28 26 28 strengthening Selection Sewerage Authority by Dessie Town ET-MOWIE-75736-CS-INDV / Selection and Employmentasw2q of Component 3: Project Individual 2018-09- 2018-11- 2019-12- 2018-11- 2019-12- 2018-12- 2019-12- 2019-12- Financial Specialist for IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,575.98 Signed 2018-09-14 12 02 18 23 18 28 18 28 Bishoftu town Water Supply strengthening Selection and Sewerage Authority by Bishoftu Town ET-MOWIE-75738-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Gambella town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Gambella Town ET-MOWIE-75746-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Jima Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Jima Town ET-MOWIE-75749-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Semera Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Semera Town ET-MOWIE-75750-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Deghabur town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Deghabur Town ET-MOWIE-75753-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for Harar Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Harar Town ET-MOWIE-75755-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Diredewa town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Diredewa Town ET-MOWIE-75757-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Sodo 2018-07- 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,716.23 Signed 2018-09-14 town Water Supply and 03 02 17 23 15 28 15 28 strengthening Selection Sewerage Authority by Sodo Town Page 12 ET-MOWIE-75758-CS-INDV / Selection and Employment of Financial Specialist for Component 3: Project Individual 2018-06- 2018-11- 2018-08- 2018-11- 2018-10- 2018-12- 2018-11- 2019-12- Debreberhan town Water IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,735.33 Signed 2018-09-14 01 02 01 23 29 28 29 28 Supply and Sewerage strengthening Selection Authority by Debreberhan Town ET-MOWIE-75810-CS-INDV / Selection and Employment of Component 3: Project Individual 2018-06- 2018-10- 2019-02- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- Project Coordinator for IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,536.05 Signed 2018-09-12 01 31 18 21 16 26 16 26 Bahirdar Town Water Supply strengthening Selection Project by Bahirdar Town ET-MOWIE-75811-CS-INDV / Selection and Employment of Component 3: Project Individual 2018-05- 2018-10- 2018-10- 2018-11- 2018-11- 2018-12- 2018-11- 2019-12- Project Coordinator for IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,698.88 Signed 2018-09-12 01 31 30 21 01 26 01 26 Gonder Town Water Supply strengthening Selection Project by Gonder Town ET-MOWIE-75866-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Dessie Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Dessie Town ET-MOWIE-75871-CS-INDV / Selection and Employment of Project Coordinator for Component 3: Project Individual 2018-06- 2018-12- 2018-10- 2018-12- 2019-11- 2019-01- 2018-11- 2019-07- Debrebirhan Town Water IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,550.54 Signed 2018-10-15 28 03 08 24 25 28 25 27 Supply and Sewerage strengthening Selection Enterprise by Debrabrihan Town ET-MOWIE-75872-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2019-12- 2018-12- 2019-12- 2018-12- 2019-12- 2019-01- 2019-12- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,537.11 Signed 2018-10-15 Bishoftu Town Water Supply 19 03 10 24 18 28 18 28 strengthening Selection and Sewerage Enterprise by Bishoftu Town ET-MOWIE-75873-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Jimma Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Jimma Town ET-MOWIE-75874-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Semera Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Semera Town ET-MOWIE-75875-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Harar Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Harar Town ET-MOWIE-75876-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Diredewa Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Diredewa Town ET-MOWIE-75877-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Mekelle Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Mekelle Town ET-MOWIE-75880-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Jigjiga Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Jigijiga Town ET-MOWIE-75881-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 DeghaburTown Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by DeghaburTown ET-MOWIE-75882-CS-INDV / Selection and Employment of Component 3: Project Individual Under 2018-07- 2018-12- 2018-12- 2019-01- 2020-01- Technical Specialist for MOWIE IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-10-15 Implementation 01 03 24 28 28 Program management unit by strengthening Selection MoWIE ET-MOWIE-75883-CS-INDV / Component 3: Project Individual Selection and Employment of Under 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Prior Consultant Open 7,500.00 0.00 2018-10-15 Procurement Specialist for Implementation 03 24 28 28 strengthening Selection MoWIE PMU by MoWIE ET-MOWIE-77731-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-06- 2018-11- 2018-09- 2018-12- 2020-01- 2019-01- 2020-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,204.12 Signed 2018-09-26 SodoTown Water Supply and 11 14 30 05 20 09 20 09 strengthening Selection Sewerage Enterprise by Sodo Town ET-MOWIE-77735-CS-INDV / Selection and employment of Component 3: Project Individual 2018-07- 2018-11- 2018-07- 2018-12- 2018-09- 2019-01- 2018-09- 2020-01- financial specialist for IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,880.10 Signed 2018-09-26 02 14 25 05 11 09 11 09 Arbaminch town WSSE for strengthening Selection Arbaminch Town ET-MOWIE-77736-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for 2018-08- 2018-11- 2018-07- 2018-12- 2018-08- 2019-01- 2018-08- 2020-01- IDA / 60070 management & institutional Post Consultant Open 6,600.00 2,676.54 Signed 2018-09-26 Nekemte Town Water Supply 16 14 03 05 01 09 01 09 strengthening Selection and Sewerage Enterprise by Nekemte Town ET-MOWIE-77737-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for Asella Pending 2018-11- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-26 Town Water Supply and Implementation 14 05 09 04 strengthening Selection Sewerage Enterprise by Asella Town ET-MOWIE-77738-CS-INDV / Selection and Employment of Financial specialist for Component 3: Project Individual 2019-05- 2018-11- 2018-09- 2018-12- 2018-07- 2019-01- 2018-09- 2020-01- Shashamene Town Water IDA / 60070 management & institutional Post Consultant Open 6,600.00 3,922.27 Signed 2018-09-26 11 14 09 05 11 09 17 09 Supply and Sewerage strengthening Selection Enterprise by Shashamene Town ET-MOWIE-77734-CS-CDS / Selection and employment of Component 2: Sanitation and consultant for construction water supply services Under 2018-09- 2018-12- 2019-02- 2019-08- supervision and contract IDA / 60070 Post Direct Selection Direct 110,011.00 0.00 2018-11-30 improvement in secondary Implementation 12 10 13 12 administration for Dire Dewa cities Town WSSE by Dire Dewa Town ET-MOWIE-107048-CS-INDV / Selection and Employment Component 3: Project Individual Under 2019-05- 2019-05- 2020-02- 2019-05- 2020-05- 2019-06- 2023-06- of Individual Procurement IDA / 60070 management & institutional Prior Consultant Open 100,000.00 0.00 2019-04-01 Implementation 09 05 27 26 06 30 29 Consultant/Specialist by Water strengthening Selection Development Commission ET-MOWIE-107059-CS-INDV / Selection and Employment Component 3: Project Individual of Individual Technical Pending 2019-05- 2019-05- 2019-06- 2023-04- IDA / 60070 management & institutional Post Consultant Open 100,000.00 0.00 2019-04-01 Consultant/ Specialist by Implementation 04 18 22 27 strengthening Selection Water Development Commission Page 13 ET-MOWIE-107052-CS-INDV / Selection and Employment of Contract Management Component 3: Project Individual 2019-04- 2019-05- 2019-08- 2019-05- 2019-11- 2019-06- 2019-11- 2023-07- Specialist for Water IDA / 60070 management & institutional Post Consultant Open 100,000.00 22,948.29 Signed 2019-04-01 30 04 30 25 05 29 13 08 Development commission strengthening Selection Urban WSSP II by Water Development Commission ET-MOWIE-107049-CS-INDV / Selection and Employment of Individual Financial Component 3: Project Individual 2019-04- 2019-05- 2019-10- 2019-05- 2019-11- 2019-06- 2019-11- 2023-07- Management Consultant/ IDA / 60070 management & institutional Post Consultant Open 100,000.00 24,407.63 Signed 2019-04-01 30 04 11 25 05 29 14 08 Specialist for Urban WSSP II by strengthening Selection Water Development Commission ET-MOWIE-110854-CS-INDV Component 3: Project Individual Under 2019-06- 2019-06- 2019-06- 2022-12- / Selection and Employment IDA / 60070 management & institutional Post Consultant Open 50,000.00 0.00 2019-04-30 Implementation 02 09 30 28 of Social Safeguard Senior strengthening Selection ET-MOWIE-107057-CS-INDV / Selection and Employment of Environmental and Social Component 2: Sanitation and Safeguard Specialist for review Individual water supply services Pending 2019-07- 2019-08- 2019-09- 2019-11- of 3 towns ( Adama, Dire IDA / 60070 Post Consultant Open 52,000.00 0.00 2019-06-20 improvement in secondary Implementation 24 14 07 06 Dewa, Mekele) feasibility Selection cities study and detail design by Water Development Commission ET-MOWIE-118398-CS-INDV / Selection and Employment of Environmental and Social Component 2: Sanitation and Individual Safeguard Specialist for review water supply services Pending 2019-08- 2019-08- 2019-10- 2019-12- IDA / 60070 Post Consultant Open 35,000.00 0.00 2019-06-20 of 2 towns ( Hawasa and improvement in secondary Implementation 08 29 03 02 Selection Bahirdar) feasibility study and cities detail design by Water Development Commission ET-MOWIE-143029-CS-INDV / Selection and employment Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-05- of Sociologist for WDC by IDA / 60070 management & institutional Post Consultant Open 25,000.00 21,813.30 Signed 2019-11-15 20 03 03 24 23 28 23 28 Water Development strengthening Selection Commission ET-MOWIE-143055-CS-INDV Component 2: Sanitation and / Selection and Employment Individual water supply services 2018-07- 2020-01- 2019-02- 2020-02- 2019-02- 2020-03- 2019-01- 2021-03- of sanitation and Hygiene IDA / 60070 Post Consultant Open 30,000.00 5,536.05 Signed 2019-11-28 improvement in secondary 25 16 28 06 22 12 28 12 specialist by water Selection cities Development Commission. ET-MOWIE-143022-CS-INDV / Selection and Employment Component 3: Project Individual Under 2020-01- 2020-01- 2020-02- 2020-06- of Water Supply and Sanitation IDA / 60070 management & institutional Prior Consultant Open 30,000.00 0.00 2019-11-15 Implementation 03 24 28 27 Regulatory Specialist for WDC strengthening Selection by World Bank country office ET-MOWIE-143032-CS-INDV / Selection and employment Component 3: Project Individual 2019-04- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- of Environmental specialist for IDA / 60070 management & institutional Post Consultant Open 35,000.00 20,755.86 Signed 2019-11-15 30 03 03 24 23 28 23 27 Water Development strengthening Selection Commission by WDC ET-MOWIE-143016-CS-INDV / Selection and employment Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-02- 2020-06- 2020-03- 2020-06- 2020-08- of legal specialist for WDC by IDA / 60070 management & institutional Post Consultant Open 40,000.00 21,341.44 Signed 2019-11-28 19 16 03 06 23 12 23 09 Water Development strengthening Selection Commission ET-MOWIE-143025-CS-INDV / Selection and Employment Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- of Technical Specialist for IDA / 60070 management & institutional Post Consultant Open 35,000.00 31,319.66 Signed 2019-11-15 18 03 03 24 23 28 23 27 WDC by Water Development strengthening Selection Commission ET-MOWIE-143026-CS-INDV / Selection and Employment Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- of Economist for WDC by IDA / 60070 management & institutional Post Consultant Open 30,000.00 28,520.21 Signed 2019-11-15 20 03 03 24 23 28 23 27 Water Development strengthening Selection Commission ET-MOWIE-143012-CS-INDV / Selection and Employment Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-03- 2020-06- 2020-09- of Governance/Public Policy IDA / 60070 management & institutional Post Consultant Open 50,000.00 48,149.24 Signed 2019-11-22 20 10 03 31 23 06 23 02 Specialist for WDC by Water strengthening Selection Development Commission ET-MOWIE-145062-CS-QBS Component 2: Sanitation and / Selection and Employment Individual water supply services Pending 2020-01- 2020-02- 2020-03- 2021-03- of business management IDA / 60070 Post Consultant Open 30,000.00 0.00 2019-11-28 improvement in secondary Implementation 16 06 12 12 specialist by the Water Selection cities Development Commission ET-MOWIE-75885-CS-INDV / Component 3: Project Individual Selection and Employment of Under 2019-01- 2019-01- 2019-02- 2020-02- IDA / 60070 management & institutional Prior Consultant Open 7,500.00 0.00 2018-11-15 Procurement Specialist for Implementation 03 24 28 28 strengthening Selection MoWIE PMU by MoWIE ET-MOWIE-181047-CS-INDV / Selection and Employment of one Additional Individual Component 3: Project Individual Under 2020-10- 2020-08- 2020-09- 2020-10- 2021-10- Procurement Consultant for IDA / 60070 management & institutional Prior Consultant Open 30,000.00 0.00 2020-07-08 Implementation 28 26 16 21 21 Water Development strengthening Selection Commission implemented by WDC ET-MOWIE-189851-CS-INDV / Selection and Employment of Individual Consultant who Component 3: Project Individual Pending 2020-11- 2020-11- 2020-12- 2021-12- provide support in selection IDA / 60070 management & institutional Post Consultant Open 75,000.00 0.00 2020-09-15 Implementation 03 24 29 29 of contractor and contract strengthening Selection administration of 5 towns FSTP DBO contract. Page 14