Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: 05 March 2014, Revision 14 November 2016 2. Date of General Procurement Notice: March 30, 2014 3. Period covered by this procurement plan: March 2014 – December 2021 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1.500,000 All 2. NCB (Goods) US$ <1.500,000 None (Approved in Plan) 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) US$ <5 million None (Approved in Plan) 5 (Non-Consultant Services) US$ <1.500,000 Non (Approved in Plan) 6 (Non-Consultant Services) US$ above1.500,000 All 2. Prequalification. Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual issued by the PIU of the PCDS 5. Any Other Special Procurement Arrangements: None 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Comme No. n d stic by Bank nts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultan t Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 5. Consultants (firm) US$ 500,000 All Consultants (firm)