Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non-consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Shopping Up to USD 100,000 (INR 6.5 m) Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from any given state. (d) Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g) Two or three envelope system will not be used (except when using the e-procurement system assessed and agreed by the Bank). (h) No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget (FBS) Must meet the requirements as per Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis (LCS) Must meet the requirements as per Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Qualification Estimated not to exceed USD 300,000, and (CQ) must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for 1. Executive, Assistant Engineers who are responsible for 2 weeks Continuous Procurement – multiple trainings 2. Contract management training – multiple trainings 2 weeks Continuous Customized training on Procurement Procedures arranged for 3. Executive, Assistant Engineers who are responsible for 1 week Continuous Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-11-03 2020-02-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Executing Agency(ies): Telengana Ground Water WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TELENGANA GW-23242- CW-RFB / (i)Protection works (126) for piezometers drilled under HP-II in Southern Telangana Region Water Resources Monitoring Request for Single Stage - One and IBRD / 87250 Post Limited 90,770.00 0.00 Canceled 2017-10-02 2017-11-26 2018-02-24 System Quotations Envelope (ii)Rejuvenation of existing piezometers (86) for effective water level measurements in piezometers constructed during HP I & II. IN-TELENGANA GW-23262- Water Resources Monitoring Request for Single Stage - One CW-RFQ / Civil Works for IBRD / 87250 Post Limited 7,692.00 0.00 Canceled 2018-02-05 2018-03-19 2018-05-18 System Quotations Envelope Purpose Driven Studies IN-TELENGANA GW-24093- CW-RFQ / (i) Protection works (98) for Peizometers drilled under HP-II covering Cluster of Eastern Telangana and Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 91,850.00 0.00 Canceled 2017-09-30 2017-11-25 2018-02-23 (ii) Rejuvenation of existing System Quotations Envelope piezometers (205) for effective water level measurements in piezometers constructed during HP I & II. IN-TELENGANA GW-24096- CW-RFQ / (i) Protection works (76) for Peizometers drilled under HP-II covering Cluster of Northern Telangana and Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 67,550.00 0.00 Canceled 2017-09-30 2017-11-25 2018-02-23 (ii) Rejuvenation of existing System Quotations Envelope piezometers (135) for effective water level measurements in piezometers constructed during HP I & II. NHP-2018-2019-TSGW- 339383 / Protection works to Water Resources Monitoring Request for Single Stage - One Piezometers of less than 50 IBRD / 87250 Post Open - National 78,461.54 70,266.09 Signed 2018-09-15 2018-11-10 2019-01-09 System Quotations Envelope m drilled under HP-II in Southern Region NHP-2018-2019-TSGW- 946553 / Protection works to Water Resources Monitoring Request for Single Stage - One Piezometers of less than 50 IBRD / 87250 Post Open - National 53,846.15 50,521.90 Signed 2018-09-16 2018-11-11 2019-01-10 System Quotations Envelope m drilled under HP-II in Northern Region Page 1 NHP-2018-2019-TSGW- 834014 / Protection works to Under Water Resources Monitoring Request for Single Stage - One Piezometers less than 50m IBRD / 87250 Post Open - National 52,307.69 0.00 Implementati 2018-09-17 2018-11-12 2019-01-11 System Quotations Envelope drilled under HP-II in on Eastern Telangana Region NHP-2018-2019-TSGW- 564746 / Rejuvenation of Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 84,615.38 73,712.51 Signed 2018-09-29 2018-11-24 2019-01-23 Existing PZ for effective System Quotations Envelope water level monitoring NHP-2018-2019-TSGW- Pending 903276 / Upgradation of Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 153,846.15 0.00 Implementati 2018-10-08 2018-10-13 2018-11-24 2019-02-06 2019-03-13 2019-09-09 State Data , Training cum System Envelope on Information Centre NHP-2018-2019-TSGW- Pending Water Resources Monitoring Request for Single Stage - One 721719 / Civil works for IBRD / 87250 Post Open - National 38,461.54 0.00 Implementati 2018-10-15 2018-12-10 2019-06-08 System Quotations Envelope Purpose Driven Studies (Yr1) on IN-TELENGANA GW-88377- CW-RFB / Construction of PZs with Protection works Pending to improve GW Monitoring Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 1,230,769.00 0.00 Implementati 2019-01-21 2019-01-26 2019-03-09 2019-05-22 2019-06-26 2019-12-23 Network in the state System Envelope on Piezometers(Medium 50- 100m). (To have 3 PZs in each GW assessment unit) NHP-2018-2019-TSGW- 424962 / Construction of Piezometers (50-100 m)with Pending Water Resources Monitoring Single Stage - Two Protection works to improve IBRD / 87250 Post Request for Bids Open - National 1,230,769.00 0.00 Implementati 2019-05-15 2019-05-20 2019-07-01 2019-09-13 2019-10-18 2020-04-15 System Envelope GW Monitoring Network in on the state. (To have 3 PZs in each GW assessment unit) NHP-2019-2020-TSGW- 767785 / Establishment of Pending Regional Ground Water Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 318,500.00 0.00 Implementati 2019-07-15 2019-07-20 2019-08-31 2019-11-13 2019-12-18 2020-06-15 Information Centre in System Envelope on Karimnagar including Infrastructure GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TELENGANA GW-23217- GO-RFQ / Procurement of Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 76,923.07 0.00 Canceled 2017-09-11 2017-11-10 2018-01-09 Borehole Logging Equipment System Quotations Envelope with AMC Support IN-TELENGANA GW-23260- GO-RFQ / To create resource material (Annual Reports, pamphlets, Brochure, posters, audio visuals, documentaries Water Resources Operations Request for Single Stage - One IBRD / 87250 Post Limited 17,538.00 0.00 Canceled 2018-02-03 2018-03-18 2018-04-17 etc.,)on water conservation & and Planning System Quotations Envelope management awareness creation to water users (IEC) & Resource material for PDS & DSS Page 2 IN-TELENGANA GW-23278- GO-RFQ / Procurement and Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 12,308.00 0.00 Canceled 2017-12-05 2018-01-10 2018-02-09 Installation of ACs (10) for System Quotations Envelope SDC and Conference Hall IN-TELENGANA GW-24074- GO-RFQ / Basic Field equipment for field officers for Strengthening Manual Observations - 32units (Each Water Resources Monitoring Request for Single Stage - One unit Consists of WL IBRD / 87250 Post Limited 69,615.00 0.00 Canceled 2017-09-21 2017-11-16 2017-12-16 System Quotations Envelope Indicators -2, Geological Survey Kits-2, Infiltrometre- 1, 100m Mesuring Tapes-5, 50m Measuring Tapes-5, Dumpy Level -1) IN-TELENGANA GW-24071- GO-RFQ / Basic Field equipment for field officers for Strengthening Manual Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 37,700.00 0.00 Canceled 2017-12-08 2018-01-20 2018-02-20 Observations (98 GPS - 3 System Quotations Envelope Units for Each District Offices(31Districts) and 5 units for Head Office) IN-TELENGANA GW-24088- GO-DIR / Procurement of IT Equipment for Data Centres Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 83,385.00 0.00 Canceled 2017-12-09 2018-01-27 2018-02-26 (Desktops, Printers, Laptops, System Quotations Envelope HDDs, A0 Plotter etc) through GEM IN-TELENGANA GW-37063- GO-RFB / WQ Lab Water Resources Monitoring Single Stage - One IBRD / 87250 Post Request for Bids Open - National 123,100.00 0.00 Canceled 2017-11-27 2017-12-02 2017-12-23 2018-01-09 2018-02-02 2018-04-04 Equpiment Up gradation at System Envelope Hyderabad and Karimnagar NHP-2018-2019-TSGW- 261629-GO-SH-QU / Basic Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 92,692.31 160,806.64 Signed 2018-07-28 2018-09-22 2018-11-21 field equipment for field System Quotations Envelope officers NHP-2018-2019-TSGW- 127898 / IT Equipment for Pending Water Resources Monitoring Request for Single Stage - One Data Centres - IBRD / 87250 Post Open - National 4,615.38 0.00 Implementati 2018-07-16 2018-09-10 2018-11-09 System Quotations Envelope Communication equipment on (Tabs) NHP-2018-2019-TSGW- Under Water Resources Monitoring Request for Single Stage - One 983848 / IT Equipment for IBRD / 87250 Post Open - National 52,461.54 34,103.18 Implementati 2018-07-16 2018-09-10 2018-11-09 System Quotations Envelope Data Centres - UPS System on NHP-2018-2019-TSGW- Pending 664034 / A/Cs 2T for Data Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 16,000.00 0.00 Implementati 2018-09-09 2018-11-04 2019-01-03 Centres and Water Quality System Quotations Envelope on Labs NHP-2018-2019-TSGW- Under 965817 / Updation of Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 94,584.62 0.00 Implementati 2018-08-28 2018-10-23 2018-12-22 existing Water Quality Labs System Quotations Envelope on at Hyderabad & Karimnagar NHP-2018-2019-TSGW- Water Resources Information 167277 / Procurement of IBRD / 87250 Post Direct Selection Direct 1,538.46 1,304.08 Completed 2018-07-20 2018-07-25 2018-08-29 2019-02-25 Systems SOI Toposheets Page 3 NHP-2018-2019-TSGW- 953596 / To create resource material (Annual Pending Institutional Capacity Request for Single Stage - One Reports,pamplets,Brochure,pos IBRD / 87250 Post Open - National 7,692.31 0.00 Implementati 2018-10-27 2018-12-22 2019-02-20 Enhancement Quotations Envelope ters,audiovisuals,documentarie on s etc) on water conservation & management awareness NHP-2018-2019-TSGW- 218424 / Procurement of equipment for Tanks as Pending Water Resources Operations Request for Single Stage - One Source for regional IBRD / 87250 Post Open - National 46,153.85 0.00 Implementati 2018-08-20 2018-10-15 2018-12-14 and Planning System Quotations Envelope Groundwater Recharge using on Managed Aquifer Storage & Recovery (ASR) NHP-2018-2019-TSGW- Water Resources Monitoring 553646 / Software for Data IBRD / 87250 Post Direct Selection Direct 30,769.23 34,286.86 Completed 2018-07-25 2018-07-30 2018-09-03 2019-03-02 System Center - GIS software NHP-2018-2019-TSGW- Under Water Resources Monitoring Request for Single Stage - One 319070 / Software for Data IBRD / 87250 Post Open - National 69,230.77 0.00 Implementati 2018-08-13 2018-10-08 2018-12-07 System Quotations Envelope Center - Other software on NHP-2018-2019-TSGW- Pending Water Resources Operations Request for Single Stage - One 448681 / Resource material IBRD / 87250 Post Open - National 10,984.62 0.00 Implementati 2018-11-17 2019-01-12 2019-03-28 and Planning System Quotations Envelope for PDS & DSS on NHP-2018-2019-TSGW- Water Resources Monitoring Request for Single Stage - One 551441 / IT Equipment for IBRD / 87250 Post Open - National 9,307.69 10,881.10 Completed 2018-11-03 2018-12-29 2019-02-27 System Quotations Envelope Data Centres - Printer IN-TELENGANA GW- 108349-GO-DIR / Software Water Resources Monitoring IBRD / 87250 Post Direct Selection Direct 73,470.38 67,093.87 Signed 2019-03-30 2019-04-04 2019-05-09 2019-11-05 for data centre - surfer System software NHP-2019-2020-TSGW- Pending Water Resources Monitoring Request for Single Stage - One 510934 / A/Cs 2T for DDCs IBRD / 87250 Post Open - National 46,030.77 0.00 Implementati 2019-07-02 2019-08-27 2019-09-26 System Quotations Envelope (31+3 labs) on NHP-2019-2020-TSGW- Under Water Resources Monitoring Single Stage - Two 586066 / Procurement of IBRD / 87250 Post Request for Bids Open - National 230,769.23 0.00 Implementati 2019-09-05 2019-09-10 2019-10-10 2019-11-28 2019-12-19 2020-03-18 System Envelope DWLRs with Telemetry on NHP-2019-2020-TSGW- Pending Water Resources Monitoring Request for Single Stage - One 325673 / Portable Units for IBRD / 87250 Post Open - National 36,925.00 0.00 Implementati 2019-07-15 2019-09-09 2019-10-09 System Quotations Envelope WQ Test on NHP-2019-2020-TSGW- Pending 261304 / IT Equipment for Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 33,846.15 0.00 Implementati 2019-12-23 2020-02-11 2020-03-27 Data Centres - Work System Quotations Envelope on Stations for SDC NHP-2019-2020-TSGW- Under 643223 / IT Equipment for Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 50,769.23 0.00 Implementati 2019-06-25 2019-08-20 2019-09-19 Data Centres - Data System Quotations Envelope on Analysis System (DAS) NHP-2019-2020-TSGW- 211566 / IT Equipment for Pending Water Resources Monitoring Request for Single Stage - One Data Centres - Audio visual IBRD / 87250 Post Open - National 25,384.62 0.00 Implementati 2019-08-07 2019-10-02 2019-11-16 System Quotations Envelope equipment for Distance on learning Page 4 NHP-2019-2020-TSGW- Pending 828303 / Softwares for Data Water Resources Monitoring IBRD / 87250 Post Direct Selection Direct 76,153.85 0.00 Implementati 2019-12-03 2019-12-06 2019-12-26 2020-01-25 Centres (GIS application System on softwares) NHP-2019-2020-TSGW- Pending 653442 / IT Equipment for Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 10,153.85 0.00 Implementati 2019-07-20 2019-09-08 2019-10-23 Data Centres - Printers for System Quotations Envelope on SDC IN-TELENGANA GW- 116685-GO-DIR / Procurement (1 no.) and upgradation (1 no.) of Ground Water Modelling Water Resources Operations Software (Visual MODFLOW) IBRD / 87250 Post Direct Selection Direct 10,000.00 9,398.89 Signed 2019-06-10 2019-06-15 2019-07-20 2020-01-16 and Planning System and Procurement (1 no.) and upgradation (1 no.) of Geochemical Modelling Software (Aquachem) for Purpose Driven Study IN-TELENGANA GW- 116686-GO-DIR / Procurement of Geological Modelling Software (Rockworks - 1 nos) for Water Resources Operations IBRD / 87250 Post Direct Selection Direct 5,500.00 6,216.20 Signed 2019-06-12 2019-06-17 2019-07-22 2020-01-18 Purpose Drive Study on and Planning System Impact of Urbanization on GW Quality & Quantity and its Management in GHMC Area, Hyderabad. IN-TELENGANA GW- 117255-GO-DIR / Procurement of Ground Water (fracture zone) Pending Modelling software to Water Resources Operations IBRD / 87250 Post Direct Selection Direct 3,100.00 0.00 Implementati 2019-06-12 2019-06-17 2019-07-22 2020-01-18 simulate Groundwater Flow and Planning System on in fractured zone to address local to regional-scale surface water and ground water interaction for PDS. NHP-2018-2019-TSGW- 619408 / IT Equipment for Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 84,620.00 74,020.65 Signed 2019-06-03 2019-07-29 2019-09-27 Data Centres - computers & System Quotations Envelope laptops IN-TELENGANA GW- 156454-GO-RFQ / Procurement of Data Retrieval and Analysis Pending Systems (8 nos) for PDS Water Resources Information Request for Single Stage - One IBRD / 87250 Post Open - National 7,693.00 0.00 Implementati 2020-02-03 2020-03-01 2020-03-31 study on Impact of Systems Quotations Envelope on urbanisation on GW quality & quantity and its management in GHMC Area, Hyderabad NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TELENGANA GW-23248- CS-QCBS / Consultancy Services for Study to delineate basin wise subsurface geometry in 3D Water Resources Operations Quality And Cost- using existing data and IBRD / 87250 Post Open - National 738,460.00 0.00 Canceled 2018-01-18 2018-02-08 2018-03-24 2018-04-21 2018-05-21 2018-06-25 2018-07-30 2021-07-29 and Planning System Based Selection evaluation of aquifer characteristics in Telangana region to develop comprehensive ground water Atlas NHP-2018-2019-TSGW- 954549 / Development of website, Village GW Water Resources Information Quality And Cost- Pending estimation software, data IBRD / 87250 Post Open - National 338,461.54 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-12 2019-01-11 2019-02-15 2019-03-22 2020-03-21 Systems Based Selection Implementation entry & analysis software, mobile app design, creation & automation of central DB NHP-2018-2019-TSGW- 995210 / Comprehensive Consultant Planing for interiors and Water Resources Monitoring Pending IBRD / 87250 Post Qualification Open - National 31,538.46 0.00 2018-07-23 2018-08-13 2018-09-26 2018-10-26 2018-11-30 2019-01-14 Architecture for DDCs, SDC System Implementation Selection and Training cum Information Centres INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TELENGANA GW-36922- Individual Institutional Capacity CS-CDS / Hiring technical IBRD / 87250 Post Consultant Limited 11,538.00 0.00 Canceled 2017-12-15 2017-12-20 2017-12-27 2018-01-10 2018-05-10 Enhancement and financial experts Selection IN-TELENGANA GW-36911- CS-CDS / Procurement of Services for Comprehensive Individual Water Resources Monitoring Planing for interiors and IBRD / 87250 Post Consultant Limited 31,500.00 0.00 Canceled 2018-01-25 2018-01-30 2018-02-06 2018-02-28 2018-06-28 System Architecture for DDCs, SDC Selection and Training cum Information Centres NHP-2018-2019-TSGW- Individual Institutional Capacity Pending 452849 / Hiring Technical & IBRD / 87250 Post Consultant Open 4,615.38 0.00 2018-08-23 2018-10-11 2018-11-01 2018-12-06 2019-06-04 Enhancement Implementation financial Experts Selection NHP-2018-2019-TSGW- 190181 / Consultancy charges for PDS study on Water Resources Operations Impact of Urbanization on IBRD / 87250 Post Direct Selection Direct 30,769.23 28,118.72 Signed 2018-07-16 2018-07-26 2018-09-29 2019-03-28 and Planning System Gw Quality & Quantity & its Management in GHMC Area, Hyderabad NHP-2018-2019-TSGW- 161599 / Consultancy charges for the PDS study on Tanks as Source for Water Resources Operations Pending IBRD / 87250 Post Direct Selection Direct 30,769.23 0.00 2018-07-18 2018-07-28 2018-10-01 2019-03-30 regional Groundwater and Planning System Implementation Recharge using Managed Aquifer Storage & Recovery (ASR) Page 6 NHP-2018-2019-TSGW- Individual Institutional Capacity Pending 436795 / Hiring financial IBRD / 87250 Post Consultant Open 4,615.38 0.00 2018-08-23 2018-10-11 2018-11-01 2018-12-06 2019-06-04 Enhancement Implementation Experts Selection IN-TELENGANA GW- 116824-CS-INDV / Individual Comprehensive planning for Water Resources Monitoring Under IBRD / 87250 Post Consultant Open 16,155.00 0.00 2019-05-31 2019-07-05 2019-07-15 2019-08-05 2019-10-04 interiors and architecture for System Implementation Selection DDCs, SDC and Training Cum Information Centre Page 7