Procurement Plan for WBADMI Project (P105311) I. General 1. Bank’s approval Date of the procurement Plan Aug 25 2011 2. Date of General Procurement Notice: May 10 2010 3. Period covered by this procurement plan: The procurement period of project covered from year 1st June 2011 to 31st May 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above 1000 000 LIB above 200 000 2. NCB (Goods) >50 000 & < 1000 000 3. NCB (Non-Consultant Services) Do 4. ICB (Works) Above 5000 000 5. NCB (Works) Upto 5000 000 6. National shopping < 50 000 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project is using a procurement manual, which is agreed with World Bank 5. Any Other Special Procurement Arrangements: Retroactive financing is applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of Nil - no - - the ICB (Works) July 9, 2010 Summary of Nil Nil the ICB (Goods) Summary of 22 150 no post 10 pkgs the NCB are (Works) through shopping Summary of Nil All goods the NCB are (Goods) through shopping (75 pkgs) Summary of Nil Nil the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 300,000 2. Single Source (Firms) Above USD 100 000 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Retroactive financing applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 1.4 4 - All post number of review contracts that will be let under QCBS Summary of 5.5 4 Prior Two Post number of review contracts that July 9, 2010 will be let under other methods July 9, 2010 PROCUREMENT India : IN West Bengal Accelerated Development of Minor Irrigation PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-09-27 2019-07-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P105311 GPN Date: Project Name: IN West Bengal Accelerated Development of Minor Irrigation Loan / Credit No: IBRD / 80900 Executing Agency(ies):DPMU Purulia WORKS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPMU - PURULIA- 25143-CW-RFB / Construction of Pump Dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-02 Mouza- IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Ulda Block Barabazar in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 25210-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-03, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 29 28 -Ulda, Block- barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25216-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-07, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Ulda, Block- barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25329-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Ulda PDW-08, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Ulda, Block- barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25331-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-02, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25332-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-03, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 22 21 -Kuda, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25335-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-04, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25336-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-06, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25338-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Kuda PDW-08, Mouza IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 -Kuda, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25339-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-03, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25340-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-04, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25341-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-05, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25342-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-06, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25343-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Banjora PDW-07, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Banjora, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25344-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-03, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25345-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-06, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25346-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-07, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25347-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-08, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25348-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Sarishabahal PDW-09, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Sorishabahal, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25349-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-02, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25350-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-03, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25351-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-04, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25352-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-05, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25353-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-06, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25354-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-07, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 Page 1 IN-DPMU - PURULIA- 25355-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-08, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25356-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-09, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25357-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-11, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25358-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-12, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25360-CW-RFB / Construction of Pump dug Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- well Dhabani PDW-14, IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 Mouza -Dhabani, Block- Bandwan under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25362-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 42,563.20 Signed Banjora WDS-02, Mouza - Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-951, Block- Barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25363-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Banjora WDS-05, Mouza - IBRD / 80900 Post Open - National 25,523.79 Signed Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-745 & 746, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25364-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 23,889.00 Signed Banjora WDS-06, Mouza - Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-599, Block- Barabazar under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25365-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Banjora WDS-07, Mouza - IBRD / 80900 Post Open - National 36,432.97 Signed Bids One Envelope 18 23 25 18 21 20 Banjora, JL No.-75, Plot No.-88, 89 & 90, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25366-CW-RFB / Construction of Water Detention Structure Kuda Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 18,847.61 Signed WDS-01, Mouza -Kuda, JL Bids One Envelope 18 23 25 18 21 20 No.-15, Plot No.-500, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25367-CW-RFB / Construction of Water Detention Structure Mahilidih WDS-02, Mouza Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IBRD / 80900 Post Open - National 44,126.66 Signed -Mahilidih, JL No.-10, Plot Bids One Envelope 18 23 25 18 21 20 No.-413 to 416 & 252, 253 Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25368-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Krishnanagar WDS-02, IBRD / 80900 Post Open - National 28,553.98 Signed Bids One Envelope 18 23 25 18 21 20 Mouza -Krishnanagar, JL No.-46, Plot No.-1003, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25371-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Krishnanagar WDS-05, IBRD / 80900 Post Open - National 32,950.97 Signed Bids One Envelope 18 23 25 18 21 20 Mouza -Krishnanagar, JL No.-46, Plot No.-286, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25372-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Hullung WDS-01, Mouza - IBRD / 80900 Post Open - National 28,773.96 Signed Bids One Envelope 18 23 25 18 21 20 Hullung, JL No.-29, Plot No.-341, 350 & 351, Block- Manbazar-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25383-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinda IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Hatinda, Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25384-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Shyampur IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Chargali, Block- Purulia-II under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25385-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Manipur IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Manipur, Block- Purulia-II under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25386-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Dumdumi IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - Dumdumi, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25387-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Raghabpur IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - Raghabpur, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25388-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Pirargarya IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza - Pirargarya, Block- Purulia- II under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 25389-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Bagdadih IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Bagdadih, Block- Purulia-I under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25390-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Kuchung IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-02, Mouza -Kuchung, Block- Puncha under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25391-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chandra IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-02, Mouza -Chandra, Block- Puncha under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25392-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chandra IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-01, Mouza -Chandra, Block- Puncha under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25403-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-IV, Mouza -Anara, Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25404-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-III, Mouza -Anara, Block- Para under WBADMI Project for the year 2017-18 Page 2 IN-DPMU - PURULIA- 25405-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-II, Mouza -Anara, Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25406-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Anara IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Anara, Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25408-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Chautala IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Chautala, Block- Para under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25409-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Udaypur IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-I, Mouza -Udaypur, Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25410-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinada IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-III, Mouza -Hatinada, Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 25411-CW-RFB / Construction of Solar Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- Pump dug well Hatinada IBRD / 80900 Post Open - National 0.00 Canceled Bids One Envelope 18 23 25 18 21 20 PDW-II, Mouza -Hatinada, Block- Joypur under WBADMI Project for the year 2017-18 IN-DPMU - PURULIA- 26034-CW-RFB / Construction of Chinese Pending carp hatchery with supply Request for Single Stage - 2017-08- 2017-08- 2017-09- 2017-09- 2017-10- 2017-11- IBRD / 80900 Post Open - National 0.00 Implement of input for operational at Bids One Envelope 28 30 15 22 13 13 ation Mouza- Joyramdi, Jl No.- 178, Plot-163 under WBADMI Project IN-DPMU - PURULIA- 33448-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,609.90 Signed Banjora WDS 8, Mouza - Bids One Envelope 01 06 18 19 26 24 Banjora, Block - Barabazar , in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 32581-CW-RFB / Construction of Water Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure IBRD / 80900 Post Open - National 25,630.22 Signed Bids One Envelope 31 05 17 19 26 24 Banjora WDS-3, Mouza- Banjora, Block- barabazar in the district of Purulia IN-DPMU - PURULIA- 33909-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 33,935.67 Signed Jasodih WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jasodih, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33910-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 123,547.20 Signed Jasodih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jasodih, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33923-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 38,023.80 Signed WDS 8, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 32580-CW-RFB / Construction of Water Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure Ulda IBRD / 80900 Post Open - National 23,183.60 Signed Bids One Envelope 31 05 17 19 26 24 WDS-3, Mouza-Ulda, Block- barabazar in the district of Purulia IN-DPMU - PURULIA- 32343-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 39,345.30 Signed Gitinglahar WDS-I, Mouza Bids One Envelope 31 05 17 19 26 24 -Gitinglahar, Block- Balrampur under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 33449-CW-RFB / Construction of Water Detention Structure Loto Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 47,057.28 Signed WDS 1, Mouza - Loto, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33455-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 40,463.46 Signed WDS 1, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33958-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 52,476.95 Signed (Jadublabra WDS), Mouza Bids One Envelope 01 06 18 19 26 24 - Goyalberia, Block - Santuri, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33646-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,674.26 Signed Salghati WDS - I, Mouza - Bids One Envelope 01 06 18 19 26 24 Salghati, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33654-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 25,600.26 Signed Gosaidih WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33655-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 30,592.22 Signed Gosaidih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33656-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,191.76 Signed Gosaidih WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Gosaidih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33657-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 57,898.48 Signed Raiddih WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Raiddih, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33667-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 15,767.63 Signed JaragoraWDS 6, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33675-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 3, Mouza IBRD / 80900 Post Open - National 31,405.60 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33316-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 24,111.70 Signed Sorisabahal WDS-1, Mouza Bids One Envelope 01 06 18 19 26 24 - Sorisabahal, Block- Barabazar in the district of Purulia Under WBADMI Project. IN-DPMU - PURULIA- 34423-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Kiribera WDS -2), Mouza Bids One Envelope 01 06 18 19 26 24 ation - Kiribera, Block - Jhalda 1 in Purulia District under WBADMI Project. Page 3 IN-DPMU - PURULIA- 34424-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 32,335.78 Signed (Kiribera WDS -3), Mouza Bids One Envelope 01 06 18 19 26 24 - Kiribera, Block - Jhalda 1 in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34430-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 78,561.89 Signed (Sutabai WDS), Mouza - Bids One Envelope 01 06 18 19 26 24 Sutabai, Block - Kashipur in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33903-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Bankudih WDS 1, Mouza - IBRD / 80900 Post Open - National 41,580.30 Signed Bids One Envelope 01 06 18 19 26 24 Bankudih, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33911-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,662.40 Signed Susunia WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Susunia, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33912-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 31,191.26 Signed Susunia WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Susunia, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33913-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 20,930.82 Signed Purdaha WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33914-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 21,546.20 Signed Purdaha WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33915-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 23,878.53 Signed Purdaha WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Purdaha, Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33916-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 50,159.76 Signed WDS 1, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33917-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 34,785.35 Signed WDS 2, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33918-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 26,848.95 Signed WDS 3, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33919-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 14,806.47 Signed WDS 4, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33920-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 24,464.39 Signed WDS 5, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33921-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 39,969.71 Signed WDS 6, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33922-CW-RFB / Construction of Water Detention Structure Haridi Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 38,303.68 Signed WDS 7, Mouza - Haridi, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33924-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Chandanpur WDS 1, IBRD / 80900 Post Open - National 17,381.72 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Chandanpur , Block - Manbazar II, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33926-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gohaldanga WDS 1, Mouza IBRD / 80900 Post Open - National 210,037.28 Signed Bids One Envelope 01 06 18 19 26 24 - Gohaldanga, Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34553-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Harada WDS 1), Mouza - Bids One Envelope 01 06 18 19 26 24 ation Harada, Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34554-CW-RFB / Construction of Water Detention Structure (Polpol Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 36,546.67 Signed WDS 1), Mouza - Polpol , Bids One Envelope 01 06 18 19 26 24 Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34555-CW-RFB / Construction of Water Pending Detention Structure (Polpol Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement WDS 2), Mouza - Polpol, Bids One Envelope 01 06 18 19 26 24 ation Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34556-CW-RFB / Construction of Water Detention Structure (Rugri Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 42,421.61 Signed WDS 1), Mouza - Rugri , Bids One Envelope 01 06 18 19 26 24 Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34557-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 234,945.58 Signed (Kadampur WDS 1), Bids One Envelope 01 06 18 19 26 24 Mouza - Kadampur , Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 34558-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 69,603.10 Signed (Karandih WDS 1), Mouza Bids One Envelope 01 06 18 19 26 24 - Karandih, Block - Arsha in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33658-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Raghunathpur WDS 1, IBRD / 80900 Post Open - National 27,262.75 Signed Bids One Envelope 01 06 18 19 26 24 Mouza Raghunathpur, Block - Manbazar 2, in Purulia District under WBADMI Project Page 4 IN-DPMU - PURULIA- 33659-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Raghunathpur WDS 2, IBRD / 80900 Post Open - National 49,050.07 Signed Bids One Envelope 01 06 18 19 26 24 Mouza Raghunathpur, Block - Manbazar 2, in Purulia District under WBADMI Project IN-DPMU - PURULIA- 33661-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,305.64 Signed Jambedi WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jambedi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33662-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 27,628.66 Signed Jambedi WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jambedi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33663-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 11,668.15 Signed Dhabani WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Dhabani, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33664-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 33,550.90 Signed Dhabani WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Dhabani, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33665-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 35,676.93 Signed JaragoraWDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33666-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 32,026.04 Signed Jaragora WDS 3, Mouza - Bids One Envelope 01 06 18 19 26 24 Jaragora, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33668-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 26,981.25 Signed Murgadi WDS 1, Mouza - Bids One Envelope 01 06 18 19 26 24 Murgadi, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33669-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 2, IBRD / 80900 Post Open - National 39,331.60 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33670-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 3, IBRD / 80900 Post Open - National 32,098.47 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33671-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 4, IBRD / 80900 Post Open - National 31,928.11 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33672-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Radhamohanpur WDS 6, IBRD / 80900 Post Open - National 37,093.81 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Radhamohanpur, Block - Manbazar 2, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33673-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 1, Mouza IBRD / 80900 Post Open - National 11,484.98 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33674-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 2, Mouza IBRD / 80900 Post Open - National 17,688.03 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33676-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Gokulnagar WDS 6, Mouza IBRD / 80900 Post Open - National 12,377.00 Signed Bids One Envelope 01 06 18 19 26 24 - Gokulnagar, Block - Barabazar, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33678-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 54,457.61 Signed WDS 2, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33679-CW-RFB / Construction of Water Detention Structure Karma Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 52,655.32 Signed WDS 3, Mouza - Karma, Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33680-CW-RFB / Construction of Water Detention Structure Dava Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 102,008.76 Signed WDS 1, Mouza - Dava , Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33681-CW-RFB / Construction of Water Detention Structure Dava Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 94,049.60 Signed WDS 2, Mouza - Dava , Bids One Envelope 01 06 18 19 26 24 Block - Balarampur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33436-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Krishnanagar WDS 1, IBRD / 80900 Post Open - National 16,127.18 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Krishananagar, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33437-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Krishnanagar WDS 6, IBRD / 80900 Post Open - National 20,047.42 Signed Bids One Envelope 01 06 18 19 26 24 Mouza - Krishananagar, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33438-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Amakoncha WDS 1, Mouza IBRD / 80900 Post Open - National 19,983.30 Signed Bids One Envelope 01 06 18 19 26 24 - Amakoncha, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33439-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 19,183.04 Signed WDS 1, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33440-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 34,322.94 Signed WDS 2, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. Page 5 IN-DPMU - PURULIA- 33441-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 19,228.66 Signed WDS 4, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33443-CW-RFB / Construction of Water Detention Structure Sijadih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 15,256.04 Signed WDS 5, Mouza - Sijadih, Bids One Envelope 01 06 18 19 26 24 Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33444-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,570.66 Signed Jangidiri WDS 2, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33445-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 10,613.44 Signed Jangidiri WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33446-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 23,747.29 Signed Jangidiri WDS 8, Mouza - Bids One Envelope 01 06 18 19 26 24 Jangidiri, Block - Manbazar 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33447-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 31,001.32 Signed Banjora WDS 4, Mouza - Bids One Envelope 01 06 18 19 26 24 Banjora, Block - Barabazar , in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33967-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 118,628.18 Signed (Malancha Asta WDS), Bids One Envelope 01 06 18 19 26 24 Mouza - Malancha , Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33972-CW-RFB / Construction of Water Detention Structure (Chelia Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 54,639.07 Signed I WDS), Mouza - Chelia , Bids One Envelope 01 06 18 19 26 24 Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33973-CW-RFB / Construction of Water Pending Detention Structure (Chelia Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement II WDS), Mouza - Chelia , Bids One Envelope 01 06 18 19 26 24 ation Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33974-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 32,864.50 Signed (Mazarmura WDS), Mouza Bids One Envelope 01 06 18 19 26 24 - Mazarmura , Block - Kashipur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33976-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Khanna WDS), Mouza - Bids One Envelope 01 06 18 19 26 24 ation Anandapur, Block - Neturia, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33977-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- (Metyalsahar WDS), Mouza IBRD / 80900 Post Open - National 90,141.98 Signed Bids One Envelope 01 06 18 19 26 24 - Metyalsahar , Block - Raghunathpur, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33979-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 0.00 Implement (Mahatomara WDS 2), Bids One Envelope 01 06 18 19 26 24 ation Mouza - Mahatomara , Block - Jhalda 1, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 33319-CW-RFB / Construction of Water Detention Structure, Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Lakrahonda WDS-1, Mouza IBRD / 80900 Post Open - National 13,006.29 Signed Bids One Envelope 01 06 18 19 26 24 - Lakrahonda, Block- barabazar in the district of Purulia Under WBADMI Project. IN-DPMU - PURULIA- 33285-CW-RFB / Construction of Water Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- Detention Structure IBRD / 80900 Post Open - National 38,828.88 Signed Bids One Envelope 01 06 18 19 26 24 Chotosagen WDS 1, Mouza- Chotosagen, Block- Manbazar 1 in the district of Purulia IN-DPMU - PURULIA- 36114-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 42,530.40 Signed Dhelatbamu WDS-I, Mouza Bids One Envelope 10 10 22 19 26 24 -Dhelatbamu, Block- Barabazar under WBADMI Project for the year 2017- 18 IN-DPMU - PURULIA- 36132-CW-RFB / Construction of water detention structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 17,809.98 Signed Haludbani WDS-01, mouza- Bids One Envelope 10 10 22 19 26 24 Haludbani, Block-Bundwan under WBADMIP for the year 2017-18 IN-DPMU - PURULIA- 36134-CW-RFB / Construction of water detention structure Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 16,397.21 Signed Gokulnagar WDS-07, Bids One Envelope 10 10 22 19 26 24 mouza-Gokulnagar , Block- Barabazar under WBADMIP for the year 2017-18 IN-DPMU - PURULIA- 36171-CW-RFB / Construction of Water Detention structure Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-02- 2018-03- 2018-06- Gokulnagar WDS-09, IBRD / 80900 Post Open - National 10,498.06 Signed Bids One Envelope 24 24 05 19 26 24 Mouza- Gokulnagar, Block- Barabazar in Purulia District under WBADMIP for the year 2017-18. IN-DPMU - PURULIA- 36172-CW-RFB / Construction of Water Detention structure Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 13,738.87 Signed Jaragora WDS-07, Mouza- Bids One Envelope 24 24 05 19 26 24 Jaragora, Block- Manbazar- II in Purulia District under WBADMIP IN-DPMU - PURULIA- 36117-CW-RFB / Construction of Water Detention Structure Raidih Request for Single Stage - 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-06- IBRD / 80900 Post Open - National 35,794.18 Signed WDS-01, Mouza-Raidih, Bids One Envelope 10 10 22 19 26 24 Block-Barabazar under WBADMI project for ther yera 2017-18 IN-DPMU - PURULIA- 64446-CW-RFQ / Topographical survey of proposed reservoir/ Pending Request for Single Stage - 2018-06- 2018-07- 2018-08- irrigation tank/SFMIS/WDS IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 03 29 28 preparation of 34 Nos. ation DPRs of WDS in the district of Purulia und WBADMIP IN-DPMU - PURULIA- 76102-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 79,695.01 Signed Hullung WDS 2, Mouza - Bids One Envelope 12 14 29 31 04 05 Hullung, Block - Manbazar I, in Purulia District under WBADMI Project. IN-DPMU - PURULIA- 76103-CW-RFB / Construction of Water Detention Structure Bari Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 3, Mouza - Bari, IBRD / 80900 Post Open - National 30,940.66 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. Page 6 IN-DPMU - PURULIA- 76104-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Majhihira WDS 1, Mouza - IBRD / 80900 Post Open - National 105,796.50 Signed Bids One Envelope 12 14 29 31 04 05 Majhihira, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76106-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 4, Mouza - IBRD / 80900 Post Open - National 39,150.37 Signed Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76107-CW-RFB / Construction of Water Detention Structure Bamni WDS 1, Mouza - Chokya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 38,504.50 Signed Bhabanipur, Block - Bids One Envelope 12 14 29 31 04 05 Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76108-CW-RFB / Construction of Water Detention Structure Bari Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 2, Mouza - Bari, IBRD / 80900 Post Open - National 60,869.08 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76110-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Majhihira WDS 2, Mouza - IBRD / 80900 Post Open - National 48,247.16 Signed Bids One Envelope 12 14 29 31 04 05 Majhihira, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76111-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 5, Mouza - Tukya, IBRD / 80900 Post Open - National 61,570.82 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76112-CW-RFB / Construction of Water Detention Structure Bamni WDS 2, Mouza - Chokya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- IBRD / 80900 Post Open - National 24,877.00 Signed Bhabanipur, Block - Bids One Envelope 12 14 29 31 04 05 Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76113-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 2, Mouza - Tukya, IBRD / 80900 Post Open - National 65,225.73 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76114-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 2, Mouza - IBRD / 80900 Post Open - National 20,159.87 Signed Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76130-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Jangidiri WDS 12, Mouza IBRD / 80900 Post Open - National 25,350.54 Signed Bids One Envelope 12 14 29 31 04 05 - Jangidiri, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76134-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Baliguma WDS 5, Mouza - IBRD / 80900 Post Open - National 27,802.79 Signed Bids One Envelope 12 14 29 31 04 05 Baliguma, Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76135-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 3, Mouza - Tukya, IBRD / 80900 Post Open - National 45,250.33 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76136-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 1, Mouza - Tukya, IBRD / 80900 Post Open - National 82,986.06 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76137-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- Jangidiri WDS 10, Mouza IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 14 29 31 04 05 - Jangidiri, Block - ation Manbazar I, in Purulia District under WBADMI Project for the year 2018- 19. IN-DPMU - PURULIA- 76138-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 4, Mouza - Tukya, IBRD / 80900 Post Open - National 55,474.54 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 76139-CW-RFB / Construction of Water Detention Structure Kesya Request for Single Stage - 2018-09- 2018-09- 2018-10- 2018-12- 2019-02- 2019-05- WDS 1, Mouza - Kesya, IBRD / 80900 Post Open - National 25,815.13 Signed Bids One Envelope 12 14 29 31 04 05 Block - Manbazar I, in Purulia District under WBADMI Project for the year 2018-19. IN-DPMU - PURULIA- 79665-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- Budwan WDS 5, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 27 Budwan, Jl No-71, Plot No- ation 2102, Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79671-CW-RFB / Construction of Water Detention Structure Dhelatbamu WDS 2, Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 31,605.75 Signed Mouza- Dhelatbamu, Jl Bids One Envelope 12 12 20 22 26 27 No-57, Plot No- 14, Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79684-CW-RFB / Construction of Water Detention Structure Dhelatbamu WDS 5, Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 37,775.47 Signed Mouza- Dhelatbamu, Jl Bids One Envelope 12 12 20 22 26 27 No-57, Plot No- 4,5 Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79686-CW-RFB / Construction of Water Detention Structure Puriara WDS 2, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 103,612.71 Signed Dhelatbamu, Jl No-52, Plot Bids One Envelope 12 12 20 22 26 27 No- 4903, Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79692-CW-RFB / Construction of Water Detention Structure Sarisabahal WDS 3, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 37,643.59 Signed Sarisabahal, Jl No-28, Plot Bids One Envelope 12 12 20 22 26 27 No- 2352,2354 Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79694-CW-RFB / Construction of Water Detention Structure Gosaidihi WDS 6, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 33,249.07 Signed Gosaidihi, Jl No-56, Plot Bids One Envelope 12 12 20 22 26 27 No- 33,34 Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. Page 7 IN-DPMU - PURULIA- 79695-CW-RFB / Construction of Water Detention Structure Raidihi Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- WDS 3, Mouza- Raidihi, IBRD / 80900 Post Open - National 56,428.12 Signed Bids One Envelope 12 12 20 22 26 27 Jl No-55, Plot No- 1119, Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79701-CW-RFB / Construction of Water Detention Structure Raidihi WDS 5, Mouza- Raidihi, Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 44,086.47 Signed Jl No-55, Plot No- 152, Bids One Envelope 12 12 20 22 26 27 158 Block- Barabazar in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79704-CW-RFB / Construction of Water Detention Structure Dhabani WDS 1, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 37,873.52 Signed Dhabani, Jl No- 1, Plot Bids One Envelope 12 12 20 22 26 27 No- 1042, 1043 Block- Bundwan in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79706-CW-RFB / Construction of Water Detention Structure Saga Supurdihi WDS 1, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 35,355.06 Signed Saga, Jl No- 12, Plot No- Bids One Envelope 12 12 20 22 26 27 831, 833, 834 Block- Bundwan in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79708-CW-RFB / Construction of Water Detention Structure Saga Supurdihi WDS 3, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 35,720.40 Signed Saga, Jl No- 12, Plot No- Bids One Envelope 12 12 20 22 26 27 913, Block- Bundwan in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79715-CW-RFB / Construction of Water Detention Structure Baliguma WDS 3, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 34,560.36 Signed Baliguma, Jl No- 11, Plot Bids One Envelope 12 12 20 22 26 27 No- 797, Block- Manbazar- I in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79722-CW-RFB / Construction of Water Detention Structure Deoli Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- WDS, Mouza- Deoli, Jl No- IBRD / 80900 Post Open - National 108,345.42 Signed Bids One Envelope 12 12 20 22 26 27 84, Plot No- 4338, Block- Hura in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79726-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- Dhabani WDS, Mouza- IBRD / 80900 Post Open - National 60,556.68 Signed Bids One Envelope 12 12 20 22 26 27 Dhabani, Jl No- 105, Plot No- 301, 302 Block- Hura in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79728-CW-RFB / Construction of Water Detention Structure Kesabpur WDS, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 36,324.43 Signed Kesabpur, Jl No- 78, Plot Bids One Envelope 12 12 20 22 26 27 No- 2615, Block- Hura in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79729-CW-RFB / Construction of Water Detention Structure Motipur WDS, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 46,790.66 Signed Motipur, Jl No- 90, Plot Bids One Envelope 12 12 20 22 26 27 No- 3557, 3564 Block- Hura in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 79730-CW-RFB / Construction of Water Detention Structure Under Parashya WDS, Mouza- Request for Single Stage - 2018-10- 2018-10- 2018-11- 2019-01- 2019-02- 2019-05- IBRD / 80900 Post Open - National 0.00 Implement Parashya, Jl No- 116, Plot Bids One Envelope 12 12 20 22 26 27 ation No- 6098, Block- Hura in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 81586-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 1 in block- ation baghmundi, Jl No-107, plot no- 19 under A-I division for the year 2018-19. IN-DPMU - PURULIA- 81588-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 2 in block- ation baghmundi, Jl No-107, plot no- 75 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81590-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 3 in block- ation baghmundi, Jl No-107, plot no- 418 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81591-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 4 in block- ation baghmundi, Jl No-107, plot no- 748, 749 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81592-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 6 in block- ation baghmundi, Jl No-107, plot no- 744 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81594-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 8 in block- ation baghmundi, Jl No-107, plot no- 350 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81596-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 9 in block- ation baghmundi, Jl No-107, plot no- 328 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81597-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Andhra Alias Hatinada IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 WDS 10 in block- ation baghmundi, Jl No-107, plot no- 821 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81598-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Ajodhya WDS 3 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-108, plot no- 1176 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81599-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Ajodhya WDS 4 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-108, plot no- 1275 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81600-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Ajodhya WDS 5 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-108, plot no- 780, 781, 839 under A- I division for the year 2018-19 Page 8 IN-DPMU - PURULIA- 81601-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Ajodhya WDS 6 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-108, plot no- 1111 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81602-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Chhatni WDS 2 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-111, plot no- 78 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81604-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Chhatni WDS 4 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-111, plot no- 101 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81606-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Lahadungri WDS 1 in Bids One Envelope 15 15 17 18 25 23 ation block- baghmundi, Jl No- 112, plot no- 161 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81607-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Shilingda WDS 1 in block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 baghmundi, Jl No-113, plot ation no- 377, 378 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81610-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Shilingda WDS 2 in block- Bids One Envelope 15 15 17 18 25 23 ation baghmundi, Jl No-113, plot no- 147 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81611-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Kiribera WDS 1 in block- Bids One Envelope 15 15 17 18 25 23 ation Jhalda-I, Jl No- 24, plot no- 339-345 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81612-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Mahatomara WDS 1 in Bids One Envelope 15 15 17 18 25 23 ation block- Jhalda-I, Jl No- 23, plot no- 1218 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81613-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Jamadar WDS in block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 Santuri, Jl No- 100, plot ation no- 2775-2780 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81614-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- Simuldanga Bokdip WDS IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 15 15 17 18 25 23 in block- Santuri, Jl No- ation 89, plot no- 4926-4928, 4958 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81615-CW-RFB / Construction of Water Detention Structure Sija Pending WDS 6 in block- Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Raghunathpur-I & Bids One Envelope 15 15 17 18 25 23 ation Kashipur, Jl No- 199 &89 , plot no- 542,818,887,821 under A-I division for the year 2018-19 IN-DPMU - PURULIA- 81616-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Jorethol WDS in block- Bids One Envelope 15 15 17 18 25 23 ation Kashipur, Jl No- 154 , plot no- 1227 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 81617-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2018-11- 2018-11- 2018-12- 2019-02- 2019-03- 2019-06- IBRD / 80900 Post Open - National 0.00 Implement Kalhajhor WDS in block- Bids One Envelope 15 15 17 18 25 23 ation Kashipur, Jl No- 4, plot no- 204, 207 under A-I division for the year 2018- 19 IN-DPMU - PURULIA- 87454-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Dhabani Tetulchita WDS IBRD / 80900 Post Open - National 28,145.76 Signed Bids One Envelope 05 05 10 14 18 17 1, Mouza- Dhabani, Jl no- 205, Plot No- 626, 624, Block- Manbazar -II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87462-CW-RFB / Construction of Water Detention Structure Raidihi Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- WDS 6, Mouza- Raidihi, Jl IBRD / 80900 Post Open - National 47,160.68 Signed Bids One Envelope 05 05 10 14 18 17 no- 55, Plot No- 1232, Block- Barabazar under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87466-CW-RFB / Construction of Water Detention Structure Radhamohanpur WDS 7, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Mouza- Radhamohanpur, Jl IBRD / 80900 Post Open - National 83,115.30 Signed Bids One Envelope 05 05 10 14 18 17 no- 202, Plot No- 929,932,933,927,934 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87471-CW-RFB / Construction of Water Detention Structure Mukundapur WDS 1, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- IBRD / 80900 Post Open - National 49,038.51 Signed Mouza- Mukundapur, Jl no- Bids One Envelope 05 05 10 14 18 17 367, Plot No- 649,650,655,657 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87473-CW-RFB / Construction of Water Detention Structure Mukundapur WDS 2, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- IBRD / 80900 Post Open - National 41,949.69 Signed Mouza- Mukundapur, Jl no- Bids One Envelope 05 05 10 14 18 17 367, Plot No- 280, Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87474-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Dangardih WDS 1, Mouza- IBRD / 80900 Post Open - National 18,955.06 Signed Bids One Envelope 05 05 10 14 18 17 Dangardih, Jl no- 199, Plot No- 3877, Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87476-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Jambedia WDS 5, Mouza- IBRD / 80900 Post Open - National 28,518.56 Signed Bids One Envelope 05 05 10 14 18 17 Jambedia, Jl no- 208, Plot No- 941, Block- Manbazar- II under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 87477-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Budwan WDS 4, Mouza- IBRD / 80900 Post Open - National 28,665.96 Implement Bids One Envelope 05 05 10 14 18 17 Budwan, Jl no- 79, Plot ation No- 1084, Block- Manbazar- II under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 87478-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Dhabani WDS 3, Mouza- IBRD / 80900 Post Open - National 28,195.87 Signed Bids One Envelope 05 05 10 14 18 17 Dhabani, Jl no- 205, Plot No- 314,316,317 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87482-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- Dhadangar WDS 1, Mouza- IBRD / 80900 Post Open - National 29,035.39 Signed Bids One Envelope 05 05 10 14 18 17 Dhadangar, Jl no- 240, Plot No- 369, Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 Page 9 IN-DPMU - PURULIA- 87483-CW-RFB / Construction of Water Detention Structure Jambedia WDS 3, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- IBRD / 80900 Post Open - National 49,668.31 Signed Jambedia, Jl no- 208, Plot Bids One Envelope 05 05 10 14 18 17 No- 92,107,148 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87484-CW-RFB / Construction of Water Detention Structure Hensla Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- WDS 1, Mouza- Hensla, Jl IBRD / 80900 Post Open - National 29,662.90 Signed Bids One Envelope 05 05 10 14 18 17 no- 207, Plot No- 541, Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87485-CW-RFB / Construction of Water Detention Structure Nunyachatra WDS 1, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- IBRD / 80900 Post Open - National 30,610.91 Signed Mouza- Nunyachatra, Jl no- Bids One Envelope 05 05 10 14 18 17 211/261, Plot No- 78, Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 87486-CW-RFB / Construction of Water Detention Structure Hensla Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- WDS 4, Mouza- Hensla, Jl IBRD / 80900 Post Open - National 27,515.69 Signed Bids One Envelope 05 05 10 14 18 17 no- 207, Plot No- 67,73,174 Block- Manbazar- II under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 87487-CW-RFB / Construction of Water Detention Structure Hensla Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- WDS 5, Mouza- Hensla, Jl IBRD / 80900 Post Open - National 22,864.64 Signed Bids One Envelope 05 05 10 14 18 17 no- 207, Plot No- 1847,1848 Block- Manbazar- II under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 87488-CW-RFB / Construction of Water Detention Structure Jhariadihi WDS 1, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-07- IBRD / 80900 Post Open - National 35,377.27 Signed Jhariadihi, Jl no- 206, Plot Bids One Envelope 05 05 10 14 18 17 No- 59,60,61,62 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91821-CW-RFB / Construction of Check Dam at KUMRA JORE Under Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- (Anara CD), Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 24 30 03 08 06 Anara, JL No-128, Plot No- ation 2183,2184 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91824-CW-RFB / Construction of Check Dam at BERYADI Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- (Berayadi CD), Mouza- IBRD / 80900 Post Open - National 154,182.09 Signed Bids One Envelope 24 24 30 03 08 06 Berayadi, JL No-101, Plot No- 232 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91827-CW-RFB / Construction of Check Dam at CHITARI (Chitari Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- CD), Mouza- Chitari, JL IBRD / 80900 Post Open - National 126,447.77 Signed Bids One Envelope 24 24 30 03 08 06 No-20, Plot No- 13,14,15 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91828-CW-RFB / Construction of Check Dam at JABARRAH Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- (Jabarrah CD), Mouza- IBRD / 80900 Post Open - National 140,145.98 Signed Bids One Envelope 24 24 30 03 08 06 Jabarrah, JL No-119, Plot No- 4776,4775 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91829-CW-RFB / Construction of Check Dam at KUSHGORA- Under GOPINATHPUR (Kushgora Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement 1911 CD), Mouza- Bids One Envelope 24 24 30 03 08 06 ation Kushgora, JL No-136, Plot No- 1911 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91837-CW-RFB / Construction of Check Dam at NADIHA Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- SAMSAN GHAT (Nadiha IBRD / 80900 Post Open - National 125,144.99 Signed Bids One Envelope 24 24 30 03 08 06 CD), Mouza- Nadiha, JL No-16, Plot No- 1380 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91839-CW-RFB / Construction of Check Dam at RAMKRISHNAPUR Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 89,642.70 Signed (Ramkrishnapur CD), Bids One Envelope 24 24 30 03 08 06 Mouza- Ramkrishnapur, JL No-30, Plot No- 6,9 Block- Para in the district of Purulia under WBADMIP for the year 2018-19. IN-DPMU - PURULIA- 91855-CW-RFB / Construction of Water Detention Structure Tukya Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- WDS 7, Mouza- Tukya, Jl IBRD / 80900 Post Open - National 48,763.06 Signed Bids One Envelope 24 24 30 03 08 06 no- 6, Plot No- 1022,1023,1025 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91858-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Paisagora WDS 1, Mouza- IBRD / 80900 Post Open - National 17,280.69 Signed Bids One Envelope 24 24 30 03 08 06 Paisagora, Jl no- 113, Plot No- 261 Block- Manbazar - I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91860-CW-RFB / Construction of Water Detention Structure Majhihira WDS 6, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 51,934.91 Signed Majhihira, JL no- 22, Plot Bids One Envelope 24 24 30 03 08 06 No- 2984,2902 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91865-CW-RFB / Construction of Water Detention Structure Majhihira WDS 3, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 45,649.38 Signed Majhihira, JL no- 22, Plot Bids One Envelope 24 24 30 03 08 06 No- 1668,1669 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91869-CW-RFB / Construction of Water Detention Structure Kuda Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- WDS 3, Mouza- Kuda, JL IBRD / 80900 Post Open - National 39,688.97 Signed Bids One Envelope 24 24 30 03 08 06 no- 15, Plot No- 729,723 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91871-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Hullung WDS 5, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 24 24 30 03 08 06 Hullung, JL no- 29, Plot ation No- 1532 Block- Manbazar -I under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 91873-CW-RFB / Construction of Water Detention Structure Hullung WDS 4, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 31,185.75 Signed Hullung, JL no- 29, Plot Bids One Envelope 24 24 30 03 08 06 No- 1169,1170,1171,1172,612 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91876-CW-RFB / Construction of Water Detention Structure Bagalddhora WDS 2, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 37,929.13 Signed Mouza- Bagalddhora, JL Bids One Envelope 24 24 30 03 08 06 no- 105, Plot No- 1312 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91877-CW-RFB / Construction of Water Detention Structure Bagalddhora WDS 1, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 40,476.61 Signed Mouza- Bagalddhora, JL Bids One Envelope 24 24 30 03 08 06 no- 105, Plot No- 1210 Block- Manbazar -I under WBADMIP Purulia for the year 2018-2019 Page 10 IN-DPMU - PURULIA- 91878-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Tilaboni WDS 2, Mouza- IBRD / 80900 Post Open - National 39,321.56 Signed Bids One Envelope 24 24 30 03 08 06 Tilaboni, JL no- 153, Plot No- 349,352 Block- Barabazar under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91880-CW-RFB / Construction of Water Detention Structure Rupapatiya WDS 4, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 45,052.50 Signed Rupapatiya, JL no- 87, Bids One Envelope 24 24 30 03 08 06 Plot No- 2712,2772,2773 Block- Barabazar under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91890-CW-RFB / Construction of Water Detention Structure Pukurkata WDS 1, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 28,421.79 Signed Pukurkata, JL no- 52, Plot Bids One Envelope 24 24 30 03 08 06 No- 210,211,212,208,209,207 Block- Bundwan under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91893-CW-RFB / Construction of Water Detention Structure Under Natundihi WDS 1, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement Natundihi, JL no- 57, Plot Bids One Envelope 24 24 30 03 08 06 ation No- 127,128,131,132,133 Block- Bundwan under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91895-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Kuilapal WDS 1, Mouza- IBRD / 80900 Post Open - National 49,411.28 Signed Bids One Envelope 24 24 30 03 08 06 Kuilapal, JL no- 59, Plot No- 926,1024 Block- Bundwan under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 91897-CW-RFB / Construction of Water Detention Structure Patapahari WDS 1, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 23,567.84 Signed Patapahari, JL no- 192, Bids One Envelope 24 24 30 03 08 06 Plot No- 1460,1486 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91898-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Susunia WDS 4, Mouza- IBRD / 80900 Post Open - National 39,832.51 Signed Bids One Envelope 24 24 30 03 08 06 Susunia, JL no- 198, Plot No- 69-71-1524-1514-1517 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91899-CW-RFB / Construction of Water Detention Structure Chandanpur WDS 2, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 27,576.63 Signed Mouza- Chandanpur, JL no- Bids One Envelope 24 24 30 03 08 06 204, Plot No- 1486 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91901-CW-RFB / Construction of Water Detention Structure Chandanpur WDS 4, Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 16,643.03 Signed Mouza- Chandanpur, JL no- Bids One Envelope 24 24 30 03 08 06 204, Plot No- 1339,1341 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91902-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- Goyalapara WDS 1, Mouza- IBRD / 80900 Post Open - National 17,984.41 Signed Bids One Envelope 24 24 30 03 08 06 Goyalapara, JL no- 200, Plot No- 475 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 91903-CW-RFB / Construction of Water Detention Structure Under Goyalapara WDS 2, Mouza- Request for Single Stage - 2018-12- 2018-12- 2019-01- 2019-04- 2019-05- 2019-08- IBRD / 80900 Post Open - National 0.00 Implement Goyalapara, JL no- 200, Bids One Envelope 24 24 30 03 08 06 ation Plot No- 508-514,535-540 Block- Manbazar-II under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93673-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kulgora WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Kulgora, JL no- 42, Plot ation No- 1788, 3646, 3637, 3635 Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93674-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 8, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- ation 85, Plot No- 1336, Block- Hura under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 93675-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 21, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 8,022.52 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 949, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93676-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 10, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 5,634.21 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 640, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93677-CW-RFB / Construction of Water Detention Structure Piyalsole WDS 1, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 40,285.69 Signed Piyalsole, JL no- 186, Plot Bids One Envelope 18 18 26 30 04 02 No- 942,943, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93678-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 5, IBRD / 80900 Post Open - National 19,754.27 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- 85, Plot No- 2746, Block- Hura under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 93679-CW-RFB / Construction of Water Detention Structure Nadiha Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- WDS 1, Mouza- Nadiha, IBRD / 80900 Post Open - National 79,101.29 Signed Bids One Envelope 18 18 26 30 04 02 JL no- 44, Plot No- 1605, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93680-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 7, IBRD / 80900 Post Open - National 97,575.80 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- 85, Plot No- 1550, Block- Hura under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 93681-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 4, IBRD / 80900 Post Open - National 42,965.07 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- 85, Plot No- 3016, Block- Hura under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 93682-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 1, IBRD / 80900 Post Open - National 56,758.51 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- 85, Plot No- 1109, Block- Hura under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 93683-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Chakalta WDS 2, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Chakalta, JL no- 76, Plot ation No- 1445,1447, Block- Hura under WBADMIP Purulia for the year 2018- 2019 Page 11 IN-DPMU - PURULIA- 93684-CW-RFB / Construction of Water Detention Structure Tetla Under WDS 1, Mouza- Tetla, JL Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement no- 172, Plot No- 514, Bids One Envelope 18 18 26 30 04 02 ation 515, 509, 508, 511, 512, 606 Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93685-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Makarkendi WDS 6, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Mouza- Makarkendi, JL no- ation 48, Plot No- 1387, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93686-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 11, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 7,816.19 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 2473, 2492, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93687-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 18, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 39,577.22 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 865, 771, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93688-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Makarkendi WDS 24, IBRD / 80900 Post Open - National 25,703.38 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Makarkendi, JL no- 48, Plot No- 1914, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93689-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 19, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 7,084.63 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 855, 856, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93690-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Makarkendi WDS 9, IBRD / 80900 Post Open - National 10,104.57 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Makarkendi, JL no- 48, Plot No- 1250, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93692-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Makarkendi WDS 16, IBRD / 80900 Post Open - National 8,331.96 Signed Bids One Envelope 18 18 26 30 04 02 Mouza- Makarkendi, JL no- 48, Plot No- 2328, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93694-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Makarkendi WDS 3, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Mouza- Makarkendi, JL no- ation 48, Plot No- 125, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93695-CW-RFB / Construction of Water Detention Structure Chirudi WDS 1, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 40,768.43 Signed Chirudi, JL no- 180, Plot Bids One Envelope 18 18 26 30 04 02 No- 795, 800, 855, 858, 785, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93698-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Fufundi WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Fufundi, JL no- 87, Plot ation No- 183, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93700-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Kusumjoria WDS 3, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 18 18 26 30 04 02 Mouza- Kusumjoria, JL no- ation 85, Plot No- 425, 426, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93704-CW-RFB / Construction of Water Detention Structure Pialasole WDS 1, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 64,584.37 Signed Pialasole, JL no- 66, Plot Bids One Envelope 18 18 26 30 04 02 No- 786, 787, 788, 789, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93705-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Fufundi WDS 2, Mouza- IBRD / 80900 Post Open - National 86,846.67 Signed Bids One Envelope 18 18 26 30 04 02 Fufundi, JL no- 87, Plot No- 2235, 2236, 2237, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93707-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Motipur WDS 2, Mouza- IBRD / 80900 Post Open - National 42,024.95 Signed Bids One Envelope 18 18 26 30 04 02 Motipur, JL no- 90, Plot No- 3883, Block- Hura under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93713-CW-RFB / Construction of Water Detention Structure Golkidi Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- WDS 1, Mouza- Golkidi, IBRD / 80900 Post Open - National 22,539.97 Signed Bids One Envelope 18 18 26 30 04 02 JL no- 148, Plot No- 691, 692, 714, 716, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93716-CW-RFB / Construction of Water Detention Structure Makarkendi WDS 4, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 8,250.47 Signed Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 48, Plot No- 1921, 1922, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93718-CW-RFB / Construction of Water Detention Structure Ichadi WDS 1, Mouza- Ichadi, JL Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 38,940.02 Signed no- 173, Plot No- 52, 53, Bids One Envelope 18 18 26 30 04 02 54, 55, 56, 63, 65, 68, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93721-CW-RFB / Construction of Water Detention Structure Under Makarkendi WDS 12, Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Mouza- Makarkendi, JL no- Bids One Envelope 18 18 26 30 04 02 ation 48, Plot No- 560, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93724-CW-RFB / Construction of Water Detention Structure Ichadi WDS 2, Mouza- Ichadi, JL Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- no- 173, Plot No- Block- IBRD / 80900 Post Open - National 73,900.00 Signed Bids One Envelope 18 18 26 30 04 02 753, 754, 755, 758, 759, 760, 761, 762, 763, 764, 766, 767, Block- Manbazar- I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 93734-CW-RFB / Construction of Water Detention Structure Request for Single Stage - 2019-01- 2019-01- 2019-02- 2019-04- 2019-06- 2019-09- Chepua WDS 1, Mouza- IBRD / 80900 Post Open - National 50,007.61 Signed Bids One Envelope 18 18 26 30 04 02 Chepua, JL no- 157, Plot No- 3090, 3091, 3075, Block- Manbazar-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95059-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Piskapahari WDS 5, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Mouza- Piskapahari, Jl no- ation 91, Plot No- 2564, Block- Arsha under WBADMIP Purulia for the year 2018- 2019 Page 12 IN-DPMU - PURULIA- 95061-CW-RFB / Construction of Water Detention Structure Patura Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- WDS 2, Mouza- Patuara, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Jl no- 87, Plot No- 6240, ation Block- Arsha under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95065-CW-RFB / Construction of Water Detention Structure Under Chamardag WDS 1, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Chamardag, Jl no- 38, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 450, 504-509, 511-513, 1065, 1153 Block- Jhalda-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95068-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Chowpad WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Chowpad, Jl no- 44, Plot ation No- 1225, Block- Jhalda-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95069-CW-RFB / Construction of Water Detention Structure Under Kerwari WDS 1, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Kerwari, Jl no- 37, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 1558, 1560, 1562, 1564 Block- Jhalda-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95072-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Piskapahari WDS 1, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Mouza- Piskapahari, Jl no- ation 91, Plot No- 1797, Block- Arsha under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95074-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Chowpad WDS 2, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Chowpad, Jl no- 44, Plot ation No- 22, Block- Jhalda-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95075-CW-RFB / Construction of Water Detention Structure Paparu Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- WDS 1, Mouza- Paparu, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 no- 36, Plot No- 507 Block- ation Jhalda-I under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95076-CW-RFB / Construction of Water Detention Structure Buribir Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- WDS 3, Mouza- Buribir, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 no- 41, Plot No- 6217 ation Block- Jhalda-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95077-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Kumirdiha WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Kumirdiha, Jl no- 72, Plot ation No- 1322, Block- Arsha under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95078-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Patuara WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Patuara, Jl no- 87, Plot ation No- 1151-1156, 1165, Block- Arsha under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95079-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- Piskapahari WDS 4, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 Mouza- Piskapahari, Jl no- ation 91, Plot No- 527, 529, Block- Arsha under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95080-CW-RFB / Construction of Water Detention Structure Buribir Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- WDS 1, Mouza- Buribir, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 no- 41, Plot No- 883 Block- ation Jhalda-I under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95378-CW-RFB / Construction of Water Detention Structure Lakhy Under WDS, Mouza- Goyalbaria, Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Jl no- 100, Plot No- 2903, Bids One Envelope 22 22 02 04 08 06 ation 2904, 2905, 2906, Block- Santuri under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95383-CW-RFB / Construction of Water Detention Structure Under Murudunka WDS, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Salberya, Jl no- 89, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 453, 548, 552, 759, Block- Santuri under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95388-CW-RFB / Construction of Water Detention Structure Under Kendthol WDS, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Kenthol, Jl no- 97, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 06, 12, 13, 14, 15, Block- Santuri under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95393-CW-RFB / Construction of Water Detention Structure Under Namodanga WDS, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Manihara, Jl no- 107, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 3297, 3298, 3299, 3304 & 4290, Block- Kashipur under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95396-CW-RFB / Construction of Water Detention Structure Dabar Under Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- WDS, Mouza- Dabar, Jl no- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 22 22 02 04 08 06 207, Plot No- 862, Block- ation Raghunathpur-I under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95398-CW-RFB / Construction of Water Detention Structure Sona Under WDS, Mouza- Goyalbaria, Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Jl no- 100, Plot No- 2991, Bids One Envelope 22 22 02 04 08 06 ation 2992, 2993, 3042, Block- Santuri under WBADMIP Purulia for the year 2018- 2019 IN-DPMU - PURULIA- 95400-CW-RFB / Construction of Water Detention Structure Under Pochagora WDS, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Pochagora, Jl no- 70, Plot Bids One Envelope 22 22 02 04 08 06 ation No- 3429, 3432 & 3431, Block- Kashipur under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 95403-CW-RFB / Construction of Water Detention Structure Under Jagannathdih WDS, Mouza- Request for Single Stage - 2019-01- 2019-01- 2019-03- 2019-05- 2019-06- 2019-10- IBRD / 80900 Post Open - National 0.00 Implement Jagannathdih, Jl no- 134, Bids One Envelope 22 22 02 04 08 06 ation Plot No- 1670-1679 & 1683, Block- Kashipur under WBADMIP Purulia for the year 2018-2019 IN-DPMU - PURULIA- 96338-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Makarkendi WDS 23 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Manbazar-I, Mouza- ation Makarkendi, Jl No-48, Plot no- 2607 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96339-CW-RFB / Construction of Water Detention Structure Under Jabarrah WDS 1 in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Hura, Mouza- Jabarrah, Jl Bids One Envelope 05 05 09 11 15 13 ation No-33, Plot no- 2646-2647- 2648-2650-2651 under WBADMIP for the year 2018-19 Page 13 IN-DPMU - PURULIA- 96345-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kusumjuria WDS 2 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Hura, Mouza- ation Kusumjuria, Jl No-85, Plot no- 180-181 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96351-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Parasibona WDS 1 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Hura, Mouza- ation Parasibona, Jl No- 6, Plot no- 63 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96355-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Baliguma WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Manbazar-I, Mouza- ation Baliguma, Jl No- 11, Plot no- 502-503 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96359-CW-RFB / Construction of Water Detention Structure Under Bhunrasol WDS 1 in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Manbazar-I, Mouza- Bids One Envelope 05 05 09 11 15 13 ation Bhunarasole, Jl No- 114, Plot no- 56-72-73 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96364-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kalaboni WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Manbazar-I, Mouza- ation Kalabani, Jl No- 8, Plot no- 811-864-865-866 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96367-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kaparra WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Manbazar-I, Mouza- ation Kaparra, Jl No- 18, Plot no- 813-814 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96369-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kaparra WDS 2 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Manbazar-I, Mouza- ation Kaparra, Jl No- 18, Plot no- 1449-1451 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96376-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kaparra WDS 3 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Manbazar-I, Mouza- ation Kaparra, Jl No- 18, Plot no- 1383-1384 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96381-CW-RFB / Construction of Water Detention Structure Under Radhamadhabpur WDS 1 Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement in Block- Manbazar-I, Bids One Envelope 05 05 09 11 15 13 ation Mouza- Radhamohanpur, Jl No- 156, Plot no- 716-714- 715 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96382-CW-RFB / Construction of Water Detention Structure Anara Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 1 in Block- Para, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Mouza- Anara, Jl No- 128, ation Plot no- 690-691-675-673 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96384-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kashiberia WDS 1 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Para, Mouza- ation Kashiberia, Jl No- 85, Plot no- 97 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96387-CW-RFB / Construction of Water Detention Structure Palma Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 1 in Block- Para, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Mouza- Palma, Jl No- 131, ation Plot no- 3074-3065-3066 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96390-CW-RFB / Construction of Water Detention Structure Palma Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 2 in Block- Para, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Mouza- Palma, Jl No- 131, ation Plot no- 3053 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96394-CW-RFB / Construction of Water Detention Structure Palma Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 4 in Block- Para, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Mouza- Palma, Jl No- 131, ation Plot no- 2830-2831 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96397-CW-RFB / Construction of Water Detention Structure Choto Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Urma WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- Chota ation Urma, Jl No- 12, Plot no- 454-455 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96400-CW-RFB / Construction of Water Detention Structure Under Fatepur WDS 2 in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Balarampur, Mouza- Bids One Envelope 05 05 09 11 15 13 ation Fatepur, Jl No- 66, Plot no- 323, 297-302, 294, 293 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96402-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Fatepur WDS 3 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Fatepur, Jl No- 66, Plot no- 482-467-481-480 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96403-CW-RFB / Construction of Water Detention Structure Under Fatepur WDS 5 in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Balarampur, Mouza- Bids One Envelope 05 05 09 11 15 13 ation Fatepur, Jl No- 66, Plot no- 1208, 1206, 1185-1195 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96405-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Jugidih Kashidih WDS 3 IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 in Block- Balarampur, ation Mouza- Jugidih Kashidih, Jl No- 18, Plot no- 562 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96406-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Jugidih Kashidih WDS 4 IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 in Block- Balarampur, ation Mouza- Jugidih Kashidih, Jl No- 18, Plot no- 728 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96409-CW-RFB / Construction of Water Detention Structure Under Jugidih Kashidih WDS 6 Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement in Block- Balarampur, Bids One Envelope 05 05 09 11 15 13 ation Mouza- Jugidih Kashidih, Jl No- 18, Plot no- 1963, 1442, 1953, 1215, 1955 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96412-CW-RFB / Construction of Water Detention Structure Kana Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- Kana, ation Jl No- 25, Plot no- 421- 427 under WBADMIP for the year 2018-19 Page 14 IN-DPMU - PURULIA- 96414-CW-RFB / Construction of Water Detention Structure Karma Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 7 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Karma, Jl No- 20, Plot no- 1561, 1562 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96416-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Kerowa WDS 2 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Kerowa, Jl No- 17, Plot no- 2024 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96424-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Latadaha WDS 2 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Latadaha, Jl No- 13, Plot no- 1381 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96426-CW-RFB / Construction of Water Detention Structure Mirmi Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Mirmi, Jl No- 4, Plot no- 401, 436 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96429-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Ruchap WDS 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Balarampur, Mouza- ation Ruchap, Jl No- 84, Plot no- 638, 333, 634 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96432-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Serenghatu WDS 4 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Balarampur, Mouza- ation Serenghatu, Jl No- 5, Plot no- 36 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96434-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Serenghatu WDS 6 in IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Block- Balarampur, Mouza- ation Serenghatu, Jl No- 5, Plot no- 954 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96437-CW-RFB / Construction of Check dam over Amlatora Jore at Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Amlatora in Block- Hura, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Mouza- Amlatora, JL No- ation 57, Plot no- 219,220 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96440-CW-RFB / Construction of Check Under Dam at Hatibari in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Hura, Mouza- Hatibari, JL Bids One Envelope 05 05 09 11 15 13 ation No- 45, Plot no- 753 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96443-CW-RFB / Construction of Check Under Dam at Kaliabasa in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Hura, Mouza- Kaliabasa, Bids One Envelope 05 05 09 11 15 13 ation JL No- 98, Plot no- 3855 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96447-CW-RFB / Construction of Check Under Dam at Kusumjora in Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Block- Hura, Mouza- Bids One Envelope 05 05 09 11 15 13 ation Kusumjora, JL No- 85, Plot no- 2633 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96449-CW-RFB / Construction of Check Dam over Patloi Jore at Pending Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Madandih CD 1 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Hura, Mouza- Madandih, ation JL No- 27, Plot no- 1012,1013 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96450-CW-RFB / Construction of Check Dam over Patloi jore at Under Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- Madandih CD 2 in Block- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 09 11 15 13 Hura, Mouza- Madandih, ation Jl No- 27, Plot no- 359,360 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 96452-CW-RFB / Construction of Check Under Dam at Parashya in Block- Request for Single Stage - 2019-02- 2019-02- 2019-03- 2019-05- 2019-06- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement Hura, Mouza- Parashya, Jl Bids One Envelope 05 05 09 11 15 13 ation No- 116, Plot no- 3517 under WBADMIP for the year 2018-19 IN-DPMU - PURULIA- 98629-CW-RFQ / Excavation of Chargali Under HAPPA-II and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Chargali, JL No-73, Plot - 393, Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98632-CW-RFQ / Excavation of Chargali Under HAPPA-III and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Chargali, JL No-73, Plot - 419, Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98635-CW-RFQ / Excavation of Chargali Under HAPPA-IV and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Chargali, JL No-73, Plot - 21,62 Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98637-CW-RFQ / Excavation of Chargali Under HAPPA-VI and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Chargali, JL No-73, Plot - 882,986 Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98638-CW-RFQ / Excavation of Shiuli Under HAPPA-I and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Shiuli, JL No-75, Plot - 2901 Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98641-CW-RFQ / Excavation of Shiuli Under HAPPA-II and installation Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement of sign board at Mouza- Quotations One Envelope 04 27 14 ation Shiuli, JL No-75, Plot - 1324 Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98643-CW-RFQ / FOR Excavation of Shiuli HAPPA-III and installation Under Request for Single Stage - 2019-02- 2019-02- 2019-03- of sign board at Mouza- IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 04 27 14 Shiuli, JL No-75, Plot - ation 2886,2892 Block-Purulia-II under WBADMIP Purulia District during 2018-2019. IN-DPMU - PURULIA- 98644-CW-RFQ / TOPOGRAPHICAL SURVEY OF PROPOSED RESERVOIR/ IRRIGATION Under TANKS / SFMIS / WDS, Request for Single Stage - 2019-02- 2019-02- 2019-03- IBRD / 80900 Post Open - National 0.00 Implement PREPARATION OF DPRS Quotations One Envelope 04 27 14 ation OF 34 Nos. WATER DETENTION STRUCTURE (WDS)IN THE DISTRICT OF PURULIA DURING THE YEAR 2018-2019 IN-DPMU - PURULIA- 102222-CW-RFQ / Horticulture plantation at Under Plot No.-430, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block Baghmundi under ASS Horticulture activity under WBADMIP. Page 15 IN-DPMU - PURULIA- 102224-CW-RFQ / Horticulture plantation at Under Plot No.-461,464,466,467, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Hesadi, JL No.-75, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102225-CW-RFQ / Horticulture plantation at Under Plot No.-830,833, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102227-CW-RFQ / Horticulture plantation at Under Plot No.-1087, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102228-CW-RFQ / Horticulture plantation at Under Plot No.-57, 58, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102230-CW-RFQ / Horticulture plantation at Under Plot No.-150, 151,156,159, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Hesadi, Jl No.-75, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102262-CW-RFQ / Horticulture plantation at Under Plot No.-76,77,97, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102271-CW-RFQ / Horticulture plantation at Under Plot No.-102, 103, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102274-CW-RFQ / Horticulture plantation at Under Plot No.-163, 165, 166, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Hesadi, Jl No.-75, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102276-CW-RFQ / Horticulture plantation at Under Plot No.-1161, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hesadi, Jl No.-75, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102279-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 222,215,216,217,218, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Bhuigora, Jl No.-80, GP- ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102282-CW-RFQ / Horticulture plantation at Under Plot No.-299,300, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Bhuigora, Jl No.-80, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102285-CW-RFQ / Horticulture plantation at Plot No.- Under 288,289,290,284,286,287,259, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Bhuigora, Jl No.-80, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102287-CW-RFQ / Horticulture plantation at Under Plot No.-364, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Bhuigora, Jl No.-80, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102290-CW-RFQ / Horticulture plantation at Under Plot No.-869,871, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Bhuigora, Jl No.-80, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102295-CW-RFQ / Horticulture plantation at Under Plot No.-119,118, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Kuchrirekha, Jl No.-109, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102298-CW-RFQ / Horticulture plantation at Plot No.- Under 324,329,323,325,326,327,330, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 341,333,222, Mouza- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Jl No.-108, GP- Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102302-CW-RFQ / Horticulture plantation at Under Plot No.-156,157,158, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Ranga, Jl No.-106, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102304-CW-RFQ / Horticulture plantation at Under Plot No.-246,266,267, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Ranga, Jl No.-106, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102307-CW-RFQ / Horticulture plantation at Under Plot No.-344,310, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Ranga, Jl No.-106, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102309-CW-RFQ / Horticulture plantation at Under Plot No.-491, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Hatinada, Jl No.-107, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102311-CW-RFQ / Horticulture plantation at Under Plot No.-50,46,124, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Baghmundi, Jl No.-105, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102312-CW-RFQ / Horticulture plantation at Under Plot No.-2270,2271, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Saharjuri, Jl No.-76, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102314-CW-RFQ / Horticulture plantation at Under Plot No.-949, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Saharjuri, Jl No.-76, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102320-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 656,678,672,688,687, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Chhatni, Jl No.-111, GP- ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. Page 16 IN-DPMU - PURULIA- 102322-CW-RFQ / Horticulture plantation at Under Plot No.-611, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Teliabhasa, Jl No.-81, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102324-CW-RFQ / Horticulture plantation at Under Plot No.-170,205, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Teliabhasa, Jl No.-81, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102327-CW-RFQ / Horticulture plantation at Plot No.- Under 404,405,406,413,414,419,120, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 408,410,407,409,411, Mouza- Bids One Envelope 05 05 16 16 20 17 ation Teliabhasa, Jl No.-81, GP- Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102336-CW-RFQ / Horticulture plantation at Under Plot No.-385,387,400, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Teliabhasa, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 81, GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102337-CW-RFQ / Horticulture plantation at Under Plot No.-686,687, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Kalha, Jl No.-79, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102341-CW-RFQ / Horticulture plantation at Under Plot No.-113, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Silingda, Jl No.-113, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102342-CW-RFQ / Horticulture plantation at Under Plot No.-2307, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Saharjura, Jl No.-76, GP- Bids One Envelope 05 05 16 16 20 17 ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102344-CW-RFQ / Horticulture plantation at Under Plot No.-134, Mouza-Alkusi, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Jl No.-84, GP-Ajodhya, Bids One Envelope 05 05 16 16 20 17 ation Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102346-CW-RFQ / Horticulture plantation at Under Plot No.-6738, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Birgram, Jl No.-59, GP- Bids One Envelope 05 05 16 16 20 17 ation Birgram, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102349-CW-RFQ / Horticulture plantation at Under Plot No.-849, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Chakaichalong, Jl No.-31, Bids One Envelope 05 05 16 16 20 17 ation GP-Serengdi, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102398-CW-RFQ / Horticulture plantation at Plot No.- 1038,1642,1643, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Deoli, Jl No.-19, GP- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Tunturi Suisa, Block- ation Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102399-CW-RFQ / Horticulture plantation at Plot No.- Under 1057,914,927,1052,1055, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza- Rangamati, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 1, GP-Tunturi Suisa, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102400-CW-RFQ / Horticulture plantation at Under Plot No.- 745,762, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Dava, Jl No.-61, GP-Sindri, Bids One Envelope 05 05 16 16 20 17 ation Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102401-CW-RFQ / Horticulture plantation at Under Plot No.- 4796,4804, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Karru Koredi, Jl No.-53, Bids One Envelope 05 05 16 16 20 17 ation GP-Sindri, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102403-CW-RFQ / Horticulture plantation at Under Plot No.-2641,2642,2644, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Torang, Jl No.-62, Bids One Envelope 05 05 16 16 20 17 ation GP-Sindri, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102406-CW-RFQ / Horticulture plantation at Plot No.-109, 110, 111, Under 112, 113, 114, 115, 116, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 117, 118, 106, Mouza- Bids One Envelope 05 05 16 16 20 17 ation Sonkupi Niltanr, Jl No.- 127, GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102408-CW-RFQ / Horticulture plantation at Under Plot No.-31,22,18,23,2,8, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Banshidih, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 144, GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102409-CW-RFQ / Horticulture plantation at Under Plot No.- 80,81, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Panra, Jl No.-145, GP- Bids One Envelope 05 05 16 16 20 17 ation Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102410-CW-RFQ / Horticulture plantation at Under Plot No.-86,1012,1021,1018, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Panra, Jl No.-145, Bids One Envelope 05 05 16 16 20 17 ation GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102413-CW-RFQ / Horticulture plantation at Under Plot No.-426,203,204, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Khududih, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 140, GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102414-CW-RFQ / Horticulture plantation at Under Plot No.-288,291,292,295, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Chirugora, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 142, GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102416-CW-RFQ / Horticulture plantation at Under Plot No.-61,60,197, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Srirampur, Jl No.-139, GP- Bids One Envelope 05 05 16 16 20 17 ation Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102418-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 149,148,349,350,347,339, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Mouza-Kanrda, Jl No.-137, ation GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102420-CW-RFQ / Horticulture plantation at Under Plot No.-521,522,523, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Kanrda, Jl No.-137, Bids One Envelope 05 05 16 16 20 17 ation GP-Matha, Block- Baghmundi under ASS Horticulture activity under WBADMIP. Page 17 IN-DPMU - PURULIA- 102421-CW-RFQ / Horticulture plantation at Under Plot No.-329,186,266, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Hesadi, Jl No.-75, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102422-CW-RFQ / Horticulture plantation at Under Plot No.-501,888,722, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Bhuigora, Jl No.-80, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102423-CW-RFQ / Horticulture plantation at Plot No.-76,86,61,71,88,344, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Bongada, Jl No.-77, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 GP-Ajodhya, Block- ation Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102425-CW-RFQ / Horticulture plantation at Plot No.- Under 190,191,192,135,137,151, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Bongada, Jl No.-77, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102426-CW-RFQ / Horticulture plantation at Plot No.-907,875,193,409, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Saharjuri, Jl No.-76, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 GP-Ajodhya, Block- ation Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102428-CW-RFQ / Horticulture plantation at Plot No.- Under 620,32,68,69,63,106,294,295, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 299, Mouza-Sonahara, Jl Bids One Envelope 05 05 16 16 20 17 ation No.-78, GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102429-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 12,13,50,25,26,27,28, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Kusumtikri, Jl No.-74, GP- ation Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102430-CW-RFQ / Horticulture plantation at Plot No.- Under 111,112,115,108,103,469,124, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 125,127, Mouza- Bids One Envelope 05 05 16 16 20 17 ation Puniasassan, Jl No.-110, GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102431-CW-RFQ / Horticulture plantation at Plot No.- Under 815,469,691,693,695,696,697, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Chhatni, Jl No.-111, Bids One Envelope 05 05 16 16 20 17 ation GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102433-CW-RFQ / Horticulture plantation at Plot No.-813,666,669, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Kalha(Kherghutu), IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Jl No.-79, GP-Ajodhya, ation Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102434-CW-RFQ / Horticulture plantation at Plot No.-106,181,151, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Kalha(Kherghutu), IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Jl No.-79, GP-Ajodhya, ation Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102435-CW-RFQ / Horticulture plantation at Plot No.-48,69,228,1196, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Silingda, Jl No.-113, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 GP-Ajodhya, Block- ation Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102436-CW-RFQ / Horticulture plantation at Under Plot No.-629,628,322, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Simulbera, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 119, GP-Ajodhya, Block- Baghmundi under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102438-CW-RFQ / Horticulture plantation at Under Plot No.-121,122,123,130, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Gurur, Jl No.-5, GP- Bids One Envelope 05 05 16 16 20 17 ation Gurur, Block- Bundwan under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102440-CW-RFQ / Horticulture plantation at Under Plot No.-1607,1604,1605, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Parbaid, Jl No.-4, Bids One Envelope 05 05 16 16 20 17 ation GP-Gurur, Block- Bundwan under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102441-CW-RFQ / Horticulture plantation at Pending Plot No.-468,467,561, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Gokulnagar, Jl No.- Bids One Envelope 05 05 16 16 20 17 ation 103, GP-Berada, Block- Barabazar under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102513-CW-RFQ / Horticulture plantation at Plot No.-1209, 1210, Mouza- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Sarisabahal, Jl No.-28, GP- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Dhelatbamu, Block- ation Barabazar under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102516-CW-RFQ / Horticulture plantation at Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Plot No.-764, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Tuima, Jl No.-92, Block- ation Barabazar under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102517-CW-RFQ / Horticulture plantation at Under Plot No.-3614, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Kaipara, Jl No.-66, GP- Bids One Envelope 05 05 16 16 20 17 ation Banjora, Block- Barabazar under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102518-CW-RFQ / Horticulture plantation at Under Plot No.-1145, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Raidih, Jl No.-55, GP- Bids One Envelope 05 05 16 16 20 17 ation Dhelatbamu, Block- Barabazar under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102521-CW-RFQ / Horticulture plantation at Under Plot No.-427,418,419, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Mouza-Chakya, Jl No.-27, Bids One Envelope 05 05 16 16 20 17 ation GP-Bamni Majhihira, Block- Manbazar-1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102523-CW-RFQ / Horticulture plantation at Plot No.- 1,57,81,103,116,232,80,55,63, Under 93,117,240,231,64,94,104,105 Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement ,106,161,66,95,96, Bids One Envelope 05 05 16 16 20 17 ation 107,114,125,143,182, Mouza- Bhalubasa, Jl No.-160, GP- Bhalubasa, Block- Manbazar-1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102524-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 1058,1059,1074,1061, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Mouza-Nipena, Jl No.-159, ation GP-Bhalubasa, Block- Manbazar-1 under ASS Horticulture activity under WBADMIP. Page 18 IN-DPMU - PURULIA- 102527-CW-RFQ / Horticulture plantation at Under Plot No.-942,943, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Piyalsole, Jl No.-186, GP- Bids One Envelope 05 05 16 16 20 17 ation Bisri, Block- Manbazar-1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102528-CW-RFQ / Horticulture plantation at Plot No.-1,716, Mouza- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Radhamadhabpur, Jl No.- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 156, GP-Bhalubasa, Block- ation Manbazar-1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102530-CW-RFQ / Horticulture plantation at Under Plot No.-135, Mouza-Ankro, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Jl No.-271, GP-Ankro Boro Bids One Envelope 05 05 16 16 20 17 ation Kadam, Block- Manbazar-2 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102534-CW-RFQ / Horticulture plantation at Plot No.- Under 2135,2134,2136,2137,2138,21 Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement 40,2141, Mouza-Kultar, Jl Bids One Envelope 05 05 16 16 20 17 ation No.-193, GP-Dighi, Block- Manbazar-2 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102536-CW-RFQ / Horticulture plantation at Pending Plot No.-79, Mouza-Amtore, Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Jl No.-137, GP-Natundihi, Bids One Envelope 05 05 16 16 20 17 ation Block- Raghunathpur 1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102539-CW-RFQ / Horticulture plantation at Plot No.-727,728,729,730, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Namobathan, Jl No.- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 144, GP-Natundihi, Block- ation Raghunathpur 1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102541-CW-RFQ / Horticulture plantation at Plot No.-779,762,780, Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- Mouza-Namobathan, Jl No.- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 144, GP-Natundihi, Block- ation Raghunathpur 1 under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102543-CW-RFQ / Horticulture plantation at Under Plot No.-2990,1161, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Goalberia, Jl No.-100, GP- Bids One Envelope 05 05 16 16 20 17 ation Garshika, Block- Santuri under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102545-CW-RFQ / Horticulture plantation at Under Plot No.-1640, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Chairabari, Jl No.-64, GP- Bids One Envelope 05 05 16 16 20 17 ation Murardih, Block- Santuri under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102547-CW-RFQ / Horticulture plantation at Plot No.- Under Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 3091,3092,3093,3094, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 05 05 16 16 20 17 Mouza-Chitra, Jl No.-49, ation GP-Udaypurjoinagar, Block- Para under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102548-CW-RFQ / Horticulture plantation at Under Plot No.-3286, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Tentulda, Jl No.-11, GP- Bids One Envelope 05 05 16 16 20 17 ation Bahra, Block- Para under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102551-CW-RFQ / Horticulture plantation at Under Plot No.-37,38,57, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Reshagora, Jl No.-51, GP- Bids One Envelope 05 05 16 16 20 17 ation Bahra, Block- Para under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 102552-CW-RFQ / Horticulture plantation at Under Plot No.-901,902, Mouza- Request for Single Stage - 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 80900 Post Open - National 0.00 Implement Kataboni, Jl No.-14, GP- Bids One Envelope 05 05 16 16 20 17 ation Bahra, Block- Para under ASS Horticulture activity under WBADMIP. IN-DPMU - PURULIA- 114936-CW-RFB / Orchard Plantation at Plot No.- Pending 327,555,356,357, Mouza- Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- IBRD / 80900 Post Open - National 0.00 Implement Khairabahal, Jl No.-98, Bids One Envelope 28 28 27 09 23 19 ation Block- Purulia-II under ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114937-CW-RFB / Orchard Plantation at Plot No.-309, Pending Mouza-Mamurjore, Jl No.- Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- IBRD / 80900 Post Open - National 0.00 Implement 124, Block- Purulia-II Bids One Envelope 28 28 27 09 23 19 ation under ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114939-CW-RFB / Orchard Plantation at Plot No.-294, Pending Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- Mouza-Modhagora, Jl No.- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 28 28 27 09 23 19 99, Block- Purulia-II under ation ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114940-CW-RFB / Orchard Plantation at Plot No.-305, Pending Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- Mouza-Modhagora, Jl No.- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 28 28 27 09 23 19 99, Block- Purulia-II under ation ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114941-CW-RFB / Orchard Plantation at Plot No.-913, Pending Mouza-Mamurjore, Jl No.- Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- IBRD / 80900 Post Open - National 0.00 Implement 124, Block- Purulia-II Bids One Envelope 28 28 27 09 23 19 ation under ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114942-CW-RFB / Orchard Plantation at Plot No.- Pending 513,514, Mouza- Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- IBRD / 80900 Post Open - National 0.00 Implement Mamurjore, Jl No.-124, Bids One Envelope 28 28 27 09 23 19 ation Block- Purulia-II under ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 114943-CW-RFB / Orchard Plantation at Plot No.-308, Pending 310, 314, Mouza- Request for Single Stage - 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2020-01- IBRD / 80900 Post Open - National 0.00 Implement Mamurjore, Jl No.-124, Bids One Envelope 28 28 27 09 23 19 ation Block- Purulia-II under ASS Horticulture activity under WBADMIP (AM Divison) IN-DPMU - PURULIA- 121728-CW-RFB / Construction of Water Detention Structure Under Kumardi WDS 1, Mouza- Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Kumardi, Jl No- 158, Bids One Envelope 12 12 20 22 26 24 ation Plot no- 1075,1076,1071,104,107,108, Block –Manbazar-I in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121731-CW-RFB / Construction of Water Detention Structure Kultar Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 2, Mouza- Kultar, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Jl No- 193, Plot no- ation 2425,2126 Block –Manbazar-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121736-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Chakya WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Chakya, Jl No- 29, Plot ation no- 829 Block –Manbazar-I in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121738-CW-RFB / Construction of Water Detention Structure Parbaid WDS 1, Mouza- Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Parbaid, Jl No- 4, Plot IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 no- ation 1517,1518,1519,1520,1522,15 23,1524,1527,1631 Block –Bundwan in the district of Purulia under WBADMIP Page 19 IN-DPMU - PURULIA- 121739-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Kashidi WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Kashidi, Jl No- 160, Plot ation no- 81,86,87,88 Block –Manbazar I in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121740-CW-RFB / Construction of Water Detention Structure Tuima Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 1, Mouza- Tuima, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Jl No- 92, Plot no- 764 ation Block –Barabazar in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121741-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Kaipara WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Kaipara, Jl No- 66, Plot ation no- 3614 Block –Barabazar in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121743-CW-RFB / Construction of Water Detention Structure Under Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Parbaid WDS 2, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Parbaid, Jl No- 4, Plot ation no- 130 Block –Bundwan in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121744-CW-RFB / Construction of Water Detention Structure Ankro Under WDS 1, Mouza- Ankro, Jl Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement No- 271/221, Plot no- Bids One Envelope 12 12 20 22 26 24 ation 6493,6494,6495,6496,6497,64 99 Block –Manbazar II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121746-CW-RFB / Construction of Water Detention Structure Simni Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 3, Mouza- Simni, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 175, Plot no- 142,144 ation Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121748-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Khatanga WDS 3, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Khatanga, Jl No- 191, ation Plot no- 226,227 Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121752-CW-RFB / Construction of Water Detention Structure Simni Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 5, Mouza- Simni, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 175, Plot no- 144 ation Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121753-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Khatanga WDS 2, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Khatanga, Jl No- 191, ation Plot no- 332 Block –Jhalda- II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121756-CW-RFB / Construction of Water Detention Structure Simni Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 6, Mouza- Simni, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 175, Plot no- 1726 ation Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121760-CW-RFB / Construction of Water Detention Structure Simni Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 4, Mouza- Simni, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 175, Plot no- 165,166 ation Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121764-CW-RFB / Construction of Water Detention Structure Pending Mamaru WDS 1, Mouza- Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Mamaru, Jl No- 194, Plot Bids One Envelope 12 12 20 22 26 24 ation no- 1228,1239,1516 Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121765-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Belamu 2, Mouza- Belamu, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Jl No- 187, Plot no- 25-31 ation Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121766-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Khatanga WDS 1, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Khatanga, Jl No- 191, ation Plot no- 1882,1883 Block –Jhalda-II in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121768-CW-RFB / Construction of Water Detention Structure Kalha Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 4, Mouza- Kalha, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 79, Plot no- 268 Block ation –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121769-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Kumirdiha WDS 2, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Mouza- Kumirdiha, Jl No- ation 72, Plot no- 1923,1924 Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121771-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Saharjuri WDS 7, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Saharjuri , Jl No- 76, ation Plot no- 910 Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121772-CW-RFB / Construction of Water Pending Detention Structure Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Patuara WDS 7, Mouza- Bids One Envelope 12 12 20 22 26 24 ation Patuara, Jl No- 87, Plot no- 3266 Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121773-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Patuara WDS 11, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Patuara, Jl No- 87, Plot ation no- 3024,3085 Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121777-CW-RFB / Construction of Patuara Pending Happa 7, Mouza- Patuara, Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Jl No- 87, Plot no- 2575 Bids One Envelope 12 12 20 22 26 24 ation Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121778-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Saharjuri WDS 4, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Saharjuri , Jl No- 76, ation Plot no- 36 Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121779-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Saharjuri WDS 2, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Saharjuri , Jl No- 76, ation Plot no- 2161 Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121780-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Saharjuri WDS 5, Mouza- IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Saharjuri , Jl No- 76, ation Plot no- 490 Block –Baghmundi in the district of Purulia under WBADMIP Page 20 IN-DPMU - PURULIA- 121788-CW-RFB / Construction of Water Detention Structure Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- Kumirdiha WDS 4, IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 Mouza- Kumirdiha, Jl No- ation 72, Plot no- 343,344,264,345 Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121952-CW-RFB / Construction of Water Detention Structure Kalha Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 2, Mouza- Kalha, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 79, Plot no- 182, 252, ation Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121954-CW-RFB / Construction of Water Detention Structure Pending Saharjuri WDS 3, Mouza- Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Saharjuri , Jl No- 76, Bids One Envelope 12 12 20 22 26 24 ation Plot no- 463, 464, 465 Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121956-CW-RFB / Construction of Water Detention Structure Kalha Pending Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- WDS 1, Mouza- Kalha, Jl IBRD / 80900 Post Open - National 0.00 Implement Bids One Envelope 12 12 20 22 26 24 No- 79, Plot no- 644, 645, ation Block –Baghmundi in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121957-CW-RFB / Construction of Patuara Pending Happa 10, Mouza- Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Patuara, Jl No- 87, Plot Bids One Envelope 12 12 20 22 26 24 ation no- 3323 Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 121958-CW-RFB / Construction of Patuara Pending Happa 9, Mouza- Patuara, Request for Single Stage - 2019-07- 2019-07- 2019-08- 2019-10- 2019-11- 2020-02- IBRD / 80900 Post Open - National 0.00 Implement Jl No- 87, Plot no- 2593 Bids One Envelope 12 12 20 22 26 24 ation Block –Arsha in the district of Purulia under WBADMIP IN-DPMU - PURULIA- 123163-CW-RFQ / PROCUREMENT OF TOPOGRAPHICAL SURVEY OF PROPOSED RESERVOIR/ IRRIGATION TANKS / SFMIS / WDS, Pending Request for Single Stage - 2019-07- 2019-08- 2019-09- PREPARATION OF DPRS IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 25 17 01 OF 18 Nos. WATER ation DETENTION STRUCTURE (WDS) IN THE BLOCK- BALARAMPUR IN DISTRICT OF PURULIA DURING THE YEAR 2019- 2020 IN-DPMU - PURULIA- 123164-CW-RFQ / PROCUREMENT OF TOPOGRAPHICAL SURVEY OF PROPOSED RESERVOIR/ IRRIGATION Pending TANKS / SFMIS / WDS, Request for Single Stage - 2019-07- 2019-08- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement PREPARATION OF DPRS Quotations One Envelope 25 17 01 ation OF 11 Nos. WATER DETENTION STRUCTURE (WDS) IN THE BLOCK- JHALDA-II IN DISTRICT OF PURULIA DURING THE YEAR 2019-2020 IN-DPMU - PURULIA- 123165-CW-RFQ / PROCUREMENT OF TOPOGRAPHICAL SURVEY OF PROPOSED RESERVOIR/ IRRIGATION Pending TANKS / SFMIS / WDS, Request for Single Stage - 2019-07- 2019-08- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement PREPARATION OF DPRS Quotations One Envelope 25 17 01 ation OF 26 Nos. WATER DETENTION STRUCTURE (WDS) IN THE BLOCK- BAGHMUNDI IN DISTRICT OF PURULIA DURING THE YEAR 2019- 2020 GOODS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPMU - PURULIA- 26005-GO-RFQ / Supply of Inputs to the FMPG (Fisheries Mass Production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 4,764.88 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Bara Bundh Mouza- Swarupdi in manbazar-I Block. IN-DPMU - PURULIA- 26006-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 4,359.52 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Durlab Bundh, Block- Barabazar IN-DPMU - PURULIA- 26008-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- Group) for the purpose of IBRD / 80900 Post Open - National 4,031.62 Signed Quotations One Envelope 30 15 22 fisheries mass production at Hesaldi Bundh, Nitujara Bundh & Salgambara Bundh, Block- Baghmundi IN-DPMU - PURULIA- 26010-GO-RFQ / Supply of Inputs to the FMPG (Fisheries mass production Request for Single Stage - 2017-08- 2017-09- 2017-09- Group) for the purpose of IBRD / 80900 Post Open - National 3,995.83 Signed Quotations One Envelope 30 15 22 fisheries mass production at Sasandhara Bundh, Bandarjabra Bundh & Jore Bundh, Block- Baghmundi IN-DPMU - PURULIA- 26015-GO-RFQ / Supply of Inputs to the women beneficiaries of FIG Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 3,388.10 Signed (Fisheries Interest Group) Quotations One Envelope 30 15 22 for the purpose of cage culture activity in project area. IN-DPMU - PURULIA- 26000-GO-RFQ / Supply of Inputs to the FMPG (Fisheries Mass Production Request for Single Stage - 2017-08- 2017-09- 2017-09- IBRD / 80900 Post Open - National 1,607.10 Signed Group) for the purpose of Quotations One Envelope 30 15 22 fisheries mass production at Thakur Sayer Bundh in Kashipur Block. IN-DPMU - PURULIA- 38232-GO-RFQ / Supply of Request for Single Stage - 2018-02- 2018-03- 2018-04- Computer, Printer, UPS at IBRD / 80900 Post Open - National 3,643.07 Signed Quotations One Envelope 21 29 06 DPMU, Purulia under WBADMI Project. IN-DPMU - PURULIA- 71241-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Gosai Bundh, Natun Bundh & Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,309.87 Signed Chaitan Sayer Bundh and Quotations One Envelope 05 21 28 Supply of Inputs to the FIG for fisheries demonstration in Anti Bundh & Choto Ghorer Bundh in Purulia District. IN-DPMU - PURULIA- 71244-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,350.14 Signed mass production at Mahato Quotations One Envelope 05 21 28 Bundh, Gora Bundh & Chanda Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71245-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Mudihar Bundh & Bara Pukur Bundh in Purulia District. IN-DPMU - PURULIA- 71248-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Majhpahari Bara Jore Bundh in Purulia District. IN-DPMU - PURULIA- 71250-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 4,604.84 Signed Quotations One Envelope 05 21 28 mass production at Thakur Bundh & Nayan Bundh in Purulia District. IN-DPMU - PURULIA- 71251-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 2,838.84 Signed Quotations One Envelope 05 21 28 mass production at Vanga Bundh & Majhi Bundh in Purulia District. Page 21 IN-DPMU - PURULIA- 71262-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,950.52 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Dumur Bundh, in Purulia District. IN-DPMU - PURULIA- 71263-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at Burir ation Bundh, Choin Bundh in Purulia District. IN-DPMU - PURULIA- 71264-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at IBRD / 80900 Post Open - National 4,788.11 Signed Quotations One Envelope 05 21 28 Matkam Goria , Balichara Bundh,Gur Bundh,Adhar Bundh,Upar Bundh & Tumba Dari in Purulia District. IN-DPMU - PURULIA- 71269-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 6,778.19 Signed Quotations One Envelope 05 21 28 mass production at Hatisura Bundh& Bastardi Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71272-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at Sutabai ation Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71275-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Bhatuikend Bara Bundh, in Purulia District. IN-DPMU - PURULIA- 71278-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Tatultola Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71280-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,221.82 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Hir Bundh in Purulia District. IN-DPMU - PURULIA- 71281-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,831.32 Signed Ramapada Goria, Kendu Quotations One Envelope 05 21 28 Bundh, Tuyu Bundh, Tudu Bundh, Gokulnagar WDS-1 & Gokulnagar WDS-7 in Purulia District. IN-DPMU - PURULIA- 71285-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at Uppar IBRD / 80900 Post Open - National 4,597.69 Signed Quotations One Envelope 05 21 28 Bundh, Malidih WDS-2 Bundh, Mahato Bundh & Laya Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71290-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- Haludbani pukur Bundh, IBRD / 80900 Post Open - National 6,510.48 Signed Quotations One Envelope 05 21 28 Haridi WDS-3 Bundh, Haridihi WDS-8, Jambediya WDS-1, Jaragora WDS-1, Murgadih WDS-1 & Namo Bundh in Purulia District. IN-DPMU - PURULIA- 71292-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 2,246.93 Signed Purdaha WDS-3 Bundh, Quotations One Envelope 05 21 28 Purdaha WDS-1, Radhamohanpur WDS-3 Bundh & Radhamohanpur WDS-6 Bundh in Purulia District. IN-DPMU - PURULIA- 71295-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,884.82 Signed mass production at Quotations One Envelope 05 21 28 Jambediya WDS-2 Bundh & Raghunathpur WDS-1 Bundh in Purulia District. IN-DPMU - PURULIA- 71299-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,860.48 Signed Susunia WDS-3 Bundh, Quotations One Envelope 05 21 28 Susunia WDS-1 Bundh, Bhakta Bundh, Natun Bundh, Naran Bundh & Natun Bundh in Purulia District. IN-DPMU - PURULIA- 71302-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at Lal IBRD / 80900 Post Open - National 5,322.64 Signed Quotations One Envelope 05 21 28 Bundh and Supply of Inputs to the FIG for fisheries demonstration in Pendra Bundh in Purulia District. IN-DPMU - PURULIA- 71305-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Request for Single Stage - 2018-08- 2018-08- 2018-08- Kalfulia, Dhiridadi , IBRD / 80900 Post Open - National 2,087.91 Signed Quotations One Envelope 05 21 28 Karkacha, Turgu Dhara & Bara Kocha Bundh and Supply of Inputs to the FIG for fisheries demonstration in Pakar Bundh in Purulia District. IN-DPMU - PURULIA- 71308-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 1,880.41 Signed Quotations One Envelope 05 21 28 mass production at Shambu Goria Bundh & Sayer Bundh in Purulia District. IN-DPMU - PURULIA- 71310-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Lipsi, Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,300.32 Signed Chatra Gorai, Ralidarha, Quotations One Envelope 05 21 28 Surajharna, Adal, Shimul Goria, Darir, Mahalghutu & Bhanga Hir Bundh in Purulia District. IN-DPMU - PURULIA- 71313-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- mass production at IBRD / 80900 Post Open - National 4,100.68 Signed Quotations One Envelope 05 21 28 Aharbera, Jamnala, Dhaniram, Porogora, Shimuljhara & Kud Goria Bundh in Purulia District. IN-DPMU - PURULIA- 71319-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 4,089.51 Signed Quotations One Envelope 05 21 28 mass production at Chagalkandi Bundh in Purulia District. IN-DPMU - PURULIA- 71323-GO-RFQ / Supply of Inputs to the FIG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,608.92 Signed fisheries demonstration in Quotations One Envelope 05 21 28 Kamarhir Bundh in Purulia District. IN-DPMU - PURULIA- 71324-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 5,117.74 Signed Quotations One Envelope 05 21 28 mass production at Chaitan Goria Bundh & Diwan Bundh in Purulia District. IN-DPMU - PURULIA- 71326-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries mass production at Hura Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,572.57 Signed Bundh and Supply of Quotations One Envelope 05 21 28 Inputs to the FIG for fisheries demonstration in Bamun Bundh in Purulia District. IN-DPMU - PURULIA- 71329-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Ahar Bundh in Purulia District. IN-DPMU - PURULIA- 71332-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 3,991.43 Signed Quotations One Envelope 05 21 28 mass production at Dumdumi Bundh in Purulia District. Page 22 IN-DPMU - PURULIA- 71334-GO-RFQ / Supply of Inputs to the FMPG for Pending Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 05 21 28 mass production at ation Galinda Bundh & Saheb Bundh in Purulia District. IN-DPMU - PURULIA- 71337-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- the purpose of fisheries IBRD / 80900 Post Open - National 5,678.93 Signed Quotations One Envelope 05 21 28 mass production at Tubku Bundh & Natun Bundh in Purulia District. IN-DPMU - PURULIA- 71340-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Sayer Bundh in Purulia District. IN-DPMU - PURULIA- 71341-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 5,128.34 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Choika Bundh in Purulia District. IN-DPMU - PURULIA- 71343-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 3,079.84 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Mahul Bundh in Purulia District. IN-DPMU - PURULIA- 71345-GO-RFQ / Supply of Inputs to the FMPG for the purpose of fisheries Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 4,537.52 Signed mass production at Jagat Quotations One Envelope 05 21 28 Goria Bundh, Bhutlaha Bundh & Jamuna Bundh in Purulia District. IN-DPMU - PURULIA- 71348-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,766.64 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Bara Bundh in Purulia District. IN-DPMU - PURULIA- 71350-GO-RFQ / Supply of Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 6,316.39 Signed the purpose of fisheries Quotations One Envelope 05 21 28 mass production at Asur Bundh in Purulia District. IN-DPMU - PURULIA- 71353-GO-RFQ / Supply of Pending Inputs to the FMPG for Request for Single Stage - 2018-08- 2018-08- 2018-08- IBRD / 80900 Post Open - National 0.00 Implement the purpose of fisheries Quotations One Envelope 05 21 28 ation mass production at Dubai Bundh in Purulia District. IN-DPMU - PURULIA- 71380-GO-RFQ / Supply of Inputs to the women members of Self Help Request for Single Stage - 2018-08- 2018-08- 2018-08- Group (SHG)/ Water users IBRD / 80900 Post Open - National 4,646.52 Signed Quotations One Envelope 05 21 28 Association (WUA) for the purpose of spawn to fingerling production in various Districts of Purulia. IN-DPMU - PURULIA- 93755-GO-RFQ / Supply of supplementary fish feed & Under Request for Single Stage - 2019-01- 2019-02- 2019-02- prophylactics for mass IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 20 05 12 production of carp fish in ation the district of Purulia during year 2018-19. IN-DPMU - PURULIA- 95084-GO-RFQ / Supply of materials for workshop of CW & CSP for enhancing Under Request for Single Stage - 2019-01- 2019-02- 2019-02- knowledge in overall IBRD / 80900 Post Open - National 0.00 Implement Quotations One Envelope 23 08 15 functioning of WUA & ation related works at Purulia, WBADMIP during the year of 2018-19. IN-DPMU - PURULIA- 123166-GO-RFQ / Supply of Air-Conditioner and A3 Pending Printer for the Office of Request for Single Stage - 2019-07- 2019-08- 2019-09- IBRD / 80900 Post Open - National 0.00 Implement the Assistant Engineer (A- Quotations One Envelope 25 17 01 ation I), Purulia-II (A-I) Subdivision under DPMU Purulia, WBADMIP NON CONSULTING SERVICES Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference Actual Short List and Request for Opening of Combined Loan / Market Contract Type Process Expression of Evaluation of Contract No. / Description Component Review Type Method Amount Terms of Reference Draft Request for Proposals as Technical Proposals Evaluation Report Signed Contract Credit No. Approach Status Interest Notice Technical Proposal Completion (US$) Proposals Issued / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Actual Planned Actual Planned Actual Contract INDIVIDUAL CONSULTANTS Page 23