Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2012]: Revision 6 of Updated Procurement Plan, December 2016] 2. Date of General Procurement Notice: April 13, 2012 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of procurement Substantial risk Mandatory Prior Methods review thresholds thresholds (US$ (US$ millions) millions) Works (including turnkey, supply & ICB ≥ 5 10 installation of plant and equipment, NCB < 5 and PPP) RfQ < 0.2 Goods, information technology and ICB ≥ 1 2 non-consulting services NCB < 1 RfQ<0.1 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project IDA-H7270 November 2015 issued by Bagre Growth 4. Any Other Special Procurement Arrangements: not applicable 5. Summary of the Procurement Packages 1 2 3 4 5 6 7 Ref. Description Estimate Packages Dome Review Commen No. d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million February 21st, 2018 (yes/n o) Summary of the NCB 3.4 6 No Post (Works) Summary of the NCB 1.7 6 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Substantial risk Mandatory Prior Methods review thresholds thresholds (US$ (US$ millions) millions) Consultants: firms CQ< 0.3 1 Consultants: individuals No threshold 0.3 2. Short list comprising entirely of national consultants: Short list of consulting services, estimated to cost less than $ 200,000 or for Engineering & Construction supervision ≦ $400.000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. No. Description of Estimate Packages Review Comments Assignment d by Bank Cost (Prior / US$ Post) million Summary of number of 3 12 All post contracts that will be let review under QCBS - FBS - LCS Summary of number of 0.6 6 Post CQS contracts that will be let under other methods February 21st, 2018 PROCUREMENT Burkina Faso : Burkina Faso - Bagre Growth Pole Project PLAN General Information Country: Burkina Faso Bank’s Approval Date of the Original Procurement Plan: 2017-10-16 2019-08-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P119662 GPN Date: Project Name: Burkina Faso - Bagre Growth Pole Project Loan / Credit No: IDA / H7270, IDA / 61840 Executing Agency(ies): Bagre Growth Pole WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26257-CW-RFB / Construction de parcs de Development of Critical Single Stage - One En attente IDA / H7270 A posteriori Appel d'offres Open - National 1,414,000.00 0.00 2017-12-10 2017-12-15 2018-01-14 2018-01-24 2018-02-07 2018-07-07 vaccination, magasins, d'aires Infrastructure Envelope d'exécution de séchages (lots 1,2,3 et 4) BF-PPCB-26309-CW-DIR / Passation de Development of Critical En attente Extension du réseau IDA / H7270 A posteriori marché de gré à Direct 100,000.00 0.00 2017-09-30 2017-10-05 2017-11-09 2018-05-08 Infrastructure d'exécution électrique à Bagré gré BF-PPCB-26313-CW-RFB / Réalisation des travaux de Development of Critical Single Stage - One En attente mise en place d'un système IDA / H7270 A posteriori Appel d'offres Open - National 370,000.00 0.00 2017-11-15 2017-11-20 2017-12-20 2017-12-30 2018-01-20 2018-06-19 Infrastructure Envelope d'exécution de protection du canal primaire contre les noyades BF-PPCB-26185-CW-RFB / Entretien des infrastructures Development of Critical Single Stage - One En cours IDA / H7270 A posteriori Appel d'offres Open - National 360,000.00 0.00 2017-06-01 2017-06-06 2017-07-06 2017-07-20 2017-08-10 2018-08-05 hydrauliques et de Infrastructure Envelope d'exécution désenclavement BF-PPCB-26295-CW-RFB / travaux d'aménagement des Development of Critical Single Stage - One En attente IDA / H7270 A posteriori Appel d'offres Open - National 500,000.00 0.00 2017-10-15 2017-10-20 2017-11-19 2017-11-29 2017-12-20 2018-04-19 zones pastorales de Infrastructure Envelope d'exécution Doubégué et de Tcherbo BF-PPCB-50696-CW-RFQ / Improvement of institutional Travaux de reboisement et capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 160,000.00 0.00 2018-05-06 2018-07-01 2018-09-29 de protection des berges du management and investment Envelope d'exécution Nakanbé climate in the Project Area BF-PPCB-26294-CW-RFB / Travaux d’assainissement collectif de la Cité de Bagrépôle et de construction Development of Critical Single Stage - One IDA / H7270 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2018-02-15 2018-02-20 2018-03-22 2018-04-01 2018-04-22 2018-08-20 de deux dalots entre la cité Infrastructure Envelope ouvrière et le Centre écotouristique (CET) de Bagré BF-PPCB-26266-CW-RFB / construction d’infrastructures Development of Critical Single Stage - One socio-économique économiques IDA / H7270 A posteriori Appel d'offres Open - National 520,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-10-30 2017-11-09 2017-11-30 2018-03-30 Infrastructure Envelope au profit de toutes les PAP (lots 1  et 2) BF-PPCB-50694-CW-RFB / Improvement of institutional Construction de latrines au capacity for better zone Single Stage - One IDA / H7270 A posteriori Appel d'offres Open - National 240,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-04-19 2018-05-03 2018-05-24 2018-09-21 profit des Personnes affectés management and investment Envelope par le projet climate in the Project Area Page 1 BF-PPCB-86969-CW-RFB / Development of Critical Open - Single Stage - One En cours Travaux de construction de IDA / 61840 A priori Appel d'offres 21,000,000.00 0.00 2019-03-25 2019-03-30 2019-05-14 2019-06-13 2019-07-04 2020-09-26 Infrastructure International Envelope d'exécution routes bitumées BF-PPCB-86976-CW-RFB / Development of Critical Open - Single Stage - One En cours Travaux de construction de IDA / 61840 A posteriori Appel d'offres 9,400,000.00 0.00 2019-03-25 2019-03-30 2019-05-14 2019-05-29 2019-06-19 2020-12-10 Infrastructure International Envelope d'exécution routes en terres et pistes BF-PPCB-87287-CW-RFB / Development of Critical Single Stage - One En attente Extension du réseau IDA / 61840 A posteriori Appel d'offres Open - National 3,520,000.00 0.00 2019-09-30 2019-10-05 2019-11-04 2019-11-11 2019-11-28 2020-11-22 Infrastructure Envelope d'exécution électrique BF-PPCB-105136-CW-RFB / entretien des ouvrages Development of Critical Single Stage - One En attente IDA / 61840 A posteriori Appel d'offres Open - National 300,000.00 0.00 2019-03-25 2019-03-30 2019-04-29 2019-05-06 2019-05-20 2020-05-19 hydraulique et de Infrastructure Envelope d'exécution désenclavement BF-PPCB-105148-CW-RFQ / construction de clôture Improvement of institutional grillagée pour la réalisation capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 40,000.00 0.00 2019-04-06 2019-05-03 2019-07-02 pour les travaux de management and investment Envelope d'exécution reboisement et de protection climate in the Project Area des berge du Nakanbé GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26119-GO-RFB / Acquisition d'engrais pour Development of Critical Single Stage - One En cours l'appui des PAP à la mise IDA / H7270 Services and direct support A posteriori Appel d'offres Open - National 540,000.00 0.00 2017-10-15 2017-10-20 2017-11-19 2017-11-29 2017-12-27 2018-02-25 Envelope d'exécution en exploitation des terres to smallholders and SMEs aménagées BF-PPCB-26437-GO-RFQ / Improvement of institutional Acquisition de mobiliers capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 62,000.00 0.00 2017-03-06 2017-04-17 2017-06-16 de bureau et d’armoires de management and investment Envelope d'exécution rangements climate in the Project Area Improvement of institutional BF-PPCB-26421-GO-RFQ / capacity for better zone Single Stage - One Fourniture de service d’accès IDA / H7270 A posteriori Demande de prix Limited 70,000.00 57,062.41 Signé 2017-03-20 2017-05-15 2017-06-14 management and investment Envelope internet climate in the Project Area BF-PPCB-26436-GO-RFB / Improvement of institutional Acquisition de matières capacity for better zone Single Stage - One En cours premières pour la production IDA / H7270 A posteriori Appel d'offres Open - National 98,790.00 0.00 2017-03-10 2017-03-15 2017-04-14 2017-04-28 2017-06-02 2017-11-29 management and investment Envelope d'exécution piscicole au profit du CEP climate in the Project Area de Bagrépôle BF-PPCB-26435-GO-RFB / Improvement of institutional Production et diffusion capacity for better zone Single Stage - One En attente d'outils de communication IDA / H7270 A posteriori Appel d'offres Open - National 164,000.00 0.00 2017-09-01 2017-09-06 2017-10-06 2017-10-13 2017-11-03 2018-01-02 management and investment Envelope d'exécution et d’édition de documents au climate in the Project Area profit du CNPPC BF-PPCB-26282-GO-RFQ / Improvement of institutional Acquisition de Botteleuses capacity for better zone Single Stage - One En cours IDA / H7270 A posteriori Demande de prix Limited 48,000.00 0.00 2017-09-10 2017-10-16 2017-12-15 pour l’appui aux PAP management and investment Envelope d'exécution éleveurs climate in the Project Area Page 2 BF-PPCB-26265-GO-RFB / Improvement of institutional Acquisition d'équipements de capacity for better zone Single Stage - One En attente production et de IDA / H7270 A posteriori Appel d'offres Open - National 600,000.00 0.00 2017-09-15 2017-09-20 2017-10-20 2017-10-30 2017-11-20 2018-01-19 management and investment Envelope d'exécution transformation au profit des climate in the Project Area PAP BF-PPCB-26270-GO-RFQ / Improvement of institutional fourniture de services capacity for better zone Single Stage - One d'assurance santé au profit IDA / H7270 A posteriori Demande de prix Limited 98,000.00 84,780.64 Signé 2017-06-06 2017-07-18 2018-07-13 management and investment Envelope du personnel et de véhicules climate in the Project Area automobiles de Bagrépôle BF-PPCB-26307-GO-RFB / Improvement of institutional Acquisition 04 véhicules 4X4 capacity for better zone Single Stage - One En cours IDA / H7270 A posteriori Appel d'offres Open - National 264,000.00 0.00 2017-03-01 2017-03-06 2017-04-05 2017-04-19 2017-05-10 2017-07-09 Pick up double cabine et management and investment Envelope d'exécution une station WAGON climate in the Project Area Improvement of institutional BF-PPCB-26296-GO-DIR / Passation de capacity for better zone En cours Mise à jour du logiciel IDA / H7270 A posteriori marché de gré à Direct 80,000.00 0.00 2017-08-15 2017-08-20 2017-09-24 2017-11-23 management and investment d'exécution TOM2PRO gré climate in the Project Area BF-PPCB-26284-GO-RFQ / Acquisition de produits Improvement of institutional vétérinaires ,de sous-produits capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 54,000.00 0.00 2017-09-25 2017-10-31 2017-12-30 agro industriels (SPAI) et de management and investment Envelope d'exécution Semences fourragères pour climate in the Project Area l’appui aux PAP éleveurs Improvement of institutional BF-PPCB-26297-GO-RFB / capacity for better zone Single Stage - One En cours Acquisition de copieurs et IDA / H7270 A posteriori Appel d'offres Open - National 80,000.00 0.00 2016-10-01 2016-10-06 2016-11-05 2016-11-15 2016-12-06 2017-02-04 management and investment Envelope d'exécution d’équipements informatiques climate in the Project Area BF-PPCB-26353-GO-RFQ / Improvement of institutional Acquisition de fournitures de capacity for better zone Single Stage - One En cours bureau, produits d’entretien, IDA / H7270 A posteriori Demande de prix Limited 80,000.00 0.00 2017-03-06 2017-04-10 2017-10-07 management and investment Envelope d'exécution d’encres et de petits climate in the Project Area matériels et outillages Improvement of institutional BF-PPCB-26405-GO-RFQ / capacity for better zone Single Stage - One En attente Mise en place d’un système IDA / H7270 A posteriori Demande de prix Limited 10,000.00 0.00 2017-09-05 2017-10-08 2017-11-07 management and investment Envelope d'exécution audio conférence climate in the Project Area Improvement of institutional BF-PPCB-26415-GO-RFQ / capacity for better zone Single Stage - One En cours Acquisition et l’installation IDA / H7270 A posteriori Demande de prix Limited 50,000.00 0.00 2017-09-05 2017-10-10 2017-12-09 management and investment Envelope d'exécution d’un groupe électrogène climate in the Project Area BF-PPCB-26434-GO-RFQ / Improvement of institutional Acquisition de petits capacity for better zone Single Stage - One En attente matériels pour la production IDA / H7270 A posteriori Demande de prix Limited 40,000.00 0.00 2017-08-20 2017-10-01 2017-10-31 management and investment Envelope d'exécution piscicole au profit du CEP climate in the Project Area de Bagrépôle BF-PPCB-26443-GO-RFQ / Improvement of institutional Mise en place d'un système capacity for better zone Single Stage - One d'optimisation de la bande IDA / H7270 A posteriori Demande de prix Limited 16,000.00 0.00 Annulé 2017-09-15 2017-10-20 2017-11-19 management and investment Envelope passante et de cryptage de climate in the Project Area données Page 3 BF-PPCB-50704-GO-RFQ / Improvement of institutional Interconnections des sites du capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 17,000.00 0.00 2018-06-20 2018-07-25 2018-09-23 PEP et de l’IFODER au management and investment Envelope d'exécution siège de Bagrépôle climate in the Project Area BF-PPCB-50701-GO-RFQ / Improvement of institutional Acquisition de matériel capacity for better zone Single Stage - One En attente informatique et mise en IDA / H7270 A posteriori Demande de prix Limited 64,000.00 0.00 2018-05-06 2018-06-10 2018-09-08 management and investment Envelope d'exécution place d'un système Visio- climate in the Project Area conférence BF-PPCB-50693-GO-RFQ / Improvement of institutional Acquisition d’équipements capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 30,000.00 0.00 2018-03-20 2018-04-24 2018-07-23 techniques au profit de la management and investment Envelope d'exécution radio Bagrépôle FM climate in the Project Area Improvement of institutional BF-PPCB-50702-GO-RFQ / capacity for better zone Single Stage - One En attente Entretien et réparation de IDA / H7270 A posteriori Demande de prix Limited 30,000.00 0.00 2018-03-20 2018-04-24 2019-04-24 management and investment Envelope d'exécution matériel roulant climate in the Project Area BF-PPCB-66885-GO-RFQ / Réalisation d'un film documentaire (succes story) Improvement of institutional sur les leçons à tirer de la capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 24,000.00 0.00 2018-07-05 2018-07-28 2018-08-27 cohabitation des management and investment Envelope d'exécution communautés installées et climate in the Project Area des communautés d'accueil de Biré et de Guirmogo BF-PPCB-66888-GO-DIR / Improvement of institutional acquisition, paramétrage du Passation de capacity for better zone En attente module TOM Monitoring du IDA / H7270 A posteriori marché de gré à Direct 50,000.00 0.00 2018-06-30 2018-07-05 2018-07-26 2018-09-24 management and investment d'exécution logiciel TOM2PRO et gré climate in the Project Area formation des utilisateurs BF-PPCB-66890-GO-RFQ / Improvement of institutional Mise en place d'un dispositif capacity for better zone Single Stage - One En attente de sécurisation des accès IDA / H7270 A posteriori Demande de prix Limited 9,000.00 0.00 2018-07-20 2018-08-09 2018-09-08 management and investment Envelope d'exécution aux locaux techniques de climate in the Project Area Bagrépôle Improvement of institutional BF-PPCB-66891-GO-RFQ / capacity for better zone Single Stage - One En attente Mise en place d'un système IDA / H7270 A posteriori Demande de prix Limited 10,000.00 0.00 2018-07-15 2018-08-07 2018-09-06 management and investment Envelope d'exécution de sauvegarde des données climate in the Project Area BF-PPCB-26419-GO-RFQ / Improvement of institutional Fourniture et pose de capacity for better zone Single Stage - One IDA / H7270 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2017-08-30 2017-10-04 2017-11-03 rideaux au siège de management and investment Envelope Bagrépôle à Ouagadougou climate in the Project Area Improvement of institutional BF-PPCB-105150-GO-RFB / capacity for better zone Single Stage - One En attente acquisition de matériels IDA / 61840 A posteriori Appel d'offres Open - National 180,000.00 0.00 2019-04-10 2019-04-15 2019-05-15 2019-05-22 2019-06-12 2019-09-10 management and investment Envelope d'exécution roulants climate in the Project Area BF-PPCB-105151-GO-RFB / Improvement of institutional Équipements informatiques, capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Appel d'offres Open - National 105,000.00 0.00 2019-04-10 2019-04-15 2019-05-15 2019-05-29 2019-06-12 2019-08-11 licences, antivirus et management and investment Envelope d'exécution mobiliers de bureau climate in the Project Area Page 4 BF-PPCB-105190-GO-RFB / Matériels pour l'équipement Development of Critical Single Stage - One En attente des unités de transformation IDA / 61840 Services and direct support A posteriori Appel d'offres Open - National 200,000.00 0.00 2019-05-15 2019-05-20 2019-06-19 2019-06-26 2019-07-17 2019-09-15 Envelope d'exécution au profit des personnes to smallholders and SMEs affectées par le projet BF-PPCB-105199-GO-RFQ / Improvement of institutional Acquisition de pneumatiques capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 26,000.00 0.00 2019-06-04 2019-07-05 2020-07-04 pour l'entretien des véhicules management and investment Envelope d'exécution automobiles climate in the Project Area BF-PPCB-105205-GO-RFB / Improvement of institutional Outils mobiles pour la capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Appel d'offres Open - National 100,000.00 0.00 2019-04-01 2019-04-06 2019-05-06 2019-05-13 2019-06-03 2019-08-02 collecte et le suivi des management and investment Envelope d'exécution activités climate in the Project Area BF-PPCB-105209-GO-RFQ / Improvement of institutional service d'assurance du capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 30,000.00 0.00 2019-07-06 2019-08-10 2020-08-09 matériel roulant du Projet management and investment Envelope d'exécution Pôle de Croissance de Bagré climate in the Project Area BF-PPCB-105215-GO-RFB / acquisition d'un logiciel de Investment Promotion and Single Stage - One En attente gestion comptable et des IDA / 61840 A posteriori Demande de prix Limited 30,000.00 0.00 2019-04-30 2019-05-31 2019-07-30 Investment Climate Envelope d'exécution ressources humaines au profit de l'ABI BF-PPCB-105217-GO-RFB / Production et diffusion Investment Promotion and Single Stage - One En attente d'outils de communication au IDA / 61840 A posteriori Appel d'offres Open - National 166,000.00 0.00 2019-05-30 2019-06-04 2019-07-04 2019-07-11 2019-08-01 2019-12-29 Investment Climate Envelope d'exécution profit de l'ABI et de Bagrépôle BF-PPCB-105218-GO-RFQ / Édition du bulletin Investment Promotion and Single Stage - One En attente d'information de Bagrépôle IDA / 61840 A posteriori Demande de prix Limited 24,000.00 0.00 2019-04-06 2019-05-07 2019-12-03 Investment Climate Envelope d'exécution et brochures sur les réalisation du PPCB BF-PPCB-105219-GO-RFB / acquisition de logiciel de Investment Promotion and Single Stage - One En attente IDA / 61840 A posteriori Appel d'offres Open - National 90,000.00 0.00 2019-08-01 2019-08-06 2019-09-05 2019-09-12 2019-10-03 2019-12-02 suivi des investisseurs au Investment Climate Envelope d'exécution profit de l'ABI BF-PPCB-105213-GO-DIR / Improvement of institutional Acquisition de carburant et Passation de capacity for better zone En attente de lubrifiant pour le IDA / 61840 A posteriori marché de gré à Direct 120,000.00 0.00 2019-03-31 2019-04-05 2019-04-19 2020-04-18 management and investment d'exécution fonctionnement du matériel gré climate in the Project Area roulant du projet NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26432-NC-RFQ / Recrutement d’un prestataire Improvement of institutional pour l’appui à l’organsinions capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 30,000.00 0.00 2017-04-06 2017-05-18 2018-05-13 des sessions du Comité management and investment Envelope d'exécution National de Pilotage des climate in the Project Area Pôles de Croissance Page 5 BF-PPCB-105192-NC-DIR / Development of Critical Passation de En attente mise en place d'un numéro IDA / 61840 Services and direct support A posteriori marché de gré à Direct 50,000.00 0.00 2019-03-31 2019-04-05 2019-04-26 2019-05-26 d'exécution vert d'alerte et de secours to smallholders and SMEs gré BF-PPCB-105194-NC-RFQ / service d'appui à Improvement of institutional l'organisation des ateliers de capacity for better zone Single Stage - One En attente IDA / H7270 A posteriori Demande de prix Limited 50,000.00 0.00 2019-04-10 2019-05-11 2020-05-10 Bagrépôle et des sessions du management and investment Envelope d'exécution Comité National Pilotage des climate in the Project Area Pôles de Croissance BF-PPCB-105196-NC-RFQ / services de maintenance et Investment Promotion and Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 24,000.00 0.00 2019-03-30 2019-04-30 2020-04-29 de réparation des Investment Climate Envelope d'exécution climatiseurs BF-PPCB-105197-NC-RFQ / Improvement of institutional services de maintenance et capacity for better zone Single Stage - One En attente de réparation des IDA / 61840 A posteriori Demande de prix Limited 20,000.00 0.00 2019-06-04 2019-07-05 2020-07-04 management and investment Envelope d'exécution équipements informatiques et climate in the Project Area copieurs Improvement of institutional BF-PPCB-105195-NC-RFQ / capacity for better zone Single Stage - One En attente service de maintenance et de IDA / 61840 A posteriori Demande de prix Limited 24,000.00 0.00 2019-05-20 2019-06-20 2020-06-19 management and investment Envelope d'exécution réparation des climatiseurs climate in the Project Area BF-PPCB-105201-NC-RFQ / Improvement of institutional Services de pause café et de capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 20,000.00 0.00 2019-04-04 2019-05-05 2020-05-04 restauration au profit de management and investment Envelope d'exécution Bagrépôle climate in the Project Area BF-PPCB-105203-NC-RFQ / Improvement of institutional Services d'entretien et de capacity for better zone Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 30,000.00 0.00 2019-05-10 2019-06-10 2020-06-09 réparation de matériel management and investment Envelope d'exécution roulant climate in the Project Area Improvement of institutional BF-PPCB-105212-NC-RFQ / capacity for better zone Single Stage - One En attente Assurance santé du IDA / 61840 A posteriori Demande de prix Limited 95,000.00 0.00 2019-07-06 2019-08-10 2020-08-09 management and investment Envelope d'exécution personnel climate in the Project Area CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-14255-CS-QCBS / mise en place outils de Improvement of institutional Sélection fondée gestion du courrier et d'un capacity for better zone En attente IDA / H7270 A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-09-15 2017-09-29 2017-10-13 2017-11-12 2017-11-26 2017-12-13 2017-12-30 2018-05-29 système d'information de management and investment d'exécution le coût suivi évaluation et de climate in the Project Area pilotage BF-PPCB-26289-CS-QCBS / Improvement of institutional Sélection fondée Réalisation de la revue du capacity for better zone En attente IDA / H7270 A posteriori sur la qualité et Open - National 150,000.00 0.00 2017-09-30 2017-10-14 2017-10-31 2017-11-30 2017-12-14 2018-01-11 2018-01-25 2018-06-24 plan stratégique de management and investment d'exécution le coût Bagrépôle climate in the Project Area Page 6 BF-PPCB-26288-CS-QCBS / Réalisation des évaluations Improvement of institutional Sélection fondée environnementales et sociales capacity for better zone sur les En attente du mini-marché et du centre IDA / H7270 A posteriori Open - National 100,000.00 0.00 2017-09-30 2017-10-14 2017-11-07 2017-11-17 2017-12-01 2018-01-30 management and investment qualifications des d'exécution de formation professionnelle, climate in the Project Area consultants des travaux de réhabilitation du barrage de Lega ... BF-PPCB-26308-CS-QCBS / Improvement of institutional Sélection fondée Réalisation de bornage et capacity for better zone IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 Annulé 2017-07-01 2017-07-22 2017-09-04 2017-10-04 2017-10-11 2017-11-04 2017-11-18 2018-05-17 l’immatriculation des sites management and investment le coût aménagés climate in the Project Area BF-PPCB-26246-CS-QCBS / Etude d’actualisation de Sélection fondée Development of Critical En cours l’APD et du DAO des IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-09-05 2017-09-26 2017-10-13 2017-11-12 2017-11-19 2017-12-13 2017-12-27 2017-12-31 Infrastructure d'exécution travaux de construction de le coût routes et pistes BF-PPCB-26269-CS-QCBS / Etude d'adaptation et suivi contrôle des travaux de Sélection fondée Development of Critical En attente construction de  parcs de IDA / H7270 A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-09-20 2017-10-04 2017-10-21 2017-11-20 2017-11-27 2017-12-21 2018-01-04 2018-08-02 Infrastructure d'exécution vaccination et le coût d'infrastructures au profit des PAP BF-PPCB-26293-CS-CQS / études techniques, Sélection fondée élaboration de DAO et suivi- Development of Critical sur les En cours contrôle des travaux IDA / H7270 A posteriori Open - National 100,000.00 0.00 2017-09-15 2017-09-29 2017-10-23 2017-11-06 2017-11-20 2018-06-18 Infrastructure qualifications des d'exécution d’assainissement collectif de consultants la Cité de Bagrépôle et de construction de dalots Improvement of institutional Sélection fondée BF-PPCB-26355-CS-CQS / capacity for better zone sur les En cours Mise en place d’un service IDA / H7270 A posteriori Open - National 20,000.00 0.00 2017-06-01 2017-06-22 2017-07-07 2017-08-06 2017-08-20 2017-10-19 management and investment qualifications des d'exécution de messagerie électronique climate in the Project Area consultants BF-PPCB-26424-CS-QCBS / Mise en place d’outils de Improvement of institutional gestion automatisée du Sélection fondée capacity for better zone En attente courrier et d’un système IDA / H7270 A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-07-20 2017-08-10 2017-09-19 2017-10-19 2017-11-02 2017-11-30 2017-12-28 2018-04-27 management and investment d'exécution d’information de suivi le coût climate in the Project Area évaluation et de pilotage de Bagrépôle Improvement of institutional Sélection fondée BF-PPCB-26292-CS-CQS / capacity for better zone sur les En attente Réalisation du bilan IDA / H7270 A posteriori Open - National 100,000.00 0.00 2017-12-15 2017-12-29 2018-02-11 2018-02-25 2018-03-25 2018-05-24 management and investment qualifications des d'exécution technique du PPCB climate in the Project Area consultants BF-PPCB-26433-CS-QCBS / Etude technique, d’APD et élaboration de DAO pour la Sélection fondée Development of Critical En attente réalisation des travaux IDA / H7270 A posteriori sur la qualité et Open - National 120,000.00 0.00 2017-09-15 2017-10-06 2017-10-30 2017-11-29 2017-12-13 2018-01-10 2018-02-07 2018-07-07 Infrastructure d'exécution d’aménagement de la Zone le coût industrielle et commerciale de Bagrépôle BF-PPCB-26354-CS-CQS / Sélection fondée Etude technique et suivi Development of Critical sur les En cours contrôle des travaux IDA / H7270 A posteriori Open - National 190,000.00 0.00 2016-11-01 2016-11-22 2017-01-05 2017-02-04 2017-03-11 2017-11-06 Infrastructure qualifications des d'exécution d’aménagement de la zone consultants pastorale Page 7 BF-PPCB-26271-CS-QCBS / Elaboration d’un dossier technique pour le Sélection fondée recrutement d’un opérateur Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 416,000.00 0.00 2016-06-01 2016-06-22 2016-08-05 2016-09-04 2016-10-04 2016-11-08 2016-12-13 2017-12-08 privé chargé de la gestion Infrastructure d'exécution le coût de l’eau, de l’entretien des ouvrages hydrauliques et la collecte des redevances BF-PPCB-26302-CS-CQS / Réalisation de la situation Improvement of institutional Sélection fondée de référence capacity for better zone sur les En attente IDA / H7270 A posteriori Open - National 120,000.00 0.00 2017-08-25 2017-09-08 2017-10-02 2017-10-16 2017-11-02 2018-01-01 environnementale sur l’eau management and investment qualifications des d'exécution et l’air en rive gauche du climate in the Project Area consultants Nakambé BF-PPCB-26287-CS-QCBS / Actualisation des EIES et Improvement of institutional Sélection fondée PAR des travaux de capacity for better zone En attente IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-09-30 2017-10-14 2017-10-31 2017-11-30 2017-12-07 2017-12-31 2018-01-14 2018-04-14 construction de routes/pistes management and investment d'exécution le coût et d’extension du réseau climate in the Project Area électrique BF-PPCB-32280-CS-QCBS / Etude diagnostique technique de l'ensemble des Sélection fondée dégradations des Development of Critical En attente IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-10-16 2017-10-30 2017-11-13 2017-12-13 2017-12-20 2018-01-10 2018-01-24 2018-06-23 aménagements existants à Infrastructure d'exécution le coût Bagré (3380 HA) et évaluation des coûts de réhabilitation BF-PPCB-26125-CS-QCBS / Recrutement d'un consultant chargé de l'élaboration d'un Improvement of institutional dossier technique pour le Sélection fondée capacity for better zone recrutement d'un opérateur IDA / H7270 A posteriori sur la qualité et Open - National 416,000.00 0.00 Annulé 2017-08-24 2017-09-07 2017-09-24 2017-10-24 2017-11-03 2017-12-01 2017-12-15 2018-06-13 management and investment privé chargé de la gestion le coût climate in the Project Area de l'eau, de l'entretien des ouvrages hydrauliques et la collecte des redevances BF-PPCB-50667-CS-QCBS / Sélection fondée Actualisation APD et DAO Development of Critical IDA / H7270 A posteriori sur la qualité et Open - National 200,000.00 0.00 Annulé 2018-04-01 2018-04-22 2018-05-13 2018-05-14 2018-05-21 2018-06-18 2018-07-02 2018-10-30 des travaux d'extension du Infrastructure le coût reseau électrique BF-PPCB-50676-CS-QCBS / Bornage, morcellement et Development of Critical Sélection fondée immatriculation des parcelles En cours IDA / H7270 Services and direct support A posteriori sur la qualité et Open - National 440,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-12-23 des périmètres aménagés des d'exécution to smallholders and SMEs le coût 2200 ha à l'aval du barrage en rive gauche BF-PPCB-50677-CS-QCBS / Bornage, morcellement et Sélection fondée immatriculation des parcelles Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 455,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-01-30 2018-02-27 2018-12-09 des périmètres aménagés des Infrastructure d'exécution le coût 2194 ha en rive droite à l'aval du barrage BF-PPCB-50680-CS-QCBS / Bornage, morcellement et immatriculation des parcelles Sélection fondée Development of Critical En cours des périmètres aménagés IDA / H7270 A posteriori sur la qualité et Open - National 210,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-09-14 Infrastructure d'exécution existant des 1200 ha en rive le coût droite à l'aval du barrage Page 8 BF-PPCB-50691-CS-QCBS / Bornage, morcellement et Sélection fondée immatriculation des parcelles Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 166,500.00 0.00 2017-09-01 2017-09-22 2017-10-20 2017-11-19 2017-12-03 2017-12-31 2018-01-21 2018-07-25 des périmètres aménagés des Infrastructure d'exécution le coût 680 ha existants à l'aval du barrage en rive gauche BF-PPCB-50678-CS-QCBS / Bornage morcellement et Sélection fondée immatriculation des parcelles Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 355,000.00 0.00 2017-09-01 2017-09-22 2017-10-07 2017-11-06 2017-11-20 2017-12-25 2018-01-22 2018-08-05 des périmètres aménagés des Infrastructure d'exécution le coût 1500 ha en rive gauche ancien Improvement of institutional Sélection fondée BF-PPCB-50706-CS-QCBS / capacity for better zone En attente IDA / H7270 A posteriori sur la qualité et Open - National 60,000.00 0.00 2018-04-15 2018-05-06 2018-06-03 2018-07-03 2018-07-17 2018-08-21 2018-09-11 2018-11-10 Mise en place d’un intranet management and investment d'exécution le coût climate in the Project Area BF-PPCB-50700-CS-CQS / Improvement of institutional Sélection fondée Elaboration d’un manuel de capacity for better zone sur les management sur l’hygiène, IDA / H7270 A posteriori Open - National 40,000.00 0.00 Annulé 2018-04-01 2018-04-22 2018-05-13 2018-05-27 2018-06-24 2018-08-23 management and investment qualifications des santé et sécurité et climate in the Project Area consultants environnement de Bagrépôle BF-PPCB-66881-CS-QCBS / Sélection fondée Suivi contrôle et coordination Development of Critical Open - En cours IDA / 61840 A posteriori sur la qualité et 575,000.00 0.00 2018-07-15 2018-07-29 2018-08-12 2018-09-26 2018-10-03 2018-10-17 2018-10-31 2019-10-31 des travaux de construction Infrastructure International d'examen le coût de pistes et routes en terres BF-PPCB-66882-CS-QCBS / Sélection fondée Suivi contrôle et coordination Development of Critical Open - En cours IDA / 61840 A posteriori sur la qualité et 675,000.00 0.00 2018-06-30 2018-07-14 2018-07-28 2018-09-11 2018-09-18 2018-10-02 2018-10-12 2019-12-06 des travaux de construction Infrastructure International d'examen le coût de routes bitumées BF-PPCB-66883-CS-CQS / Improvement of institutional Sélection fondée réalisation du Bilan capacity for better zone sur les En cours technique du Projet, IDA / H7270 A posteriori Open - National 180,000.00 0.00 2018-06-30 2018-07-14 2018-08-04 2018-08-11 2018-08-21 2018-11-19 management and investment qualifications des d'exécution capitalisation des bonnes climate in the Project Area consultants pratiques... BF-PPCB-66892-CS-CQS / Sélection fondée mission de suivi contrôle des Development of Critical sur les En cours travaux de construction de IDA / H7270 A posteriori Open - National 140,000.00 0.00 2018-06-25 2018-07-05 2018-07-17 2018-07-24 2018-08-03 2019-01-30 Infrastructure qualifications des d'exécution magasins et aires de consultants séchages BF-PPCB-66893-CS-CQS / Sélection fondée Actualisation des études Development of Critical sur les En cours APD et DAO des travaux IDA / H7270 A posteriori Open - National 180,000.00 0.00 2018-06-30 2018-07-14 2018-08-02 2018-08-09 2018-08-23 2018-11-21 Infrastructure qualifications des d'examen d'extension du réseau consultants électrique BF-PPCB-74282-CS-LCS / Improvement of institutional Audit comptable et financier capacity for better zone Sélection au En cours IDA / 61840 A priori Open - National 60,000.00 0.00 2018-08-31 2018-09-14 2018-09-22 2018-10-22 2018-10-27 2018-11-13 2018-12-04 2021-12-03 des trois exercices (2018, management and investment moindre coût d'examen 2019 et 2020) du Projet climate in the Project Area BF-PPCB-50698-CS-QCBS / Improvement of institutional Sélection fondée Etude de capitalisation et de capacity for better zone IDA / H7270 A posteriori sur la qualité et Open - National 80,000.00 0.00 Annulé 2018-07-15 2018-08-05 2018-08-26 2018-09-23 2018-10-07 2018-10-15 2018-10-30 2018-12-29 valorisation des expériences management and investment le coût du PPCB climate in the Project Area Page 9 Improvement of institutional BF-PPCB-26303-CS-QCBS / Sélection fondée capacity for better zone Evaluation finale du IDA / H7270 A posteriori sur la qualité et Open - National 170,000.00 0.00 Annulé 2017-10-31 2017-11-14 2017-12-08 2018-01-07 2018-01-14 2018-02-11 2018-03-04 2018-06-02 management and investment PPCB le coût climate in the Project Area BF-PPCB-26286-CS-QCBS / Etudes diagnostique et Improvement of institutional techniques pour la Sélection fondée capacity for better zone réalisation des travaux de IDA / H7270 A posteriori sur la qualité et Open - National 160,000.00 0.00 Annulé 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2017-12-26 2018-01-19 2018-02-02 2018-04-03 management and investment reboisement de 60 ha det le coût climate in the Project Area d’aménagement de 40 ha de périmètres maraichers Sélection fondée BF-PPCB-105152-CS-CQS / Investment Promotion and sur les En attente Mise à jour du site Web de IDA / 61840 A posteriori Open - National 50,000.00 0.00 2019-04-30 2019-05-14 2019-06-04 2019-06-18 2019-07-09 2019-10-07 Investment Climate qualifications des d'exécution Bagrépôle et de l'ABI consultants BF-PPCB-105153-CS-QCBS / Improvement of institutional Mise en place système Sélection fondée capacity for better zone En attente d'information de suivi- IDA / 61840 A posteriori sur la qualité et Open - National 140,000.00 0.00 2019-05-05 2019-05-19 2019-06-09 2019-07-09 2019-07-16 2019-08-06 2019-08-27 2020-02-23 management and investment d'exécution évaluation et de pilotage de le coût climate in the Project Area Bagrépôle BF-PPCB-105154-CS-CQS / Improvement of institutional Sélection fondée Réalisation de la situation capacity for better zone sur les En attente IDA / 61840 A posteriori Open - National 50,000.00 0.00 2019-03-30 2019-04-13 2019-04-27 2019-05-11 2019-05-25 2019-08-23 de référence du financement management and investment qualifications des d'exécution additionnel du PPCB climate in the Project Area consultants BF-PPCB-105155-CS-QCBS / Sélection fondée Investment Promotion and En attente Elaboration du plan IDA / 61840 A posteriori sur la qualité et Open - National 90,000.00 0.00 2019-04-10 2019-04-24 2019-05-15 2019-06-14 2019-06-21 2019-07-19 2019-08-02 2019-10-31 Investment Climate d'exécution stratégique de l'ABI le coût Improvement of institutional BF-PPCB-105157-CS-QCBS / Sélection fondée capacity for better zone En attente stratégie de communication IDA / 61840 A posteriori sur la qualité et Open - National 100,000.00 0.00 2019-04-15 2019-04-29 2019-05-20 2019-06-19 2019-07-03 2019-07-24 2019-08-14 2019-10-13 management and investment d'exécution de l'ABI et de Bagrépôle le coût climate in the Project Area BF-PPCB-105158-CS-CQS / Sélection fondée Situation des investissements Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 50,000.00 0.00 2019-05-05 2019-05-19 2019-06-09 2019-06-23 2019-07-07 2019-10-05 dans le pôle de croissance Investment Climate qualifications des d'exécution de Bagré consultants BF-PPCB-105161-CS-CQS / Sélection fondée Elaboration d'un manuel de Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-04-25 2019-05-09 2019-05-30 2019-06-13 2019-06-27 2019-08-26 gestion de la banque de Investment Climate qualifications des d'exécution projets au profit de l'ABI consultants BF-PPCB-105163-CS-QCBS / Étude économique sur les Sélection fondée filières porteuses et analyse Investment Promotion and En attente IDA / 61840 A posteriori sur la qualité et Open - National 100,000.00 0.00 2019-05-05 2019-05-19 2019-06-09 2019-07-09 2019-07-16 2019-08-13 2019-08-27 2019-11-25 sectorielle spatiale et la Investment Climate d'exécution le coût typologie des produits du PCB BF-PPCB-105166-CS-CQS / Sélection fondée Sratégie de promotion des Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-05-30 2019-06-13 2019-07-04 2019-07-18 2019-08-08 2019-11-06 investissements du pôle de Investment Climate qualifications des d'exécution croissance de Bagré consultants BF-PPCB-105159-CS-CQS / Sélection fondée Elaboration manuel de Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-03-30 2019-04-13 2019-05-04 2019-05-11 2019-05-25 2019-07-09 gestion de la banque de Investment Climate qualifications des d'exécution projet de l'ABI consultants Page 10 Improvement of institutional Sélection fondée BF-PPCB-105169-CS-CQS / capacity for better zone sur les En attente Etudes environnementale et IDA / 61840 A posteriori Open - National 20,000.00 0.00 2019-03-30 2019-04-20 2019-05-11 2019-05-18 2019-06-08 2019-09-06 management and investment qualifications des d'exécution sociale des basfonds de Beka climate in the Project Area consultants Improvement of institutional Sélection fondée BF-PPCB-105172-CS-CQS / capacity for better zone sur les En attente service de recrutement du IDA / 61840 A posteriori Open - National 50,000.00 0.00 2019-04-01 2019-04-15 2019-05-06 2019-05-13 2019-06-03 2019-08-02 management and investment qualifications des d'exécution personnel climate in the Project Area consultants BF-PPCB-105173-CS-CQS / Étude d'impact Sélection fondée environnemental et Development of Critical sur les En attente IDA / 61840 A posteriori Open - National 160,000.00 0.00 2019-04-15 2019-04-29 2019-05-20 2019-06-03 2019-06-17 2019-08-16 élaboration de PAR des Infrastructure qualifications des d'exécution travaux d'extension du consultants réseau électrique BF-PPCB-105179-CS-QBS / Improvement of institutional Révision des plans d'action capacity for better zone Sélection fondée En attente IDA / H7270 A posteriori Open - National 120,000.00 0.00 2019-04-25 2019-05-09 2019-05-23 2019-06-22 2019-06-29 2019-07-13 2019-07-27 2019-09-25 de réinstallation des zones management and investment sur la qualité d'exécution pastorales et industrielles climate in the Project Area BF-PPCB-105180-CS-QCBS / Sélection fondée Étude diagnostique pour Development of Critical En attente IDA / 61840 A posteriori sur la qualité et Open - National 400,000.00 0.00 2019-04-15 2019-04-29 2019-05-20 2019-06-19 2019-06-26 2019-07-17 2019-08-07 2020-01-04 l'aménagement d'un parc Infrastructure d'exécution le coût industriel Improvement of institutional BF-PPCB-105182-CS-QCBS / Sélection fondée capacity for better zone En cours Revue du plan stratégique IDA / H7270 A posteriori sur la qualité et Open - National 150,000.00 0.00 2019-03-31 2019-04-14 2019-05-05 2019-06-04 2019-06-11 2019-07-02 2019-07-23 2019-10-21 management and investment d'examen de Bagrépôle le coût climate in the Project Area BF-PPCB-105184-CS-CQS / Improvement of institutional Sélection fondée situation de référence capacity for better zone sur les En cours environnementale de l'eau IDA / 61840 A posteriori Open - National 60,000.00 0.00 2019-04-10 2019-04-24 2019-05-15 2019-05-29 2019-06-12 2019-09-10 management and investment qualifications des d'examen est des organismes végétaux climate in the Project Area consultants de la zone de Bagré INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26312-CS-INDV / Suivi contrôle des travaux de mise en place d’un Development of Critical En attente IDA / H7270 A posteriori Individuel Limited 10,000.00 0.00 2017-10-15 2017-10-20 2017-11-10 2017-12-01 2018-04-30 système de prévention contre Infrastructure d'exécution les noyades dans le canal primaire BF-PPCB-26430-CS-INDV / Etude technique pour la mise en place d'un système Development of Critical En cours IDA / H7270 A posteriori Individuel Limited 20,000.00 0.00 2017-08-25 2017-08-30 2017-09-13 2017-10-04 2017-12-03 de prévention contre les Infrastructure d'exécution noyades dans le canal primaire BF-PPCB-26285-CS-INDV / Suivi contrôle des travaux de mise en place d’un Development of Critical En attente IDA / H7270 A posteriori Individuel Open 10,000.00 0.00 2017-10-15 2017-11-17 2017-12-01 2017-12-15 2018-05-14 système de prévention contre Infrastructure d'exécution les noyades dans le canal primaire Page 11 BF-PPCB-26438-CS-CDS / Réalisation de la situation Improvement of institutional Sélection de de référence capacity for better zone En attente IDA / H7270 A posteriori consultants par Direct 80,000.00 0.00 2017-09-30 2017-10-10 2017-12-14 2018-02-12 environnementale sur les management and investment d'exécution entente directe sols des extension Nord 2 et climate in the Project Area Est BF-PPCB-32605-CS-INDV / Mission d'analyse des demandes d'indemnisation des entreprises chargées des Improvement of institutional travaux lot 1 suite au rendu capacity for better zone En attente des résultats de l'adaptation IDA / H7270 A posteriori Individuel Open 80,000.00 0.00 2017-10-18 2017-11-29 2017-12-06 2017-12-20 2018-02-03 management and investment d'exécution des études techniques climate in the Project Area d'exécution des travaux d'aménagement de 2582 HA en rive gauche du Nakambé à Bagré Improvement of institutional BF-PPCB-66884-CS-CDS / Sélection de capacity for better zone En cours Actualisation du manuel IDA / H7270 A posteriori consultants par Direct 10,000.00 0.00 2018-06-25 2018-07-05 2018-07-18 2018-08-17 management and investment d'examen d'exécution du PPCB entente directe climate in the Project Area BF-PPCB-66889-CS-INDV / mission d'expertise et réalisation d'étude technique détaillée en vue de la Development of Critical En cours IDA / H7270 A posteriori Individuel Limited 50,000.00 0.00 2018-06-20 2018-06-25 2018-07-02 2018-07-16 2018-08-30 réalisation des travaux de Infrastructure d'exécution confortement du siphon situé sur le périmètre aménagé des 2582 ha à Bagré BF-PPCB-68396-CS-INDV / Improvement of institutional Élaboration manuel de capacity for better zone En cours management sur l'hygiène IDA / H7270 A posteriori Individuel Open 40,000.00 0.00 2018-06-29 2018-07-25 2018-08-01 2018-08-11 2018-09-10 management and investment d'exécution santé sécurité et climate in the Project Area environnement BF-PPCB-26310-CS-INDV / Contrôle à pieds d’œuvre Development of Critical construction d’infrastructures IDA / H7270 A posteriori Individuel Limited 16,000.00 0.00 Annulé 2017-10-01 2017-10-06 2017-10-27 2017-11-10 2018-03-10 Infrastructure socio-économiques au profit des PAP BF-PPCB-105167-CS-INDV / Improvement of institutional Formation sur la négociation capacity for better zone En attente IDA / 61840 A posteriori Individuel Open 20,000.00 0.00 2019-06-25 2019-07-21 2019-08-04 2019-08-18 2019-09-17 et la contractualisation en management and investment d'exécution matière commerciale climate in the Project Area BF-PPCB-105175-CS-INDV / Improvement of institutional Audit global des instruments capacity for better zone En attente IDA / 61840 A posteriori Individuel Open 40,000.00 0.00 2019-04-01 2019-04-27 2019-05-04 2019-05-18 2019-07-17 de sauvegardes management and investment d'exécution environnementales et sociales climate in the Project Area Improvement of institutional BF-PPCB-105185-CS-CDS / Sélection de capacity for better zone En attente Réalisation des analyses IDA / 61840 A posteriori consultants par Direct 12,400.00 0.00 2019-04-05 2019-04-15 2019-06-05 2019-07-05 management and investment d'exécution microbiologiques des sols entente directe climate in the Project Area Page 12