Madagascar PPCR: procurement plan summary I. General 2. Bank’s approval Date of the procurement Plan Original: February 2018 3. Date of General Procurement Notice: Dec 7, 2017 4. Period covered by this procurement plan: The procurement period of project covered from February 2018 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] not applicable Post Review Threshold: Procurement Decisions subject to Post Review by the Bank Procurement Method Post Review Threshold Comments US$ 1. Shopping (Goods) Below US$ 25,000 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: not applicable 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] not applicable III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 50,000 Except for componant « A.3 Développement des connaissances sur February 15, 2018 la vulnérabilité des infrastructures publiques » which has been divided into 3 sub- componants below US$50,000 that should all be submitted to prior review 2. Single Source (Firms) All 3. Individual All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_34,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / Post) C-03/17 Summary of 370,000 4 Prior C-04/17 number of C-05/17 contracts that C-19/17 will be let under QCBS C-02/17 Summary of 135,000 3 Post C-08/17 number of C-17/17 contracts that will be let under QCBS C-11A/17 Summary of 147,000 4 Prior CQS C-11B/17 number of C-11C/17 contracts that C-20/17 will be let under other methods C-01/17 Summary of 278,000 12 Post CQS C-12/17 number of C-13/17 contracts that C-14/17 will be let C-18/17 February 15, 2018 C-20/17 under other C-21/17 methods C-22A/17 C-22B/17 C-23/17 C-24/17 C-25/17 CI-001/17 Summary of 85,000 4 Prior IC CI-002/17 number of CI-003/17 contracts that CI-004/17 will be let under other methods February 15, 2018 PROCUREMENT Madagascar : Madagascar Pilot Program for Climate Resilience Phase I PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan: 2018-02-27 2020-01-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158816 GPN Date: Project Name: Madagascar Pilot Program for Climate Resilience Phase I Loan / Credit No: TF / A5362 Executing Agency(ies): EMERGENCY PREVENTION AND MANAGEMENT UNIT WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual T01/2018/CPGU/PPCR / Implementation Support and Single Stage - One En cours Travaux d'agencement et TF / A5362 A posteriori Demande de prix Limited 0.00 2018-09-15 2018-11-10 2018-12-10 M&E Envelope d'exécution aménagement Bureau CPGU GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F01/2018/CPGU/PPCR / Fourniture de matériels Implementation Support and Single Stage - One TF / A5362 A posteriori Demande de prix Limited 23,946.32 Achevé 2018-04-17 2018-05-29 2018-06-19 informatiques et M&E Envelope bureautiques du CPGU/PPCR F02/2018/CPGU/PPCR / Fourniture de matériels de Implementation Support and Single Stage - One TF / A5362 A posteriori Demande de prix Limited 8,701.48 Achevé 2018-04-17 2018-06-05 2018-12-02 communication pour le M&E Envelope CPGU/PPCR F04/2018/CPGU/PPCR / Fourniture de matériels Strengthening climate Single Stage - One informatiques pour TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 0.00 Annulé 2018-04-17 2018-05-29 2018-06-28 Envelope l'établissement des Atlas des management risques climatiques F05/2018/CPGU/PPCR / Hébergement et de Strengthening climate Passation de restauration du Team TF / A5362 resilience and climate risk A posteriori marché de gré à Direct 2,093.39 Achevé 2018-04-30 2018-05-02 2018-05-06 2018-05-09 Building Equipe CPGU / management gré PPCR F03/2018/CPGU/PPCR / Fourniture de matériels Strengthening climate informatiques pour pour le Single Stage - One En cours TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 0.00 2018-08-15 2018-09-26 2018-10-26 renforcement du service Envelope d'exécution management d'informations climatiques MAPROOM F06/2018/CPGU/PPCR / Fourniture de matériels Strengthening climate informatiques pour Single Stage - One TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 34,794.56 Signé 2018-08-15 2018-09-26 2018-10-26 l'élaboration de Scénario Envelope management Climatique de la Direction Générale de la Météorologie Page 1 F07/2018/CPGU/PPCR / Passation de Fourniture de logiciel de Implementation Support and TF / A5362 A posteriori marché de gré à Direct 9,404.11 Signé 2018-08-17 2018-08-22 2018-09-26 2018-10-26 gestion informatisée M&E gré TOM2PRO Version 2 F10/2019/CPGU/PPCR / Fourniture et installation de Strengthening climate Single Stage - One En cours Matériels informatiques pour TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 0.00 2019-03-02 2019-04-12 2019-06-11 Envelope d'exécution les données ATLAS des management risques F016/2019/CPGU/PPCR / Strengthening climate Single Stage - One En attente Fournitures et divers TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 0.00 2019-09-11 2019-10-26 2019-11-25 Envelope d'exécution matériels techniques management NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F08/2018/CPGU/PPCR / Fourniture de services de Strengthening climate Single Stage - One Duplication du document TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 1,457.66 Signé 2019-02-23 2019-04-02 2019-04-17 Envelope SPCR et des documents du management SNGRC/PNGRC MG-CPGU-156100-NC-RFQ / Fourniture de service de Traduction en malagasy des normes de construction des Strengthening climate bâtiments Résistants aux Single Stage - One En attente TF / A5362 resilience and climate risk A posteriori Demande de prix Limited 0.00 2020-02-03 2020-02-25 2020-03-26 aléas climatique et de la Envelope d'exécution management Directive pour la construction des cases d’habitation traditionnelles face aux cyclones CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C01/2018/CPGU/PPCR / Diagnostic des études, des planifications ,et des capacités institutionnelles au Strengthening climate Sélection fondée fin d'élaboration de TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-04-18 2018-05-09 2018-06-06 2018-07-04 2018-07-25 2018-08-29 2018-09-19 2019-02-16 stratégies et plan de management le coût communication multi et intersectoriel sur les changements climatiques et la résilience C02/2018/CPGU/PPCR / Élaboration de scénarios climatiques et de scénarios d'évolution du climat en considérant les résultats du Strengthening climate Sélection fondée Open - 5ème évaluation du GIEC TF / A5362 resilience and climate risk A posteriori sur la qualité et 0.00 Annulé 2018-04-25 2018-05-16 2018-06-29 2018-07-27 2018-08-26 2018-09-30 2018-11-04 2019-04-03 International par la mise à l'échelle management le coût national, infra-national ou autre échelon des scénarios actuels aux fins de l'élaboration du PNA Page 2 C003/2018/CPGU/PPCR / Renforcement du service d'informations climatiques Strengthening climate Sélection fondée Open - MAPROOM de Madagascar TF / A5362 resilience and climate risk A posteriori sur la qualité et 0.00 Annulé 2018-05-02 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-04-10 International pour répondre aux besoins management le coût des secteurs clés de développement C11/2018/CPGU/PPCR / Analyses économiques et financières des impacts Strengthening climate Sélection fondée des catastrophes et des TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-10-09 2018-10-30 2018-12-04 2019-01-01 2019-01-22 2019-02-19 2019-03-19 2019-07-17 changements climatiques et management le coût études comparatives des mécanismes de protection financière potentiels C12/2018/CPGU/PPCR / Détermination d'une stratégie d'intégration de résilience Strengthening climate Sélection fondée climatique dans les TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-05-08 2018-05-29 2018-07-03 2018-07-31 2018-08-21 2018-09-18 2018-10-16 2019-02-13 documents de planifications management le coût sectorielles, locales et régionales C14/2018/CPGU/PPCR / Etudes préalables pour la mise en oeuvre (1) d'un projet de résilience des villes Sélection fondée Development of the SPCR côtières et (2) d'un projet de TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2018-09-04 2018-09-25 2018-10-30 2018-11-27 2018-12-18 2019-01-15 2019-02-12 2019-06-12 and investment plan résilience des communautés le coût et des moyens de subsistances pour le Grand Sud de Madagascar C15/2018/CPGU/PPCR / Sélection fondée Etude de faisabilité de mise Development of the SPCR TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2018-09-11 2018-10-02 2018-11-06 2018-12-04 2018-12-25 2019-01-29 2019-02-26 2019-05-27 en place de projets and investment plan le coût d'infrastructures vertes C16/2018/CPGU/PPCR / Sélection fondée Etude de faisabilité pour un Development of the SPCR TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2018-09-18 2018-10-09 2018-11-13 2018-12-11 2019-01-01 2019-01-29 2019-02-26 2019-05-27 projet de résilience agricole and investment plan le coût (agri-business) C17/2018/CPGU/PPCR / Etude pour la mise en Sélection fondée œuvre du processus de Development of the SPCR TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2018-09-25 2018-10-16 2018-11-20 2018-12-18 2019-01-08 2019-02-05 2019-03-05 2019-06-03 renforcement des politiques and investment plan le coût publiques et des capacités pour la résilience climatique C04/2018/CPGU/PPCR / Modélisation des risques climatiques et de leurs impacts (socio6économiques et environnementaux) et Strengthening climate Sélection fondée Modélisation de la TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-07-12 2018-08-02 2018-09-06 2018-10-04 2018-10-25 2018-11-22 2018-12-20 2019-06-18 vulnérabilité des management le coût infrastructures clés (bâtiments, routières, agricoles, santé, écoles, énergies et des ressources en eau) C05/20118/CPGU/PPCR / Etablissement des Atlas Strengthening climate Sélection fondée des risques climatiques du TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-05-22 2018-06-12 2018-07-17 2018-08-14 2018-09-04 2018-10-02 2018-10-30 2019-03-29 Grand Sud et Menabe management le coût (Régions Anosy-Androy- Menabe) Page 3 C06/2018/CPGU/PPCR / Etudes hydrométéorologiques pour une meilleure maîtrise de la gestion des bassins Strengthening climate Sélection fondée versants et des ressources TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-06-07 2018-06-28 2018-08-02 2018-08-30 2018-09-20 2018-10-18 2018-11-15 2019-04-14 en eau (Fleuves Morondava management le coût MENABE - Betsiboka BOINA - Fierenana ATSIMO ANDREFANA) C07/2018/CPGU/PPCR / Élaboration des textes régissant l'application du Strengthening climate Sélection fondée guide de référence pour la TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-05-24 2018-06-14 2018-07-19 2018-08-16 2018-09-06 2018-10-04 2018-11-01 2019-03-01 construction des cases management le coût d'habitation traditionnelles et Vulgarisation du guide C08/2018/CPGU/PPCR / Etudes sur les normes relatives à la résilience Strengthening climate Sélection fondée des différentes TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-05-28 2018-06-18 2018-07-23 2018-08-20 2018-09-10 2018-10-08 2018-11-05 2019-03-05 infrastructures clés: Mise à management le coût jour de TBM, Mise à jour GPRCIM C09/2018/CPGU/PPCR / Strengthening climate Sélection fondée Mise à jour des règles de TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-05-30 2018-06-20 2018-07-25 2018-08-22 2018-09-12 2018-10-10 2018-11-07 2019-03-07 construction des bâtiments management le coût paracycloniques C10/2018/CPGU/PPCR / Renforcement des études de vulnérabilités socio- économiques et Strengthening climate Sélection fondée environnementales des villes TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-07-12 2018-08-02 2018-09-06 2018-10-04 2018-10-25 2018-11-22 2018-12-20 2019-05-19 urbaines côtières et non management le coût côtières et proposer des mesures de renforcement de résilience - Grand Tanà et Morondava C07A/2018/CPGU/PPCR / Mise à jour des règles de construction des bâtiments para cycloniques et Strengthening climate Sélection fondée élaboration des textes TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 69,781.21 Signé 2018-08-10 2018-08-31 2018-10-05 2018-11-02 2018-11-23 2018-12-21 2019-01-18 2019-07-17 régissant l'application de la management le coût directive de référence pour la construction des cases d'habitation traditionnelle et vulgarisation des documents C21A/2018/CPGU/PPCR / Recrutement Consultant Firm pour Élaboration de Strengthening climate Sélection fondée projet de texte d'application TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-08-30 2018-09-20 2018-11-03 2018-12-01 2018-12-31 2019-02-04 2019-03-11 2019-05-10 sur la loi GRC et la management le coût finalisation du plan d'action GRC C22A/2018/CPGU/PPCR / Sélection fondée Implementation Support and Audit des comptes du Projet TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-04-14 M&E PPCR le coût C05A/2018/CPGU/PPCR / Recrutement Consultant Firm pour les Etablissement Strengthening climate Sélection fondée et vulgarisation des Atlas TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-11-05 2018-11-26 2018-12-31 2019-01-28 2019-02-18 2019-03-18 2019-04-15 2019-08-13 des risques et de management le coût vulnérabilité du Grand sud et Menabe (Régions Androy- Menabe) Page 4 C09A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Sélection fondée Firm pour l'Évaluation de la TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-11-19 2018-12-10 2019-01-14 2019-02-11 2019-03-04 2019-04-01 2019-04-29 2019-07-28 vulnérabilité des management le coût infrastructures clés C10A/2018/CPGU/PPCR / Recrutement Consultant Firm pour le Renforcement Strengthening climate Sélection fondée des études de vulnérabilités TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-11-19 2018-12-10 2019-01-14 2019-02-11 2019-03-04 2019-04-01 2019-04-29 2019-07-28 socio-économiques et management le coût environnementales des villes urbaines côtières (Toamasina- Morondava) MG-CPGU-93735-CS-LCS / Implementation Support and Sélection au En cours Audit des comptes du projet TF / A5362 A posteriori Open - National 0.00 2019-01-07 2019-01-28 2019-03-13 2019-04-10 2019-05-10 2019-06-14 2019-07-19 2020-01-15 M&E moindre coût d'exécution PPCR C08A/2018/CPGU/PPCR / Recrutement Consultant Firm pour la Mise à jour du Guide de Protection Routière Contre les Strengthening climate Sélection fondée En cours Inondations (GPRCIM) TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 2019-02-15 2019-02-20 2019-03-27 2019-04-24 2019-05-09 2019-05-26 2019-06-16 2019-09-14 d'exécution aboutissant à l'élaboration management le coût des Normes pour les infrastructures routières résistantes aux inondations à Madagascar C04A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Sélection fondée Firm pour la Modélisation TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2019-08-15 des risques climatiques et de management le coût leurs impacts C06A/2018/CPGU/PPC6 / Etudes des risques de débordement du fleuve Strengthening climate Sélection fondée FIERENANA et identification TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2019-03-15 2019-03-30 2019-04-30 2019-05-28 2019-06-15 2019-06-30 2019-07-24 2019-11-01 des travaux d'aménagement management le coût pour la protection de la ville de Toliara C15A/2018/CPGU/PPCR / Etudes préalables de mise en oeuvre d'un projet de Sélection fondée Development of the SPCR résilience des communautés TF / A5362 A posteriori sur la qualité et Open - National 0.00 Annulé 2019-03-18 2019-04-02 2019-05-01 2019-05-29 2019-06-28 2019-07-18 2019-08-12 2019-10-11 and investment plan et des moyens de le coût subsistances pour le Grand sud de Madagascar C12A/2018/CPGU/PPCR / Recrutement Consultant Firm pour la Détermination Strengthening climate Sélection fondée d'une méthodologie TF / A5362 resilience and climate risk A posteriori sur la qualité et Open - National 0.00 Annulé 2018-11-26 2018-12-17 2019-01-21 2019-02-18 2019-03-11 2019-04-08 2019-05-06 2019-08-04 d'intégration de résilience management le coût climatique dans les politiques, les plans, et les stratégies sectorielles clés C14A/2019/CPGU/PPCR / Etudes de vulnérabilités des Sélection fondée villes côtières et proposition Development of the SPCR sur les En cours de mesures d’adaptations TF / A5362 A posteriori Open - National 0.00 2019-07-22 2019-08-01 2019-08-30 2019-09-09 2019-09-22 2019-12-31 and investment plan qualifications des d'exécution adéquates : consultants Cas des agglomérations de Toamasina et de Mahajanga INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 003/2017-CI/CPGU/PPCR / Le responsable technique sera chargé d'assurer la Implementation Support and TF / A5362 A posteriori Individuel Open 8,948.40 Achevé 2018-02-27 2018-03-27 2018-04-10 2018-04-22 2019-10-21 gestion opérationnelle des M&E activités techniques du Projet 001/2017-CI/CPGU/PPCR / Responsable Administratif financier sera chargé Implementation Support and d'assurer la gestion des TF / A5362 A posteriori Individuel Open 10,439.80 Résilié 2018-02-27 2018-03-27 2018-04-10 2018-04-22 2019-10-21 M&E ressources allouées au projet (financières, humaines et matérielles) 002/2017-CI/CPGU/PPCR / Le Responsable en Passation de Marchés sera chargé d'assurer toutes les étapes de la passation de marchés Implementation Support and TF / A5362 A posteriori Individuel Open 8,948.40 Résilié 2018-02-27 2018-03-27 2018-04-10 2018-04-22 2019-10-21 (publication, présélection, M&E préparation des documents d'appel d'offres, l'évaluation des offres et l'attribution du marché. C13/2018/CPGU/PPCR / Traduction en Français du Development of the SPCR TF / A5362 A priori Individuel Direct 0.00 Annulé 2018-04-26 2018-05-06 2018-05-27 2018-07-01 2018-12-28 document SPCR et des plans and investment plan d'investissement C18/2018/CPGU/PPCR / Strengthening climate Consultance pour facilitation TF / A5362 resilience and climate risk A posteriori Individuel Direct 447.42 Achevé 2018-04-30 2018-05-10 2018-05-17 2018-06-07 2018-06-14 Team Building - Equipe management CPGU - PPCR C03A/2018/CPGU/PPCR / Strengthening climate Sélection de Renforcement du service TF / A5362 resilience and climate risk A posteriori consultants par Direct 55,843.00 Signé 2018-08-10 2018-08-20 2018-10-24 2019-02-01 d'informations climatiques management entente directe MAPROOM de Madagascar C02A/2018/CPGU/PPCR / Élaboration des scénarios Strengthening climate Sélection de climatiques et des scénarios TF / A5362 resilience and climate risk A posteriori consultants par Direct 77,275.00 Signé 2018-08-10 2018-08-20 2018-10-24 2019-02-01 d'évolution du climat de management entente directe Madagascar C01A/2018/CPGU/PPCR / Recrutement Consultant International pour le Strengthening climate diagnostic sur les politiques TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 Annulé 2018-08-10 2018-08-15 2018-09-05 2018-10-10 2018-12-09 publiques et capacités management institutionnelles en matière de résilience climatique et GRC à Madagascar C01B/2018/CPGU/PPCR / Recrutement Consultant Expert National en résilience Strengthening climate climatique et gestion des TF / A5362 resilience and climate risk A posteriori Individuel Open 18,312.78 Signé 2018-08-10 2018-09-28 2018-10-19 2018-11-23 2019-01-22 risques et des catastrophes management pour le diagnostic sur les politiques publiques et capacités institutionnelles Page 6 C11A/2018/CPGU/PPCR / Recrutement Consultant Expert International en Strengthening climate finances publiques pour les TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 Annulé 2018-08-10 2018-08-15 2018-09-05 2018-10-10 2018-12-09 Etudes sur les impacts management économiques et budgétaires des catastrophes à Madagascar C11B/2018/CPGU/PPCR / Recrutement Consultant Expert National en finances Strengthening climate publiques pour les Etudes TF / A5362 resilience and climate risk A posteriori Individuel Open 3,469.22 Signé 2018-08-10 2018-09-28 2018-10-19 2018-11-23 2019-01-22 sur les impacts économiques management et budgétaires des catastrophes à Madagascar C11C/2018/CPGU/PPCR / Recrutement Consultant Expert National en Résilience climatique et Strengthening climate Gestion des Risques et des TF / A5362 resilience and climate risk A posteriori Individuel Open 3,016.22 Signé 2018-08-10 2018-09-28 2018-10-19 2018-11-23 2019-01-22 Catastrophes pour les management Etudes sur les impacts économiques et budgétaires des catastrophes à Madagascar C20A/2018/CPGU/PPCR / Recrutement Consultant Firm pour les Formation et sensibilisation sur les Strengthening climate Sélection de directives de construction des TF / A5362 resilience and climate risk A posteriori consultants par Direct 28,176.40 Achevé 2018-08-10 2018-08-20 2018-10-24 2018-12-23 infrastructures concernant management entente directe l'alimentation en eaux potables (AEP) résilientes aux aléas climatiques C13A/2018/CPGU/PPCR / Strengthening climate Traduction en Français du TF / A5362 resilience and climate risk A posteriori Individuel Direct 2,017.33 Achevé 2018-06-28 2018-07-08 2018-07-22 2018-08-26 2018-10-25 document SPCR et des plans management d'investissement C27A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Expert national pour TF / A5362 resilience and climate risk A posteriori Individuel Limited 8,420.59 Signé 2018-09-10 2018-09-15 2018-10-06 2018-11-10 2019-01-09 l'Élaboration des projets de management textes relatifs à la GRC C24A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Expert national pour la TF / A5362 resilience and climate risk A posteriori Individuel Limited 2,194.80 Achevé 2018-09-20 2018-09-25 2018-10-16 2018-11-20 2018-12-20 Formation en GRC de la management CPGU en tant qu'AGEX C25A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Expert pour Facilitation des TF / A5362 resilience and climate risk A posteriori Individuel Limited 787.41 Achevé 2018-09-28 2018-10-03 2018-10-24 2018-11-28 2019-11-23 team-building du CPGU et management des team-building du CAMEO PPCR C23A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Sélection de Firm pour Formation en TF / A5362 resilience and climate risk A posteriori consultants par Direct 2,781.91 Achevé 2018-09-20 2018-09-30 2018-12-04 2019-01-03 Gestion de projet de la management entente directe CPGU en tant qu'AGEX Page 7 C26A/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate Sélection de Firm pour Formation en TF / A5362 resilience and climate risk A posteriori consultants par Direct 20,000.00 Signé 2018-09-20 2018-09-30 2018-12-04 2019-01-03 Résilience climatique du management entente directe CAMEO PPCR C01AI/2018/CPGU/PPCR / Recrutement Consultant International Expert en Analyse politiques, institutionnelles et de Strengthening climate gouvernance pour le TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 Annulé 2018-08-28 2018-09-02 2018-09-23 2018-10-28 2018-12-27 diagnostic sur les politiques management publiques et capacités institutionnelles en matière de résilience climatique et GRC à Madagascar C11AI/2018/CPGU/PPCR / Recrutement Consultant Expert International en Strengthening climate finances publiques pour les TF / A5362 resilience and climate risk A posteriori Individuel Limited 16,416.00 Signé 2018-08-28 2018-09-02 2018-09-23 2018-10-28 2018-12-27 Etudes sur les impacts management économiques et budgétaires des catastrophes à Madagascar 004/2019-CI/CPGU/PPCR / Responsable Administratif financier sera chargé Implementation Support and d'assurer la gestion des TF / A5362 A posteriori Individuel Open 13,868.99 Signé 2019-01-04 2019-02-22 2019-03-15 2019-04-19 2019-10-16 M&E ressources allouées au projet (financières, humaines et matérielles) MG-CPGU-93750-CS-INDV / Le Responsable en Passation de Marchés sera chargé d'assurer toutes les étapes de la passation de marchés Implementation Support and TF / A5362 A posteriori Individuel Open 13,839.47 Signé 2019-01-04 2019-02-01 2019-02-15 2019-02-27 2020-08-27 (publication, présélection, M&E préparation des documents d'appel d'offres, l'évaluation des offres et l'attribution du marché. CI28/2019/CPGU/PPCR / Recrutement du Responsable Implementation Support and Technique du Programme TF / A5362 A posteriori Individuel Direct 11,581.07 Signé 2019-02-01 2019-02-07 2019-02-11 2019-02-15 2019-12-31 M&E Pilote pour la Résilience Climatique (PPCR) C05A/2018/CPGU/PPCR-2 / Recrutement Consultant Strengthening climate Sélection de Firm pour l'Etablissement et En cours TF / A5362 resilience and climate risk A posteriori consultants par Direct 0.00 2019-02-22 2019-03-04 2019-05-08 2019-11-04 la vulgarisation des Atlas d'exécution management entente directe des risques et de vulnérabilité C12A/2019/CPGU/PPCR / Détermination d'une Strengthening climate Sélection de méthodologie d'intégration de En cours TF / A5362 resilience and climate risk A posteriori consultants par Direct 0.00 2019-02-18 2019-02-28 2019-05-04 2019-10-31 résilience climatique dans les d'exécution management entente directe politiques, les plans et les stratégies sectorielles clés. C27B/2018/CPGU/PPCR / Recrutement Consultant Strengthening climate En cours Expert national pour la TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 2019-02-18 2019-02-23 2019-03-16 2019-04-20 2019-06-19 d'exécution Finalisation du plan d'action management GRC Page 8 C29/2019/CPGU/PPCR / Formation et sensibilisation Strengthening climate Sélection de sur les directives de TF / A5362 resilience and climate risk A posteriori consultants par Direct 7,214.15 Signé 2019-02-18 2019-02-28 2019-04-09 2019-05-09 construction des management entente directe infrastructures concernant l'AEP CI30/2019/CPGU/PPCR / Strengthening climate En cours Consultant Facilitateur - TF / A5362 resilience and climate risk A posteriori Individuel Direct 0.00 2019-04-12 2019-04-22 2019-04-29 2019-05-20 2019-05-27 d'exécution Team Building CAMEO management CI31/2019/CPGU/PPCR / Strengthening climate Consultant - facilitateur - TF / A5362 resilience and climate risk A posteriori Individuel Direct 0.00 Annulé 2019-11-03 2019-11-13 2019-11-20 2019-12-11 2019-12-13 TEAM BUILDING CPGU management C14A/2018/CPGU/PPCR / Recrutement Consultant Expert pour les Etudes de Development of the SPCR vulnérabilité en vue de la TF / A5362 A posteriori Individuel Limited 0.00 Annulé 2019-03-15 2019-03-20 2019-04-10 2019-05-15 2019-07-14 and investment plan mise en oeuvre d'un projet de résilience des villes côtières de Madagascar CI35B/2019/CPGU/PPCR / Service d'un EXPERT NATIONAL EN GESTION Strengthening climate FINANCIERE pour TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 Annulé 2019-09-05 2019-09-10 2019-10-01 2019-10-30 2019-12-29 l'élaboration de manuel de management procédures de gestion de fonds national de contingence CI33/2019/CPGU/PPCR / Élaboration de plans de Strengthening climate continuité des services En attente TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 2019-09-10 2019-09-15 2019-09-30 2019-10-24 2019-12-23 essentiels de base (eau, d'exécution management santé, énergie- hydrocarbures...) CI35A/2019/CPGU/PPCR / Service d'un EXPERT NATIONAL JURISTE pour Strengthening climate l'élaboration de manuel de TF / A5362 resilience and climate risk A posteriori Individuel Limited 0.00 Annulé 2019-09-12 2019-09-17 2019-10-02 2019-10-28 2019-12-27 procédures de gestion de management fonds de contingence national CI32/2019/CPGU/PPCR / Etude de développement de Strengthening climate En cours Plan stratégique de la mise TF / A5362 resilience and climate risk A posteriori Individuel Direct 0.00 2019-09-10 2019-09-20 2019-10-05 2019-10-27 2019-12-26 d'examen en place de structure management décentralisée du BNGRC MG-CPGU-156103-CS-INDV / Service d'un EXPERT NATIONAL EN GESTION FINANCIÈRE pour Implementation Support and En attente TF / A5362 A posteriori Individuel Limited 0.00 2020-02-03 2020-02-08 2020-02-15 2020-02-29 2020-05-29 l'élaboration de manuel de M&E d'exécution procédures de gestion de fonds national de contingence MG-CPGU-156105-CS-INDV / Service d'un EXPERT NATIONAL JURISTE pour Implementation Support and En attente l'élaboration de manuel de TF / A5362 A posteriori Individuel Limited 0.00 2020-02-03 2020-02-08 2020-02-15 2020-02-29 2020-05-29 M&E d'exécution procédures de gestion de fonds de contingence national Page 9 MG-CPGU-156106-CS-INDV / Élaboration de projet de Implementation Support and En attente TF / A5362 A posteriori Individuel Direct 0.00 2020-02-03 2020-02-13 2020-02-20 2020-03-05 2020-05-04 texte d'application de la M&E d'exécution PNRRC MG-CPGU-156112-CS-INDV / Consultant - facilitateur - Implementation Support and En attente TF / A5362 A posteriori Individuel Direct 0.00 2020-04-02 2020-04-12 2020-04-19 2020-05-10 2020-05-17 TEAM BUILDING DE LA M&E d'exécution CPGU CI36/2020/CPGU/PPCR / Consultant - facilitateur - Implementation Support and En attente TF / A5362 A posteriori Individuel Direct 0.00 2020-01-28 2020-01-30 2020-01-31 2020-02-02 2020-02-09 TEAM BUILDING DU M&E d'exécution CAMEO Page 10