Nigeria For Women Project PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Nigeria For Women Project] P161364] Project Implementation agency: [Federal Ministry of Women Affairs and Social Development] Date of the Procurement Plan: [August 31, 2018] Period covered by this Procurement Plan: [August 31,2018 to December 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project will use the CDD procurement under this project. CDD manual will be produced by the project. PROCUREMENT Nigeria : Nigeria For Women Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-09-10 2020-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161364 GPN Date: Project Name: Nigeria For Women Project Loan / Credit No: IDA / V1770, IDA / 62710 Executing Agency(ies): Federal Ministry of Women Affairs and Social Development WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-MOSWAD-82940-CW- RFQ / Partitioning of FPIU Project Management, Request for Single Stage - One Nigeria For Women Project IDA / 62710 Monitoring and Evaluation Post Limited 26,230.00 22,614.17 Completed 2018-10-29 2018-11-19 2018-12-24 2018-12-04 2019-01-07 Quotations Envelope (NFWP) Office and Learning Accommodation Abuja. NG-MOSWAD-103885-CW- Project Management, Request for Single Stage - One RFQ / Minor Rehabilitation IDA / 62710 Monitoring and Evaluation Post Limited 25,000.00 11,170.37 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-11 2019-10-29 Quotations Envelope at the FPIU Office Abuja and Learning NG-MOSWAD-103895-CW- Project Management, Request for Single Stage - One RFQ / Car Ports for the Six IDA / 62710 Monitoring and Evaluation Post Limited 60,000.00 54,964.58 Completed 2019-03-07 2019-04-03 2019-05-02 2019-06-14 2019-10-29 Quotations Envelope (6) SPIUs and Learning NG-MOSWAD-103896-CW- Project Management, Request for Single Stage - One RFQ / Car Ports at the IDA / 62710 Monitoring and Evaluation Post Limited 15,000.00 87,850.95 Completed 2019-03-07 2019-08-02 2019-05-02 2019-08-26 2019-10-29 Quotations Envelope FPIU Office, Abuja and Learning NG-MOSWAD-111048-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-04 2019-06-29 2019-12-26 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Abia State NG-MOSWAD-110078-CW- RFQ / Partitioning of six (6) SPIUs Offices in Abia, Project Management, Ogun, Edo, Taraba, Niger Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 198,000.00 0.00 Canceled 2019-04-20 2019-06-15 2019-12-12 and Kebbi States. The Quotations Envelope and Learning works are scattered in the states. NCB will not be a better method. NG-MOSWAD-112236-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-14 2019-07-09 2020-01-05 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Edo State NG-MOSWAD-112237-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-04 2019-06-29 2019-12-26 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Ogun State NG-MOSWAD-112238-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-04 2019-06-29 2019-12-26 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Taraba State Page 1 NG-MOSWAD-112239-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-04 2019-06-29 2019-12-26 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Niger State NG-MOSWAD-112240-CW- Project Management, Pending RFQ / Minor Rehabilitation Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 0.00 Implementat 2019-05-04 2019-06-29 2019-12-26 and Partitioning of SPIU Quotations Envelope and Learning ion Offices in Kebbi State NG-MOSWAD-120009-CW- RFQ / Minor landscaping Project Management, work of the FPIU office Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 35,000.00 0.00 Canceled 2019-06-29 2019-08-24 2020-02-20 premises including the back Quotations Envelope and Learning view with 40 Ft. container Offices. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-76402-GO- Project Management, RFQ / Procurement of Request for Single Stage - One IDA / V1770 Monitoring and Evaluation Prior Limited 245,538.00 315,098.37 Completed 2018-09-22 2018-10-30 2018-11-17 2019-01-11 2019-05-16 2019-03-13 Operational Vehicles for the Quotations Envelope and Learning Federal Coordinating Unit NG-MOSWAD-83083-GO- RFQ / Procurement of Project Management, Request for Single Stage - One Computers, Accessories and IDA / 62710 Monitoring and Evaluation Post Limited 34,279.00 82,422.60 Completed 2018-10-30 2018-11-19 2018-12-25 2018-12-19 2019-06-23 2018-12-23 Quotations Envelope related Items for the FPIU, and Learning Nigeria for Women Project. NG-MOSWAD-83354-GO- RFQ / Procurement of Fiber Project Management, Internet and Server Room Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 64,793.00 54,726.34 Completed 2018-10-28 2018-11-20 2018-12-23 2018-12-04 2019-06-21 2019-02-13 Implementation for the Quotations Envelope and Learning FPIU, Nigeria For Women Project. NG-MOSWAD-83360-GO- Project Management, RFQ / Procurement of Video Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 50,417.00 42,748.76 Completed 2018-10-29 2018-11-20 2018-12-24 2018-12-05 2019-06-22 2018-12-31 Conferencing device for FPIU Quotations Envelope and Learning of NFWP's Office. NG-MOSWAD-83367-GO- Project Management, Request for Single Stage - One RFQ / Procurement of IDA / 62710 Monitoring and Evaluation Post Limited 9,054.00 7,676.97 Completed 2018-10-30 2018-11-20 2018-12-25 2018-12-05 2019-06-23 2018-12-31 Quotations Envelope Inverter for FPIU of and Learning NFWP's Office. NG-MOSWAD-83925-GO- Project Management, DIR / Procurement of IDA / 62710 Monitoring and Evaluation Prior Direct Selection Direct 22,951.00 18,348.00 Completed 2018-10-29 2018-12-18 2018-11-03 2019-02-15 2018-12-08 2019-03-27 2019-06-06 2019-07-08 Accounting Software and Learning (Flexible) NG-MOSWAD-98241-GO- Project Management, Request for Single Stage - One RFQ / Air Conditioners for IDA / 62710 Monitoring and Evaluation Post Limited 5,500.00 12,750.33 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-05 2019-09-30 2019-03-07 Quotations Envelope FPCU, Abuja and Learning NG-MOSWAD-98243-GO- Project Management, Request for Single Stage - One RFQ / Sound Proof Standby IDA / 62710 Monitoring and Evaluation Post Limited 20,500.00 16,897.00 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-05 2019-09-30 2019-03-07 Quotations Envelope Generator and Learning Page 2 NG-MOSWAD-98249-GO- RFQ / ICT, Security Project Management, Equipment and Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 14,000.00 25,720.76 Completed 2019-02-06 2019-02-18 2019-04-03 2019-03-07 2019-09-30 2019-04-18 Installation(Digital Camera, Quotations Envelope and Learning DSTV, CCTV, INTERCOM Facility and TV sets. NG-MOSWAD-98287-GO- Project Management, RFQ / Computers, Printers, Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 35,000.00 82,762.61 Completed 2019-02-06 2018-11-26 2019-04-03 2018-12-19 2019-09-30 2018-12-23 Photocopiers etc. for FPIU Quotations Envelope and Learning additional Staff NG-MOSWAD-98238-GO- Project Management, Request for Single Stage - One RFQ / Operational Vehicles IDA / 62710 Monitoring and Evaluation Post Limited 364,312.00 0.00 Canceled 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Quotations Envelope for Six (6) SPIU States and Learning NG-MOSWAD-103888-GO- RFQ / Window Blinds and Project Management, Internal Decorations at Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 60,000.00 40,021.80 Completed 2019-03-07 2019-04-02 2019-05-02 2019-06-28 2019-10-29 2020-01-20 SPIUs Offices in Abia, Quotations Envelope and Learning Ogun, Edo, Taraba, Niger and Kebbi States NG-MOSWAD-103889-GO- Project Management, RFQ / Window Blinds and Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 15,000.00 5,219.58 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-10 2019-10-29 2019-04-30 Internal Decorations at Quotations Envelope and Learning FPIU Abuja NG-MOSWAD-103891-GO- Project Management, Request for Single Stage - One RFQ / 40 Ft. Container for IDA / 62710 Monitoring and Evaluation Post Limited 30,000.00 20,000.00 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-09 2019-10-29 2019-06-27 Quotations Envelope use at FPIU Abuja and Learning NG-MOSWAD-103897-GO- Project Management, Request for Single Stage - One RFQ / Kitchen Utensils for IDA / 62710 Monitoring and Evaluation Post Limited 1,500.00 1,797.08 Completed 2019-03-07 2019-04-03 2019-05-02 2019-05-13 2019-10-29 2019-06-10 Quotations Envelope use at FPIU Office Abuja and Learning NG-MOSWAD-103986-GO- RFQ / Furnishing of an Project Management, Request for Single Stage - One Office for the Hon. IDA / 62710 Monitoring and Evaluation Post Limited 20,000.00 15,856.38 Completed 2019-03-08 2019-04-03 2019-05-03 2019-04-22 2019-10-30 2019-05-07 Quotations Envelope Minister/Permanent Secretary and Learning at the FPIU Office Abuja NG-MOSWAD-110063-GO- RFB / Office Furniture for States Project Project Management, Pending Single Stage - One Implementation Units IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 450,000.00 0.00 Implementati 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope (SPIUs) in Abia, Edo, Ogun, and Learning on Taraba, Niger and Kebbi States under NCB2, Lot 1 NG-MOSWAD-76400-GO- Project Management, Request for Single Stage - One RFQ / Procurement of IDA / V1770 Monitoring and Evaluation Post Limited 50,000.00 41,978.38 Completed 2018-09-19 2018-11-19 2018-11-14 2018-12-05 2019-05-13 2019-01-25 Quotations Envelope Furniture and Equipment and Learning for FPMU NG-MOSWAD-110061-GO- RFB / Fed. Support Ministries & SPIUs NCB1 Lot 1 - Computers & Office Rel. Equip. NCB1 Lot 2 - Video Conferencing, Internet Project Management, Pending Single Stage - One Servers, Inverters etc IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 1,410,000.00 0.00 Implementati 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope NCB1 Lot 3 - Generating and Learning on Sets NCB1 Lot 4 - Air Conditioners, Refrigerators etc NCB1 Lot 5 - Seurity/Comm. Equip. Page 3 NG-MOSWAD-98294-GO- RFQ / Office Computers, Project Management, Request for Single Stage - One Accessories and Related IDA / 62710 Monitoring and Evaluation Post Limited 85,000.00 0.00 Canceled 2019-02-06 2019-04-03 2019-09-30 Quotations Envelope Equipment for Abia State and Learning Project Implementation Unit NG-MOSWAD-112242-GO- RFQ / External Diesel Tank Project Management, Request for Single Stage - One (1500 Liters) and Armored IDA / 62710 Monitoring and Evaluation Post Limited 4,500.00 3,227.59 Completed 2019-05-04 2019-07-09 2019-06-29 2019-09-03 2019-12-26 2020-01-18 Quotations Envelope Cable 4x35mm2 (30mtrs) for and Learning FPIU Office, Abuja NG-MOSWAD-120020-GO- RFQ / Supply and Installation of Furniture and Project Management, Request for Single Stage - One fittings for the 40 Ft. IDA / 62710 Monitoring and Evaluation Post Limited 45,000.00 31,774.03 Completed 2019-06-29 2019-08-01 2019-08-24 2019-08-19 2020-02-20 2019-08-26 Quotations Envelope Container Offices along with and Learning an adjacent office at the FPIU NG-MOSWAD-126199-GO- RFQ / Federal Support Ministries Equipment Project Management, (FMWASD, FMF, OAGF - Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 50,000.00 33,974.41 Completed 2019-08-19 2019-08-15 2019-10-14 2019-09-05 2020-04-11 2019-09-27 10 Desktops, 2 Laptops, 10 Quotations Envelope and Learning Printers/Photocopiers and Accessories (Power Surge, UPS, Stabilizers etc) plus NG-MOSWAD-127532-GO- Project Management, Request for Single Stage - One RFQ / Camera and Projector IDA / 62710 Monitoring and Evaluation Post Limited 1,500.00 918.21 Completed 2019-08-24 2019-08-22 2019-10-19 2019-09-03 2020-04-16 2019-09-09 Quotations Envelope Accessories and Learning NG-MOSWAD-130318-GO- RFQ / Office Computers and other Equipment and Project Management, Accessories Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 45,000.00 33,633.80 Completed 2019-09-14 2019-09-10 2019-11-09 2019-10-07 2020-05-07 2020-01-18 (Printers/photocopiers, Quotations Envelope and Learning Computers etc) for the New Minister New Staff at the FPIU NG-MOSWAD-110072-GO- RFB / Security/Communication Equipment and Accessories Project Management, for States Project Single Stage - One IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 75,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Implementation Units Envelope and Learning (SPIUs) in Abia, Edo, Ogun, Taraba, Niger and Kebbi States under NCB1, Lot 5. NG-MOSWAD-110070-GO- RFB / Air Conditioners and Accessories, Refrigerators and Water Dispensers for Project Management, Single Stage - One States Project IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope Implementation Units and Learning (SPIUs) in Abia, Ogun, Edo, Taraba, Niger and Kebbi States under NCB1, Lot 4 NG-MOSWAD-110069-GO- RFB / Generating Sets and for States Project Project Management, Single Stage - One Implementation Units IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 120,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope (SPIUs) in Abia, Ogun, Edo, and Learning Taraba, Niger and Kebbi States under NCB1, Lot 3 Page 4 NG-MOSWAD-110071-GO- RFB / Video Conferencing Device, Fibre Internet & Server, Power Inverters for Project Management, Single Stage - One States Project IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 570,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope Implementation Units and Learning (SPIUs) in Abia, Edu, Ogun, Taraba, Niger and Kebbi States under NCB1, Lot2 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-98350-NC- RFQ / Insurance cover for Project Management, Under Request for Single Stage - One Project Vehicles (4Nos IDA / 62710 Monitoring and Evaluation Post Limited 50,000.00 19,304.31 Implementati 2019-02-06 2019-04-11 2019-04-03 2019-04-25 2019-09-30 2019-05-03 Quotations Envelope Vehicles at FPIU and 6Nos and Learning on at SPIUs) NG-MOSWAD-98355-NC- Project Management, Request for Single Stage - One RFQ / Security Guards for IDA / 62710 Monitoring and Evaluation Post Limited 20,000.00 15,247.84 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-06 2019-09-30 2020-03-02 Quotations Envelope NFWP Office, Abuja and Learning NG-MOSWAD-98360-NC- Project Management, Request for Single Stage - One RFQ / Cleaning Services for IDA / 62710 Monitoring and Evaluation Post Limited 18,000.00 15,017.46 Completed 2019-02-09 2019-02-15 2019-04-06 2019-03-04 2019-10-03 2020-03-03 Quotations Envelope NFWP Ofiice, Abuja. and Learning NG-MOSWAD-103985-NC- RFQ / Production and Project Management, Request for Single Stage - One Printing of Thematic Reports IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 46,250.74 Completed 2019-03-08 2019-06-06 2019-05-03 2019-07-05 2019-10-30 2019-07-25 Quotations Envelope plus other project and Learning documents CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-95169-CS- CQS / Community Services Project Management, Consultant on Baseline Survey and Risk IDA / 62710 Monitoring and Evaluation Post Qualification Limited 180,000.00 135,243.72 Signed 2019-01-26 2019-02-24 2019-02-09 2019-05-13 2019-03-11 2019-06-10 2019-04-15 2019-06-11 2019-10-12 Planning (3) tier States and Learning Selection Northern States NG-MOSWAD-95173-CS- CQS / Community Services Project Management, Consultant on Baseline Survey & Risk IDA / 62710 Monitoring and Evaluation Post Qualification Limited 150,000.00 119,918.39 Signed 2019-01-26 2019-02-24 2019-02-09 2019-05-13 2019-03-11 2019-06-10 2019-04-15 2019-06-11 2019-10-12 Planning Local/Community/ and Learning Selection Assessment three(3) tier Southern States NG-MOSWAD-110287-CS- CQS / Communication Project Management, Consultant Under Strategy Consultant - IDA / 62710 Monitoring and Evaluation Post Qualification Limited 250,000.00 0.00 2019-04-15 2019-07-09 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Implementation (Preparation of and Learning Selection Communication Strategy) NG-MOSWAD-95144-CS- Project Management, Consultant CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Qualification Open - National 250,000.00 0.00 Canceled 2019-02-18 2019-03-29 2019-03-11 2019-04-24 2019-05-24 2019-06-28 2019-12-25 Contract Recruitment Agency and Learning Selection Page 5 NG-MOSWAD-110289-CS- CQS / HR Recruitment Project Management, Consultant Agency/Firm for the Under IDA / 62710 Monitoring and Evaluation Post Qualification Limited 250,000.00 0.00 2019-04-15 2019-08-23 2019-04-29 2019-07-10 2019-05-29 2019-07-03 2019-12-30 recruitment of various staff, Implementation and Learning Selection Advisers and Young Professionals NG-MOSWAD-120004-CS- Project Management, Consultant CQS / Local Government IDA / 62710 Monitoring and Evaluation Post Qualification Limited 200,000.00 0.00 Under Review 2019-06-24 2019-08-23 2019-07-08 2019-08-07 2019-09-11 2020-03-09 Areas (LGAs) Facilitating and Learning Selection Consultants NG-MOSWAD-172802-CS- CQS / Engagement of Project Management, Consultant Consultant for the Design Under IDA / 62710 Monitoring and Evaluation Post Qualification Limited 255,000.00 0.00 2020-05-12 2020-05-19 2020-05-26 2020-06-22 2020-06-25 2020-07-30 2021-01-26 and Deployment of Implementation and Learning Selection Management Information System(MIS) NG-MOSWAD-173091-CS- Consultant CQS / Engagement of GBV IDA / 62710 Building Social Capital Post Qualification Limited 190,850.00 0.00 Canceled 2020-05-12 2020-05-20 2020-05-26 2020-06-25 2020-07-30 2021-01-26 Mapping Consultant Selection NG-MOSWAD-177289-CS- Project Management, Least Cost CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Open - National 6,000.00 0.00 Canceled 2020-06-02 2020-06-02 2020-06-23 2020-08-06 2020-09-03 2020-10-03 2020-11-07 2020-12-12 2021-06-10 Selection External Auditor for NFWP and Learning NG-MOSWAD-177711-CS- Project Management, Consultant Under CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Qualification Limited 6,000.00 0.00 2020-06-03 2020-06-03 2020-06-17 2020-06-12 2020-07-17 2020-06-14 2020-08-21 2021-02-17 Implementation External Auditor for NFWP and Learning Selection NG-MOSWAD-112241-CS- Project Management, Consultant CQS / Web Development, IDA / 62710 Monitoring and Evaluation Post Qualification Limited 50,000.00 0.00 Canceled 2019-04-29 2019-05-13 2019-06-12 2019-07-17 2020-01-13 Hosting and Management and Learning Selection Consultant/Firm INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-76579-CS- Project Management, Individual INDV / Engagement of IDA / V1770 Monitoring and Evaluation Prior Consultant Limited 60,000.00 90,604.80 Signed 2018-09-17 2018-11-09 2018-09-22 2018-11-27 2018-10-13 2018-12-18 2018-11-17 2018-12-04 2019-05-16 Procurement Consultant and Learning Selection NG-MOSWAD-95162-CS- INDV / Engagement of 1 Executive Assistant, 1 Young Project Management, Individual Nigerian Professional and 1 IDA / 62710 Monitoring and Evaluation Post Consultant Open 80,000.00 0.00 Under Review 2019-01-16 2019-06-24 2019-03-06 2019-03-27 2019-05-01 2019-10-28 Administrative Assistance and Learning Selection under the Federal Project Coordinator's Office NG-MOSWAD-95295-CS- Project Management, Individual INDV / Grievance Redress & IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Under Review 2019-01-26 2019-04-19 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Feedback Mechanism and Learning Selection NG-MOSWAD-95298-CS- Project Management, Individual INDV / Community IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Under Review 2019-01-26 2019-02-24 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Institution Building Adviser and Learning Selection NG-MOSWAD-103892-CS- Project Management, Individual INDV / Community IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 9,155.38 Completed 2019-03-02 2019-04-19 2019-03-07 2019-07-08 2019-03-28 2019-07-31 2019-05-02 2019-08-05 2019-10-29 2020-01-28 Procurement Manual and Learning Selection Consultant Page 6 NG-MOSWAD-103982-CS- INDV / Engagement of 15 Young Nigerian Professionals by the Recruitment Agency - (To support the following Project Management, Individual Advisers - (Livehood, BCC, IDA / 62710 Monitoring and Evaluation Post Consultant Open 225,000.00 0.00 Under Review 2019-03-03 2019-10-30 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Community Institution and Learning Selection Building, Gender, Innovation & Partnership, Project Comm & Public Relations, M&E, Fin Mgt. & Proc. Spec.) NG-MOSWAD-103984-CS- INDV / Engagement of a Project Management, Individual Web Developer for FPIU, IDA / 62710 Monitoring and Evaluation Post Consultant Open 50,000.00 0.00 Canceled 2019-03-03 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Abuja and SPIUs in Abia, and Learning Selection Ogun, Edo, Taraba, Niger and Kebbi States NG-MOSWAD-103987-CS- INDV / Engagement of IT Project Management, Individual Under Staff to handle ICT related IDA / 62710 Monitoring and Evaluation Post Consultant Limited 20,000.00 0.00 2019-03-03 2019-06-24 2019-03-08 2019-03-29 2019-05-03 2019-10-30 Implementation problems in FPIU Office, and Learning Selection Abuja NG-MOSWAD-98348-CS- Project Management, Individual INDV / Community Driven IDA / 62710 Monitoring and Evaluation Prior Consultant Limited 10,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Manual Consultant and Learning Selection NG-MOSWAD-115087-CS- Project Management, Individual INDV / Community Driven Under IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 0.00 2019-05-20 2019-06-12 2019-05-25 2019-06-15 2019-07-20 2020-01-16 Development Operations Implementation and Learning Selection Manual NG-MOSWAD-116137-CS- INDV / Supervision Engineer for the Minor Rehabilitation Project Management, Individual and Partitioning in the Six IDA / 62710 Monitoring and Evaluation Post Consultant Limited 25,000.00 21,502.27 Completed 2019-05-27 2019-06-14 2019-06-01 2019-06-25 2019-06-22 2019-07-24 2019-07-27 2019-07-29 2020-01-23 2020-01-20 States Projects and Learning Selection Implementation Units (SPIUs) Offices NG-MOSWAD-75969-CS- INDV / Engagement of Project Management, Individual Consultant for the IDA / V1770 Monitoring and Evaluation Post Consultant Open 10,000.00 0.00 Canceled 2018-10-24 2019-01-06 2018-12-12 2019-01-02 2019-02-06 2019-08-05 Preparartion of Community- and Learning Selection Driven Developent Manual NG-MOSWAD-126201-CS- Project Management, Individual INDV / Technical Assistant IDA / 62710 Monitoring and Evaluation Post Consultant Limited 30,000.00 13,601.92 Signed 2019-08-19 2019-08-29 2019-08-24 2019-10-25 2019-09-14 2019-11-05 2019-10-19 2019-11-05 2020-04-16 (1 No.) and Executive and Learning Selection Assistant (1 No.) NG-MOSWAD-126196-CS- Project Management, Individual INDV / Niger State Project IDA / 62710 Monitoring and Evaluation Post Consultant Limited 65,000.00 4,548.59 Signed 2019-08-19 2019-09-03 2019-08-24 2019-09-17 2019-09-14 2019-09-17 2019-10-19 2019-05-09 2020-04-16 Coordinator Engagement and Learning Selection NG-MOSWAD-126193-CS- Project Management, Individual INDV / Edo State Project IDA / 62710 Monitoring and Evaluation Post Consultant Limited 65,000.00 54,583.06 Signed 2019-08-19 2019-09-03 2019-08-24 2019-09-17 2019-09-14 2019-09-17 2019-10-19 2019-05-09 2020-04-16 Coordinator Engagement and Learning Selection NG-MOSWAD-127527-CS- Project Management, Individual INDV / Community IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Under Review 2019-08-26 2019-10-30 2019-10-14 2019-10-29 2019-12-03 2020-05-31 Institution Building Adviser and Learning Selection Page 7 NG-MOSWAD-130316-CS- INDV / Engagement of Local Government Area Coordinators by the HR Firm for the six SPCUs as follows: Project Management, Individual 1. Abia State - 3No IDA / 62710 Monitoring and Evaluation Prior Consultant Open 500,000.00 0.00 Under Review 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 2. Edo State - 3 No and Learning Selection 3 Ogun State - 3No 4. Taraba State - 3No 5. Kebbi State - 3 No 6. Niger State - 3 No Total for the six States is 18 NG-MOSWAD-174588-CS- Under CDS / Engagement of GBV IDA / 62710 Building Social Capital Prior Direct Selection Direct 460,000.00 0.00 2020-05-21 2020-06-03 2020-05-31 2020-06-19 2020-08-04 2021-01-31 Implementation Mapping Consultant Firm Project Management, Individual NG-MOSWAD-127353-CS- IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 0.00 Canceled 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 INDV / Front Desk Officer and Learning Selection NG-MOSWAD-95299-CS- Project Management, Individual INDV / Innovation and IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Canceled 2019-01-26 2019-02-21 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Partnership Adviser and Learning Selection NG-MOSWAD-95164-CS- Project Management, Individual INDV / Project IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Canceled 2019-02-25 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-08-09 Communication / Public and Learning Selection relation Adviser NG-MOSWAD-94721-CS- Project Management, Individual CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Canceled 2019-02-04 2019-02-24 2019-03-09 2019-03-30 2019-05-04 2019-10-31 Monitoring & Evaluation and Learning Selection Specialist by FPCU, NFWP NG-MOSWAD-76026-CS- Individual INDV / Engagement IDA / V1770 Livelihoods Program Post Consultant Limited 90,000.00 0.00 Canceled 2018-10-02 2019-01-02 2018-10-07 2018-10-28 2018-12-02 2019-05-31 Livelihood Support Technical Selection Expert NG-MOSWAD-130317-CS- INDV / Engagement of Facilitators for LGAs and Wards by HR Firm for the Six SPCUs as follows: 1. Abia State - 9No Project Management, Individual 2. Edo State - 9No IDA / 62710 Monitoring and Evaluation Prior Consultant Open 600,000.00 0.00 Canceled 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 3. Ogun State - 9No and Learning Selection 4. Taraba State - 9No 5. Kebbi State - 9No 6. Niger State - 9No Total for the six States is 54 NG-MOSWAD-76015-CS- Project Management, Individual INDV / Engagement of IDA / V1770 Monitoring and Evaluation Post Consultant Limited 40,000.00 0.00 Canceled 2018-10-02 2019-01-02 2018-10-12 2018-11-02 2018-12-07 2019-06-05 Gender Specialist and Learning Selection NG-MOSWAD-103983-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Open 80,000.00 0.00 Canceled 2019-03-03 2019-04-19 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Behavioral Change and Learning Selection Communication Adviser NG-MOSWAD-114531-CS- Project Management, Individual INDV / Procurement IDA / 62710 Monitoring and Evaluation Prior Consultant Open 300,000.00 0.00 Canceled 2019-05-13 2019-09-12 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Consultants (6Nos) to and Learning Selection support the Six (6) SPIUs Page 8 NG-MOSWAD-76030-CS- Project Management, Individual INDV / Engagement of IDA / V1770 Monitoring and Evaluation Post Consultant Limited 40,000.00 0.00 Canceled 2018-10-02 2019-02-21 2018-10-07 2018-10-28 2018-12-02 2019-05-31 Social Environmental and Learning Selection Safeguards Specialist NG-MOSWAD-140893-CS- Project Management, Individual INDV / Project IDA / 62710 Monitoring and Evaluation Post Consultant Limited 20,000.00 0.00 Canceled 2019-10-17 2019-10-22 2019-11-12 2019-12-17 2020-06-14 Implementation Manual and Learning Selection (PIM) Review Consultant NG-MOSWAD-76033-CS- INDV / Engagement of Consultant for the Project Management, Individual Preparartion of Project IDA / V1770 Monitoring and Evaluation Post Consultant Limited 30,000.00 0.00 Canceled 2018-10-24 2018-10-23 2018-10-29 2018-12-07 2018-11-19 2018-12-24 2019-06-22 Implementation and Learning Selection Manual(Federal Coordinating Office and States PIUs Page 9