Procurement Plan COFFEE SECTOR COMPETITIVENESS PROJECT I. General 1. Project information: Country: Burundi Borrower: Government of Burundi Project Name: Coffee Sector Competitiveness Project Grant No: TBC Project ID No: P151869 Project Implementing Agencies: Ministry of Agriculture and Livestock 2. Bank’s approval Date of the procurement Plan [Negotiations Date: TBC] 3. Date of General Procurement Notice: TBC 4. Period covered by this procurement plan: 30-Sep-2015– 31-mars-2017 (18 months) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments 1. ICB and LIB (Goods)  500,000 2. NCB (Goods)  500,000 3. ICB (Works)  5,000,000 4. NCB (Works)  5, 000,000 5. ICB (Non-Consultant Services)  500,000 2. Prequalification. Bidders for _____________ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA La Participation communautaire à la passation de marchés sera utilisée pour les marchés à réaliser au niveau des sous-projets. [To be more elaborated in project implementation manual and community related documents]. The goods, works and services will be procured following simplified procurement procedures as described in the PIM for community-based projects. Under the PIM the main procurement methods to be used would be the following: (i) Shopping for goods and works where quotations are solicited from at least three qualified suppliers or contractors on basis of simplified documents; (ii) Local bidding for goods and works which is an open competition similar to NCB apart from that the invitation for bids is advertised using radio, local (instead of national) newspapers or through posting notices at strategic places in the community, (iii) community force account where the communities implement themselves the subproject using their own resource and (iv) Direct contracting. For services the selection methods to be used are the following: (i) Individual consultants; (ii) consultants qualifications and (iii) single source selection for the selection of individual consultants and firms. All the above mentioned selection method will be applied as spelled out in the Bank's consultant guidelines. The PIM will describe the details in a clear and simple language that be easily understood by the targeted users. 4. Reference to (if any) Project Operational/Procurement Manual: Not yet available 5. Any Other Special Procurement Arrangements: N/A 6. Procurement Packages with Methods and Time Schedule A. PPA 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid- (US$) (yes/no) (Prior / Opening Post) Date 1 Fourniture d'une 40,000 Shopping No No Post July 2015 camionnette 4x4 2 Fourniture et 30,000 Shopping No No Post July 2015 équipements de bureau, ordinateurs, photocopieuse, scanner, etc. B. PROJET CAFÉ 1. Travaux, Fournitures, Systèmes IT et Services non consultant a. Travaux 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid-Opening (US$) (yes/no) (Prior / Date Post) 1 Travaux de réhabilitation 1,200,000 NCB No No Post May 2016 Non inclus de 30 km de routes 300,000 $ rurales d'accès aux SDL US pour études et surveillance 2 Travaux de 160,100 NCB No No Post Feb 2016 Réhabilitation des Bureaux de l’ARFIC (aménagement des bureaux, climatiseurs, etc.) 3 Construction de 50 bacs 107,700 NCB No No Post Nov 2016 Non compris de traitement des eaux la usées contribution des bénéficiaires de 152,600 $ US 4 Travaux de rénovation 61,000 shopping No No Post Feb 2016 bureaux de l’UGP b. Fournitures, Systèmes IT et Services non consultant 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid-Opening (US$) (yes/no) (Prior / Date Post) 1 Approvisionnement en 2,500,000 ICB No No Prior Feb 2016 insecticides, fongicides et autres produits phytosanitaires pour 2016-2017 2 Approvisionnement en 350,000 NCB No No Prior April 2016 engrais pour le rajeunissement 2016- 2017 3 Acquisition des 300,000 NCB No No Post March 2016 véhicules pour UGP, ARFIC et INTERCAFE et CNAC 4 Acquisition de 13 motos 78,000 NCB No No Post April 2016 pour la CNAC 5 Equipement de bureau 225,000 NCB No No Post Oct 2015 (Ordinateurs, imprimante, Photocopieuses, scanners, etc) pour l’UGP, ARFIC et INTERCAFE et CNAC 6 Mobilier de bureau pour 55,000 NCB No No Post Apr 2016 l’UGP, ARFIC, INTERCAFE et CNAC 7 Acquisition des 185,000 NCB No No Post Aug 2016 Non compris la Equipements de contribution des laboratoire pour ARFIC bénéficiaires de équipements de 228,500 $ US laboratoires de dégustation pour INTERCAFE (SDL) 8 Fourniture d’un groupe 81,200 NCB No No Post Feb 2016 électrogène pour UGP 9 Renforcement capacités 101,500 NCB No No Post July 2016 A déterminer logistiques de l’ISABU plus tard les articles 10 Conception, fourniture et 111,900 NCB No No Post May 2016 maintenance d’un logiciel de vente de café pour ARFIC/Guichet unique 11 Conception d’un logiciel 188,100 NCB No No Post July 2016 en ligne et fourniture et installation des équipements en appui à la production des statistiques fiables sur le café 12 Fourniture et Installation 50,800 ED No No Post Jan 2016 La NO se fera d’un logiciel de gestion par mail au TTL financière et comptable et formation pour l’UGP 13 Fourniture et Installation 50,800 ED No No Post Jan 2016 La NO se fera d’un logiciel de suivi- par mail au TTL évaluation et Formation pour l’UGP 14 Fourniture et Installation 20,300 Shopping No No Post Jan 2016 des Logiciels bureautiques et Formation pour l’UGP 15 Production fiches 10,400 Shopping No No Post Feb 2016 techniques et films documentaires sur nouvelles techniques de conduite de la caféicultures III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms)  200,000 2. Single Source (Firms)  100,000 3. Individual Consultants  100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule A. PPA 1 2 3 4 5 6 7 Ref. Description of Assignment Estimate Selection Review Expected Comments No. d Cost Method by Bank Proposals (US$) (Prior / Submission Post) Date 1 Enquête sur le verger caféicole et 100,000 QC Post Apr 2015 localisation des SDL 2 Elaboration d’un Système intégré 50,000 QC Post Apr 2015 de Gestion (Management Information System) 3 Renforcement des capacités des 40,000 QC Post May 2015 institutions partenaires du Projet (ARFIC, INTERCAFE, CNAC, ect.) en Gestion, Cpté, PM, SE, etc.) 4 Elaboration des Manuels (manuel 33,000 CI Post Apr 2015 d’exécution et manuels de Gestion Administratives et Financières du Projet, INTERCAFE, ARFIC et CNAC) B. PROJET CAFE 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Cost (US$) Method by Bank Proposals (Prior / Submission Post) Date 1 Etudes technique d’exécution et 300,000 SFQC Post Nov 2015 Surveillance des travaux de réhabilitation de 30 km de pistes+ autres études pour les autres travaux prévus en 2015-2016 2 Rationalisation politique de la 259,400 SFQC Prior Déc 2016 filière et cadre réglementaire en appui à l’ARFIC 3 Mise en place système de 184,700 QC Post Sept 2016 traçabilité en appui à ARFIC 4 Elaboration de la stratégie 83,000 QC Post June 2016 marketing en appui INTERCAFE 5 Formation des acteurs sur la 80,600 QC Post Jan 2016 qualité du café et la démarche qualité + formation préparatoire et qualifiantes des Q graders en appui à ARFIC 6 Elaboration de la stratégie et 78,100 QC Post Dec 2015 situation de base genre dans la filière café en appui à la CNAC 7 Evaluation impact 77,800 QC Post Jan 2016 environnemental et social 8 Evaluation des coûts de 62,200 QC Post Apr 2016 production au niveau des maillons de la filière café en appui à l’ARFIC 9 Audit comptable et financier 52,200 SMC Post March 2017 externe, exercice 2016 et 2017 10 Audit des SDL existants en vue 31,100 SMC Post Dec 2016 de la certification en appui à INTERCAFE 11 Elaboration plan stratégique de 62,200 CI Post March 2016 l’INTERCAFE 12 Conception et production d'un 51,900 CI Post July 2016 guide de gestion durable de l'exploitation caféicole du Burundi pour la CNAC 13 Audit organisationnel, technique 51,900 CI Post Feb 2016 et financier de l’INTERCAFE 14 Elaboration de la stratégie de 46,700 CI Post April 2016 communication de l’INTERCAFE 15 Évaluation de la capacité 41,500 CI Post Apr 2016 existante pour le dialogue secteur public / secteur privé (y compris l’étude sur le cadre de concertation des acteurs de la filière) an appui à ARFIC 16 Formation des Cadres de l’ARFIC 38,200 CI Post May 2016 sur la Gouvernance, partenariat public-privé, suivi&évaluation, etc. 17 Formation des Cadres ARFIC sur 38,200 CI Post March 2016 Norme / grade standard de qualité 18 Formation du personnel des 31,100 CI Post June 2016 laboratoires (Appui ARFIC) 19 Formation Suivi et Evaluation et 29,000 CI Post Janv 2016 planification stratégique axée sur les résultats pour INTERCAFE 20 Conception des documents sur les 27,100 CI Post June 2016 procedures d’accréditation des laboratoires en appui à l’ARFIC 21 Amélioration capacité technique, 22,100 CI Post May 2016 opérationnelle et managériale des SDL (Conception et production de guide) en appui à ARFIC 22 Formation des formateurs à 13,300 CI Post March 2016 l'accréditation (Appui à ARFIC) 23 Renforcement des capacités des 10,400 CI Post Aug 2016 organisations de la filière sur le plaidoyer en faveur de l’interprofession du café 24 Recrutement du Staff d de l’UGP Sur une période de 2 Projet ans 24.1  Coordonnateur 80,000 CI Prior July 2015 24.2  Responsable de gestion 75,000 CI Prior July 2015 administrative et financière 24.3  Spécialiste de la 72,000 CI Prior July 2015 passation des marchés 24.4  Spécialiste de S&E 72,000 CI Prior July 2015 24.5  Responsable technique 72,000 CI Prior July 2015 24.6  Auditeur interne 66,000 CI Prior July 2015 24.7  Spécialiste de genre et 66,000 CI Prior July 2015 inclusion sociale 24.8  Spécialiste de 66,000 CI Prior July 2015 l'environnement 24.9  Comptable 44,000 CI Prior July 2015 (*): FMS and PS staff supporting INTERCAFE and CNAC will be also selected using WB procedures, including prior review requirements. PROCUREMENT Burundi : Burundi Coffee Sector Competitiveness Project PLAN General Information Country: Burundi Banks Approval Date of the Original Procurement Plan: 2017-08-31 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-08-31 Project ID: P151869 GPN Date: Project Name: Burundi Coffee Sector Competitiveness Project Loan / Credit No: IDA / D0570 Executing Agency(ies): Ministry of Agriculture and Livestock WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4 ? Coordination, BI-MINAGRIE-20599-CW-RFQ / Request for Single Stage - One Pending IDA / D0570 monitoring and knowledge Post Limited 29,000.00 0.00 2017-08-14 2017-10-09 2018-04-07 office renovation Quotations Envelope Implementation management MOF -REF-1 / Rénovation des Component 1 ? Institutional Single Stage - One Pending bureaux et laboratoire principal IDA / D0570 strengthening and value chain Post Request for Bids Open - National 198,000.00 0.00 2017-09-13 2017-09-18 2017-10-30 2017-11-29 2018-01-03 2018-07-02 Envelope Implementation (ARFIC) governance Component 4 ? Coordination, MOF -REF-2 / Rénovation des Request for Single Stage - One Pending IDA / D0570 monitoring and knowledge Post Limited 29,000.00 0.00 2017-06-30 2017-08-25 2018-02-21 bureaux UCP Quotations Envelope Implementation management GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 ? Coffee growers MOF -REF-3 / Fourniture des Single Stage - One Pending IDA / D0570 productive capacity Post Request for Bids Open - International 500,000.00 0.00 2017-06-12 2017-06-17 2017-07-29 2017-08-28 2017-10-02 2018-03-31 engrais (500 tonnes - 2017) NPK Envelope Implementation enhancement MOF -REF-4 / Component 2 ? Coffee growers Single Stage - One Pending Approvisionnement en fongicide IDA / D0570 productive capacity Prior Request for Bids Open - International 1,505,085.00 0.00 2017-05-02 2017-05-07 2017-06-18 2017-07-18 2017-08-22 2018-02-18 Envelope Implementation et insecticide enhancement Component 1 ? Institutional Pending MOF -REF-5 / Vehicules (10) IDA / D0570 strengthening and value chain Prior UN Agencies (Direct) Direct 450,000.00 0.00 2017-02-07 2017-02-07 2017-02-07 2017-02-07 Implementation governance Component 1 ? Institutional Pending MOF -REF-6 / Véhicules (6) IDA / D0570 strengthening and value chain Prior UN Agencies (Direct) Direct 290,000.00 0.00 2017-07-07 2017-07-07 2017-07-07 2017-07-07 Implementation governance Component 1 ? Institutional Single Stage - One Pending MOF -REF-7 / Motos (9) IDA / D0570 strengthening and value chain Post Request for Bids Open - National 76,500.00 0.00 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Envelope Implementation governance MOF -REF-9 / Achat de 2 Ordinateurs centraux dans le Component 3 ? Coffee quality Request for Single Stage - One Pending cadre de l'Appui à la production IDA / D0570 Post Limited 30,000.00 0.00 2017-06-30 2017-08-25 2018-02-21 improvement and market access Quotations Envelope Implementation des statistiques / Département des statistiques ARFIC MOF -REF-12 / Fourniture et Component 1 ? Institutional Single Stage - One Pending é uipement de installation des q IDA / D0570 strengthening and value chain Post Request for Bids Open - International 370,000.00 0.00 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 Envelope Implementation contrôle de qualité café governance MOF -REF-13 / Kits matériels Component 2 ? Coffee growers moniteurs (salopettes, bottes, Single Stage - One Pending IDA / D0570 productive capacity Post Request for Bids Open - National 90,120.00 0.00 2017-07-02 2017-07-07 2017-08-18 2017-09-17 2017-10-22 2018-04-20 imperméables, triangles à Envelope Implementation enhancement pentes) MOF -REF-16 / Equipements informatiques et de reprographie pour l'UCP (Ordinateur fixe, Component 4 ? Coordination, Request for Single Stage - One Pending Ordinateur portable docking IDA / D0570 monitoring and knowledge Post Limited 42,500.00 0.00 2017-02-13 2017-04-10 2017-10-07 Quotations Envelope Implementation station, Imprimante grande management capacité, Imprimante moyenne capacité) MOF -REF-17 / Mobilier de bureau à la CNAC au niveau Component 1 ? Institutional Request for Single Stage - One Pending national et régional (tables, IDA / D0570 strengthening and value chain Post Limited 13,650.00 0.00 2017-04-18 2017-06-13 2017-12-10 Quotations Envelope Implementation chaises, té agères, armoires, governance etc.) Component 4 ? Coordination, MOF -REF-18 / Mobilier de Request for Single Stage - One Pending IDA / D0570 monitoring and knowledge Post Limited 36,000.00 0.00 2017-02-15 2017-04-12 2017-10-09 burau pour l'UNCP Quotations Envelope Implementation management MOF -REF-19 / Achat de matériel pour les formations des Component 3 ? Coffee quality Request for Single Stage - One Pending Q graders en 2018 (5 coffee IDA / D0570 Post Limited 30,300.00 0.00 2017-07-20 2017-09-14 2018-03-13 improvement and market access Quotations Envelope Implementation Taster's flavor Wheel etc.) et Equipement Labo de dégustation MOF -REF-20 / Achat des engrais pour cultures Component 2 ? Coffee growers Single Stage - One Pending intercalires, pépinères,caféiers IDA / D0570 productive capacity Post Request for Bids Open - National 376,670.00 0.00 2017-06-26 2017-07-01 2017-08-12 2017-09-11 2017-10-16 2018-04-14 Envelope Implementation és regénré et recépsé enhancement (DAP+Urée) MOF -REF-21 / Achat du Component 2 ? Coffee growers Single Stage - One Pending matériel pour pépinères 2017 et IDA / D0570 productive capacity Post Request for Bids Open - National 64,705.00 0.00 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-04-23 Envelope Implementation pour plants 2018 enhancement Page 1 MOF -REF-22 / Achat de Component 2 ? Coffee growers produits phytosanitaires pour les Request for Single Stage - One Pending IDA / D0570 productive capacity Post Limited 25,162.00 0.00 2017-07-03 2017-08-28 2018-02-24 cultures intercalaires et les Quotations Envelope Implementation enhancement pépinières MOF -REF-24 / Fumure Component 2 ? Coffee growers Single Stage - One Pending organique pour caféiers à IDA / D0570 productive capacity Post Request for Bids Open - National 154,117.00 0.00 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 Envelope Implementation renouveler + caféier à recéper enhancement Component 2 ? Coffee growers MOF -REF-26 / Etablissement Single Stage - One Pending IDA / D0570 productive capacity Post Request for Bids Open - National 60,000.00 0.00 2017-06-25 2017-06-30 2017-08-11 2017-09-10 2017-10-15 2018-04-13 des cahiers des caféiculteurs Envelope Implementation enhancement MOF -REF-8 / Fournitures pour Appui logistique et matériel informatique et de reprographie pour l'ARFIC, INTERCAFE, Component 1 ? Institutional CNAC & ISABU (imprimantes, Single Stage - One Pending IDA / D0570 strengthening and value chain Post Request for Bids Open - National 156,050.00 0.00 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 ordinateurs, Appareil photo Envelope Implementation governance numérique, etc.) + Achat de 6 ordinateurs portables, de 2 ordinateurs de bureaux et de 5 impr Component 2 ? Coffee growers MOF -REF-10 / Achat matériel Single Stage - One Pending IDA / D0570 productive capacity Post Request for Bids Open - International 401,310.00 0.00 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 de traitement et de protection Envelope Implementation enhancement Component 2 ? Coffee growers MOF -REF-11 / Matériel de taille Single Stage - One Pending IDA / D0570 productive capacity Post Request for Bids Open - National 55,000.00 0.00 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 (scie et sécateur) Envelope Implementation enhancement NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-25 / Achat de prestations de services (Régie Nationale des Postes: RNP) pour Component 2 ? Coffee growers Pending la collecte des fonds des IDA / D0570 productive capacity Prior Direct Selection Direct 23,000.00 0.00 2017-06-25 2017-06-30 2017-08-04 2018-01-31 Implementation caféiculteurs (partie non enhancement subventionnée de du coûts des engrais) MOF -REF-27 / Sélection d'un prestataire de services pour Component 4 ? Coordination, l'élaboration d'un devis quantitatif Request for Single Stage - One Pending IDA / D0570 monitoring and knowledge Post Limited 1,000.00 0.00 2017-06-24 2017-08-19 2018-02-15 suivi et contrôle des travaux Quotations Envelope Implementation management relatifs au réaménagement des bureaux de l'UC-PACSC CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-28 / Etudes techniques et surveillance des Component 3 ? Coffee quality Quality And Cost- Pending travaux de Réhabilitation des IDA / D0570 Post Open - National 104,000.00 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-24 2017-10-24 2017-11-28 2018-01-02 2018-03-03 improvement and market access Based Selection Implementation pistes rurales d'accès aux SDL: 60 km Component 1 ? Institutional Consultant MOF -REF-29 / Preparation du Pending IDA / D0570 strengthening and value chain Post Qualification Open - International 60,000.00 0.00 2017-06-26 2017-07-17 2017-08-30 2017-09-29 2017-11-03 2018-05-02 Coffee - Act Implementation governance Selection MOF -REF-30 / Audit comptable Component 4 ? Coordination, Pending et financier externe, exercice IDA / D0570 monitoring and knowledge Post Least Cost Selection Open - National 50,000.00 0.00 2017-07-11 2017-08-01 2017-09-14 2017-10-12 2017-11-11 2017-12-16 2018-01-20 2018-07-19 Implementation 2017 et 2018 management MOF -REF-31 / Audit organisationnel, technique et Component 1 ? Institutional Consultant Pending financier de l'INTERCAFE + IDA / D0570 strengthening and value chain Post Qualification Open - International 114,125.00 0.00 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 Implementation Elaboration d'un plan stratégique governance Selection de l'INTERCAFE MOF -REF-32 / Elaboration de Consultant Component 3 ? Coffee quality Pending la stratégie marketing ( AT IDA / D0570 Post Qualification Open - International 83,000.00 0.00 2017-07-04 2017-07-25 2017-09-07 2017-10-07 2017-11-11 2018-05-10 improvement and market access Implementation internationale et AT nationale) Selection Consultant MOF -REF-34 / Audit des SDL Component 3 ? Coffee quality Pending IDA / D0570 Post Qualification Open - National 31,100.00 0.00 2017-06-08 2017-06-29 2017-08-12 2017-09-11 2017-10-16 2018-04-14 existantes improvement and market access Implementation Selection MOF -REF-41 / Etudes techniques pour la conception, Component 2 ? Coffee growers Consultant plans et DAO pour la Pending IDA / D0570 productive capacity Post Qualification Open - National 20,000.00 0.00 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-05-16 construction et qé uipement Implementation enhancement Selection laboratoire de biotechnologie ISABU MOF -REF-42 / Etudes techniques pour conception, plans et DAO pour la construire d'un laboratoire de défense de la Component 2 ? Coffee growers Consultant Pending culture du café contre les IDA / D0570 productive capacity Post Qualification Open - National 10,000.00 0.00 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Implementation principales maladies et enhancement Selection ravageurs du café (Labo phytopathologie, entomologie, etc.) MOF -REF-56 / Recrutement Component 4 ? Coordination, Consultant d'un consultant pour l'évaluation Pending IDA / D0570 monitoring and knowledge Post Qualification Open - National 45,000.00 0.00 2017-05-18 2017-06-08 2017-07-22 2017-08-21 2017-09-25 2018-03-24 de l'impact environnemental et Implementation management Selection social du projet Page 2 MOF -REF-57 / Recrutement d'un consultant pour l'élaboration Component 1 ? Institutional Consultant des té udes techniques Pending IDA / D0570 strengthening and value chain Post Qualification Open - National 22,000.00 0.00 2017-07-11 2017-08-01 2017-09-14 2017-10-14 2017-11-18 2018-05-17 d'exécution des travaux de Implementation governance Selection rénovation des bureaux et laboratoire principal (ARFIC) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-37 / Formation des utilisateurs du marché de café sur la gestion des risques et Component 3 ? Coffee quality Individual Consultant Pending IDA / D0570 Post Limited 36,250.00 0.00 2017-07-24 2017-07-29 2017-08-19 2017-09-23 2018-03-22 techniques commerciales du improvement and market access Selection Implementation é s, 15 staff café: 65 sociéte Intercafé, CNAC et ARFIC MOF -REF-38 / Suivi-évaluation Component 1 ? Institutional Individual Consultant Pending et planification stratégique axée IDA / D0570 strengthening and value chain Post Limited 29,000.00 0.00 2017-07-03 2017-07-08 2017-07-29 2017-09-02 2018-03-01 Selection Implementation sur les résultats governance MOF -REF-39 / Evaluation des Component 1 ? Institutional Individual Consultant Pending coûts de production au niveau IDA / D0570 strengthening and value chain Post Limited 62,250.00 0.00 2017-07-14 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Selection Implementation des maillons de la filère café governance MOF -REF-43 / Etudes techniques pour conception, plans et DAO pour la Component 2 ? Coffee growers Individual Consultant Pending é uipement d'un IDA / D0570 construction et q productive capacity Post Limited 10,000.00 0.00 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 Selection Implementation centre de documentation sur le enhancement café et formation des caféiculteurs MOF -REF-44 / Recrutement Component 2 ? Coffee growers d'un assistant technique d'appui Individual Consultant Pending IDA / D0570 productive capacity Post Limited 12,000.00 0.00 2017-06-26 2017-07-01 2017-07-22 2017-08-26 2018-02-22 à la Recherche à l'ISABU (cadre Selection Implementation enhancement permanent) MOF -REF-45 / Recrutement Component 4 ? Coordination, Individual Consultant Pending des experts de l'UNCP du IDA / D0570 monitoring and knowledge Post Direct 280,000.00 0.00 2016-11-16 2016-11-26 2016-12-17 2017-01-21 2017-07-20 Selection Implementation PACSC management MOF -REF-46 / Elaboration de Component 1 ? Institutional Individual Consultant Pending la stratégie genre dans la filière IDA / D0570 strengthening and value chain Post Limited 30,000.00 0.00 2017-05-16 2017-05-21 2017-06-11 2017-07-16 2018-01-12 Selection Implementation café governance MOF -REF-48 / Consultant pour mobiliser les acteurs dans le Component 3 ? Coffee quality Pending cadre de la participation des IDA / D0570 Post Direct Selection Direct 10,000.00 0.00 2017-04-22 2017-05-02 2017-07-06 2018-01-02 improvement and market access Implementation acteurs de la filière café à la SCAA MOF -REF-49 / Consultant pour mobiliser les acheteurs dans le Component 3 ? Coffee quality Pending cadre de la participation des IDA / D0570 Post Direct Selection Direct 10,000.00 0.00 2017-07-06 2017-07-16 2017-09-19 2018-03-18 improvement and market access Implementation acteurs de la filière café aux Café Show Séoul/afrique MOF -REF-50 / Consultant pour mobiliser les acteurs dans le Component 3 ? Coffee quality Pending IDA / D0570 Post Direct Selection Direct 10,000.00 0.00 2017-07-10 2017-07-20 2017-09-23 2018-03-22 cadre de la participation des improvement and market access Implementation acteurs de la filière aux SCAJ MOF -REF-51 / Consultant pour mobiliser les acteurs dans le Component 3 ? Coffee quality Pending IDA / D0570 Post Direct Selection Direct 10,000.00 0.00 2017-07-15 2017-07-25 2017-09-28 2018-03-27 cadre de la participation des improvement and market access Implementation acteurs de la filière aux SCAE MOF -REF-52 / Recrutement d'un consulant pour aider à Component 3 ? Coffee quality Individual Consultant Pending IDA / D0570 Post Direct 15,000.00 0.00 2017-08-01 2017-08-11 2017-09-01 2017-10-06 2018-04-04 sensibiliser les acheteurs improvement and market access Selection Implementation internationaux MOF -REF-54 / Recrutement d'un consultant chargé d'auditer Component 3 ? Coffee quality Pending IDA / D0570 Post Direct Selection Direct 18,000.00 0.00 2017-05-15 2017-05-25 2017-07-29 2018-01-25 et de gérer la base des données improvement and market access Implementation de la COE 2017 MOF -REF-55 / Recrutement Component 1 ? Institutional d'un consultant pour l'élaboration Individual Consultant Pending IDA / D0570 strengthening and value chain Post Limited 12,000.00 0.00 2017-05-18 2017-05-23 2017-06-13 2017-07-18 2018-01-14 d'un manuel de suivi-évaluation Selection Implementation governance de la CNAC Page 3