VIETNAM Da Nang Sustainable City Development Project Textual Part of Procurement Plan I. General 1. Bank’s Approval Date of the Procurement Plan: Original: March 8, 2013. Latest Updated Procurement Plan: June 20, 2017 2. Date of General Procurement Notice: July 2, 2013 3. Period covered by this procurement plan: From June 2017 to June 2019 II. Applicable Rules and Procedures 1. Procurement for the proposed project shall be carried out in accordance with the World Bank’s “Guidelines: Procurement of Goods, Works and Non-Consulting Services Under IBRD Loans, IDA Credits & Grants by World Bank Borrowers” dated January 2011, revised July 2014 (referred to as the Procurement Guidelines) and “Guidelines: Selection and Employment of Consultants Under IBRD Loans, IDA Credits & Grants by World Bank Borrowers” dated January 2011, revised July 2014 (the Consultant Guidelines). III. Goods and Works and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. These thresholds are subject to change by the Bank during the project implementation based on its assessment of the project procurement implementation capacity and risks: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$2 million All contracts above thresholds 2. NCB (Goods) Above US$2 million All contracts above thresholds 3. ICB (Works) Above US$10 million All contracts above thresholds 4. NCB (Works) Above US$10 million All contracts above thresholds 5. Shopping N/A No prior review 6. Direct Contracting (Goods) Above US$2 million All contracts above thresholds 7. Direct Contracting (Works) Above US$10 million All contracts above thresholds July 9, 2010 2. Prequalification: Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 4. Reference to Project Operational/Procurement Manual: The Project Implementation Manual dated March 1, 2013 and approved by the Da Nang City People’ Committee as referred to in the Financing Agreement. 5. Any Other Special Procurement Arrangements: No. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants. These thresholds are subject to change by the Bank during the project implementation based on its assessment of the project procurement implementation capacity and risks: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$1 million All contracts above thresholds 2. Single Source (Firms) Above US$1 million All contracts above thresholds 3. Individuals Above US$300,000 All contracts above thresholds 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Reference to Project Operational/Procurement Manual: The Project Implementation Manual dated March 1, 2013 and approved by the Da Nang City People’ Committee as referred to in the Financing Agreement. 4. Any Other Special Selection Arrangements: Not applicable. July 9, 2010 PROCUREMENT Vietnam : Danang Sustainable City Development Project (SCDP) PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2017-10-31 2019-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P123384 GPN Date: Project Name: Danang Sustainable City Development Project (SCDP) Loan / Credit No: IDA / 52330 Executing Agency(ies): Da Nang Priority Infrastructure Investment Project Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Package 3.6 / Package 3.6: Construction of Bridges on Single Stage - One IDA / 52330 Prior Request for Bids Open - National 7,601,093.44 Signed Hoa Phuoc - Hoa Khuong Envelope Road 1.11 / Extension of Capacity of Hoa Xuan Wastewater Treatment Plant Open - Single Stage - One IDA / 52330 Prior Request for Bids 7,638,205.48 Signed and Operation and International Envelope Maintenance of the Plant for 5 Years Package 1.2 / Construction of Lien Chieu Wastewater Treatment Plant and Open - Single Stage - One IDA / 52330 Prior Request for Bids 7,616,257.05 Signed ancillary works and International Envelope Operation & Maintenance of the Plant for 5 Years Package 3.5 / Package 3.5: Single Stage - One Construction of Hoa Phuoc - IDA / 52330 Prior Request for Bids Open - National 12,819,040.03 Signed Envelope Hoa Khuong Road 3.2 / Construction of Infrastructure of resettlement Single Stage - One IDA / 52330 Prior Request for Bids Open - National 5,628,093.52 Signed areas in the South of Envelope Danang City under SCDP B55b / Upgrading of Son Open - Single Stage - One Tra Wastewater Treatment IDA / 52330 Prior Request for Bids 11,133,253.79 Signed International Envelope Plant 1-7 / Rehabilitation of drainage system in Hai Single Stage - One IDA / 52330 Post Request for Bids Open - National 7,656,983.16 Signed 2017-11-02 2017-11-06 2017-12-12 2018-01-01 2018-01-03 2019-06-28 Chau, Son Tra and Lien Envelope Chieu districts 1-9 / Construction of wastewater collection system Under Single Stage - One and pumping station in Son IDA / 52330 Prior Request for Bids Open - National 0.00 Implementati 2018-02-15 2018-02-20 2018-03-26 2018-05-25 2018-06-01 2019-06-01 Envelope Tra, Hai Chau and Lien on Chieu districts 1-14 / Construction of Under tertiary wastewater drainage Single Stage - One IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2018-03-10 2018-03-15 2018-04-18 2018-06-09 2018-06-13 2019-06-10 pipeline and household Envelope on connection in My Khe area Page 1 1-12 / Construction of auto- monitoring system for wastewater treatment plants Pending Single Stage - One and supervision of all IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2018-01-09 2018-01-14 2018-02-17 2018-04-18 2018-04-25 2019-04-25 Envelope wastewater treatment and on collection system in Danang city 1-13 / Construction of wastewater collector pipeline, primary and secondary Under Open - Single Stage - One transfering pipelines and IDA / 52330 Prior Request for Bids 0.00 Implementati 2018-01-22 2018-01-27 2018-03-17 2018-05-16 2018-05-23 2019-05-23 International Envelope wastewater pumping station on in My Khe and My An areas 3-10 / Construction of Single Stage - One infrastructure of resettlement IDA / 52330 Post Request for Bids Open - National 1,630,646.95 Signed 2018-01-20 2018-01-25 2018-02-28 2018-05-02 2018-05-09 2019-05-09 Envelope areas in DH2 road 3-8-3-9 / Construction of Single Stage - One IDA / 52330 Prior Request for Bids Open - National 8,801,775.91 Signed 2017-08-11 2017-11-06 2017-12-11 2017-12-29 2018-01-02 2019-08-25 HD2 road Envelope 1-4 / Wastewater transferring pipleline from Pending Single Stage - One the west of Khue Dong IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2018-04-26 2018-04-27 2018-06-04 2018-06-24 2018-06-28 2019-06-23 Envelope bridge to Hoa Xuan on wastewate treatment plant 1-15 / Construction of Pending tertiary wastewater drainage Single Stage - One IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2018-04-10 2018-04-15 2018-05-19 2018-06-25 2018-06-29 2019-06-26 pipeline and household Envelope on connection in My An area 3-11 / Tree planting and Pending water supply for tree Single Stage - One IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2019-03-29 2019-03-29 2019-04-20 2019-04-27 2019-04-27 2019-05-27 watering on Hoa Phuoc - Envelope on Hoa Khuong road 2-9 / Construction of Pending pedestrian bridge over Dien Single Stage - One IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2019-07-19 2019-07-22 2019-08-24 2019-10-23 2019-11-16 2020-05-18 Bien Phu Road in front of Envelope on the March 29 Park GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2-4-2-5 / Supply, installation of ticketing system, intelligent transport Under Open - Single Stage - One system for public transport IDA / 52330 Prior Request for Bids 0.00 Implementati 2016-11-25 2016-11-25 2017-05-30 2017-12-30 2018-01-15 2019-07-19 International Envelope system and traffic signal on priority system for bus rapid transit (BRT) (including 2 lots) 4-7E / Procurement of Pending equipment for monitoring Single Stage - One IDA / 52330 Post Request for Bids Open - National 0.00 Implementati 2018-06-07 2018-06-07 2018-07-15 2018-09-20 2018-09-27 2019-03-26 and managing public Envelope on transport Page 2 4-8 / Procurment of software for Da Nang Traffic Light and Public Transport Pending Management Centre Request for Single Stage - One IDA / 52330 Post Open - National 0.00 Implementati 2018-05-25 2018-09-03 2019-03-02 (DATRAMAC) and Quotations Envelope on departments for management and operation of public transport system 4-9B / Procurement of Pending office equipment for Project Request for Single Stage - One IDA / 52330 Post Open - National 0.00 Implementati 2018-05-14 2018-08-22 2018-11-20 Management Unit in project Quotations Envelope on implementation 2-6 / Procurement of bus, rescue vehicle and operation Open - Single Stage - One IDA / 52330 Prior Request for Bids 0.00 Canceled 2018-02-04 2018-02-09 2018-04-17 2018-06-16 2018-06-23 2019-06-23 of bus rapid transit system International Envelope (5 years) 2-6A / Procurement of bus Under Open - Single Stage - One for BRT trunk route and IDA / 52330 Prior Request for Bids 0.00 Implementati 2019-05-19 2019-05-22 2019-07-03 2019-09-23 2019-09-29 2020-10-12 International Envelope additional routes system on 2-4 / Supply, installation of Pending ticketing system, intelligent Open - Single Stage - One IDA / 52330 Prior Request for Bids 0.00 Implementati 2019-06-29 2019-07-02 2019-08-13 2019-11-25 2019-12-01 2021-02-23 transport system for public International Envelope on transport system NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Package 3.3: CSC Comp 2 and 3 / Package 3.3: Consulting Services for Quality And Cost- Open - IDA / 52330 Prior 3,835,018.12 Canceled Contract Management and Based Selection International Construction Supervision for Component 2 and 3 2.1 Part 2 / On-Site Supervision of Equipment Consultant Open - Installation and Technical IDA / 52330 Prior Qualification 2,945,937.29 Signed International Assistance for Operation of Selection BRT System 4.14 / Consulting Services Least Cost Open - for Financial Audit for IDA / 52330 Prior 19,939.88 Signed Selection International Phase I of the Project Package 1.1, Part 2 / Package 1.1, Part 2: Consulting Services for Contract Management, Quality And Cost- Open - IDA / 52330 Prior 3,047,091.00 Signed Construction Supervision and Based Selection International Procurement Support for Component 1 (Drainage and Wastewater Improvement) Page 3 4.15 / Project performance audit, monitoring and evaluation of project Quality And Cost- Open - IDA / 52330 Prior 319,548.77 Signed outcomes under Danang Based Selection International Sustainable City Development Project 4-2 / Consulting service for technical asisstance for Da Nang Traffic Light and Quality And Cost- Pending IDA / 52330 Post Open - National 0.00 2018-03-23 2018-03-28 2018-05-27 2018-07-01 2018-07-16 2018-08-07 2018-08-21 2019-06-22 Public Transport Based Selection Implementation Management Centre (DATRAMAC) 4-18B / Consulting service for Internal Audit for Consultant Pending Danang Sustainable City IDA / 52330 Post Qualification Open - National 0.00 2018-08-03 2018-08-06 2018-09-06 2018-10-06 2018-10-16 2019-12-31 Implementation Development Project (phase Selection 2) 4-2F / Consulting service Consultant for survey and development Under IDA / 52330 Post Qualification Open - National 0.00 2018-08-20 2018-08-23 2018-09-23 2018-10-25 2018-11-04 2019-05-05 of a traffic simulation model Implementation Selection for Danang city 2-1A / Consulting service for on-site supervision of equipment installation and Quality And Cost- Open - Under IDA / 52330 Prior 0.00 2018-11-30 2018-12-03 2019-02-22 2019-03-26 2019-04-25 2019-06-09 2019-07-04 2020-12-27 technical assistance for Based Selection International Implementation operation of bus rapid transit system (phase 2) 2-1B / Communication for Quality And Cost- Pending BRT system and public IDA / 52330 Post Open - National 0.00 2018-11-30 2018-12-03 2019-02-22 2019-03-26 2019-04-25 2019-06-09 2019-07-04 2021-02-25 Based Selection Implementation transport system 4-19 / Consulting service Least Cost Pending for financial audit for the IDA / 52330 Post Open - National 0.00 2017-11-03 2017-12-15 2018-02-28 2018-04-04 2018-05-04 2018-06-20 2018-06-27 2019-10-25 Selection Implementation project for phase 2 4-15A / Consulting service for project implementation Consultant Pending audit, monitoring and IDA / 52330 Post Qualification Open - National 0.00 2018-10-25 2018-10-28 2018-11-28 2018-12-30 2019-01-09 2019-04-30 Implementation evaluation of project Selection outcomes (phase 2) 3-3B / Consulting services for contract management and construction supervision for Component 1 (package 1.4), Consultant Under Component 2 - Bus Rapid IDA / 52330 Post Qualification Open - National 0.00 2019-04-29 2019-05-02 2019-05-26 2019-06-22 2019-06-30 2019-12-31 Implementation Transit Development (BRT Selection Infrastructure only) and Component 3 - Urban strategic roads 3-3C / Consulting services for contract management and construction supervision for Component 1 - Drainage and Wastewater Improvement, Quality And Cost- Open - IDA / 52330 Prior 0.00 Under Review 2019-05-07 2019-05-10 2019-06-23 2019-07-26 2019-08-25 2019-10-27 2019-12-30 2021-06-30 Component 2 - Bus Rapid Based Selection International Transit Development (BRT Infrastructure only) and Component 3 - Urban strategic roads Page 4 4-1 / Consulting services for study on transport Quality And Cost- Open - system model of the city IDA / 52330 Prior 0.00 Canceled 2017-11-09 2017-11-11 2018-04-09 2018-06-15 2018-07-15 2018-10-08 2018-10-15 2020-04-17 Based Selection International after relocating the railway to the new alignment INDIVIDUAL CONSULTANTS Page 5