The Second Ho Chi Minh City Environmental Sanitation Project (HCMCES2) - PPTAF Subproject UPDATE PROCUREMENT PLAN UNTIL MAY 26, 2017 Revised Contract (USD) Type Review Cost Contract No Packa Selection of by WB Issuance Issuance Proposal Contract Contract Description Estimate PPTAF Counterpart Duration . ge No. Method Contr (Prior of REOI of RFP Submission Signing Start (USD) funds funds (months) act or Post) A. FOR CONSULTING SERVICES Preparation of Detailed Design and Bidding April 15, Feb 07, March Dec 03, Dec 03, 01 PP-01 Documents for District 1,758,611 1,858,483 110,023 QCBS LS Prior 18 2013 2015 21, 2015 2015 2015 2 sewerage and wastewater systems. Consultant to support PMU during the preparation of tender June 28, Dec 10, Dec 13, Dec 28, Dec 28, 02 PP-02 190,000 331,007 - IC TB Prior 36 documents and selection 2012 2012 2012 2012 2012 of consultants for PP- 01. PP-03 and PP-04 Consultant to upplement April 04, April 10, April 15, April 03 PP-02a the Eviromental Impact 100,000 86,648 - SSS LS Prior - 19 2013 2013 2013 15, 2013 Assessment Additional Consulting April 17, April 22, May 05, May 05, 04 PP-02b Services for Completion 112,000 115,938 - SSS LS Prior - 18 2013 2013 2013 2013 of the Feasibility Study Feb 02, June 14, July 22, Otc 22, Otc 22, 05 PP-03 Design of Interceptor 2,600,000 1,803,128 - QCBS LS Prior 25 2013 2013 2013 2013 2013 Consultant to select the Feb 02, July 04, Aug 14, Jan 25, Jan 25, 06 PP-04 contractor for design, 1,000,000 661,984 - QCBS LS Prior 16 2013 2013 2013 2014 2014 build of wastewater Total A: 5,760,611 4,857,188 110,023 Revised Contract Type Review Cost No Packa Selection of by WB Issuance Bids Description Estimate Contract Signing Delivery Date . ge No. PPTAF Counterpart Method Contr (Prior of RFQ Received (USD) funds funds act or Post) B. FOR GOODS, NON-CONSULTING SERVICES 01 PP-05 Strengthening the 49,000 94,362 - SOE Prior - - Feb 19, 2014 - capacity - for the IMA 02 PP-06 Office equipment for June 13, June 13, 49,000 48,450 - Shopping LS Post July 19, 2013 July 29, 2013 PMU 2013 2013 Total B: 98,000 142,812 - Total (A + B) 5,858,611 5,000,000 110,023(*) (*): The value before the cost incurred for the PP-01 contract is 70.223USD.