Procurement Plan Project Name: Myanmar Electric Power Project Implementing Agency: Myanmar Electric Power Enterprise (MEPE) I. General 1. Bank’s approval Date of the procurement Plan : August 27, 2013 2. Date of General Procurement Notice: October 23, 2013 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) >100,000 All 2. Shopping (Goods) < 100,000 First Contract 2. Prequalification. Bidders for Combined-Cycle Gas Turbine (CCGT) Power Plant shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 Ref. Description Procurement Domestic Review Comments No. Method Preference by Bank (yes/no) (Prior / Post) MEPE- CCGT Power ICB No Prior S&I-1 Plant (Supply & Installation) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments (USD) 1. Competitive Methods (Firms)  100,000 2. Single Source (Firms) All 3. Individual  50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: In case the advance procurement to hire an international consulting firm will assist MEPE in the procurement of CCGT power plant, the retroactive financing will apply. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Ref. No. Description of Assignment Selection Review Comments Method by Bank (Prior / Post) MEPE- Technical Assistance (TA) for Firm Prior CS-1 the National Electrification QCBS Plan MEPE- TA for financial analysis and Firm Prior CS-2 forecasting QBS MEPE- TA for economic valuation of Firm Prior CS-3 cost of gas supply QBS MEPE- TA on electricity tariffs Firm Prior CS-4 QCBS MEPE- TA on Environmental and Firm Prior CS-5 Social Safeguards QCBS MEPE- Procurement Specialist Individual Prior CS-6 MEPE- FM Specialist Individual Prior CS-7 MEPE- Owners Engineer Firm Prior CS-8 QCBS