Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: November 2013; Revision: …………….] 2. Date of General Procurement Notice: 9th July 2013 3. Period covered by this procurement plan: The procurement period of project covered from year July 2013 to April 2015. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 3,000,000 All 2. NCB (Goods) Above US$ 1,000,000 First contract subject to prior review 3. ICB (Works) Above US$ 40, 000,000 All 4. NCB (Works) Above US$ 10, 000,000 First contract subject to prior review 5. Non-Consultant Services Below US$ 1,000,000 First contract subject to prior review 6 Public Private Partnership (PPP) under Below US$40, 000,000 All contracts above NCB Conditions US$10,000,000 will be prior reviewed 7 Public Private Partnership (PPP) under Above US$40, 000,000 All ICB Conditions 2. Pre-qualification [Bidders shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines]: Not Applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per the OPCS March 2012 Guidelines for managing Procurement under CDD projects, Community Based Procurement (CBP) will implement through community Force Account/ or Shopping and Local Competitive Bidding method (LCB). LCB procedure will be limited to local advertisement using such as media as local newspaper or radio, posting notices at strategic places, circulating such notices or reading them out in community meetings or other public gatherings. 4. Reference to (if any) Project Operational/Procurement Manual: A Procurement Manual is developed for the project as per Bank’s Procurement Guidelines. The manual will be reviewed by the Bank and procurement in the project will be done as per procedures described in the Manual and agreed with the Bank. 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] The following provisions constitute additional provisions applicable for purposes of National Competitive Bidding (NCB). NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: • Only the model bidding document for procurement of works through NCB agreed with the Bank (and as amended for time to time), shall be used for bidding; • Invitations to bid shall be advertised in at least one widely circulated national daily newspaper, at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small scale enterprises or enterprises from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • Extension of bid validity shall not be allowed for prior review packages, without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for prior approved packages, all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); • Re-bidding shall not be carried out without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; • Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; • Two or three envelop system will not be used. However, two part bidding for NCB works (as described in the model bidding document) has been agreed by the Bank under this project, as followed in a similar Bank funded project “Pradhan Mantri Gram Sadak Yojana (PMGSY)”. • Domestic preferences shall not be applicable. • All procurement of works through NCB in the four participating states will be done through a standardized e-procurement system acceptable to the Bank. • As per paragraph 1.14(e) of the World Bank’s Procurement Guidelines, the Association’s right to inspect the accounts and records of bidders, suppliers and contractors will be included in the bidding documents. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / million Post) Summary of Post/ the ICB None None No Prior (Works) Summary of Post/ the ICB None None No Prior (Goods) Summary of the NCB 158.93 6 No Prior All (Works) Summary of 1st contract the NCB 149.07 296 No Post for Prior (Works) Review Summary of Post/ the NCB None None No Prior (Goods) Summary of the ICB Post/ (Non- None None No Prior Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 1st contract for Prior Review 2. Single Source (Firms) All All 3. Individual Above US$ 50,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of number of 44.01 17 Prior All contracts that will be let under QCBS 2 Summary of 1st contract number of 2.87 6 Post for Prior contracts that will Review be let under QCBS 3 Summary of number of 1st contract contracts that will 1.49 13 Post for Prior be let under other Review methods PROCUREMENT India : IN Rural Water Supply and Sanitation Project for Low Income States PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-03-08 2018-10-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132173 GPN Date: Project Name: IN Rural Water Supply and Sanitation Project for Low Income States Loan / Credit No: IDA / 53450 Executing Agency(ies):Public Health Engineering Department, Drinking Water and Sanitation Department, State Project Management Unit Lucknow, State Project Management Unit (Assam), National Project Management Unit (RWSS) WORKS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR - 21 GHOGHA GHAT Multi Village Piped / Design and build of all system components of Request for Single Stage - GHOGHAGHAT Multi IDA / 53450 Prior Open - National 6,031,231.33 Signed Bids One Envelope Village piped water supply scheme including billing and collection of tariff from customers WBR No. 7 [Chota Govindpur,Baghbera, Jh] / Request for Open - Single Stage - Rural Pipe Water Supply IDA / 53450 Prior 37,362,992.55 Signed Bids International One Envelope Scheme - Chhota Govindpur and Baghbera, Jharkhand Under W14/JH/207 / Udikel-MVS Request for Single Stage - 2017-09- 2017-10- 2017-12- 2018-02- 2018-04- 2025-03- IDA / 53450 Post Open - National 0.00 Implement (Khunti) Bids Two Envelope 15 15 14 26 02 31 ation IN-SPMU-ASSAM-22915- Pending Request for Single Stage - 2018-01- 2018-03- 2018-05- CW-RFQ / Furnishing of IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 09 06 20 DPMU office, Jorhat ation IN-SPMU-ASSAM-22921- CW-RFQ / Repair, Pending Request for Single Stage - 2017-11- 2018-01- 2018-03- renovation and upgradation IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 20 15 31 of existing building of ation Kamrup district level testing laboratory IN-SPMU-ASSAM-22925- CW-RFQ / Repair, Request for Single Stage - 2017-11- 2018-01- 2018-03- renovation and upgradation IDA / 53450 Post Open - National 18,896.77 Signed Quotations One Envelope 20 15 31 of existing building of Jorhat district level testing laboratory IN-SPMU-ASSAM-22926- CW-RFQ / Repair, Pending renovation and upgradation Request for Single Stage - 2017-11- 2018-01- 2018-03- IDA / 53450 Post Open - National 0.00 Implement of existing building of Quotations One Envelope 20 15 31 ation Hailakandi district level testing laboratory IN-SPMU-ASSAM-22928- CW-RFQ / Extension, Repair, renovation and Request for Single Stage - 2017-11- 2018-01- 2018-03- IDA / 53450 Post Open - National 9,319.98 Signed upgradation of existing Quotations One Envelope 20 15 31 building of Bongaigaoni district level testing laboratory IN-SPMU-ASSAM-22929- CW-RFQ / Extension, Repair, renovation and Request for Single Stage - 2017-11- 2018-01- 2018-03- IDA / 53450 Post Open - National 6,065.07 Signed upgradation of existing Quotations One Envelope 20 15 31 building of Morigaon district level testing laboratory IN-SPMU-ASSAM-22930- CW-RFQ / Extension, Pending Repair, renovation and Request for Single Stage - 2017-11- 2018-01- 2018-03- IDA / 53450 Post Open - National 0.00 Implement upgradation of existing Quotations One Envelope 20 15 31 ation building of Sivasagar district level testing laboratory W17/JHDM/019 / Pending Request for Single Stage - 2017-11- 2018-01- 2018-07- Renovation of Existing IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 19 14 13 Laboratory (Dumka) ation W17/JHES/021 / Pending Request for Single Stage - 2017-11- 2018-01- 2018-07- RENOVATION OF IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 19 14 13 EXISTING LAB ation W14/JH/236 / Under Request for Single Stage - 2017-10- 2017-12- 2018-12- CONSTRUCTION & IDA / 53450 Post Open - National 92,228.81 Implement Quotations One Envelope 15 10 10 SUPPLY OF PWS ation Piskahatu IN-SPMU-ASSAM-21480- CW-RFB / Design, Build, Operate and Transfer Multi-village Water Supply Pending Request for Single Stage - 2017-12- 2017-12- 2018-01- 2018-04- 2018-05- 2026-06- Scheme, Greater Jogighopa IDA / 53450 Prior Open - National 0.00 Implement Bids Two Envelope 11 16 27 19 31 25 Piped Water Supply ation Scheme in Bongaigaon District with operation and maintenance period of five years. IN-SPMU-ASSAM-21436- CW-RFB / Design, Build, Operate and Transfer Multi-village Water Supply Request for Single Stage - Under 2017-10- 2017-11- 2017-12- 2018-03- 2018-04- 2026-05- Scheme, Greater Mayang IDA / 53450 Prior Open - National 0.00 Bids Two Envelope Review 31 05 17 09 20 15 Piped Water Supply Scheme in Morigaon District with operation and maintenance period of five years. IN-SPMU-ASSAM-21446- CW-RFB / Design, Build, Operate and Transfer Multi-village Water Supply Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-05- 2026-06- Scheme, Amguri-Gaurisagar IDA / 53450 Prior Open - National 0.00 Implement Bids Two Envelope 20 25 06 29 10 04 Piped Water Supply ation Scheme in Sivasagar District with operation and maintenance period of five years. W17/JHSK/011 / Pending Request for Single Stage - 2017-11- 2018-01- 2018-07- Renovation of Water IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 19 14 13 Quality Testing Laboratory, ation Saraikela W14/JH/083 / Under CONSTRUCTION & Request for Single Stage - 2017-09- 2017-10- 2017-11- 2018-02- 2018-03- 2025-02- IDA / 53450 Post Open - National 0.00 Implement SUPPLY OF PWSS Lapo- Bids Two Envelope 15 15 26 08 15 06 ation dumaria W14/JH/246 / Under CONSTRUCTION & Request for Single Stage - 2017-09- 2017-10- 2017-11- 2018-02- 2018-03- 2025-02- IDA / 53450 Post Open - National 0.00 Implement SUPPLY OF PWS Bids Two Envelope 15 15 26 08 15 06 ation Satbarwa/ Bakoria, Palamu Under W14/JH/208 / Request for Single Stage - 2017-09- 2017-10- 2017-11- 2018-02- 2018-03- 2025-02- IDA / 53450 Post Open - National 0.00 Implement Construction of Kanti-MVS Bids Two Envelope 15 15 26 08 15 06 ation W14/JH/185 / Itagarh Under Request for Single Stage - 2017-09- 2017-10- 2017-12- 2018-02- 2018-03- 2025-02- Water Supply Scheme IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 15 20 01 13 20 11 (MVS) ation W14/JH/184 / Dudra Under Request for Single Stage - 2017-09- 2017-10- 2017-12- 2018-02- 2018-03- 2025-02- Kamalpur Water Supply IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 15 20 01 13 20 11 Scheme (MVS) ation W17/JHKH/009 / Pending Renovation of Water Request for Single Stage - 2017-11- 2018-01- 2018-07- IDA / 53450 Post Open - National 0.00 Implement Quality Testing Laboratory, Quotations One Envelope 19 14 13 ation Khunti W14/JH/001 / Karmkitta- Under Request for Single Stage - 2017-09- 2017-10- 2017-11- 2018-02- 2018-03- 2025-02- Tarni MVS Scheme IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 15 15 26 08 15 06 (Dumka) ation W17/JHGR/012 / Pending Renovation of Water Request for Single Stage - 2017-11- 2018-01- 2018-07- IDA / 53450 Post Open - National 0.00 Implement Quality Testing Laboratory, Quotations One Envelope 19 14 13 ation Garhwa IN-SPMU-UP-29914-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Holapur , IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Gonda ation IN-SPMU-UP-30067-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Jalalpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Routiha, Gonda ation IN-SPMU-UP-30069-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Nahawa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Parsaura, Gonda ation IN-SPMU-UP-30070-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Kalwari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Gonda ation IN-SPMU-UP-30078-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Basalatpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Gonda ation IN-SPMU-UP-30080-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Malauna, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Gonda ation IN-SPMU-UP-30082-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Madhopur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Gonda ation IN-SPMU-UP-30120-CW- Pending Request for Single Stage - 2017-11- 2017-11- 2018-01- 2018-03- 2018-04- 2018-10- RFB / Batch 2 Thuma IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 06 21 25 22 Mohan, Ballia ation IN-SPMU-UP-30153-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 Bhaisa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 khoot, Santkabeer Nagar, ation IN-SPMU-UP-30242-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 Khazuri, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Santkabeer Nagar ation IN-SPMU-UP-30247-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 Tema IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Rahmat, Santkabeer Nagar ation IN-SPMU-UP-30257-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 Molnapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Santkabeer Nagar ation Page 1 IN-SPMU-UP-30262-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Parjapatipur, Santkabeer ation Nagar IN-SPMU-UP-31763-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Umaria,Santkabeernagar ation IN-SPMU-UP-31770-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Madhavpur, ation SantkabeerNagar IN-SPMU-UP-31776-CW- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-05- 2018-11- RFB / Batch 2 Mudiyari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 05 20 25 21 Santkabeer Nagar ation IN-SPMU-UP-32629-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Khanpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Gonda ation IN-SPMU-UP-32664-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Bahadurpur Ta. IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Ibrahimpur, Allahabad ation IN-SPMU-UP-33557-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Akbarpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Urf Gangaganj, Allahabad ation IN-SPMU-UP-34014-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Kakra, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Allahabad ation IN-SPMU-UP-34044-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Patana IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Uparhar, Allahabad ation IN-SPMU-UP-34066-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Badpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 (Vedpur) Uparhar, ation Allahabad IN-SPMU-UP-34322-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Tikari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Allahabad ation IN-SPMU-UP-34769-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Achhola IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Uparhar, Allahabad ation IN-SPMU-UP-34771-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Chaukatha IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Narwar , Allahabad ation IN-SPMU-UP-34905-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Alampur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Narhi, Fatehpur ation IN-SPMU-UP-34919-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Firozpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Fatehpur ation IN-SPMU-UP-34942-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Sihar, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Fatehpur ation IN-SPMU-UP-34944-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Tanda, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Fatehpur ation IN-SPMU-UP-35087-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kishoi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Fatehpur ation IN-SPMU-UP-35089-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kudhan, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Fatehpur ation IN-SPMU-UP-35103-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Ibrahimpur, Fatehpur ation IN-SPMU-UP-35104-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Karanpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Fatehpur ation IN-SPMU-UP-35112-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Hajipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Gang, Fatehpur ation IN-SPMU-UP-35113-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Nasirpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Belwara, Fatehpur ation IN-SPMU-UP-35256-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Husenpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Ghazipur ation IN-SPMU-UP-35340-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kathut, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Ghazipur ation IN-SPMU-UP-35341-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Nagwa Urf IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Nawapara, Ghazipur ation IN-SPMU-UP-35343-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-03- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Tiwaripur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 10 15 29 11 16 12 Ghazipur ation IN-SPMU-UP-35567-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Amba, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-35572-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Chandpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-35601-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Tatepur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-35609-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Gaura IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Purwar, Varanasi ation IN-SPMU-UP-35724-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Domari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-38689-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Batch 2 Khatagia, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Allahabad ation IN-SPMU-UP-38690-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Batch 2 Anthaiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Allahabad ation IN-SPMU-UP-38693-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Nibi TA. Khaivi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Allahabad ation IN-SPMU-UP-38694-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Batch 2 Taroila, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Allahabad ation IN-SPMU-UP-38696-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Gosandepur, Ghazipur ation IN-SPMU-UP-38698-CW- Pending Request for Single Stage - 2017-11- 2017-12- 2018-01- 2018-03- 2018-05- 2018-11- RFB / Batch 2 Baramar, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 30 05 16 31 05 01 Allahabad ation IN-SPMU-BIHAR-40693- Pending CW-RFB / DBOMT Mahgu Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40695- Pending CW-RFB / DBOM Lila Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40696- Pending CW-RFB / DBOM Kathutia Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Kalan Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40697- Pending CW-RFB / DBOM Karkuri Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Patna under Batch-II IN-SPMU-BIHAR-40699- CW-RFB / DBOM Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Kathutiya Khurd Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Patna ation under Batch-II IN-SPMU-BIHAR-40701- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Wadipur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40703- Pending CW-RFB / DBOMT Ajni Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement east Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under Batch-II IN-SPMU-BIHAR-40704- Pending CW-RFB / DBOMT Kanahi Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40705- Pending CW-RFB / DBOMT Ajni Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement West Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under Batch-II IN-SPMU-BIHAR-40706- Pending CW-RFB / DBOMT Sattar Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Patna under Batch-II Page 2 IN-SPMU-BIHAR-40707- Pending CW-RFB / DBOMT Akha Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40710- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Buzurgabad Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40709- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Makdumpur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40713- Pending CW-RFB / DBOMT Dihi Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40714- Pending CW-RFB / DBOMT Lakhni Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Bigha Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40717- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Hirachak Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40718- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Dhayan chakki Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Begusarai ation under batch-II IN-SPMU-BIHAR-40719- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Pokhara Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40720- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Gangraho Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40722- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Gopalpur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40723- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Harerampur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40724- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Shivchak Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40725- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Lalunagar (Lakho) Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Begusarai ation under batch-II IN-SPMU-BIHAR-40727- Pending CW-RFB / Mirzapur Single Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Village Scheme, Begusarai Bids Two Envelope 26 31 11 13 23 23 ation under batch-II IN-SPMU-BIHAR-40730- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Hatiyakand Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40729- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Begampur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40732- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Ismailpur & Dhibra single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Patna ation under Batch-II IN-SPMU-BIHAR-40733- Pending CW-RFB / DBOMT Patla Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40734- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Hisarpur Single village Bids Two Envelope 26 31 11 13 23 23 ation scheme, Patna under Batch-II IN-SPMU-BIHAR-40736- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Brijnarayan Single village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40738- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Paranpur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40739- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- CHAKRAHIMA Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Patna ation under Batch-II IN-SPMU-BIHAR-40740- Pending CW-RFB / DBOMT Sagi-II Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40741- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement ABDALPUR Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40742- Pending CW-RFB / DBOMT Tetrahi Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40743- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement ANDARI Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40744- Pending CW-RFB / DBOMT Rajura Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40747- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Govindpur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40748- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement GAWASPUR Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40749- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Pirnagar Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40750- Pending CW-RFB / DBOMT KAJI Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement BIGHA Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40751- Pending CW-RFB / DBOMT Jana Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40756- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement KOHAWAN Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40758- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Pansala Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40759- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement NATHUPUR Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40760- Pending CW-RFB / DBOMT Mortar Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40761- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement THEGUA Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Patna under Batch-II IN-SPMU-BIHAR-40762- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Musepur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40765- Pending CW-RFB / DBOMT Kaura Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40767- Pending CW-RFB / DBOMT Chakki Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40770- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Bahauchack Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II Page 3 IN-SPMU-BIHAR-40771- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Rajadumri Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Begusarai under batch-II IN-SPMU-BIHAR-40819- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Matihani Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Muzaffarpur under Batch-II IN-SPMU-BIHAR-40820- Pending CW-RFB / DBOMT Rannu Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Rai Single Village Scheme Bids Two Envelope 26 31 11 13 23 23 ation Muzaffarpur under Batch- II IN-SPMU-BIHAR-40821- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Dhanaur West Single Bids Two Envelope 26 31 11 13 23 23 ation Village Scheme Muzaffarpur under Batch- II IN-SPMU-BIHAR-40822- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Devpura & Saidpur Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Begusarai ation under batch-II IN-SPMU-BIHAR-40823- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Gosrawan Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40825- Pending CW-RFB / DBOMT Bara Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40824- Pending CW-RFB / DBOMT Simra Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement West Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40826- Pending CW-RFB / DBOMT Sagi-I Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 26 31 11 13 23 23 ation Begusarai under batch-II IN-SPMU-BIHAR-40827- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Gyaspur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40828- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Bhagwanbigha Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Hilsa, ation Nalanda under batch-II IN-SPMU-BIHAR-40829- CW-RFB / DBOMT Raila Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Narayan Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme Muzaffarpur Under ation Batch-II IN-SPMU-BIHAR-40830- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Mohammadpur Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Hilsa, ation Nalanda under batch-II IN-SPMU-BIHAR-40831- Pending CW-RFB / DBOMT Kamla Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Baliya Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40832- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Kulwapokhar Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Hilsa, Nalanda ation under batch-II IN-SPMU-BIHAR-40833- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Laxman Nagar Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme ation Muzaffarpur Under Batch- II IN-SPMU-BIHAR-40834- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Musahri Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Hilsa, Nalanda ation under batch-II IN-SPMU-BIHAR-40835- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-04- 2019-04- Bongrapokhar Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 02 12 12 Village Scheme, Hilsa, ation Nalanda under batch-II IN-SPMU-BIHAR-40836- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Bhagwanpur Chapra Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme ation Muzaffarpur Under Batch- II IN-SPMU-BIHAR-40838- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Tarapur Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Hilsa, Nalanda ation under batch-II IN-SPMU-BIHAR-40840- CW-RFB / DBOMT Nirpur Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Single Village Scheme, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Hilsa, Nalanda under ation batch-II IN-SPMU-BIHAR-40842- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Hasepur Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Hilsa, Nalanda ation under batch-II IN-SPMU-BIHAR-40843- Pending CW-RFB / DBOMT Yusuf Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Patti Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40844- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Sanathi Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40845- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Bahadurpur Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Hilsa, Nalanda ation under batch-II IN-SPMU-BIHAR-40850- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Muriyari Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40852- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Parmanandpur Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme ation Muzaffarpur Under Batch- II IN-SPMU-BIHAR-40853- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Chatursi Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40854- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Nimakole Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Hilsa, Nalanda under batch-II IN-SPMU-BIHAR-40855- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Patiyasa Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40856- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Dwarika Bigha Single Bids Two Envelope 26 31 11 13 23 23 ation Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40858- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Ratanpur Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40860- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Bhairwa Single Village Bids Two Envelope 26 31 11 13 23 23 ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40868- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Ganiyari Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 31 11 13 23 23 SchemeMuzaffarpur Under ation Batch-II IN-SPMU-BIHAR-40869- CW-RFB / DBOMT Basant Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- Phulwari Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Scheme, Nalanda under ation batch-II IN-SPMU-BIHAR-40870- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Bishumpur, Baghanagri IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 East Single Village Scheme ation Muzaffarpur Under Batch- II IN-SPMU-BIHAR-40872- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- NANDA BIGHA Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40873- CW-RFB / DBOMT Chako- Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Chapra Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Scheme Muzaffarpur Under ation Batch-II IN-SPMU-BIHAR-40875- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-04- 2018-04- 2019-04- CHATIYANA-NAJIB IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 02 12 12 NAGAR Single Village ation Scheme, Nalanda under batch-II Page 4 IN-SPMU-BIHAR-40877- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Bishunpur Baghanagri IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 West Single Village ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40878- CW-RFB / DBOMT BIRJU Pending MILKI-MOMIN CHAK- Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement CHAKHA MIND- Bids Two Envelope 26 31 11 13 23 23 ation PAINAPUR Single Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40880- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Jalalpur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40881- CW-RFB / DBOMT Pending HUSSAINPUR-MAHMA Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement CHAK-BALBAPAR Single Bids Two Envelope 26 31 11 13 23 23 ation Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40882- Pending CW-RFB / DBOMT Locha Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme Bids Two Envelope 27 01 12 14 24 24 ation Muzaffarpur Under Batch- II IN-SPMU-BIHAR-40884- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement NEPURA Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40886- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Bahadurpur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme Muzaffarpur Under Batch-II IN-SPMU-BIHAR-40887- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- MAHAMADPUR Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40889- CW-RFB / DBOMT DURGANAGAR- Pending Request for Single Stage - 2017-12- 2017-12- 2018-02- 2018-03- 2018-03- 2019-03- SHANKERPUR-BANGALI IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 31 11 13 23 23 BIGHA Single Village ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40890- CW-RFB / DBOMT Dorain Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- khaira Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Scheme, Munger Under ation Batch-II IN-SPMU-BIHAR-40891- CW-RFB / DBOMT Pending GULZAR BIGHA- Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement TAROKHAR-JIBLAT Bids Two Envelope 27 01 12 14 24 24 ation BIGHA Single Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40893- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Muskipur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Munger Under Batch-II IN-SPMU-BIHAR-40896- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Durgapur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Munger Under Batch-II IN-SPMU-BIHAR-40897- CW-RFB / DBOMT Pending THAKUR BIGHA- Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement BISHUNPUR-KALI BIGHA Bids Two Envelope 27 01 12 14 24 24 ation Single Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40898- Pending CW-RFB / DBOMT Sanrhi Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Munger Under Batch-II IN-SPMU-BIHAR-40900- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- KHARUARA-YADAV TOLA IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Single Village Scheme, ation Nalanda under batch-II IN-SPMU-BIHAR-40902- Pending CW-RFB / DBOMT Baha Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Chouki Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Munger Under Batch-II IN-SPMU-BIHAR-40903- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- RATANPURA Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40905- Pending CW-RFB / DBOMT Harpur Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Munger Under Batch-II IN-SPMU-BIHAR-40907- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Pyarpur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Munger Under Batch-II IN-SPMU-BIHAR-40909- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- AJAYPUR-HORIL BIGHA IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Single Village Scheme, ation Nalanda under batch-II IN-SPMU-BIHAR-40910- CW-RFB / DBOMT Pending BELDARIYA-DHARMPUR- Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement BHOJPUR-TARAPUR Bids Two Envelope 27 01 12 14 24 24 ation Single Village Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40911- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- MILKIPUR-HARIHAR IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 BIGHA Single Village ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40912- Pending CW-RFB / DBOMT Mandal Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40913- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- RANGILA BIGHA Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40916- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- KAMDARGANJ Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40917- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Piperpati Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40920- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Ranipatra Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40921- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement BALBAPAR Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40923- Pending CW-RFB / DBOMT Bansar Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Purnea Under Batch-II IN-SPMU-BIHAR-40926- CW-RFB / DBOMT MANIYAWAN-SUNDER Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- BIGHA-EAST SUNDER IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 BIGHA Single Village ation Scheme, Nalanda under batch-II IN-SPMU-BIHAR-40928- CW-RFB / DBOMT Chandi Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Kathua Single Village IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Scheme, Purnea Under ation Batch-II IN-SPMU-BIHAR-40929- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- LAKHICHAK Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Nalanda ation under batch-II IN-SPMU-BIHAR-40930- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Nandgola Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40934- Pending CW-RFB / DBOMT Dhima Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Tola Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40935- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Rampurwa Bagha- II IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Single Village Scheme, ation W.Chmaparan under batch- II IN-SPMU-BIHAR-40936- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Bhagwa Tola Single Bids Two Envelope 27 01 12 14 24 24 ation Village Scheme, Purnea Under Batch-II Page 5 IN-SPMU-BIHAR-40938- Pending CW-RFB / DBOMT Dumri Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Purnea Under Batch-II IN-SPMU-BIHAR-40939- Pending CW-RFB / DBOMT Dev Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Uttar Tola Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40942- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Nagrahi Tola Single Bids Two Envelope 27 01 12 14 24 24 ation Village Scheme, Purnea Under Batch-II IN-SPMU-BIHAR-40944- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Lodhipur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada Under Batch-II IN-SPMU-BIHAR-40946- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Banchehri Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, W.Chmaparan under batch-II IN-SPMU-BIHAR-40947- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Piprakhurd Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada under Batch-II IN-SPMU-BIHAR-40949- CW-RFB / DBOMT Barwat Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- sena (Part II) Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, ation W.Chmaparan under batch- II IN-SPMU-BIHAR-40952- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Keshauriya Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada Under Batch-II IN-SPMU-BIHAR-40950- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Nawalpur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, W.Chmaparan under batch-II IN-SPMU-BIHAR-40954- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Sirpatiy Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada Under Batch-II IN-SPMU-BIHAR-40955- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Bhangaha (part I) Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, ation W.Chmaparan under batch- II IN-SPMU-BIHAR-40957- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Chourma Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada Under Batch-II IN-SPMU-BIHAR-40958- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Gonibigha Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Nawada Under Batch-II IN-SPMU-BIHAR-40959- Pending CW-RFB / DBOMT Faldu Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Nawada under Batch-II IN-SPMU-BIHAR-40967- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Kathbangaon Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Banka under batch-II IN-SPMU-BIHAR-40968- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Dhobidi Khushalpur Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Banka ation under batch-II IN-SPMU-BIHAR-40969- CW-RFB / DBOMT Kothia, Pending Rampur Noor Nagar, Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Jalalpur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Saran under Batch-II IN-SPMU-BIHAR-40970- Pending CW-RFB / DBOMTLalsiya Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Banka under batch-II IN-SPMU-BIHAR-40971- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Jatuwa, Fakull, Chapra IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 sadar Single Village ation Scheme, Saran under Batch-II IN-SPMU-BIHAR-40972- Pending CW-RFB / DBOMT Hassai Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Banka under batch-II IN-SPMU-BIHAR-40973- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Shohsarai, Bajitpur Maiki, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Garkha Single Village ation Scheme, Saran Under Batch-II IN-SPMU-BIHAR-40974- Pending CW-RFB / DBOMT Dauna Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Banka under batch-II IN-SPMU-BIHAR-40975- CW-RFB / DBOMT Pending Rampur, Rampur Noor Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Nagar, Jalalpur Single Bids Two Envelope 27 01 12 14 24 24 ation Village Scheme, Saran under Batch-II IN-SPMU-BIHAR-40976- Pending CW-RFB / DBOMT Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Jankipur Single Village Bids Two Envelope 27 01 12 14 24 24 ation Scheme, Banka under batch-II IN-SPMU-BIHAR-40977- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Sahbajpur, Mibarakpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Marhaurah Single Village ation Scheme, Saran under Batch-II IN-SPMU-BIHAR-40978- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Changeri Mirzapur Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Banka ation under batch-II IN-SPMU-BIHAR-40980- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Betaura Khas Satjora, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Panapur Single Village ation Scheme, Saran under Batch-II IN-SPMU-BIHAR-40982- Pending CW-RFB / DBOMT Bhusar Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Banka under batch-II IN-SPMU-BIHAR-40983- CW-RFB / DBOMT Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Sanichanda SVS IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Mubarakpur, Marhaura ation Single Village Scheme, Saran under Batch-II IN-SPMU-BIHAR-40984- Pending CW-RFB / DBOMT Asi Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Single Village Scheme, Bids Two Envelope 27 01 12 14 24 24 ation Banka under batch-II IN-SPMU-BIHAR-40985- CW-RFB / DBOMT Pending Goskhap SVS Rasulpur Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- IDA / 53450 Post Open - National 0.00 Implement Amnour Amnour Single Bids Two Envelope 27 01 12 14 24 24 ation Village Scheme, Saran under Batch-II IN-SPMU-BIHAR-40986- CW-RFB / DBOMT Aloni, Pending Request for Single Stage - 2017-12- 2018-01- 2018-02- 2018-03- 2018-03- 2019-03- Sargatti, Garkha Single IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 01 12 14 24 24 Village Scheme, Saran ation under Batch-II IN-SPMU-UP-42219-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Rehali, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 03 08 19 04 08 05 Gonda ation IN-SPMU-UP-42221-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 03 08 19 04 08 05 Dasrathpur, Bahraich ation IN-SPMU-UP-42243-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Maniya IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 03 08 20 05 09 06 Uparhar, Allahabad ation IN-SPMU-UP-42415-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Semri IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Malmala, Bahraich ation IN-SPMU-UP-42416-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Khasha IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Mohammadpur, Bahraich ation IN-SPMU-UP-42417-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Sarai Ali, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Bahraich ation IN-SPMU-UP-42418-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Barauli, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Bahraich ation IN-SPMU-UP-42419-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Balamakan, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Bahraich ation IN-SPMU-UP-42420-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Rampur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Kndauli, Bahraich ation Page 6 IN-SPMU-UP-42429-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Narauli, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Fatehpur ation IN-SPMU-UP-42436-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bharsari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Fatehpur ation IN-SPMU-UP-42438-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Gazipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Kkhurd, Fatehpur ation IN-SPMU-UP-42439-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Siakatai, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Santkabir Nagar ation IN-SPMU-UP-42440-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Pakri IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Apaji, Santkabir Nagar ation IN-SPMU-UP-42453-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Jangal IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Dasahar, Santkabir Nagar ation IN-SPMU-UP-42464-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Maheshwarpur, Santkabir ation Nagar IN-SPMU-UP-42465-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Senari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 SantkabirNagar ation IN-SPMU-UP-42468-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Rampur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Uparhar, Allahabad ation IN-SPMU-UP-42471-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Deorakh, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Allahabad ation IN-SPMU-UP-42473-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Semraha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Allahabad ation IN-SPMU-UP-42477-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Gandaila IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Uparhar, Allahabad ation IN-SPMU-UP-42478-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bhuipara IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 04 09 20 05 09 06 Uparhar, Allahabad ation IN-SPMU-UP-42525-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Garhachampa Village, ation Allahabad IN-SPMU-UP-42529-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Purwa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Uparhar, Allahabad ation IN-SPMU-UP-42536-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Lawayan IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Khurd, Allahabad ation IN-SPMU-UP-42574-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Narhar IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Gonda, Bahraich ation IN-SPMU-UP-42590-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Hatwa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Uparhar, Allahabad ation IN-SPMU-UP-42591-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Mahewa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 05 10 21 06 10 07 Uparhar, Allahabad ation IN-SPMU-UP-42824-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Padohiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Bahraich ation IN-SPMU-UP-42829-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-02- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Nasirpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 08 13 24 09 13 10 Ballia ation IN-SPMU-UP-43211-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Lakhrampur, Bahraich ation IN-SPMU-UP-44755-CW- RFB / Upgradation of Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- Existing District Level IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Water Testing Laboratory ation in 14 Districts of Uttar Pradesh IN-SPMU-UP-44756-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bibiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Bahraich ation IN-SPMU-UP-44757-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bijaura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Allahabad ation IN-SPMU-UP-44760-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Bahorikapur, Bahraich ation IN-SPMU-UP-44765-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Basauna IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Mafi, Bahraich ation IN-SPMU-UP-44767-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Rampurwa, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Bahraich ation IN-SPMU-UP-44770-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Chaukhdiya, Bahraich ation IN-SPMU-UP-44771-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 19 24 07 20 24 21 Dellapurwa, Bahraich ation IN-SPMU-UP-44811-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Devidaspur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44812-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Dokari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44813-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Gajipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Kodari, Bahraich ation IN-SPMU-UP-44814-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Gangapurwa, Bahraich ation IN-SPMU-UP-44815-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Naubana, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44816-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Chulama, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44817-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Dharampur, Bahraich ation IN-SPMU-UP-44818-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Dhanpara, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44819-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Alahiyapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44820-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Supani, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44821-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Tendwa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bajantpur, Bahraich ation IN-SPMU-UP-44822-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Pure Jaita, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44823-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bulha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44824-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Chandela, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44825-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Chailal, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44826-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Chandradipa, Bahraich ation IN-SPMU-UP-44827-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Huzoorpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44828-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Jagta IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Jallalpur, Bahraich ation IN-SPMU-UP-44829-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Jaisinghpur, Bahraich ation IN-SPMU-UP-44830-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Khairisamyasa, Bahraich ation Page 7 IN-SPMU-UP-44832-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Hemariya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44833-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Laukiha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44834-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Materpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44835-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Mudhapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44836-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Murtiha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44837-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Raigarh IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Baheda, Bahraich ation IN-SPMU-UP-44838-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Sadhuwapur Gokulpur, ation Bahraich IN-SPMU-UP-44840-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Sayyad IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Nagar, Bahraich ation IN-SPMU-UP-44841-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Pipraon IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Ta. Karchana, Allahabad ation IN-SPMU-UP-44843-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Mawaiya IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Uparhar, Allahabad ation IN-SPMU-UP-44857-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Kharauwa, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Gonda ation IN-SPMU-UP-44858-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Devra Nar, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Fatehpur ation IN-SPMU-UP-44859-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Mishirpura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Varanasi ation IN-SPMU-UP-44860-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Bariya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Bahraich ation IN-SPMU-UP-44861-CW- Pending Request for Single Stage - 2018-01- 2018-01- 2018-03- 2018-05- 2018-06- 2018-12- RFB / Batch 2 Chandayar IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 25 22 Walipur, Ballia ation IN-SPMU-UP-49201-CW- Under Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Ahmadpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Asrauli Uparhar, Allahabad ation IN-SPMU-UP-49203-CW- Under Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Babhani IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Hethar, Allahabad ation IN-SPMU-UP-49208-CW- Under Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Bahmalpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Allahabad ation IN-SPMU-UP-49213-CW- Under Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Bahorikapur, Allahabad ation IN-SPMU-UP-49426-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Barhauli, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49428-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Bhabhaura IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-49430-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Bundwan, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49432-CW- Under RFB / Batch 2 Chaq Sekh Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Ahmed Urf Kusetha, Bids Two Envelope 25 02 13 26 31 27 ation Allahabad IN-SPMU-UP-49435-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Chauka, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49438-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Chhatava IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-49475-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Bharkhokha, Ballia ation IN-SPMU-UP-49486-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Baghoonch, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-49503-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Tikhampur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-49506-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Dighiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49509-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Ramna, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Varanasi ation IN-SPMU-UP-49512-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Kaithi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Varanasi ation IN-SPMU-UP-49514-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Dulapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49515-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Tikari, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Varanasi ation IN-SPMU-UP-49521-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Gaddopur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49544-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Ganeshipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-49550-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Habeliya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49585-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Jalalpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Ghoshi, Allahabad ation IN-SPMU-UP-49677-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Ramchandipur, Varanasi ation IN-SPMU-UP-49679-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Muridpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-49684-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Jera and IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Saray Kala, Allahabad ation IN-SPMU-UP-49688-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kabra, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49690-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kaneda IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-49698-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Karuwa, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49705-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Lootha IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 kala, Varanasi ation IN-SPMU-UP-49709-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Katwarupur, Allahabad ation IN-SPMU-UP-49711-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Chhitauni , IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Varanasi ation IN-SPMU-UP-49717-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kosda IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Khurd, Allahabad ation IN-SPMU-UP-49723-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Unchadeeh IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 , SiddharthNagar ation IN-SPMU-UP-49729-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Tandawa , IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 SiddharthNagar ation IN-SPMU-UP-49735-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sohana, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 SiddharthNagar ation Page 8 IN-SPMU-UP-49758-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Siswa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Bujurg, SiddharthNagar ation IN-SPMU-UP-49764-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sikautha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Siddharth Nagar ation IN-SPMU-UP-49767-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Semra, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 SiddharthNagar ation IN-SPMU-UP-49771-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Rasulpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 20 25 08 21 26 22 Siddharth Nagar ation IN-SPMU-UP-49775-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kukhuri, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49779-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Kusungur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49781-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Lai Group, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49784-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Lakhanpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-49785-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Lawayan IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Kala Uparhar, Allahabad ation IN-SPMU-UP-49794-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Madafa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Kala, Allahabad ation IN-SPMU-UP-49809-CW- Under RFB / Batch 2 Madara Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Mukundpur Uparhar, Bids Two Envelope 25 02 13 26 31 27 ation Allahabad IN-SPMU-UP-49817-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Mahewakala, Allahabad ation IN-SPMU-UP-49821-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Malak IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Herher, Allahabad ation IN-SPMU-UP-49827-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Mirzapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-50015-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Ramwapur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Jagatram, Siddharth Nagar ation IN-SPMU-UP-50045-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Pipra IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Pandey, Siddharth Nagar ation IN-SPMU-UP-50051-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Pedari IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Mustahkam, Siddharth ation Nagar IN-SPMU-UP-50056-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Patna IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Bishunpur, Siddharth ation Nagar IN-SPMU-UP-50058-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Marwatiya, Siddharth ation Nagar IN-SPMU-UP-50063-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Manikaura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Siddharth Nagar ation IN-SPMU-UP-50071-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Malda, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 21 26 09 22 27 23 Siddharth Nagar ation IN-SPMU-UP-50419-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Mubarakpur Uparhar, ation Allahabad IN-SPMU-UP-50423-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Nadula, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-50424-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Nahawa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Urf Nimikla, Allahabad ation IN-SPMU-UP-50428-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Maina IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Khas, Siddharth Nagar ation IN-SPMU-UP-50455-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Nasirpatti, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Allahabad ation IN-SPMU-UP-50463-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Mahadeiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50468-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Onaur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-50471-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Madanpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50474-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Laljot, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50475-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Palikaranpur Uparhar, ation Allahabad IN-SPMU-UP-50484-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Lakda, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50528-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Kot Khas, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50536-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Kharika IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Pandey, Siddharth Nagar ation IN-SPMU-UP-50543-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch 2 Panasa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 25 02 13 26 31 27 Uparhar, Allahabad ation IN-SPMU-UP-50542-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Khairkaura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 22 27 10 23 28 24 Siddharth Nagar ation IN-SPMU-UP-50774-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2Khairi IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Sheetal Prasad, Siddharth ation Nagar IN-SPMU-UP-50776-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Kanchanpur, Siddharth ation Nagar IN-SPMU-UP-50814-CW- Pending RFB / Batch-2 Kan Bhari Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50822-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Pipra IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Scheme Distt. Ballia ation IN-SPMU-UP-50825-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sahras IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Pali, Ballia ation IN-SPMU-UP-50819-CW- Pending RFB / Batch-2 Hata khas Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50830-CW- Pending RFB / Batch-2 Golhaura Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50828-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Saraya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-50836-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sarwar IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Kakar Ghatt, Balliai ation IN-SPMU-UP-50835-CW- Pending RFB / Batch-2 Gauhaniya Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Raj PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50848-CW- Pending RFB / Batch-2 Ganwariya Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50853-CW- Pending RFB / Batch-2 Gangwal Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50860-CW- Pending RFB / Batch-2 Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Gadakhauwa PWS Bids Two Envelope 23 28 11 24 29 25 ation Scheme Distt. Siddharth Nagar Page 9 IN-SPMU-UP-50864-CW- Pending RFB / Batch-2 Deipar Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50870-CW- Pending RFB / Batch-2 Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Chaukhadha PWS Scheme Bids Two Envelope 23 28 11 24 29 25 ation Distt. Siddharth Nagar IN-SPMU-UP-50875-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Shivpur Diyar IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Numbrey, Ballia ation IN-SPMU-UP-50878-CW- Pending RFB / Batch-2 Charthari Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50879-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sonki Bhat, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-50881-CW- Pending RFB / Batch-2 Chakai Jot Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50882-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Sripatipur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-50884-CW- Pending RFB / Batch-2 Biskohar Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 23 28 11 24 29 25 ation Siddharth Nagar IN-SPMU-UP-50886-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Udaypura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-50889-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Udhran, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Ballia ation IN-SPMU-UP-50893-CW- Pending Request for Single Stage - 2018-02- 2018-02- 2018-04- 2018-06- 2018-07- 2019-01- RFB / Batch-2 Abhaypur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 23 28 11 24 29 25 Fatehpur ation IN-SPMU-UP-51080-CW- Pending RFB / Batch-2 Bhujrahi Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51083-CW- Pending RFB / Batch-2 Bhatijwapur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51086-CW- Pending RFB / Batch-2 Bhanpur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Rain PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51087-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Adampur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51091-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Baghauli, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51092-CW- Pending RFB / Batch-2 Bahariya Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51094-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Baigaon, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51095-CW- Pending RFB / Batch-2 Baghini Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51099-CW- Pending RFB / Batch-2 Bagdihwa Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Siddharth Nagar IN-SPMU-UP-51106-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Pandila, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51110-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Bhaupur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51114-CW- Pending RFB / Batch-2 Umari Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Khurd PWS Scheme Bids Two Envelope 26 03 14 27 01 28 ation Distt. Sant Kabir Nagar IN-SPMU-UP-51115-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Devmai, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 fatehpur ation IN-SPMU-UP-51113-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Pipari IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 (Piyari, Allahabad ation IN-SPMU-UP-51116-CW- Pending RFB / Batch-2 Pharendiya Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation Kabir Nagar IN-SPMU-UP-51120-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Pipraon, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51122-CW- Pending RFB / Batch-2 Neeba Horil Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation Kabir Nagar IN-SPMU-UP-51119-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Galatha IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51124-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Pure IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghasi, Allahabad ation IN-SPMU-UP-51125-CW- Pending RFB / Batch-2 Manjhariya Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation Kabir Nagar IN-SPMU-UP-51129-CW- Pending RFB / Batch-2 Kali Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Lagdishpur PWS Scheme Bids Two Envelope 26 03 14 27 01 28 ation Distt. Sant kabir Nagar IN-SPMU-UP-51133-CW- Pending RFB / Batch-2 Jigina Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation kabir Nagar IN-SPMU-UP-51149-CW- Pending RFB / Batch 2 Raipura Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Uparhar - Kanjauli Bids Two Envelope 28 05 16 29 03 30 ation Uparhar, Allahabad IN-SPMU-UP-51150-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Guneer, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51153-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Rampur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51148-CW- Pending RFB / Batch-2 Jagdishpur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Urf Lahuradeva PWS Bids Two Envelope 26 03 14 27 01 28 ation Scheme Distt. Sant kabir Nagar IN-SPMU-UP-51152-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ibrahimpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51154-CW- Pending RFB / Batch 2 Rasoolpur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Kashipur Uparhar, Bids Two Envelope 28 05 16 29 03 30 ation Allahabad IN-SPMU-UP-51157-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Rawatpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51160-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Samaha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51162-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ijaura IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 khurd, fatehpur ation IN-SPMU-UP-51161-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Sangram IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Patti, Allahabad ation IN-SPMU-UP-51164-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Khalispur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51163-CW- Pending RFB / Batch-2 Dulhipar Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation Kabir Nagar IN-SPMU-UP-51167-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Sarai IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Dadan Uparhar, Allahabad ation Page 10 IN-SPMU-UP-51170-CW- Pending RFB / Batch-2 Barghat Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation kabir Nagar IN-SPMU-UP-51171-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Kotla, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51173-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Sarairah IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 urf Korari, Allahabad ation IN-SPMU-UP-51174-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Lahangi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51179-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Tarvai, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51180-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Lakhpura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51184-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Ujihani IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Aima, Allahabad ation IN-SPMU-UP-51185-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Mahadevpur, Fatehpur ation IN-SPMU-UP-51187-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Makhdumpur Kalan, ation Fatehpur IN-SPMU-UP-51181-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Teliya IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Tara, Allahabad ation IN-SPMU-UP-51191-CW- Pending RFB / Batch-2 Aura dand Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement G.P PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Sant kabir Nagar IN-SPMU-UP-51194-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Mirmau, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51197-CW- Pending RFB / Batch-2 Amraha Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement PWS Scheme Distt. Sant Bids Two Envelope 26 03 14 27 01 28 ation kabir Nagar IN-SPMU-UP-51192-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Tharwai, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Allahabad ation IN-SPMU-UP-51198-CW- Pending RFB / Batch-2 Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Paigambarpur Rikouha Bids Two Envelope 26 03 14 27 01 28 ation PWS Scheme Distt. Fatehpur IN-SPMU-UP-51193-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Tikari - IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Saidabad, Allahabad ation IN-SPMU-UP-51203-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Nizamuddeenpur, Fatehpur ation IN-SPMU-UP-51202-CW- Pending RFB / Batch-2 Shyam Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Patti PWS Scheme Distt. Bids Two Envelope 26 03 14 27 01 28 ation Kushinagar IN-SPMU-UP-51210-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Rasulpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Bhandra, Fatehpur ation IN-SPMU-UP-51215-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ravatpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 (Khajuwa), Fatehpur ation IN-SPMU-UP-51220-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Umapur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Kala, Allahabad ation IN-SPMU-UP-51221-CW- Under Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Upraura IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Uparhar, Allahabad ation IN-SPMU-UP-51222-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ravatpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Aung, Fatehpur ation IN-SPMU-UP-51224-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ravatpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 (Telyani), Fatehpur ation IN-SPMU-UP-51226-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Baidaura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51229-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Shivrajpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51232-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Bhoga Jot, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51227-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Bhainsaha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51231-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Surajipur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Fatehpur ation IN-SPMU-UP-51236-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Chakujot, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51238-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Chauksahar, Bahraich ation IN-SPMU-UP-51237-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Sakadarpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. Gonda ation IN-SPMU-UP-51244-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Gajadharpur, Bahraich ation IN-SPMU-UP-51240-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Tarapur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Bhitaura ation IN-SPMU-UP-51246-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Ranijot IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. Gonda ation IN-SPMU-UP-51242-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Daulatpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51249-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Haibatpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51250-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Mijhaura IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. Gonda ation IN-SPMU-UP-51253-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ichachhapur, Bahraich ation IN-SPMU-UP-51255-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Intaha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51257-CW- Pending RFB / Batch-2 Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Dumariyadeeh Zone-II Bids Two Envelope 26 03 14 27 01 28 ation PWS Scheme Distt. Gonda IN-SPMU-UP-51256-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Jhingaha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51245-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Aaspur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51259-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Khaira IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Kalan, Bahraich ation IN-SPMU-UP-51264-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-1 Akberpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51267-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Madhawapur, Bahraich ation IN-SPMU-UP-51265-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Kotiya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 bahraich ation IN-SPMU-UP-51269-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Babura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51268-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Araji kasba IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Swad, ghazipur ation Page 11 IN-SPMU-UP-51272-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Baghan, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51271-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Mahasi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51273-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Mjhara, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51276-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Bavara, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51277-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Bayepur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51280-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Raja IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Rehua, Bahraich ation IN-SPMU-UP-51279-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Sikandarpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51274-CW- Pending RFB / Batch-2 Tajpur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Manjha PWS Scheme Bids Two Envelope 26 03 14 27 01 28 ation Distt. Ghazipur IN-SPMU-UP-51278-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Muwafikpur, Bahraich ation IN-SPMU-UP-51283-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Charipur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51286-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Rajapurkalan, Bahraich ation IN-SPMU-UP-51287-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Raundopur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51282-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Sawana IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51291-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Rewali, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51285-CW- Pending RFB / Batch-2 Sadhopur Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement urf Rampur PWS Scheme Bids Two Envelope 26 03 14 27 01 28 ation Distt. Ghazipur IN-SPMU-UP-51295-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Shahawapur Mahipal ation Singh, Bahraich IN-SPMU-UP-51296-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Chochakpur, Ghazipur ation IN-SPMU-UP-51298-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Dewariya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51300-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Reotipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51301-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Sai Gaon, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51303-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Deoria, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51307-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Sisia Chak, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51297-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Shakkarpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51308-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Dubaitha, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Ghazipur ation IN-SPMU-UP-51305-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Dharwar IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 Kalan, Ghazipur ation IN-SPMU-UP-51314-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Urra, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bahraich ation IN-SPMU-UP-51311-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Dullahpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 26 03 14 27 01 28 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51399-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Raval Zone- IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 II PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51402-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Bara PWS IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 Scheme Distt. Ghazipur ation IN-SPMU-UP-51404-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Raval Zone- IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 I PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51408-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Firojpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51412-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Garoa, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51423-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Shekh IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Dahir, Bahraich ation IN-SPMU-UP-51422-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Gauranm IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Sadkalpur, Ghazipur ation IN-SPMU-UP-51424-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Salkhan IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Sonebhadra IN-SPMU-UP-51426-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Balipur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 and Sarak, Ballia ation IN-SPMU-UP-51427-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Patna IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51428-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Kundari IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Sonebhadra IN-SPMU-UP-51430-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Bharsouta, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51431-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Pathara IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51432-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Parmeth IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51433-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Bhojapur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51434-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Pallia IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 Bujurg PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51437-CW- Pending RFB / Batch-2 Nariyaon Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Urf Umarganj PWS Bids Two Envelope 27 04 15 28 02 29 ation Scheme Distt. Ghazipur IN-SPMU-UP-51438-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Bishunpura, Ballia ation IN-SPMU-UP-51441-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Narayanpur IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 27 04 15 28 02 29 PWS Scheme Distt. ation Ghazipur IN-SPMU-UP-51442-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Chak Haji IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Urf Shekhpur, Ballia ation IN-SPMU-UP-51443-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Jamuav, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51448-CW- Pending RFB / Batch-2 Nari Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- IDA / 53450 Post Open - National 0.00 Implement Pachdevra PWS Scheme Bids Two Envelope 27 04 15 28 02 29 ation Distt. Ghazipur IN-SPMU-UP-51449-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Chandpura, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation Page 12 IN-SPMU-UP-51450-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-1 Jangipur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51457-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Diuli, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51456-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Katariya, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51455-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Jeevpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51459-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Dopahi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51460-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Khizirpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51461-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Lakhanchandpur, Ghazipur ation IN-SPMU-UP-51463-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Matsa, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51474-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Goniya IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Chhapra, Ballia ation IN-SPMU-UP-51475-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Mednipur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51477-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Jagdeva, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51480-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Monikpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ghazipur ation IN-SPMU-UP-51484-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 kachhuwa IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ojha, Ballia ation IN-SPMU-UP-51491-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Madadih, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51493-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Majhoua, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51505-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Kadiyari IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Patti (Saray Bharti Vill), ation Ballia IN-SPMU-UP-51509-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch-2 Nandpur, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51514-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Narhi, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-51517-CW- Pending Request for Single Stage - 2018-02- 2018-03- 2018-04- 2018-06- 2018-08- 2019-01- RFB / Batch 2 Pilue, IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 28 05 16 29 03 30 Ballia ation IN-SPMU-UP-61774-CW- RFB / Batch-2 Katara Bhogchand Kanakpur Pending PWS Scheme Distt. Gonda. Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- IDA / 53450 Post Open - National 0.00 Implement This is SMVS and Bids Two Envelope 07 12 23 05 10 08 ation includes Two G.Ps. namely -1.Katara Bhogchand 2.Kanakpur District-Gonda IN-SPMU-UP-61775-CW- RFB / Batch-2 Chaura (Ghorahara) PWS Scheme Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- Distt. Ballia . This is IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 SMVS and includesTwo ation G.Ps. namely -1.Janeri 2.Ghaura District-Ballia IN-SPMU-UP-61793-CW- RFB / Batch-2 Deochandpur PWS Scheme Distt. Ghazipur. Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- This is SMVS and IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 includes Five G.Ps. namely ation -1Deochandpur 2.Malik Shah Pur 3.Bisun Pura 4.Mirpur Tirwah 5.Phulwari Khurd District-Ghazipur IN-SPMU-UP-61794-CW- RFB / Batch-2 Malsa Kalan PWS Scheme Distt. Ghazipur. Pending This is SMVS and Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- IDA / 53450 Post Open - National 0.00 Implement includes Five G.Ps. namely Bids Two Envelope 07 12 23 05 10 08 ation -1.Malsa Kalan 2.Bhagirathpur 3.Rampur Patti Sarnam Khan-1, 4.Gadha Chhanbey, 5. Chak Medni no.2 District- Ghazipur. IN-SPMU-UP-61796-CW- RFB / Batch-2 Baheri Pending PWS Scheme Distt. Ballia. Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- IDA / 53450 Post Open - National 0.00 Implement This is SVS and includes Bids Two Envelope 07 12 23 05 10 08 ation only one G.P. namely Baheri. District- Ballia IN-SPMU-UP-61799-CW- RFB / Batch-2 Marchi Pending Khurd PWS Scheme Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- IDA / 53450 Post Open - National 0.00 Implement Distt. Ballia. It is a SVS Bids Two Envelope 07 12 23 05 10 08 ation for single G.P. namely Marchi Khurd. District- Ballia. IN-SPMU-UP-61801-CW- RFB / Batch-2 Rampur Chit PWS Scheme Distt. Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- Ballia.This is SVS and IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 includes only one GP ation namely Rampur Chit in District Ballia. IN-SPMU-UP-61822-CW- RFB / Batch-2 Rampur Korahara PWS Scheme Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- District- Ballia . This is IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 SVS and includes only one ation G.P. namely Rampur Korahara in Distt Ballia. IN-SPMU-UP-61825-CW- RFB / Batch-2 Sherpur PWS Scheme Distt. Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- Ghazipur. This is SVS and IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 includes only one G.P. ation namely Sherpur. District- Ghazipur. IN-SPMU-UP-61832-CW- RFB / Batch-2 Chittupur Pending PWS Scheme Distt. Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- IDA / 53450 Post Open - National 0.00 Implement Varanasi.This is SVS and Bids Two Envelope 07 12 23 05 10 08 ation includes only one G.P. namely Chittupur. District- Varanasi. IN-SPMU-UP-61833-CW- RFB / Batch-2 Shrigoverdhanpur PWS Pending Request for Single Stage - 2018-05- 2018-05- 2018-06- 2018-09- 2018-10- 2019-04- Scheme Distt. Varanasi . IDA / 53450 Post Open - National 0.00 Implement Bids Two Envelope 07 12 23 05 10 08 This scheme is SVS and ation includes only one G.P. namely Shrigoverdhanpur. District- Varanasi IN-SPMU-UP-70430-CW- RFQ / Interior work including Internal Partition Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- for proposed new offices of IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 25 19 18 SPMU & SWSM in the ation State Laboratory Building in U.P. Jal Nigam Campus. IN-SPMU-UP-70431-CW- RFQ / Internal Electrification,Air conditioning work including Pending Request for Single Stage - 2018-07- 2018-09- 2019-03- installation of old ACs and IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 25 19 18 Fire Protection work for ation proposed new office of SPMU & SWSM in the State Laboratory Building in U.P. Jal Nigam Campus. GOODS Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPMU-ASSAM-21422- GO-RFQ / Printing and Pending Request for Single Stage - 2018-05- 2018-06- 2018-07- supply of flipchart, snakes IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 01 26 26 and ladder game, card ation sorting game IN-SPMU-ASSAM-21427- Pending Request for Single Stage - 2018-07- 2018-09- 2018-10- GO-RFQ / Printing and IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 25 19 19 supply of calendar 2019 ation IN-SPMU-ASSAM-22806- GO-RFQ / Furniture, Request for Single Stage - 2017-09- 2017-11- 2017-12- IDA / 53450 Post Open - National 7,700.73 Signed fixtures and equipment for Quotations One Envelope 20 15 15 DPMU, Bongaigaon IN-SPMU-ASSAM-22812- GO-RFQ / Furniture, Request for Single Stage - Terminate 2017-09- 2017-11- 2017-12- IDA / 53450 Post Open - National 10,218.48 fixtures and equipment for Quotations One Envelope d 24 19 19 DPMU, Sivasagar Page 13 IN-SPMU-ASSAM-22818- GO-RFQ / Furniture, Request for Single Stage - Terminate 2017-09- 2017-11- 2017-12- IDA / 53450 Post Open - National 693.83 fixtures and equipment for Quotations One Envelope d 24 19 19 DPMU, Morigaon IN-SPMU-ASSAM-22827- Pending GO-RFQ / Provisions for Request for Single Stage - 2018-01- 2018-03- 2018-04- IDA / 53450 Post Open - National 0.00 Implement chemicals for project Quotations One Envelope 10 07 21 ation district laboratory IN-SPMU-ASSAM-22829- GO-RFQ / Provision of Pending computers and peripherals Request for Single Stage - 2018-02- 2018-04- 2018-05- IDA / 53450 Post Open - National 0.00 Implement for strengthening of MIS Quotations One Envelope 11 08 23 ation system for project district laboratory IN-SPMU-ASSAM-22850- GO-RFQ / Provisions of Pending Request for Single Stage - 2017-12- 2018-02- 2018-03- laboratory furniture & IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 20 14 31 accessories for project ation district laboratories G17/JHDM/001 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- Printing/Purchase/ Display IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 16 10 11 of IEC Materials ation G17/JHDM/004 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Furniture & Fixtures IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 20 21 for Laboratory ation G17/JHDM/005 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Equipment for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 20 21 Laboratory ation G17/JHDM/006 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Glassware for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 20 21 Laboratory ation G17/JHDM/007 / Purchase Pending Request for Single Stage - 2018-01- 2018-03- 2018-06- of Consumables IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 30 27 25 (Chemicals) for Laboratory ation G17/JHDM/008 / Purchase Pending Request for Single Stage - 2018-01- 2018-03- 2018-06- of Laptop & GPS Set for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 30 27 25 Laboratory ation Pending G17/JHDM/009 / Purchase Request for Single Stage - 2018-01- 2018-03- 2018-06- IDA / 53450 Post Open - National 0.00 Implement of FTK Kit Quotations One Envelope 30 27 25 ation G17/JHES/001 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Equipment for referral IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 20 21 lab ation Pending G17/JHES/002 / Purchase Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement of Equipment for other lab Quotations One Envelope 26 27 28 ation G17/JHES/003 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Chemicals for water IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 quality lab ation G17/JHES/004 / Purchase Pending Request for Single Stage - 2017-12- 2018-03- 2018-06- of (Glasswares) for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 07 05 Laboratory ation G17/JHES/005 / Purchase Pending of Computer/Laptop, Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement Software and GPS set for Quotations One Envelope 26 27 28 ation lab Pending G17/JHES/006 / Purchase Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement of FTK Kit Quotations One Envelope 26 27 28 ation G17/JHGR/001 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- Printing/Purchase/ Display IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 16 17 18 of IEC materials ation G17/JHGR/004 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Furniture & Fixtures IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 for Laboratory ation G17/JHGR/005 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Equipment for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation G17/JHGR/006 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Glassware for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation G17/JHGR/007 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Consumables IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 (Chemicals) for Laboratory ation G17/JHGR/008 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Laptop & GPS Set for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation Pending G17/JHGR/009 / Purchase Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement of FTK Kit Quotations One Envelope 26 27 28 ation G17/JHKH/001 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- Printing/Purchase/ Display IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 16 17 18 of IEC materials ation G17/JHKH/004 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Furniture & Fixtures IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 for Laboratory ation G17/JHKH/005 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Equipment for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation G17/JHKH/006 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Glassware for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation G17/JHKH/007 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Consumables IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 (Chemicals) for Laboratory ation G17/JHKH/008 / Purchase Pending Request for Single Stage - 2017-12- 2018-02- 2018-05- of Laptop & GPS Set for IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 28 Laboratory ation Pending G17/JHKH/009 / Purchase Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement of FTK Kit Quotations One Envelope 26 27 28 ation Pending G17/JHKH/010 / Purchase Request for Single Stage - 2017-10- 2017-12- 2018-03- IDA / 53450 Post Open - National 0.00 Implement of LCD Projector Quotations One Envelope 05 07 07 ation Pending G17/JHKH/011 / Purchase Request for Single Stage - 2017-10- 2017-12- 2018-03- IDA / 53450 Post Open - National 0.00 Implement of Xerox Machine Quotations One Envelope 05 07 07 ation G17/JHSK/001 / Pending Request for Single Stage - 2017-10- 2017-12- 2018-03- Procurement of Photocopier IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 25 27 27 Machine ation G17/JHSK/003 / Pending Request for Single Stage - 2018-02- 2018-04- 2018-07- Procurement of Air IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 20 24 23 Conditioner ation Pending G17/JHSK/004 / Request for Single Stage - 2017-10- 2017-12- 2018-06- IDA / 53450 Post Open - National 0.00 Implement Procurement of Generator Quotations One Envelope 05 07 05 ation G17/JHSK/005 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of Furniture IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 & Fixture ation G17/JHSK/006 / Pending Request for Single Stage - 2017-11- 2018-01- 2018-07- Procurement of Coffee IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 08 10 09 Vending Machine ation G17/JHSK/007 / Pending Request for Single Stage - 2017-10- 2017-12- 2018-06- Procurement of Office IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 24 26 24 Stationery ation G17/JHSK/008 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of Furniture IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 & Fixtures for Laboratory ation G17/JHSK/009 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of Equipment IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 for Laboratory ation G17/JHSK/010 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of Glassware IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 for Laboratory ation G17/JHSK/011 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 Consumables (Chemicals) ation for Laboratory G17/JHSK/012 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Procurement of Desktop IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 & GPS Set for Laboratory ation Pending G17/JHSK/013 / Purchase Request for Single Stage - 2017-12- 2018-02- 2018-08- IDA / 53450 Post Open - National 0.00 Implement of FTK Kit Quotations One Envelope 26 27 26 ation G17/JHSP/001 / Pending Request for Single Stage - 2017-12- 2018-02- 2018-08- Printing/Purchase of IEC IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 26 27 26 materials ation G17/JHSP/002 / Pending Request for Single Stage - 2018-01- 2018-03- 2018-09- Hardware,Software,Furnitur IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 10 14 10 e & Fixtures for SPMU ation IN-SPMU-ASSAM-21871- GO-RFQ / Procurement of Request for Single Stage - 2017-08- 2017-10- 2018-01- additional chairs for the IDA / 53450 Post Open - National 7,359.39 Completed Quotations One Envelope 09 04 17 extension portion of the SPMU, NNP-Assam office Page 14 IN-SPMU-ASSAM-21640- GO-RFQ / Power backup system for extension part of SPMU, NNP-Assam Request for Single Stage - 2017-09- 2017-11- 2018-02- office - 1 no. 40 kVA IDA / 53450 Post Open - National 9,017.84 Signed Quotations One Envelope 12 07 20 salient diesel genset with automatic changing over/ switch over facility with accessories and RCC foundation. IN-SPMU-ASSAM-22902- Request for Single Stage - 2017-09- 2017-11- 2017-12- GO-RFQ / Computers and IDA / 53450 Post Open - National 29,196.16 Signed Quotations One Envelope 17 12 12 peripherals IN-SPMU-ASSAM-22804- GO-RFQ / Furniture, Request for Single Stage - Terminate 2017-09- 2017-11- 2017-12- IDA / 53450 Post Open - National 472.51 fixtures and equipment for Quotations One Envelope d 20 15 15 DPMU, Jorhat IN-SPMU-ASSAM-22856- GO-RFQ / Equipment and Request for Single Stage - 2017-08- 2017-10- 2017-11- IDA / 53450 Post Open - National 3,098.94 Completed accessories for SPMU, Quotations One Envelope 22 17 16 NNP-Assam IN-SPMU-ASSAM-33064- GO-RFQ / Computers and Request for Single Stage - 2017-11- 2018-01- 2018-02- IDA / 53450 Post Open - National 19,161.54 Completed peripherals for SPMU and Quotations One Envelope 12 07 06 DPMUs IN-SPMU-ASSAM-41001- GO-RFQ / Procurement of Office Stationery for State Request for Single Stage - 2018-01- 2018-03- 2018-04- IDA / 53450 Post Open - National 5,230.34 Signed Project Management Unit, Quotations One Envelope 08 08 07 Neer Nirmal Pariyojana- Assam IN-SPMU-BIHAR-41450- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Tally package for SPMU Quotations One Envelope 15 07 09 ation and DPMU IN-SPMU-BIHAR-41467- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Software Viz. Anti- Virus- Quotations One Envelope 15 07 09 ation 20 Unit for SPMU IN-SPMU-BIHAR-41469- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Technical Software for Quotations One Envelope 15 07 09 ation SPMU, RWSSP IN-SPMU-BIHAR-41509- GO-RFQ / Procurement of Pending Request for Single Stage - 2018-01- 2018-02- 2018-03- 12 Sets of Construction IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 15 07 09 Quality Check Tools and ation Equipment-12 Unit for SPMU IN-SPMU-BIHAR-42058- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc. Quotations One Envelope 18 10 12 ation for DPMU, Patna IN-SPMU-BIHAR-42061- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc. Quotations One Envelope 18 10 12 ation for DPMU, Begusarai IN-SPMU-BIHAR-42064- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc Quotations One Envelope 18 10 12 ation for DPMU, West Champaran IN-SPMU-BIHAR-42067- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc Quotations One Envelope 18 10 12 ation for DPMU, Banka IN-SPMU-BIHAR-42070- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc Quotations One Envelope 18 10 12 ation for DPMU, Saran IN-SPMU-BIHAR-42075- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc Quotations One Envelope 18 10 12 ation for DPMU, Purnea IN-SPMU-BIHAR-42081- Pending GO-RFQ / Procurement of Request for Single Stage - 2018-01- 2018-02- 2018-03- IDA / 53450 Post Limited 0.00 Implement Furniture/Workstation etc. Quotations One Envelope 18 10 12 ation for DPMU, Munger IN-SPMU-UP-48544-GO- Pending Request for Single Stage - 2018-03- 2018-05- 2018-11- RFQ / Procurement of 139 IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 15 10 06 Tablets for batch-2 SOs ation IN-SPMU-ASSAM-52215- GO-RFQ / Procurement of Audio Conferencing System for Installation in the Request for Single Stage - 2018-03- 2018-05- 2018-07- IDA / 53450 Post Open - National 4,667.59 Signed Conference Hall of State Quotations One Envelope 18 16 15 Project Management Unit, Neer Nirmal Pariyojana- Assam IN-SPMU-ASSAM-52219- GO-RFQ / Procurement of Local Area Network in the Request for Single Stage - 2018-03- 2018-05- 2018-07- Extended Office Portion of IDA / 53450 Post Open - National 412.87 Signed Quotations One Envelope 18 16 15 State Project Management Unit, Neer Nirmal Pariyojana-Assam IN-SPMU-ASSAM-60051- Request for Single Stage - 2018-05- 2018-06- 2018-07- GO-RFQ / Procurement of IDA / 53450 Post Open - National 2,991.35 Signed Quotations One Envelope 02 30 30 a Digital Photocopier Machine IN-SPMU-ASSAM-60057- Request for Single Stage - 2018-05- 2018-06- 2018-07- GO-RFQ / Procurement of IDA / 53450 Post Open - National 3,283.49 Signed Quotations One Envelope 02 30 30 Computer Peripherals IN-SPMU-ASSAM-61947- GO-RFQ / Procurement of Furniture, Fixtures and Request for Single Stage - 2018-07- 2018-08- 2018-09- Equipment for District IDA / 53450 Post Open - National 0.00 Canceled Quotations One Envelope 02 30 29 Project Management Unit- Jorhat, Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-61949- GO-RFQ / Procurement of Furniture, Fixtures and Request for Single Stage - 2018-07- 2018-08- 2018-09- Equipment for District IDA / 53450 Post Open - National 10,670.11 Signed Quotations One Envelope 02 30 29 Project Management Unit- Sivasagar, Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-22846- GO-RFB / Supply of additional equipment Request for Single Stage - 2017-10- 2017-10- 2017-12- 2018-02- 2018-04- 2018-06- required in existing district IDA / 53450 Post Open - National 0.00 Canceled Bids Two Envelope 25 30 11 23 06 20 level water testing laboratories for testing as per UDWQMP of GoI (for project districts) IN-SPMU-ASSAM-75672- GO-RFB / Supply, Installation and Testing of Equipment, Chemicals and Under Request for Single Stage - 2018-09- 2018-09- 2018-11- 2018-12- 2019-01- 2019-03- Glassware for Water IDA / 53450 Post Open - National 0.00 Implement Bids One Envelope 12 22 01 01 05 06 Quality Monitoring and ation Surveillance Laboratory in the Six Project Districts under Neer Nirmal Pariyojana- Assam (Six Lots) IN-SPMU-ASSAM-61947- GO-RFQ-2 / Procurement of Furniture, Fixtures and Under Request for Single Stage - 2018-09- 2018-11- 2018-12- Equipment for District IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 16 14 14 Project Management Unit- ation Jorhat, Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-21426- GO-RFQ / Printing & Pending installation of promotional Request for Single Stage - 2018-10- 2018-12- 2019-01- IDA / 53450 Post Open - National 0.00 Implement board and printing & Quotations One Envelope 28 26 25 ation supply of board game with dice IN-SPMU-ASSAM-21354- Pending GO-RFQ / Printing & Request for Single Stage - 2018-10- 2018-12- 2019-01- IDA / 53450 Post Open - National 0.00 Implement supply of leaflet and Quotations One Envelope 28 26 25 ation booklabel for school children NON CONSULTING SERVICES Bid Evaluation Activity Reference Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificati Process Prequalification Bidding Documents Report and Contract No. / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process on (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPMU-ASSAM-21499- NC-RFQ / Security Audit Request for Single Stage - 2017-07- 2017-09- 2017-11- IDA / 53450 Post Limited 431.58 Completed of Web Application under Quotations One Envelope 23 01 15 Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-21501- NC-RFQ / Empanelment of Request for Single Stage - 2017-07- 2017-09- 2018-09- IDA / 53450 Post Open - National 65,972.72 Signed agencies for hiring of Quotations One Envelope 23 08 23 vehicles on monthly basis IN-SPMU-ASSAM-21506- NC-RFQ / Empanelment of Request for Single Stage - 2017-07- 2017-09- 2018-09- agencies for hiring of IDA / 53450 Post Open - National 219.82 Signed Quotations One Envelope 23 08 23 vehicles for local journey on daily/half day basis IN-SPMU-ASSAM-21507- NC-RFQ / Empanelment of Request for Single Stage - 2017-07- 2017-09- 2018-09- agencies for hiring of IDA / 53450 Post Open - National 332.77 Signed Quotations One Envelope 23 08 23 vehicles for outstation journey on daily basis. IN-SPMU-ASSAM-22912- Request for Single Stage - 2017-08- 2017-10- 2018-10- NC-RFQ / Hiring of IDA / 53450 Post Open - National 6,953.37 Signed Quotations One Envelope 10 05 20 security services Pending G17/JHDM/002 / Fixing of Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement Signage Board Quotations One Envelope 16 10 11 ation Page 15 Pending G17/JHDM/003 / Wall Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement writing in Multi Colour Quotations One Envelope 16 10 11 ation Pending G17/JHGR/002 / Fixing of Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement Signage Board Quotations One Envelope 16 17 18 ation Pending G17/JHGR/003 / Wall Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement writing in Multi Colour Quotations One Envelope 16 17 18 ation Pending G17/JHKH/002 / Fixing of Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement Signage Board Quotations One Envelope 16 17 18 ation Pending G17/JHKH/003 / Wall Request for Single Stage - 2017-12- 2018-02- 2018-05- IDA / 53450 Post Open - National 0.00 Implement writing in Multi Colour Quotations One Envelope 16 17 18 ation G17/JHSK/002 / Wall Pending Request for Single Stage - 2017-11- 2018-01- 2018-05- Writing, Sign Board & IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 29 31 01 Other IEC activities ation G17/JHSP/004 / Pending Development of Request for Single Stage - 2018-01- 2018-03- 2018-09- IDA / 53450 Post Open - National 0.00 Implement Documentary films on case Quotations One Envelope 03 07 03 ation studies IN-SPMU-ASSAM-22908- NC-RFQ / Engagement of agency for preparation of comprehensive GIS Request for Single Stage - 2017-10- 2017-12- 2018-04- IDA / 53450 Post Open - National 0.00 Canceled database for Khetri gram Quotations One Envelope 08 03 17 panchayat in Kamrup (M) district under Neer Nirmal Pariyojana on pilot basis Pending G17/JHSP/003 / AMC for Request for Single Stage - 2017-12- 2018-02- 2018-08- IDA / 53450 Post Open - National 0.00 Implement H/W & S/W SPMU Office Quotations One Envelope 26 27 26 ation G17/JHES/007 / Printing Pending of Pamphlets Leaflets in Request for Single Stage - 2017-12- 2018-03- 2018-09- IDA / 53450 Post Open - National 0.00 Implement Multi-colour, Registers, Quotations One Envelope 25 05 01 ation Jamshedpur G17/JHES/008 / Fixing of Pending Hoardings at Entry, Exit Request for Single Stage - 2017-11- 2018-02- 2018-08- IDA / 53450 Post Open - National 0.00 Implement & other places of the Quotations One Envelope 25 03 02 ation District, Jamshedpur G17/JHES/009 / Wall Pending Request for Single Stage - 2018-01- 2018-04- 2018-10- writing in Multi-colour, IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 25 05 02 Jamshedpur ation G17/JHES/010 / Scheme Pending Request for Single Stage - 2018-01- 2018-04- 2018-10- Wise Project Display Board IDA / 53450 Post Open - National 0.00 Implement Quotations One Envelope 25 05 02 , Jamshedpur ation IN-SPMU-ASSAM-41004- NC-RFQ / Preparation of Scaled Down 3D Animated Request for Single Stage - 2018-01- 2018-03- 2018-05- IDA / 53450 Post Open - National 1,708.39 Signed Illustration of the Project Quotations One Envelope 10 10 09 under Neer Nirmal Pariyojana-Assam. IN-SPMU-ASSAM-60062- NC-RFQ / Hiring of Vehicle on Monthly Basis Request for Single Stage - 2018-04- 2018-06- 2019-07- IDA / 53450 Post Open - National 8,488.64 Signed for District Project Quotations One Envelope 27 16 01 Management Unit-Kamrup, Neer Nirmnal Pariyojana- Assam IN-SPMU-ASSAM-66608- NC-RFQ / Hiring of Vehicle on Monthly Basis Request for Single Stage - 2018-07- 2018-08- 2019-09- IDA / 53450 Post Open - National 7,366.62 Signed for District Project Quotations One Envelope 03 22 06 Management Unit- Morigaon, Neer Nirmnal Pariyojana-Assam IN-SPMU-ASSAM-66612- NC-RFQ / Hiring of Vehicle on Monthly Basis Request for Single Stage - 2018-07- 2018-08- 2019-09- IDA / 53450 Post Open - National 7,366.62 Signed for District Project Quotations One Envelope 03 22 06 Management Unit-Jorhat, Neer Nirmnal Pariyojana- Assam IN-SPMU-UP-70434-NC- RFQ / I.E.C. Activities about J.E. & A.E.S. using 18 Hordings &27 Unipols Pending and 454 Flexies in Neer Request for Single Stage - 2018-08- 2018-10- 2019-03- IDA / 53450 Post Limited 0.00 Implement Nirmal Pariyojna Districts Quotations One Envelope 07 02 31 ation namely Gorakhpur, Deoria, Kushinagar, Basti, Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda. IN-SPMU-UP-70437-NC- RFQ / I.E.C. Activities about J.E. & A.E.S. usingVideo Message Clips In Cinema halls in Neer Pending Nirmal Pariyojna Districts Request for Single Stage - 2018-08- 2018-10- 2019-04- IDA / 53450 Post Limited 0.00 Implement Gorakhpur, Deoria, Quotations One Envelope 11 06 04 ation Kushinagar, Basti, Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda.(04 times a day in 50 halls for 90 days) IN-SPMU-UP-70438-NC- RFQ / I.E.C. Activities about J.E. & A.E.S. using Akashwani Radio in Neer Nirmal Pariyojna Districts Pending Request for Single Stage - 2018-08- 2018-10- 2019-04- Gorakhpur, Deoria, IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 18 13 11 Kushinagar, Basti, ation Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda.(04 times a day for 90 days) IN-SPMU-UP-70439-NC- RFQ / I.E.C. Activities about J.E. & A.E.S. using F.M.Radio in Neer Nirmal Pending Pariyojna Districts namely Request for Single Stage - 2018-08- 2018-10- 2019-04- IDA / 53450 Post Limited 0.00 Implement Gorakhpur, Deoria, Quotations One Envelope 12 07 05 ation Kushinagar, Basti, Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda.(04 times a day for 90 days) IN-SPMU-UP-70440-NC- RFQ / Procurement of 04 video messages 60second each for I.E.C. Activities about J.E. & A.E.S. in Pending Request for Single Stage - 2018-08- 2018-10- 2019-04- Neer Nirmal Pariyojna IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 13 08 06 Districts namely ation Gorakhpur, Deoria, Kushinagar, Basti, Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda. IN-SPMU-UP-70435-NC- RFQ / I.E.C. Activities about J.E. & A.E.S. using 09 Video Vans in Neer Nirmal Pariyojna Districts Under Request for Single Stage - 2018-08- 2018-10- 2019-04- namely Gorakhpur, Deoria, IDA / 53450 Post Limited 0.00 Implement Quotations One Envelope 25 20 18 Kushinagar, Basti, ation Siddharthnagar, Sant Kabir Nagar, Ballia, Behraich & Gonda.(01 Van in each district for 45 days) IN-SPMU-ASSAM-76063- NC-RFQ / Hiring of Under Vehicle on Monthly Basis Request for Single Stage - 2018-09- 2018-11- 2019-11- IDA / 53450 Post Open - National 0.00 Implement for District Project Quotations One Envelope 12 01 16 ation Management Unit- Bongaigaon, Neer Nirmal Pariyojana-Assam IN-SPMU-ASSAM-76065- NC-RFQ / Hiring of Under Vehicle on Monthly Basis Request for Single Stage - 2018-09- 2018-11- 2019-11- IDA / 53450 Post Open - National 0.00 Implement for District Project Quotations One Envelope 12 01 16 ation Management Unit- Hailakandi, Neer Nirmal Pariyojana-Assam IN-SPMU-ASSAM-76066- NC-RFQ / Hiring of Under Vehicle on Monthly Basis Request for Single Stage - 2018-09- 2018-11- 2019-11- IDA / 53450 Post Open - National 0.00 Implement for District Project Quotations One Envelope 12 01 16 ation Management Unit- Sivasagar, Neer Nirmal Pariyojana-Assam CONSULTING FIRMS Activity Reference Actual Short List and Request for Opening of Combined Loan / Market Contract Type Process Expression of Evaluation of Contract No. / Description Component Review Type Method Amount Terms of Reference Draft Request for Proposals as Technical Proposals Evaluation Report Signed Contract Credit No. Approach Status Interest Notice Technical Proposal Completion (US$) Proposals Issued / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Actual Planned Actual Planned Actual Contract WBR No. 29 / Hiring of Human Resource Agency for Recruitment and Quality And Open - Management of IDA / 53450 Prior Cost-Based 422,823.21 Signed International Professionals for 10 Selection District Project Management Units (DPMUs) - U.P. Consultant C17/JHSP/001 / Hiring of 2017-10- 2017-12- 2018-01- 2018-02- 2019-02- IDA / 53450 Post Qualification Open - National 0.00 Canceled 2017-10-10 External Auditors 31 14 13 17 17 Selection Consultant C17/JHSP/002 / Hiring of 2017-10- 2017-12- 2018-01- 2018-02- 2019-02- IDA / 53450 Post Qualification Open - National 0.00 Canceled 2017-10-10 Internal Auditors 31 14 13 17 17 Selection C17/JHSP/003 / Sector Consultant Development Studies Pending 2018-01- 2018-03- 2018-04- 2018-05- 2018-11- IDA / 53450 Post Qualification Open - National 0.00 2018-01-05 (Hiring of Technical,Social Implementation 26 11 10 15 11 Selection & Communication Institution) C17/JHSP/004 / Quality And Pending 2018-01- 2018-02- 2018-03- 2018-04- 2018-05- 2018-06- 2019-06- IDA / 53450 Post Open - National 0.00 2017-12-18 Environment Audit Cost-Based Implementation 08 21 21 20 25 29 29 Selection C17/JHSP/005 / Hiring of Quality And Pending 2018-01- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2019-07- IDA / 53450 Post Open - National 0.00 2018-01-05 Media Agency Cost-Based Implementation 26 11 08 08 12 17 17 Selection C17/JHSP/006 / Hiring of Quality And outsourcing agency for Pending 2017-10- 2017-11- 2017-12- 2018-01- 2018-02- 2018-03- 2019-03- IDA / 53450 Post Cost-Based Open - National 0.00 2017-09-10 recruitment and HR Implementation 01 14 12 11 15 22 22 Selection Management Page 16 C17/JHSP/007 / Hiring of Agency for preparing a module for Grievance Consultant Pending 2017-10- 2017-12- 2018-01- 2018-02- 2018-08- Redressal System for IDA / 53450 Post Qualification Open - National 0.00 2017-10-10 Implementation 31 14 13 17 16 Water Supply schemes Selection under the existing system of the Department IN-SPMU-ASSAM-21323- CS-CQS / Hiring of Media Agency to Design, Develop Consultant and Deploy Audio-Visual 2017-08- 2017-09- 2017-10- 2017-11- 2018-05- IDA / 53450 Post Qualification Open - National 203,497.97 Terminated 2017-07-20 Media for Information, 01 14 14 18 20 Selection Education and Communication under Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-22939- CS-CDS / Third party Quality And quality assurance Pending 2017-12- 2018-01- 2018-02- 2018-03- 2018-04- 2018-06- 2021-06- IDA / 53450 Post Cost-Based Open - National 0.00 2017-11-17 consultant (TPQAC) for Implementation 08 21 18 20 24 05 19 Selection Morigaon, Sivasagar and Bongaigaon sub-projects IN-SPMU-BIHAR-39169- CS-QCBS / Selection of Quality And Pending 2017-12- 2018-02- 2018-03- 2018-04- 2018-05- 2018-06- 2019-06- Project Management IDA / 53450 Post Cost-Based Open - National 0.00 2017-12-08 Implementation 29 11 11 10 15 19 19 Consultancy at SPMU Selection Level. 10 EOIs received and evaluated. IN-SPMU-BIHAR-40672- CS-LCS / Selection of Consultant for Sector Least Cost Pending 2018-02- 2018-03- 2018-04- 2018-04- 2018-05- 2018-05- 2018-11- IDA / 53450 Post Open - National 0.00 2018-01-10 Development Studies - Selection Implementation 07 23 20 30 10 20 16 Impact Study/ assessment of RWSSP, Bihar IN-SPMU-BIHAR-40675- CS-LCS / Selection of Consultant for Assessment Least Cost Pending 2018-01- 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- 2018-11- of Project withdrawal IDA / 53450 Post Open - National 0.00 2018-01-10 Selection Implementation 31 12 09 19 29 09 05 strategy with respect to capacity of PRIs in RWSSP, Bihar IN-SPMU-ASSAM-41015- Quality And CS-QCBS / Preparation of Under 2018-01- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2019-01- IDA / 53450 Post Cost-Based Open - National 0.00 2018-01-08 a State Rural Drinking Implementation 29 14 11 11 15 20 31 Selection Water Supply Policy for Assam IN-SPMU-ASSAM-41030- CS-QCBS / Provision of Technical Support to the Project Districts under Quality And Neer Nirmal Pariyojana in Under 2018-01- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2020-08- IDA / 53450 Post Cost-Based Open - National 0.00 2018-01-09 the state of Assam, in Implementation 30 15 12 12 16 21 04 Selection implementation of SLWM component under SBM-G, through Technical Support Unit IN-NPMU-44751-CS-QCBS / Invitation for Expression of Interest (EoI) for engaging Project Quality And 2018-02- 2018-04- 2018-05- 2018-06- 2018-07- 2018-08- 2019-08- Management Consultancy IDA / 53450 Prior Cost-Based Open - National 0.00 Canceled 2018-01-19 09 24 22 21 26 30 30 in Water Division of Selection Ministry of Drinking Water & Sanitation, Government of India, New Delhi. IN-NPMU-55920-CS-QCBS / Project Management Quality And Consultancy for Rural Open - Under 2018-04- 2018-05- 2018-06- 2018-07- 2018-08- 2018-09- 2020-03- IDA / 53450 Prior Cost-Based 0.00 2018-03-27 water supply and International Implementation 10 24 21 21 25 29 31 Selection Sanitation project-Low income State (RWSSP-LIS) IN-SPMU-JHARKHAND- 56674-CS-QCBS / Selection of Consultant/Agency for Quality And preparartion of DPR for Pending 2018-05- 2018-06- 2018-07- 2018-08- 2018-09- 2018-10- 2018-12- IDA / 53450 Post Cost-Based Open - National 0.00 2018-04-11 SLRM & FSM in 38 GPs Implementation 02 15 13 12 16 21 20 Selection of Chhotagobindpur- Baghbera Water Supply Scheme area, East Singhbhum IN-SPMU-JHARKHAND- 57954-CS-QCBS / Selection of Consultant/Agency for Quality And Pending 2018-05- 2018-06- 2018-07- 2018-08- 2018-09- 2018-10- 2018-12- Community based IDA / 53450 Post Cost-Based Open - National 0.00 2018-04-11 Implementation 02 15 13 12 16 21 20 preparartion of DPR for Selection SLWM in 176 GPs of NNP schemes of Jharkhand. IN-SPMU-JHARKHAND- 72658-CS-CQS / The information security auditor will have to carry out an assessment of the Consultant Pending 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- vulnerabilities, threats and IDA / 53450 Post Qualification Open - National 0.00 2018-08-09 Implementation 24 21 12 16 15 risks that exist in website Selection through Internet Vulnerability Assessment and Black box Penetration Testing. IN-SPMU-JHARKHAND- 79890-CS-LCS / Hiring Services of External Least Cost Pending 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- Auditors for JSWSMS IDA / 53450 Post Open - National 0.00 2018-10-08 Selection Implementation 24 30 28 17 11 06 02 under RWSSP-LIS for Financial Year 2017-2018 for SPMU, DPMUs,,MVWSCs & VWSCs INDIVIDUAL CONSULTANTS Page 17