PROCUREMENT PLAN (Textual Part) Project information: The Gambia COVID-19 Preparedness and Response Project (P173798) Project Implementation agency: Ministry of Health Date of the Procurement Plan: March 20, 2020 Period covered by this Procurement Plan: March 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Streamlined procedures for approval of emergency procurement to expedite decision making and approvals by the Borrower have been agreed. This procurement approach prioritizes fast track emergency procurement for the emergency required goods, works and services. Key measures to fast track procurement include use of simple and fast procurement and selection methods, direct selection, shorter bidding time, force accounts, framework agreements, increased thresholds for request for quotation (RFQ) and national procurement, minimized or no prior review for emergency procurement, among others. Thresholds for Procurement Approach/methods and Prior Review Thresholds: (1)For response/recovery phase: thresholds will be flexible to address the urgent needs and all contracts will be subject to post review. The procurement plan will be approved by the Bank and will detail the activities, methods, and mode of review by the Bank. PROCUREMENT Gambia, The : The Gambia COVID-19 Preparedness and Response Project PLAN General Information Country: Gambia, The Bank’s Approval Date of the Original Procurement Plan: 2020-04-08 2021-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173798 GPN Date: 2020-09-28 Project Name: The Gambia COVID-19 Preparedness and Response Project Loan / Credit No: IDA / D5970, TF / B4724 M Executing Agency(ies): INISTRY OF HEALTH WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GM-MOH-166712-CW-RFB / Construction of a National Component 3: Supporting Pending Single Stage - One 2021-02- Center for Infectious Diseases IDA / D5970 National and Sub-national, Post Request for Bids Limited 2,150,000.00 0.00 Implementat 2020-04-30 2020-05-05 2020-06-16 2020-07-16 2020-08-20 Envelope 16 and public health emergency Prevention and Preparedness ion laboratory and training center GM-MOH-169211-CW-RFQ / Component 3: Supporting Electrical Works at the Public Request for Single Stage - One 2020-12- IDA / D5970 National and Sub-national, Post Limited 4,900.00 4,675.57 Completed 2020-04-25 2020-04-15 2020-06-20 2020-04-17 Health Emergency Operations Quotations Envelope 17 Prevention and Preparedness Center (PHEOC) GM-MOH-166700-GO-RFQ / Temporary Storage sites for Component 1: Emergency Request for Single Stage - One 2020-12- IDA / D5970 Post Limited 100,000.00 0.00 Canceled 2020-05-05 2020-06-30 health care waste at health COVID-19 Response Quotations Envelope 27 facilities GM-MOH-168251-CW-RFQ / Component 3: Supporting Request for Single Stage - One 2020-12- Laboratory Stores IDA / D5970 National and Sub-national, Post Limited 5,000.00 0.00 Canceled 2020-04-14 2020-06-09 Quotations Envelope 06 Refurbishment Prevention and Preparedness GM-MOH-180385-CW-FCA / Component 3: Supporting 2021-01- Renovation of Isolation IDA / D5970 National and Sub-national, Post Force Account Direct 121,100.00 0.00 Canceled 2020-06-16 2020-06-21 2020-07-26 22 Centers Prevention and Preparedness GM-MOH-166667-CW-RFB / Component 3: Supporting Request for Single Stage - One 2020-07- Renovation of treatment and IDA / D5970 National and Sub-national, Post Limited 50,000.00 0.00 Canceled 2020-06-05 2020-07-22 Quotations Envelope 22 isolation centres Prevention and Preparedness Component 3: Supporting GM-MOH-186643-CW-UN / UN Agencies 2021-03- IDA / D5970 National and Sub-national, Post Direct 280,000.00 290,309.13 Completed 2020-07-30 2020-08-10 2020-08-04 2020-08-13 2020-09-08 2020-08-13 Renovation of Ndemban Clinic (Direct) 07 Prevention and Preparedness GM-MOH-189382-CW-DIR / Component 3: Supporting Expansion of Local Area 2021-03- IDA / D5970 National and Sub-national, Post Direct Selection Direct 8,000.00 7,653.30 Completed 2020-08-18 2020-08-14 2020-08-23 2020-08-14 2020-09-27 2020-08-20 Network for NPHL the data 26 Prevention and Preparedness management system GM-MOH-204427-CW-RFB / Component 3: Supporting Under Request for Single Stage - One 2021-07- Construction of two Clinical IDA / D5970 National and Sub-national, Post Open - National 250,000.00 0.00 Implementat 2020-11-21 2021-01-16 Quotations Envelope 15 Waste treatment Centers Prevention and Preparedness ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-MOH-166476-GO-RFQ / Media center equipment and live broadcasting of daily Component 1: Emergency Request for Single Stage - One IDA / D5970 Post Limited 72,000.00 154,831.59 Completed 2020-04-13 2020-04-20 2020-06-08 2020-05-18 2020-12-05 2020-08-27 situational reports etc on COVID-19 Response Quotations Envelope social media (Facebook, Youtube, and Twitter) GM-MOH-166641-GO-DIR / Component 1: Emergency Ecosteryl Waste Treatment IDA / D5970 Post Direct Selection Direct 1,360,000.00 1,452,420.68 Completed 2020-04-30 2020-03-25 2020-05-05 2020-03-25 2020-06-09 2020-04-13 2020-12-06 2021-01-05 COVID-19 Response Machines GM-MOH-166650-GO-RFQ / Produce and install 10 Component 1: Emergency Request for Single Stage - One IDA / D5970 Post Limited 39,400.00 13,244.40 Completed 2020-04-10 2020-03-31 2020-06-05 2020-04-08 2020-12-02 2020-04-29 billboards, Produce and COVID-19 Response Quotations Envelope distribute 5,000 posters Component 2: Strengthening Multi-sector, National GM-MOH-166655-GO-DIR / Institutions and Platforms for Request for Single Stage - One IT equipment for PHEOC and e- IDA / D5970 Policy Development and Post Limited 59,500.00 56,774.81 Completed 2020-04-13 2020-03-30 2020-06-08 2020-04-08 2020-12-05 2020-07-13 Quotations Envelope surveillance Coordination of Pr evention and Preparedness using One Health approach. GM-MOH-166661-GO-RFQ / Component 3: Supporting Request for Single Stage - One Infection prevention and IDA / D5970 National and Sub-national, Post Limited 84,200.00 80,228.66 Completed 2020-04-13 2020-03-25 2020-06-08 2020-04-06 2020-12-05 2020-04-17 Quotations Envelope control (IPC) materials Prevention and Preparedness Component 3: Supporting GM-MOH-166662-GO-RFQ / Request for Single Stage - One IDA / D5970 National and Sub-national, Post Limited 45,000.00 37,418.77 Completed 2020-04-13 2020-03-30 2020-06-08 2020-04-07 2020-12-05 2020-07-14 Motorbikes Quotations Envelope Prevention and Preparedness GM-MOH-166663-GO-RFB / Component 3: Supporting Medical equipment, supplies, IDA / D5970 National and Sub-national, Post Direct Selection Direct 3,946,637.00 3,946,637.10 Completed 2020-04-08 2020-04-03 2020-04-13 2020-04-03 2020-05-18 2020-04-08 2020-11-14 2020-04-27 personal protective equipment Prevention and Preparedness and 10 ambulances Component 3: Supporting GM-MOH-166664-GO-RFQ / Request for Single Stage - One IDA / D5970 National and Sub-national, Post Limited 276,000.00 263,358.79 Completed 2020-04-08 2020-03-30 2020-06-03 2020-04-07 2020-11-30 2020-10-02 Double cabin four wheel drive Quotations Envelope Prevention and Preparedness Page 1 GM-MOH-166666-GO-RFB / Intensive unit care equipment - 1 ultrasound scanner Component 3: Supporting (handheld), 20 ventilators, 10 IDA / D5970 National and Sub-national, Post Direct Selection Direct 602,100.00 0.00 Canceled 2020-04-30 2020-05-05 2020-06-09 2020-12-06 multi parameter patient Prevention and Preparedness monitors, 1 biphasic defibrillator, and 2 ECG machines (digital 12 channel) GM-MOH-166699-GO-RFQ / Component 1: Emergency Request for Single Stage - One Online Video/ Audio IDA / D5970 Post Limited 350.00 0.00 Canceled 2020-04-13 2020-06-08 2020-12-05 COVID-19 Response Quotations Envelope conferencing software GM-MOH-166658-GO-RFQ / Component 3: Supporting Request for Single Stage - One Laboratory supplies, reagents TF / B4724 National and Sub-national, Post Limited 693,910.00 479,212.04 Completed 2020-04-14 2020-04-03 2020-06-09 2020-05-19 2020-12-06 2021-01-27 Quotations Envelope and test kits Prevention and Preparedness Component 3: Supporting GM-MOH-168246-GO-RFQ / TF / B4724 National and Sub-national, Post Direct Selection Direct 38,000.00 49,260.00 Completed 2020-04-09 2020-04-16 2020-04-14 2020-04-16 2020-05-19 2020-05-18 2020-11-15 2021-01-17 Microbiology systems Prevention and Preparedness Component 3: Supporting GM-MOH-168247-GO-DIR / TF / B4724 National and Sub-national, Post Direct Selection Direct 155,000.00 174,390.02 Completed 2020-04-09 2020-04-20 2020-04-14 2020-04-16 2020-05-19 2020-06-05 2020-11-15 2020-09-21 Haematology Systems Prevention and Preparedness Component 3: Supporting GM-MOH-168249-GO-DIR / TF / B4724 National and Sub-national, Post Direct Selection Direct 82,000.00 48,320.39 Completed 2020-04-09 2020-04-16 2020-04-14 2020-04-16 2020-05-19 2020-10-01 2020-11-15 2021-01-12 Realtime PCR Machine Prevention and Preparedness GM-MOH-166640-NC-RFQ / Component 1: Emergency Request for Single Stage - One Equipment for Points of IDA / D5970 Post Limited 30,000.00 0.00 Canceled 2020-04-13 2020-06-08 2020-12-05 COVID-19 Response Quotations Envelope Entries (PoEs) GM-MOH-166478-GO-RFQ / Furniture for PHEOC (Public Component 1: Emergency Request for Single Stage - One IDA / D5970 Post Limited 29,650.00 28,238.20 Completed 2020-04-13 2020-04-01 2020-06-08 2020-04-07 2020-12-05 2020-04-14 Health Emergency Operation COVID-19 Response Quotations Envelope Center) Component 3: Supporting GM-MOH-168245-GO-DIR / IDA / D5970 National and Sub-national, Post Direct Selection Direct 280,000.00 0.00 Canceled 2020-04-09 2020-04-14 2020-05-19 2020-11-15 Upgrade of BL3 Laboratory Prevention and Preparedness GM-MOH-176397-GO-RFQ / Component 1: Emergency Request for Single Stage - One IDA / D5970 Post Limited 26,010.00 23,553.01 Completed 2020-06-05 2020-08-26 2020-07-31 2020-09-21 2021-01-27 2020-09-28 Enhancing the Call Center COVID-19 Response Quotations Envelope GM-MOH-176398-GO-RFQ / Procurement of office Component 1: Emergency Request for Single Stage - One furniture and IDA / D5970 Post Limited 14,000.00 11,278.63 Completed 2020-06-05 2020-06-17 2020-07-31 2020-07-15 2021-01-27 2020-07-24 COVID-19 Response Quotations Envelope equipment/laptops for healthcare waste management GM-MOH-176392-GO-RFQ / Component 3: Supporting Request for Single Stage - One Procurement of Items for TF / B4724 National and Sub-national, Post Limited 392,293.91 392,293.91 Completed 2020-06-05 2020-05-18 2020-07-31 2020-06-23 2021-01-27 2020-09-07 Quotations Envelope Chemistry Platform Prevention and Preparedness GM-MOH-176391-GO-RFQ / Component 3: Supporting Procurement of Items for Request for Single Stage - One TF / B4724 National and Sub-national, Post Limited 492,816.30 492,816.30 Completed 2020-06-05 2020-05-18 2020-07-31 2020-06-23 2021-01-27 2021-01-27 Molecular Testing (Upgrade of Quotations Envelope Prevention and Preparedness BL3 Lab) Component 3: Supporting GM-MOH-168248-GO-DIR / IDA / D5970 National and Sub-national, Post Direct Selection Direct 392,293.91 0.00 Canceled 2020-04-09 2020-04-14 2020-05-19 2020-11-15 Chemistry Systems Prevention and Preparedness GM-MOH-180388-GO-RFQ / Component 3: Supporting Procurement of Building Request for Single Stage - One IDA / D5970 National and Sub-national, Post Limited 600,000.00 0.00 Canceled 2020-06-21 2020-08-16 2021-02-12 Materials for the Renovation Quotations Envelope Prevention and Preparedness of Isolation Centers GM-MOH-180389-GO-RFQ / Component 1: Emergency Request for Single Stage - One Procurement of health care IDA / D5970 Post Limited 15,000.00 170,855.47 Completed 2020-06-21 2020-07-07 2020-08-16 2020-07-15 2021-02-12 2021-02-01 COVID-19 Response Quotations Envelope waste management materials GM-MOH-166696-GO-RFQ / Component 1: Emergency Request for Single Stage - One Procurement of medical waste IDA / D5970 Post Limited 90,000.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 COVID-19 Response Quotations Envelope disposal trucks Component 3: Supporting GM-MOH-166660-GO-RFQ / Request for Single Stage - One IDA / D5970 National and Sub-national, Post Limited 45,800.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 Cargo Trucks 15 Tons Quotations Envelope Prevention and Preparedness GM-MOH-189380-GO-UN / Component 3: Supporting Procurement of 2 waste UN Agencies TF / B4724 National and Sub-national, Post Direct 135,800.00 0.00 Canceled 2020-08-18 2020-08-20 2020-08-23 2020-11-05 2020-09-27 2021-03-26 management Trucks and 1 15 (Direct) Prevention and Preparedness ton Truck GM-MOH-189385-GO-DIR / Component 3: Supporting Procurement of Air IDA / D5970 National and Sub-national, Post Direct Selection Direct 450.00 391.22 Completed 2020-08-18 2020-08-19 2020-08-23 2020-08-19 2020-09-27 2020-08-19 2021-03-26 2020-08-21 Conditioner for NPHL data Prevention and Preparedness management system GM-MOH-TAB-GO-DIR / Component 3: Supporting Procurement of 5 tablets for IDA / D5970 National and Sub-national, Post Direct Selection Direct 1,800.00 1,717.56 Completed 2020-08-19 2020-08-17 2020-08-24 2020-08-17 2020-09-28 2020-08-17 2021-03-27 2020-08-21 the NPHL Data Management Prevention and Preparedness System GM-MOH-189381-GO-DIR / Component 3: Supporting Procurement of IT Equipment IDA / D5970 National and Sub-national, Post Direct Selection Direct 20,000.00 18,816.79 Completed 2020-08-19 2020-08-14 2020-08-24 2020-08-14 2020-09-28 2020-08-14 2021-03-27 2020-08-21 for NPHL data management Prevention and Preparedness system GM-MOH-220979-GO-DIR / Component 1: Emergency Procurement of ABBOT IDA / D5970 Post Direct Selection Direct 390,000.00 390,000.00 Signed 2021-02-22 2021-02-23 2021-02-27 2021-02-23 2021-04-03 2021-02-23 2021-09-30 COVID-19 Response COVID19 Rapid Test Kits Page 2 GM-MOH-222972-GO-UN / Procurement of waste Component 3: Supporting UN Agencies management trucks, wheelie IDA / D5970 National and Sub-national, Post Direct 700,000.00 441,497.55 Signed 2021-03-05 2020-11-05 2021-03-10 2020-11-05 2021-04-14 2020-12-18 2021-10-11 (Direct) bins, cargo trucks, generator Prevention and Preparedness and incinerators GM-MOH-226892-GO-RFQ / Pending Component 1: Emergency Request for Single Stage - One Emergency drugs (Adrenaline) IDA / D5970 Post Open - National 20,000.00 0.00 Implementati 2021-04-02 2021-05-28 2021-11-24 COVID-19 Response Quotations Envelope for AEFI on GM-MOH-226893-GO-RFQ / Pending Component 1: Emergency Request for Single Stage - One Procurement of 11 Waste IDA / D5970 Post Open - National 30,000.00 0.00 Implementati 2021-04-02 2021-05-28 2021-11-24 COVID-19 Response Quotations Envelope Management Containers on Pending GM-MOH-226894-GO-UN / Component 1: Emergency UN Agencies IDA / D5970 Post Direct 40,000.00 0.00 Implementati 2021-03-28 2021-04-02 2021-05-07 2021-11-03 Ultracold Freezers COVID-19 Response (Direct) on GM-MOH-226895-GO-RFQ / Software for Pending Medicines/vaccines Component 1: Emergency Request for Single Stage - One IDA / D5970 Post Open - International 45,000.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 registration, national COVID-19 Response Quotations Envelope on pharmacovigilance and AEFI system NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-MOH-184257-NC-DIR / Transportation of Medical Component 1: Emergency IDA / D5970 Post Direct Selection Direct 635,000.00 635,000.00 Completed 2020-07-14 2020-07-14 2020-07-19 2020-07-14 2020-08-23 2020-07-15 2021-02-19 2020-07-20 Supplies and Equipment from COVID-19 Response Ankara to Banjul Airport GM-MOH-186058-NC-DIR / Component 3: Supporting Sea Freight of Medical IDA / D5970 National and Sub-national, Post Direct Selection Direct 27,000.00 27,048.00 Completed 2020-07-28 2020-07-20 2020-08-02 2020-07-20 2020-09-06 2020-07-30 2021-03-05 2020-10-01 Equipment and Supplies from Prevention and Preparedness Ankara CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-MOH-168250-CS-CQS / Component 3: Supporting Consultant Inspection of medical supplies IDA / D5970 National and Sub-national, Post Qualification Limited 5,000.00 1,800.00 Completed 2020-04-09 2020-04-08 2020-04-23 2020-04-15 2020-05-23 2020-06-27 2020-04-17 2020-12-24 2020-04-24 and equipment in Ankara Prevention and Preparedness Selection GM-MOH-176403-CS-QCBS / Environmental Impact Assessment and Environmental and Social Component 3: Supporting Consultant Management Plan for the IDA / D5970 National and Sub-national, Post Qualification Open - International 100,000.00 48,309.05 Signed 2020-06-13 2020-08-26 2020-07-04 2020-08-17 2020-08-12 2020-09-16 2020-10-07 2020-10-21 2020-10-07 2021-04-19 construction of National Prevention and Preparedness Selection Emergency Treatment Centre and construction of National public health laboratory and training centre GM-MOH-176395-CS-QCBS / Architectural drawings for construction of public health Component 3: Supporting Quality And Cost- emergency laboratory and IDA / D5970 National and Sub-national, Post Open - International 600,000.00 604,438.70 Signed 2020-06-18 2020-04-15 2020-07-08 2020-08-21 2020-05-11 2020-09-18 2020-06-01 2020-10-18 2020-06-22 2020-11-22 2020-09-16 2020-12-27 2020-11-20 2021-12-27 Based Selection training center and Prevention and Preparedness construction of National Center for Infectious Diseases Component 4: GM-MOH-181509-CS-LCBS / Implementation Management Least Cost External Audit of COVID -19 IDA / D5970 Post Open - National 11,000.00 0.00 Canceled 2020-06-25 2020-06-26 2020-07-16 2020-08-29 2020-09-26 2020-10-26 2020-11-30 2021-01-04 2021-07-03 and Monitoring and Selection World Bank Project Evaluation GM-MOH-190887-CS-CQS / Construction supervision of National Emergency Component 3: Supporting Consultant Treatment Center and IDA / D5970 National and Sub-national, Post Qualification Open - National 150,000.00 0.00 Canceled 2020-10-01 2020-08-28 2020-10-22 2020-12-05 2020-09-09 2021-01-04 2021-02-08 2021-08-07 construction of National Prevention and Preparedness Selection public health laboratory and training center (local firm) GM-MOH-195887-CS-CQS / Construction supervision of National Emergency Component 3: Supporting Consultant Treatment Center and IDA / D5970 National and Sub-national, Post Qualification Open - National 120,000.00 95,100.00 Signed 2020-09-22 2020-08-28 2020-10-13 2020-09-22 2020-11-26 2020-11-06 2020-12-26 2020-11-19 2021-01-30 2020-12-01 2021-07-29 construction of National Prevention and Preparedness Selection public health laboratory and training center (local firm) Component 4: GM-MOH-197538-CS-CQS / Consultant Implementation Management Under External Audit of COVID -19 IDA / D5970 Post Qualification Open - National 11,000.00 21,714.83 2020-10-01 2020-10-01 2020-10-22 2020-12-05 2021-02-16 2021-01-04 2021-03-09 2021-02-08 2021-08-07 and Monitoring and Implementation World Bank Project Selection Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-MOH-166703-CS-CDS / Architectural drawings for construction of public health Component 3: Supporting emergency laboratory and IDA / D5970 National and Sub-national, Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-04-30 2020-05-10 2020-07-14 2021-01-10 training center and Prevention and Preparedness construction of National Center for Infectious Diseases Page 3 GM-MOH-226896-CS-INDV Individual / Recruitment of 30 data entry Component 1: Emergency Pending IDA / D5970 Post Consultant Open 15,000.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 clerks for COVID-19 COVID-19 Response Implementation Selection vaccination data GM-MOH-226906-CS-CDS / Construction supervision for the National Emergency Treatment Centre, National Component 1: Emergency Pending IDA / D5970 Post Direct Selection Direct 98,000.00 0.00 2021-03-29 2021-04-08 2021-06-12 2021-12-09 public health laboratory, COVID-19 Response Implementation national blood transfusion, and conference center (Medical equipment) Page 4